Risk Plan Example<br />

Phase 1<br />

Selection<br />

Risk Description:<br />

Solution:<br />

Unforeseen risk or conditions are discovered on the project.<br />

Risk that is not identified by client professional, competing contractors, or expert contractor<br />

will be identified and solved within 3 days maximum (unless longer time is justified and<br />

requested). The contractor will resolve unforeseen risks in the following manner:<br />

• Contractor shall immediately notify the designer and owner the same day as discovery<br />

of potential cost and time impact<br />

• Contractor shall find best possible options to minimize risk, with accompanying cost and<br />

time<br />

• All cost and time figures will be competed among the best performers<br />

• Contractor shall propose the best solution with justification and present to client<br />

representative<br />

• If client representative approves, no action required, as contractor will create change<br />

order for work, justification, pricing, and proposal within the specified time, and<br />

proceed to accomplish the work<br />

• If client objects, contractor will work around issue and document cost and time<br />

deviation on a weekly basis<br />

Documented<br />

<strong>Performance</strong>:<br />

Of our 15 most recently completed projects in similar scope to this project, less than 1% of<br />

the deviations were unforeseen. Our average response time from identification of<br />

unforeseen risk to issuance of RFI is 1 day (for these same 15 projects).<br />

16