Leighton International's Magazine, Perspective, Issue 6 2010
Leighton International's Magazine, Perspective, Issue 6 2010
Leighton International's Magazine, Perspective, Issue 6 2010
- No tags were found...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
PROJECT UPDATES<br />
17<br />
LABUAN PIPELINE PROJECT<br />
COMPLETED AHEAD<br />
OF SCHEDULE<br />
A FEATHER IN THE CAP FOR LEIGHTON MALAYSIA AND LEIGHTON OFFSHORE AS THE<br />
LABUAN WATER PIPELINE PROJECT IS COMPLETED A MONTH AHEAD OF SCHEDULE.<br />
The Government of Malaysia is<br />
undertaking the development of a Water<br />
Pipeline in Labuan, East Malaysia, to<br />
mitigate the acute water shortage on<br />
the island. In collaboration with <strong>Leighton</strong><br />
Offshore and in Joint Venture with<br />
Kencana HL, <strong>Leighton</strong> Malaysia<br />
delivered the following:<br />
The delivery of existing 26 inch<br />
pipeline – 22740 meters including the<br />
supply of additional 600 meters of<br />
new pipes by Kencana.<br />
Pre-installation pipelay analysis<br />
Install and pre-commission<br />
approximately 22.8km of submarine<br />
pipeline in max water depths of 22m.<br />
Post trench approximately 1.8km at<br />
three locations along the route<br />
Interface with existing mudflats<br />
contractor including undertaking a<br />
midpoint tie-in.<br />
A key challenge to the installation of the<br />
pipeline was the constraints that the<br />
physical characteristics of the free issued<br />
pipeline poses in terms of its stiffness,<br />
due to the relatively thick reinforced<br />
concrete weight coating and its relatively<br />
thin wall thickness.<br />
The challenges that this poses include<br />
the ability to install this pipeline using a<br />
pipe lay barge that has sufficient track<br />
tensioner capacity, and undertaking detail<br />
stress analysis using finite element<br />
methods to identify and reduce bending<br />
stresses during installation. <strong>Leighton</strong><br />
Stealth was used to install the pipeline<br />
using the S-Lay method.<br />
<strong>Leighton</strong> completed the project on<br />
the 10th September, over a month ahead<br />
of schedule.<br />
Project Manager, Edgar Ramani, said<br />
“It was a demanding project set against a<br />
very tight timeline with the contract being<br />
awarded on 17 th May, commencement of<br />
onshore installation works on 29 th May<br />
and offshore installation works on 7 th July.<br />
So to have completed one month ahead<br />
of schedule is something the team is very<br />
proud of.<br />
“We were given a very short period to<br />
complete engineering and planning. The<br />
installation of a thin wall, rigid pipeline<br />
susceptible to buckling together with poor<br />
weather conditions, plus working with a<br />
competitive budget; were among the<br />
challenging obstacles we faced. But the<br />
dedicated and focused project team<br />
overcame these challenges with great<br />
success.<br />
“We achieved this while maintaining a<br />
high standard of safety and quality – with<br />
no loss time injuries on the project and a<br />
high audit score from Lloyds Register for<br />
the environment audit with no nonconformances.<br />
We also gave something<br />
back to the local community through an<br />
environmental awareness campaign with<br />
a local community centre for disabled<br />
kids. We planted fruit trees at the centre<br />
and sponsored eight local athletes to take<br />
part in the next Malaysian Paralympics<br />
Games in Perak, Malaysia.”<br />
The team delivered the project on-time<br />
and well below budget, whilst efficiently<br />
delivering Stealth for the next offshore<br />
project, Devil Creek Development Project<br />
in Australia on schedule.