Name of work: Replacement of scrapped split AC unit with 8 nos 1.5 TR S/T AC units<br />
at St Thomas Mount, chennai (SW: AC Wiring )<br />
This will be followed by Standard EW 8 booklet (Printed form) Page no.16<br />
onwards at the time of framing the agreement.<br />
MODIFICATIONS TO NEW <strong>BSNL</strong> EW8<br />
(IN CASE OF SINGLE BID SYSTEM)<br />
S.N Referen<br />
o ce<br />
8. Clause<br />
7.3 of<br />
“Clause<br />
s of<br />
Contract<br />
”.<br />
Pg.n New EW 8<br />
o<br />
22. Payment to the contractors for Air Conditioning, Engine<br />
Alternator, Sub Station, Lifts, fire<br />
detection, fire fighting and other specialised items, during<br />
progress of work, will be<br />
regulated as below :-<br />
a) 80% of prorata of the approved price breakup of contract<br />
value on receipt of equipment at site and after satisfactory<br />
physical inspection.<br />
b) 10% of prorata of the approved price breakup of contract<br />
value after successful installation of equipment.<br />
c) 5% of the approved contract value after successful<br />
completion of Initial acceptance testing.<br />
d) 5% of the approved contract value after successful<br />
completion of the final acceptance testing.<br />
e) For the works where A/T is not applicable e.g. for substation,<br />
lift, fire fighting etc.<br />
5% of the approved contract value shall be released after<br />
clearance by Electrical inspector/ lift inspector/ Fire officer<br />
respectively.<br />
To be read<br />
as<br />
Deleted<br />
Contractor Internet Downloaded copy Sub Divisional Engineer (E)<br />
Page No. 28 of 35