CORAL BAY NICKEL HPP-2 PROJECT IN PALAWAN, PHILIPPINES<br />
By<br />
Shinichiro Yumoto, Tozo Otani, Tadashi Nagai and Isao Ikeda<br />
JGC corporation, Japan<br />
Presenter and Corresponding Author<br />
Shinichiro Yumoto<br />
Yumoto.shinichiro@jgc.co.jp<br />
ABSTRACT<br />
Coral Bay Nickel HPP-2 Project (CBNH-2 PJ.) conducted by Coral Bay Nickel Corporation (CBNC)<br />
in the Philippines was mechanically completed on February, 2009. CBNC achieved the name plate<br />
capacity operation on April, 2009. Ramp-up period was only a couple of months. This paper<br />
presents the Project overview of CBNH-2 PJ and refers to a previous project, Rio Tuba Nickel HPP-<br />
1 Project (RTNH-1 PJ), and presents a discussion of the keys to success of completing the project<br />
on schedule, within budget, with high quality and with early ramp-up, in terms of validated design,<br />
reliable EPC execution, competent operator and maintenance staff, and an EPC lump sum contract<br />
scheme. Thanks to the success of these two HPAL projects, JGC was selected as a main<br />
contractor for Taganito PJ which is underway in Philippines now.<br />