PROJECT MANUAL<br />

WALMART SUPER<br />

RCENTER<br />

La Habra, CA,<br />

USA<br />

Store Number: 5641<br />

107T-GR-NO<br />

Project Number: 19-159.25<br />

June 21, 20111<br />

For<br />

WALMART STORES, INC.<br />

Sam Walton Developmen<br />

t Complex<br />

2001 S.E. 10th Street<br />

Bentonville, Arkansas 72716-0550<br />

Architect of Record:<br />

PERKOWITZ + RUTH ARCHITECTS<br />

1111 West Ocean Boulevard, 21 st Floor<br />

Long Beach, Californiaa 90802<br />

(562) 628-80000


UniSpec II 06/21/11<br />

DOCUMENT 00007 – SEALS PAGE<br />

PROJECT:<br />

Name:<br />

Walmart Supercenter<br />

Location:<br />

La Habra, CA<br />

Project Number: 10-159.25<br />

Store Number: 5641<br />

ARCHITECT OF RECORD<br />

Don Grainger<br />

Perkowitz + Ruth Architects<br />

111 W. Ocean Blvd., 21 st Floor<br />

Long Beach, CA 90802<br />

Architect of Record<br />

Date<br />

00007 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


THIS PAGE<br />

INTENTIONALLY<br />

LEFT BLANK<br />

00007 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


SEALS PAGE (Continued)<br />

STRUCTURAL ENGINEER OF RECORD<br />

Justin Hartman, P.E.<br />

Wallace Engineering Structural Consultants, Inc.<br />

200 East Brady Street<br />

Tulsa, OK 74103<br />

Structural Engineer of Record<br />

Date<br />

00007 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


THIS PAGE<br />

INTENTIONALLY<br />

LEFT BLANK<br />

00007 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


SEALS PAGE (Continued)<br />

MECHANICAL ENGINEER OF RECORD<br />

David P. Kimball, P.E.<br />

Suite 5238<br />

1805 North Second Street<br />

Rogers, AR 72756<br />

Mechanical Engineer of Record<br />

Date<br />

ELECTRICAL ENGINEER OF RECORD<br />

Keith A. Williams, P.E.<br />

Suite 5296<br />

1805 North Second Street<br />

Rogers, AR 72756<br />

Electrical Engineer of Record<br />

Date<br />

00007 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


THIS PAGE<br />

INTENTIONALLY<br />

LEFT BLANK<br />

00007 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


SEALS PAGE (Continued)<br />

REFRIGERATION ENGINEER OF RECORD<br />

Eric J. Mills, P.E.<br />

Suite 5252<br />

1805 North Second Street<br />

Rogers, AR 72756<br />

Refrigeration Engineer of Record<br />

Date<br />

00007 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


THIS PAGE<br />

INTENTIONALLY<br />

LEFT BLANK<br />

00007 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


SEALS PAGE (Continued)<br />

FIRE PROTECTION ENGINEER OF RECORD<br />

James E. Cooper, P.E.<br />

Suite 3857<br />

1805 North Second Street<br />

Rogers, AR 72756<br />

Fire Protection Engineer of Record<br />

Date<br />

END OF DOCUMENT<br />

00007 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


THIS PAGE<br />

INTENTIONALLY<br />

LEFT BLANK<br />

00007 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 062411<br />

SECTION 00010 – TABLE OF CONTENTS<br />

Division<br />

Section Title<br />

INTRODUCTORY INFORMATION<br />

00001 Project Title Page<br />

00007 Seals Page<br />

00010 Table of Contents<br />

BIDDING REQUIREMENTS<br />

Bidding Requirements (including Invitation to Bids, Instructions to Bidders, and Bid Forms) are issued by the<br />

Owner under separate cover and are not included in the Project Manual.<br />

CONTRACTING REQUIREMENTS<br />

Contracting Requirements (including General Conditions, Agreement, Bond, and Certificate Forms) are issued by<br />

the Owner under separate cover and are not included in the Project Manual.<br />

SPECIFICATIONS<br />

DIVISION 1 - GENERAL REQUIREMENTS<br />

01100 Summary<br />

01255 Request For Information<br />

01310 Project Management and Coordination<br />

01311 Project Meetings<br />

01320 Construction Progress Documentation<br />

01330 Submittal Procedures<br />

01432 Electrical Installer Qualifications<br />

01452 Contractor's Quality Control<br />

01454 Architect-Engineer Quality Assurance<br />

01455 Mechanical Equipment Testing, Adjusting, and Balancing<br />

01456 Civil Engineer Consultant Quality Assurance Observation<br />

01458 Laboratory Testing Services<br />

01459 Neutralization Enclosure Quality Control<br />

01500 Temporary Facilities And Controls<br />

01600 Product Requirements<br />

01640 Owner Furnished Products<br />

01700 Execution Requirements<br />

01731 Cutting and Patching<br />

01740 Cleaning<br />

01742 Construction/Demolition Waste Management and Disposal<br />

01743 Hazardous/Universal Waste Management and Disposal<br />

01770 Contract Closeout<br />

00010 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


DIVISION 2 - SITE CONSTRUCTION (BUILDING RELATED)<br />

02023 Selective Site Demolition<br />

02223 Removal and Recycling of Vinyl Composition Tile (VCT)<br />

02224 Removal and Recycling of Acoustical Ceiling Tile (ACT)<br />

02251 Shoring<br />

02361 Termite Control<br />

02768 Tactile Warning Systems<br />

02821 Chain Link Fences and Gates (Building Related)<br />

02823 Ornamental Metal Fences and Gates<br />

02845 Cart Corral<br />

02870 Site Furnishings<br />

DIVISION 2.1 - SITE CONSTRUCTION (CIVIL ENGINEERING CONSULTANT DESIGN)<br />

The Sections within this Division and other Divisions listed within the Wal-Mart Sitework Specifications Table of<br />

Contents page are the responsibility of the Civil Engineering Consultant, and not the responsibility of the Architect<br />

of Record. The Civil Engineering Consultant, the seal and license number of the Professional Engineer registered in<br />

the State where the project is located, are shown on the Wal-Mart Sitework Specifications Table of Contents page.<br />

DIVISION 3 - CONCRETE<br />

03310 Structural Concrete and Exterior Concrete Slabs<br />

03312 Cast-In-Place Concrete Slabs (Interior)<br />

03362 Burnished Floor Finishes<br />

03363 Burnished Concrete Floor Finishes (Existing Floors)<br />

03450 Plant-Precast Architectural Concrete<br />

03930 Concrete Rehabilitation<br />

DIVISION 4 - MASONRY<br />

04711 Manufactured Stone Veneers<br />

DIVISION 5 - METALS<br />

05090 Post-Installed Concrete and Masonry Anchors<br />

05120 Structural Steel<br />

05400 Cold Formed Metal Framing<br />

05500 Metal Fabrications<br />

DIVISION 6 - WOOD AND PLASTICS<br />

06065 Plastic Materials<br />

06100 Rough Carpentry<br />

06200 Finish Carpentry<br />

06400 Architectural Woodwork<br />

06424 Protective Surfacing<br />

06615 Non-Fiberglass Reinforced Plastic Panels<br />

06616 Simulated Stone Fabrications<br />

00010 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


DIVISION 7 - THERMAL AND MOISTURE PROTECTION<br />

07190 Water Repellents<br />

07210 Building Insulation<br />

07243 Water-Drainage Exterior Insulation And Finish System (EIFS)<br />

07411 Metal Wall Panels<br />

07500 Membrane Roofing<br />

07525 Fluid-Applied Membrane Air Barrier<br />

07611 Sheet Metal Soffit<br />

07620 Sheet Metal Flashing and Trim<br />

07711 Gutters and Downspouts<br />

07721 Manufactured Curbs<br />

07722 Roof Hatches<br />

07815 Mineral Fiber Fireproofing<br />

07840 Firestopping<br />

07900 Joint Sealers<br />

DIVISION 8 - DOORS AND WINDOWS<br />

08110 Steel Doors and Frames<br />

08311 Access Doors and Frames<br />

08332 Overhead Rolling Closure<br />

08337 Coiling Counter Shutters<br />

08360 Sectional Overhead Doors<br />

08381 Flexible Strip Doors<br />

08383 Traffic Doors<br />

08411 Aluminum Framed Storefronts<br />

08462 Automatic Sliding Entrance Doors<br />

08710 Door Hardware and Hardware Schedule<br />

08800 Glazing<br />

DIVISION 9 - FINISHES<br />

09100 Lath and Plaster (Stucco)<br />

09250 Gypsum Board<br />

09310 Ceramic Tile<br />

09330 Quarry Tile<br />

09511 Acoustical Panel Ceilings<br />

09650 Resilient Flooring<br />

09655 Resilient Base and Accessories<br />

09680 Carpet<br />

09900 Paints and Coatings<br />

09965 Graffiti Resistant Coatings<br />

DIVISION 10 - SPECIALTIES<br />

10160 Metal Toilet Compartments<br />

10240 Equipment Screens<br />

10260 Wall and Corner Guards<br />

10293 Bird Control Devices<br />

10350 Flagpoles<br />

10671 Pharmacy Racks<br />

10672 Mobile Storage Carts<br />

10675 Modular Rack and Fence System<br />

10810 Toilet Accessories<br />

00010 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


DIVISION 11 - EQUIPMENT<br />

11025 Lock Boxes<br />

11160 Loading Dock Equipment<br />

11400 Food Service Equipment<br />

DIVISION 12 - FURNISHINGS<br />

NOT APPLICABLE<br />

DIVISION 13 - SPECIAL CONSTRUCTION<br />

13080 Seismic Protection for Mechanical, Electrical and Refrigeration<br />

13121 Fabric Structures<br />

13123 Glazed Structures<br />

13425 Sub-Metering Instrumentation<br />

13810 Energy Management System<br />

13900 Fire Suppression<br />

DIVISION 14 - CONVEYING SYSTEMS<br />

NOT APPLICABLE<br />

DIVISION 15 - MECHANICAL<br />

15050 Basic Mechanical Materials and Methods<br />

15100 Building Services Piping and Equipment<br />

15190 Fuel Gas Piping<br />

15410 Plumbing Fixtures<br />

15480 Domestic Water Heaters<br />

15600 Refrigeration Systems<br />

15700 Heating, Ventilating, and Air Conditioning Equipment<br />

15800 Air Distribution<br />

DIVISION 16 - ELECTRICAL<br />

16050 Basic Electrical Materials And Methods<br />

16100 Wiring Methods<br />

16265 Static Uninterrupted Power Supply<br />

16405 Electrical Distribution Center<br />

16410 Enclosed Switches and Circuit Breakers<br />

16452 Track Busway Systems<br />

16500 Lighting<br />

16700 Communications<br />

END OF TABLE OF CONTENTS<br />

00010 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 01100 – SUMMARY<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Definitions.<br />

2. Work covered by Contract Documents.<br />

3. Work by Wal-Mart or Separate Contractors.<br />

4. Contractor use of site and premises.<br />

5. Coordination with occupants.<br />

6. Partial occupancy.<br />

1.2 REFERENCES AND STANDARDS<br />

A. Applicability: The publications listed in the REFERENCES paragraph of an individual section shall apply only to<br />

the extent referenced within the text of that section. Unless the Contract Documents include more stringent<br />

requirements, applicable construction industry standards form a part of these specifications and have the same<br />

force and effect as if bound or copied directly into the Contract Documents. Publications are referenced within the<br />

text by the basic designation only.<br />

B. Publication Dates: Standards and publications referenced in the Specifications shall mean the latest edition as of<br />

the date of commencement of the Work as stated in Clause 1.2.6 of the General Condition unless otherwise<br />

specifically dated.<br />

C. Copies of Standards: Wal-Mart or the Architect will not provide copies of references cited within the<br />

specifications. Copies may be obtained directly from publication source.<br />

1.3 DEFINITIONS<br />

A. Furnish: Purchase and deliver to project site, ready for installation.<br />

B. Install: Unpack, assemble, set in final position, fasten in place, make final connections, clean, adjust, and leave<br />

ready for use.<br />

C. Provide: Furnish and install.<br />

D. Receive: Accepting a delivery (Entity responsible for accepting a delivery).<br />

E. Final Connections: Complete plumbing, mechanical, and electrical connections as required and recommended by<br />

manufacturer for optimum operation of equipment.<br />

1.4 WORK COVERED BY CONTRACT DOCUMENTS<br />

A. Work of this Contract comprises the general construction required for renovation and adaptation of an existing<br />

building to a Walmart Supercenter.<br />

B. Refer to Drawings for full scope of Work.<br />

1.5 WORK BY WAL-MART OR SEPARATE CONTRACTORS<br />

A. Wal-Mart has its own forces who will perform certain Work on the project; items noted 'NIC' (Not In Contract)<br />

which will commence as indicated on the Construction Schedule.<br />

01100 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Wal-Mart may award separate contracts for work at the Site, which will be executed concurrent with work of this<br />

Contract. Consult and cooperate with separate contractors to the full extent provided for in the Conditions of the<br />

Contract.<br />

C. During setup of equipment by the Owner or separate contractors, make crane service available to hoist equipment<br />

directly from trucks to final position. Coordinate schedule with Wal-Mart's Construction Manager.<br />

1.6 CONTRACTOR USE OF SITE AND PREMISES<br />

A. General: Contractor shall have full use of premises for construction operations, including use of Project site,<br />

during construction period.<br />

B. Contractor's use of premises is limited only by the following:<br />

1. Owner's right to perform work or to retain other contractors on portions of Project.<br />

2. Access to site and premises by the public agencies granted access for inspection of the Work.<br />

3. Wal-Mart occupancy of existing work or partially completed work.<br />

4. Access to site and premises by the public to areas required to remain open to store customers and Wal-Mart<br />

associates.<br />

5. Access as permitted or restricted by Wal-Mart Construction Manager or Store Manager as described in<br />

paragraph: Coordination with Occupants below.<br />

C. Do not unreasonably encumber site with products or equipment.<br />

D. Maintain the following conditions at all times during the construction period until possession by Wal-Mart.<br />

1. Maintain building weathertight and secure.<br />

2. Maintain building security and fire alarm systems in operation. (In the event both systems should fail, the<br />

Fire Alarm System shall have priority over the Security System.)<br />

a. Contract with local alarm company to maintain service, and repair existing systems as required due<br />

to work relating to this Contract.<br />

b. Alarm Company:<br />

1) Visit site and be familiar with existing conditions.<br />

2) Respond to service calls within 24 hours.<br />

c. Provide on-site guard services in the event the existing system is disabled for 8 hours or more.<br />

d. Coordinate security alarm with Section 01500 - Temporary Facilities and Controls.<br />

e. Contact Wal-Mart Alarm Central Control at (479) 273-4600 for additional information and<br />

coordination relating to work associated with existing alarm systems.<br />

3. Maintain access and egress from the building.<br />

1.7 COORDINATION WITH OCCUPANTS<br />

A. Owner will occupy premises during entire period of construction for the conduct of Owner's normal, daily<br />

operations. Cooperate with Wal-Mart Construction Manager in construction operations to minimize delays,<br />

inconvenience, or conflict to Owner's daily business operations and customer traffic. The Contractor shall obtain<br />

permission from the Owner for interruptions of utility services to the building. Accidental interruptions shall be<br />

restored immediately.<br />

1. Any Contractor work operations that may disrupt or interfere with Wal-Mart or building operation or<br />

function shall be reviewed and approved by Wal-Mart Construction Manager.<br />

2. Submit written request for approval to Wal-Mart Construction Manager 14 calendar days in advance of<br />

date Contractor work operations are required to begin.<br />

B. Contractor personnel shall not enter "restricted" area of building without prior approval of Wal-Mart Store<br />

Manager. Requirements regarding "restricted areas" of building will be discussed by Wal-Mart Construction<br />

Manager at the Preconstruction Conference.<br />

C. Maintain all building exits and provide clear pathways to exits. Relocate exits or provide temporary exits as<br />

required for construction operations and construction sequence phases. Locate temporary exits in conformance<br />

with code exiting requirements.<br />

01100 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Contractor shall minimize noise or vibration that would disturb Owner's operations. When directed by Owner,<br />

Contractor shall perform disruptive operations at designated time of day or night in order to minimize disturbance<br />

to Owner's operations.<br />

E. Contractor shall maintain watertight conditions in operating portions of the building during construction.<br />

F. Coordinate with Wal-Mart Construction Manager for maintenance of access and for the operations and<br />

maintenance of existing utilities and services.<br />

1.8 PARTIAL OCCUPANCY<br />

A. Wal-Mart shall have the option to occupy any completed or partially completed portions of the Work.<br />

B. Cooperate with Wal-Mart to minimize conflict, and schedule the Work to facilitate Wal-Mart's operations.<br />

C. Prior to Wal-Mart occupancy in areas of new work, the following provisions shall be in place:<br />

1. Illuminated exit signs are operational.<br />

2. Exit doors, including required panic hardware, are operational.<br />

3. Lighted, enclosed walkways and other temporary safety measures are in place if required by authorities<br />

having jurisdiction.<br />

4. Fire sprinkler system is operational.<br />

5. Doors required for Wal-Mart's security purposes are operational.<br />

D. After Wal-Mart Occupancy:<br />

1. Keep exit routes and exit doors free from obstructions.<br />

2. Maintain exit signs and fire sprinkler system in operational condition.<br />

3. Provide security for Wal-Mart's products, equipment, and operations.<br />

4. Do not permit smoking in the building.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01100 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 100710<br />

SECTION 01255 – REQUEST FOR INFORMATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Requests for Information (RFI) procedures.<br />

1.2 DEFINITION<br />

A. Requests for Information: A formal online process used during the construction phase to facilitate communication<br />

between the Contractor, the Wal-Mart Construction Manager (CM) or the Mechanical Services Construction<br />

Manager (MSCM), and the Professional of Record (POR) with regard to requests for additional information and<br />

clarification of the intent of the Contract Documents (Drawings and Specifications).<br />

B. Professional of Record (POR): The Architect of Record (AOR) or the Civil Engineering Consultant (CEC).<br />

C. Architect of Record (AOR): The prime consultant in charge of overall design and coordination of the project. The<br />

AOR will be the administrator for all construction RFIs classified as “BLDG”.<br />

D. Civil Engineering Consultant (CEC): The Registered Engineer in responsible charge of the civil design for the<br />

project. The CEC will be the administrator for sitework RFIs classified as “SITE”.<br />

E. Wal-Mart Construction Manager (CM): The Wal-Mart building and sitework Construction Manager for the<br />

Project.<br />

F. Mechanical Services Construction Manager (MSCM): The Walmart Mechanical (HVAC, Refrigeration and EMS)<br />

construction manager for the Project.<br />

1.3 REQUEST FOR INFORMATION SUBMITTAL<br />

A. Submit requests for information for conditions requiring clarification of the Contract Documents on Wal-Mart<br />

Construction RFI website as designated by Wal-Mart (www.bldgportal.com, enter username and password, select<br />

Construction RFI). POR will not respond to requests for information unless this format is utilized and all<br />

appropriate information is provided. Faxed or emailed RFIs will not be reviewed.<br />

B. Do not use Request for Information process during bidding phase. For questions during bidding phase, refer to<br />

Invitation to Bid issued by Wal-Mart Contract Administrator.<br />

C. Submit in accordance with procedure as follows (See Process Flow Chart at the end of this Section):<br />

1. Subcontractors, manufacturers, and suppliers shall submit request for additional information and<br />

clarification to Contractor.<br />

2. Contractor shall contact Wal-Mart CM or MSCM, as applicable, with requests for additional information or<br />

clarification. Wal-Mart CM or MSCM will not accept requests for information or clarification submitted<br />

directly from subcontractors, manufacturers, or suppliers.<br />

3. Wal-Mart CM or MSCM will provide response to Contractor or will direct Contractor to submit a formal<br />

Request for Information.<br />

a. Submit a formal RFI only if authorized by the Wal-Mart CM or MSCM. Submittal to Construction<br />

RFI website signifies authorization has been given.<br />

b. Generate Requests for Information by one source per project.<br />

c. Submit one request for information per website entry.<br />

4. POR will review formal requests from Contractor and provide response within 2 working days.<br />

5. POR’s response shall not be considered as a Change Order or Change Directive, nor does it authorize<br />

changes in the Contract Sum or Contract Time.<br />

01255 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Scheduling, Costing, and Owner Provided Equipment Coordination: Direct to the Owner’s Construction Manager.<br />

1.4 PENALTY FOR FAILURE TO FOLLOW PROCEDURE<br />

A. A $250 administrative cost will be assessed to the Contractor for each Request for Information submitted which<br />

does not follow the procedure specified above.<br />

1.5 REIMBURSEMENT FOR ARCHITECTURAL AND ENGINEERING FEES<br />

A. The Contractor shall be charged administrative costs and professional fees incurred by Wal-Mart for additional<br />

Architectural and Engineering services associated with the correction of completed Work which is not in<br />

accordance with the Contract Documents. See Article 10 of the General Conditions of the Contract for<br />

Construction for provisions relating to Correction of Work.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01255 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


01255 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Subcontractor , manufacturer,<br />

supplier, or other<br />

party submits request for<br />

information to Contractor<br />

Wal-Mart Construction<br />

Manager provides response<br />

to Contractor<br />

Contractor contacts<br />

Wal-Mart Construction<br />

Manager (CM) with request<br />

for information. CM<br />

will provide response or<br />

authorize Formal RFI.<br />

Wal-Mart Construction<br />

Manager authorizes Contractor<br />

to submit formal<br />

Request for Information to<br />

Wal-Mart<br />

REQUEST FOR<br />

INFORMATION<br />

PROCESS FLOW CHART<br />

WAL-MART<br />

STORES, SUPERCENTER,<br />

SAM’S CLUB,<br />

MARKET<br />

Contractor submits Request<br />

for Information to<br />

POR on Wal-Mart<br />

Construction RFI Website<br />

POR notifies appropriate<br />

consultant for response on<br />

Construction RFI Website<br />

Consultant answers RFI on<br />

Construction RFI Website<br />

Contractor issues response<br />

to subcontractor, manufacturer,<br />

supplier, or other<br />

party.<br />

POR issues response to<br />

Contractor on Construction<br />

RFI Website<br />

01255 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 012811<br />

SECTION 01310 – PROJECT MANAGEMENT AND COORDINATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Project Management and Coordination:<br />

a. Construction Manager.<br />

b. Project Coordination.<br />

1.2 WAL-MART CONSTRUCTION MANAGER<br />

A. Wal-Mart will assign this project to a staff Wal-Mart Construction Manager. The Wal-Mart Construction<br />

Manager is the Owner's representative in all matters relating to the Work.<br />

B. Wal-Mart will assign this project to a staff Wal-Mart Mechanical Services Construction Manager. The Wal-Mart<br />

Mechanical Services Construction Manager is the Owner’s representative in all matters relating to the Energy<br />

Management System, HVAC equipment and refrigeration equipment.<br />

C. Cooperate with the Wal-Mart Construction Manager and Wal-Mart Mechanical Services Construction Manager in<br />

all matters relating to the Work on this project.<br />

D. During construction, coordinate use of site and facilities through the Wal-Mart Construction Manager.<br />

E. Comply with Wal-Mart Construction Manager's and Wal-Mart Mechanical Services Construction Manager’s<br />

procedures for project communications, reports and records, and coordination with drawings, and comply with<br />

recommendations and resolution of ambiguities and conflicts.<br />

F. Comply with instructions of the Wal-Mart Construction Manager for use of temporary utilities and construction<br />

facilities.<br />

G. Coordinate use of site during Wal-Mart fixture setup work under instructions of the Wal-Mart Construction<br />

Manager.<br />

1.3 PROJECT MEETINGS<br />

A. Schedule and conduct pre-construction, pre-installation, or pre-work conferences as specified and required in the<br />

various specification sections. Provide Architect of Record seven days notice prior to expected time for each<br />

required conference.<br />

1.4 PROJECT COORDINATION<br />

A. Coordinate scheduling, submittals, and work of the various Sections of specifications to ensure efficient and<br />

orderly sequence of installation of interdependent construction elements, with provisions for accommodating items<br />

installed at a later date and under separate contracts.<br />

B. Obtain necessary drawings, manufacturer's product data, and other necessary data to provide a complete and<br />

proper installation.<br />

1. Check field dimensions prior to installing equipment and furnishings. Verify necessary clearances and<br />

means of access from equipment storage to final position.<br />

2. Make shop drawings and manufacturer's rough-in requirements available to trades involved.<br />

01310 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Verify that utility requirements of operating equipment are compatible with building utilities. Coordinate work of<br />

various specification Sections for installation and final connection of equipment.<br />

1. Verify that mechanical, plumbing, and electrical rough-ins have been properly located.<br />

D. Coordinate space requirements and installation of mechanical and electrical work which are indicated<br />

diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduits as closely as practicable.<br />

Make runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other<br />

installations, for maintenance, and for repairs.<br />

E. In finished areas, conceal pipes, ducts, and wiring in the construction. Coordinate locations of fixtures and outlets<br />

with finish elements.<br />

F. Coordinate completion and clean up of work of separate Sections in preparation for Substantial Completion and<br />

for portions of Work designated for Owner’s partial occupancy after possession.<br />

G. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in<br />

accordance with Contract Documents, to minimize disruption of Owner's activities.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01310 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II - SPECIFICATIONS LIBRARY 051500<br />

SECTION 01311 – PROJECT MEETINGS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Preconstruction conference.<br />

2. Preinstallation conferences.<br />

3. Progress and quality control meetings.<br />

1.2 PROJECT MEETINGS<br />

A. Conduct project meetings, as a part of the overall project coordination effort, to coordinate construction activities<br />

and Work.<br />

1.3 ATTENDEES' AUTHORITY<br />

A. Persons designated by Contractor, subcontractors, and suppliers to attend project meetings: Possess authority to<br />

commit entities they represent to items agreed upon in project meetings.<br />

1.4 PRECONSTRUCTION CONFERENCE<br />

A. Schedule a preconstruction conference at project site or other designated location after execution of the Contract<br />

and prior start of Work.<br />

B. Attendance: Wal-Mart Construction Manager, Owner's Representative, Contractor Project Coordination<br />

Administrator, Contractor Quality Control Representative, Contractor Project Field Superintendent, roofing,<br />

mechanical, plumbing, fire protection, and electrical subcontractor field supervisory personnel.<br />

C. Minimum Agenda:<br />

1. Organizational arrangement of Contractor's forces and personnel, and those of subcontractors, material<br />

suppliers and Wal-Mart Construction Manager.<br />

2. Contractor certificates of insurance.<br />

3. Status of Contractor-required submittals; list of subcontractors, schedule of values, etc.<br />

4. Approved Progress Schedule. Work hours. Work outside of normal working hours.<br />

5. Specific building regulations for Work within and adjacent to existing building.<br />

6. Critical work sequencing.<br />

7. Procedures for processing field decisions. Request for Information procedures.<br />

8. Change order process and procedures for processing change orders.<br />

9. Procedures for processing applications for payment. Contract closeout procedures.<br />

10. Wal-Mart furnished equipment and materials process, procedures, and coordination.<br />

11. Wal-Mart installed equipment and materials process, procedures, and coordination.<br />

12. Wal-Mart separate vendor process, procedures, and coordination.<br />

13. Submittal process, procedures, and coordination.<br />

14. Temporary facilities and controls by Owner.<br />

15. Temporary utilities provided by Owner.<br />

16. Procedures for preparation and maintenance of Project Record Documents.<br />

17. Contractor office, work, storage, and parking areas.<br />

18. Work area security requirements.<br />

19. Safety procedures, first aid, and occupational safety and health requirements.<br />

20. Housekeeping, cleanliness, noise and dust control of work areas.<br />

21. Quality of workmanship required.<br />

22. Wal-Mart furnished testing and inspection services.<br />

23. Contractor's quality control procedures and requirements, inspection, testing, and documentation.<br />

01311 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Documentation: Record minutes of conference and distribute copies to Wal-Mart Construction Manager,<br />

participants, and those affected by decisions made, 2 working days after conference date. Recording, producing,<br />

and distributing by Contractor.<br />

1.5 PREINSTALLATION CONFERENCES<br />

A. When required in individual specification Section, conduct a Preinstallation Conference at project site prior to start<br />

of Work of Section or related sections.<br />

B. Notify Wal-Mart Construction Manager 14 working days in advance of meeting date.<br />

C. Attendance Required: Wal-Mart Construction Manager, Owner's Representative, Contractor Project Coordination<br />

Administrator, Contractor Quality Control Representative, Contractor Project Field Superintendent, any<br />

subcontractor, supplier, or installer directly affecting, or affected by, Work of specific Section.<br />

D. Minimum Agenda: Review conditions of installation, progress of other construction activities, and preparations<br />

for Work of Section or related Sections, including requirements for:<br />

1. Contract documents.<br />

2. Related change orders.<br />

3. Equipment and material deliveries.<br />

4. Shop drawings and product data.<br />

5. Possible conflicts and compatibility problems.<br />

6. Weather limitations.<br />

7. Time schedules.<br />

8. Manufacturer's instructions and recommendations.<br />

9. Compatibility of materials.<br />

10. Acceptability of substrates.<br />

11. Temporary facilities required.<br />

12. Space and access limitations.<br />

13. Governing codes and regulations.<br />

14. Inspection and testing requirements.<br />

15. Required performance results.<br />

E. Documentation: Record minutes of conference and distribute copies to Wal-Mart Construction Manager,<br />

participants, and those affected by decisions made, 2 working days after conference date. Recording, producing,<br />

and distributing by Contractor.<br />

1.6 PROGRESS AND QUALITY CONTROL MEETINGS<br />

A. Schedule and conduct progress meetings throughout the progress of the Work at intervals determined by the Wal-<br />

Mart Construction Manager.<br />

B. Attendance Required: Wal-Mart Construction Manager, Owner's Representative, Contractor Project Coordination<br />

Administrator, Contractor Quality Control Representative, and Contractor Project Field Superintendent.<br />

C. Minimum Agenda: Review items of significance that may affect project progress, including the following:<br />

1. Minutes of previous meetings.<br />

2. Work progress in relation to Contractor's construction schedule.<br />

3. Status of required submittals.<br />

4. Payment request status. Documentation of information for payment requests.<br />

5. Field observations, Requests for Information, discussions of problems, and agreement on solutions.<br />

6. Quality of materials and workmanship.<br />

7. Corrective measures to regain quality of materials and workmanship; status of products, assemblies, or<br />

systems requiring replacement.<br />

8. Status of change orders.<br />

9. Corrective measures to regain projected schedules.<br />

10. Planned progress for period prior to next scheduled Progress Meeting.<br />

01311 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


11. Effect of proposed project changes (if any) on construction schedule and coordination.<br />

12. Temporary facilities and services.<br />

13. Jobsite housekeeping and cleanliness.<br />

D. Documentation: Record minutes of conference and distribute copies to Wal-Mart Construction Manager,<br />

participants, and those affected by decisions made, 2 working days after conference date. Recording, producing,<br />

and distributing by Contractor.<br />

E. Construction Schedule Update: Revise construction schedule after each progress meeting where schedule<br />

revisions have been made or recognized. Issue updated schedule concurrently with report of meeting.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01311 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 102910<br />

SECTION 01320 – CONSTRUCTION PROGRESS DOCUMENTATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Progress Schedules and Reports.<br />

1.2 CONSTRUCTION PROGRESS CHART<br />

A. Progress of the Project will be monitored using bar charts. Requirements herein provide for planning and<br />

execution of the Work and are to assist the Wal-Mart Construction Manager in evaluating progress of the Work<br />

economically and chronologically.<br />

B. The Contractor shall be familiar, in detail, with the milestones listed in the Invitation to Bid. By submitting a bid,<br />

the Contractor acknowledges that the Construction milestones are feasible, reasonable, and are a workable<br />

schedule for the Work.<br />

C. Delivery times for Wal-Mart Furnished Items are specified in Section 01640. Coordinate delivery of these items<br />

with progress of the Work.<br />

D. Prior to construction, the Contractor may request reasonable changes to the Construction Progress Bar Chart,<br />

provided delivery dates specified in Section 01640 and the contract completion date are not changed. The Wal-<br />

Mart Construction Manager will review requested changes. Upon approval by Wal-Mart, Bar Chart shall become<br />

the "Approved Construction Progress Chart" by which the Contractor shall plan, organize, direct, coordinate, and<br />

execute the Work, and the basis of evaluating progress of the Work.<br />

E. If, in the opinion of the Wal-Mart Construction Manager, any of the dates specified in Section 01640 are not<br />

completed by the Contractor on or before the stated time period and after 48 hours written notice to the Contractor,<br />

Wal-Mart may proceed to carry out the work in accordance with Paragraph 13.3 of the General Conditions.<br />

F. The Contractor shall perform work directed by the Wal-Mart Construction Manager to meet the Wal-Mart contract<br />

completion date and shall maintain the original management and supervision team to continue their office and job<br />

site duties on a full-time basis through Grand Opening and/or any other time the Contractor has any work being<br />

performed on the project regardless of the date or condition of project completion.<br />

1.3 CONSTRUCTION SCHEDULE<br />

A. Using the milestones listed in the Invitation for Bids; the Contractor shall develop a detailed Construction<br />

Schedule with activity time duration in calendar days further describing his method for performing the Work. The<br />

Contractor shall review the Contractor's schedule with the Wal-Mart Construction Manager within 3 weeks from<br />

award of Contract, or at the Pre-Construction Meeting, whichever is first. Failure of the Contractor to have a<br />

construction schedule approved by the Wal-Mart Construction Manager will be considered cause to withhold<br />

progress payments.<br />

1. The milestones listed in the Invitation for Bids shall not to be construed as an indication by the Owner as to<br />

means, methods, or techniques of construction to be employed by the Contractor.<br />

2. Critical path activities shall be indicated on the Contractor's detailed construction schedule.<br />

01320 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 SCHEDULE UPDATES<br />

A. The Contractor shall provide to the Wal-Mart Construction Manager regular updated reports on the Construction<br />

Schedule as determined by the Wal-Mart Construction Manager. The Contractor shall maintain a current weekly<br />

updated detailed construction schedule in the site construction field office.<br />

1. Construction Schedule Updating: Progress information to be included in schedule updates includes actual<br />

start and finish dates, percentage complete, remaining duration or projected finish dates for all activities in<br />

progress during reporting period. Schedule updates may also include approved added activity descriptions.<br />

Updates to the schedule shall not change any milestone dates or the contract completion date.<br />

B. Periodically, at times to be determined by Wal-Mart, the Wal-Mart Construction Manager will visit the job site for<br />

a meeting with the Contractor's Project Manager and Superintendent. This meeting is to review progress to date,<br />

and to project upcoming work.<br />

C. Prior to the Contract Substantial Completion Date, Contractor shall affirm to the Owner a commitment to meet the<br />

Contract Substantial Completion Date and all obligations and conditions of the Contract on or before the agreed<br />

upon Substantial Completion Date. Contractor shall make this affirmation by completing the attached “90 day<br />

Contractor’s Commitment Letter,” which shall be signed by an officer of Contractor, and delivered to the Owner<br />

no sooner than 100 days prior to the Contract Completion Date and no later than 90 days prior to that date.<br />

1.5 RECOVERY PLAN<br />

A. Should the updated approved Construction Schedule show the Contractor to be behind schedule, the Contractor<br />

shall immediately devise a plan for recovery of lost time within one week and submit it to the Wal-Mart<br />

Construction Manager for approval. Once approved by the Wal-Mart Construction Manager, the Contractor shall<br />

immediately put the recovery plan into action.<br />

B. During the period covered by the recovery plan, the Contractor's progress will continue to be monitored against the<br />

Approved Construction Progress Chart. If the Contractor does not recover from delay as detailed in the recovery<br />

plan, Wal-Mart may exercise the option to carry out the work as specified above.<br />

C. The Contractor shall bear all costs and expenses related to recovery from the Contractor's delays, including costs,<br />

expenses, and lost sales incurred by Wal-Mart.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01320 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


[GENERAL CONTRACTOR'S LETTERHEAD]<br />

[DATE]<br />

[CM]______________, Construction Manager<br />

Wal-Mart Stores, Inc.<br />

2001 S.E. 10th Street<br />

Bentonville, AR 72756<br />

Re: [State] - [Site/City]_______; Store # ______<br />

90 day Contractor's Commitment Letter<br />

Dear [CM]__________:<br />

[Contractor] acknowledges and recognizes the importance of completing its Work on or before the Contract Substantial<br />

Completion Date and has agreed to provide all materials, equipment, supplies and personnel, services, and labor necessary to<br />

complete the Work as set forth in the Contract Documents on or before that date.<br />

[Contractor] hereby affirms its commitment to meet the Contract Substantial Completion Date of [Date], as set forth in its<br />

Construction Agreement with Wal-Mart Stores, Inc., and any amendments thereto, and further affirms that it has either met<br />

all obligations and conditions of the Contract, or shall do so prior to the agreed upon Substantial Completion Date, [Date].<br />

[Contractor] represents that the undersigned is an officer of [Contractor] and is authorized to make this commitment.<br />

[CONTRACTOR]<br />

By: ___________________<br />

Title: __________________<br />

Date: __________________<br />

01320 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 01330 (01 3300) – SUBMITTAL PROCEDURES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Submittal procedures prior to and during construction.<br />

B. Related Requirements:<br />

1. Section 01458 - Testing Laboratory Services: Submittals required for tests and inspections.<br />

2. Section 01600 - Product Requirements: Requirements for product selection and product options.<br />

3. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

4. Section 01770 - Contract Closeout: Closeout submittals.<br />

1.2 PROCESS AND RESPONSIBILITIES<br />

A. Contractor Responsibilities:<br />

1. Submit required submittals to Architect unless otherwise specified.<br />

2. Comply with submittal requirements defined within individual Sections. Submittals procedures described<br />

herein shall apply unless otherwise stated in individual Sections.<br />

3. Package each submittal appropriately for transmittal and handling.<br />

4. Identify Project, Contractor, subcontractor or supplier, product or items being submitted, pertinent Drawing<br />

sheet and detail numbers, and Specification Section number, as applicable.<br />

5. Assemble, coordinate, and review submittals of subcontractors, suppliers, and manufacturers.<br />

6. Review submittal for verification of products required, field dimensions, adjacent construction, and<br />

coordination of information.<br />

7. Apply Contractor's Submittal Review stamp, signed or initialed and dated, certifying compliance with<br />

Contract Documents.<br />

8. Identify email transmittal of submittals in the subject line as follows:<br />

a. Walmart, Street, City, State, Store #, Store type (“SC” Super Center, “Sam’s” Sam’s Club, “NM”<br />

Market), Submittal name (e.g., concrete mix design, sieve analysis, etc.), Date of Submittal.<br />

9. Forward executed copy of Submittal Review Form to supplier within 5 days after receipt of submittal with<br />

copies to Architect and Walmart's Construction Manager.<br />

10. Schedule submittals to expedite the Work. Coordinate submission of related items into single submittal.<br />

11. Submit submittals items required within an individual Specification Section into a single submittal.<br />

12. Identify variations from Contract Documents and limitations of product and system which may be<br />

detrimental to successful performance of the completed Work.<br />

13. Provide space on submittal for Contractor, Architect, and Architect's Consultant review stamps.<br />

14. Allow 10 working days for review.<br />

15. Revise and resubmit submittals when required. Identify changes made since previous submittal.<br />

16. Notify Vendor or Subcontractor of approval by Authority Having Jurisdiction of Deferred Submittal<br />

package.<br />

17. Distribute copies of reviewed submittals to concerned parties and to Record Documents file. Instruct<br />

parties to promptly report inability to comply with provisions.<br />

B. Supplier Responsibilities - Owner Furnished Products:<br />

1. Subcontractors, vendors, and suppliers (including suppliers of Owner furnished products) shall forward<br />

copies of submittals to the Contractor.<br />

2. Prepare submittals in accordance with requirements in individual Specification Sections and Contractor<br />

responsibilities specified herein.<br />

C. Architect Responsibilities: Review submittals and take appropriate action as follows.<br />

1. Shop Drawings and Product Data: Architect will mark submittals to indicate appropriate action.<br />

2. Return reviewed Submittals to Contractor by mail carrier service providing delivery tracking.<br />

01330 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Submittals for Information: Architect will not return submittals sent for information only.<br />

4. Forward submittals to proper sub-consultant for review as necessary.<br />

D. Unrequested Submittals: Submittals transmitted to Architect or Architect's Consultants that are not indicated or<br />

requested will not be reviewed. Architect will dispose of unrequested submittal items.<br />

1.3 TRANSMITTAL<br />

A. Transmit each submittal using a transmittal form. Submit to Architect unless indicated otherwise.<br />

1. Transmit submittals to be reviewed by Architect to:<br />

Team Walmart<br />

P+R ARCHITECTS<br />

111 W. Ocean Blvd., 21 st Floor<br />

Long Beach, CA 90802<br />

FAX (562) 901-1540<br />

Attn: SUBMITTAL REVIEWER<br />

2. Transmit submittals to be submitted directly to Structural Engineer of Record to:<br />

Structural Consultant<br />

Wallace Engineering<br />

200 East Brady Street<br />

Tulsa, Oklahoma 74103<br />

cjohnson@wallacesc.com<br />

Attn: SUBMITTAL REVIEWER<br />

3. Transmit 3 copies of fire protection submittals to the Owner’s Fire Protection Consultant listed below<br />

within 30 day of prime contract award. Send one copy of the submittal transmittal to the Architect listed<br />

above.<br />

James E. Cooper<br />

1805 North Second Street, Suite 3857<br />

Rogers, AR 72756<br />

(479) 619-3857<br />

Attn: SUBMITTAL REVIEWER<br />

4. Transmit sitework submittals directly to Owner's Civil Engineering Consultant of Record listed on first<br />

page of Division 2.1 "Walmart Sitework Specifications".<br />

B. In addition to recipients stated above, transmit submittals to those parties as may be required in the individual<br />

specification section.<br />

1.4 DEFERRED SUBMITTALS<br />

A. Definition: Deferred Submittal are submittals required by the AJH for code compliance but which, rather than<br />

being submitted at the time of permit application, have been allowed by the AHJ to be deferred until after Contract<br />

award to enable the successful Contractor, Subcontractor, or Supplier to submit the applicable submittals.<br />

B. Submit the deferred submittals to the extent indicated on the Deferred Submittal Table located on the Drawing<br />

Cover Sheet.<br />

C. Prepare submittals in accordance with requirements stated in the applicable individual Specifications Sections and<br />

the applicable requirements herein:<br />

D. Process:<br />

1. Immediately after award of the Contract, the Contractor shall contact the AHJ to coordinate and determine<br />

the AHJ requirements for deferred submittals. Information obtained shall include such requirements as<br />

number of copies; extent of detail of information to be submitted; review, if required, by Professional of<br />

Record (Architect or Engineer); and other necessary process and procedural requirements.<br />

2. The Contractor, or other entity, responsible for the submittal shall submit, track, and report submittal status<br />

to the Walmart Construction Manager through final approval and issue of permit.<br />

01330 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Communicate with vendors, suppliers, and Subcontractors the AHJ requirements for deferred submittals.<br />

Receive, review, and stamp submittals in accordance with submittal requirements herein.<br />

4. Transmit deferred submittals directly to AHJ unless otherwise requested by AHJ to obtain prior review and<br />

approval by Professional of Record.<br />

5. Upon approval by AHJ, obtain permits and pay permit fees and other fees required by the AHJ.<br />

6. Attach approved deferred submittals to the approved "Permit Set" documents at the project site.<br />

7. Do not install deferred submittals until corresponding submittal documents have been approved by the<br />

AHJ.<br />

1.5 SUBMITTAL REQUIREMENTS<br />

A. Shop Drawings:<br />

1. Submit Drawings with graphic information at accurate scale. Show dimensions and note which dimensions<br />

are based on field measurement. Identify materials and products in Work shown. Indicate compliance with<br />

specified standards and special coordination requirements. Do not use reproductions of Contract Drawings<br />

as Shop Drawings.<br />

2. Include on each Shop Drawing the drawing title, number, original issue date, and revision numbers and<br />

dates, in addition to other required identifying information.<br />

3. Identify details by reference to sheet, detail, schedule, or room names shown on the Contract Drawings.<br />

4. Identify numerical values in English units.<br />

5. Size: Not less than 8-1/2 by 11 inches nor more than 30 by 42 inches.<br />

a. For Shop Drawings submitted on sheets larger than 8-1/2 x 11 inches, submit reproducible<br />

transparency and blueline or blackline reproduction.<br />

b. For Shop Drawings submitted on sheets 8-1/2 x 11 inches, conform to requirements for Product<br />

Data and submit as a bound volume for submittal required.<br />

6. Number of Copies Required: Submit one reproducible transparency and one blueline or blackline<br />

reproduction. Submit additional copies to AHJ for approval if required. Comply with requirements of AHJ<br />

with regard to signing and sealing of submittals by Registered Professional licensed in the State in which<br />

project is located.<br />

a. One copy will be returned to the Contractor.<br />

b. Structural Steel, Bar Joists and Joist Girders, and Steel Roof Deck: Contractor shall submit Shop<br />

Drawings directly to Structural Engineer of Record via email.<br />

B. Product Data:<br />

1. Manufacturer's standard schematic drawings and diagrams:<br />

a. Clearly mark to identify pertinent products.<br />

b. Show performance characteristics and capacities.<br />

c. Show dimensions and clearances required.<br />

d. Show wiring or piping diagrams and controls.<br />

e. Modify drawings and diagrams to delete information not applicable to this work.<br />

f. Supplement standard drawings and diagrams to provide complete information applicable to this<br />

work.<br />

2. Mark each copy to identify applicable products, models, options, and other data. Supplement Product Data<br />

with material prepared for the Work to satisfy submittal requirements for which Product Data does not<br />

exist. Note that the material is developed specifically for this Contract.<br />

3. Submit Product Data for each Section as a complete, bound volume. Include table of contents listing page<br />

and catalog item numbers for Product Data.<br />

4. Indicate, by prominent contrasting color notation on each product being submitted, the Specifications<br />

Section and paragraph numbers to which it pertains.<br />

5. Where printed Product Data includes information on several products, some of which are not required,<br />

mark copies to indicate information applicable to Work and clearly cross out other information not<br />

applicable to Work. Include the following information:<br />

a. Manufacturer's printed recommendations or instructions.<br />

b. Compliance with referenced standards.<br />

c. Application of testing agency labels and seals.<br />

d. Notation of dimensions verified by field measurement.<br />

e. Notation of coordination requirements.<br />

01330 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


6. Product Data For Information: Written information not requiring action by Walmart Construction Manager<br />

or Architect; for verification of compliance with requirement. Submittal not complying with requirements<br />

will be rejected.<br />

7. Number of Copies Required: Four.<br />

C. Engineering Calculations:<br />

1. Submit calculations signed and sealed by a Registered Professional Engineer licensed in the State where<br />

project is located. Comply with requirements of Authority Having Jurisdiction with regard to signing and<br />

sealing of submittals.<br />

D. Certifications:<br />

1. Certify manufacturer's or installer's qualifications, compliance with tests or specified criteria, or other<br />

factors as required in individual Specification Sections.<br />

2. Submit supporting reference data, affidavits, and certifications as required.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01330 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 062510<br />

SECTION 01432 (01 4323) – ELECTRICAL INSTALLER QUALIFICATIONS<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Qualification requirements for work performed on electrical conductors and equipment.<br />

B. Related Requirements:<br />

1. General Conditions: Inspections, testing, and approvals required by public authorities.<br />

1.2 DEFINITIONS<br />

A. Electrical Worker: For the purposes of the requirements of this Section, electrical workers are defined as those<br />

workers who perform work on the Project on electrical conductors of 50 volts or greater and electrical equipment<br />

of 50 volts or greater.<br />

1.3 SUBMITTALS<br />

A. Certification: Submit Certification of Compliance stating that electrical workers will meet qualifications stated<br />

herein.<br />

B. Statement: Submit statement of anticipated non-compliance, if applicable, and proposed alternative procedure as<br />

specified below.<br />

1.4 CONTRACTOR QUALIFICATIONS<br />

A. Electrical workers, as defined above, doing work on the Project shall be either:<br />

1. a licensed electrician or<br />

2. an apprentice working under an approved governmental or trade organization apprenticeship program<br />

whose work is being directly overseen by a licensed electrician.<br />

B. If state or local requirements or industry standards require more stringent qualifications of electrical workers than<br />

the minimum requirements stated above, the electrical workers shall possess such qualifications required by such<br />

State or local requirements or industry standards in lieu of the minimum requirements stated in this Section.<br />

C. If Contractor, subcontractor, or any sub-subcontractor fails to meet the above qualifications on the Project, then<br />

Owner may, without limitation, at Owner's sole discretion:<br />

1. prevent Contractor from participating on bids with regard to additional Owner projects for a minimum of<br />

90 days for the first violation of the above-stated requirement; and<br />

2. permanently suspend Contractor from bidding on future Owner projects for violation of the above stated<br />

requirements two or more times.<br />

D. If Contractor believes, based upon its experience and judgment, that compliance with requirements of this Section<br />

cannot reasonably be achieved, Contractor shall provide Owner with written notification stating why Contractor<br />

believes compliance cannot be achieved and stating how Contractor proposes to proceed with electrical work on<br />

the Project.<br />

PART 2 PRODUCTS<br />

Not Used.<br />

01432 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01432 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 01452 (01 4517) – CONTRACTOR’S QUALITY CONTROL<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Administrative and procedural requirements for Contractor quality assurance and quality control.<br />

B. Related Requirements:<br />

1. General Conditions: Inspections, testing, and approvals required by public authorities.<br />

2. Section 01454 - Architect-Engineer Quality Assurance: Site observation by Owner’s Architect and<br />

Engineer Consultants except Civil Engineering Consultant.<br />

3. Section 01455 - Testing, Adjusting, and Balancing: Wal-Mart procurement of test and balance for heating,<br />

ventilating, and air conditioning systems.<br />

4. Section 01456 - Civil Engineering Consultant Quality Assurance Observation: Site observation by<br />

Owner’s Civil Engineering Consultant.<br />

5. Section 01458 - Testing Laboratory Services: Quality Requirements of Owner’s Construction Testing<br />

Laboratory (CTL) and services.<br />

6. Section 01770 - Contract Closeout: Project Record Documents.<br />

C. Contractor testing and inspection are required to verify compliance with requirements specified or indicated.<br />

These services do not relieve Contractor of responsibility for compliance with the Contract Document<br />

requirements.<br />

1. Contractor testing and inspection includes testing or inspection to be performed by and under the<br />

responsibility of the General Contractor as well as that required by the manufacturer, manufacturer’s<br />

representative, product supplier, or other party under the responsibility of the Contractor.<br />

2. Requirements in this section are independent of testing and inspection specified for the Owner’s<br />

Construction Testing Laboratory (CTL) specified in Section 01458. Testing and inspection by the CTL<br />

will be paid for by the Owner at performed at no cost to the Contractor.<br />

3. Specific quality-assurance and -control requirements for individual construction activities are specified in<br />

the Sections that specify those activities. Requirements in those Sections may also cover production of<br />

standard products.<br />

4. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -<br />

control procedures that facilitate compliance with the Contract Document requirements.<br />

5. Requirements for Contractor to provide quality-assurance and -control services required by Architect,<br />

Owner’s CTL, Wal-Mart Construction Manager, or authorities having jurisdiction are not limited by<br />

provisions of this Section.<br />

1.2 DEFINITIONS<br />

A. Testing: Evaluation of systems, primarily requiring physical manipulation and analysis of materials, in accordance<br />

with approved standards.<br />

B. Inspection: Evaluation of systems primarily requiring observation and engineering judgement.<br />

C. Quality Assurance: Activities, actions, and procedures performed before and during execution of the Work to<br />

guard against defects and deficiencies and substantiate that proposed construction will substantially comply with<br />

construction documents.<br />

D. Quality Control: Tests, inspections, procedures, and related actions during and after execution of the Work to<br />

evaluate that actual products incorporated into the Work and completed construction substantially comply with<br />

construction documents.<br />

01452 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Quality assurance and quality control may be performed by either the Contractor or the Construction Testing<br />

Laboratory employed by the Owner.<br />

F. Mockups: Full-size, physical assemblies that are constructed on-site. Mockups are used to verify or demonstrate<br />

aesthetic effects and, where indicated, qualities of materials and execution, and to review construction,<br />

coordination, testing, or operation; they are not Samples. Approved mockups establish the standard by which the<br />

Work will be judged.<br />

G. Architect of Record (AOR): The prime consultant in charge of overall design and coordination of the building.<br />

H. Engineer of Record (EOR): The Registered Engineer in responsible charge of engineering design for the project.<br />

I. Structural Engineer of Record (SER): The Registered Engineer in responsible charge of the structural design for<br />

the project.<br />

J. Civil Engineering Consultant (CEC): The Registered Engineer in responsible charge of the civil design for the<br />

project.<br />

K. Architect - Engineer (A/E): A collective term to include the AOR, CEC, SER, and the Mechanical, Electrical, and<br />

Fire Protection EOR.<br />

L. Construction Testing Laboratory (CTL): The independent testing and inspection agency employed by the Owner.<br />

M. Independent Test and Balance Agent (ITBA): The independent HVAC testing and balancing agency employed by<br />

the Owner.<br />

N. Special Inspector (SI): The Special Inspector under the direct supervision of a registered civil/structural engineer<br />

(unless otherwise specified) regularly engaged in inspection, and experienced with the type of work requiring<br />

related testing and inspection. The categories of special inspector are specified in Section 01458.<br />

O. Building Official: The Officer or his duly authorized representative charged with the administration and<br />

enforcement of the local building code.<br />

P. Deviation: A deviation is any item or component of work that does not substantially conform to the requirements<br />

of the construction documents and which has not been corrected by the end of business on the day it is identified.<br />

1.3 CONFLICTING REQUIREMENTS<br />

A. General: If compliance with two or more standards is specified and the standards establish different or conflicting<br />

requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer<br />

uncertainties and requirements that are different, but apparently equal, to Architect/Engineer for a decision before<br />

proceeding.<br />

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum<br />

provided or performed. The actual installation may comply exactly with the minimum quantity or quality<br />

specified, or it may exceed the minimum within reasonable limits. Refer uncertainties to Architect/Engineer for a<br />

decision before proceeding.<br />

1.4 SUBMITTALS<br />

A. Test and Inspection Reports:<br />

1. Site Work Testing and Inspection: After each inspection or test, distribute report within 3 working days of<br />

time services were performed as follows:<br />

a. Site Work Civil Engineering Consultant (CEC): 1 copy.<br />

b. Building Official: Quantities as required.<br />

c. Owner.<br />

01452 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Building Testing and Inspection: After each inspection or test, distribute report within 3 working days of<br />

time services were performed as follows:<br />

a. Structural Engineer of Record (SER): 1 copy (Construction Administration Leader).<br />

b. Building Official: Quantities as required.<br />

c. Owner.<br />

d. Architect of Record: 2 copies (Construction Administration Leader).<br />

3. Report of non-conforming work.<br />

1.5 REPORTS<br />

A. Submit reports as required herein and conduct and interpret tests and inspections.<br />

B. Testing and Inspection Report: Submit test and inspection reports including the following information:<br />

1. Date issued.<br />

2. Project title and number.<br />

3. Store number.<br />

4. Firm name and address.<br />

5. Name and signature of tester or inspector.<br />

6. Name and seal of registered engineer in responsible charge (as applicable).<br />

7. Date and time of sampling.<br />

8. Date of test or inspection.<br />

9. Identification of product and specification section.<br />

10. Location in project, including elevations, grid location and detail.<br />

11. Type of test or inspections.<br />

12. Results of tests or inspections and interpretation of same.<br />

13. Observations regarding compliance with Contract Documents or deviations therefrom.<br />

C. Submit a separate final signed report stating whether the work requiring inspection is, to the best of the inspector's<br />

knowledge, in conformance with the approved plans, specifications, and the applicable workmanship provisions of<br />

the building code.<br />

D. Reports shall be made on 8-1/2 by 11 white paper, suitable for photocopying and binding in booklet form. Sheets<br />

shall have the Contractor’s letterhead (including phone number and address). Larger sheets shall be folded and<br />

bound into the booklet.<br />

E. Tests and inspections reports indicating non-conformance (deviations) to the Contract Documents shall be brought<br />

to the attention of the A/E within 24 hours upon discovery.<br />

F. Contractor shall send an RFI to the A/E on the same day of non-conformance (deviation) notification.<br />

1.6 QUALITY CONTROL<br />

A. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect<br />

field-assembled components and equipment installation, including service connections. Report results in writing<br />

as specified in Division 1 Section "Submittal Procedures".<br />

B. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility,<br />

provide quality-control services, including retesting and reinspecting, for construction that replaced Work that<br />

failed to comply with the Contract Documents.<br />

1.7 OWNER RESPONSIBILITIES<br />

A. Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing<br />

agency to perform these services.<br />

1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged<br />

and a description of types of testing and inspecting they are engaged to perform.<br />

01452 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to<br />

comply with the Contract Documents will be charged to Contractor, and the Contract Sum will be adjusted<br />

by Change Order.<br />

1.8 CONTRACTOR RESPONSIBILITIES<br />

A. Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Unless otherwise indicated,<br />

provide quality-control services specified and those required by authorities having jurisdiction. Perform qualitycontrol<br />

services required of Contractor by authorities having jurisdiction, whether specified or not.<br />

B. Where a third party service is specified, engage a qualified testing agency to perform these quality-control<br />

services. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.<br />

C. Contractor shall pay for:<br />

1. Tests and inspections at the source or prior to incorporation into the Work of materials, products, or<br />

equipment to certify compliance with Contract Documents.<br />

2. Additional tests, samples, inspection, or engineering services the Contractor determines appropriate for<br />

performance of Work or for Contractor's convenience.<br />

3. Additional tests and inspections when initial tests or inspections indicate Work does not comply with<br />

Contract Documents.<br />

4. Tests and inspections required or conducted by public authorities as part of permits or inspection fees.<br />

5. Other tests and inspections indicated to be "by Contractor".<br />

D. Provide incidental labor and facilities to provide access to Work to be tested, to obtain and handle samples at the<br />

site or at source of products to be tested, to facilitate tests and inspections, and to provide storage and curing of test<br />

samples. Provide lift equipment as required for inspection personnel of the Owner or the Owners’s<br />

representatives.<br />

E. Provide 14 days written notice to A/E prior to expected time for operations requiring observation, inspecting, and<br />

testing. If work to be observed is covered prior to notification, uncover work as required.<br />

F. Notify in writing the Wal-Mart Construction Manager three working days prior to expected time for operations<br />

requiring inspecting and testing services.<br />

G. Repair and protect the work regardless of assignment of responsibility for inspection, testing, or similar services.<br />

1. Protect work exposed by or for quality assurance and quality control service activities.<br />

2. Upon completion of inspection, testing, sample-taking, and similar services, restore constructed areas to<br />

conform to Contract Documents.<br />

H. Costs, including without limitation additional professional fees and expenses, of any required redesign or reengineering<br />

required by non-conforming tests and inspections will be deducted from the sum due the Contractor.<br />

I. Provide a Letter of Conformance at the completion of the Project to the Wal-Mart Construction Manager, with<br />

copy to the AOR, stipulating that the Project has been built per the Contract Documents.<br />

J. Maintain a copy of Contract Drawings and Specifications with all Addenda and Change Orders. Use the Contract<br />

Documents supplemented by the approved shop drawings and applicable material and workmanship provisions of<br />

the Code for testing and inspection of the work.<br />

K. Provide qualified personnel at site to comply with schedule and submit reports for each test and inspection as<br />

defined in Part 3 of this Section.<br />

L. Perform specified inspection, sampling, and testing of products in accordance with specified standards.<br />

M. Ascertain compliance of materials and mixes with requirements of Contract Documents.<br />

N. Perform testing and inspection in a timely manner to avoid delay of work.<br />

01452 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


O. Notify Wal-Mart Construction Manager and CEC or AOR, as applicable of observed non-conformance of Work or<br />

Products. If observed deviations from the Contract Drawings, Specifications, or building code will be probable<br />

cause of subsequent rejection of work or material, notify the Wal-Mart Construction Manager and,CEC or AOR<br />

sufficiently in advance for determination to continue operations or take corrective measures before continuing.<br />

P. Deviations from the Contract Documents will be entered into the on-line Wal-Mart Observation Log by other<br />

parties performing Quality Control construction observation. The Contractor shall track deviations, as defined<br />

above, and resolutions and remedial repairs to deviations and subsequent conformance to the Contract Documents<br />

on the Observation Log (www.bldgportal.com, enter username and password, select Observation Log). Follow<br />

instructions on the Observation Log website.<br />

Q. The Wal-Mart Construction Manager in conjunction with the CTL and/or SI will determine when to involve the<br />

AOR or EOR for remedial action.<br />

R. Perform retesting due to non-conformance with the Contract Documents.<br />

S. Costs for retesting performed by the CTL due to non-conformance with the Contract Documents will be deducted<br />

from the Sum due the Contractor.<br />

T. If additional A/E site or FPT visits are required beyond those described in Section 01454 as determined by Wal-<br />

Mart to determine correction to non-conforming work, the Contractor shall reimburse the Owner the sum of $4000<br />

for each additional visit to cover A/E expenses. Additional A/E site observations or FPTs will be performed as<br />

required until all deviations have been corrected by the Contractor and closed by the A/E consultant.<br />

U. If ITBA retesting visits are required as described in Section 01455 as determined by Wal-Mart to determine<br />

correction to non-conforming work, the Contractor shall pay to ITBA the sum of $6500 for each retesting visit to<br />

cover ITBA expenses. ITBA retesting visits will be performed as required until all deviations have been corrected<br />

by the Contractor and closed by the ITBA and/or A/E consultant.<br />

V. Cooperate with CTL/SI personnel, and provide access to the Work and to Contractor’s facilities.<br />

W. Submit test and inspection reports to the A/E consultant and other designated persons as specified in individual<br />

sections. Submit test and inspection reports to the Building Official as required.<br />

X. Provide a final conformance letter to Wal-Mart. An example is attached at the end of this section.<br />

Y. Testing and inspection by the Building Official does not preclude the normal field involvement and site<br />

observations by the A/E consultant, nor shall it relieve the Contractor of any responsibility to complete the work in<br />

accordance with the approved drawings and specifications.<br />

PART 2 PRODUCTS<br />

Not Used.<br />

PART 3 EXECUTION<br />

3.1 PRODUCTION TESTING<br />

A. General Requirements:<br />

1. Testing shall be conducted as specified in the individual specification sections.<br />

2. If inspection of fabricators work is required, the Owner's representative may require testing and inspection<br />

of the work at the plant, before shipment. Owner, Architect, and Structural Engineer of Record (SER)<br />

reserve the right to reject material not complying with the Contract Documents.<br />

3. Testing and inspection shall be performed in accordance with the industry standard used as the reference<br />

for the specific material or procedure unless other criteria are specified. In the absence of a referenced<br />

standard, tests shall be accomplished in accordance with generally accepted industry standards.<br />

01452 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


END OF SECTION<br />

4. Work shall be checked as it progresses, but failure to detect any defective work or materials shall in no way<br />

prevent later rejection if defective work or materials are discovered, nor shall it obligate Owner to accept<br />

such work.<br />

01452 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


[Example Conformance Letter from Contractor. Text in parentheses are to be edited for each individual project]<br />

[Date]<br />

[Mr. Construction Manager]<br />

Wal-Mart Construction<br />

Sam M. Walton Development Complex<br />

2001 S. E. 10 th Street<br />

Bentonville, Arkansas 72716<br />

[Re: Supercenter (Store #xxx) – City, State]<br />

[Dear Construction Manager:]<br />

The purpose of this letter is to state to Wal-Mart Stores, Inc. that, to the best of our knowledge, the construction on the above<br />

referenced project has been completed in substantial conformance with the approved Contract Documents.<br />

We performed construction testing, observation, and testing as required by the Contract Document. To our knowledge,no<br />

outstanding items exist except as may be otherwise entered and shown on the Wal-Mart Observation Log.<br />

Sincerely,<br />

[GENERAL CONTRACTOR]<br />

[Include signature and date of signature]<br />

cc:<br />

File<br />

[ARCHITECT OF RECORD]<br />

[ENGINEER OF RECORD]<br />

01452 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 012811<br />

SECTION 01454 (01 4518) – ARCHITECT-ENGINEER QUALITY ASSURANCE<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Quality assurance site observation of construction by Architect and Engineers of Record including the<br />

Architect; Mechanical, Refrigeration, Electrical, Structural, and Fire Protection Engineers; and the Grocery<br />

Consultant, but excluding the Civil Engineering Consultant. Civil Engineering Consultant quality<br />

assurance is specified in Section 01456.<br />

2. Functional Performance Test (FPT) by Engineers of Record.<br />

3. Work required herein is not the responsibility of the Contractor and will be performed at no cost to the<br />

Contractor, except as otherwise specified. Provisions included herein are for information purposes only to<br />

provide the Contractor knowledge of the presence and responsibility of the Wal-Mart Architectural and<br />

Engineering Consultants.<br />

B. Related Requirements:<br />

1. General Conditions: Inspections, testing, and approvals required by public authorities.<br />

2. Section 01452 - Contractor Quality Control: Administrative and procedural requirements for Contractor<br />

quality assurance and quality control.<br />

3. Section 01455 - Testing, Adjusting, and Balancing: Wal-Mart procurement of test and balance for heating,<br />

ventilating, and air conditioning systems.<br />

4. Section 01456 - Civil Engineering Consultant Quality Assurance Observation: Site observation by<br />

Owner’s Civil Engineering Consultant.<br />

5. Section 01458 - Construction Laboratory Testing Services: Quality Requirements of Owner’s Construction<br />

Testing Laboratory (CTL) and services.<br />

1.2 DEFINITIONS<br />

A. Observation: Evaluation of systems primarily requiring observation and professional judgement.<br />

B. Quality Assurance: Activities, actions, and procedures performed before and during execution of the Work to<br />

guard against defects and deficiencies and substantiate that proposed construction will substantially comply with<br />

construction documents.<br />

C. Quality Control: Tests, inspections, procedures, and related actions during and after execution of the Work to<br />

evaluate that actual products incorporated into the Work and completed construction substantially comply with<br />

construction documents.<br />

D. Quality assurance and quality control may be performed by either the Contractor or the Construction Testing<br />

Laboratory employed by the Owner.<br />

E. Architect of Record (AOR): The prime consultant in charge of overall design and coordination of the building.<br />

F. Engineer of Record (EOR): The Registered Engineer in responsible charge of engineering design for the project.<br />

G. Structural Engineer of Record (SER): The Registered Engineer in responsible charge of the structural design for<br />

the project.<br />

H. Civil Engineering Consultant (CEC): The Registered Engineer in responsible charge of the civil design for the<br />

project.<br />

I. Architect - Engineer (A/E): A collective term to include the AOR, SER, Grocery Consultant, and the Mechanical,<br />

Refrigeration, Electrical, and Fire Protection EOR.<br />

01454 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


J. Grocery Consultant: Consultant that provides professional design services and construction documents related to<br />

grocery design for the project.<br />

K. Fire Protection Consultant: Consultant that provides professional design services and construction documents<br />

related to fire protection for the project.<br />

L. Construction Testing Laboratory (CTL): The independent testing and inspection agency employed by the Owner:<br />

M. Building Official: The Officer or his duly authorized representative charged with the administration and<br />

enforcement of the local building code.<br />

N. Deviation: A deviation is any item or component of work that does not substantially conform to the requirements<br />

of the construction documents and which has not been corrected by the end of business on the day it is identified.<br />

O. Functional Performance Test (FPT): On-site testing by the EOR of the installed mechanical, refrigeration, EMS,<br />

and electrical systems.<br />

1.3 COORDINATION WITH CONTRACTOR<br />

A. The Contractor will:<br />

1. Cooperate with A/E personnel and provide access to the Work and to Contractor’s facilities.<br />

2. Provide incidental labor and facilities to provide access to Work to facilitate observation and testing.<br />

Provide lift equipment as required for A/E personnel.<br />

3. Provide A/E 14 days written notice prior to expected time for activities requiring observation and FPT<br />

services.<br />

4. Maintain a copy of Contract Drawings and Specifications with all Addenda and Change Orders<br />

supplemented by the approved shop drawings and applicable material and workmanship provisions of the<br />

Code for use by the A/E.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

3.1 QUALITY ASSURANCE OBSERVATION<br />

A. The A/E will perform construction site observations and the FPT as agreed to with the Owneras listed below or as<br />

otherwise requested by the Authority Having Jurisdiction or Wal-Mart Construction Manager to check a sample of<br />

the constructed Workfor general conformance with the Contract Documents.<br />

01454 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


WAL-MART A/E CONSULTANT QUALITY ASSURANCE OBSERVATION/FPT SCHEDULE<br />

Consultant 1 st Visit* 2 nd Visit* 3 rd Visit* 4 th Visit* FPT<br />

Architectural<br />

Structural<br />

Mechanical<br />

Energy<br />

Management<br />

3 to 4 wks after<br />

const start<br />

(Foundation)<br />

4 to 6 wks after<br />

const start<br />

(Foundation)<br />

During underground<br />

rough-in<br />

Approximately every 6 wks for remaining duration of<br />

construction<br />

12 – 14 wks<br />

(CMU Walls)<br />

During<br />

overhead<br />

rough-in<br />

8 to 12 wks<br />

(Structural steel)<br />

6 to 12 wks<br />

(Final)<br />

1 to 2 wks -- 4 wks after<br />

Poss Date<br />

1 to 2 wks 4 wks after<br />

Poss Date<br />

Fire Protection 6 to 8 wks 1 to 2 wks 1 to 2 wks after Poss<br />

Date<br />

Electrical<br />

During overhead<br />

rough-in<br />

4 to 6 wks 1 to 2 wks -- 4 wks after<br />

Poss Date<br />

Sub-metering 1 to 2 wks 4 wks after<br />

Poss Date<br />

--<br />

Refrigeration<br />

Grocery<br />

Consultant<br />

1 to 2 wks<br />

after system startup<br />

1 to 2 wks 1 to 2 wks<br />

after Poss<br />

Date<br />

1 wk after GO<br />

Date<br />

* All visits are shown as weeks prior to possession unless otherwise noted.<br />

B. Time frames listed in the above schedule are general in nature.<br />

C. Specific items to be witnessed during the construction site observation (including but not limited to) are listed<br />

below in more detail by discipline to assist in scheduling the site observation at the proper time.<br />

D. Architectural: Architectural consultant site observation shall be by a competent representative of the AOR having<br />

complete knowledge of the project.<br />

1. Verify roof membrane installation, roof drainage system, anchoring of roof-top equipment, flashing, and<br />

exterior paint.<br />

2. Verify egress compliance, fire stopping, integrity of building envelope, sealing of floor cracks, cleanability,<br />

health department compliance, and proper sealants.<br />

3. Review architecturally related construction documents currently used by the Contractor to assure that<br />

revisions and Construction Change Directives are incorporated and executed.<br />

4. Review, discuss and address outstanding Requests for Information (RFI).<br />

5. Review and discuss with the Contractor, Construction Change Directives, Construction Bulletins, and<br />

Preliminary Change Order Budget (PCOB) to assure the correct scope of work is understood and included.<br />

6. Observe construction in progress and work completed, to determine if project is being constructed to meet<br />

the requirements of the Construction Documents. Report deviations on the on-line Observation Log.<br />

7. Review and discuss with the Contractor, outstanding permit applications made by the AOR and<br />

requirements of existing permits applied for or received by the AOR.<br />

01454 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


8. Documentation:<br />

a. Summarize observations with Contractor before leaving the site.<br />

b. Contact Walmart Construction Manager within 1 business day by e-mail or phone to provide a brief<br />

summary of site observation.<br />

c. Provide Contractor and Walmart Construction Manager a written summary of the site observation<br />

within 2 business days.<br />

d. Record newly noted deviations and mark previously noted deviations if found to be in substantial<br />

conformance.<br />

E. Structural:<br />

1. 1 st Visit: Verify vertical reinforcing, control joint placement, foundation sizes, and anchor bolt placement.<br />

2. 2 nd Visit: Verify CMU placement, grouting procedures, and vertical and horizontal reinforcing.<br />

3. 3 rd Visit: Verify Structural steel connections, damage to structural steel members, roof decking attachment,<br />

and grouting voids.<br />

4. 4 th Visit: Verify structural steel connections, slab placement, and repair of previous deviations.<br />

F. Mechanical:<br />

1. 1 st Visit: Verify underground plumbing rough-in, grease/oil separator installation, and underground utility<br />

building entrances.<br />

2. 2 nd Visit: Verify types of plumbing materials, roof-top unit installation, above slab plumbing rough-in, and<br />

ductwork installation.<br />

3. 3 rd Visit: Final finish out (diffusers, escutcheons) and final equipment installation.<br />

4. 1 st FPT: Test operation and control of mechanical HVAC equipment.<br />

G. Energy Management:<br />

1. 1 st Visit (coordinate timing with 3 rd Mechanical Visit): Verify EMS cable is installed in conduit, wires<br />

labeled, wires landed on correct points, and correct number of wires in the conduit.<br />

2. 1 st FPT: Test operation and control of energy management system.<br />

H. Fire Protection:<br />

1. 1st Visit: Verify type of material, progress of installation (rough-in should be complete and ready for<br />

ceiling paint), underground stub-up, main locations and elevations, hanger and hanger spacing and if<br />

possible re-verify available water supply.<br />

2. 2 nd Visit: Verify the fire sprinkler systems are in conformance with the Contract Documents and shop<br />

drawings, review sprinkler head locations, main and branchline installation, and system testing.<br />

3. 3 rd Visit: Review correction of deviation issues.<br />

I. Electrical:<br />

1. 1 st Visit: Verify underground utilities.<br />

2. 2 nd Visit: Verify lighting, conduit routing and materials, and device locations.<br />

3. 3 rd Visit: Verify panels, circuiting, lighting, grounding, and exit signs.<br />

4. 1 st FPT: Test operation and control of electrical equipment.<br />

J. Sub-metering:<br />

1. 1 st Visit: Verify sub-metering contractor has been scheduled.<br />

2. 1 st FPT: Test operation and control of electrical equipment.<br />

K. Refrigeration:<br />

1. 1 st Visit: Pre-FPT test for refrigeration circuit operation, rack I/O operation, control parameters and sensor<br />

calibration verification.<br />

2. 1 st FPT: Test operation and control of mechanical refrigeration equipment.<br />

L. Grocery: If the AOR uses a Subconsultant to provide grocery design, the same Subconsultant shall perform the<br />

grocery construction site visit.<br />

1. 1 st Visit: Verify types of materials, progress of installation of equipment, finishes, and sealants.<br />

2. 2 nd Visit: Verify installation of equipment, proper placement of moveable equipment, proper sealants<br />

installed, all finishes and surfaces are sealed and easily cleanable.<br />

01454 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


M. The A/E shall monitor the construction schedule and coordinate with the Contractor to schedule site visits to occur<br />

at the most appropriate time. The A/E shall notify the Contractor and Walmart Construction Manager in advance<br />

of the date and time of each scheduled site visit.<br />

N. Testing and inspections by the Building Official shall not preclude the normal field involvement and site<br />

observations by the A/E, nor will it relieve the Contractor of any responsibility to complete the work in accordance<br />

with the approved drawings and specifications.<br />

O. The A/E shall not have control over or responsibility for construction means, techniques, sequences of operations<br />

or for safety programs and procedures in connection with the construction work.<br />

P. The A/E shall provide a final conformance letter to Wal-Mart, at such time the AOR deems the project<br />

substantially complete. An example is attached at the end of this section.<br />

Q. Work will be checked as it progresses, but failure to detect defective work or materials shall in no way prevent<br />

later rejection if defective work or materials are discovered, nor shall it obligate Owner to accept such work.<br />

3.2 FUNCTIONAL PERFORMANCE TESTING (FPT)<br />

A. The Wal-Mart Mechanical Consultant and Electrical Consultant (EOR) will perform the FPT as agreed to with the<br />

Owneras listed above in the Wal-Mart A/E Consultant Quality Assurance Site Observation/FPT Schedule to check<br />

the mechanical, refrigeration, electrical and energy management system workfor functional operation and general<br />

conformance with the Contract Documents.<br />

3.3 DEFICIENCY PROVISIONS<br />

A. The observation and FPT site visits listed above are the maximum number of visits to be performed at Owners<br />

expense. Should there be outstanding items of non-conformance with the Contract Documents that warrant<br />

additional site visits to be performed by the A/Es, the A/Es shall receive approval from Wal-Mart prior to<br />

performing additional construction site observations or FPTs until all deviations have been corrected by the<br />

Contractor and closed by the A/E. Reimbursement by the Contractor for costs for additional A/E site visits will be<br />

as specified in Section 01452.<br />

B. Deviations from the Contract Documents shall be entered into the on-line Wal-Mart Observation Log by the A/E<br />

as required and will be tracked and noted by the A/E when resolved by subsequent conformance by the Contractor.<br />

1. Observation Log: www.bldgportal.com, enter username and password, select Observation Log. Follow<br />

instructions on the Observation Log website.<br />

01454 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


[Example Conformance Letter from Architect and Engineer Of Record. Text in parentheses are to be edited for each<br />

individual project]<br />

[Date]<br />

[Mr. Construction Manager]<br />

Wal-Mart Construction<br />

Sam M. Walton Development Complex<br />

2001 S. E. 10 th Street<br />

Bentonville, Arkansas 72716<br />

[Re: Supercenter (Store #xxx) – City, State]<br />

[Dear Construction Manager:]<br />

The purpose of this letter is to state to Wal-Mart Stores, Inc. that, to the best of our knowledge, the construction on the above<br />

referenced project has been completed in substantial conformance with the approved Contract Documents and with the<br />

provisions of the applicable building code.<br />

We performed construction observation visits and functional performance tests as agreed to by the Owner and as required by<br />

our scope of services to verify general conformance of the work. To our knowledgeand our construction observations,no<br />

outstanding items exist except as may be otherwise entered and shown on the Wal-Mart Observation Log.<br />

Sincerely,<br />

[ARCHITECTURAL FIRM ]<br />

[ENGINEERING FIRM]<br />

[Include a seal, signature and date of signature]<br />

[ARCHITECT OF RECORD]<br />

[ENGINEER OF RECORD]<br />

cc: File<br />

01454 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 01455 – MECHANICAL EQUIPMENT TESTING, ADJUSTING, AND BALANCING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Administrative and procedural requirements for test and balance services for mechanical equipment.<br />

B. Related Requirements:<br />

1. Section 01458 - Testing Laboratory Services: Owner procurement of testing laboratory services for site<br />

and building testing and inspection.<br />

2. Section 13810 - Energy Management System (EMS).<br />

3. Section 15600 - Refrigeration Systems.<br />

4. Section 15700 - Heating, Ventilating, and Air Conditioning Equipment: HVAC system equipment.<br />

5. Section 15800 - Air Distribution: HVAC system ductwork and diffusers.<br />

1.2 SELECTION AND PAYMENT<br />

A. Employment and payment for services of an Independent Test and Balance Agency (ITBA) to perform specified<br />

testing and balancing of environmental systems will be by Wal-Mart, except as otherwise specified.<br />

1.3 RESPONSIBILITIES<br />

A. Wal-Mart Responsibilities:<br />

1. Wal-Mart will obtain the services of an Independent Test and Balance Agency (ITBA) certified by National<br />

Environmental Balancing Bureau (NEBB) or Associated Air Balance Council (AABC).<br />

2. Upon completion of final system Test and Balance, a copy of ITBA report, will be uploaded to the Building<br />

Portal for the Contractor and Engineer of Record (EOR). If mechanical system deficiencies exist, those<br />

deficiencies will be listed in the Building Portal Observation Log for the Contractor's correction. If the<br />

Contractor fails to respond and correct these deficiencies within seven days, the Owner will authorize<br />

repairs as judged necessary and take necessary contractual action to recover adequate compensation for<br />

repair expenses.<br />

B. Contractor Responsibilities:<br />

1. Provide balancing dampers as specified and shown on the Drawings for proper balancing of systems.<br />

01455 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Prepare system for test and balance as follows:<br />

a. Install and adjust mechanical systems and have fully operational with deficiencies corrected two<br />

weeks prior to Wal-Mart Possession Date. Mechanical systems include roof top units (RTU), water<br />

source heat pumps (WSHP), air handling units (AHU), pump package, fluid coolers, chillers, and<br />

associated equipment and piping.<br />

b. One day prior to starting test and balance procedure, provide new filters equal in quality to factory<br />

installed filters. Filters: Class 1, 30 percent efficiency, radial pleat design with 15 pleats per linear<br />

foot.<br />

c. Verify that duct work is clean and sealed tight against leaks.<br />

d. Verify that controls, dampers, and actuators are installed, adjusted, calibrated, and accessible.<br />

e. Prior to starting test and balance, clean and flush piping for condenser water loop per specifications.<br />

f. Remove start-up strainers and clean equipment strainers after system flush is complete.<br />

g. To maintain schedules and prevent return trips, have experienced personnel available to correct<br />

mechanical system deficiencies while ITBA is on site.<br />

h. Secure control dampers after test and balance as directed by ITBA.<br />

i. Provide access to equipment and specialties required to carry out the ITBA work including<br />

providing the following:<br />

1) Access panels.<br />

2) Ladders and lifts.<br />

3) Personnel to assist with access as needed.<br />

3. Notify Wal-Mart Mechanical Services Construction Manager and ITBA when mechanical systems are<br />

ready for test and balance. If Contractor fails to notify Wal-Mart Mechanical Services Construction<br />

Manager of status, ITBA will be scheduled into store two weeks prior to Possession Date.<br />

1.4 CONTRACTOR AND ITBA COORDINATION AND SCHEDULING<br />

A. Coordination and scheduling between the Contractor and ITBA shall be as follows:<br />

1. The Contractor will be contacted by the ITBA approximately six weeks prior to Wal-Mart Possession Date.<br />

2. The initial ITBA visit date will be scheduled for one week after OEM final start-up is complete. The ITBA<br />

will schedule the initial visit with the Contractor approximately four weeks prior to date of visit.<br />

3. The Contractor shall have the mechanical systems ready for the ITBA visit at least two weeks prior to Wal-<br />

Mart Possession Date.<br />

4. The ITBA will provide a Project Information Worksheet and a Pre Test and Balance Checklist to be<br />

completed and signed by the Contractor prior to the ITBA visit. One week prior to the ITBA visit, the<br />

Contractor shall send the ITBA the signed off Pre Test and Balance Checklist. Any exceptions to the list<br />

shall be noted and reviewed with the ITBA for possible schedule changes. Worksheet and Checklist forms<br />

are included at the end of this section.<br />

5. Upon arrival at the project, the ITBA will meet with the Contractor and the mechanical and electrical subcontractors<br />

to review the project and verify all equipment is installed and operating.<br />

1.5 CORRECTION OF DEFICIENCIES<br />

A. Initial ITBA Visit:<br />

1. Each day the ITBA is on site, noted deficiencies will be provided to the Contractor in a list format for<br />

correction.<br />

2. The Contractor will sign the list to acknowledge its receipt.<br />

3. The Contractor will sign off on each listed item as it is corrected and submit the list to the ITBA when all<br />

items are corrected.<br />

B. Return ITBA Visits:<br />

1. If the items cannot be completed prior to the departure of the ITBA, a return visit will be made to verify the<br />

completion of the list and finalize the ITBA work.<br />

2. Should a return trip be necessary, the Contractor will forward the completed, signed off, deficiency list to<br />

the ITBA and schedule a return visit.<br />

3. The Contractor will have the sub-contractors present for the return visit.<br />

4. One return visit for deficiencies is included in the ITBA scope of work. Additional visits are considered<br />

retesting.<br />

01455 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.6 RETESTING<br />

A. Should the ITBA work not be completed due to non-conformance by the Contractor within the initial and return<br />

visits, retesting visits shall be made until all deficiencies are corrected. Contractor shall pay ITBA for costs for<br />

retesting at a rate specified in Section 01452. ITBA will not schedule retesting visit until payment is received<br />

from Contractor.<br />

B. Retesting shall follow the procedures for correction of deficiencies described in above.<br />

1.7 TESTING, ADJUSTING, AND BALANCING BY ITBA<br />

A. Testing and balancing shall be supervised by a Registered Professional Engineer. Personnel involved in execution<br />

of the work for ITBA shall be technicians experienced and trained specifically in testing and balancing of<br />

mechanical systems. Instruments used by ITBA shall be recently and accurately calibrated and maintained in good<br />

working order. Verification of equipment calibration shall be submitted in final test report if requested by Wal-<br />

Mart. Test, adjust, and balance specified equipment in accordance with governing NEBB or AABC Procedural<br />

Standards.<br />

B. Procedures:<br />

1. Make preliminary system check on mechanical, control and Energy Management systems and equipment to<br />

be tested to determine that equipment, duct work, etc. is installed and will operate. Deficiencies shall be<br />

immediately reported to Contractor's job site superintendent and the Wal-Mart Mechanical Services<br />

Construction Manager.<br />

2. Air Side Testing and Balancing: Perform the following air side testing and balancing for RTUs, AHUs,<br />

WSHPs, exhaust fans and exhaust hoods. Record readings for inclusion into final report:<br />

a. Record unit manufacturer, model number, and unit number.<br />

b. Test and adjust fan speeds to deliver design CFM and record for each unit.<br />

c. Test and adjust system for design CFM outside air.<br />

d. Measure and record unit voltage, amperage and fan speeds and final operating conditions.<br />

e. Test and record supply and return external static pressures at respective plenums. Seal access holes<br />

with rubber or metal snap-in plugs. The use of duct tape to seal access holes will not be permitted.<br />

f. Test and adjust the volume dampers in the main duct runs to each diffuser, grille, and register to<br />

provide ±10% of design CFM requirements.<br />

g. Identify each diffuser, grille, and register location and area.<br />

h. Provide AHU unit static pressure profile including unit suction static pressure, fan suction static<br />

pressure, and fan discharge static pressure.<br />

3. If any system or outlet is not within +/- 10 percent of design capacity at design rpm, determine the reason.<br />

Check duct work and plenums for leaks; coils, filter, for excessive pressure drop, etc.; and list on HVAC<br />

Deficiency Report.<br />

C. Reports:<br />

1. Testing and balancing data, measurements, reading, verification, settings, and deficiencies shall be recorded<br />

and compiled in a complete report. Record data on applicable NEBB or AABC certified reporting forms.<br />

Report shall include summary sheet of deficiencies with status (corrected or not corrected at time of report)<br />

and recommendations.<br />

2. Upload report to Wal-Mart Building Portal website within seven days after final test and balance.<br />

3. Before leaving job site, ITBA shall provide to the Contractor, a list of remaining HVAC system<br />

deficiencies for correction.<br />

D. Guarantee test and balance for period of 90 days from date of final acceptance of the Test and Balance Report.<br />

During this period, ITBA shall correct deficiencies at no cost to Wal-Mart.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

01455 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

END OF SECTION<br />

Not Used.<br />

01455 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PRE TEST & BALANCE CHECKLIST<br />

This pre test and balance checklist will be provided to the Contractor by the ITBA prior to the initial test and balance visit.<br />

Each mechanical subcontractor, as applicable, will verify and initial each item and return the checklist to the General<br />

Contractor. The General Contractor will fax the checklist to the ITBA to confirm readiness.<br />

All equipment is running (Field Verify)<br />

Ductwork is complete<br />

Balancing dampers are installed and wide open<br />

Grilles, registers, diffusers are installed<br />

Power and/or gas to all RTU’s<br />

Filters are clean<br />

Exhaust fans and hood fans are running<br />

Grease filters are installed in exhaust hoods<br />

RTU – Start up completed by OEM<br />

Exhaust/Relief fan – Rotation/Operation confirmed<br />

Fluid cooler – Start up completed by OEM<br />

Pump package – Start up completed<br />

Start-up strainers have been removed from equipment<br />

Strainers in condenser water and refg loops have been<br />

cleaned<br />

Glycol has been added to the condenser loop<br />

Are the HVAC systems complete, fully functional and ready<br />

for testing and balancing?<br />

Yes No Initials Comments<br />

I CERTIFY THAT THE ABOVE ITEMS HAVE BEEN CHECKED AND THAT THE SYSTEMS ARE READY FOR TESTING<br />

AND BALANCING<br />

_____<br />

Sub-Contractor Company Name Date Sub-Contractor Signature Sub-Contractor Printed Name<br />

INDEPENDENT TEST AND BALANCE AGENCY:______________________________________________________<br />

ITBA Contact Person_______________________Phone:____________ Fax:______________________<br />

01455 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PROJECT INFORMATION WORKSHEET<br />

This worksheet will be provided to the Contractor by the ITBA prior to the initial test and balance visit. The Contractor will<br />

complete the worksheet and fax to the ITBA prior to initial visit.<br />

Store No._________<br />

Sq. Ft.______________________<br />

Store Location:_____________________________<br />

_____________________________<br />

Possession Date:__________________<br />

Grand Opening Date:____________________<br />

Supercenter Wal-Mart Market Sam’s Club<br />

New Expansion Relocation<br />

Roof Top Unit Manufacturer: Carrier Aaon Lennox<br />

Air Handling Unit Manufacturer: Munters Seasons-4<br />

GENERAL CONTRACTOR:__________________________________________________________<br />

Address:_____________________________________________________________________________<br />

Project Mgr.:___________________________________ Phone:_________________________________<br />

Email:_________________________________________Fax:___________________________________<br />

Website:______________________________________________________________________________<br />

CONSTRUCTION SITE SUPERVISOR:__________________________________________________<br />

Jobsite Phone:________________________Fax:__________________ Cell:________________________<br />

MECHANICAL CONTRACTOR:________________________________________________________<br />

Phone:______________________________Fax:______________________________________________<br />

ELECTRICAL CONTRACTOR:________________________________________________________<br />

Phone: _____________________________Fax:______________________________________________<br />

WAL-MART CONSTRUCTION MANAGER:_____________________________________________<br />

Phone: _____________________________Fax:______________________________________________<br />

WAL-MART MECHANICAL SERVICES:<br />

Phone: ______________________________Fax:______________________________________________<br />

---------------------------------------------------------------------------------------------------------------------------------<br />

INDEPENDENT TEST AND BALANCE AGENCY:__________________________________________<br />

ITBA Contact Person_______________________Phone:____________ Fax:______________________<br />

01455 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 123010<br />

SECTION 01456 – CIVIL ENGINEERING CONSULTANT QUALITY ASSURANCE OBSERVATION<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Quality assurance site observation of construction by the Civil Engineering Consultant of Record.<br />

2. Work required herein is not the responsibility of the Contractor and will be performed at no cost to the<br />

Contractor. Provisions included herein are for information purposes only to provide the Contractor<br />

knowledge of the presence and responsibility of the Wal-Mart Civil Engineering Consultants.<br />

B. Related Documents and Sections:<br />

1. General Conditions: Observations, testing, and approvals required by public authorities.<br />

2. Section 01452 - Contractor Quality Control: Administrative and procedural requirements for Contractor<br />

quality assurance and quality control.<br />

3. Section 01454 - Architect-Engineer Quality Assurance Observation: Site observation by Owner’s<br />

Architect and Engineer Consultants.<br />

4. Section 01458 - Construction Laboratory Testing Services: Quality Requirements of Owner’s Construction<br />

Testing Laboratory (CTL) and services.<br />

1.2 DEFINITIONS<br />

A. Observation: Evaluation of systems primarily requiring observation and professional judgment.<br />

B. Quality Assurance: Activities, actions, and procedures performed before and during execution of the Work to<br />

guard against defects and deficiencies and substantiate that proposed construction will substantially comply with<br />

construction documents.<br />

C. Quality Control: Tests, inspections, procedures, and related actions during and after execution of the Work to<br />

evaluate that actual products incorporated into the Work and completed construction substantially comply with<br />

construction documents.<br />

D. Quality assurance and quality control may be performed by either the Contractor, the CEC, or the Construction<br />

Testing Laboratory employed by the Owner.<br />

E. Architect of Record (AOR): The prime consultant in charge of overall design and coordination of the building.<br />

F. Engineer of Record (EOR): The Registered Engineer in responsible charge of engineering design for the project.<br />

G. Structural Engineer of Record (SER): The Registered Engineer in responsible charge of the structural design for<br />

the project.<br />

H. Civil Engineering Consultant (CEC): The Registered Engineer in responsible charge of the civil design for the<br />

project.<br />

I. Architect - Engineer (A/E): A collective term to include the AOR, CEC, SER, and the Mechanical, Electrical, and<br />

Fire Protection EOR.<br />

J. Construction Testing Laboratory (CTL): The independent testing and inspection agency employed by the Owner.<br />

K. Building Official: The Officer or his duly authorized representative charged with the administration and<br />

enforcement of the local building code.<br />

01456 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


L. Deviation: A deviation is any item or component of work that does not substantially conform to the requirements<br />

of the construction documents and which has not been corrected by the end of business on the day it is identified.<br />

1.3 COORDINATION WITH CONTRACTOR<br />

A. The Contractor will:<br />

1. Cooperate with CEC personnel, and provide access to the Work and to Contractor’s facilities.<br />

2. Provide incidental labor and facilities to provide access to Work to facilitate observation. Provide lift<br />

equipment as required for CEC observation personnel.<br />

3. Provide CEC 7 day notice prior to expected time for operations requiring inspecting services.<br />

4. Maintain a copy of Contract Drawings and Specifications with all Addenda and Change Orders<br />

supplemented by the approved shop drawings and applicable material and workmanship provisions of the<br />

Code for use by the CEC in facilitating observation of the work.<br />

PART 2 PRODUCTS<br />

Not Used.<br />

PART 3 EXECUTION<br />

3.1 CEC OBSERVATIONS<br />

A. CEC will perform observations in accordance with the Civil Engineering Consultant Special Observations<br />

Guideline located in the Design Collective at the Wal-Mart Bldg Portal website.<br />

B. Perform site observations as agreed to with the Owner as listed below or as otherwise requested by the Authority<br />

Having Jurisdiction or Wal-Mart Construction Manager to check a sample of the constructed Work for general<br />

conformance with the Contract Documents.<br />

C. Perform a minimum of the following site observations as outlined in the Wal-Mart Civil Engineering Consultant<br />

Special Observation Guidelines located on the Wal-Mart Bldg Portal website.<br />

1. First visit 16 to 18 weeks (or approximately 120 days) prior to possession.<br />

2. Second visit 8 to 9 weeks (or approximately 60 days) prior to possession.<br />

3. Third visit 1 to 2 weeks (or approximately 10 days) prior to possession.<br />

4. Landscaping and Irrigation System: One visit 2 months prior to end of landscape warranty period.<br />

Reference Section 02900.<br />

D. The observations listed above are the minimum number of observations to be performed. Additional visits as<br />

considered necessary by CEC or as required in the individual specifications sections shall also be performed by the<br />

CEC. Should there be outstanding items of non-conformance with the Contract Documents that warrant additional<br />

site observations to be performed by the CEC, the CEC shall receive approval from Wal-Mart prior to performing<br />

an additional site observation.<br />

E. Deviations from the Contract Documents shall be entered into the on-line Wal-Mart Observation Log by the CEC<br />

as required and will be tracked and noted by the CEC when resolved by subsequent conformance by the<br />

Contractor.<br />

1. Observation Log: www.bldgportal.com, enter username and password, select Observation Log. Follow<br />

instructions on the Observation Log website.<br />

F. The CEC shall not have control over or responsibility for construction means, techniques, sequences of operations<br />

or for safety programs and procedures in connection with the construction work.<br />

G. The CEC shall provide a final conformance letter to Wal-Mart. An example is attached at the end of this section.<br />

01456 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


H. Work will be checked as it progresses, but failure to detect any defective work or materials shall in no way prevent<br />

later rejection if defective work or materials are discovered, nor shall it obligate Owner to accept such work.<br />

END OF SECTION<br />

01456 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


[Example Conformance Letter from the CEC. Text in parentheses are to be edited for each individual project]<br />

[Date]<br />

[Mr. Construction Manager]<br />

Wal-Mart Construction<br />

Sam M. Walton Development Complex<br />

2001 S. E. 10 th Street<br />

Bentonville, Arkansas 72716<br />

[Re: Supercenter (Store #xxx) – City, State]<br />

[Dear Construction Manager:]<br />

The purpose of this letter is to state to Wal-Mart Stores, Inc. that, to the best of our knowledge, the construction on the above<br />

referenced project has been completed in substantial conformance with the approved Contract Documents.<br />

We performed construction observation visits as agreed to by the Owner and as required by our scope of services to verify<br />

general conformance of the work. To our knowledge and our construction observations, no outstanding items exist except as<br />

may be otherwise entered and shown on the Wal-Mart Observation Log.<br />

Sincerely,<br />

[CIVIL ENGINEERING CONSULTANT FIRM ]<br />

[Include a seal, signature and date of signature]<br />

ENGINEER OF RECORD<br />

cc: File<br />

01456 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 01458 (01 4529) – TESTING LABORATORY SERVICES<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Administrative and procedural requirements for Owner provided testing and inspection services.<br />

B. Related Requirements:<br />

1. General Conditions: Inspections, testing, and approvals required by public authorities.<br />

2. Section 01770 - Contract Closeout: Project Record Documents.<br />

3. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished work and<br />

Work of other Contractors.<br />

4. Section 01452 - Contractor Quality Control: Administrative and procedural requirements for Contractor<br />

quality assurance and quality control.<br />

5. Section 01454 - Architect-Engineer Quality Assurance Observation: Site observation by Owner’s<br />

Architect and Engineer Consultants.<br />

6. Section 01455 - Testing, Adjusting, and Balancing: Wal-Mart procurement of test and balance for heating,<br />

ventilating, and air conditioning systems.<br />

7. Section 01456 - Civil Engineering Consultant Quality Assurance Observation: Site observation by<br />

Owner’s Civil Engineering Consultant.<br />

C. General requirements for testing and inspection to be performed by the Contractor is specified in Section 01452.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. The publications are<br />

referred to within the text by the basic designation only.<br />

B. American Association of State Highway and Transportation Officials (AASHTO):<br />

1. AASHTO R18 - Establishing and Implementing a Quality System for Construction Materials Testing<br />

Laboratories.<br />

C. ASTM International (ASTM):<br />

1. ASTM C 1077 - Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and<br />

Criteria for Laboratory Evaluation.<br />

2. ASTM C 1093 - Accreditation of Testing Agencies for Unit Masonry.<br />

3. ASTM D 3740 - Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and<br />

Rock as Used in Engineering Design and Construction.<br />

4. ASTM D 3666 - Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials.<br />

5. ASTM D 7186 - Quality Assurance Observation of Roof Construction and Repair.<br />

6. ASTM E 329 - Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction.<br />

7. ASTM E 543 - Agencies Performing Nondestructive Testing.<br />

8. ASTM E 699 - Criteria for Evaluation of Agencies Involved in Testing, Quality Assurance, and Evaluating<br />

Building Components in Accordance with Test Methods Promulgated by ASTM Committee E-6.<br />

1.3 DEFINITIONS<br />

A. Testing: Evaluation of systems, primarily requiring physical manipulation and analysis of materials, in accordance<br />

with approved standards.<br />

B. Inspection: Evaluation of systems primarily requiring observation and engineering judgment.<br />

01458 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Quality Assurance: Activities, actions, and procedures performed before and during execution of the Work to<br />

guard against defects and deficiencies and substantiate that proposed construction will substantially comply with<br />

construction documents.<br />

D. Quality Control: Tests, inspections, procedures, and related actions during and after execution of the Work to<br />

evaluate that actual products incorporated into the Work and completed construction substantially comply with<br />

construction documents.<br />

E. Quality assurance and quality control may be performed by either the Contractor or the Construction Testing<br />

Laboratory employed by the Owner.<br />

F. Construction Testing Laboratory (CTL): The independent testing and inspection agency employed by the Owner.<br />

G. Architect of Record (AOR): The prime consultant in charge of overall design and coordination of the building.<br />

H. Engineer of Record (EOR): The Registered Engineer in responsible charge of engineering design for the project.<br />

I. Structural Engineer of Record (SER): The Registered Engineer in responsible charge of the structural design for<br />

the project.<br />

J. Civil Engineering Consultant (CEC):The Registered Engineer in responsible charge of the civil design for the<br />

project.<br />

K. Architect - Engineer (A/E): A collective term to include the AOR, CEC, SER, and the Mechanical, Electrical, and<br />

Fire Protection EOR.<br />

L. Special Inspector (SI): The Special Inspector under the direct supervision of a registered civil/structural<br />

engineer(unless otherwise specified) regularly engaged in inspection, and experienced with the type of work<br />

requiring related testing and inspection. The categories of special inspector are:<br />

1. Technical I(TI): A Technician who is an employee of a qualified and approved testing laboratory. Lab<br />

work shall be performed in a qualified testing laboratory.<br />

2. Technical II (TII): A Technician with a minimum of 2 years experience, or a graduate engineer, and is an<br />

employee of a qualified and approved testing laboratory.<br />

3. Technical III (TIII): An engineer regularly engaged in related work with a minimum of 4 years of<br />

experience, licensed in the State in which the project is located, and is an employee of a qualified and<br />

approved testing laboratory. This licensed engineer shall review and approve all final field reports.<br />

4. Structural I (StI): A graduate civil/structural engineer, or other trained and experienced personnel<br />

acceptable to the SER, with experience in the testing and inspection of related structural systems.<br />

5. Structural II (StII): A civil/structural engineer regularly engaged in related work with a minimum of 4<br />

years of experience, licensed in the State in which the project is located. The licensed engineer shall<br />

review and approve all inspection reports.<br />

6. Independent Roofing Inspector (IRI): A technician employed or subcontracted by theCTL for the purpose<br />

of field observation of roofing installation. The IRI shall be certified as a Registered Roofing Observer<br />

(RRO) by the Institute of Roofing, Waterproofing, and Building Envelope Professionals (RCI) (Formerly<br />

Roof Consultants Institute).<br />

7. Roofing Technician: A technician employed by the CTL with training and experience in roofing<br />

construction or inspection. The Roofing Technician shall be under the direct supervision of the IRI and<br />

shall provide continuous inspection during roofing work.<br />

8. Unique special inspector requirements, for specific materials and system, are noted in related technical<br />

specification sections.<br />

M. Building Official: The Officer or his duly authorized representative charged with the administration and<br />

enforcement of the local building code.<br />

N. Continuous Inspection: The full-time observation of work requiring special inspection by an approved special<br />

inspector who is present in the area where the work is being performed.<br />

01458 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


O. Periodic Inspection: The part-time or intermittent observation of work requiring special inspection by an approved<br />

special inspector who is present in the area where the work has been or is being performed and at the completion<br />

of the work.<br />

P. Deviation: Any item or component of work that does not substantially conform to the requirements of the<br />

construction plans and/or specifications and which has not been corrected by the end of business on the day it is<br />

identified. A life-safety deviation is any construction deviation that poses a serious hazard to any person.<br />

1.4 CONSTRUCTIONTESTING LABORATORY (CTL) QUALITY REQUIREMENTS<br />

A. CTL shall comply with requirements of ASTM C 1077, ASTM C 1093, ASTM D 3740, ASTM D 3666, ASTM E<br />

329, ASTM E 543, ASTM E 699, and AASHTO R18.<br />

B. CTL shall be authorized to operate in state in which Project is located.<br />

C. CTL Testing Equipment shall be calibrated at reasonable intervals with devices of an accuracy traceable to either<br />

National Institute of Standards and Technology (NIST) standards or accepted values of natural physical constants.<br />

D. CTL shall have and maintain a written Quality Manual (QM) for its laboratory conforming to the Appendix<br />

requirements ASTM E329 or AASHTO R18. The QM shall be available for review by the Wal-Mart Construction<br />

Manager upon request. The QM shall be organized similar to Quality Manual Requirements of AASHTO R18 and<br />

include the following:<br />

1. Organization and Organizational Policies.<br />

2. Staff.<br />

3. Equipment.<br />

4. Test Data Control and Reports.<br />

5. Diagnostic and Corrective Action.<br />

6. Internal Quality System Review.<br />

7. Subcontracting.<br />

8. Statement certifying compliance with ASTM standards specified above.<br />

1.5 OWNER RESPONSIBILITIES<br />

A. Employment and payment for services of an Construction Testing Laboratory (CTL) and/or Special Inspector (SI)<br />

to perform specified testing and inspecting will be by the Owner under separate contract except for specified<br />

testing required to be selected and paid for by the Contractor as may be required by individual specification<br />

sections.<br />

1.6 CONSTRUCTION TESTING LABORATORYAND SPECIAL INSPECTOR RESPONSIBILITIES<br />

A. Responsibilities include inspections, tests, and related actions including reports performed by testing or inspection<br />

service. They do not include Contract enforcement activities performed by the Wal-Mart Construction Manager or<br />

authorities having jurisdiction.<br />

1. Provide the Architect of Record a copy of the contractual provisions defining the CTL’s and SI’s scope of<br />

services.<br />

B. The CTL/SIrepresentative shall attend a pre-construction meeting prior to actual start of the Project.Except for the<br />

roofing inspection, the CTL/SI representative shall be the Registered Professional Engineer assigned to the project.<br />

C. Maintain a copy of Contract Drawings and Specifications with all Addenda and Change Orders. Use the Contract<br />

Documents supplemented by the approved shop drawings and applicable material and workmanship provisions of<br />

the Code for testing and inspection of the work.<br />

D. Provide qualified personnel at site to comply with schedule and submit reports for each test and inspection as<br />

defined in Part 3 of this Section. Testing and inspection, except roofing inspection, shall be under supervision of<br />

the Registered Professional Engineer (P.E.) in the state where Project is located.<br />

01458 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Perform specified inspection, sampling, and testing of work, materials, and equipment in accordance with<br />

specified standards.<br />

F. Ascertain compliance of materials and mixes with requirements of Contract Documents.<br />

G. Perform testing and inspections in a timely manner to avoid delay of work. Schedule and coordinate testing and<br />

inspections with Contractor and appropriate sub-contractors and installers.<br />

H. If observed deviations from the Contract Drawings, Specifications, or building code will be probable cause of<br />

subsequent rejection of work or material, notify Contractor, the Wal-Mart Construction Manager, Sitework<br />

Engineering Consultant, and Architect of Record, sufficiently in advance for determination to continue operations<br />

or take corrective measures before continuing. If uncorrected after a reasonable period of time, bring the situation<br />

to the attention of the Structural Engineer of Record, the Building Official, and to the Architect of Record.<br />

I. Track resolutions and remedial repairs to deviations and subsequent conformance to the Contract Documents on<br />

the Observation Log.<br />

J. Report any observed life safety issue immediately to Contractor and Wal-Mart Construction Manager. After<br />

notification is given to the Contractor and the Wal-Mart Construction Manager, the CTL/SI shall also log the life<br />

safety issue on Wal-Mart’s Observation Log.<br />

K. Perform retesting due to non-conformance with the Contract Documents. Costs will be deducted from the Sum<br />

due the Contractor.<br />

L. Provide a final conformance letter to Wal-Mart, the SER and the AOR. An example is attached at the end of this<br />

section.<br />

M. Testing and inspection by the Building Official do not preclude the normal field involvement and site observations<br />

by Architect or Structural Engineer of Record, nor shall it relieve the Contractor of any responsibility to complete<br />

the work in accordance with the approved drawings and specifications.<br />

N. Construction Testing Laboratory And Special Inspector Limits On Authority: The CTL or SI may not:<br />

1. Release, revoke, alter, or enlarge on requirements of Contract Documents.<br />

2. Approve or accept any portion of the Work.<br />

3. Assume any duties of Contractor.<br />

4. Stop the Work.<br />

O. Testing and inspecting services performed by the CTL (Construction Testing Laboratory) are required to verify<br />

compliance with requirements specified or indicated.<br />

1. CTL services do not relieve Contractor of responsibility for compliance with the Contract Document<br />

requirements nor limit Contractor's other quality-assurance and -control procedures that facilitate<br />

compliance with the Contract Document requirements.<br />

2. Specific quality-assurance and -control requirements for individual construction activities shall be as<br />

specified in the Sections that specify those activities.<br />

3. Requirements for Contractor to provide quality-assurance and -control services required by Architect,<br />

Owner, Construction Manager, or authorities having jurisdiction do not limit responsibilities of the CTL.<br />

1.7 ROOF OBSERVATION PROGRAM<br />

A. The CTL shall develop a comprehensive Roof Observation Program to be administered by the IRI outlining the<br />

specific activities and details of roofing site observations and to be implemented in accordance with Section<br />

07500. The program shall conform and implement the requirements of ASTM D 7186 including the applicable<br />

forms therein.<br />

1.8 CONTRACTOR RESPONSIBILITIES<br />

A. Cooperate with CTL/SI personnel, and provide access to the Work and to manufacturer's facilities.<br />

01458 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Provide incidental labor and facilities to provide access to Work to be tested, to obtain and handle samples at the<br />

site or at source of products to be tested, to facilitate tests and inspections, and to provide storage and curing of test<br />

samples. Provide lift equipment as required for inspection personnel of the Owner or the Owner’s representatives.<br />

C. Provide CTL 24 hour notice prior to expected time for operations requiring inspecting and testing services.<br />

D. Notify in writing the Wal-Mart Construction Manager three working days prior to expected time for operations<br />

requiring inspecting and testing services.<br />

E. Provide the CTL/SI with access to the internet for the purpose of logging deviations onto the Wal-Mart<br />

Observation Logon the Wal-Mart Building Portal website.<br />

1.9 CONSTRUCTION TESTING LABORATORY REPORTS<br />

A. The CTL shall submit reports and other items as required in this paragraph.<br />

B. CTL Information: Testing laboratory name, address, and telephone number, and names of full time Registered<br />

Engineer and responsible officer.<br />

C. Roof Observation Program.<br />

D. Test and Inspection Reports:<br />

1. Submit test and inspection reports showing the following information:<br />

a. Date issued.<br />

b. Project title and number.<br />

c. Store number.<br />

d. Firm name and address.<br />

e. Name and signature of tester or inspector.<br />

f. Name and seal of registered engineer in responsible charge (as applicable).<br />

g. Date and time of sampling.<br />

h. Date of test or inspection.<br />

i. Identification of product and specification section.<br />

j. Location in project, including elevations, grid location and detail.<br />

k. Type of test or inspections.<br />

l. Results of tests or inspections and interpretation of same.<br />

m. Observations regarding compliance with Contract Documents or deviations therefrom.<br />

E. Submit required reports and other items to the following:<br />

1. CEC: 1 copy (Site work T&I only).<br />

2. SER: 1 copy (Construction Administration Leader) (Bldg T&I only).<br />

3. AOR: 2 copies (Construction Administration Leader) (Bldg T&I and Roof Observation Program).<br />

4. Contractor: 3 copies.<br />

5. Building Official: Quantities as required.<br />

6. Owner.<br />

F. Submit a separate final signed report stating the work requiring inspection is, to the best of the inspector's<br />

knowledge, in conformance with the Contract Documents.<br />

G. Reports shall be made on 8-1/2 by 11 white paper, suitable for photocopying and binding in booklet form. Sheets<br />

shall have the CTL letterhead (including phone number and address). Larger sheets shall be folded and bound into<br />

the booklet.<br />

H. Submit Test and Inspection Reports within 3 working days of T&I occurrence.<br />

I. Tests and inspections indicating non-conformance (deviations) to the Contract Documents shall be brought to the<br />

attention of the Contractor, Sitework Engineering Consultant, and Architect of Record upon discovery in the form<br />

of hard copy reports and entered into the Wal-Mart Observation Log within 24 hours.<br />

01458 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


J. Deviations from the Contract Documents, as defined above, shall be logged onto the Wal-Mart Observation Log<br />

by the CTL/SI representative on site (www.bldgportal.com, enter username and password, select Observation<br />

Log). Follow instructions on the Observation Log website for entry of information.<br />

K. The Wal-Mart Construction Manager in conjunction with the CTL and/or SI will determine when to involve the<br />

AOR or EOR for remedial action.<br />

PART 2 PRODUCTS<br />

Not Used.<br />

PART 3 EXECUTION<br />

3.1 PRODUCTION TESTING<br />

A. General Requirements:<br />

1. Testing shall be conducted as specified in the individual specification sections.<br />

2. Tests and inspections shall, as a minimum, be performed by Technical I (TI)inspector if not otherwise<br />

specified in the individual section.<br />

3. If inspection of fabricators work is required, the Owner's representative may require testing and inspection<br />

of the work at the plant before shipment.<br />

4. Testing and inspection shall be performed in accordance with the industry standard used as the reference<br />

for the specific material or procedure unless other criteria are specified. In the absence of a referenced<br />

standard, tests shall be accomplished in accordance with generally accepted industry standards.<br />

5. Work shall be checked as it progresses, but failure to detect any defective work or materials shall in no way<br />

prevent later rejection if defective work or materials are discovered, nor shall it obligate Owner to accept<br />

such work.<br />

B. Applicable Sections: Testing by the Owner’s Construction Testing Laboratory is summarized in the following<br />

CTL Testing and Inspection Program Summary Schedule. Refer to the applicable individual sections for specific<br />

details. The Schedule provides summary information only and does not preclude or supersede requirements<br />

contained in the individual sections.<br />

01458 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CTL Testing and Inspection Program<br />

Summary Schedule<br />

Section & Title<br />

Description of Test or Observation<br />

Type of<br />

Inspector<br />

Report<br />

Frequency<br />

02300 - Earthwork Tests:Classification of Materials,<br />

Laboratory Testing, Field Density Tests<br />

Observation:Subgrades/excavation bases,<br />

bearing capacity, presence of<br />

groundwater, cut & fill slopes.<br />

02340 - Soil<br />

Unconfined compression tests, density<br />

Stabilization<br />

tests<br />

02715 - Base Course Tests:Field density, thickness.<br />

02740 - Asphalt<br />

Pavement<br />

02751 - Concrete<br />

Pavement<br />

02765 - Pavement<br />

Markings<br />

02770 - Curbs and<br />

Sidewalks<br />

Inspection: Placement<br />

Testing:Core sampling & tests, thickness,<br />

smoothness, field density, lab tests.<br />

Inspection:Placement.<br />

Testing:Lab test, field tests, core<br />

sampling & testing.<br />

Inspection:Placement, mix.<br />

01458 - 7<br />

TI, TII,or TIII<br />

as specified<br />

As specified in Paragraph:<br />

CONSTRUCTION<br />

TESTING LABORATORY<br />

REPORTS<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11<br />

TI<br />

TI<br />

TI<br />

TI<br />

Same<br />

Same<br />

Same<br />

Same<br />

Testing: Wet film thickness. TI Same<br />

Testing: Lab test, field tests, core<br />

sampling & testing.<br />

Inspection: Placement, mix.<br />

Testing: SRW unit compression test, lab<br />

and field soil tests.<br />

02830 - Segmental<br />

Retaining Wall System<br />

02900- Planting Testing: Topsoil analysis<br />

Inspection: Verify depth of topsoil.<br />

03310 - Structural Testing:Lab test, field tests<br />

Concrete and Exterior Inspection:Forms, slabs, reinforcement,<br />

Concrete Slabs conc. mix, placement, curing, embedded<br />

03312 - Cast-In-Place<br />

Concrete Slabs<br />

(Interior)<br />

03362 -Burnished<br />

Concrete Floor Finishes<br />

03410 - Plant Precast<br />

Structural Concrete<br />

Panels<br />

04200 -Masonry Mortar<br />

& Grout<br />

04200 -Concrete<br />

Masonry Units<br />

05090 - Post Installed<br />

Concrete and Masonry<br />

Anchors<br />

items<br />

Testing:Lab test, field tests<br />

Inspection:Forms, slabs, reinforcement,<br />

conc. mix, placement, curing, embedded<br />

items, hardener/densifier<br />

Testing: Gloss measurement, slip<br />

resistance measurement.<br />

Inspection: Precast panel erection<br />

including member configuration, finish,<br />

connections, welding and grouting<br />

Testing:Mortar and Grout<br />

Verification of mixes.<br />

Testing:Strength tests<br />

Inspection:Placement, bond beams,<br />

openings, pilasters, reinforcement,<br />

grouting<br />

Testing: Pullout & sheer test if reqd.<br />

Inspection: Anchor holes, anchor size,<br />

embedment, and tightening.<br />

05120 - Structural Steel Testing: Bolting, Shop & Field Welding<br />

Inspection:Welding, fasteners, submittals,<br />

detail compatibility<br />

TI<br />

TII<br />

TI<br />

TI, TII, or StI<br />

as specified<br />

TI, TII, or StI<br />

as specified<br />

TI<br />

TI<br />

TI<br />

TII or StI<br />

TII or StI<br />

TII or StI<br />

Same<br />

Same<br />

Per test/observation<br />

Same<br />

Same<br />

Same<br />

Per observaton<br />

Same<br />

Same<br />

Same<br />

Same


05210 - Steel Joists Testing: Bolting, Shop & Field Welding<br />

Inspection:Welding, fasteners, materials,<br />

submittals, detail compatibility<br />

05300 - Metal Deck Inspection:Welding, fasteners, materials,<br />

submittals, detail compatibility<br />

05400 - Cold Formed Inspection:Welding, fasteners, materials,<br />

Metal Framing<br />

07243 - Water-Drainage<br />

Exterior Insulation and<br />

Finish System<br />

07500 - Membrane<br />

Roofing<br />

09511 - Acoustical<br />

Panel Ceilings<br />

09650 - Resilient<br />

Flooring<br />

Architectural Drawings<br />

Architectural Drawings<br />

END OF SECTION<br />

submittals, detail compatibility<br />

Inspection: Verifying field preparation of<br />

materials, expiration dates, installation of<br />

components, curing of components,<br />

installation of joints and sealants, applied<br />

dry-film thickness, interface of coating<br />

material with flashings<br />

Full time inspection of roofing<br />

installation.<br />

TII or StI<br />

TII or StI<br />

TII or StI<br />

TI<br />

Wal-Mart<br />

Independent<br />

Roofing Inspector<br />

(IRI)<br />

TI<br />

Same<br />

Same<br />

Same<br />

Per test/observation<br />

Completion of Roofing<br />

Inspection: Installation of acoustical<br />

Per observation<br />

panel ceilings<br />

Testing:Moisture Test of concrete slab TI Per Test<br />

Inspection: Installation and securement<br />

of Building Mounted Signage<br />

Inspection: Installation and securement<br />

of Pylon Signage<br />

TI<br />

TI<br />

Completion of Sign<br />

Installation<br />

Completion of Sign<br />

Installation<br />

01458 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Mr. Construction Manager<br />

Wal-Mart Construction<br />

Sam M. Walton Development Complex<br />

2001 S. E. 10 th Street<br />

Bentonville, Arkansas 72716<br />

Re: Supercenter (Store #xxx) – City, State<br />

Dear Construction Manager:<br />

The purpose of this letter is to state to Wal-Mart, the Architect of Record and the Engineer of Record that, to the best of our<br />

knowledge, the construction on the above referenced project has been completed in substantial conformance with the<br />

approved Contract Documents and with the provisions of the applicable building code.In the capacity of owner’s testing and<br />

inspecting agency, periodic reports as well as a final report have been issued.Those reports state thatall of the on-site<br />

inspection and testing has been performed.Work requiring inspection was, to the best of the inspector’s knowledge, in<br />

conformance with the approved plans, specifications, and applicable workmanship provisions of the code.<br />

To our knowledge no outstanding items exist except as otherwise may be entered and shown on the Wal-Mart Observation<br />

Log.<br />

Sincerely,<br />

Testing and Inspection Agency<br />

Include a seal, signature and date of signature<br />

cc:ARCHITECT OF RECORD<br />

ENGINEER OF RECORD<br />

01458 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 01459 – NEUTRALIZATION ENCLOSURE QUALITY CONTROL<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Neutralization Enclosure.<br />

B. Related Requirements:<br />

1. Section 15700 - Heating, Ventilating, And Air Conditioning Equipment: Air Curtains.<br />

1.2 NEUTRALIZATION ENCLOSURE<br />

A. The entire area of the sales floor plus additional areas as indicated which have open access to the vestibule air<br />

entrance system is defined as a "positive" air pressurization area for the purpose of maintaining a constant internal<br />

air pressure.<br />

B. Contractor shall provide an air tight enclosure defining the neutralization area as indicated including, but not be<br />

limited to, the following:<br />

1. Perimeter wall construction.<br />

2. Internal wall construction.<br />

3. Penetrations of walls defining the area.<br />

C. Upon completion of neutralization perimeter wall and penetrations, the air curtain manufacturer specified in<br />

Section 15700 shall have complete access to the construction areas for the purpose of determining the acceptance<br />

level of the neutralization enclosure.<br />

D. Contractor shall cooperate with and assist manufacturer's representative and correct deviations.<br />

1.3 SUBMITTALS<br />

A. Closeout Submittals: Upon completion of construction but prior to final acceptance, complete, sign, and submit<br />

Certification of Project Quality Assurance in accordance with requirements of Section 01770. Certification form<br />

is included at the end of this Section.<br />

1.4 QUALITY ASSURANCE<br />

A. Monitor quality of construction provided by Contractor, subcontractors, suppliers, manufacturers, including<br />

products, services, site conditions, and workmanship.<br />

B. Comply with manufacturer's instructions and specifications, including each step in sequence of installation.<br />

1. Should manufacturer's instructions conflict with Contract Documents, request clarification from Architect<br />

before proceeding.<br />

C. Comply with specified standards as a minimum level of quality for the Work except where more stringent<br />

tolerances, codes, local governing officials, or specified requirements indicate higher standards or more precise<br />

workmanship.<br />

D. Perform Work by persons who are thoroughly qualified and trained in their respective trade to produce<br />

workmanship of specified quality.<br />

E. Secure products in-place with positive anchorage devices designed and sized to withstand stresses, vibration,<br />

physical distortion, or disfigurement.<br />

01459 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 PRE-CONSTRUCTION MEETING<br />

A. Contractor shall schedule a pre-construction meeting in advance of Work defining the construction of the<br />

neutralization wall. Contractor, Air Curtain Manufacturer's Representative (Section 15700), and primary<br />

subcontractors shall attend meeting.<br />

1. Notify the Wal-Mart Construction Manager 7 days in advance of scheduled meeting date.<br />

B. Contractor shall be responsible for preparing and distributing a meeting agenda at least two 2 days before the<br />

scheduled meeting. The agenda shall, as a minimum, address the following issues.<br />

1. Discuss the purpose of the neutralization construction as defined herein. Review in detail the scope of<br />

Work relating to construction of wall.<br />

2. Coordination of construction efforts between trades in building the perimeter walls of neutralization area.<br />

3. Responsibilities for sealing penetrations of neutralization wall.<br />

4. Determination of acceptable neutralization wall construction.<br />

5. Review details and specifications regarding Air Curtain construction and equipment and submit<br />

information.<br />

C. Contractor shall record the proceeding of the meeting and prepare minutes reflecting the conversations and<br />

discussions. Copy each attendee in addition to the Wal-Mart Construction Manager.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

3.1 CONTRACTOR FIELD INSPECTION AND TESTING<br />

A. Inspect Work provided under this Contract to ensure Work is in compliance with Contract requirements.<br />

B. Examination Of Work: Performed prior to beginning Work and prior to beginning each segment of Work and<br />

includes:<br />

1. Review of Contract requirements.<br />

2. Review of shop drawings and other submittal data after return and approval.<br />

3. Examination to assure materials and equipment conform to Contract requirements.<br />

4. Examination to assure required preliminary or preparatory Work is complete.<br />

C. Initial Inspection: Performed when representative portion of each segment of Work is completed and includes:<br />

1. Performance of required tests.<br />

2. Quality of workmanship.<br />

3. Review for omissions or dimensional errors.<br />

4. Examination of products used, connections and supports.<br />

5. Approval or rejection of inspected segment of Work.<br />

D. Follow-Up Inspections: Performed daily and more frequently as necessary to assure non-complying Work has<br />

been corrected.<br />

E. No components of the neutralization wall shall be covered or concealed within construction before Work is<br />

examined and found acceptable with respect to neutralization wall construction.<br />

END OF SECTION<br />

01459 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


NEUTRALIZATION ENCLOSURE<br />

CERTIFICATION OF PROJECT QUALITY ASSURANCE<br />

Project Location:<br />

Date:<br />

(City)<br />

(State)<br />

Project Number:<br />

Store Number:<br />

The following project items have been completed in accordance with the Contract Documents and found acceptable by the<br />

undersigned based on material tests and field inspections.<br />

PROJECT ITEM<br />

Exterior perimeter construction of neutralization wall.<br />

Penetrations of exterior perimeter walls which define neutralization area.<br />

Perimeter seal between roof edge and exterior wall defining neutralization wall.<br />

Continuous seal between interior neutralization wall roof construction.<br />

Penetrations of interior walls which define neutralization area.<br />

Installation of air curtains.<br />

Continuous RTU Sales Floor Fan Operation (pressurization / neutralization) during store operation hours.<br />

Construction detailing including, but not limited to, the following:<br />

ARCHITECTURAL DRAWINGS<br />

Neutralization Wall as indicated on Floor Plan and per Floor Plan General Note indicating Neutralization Wall<br />

requirements, Sheet A-1.<br />

Wall Section between Stockroom and Sales Area, Sheet _____ , Detail _____ .<br />

Wall Section between Stockroom and Corridor, Sheet _____ , Detail _____ .<br />

PLUMBING DRAWINGS<br />

Piping/Conduit Penetration at Neutralization Wall, Sheet ______ , Detail ______ .<br />

SPECIFICATIONS<br />

Expanding Foam Sealant installed at penetrations as specified in Section 07900 - Joint Sealants.<br />

Airtight Firestopping Sealant installed at Fire Rated penetrations as specified in Section 07840 - Firestopping.<br />

Statement of Conformance:<br />

This Certification is provided as a Record Document. The undersigned hereby declares and certifies that the aforementioned<br />

items of construction have been completed in accordance with Contract Documents and the structure is considered ready for<br />

its intended use.<br />

CONTRACTOR:<br />

________________________________<br />

(Contact name of Contractor)<br />

___________________________________<br />

(Contractor signature and Title of Signatory)<br />

END OF FORM<br />

01459 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 01500 – TEMPORARY FACILITIES AND CONTROLS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Temporary Utilities: Electricity, lighting, heat, ventilation, telephone service, water, and sanitary facilities.<br />

2. Temporary Controls: Barriers, enclosures and fencing, signage, protection of the Work, and water control.<br />

3. Construction Facilities: All-weather access roads, parking, progress cleaning, temporary buildings, and<br />

staging areas.<br />

1.2 TEMPORARY ELECTRICITY<br />

A. Provide temporary electricity through Pre-manufactured Electrical Service and Distribution Center (EDC). See<br />

Section 16405 for requirements.<br />

1. Temporary electrical service shall include, but is not limited to the following:<br />

a. Coordination with local utility for providing primary service and permanent site electrical<br />

transformer.<br />

b. Coordination of site grading and preparation for primary power and permanent site electrical<br />

transformer installation.<br />

c. Coordination of structural foundation requirements to support Electrical Distribution Center as<br />

specified in Section 16405.<br />

d. Coordination and availability of crane services as required for erection and installation of Electrical<br />

Distribution Center.<br />

2. Provide and pay for power service required for construction.<br />

B. Provide adequate distribution equipment, wiring, and outlets to provide single phase branch circuits for power and<br />

lighting. Provide temporary feeders to limit voltage loss to 5% overall from local utility power lines to provide<br />

electric requirements for project during construction.<br />

C. Provide main service disconnect and overcurrent protection at convenient location. Provide necessary<br />

transformers, meters, cables, protective devices, switches, etc., as required.<br />

1.3 TEMPORARY LIGHTING<br />

A. Provide and maintain lighting for construction operations.<br />

B. Permanent building lighting may be utilized during construction.<br />

1.4 TEMPORARY HEAT<br />

A. Provide and pay for heat devices and heat as required to maintain specified conditions for construction operations.<br />

B. Prior to operation of permanent equipment for temporary heating purposes, verify that installation is approved for<br />

operation, equipment is lubricated and filters are in place. Provide and pay for operation, maintenance, and regular<br />

replacement of filters and worn or consumed parts.<br />

C. Maintain minimum ambient temperature of 50 degrees F in areas where construction is in progress, unless<br />

indicated otherwise in specifications.<br />

1.5 TEMPORARY VENTILATION<br />

A. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust,<br />

fumes, vapors, or gases.<br />

01500 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.6 TELEPHONE SERVICE<br />

A. Provide, maintain and pay for telephone service to field office at time of project mobilization.<br />

1.7 TEMPORARY WATER SERVICE<br />

A. Provide, maintain and pay for suitable quality water service required for construction operations.<br />

B. Extend branch piping with outlets located so water is available by hoses with threaded connections. Provide<br />

temporary pipe insulation to prevent freezing.<br />

C. Connect to existing water source. Owner will pay cost of water used. Exercise measures to conserve water.<br />

1.8 TEMPORARY SANITARY FACILITIES<br />

A. Provide and maintain required chemical toilet facilities.<br />

B. Locate as directed by Wal-Mart Construction Manager. Maintain facilities clean and serviced as necessary and in<br />

compliance with local health code requirements.<br />

C. Existing facilities shall not be used.<br />

1.9 BARRIERS<br />

A. Protect non-owned vehicular traffic, stored materials, site and structures from damage.<br />

B. Provide barriers to prevent unauthorized entry to construction areas to allow for Owner's use of site, and to protect<br />

existing facilities and adjacent properties from damage from construction operations.<br />

C. Provide barricades and covered walkways required by governing authorities for public rights-of-way, to allow for<br />

Owner's use of site, and for public access to existing building.<br />

1. Erect barricades using 1/2 inch plywood on 2x4 framing. Supports shall be as required to uphold barricade.<br />

Verify requirements with Wal-Mart Construction Manager.<br />

2. Construct 8 feet high unless otherwise directed by Owner.<br />

3. Shopping carts shall not be used as barricades.<br />

1.10 TEMPORARY FENCING FOR CONSTRUCTION/DEMOLITION WASTE CONTAINERS<br />

A. General:<br />

1. Provide commercial grade temporary chain link fencing around waste storage and sorting areas as specified<br />

in Section 01742.<br />

2. Fencing shall be 8 feet high.<br />

3. Maintain access to fire hydrants and hose connections, emergency vehicles, and other site specific<br />

conditions as required by Authority Having Jurisdiction.<br />

4. Obtain permits required by AHJ for usage and placement of temporary chain link fencing.<br />

B. Materials:<br />

1. Posts: Galvanized steel pipe. Posts shall be suitable for setting in concrete footings, driving into ground as<br />

required by local conditions.<br />

2. Fabric: Woven galvanized steel wire in 2 inch mesh. Provide in continuous lengths to be wire tied to fence<br />

posts.<br />

3. Gates: Provide personnel and vehicle gates of the quantity and size required for functional access to waste<br />

container storage area.<br />

a. Fabricate of same material as used for fencing.<br />

b. Equip with locks.<br />

01500 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Installation: Comply with manufacturer’s recommendations.<br />

1. Post and Fabric: Set posts in concrete footings, drive posts in ground, or set in holes and backfill to<br />

accommodate local conditions. Attach fabric to posts.<br />

2. Gates: Install gates with required hardware.<br />

1.11 TEMPORARY CONSTRUCTION FENCING<br />

A. Construction: Commercial grade chain link fence, 6 feet high.<br />

B. Provide fence around area of expansion and staging area.<br />

C. Coordinate installation and relocation with all trades, Wal-Mart Construction Manager, and the Store Manager.<br />

D. Equip with vehicular and pedestrian gates with locks.<br />

1.12 WATER CONTROL<br />

A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.<br />

B. Protect site from puddling or running water. Provide water barriers as required to protect site from soil erosion.<br />

C. The Contractor shall at all times protect all activities of his construction, excavations, fill areas, embankments,<br />

trenches structures or building from damage from rainwater, spring water, ground water, backing up of drains,<br />

sewers and all other water encountered during his operations. He shall provide all pumps, equipment and<br />

enclosures necessary to provide adequate protection.<br />

1.13 EXTERIOR ENCLOSURES<br />

A. Provide temporary weather-tight closure of exterior openings to provide acceptable working conditions and<br />

protection for Products, to allow for temporary heating and maintenance of required ambient temperatures<br />

identified in individual specification Sections, and to prevent entry of unauthorized persons.<br />

B. Provide access doors with self-closing hardware and locks.<br />

1.14 INTERIOR ENCLOSURES<br />

A. Provide temporary partitions as required to separate work areas from Owner occupied areas, to prevent penetration<br />

of dust and moisture into Owner occupied areas, and to prevent damage to existing materials and equipment.<br />

B. Framing and plywood sheet materials with closed joints and sealed edges at intersections with existing surfaces.<br />

1.15 FIELD OFFICES AND SHEDS<br />

A. Contractor's Office:<br />

1. Size as required for Contractor's use and to provide space for project meetings.<br />

2. Adequate electrical power, lighting, heating, and cooling to maintain human comfort.<br />

3. Office space with desk and chair, layout table, plan rack, and facilities for storage of Project Record<br />

Documents.<br />

4. In addition to Contractor office space, provide office space with one additional desk and chair for use by<br />

Wal-Mart Construction Testing Laboratory personnel.<br />

5. Furnishings in meeting area:<br />

a. Conference table and chairs for at least eight persons.<br />

b. Racks and files for Project Record Documents in, or adjacent to, the meeting area.<br />

c. Other furnishings: Contractor's option.<br />

6. Contractor's office and sheds shall not be used as living accommodations.<br />

B. Storage Sheds: Structurally sound, weathertight, on proper foundations, with floors raised above ground.<br />

01500 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Locate office and sheds minimum 30 feet from structures.<br />

1.16 CONSTRUCTION AIDS<br />

A. Provide construction aids required to facilitate execution of Work, including stairs, ladders, ramps, staging,<br />

platforms, railings, cranes, scaffolds, hoists, chutes, runways, and other required facilities and equipment.<br />

B. Coordinate crane service required for erection of structural steel, installation of HVAC Rooftop Units, Electrical<br />

Distribution Center (when used), and other crane services as required to accommodate Wal-Mart's needs.<br />

1.17 PROTECTION OF EXISTING WORK<br />

A. The existing building shall be protected from moisture, dust and debris. Install dust partitions or drapes as shown<br />

or as required to keep dust and moisture from the building premises.<br />

B. Damage to existing property (including merchandise), which occurs during the process of construction shall be<br />

repaired or replaced at no additional cost to the Owner. Contractor shall pay costs for damaged incurred.<br />

C. Provide suitable temporary watertight coverings over openings as required to protect interior work from inclement<br />

weather and related/adjacent construction areas.<br />

D. Maintain benchmarks, monuments and other reference point. If disturbed or destroyed, replace as directed.<br />

E. Protect existing adjacent streets, sidewalks, curbs, buildings and property, including trees, lawns and plants.<br />

1.18 PROTECTION OF INSTALLED WORK<br />

A. Protect installed Work; provide special protection where specified in individual specification Sections.<br />

B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to<br />

minimize damage.<br />

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.<br />

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects,<br />

by protecting with durable sheet materials.<br />

E. Minimize traffic and storage on roofed surfaces. If traffic or storage is necessary, obtain recommendations for<br />

protection from roofing material manufacturer.<br />

F. Do not operate cranes or other heavy equipment on concrete floor slabs if damage could result from such<br />

operations.<br />

G. Prohibit traffic from landscaped areas.<br />

1.19 SECURITY<br />

A. Maintain the integrity of the existing building security and security systems at all times. Provide security and<br />

facilities to protect Work and Owner's operations from unauthorized entry, vandalism, and theft.<br />

B. Obtain permission and coordinate with Owner's security program through Wal-Mart Construction Manager at least<br />

12 hours prior to the modification of any existing security system.<br />

C. Building Security: Employ a certified and bonded uniformed guard service licensed in the State in which project<br />

is located to provide security guard(s) to provide security and facilities to protect Wal-Mart Store facilities from<br />

unauthorized entry, vandalism and theft during performance of all work operations during Wal-Mart Store nonoperational<br />

hours.<br />

01500 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Provide continuous security at openings cut into existing exterior walls and roofs.<br />

1.20 ACCESS ROADS AND PARKING<br />

A. Construct and maintain temporary all weather roads accessing public thoroughfares to serve building pad and<br />

construction staging area.<br />

B. Extend and relocate as Work progress requires. Provide detours necessary for unimpeded traffic flow.<br />

C. Provide and maintain access to fire hydrants, free of obstructions.<br />

D. Provide temporary parking areas to accommodate construction personnel.<br />

E. When site space is not adequate, provide additional off- site parking.<br />

F. Provide 100 foot x 100 foot all weather material staging area exclusive of building pad.<br />

1.21 SIGNAGE<br />

A. Temporary Construction Signage: Provide temporary signage for identification as required due to obscurity<br />

caused by construction. Provide signage for traffic control and safety information. Provide temporary pavement<br />

striping for traffic control and pedestrian safety. Provide temporary handicap parking spaces if existing spaces are<br />

at a non-accessible location to the building entrance.<br />

B. Coming Soon Banner: Provide “Coming Soon Banner” in accordance with the detail and information shown on<br />

the drawings. Banners, which are to be furnished by the Contractor shall be ordered using the “Coming Soon Sign<br />

Order Form” included at the end of this section.<br />

1.22 INFORMATION/SAFETY BOARD<br />

A. Provide 4 foot x 8 foot x 3/4 inch C/D exterior glue plywood to be attached on the existing exterior wall at a<br />

location designated by the Wal-Mart Construction Manager.<br />

B. The board shall contain but not be limited to the following:<br />

1. OSHA Safety Requirements.<br />

2. Federal and State Hiring Regulations.<br />

3. Wal-Mart Safety Regulations and Procedures.<br />

4. Wal-Mart Construction Site and Safety Rules.<br />

5. Pertinent State, Local, and Federal Employment Regulations.<br />

6. Building Permits.<br />

7. Emergency telephone numbers.<br />

8. Job Site Safety Meeting notifications.<br />

9. EPA Permits or Notification regarding Asbestos or other Toxic or Hazardous Materials.<br />

10. Other information required to comply with applicable OSHA, EPA and Federal safety laws.<br />

C. Protect posted information with either plastic sleeves stapled to the board or 6 mil clear plastic sheathing over<br />

entire board providing access for posting of additional information.<br />

1.23 TEMPORARY FIRE PROTECTION<br />

A. Contractors and sub-contractors and their agents and employees shall comply with local fire protection codes and<br />

OSHA Regulations.<br />

1. Provide a minimum of one U.L. listed 2A:20BC dry chemical fire extinguisher, or one standard U.L. listed<br />

2-1/2 ga. Water (E-10) and one U.L. listed 10BC carbon dioxide fire extinguisher mounted together, in<br />

each of the following areas:<br />

a. Each 3000 sq. ft. of work area or fraction thereof with minimum of two extinguishers.<br />

01500 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Contractor's superintendent, or other assistant superintendents, shall be appointed as project fire warden for<br />

entire construction period.<br />

3. Train workmen in proper use of each type fire extinguisher.<br />

4. Post telephone number of fire department, specific information on location of on-site fire fighting<br />

equipment and procedure to be followed in event of fire.<br />

5. Maintain free access at all times to fire extinguisher equipment, street fire hydrants, and outside<br />

connections for standpipe hose systems.<br />

B. Maintain exit facilities and access thereto free of material and other obstructions. If any exits are rendered<br />

inoperative during remodeling, provide the same number of temporary exits and maintain a sufficient number of<br />

required exits and exit width as required by building codes and the authority having jurisdiction.<br />

1.24 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS<br />

A. Remove temporary above grade or buried utilities, equipment, facilities, materials, prior to Final Application for<br />

Payment inspection.<br />

B. Clean and repair damage caused by installation or use of temporary work.<br />

C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during<br />

construction to specified condition.<br />

D. At completion of construction, remove fencing, guardrails, barricades, temporary signage and temporary<br />

coverings.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01500 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Coming Soon Sign<br />

Order Form<br />

Project Type<br />

SuperCenter………____<br />

SAM’S…………….____<br />

Wal-Mart…………____<br />

WMT Neighborhood<br />

Market……………_____<br />

Project Store # :____________<br />

City & State: _____________________________<br />

Send To:<br />

________________________________<br />

(General Contractor / Superintendent)<br />

___________________________________________________________<br />

___________________________________________________________<br />

___________________________________________________________<br />

___________________________________<br />

Phone # ______________________________________________<br />

Send form to FastSigns by one of the following methods.<br />

Email ……… 279@fastsigns.com or joe.waugh@fastsigns.com<br />

Fax…………. (479) 872-2505<br />

Phone………. (877) 818-0870 Toll free<br />

One 4’x 8’ banner will be sent to the contact noted above. The<br />

package will include a detail for the installation with wood or steel<br />

post.<br />

01500 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 121809<br />

SECTION 01600 (01 6000) – PRODUCT REQUIREMENTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Basic Product Requirements.<br />

2. Product Options.<br />

3. Product Substitution Requirements.<br />

4. Direct Purchase Products.<br />

5. Product Delivery Requirements.<br />

6. Product Storage and Handling Requirements.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: Requirements related to Owner and Wal-Mart furnished<br />

products.<br />

1.2 DEFINITIONS<br />

A. Products: Defined as new material, machinery, components, equipment, fixtures, and systems forming the Work.<br />

Does not include machinery and equipment used for preparation, fabrication, conveying and erection of the Work.<br />

Products may also include existing materials or components required for reuse.<br />

1.3 BASIC PRODUCT REQUIREMENTS<br />

A. For products or workmanship specified by association, trade, or other consensus standards, comply with<br />

requirements of the standard, except when more rigid requirements are specified or are required by applicable<br />

codes.<br />

B. Conform to reference standard by date of issue current on date of Contract Documents.<br />

C. Obtain copies of standards when required by Contract Documents.<br />

D. Should specified reference standards conflict with Contract Documents, request clarification from Architect before<br />

proceeding.<br />

E. The contractual relationship, duties, and responsibilities of the parties to the Contract shall not be altered from the<br />

Contract Documents by mention or inference otherwise in any reference document.<br />

1.4 PRODUCT OPTIONS<br />

A. Products Specified by Naming a Single Manufacturer and/or Model Number: Provide specified product only<br />

unless otherwise specifically permitted in the specifications.<br />

B. Products Specified by Naming Two or More Manufacturers: Provide specified products of manufacturers and<br />

models named only, meeting specifications and specified requirements unless otherwise specifically permitted in<br />

the specifications.<br />

C. Products Specified by Reference Standards or by Description Only: Provide any product meeting specified<br />

reference standard or description.<br />

01600 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 PRODUCT SUBSTITUTION REQUIREMENTS<br />

A. No substitutions permitted. Provide specified products only unless otherwise specifically permitted in the<br />

specifications.<br />

1.6 DIRECT PURCHASE PRODUCTS<br />

A. Direct purchase products shall be purchased directly by the General Contractor from the Manufacturer or the Pre-<br />

Negotiated Supplier as specified in the individual Specifications Sections. Direct purchased products shall not be<br />

purchased by any subcontractor regardless of the discipline or subcontract involved in the installation.<br />

1.7 PRODUCT DELIVERY REQUIREMENTS<br />

A. Transport and handle products in accordance with manufacturer's instructions. Deliver materials and equipment at<br />

such stages of work in order to expedite the Work and minimize storage requirements.<br />

B. Schedule delivery for Wal-Mart and Owner furnished and installed equipment such that upon delivery of<br />

equipment to the site, sufficient equipment provisions are in place ready for installation and hook-up.<br />

C. Promptly inspect shipments to assure that products comply with requirements, quantities are correct, and products<br />

are undamaged.<br />

D. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, and damage.<br />

Do not use damaged materials and equipment.<br />

1.8 PRODUCT STORAGE AND HANDLING REQUIREMENTS<br />

A. Provide safe storage of products.<br />

B. Store and protect products in accordance with manufacturer's instructions, with seals and labels intact and legible.<br />

Store sensitive products in weather-tight, climate controlled enclosures.<br />

C. For exterior storage of fabricated products, place on sloped supports, above ground.<br />

D. Provide off-site storage and protection when site does not permit on-site storage or protection.<br />

E. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent<br />

condensation.<br />

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.<br />

G. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.<br />

H. Arrange storage of products to permit access for inspection. Periodically inspect to assure products are<br />

undamaged and are maintained under specified conditions.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Provide interchangeable components of the same manufacturer, for components being replaced.<br />

B. Do not use materials and equipment removed from existing premises, except as specifically permitted by the<br />

Contract Documents.<br />

01600 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01600 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 01640 (01 6400) – OWNER FURNISHED PRODUCTS<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner Furnished Products.<br />

B. Related Requirements:<br />

1. Section 01600 - Product Requirements: General product requirements related to all products.<br />

1.2 DEFINITIONS<br />

A. Defined in Construction Agreement. Owner may also be referred to as “Wal-Mart”.<br />

1.3 RESPONSIBILITIES FOR OWNER FURNISHED PRODUCTS<br />

A. Product Delivery: Product supplier will deliver products to jobsite for Contractor to receive on delivery date<br />

established by Contractor. Supplier will contact Contractor after Award of Contract to establish a product delivery<br />

and installation date, quantities of materials, and a coordination procedure. In the event Supplier contact cannot be<br />

made, contact Wal-Mart Store Planning at (479) 204-0684 (select option 1) and construction.buyouts@walmart.com.<br />

B. Owner Responsibilities:<br />

1. Responsibilities by Owner shall correspond to the party furnishing the product as specified hereinafter.<br />

2. Arrange for delivery of supplier furnished shop drawings, product data, samples, and installation<br />

instructions to Contractor.<br />

3. Arrange and pay for product delivery to site, in accordance with agreed upon construction schedule.<br />

a. Deliver supplier's shipment list of materials to Contractor.<br />

b. Submit claims for transportation damage.<br />

c. Arrange for replacement of damaged, defective, or missing items.<br />

d. Arrange for manufacturers' warranties, bonds, services, and inspections, as required.<br />

C. Contractor Responsibilities:<br />

1. Review supplier furnished shop drawings, product data, and samples under provisions of Section 01330.<br />

Submit to supplier with notification to Architect, Owner, and Wal-Mart's Construction Department of any<br />

discrepancies or problems anticipated in the use the products.<br />

2. Receive and unload products at the Site when specified.<br />

3. Verify quantity of products furnished with shop drawings, Final Field Use Drawings, or Bills of Lading as<br />

applicable.<br />

4. Promptly inspect products upon receipt for shortages, damaged, or defective items; report to Owner and<br />

Wal-Mart's Construction Department. Upon notification, Owner will arrange for delivery of replacement<br />

products.<br />

5. Handle products at site, including uncrating, storage, and protection unless otherwise specified.<br />

6. Install products when specified.<br />

7. Provide for installation and hook-up at time of delivery of Owner installed equipment.<br />

8. Protect installed products from damage.<br />

9. Replace items damaged by Contractor.<br />

10. Remove trash, debris, and rubbish.<br />

11. Manufacturing Defects: Report suspected product manufacturing defects to Wal-Mart Construction<br />

Manager and Product Supplier. Upon notification, Owner will arrange for repair of product manufacturing<br />

defects.<br />

01640 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 CONTRACTOR INSTALLATION OF OWNER FURNISHED PRODUCTS<br />

A. Install in accordance with manufacturer's instructions.<br />

B. Coordinate installation of Owner installed products and equipment.<br />

C. Work in harmony with all subcontractors, suppliers and manufacturers.<br />

D. Unpack and set in place, plumb, level, and secure.<br />

E. Connect to mechanical, plumbing, and electrical systems as required.<br />

F. Remove packaging and clean products.<br />

G. Test and adjust as required.<br />

PART 2 PRODUCTS<br />

NOT USED<br />

PART 3 EXECUTION<br />

3.1 PRODUCTS FURNISHED BY OTHERS SCHEDULE<br />

A. Equipment will be furnished by the Owner for installation by either the Contractor or by others as specified in the<br />

Products Furnished by Others Schedule included hereinafter.<br />

B. The Products Furnished by Others Schedule includes a listing of Owner furnished products as required in the listed<br />

specifications sections or drawings. Refer to the applicable drawings or individual sections for specific details<br />

regarding Owner furnished products therein. The Schedule provides summary information only and does not<br />

preclude or supersede requirements contained in the individual sections.<br />

C. Unless otherwise specified, Contractor shall coordinate delivery date of Owner furnished equipment. If significant<br />

order lead times are required for a specific product, lead time shall be as specified for that product.<br />

D. Meat Market equipment, fixtures, and cases shall be set in place by the Equipment Manufacturer in the locations<br />

shown on the Drawings. If discrepancy occurs or locations are in question, contact the Wal-Mart Construction<br />

Manager for clarification and directive prior to proceeding with the Work.<br />

3.2 CONTACTS<br />

A. Contact information for vendors of Owner Furnished Equipment will be made available to the Contractor at the<br />

Pre-Construction Conference or upon request by the Contractor to the Construction Manager. A limited list of<br />

contacts are as follows:<br />

1. Floral Cases: Structural Concepts, 888 Porter Rd., Muskegon, MI 49441.<br />

2. ATMs: Walmart Financial Services, Gene Wallace, (479) 204 1610.<br />

01640 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PRODUCTS FURNISHED BY OTHERS SCHEDULE<br />

Specification<br />

Section<br />

Description Furnished By Received By Installed By<br />

Order<br />

Date*<br />

Delivery Date*<br />

01455 Test and Balance Owner Owner Owner 1 week<br />

02812<br />

Automatic Controllers and associated<br />

equipment<br />

Owner Contractor Contractor Contractor to schedule<br />

02845 Cart Corrals Owner Contractor Contractor 4 weeks<br />

02870<br />

Metal Bicycle Parking Rack,<br />

Metal Bench and Waste Container<br />

Owner Contractor Contractor Contractor to schedule<br />

05500 Metal Fabrications<br />

• Jib Crane Hoist Arm and Railing<br />

Assembly<br />

• LP Monitor Wall Mount and Ceiling<br />

Mount Support Assemblies<br />

• Interior Galvanized Steel Pipe Bollards<br />

(Base Plate Mounted)<br />

• Interior Stainless Steel Pipe Bollards<br />

(Floor Mounted)<br />

• Interior Galvanized Steel Pipe Bollards<br />

(Floor Mounted)<br />

Owner Contractor Contractor Contractor to schedule<br />

Owner Contractor Contractor Contractor to schedule<br />

Owner Contractor Contractor Owner to schedule<br />

Owner Contractor Contractor Owner to schedule<br />

Owner Contractor Contractor Owner to schedule<br />

Drawings<br />

• Stainless Steel Floor Mounted Railing Owner Contractor Contractor Owner to schedule<br />

• Refrigerated Case Corner Protection<br />

(Stainless Steel Angled Corner Guards)<br />

Owner Contractor Contractor Owner to schedule<br />

06065 Thermoplastic Sleeves for Pipe Bollards Owner Contractor Contractor Contractor to schedule<br />

Drawings<br />

Garden Center Hose Cart Assembly<br />

(Reel, Hose, & Watering Wand)<br />

Owner Contractor Owner Possession Date<br />

07721 Structural and Adapter Roof Curbs Owner Contractor Contractor Contractor to schedule<br />

08110 Steel Doors and Frames Owner Contractor Contractor Contractor to schedule<br />

08332 Overhead Rolling Closures Owner Contractor Contractor Contractor to schedule<br />

08337 Coiling Counter Shutter Owner Contractor Contractor Contractor to schedule<br />

08360 Sectional Overhead Doors Owner Contractor Owner Contractor to schedule<br />

08383 Traffic Doors Owner Contractor Contractor Contractor to schedule<br />

08462 Automatic Sliding Entrance Doors Owner Owner Owner Contractor to schedule<br />

08710<br />

All Door Hardware except Positive Lock<br />

Exit Device<br />

Owner Contractor Contractor Contractor to schedule<br />

08710 Positive Lock Exit Device Owner Contractor Contractor Contractor to schedule<br />

09310 Vestibule Tile and Accessories Owner Contractor Contractor Contractor to schedule<br />

01640 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Specification<br />

Section<br />

09650<br />

Description Furnished By Received By Installed By<br />

Resilient Flooring and Adhesive.<br />

PVC to Concrete Transition Strip.<br />

Order<br />

Date*<br />

Delivery Date*<br />

Owner Contractor Contractor Contractor to schedule<br />

09680 Carpet Owner Contractor Contractor Contractor to schedule<br />

09900 Paints and Primers (Limited Quantities) Owner Contractor Contractor Contractor to schedule<br />

10671 Pharmacy Racks and Wall Standards Owner Contractor Contractor Contractor to schedule<br />

10675 Modular Rack and Fence Owner Contractor Contractor Contractor to schedule<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Signage (unless noted otherwise) Owner Owner Owner<br />

Menu Board signage railing and required<br />

accessories<br />

Contractor coord.<br />

with Sign Dept.<br />

Owner Contractor Contractor 1-4 weeks<br />

10810 Soap Dispensers Owner Contractor Contractor Possession date<br />

10810<br />

10810<br />

Paper Towel Dispensers, Surface Mounted<br />

At Pharmacy and Pharmacy Toilet<br />

Paper Towel Dispensers, Surface Mounted<br />

At Grocery<br />

Owner Owner Owner Contractor to schedule<br />

Owner Contractor Contractor Contractor to schedule<br />

11160 Loading Dock Equipment Owner Contractor Owner Contractor to schedule<br />

11400 Breakroom Refrigerated Case Owner Contractor Contractor Contractor to schedule<br />

11400 Food Service Equipment<br />

Refer to Grocery Drawings for Schedule of<br />

Equipment<br />

Contractor coordinate<br />

with equip supplier<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Rack<br />

Anchorage<br />

Drawings<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawing<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Architectural<br />

Drawings<br />

Stock Room Motorized Racks Owner Owner Owner 1 – 4 weeks<br />

High Stock Fixed Racks Owner Owner Owner 1 – 4 weeks<br />

Anchors for High Stock Fixed Racks Owner Owner Contractor 1 – 4 weeks<br />

Balers/Compactors Owner Owner Owner 3 weeks<br />

Safe Owner Contractor Contractor 9 weeks 27 days<br />

Photo Lab Equipment Owner Owner<br />

Owner<br />

Contr.<br />

Hook-Up<br />

After Possession date<br />

Modular Photo Lab (Casework) Owner Owner Owner Contractor to schedule<br />

Pharmacy Water Filtration System Owner Contractor Contractor 4 –6 weeks<br />

12" Convex Mirror in Pharmacy Owner Contractor Contractor 4 - 6 weeks<br />

Fire Extinguishers Contractor Contractor Contractor Contractor to schedule<br />

Insect Control Units Owner Contractor Contractors Contractor to schedule<br />

13121 Fabric Structures Owner Contractor Contractor 8 weeks<br />

01640 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Specification<br />

Section<br />

13425<br />

13425<br />

Description Furnished By Received By Installed By<br />

Main Demand Sub-Meter for Sub-Metering<br />

Instrumentation System<br />

Data Logger and CT Sub-Meter for Sub-<br />

Metering Instrumentation System<br />

Order<br />

Date*<br />

Delivery Date*<br />

Owner Owner Owner Contractor to schedule<br />

Owner Contractor Contractor Contractor to schedule<br />

13810 Energy Monitoring and Control Systems Owner Contractor Contractor Contractor to schedule<br />

Plumbing<br />

Drawings<br />

Domestic Water Booster Pump (If required<br />

by Drawings)<br />

Owner Contractor Contractor Contractor to schedule<br />

15600,<br />

Grocery<br />

Drawings<br />

15600,<br />

Grocery<br />

Drawings<br />

15600,<br />

Grocery<br />

Drawings<br />

Grocery<br />

Drawings<br />

Grocery<br />

Drawings<br />

Refrigeration including<br />

Condensers/Evaporators, Refrigerated<br />

Cases, & Refrigeration Alarm System.<br />

Self Contained Refrigerated Cases, Ice<br />

Flakers, &Produce Misting System (Where<br />

indicated)<br />

Owner Contractor Contractor<br />

Owner Contractor Contractor<br />

Compressor Racks Owner Contractor Contractor<br />

R.O. Water Filter Equipment Owner Contractor Contractor<br />

Walk-in Freezers and Cooler Owner Owner Owner<br />

Contr. To coord. W/<br />

Wal-Mart Mechanical<br />

Services Dept.<br />

Contr. To coord. W/<br />

Wal-Mart Mechanical<br />

Services Dept.<br />

Contr. To coord. W/<br />

Wal-Mart Mechanical<br />

Services Dept.<br />

Contr. To coord. W/<br />

Wal-Mart Mechanical<br />

Services Dept.<br />

Contr. To coord. W/<br />

Wal-Mart Mechanical<br />

Services Dept.<br />

15700 Roof Top Air Conditioning Units Owner Contractor Contractor Contractor to schedule<br />

15700 Sales Area Air Handling Units Owner Contractor Contractor Contractor to schedule<br />

15800 Drop Box Diffusers Owner Contractor Contractor Contractor to schedule<br />

16265 Central UPS Owner Contractor Contractor 3 weeks<br />

16405 Electrical Distribution Center (EDC) Owner Contractor Contractor<br />

16500 Lighting Fixtures as Noted Owner Contractor Contractor<br />

Contractor to schedule<br />

Allow 10 week<br />

minimum lead time<br />

Contractor to schedule<br />

Allow 4 week<br />

minimum lead time<br />

16525<br />

(Div 2.1)<br />

Site Lighting: Poles, Anchor bolts,<br />

Luminaires, and Lamps.<br />

Owner Contractor Contractor Contractor to schedule<br />

16700 Satellite Dish Equipment and Cabling Owner Owner Owner 3 weeks<br />

16700 Telephone<br />

• Telephone Service Installed Owner Owner Owner 10 weeks 4 weeks<br />

• Telephone System (Phase 1) Owner Owner Owner 4 weeks<br />

• Telephone System (Phase 2) Owner Owner Owner<br />

2 weeks after<br />

possession<br />

01640 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Specification<br />

Section<br />

Description Furnished By Received By Installed By<br />

Order<br />

Date*<br />

Delivery Date*<br />

Electrical<br />

Drawings<br />

Fire and Security Alarm System<br />

• Fire Alarm System Owner Owner Owner 4 weeks<br />

• Burglar Alarm System Owner Owner Owner 4 weeks<br />

* Dates are based on number of weeks prior to possession (unless noted otherwise).<br />

END OF SCHEDULE<br />

01640 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052810<br />

SECTION 01700 – EXECUTION REQUIREMENTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Examination of existing conditions.<br />

2. General construction requirements.<br />

3. Work within and adjacent to existing building areas.<br />

1.2 EXAMINATION<br />

A. Verify existing conditions prior to bidding and commencement of Work. If discrepancies are found between what<br />

is shown on the Drawings and existing field conditions, notify the Wal-Mart Construction Manager and the<br />

Architect to determine action to be taken to resolve differences.<br />

B. Verify the existing structural column dimensions, structural bearing heights, existing dimensions, top of masonry<br />

elevations, and joist bearing elevations prior to the fabrication of any structural items. The beginning of structural<br />

steel fabrication by the General Contractor, Steel Supplier, Steel Fabricator, or Joist Manufacturer means<br />

acceptance of the existing conditions.<br />

C. Utility locations shown are approximate. Field verify the exact location and depths of existing utilities (whether<br />

shown or not) prior to the submission of bid or the commencement of construction. Notify the Wal-Mart<br />

Construction Manager of the discovery of existing utilities not shown or noted on Drawings.<br />

D. Field locate and verify property lines, easements, setbacks and restrictions. Obtain services of a Registered<br />

Surveyor to establish property lines and setbacks prior to the commencement of construction and flag property<br />

lines and setbacks.<br />

E. Verify grades and proposed final grades. If ramps, stoops, or stairs are installed, verify final grades surrounding<br />

the new construction and adjust stair risers, ramp lengths, limits of paving, etc., to accommodate the required ramp<br />

slope, riser heights, or paving areas. Conform to ADA requirements for ramps and stairs unless otherwise<br />

specifically noted.<br />

F. Verify the existing finish floor elevation at new openings of the existing building prior to establishing the finish<br />

floor elevation. Verify existing footing depths and match at new work to insure proper block coursing.<br />

G. Core the roof insulation to determine its thickness prior to Bidding. The roof insulation thickness of the new work<br />

shall match that of existing.<br />

1.3 GENERAL CONSTRUCTION REQUIREMENTS<br />

A. Perform work in a safe and workmanlike manner and in strict accordance with the local governing Building Code,<br />

National Electric Code, ADA-ADAAGS (Federal Handicap Accessibility Standards), and all applicable codes,<br />

regulations and ordinances having jurisdiction.<br />

B. Subcontractors shall be familiar with drawings and specifications in their related field. Failure to be acquainted<br />

with this knowledge will not relieve subcontractors the responsibility for performing the work properly. No<br />

additional compensation will be allowed due to conditions that occur through to failure to familiarize workers.<br />

C. Complete roof framing, decking, and roofing system immediately upon the demolition of the exterior wall to<br />

eliminate potential water damage or moisture infiltration.<br />

01700 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 WORK WITHIN AND ADJACENT TO EXISTING BUILDING AREAS<br />

A. Comply with Wal-Mart building and Store Manager regulations for work within building. Specific regulations<br />

will be discussed by Wal-Mart Construction Manager at Preconstruction Conference.<br />

B. The following provisions shall apply to construction work within a totally enclosed building which is currently<br />

operating and open to the public.<br />

1. Do not operate gasoline or diesel powered equipment within the building.<br />

2. Operate gasoline or diesel powered generators or compressors outside the building and away from air<br />

intakes.<br />

3. Electric equipment and equipment operated by propane or compressed air may be operated within the<br />

building.<br />

4. Provide catalytic converters on mufflers of propane powered equipment operated within the building and<br />

maintain and operate equipment in compliance with local, state and federal regulations.<br />

a. Store and handle propane fuel in compliance with local, state and federal regulations.<br />

b. Do not allow propane fuel inside the building except during operation of propane equipment.<br />

c. Refuel propane powered equipment outside the building.<br />

5. Size temporary electrical cords adequately for voltage, current load and length.<br />

6. Route temporary electrical cords and air hoses in compliance with applicable OSHA requirements.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

Not Used.<br />

END OF SECTION<br />

01700 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082605<br />

SECTION 01731 – CUTTING AND PATCHING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Requirements and limitations for cutting and patching Work.<br />

2. Products for patching and extending Work.<br />

3. Transitions and adjustments.<br />

4. Repair of damaged surfaces, finishes and cleaning.<br />

B. Related Sections:<br />

1. Section 01500 - Temporary Facilities and Controls: Temporary barriers.<br />

2. Section 02023 - Selective Site Demolition: Procedures for removing existing materials and equipment.<br />

1.2 PERFORMANCE REQUIREMENTS<br />

A. Cutting and patching includes cutting into existing construction to provide for installation or performance of other<br />

work and subsequent fitting and patching required to restore surfaces to their original condition.<br />

B. Cut into or partially remove portions of the existing building as required for new construction. Include such work<br />

as:<br />

1. Cutting, moving or removal of items shown to be cut, moved or removed.<br />

2. Cutting, moving or removal of items not shown to be cut, moved, or removed, but which must be cut,<br />

moved, or removed to allow for new construction. Work or items which are to remain in the finished work<br />

shall be patched or reinstalled after cutting, moving, or removal, and joints and finishes shall match<br />

adjacent or similar work.<br />

3. Removal of existing surface finishes as needed to install new work and finishes.<br />

4. Removal of abandoned items and removal of items serving no useful purpose; such as abandoned piping<br />

and electrical conduits to nearest J-boxes.<br />

5. Repair or removal of dangerous or unsanitary conditions resulting from alterations work.<br />

C. Structural Work:<br />

1. Do not cut and patch structural work in manner resulting in reduction of load-carrying capacity or load and<br />

deflection ratio.<br />

2. Submit proposal for cutting and patching of structural work and obtain Wal-Mart Construction Manager's<br />

approval prior to the structural alterations.<br />

D. Operational Limitations:<br />

1. Do not cut and patch in manner resulting in decreased performance, shortened useful life, or increased<br />

maintenance.<br />

2. Submit proposals for cutting and patching operational elements and safety components and obtain Wal-<br />

Mart Construction Manager's acceptance prior to the work.<br />

E. Quality Limitations: Do not cut and patch work exposed to view (exterior and interior) in manner resulting in<br />

noticeable reduction of aesthetic qualities and similar qualities, as determined by the Wal-Mart Construction<br />

Manager.<br />

F. Limitation on Acceptance: Wal-Mart Construction Manager's acceptance to proceed with cutting and patching<br />

shall not waive right to later require removal or replacement of work found to be cut and patched in unsatisfactory<br />

manner as determined by Wal-Mart Construction Manager.<br />

01731 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Use materials for cutting and patching that are identical to existing materials. If identical materials are not<br />

available or cannot be used, use materials that match existing adjacent surfaces to fullest extent possible with<br />

regard to visual effect. Use materials for cutting and patching that will result in equal or better performance<br />

characteristics.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces to be cut and patched and conditions under which work is to be performed before cutting. Take<br />

corrective action before proceeding with work if unsafe or otherwise unsatisfactory conditions are encountered.<br />

3.2 PREPARATION<br />

A. Temporary Support: Provide temporary support of work to be cut to prevent failure.<br />

B. Protection:<br />

1. Protect other work during cutting and patching to prevent damage.<br />

2. Provide protection from adverse weather conditions for that part of project that may be exposed during<br />

cutting and patching operations.<br />

3. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.<br />

4. Take precautions not to cut existing pipe, conduit, or duct serving building but scheduled to be relocated<br />

until provisions have been made to bypass them.<br />

3.3 CUTTING AND PATCHING<br />

A. Remove, cut, and patch Work in a manner to minimize damage and to provide means of restoring products,<br />

materials and finishes to original condition.<br />

B. Cut work using methods that are least likely to damage work to be retained or adjoining work.<br />

C. Where cutting is required, use hand or small power tools designed for sawing or grinding rather than hammering<br />

or chopping. Cut through concrete and masonry using cutting machines such as a carborundum saw or core drill.<br />

Cut holes and slots neatly to size required with minimum disturbance of adjacent work. To avoid marring existing<br />

finished surfaces, cut and drill from exposed or finished side into concealed surfaces. Temporarily cover openings<br />

when not in use.<br />

D. Patch with seams that are durable and as invisible as possible. Comply with specified tolerances for work.<br />

E. If the surrounding surface cannot be matched, repaint or recoat the entire surface to the nearest corner or transition<br />

point.<br />

3.4 TRANSITIONS<br />

A. Where expansion new Work abuts or aligns with existing Work, provide a smooth and even transition. Patched<br />

Work shall match existing adjacent Work in texture and appearance.<br />

B. Patched Work shall match existing adjacent Work in texture and appearance so as to make the patch or transition<br />

invisible to the eye at a distance of no closer than three feet.<br />

C. When finished surfaces are cut so that a smooth transition with expansion new Work is not possible, terminate<br />

existing surface along a straight line at a natural line of division.<br />

01731 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Where two or more spaces are indicated to become one space, reconstruct ceilings to provide horizontal planes<br />

without breaks, steps or bulkheads.<br />

E. In cases of extreme change of ceiling or floor, obtain instructions from the Wal-Mart Construction Manager for<br />

method of making an acceptable transition.<br />

3.5 REPAIR OF DAMAGED SURFACES<br />

A. Patch or replace portions of existing surfaces, which are damaged, discolored, or showing imperfections. Repair<br />

substrate prior to patching finish.<br />

B. Restore existing work that is damaged during construction to a condition equal to its condition at the time of the<br />

start of the Work.<br />

C. At locations in existing areas where partitions are removed, patch the floors, walls, and ceilings with finish<br />

materials to match new finishes.<br />

D. Where plumbing is removed and capped below finish floor, core drill concrete floor as required and cap a<br />

minimum of 8" below floor. Patch new concrete to match existing floor.<br />

3.6 FINISHES<br />

A. Finish surfaces as specified in individual product sections.<br />

B. Finish patched area shall produce uniform finish and texture over entire area. When finish cannot be matched,<br />

refinish entire surface to nearest intersections.<br />

3.7 MATCHING AND REPLACING EXISTING WORK<br />

A. Where a product or type of construction occurs in the existing building, which is not specified as a part of the new<br />

work, provide such products or types of construction as needed to patch, extend, or match the existing work.<br />

B. Provide materials and finishes used for expansion Work of same type as existing materials and finishes.<br />

C. Patching, extending, or matching shall be consistent with existing standards of quality.<br />

D. Remove existing items, services, finishes, or surfaces as required for the installation of new construction. Provide<br />

furring for conduits and piping, shown or not, and finish furring to match adjacent existing finishes.<br />

E. Repair, re-route, and extend all services, piping, and conduit of existing items and equipment as required during<br />

construction operations for installation and operation of new items and equipment. This includes all items shown<br />

or not shown on the Drawings. Re-install existing equipment or related items in areas affected by Work as<br />

required for proper operation.<br />

F. Where existing finishes are to remain, clean, repair, patch and repaint as necessary to blend in with adjacent work.<br />

END OF SECTION<br />

01731 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 01740 – CLEANING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Cleaning and maintenance of site premises.<br />

B. Related Requirements:<br />

1. Section 01742 - Construction/Demolition Waste Management and Disposal: Disposal and removal of nonhazardous<br />

construction and demolition waste.<br />

2. Section 01743 - Hazardous/Universal Waste Management and Disposal: Disposal and removal of<br />

hazardous construction and demolition waste.<br />

1.2 REGULATORY REQUIREMENTS<br />

A. Codes and Standards: Comply with applicable Federal, State and Local codes and regulations relative to<br />

environmental safety regulations.<br />

B. Hazards Controls: Store volatile waste in covered metal containers and remove from premises daily. Prevent<br />

accumulation of wastes which create hazardous conditions.<br />

C. Pollution Control:<br />

1. Do not burn or bury rubbish and waste materials on the project site.<br />

2. Do not disposal of volatile fluid wastes (such as mineral spirits, oil or paint thinner) in storm or sanitary<br />

sewer systems or into streams or waterways.<br />

3. Do not disposal of any toxic chemicals in storm or sanitary sewer systems. Comply with EPA<br />

requirements regarding disposal.<br />

PART 2 - PRODUCTS<br />

2.1 CLEANING MATERIALS<br />

A. Use only cleaning materials recommended by manufacturer of surface to be cleaned.<br />

B. Use cleaning materials only on surfaces recommended by cleaning material manufacturer.<br />

C. Cleaning materials shall be clearly labeled and safely stored when not in use. Maintain control of cleaning<br />

materials while in use. Do not leave unattended. No flammable materials or liquids may be stored in the existing<br />

building or in the new addition.<br />

PART 3 - EXECUTION<br />

3.1 CLEANING REQUIREMENTS<br />

A. Oversee cleaning and ensure that building and grounds are maintained free from accumulations of waste materials<br />

and rubbish.<br />

B. In exterior work, sprinkle dusty debris with fine water mist to control accumulation of dust. Avoid puddling.<br />

C. Vacuum clean interior building areas when ready to receive finish painting and continue vacuum cleaning on an<br />

as-needed basis until building is ready for acceptance or occupancy.<br />

01740 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Schedule cleaning operations so that dust and other contaminants resulting from cleaning process will not fall on<br />

wet, newly-painted surfaces.<br />

E. Clean exterior premises daily. Do not let debris enter customer areas.<br />

3.2 ACOUSTICAL PANEL CEILING AND EXPOSED OVERHEAD STRUCTURE CLEANING<br />

A. Clean existing exposed surfaces of acoustical panel ceilings in all areas. Clean existing exposed overhead<br />

structure. Surfaces to be cleaned include the following:<br />

1. Acoustical tile ceilings to remain in place including trim, edge moldings, suspension system members,<br />

diffusers, speakers, and camera mounts.<br />

2. Exposed overhead structure to remain in place including, but not limited to, structural steel, steel joists,<br />

metal deck, drop boxes, ductwork, and bracing members.<br />

B. Qualifications: Cleaning shall be done by a reputable firm regularly engaged in cleaning of acoustical tile ceilings<br />

and overhead structure and shall have been in business for a continuous period of not less than 2 years. Firm shall<br />

be experienced in work of the nature and scale similar to this project.<br />

C. Products and Procedure:<br />

1. Cleaning Products: Accomplish cleaning using solutions and products specifically formulated and<br />

recommended for cleaning the surfaces involved. Products shall be non-toxic and non-caustic to metal or<br />

acoustic surfaces. Products shall be enzyme based or of such ingredients to effectively clean, whiten, and<br />

dissolve nicotine tar, cooking oils and grease, soiling, soot, smoke, mildew, and dirt films. Products<br />

containing bleach will not be allowed. Products shall be by a manufacturer regularly engaged in the<br />

production of such products.<br />

2. Procedure: Cleaning procedure shall be as follows:<br />

a. Cover entirely with drop cloths, all merchandise, furniture, equipment, and floors in areas to be<br />

cleaned.<br />

b. Dust or vacuum tiles and tile suspension system and structural members to remove loose dirt and<br />

dust.<br />

c. Apply cleaning solutions by spray or mist at a rate recommended by product instructions depending<br />

on type and porosity of surface to be cleaned.<br />

d. Allow sufficient time as recommended by product instructions for solutions to react.<br />

e. Remove solutions with sponges and wipe dry.<br />

f. Follow written instructions of product manufacturer where such instructions vary from, or are in<br />

addition to, the foregoing procedures.<br />

D. Coordination and Scheduling: Perform cleaning during periods when store is closed or during low traffic periods,<br />

typically between 10:00 PM and 6:00 AM. Coordinate cleaning schedule with store manager. Submit to the store<br />

manager, a mutually agreed upon cleaning schedule at least 7 days prior to commencement of cleaning operations.<br />

E. Cleaning shall be completed within 45 days of possession of area cleaned. Schedule with Wal-Mart Construction<br />

Manager.<br />

3.3 TRASH REMOVAL<br />

A. On a daily basis, clean work areas and access, and dispose of waste materials, rubbish and debris.<br />

B. Disposal of non-hazardous demolished materials shall be at Contractor’s expense as specified in Section 01742.<br />

C. Disposal of hazardous materials shall be at Contractor’s expense as specified in Section 01743.<br />

D. Deposit waste materials, rubbish, and debris in waste containers as specified in Section 01742. Perform<br />

segregation of waste materials into the various classification and segregated materials.<br />

E. Do not allow waste materials, rubbish and debris to accumulate and become an unsightly or hazardous condition.<br />

01740 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


F. Keep streets and access to site free of rubbish and debris.<br />

3.4 FINAL CLEANING<br />

A. Execute final cleaning prior to final inspection as follows:<br />

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape<br />

development areas, of rubbish, waste material, litter, and other foreign substances.<br />

2. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.<br />

3. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.<br />

4. Remove tools, construction equipment, machinery, and surplus material from Project site.<br />

5. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and<br />

similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective<br />

surfaces to their original condition.<br />

6. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches,<br />

equipment vaults, manholes, attics, and similar spaces.<br />

7. Clean debris from roofs, gutters, downspouts, and drainage systems.<br />

8. Vacuum carpet and similar soft surfaces, removing debris and excess nap; shampoo if visible soil or stains<br />

remain.<br />

9. Vacuum clean all interior floor surfaces.<br />

10. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing<br />

compounds and other noticeable, vision-obscuring materials. Replace chipped or broken glass and other<br />

damaged transparent materials. Polish mirrors and glass, taking care not to scratch surfaces.<br />

11. Remove labels that are not permanent.<br />

12. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and<br />

surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or<br />

restoration.<br />

13. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication,<br />

paint, and mortar droppings, and other foreign substances.<br />

14. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water<br />

exposure.<br />

15. Replace disposable air filters and clean permanent air filters of equipment operated during construction.<br />

Clean exposed surfaces of diffusers, registers, and grills.<br />

16. Clean ducts, blowers, and coils if units were operated without filters during construction.<br />

17. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. Replace burned-out<br />

bulbs, and those noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and<br />

mercury vapor fixtures.<br />

18. Leave Project clean and ready for occupancy.<br />

B. Cleaning of Toilets Prior to Possession:<br />

1. Immediately prior to possession, clean toilets thoroughly including each toilet fixture and accessory.<br />

2. Clean entire wall and floor surfaces using cleaning solutions and wipe dry to prevent surface film or<br />

residue.<br />

3. Clean water closets and sinks with scrubbing cleansers to remove stains and deposits.<br />

4. Clean and polish stainless steel accessories and toilet partitions to a spotless luster using soap, ammonia, or<br />

mild detergent and water. Apply with sponge or soft cloth, rinse with clear water, and wipe dry. As an<br />

alternate, use a commercial stainless steel cleaner and polish.<br />

5. Clean mirror surfaces using glass cleaner.<br />

C. Employ skilled workmen for final cleaning.<br />

D. Prior to final completion or Owner possession, conduct an inspection of sight-exposed interior and exterior<br />

surfaces and all work areas with the Wal-Mart Construction Manager to verify that entire Work is clean.<br />

END OF SECTION<br />

01740 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 01742 (01 7420) – CONSTRUCTION/DEMOLITION WASTE MANAGEMENT AND DISPOSAL<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Administrative and procedural requirements for nonhazardous demolition and construction<br />

waste removal and disposal.<br />

B. Related Requirements:<br />

1. Section 01500 - Temporary Facilities and Controls. Temporary chain link fencing for construction and<br />

demolition waste management containers.<br />

2. Section 01740 - Cleaning. Site and premises cleanup during and at completion of construction.<br />

3. Section 01743 - Hazardous/Universal Waste Management and Disposal: Disposal and removal of<br />

hazardous construction and demolition waste.<br />

4. Section 02023 - Selective Site Demolition.<br />

5. Section 02223 - Removal and Recycling of Vinyl Composition Tile (VCT).<br />

6. Section 02224 - Removal and Recycling of Acoustical Ceiling Tile (ACT).<br />

1.2 DEFINITIONS<br />

A. Construction Waste: Building and site improvement solid waste materials resulting from construction,<br />

remodeling, renovation, or repair operations. Construction waste includes shipping and packaging and discarded<br />

temporary construction materials.<br />

B. Non-Hazardous Landfill: A landfill that accepts non-hazardous resources such as household, commercial, and<br />

industrial waste, resulting from construction, remodeling, repair, and demolition operations, has a solid waste<br />

facilities permit from the State Waste Management Regulatory Board, and is in full compliance with Federal, State<br />

and local Environmental Regulatory Agencies.<br />

C. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition<br />

operations.<br />

D. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit<br />

in landfill acceptable to Authorities Having Jurisdiction.<br />

E. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.<br />

F. C&D Recycling Center: A facility that receives only construction and demolition material that has been separated<br />

for reuse prior to receipt.<br />

G. Inert Disposal Facility or Inert Waste Landfill: A disposal facility that accepts only inert waste such as soil and<br />

rock, fully cured asphalt paving, uncontaminated concrete (including fiberglass or steel reinforcing rods embedded<br />

in the concrete), brick, glass, and ceramics, for land disposal.<br />

H. Mixed Debris: Comingled recyclable and non-recyclable construction and demolition materials.<br />

I. Mixed Debris Recycling Facility: A processing facility that accepts loads of comingled construction and<br />

demolition debris for the purpose of recovering re-usable and recyclable materials and disposing the nonrecyclable<br />

residual materials.<br />

J. Recycling: The process of sorting, cleansing, treating, and reconstituting materials for the purpose of using the<br />

altered form in the manufacture of a new product. Recycling does not include burning, incinerating, or thermally<br />

destroying solid waste.<br />

01742 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


K. Re-use: The use, in the same or similar form as it was produced, of a material which might otherwise be<br />

discarded.<br />

L. Solid Waste: Putrescible and nonputrescible solid, semisolid, and liquid wastes, including garbage, trash, refuse,<br />

paper, rubbish, ashes, industrial wastes, demolition and construction wastes, abandoned vehicles and parts thereof,<br />

discarded home and industrial appliances, dewatered, treated, or chemically fixed sewage sludge which is not<br />

hazardous waste, manure, vegetable or animal solid and semisolid wastes, and other discarded solid and semisolid<br />

wastes. "Solid waste" does not include hazardous waste, radioactive waste, or medical waste as defined or<br />

regulated by State law.<br />

M. Source-Separated: Materials, including comingled recyclables, that have been separated or kept separate from the<br />

solid waste stream at the point of generation, for the purpose of additional sorting or processing of those materials<br />

for reuse or recycling in order to return them to the economic mainstream in the form of raw materials for new,<br />

reused, or reconstituted products which meet the quality standards necessary to be used in marketplace.<br />

N. Waste Hauler: A company that possesses a valid permit from the local waste management authority to collect and<br />

transport solid wastes from individuals or businesses for the purpose of recycling or disposal.<br />

O. C&D Waste Management Advisor: A person or company that normally works in the field of Construction Waste,<br />

Demolition, and Recycling, such as Oakleaf (www.oakleafwaste.com), Waste Management (www.wm.com, 877-<br />

374-1304, WMWalmartcontractors@wm.com), or a local, state, or national licensed professional demolition or<br />

deconstruction contractor. The C&D Waste Management Advisor shall be independent from and with no direct<br />

affiliation or relationship with Contractor.<br />

P. Construction Waste Management Plan: The Construction Waste Management Plan identifies the construction<br />

waste diversion expectations including diversions percentages and tons of the targeted materials and the locations<br />

for the legal reuse, recycling, or disposal.<br />

Q. C&D Waste and Recycle Program Manager: The individual charged with managing the C&D Waste and Recycle<br />

Program for the Contractor. This person does not have to be an employee of the Contractor, but must operate<br />

under the guidance and direction of the Contractor.<br />

R. C&D Training Manual: A site specific training manual that explains the processes and procedures for handling the<br />

C&D Waste and Recycle needs. Contents include but are not limited to the following:<br />

1. Materials to be recycled.<br />

2. Materials to be re-used.<br />

3. Materials to be salvaged.<br />

4. Plan and procedure for recycling of lunch and break-time refuse.<br />

5. Facilities to be utilized for the purposes specified above.<br />

1.3 PERFORMANCE GOAL<br />

A. The waste management objective is to recycle, reuse, or salvage non-hazardous waste generated by the Work and<br />

to eliminate or minimize the amount of waste going to landfills.<br />

B. The Waste Management Plan does not relieve Contractor of responsibility for adequate and continuing control of<br />

pollutants and other environmental protection measures, including, but not limited to requirements specified in<br />

Section 02370.<br />

1.4 PRE-BID REQUIREMENTS<br />

A. Review Contract Documents and Site conditions.<br />

B. Contact at least one C&D Waste Management Advisor and complete the Construction Waste Management Plan<br />

utilizing the following criteria:<br />

1. Estimate total Project construction and demolition materials, in tons, to be generated.<br />

01742 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Designate types and quantities of materials that are anticipated to be feasible for on-site processing, and<br />

source-separation for recycling, re-use, or salvaging on Project.<br />

3. Research and locate construction and demolition waste and recycle facilities and mixed debris recycling<br />

facilities in the area of Project.<br />

4. Maximize, to the extent possible, the use of all available means to legally divert non-hazardous<br />

construction and demolition waste and recyclable materials away from landfills in the area of Project. Be<br />

thorough in the process of locating facilities to be used in the diversion of C&D materials away from<br />

landfills. Contact C&D professionals, locally, nationally and over the internet, to maximize diversion<br />

efforts. Utilize state and national recycling programs when applicable as well as local programs.<br />

5. Include anticipated on-site and off-site processing and source separation as well as mixed debris recycling<br />

for re-use, salvaging and recycling needs.<br />

C. Submit Waste Management Plan signed by C&D Waste Management Advisor no later than 24 hours after Bid<br />

Time to: cdwaste@wal-mart.com. Use form at the end of this Section.<br />

1.5 ADMINISTRATIVE REQUIREMENTS<br />

A. Waste Management Conference: Convene Waste Management Conference at Site prior to container placement.<br />

Require attendance of all parties directly affecting work of this Section, including, but not limited to the following:<br />

1. C&D Waste Management Advisor.<br />

2. C&D Waste and Recycle Program Manager.<br />

3. Wal-Mart Construction Manager.<br />

4. Contractor’s Project Manager and job site superintendents.<br />

5. All subcontractors and a representative from Hauler(s), if appropriate.<br />

6. Local Authority having Jurisdiction, if applicable.<br />

7. Owner’s Construction Testing Laboratory (CTL).<br />

B. Notify attendees at least two weeks prior to Conference.<br />

C. Conference agenda shall include:<br />

1. Distribution to all attendees of C&D Waste and Recycle training manual, prepared by the C&D Waste<br />

Advisor and the C&D Waste and Recycle Program Manager, site specific to this project.<br />

2. Program procedures, coordination processes and scheduling details for the Construction Waste<br />

Management Program.<br />

3. Clarification of communication procedures and agreements between affected parties including offsite<br />

receiving facilities.<br />

4. Thorough review of approved Waste Management Plan.<br />

5. Discussion of waste management responsibilities of each subcontractor and Contractor as well as the duties<br />

of C&D Program Manager.<br />

6. Review and verification of the container and bin requirements of each contractor and subcontractor, to<br />

avoid delays.<br />

7. Approved on-site location of containers and bins.<br />

8. Review of transportation methods and lead-time requirements for transporting to and from the recycling<br />

and disposal facilities.<br />

9. Review of lunch and break recycling plan for bottles, cans and waste.<br />

10. Review of training procedures for each subcontractor as he comes on Site for the first time.<br />

11. Review of procedures for reporting of C&D Waste and Recycle materials to the Walmart web-based<br />

system.<br />

D. Furnish a typed copy of the attendance log, with signatures and conference minutes, to each party attending, within<br />

5 working days of Conference.<br />

1.6 SUBMITTALS<br />

A. Submit, within five days of prime contract award, the name, phone number and e-mail address of C&D Waste and<br />

Recycle Program Manager to cdwaste@wal-mart.com.<br />

01742 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Progress Reports:<br />

1. Submit monthly reports to Wal-Mart on Wal-Mart’s designated web-based reporting system.<br />

2. Include quantities, in tons, of materials generated in the Work, as indicated on the web-based reporting<br />

system.<br />

3. Report non-hazardous waste material disposal.<br />

4. Report on-site and off-site reuse materials.<br />

5. Report in units for salvage items where no tonnage measurements are feasible.<br />

6. Indicate locations where materials are delivered for re-use, recycle, salvage, or transfer.<br />

7. Upload weight tickets, receipts, or invoices, if available, with the material entries. Documents shall be<br />

from facilities or disposal site operators that can legally accept the materials for the purpose of re-use,<br />

salvaging, or disposal.<br />

8. Where no documents are available, such as for materials used on-site, upload photos of materials being<br />

entered. Include documentation that describes how the materials were used.<br />

9. Reporting shall be up-to-date before progress payment requests are made.<br />

PART 2 - PRODUCTS<br />

Not Used.<br />

PART 3 - EXECUTION<br />

3.1 GENERAL REQUIREMENTS<br />

A. Take a pro-active, leadership role in the management of construction and demolition waste recycle efforts.<br />

Require subcontractors, vendors, and suppliers to participate in this effort.<br />

B. Develop Site specific procedures to incorporate the C&D Waste Management Plan and Performance of Diversion<br />

Goals.<br />

C. Practice efficient waste management when sizing, cutting, and installing products and other materials. Use all<br />

reasonable means to divert construction and demolition waste from landfills.<br />

D. Exercise diligence in the planning and execution of Waste Management Plan.<br />

E. Train workers, subcontractors, and suppliers on waste management procedures as appropriate for Work occurring<br />

at Site.<br />

F. Post in the Contractor’s field office, the site-specific C&D plan, including Site Map showing container locations,<br />

concrete washout, and lunch and break areas.<br />

G. Supply workers and subcontractors with a copy of Waste Management Plan and the Site-specific C&D Training<br />

Manual.<br />

H. Comply with the requirements of Section 01743 for hazardous construction and demolition waste management and<br />

disposal.<br />

3.2 MATERIALS TO BE RECYCLED<br />

A. Recycling may consist, but not necessarily include nor be limited to, non-hazardous demolition and construction<br />

waste and debris to be disposed of and not to be reused, or considered of value to the Contractor and retained in<br />

the Contractor’s possession.<br />

B. Maximize recycling and reuse of materials. Sale or donation of waste suitable for reuse shall be acceptable.<br />

Salvaged materials, other than those specified in other Sections to be salvaged and re-used, shall not be used in this<br />

Project.<br />

01742 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Revenues: Savings or revenues obtained from recycled, re-used, or salvaged materials shall accrue to Contractor<br />

unless otherwise noted in the Contract Documents.<br />

3.3 REGULATORY REQUIREMENTS<br />

A. Comply with federal, state, or local statutory environmental requirements for diversion of construction and<br />

demolition waste from landfills as applicable. Firms and facilities used for recycling, reuse, and disposal shall be<br />

appropriately permitted for the intended use to the extent required by federal, state, and local environmental<br />

Authorities Having Jurisdiction.<br />

B. Negotiate and sign agreements for required services in compliance with state and local environmental regulations<br />

and specified requirements.<br />

3.4 ONSITE SORTING AND STORAGE OF WASTE<br />

A. Sorting and storage of waste shall be the Contractor’s responsibility whether the waste was generated by the<br />

Contractor or by Owner.<br />

B. Provide temporary fencing for storing unsorted waste and securing waste and recycling containers as specified in<br />

Section 01500. Establish storage area at least 50 feet from the project property line or as allowed by Owner<br />

Construction Manager.<br />

1. Coordinate location with Wal-Mart Construction Manager prior to installing fencing.<br />

C. Enclose hazardous waste, non-hazardous waste, and recycling containers within temporary fencing which shall<br />

remain locked at all times. Provide controlled access to container storage area for disposal.<br />

D. Designate a fenced sorting area separate from and immediately adjacent to the waste container storage area with<br />

sufficient space to sort waste for storage and disposal.<br />

E. Prevent runoff from waste storage and sorting areas. Inspect areas used for storing materials for evidence of, or<br />

the potential for, pollutants entering the storm drainage system or discharging from the site.<br />

F. Sort waste into storage containers and clear the waste sorting area at least twice every 12 hours.<br />

G. Prevent unauthorized disposal of wastes generated off-site.<br />

H. Set open top containers back at least 4 feet from fencing.<br />

3.5 CONTAINERS<br />

A. Classify containers by markings or signage to accept materials sorted with respect to type of waste or type of<br />

material.<br />

B. Clearly identify containers to receive recyclable materials.<br />

3.6 SEPARATION AND RECYCLING<br />

A. Unless otherwise specified, separate hazardous waste, non-hazardous waste, and recyclables.<br />

B. Source separated materials may include, but are not limited to, the following:<br />

1. Acoustical Ceiling Tiles (ACT) (specified in Section 02224).<br />

2. Asphalt and concrete.<br />

3. Brick, masonry, tiles and rocks.<br />

4. Building materials (doors, windows, fixtures, etc.).<br />

5. Cardboard and packaging materials.<br />

6. Carpet, carpet padding and foam.<br />

7. Concrete slurry.<br />

01742 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


8. Construction and demolition debris.<br />

9. Film plastic and styrofoam.<br />

10. Gypsum wallboard.<br />

11. Metal (ferrous and non-ferrous).<br />

12. Mixed construction and demolition waste and miscellaneous construction debris.<br />

13. Plant and tree trimmings (land clearing debris).<br />

14. Trash and garbage.<br />

15. Vinyl Composition Tile (VCT) (specified in Section 02223).<br />

16. Wire and cable.<br />

17. Wood.<br />

18. Porcelain.<br />

19. Reuse or Salvage Materials.<br />

20. Soils.<br />

21. Other (describe in the Plan).<br />

C. Comingled Materials: Where acceptable to recycling facility, place waste products and recyclable materials into a<br />

single container and transport to recycling facility.<br />

D. Clean all materials that are contaminated prior to placing in source separated containers.<br />

E. Deliver materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to<br />

recycling process.<br />

F. Arrange for collection by or delivery to the appropriate recycling or reuse facility.<br />

3.7 NON-RECYCLABLE MATERIAL DISPOSAL AND WASTE HAULING<br />

A. Except for items or materials to be recycled as specified above, remove waste materials from Project site and<br />

legally dispose of it in a landfill or incinerator acceptable to Authorities Having Jurisdiction.<br />

B. Except as otherwise specified, do not allow waste materials that are to be disposed of to accumulate on-site.<br />

C. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.<br />

D. Do not burn waste materials on or off Site.<br />

END OF SECTION<br />

01742 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT PLAN<br />

Complete the information on this form for construction and demolition (C & D) materials that will be reused, recycled, or<br />

disposed from the project in accordance with Section 01742 of the Specifications. (Type into form – do not hand write)<br />

Project Name: __ Location: __<br />

Type of Project: New Construction Relocation Site Clearing Only<br />

On Site Relocation Expansion Other<br />

Remodel<br />

Demolition Only<br />

Was there difficulty finding Salvage or Re-Use vendors? Yes No If yes, explain manner of difficulty:<br />

If the estimated amount of reused or recycled materials is less than 50% of total estimated amount of material disposed, explain<br />

why:<br />

C & D ESTIMATED WASTE GENERATED (TONS)<br />

Complete and submit no later than 24 hours after Bid Time as specified in Section 01742.<br />

Estimated<br />

Vendor or Facility Used (Destination)<br />

Estimated Tons<br />

Tons of<br />

(Bus name, city, state, contact name, phone no.)<br />

Material Type<br />

of Disposed/<br />

Reused/<br />

Landfilled<br />

Recycled<br />

Acoustical Ceiling Tiles<br />

Asphalt & Concrete<br />

Bricks/Masonry/Tiles<br />

Building Materials (doors, windows,<br />

fixtures, etc.) <br />

Cardboard<br />

Carpet/Carpet Padding/Foam<br />

Concrete Slurry<br />

Construction / Demolition<br />

Film Plastic & Styrofoam Blocks<br />

Gypsum Wallboard<br />

Metal<br />

Mixed C&D Waste & Misc Const<br />

Debris<br />

Plant & Tree Trimmings<br />

PVC Plank Flooring<br />

Trash/Garbage<br />

VCT Floor Tile<br />

Wire and Cable<br />

Wood<br />

Other (Describe)<br />

Other (Describe)<br />

TOTAL<br />

Estimated percent of waste diverted<br />

from landfill<br />

01742 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


BLANK PAGE<br />

01742 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 01743 (01 7430) – HAZARDOUS / UNIVERSAL WASTE MANAGEMENT AND DISPOSAL<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Management and disposal of hazardous wastes as follows:<br />

1. Management of certain universal and e-scrap wastes by the Contractor and disposal thereof through the<br />

services of a pre-selected waste management vendor to recycle through vendor’s waste pick-up and recycle<br />

program.<br />

2. Management of and disposal by the Contractor of all other hazardous wastes.<br />

B. Related Requirements:<br />

1. Section 01500 - Temporary Facilities and Controls: Temporary chain link fencing for construction and<br />

demolition waste management containers.<br />

2. Section 01740 - Cleaning.<br />

3. Section 01742 - Construction/Demolition Waste Management and Disposal: Onsite sorting and storage of<br />

hazardous waste.<br />

4. Section 02023 - Selective Site Demolition.<br />

5. Section 02223 - Removal and Recycling of Vinyl Composition Tile (VCT).<br />

6. Section 02224 - Removal and Recycling of Acoustical Ceiling Tile (ACT).<br />

7. Section 09900 - Paints and Coatings.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. Resource Conservation Recovery Act (RCRA).<br />

C. Title 40 U.S. Code of Federal Regulations (40 CFR):<br />

1. 40 CFR 273 – Universal waste regulations.<br />

2. 40 CFR 261.3 – Definition of hazardous waste.<br />

1.3 DEFINITIONS<br />

A. Hazardous Waste: As defined by the U.S. Environmental Protection Agency (EPA) in 40 CFR 261.3, and as<br />

defined by specific state and local jurisdictions. Identify hazardous wastes that are produced through construction<br />

operations in accordance with federal, state and local laws. Materials shall be considered hazardous wastes as<br />

appropriate according to applicable regulations regardless of whether the material was supplied by Wal-Mart.<br />

1. Hazardous waste for the purposes of this Work shall include, but not limited to paint waste, adhesive waste,<br />

solvents, acids/corrosives, fuels and petroleum based products, aerosols, and including liquid residue<br />

remaining in containers thereof.<br />

B. Universal Waste: As defined by the U.S. Environmental Protection Agency (EPA) in 40 CFR 273 and as defined<br />

by specific state and local jurisdictions.<br />

PART 2 - PRODUCTS (Not Used)<br />

01743 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 GENERAL<br />

A. Regulatory Requirements:<br />

1. Comply with federal, state, and local standards and regulations regarding the classification, storage,<br />

transportation, and disposal of hazardous waste.<br />

2. Comply with Occupational Safety and Health Administration requirements for hazardous waste.<br />

B. The Contractor shall assume the responsibility as the generator of the hazardous and universal waste generated on<br />

the site.<br />

C. No construction chemicals, hazardous materials or hazardous waste shall remain at the Site upon project<br />

completion including those generated or utilized by subcontractors or supplied by Wal-Mart, but shall be removed,<br />

or appropriately and lawfully reused, recycled, or disposed.<br />

D. Obtain Environmental Protection Agency (EPA) or state Resource Conservation Recovery Act (RCRA)<br />

identification number as generator of hazardous waste. Walmart or Sams EPA or state RCRA identification<br />

numbers assigned specifically to Wal-Mart or Sam’s Club to manage or transport hazardous waste may not be<br />

used by the Contractor.<br />

3.2 UNIVERSAL AND E-SCRAP WASTE MANAGEMENT AND RECYCLING<br />

A. Manage universal and e-scrap waste, including collection, sorting, and preparation for pick up by pre-selected<br />

vendor for recycling.<br />

B. Dispose of universal and e-scrap wastes by recycling through Wal-Mart preselected Waste Management Vendor as<br />

follows: Waste Management, Roseville, MN (800) 664-1434.<br />

C. Assume costs associated with disposing of the waste through Waste Management vendor.<br />

D. Follow instructions for Universal Waste Recyclying for Walmart Construction Contractors at Waste Management<br />

website https://www.wmlamptracker/walmartconstruction including account setup, packaging guidelines, ordering<br />

packaging supplies, and scheduling waste pickups. Manage universal and e-scrap waste according to the process,<br />

tools, and resources available on the website.<br />

E. Management, recycling and disposal of non-hazardous or hazardous waste not specifically identified in this<br />

Section or other Sections is responsibility of Contractor.<br />

3.3 HAZARDOUS WASTE MANAGEMENT (EXCLUDING E-SCRAP AND UNIVERSAL WASTE) AND<br />

DISPOSAL<br />

A. Manage and dispose of hazardous wastes generated at the Site, regardless of who supplied the materials.<br />

B. Onsite Sorting and Storage:<br />

1. Establish enclosed and fenced storage area on site as specified in Section 01742.<br />

2. Provide signage as required by RCRA including but not limited to the following:<br />

a. Post “NO SMOKING” signs in areas containing hazardous waste.<br />

b. Mark each container of hazardous waste with the words “HAZARDOUS WASTE” and an<br />

accumulation start date (the date the waste was first placed in the container).<br />

3. Accumulate each type of hazardous waste in a separate hazardous waste container with a watertight<br />

closeable lid.<br />

4. All open tops must be enclosed behind a fence which will remain locked at all times with access controlled<br />

by the Contractor or its designee. Contractor or the designee shall be available at all times of day or night<br />

on the jobsite to provide access and control for disposal or shall designate an area immediately outside of<br />

the locked area with sufficient space to stage items pending disposal.<br />

01743 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. If a staging area is utilized it shall be located in an area enclosed by fencing but shall be accessible at all<br />

times, or if locked those requiring access shall be provided keys. In the event Contractor designates an area<br />

for staging waste, the staging area must be cleared and all material properly disposed of twice per 12 hour<br />

shift to prevent accumulation of items. Any material in the staging area shall be protected from the<br />

elements to prevent any potential runoff while waiting disposal.<br />

6. Contractor shall address in the Hazardous Waste Management and Disposal Plan prevention of<br />

unauthorized disposal by persons “throwing” items over fencing. Prevention measures may include but are<br />

not limited to open tops set back from the fencing, barbed-wire on top of fencing, or lids on the open tops.<br />

C. Training:<br />

1. Employees and subcontractors shall be familiar with proper hazardous waste management procedures<br />

relevant to their individual responsibilities on the site.<br />

2. Employees and subcontractors shall be familiar with emergency procedures regarding spills, reactions, and<br />

fires involving hazardous waste.<br />

D. Documentation:<br />

1. Retain copies of hazardous waste disposal manifests at Contractor’s office in hard copy or electronic form.<br />

Hazardous waste disposal documentation shall be available upon request. Retain hazardous waste disposal<br />

manifests for not less than 3 years.<br />

2. Document training conducted with each employee and subcontractor and retain documentation in<br />

Contractor’s Field Office.<br />

E. Disposal and Transportation:<br />

1. Hazardous waste accumulated from the Site shall be transported to a disposal or recycling facility by a<br />

certified hazardous waste hauler.<br />

3.4 HAZARDOUS WASTE MANAGEMENT AND DISPOSAL PLAN<br />

A. Develop a written site-specific Hazardous Waste Management and Disposal Plan including, as a minimum, the<br />

proposed plans, processes, and procedures of management and disposal of hazardous waste including, but not<br />

limited to, the requirements specified in this Section.<br />

1. The Hazardous Waste Management and Disposal Plan shall identify the certified hazardous waste hauler<br />

for the project.<br />

2. The Contractor’s employees, sub-contractors, and their employees shall effectively execute the<br />

Contractor’s Hazardous Waste Management and Disposal Plan.<br />

END OF SECTION<br />

01743 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 01770 (01 7700) – CONTRACT CLOSEOUT<br />

PART 1 -GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes<br />

1. Closeout Procedures.<br />

2. Final Closeout Submittals.<br />

3. Closeout Document Submission.<br />

4. Record Letters of Conformance.<br />

5. Letters of Certification.<br />

6. Project Record Documents.<br />

7. Operations and Maintenance Data.<br />

8. Warranties and Bonds.<br />

B. Related Requirements:<br />

1. Section 01740 - Cleaning: Requirements for final cleaning.<br />

1.2 CLOSEOUT PROCEDURES<br />

A. Comply with closeout submittal requirements defined within individual Sections. Submittal procedures described<br />

herein shall apply unless otherwise described in individual Sections.<br />

B. When Contractor considers Work to be Substantially Complete, submit written certification to Wal-Mart<br />

Construction Manager as follows.<br />

1. Contract Documents have been reviewed.<br />

2. Work has been inspected.<br />

3. Work is complete in accordance with Contract Documents.<br />

4. Work is ready for inspection.<br />

1.3 FINAL CLOSEOUT SUBMITTALS<br />

A. Before final application for payment will be approved, final closeout submittals shall be received and approved by<br />

Owner. If Contractor fails to provide a fully completed Electronic Closeout Document Submission within 90 days<br />

after Substantial Completion of the Work, then Contractor agrees to pay Owner the sum of $250.00 per day, as<br />

liquidated damages and not as a penalty, until the fully completed Electronic Closeout Document Submission is<br />

received and approved by Owner Contract Administration.<br />

1.4 ELECTRONIC CLOSEOUT DOCUMENT SUBMISSION<br />

A. Submit Closeout Documents electronically through Wal-Mart’s approved online system. Documents included in<br />

Electronic Closeout Document Submission shall consist only of the items in the following numbered list. Note<br />

that all closeout documents are not necessarily included in the Electronic Closeout Document Submission. If any<br />

item is not applicable, include a “Not Applicable” sheet within the uploaded section of the Electronic Closeout<br />

Document Submission. The Electronic Closeout Document Submission shall not be compiled based only on the<br />

brief description of each item in the following list. It is compulsory that the individual sections and references be<br />

examined to comprehend the full description of the specific item to be included. Include the following:<br />

1. Contractor’s Statement of Warranty. (Reference Article 9 of General Conditions.) (Reference form<br />

included at end of this Section.)<br />

2. Copy of Certificate of Occupancy.<br />

3. List of Subcontractors: Final list of Subcontractors used complete with telephone numbers, addresses, and<br />

after hours telephone numbers. (Reference Article 12 of General Conditions.)<br />

01770 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Signed and notarized lien waivers from Contractor and all Subcontractors on the Wal-Mart form (Affidavit<br />

of Total Release and Certification of all Bills Paid). (Reference form included at end of this Section.) The<br />

form shall have no modifications or changes made thereon.<br />

5. Copies of Performance and Payment Bond. (Reference Article 20 of General Conditions.)<br />

6. Consent of Surety to Final Payment from Bonding Company. (Reference Article 7 of General Conditions.)<br />

7. Substantial Completion Punchlist: Building, Civil, and HVAC/refrigeration punchlists showing items<br />

completed and approved by Owner. (Reference Article 4 of General Conditions.)<br />

8. Registration of Storage Tanks with State. (Sections 11140 and 13220 if specified.)<br />

9. Maintenance Data Sheet. (Reference form at the end of this Section.)<br />

10. Verification of transmittal to Store Manager of all Project Record Documents specified hereinafter and<br />

Operations and Maintenance Manuals. This shall be in the form of a Letter of Transmittal with a statement<br />

signed by the Store Manager verifying that the O & M manuals have been placed in the Electrical<br />

Distribution Center (EDC) by the Contractor and the placement witnessed by the Store Manager.<br />

11. Warranties: Include warranties for the following as applicable when the specified Section is included in the<br />

project.<br />

a. Termite Control (Section 02361).<br />

b. Sewage Lift Station (Section 02532).<br />

c. Ornamental Fence (Section 02823).<br />

d. Planting: Plant Guarantee (Section 02900).<br />

e. Concrete: Densifier Warranty (Section 03362).<br />

f. Metal Roof Panels: Standing Seam Metal Roof (Section 07412).<br />

g. Exterior Wall Panel System (Section 07425).<br />

h. Composite Wall Panels (Section 07430).<br />

i. Membrane Roofing. Submit Roofing Warranty included at the end of Roofing Section (Sections<br />

07500, 07511, or 07550). Manufacturer’s standard warranty will not be considered as a substitute<br />

for the warranty included therein.<br />

j. Traffic Doors (Section 08383).<br />

k. Automatic Swing Entrance Doors (Section 08461).<br />

l. Automatic Sliding Entrance Doors (Section 08462).<br />

m. Translucent Panel Canopy System (Section 08951).<br />

n. Paint: Elastomeric Coating System Warranty. (Section 09900 or 09985).<br />

o. Fuel Station Equipment System (Section 11145).<br />

p. Heating, Ventilating, and Air Conditioning Equipment: HVAC Components (Section 15700).<br />

q. Heating, Ventilating, and Air Conditioning Equipment: Water Source Heat Pumps (Section 15700).<br />

r. Heating, Ventilating, and Air Conditioning Equipment: Fluid Coolers (Section 15700).<br />

s. Heating, Ventilating, and Air Conditioning Equipment: Pre-Fabricated Pump Package (Section<br />

15700).<br />

t. Site Lighting (Section 16525).<br />

12. Letters of Certification: Include separate letter for each certification required within the sections listed<br />

below. Include letters for the following as applicable when the specified Section is included in the project.<br />

a. Neutralization Enclosure Quality Control (Section 01459).<br />

b. Rough Carpentry. (Section 06100).<br />

c. Exterior Insulation and Finish System (Section 07243)<br />

d. Membrane Roofing (Section 07500).<br />

1) Letter of Certification of installer’s qualifications and conformance with specified tests and<br />

criteria.<br />

e. Sheet Metal Flashing (Section 07620).<br />

f. Glazing (Section 08800).<br />

g. Resinous Flooring. (Section 09675).<br />

h. Vehicle Service Equipment Systems (Section 11140).<br />

1) Statement of Certified Installer.<br />

i. Fuel Station Equipment System (Section 11145).<br />

j. Building Services Piping: (Section 15100).<br />

1) Certification of testing/inspection contractor.<br />

01770 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


13. Record Letters of Conformance: Include separate letter for each item listed below. Include letters for the<br />

following as applicable when the specified specification section is included in the project.<br />

a. Architect of Record (Section 01454).<br />

b. Engineer of Record (Section 01454).<br />

c. Civil Engineering Consultant (Section 01456).<br />

d. Construction Testing Laboratory (Section 01458).<br />

e. Membrane Roofing (Section 07500).<br />

f. Fire Suppression. (Including Fire Pump & Water Storage Tank if Specified) (Section 13900).<br />

Kitchen Exhaust Hood Fire Suppression System (ANSUL System) (Section 15700). HVAC<br />

Mechanical Systems (Section 15700).<br />

g. Energy Management System (Section 13810).<br />

h. Submetering System (Section 13425).<br />

i. Refrigeration Mechanical Systems (Section 15600).<br />

14. Inspection Reports: Include separate report for each required item listed below. Include reports for the<br />

following as applicable when the specified Section is included in the project.<br />

a. Membrane Roofing (Section 07500). Include the following:<br />

1) Roof Inspection Checklist.<br />

2) Periodic site inspection reports.<br />

3) Site Inspection Certificate.<br />

b. Paints and Coatings (Section 09900). Elastomeric Coating.<br />

c. Vehicle Service Equipment Systems (Section 11140).<br />

1) Testing and Inspection Reports.<br />

d. Fuel Station Equipment System (Section 11145).<br />

e. Loading Dock Equipment. (Section 11160).<br />

1) Certificate of Inspection.<br />

f. Building Services Piping (Section 15100).<br />

1) Video Inspection Report.<br />

2) Dye Testing Report (If specified).<br />

g. Siphonic Primary Roof Drain System (Section 15160).<br />

1) Siphonic Drainage System Post-Installation Checklist.<br />

h. Refrigeration Equipment (Section 15600).<br />

1) Start-up Report.<br />

i. Energy Management System (EMS) (Section 13810).<br />

1) Start-up Report and Punch list.<br />

15. Copy of Signed Notice of Termination of NPDES Construction General Permit with proof of submittal to<br />

appropriate agency. This is only applicable for those permits issued to the General Contractor. (Section<br />

02370 erosion)<br />

1.5 RECORD LETTERS OF CONFORMANCE<br />

A. Submit Record Letters of Conformance as a Closeout Submittal. By submitting Record Letter of Conformance,<br />

the Contractor declares that the product identified by manufacturer's name and model number is the product<br />

specified and is suitable for the intended use as defined within the Contract Documents and has been provided and<br />

placed in operational condition in accordance with the manufacturer's published instructions and the Contract<br />

Documents.<br />

1. Submit completed Record Letter of Conformance for each product selected as indicated within each<br />

Section.<br />

2. Complete required information on form and sign in ink by person authorized to sign on behalf of the<br />

Contractor.<br />

3. No modifications shall be made to the form.<br />

4. Record Letters of Conformance, when required, are located at the end of the respective Section.<br />

1.6 LETTERS OF CERTIFICATION<br />

A. Certify manufacturer's or installer's qualifications, conformance with tests or specified criteria, or other factors as<br />

required in individual specification sections.<br />

01770 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Submit supporting reference data, affidavits, and certifications as required.<br />

1.7 PROJECT RECORD DOCUMENTS<br />

A. Maintain on site, one set of the following record documents. Record actual revisions to the Work.<br />

1. Contract Drawings (Building and Civil).<br />

2. Specifications.<br />

3. Addenda.<br />

4. Change Orders and other Modifications to the Contract.<br />

5. Reviewed shop drawings, product data, and samples.<br />

B. Maintain Record Documents separate from documents used for construction.<br />

C. As-Built Record Documents and Shop Drawings: Record as-builts shall be maintained and submitted for the<br />

primary purpose of recording the locations for concealed interior and exterior underground utilities as specified in<br />

the individual specifications. Legibly record actual measured horizontal and vertical locations of interior and<br />

exterior underground utilities and appurtenances, referenced to permanent surface improvements.<br />

D. Record required as-built information concurrent with construction progress. Do not permanently conceal work<br />

until required information has been recorded.<br />

E. At Project completion, the Contractor shall place the Record Documents (including Building and Civil Record<br />

Drawings, Specifications, Addenda, and Change Orders) enclosed in a plastic pipe tube (fixed cap at one end and a<br />

threaded-cap on the other end) for storage in the Electrical Room unless otherwise specified to be located in<br />

another location in the individual sections. Placement shall be in the presence of and witnessed by the Store<br />

Manager.<br />

1.8 OPERATION AND MAINTENANCE DATA<br />

A. Operation and Maintenance data shall include a suitably bound set of descriptive literature, maintenance and<br />

operation data, and parts lists for each item of equipment provided under this Contract that will require<br />

maintenance or special operating procedures, including drawings, instructions, or manuals supplied with<br />

equipment furnished by others and installed under this Contract. Submittal of O&M data shall be in the form of<br />

the bound set of O&M data and placement by the Contractor in the Electrical Distribution Center (EDC) room<br />

within the building unless otherwise specified to be located in another location in the individual sections. Do not<br />

include O&M data in the Electronic Closeout Document Submission or submit to Wal-Mart Contract<br />

Administration. Placement of documents shall be witnessed by the Store Manager and shall be at least 14 days<br />

prior to final inspection.<br />

1.9 WARRANTIES AND BONDS<br />

A. Prior to Final Application for Payment, submit required warranties and bonds through the Electronic process.<br />

1. Assemble documents from Subcontractors, suppliers, and manufacturers.<br />

2. For equipment put into use with Owner's acceptance during construction, submit within ten days after first<br />

operation, listing date of acceptance as start of warranty period.<br />

3. For items of Work delayed materially beyond Date of Substantial Completion, provide updated submittal<br />

within ten days after acceptance, listing date of acceptance as start of warranty period.<br />

END OF SECTION<br />

01770 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


WAL-MART STORES, INC.<br />

MAINTENANCE DATA SHEET<br />

Complete all Sections Prior To Final Payment<br />

Location:<br />

Size:<br />

Store/Club No.:<br />

Possession Date:<br />

TYPE OF BUILDING CONSTRUCTION<br />

Walls:<br />

Roof (circle one): SBS BUR TPO Metal Other (explain)<br />

Roofing Mfg.<br />

Warranty Information. (years)<br />

Roof (circle one): SBS BUR TPO Metal Other (explain)<br />

Roofing Mfg.<br />

Warranty Information. (years)<br />

STORE/CLUB TYPE (Check Those That Apply)<br />

Free Standing New Store Take-over Store<br />

Strip Center Relocation Stockroom Add'n.<br />

Mall Remodel Expansion Back Front<br />

L. Side R. Side<br />

Developer:<br />

Gen. Contractor:<br />

Subcontractors:<br />

Electrical:<br />

Plumbing:<br />

Fire Protection:<br />

Roofing:<br />

Ht/Vent/Cool:<br />

EMS:<br />

Refrigeration:<br />

Paving:<br />

Painting:<br />

Storefront:<br />

Earthwork:<br />

Site Utility:<br />

Company Name Location Business Phone Emerg. Phone<br />

01770 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Striping:<br />

Fencing:<br />

Concrete Ext.:<br />

Concrete Int.:<br />

Masonry:<br />

Struct. Steel:<br />

Overhead Doors:<br />

Auto. Doors:<br />

Flooring:<br />

Landscaping:<br />

Irrigation:<br />

HEATING AND AIR CONDITIONING EQUIPMENT<br />

GAS FIRED [ ] ELECTRIC HEAT [ ]<br />

Quantity Manufacturer Model No. Heat/Cool (BTU's) Cool Only (BTU's)<br />

MISCELLANEOUS INFORMATION<br />

Quantity Manufacturer Catalog/ Model No. Volts/Watts<br />

Parking Lot Lighting:<br />

Lighting Poles:<br />

Light Fixtures:<br />

Ballasts:<br />

Lamps:<br />

Ceiling Light Fixtures:<br />

High Bay:<br />

Ballasts:<br />

Lamps:<br />

Pendant Mount:<br />

Ballasts:<br />

Lamps:<br />

01770 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Fluorescent Mount:<br />

Ballasts:<br />

Lamps:<br />

PRODUCTS<br />

Door Closers:<br />

Panic Hardware:<br />

Auto. Doors:<br />

Ceiling Panels:<br />

Floor Tile:<br />

Rubber:<br />

VCT:<br />

PVC:<br />

Ceramic:<br />

R.R. Partition:<br />

EMS:<br />

Refrigeration:<br />

Domestic Water<br />

Booster Pump:<br />

Fire Pump:<br />

Jockey Pump:<br />

Exit Lights:<br />

Emergency Lights:<br />

Manufacturer Model/Serial # Color/Style (If Applicable)<br />

Note: Include all information requested, including Owner Provided Parts.<br />

DNA: Does Not Apply<br />

END OF MAINTENANCE DATA SHEET<br />

01770 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


[CONTRACTOR’S LETTERHEAD]<br />

CONTRACTOR’S STATEMENT OF WARRANTY<br />

DATE:<br />

PROJECT:<br />

LOCATION:<br />

OWNER: Wal-Mart Stores, Inc.<br />

702 SW 8 th Street<br />

Bentonville, AR 72712<br />

CONTRACT: Construction Agreement Between Owner and Contractor, dated______________20____.<br />

Contractor hereby: (1) warrants that the Work for Project complies with Article 9 of the General Conditions; (2)<br />

acknowledges that its warranty obligations under such Article 9 extends one year beyond the actual date of Substantial<br />

Completion of the Project; and (3) affirms, and acknowledges the enforceability of, all other warranties made by Contractor<br />

in the Contract.<br />

Terms used but not defined herein shall have the meanings given to them in the above referenced Contract.<br />

The undersigned Contractor hereby makes the certifications set forth herein to Wal-Mart as of the _______day of<br />

_____________________, 20______.<br />

Witness:<br />

_______________________________________<br />

Contractor: _______________________<br />

By: _____________________________<br />

Print Name: _____________________________Name: __________________________<br />

STATE OF______________________________<br />

COUNTY OF ___________________________<br />

Title: ___________________________<br />

On this the ______________ day of _______________________________________, 20_______<br />

before me, a Notary Public, within and for the State and County aforesaid, personally appeared, to me well know (or proved<br />

to me on the basis of satisfactory evidence), who stated upon oath that (s)he had executed the foregoing instrument for the<br />

consideration set forth therein.<br />

____________________________________________<br />

Notary Public<br />

My commission expires: ________________________<br />

01770 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


WALMART SITEWORK SPECIFICATIONS TABLE OF CONTENTS<br />

Division<br />

Section Title<br />

Deleted: Table of Contents Generated<br />

by Masterworks: 05/27/2011<br />

DIVISION 2 - SITE CONSTRUCTION<br />

02220 Site Demolition<br />

02230 Site Clearing<br />

02300 Earthwork<br />

02318 Rock Excavation (Not Used)<br />

02340 Soil Stabilization<br />

02370 Erosion and Sedimentation Control (Including SWPPP) (Not Used)<br />

02375 Stone Protection (Rip-rap) (Not Used)<br />

02510 Water Distribution<br />

02532 Sewage Lift Station (Not Used)<br />

02535 Sanitary Sewage Systems<br />

02536 Sewer Manholes, Frames, And Covers<br />

02555 Natural And Propane Gas Distribution<br />

02630 Storm Drainage (Not Used)<br />

02715 Base Course<br />

02740 Asphaltic Concrete Paving<br />

02751 Concrete Paving<br />

02765 Pavement Markings<br />

02770 Curbs And Sidewalks<br />

02787 Seal Coat<br />

02812 Site Irrigation System<br />

02822 Chain Link Fences And Gates (Site)<br />

02830 Segmental Retaining Wall Systems (Not Used)<br />

02890 Traffic Signs And Signals<br />

02900 Planting<br />

DIVISION 16 - ELECTRICAL<br />

16525 Site Lighting<br />

END OF TABLE OF CONTENTS<br />

Deleted: (400 W)<br />

Deleted: 16525 ... [1]


SEALS PAGE<br />

PROJECT:<br />

Name:<br />

Location:<br />

Project Number: 20100751<br />

Store Number: 5641-01<br />

Wal-Mart<br />

La Habra, CA<br />

CIVIL ENGINEERING CONSULTANT OF RECORD<br />

GreenbergFarrow<br />

19000 MacArthur Blvd, Suite 250<br />

Irvine, CA 92612<br />

t: 949.296.0450<br />

f: 949.296.0479<br />

Deleted: Civil Engineer’s Name<br />

Deleted: One West Third Street<br />

Deleted: <br />

Suite 100<br />

Formatted: Indent: Left: 18 pt,<br />

First line: 18 pt<br />

Deleted: Tulsa, OK 74103-3501<br />

Farman Shirmohammadi, P.E._<br />

Civil Engineering Consultant of Record<br />

_________<br />

Date<br />

Deleted: ______________<br />

Formatted: Underline<br />

Deleted: _____________________<br />

Formatted: Tabs: 396 pt, Left +<br />

468 pt, Right + Not at 463.5 pt<br />

Formatted: Font: 11 pt<br />

Formatted: Font: 11 pt<br />

Formatted: Font: 11 pt<br />

Formatted: Font: 11 pt


Page 1: [1] Deleted Mike Holmes 10/15/2011 12:41:00 PM<br />

16525 Site Lighting (1000 W)


UniSpec II 052711<br />

SECTION 02023 – SELECTIVE SITE DEMOLITION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Procedures for demolition and removal of existing building elements.<br />

2. Protection of existing construction.<br />

3. Salvaged material and items.<br />

4. Schedule of building demolition.<br />

5. Disposal of demolished materials (non-hazardous and hazardous).<br />

B. Related Requirements:<br />

1. Section 01100 - Summary: Restrictions for Work within and adjacent to existing building areas.<br />

2. Section 01500 - Temporary Facilities and Controls: Temporary protection and barriers.<br />

3. Section 01700 - Execution Requirements.<br />

4. Section 01731 - Cutting and Patching: Requirements and limitations for cutting and patching Work.<br />

5. Section 01742 - Construction/Demolition Waste Management And Disposal: Removal and disposal of<br />

non-hazardous demolition waste and debris and management of salvaged items.<br />

6. Section 01743 - Hazardous/Universal Waste Management and Disposal: Disposal and removal of<br />

hazardous construction and demolition waste.<br />

7. Section 02251 - Shoring: Requirements for shoring and bracing.<br />

1.2 SYSTEM DESCRIPTION<br />

A. Selective Demolition Requirements:<br />

1. Perform demolition in construction sequence phases according to Construction Sequence Drawings.<br />

2. Work necessary and required to facilitate the new construction indicated.<br />

3. Demolish so that construction, new and existing, can be performed and completed in accordance with<br />

construction documents.<br />

4. Visit the project site and become familiar with the existing conditions and project requirements.<br />

5. Clarify the scope of the Work under this Section including salvage material. The Owner will be<br />

responsible for removing materials and equipment which the Owner wishes to salvage prior to the<br />

beginning of this Work.<br />

6. Retain existing fire protection sprinkler system in place and active.<br />

7. Contractor is responsible for damage to existing structure and replacement or repair of damage.<br />

8. Repair, replace, or rebuild existing construction as required or as directed which has been removed, altered,<br />

or disrupted to allow for new construction. Correct existing construction to match adjacent construction,<br />

new or existing as specified in Section 01731.<br />

B. Regulatory Requirements:<br />

1. Conform to applicable code for demolition of structures, safety of adjacent structures, dust control, runoff<br />

control, and disposal.<br />

2. Obtain required permits from authorities having jurisdiction and submit to Wal-Mart.<br />

3. Notify affected utility companies before starting work and comply with their requirements. Submit<br />

Certificates for severance of utility services and submit confirmation documentation of all utility company<br />

contacts to Wal-Mart.<br />

4. Do not close or obstruct roadways, sidewalks, or hydrants without permits from authorities having<br />

jurisdiction and Wal-Mart Construction Manager.<br />

5. Conform to applicable regulatory procedures when discovering hazardous or contaminated materials.<br />

6. Test soils around buried tanks for contamination (where buried tanks occur).<br />

02023 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.3 PROJECT CONDITIONS<br />

A. Conditions of Structure:<br />

1. Owner assumes no responsibility for actual condition of items or structures to be demolished.<br />

2. Conditions existing at time of inspection for bidding purposes will be maintained by Owner insofar as<br />

practical.<br />

3. Variations within structure may occur by Owner's removal and salvage operations prior to start of selective<br />

demolition work.<br />

B. Traffic: Conduct selective demolition and debris removal in manner to ensure minimum interference with roads,<br />

streets, walks, and other adjacent occupied or used facilities. Provide traffic controls as specified in Section<br />

01500.<br />

1.4 QUALITY ASSURANCE<br />

A. Qualifications: Engage only personnel who can demonstrate not less than five (5) years successful experience in<br />

Work of similar character.<br />

B. Performance Criteria:<br />

1. Requirements of Structural Work: Do not cut structural work in a manner resulting in a reduction of loadcarrying<br />

capacity of load/deflection ratio.<br />

2. Operational and Safety Limitations: Do not cut operational elements and safety-related components in a<br />

manner resulting in a reduction of capacities to perform in a manner intended or resulting in a decreased<br />

operational life, increased maintenance, or decreased safety.<br />

3. Visual Requirements: Do not cut work which is exposed on the exterior or exposed in occupied spaces of<br />

the building in a manner resulting in a reduction of visual qualities or resulting in substantial evidence of<br />

the demolition work judged by the Architect to be cut and patched in a visually unsatisfactory manner.<br />

4. Loading: Do not superimpose loads at any point upon existing structure beyond design capacity including<br />

loads attributable to materials, construction equipment, demolition operations, and shoring and bracing.<br />

5. Vibration: Do not use means, methods, techniques, or procedures which would induce vibration into any<br />

element of the structure.<br />

6. Fire: Do not use means, methods, techniques, or procedures which would produce any fire hazard.<br />

7. Water: Do not use means, methods, techniques, or procedures which would produce water run-off, and<br />

water pollution.<br />

8. Air Pollution: Do not use means, methods, techniques or procedures which would produce uncontrolled<br />

dust, fumes, or other damaging air pollution.<br />

1.5 UTILITY SERVICES<br />

A. Maintain existing utilities. Keep in service and protect against damage during demolition operations.<br />

B. Do not interrupt existing utilities serving occupied or used facilities except when authorized in writing by<br />

authorities having jurisdiction and approval by Wal-Mart Construction Manager.<br />

C. Provide temporary services during interruptions to existing utilities as acceptable to governing authorities.<br />

D. Locate, identify, stub off, and disconnect utility services not to remain.<br />

E. Provide by-pass connections as necessary to maintain continuity of service to occupied areas of building.<br />

F. Provide advance notice to Wal-Mart if shut-down of service is necessary during change-over.<br />

1.6 PROJECT SITE<br />

A. Indicated "Existing Construction" was obtained from existing drawings. Verify existing conditions and notify the<br />

Wal-Mart Construction Manager of discrepancies before proceeding with the Work.<br />

02023 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Perform removal, cutting, drilling, etc., of existing work with extreme care, and use small tools in order not to<br />

jeopardize the structural integrity of the building.<br />

C. Occupancy: Contractor will have limited use of the facility during construction as specified in Section 01700.<br />

D. Condition of Structure: The Owner assumes no responsibility for the actual condition of portions of the structure<br />

to be demolished.<br />

E. Protection: Ensure that the safe passage of persons around the area of demolition is provided. Conduct operations<br />

to prevent damage to adjacent buildings, structures, and other facilities, and injury to persons.<br />

1.7 SEQUENCING AND SCHEDULING<br />

A. Comply with Wal-Mart approved schedule for sequence of operations for selective demolition work.<br />

B. Include coordination for shut-off, capping, and continuation of utility services as required, together with details for<br />

dust and noise control.<br />

C. Provide detailed sequence of demolition and removal work to ensure uninterrupted progress of Owner's on-site<br />

operations.<br />

D. Conduct selective demolition work in manner to minimize disruption of Owner's normal operations.<br />

E. Provide Wal-Mart advance notice of demolition activities impacting Wal-Mart's normal operations as specified in<br />

Section 01700.<br />

1.8 SHORING AND BRACING<br />

A. Provide temporary shoring, bracing and supports for building structure as required for support of structure during<br />

demolition of existing structural elements and to prevent movement, settlement of existing building and adjacent<br />

buildings and facilities to remain as specified in Section 02251.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Designated materials and equipment for re-installation: Carefully remove, store, and protect.<br />

B. Contractor's Salvage:<br />

1. Contractor shall verify with and obtain approval from Wal-Mart Construction Manager for all Contractor<br />

salvage items prior to their removal from site.<br />

2. Transport salvaged items from site as items are removed.<br />

3. Storage or sale of removed items on site not permitted.<br />

C. Replace materials scheduled for reuse which are damaged to the extent that they cannot be reused. Replace with<br />

equal quality material at no additional cost to the Owner as specified in Section 01700.<br />

D. Coordinate with the Owner on disposition of salvage items not scheduled for reuse, demolished materials, and<br />

equipment. Deliver salvaged materials, not reused, as directed, by or to the Owner.<br />

E. Comply with the requirements of Section 01742 for management of salvaged items.<br />

02023 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas of Work under this Section. Do not proceed with Work until unsatisfactory<br />

conditions have been corrected.<br />

B. Starting Work constitutes acceptance of existing conditions.<br />

3.2 PREPARATION<br />

A. Ensure safe passage of persons around area of demolition.<br />

B. Erect temporary covered passageways as specified in Section 01500.<br />

C. Protect existing finish work to remain in place.<br />

D. Protect floors with suitable coverage.<br />

E. Construct temporary insulated solid dustproof partitions where noise or extensive dirt or dust operations are<br />

performed. Equip partitions with dustproof doors and security locks if required as specified in Section 01500.<br />

F. Provide temporary weather protection between demolition and removal of existing construction on exterior<br />

surfaces and installation of new construction to ensure no water leakage or damage occurs to structure or interior<br />

areas of existing building as specified in Section 01500.<br />

G. Cease operations and notify Wal-Mart Construction Manager immediately if safety of structure appears to be<br />

endangered.<br />

H. Take precautions to support structure until determination is made for continuing operations.<br />

I. Cover and protect furniture, equipment, and fixtures to remain from soiling or damage when demolition work is<br />

performed in rooms or areas from which such items have not been removed.<br />

3.3 DEMOLITION<br />

A. The Owner will remove or, under separate contract, have materials and equipment which the Owner requires<br />

removed, prior to commencement of Work under this Section. Coordinate scheduling of removal of Owner<br />

materials and equipment with Wal-Mart Construction Manager and Store Manager.<br />

B. Demolition:<br />

1. Perform demolition work in systematic manner.<br />

2. Demolish concrete and masonry in small sections.<br />

3. Cut concrete and masonry at junctures with construction to remain, using masonry saws or hand tools, and<br />

make cuts straight and square with building.<br />

4. Do not use powder-driven impact tools.<br />

5. Locate demolition equipment throughout structure and promptly remove debris to avoid imposing<br />

excessive loads on supporting walls, floor, or framing.<br />

6. For interior slabs on grade, use removal methods that will not crack or structurally disturb adjacent slabs or<br />

partitions.<br />

7. Perform cutting of existing concrete and masonry construction with saws and core drills. Do not use jackhammers<br />

or explosives.<br />

8. Patch with seams which are durable and as invisible as possible. Comply with specified tolerances for the<br />

work.<br />

9. Where selective demolition terminates at a "surface" or construction "to remain," completely remove all<br />

traces of material selectively demolished, including mortar beds. Provide smooth, even substrate transition<br />

as specified in Section 01731.<br />

02023 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


10. Demolition shall be carried out in a safe manner and in strict accordance with OSHA regulations.<br />

11. The Contractor shall field verify the extent of demolition. The Work includes, but is not limited to, the<br />

demolition and removal of walls, doors, fixtures, plumbing, mechanical and electrical items including<br />

conduits and ductwork as shown on Drawing or as required for the installation of the new Work for a<br />

complete job.<br />

12. When utilities are removed, cap and seal a minimum of 8" below finish floor or a minimum of 6" above<br />

finish ceiling.<br />

13. When removing existing structural items, provide adequate shoring, bracing and support systems to keep<br />

the existing structure intact and in a safe condition. Refer to Section 02251.<br />

C. Environmental Controls:<br />

1. Use water sprinkling, temporary enclosures, and other suitable methods to limit dust and dirt rising and<br />

scattering in air to lowest practical level.<br />

2. Comply with governing regulations pertaining to environmental protection.<br />

3. Do not use water when it may create hazardous or objectionable conditions, such as ice, flooding, or<br />

pollution.<br />

D. Below Grade Demolition:<br />

1. Demolish and remove below grade wood or metal construction.<br />

2. Break up below grade concrete slabs.<br />

E. Filling Below-Grade Voids:<br />

1. Fill below grade areas and voids resulting from demolition work.<br />

2. Use fill consisting of earth, gravel, or sand, free of trash and debris, stones over 6 inches diameter, roots, or<br />

other organic matter.<br />

F. If unanticipated mechanical, electrical, or structural elements conflicting with intended function or design are<br />

encountered, submit written report of nature and extent of conflict to Architect and Wal-Mart Construction<br />

Manager. Rearrange demolition schedule to continue job progress without delay.<br />

3.4 DISPOSAL OF DEMOLISHED MATERIALS<br />

A. Dispose of non-hazardous demolished materials as specified in Section 01742.<br />

B. Deposit waste materials, rubbish, and debris in waste containers.<br />

C. Do not allow waste materials, rubbish, and debris to accumulate and become an unsightly or hazardous condition.<br />

D. If hazardous materials are encountered during demolition operations, comply with applicable regulations, laws,<br />

and ordinances concerning removal, handling, and protection against exposure or environmental pollution. Notify<br />

Wal-Mart Construction Manager, in writing, of hazardous materials encountered.<br />

E. Comply with the requirements of Section 01743 for hazardous construction and demolition waste management and<br />

disposal.<br />

3.5 POLLUTION CONTROLS<br />

A. Use temporary enclosures and other suitable methods to limit the amount of dust and dirt rising and scattering in<br />

the air to the lowest practical level.<br />

B. Comply with governing authorities pertaining to environmental protection.<br />

C. Clean adjacent portion of the structure and improvement of dust, dirt and debris caused by demolition operations,<br />

as directed by the Wal-Mart Construction Manager and governing authorities. Return adjacent areas to conditions<br />

existing prior to the start of the work.<br />

D. Burning of trash, debris, or removed materials not permitted on site.<br />

02023 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.6 SCHEDULE OF SELECTIVE DEMOLITION<br />

A. Remove and dispose of existing building items and adjacent sitework items as required for Work and as indicated<br />

on Drawings.<br />

B. Sitework Adjacent to Building:<br />

1. Fencing, gates and concrete post footings.<br />

2. Asphalt concrete paving.<br />

3. Metal handrails and railings.<br />

C. Interior or Exterior Slab on Grade:<br />

1. Locate portion of existing concrete slab to be removed. Saw cut perimeter of existing slab minimum of<br />

50% of slab thickness to provide a breaking point to remove existing concrete.<br />

2. Wet saw concrete slabs along straight lines to a minimum depth of 2 inches where concrete is to be<br />

removed. The method of removal shall maintain the undamaged slab edge within the sawed line. Jack<br />

hammers may be used only “after hours” and with permission from the Wal-Mart Construction Manager.<br />

Jack hammers may not be used to remove/cut concrete from the existing slab, but only to break up concrete<br />

which has already been saw cut from the concrete slab.<br />

3. Break concrete slab to be removed into portions easily removed, maximum 3 feet dimension at any side.<br />

4. Remove concrete pieces within removed area down to the existing subgrade.<br />

D. Exterior Masonry:<br />

1. Locate portion of existing masonry wall to be removed. Units which are removed: "tooth" from existing<br />

construction.<br />

2. Verify that temporary supports, enclosures, and bracing are in place and adequate for intended purpose.<br />

3. Remove only that portion of the exterior wall which is required for the indicated new construction.<br />

E. Below Grade Construction:<br />

1. Remove below grade construction including foundation work, column footings, and abandon mechanical,<br />

plumbing, and electrical work as indicated.<br />

F. Interior Walls and Partitions:<br />

1. Remove interior walls and partitions as indicated.<br />

2. Remove all top and bottom framing tracks and overhead braces of partitions being removed.<br />

G. Doors and Frames:<br />

1. Remove hollow metal doors and frames.<br />

2. Remove aluminum storefront doors and frames.<br />

3. Remove aluminum automatic doors and frames.<br />

H. Interior Finishes:<br />

1. Remove carpet and carpet adhesives.<br />

I. Mechanical System:<br />

1. Remove mechanical equipment and related ductwork as indicated.<br />

2. Provide temporary weathertight protection of openings in roof and exterior walls.<br />

3. Remove accessories to the mechanical system including, but not limited to, hanger straps.<br />

J. Plumbing:<br />

1. Remove plumbing fixtures and accessories including exposed supply, waste, and vent piping as indicated.<br />

2. Identify concealed piping within and below slab construction, and cap a minimum of 3 inches below finish<br />

floor unless otherwise noted.<br />

02023 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


K. Electrical Service:<br />

1. Remove abandoned electrical fixtures, conduit, boxes, and wiring as indicated.<br />

2. Remove electrical circuits including conduct as indicated.<br />

END OF SECTION<br />

02023 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec – Civil (Master Site Specifications) 052711<br />

SECTION 02220 (02 4100) - SITE DEMOLITION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Demolition of structures, paving, and utilities.<br />

2. Filling voids created as a result of removals or demolition.<br />

B. Related Requirements:<br />

1. Section 01742 - Construction and Demolition Waste Management and Disposal.<br />

2. Section 01743 - Hazardous/Universal Waste Management and Disposal.<br />

3. Section 02223 - Removal and Recycling of Vinyl Composition Tile (VCT).<br />

4. Section 02224 - Removal and Recycling of Acoustical Ceiling Tile (ACT).<br />

5. Section 02230 - Site Clearing: Clearing of trees and other plant vegetation<br />

6. Section 02300 - Earthwork: Placement of fill material<br />

1.2 REGULATORY REQUIREMENTS<br />

A. Conform to applicable State and local codes for demolition of structures, safety of adjacent structures, dust control,<br />

runoff control, and pollution prevention.<br />

Deleted: Section 02370 - Erosion<br />

and Sedimentation Control (Including<br />

SWPPP): Erosion protection during<br />

demolition operations.<br />

B. Obtain required permits and licenses from appropriate authorities. Pay associated fees including disposal charges.<br />

C. Notify affected utility companies before starting work and comply with their requirements.<br />

D. Do not close or obstruct public or private roadways, sidewalks, or fire hydrants without appropriate permits or<br />

written authorization.<br />

E. If hazardous, contaminated materials or other environmental related conditions are discovered, stop work immediately<br />

and notify the Wal-Mart Construction Manager for action to be taken. Do not resume work until specifically<br />

authorized by the Construction Manager.<br />

F. Comply with the requirements of Section 01743 for hazardous construction and demolition waste management<br />

and disposal.<br />

G. Test soils around buried tanks for contamination. Coordinate notification for mobilization to site and required observation<br />

of tank removal with Wal-Mart Civil Engineering Consultant.<br />

1.3 SUBMITTALS<br />

A. Project Record Documents: Accurately record actual locations of capped utilities and subsurface obstructions that<br />

will remain after demolition. Submit record as part of closeout submittals.<br />

1.4 PROJECT CONDITIONS<br />

A. Structures to be demolished will be discontinued in use and vacated prior to start of work.<br />

B. Owner assumes no responsibility for condition of structures to be demolished.<br />

C. Conditions existing at time of inspection for bidding purposes will be maintained by Owner as reasonably practical.<br />

Variations within structures may occur by Owner's removal and salvage operations prior to start of demolition<br />

work.<br />

02220-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. Unless otherwise indicated in Contract Documents or specified by the Owner, items of salvageable value to Contractor<br />

shall be removed from site and structures. Storage or sale of removed items on site will not be permitted<br />

and shall not interfere with other work specified.<br />

E. Explosives shall not be brought to site or used without written consent of authorities having jurisdiction. Such<br />

written consent will not relieve Contractor of total responsibility for injury to persons or for damage to property<br />

due to blasting operations. Performance of required blasting shall comply with governing regulations.<br />

PART 2 - PRODUCTS<br />

2.1 FILL MATERIALS<br />

A. Fill material shall be aggregate fill materials as specified in Section 02300.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Provide, erect, and maintain erosion control devices, temporary barriers, and security devices at locations indicated<br />

on Construction Drawings.<br />

B. Protect existing landscaping materials, appurtenances, and structures, which are not to be demolished. Repair<br />

damage to existing items to remain caused by demolition operations.<br />

C. Prevent movement or settlement of adjacent structures. Provide bracing and shoring as necessary.<br />

D. Mark location of utilities. Protect and maintain in safe and operable condition utilities that are to remain. Prevent<br />

interruption of existing utility service to occupied or used facilities, except when authorized in writing by authorities<br />

having jurisdiction. Provide temporary services during interruptions to existing utilities as acceptable to governing<br />

authorities and Owner.<br />

E. Notify adjacent property owners of work that may affect their property, potential noise, utility outages, or other<br />

disruptions. Obtain written permission from adjacent property owners when demolition equipment will traverse,<br />

infringe upon, or limit access to their property. Coordinate notice with Owner.<br />

3.2 GENERAL DEMOLITION REQUIREMENTS<br />

A. Conduct demolition to minimize interference with adjacent structures or pavements to remain.<br />

B. Cease operations immediately if adjacent structures appear to be in danger. Notify authority having jurisdiction.<br />

Do not resume operations until directed by authority.<br />

C. Conduct operations with minimum of interference to public or private access. Maintain ingress and egress at all<br />

times.<br />

D. Sprinkle work with water to minimize dust. Provide hoses and water connections for this purpose.<br />

E. Comply with governing regulations pertaining to environmental protection.<br />

F. Clean adjacent structures and improvements of dust, dirt, and debris caused by demolition operations. Return adjacent<br />

areas to condition existing prior to start of work.<br />

3.3 DEMOLITION<br />

A. Demolish site improvements designated to be removed as shown on the drawings. Site improvements shall include<br />

but not be limited to structures, retaining walls, foundations, pavements, curbs and gutters, drainage structures,<br />

utilities, signage or landscaping.<br />

02220-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Disconnect and cap or remove utilities to be abandoned as shown on the drawings.<br />

C. Fill or remove underground tanks, piping, and appurtenances as shown.<br />

D. Demolish buildings designated to be removed as shown on the drawings. Demolish buildings completely and remove<br />

from site using methods as required to complete work within limitations of governing regulations. Small<br />

structures may be removed intact when acceptable to Owner and authorities having jurisdiction.<br />

E. Locate demolition equipment and remove materials to prevent excessive loading to supporting walls, floors, or<br />

framing.<br />

F. Demolish concrete and masonry in small sections. Break up concrete slabs-on-grade that are 2-feet or more below<br />

proposed subgrade to permit moisture drainage. Remove slabs-on-grade and below grade construction within 2-<br />

feet of proposed subgrade.<br />

3.4 FILLING BASEMENTS AND VOIDS<br />

A. Completely fill below grade areas and voids resulting from demolition or removal of structures, underground fuel<br />

storage tanks, wells, cisterns, etc., using aggregate fill materials consisting of stone, gravel, or sand free from debris,<br />

trash, frozen materials, roots, and other organic matter.<br />

B. Areas to be filled shall be free of standing water, frost, frozen or unsuitable material, trash, and debris prior to fill<br />

placement.<br />

C. Place fill materials in accordance with Section 02300 unless subsequent excavation for new work is required.<br />

D. Grade surface to match adjacent grades and to provide flow of surface drainage after fill placement and compaction.<br />

3.5 DISPOSAL OF DEMOLISHED MATERIALS<br />

A. Remove from site debris, rubbish, and other materials resulting from demolition operations. Leave areas of work<br />

in clean condition.<br />

B. No burning of any material, debris, or trash on-site or off-site will be allowed except when allowed by appropriate<br />

governing authority and Owner. If allowed as stated above, burning shall be performed in manner prescribed by<br />

governing authority. Attend burning materials until fires have burned out and have been completely extinguished.<br />

C. Transport materials removed from demolished structures with appropriate vehicles and dispose off-site to areas<br />

that are approved for disposal by governing authorities and appropriate property owners.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02220-3<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec II 052711<br />

SECTION 02223 (02 4114) – REMOVAL AND RECYCLING OF VINYL COMPOSITION TILE (VCT)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Procedures for removal and recycling of existing vinyl composition tile (VCT) including the<br />

following:<br />

1. Selective removal of existing vinyl composition tile (VCT) which is determined acceptable for recycling.<br />

2. Containerizing and loading VCT for transport to Recycling Firm.<br />

3. Coordination with Wal-Mart for shipment of VCT to Recycling Firm.<br />

B. Related Requirements:<br />

1. Section 01100 - Summary: Restrictions for Work within and adjacent to existing building areas.<br />

2. Section 01500 - Temporary Facilities and Controls: Temporary protection and barriers.<br />

3. Section 01731 - Cutting and Patching: Requirements and limitations for cutting and patching Work.<br />

4. Section 01742 - Construction and Demolition Waste Management and Disposal.<br />

5. Section 01743 - Hazardous/Universal Waste Management and Disposal.<br />

6. Section 02023 - Selective Site Demolition.<br />

1.2 DEFINITIONS<br />

A. Recycling Firm: Linron Company, Houston, TX (713) 802-9137.<br />

1. Program Information and Assistance: Ron Harris.<br />

2. Shipping and Receiving: Alison Harris Alison@linron.com<br />

1.3 SEQUENCING AND SCHEDULING<br />

A. Coordinate removal work with work of Section 02023.<br />

1.4 ACCEPTABLE VCT MATERIALS<br />

A. Unless otherwise modified by Recycling Firm Guidelines, products acceptable for recycling include all brands of<br />

vinyl composition materials.<br />

B. Condition of Acceptable Materials:<br />

1. Store recyclable materials off of grade and protected from weather.<br />

2. Material being recycled shall be dry and free of debris.<br />

3. Package recyclable materials in accordance with the requirements of Recycling Firm.<br />

4. Material being recycled shall not come into contact with asbestos containing material, hazardous waste<br />

materials or special waste.<br />

C. Unless otherwise modified by Recycling Firm Guidelines, products not acceptable for recycling include:<br />

1. Tile or adhesive containing asbestos. Test tile or adhesive suspected to contain asbestos prior to recycling.<br />

2. Slip resistant tile.<br />

3. Tan colored tile.<br />

4. Red colored tile.<br />

5. Dark colored tile. Contact Recycling Firm for specific acceptable colors.<br />

6. PVC plank (wood look) tile.<br />

7. Bulk removed tile containing foreign material or debris.<br />

D. Dispose of unacceptable VCT in accordance with the requirements of Section 01742 and Section 01743.<br />

02223 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

Not used.<br />

PART 3 - EXECUTION<br />

3.1 GENERAL<br />

A. Recycling by Contractor is mandatory for VCT which is acceptable under the terms of Recycling Firm.<br />

3.2 EXAMINATION<br />

A. Survey and assess the quantity of acceptable VCT to be removed.<br />

3.3 COORDINATION AND APPROVAL<br />

A. Contact and coordinate the precise details and execution of the recycling program with Recycling Firm.<br />

B. Verify that the old VCT tiles can be recycled.<br />

3.4 VCT REMOVAL<br />

A. Sweep all debris from VCT surfaces. Remove excessive buildup of wax and other debris.<br />

B. Remove vinyl composition tiles to be recycled. Tile may be removed using normal removal methods.<br />

3.5 LOADING AND SHIPPING<br />

A. Prepare VCT for shipment in accordance with Recycling Firm guidelines and instructions. Preparation shall be in<br />

strict accordance with the guidelines provided and shall take precedence over any conflicting provisions stated<br />

herein. Contact Recycling Firm for coordination of preparation and to obtain specific loading and shipping<br />

instruction prior to removal of VCT.<br />

B. Load and ship only full truckloads of VCT.<br />

C. Full truckload is defined by Recycling Firm by number of VCT containers. Contact Recycling Firm for quantity.<br />

D. Quantities considered to be less than full truckloads shall not be recycled under this program. Dispose of VCT not<br />

accepted by Recycling Firm in accordance with the requirements of Section 01742.<br />

E. Include only material generated from the Site of this Project in shipment of VCT materials.<br />

F. Containerize vinyl composition tile that is acceptable for recycling. Recycling Firm will provide containers.<br />

Containers will be provided with shipment of new tile or will be supplied upon notification to Recycling Firm.<br />

Containers will suitable for placement on pallets.<br />

G. Shrink wrap top portion of containers for top closure. Place containers on pallets.<br />

H. Fill containers to the maximum fill line indicated on the container.<br />

I. Store loaded containers in a dry location.<br />

J. Contact Wal-Mart Store Planner or Recycling Firm for arrangement of carrier for shipping. A shipping load is to<br />

be determined by Recycling Firm. Prepare a packing list printed and affixed to each container. Each carrier shall<br />

carry a Bill of Lading with each shipment.<br />

02223 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


K. Load and secure pallets onto trailers to prevent shifting in transit.<br />

3.6 NON-COMPLIANCE<br />

A. Costs for transportation and disposal of non-compliant materials shipped by the Contractor to the Recycling Firm<br />

may be deducted from payments due Contractor.<br />

END OF SECTION<br />

02223 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 02224 (02 4115) – REMOVAL AND RECYCLING OF ACOUSTICAL CEILING TILE (ACT)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Procedures for removal and recycling of existing acoustical ceiling tile (ACT) including the<br />

following:<br />

1. Submission of application for recycling of ACT to Recycling Firm for project registration, approval and<br />

acceptance of removed ACT.<br />

2. Selective removal of existing acoustical ceiling tile (ACT) which is determined acceptable for reclamation.<br />

3. Palletizing, labeling, and loading ACT for transport to Recycling Firm.<br />

4. Shipment of ACT at Recycling Firm expense.<br />

B. Related Requirements:<br />

1. Section 01100 - Summary: Restrictions for Work within and adjacent to existing building areas.<br />

2. Section 01500 - Temporary Facilities and Controls: Temporary protection and barriers.<br />

3. Section 01731 - Cutting and Patching: Requirements and limitations for cutting and patching Work.<br />

4. Section 01742 - Construction and Demolition Waste Management and Disposal.<br />

5. Section 01743 - Hazardous/Universal Waste Management and Disposal.<br />

6. Section 02023 - Selective Site Demolition.<br />

1.2 DEFINITIONS<br />

A. Recycling Firm: Armstrong World Industries, Inc., Armstrong Recycling Center, (877) 276-7876,<br />

recyclingcenter@armstrong.com<br />

1.3 SEQUENCING AND SCHEDULING<br />

A. Coordinate removal work with work of Section 02023.<br />

1.4 ACCEPTABLE ACT MATERIALS<br />

A. Unless otherwise modified by Recycling Firm Guidelines, products acceptable for recycling include:<br />

1. All brands of dry, pulpable mineral fiber ceiling panels or tiles.<br />

2. All brands of dry fiberglass panels. Facing must be easily removable.<br />

3. Vinyl or scrim-faced mineral fiber panels.<br />

4. See Recycling Firm Guidelines for list of unacceptable materials and materials acceptable for recycling on<br />

a case-by-case basis.<br />

B. Condition of Acceptable Materials:<br />

1. Remove metal splines from tiles.<br />

2. Store recyclable materials off of grade and protected from weather.<br />

3. Ceiling material being recycled shall be dry and free of debris.<br />

4. Package recyclable materials in accordance with the requirements of Recycling Firm.<br />

5. Ceiling material being recycled may not come into contact with asbestos containing material, hazardous<br />

waste materials or special waste. If the area where ceilings are being removed is or has gone through<br />

abatement procedures, verification that ceilings did not come in contact with asbestos containing material is<br />

required.<br />

C. Dispose of unacceptable ACT in accordance with the requirements of Section 01742 and Section 01743.<br />

PART 2 - PRODUCTS<br />

Not used.<br />

02224 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 GENERAL<br />

A. Recycling of ACT is provided under the Recycling Firm Guidelines<br />

(http://www.armstrong.com/commceilingsna/article45691.html) and includes the acceptance, including shipment,<br />

of removed ACT at no cost to Contractor as long as Recycling Firm requirements are met.<br />

B. Materials proposed for recycling are subject to on-site inspection by Recycling Firm.<br />

C. Recycling by Contractor is mandatory for ACT which is approved and accepted under the terms of Recycling<br />

Firm.<br />

3.2 EXAMINATION<br />

A. Survey and assess the quantity of acceptable ACT to be removed.<br />

3.3 COORDINATION AND APPROVAL<br />

A. Register Project with Recycling Firm by calling (877) 276-7876, option 1 then 8. Coordinate the precise details<br />

and execution of recycling program with Recycling Firm.<br />

B. Verify that ACT to be removed is acceptable to Recycling Firm.<br />

C. Submit Asbestos Survey provided by Owner, year of building construction and details of any prior or current<br />

asbestos abatement to Recycling Firm via email address above. Submit one additional copy each to Wal-Mart<br />

Construction Manager and Architect in accordance with the requirements of Section 01330.<br />

D. Receive return authorization and return labels from Recycling Firm.<br />

E. Schedule material pickup by submitting Contractor’s Application for Recycling (Form A at end of this Section)<br />

and Recycling Logistics Form (Form B at end of this Section) to Recycling Firm via email address above at least<br />

five days prior to desired pickup date. Submit one additional copy each to Wal-Mart Construction Manager and<br />

Architect in accordance with the requirements of Section 01330 and upload to Wal-Mart’s designated web-based<br />

reporting system.<br />

F. Obtain completed Recycling Receipt (Form C at end of this Section) from Recycling Firm. Upload to Wal-Mart’s<br />

designated web-based reporting system.<br />

G. If materials are not accepted by Recycling Firm, submit statement indicating reason for non-acceptance to Wal-<br />

Mart via Wal-Mart’s designated web-based reporting system.<br />

3.4 ACT REMOVAL<br />

A. Remove acoustical ceiling tiles to be recycled from grid.<br />

B. Where removal terminates at a "surface" or construction "to remain," completely remove all traces of material<br />

selectively removed. Provide smooth, even substrate transition as specified in Section 01731.<br />

3.5 LOADING AND SHIPPING<br />

A. Prepare recyclable materials for shipment in accordance with Recycling Firm Guidelines and instructions.<br />

Preparation shall be in accordance with Guidelines provided and shall take precedence over any conflicting<br />

provisions stated herein. Contact Recycling Firm for coordination of preparation and to obtain specific loading<br />

and shipping instruction prior to removal of ACT.<br />

02224 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Load and ship full truckloads of recyclable materials whenever possible. A full truckload is defined as not less<br />

than 30,000 sq. ft.<br />

C. Full truckloads of material will be picked up at Site. If there is less than a full truckload, contact Recycling Firm<br />

for instructions.<br />

D. Include only material generated from the Site of this Project in shipment of ACT materials.<br />

E. Palletize acoustical ceiling tile that is acceptable for recycling. Provide palletizing materials and supplies<br />

including pallets, metal bands, and stretch wrap.<br />

F. Stack ceiling panels on 4 by 4 wooden pallets and secure with metal bands or stretch wrap. Any variation from<br />

pallet size shall be approved by Recycling Firm. Palletize in one or combination of the following methods:<br />

1. Palletize on 4 ft by 4 ft pallets stacked with ceiling materials to 4 feet tall each pallet.<br />

2. Palletize on 4 ft by 4 ft pallets stacked with ceiling materials to 6 feet tall each pallet.<br />

G. Load and secure pallets onto trailers to prevent shifting in transit. Carriers will provide load stabilizers.<br />

H. Load pallets as follows:<br />

1. Forty-four 4 x 4 pallets stacked with ceiling material to 4 feet tall each and stacked on top of each other in<br />

trailer.<br />

2. Twenty-four 4 by 4 pallets with ceiling material stacked to 6 tall each pallet.<br />

3. A combination of 4 ft tall and 6 ft. tall stacked pallets to achieve equivalent quantity of above loading.<br />

3.6 NONCOMPLIANCE<br />

A. Costs for transportation and disposal of non-compliant materials shipped by the Contractor to Recycling Firm may<br />

be deducted from payments due Contractor.<br />

END OF SECTION<br />

02224 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Form A<br />

Contractor’s Application for Recycling<br />

Owner: Wal-Mart Stores, Inc.<br />

Store Number:<br />

Location:<br />

Contractor Name:<br />

Address:<br />

Telephone No.:<br />

I am duly contracted by the Owner of the facility referenced above. I am providing existing ceiling material from the facility<br />

referenced above to be shipped to Armstrong World Industries, Inc., for recycling. I have inspected the material, provided an<br />

approved negative asbestos survey to Armstrong, and hereby certify that the material is free of hazardous material and is<br />

otherwise eligible for disposal as ordinary solid municipal waste.<br />

I agree that Armstrong may refuse to accept shipments of approved ceiling materials if any shipment is, upon arrival at an<br />

Armstrong plant, either not bearing necessary labeling and identification of date, owner, site and approval, or not packaged<br />

according to the specifications, or mixed with or containing contaminated or exposed (weathered) tiles, other debris of any<br />

sort, fiberglass insulation, or products not previously approved by Armstrong, or any products which are not capable of being<br />

pulped or are otherwise unacceptable to Armstrong.<br />

In event of such refusal, Armstrong will immediately contact me. If I do not respond promptly, Armstrong will either<br />

dispose of the materials or ship those materials back to me without having accepted them. I agree to assume all costs in<br />

connection with such disposal or return shipment of refused material.<br />

Submitted By:<br />

(Signature of Authorized Representative of Contractor)<br />

(Printed Name of Authorized Representative of Contractor)<br />

Date:<br />

02224 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Form B<br />

Recycling Logistics Form<br />

Owner: Wal-Mart Stores, Inc.<br />

Store Number:<br />

Location:<br />

Contractor Name:<br />

Address:<br />

Telephone No.:<br />

Quantity of Material to Recycle:<br />

SF of material to recycle: ______ sf or ______ pallets<br />

Address for Pickup:<br />

Street:<br />

City: State: ZIP:<br />

Jobsite Contact Name:<br />

Jobsite Contact Phone:<br />

Jobsite Contact Fax:<br />

Pick Up Date:<br />

(Add additional loads if more than one shipment)<br />

Desired Pick Up Date for Load 1:<br />

Special Loading Requirements:<br />

(Loading dock height and size, parking, city/state requirements, other trade traffic to be factored into this pickup?<br />

02224 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Form C<br />

Recycling Receipt<br />

Owner: Wal-Mart Stores, Inc.<br />

Store Number:<br />

Location:<br />

Contractor Name:<br />

Address:<br />

Telephone No.:<br />

Armstrong has accepted the following for recycling from this location:<br />

Total Square footage of Ceiling Tile Material:<br />

Total net weight of Ceiling Tile Material:<br />

Received By:<br />

(Signature of Authorized Representative of Armstrong)<br />

(Printed Name of Authorized Representative of Armstrong)<br />

Date:<br />

02224 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II – Civil (Master Site Specifications) 051110<br />

SECTION 02230 - SITE CLEARING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Cleaning site of debris, grass, trees, and other plant life in preparation for site or building earthwork.<br />

2. Protection of existing structures, trees, or vegetation indicated on the Construction Drawings to remain.<br />

B. Related Requirements:<br />

1. Section 02220 – Site Demolition: Demolition and removal of structures, paving, utilities and other improvements.<br />

2. Section 02300 – Earthwork: Stripping and removal of topsoil.<br />

1.2 ENVIRONMENTAL REQUIREMENTS<br />

A. Construct temporary erosion and sediment control systems as shown on the Construction Drawings to protect adjacent<br />

properties and water resources from erosion and sedimentation.<br />

B. Clearing and grubbing shall commence in the proper sequence as shown on the Erosion and Sediment Control Plan<br />

in the Construction Drawings.<br />

C. Contractor shall conduct storm water management practices in accordance the Construction Drawings and all permits<br />

and shall enforce action taken or imposed by Federal or State agencies, including cost of fines, construction<br />

delays, and remedial actions resulting from Contractor's failure to comply with the provisions of project permits.<br />

1.3 PROJECT CONDITIONS<br />

A. Conditions existing at time of inspection for bidding purposes will be maintained by Owner as reasonably practical.<br />

PART 2 - PRODUCTS<br />

Not Used<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Identify existing plant life that is to remain and verify clearing limits are clearly tagged, identified, and marked in<br />

such manner as to ensure their protection throughout construction operations.<br />

Deleted: Section 02370 - Erosion<br />

And Sedimentation Control (Including<br />

SWPPP)<br />

Deleted: and as directed by the "Storm<br />

Water Pollution Prevention Plan"<br />

(SWPPP)<br />

Deleted: In event that sitework<br />

on this project will disturb one or more<br />

acres, starting work shall be strictly governed<br />

by the sequence of construction as<br />

specified in Section 02370 and SWPPP<br />

site maps. Contractor shall not begin<br />

construction without "National Pollution<br />

Discharge Elimination System" (NPDES)<br />

permit governing discharge of storm<br />

water from site for entire construction<br />

period. NPDES permit requires SWPPP<br />

to be in place during construction.<br />

Deleted: stated in the Phase I of the<br />

Best Management Practice Sequence<br />

specified in Section 02370 and on the<br />

SWPPP site map and subsequent to the<br />

halt in construction for performance of<br />

the inspection and certification of BMPs<br />

as stated.<br />

Deleted: with the project SWPPP and<br />

applicable NPDES<br />

Deleted:<br />

Deleted: NPDES permit<br />

3.2 PROTECTION<br />

A. Locate, identify, and protect existing utilities that are to remain.<br />

B. Protect trees, plant growth, and features designated to remain as part of final landscaping.<br />

C. Conduct operations with minimum interference to public or private accesses and facilities. Maintain ingress and<br />

egress at all times and clean or sweep roadways daily as shown on the Construction Drawings and as required by<br />

governing authorities. Dust control shall be provided with sprinkling systems or equipment provided by Contractor.<br />

02230-1<br />

Deleted: SWPPP or<br />

Deleted: y<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. Protect benchmarks, property corners, and other survey monuments from damage or displacement. If marker<br />

needs to be removed it shall be referenced by a licensed land surveyor and replaced, as necessary, in kind.<br />

E. Provide traffic control as required, in accordance with the US Department of Transportation's "Manual on Uniform<br />

Traffic Control Devices" and applicable state highway department requirements.<br />

3.3 EQUIPMENT<br />

A. Material shall be transported to and from the project site using well-maintained and operating vehicles. Transporting<br />

vehicles operating on site shall stay on designated haul roads and shall not endanger improvements by rutting,<br />

overloading, or pumping.<br />

3.4 CLEARING<br />

A. Clear areas required for access to site and execution of work.<br />

B. Unless otherwise indicated on Construction Drawings, remove trees, shrubs, grass, other vegetation, improvements,<br />

or obstructions interfering with installation of new construction. Removal includes digging out stumps and<br />

roots. Depressions caused by clearing and grubbing operations shall be filled to subgrade elevation to avoid ponding<br />

of water. Satisfactory fill material shall be placed in accordance with Section 02300.<br />

C. Remove grass, trees, plant life, stumps, and other construction debris from site to dump site that is suitable for<br />

handling such material according to state laws and regulations.<br />

D. Cut heavy growths of grass from areas before stripping and topsoil removal and remove cuttings with remainder of<br />

cleared vegetative material.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02230-2<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec II<br />

122900b<br />

SECTION 02251 – SHORING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Shoring at excavations and building structural and non-structural elements required to provide temporary<br />

support during excavating, demolition, and construction operations.<br />

2. Temporary protection including without limits for construction workers, materials, existing construction<br />

other adjacent properties, and public.<br />

B. Related Sections:<br />

1. Section 01700 - Execution Requirements: Requirements and limitations for cutting and patching Work.<br />

2. Section 01731 - Cutting and Patching.<br />

3. Section 02023 - Selective Site Demolition: Procedures for demolition and removal of existing building<br />

elements.<br />

1.2 DESIGN REQUIREMENTS<br />

A. Design and provide shoring to safely prevent collapse of materials and structures and to permit construction<br />

operations to proceed in conformance with construction sequence phases indicated on Drawings.<br />

1.3 QUALITY ASSURANCE<br />

A. Provide design of shoring by professional civil or structural engineer licensed in State in which project is located.<br />

B. Coordinate shoring design and construction with:<br />

1. Soil Investigation Report prepared for this project.<br />

2. Building structural system, including without limits to locations of footings, columns, pilasters, walls, and<br />

other related structural elements.<br />

C. Comply with pertinent requirements of Authorities Having Jurisdiction (AHJ).<br />

D. The Contractor shall be responsible for means and methods of shoring and temporary support and for the<br />

sequences and procedures to be used.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Provide materials as required for shoring system design.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where Work under this Section will be performed. Do not proceed with<br />

Work until unsatisfactory conditions have been corrected.<br />

B. Starting Work constitutes acceptance of existing conditions. Be responsible for correcting unsatisfactory and<br />

defective Work encountered after starting Work.<br />

02251 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.2 INSTALLATION<br />

A. Install shoring system in accordance with shoring design drawings.<br />

B. Coordinate placement of shoring system elements with existing Work and approved Demolition Procedures and<br />

Sequencing Plan as specified in Section 02023.<br />

C. Perform cutting and patching required by installation of shoring in accordance with approved Cutting and Patching<br />

Procedures and Sequencing Plan as specified in Section 01731.<br />

3.3 FIELD QUALITY CONTROL<br />

A. Shoring Design Engineer: Inspect and approve shoring materials and installation prior to start of any demolition<br />

work.<br />

B. Submit inspection report to Wal-Mart Construction Manager.<br />

END OF SECTION<br />

02251 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052510<br />

SECTION 02300 (31 2000) - EARTHWORK<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Excavation, filling, and backfilling for structures, pavement, and outparcels.<br />

2. Trenching and backfilling for utilities.<br />

3. Dewatering.<br />

4. Boring under crossings.<br />

B. Related Requirements:<br />

1. Section 02318 - Rock Excavation.<br />

2. Section 02340 - Soil Stabilization.<br />

3. Section 02370 - Erosion Control and Sedimentation. Temporary and permanent erosion control.<br />

4. Section 02375 - Stone Protection. Rip-rap stone for slope protection.<br />

5. Section 02251 - Shoring<br />

6. Foundation Subsurface Preparation for granular subbase below slabs on grade in the building pad<br />

preparation limits.<br />

1.2 REFERENCES<br />

Style Definition: PR1<br />

Style Definition: PR2<br />

Deleted: [EDITOR NOTE: This<br />

document is incomplete unless it is<br />

explicitly coordinated with the plans and<br />

geotechnical report. It is imperative to<br />

add and delete requirements as required<br />

to coordinate the specifications with the<br />

plans and geotechnical report. DELETE<br />

THESE EDITOR NOTES PRIOR TO<br />

PRINTING.]<br />

Formatted: Bullets and Numbering<br />

Deleted: Division 3 - Subbase<br />

requirements<br />

Deleted: building<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM)<br />

1. ASTM D422 - Particle Size Analysis of Soil.<br />

2. ASTM D1557 - Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft 3<br />

(2,700 Kn.m/m 3 )).<br />

3. ASTM D2487 - Classification of Soils for Engineering Purposes (Unified Soil Classification System).<br />

4. ASTM D2488 - Description and Identification of Soils (Visual-Manual Procedures).<br />

5. ASTM D4318 - Liquid Limit, Plastic Limit, and Plasticity Index of Soils.<br />

6. ASTM D6938 – In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods<br />

(Shallow Depth).<br />

C. American Association of State Highway and Transportation Officials (AASHTO)<br />

1. AASHTO T 88 - Particle Size Analysis of Soils.<br />

D. California Department of Transportation (Caltrans):<br />

1. Standard Specifications.<br />

E. National Fire Protection Association (NFPA)<br />

1. NFPA 70 - National Electrical Code.<br />

F. American Water Works Association (AWWA)<br />

1. AWWA C200 - Standard for Steel Water Pipe - 6 In. (150 mm) and Larger.<br />

2. AWWA C206 - Field Welding Of Steel Water Pipe.<br />

G. Public Works Standards, Inc. (PWSI)<br />

1. Standard Specifications for Public Works Construction (Greenbook).<br />

1.3 QUALITY ASSURANCE<br />

02300-1<br />

Deleted: ASTM D698 - Laboratory<br />

Compaction Characteristics of Soil Using<br />

Standard Effort (12,400 ft-lbf/ft 3 (600<br />

kN.m/m 3 )).<br />

Formatted: Bullets and Numbering<br />

Deleted: [EDITOR NOTE: Edit to<br />

include the appropriate State DOT<br />

standard if applicable.]<br />

Formatted: Bullets and Numbering<br />

Deleted: State Department of<br />

Transportation (DOT)<br />

Deleted: Standard Specifications for<br />

Construction and Materials<br />

Formatted: PR1<br />

Formatted: Bullets and Numbering<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. A Construction Testing Laboratory (CTL) selected and paid for by the Owner, will be retained to perform<br />

construction testing on site.<br />

1.4 DEFINITIONS<br />

A. Satisfactory Materials: ASTM D2487 soil classification groups GW, GP, GM, SW, SP, SM, ML, CL, CH, SC,<br />

GC, or a combination of these group symbols.<br />

1. Fill material shall further conform with the requirements below and Part 3.8, FILLING hereinafter.<br />

2. Satisfactory materials shall be free of rock or gravel larger than allowed for fill or backfill material as<br />

specified hereinafter or as shown on the drawings.<br />

3. Satisfactory materials shall contain no debris, organics (not more than 3 percent by weight), recycled<br />

asphalt concrete, waste, frozen materials, vegetation, and other deleterious matter.<br />

4. Unless specifically stated otherwise in "Foundation Subsurface Preparation" on the Drawings, the<br />

following stipulates satisfactory materials to be used as fill in specified areas:<br />

Location<br />

BUILDING AREA, SIDEWALKS AND RAMPS<br />

Top 24 inches (below bottom of slabs)<br />

Below bottom of Aggregate Base<br />

PAVEMENT AREAS<br />

Below Bottom of Aggregate Base<br />

02300-2<br />

Material<br />

Crushed Aggregate Base<br />

(in accordance with Greenbook)<br />

On-Site engineered fill soils free<br />

Of debris, free of particles larger<br />

Than 3 Inches and having less than<br />

3 Percent Organics<br />

On-Site engineered fill soils free<br />

Of debris, free of particles larger<br />

Than 3 Inches and having less than<br />

3 Percent Organics<br />

5. Imported fill soil shall not contain recycled materials, shall be non-contaminated, non-expansive and<br />

granular in nature and contain enough fine-grained material (binder) to allow cutting “neat” footing<br />

trenches and shall meet the following acceptance criteria:<br />

Percent Passing 3-Inch Sieve 100<br />

Percent Passing No. 4 Sieve 85 - 100<br />

Percent Passing No. 200 Sieve 15 - 40<br />

Plasticity Index Less than 12<br />

Expansion Index Less than 10<br />

R-Value Minimum 25<br />

Organics<br />

< 3% by weight<br />

Sulfates<br />

< 0.05 % by weight<br />

Min. Resistivity<br />

> 5,000 ohms-cm<br />

B. Unsatisfactory Materials: Materials which do not comply with the requirements for satisfactory materials are<br />

unsatisfactory.<br />

1. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction;<br />

contaminated materials and material classified as satisfactory materials which contains root and other<br />

organic matter larger than ¼ inch in diameter or frozen material. The CTL shall be notified of any<br />

contaminated materials.<br />

2. Unsatisfactory materials also include satisfactory materials not maintained at two (2) to five (5) percent<br />

above optimum for clayey soils and 0 to three (3) percent above optimum for granular soils at time of<br />

compaction.<br />

Deleted: [EDITOR NOTE: Edit the<br />

following definitions as required for the<br />

specific project and in accordance with<br />

the Geotechnical Report. Modify the<br />

classification groups and expand or<br />

modify the definition as necessary.<br />

Bracketed text and brackets shall be<br />

deleted where not applicable.]<br />

Formatted: Bullets and Numbering<br />

Deleted: [<br />

Deleted: ]<br />

Deleted: [MH,] [<br />

Deleted: ]<br />

Deleted: [<br />

Deleted: ]<br />

Deleted: to the plasticity index and<br />

liquid limits (PI and LL) specified in<br />

Paragraph<br />

Deleted: table<br />

Deleted: maximum allowable values<br />

for plasticity index (PI) and liquid limit<br />

(LL) of<br />

Deleted: PI LL<br />

Formatted: Font: Bold<br />

Formatted: Indent: Left: 72 pt<br />

Formatted: Font: Bold<br />

Formatted: Indent: Left: 72 pt<br />

Formatted: No bullets or<br />

numbering, Tabs: Not at 72 pt<br />

Deleted: <br />

Building area (below upper four<br />

feet) 20 50 <br />

Building area (upper four<br />

feet) 12 40<br />

Areas outside the building pad<br />

including outparcels<br />

(Below upper two<br />

feet) 20 50 <br />

(Upper two feet, except for depth<br />

to receive topsoil) 15 40<br />

<br />

(References to depth are to proposed<br />

subgrade elevations)<br />

Formatted: Bullets and Numbering<br />

Deleted: within 2 percent of optimum<br />

Deleted: moisture content<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


C. Rock: Rock shall be as defined in Section 02318.<br />

1.5 SUBMITTALS<br />

A. Submit 30-pound sample of each type of off-site fill material that is to be used at the site in airtight containers to<br />

the construction testing laboratory or submit gradation and certification of aggregate material that is to be used at<br />

the site to the independent testing laboratory for review.<br />

B. A minimum of 14 days prior to importing fill soils, the Contractor shall submit analytical test data that<br />

demonstrates that the proposed import soils comply with the specified criteria. Also, prior to being transported to<br />

the site, the import material shall be certified by the Contractor and the supplier that the soils do not contain any<br />

environmental contaminates regulated by local, state or federal agencies having jurisdiction. This certification<br />

shall consist of, as a minimum, analytical data specific to the source of the import material in accordance with the<br />

criteria identified in the Department of Toxic Substances Control, “Information Advisory, Clean Imported Fill<br />

Material,” dated October 2001. Prior to testing, the source of the import, the location of the import site, the prior<br />

land use of the import site and the list of constituents to be tested for the import fill source shall be submitted to the<br />

CEC for review and comment prior to sampling and testing the fill soils.<br />

Deleted: independent<br />

Formatted: Bullets and Numbering<br />

C. Submit name of each material supplier and specific type and source of each material. Change in source throughout<br />

project requires approval of Owner.<br />

D. Submit Dewatering Plans upon request by Owner.<br />

E. Shop drawings or details pertaining to excavating and filling are not required unless otherwise shown on the<br />

Drawings or if contrary procedures to Construction Documents are proposed.<br />

F. Shop drawings or details pertaining to site utilities are not required unless required by regulatory authorities or<br />

unless uses of materials, methods, equipment, or procedures that are contrary to The Drawings or Specifications<br />

are proposed. Do not perform work until Owner has accepted required shop drawings.<br />

G. Contact utility companies and determine if additional easements will be required to complete project. Provide<br />

written confirmation of the status of all easements to Owner at time of Preconstruction Conference or no later than<br />

90 days prior to project possession date.<br />

PART 2 - PRODUCTS<br />

2.1 SOIL AND ROCK MATERIALS<br />

A. Fill and Final Trench Backfill. Satisfactory materials excavated from the site or imported fill meeting these<br />

specifications.<br />

B. Imported Fill Material: Satisfactory material provided from offsite borrow areas when sufficient satisfactory<br />

materials are not available from required excavations.<br />

C. Bedding, Haunching, and Initial Backfill: Naturally or artificially graded mixture of natural or crushed gravel,<br />

crushed stone, and natural or crushed sand with a minimum sand equivalent of 30 and meeting the following<br />

gradation criteria: 100 percent passing a 1-inch sieve, a minimum of 90 percent passing the No. 4 sieve, and not<br />

more than 10 percent passing a No. 200 sieve. Bedding shall extend to a minimum of 4 inches below bottom of<br />

pipe. Initial trench backfill shall extend to a minimum of 12 inches above the top of the pipe.<br />

D. Building Subbase Material: Subbase for building and appurtenances slabs on ground shall consist of a 24 inch<br />

thickness of Crushed Aggregate Base (CAB) in accordance with the Greenbook.<br />

E. Drainage Fill: Washed, narrowly graded mixture of crushed stone, or crushed or uncrushed gravel; ASTM D448;<br />

coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2- inch sieve and 0 to 5 percent passing a No.8<br />

sieve.<br />

02300-3<br />

Deleted: Backfill. Satisfactory<br />

materials excavated from the site.<br />

Formatted: Bullets and Numbering<br />

Deleted: Trench Backfill: ASTM<br />

D2321 unless otherwise specified or<br />

shown on the drawings.<br />

Deleted: is specified in Section 03300<br />

or 03312 as applicable<br />

Deleted: Bedding: Aggregate Type<br />

as indicated on the plans or naturally or<br />

artificially graded mixture of natural or<br />

crushed gravel, crushed stone, and natural<br />

or crushed sand; ASTM D2940; except<br />

with 100 percent passing a 1-inch sieve<br />

and not more than 8 percent passing a<br />

No.200 sieve.<br />

Formatted: Bullets and Numbering<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


F. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand;<br />

ASTM D448; coarse-aggregate grading Size 67; with 100 percent passing a 1-inch sieve and 0 to 5 percent passing<br />

a No.4 sieve.<br />

G. Topsoil: Topsoil shall consist of stripping material excavated from the site. Topsoil shall consist of organic<br />

surficial soil found in depth of not more than 6-inches. Topsoil shall be as further defined in Section 02900 –<br />

Planting.<br />

2.2 APPURTENANT MATERIALS<br />

A. Stabilization fabrics and geogrids: As specified in Section 02340.<br />

B. Filter and drainage fabrics: As specified in Section 02340.<br />

C. Steel Casing Pipe: Comply with AWWA C200 minimum grade B, size, and wall thickness as indicated on The<br />

Drawings.<br />

D. Trench Utility Locator Tape: Heavy duty 6" wide underground warning tape. Tape shall be made from<br />

polyethylene material, 3.5 mils thick, with a minimum tensile strength of 1,750 psi. Place the tape at one-half the<br />

minimum depth of cover for the utility line or a maximum of 3 feet, which ever is the less, but never above the top<br />

of subgrade. Color of tape shall be determined by as follows:<br />

1. Natural Gas or Propane – Yellow.<br />

2. Electric – Red.<br />

3. Telephone – Orange.<br />

4. Water – Blue.<br />

5. Sanitary Sewer – Green.<br />

2.3 EQUIPMENT<br />

A. Transport off-site materials to project using well-maintained and operating vehicles. Once on site, transporting<br />

vehicles shall stay on designated haul roads and shall at no time endanger improvements by rutting, overloading,<br />

or pumping.<br />

2.4 SOURCE QUALITY CONTROL<br />

A. With the exception of analytical testing of import soils specified in Part 1.5, B, laboratory testing of materials<br />

proposed for use in the project shall be by the Wal-Mart Construction Testing Laboratory at no cost to Contractor.<br />

The Contractor shall provide representative samples of material obtained off-site.<br />

B. Perform R-value tests in areas to receive pavement for each type of material that is imported from off-site. R-<br />

value shall be equal to or above pavement design subgrade R-value indicated on Construction Drawings.<br />

C. Following tests shall be performed on each type of imported soil material used as compacted fill:<br />

1. Moisture and Density Relationship: ASTM D1557.<br />

2. Mechanical Analysis: ASTM D422.<br />

3. Plasticity Index: ASTM D4318.<br />

4. R-value (CTM 301), where soils are planned for use in pavement areas.<br />

5. Expansion Index (ASTM D4829)<br />

6. Corrosivity Testing (Resistivity and Sulfates)<br />

7. Organics Testing<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Identify required lines, levels, contours, datum, elevations, and grades necessary for construction as shown on the<br />

drawings.<br />

02300-4<br />

Deleted: L<br />

Formatted: Bullets and Numbering<br />

Deleted: Perform California<br />

Bearing Ratio (CBR) or Limerock<br />

Bearing Ratio (LBR) tests in outparcels<br />

and areas to receive pavement for each<br />

type of material that is imported from<br />

off-site. CBR or LBR value shall be<br />

equal to or above pavement design<br />

subgrade CBR or LBR value indicated on<br />

Construction Drawings.<br />

Deleted: on-site or<br />

Formatted: Bullets and Numbering<br />

Deleted: Moisture and Density<br />

Relationship: ASTM D698 or ASTM<br />

D1557.<br />

Mechanical Analysis: AASHTO T88<br />

or ASTM D422.<br />

Plasticity Index: ASTM D4318.<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Notify utility companies to remove or relocate public utilities that are in conflict with proposed improvements.<br />

C. Protect plant life, lawns, fences, existing structures, sidewalks, paving, and curbs, unless otherwise noted on the<br />

drawings from excavating equipment and vehicular traffic.<br />

D. Protect benchmarks, property corners, and other survey monuments from damage or displacement. If marker<br />

needs to be removed it shall be referenced by licensed land surveyor and replaced, as necessary, by same.<br />

E. Remove from site, material encountered in grading operations that, in opinion of Owner or the Owner’s<br />

Construction Testing Laboratory (CTL) is unsatisfactory material or undesirable for backfilling, subgrade, or<br />

foundation purposes. Dispose of in manner satisfactory to Owner and local governing agencies. Backfill areas<br />

with layers of satisfactory material and compact as specified herein.<br />

F. Prior to placing fill in low areas, such as previously existing creeks, ponds, or lakes, perform following<br />

procedures:<br />

1. Drain water out by gravity with ditch having flow line lower than lowest elevation in low area. If drainage<br />

cannot be performed by gravity ditch, use adequate pump to obtain the same results.<br />

2. After drainage of low area is complete, remove muck, mud, debris, and other unsatisfactory material by<br />

using acceptable equipment and methods that will keep natural soils underlying low area dry and<br />

undisturbed.<br />

3. All muck, mud, and other materials removed from low areas shall be dried on-site by spreading in thin<br />

layers for observation by the CTL. Material shall be inspected and, if found to be satisfactory for use as fill<br />

material, shall be incorporated into lowest elevation of site filling operation, but not under building<br />

subgrade or within 5'-0" of perimeter of building subgrade, paving or outparcell subgrade. If, after<br />

observation by the CTL, material is found to be unsatisfactory, it shall be removed from site.<br />

G. Locate and identify utilities that have previously been installed and protect from damage.<br />

H. Locate and identify existing utilities that are to remain and protect from damage.<br />

I. Maintain in operating condition existing utilities, previously installed utilities, and drainage systems encountered<br />

in utility installation. Repair surface or subsurface improvements shown on the Drawings.<br />

J. Verify location, size, elevation, and other pertinent data required making connections to existing utilities and<br />

drainage systems as indicated on the Drawings.<br />

K. Over excavate and properly prepare areas of subgrade that are not capable of supporting proposed systems.<br />

Stabilize these areas by using acceptable geotextile fabrics or aggregate material placed and compacted as<br />

specified in Section 02340.<br />

3.2 DEWATERING<br />

A. General:<br />

1. Dewatering activities shall conform to applicable provisions in the Erosion and Sediment Control Plan.<br />

2. Provide dewatering systems as required for excavations.<br />

3. Design and provide dewatering system using accepted and professional methods consistent with current<br />

industry practice to eliminate water entering the excavation under hydrostatic head from the bottom or<br />

sides. Design system to prevent differential hydrostatic head, which would result in floating out soil<br />

particles in a manner, termed as a “quick” or “boiling” condition. System shall not be dependent solely<br />

upon sumps or pumping water from within the excavation where differential head would result in a quick<br />

condition, which would continue to worsen the integrity of the excavation’s stability.<br />

4. Provide dewatering system of sufficient size and capacity to prevent ground and surface water flow into the<br />

excavation and to allow Work to be installed in a dry condition.<br />

5. Control, by acceptable means, all water regardless of source. Contractor shall be responsible for disposal of<br />

the water.<br />

6. Control groundwater in a manner that preserves strength of foundation soils, does not cause instability or<br />

raveling of excavation slopes, and does not result in damage to existing structures. Where necessary, lower<br />

02300-5<br />

Deleted: 02370<br />

Formatted: No bullets or<br />

numbering, Tabs: Not at 72 pt +<br />

459 pt<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


water level in advance of excavation utilizing wells, wellpoints, jet educators, or similar positive methods.<br />

The water level as measured by piezometers shall be maintained a minimum of 3 feet below prevailing<br />

excavation level.<br />

7. Commence dewatering prior to any appearance of water in excavation and continue until Work is complete<br />

to the extent that no damage results from hydrostatic pressure, flotation, or other causes.<br />

8. Open pumping with sumps and ditches will be allowed provided it does not result in boils, loss of fines,<br />

softening of the ground, or instability of slopes.<br />

9. Install wells or wellpoints, if required, with suitable screens and filters so that continuous pumping of fines<br />

does not occur. Arrange discharge to facilitate collection of samples by the Owner. During normal<br />

pumping and upon development of wells, levels of fine sand or silt in the discharge water shall not exceed<br />

5 ppm. Install sand tester on discharge of each pump during testing to verify that levels are not exceeded.<br />

10. Control grading around excavations to prevent surface water from flowing into excavation areas.<br />

11. No additional payment will be made for any supplemental measures to control seepage, groundwater, or<br />

artesian head.<br />

B. Design:<br />

1. Designate and obtain the services of a qualified dewatering specialist to provide dewatering plan as may be<br />

necessary to complete the Work.<br />

2. Contractor shall be responsible for the accuracy of the drawings, design data, and operational records<br />

required.<br />

3. Contractor shall be responsible for the design, installation, operation, maintenance, and any failure of any<br />

component of the system.<br />

C. Damages:<br />

1. Contractor shall be responsible for and shall repair any damage to work in place, other contractor’s<br />

equipment, utilities, residences, highways, roads, railroads, private and municipal well systems, adjacent<br />

structures, natural resources, habitat, existing wells, and the excavation. Contractor responsibility shall also<br />

include, damage to the bottom due to heave and including but not limited to, removal and pumping out of<br />

the excavated area that may result from Contractor’s negligence, inadequate or improper design and<br />

operation of the dewatering system, and any mechanical or electrical failure of the dewatering system.<br />

2. Remove subgrade materials rendered unsatisfactory by excessive wetting and replace with approved<br />

backfill material at no additional cost to the Owner.<br />

D. Maintaining Excavation in Dewatering Condition:<br />

1. Dewatering shall be a continuous operation. Interruptions due to power outages or any other reason will not<br />

be permitted.<br />

2. Continuously maintain excavation in a dry condition with positive dewatering methods during preparation<br />

of subgrade, installation of pipe, and construction of structures until the critical period of construction or<br />

backfill is completed to prevent damage of subgrade support, piping, structure, side slopes, or adjacent<br />

facilities from flotation or other hydrostatic pressure imbalance.<br />

3. Provide standby equipment on site, installed, wired, and available for immediate operation if required to<br />

maintain dewatering on a continuous basis in the event any part of the system becomes inadequate or fails.<br />

If dewatering requirements are not satisfied due to inadequacy or failure of dewatering system, perform<br />

such work as may be required to restore damaged structures and foundation soils at no additional cost to<br />

Owner.<br />

4. System maintenance shall include but not be limited to 24-hour supervision by personnel skilled in the<br />

operation, maintenance, and replacement of system components and any other work required to maintain<br />

excavation in dewatered condition.<br />

E. System Removal: Upon completion of the work, remove dewatering equipment from the site, including related<br />

temporary electrical service.<br />

F. Wells shall be removed or cut off a minimum of 3 feet below final ground surface, capped, and abandoned in<br />

accordance with regulations by agencies having jurisdiction.<br />

3.3 TOPSOIL EXCAVATION<br />

02300-6<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. Cut heavy growths of grass from areas before stripping and remove cuttings with remainder of cleared vegetative<br />

material.<br />

B. Strip topsoil to a depth of not less than 6 inches from areas that are to be filled, excavated, landscaped, or<br />

re-graded to such depth that it prevents intermingling with underlying subsoil or questionable material.<br />

C. Stockpile topsoil in storage piles in areas shown on The Drawings or where directed by Owner. Construct storage<br />

piles to freely drain surface water. Cover storage piles as required to prevent windblown dust. Dispose of<br />

unsuitable topsoil as specified for waste material, unless otherwise specified by Owner. Remove excess topsoil<br />

from site unless specifically noted otherwise on the Drawings.<br />

3.4 GENERAL EXCAVATION<br />

A. Classification of Excavation: The Contractor shall assure himself by site investigation or other necessary means<br />

that he is familiar with the type, quantity, quality, and character of excavation work to be performed. Excavation<br />

shall be considered unclassified excavation, except as indicated in the Contract Documents.<br />

B. When performing grading operations during periods of wet weather, provide adequate dewatering, drainage and<br />

ground water management to control moisture of soils.<br />

C. Shore, brace, and drain excavations as necessary to maintain excavation as safe, secure, and free of water at all<br />

times.<br />

D. Excavate building areas to line and grade as shown on the Drawings being careful not to over excavate beyond<br />

elevations needed for building subgrades.<br />

E. Place satisfactory excavated material into project fill areas.<br />

F. Unsatisfactory excavated material shall be disposed of in manner and location that is acceptable to Owner and<br />

local governing agencies. The Contractor shall be responsible for the disposal of concrete, asphalt concrete, soils,<br />

spoils, etc., that must be exported from the site to construct the project in accordance with the requirements of the<br />

plans and specifications at no additional cost to the Owner. Individuals, facilities, agencies, etc., may require<br />

analytical testing and other assessments of these materials to determine if these materials are acceptable. The<br />

contractor shall be responsible for performing the tests, assessments, etc., to determine the appropriate method of<br />

disposal.<br />

G. Perform excavation using capable, well-maintained equipment and methods acceptable to Owner and local<br />

governing agencies.<br />

Formatted: Bullets and Numbering<br />

Deleted: <br />

Formatted: Highlight<br />

3.5 ROCK EXCAVATION<br />

A. Rock excavation is specified in Section 02318. (Not Used)<br />

3.6 TRENCHING EXCAVATION FOR UTILITIES<br />

A. All trenching, filling, and compaction shall comply with the requirements of the plans, specifications, and the<br />

governing agency, whichever is most stringent.<br />

Formatted: Bullets and Numbering<br />

B. Trench excavation, preparation and backfill shall be conducted in accordance with the requirements of ASTM<br />

D2321, these specifications, and the drawings, whichever is most stringent.<br />

C. Contact local utility companies before excavation begins. Dig trench at proper width and depth for laying pipe,<br />

conduit, or cable. Cut trench banks vertical, if possible, and remove stones from bottom of trench as necessary to<br />

avoid point-bearing. Over-excavate wet or unstable soil, if encountered, from trench bottom as necessary to<br />

provide suitable base for continuous and uniform bedding. Replace over-excavation with satisfactory material and<br />

dispose of unsatisfactory material.<br />

02300-7<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. Trench excavation sidewalls shall be sloped, shored, sheeted, braced, or otherwise supported by means of<br />

sufficient strength to protect workmen in accordance with applicable rules and regulations established for<br />

construction by the Department of Labor, Occupational Safety and Health Administration (OSHA), and by local<br />

ordinances. Lateral travel distance to exit ladder or steps shall not be greater than 25 feet in trenches 4 feet or<br />

deeper.<br />

E. Perform trench excavation as indicated on the Drawings for specified depths. During excavation, stockpile<br />

materials suitable for backfilling in orderly manner far enough from bank of trench to avoid overloading, slides, or<br />

cave-ins.<br />

F. Remove excavated materials not required or not satisfactory as backfill or embankments and waste off-site or at<br />

on-site locations approved by the Owner and in accordance with governing regulations. Dispose of structures<br />

discovered during excavation as specified in Section 02220.<br />

G. Prevent surface water from flowing into trenches or other excavations by temporary grading or other methods, as<br />

required. Remove accumulated water in trenches and other excavations as specified.<br />

H. Open cut excavation with trenching machine or backhoe. Where machines other than ladder or wheel-type<br />

trenching machines are used, do not use clods for backfill.<br />

I. Accurately grade trench bottom to provide uniform bearing and support for each section of pipe on bedding<br />

material at every point along entire length except where necessary to excavate for bell holes, proper sealing of pipe<br />

joints, or other required connections. Dig bell holes and depressions for joints after trench bottom has been<br />

graded. Dig no deeper, longer, or wider than needed to make joint connection properly.<br />

J. The width of the trench shall provide a minimum clearance of 8 inches between the sidewalls of the pipe and the<br />

trench, as necessary to provide a trench width that is 12 inches greater than 1.25 times the outside diameter of the<br />

pipe, or to a width sufficient to ensure working room to properly and safely place and compact haunching and<br />

other embedment materials, whichever is greater<br />

K. Trench depth requirements measured from finished grade or paved surface shall meet the following requirements<br />

or applicable codes and ordinances, whichever is more stringent:<br />

1. Water Mains: 30 inches to top of pipe barrel or 6 inches below frost line, established by local building<br />

official, whichever is deeper.<br />

2. Sanitary Sewer: Elevations and grades as indicated on the drawings and as specified in Section 02535.<br />

3. Storm Sewer: Elevations and grades as indicated on the Drawings.<br />

4. Electrical Conduits: 24 inches minimum to top of conduit or as required by NEC 300-5, NEC 710-36<br />

codes, or local utility company requirements, whichever is deeper.<br />

5. TV Conduits: 18 inches minimum to top of conduit or as required by local utility company, whichever is<br />

deeper.<br />

6. Telephone Conduits: 18 inches minimum to top of conduit, or as required by local utility company,<br />

whichever is deeper.<br />

7. Gas Mains and Service: 30 inches minimum to top of pipe, or as required by local utility company,<br />

whichever is deeper.<br />

3.7 SUBGRADE PREPARATION<br />

A. Over-excavation, Scarification and Compaction: Areas exposed by excavation or stripping and on which subgrade<br />

preparations are to be performed shall be scarified to minimum depth of 8 inches and compacted as specified<br />

hereinafter.<br />

1. The subgrade soils for new interior slabs on grade, new foundations inside the building, and new<br />

foundations, sidewalks and ramps outside the building shall be prepared in accordance with the Foundation<br />

Subsurface Preparation note.<br />

2. The subgrade for areas to receive fill or pavements outside the existing building pad preparation limits<br />

identified in the Foundation Subsurface Preparation shall be prepared by over-excavation to a depth of 12<br />

inches below preconstruction site grades, or the bottom of the new aggregate base section, whichever is<br />

greater. The subgrade preparation performed for the new pavements shall extend a minimum of 5 feet<br />

02300-8<br />

Deleted: Trench width below top of<br />

pipe shall not be less than 12 inches nor<br />

more than 18 inches wider than outside<br />

surface of pipe or conduit that is to be<br />

installed to designated elevations and<br />

grades. Other trench width for pipe,<br />

conduit, or cable shall be least practical<br />

width that will allow for proper<br />

compaction of trench backfill.<br />

Formatted: Bullets and Numbering<br />

Deleted: the<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


eyond the edges of the planned improvements, or up to the existing adjacent improvements to remain,<br />

whichever occurs first. The exposed soils after over-excavation shall be prepared by scarification to a<br />

depth of 12 inches, moisture conditioned to between two (2) and five (5) percent above optimum and<br />

compaction to at least 95 percent of the maximum dry density as determined by ASTM D1557. Any soft or<br />

unstable areas identified during compaction of the bottom of the over-excavation shall be removed and<br />

compacted as engineered fill. Prior to placement of subsequent lifts of fill, proof rolling shall be performed<br />

to confirm stable conditions.<br />

3. After preparation, the finished subgrade soils for all improvements shall be kept within the moisture<br />

content requirements until the section is covered with aggregate base.<br />

B. Proofrolling: Subgrades shall be proofrolled to detect areas of insufficient compaction and soft pocket, or areas of<br />

excess yielding. Proofrolling shall be accomplished by making minimum of 2 complete passes with fully-loaded<br />

tandem-axle dump truck with a minimum weight of 20 tons, or approved equal, in each of 2 perpendicular<br />

directions while under the supervision and direction of the Construction Testing Laboratory. Limit vehicle speed<br />

to 3 mph. Areas of failure such as soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as<br />

determined by the CTL, shall be excavated and recompacted as specified herein. Continual failure areas shall be<br />

stabilized in accordance with Section 02340 at no additional cost to Owner. Subgrade exposed longer than 48<br />

hours or on which precipitation has occurred shall be re-proofrolled.<br />

3.8 FILLING<br />

A. Fill areas to contours and elevations shown on the Drawings with materials deemed satisfactory.<br />

B. Place fills in continuous lifts specified herein.<br />

C. Fill within proposed building subgrade, paving subgrade, and outparcel subgrades shall not contain rock or stone<br />

greater than 3 inches in any dimension.<br />

D. Fill materials used in preparation of subgrade shall be conditioned to within two (2) and five (5) percent above<br />

optimum for clayey subgrade and between optimum and three (3) percent above optimum for granular soils,<br />

placed in lifts or layers not to exceed 8 inches loose measure and compacted as specified hereinafter.<br />

E. Material imported from off-site shall have an R-value equal to or above pavement design subgrade R-value<br />

indicated on The Drawings.<br />

F. The limits of the subgrade preparation for new slabs, sidewalks, ramps and footings shall be as indicated in the<br />

“Foundation Subsurface Preparation.” The subgrade preparation performed for new pavements shall extend a<br />

minimum of 5 feet beyond the edges of the planned improvements, or up to the existing adjacent improvements to<br />

remain, whichever occurs first.<br />

G. Prepare building area subgrade pad in strict accordance with "Foundation Subsurface Preparation" as shown on the<br />

Drawings. The Foundation Subsurface Preparation provisions shall take precedence over the provisions of this<br />

section whenever duplication or conflict occurs.<br />

3.9 ROCK FILL<br />

A. Rock fills shall not be allowed for the project.<br />

3.10 PIPE BEDDING<br />

A. At a minimum, the pipe bedding shall consist of 4 inches of compacted (95 percent relative compaction, ASTM<br />

D1557) select sand with a minimum sand equivalent of 30 and meeting the following requirements: 100 percent<br />

passing the ¼ inch sieve, a minimum of 90 percent passing the No. 4 sieve, and not more than 10 percent passing<br />

the No. 200 sieve. The bedding shall be placed in maximum 6-inch thick lifts and compacted to a minimum<br />

relative compaction of 95 percent (ASTM D1557).<br />

02300-9<br />

Deleted: Scarification and<br />

Compaction: Areas exposed by<br />

excavation or stripping and on which<br />

subgrade preparations are to be<br />

performed shall be scarified to minimum<br />

depth of 8 inches and compacted as<br />

specified hereinafter. <br />

Deleted: 6<br />

Deleted: Unless otherwise<br />

specified for rock fill, rock or stone less<br />

than 6-inches in largest dimension may<br />

be used in fill below structures, paving,<br />

outparcels, and graded areas, up to 24<br />

inches below surface of proposed<br />

subgrade or finish grade of graded areas<br />

when mixed with satisfactory material.<br />

Rock or stone less than 2 inches in largest<br />

dimension may be used in fill within the<br />

upper 24 inches of proposed subgrade or<br />

finish grade of graded areas when mixed<br />

with satisfactory material.<br />

Formatted: Bullets and Numbering<br />

Deleted: CBR or LBR<br />

Deleted: CBR or LBR<br />

Deleted:<br />

Deleted: Building area subgrade pad<br />

Deleted: that portion of site directly<br />

beneath and 5 feet beyond building and<br />

appurtenances, including limits of future<br />

building expansion areas as shown on the<br />

Drawings<br />

Deleted: [EDITOR NOTE: Although<br />

the Pad Prep Notes takes precedents over<br />

the specifications, conflicts between the<br />

plans and specifications are unacceptable.<br />

Edit the specifications to clearly<br />

coordinate with the Pad Prep Note as<br />

shown on the drawings.]<br />

Formatted: Bullets and Numbering<br />

Deleted: Rock fill shall include onsite<br />

excavated material classified as rock<br />

excavation as specified in Section 02318.<br />

Rock fill may be utilized in fill up to 48<br />

inches below top of subgrade or finish<br />

grade of graded areas outside the<br />

proposed building, paving, and outparcell<br />

subgrade areas unless otherwise<br />

permitted in higher elevations by the<br />

CTL. Rock fill shall consist of rock<br />

having a maximum dimension not greater<br />

than 12 inches in any dimension. Rock<br />

fill shall be placed in successive<br />

horizontal layers of loose material having<br />

a thickness of approximately the<br />

maximum size of the larger rock in the<br />

lift, but not greater than 12 inches. Each<br />

layer of material shall be spread<br />

uniformly, completely saturated, and ... [1]<br />

Formatted: Bullets and Numbering<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Excavate trenches for pipe or conduit to a minimum of 4 inches below bottom of pipe and to the width as specified<br />

herein. Place 4 inches of bedding material, compact in bottom of trench to a minimum of 95 percent relative<br />

compaction (based on ASTM D1557), and shape to conform to lower portion of pipe barrel.<br />

C. Place geotextile fabric where specified on the Drawings and in accordance with Section 02340.<br />

3.11 TRENCH BACKFILLING<br />

A. Materials used for trench backfill shall comply with requirements as specified herein.<br />

B. Backfill and compact bedding, haunches, initial fills, and final backfill in accordance with fill and compaction<br />

requirements of these specifications, and the drawings, whichever is most stringent.<br />

C. Do not backfill trenches until required tests are performed and utility systems comply with and are accepted by<br />

applicable governing authorities.<br />

D. Backfill trenches to contours and elevations shown on the Drawings.<br />

Deleted: Excavate trenches for pipe<br />

or conduit to 4 inches below bottom of<br />

pipe and to the width as specified herein.<br />

Place 4 inches of bedding material,<br />

compact in bottom of trench, and shape to<br />

conform to lower portion of pipe barrel.<br />

Deleted: as<br />

Formatted: Bullets and Numbering<br />

Deleted: Backfill and compact in<br />

accordance with fill and compaction<br />

requirements in ASTM D2321 unless<br />

otherwise shown on the drawings. <br />

E. Do not backfill over porous, wet, frozen, or spongy subgrade surfaces.<br />

3.12 BORINGS AND CASINGS UNDER ROADS, HIGHWAYS, AND RAILROAD CROSSINGS<br />

A. When indicated by the Drawings, street, road, highway, or railroad crossings for utility mains installed by jacking<br />

and boring method shall be in accordance with area specifications and governing authorities.<br />

B. Excavation of approach pits and trenches within right-of-way of street, road, highway, or railroad shall be of<br />

sufficient distance from paving or railroad tracks to permit traffic to pass without interference. Tamp backfill for<br />

approach pits and trenches within right-of-way in layers not greater than 6-inches thick for entire length and depth<br />

of trench or pit. Compact backfill to 95 percent of maximum density, in accordance with ASTM D1557 obtained<br />

between two (2) and five (5) percent above optimum moisture content. Mechanical tampers may be used after<br />

cover of 6 inches has been obtained over top of barrel of pipe.<br />

C. Accomplish boring operation using commercial type boring rig. Bore hole to proper alignment and grade. Bore<br />

hole shall be within 2 inches of same diameter as largest outside joint diameter of pipe installed. Install pipe in<br />

hole immediately after bore has been made and in no instance shall hole be left unattended while open.<br />

Deleted: 98 percent of maximum<br />

density in accordance with ASTM D698,<br />

(or<br />

Deleted: )<br />

Deleted: at optimum moisture as<br />

determined by AASHTO T180<br />

D. In event subsurface operations result in failure or damage to pavement or railroad tracks within 1 year of<br />

construction, make necessary repairs to pavement or railroad tracks. If paving cracks on either side of pipe line or<br />

is otherwise disturbed or broken due to construction operations, repair or replace disturbed or broken area.<br />

E. Clean, prime, and line interior and exterior of casing pipe with two coats of asphalt coating in accordance with and<br />

governing authorities.<br />

F. Butt weld steel casing. Welds shall be full penetration single butt-welds in accordance with AWWA C206.<br />

G. Install casing and utility pipe with end seals, vent pipe, and other special equipment in accordance with area<br />

specifications and governing authorities.<br />

3.13 COMPACTION<br />

A. Compact as follows:<br />

Location<br />

Bedding, Haunches, Initial Backfill in Trenches 95<br />

Fill and Final Trench Backfill 90 to 95<br />

Subgrade Below New Slabs, Ramps, Sidewalks and Footings 90 to 95<br />

02300-10<br />

Percent of Maximum Laboratory Density<br />

ASTM D1557<br />

Deleted: ASTM D698<br />

Deleted: Subgrade & Fill below<br />

Structures, Pavement and Outparcels<br />

Deleted: 98<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


Upper 12 inches of Subgrade Below Pavements 95<br />

Aggregate Base Below Slabs, Sidewalks, Ramps, and Pavements 95<br />

B. Maintain moisture content between two (2) and five (5) percent above optimum moisture content of onsite clayey<br />

fill materials and between optimum and three (3) percent above optimum for granular soils to attain required<br />

compaction density<br />

C. Maintain moisture content between optimum and three (3) percent above optimum moisture content for imported,<br />

non-expansive soils or aggregate base materials.<br />

D. All trench subgrade soils which are disturbed during excavation, such as by accidental over-excavation of the<br />

trench bottom, or by excavation equipment with cutting teeth, shall be compacted to a minimum of 95 percent<br />

relative compaction (ASTM D1557) prior to placement of bedding material.<br />

Deleted: <br />

Deleted: & Fill in All other Areas<br />

Deleted: 95<br />

Deleted: 2<br />

Deleted: of<br />

Deleted: not less than 1 percent below<br />

and not more than 3<br />

Deleted: .<br />

Formatted: Bullets and Numbering<br />

E. Exercise proper caution when compacting immediately over top of pipes or conduits. Water jetting or flooding is<br />

not permitted as method of compaction.<br />

F. Corrective Measures for Non-Complying Compaction: Remove and recompact deficient areas until proper<br />

compaction is obtained. Continual failure areas shall be stabilized in accordance with Section 02340 at no<br />

additional cost to Owner.<br />

3.14 MAINTENANCE OF SUBGRADE<br />

A. Verify finished subgrades to ensure proper elevation and conditions for construction above subgrade.<br />

B. Maintain moisture content of between two (2) and five (5) percent above optimum moisture content for clayey<br />

subgrade materials and between optimum and three (3) percent above optimum for granular soils to attain required<br />

compaction density. Subgrade soils which are not maintained within the required moisture content range shall be<br />

conditioned as necessary to achieve the required moisture conditions within the upper 12 inches of final subgrade<br />

prior to placement of overlying aggregate base or subbase materials.<br />

Formatted: Bullets and Numbering<br />

C. Protect subgrade from excessive wheel loading during construction, including concrete trucks, dump trucks, and<br />

other construction equipment.<br />

D. Remove areas of finished subgrade found to have insufficient compaction density to depth necessary and replace<br />

in manner that will comply with compaction requirements by use of material with R-value equal to or better than<br />

design R-value of 12. Surface of subgrade after compaction shall be firm, uniform, smooth, stable, and true to<br />

grade and cross-section.<br />

Deleted: CBR or LBR<br />

Deleted: that specified on the drawings<br />

E. Construct temporary ditches and perform such grading as necessary to maintain positive drainage away from<br />

subgrade at all times.<br />

F. If the subgrade is prepared, and the disturbed by equipment, workers, weather or other sources, the exposed<br />

subgrade shall be tested to verify adequate compaction and proofrolled. If adequate compaction, moisture and<br />

stability are not verified, the disturbed subgrade shall be over-excavated, scarified, moisture conditioned and<br />

compacted as engineered fill, or stabilized to achieve the required compaction and stable subgrade conditions.<br />

These conditions shall be verified by the CTL prior to placement of aggregate base or subbase over the subgrade.<br />

3.15 BORROW AND SPOIL SITES<br />

A. Comply with NPDES and local erosion control permitting requirements for any and all on-site and off-site,<br />

disturbed spoil and borrow areas. Upon completion of spoil or borrow operations, clean up spoil or borrow areas<br />

in a neat and reasonable manner to the satisfaction of Owner or off-site property owner, if applicable.<br />

3.16 FINISH GRADING<br />

02300-11<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. Check grading of building subgrades by string line from grade stakes (blue tops) set at not more than 50-foot<br />

centers. Allowable tolerance shall be plus or minus 0.10 feet from plan grade. Provide engineering and field<br />

staking as necessary for verification of lines, grades, and elevations.<br />

B. Grade areas where finish grade elevations or contours are indicated on the Drawings, other than paved areas,<br />

outparcels, and buildings, including excavated areas, filled and transition areas, and landscaped areas. Graded<br />

areas shall be uniform and smooth, free from rock, debris, or irregular surface changes. Ground surfaces shall<br />

vary uniformly between indicated elevations. Grade finished ditches to allow for proper drainage without ponding<br />

and in manner that will minimize erosion potential. For topsoil, sodding, and seeding requirements refer to<br />

Section 02900.<br />

C. Correct settled and eroded areas within 1 year after date of completion at no additional expense to Owner. Bring<br />

grades to proper elevation.<br />

3.17 QUALITY CONTROL TESTING AND INSPECTION<br />

A. Responsibilities: Unless otherwise specified, the quality assurance testing and inspection specified below will be<br />

conducted by the Owner’s Construction Testing Laboratory (CTL) at no cost to the Contractor in accordance with<br />

Section 01458. The Contractor shall perform additional testing as considered necessary by the Contractor for<br />

assurance of quality control. Retesting required as a result of failed initial tests shall be at the Contractor’s<br />

expense.<br />

B. Field testing, frequency, and methods may vary as determined by and between the Owner and the CTL.<br />

C. Work shall be performed by a Special Inspector – Technical I unless specified otherwise. Report of testing and<br />

inspection results shall be made upon the completion of testing.<br />

Deleted: control<br />

Deleted: The Contractor shall perform<br />

additional quality control testing and<br />

inspections as considered necessary.<br />

Deleted: re<br />

D. Classification of Materials: Perform test for classification of materials used and encountered during construction<br />

in accordance with ASTM D2488 and ASTM D2487.<br />

E. Laboratory Testing Of Materials: Perform laboratory testing of materials (Proctor, Sieve Analysis, Atterberg<br />

Limits, Expansion Index Test, etc.) as specified.<br />

Deleted: Consolidation<br />

F. Proofrolling: Document and explain proofrolling inspection procedures and results in the laboratory inspection<br />

report.<br />

G. Field Density Tests.<br />

1. Building Subgrade Areas, Including 5'-0" Outside of Slabs on Grade within the Building Pad Preparation<br />

Limits: In cut areas, not less than 1 compaction test for every 2,500 sq. ft. In fill areas, same rate of testing<br />

for each 8-inch lift, measured loose.<br />

2. Paving Areas and other Areas of Construction Exclusive of Building Subgrade: In cut areas, not less than 1<br />

compaction test for every 10,000 sq. ft. In fill areas, same rate of testing for each 8-inch lift, measured<br />

loose.<br />

3. Outparcels: In cut areas, not less than 1 compaction test for every 2,500 sq. ft. In fill areas, same rate of<br />

testing for each 8-inch lift, measured loose.<br />

4. Utility Trench Backfill: Intervals not exceeding 200-feet of trench for first and every other 8-inch lift of<br />

compacted trench backfill.<br />

5. Test Method: In-place nuclear density, ASTM D6938.<br />

6. Moisture and Density tests on top of slab, footing or paving subgrade shall be performed within 48 hours<br />

prior to placement of overlying materials. If inclement weather occurs after testing, retest prior to<br />

placement of overlying materials.<br />

H. Observation and Inspection:<br />

1. Observe all subgrades/excavation bases below footings and slabs and verify design bearing capacity is<br />

achieved as required. Work shall be preformed by a Special Inspector – Technical II.<br />

2. Observe and document presence of groundwater within excavations.<br />

02300-12<br />

Deleted: Exterior Building Lines<br />

Deleted: building<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02300-13<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


Page 9: [1] Deleted<br />

10/6/2011 11:28:00 AM<br />

Rock fill shall include on-site excavated material classified as rock excavation as specified in Section<br />

02318. Rock fill may be utilized in fill up to 48 inches below top of subgrade or finish grade of<br />

graded areas outside the proposed building, paving, and outparcell subgrade areas unless<br />

otherwise permitted in higher elevations by the CTL. Rock fill shall consist of rock having a<br />

maximum dimension not greater than 12 inches in any dimension. Rock fill shall be placed in<br />

successive horizontal layers of loose material having a thickness of approximately the maximum<br />

size of the larger rock in the lift, but not greater than 12 inches. Each layer of material shall be<br />

spread uniformly, completely saturated, and compacted. Shot rock shall not be dumped into<br />

place, but shall be distributed in horizontal lifts by blading and dozing in such a manner as to<br />

ensure proper placement into final position in the embankment. Voids shall be filled with finer<br />

material including shot rock fines and limited soil fines during the spreading operation.<br />

Successive layers shall not be placed until all voids of the current lift are filled and the lift is<br />

compacted. Each successive layer of material shall adequately bond to the material on which it is<br />

placed. Compaction shall be accomplished with vibratory compactors, heavy rubber-tired rollers,<br />

or steel-wheeled rollers. Compaction shall be by uniform passes of compaction equipment in<br />

sufficient number of passes, but not less than two passes, such that no further consolidation is<br />

evident as determined by the CTL.


UniSpec – Civil (Master Site Specifications) 090109<br />

SECTION 02340 (31 3200) - SOIL STABILIZATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Excavation, treatment, and backfilling of subgrade for lime, cement, fly ash, or bridge lift stabilization.<br />

2. Geotextile fabric and geogrid for stabilization of subgrade.<br />

B. Related Requirements:<br />

1. Section 02300 - Earthwork<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C150 - Portland Cement.<br />

2. ASTM C618 - Fly Ash and Raw or Calcined Natural Pozzolan for use as a Mineral Admixture in Portland<br />

Cement Concrete.<br />

3. ASTM C977 - Quicklime and Hydrated Lime for Soil Stabilization.<br />

4. ASTM D1633 - Compressive Strength of Molded Soil-Cement Cylinders.<br />

C. American Association of State Highway and Transportation Officials (AASHTO):<br />

1. AASHTO M216 - Lime for Soil Stabilization.<br />

D. National Lime Association (NLA):<br />

1. NLA Bulletin 326 - Lime Stabilization Construction Manual.<br />

E. State Department of Transportation (DOT):<br />

1. Standard Specifications for Construction and Materials.<br />

1.3 ENVIRONMENTAL REQUIREMENTS<br />

A. Do not install mixed materials in wind in excess of 10 mph or when temperature is below 40 degrees Fahrenheit.<br />

1.4 SUBMITTALS<br />

A. Submit 30-pound sample of each material to be used at the site in airtight containers to the Construction Testing<br />

Laboratory (CTL) or submit gradation and certification of material that is to be used to the CTL for review.<br />

B. Submit name of each materials supplier and specific type and source of each material. Obtain approval of Owner<br />

prior to change in source.<br />

C. Submit mix designs, materials mix ratio, and laboratory test data to the Civil Engineering Consultant of Record 4<br />

weeks prior to beginning stabilization activities. Certify materials and mix ratios will achieve the specified requirements<br />

as indicated in the Construction Documents or as specified by state and local agencies for soil stabilization<br />

if not stated in the Construction Documents.<br />

D. Submit approved mix designs, materials mix ratio, and laboratory test data to the CTL prior to commencing stabilization<br />

activities.<br />

1.5 QUALITY ASSURANCE<br />

02340-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Perform work in accordance with state and local standards in conjunction with requirements specified herein.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Provide products from one of the following manufacturers as specified in the Materials paragraph below:<br />

1. TenCate Geosynthetics North America (Mirafi), Pendergrass, GA., (706) 693-2226, www.tencate.com<br />

2. Hanes Geo Components (WEBTEC), Winston Salem, NC. (336) 747-1600, www.hanesgeo.com<br />

3. Tensar International Corp., Atlanta, GA. (888) 828-5126, www.tensarcorp.com<br />

4. Thrace-LINQ Inc., Summerville, SC (843) 873-5800, www.thracelinq.com<br />

5. DuPont (Typar). Summerville, SC (843) 832-6860, www.typargeo.com<br />

6. Synteen Technical Fabrics, Lancaster, SC (800) 796-8336, www.synteen.com<br />

2.2 MATERIALS<br />

A. Soil Treatment Materials:<br />

1. Hydrated Lime: ASTM C977 or AASHTO M216.<br />

2. Portland Cement: ASTM C150, Type I.<br />

3. Fly Ash: ASTM C618.<br />

B. Aggregate:<br />

1. Coarse Aggregate: Crushed carbonate, crushed gravel, crushed air-cooled slag, granulated slag, a mixture<br />

of crushed and granulated slag, or other types of suitable material meeting the following gradation requirements:<br />

Sieve Size Percent Passing<br />

2 inches 100<br />

1 inch 70-100<br />

3/4 inch 50-90<br />

No. 4 30-60<br />

No. 30 7-30<br />

No. 200 0-5<br />

2. Fine Aggregate: Sand – Natural river or bank sand; washed; free of silt, clay, loam, friable or soluble materials,<br />

and organic matter meeting the following gradation requirements:<br />

C. Subsoil: Existing to be reused.<br />

Sieve Size Percent Passing<br />

No. 4 90-100<br />

No. 50 7-40<br />

No. 200 0-5<br />

D. Bridge Lift Material: Surge stone, granular fill, or shot rock fill.<br />

2.3 ACCESSORIES<br />

A. Curing Seal: Asphalt Emulsion Primer.<br />

B. Geotextile Fabric for Stabilization: Provide one of the following:<br />

1. Mirafi HP 370 or HP 570, by TenCate.<br />

2. Mirafi 140N, by TenCate<br />

3. SF40 or SF65, by DuPont.<br />

4. GTF-200 or 300, by Thrace-LINQ.<br />

5. TerraTex HD, by Hanes.<br />

02340-2<br />

Formatted: Bullets and Numbering<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


C. Geogrid for Stabilization: Provide one of the following:<br />

1. Biaxial Geogrid Type 1 (formerly BX 1100), by Tensar.<br />

2. Biaxial Geogrid Type 2 (formerly BX 1200), by Tensar.<br />

3. Mirafi BXG 11, by TenCate.<br />

4. Mirafi BXG 12, by TenCate.<br />

5. SF 11, by Synteen.<br />

6. SF 12, by Synteen<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Obtain approval of mix design before proceeding with placement.<br />

B. Start stabilization only when weather and soil conditions are favorable for successful application of proposed material.<br />

C. Proofroll subgrade to identify areas in need of stabilization.<br />

3.2 EQUIPMENT<br />

A. Perform operations using suitable, well maintained equipment capable of excavating subsoil, mixing and placing<br />

materials, wetting, consolidating, and compacting of material.<br />

3.3 EXCAVATION<br />

A. Excavate subsoil to depth sufficient to accommodate soil stabilization.<br />

B. Remove lumped subsoil, boulders, and rock that interfere with achieving uniform subsoil conditions.<br />

C. Do not excavate within normal 45 degree bearing splay of any foundation.<br />

D. Notify Construction Manager of unexpected subsurface conditions. Discontinue affected work in area until notified<br />

to resume work.<br />

E. Correct areas over-excavated in accordance with Section 02300.<br />

F. Remove excess excavated material from site.<br />

3.4 GEOTEXTILE FABRIC AND/OR GEOGRID<br />

A. Place geotextile fabric and/or geogrid over subsoil surface, lap edges and ends in accordance with manufacturer’s<br />

recommendations in those areas that are shown on Construction Drawings or in those areas that need additional<br />

stabilization prior to placement of base course. Bridge lift sections, if used, require the use of geotextile fabric such<br />

as Mirafi 140N or equal to fully encapsulate the rock section prior to placement of fill.<br />

B. Place geotextile fabric and/or geogrid in accordance with manufacturer's recommendations.<br />

Deleted: may<br />

Deleted: and/or geogrid for stabilization<br />

3.5 SOIL TREATMENT AND BACKFILLING<br />

A. Lime Stabilized Subgrade: Where indicated on Construction Drawings or as required after continual failure, treat<br />

prepared subgrade with hydrated lime in accordance with state highway department specifications.<br />

B. Cement Stabilized Subgrade: Where indicated on Construction Drawings or as required after continual failure,<br />

treat prepared subgrade with portland cement in accordance with state highway department specifications.<br />

02340-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


C. Fly Ash Stabilized Subgrade: Where indicated on Construction Drawings or as required after continual failure,<br />

treat prepared subgrade with fly ash in accordance with state highway department specifications.<br />

D. Bridge Lifts: Where indicated on Construction Drawings or as required after continual failure, or to address areas<br />

of unstable soils, over-excavate unstable soils and replace with a bridge lift of open-graded rock encapsulated in a<br />

geotextile filter fabric (Mirafi 140N). Where well-graded sand and gravel materials such as aggregate base are<br />

used for the bridge material, encapsulation with filter fabric will not be required. Bridging over existing soils shall<br />

be acceptable only when approved in writing by the Owner. Place geotextile fabric or geogrid over existing soils to<br />

be bridged. The geotextile fabric or geogrid selected shall be appropriate for the bridge lift material being placed<br />

and the degree of instability of the soil. Place bridge lift over geotextile fabric or geogrid. Where open-graded rock<br />

is used as the bridge lift material, a filter fabric shall fully encase the bridge material. Surge stone and shot rock<br />

will be reviewed by the Owner’s representative on a submittal basis. Where open-graded rock is used for bridge<br />

material, the rock shall be placed in 8 inch maximum lifts and densified by vibrational equipment prior to placement<br />

of subsequent lifts. The Owner and the Owner’s representative shall have sole discretion as to the acceptability<br />

of all submittals.<br />

Deleted: treat prepared subgrade by<br />

application of<br />

Deleted: approved<br />

E. Backfill and compaction of treated subsoil shall be in accordance with Sections 02300.<br />

F. Maintain optimum moisture of mixed materials to attain required stabilization and compaction.<br />

G. Finish subgrade surface in accordance with Section 02300.<br />

H. Remove surplus mix materials from site.<br />

3.6 CURING<br />

A. Immediately following compaction of mix, seal top surface with curing seal.<br />

B. Do not permit traffic for 72 hours after sealing top surface.<br />

3.7 FIELD QUALITY CONTROL<br />

A. Responsibilities: Unless otherwise specified, the quality control tests and inspections specified below will be conducted<br />

by the Owner’s Construction Testing Laboratory (CTL) at no cost to the Contractor in accordance with<br />

Section 01458. The Contractor shall perform additional testing or inspection as considered necessary by the Contractor<br />

for assurance of quality control.<br />

B. Unconfined compression tests on lime, fly ash, or portland cement treated mixture shall be conducted by the CTL<br />

in accordance with ASTM D1633. Mold three specimens for each mix design submitted by the Contractor to verify<br />

mix design meets the specified requirements. Cure each specimen at a constant moisture content and temperature<br />

for 28 days. Test for unconfined compressive strength and compare to the specified design strength. Perform<br />

test minimum of three weeks prior to proposed stabilization activities.<br />

C. Field Density: Field in-place density shall be determined as specified in Section 02300.<br />

D. If tests indicate work does not meet specified requirements, Contractor shall remove and replace work. Corrected<br />

areas shall be retested by the CTL.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

02340-4<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec II 030510<br />

SECTION 02361 – TERMITE CONTROL<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Soil treatment for termite control.<br />

2. Application below grade and at interior and exterior foundation perimeter.<br />

1.2 REFERENCES<br />

A. Environmental Protection Agency (EPA):<br />

1. EPA - Federal Insecticide, Fungicide and Rodenticide Act.<br />

1.3 DEFINITIONS<br />

A. Termiticide: EPA-Registered product complying with requirements of authorities having jurisdiction, in a soluble<br />

or emulsible, concentration that dilutes with water or foaming agent, and formulated to prevent termite infestation.<br />

1.4 QUALITY ASSURANCE<br />

A. Applicator Qualifications: Company specializing in performing the Work of this Section and licensed in<br />

accordance with regulations of authorities having jurisdiction for application of termiticide.<br />

B. Materials: Provide certification that termiticide is EPA approved and conforms to requirements of authority<br />

having jurisdiction.<br />

C. Regulatory Requirements: Conform to applicable requirements for application licensing and authority to use<br />

termite control chemicals.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Section 01600 - Product Requirements: Transport, handle, store, and protect Products.<br />

B. Deliver Products in manufacturer's original unopened containers with labels intact, identifying Product and<br />

manufacturer, application instructions, and EPA federal registration number.<br />

C. Do not store Products on site. Deliver Products to site at time of application.<br />

1.6 PROJECT CONDITIONS OR SITE CONDITIONS<br />

A. Environmental Requirements: Do not apply termiticide to frozen or wet soils or during rain or snow.<br />

1.7 WARRANTY<br />

A. Submit written warranty signed by termite control applicator and Contractor certifying that applied chemical<br />

termiticide treatment will prevent infestation of subterranean termites.<br />

1. State that application was made at concentration, rates, and methods recommended.<br />

2. State that if subterranean termite activity is discovered during warranty period, Contractor will retreat soil<br />

and repair damage caused by termite infestation at no additional cost to Owner.<br />

B. Cover against invasion or propagation of subterranean termites, damage to building or building contents caused by<br />

termites; repairs to building or building contents so caused.<br />

02361 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Provide for inspection of Work annually; report in writing to Wal-Mart.<br />

D. Warranty Period: 5 years.<br />

1. Owner reserves right to renew warranty for an additional 5 years.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. EPA and local authority having jurisdiction approved chemical termiticide; water based emulsion, uniform<br />

composition, with synthetic dye to permit visual identification of treated soil, bearing Federal registration number<br />

of the EPA.<br />

1. Do not use fuel oil as diluent.<br />

B. Specially formulated to prevent infestation by termites.<br />

2.2 MIX DILUTION<br />

A. Dilute and mix chemical termiticide to manufacturer's published instructions.<br />

PART 3 - EXECUTION<br />

3.1 INSPECTION<br />

A. Examine surfaces and adjacent areas to be treated. Report conditions that may adversely affect satisfactory<br />

execution of Work to Wal-Mart Construction Manager. Do not proceed with Work until unsatisfactory conditions<br />

have been corrected.<br />

1. Verify the soil surfaces are unfrozen, sufficiently dry to absorb termiticide, ready to receive treatment.<br />

B. Beginning of application means acceptance of existing soil conditions.<br />

3.2 PREPARATION<br />

A. Remove foreign matter, loosen, rake, and level soil to be treated, except previously compacted areas under slabs<br />

and foundations.<br />

3.3 APPLICATION<br />

A. Apply termiticide within 12 hours before installation of vapor retarder under slab-on-grade or finish grading<br />

outside foundation walls.<br />

B. Apply termiticide to soil using metered applicator. Apply at rates and concentration recommended by the<br />

chemical manufacturer's written instruction.<br />

C. Apply at the following locations:<br />

1. Under Floor Slabs-On-Grade.<br />

2. Both Sides of Foundation Wall.<br />

3. Exterior Foundation: Apply along outside edge of building.<br />

a. Dig trench 6 inches to 8 inches wide along outside of foundation to minimum depth of 12 inches<br />

and apply termiticide.<br />

b. Mix termiticide with soil as it is being backfilled.<br />

4. Foundation Penetrations.<br />

D. Apply as a coarse spray; provide uniform distribution.<br />

E. Post signs in areas of application to indicate termite treated areas. Remove signs after areas are covered by other<br />

construction.<br />

02361 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


F. Reapply termiticide to areas disturbed by subsequent excavation, landscape grading, or other construction<br />

activities occurring after initial termiticide application.<br />

3.4 CONSTRUCTION<br />

A. Interface with Other Work:<br />

1. Coordinate application of termiticide at foundation perimeter with finish grading and landscaping work to<br />

avoid disturbance of treated soil.<br />

3.5 FIELD QUALITY CONTROL<br />

A. Inspect and test soil areas where termiticide was applied to determine the presence of any remaining termites<br />

before covering with subsequent construction.<br />

B. Reapply termiticide to areas where inspection or testing identifies the presence of termites. Use same termiticide<br />

as for original treatment.<br />

3.6 CLEANING<br />

A. Execute in accordance with termiticide manufacturer’s instructions and current environmental regulations.<br />

END OF SECTION<br />

02361 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


02361 - 4<br />

Walmart SC #5641 – La Habra, CA<br />

PWO – 04/11/11


UniSpec – Civil (Master Site Specifications) 020310<br />

SECTION 02510 (33 1000) - WATER DISTRIBUTION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Site water piping and fittings including domestic potable waterline and fire protection system supply waterline,<br />

valves, and fire hydrants.<br />

B. Related Requirements:<br />

1. Section 02300 – Earthwork: Trenching, backfill, and compaction for utilities.<br />

1.2 REFERENCES<br />

Style Definition: Normal: Justified,<br />

Tabs: -36 pt, Left + 40.5 pt, Left +<br />

67.5 pt, Centered + 90 pt, Centered<br />

+ 112.5 pt, Centered + 126 pt,<br />

Centered + 148.5 pt, Centered +<br />

171 pt, Centered + 180 pt, Centered<br />

+ 193.5 pt, Centered + 216 pt,<br />

Centered + 252 pt, Centered + 288<br />

pt, Centered + 328.5 pt, Centered +<br />

333 pt, Centered + 387 pt,<br />

Centered + 418.5 pt, Centered +<br />

423 pt, Centered<br />

Style Definition: PR2: Tabs: 96.3<br />

pt, Left<br />

Formatted: Left, Tabs: Not at 468<br />

pt<br />

Formatted: Tabs: 468 pt, Left +<br />

495 pt, Right<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Society of Mechanical Engineers (ASME):<br />

1. ASME B 16.22 - Wrought Copper and Copper Alloy Solder Joint Pressure Fittings.<br />

C. ASTM International (ASTM):<br />

1. ASTM B88 - Seamless Copper Water Tube.<br />

2. ASTM D1784 - Rigid Poly (Vinyl Chloride) (PVC) Compounds and Chlorinated Poly (Vinyl Chloride)<br />

(CPVC) Compounds.<br />

3. ASTM D2241 - Poly (Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDR-Series).<br />

4. ASTM D2564 - Poly (Vinyl Chloride) (PVC) Solvent Cement.<br />

5. ASTM D2672 - Poly (Vinyl Chloride) (PVC) Integrally Molded Bell Ends For Solvent - Cemented Pipe<br />

Joints.<br />

6. ASTM D3139 - Joints for Plastic Pressure Pipes using Flexible Elastomeric Seals.<br />

7. ASTM F477 - Elastomeric Gaskets And Lubricant.<br />

8. ASTM F656 - Poly (Vinyl Chloride) (PVC) Cement Primer.<br />

D. American Water Works Association (AWWA):<br />

1. AWWA C104 - Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water.<br />

2. AWWA C105 - Polyethylene Encasement for Ductile Iron Piping for Water and other Liquids.<br />

3. AWWA C116 - Protective Fusion-Bonded Epoxy Coatings for the Interior and Exterior Surfaces of Ductile-<br />

Iron and Gray-Iron Fittings for Watersupply Service.<br />

4. AWWA C151 - Ductile-Iron Pipe, Centrifugally Cast, for Water or Other Liquids.<br />

5. AWWA C153 - Ductile-Iron Compact Fittings for Water Service.<br />

6. AWWA C504 - Rubber-Seated Butterfly Valves.<br />

7. AWWA C509 - Resilient-Seated Gate Valves for Water Supply Service.<br />

8. AWWA C550 - Protective Interior Coatings for Valves And Hydrants.<br />

9. AWWA C600 - Installation of Ductile-Iron Water Mains and Appurtenances.<br />

10. AWWA C605 - Installation of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water.<br />

11. AWWA C651 - Disinfecting Water Mains.<br />

12. AWWA C900 - Polyvinyl Chloride (PVC) Pressure Pipe, 4 Inches Through 12 Inches, for Water Distribution.<br />

1.3 QUALITY ASSURANCE<br />

02510-1<br />

Formatted: Centered<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Formatted: Tabs: 486 pt, Right<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Products, where marked for compliance with code or test standards, shall also mark specific standard as required<br />

in the Contract Documents.<br />

B. Perform installation in accordance with utility company or municipality requirements.<br />

C. Valves: Mark manufacturer's name and pressure rating on valve body.<br />

D. Perform disinfection of potable lines in accordance with AWWA C651.<br />

1.4 SUBMITTALS<br />

A. Furnish 1 copy of results of meter test and hydrostatic pressure test to Owner, Owners Civil Engineering Consultant<br />

(CEC), and utility company upon completion of water distribution backfilling operations.<br />

B. Project Record Documents:<br />

1. Disinfection report: Record the following:<br />

a. Type and form of disinfectant used.<br />

b. Date and time disinfectant injection start and time of completion.<br />

c. Test locations.<br />

d. Initial and 24 hour disinfectant residuals (quantity in treated water) in ppm for each outlet tested.<br />

e. Date and time of flushing start and completion.<br />

f. Disinfectant residual after flushing in ppm for each outlet tested.<br />

2. Bacteriological report: Record the following:<br />

a. Date issued, project name, testing laboratory name, address, and telephone number.<br />

b. Time and date of water sample collection.<br />

c. Name of person collecting samples.<br />

d. Test locations.<br />

e. Initial and 24 hour disinfectant residuals in ppm for each outlet tested.<br />

f. Coliform bacteria test results for each outlet tested.<br />

g. Certification that water conforms, or fails to conform, to bacterial standards.<br />

h. Bacteriologist’s signature and authority.<br />

3. Accurately record actual locations of piping mains, valves, connections, and top of pipe elevations.<br />

4. Identify and describe unexpected variations to subsoil conditions and location of uncharted utilities.<br />

PART 2 - PRODUCTS<br />

Formatted: Left, Tabs: Not at -36<br />

pt<br />

Formatted: Level 1, Tabs: 468 pt,<br />

Left + 495 pt, Right<br />

2.1 PIPE<br />

A. Pipe sizes 3-inches and smaller for installation below grade and outside building shall comply with one or combination<br />

of following:<br />

1. Seamless Copper Tubing: Type "K" soft copper, ASTM B88.<br />

a. Fittings: Wrought copper (95-5 Tin Antimony solder joint), ASME B 16.22.<br />

2. Polyvinyl Chloride (PVC) Water Pipe: Pipe, ASTM D 2241, with SDR 21 rating, continually marked with<br />

manufacturer's name, pipe size, cell classification, SDR rating, and ASTM D1784 material classification.<br />

a. Pipe joints: Integrally molded bell ends, ASTM D2672.<br />

b. Cement primer: ASTM F656.<br />

c. Solvent cement: ASTM D2564.<br />

3. 3” Cement-mortar lined Ductile Iron Pipe as designated by ANSI/AWWA C150 and as specified by the City<br />

of La Habra recommendations, standards, and specifications.<br />

B. Pipe sizes 4 to 16 inches for installation below grade and outside building shall comply with one or combination of<br />

following:<br />

1. Ductile Iron Water Pipe: AWWA C151, Pressure class 350 (4-12”) Pressure Class 250 (14-16”).<br />

02510-2<br />

Formatted: Indent: Left: 67.5 pt<br />

Formatted: Indent: Left: 67.5 pt<br />

Formatted: PR2, Tabs: Not at 96.3<br />

pt<br />

Formatted: Centered<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Formatted: Tabs: 486 pt, Right<br />

Deleted:<br />

Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


a. Fittings: Either mechanical joint or push-on joint, AWWA C153, and shall be coated with a 6-8 mil<br />

nominal thickness fusion bonded epoxy conforming to the requirements of AWWA C550 and C116,<br />

or cement mortar lined in accordance with AWWA C104.<br />

b. Elastomeric gaskets and lubricant: ASTM F477.<br />

c. Lining: Pipe shall be cement-mortar lined in accordance with AWWA C104.<br />

2. Polyvinyl Chloride (PVC) Water Pipe: Pipe, AWWA C900, rated DR 18 (Class 150), continually marked as<br />

required.<br />

a. Elastomeric gaskets and lubricant: ASTM F477 for smaller pipes.<br />

b. Pipe joints: Integrally molded bell ends, ASTM D3139.<br />

Formatted: Indent: Left: 100.8 pt,<br />

No bullets or numbering<br />

2.2 VALVES<br />

A. Gate Valves, 2-Inches and Larger:<br />

1. Manufacturer and Model: Mueller Resilient Wedge Gate Valves or approved equal.<br />

2. AWWA C509, iron body, non-rising stem with square nut, single wedge, resilient seat, flanged or mechanical<br />

joint ends, control rod, post indicator where indicated on Construction Drawings, extension box and<br />

valve key.<br />

B. Ball Valves, 2-Inches and Smaller:<br />

1. Manufacturer and Model: Mueller Oriseal or approved equal.<br />

2. Brass body, teflon coated brass ball, rubber seats and stem seals, Tee stem pre-drilled for control rod,<br />

AWWA compression inlet end, compression outlet with electrical ground connector, with control rod, extension<br />

box and valve key.<br />

C. Butterfly Valves, From 2-Inch to 24-Inch: AWWA C504, Iron body, bronze disc, resilient replaceable seat, water<br />

or lug ends, infinite position lever handle.<br />

D. Check Valves, Post Indicator Valves, And Backflow Preventors<br />

1. Refer to Section 13900 - Fire Suppression in Architectural/Building Specifications<br />

2. Fire system external backflow preventor assembly shall be 8” AMES 3000SS OSY Double Check Detector<br />

Assembly or approved equal.<br />

2.3 FIRE HYDRANTS<br />

A. Fire Hydrants: Type as required by utility company/Local Fire Department and as shown on Construction Drawings.<br />

B. Hydrant Extensions: Fabricate in multiples of 6-inches with rod and coupling to increase barrel length.<br />

C. Hose and Steamer Connections: Match sizes with utility company, with two hose nozzles, one pumper nozzle.<br />

D. Finish: Apply primer and 2 coats of enamel or special coating to color as required by utility company.<br />

2.4 ACCESSORIES<br />

A. Thrust Blocking: Thrust blocks shall be installed as shown on the “Thrust Block Detail” on the Construction Drawings.<br />

Thrust blocks for pipes smaller than 6 inches in diameter shall meet the requirements shown for 6 inch diameter<br />

pipe.<br />

B. Locked mechanical joint fittings shall be installed where vertical changes in direction are required and, if approved<br />

by Owner and governing authority, can be installed in lieu of above thrust blocking requirements.<br />

02510-3<br />

Deleted: Thrust Blocking: Place 2500<br />

psi concrete to provide sufficient bearing<br />

area to transmit unbalanced thrust from<br />

bends, tees, caps, or plugs to undisturbed<br />

soil without loading undisturbed soil in<br />

excess of 2,500 pounds per square foot<br />

when water main pressure is 100 psi.<br />

<br />

MINIMUM THRUST BLOCKING<br />

BEARING AREAS<br />

<br />

Pipe Tees 90 Bend 45<br />

Bend 22½ Bend 11¼ Bend<br />

5 5/8 Bend Cap/Plug<br />

Diameter Sq. Ft Sq.<br />

Ft Sq. Ft Sq. Ft. Sq.<br />

Ft. Sq. Ft. Sq. Ft.<br />

<br />

3" 1.0 1.0 1.0 1.0<br />

1.0 1.0 1.5<br />

4" 1.0 1.0 1.0 1.0<br />

1.0 1.0 2.0<br />

6" 1.5 2.0 1.0 1.0<br />

1.0 1.0 3.0<br />

8" 2.5 3.5 1.8 1.0<br />

1.0 1.0 4.0<br />

10" 4.0 5.5 2.8 1.5<br />

1.0 1.0 6.0<br />

12" 6.0 8.0 4.0 2.0<br />

1.5 1.0 8.5<br />

14" 8.0 11.0<br />

5.5 3.0 2.0 1.5<br />

12.0<br />

16" 10.0 14.2<br />

7.0 4.0 3.0 2.5 15.0<br />

18" 21.0 21.0 12.0 6.0<br />

4.0 3.5 24.0<br />

Formatted: Centered<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Formatted: Tabs: 486 pt, Right<br />

Deleted:<br />

Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


C. Polyethylene Encasement: Single layer of two ply cross-laminated high density polyethylene encasement per<br />

AWWA C105, Section 4.1.2, Type III, Class C (Black), Grade 33, tensile strength 5,000 psi minimum, elongation<br />

100 percent, thickness nominal 0.004 inch (4 mil).<br />

D. Trace Wire: Magnetic detectable conductor, (#12 Copper) brightly colored plastic covering imprinted with “Water<br />

Service” in large letters.<br />

PART 3 - EXECUTION<br />

Formatted: Level 1, Tabs: 468 pt,<br />

Left + 495 pt, Right<br />

3.1 EXAMINATION<br />

A. Verify that building service connection and municipal utility water main size, location, and depth are as indicated<br />

on Construction Drawings.<br />

3.2 PREPARATION<br />

A. Ream pipe and tube ends and remove burrs.<br />

B. Remove scale and dirt, on inside and outside, before assembly.<br />

C. Prepare pipe for connections to equipment with flanges or unions.<br />

D. Protect benchmarks, property corners, and other survey monuments from damage or displacement. If marker needs<br />

to be removed it shall be referenced by licensed land surveyor and replaced, as necessary, by same.<br />

3.3 TRENCHING AND BEDDING<br />

A. Excavate pipe trench and place bedding material in accordance with Section 02300.<br />

3.4 INSTALLATION - PIPE AND FITTINGS<br />

A. Maintain separation of water main from sanitary and storm sewer piping in accordance with state or local codes.<br />

B. Install ductile iron pipe and fittings in accordance with AWWA C600.<br />

C. Install PVC pipe and fittings in accordance with AWWA C605.<br />

D. Ductile iron pipe and fittings shall be installed with polyethylene encasement around the pipe for the entire length<br />

of the project except where water main is within steel casing or is concrete encased. Install polyethylene encasement<br />

in accordance with AWWA C105, Method A.<br />

E. Install pipe to allow for expansion and contraction without stressing pipe or joints or as specified by pipe manufacturer.<br />

F. Install access fittings in accordance with local codes to permit disinfection of water system performed under this<br />

Section.<br />

G. Connections with Existing Pipelines: Where connections are made between new work and existing piping, make<br />

connection using suitable fittings for conditions encountered. Make each connection with existing pipe at time and<br />

under conditions with least interference with operation of existing pipeline and in compliance with local utility<br />

company.<br />

02510-4<br />

Formatted: Centered<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Formatted: Tabs: 486 pt, Right<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


H. Form and place concrete for thrust blocks or other specified methods of retainage at each change of direction or end<br />

of pipe main.<br />

I. Place pipe to depth in accordance with Section 02300.<br />

J. Backfill trench in accordance with Section 02300.<br />

K. Install trace wire continuous over top of non-metal pipe. Bury a minimum of 6 inches below finish grade, and<br />

above pipeline.<br />

3.5 INSTALLATION - VALVES AND HYDRANTS<br />

A. Install gate valves as indicated on Construction Drawings. Support valve on concrete pads with valve stem vertical<br />

and plumb. Install valve boxes in manner that will not transmit loads, stress, or shock to valve body. Center<br />

valve box over operating nut of valve vertical and plumb. Securely fit valve box together leaving cover flush with<br />

finished surface.<br />

B. Install fire hydrant assemblies as indicated on Construction Drawings in vertical and plumb position with steamer/pumper<br />

nozzle pointed perpendicular to traffic where hydrant is adjacent to street, roadway, or parking lot drive<br />

or toward protected building unless otherwise directed by local authorities. Support hydrant assembly on concrete<br />

pad and firmly brace on side opposite inlet pipe against undisturbed soil and concrete blocking. Place minimum of<br />

6-cubic feet of crushed stone or gravel around hydrant base and barrel after thrust blocking has cured at least 24<br />

hours. Maintain vertical position of hydrant backfilling and compacting.<br />

3.6 DISINFECTION OF DOMESTIC WATER PIPING SYSTEM<br />

A. Disinfect distribution system with chlorine before acceptance for domestic operation. Chlorine dosage shall be not<br />

less than 50 parts per million. Flush lines before introduction of chlorinating materials and after contact period of<br />

not less than 24 hours. Flush with clean water after contact period until residual chlorine content is not greater than<br />

1.0 part per million. Flush water discharged from water supply lines or hydrants shall not be allowed to discharge<br />

directly onto exposed soil or turf which could result in erosion of soil. If potential for erosion exists at discharge<br />

point, measures shall be taken to prevent erosion. Open and close valves in lines being disinfected several times<br />

during contact period. After disinfection, take water sample and bacteriological test in accordance with AWWA<br />

C651. Do not place distribution system in service until approval is obtained from local governing authorities.<br />

B. Contractor shall provide a means of neutralizing the super-chlorinated water before releasing into the environment.<br />

This may be accomplished by either a method of dechlorinization, direct release into a detention area approved by<br />

Wal-Mart, or any method acceptable to federal, state, and local codes. Direct release to open ground shall not be<br />

allowed, unless contained within an on site detention facility with 6" permanent storage. In this case, the Contractor<br />

shall time the release to assure that no rainstorms are imminent. The intent of this condition is to allow the majority<br />

of the chlorine to evaporate into the atmosphere before a rainstorm has the opportunity to wash the residual<br />

downstream. Contractor shall not release super-chlorinated water directly into the sanitary sewer system, private<br />

or public, nor any storm drain system not directly discharging into the detention facility.<br />

3.7 SERVICE CONNECTIONS<br />

A. Provide water service connection in compliance with utility company requirements including reduced pressure<br />

backflow preventor (if required) and water meter with by-pass valves and sand strainer.<br />

3.8 FIELD QUALITY CONTROL<br />

A. Test water distribution system pipe installed below grade and outside building in accordance with the following<br />

procedures:<br />

02510-5<br />

Formatted: Centered<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Formatted: Tabs: 486 pt, Right<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


1. Perform testing of pipe materials, joints, and other materials incorporated into construction of water mains<br />

and force mains to determine leakage and water tightness. In the event state or local code requires more<br />

stringent test, more stringent test shall take precedence.<br />

2. Conduct piping tests before joints are covered and after concrete thrust blocks have hardened sufficiently.<br />

Fill pipeline 24 hours before testing and apply test pressure to stabilize system. Use only potable water.<br />

Test at not less than one-and-one-half times working pressure for two hours. Increase pressure in 50-psig<br />

increments and inspect each joint between increments. Hold at test pressure for 1 hour; decrease to 0 psig.<br />

Slowly increase again to test pressure and hold for 1 more hour. Maximum allowable leakage shall be 2<br />

quarts per hour per 100 joints. Remake leaking joints with new materials and repeat test until leakage is<br />

within allowed limits.<br />

B. Prepare reports of testing activities.<br />

Formatted: Hyphenate, Tabs: 495<br />

pt, Right<br />

END SECTION<br />

02510-6<br />

Formatted: Centered<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Formatted: Tabs: 486 pt, Right<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec – Civil (Master Site Specifications) 101007<br />

SECTION 02535 (33 3000) - SANITARY SEWAGE SYSTEMS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Sanitary sewer drainage piping, fittings, accessories, cleanouts, and bedding.<br />

2. Connection of site sanitary sewer system to municipal sanitary sewer systems.<br />

B. Related Requirements:<br />

1. Section 02300 – Earthwork: Trenching, backfill, and compaction for utilities<br />

2. Section 02536 - Sewer Manholes, Frames, and Covers<br />

3. Section 03310 – Cast-in-place Structural Concrete<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A74 - Cast Iron Soil Pipe and Fittings<br />

2. ASTM A746 - Ductile Iron Gravity Sewer Pipe<br />

3. ASTM C425 - Compression Joints for Vitrified Clay Pipe and Fittings<br />

4. ASTM C564 - Rubber Gaskets for Cast Iron Soil Pipe and Fittings<br />

5. ASTM C700 - Vitrified Clay Pipe, Extra Strength, Standard Strength, and Perforated<br />

6. ASTM D2241 - Poly (vinyl Chloride) (PVC) Pressure-Rated Pipe (SDR Series)<br />

7. ASTM D2657 - Heat-Joining Polyolefin pipe and Fittings<br />

8. ASTM D3034 - Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings<br />

9. ASTM D3035 - Polyethylene (PE) Plastic Pipe Using Flexible Elastomeric Seals<br />

10. ASTM D3139 - Joints for Plastic Pressure Pipe Using Flexible Elastomeric Seals<br />

11. ASTM D3261 - Butt Heat Fussion Polyethylene (PE) Plastic Fittings For Polyethylene Plastic Pipe And<br />

Tubing<br />

12. ASTM F477 - Elastomeric Seals (Gaskets) for Joining Plastic Pipe<br />

13. ASTM F1417 - Standard Test Method for Installation Acceptance of Plastic Gravity Sewer Lines Using<br />

Low-Pressure Air.<br />

C. American Water Works Association (AWWA):<br />

1. AWWA C111 - Rubber-Gasket Joints for Ductile Iron Pressure Pipe and Fittings<br />

2. AWWA C600 - Ductile-Iron Water Mains And Their Appurtenances<br />

3. AWWA C900 - Polyvinyl Chloride (PVC) Pressure Pipe, 4 In. Through 12 In, For Water Distribution<br />

4. AWWA C901 - Polyethylene (PE) Pressure Pipe, Tubing And Fittings 1/2 Inch Through 3 Inches, For Water<br />

Distribution<br />

5. AWWA C906 - Polyethylene (PE) Pressure Pipe And Fittings, 4 Inch Through 63 Inch, For Water Distribution<br />

1.3 SUBMITTALS<br />

A. Project Record Documents:<br />

1. Accurately record actual locations of pipe runs, connections, cleanouts, and invert elevations.<br />

2. Identify and describe unexpected variations to subsoil conditions and location of uncharted utilities.<br />

1.4 PROJECT CONDITIONS<br />

02535-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Coordinate work with termination of sanitary sewer connection outside building and connection to municipal sewer<br />

utility service.<br />

PART 2 - PRODUCTS<br />

2.1 SEWER PIPE, FITTINGS, AND JOINTS<br />

A. Polyvinyl Chloride Pipe (PVC): ASTM D 3034, rated SDR 35 unless otherwise specified by the utility company.<br />

Pipe shall be continually marked with manufacturer's name, pipe size, cell classification, SDR rating, and ASTM<br />

D 3034 classification.<br />

1. Pipe joints: Integrally molded bell ends, ASTM D 3034, Table 2, with factory supplied elastomeric gaskets<br />

and lubricant.<br />

B. Vitrified Clay Pipe (VCP): ASTM C700: Use only if required by local jurisdiction.<br />

1. Fittings: ASTM C700<br />

2. Joints: ASTM C425<br />

3. Gaskets: ASTM C425. Gaskets shall be manufactured from high grade, properly vulcanized elastomeric<br />

compound consisting of either basic natural or synthetic rubber. Gasket manufacturing tolerances shall<br />

comply with Rubber Manufacturer's Association tolerances for gaskets.<br />

4. Lubricant: Suitable for lubricating joint components; no deteriorating effects on gasket or pipe material,<br />

will not support growth of fungi or bacteria, and shall be of type recommended by gasket manufacturer.<br />

C. Force Main:<br />

1. High-Density Polyethylene Pipe (HDPE): AWWA C901 and C906, ASTM D3035, SDR 11 for 150 psi<br />

pressure rating.<br />

a. Fittings: Molded, AWWA C901 or C906.<br />

b. Joints: Butt fusion, ASTM D2657, flanged gasket joints at interface<br />

2. Polyvinyl Chloride Pipe (PVC): For less than 4 inches in diameter, ASTM D2241 for push-on or solvent<br />

weld joints, and for pipe 4 inches in diameter and larger, AWWA C900, Class 150 with push-on joints.<br />

a. Joints/Fittings: Push-on, ASTM D3139 with ASTM F477 gaskets.<br />

b. Solvent Cement: ASTM D2564.<br />

3. Ductile Iron Pipe (DIP): ASTM A746, Class 50, inside nominal diameter as shown on the drawings, bell<br />

and spigot end.<br />

a. Ductile Iron Pipe Joint Device: AWWA C111, rubber gasket joint devices.<br />

2.2 PIPE ACCESSORIES<br />

A. Pipe Joints: Mechanical clamp ring type, stainless steel expanding and contracting sleeve, neoprene-ribbed gasket<br />

for positive seal.<br />

B. Fittings: Same material as pipe molded or formed to suit pipe size and end design, in required tee, bends, elbows,<br />

cleanouts, reducers, traps, etc.<br />

2.3 CLEANOUTS AND MANHOLES<br />

A. Manholes shall conform to Section 02536.<br />

B. Lid and Frame: Provide in accordance with Section 02536. Provide traffic grade and rated covers and frames<br />

where cleanouts and manholes are within pavement, with the letters “SSCO” or “SANITARY SEWER” respectively<br />

cast into the cover.<br />

C. Shaft Construction: Cast iron shaft of internal diameter as specified on Construction Drawings with 2500 psi concrete<br />

collar for cleanouts.<br />

2.4 APPURTENANCES<br />

02535-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Trace Wire: Magnetic detectable conductor (#12 copper), brightly colored plastic covering, imprinted with “Sanitary<br />

Sewer Service” in large letters.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that trench cut and excavation is ready to receive work and excavations, dimensions, and elevations are as<br />

indicated on Construction Drawings.<br />

3.2 PREPARATION<br />

A. Hand trim excavations to required elevations. Correct over excavation with bedding material.<br />

B. Remove large stones or other hard matter that could damage pipe or impede consistent backfilling or compaction.<br />

3.3 BEDDING<br />

A. Excavate trench and place bedding material in accordance with Section 02300.<br />

3.4 INSTALLATION - PIPE<br />

A. Install type and class of pipe as shown on the drawings. Pipes shall be laid and maintained to the required line and<br />

grade with necessary fittings, bends, manhole risers, cleanouts and other appurtenances placed at the required locations.<br />

The pipe shall be installed with uniform bearing under the full length of the barrel of the pipe. The pipe<br />

shall be inspected for defects and cracks before being lowered into the trench. Defective, damaged or unsound<br />

pipe, or pipe that has had its grade disturbed after laying shall be taken up and replaced. Commence installation at<br />

lowest point with the bell end upgrade.<br />

B. No pipe shall be laid in water or when trench conditions are unsuitable for work.<br />

C. Pipe connecting to manholes or other structures shall terminate flush inside of the structure wall.<br />

D. Joints for PVC and CISP shall be thoroughly lubricated with an approved lubricant before pipe sections are slipped<br />

together. Open ends shall be fully protected with a stopper to prevent earth or other material from entering the<br />

pipe during construction. Carefully free interior of the pipe from dirt, cement and other deleterious material as the<br />

work progresses.<br />

E. Maintain separation of potable water main from sewer piping at crossings a minimum of 10 feet horizontal and 18<br />

inches vertical.<br />

F. Install HDPE piping and fittings to AWWA C901 and C906. Butt fusion welded per ASTM D3261.<br />

G. Route pipe in straight line parallel to roads, buildings and adjacent utilities and as shown on the drawings.<br />

H. Establish elevations of buried piping with sufficient cover as recommended by pipe manufacturer to ensure not<br />

less than 3 feet of cover, except as noted on drawings.<br />

I. Form and place concrete for thrust blocks at each elbow of pipe force main. See construction drawing for details<br />

of construction.<br />

J. Backfill trench in accordance with Section 02300.<br />

K. Install trace wire continuous over top of non-metal pipe. Bury 6 inches minimum below finish grade, above pipeline.<br />

3.5 INSTALLATION – CLEANOUTS AND MANHOLES<br />

02535-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Form bottom of excavation clean and smooth to correct elevation.<br />

B. For cleanouts, form and place cast-in-place concrete base pad with provision for sanitary sewer pipe to be installed<br />

to proper elevations.<br />

C. For manholes, construct inverts according to the following guidelines:<br />

1. Invert channel shall be smooth and accurately shaped to a semicircular bottom to match with the inside of<br />

the adjacent sewer section.<br />

2. Invert channels and structure bottoms shall be shaped with mortar and lean concrete.<br />

3. Changes in size and grade of invert shall be made gradually and evenly.<br />

4. Changes in the direction of the sewer entering branch or branches shall have a true curve of as large a radius<br />

as the manhole will permit.<br />

D. For manholes, provide manhole rings, frame, and cover as shown on the construction drawings.<br />

3.6 FIELD QUALITY CONTROL<br />

A. Field quality control shall be conducted by the Contractor in accordance with Section 01452.<br />

B. Pipes and joints shall not be completely backfilled until after inspection, testing, and approval by the Owner and<br />

local jurisdiction.<br />

C. Prior to testing for leakage, the pipe trench shall be backfilled to at least the spring line of the pipe. If required to<br />

prevent pipe movement during testing, additional backfill shall be added leaving the pipe joints uncovered to permit<br />

inspection.<br />

D. Exfiltration Test<br />

1. Each section of sewer line between successive manholes shall be tested by closing the lower end of the<br />

sewer to be tested and the inlet sewer of the upper manhole, using stoppers.<br />

2. Fill the manhole and pipe with water to a point which produces a maximum of 3 feet of head above the invert<br />

of the sewer at the center of the upper manhole; or if groundwater is present, 3 feet of head above the<br />

average adjacent groundwater level.<br />

3. The allowable leakage shall be 200 gal/inch of pipe diameter/mile/day<br />

E. Infiltration Test<br />

1. If excessive ground water is encountered in the construction of a section of the sewer, the exfiltration test<br />

shall not be used.<br />

2. The upper and lower ends of the sewer to be tested shall be closed sufficiently to prevent the entrance of<br />

water.<br />

3. Pumping of ground water shall be discontinued for at least 3 days; then infiltration shall be tested.<br />

4. Infiltration into each section of sewer between adjoining manholes shall not exceed that allowed for the exfiltration<br />

test, except that head conditions shall be a maximum of 6 feet.<br />

F. The Exfiltration Test may be limited to the manholes only when the authority having jurisdiction does not require<br />

the test and the construction manager waives the test. The Infiltration Test will always be required when excessive<br />

ground water is encountered in addition to the air test.<br />

G. Air Test: Gravity systems shall be air tested between manholes at 3.5 psi for 5 minutes per ASTM F1417 for plastic<br />

pipes.<br />

H. Deflection Test:<br />

1. Deflection tests shall be conducted on all plastic pipe using a mandrel with a diameter equal to 95 percent<br />

of the inside diameter of the pipe. The test shall be performed without mechanical pulling devices.<br />

2. Allowable Deflection: Maximum allowable pipe deflection shall not exceed 5 percent of nominal inside<br />

diameter.<br />

3. Mandrel: Mandrel, go/no-go, device shall be cylindrical in shape and constructed with either 9 or 16 evenly<br />

spaced arms or prongs. Mandrels with fewer arms will be rejected as not sufficiently accurate. Contact<br />

02535-4<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


length of mandrel's arms shall equal or exceed nominal inside diameter of sewer to be inspected. Critical<br />

mandrel dimensions shall carry tolerance of 0.01-inch maximum. Contractor shall provide mandrel and<br />

necessary equipment for mandrel test.<br />

4. Procedure: Mandrel shall be hand-pulled through flexible pipe sewer lines no earlier than 30 days after<br />

trench has been completely backfilled. Sections of sewer not passing mandrel shall be uncovered and rebedded,<br />

rerounded, or replaced to satisfaction of Owner or governing agency. Repaired section shall be retested.<br />

I. Hydrostatic Test: Force main piping shall be hydrostatically tested at 150 psi in accordance with AWWA C 600.<br />

J. Provide measuring devices, meters, water, materials, and labor for making the required tests.<br />

K. Tests shall be conducted in the presence of the Construction Manager or his designee. Test data shall be submitted<br />

to the Engineer for review and approval.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

02535-5<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec II – Civil (Master Site Specifications) 092210<br />

SECTION 02536 (33 3913) - SEWER MANHOLES, FRAMES, AND COVERS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

1.2 Section Includes:<br />

1. Monolithic concrete, modular precast concrete, masonry, and precast polyethylene manhole assemblies.<br />

1.3 Related Requirements:<br />

1. Section 02300 - Earthwork. Excavation, backfill, and compaction<br />

2. Section 02535- Sanitary Sewer Systems<br />

3. Section 02630 - Storm Drainage (Not Used)<br />

1.4 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A48 - Gray Iron Castings.<br />

2. ASTM C55 - Concrete Building Brick.<br />

3. ASTM C94 - Ready Mixed Concrete.<br />

4. ASTM C478 - Precast Reinforced Concrete Manhole Sections.<br />

5. ASTM C990 - Joints for Concrete Pipe, Manholes, and Precast Box Sections Using Preformed Flexible<br />

Joint Sealants<br />

6. ASTM D1248 - Polyethylene Plastics Molding and Extrusion Materials.<br />

7. ASTM D2412 - Determination of External Loading Characteristics of Plastic Pipe by Parallel-Plate Loading.<br />

C. International Masonry Industry All-Weather Council (IMIAC):<br />

1. Recommended Practices and Guide Specification for Cold Weather Masonry Construction.<br />

D. State Department of Transportation (DOT), Construction and Material Specifications.<br />

1.5 SUBMITTALS<br />

A. Shop Drawings: Indicate reference to Construction Drawings of manhole locations, elevations, piping with sizes,<br />

locations, and elevations of penetrations.<br />

PART 2 - PRODUCTS<br />

2.1 MANHOLES<br />

A. Cast-In-Place Concrete: Nonreinforced cast in place concrete barrel.<br />

1. Concrete: 3500 psi concrete conforming to ASTM C94.<br />

2. Forms: Steel sheet accurately shaped and fabricated of sufficient strength to form dense watertight walls to<br />

true dimensions.<br />

B. Precast Concrete: Reinforced precast concrete barrel.<br />

1. Manhole Sections: ASTM C478.<br />

2. Joints and Joint Sealant: Joint between manhole barrel sections shall conform to ASTM C990 using preformed<br />

flexible joint sealant.<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

02536-1<br />

La Habra, CA – 5641-01 10/15/11


3. Pipe Connection Sealant: Joint material between manhole barrel and adjoining pipe shall be as shown on<br />

the drawings.<br />

4. Construct manholes of precast concrete sections as required by Construction Drawings to size, shape, and<br />

depth indicated.<br />

C. Concrete Brick: ASTM C55, Grade N Type I-moisture controlled, normal weight, of same grade, type and weight<br />

as block units, nominal modular size of 3 5/8-inches x 7 5/8-inches x 2 1/4-inches.<br />

D. Precast Polyethylene:<br />

1. Manufacturer: Advanced Drainage Systems (ADS) or approved equal.<br />

2. Precast polyethylene in accordance with ASTM D1248. Nominal cylinder internal diameter shall be 48-<br />

inches and shall be designed to accept concrete filled polyethylene manhole lids and standard cast iron<br />

frames with lid or grate.<br />

3. Manholes shall have compressive strength that meets ASTM D2412 standards.<br />

E. Mortar and Grout: Mortar for finishing and sealing shall be Class "C". Honeycombing less than 2-inches deep<br />

shall be repaired using Class "D" mortar.<br />

F. Brick Transition Reinforcement: Formed steel 8-gauge wire with galvanized finish.<br />

G. Configuration:<br />

1. Barrel Construction: Concentric with eccentric cone top section.<br />

2. Shape: Cylindrical.<br />

3. Clear Inside Dimensions: 48-inches diameter minimum or as indicated on Construction Drawings.<br />

4. Design Depth: As indicated on Construction Drawings.<br />

5. Clear Lid Opening: 22-inches minimum.<br />

6. Pipe Entry: Provide openings as indicated on Construction Drawings.<br />

7. Main and Lateral Pipes: Neatly cut off main and lateral pipes flush with inside of manhole or inlet where<br />

they enter structure walls. Point up irregularities and rough edges with nonshrinking grout.<br />

H. Inverts: Shape inverts for smooth flow across structure floor as indicated on Construction Drawings. Use concrete<br />

and mortar to obtain proper grade and contour. Finish surface with fine textured wood float.<br />

2.2 COMPONENTS<br />

A. Lid and Frame:<br />

1. Manufacturer: One of the following or approved equal:<br />

a. Bass & Hays Foundry.<br />

b. Deeter Foundry, Inc.<br />

c. East Jordan Iron Works.<br />

d. Neenah Foundry.<br />

e. U.S. Foundry & Manufacturing<br />

2. ASTM A48, Class 30B minimum, heavy duty cast iron construction, machined flat bearing surface.<br />

3. Removable lid, closed or open as indicated on Construction Drawings, with sealing gasket.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify items specified by other Sections are properly sized and located.<br />

B. Verify that built-in items are in proper location and ready for roughing into work.<br />

C. Verify that the excavation for manholes is correct.<br />

3.2 PREPARATION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

02536-2<br />

La Habra, CA – 5641-01 10/15/11


A. Coordinate placement of inlet and outlet pipe or duct sleeves as indicated on Construction Drawings.<br />

3.3 PRECAST MANHOLE CONSTRUCTION<br />

A. Place base pad to proper elevation and location and trowel top surface level for placement of manhole barrel.<br />

B. Place manhole barrel plumb and level to correct elevations and anchor to base pad.<br />

1. After completion of slab foundation, lower first joint of manhole barrel into position, grooved end first, and<br />

set level and plumb on concrete base. Align and adjust to proper grade prior to placing and forming invert.<br />

Pour invert immediately after setting of first section of manhole barrel.<br />

2. Prior to setting subsequent manhole barrel sections, apply primer to tongue and groove ends and allow to<br />

set in accordance with manufacturer's recommendations. Place joint sealant on tongue end. Lower next<br />

section into position, and remove excess material from interior of structure. Add additional material on exterior<br />

of joint, if necessary, for completely watertight joint.<br />

C. Set cover frames and lids level without tipping, to correct elevations. Utilize pre-cast rings or brick and mortar to<br />

achieve final rim elevation. Maximum limit, 4 courses.<br />

3.4 CAST-IN-PLACE MANHOLE CONSTRUCTION<br />

A. Cast-in-place concrete shall conform to the applicable requirements of concrete in Division 3. Utilize steel forms.<br />

B. Place base pad to proper elevation and location and pour monolithically with invert. Base shall support pipe to<br />

first joint.<br />

C. Deposit concrete in evenly distributed layers of about 18 inches, with each layer vibrated to bond to preceding layer.<br />

D. Place gasket between all joints and paint exterior of manhole within 5 inches of the joint with mastic waterproofing.<br />

E. Place precast concrete cone.<br />

F. Set section cover frames and lids level without tipping, to correct elevations. Utilize pre-cast rings or brick and<br />

mortar to achieve final rim elevation. Maximum limit, 4 courses.<br />

3.5 MASONRY MANHOLE CONSTRUCTION<br />

A. Maintain masonry courses to uniform dimension. Form vertical and horizontal joints of uniform thickness.<br />

B. Lay masonry units in running bond. Course 3 brick units and 3 mortar joints to equal 8 inches.<br />

C. Form flush mortar joints<br />

D. Lay masonry units in full bed of mortar, with full head joints, uniformly jointed with other work.<br />

E. Install joint reinforcement 16 inches on center<br />

F. Place joint reinforcement in first and second horizontal joints above base pad and below lid frame opening<br />

G. As work progresses, build in fabricated metal items<br />

H. Cut and fit masonry for pipes as specified herein<br />

I. Set cover frames and covers level to correct elevations without tipping.<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

02536-3<br />

La Habra, CA – 5641-01 10/15/11


END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

02536-4<br />

La Habra, CA – 5641-01 10/15/11


UniSpec – Civil (Master Site Specifications) 101007<br />

SECTION 02555 (33 5000) - NATURAL AND PROPANE GAS DISTRIBUTION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Pipe and fittings for site utility natural or propane gas distribution.<br />

2. Propane storage tanks and appurtenances.<br />

3. Connection of site natural gas system and private utility company system.<br />

B. Related Requirements:<br />

1. Section 02300 – Earthwork: Trenching, backfill, and compaction for utilities<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Society of Mechanical Engineers (ASME):<br />

1. ASME B16.3 - Malleable Iron Threaded Fittings<br />

2. ASME B16.11 -Forged Steel Fittings, Socket Welding and Threaded<br />

3. ASME B16.18 - Cast Copper Alloy Solder Joint Pressure Fittings<br />

4. ASME B16.22 - Wrought Copper and Copper Alloy Solder Joint Pressure Fittings<br />

5. ASME B31.8 - Gas Transmission and Distribution Piping Systems<br />

6. ASME S00081 – Boiler and Pressure Vessel Code, Sec VIII: Pressure Vessels<br />

7. ASME Q00090 - Boiler and Pressure Vessel Code, Sec. IX: Welding and Brazing Qualifications<br />

8. ASME Boiler and Pressure Code<br />

C. ASTM International (ASTM):<br />

1. ASTM A53 - Pipe, Steel, Black and Hot-Dipped, Zinc Coated (Galvanized) Welded and Seamless<br />

2. ASTM A234 - Pipe Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and Elevated Temperature<br />

3. ASTM B32 - Solder Metal<br />

4. ASTM B88 - Seamless Copper Water Tube<br />

5. ASTM D2513 - Thermoplastic Gas Pressure Pipe, Tubing, and Fittings<br />

6. ASTM D2517 - Reinforced Epoxy Resin Gas Pressure Pipe and Fittings<br />

7. ASTM D2683 - Socket-Type Polyethylene Fittings For Outside Diameter-Controlled Polyethylene Pipe<br />

and Tubing<br />

8. ASTM D 3261 - Butt Heat Fusion Polyethylene (PE) Plastic Polyethylene (PE) Plastic Pipe And Tubing<br />

D. American Welding Society (AWS):<br />

1. AWS A5.8 - Brazing Filler Metal<br />

E. American Water Works Association (AWWA):<br />

1. AWWA C105 - Polyethylene Encasement for Ductile-Iron Piping for Water and Other Liquids<br />

F. American National Standards Institute (ANSI):<br />

1. ANSI B16.26 - Cast Copper Alloy Fittings for Flared Copper Tubes<br />

2. ANSI B31.2 - Fuel Gas Piping<br />

G. National Fire Protection Agency (NFPA):<br />

1. NFPA 54 - National Fuel Gas Code<br />

1.3 QUALITY ASSURANCE<br />

02555-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Perform installation in accordance with utility company requirements.<br />

B. Gas Cock: Manufacturer's name and pressure rating marked on valve body.<br />

C. Welding Materials and Procedures: Conform to ASME Boiler and Pressure Vessel Code and applicable state regulations.<br />

D. Welders Certification: In accordance with ASME Q00090, Sec IX.<br />

E. Conform to NFPA 54, ANSI B31.2, or ASME B31.8.<br />

1.4 SUBMITTALS<br />

A. Project Record Documents:<br />

1. Accurately record actual locations of pipe mains, valves, connections, and top of pipe elevations.<br />

2. Identify and describe unexpected variations to subsoil conditions and location of uncharted utilities.<br />

1.5 DELIVERY, STORAGE, AND HANDLING<br />

A. Deliver, store, protect, and handle products to be included.<br />

B. Deliver and store valves in shipping containers with labeling in place.<br />

PART 2 - PRODUCTS<br />

2.1 PIPE<br />

A. Steel Pipe:<br />

1. Below Ground: ASTM A53, Schedule 40, type E or S, grade B, black:<br />

a. Fittings: ASME B16.11, forged steel, or ASTM A234 forged steel welding type.<br />

b. Joints: Welded and seamless.<br />

c. Jackets: AWWA C105 polyethylene jacket, double layer, half lapped, 10-mil polyethylene tape.<br />

2. Above Ground: ASTM A53, Schedule 40, type E or S, grade B, black:<br />

a. Fittings: ASME B16.3, malleable iron, ASME B16.11, forged steel, or ASTM A234, forged steel<br />

welding type.<br />

b. Joints: Threaded.<br />

B. Copper Tubing (Propane Piping):<br />

1. Below ground: ASTM B88, Type K, internally tinned:<br />

a. Fittings: ASME B16.18, cast copper, or ASME B16.22, wrought copper; internally tinned.<br />

b. Joint: AWS A5.8 BCuP silver brazed.<br />

2. Above ground: ASTM B88, Type K, L or ASTM B75, Type GP; internally tinned:<br />

a. Fittings: ASME B16.18 cast copper, ASME B 16.22, wrought copper, or ANSI B16.26, cast copper,<br />

internally tinned.<br />

b. Joint: ASTM B32, Solder, Grade 95TA or AWS A5.8, Bcup silver brazed.<br />

C. Polyethylene Pipe (below ground only): ASTM D-2513, SDR 11.5.<br />

1. PE Fittings: ASTM D 2683, socket type or ASTM D 3261, butt type with dimensions matching<br />

ASTM D 2513, SDR 11, PE pipe.<br />

2. Joints: Mechanical or Compression fit.<br />

D. Reinforced Epoxy Resin Piping: ASTM D2517.<br />

1. Fittings: ASTM D2517.<br />

2. Joints: Bell and spigot with epoxy resin.<br />

2.2 GAS COCKS<br />

02555-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. 2 Inches and Smaller: 150 psig WOG, bronze body, bronze tapered plug, non-lubricated, Teflon packing, threaded<br />

ends with cast iron curb box, cover, and key.<br />

B. Larger than 2 inches: 125 psig WOG, Steel or Cast iron body and tapered plug, non-lubricated, Teflon packing,<br />

threaded ends, with cast iron curb box, cover, and key.<br />

C. For Applications with Line Pressure Greater than 60 psig: Over 2 Inches: Cast iron body and plug, pressure lubricated,<br />

Teflon packing, flanged ends, with cast iron curb box, cover, and key.<br />

2.3 PRESSURE REGULATING VALVES<br />

A. Single stage, malleable iron body, corrosion-resistant, pressure regulator with atmospheric vent, elevation compensator;<br />

with threaded ends for 2 inches and smaller or flanged ends for larger than 2 inches. Install earthquake<br />

actuated automatic shutoff valve, if required by local code or utility.<br />

B. Capacity: For inlet and outlet gas pressures, specific gravity, and flow rate indicated.<br />

2.4 PROPANE STORAGE TANKS<br />

A. Construction: Closed, welded steel, tested and stamped in accordance with ASME S00081, Sec VIII; minimum<br />

250 psig rating; cleaned, prime coated, and painted with 2 coats of silver anti-rust paint, and supplied with steel<br />

support saddles, pressure gage, tapping for installation of piping and accessories.<br />

B. Vaporizer: 1,000 watts, heating cable bedded in 1-inch of glass fiber insulation and covered by flexible stainless<br />

steel plate, with thermostat in weatherproof box set to turn on at -13 degrees Fahrenheit with manual off-on<br />

switch.<br />

C. Capacity: Diameter and length as shown on Construction Drawings.<br />

2.5 TRACE WIRE<br />

A. Magnetic detectable conductor, brightly colored plastic covering, imprinted with "Natural Gas Service" in large<br />

letters.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify existing conditions.<br />

B. Verify that building service connection and utility gas main size, location, and depth are as indicated on Construction<br />

Drawings.<br />

3.2 PREPARATION<br />

A. Ream pipe ends and remove burrs. Bevel plain end ferrous pipe over 2-inches diameter or thread ferrous pipe 2-<br />

inches diameter and under.<br />

B. Remove scale and dirt, on inside and outside, before assembly.<br />

C. Prepare piping connections with flanges or threading and unions.<br />

D. Comply with NFPA 54 on installation of gas lines.<br />

3.3 BEDDING<br />

A. Excavate pipe trench and place bedding material in accordance with Section 02300.<br />

02555-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


3.4 INSTALLATION - PIPING<br />

A. Maintain a minimum of 12 inches separation of gas line from sewer, water, or storm water piping in accordance<br />

with state or local code.<br />

B. Install piping to conserve space and not interfere with use of site space.<br />

C. Install piping to allow for expansion and contraction without stressing pipe or joints.<br />

D. Install cocks and other fittings as required.<br />

E. Establish elevations of buried piping in accordance with Section 02300.<br />

F. Wrap couplings and fittings of steel pipe with polyethylene tape and heat shrink over pipe in accordance with<br />

AWWA C105.<br />

G. Install trace wire continuous over top of pipe for nonmetallic pipe.<br />

H. Backfill trench in accordance with Section 02300.<br />

I. Center and plumb valve box over valve. Set box cover flush with finished ground surface. Prevent shock or stress<br />

from being transmitted through valve box to valve.<br />

J. Wrap valve and valve box with polyethylene tape and heat shrink or paint valves and valve boxes with red anti-rust<br />

primer and 1 coat of epoxy paint.<br />

3.5 SERVICE CONNECTIONS<br />

A. Provide sleeve in foundation wall for gas service main. Caulk enlarged sleeve watertight.<br />

B. Anchor service main to interior surface of foundation wall.<br />

C. Install service regulator adjacent to building wall in specified location.<br />

D. Install service regulator and riser pipe to prevent undue stress on service pipe. For plastic service pipe, use steel<br />

pipe riser from below ground to regulator.<br />

E. Provide regulator vent with rain and insect proof opening, terminating not less than 5 feet away from building<br />

openings.<br />

3.6 PROPANE TANK INSTALLATION<br />

A. Place tank legs on concrete pad, level within tolerance of 2 inches maximum.<br />

B. Prepare and grade an area outside the tank perimeter, for distance of 6 feet. Grade, place, and compact gravel fill<br />

to compacted depth of 3 inches minimum. Compact in accordance with Section 02300.<br />

C. Provide tank with relief valve, shutoff valve, pressure regulator, pressure gauge, and removable protection cover.<br />

Install piping, shutoff valve, and pressure gauge to underground piping.<br />

D. Set tank regulator to outlet pressure as indicated on Construction Drawings.<br />

E. Install vaporizer to under side of tank and secure to tank with aluminum tray and two stainless steel straps.<br />

F. Install weatherproof control box for vaporizer 40-inches above ground surface. Install on 4-inch x 4-inch cedar<br />

post, driven into ground 40 inches.<br />

02555-4<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


G. Install control wire from vaporizer to control box 20 inches below ground surface. Install service wiring 24 inches<br />

below ground from control box to building.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

02555-5<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec – Civil (Master Site Specifications ) 092809<br />

SECTION 02715 (32 1100) - BASE COURSE<br />

Style Definition: PR1: Justified<br />

Style Definition: PR2<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Aggregate base for asphaltic concrete including sand/shell base and hot-mix sand asphalt base.<br />

Formatted: Bullets and Numbering<br />

B. Related Requirements:<br />

1. Section 01458 - Testing Laboratory Services. Testing by Owner’s Construction Testing Laboratory.<br />

2. Section 02300 – Earthwork: Excavation, Backfill, and Compaction for Pavement subgrade.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM D1557 – Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbs/ft³<br />

(2,700 kN-m/m³)).<br />

2. ASTM D6938 – In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods<br />

(Shallow Depth).<br />

C. Standard Specifications for Public Works Construction (Greenbook).<br />

Formatted: Bullets and Numbering<br />

Deleted: ASTM D698 – Laboratory<br />

Compaction Characteristics of Soil Using<br />

Standard Effort (12 400 ft-lbs/ft³ (600<br />

kN-m/m³)).<br />

Deleted: Asphalt Institute.<br />

D. State Highway Department Standard Specifications.<br />

1.3 QUALITY ASSURANCE<br />

A. A Construction Testing Laboratory (CTL) selected and paid for by the Owner, will be retained to perform<br />

construction testing on site at no cost to the Contractor.<br />

1.4 SUBMITTALS<br />

A. Submit materials certificate to the Owner’s Civil Engineering Consultant and the Owner’s Construction Testing<br />

Laboratory, signed by materials producer and Contractor, certifying that materials comply with, or exceed,<br />

requirements specified herein or on the Construction Drawings. The submittal shall include laboratory test results<br />

for gradation, R-value, durability, sand equivalent, etc. for the applicable aggregate base. The submittal shall be<br />

approved prior to delivery of the aggregate base to the site.<br />

Formatted: Bullets and Numbering<br />

Formatted: Bullets and Numbering<br />

B. Submit certification of base course materials and placement as specified in Parts 2 and 3 hereinafter.<br />

1.5 WEATHER LIMITATIONS<br />

A. Do not place aggregate when base surface temperature is less than 40 degrees F, nor when air temperature is below<br />

45 degrees F. Do not place aggregate when surface is wet or frozen. Do not place aggregate when weather<br />

conditions are unfavorable otherwise.<br />

Formatted: Bullets and Numbering<br />

PART 2 - PRODUCTS<br />

2.1 BASE COURSE MATERIAL<br />

02715-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. Aggregate Base Course: Aggregate base course shall consist of a well graded, durable aggregate uniformly<br />

moistened and mechanically stabilized by compaction. Base course may consist of a granular base (crushed slag,<br />

stone, or gravel, etc), sand/shell base material, or a hot-mix sand asphalt base.<br />

B. Base course shall be as shown on the drawings, or when not shown, shall be as specified herein.<br />

1. Aggregate base below new pavements shall comply with the requirements for a Crushed Miscellaneous<br />

Base (CMB) per the Greenbook or Caltrans Class 2 Aggregate Base.<br />

C. Aggregate shall consist of clean, sound, durable particles of crushed stone, crushed slag, crushed gravel, angular<br />

sand, or other approved material. Aggregate shall be free of lumps of clay, organic matter, and other objectionable<br />

materials or coatings. The portion retained on the No. 4 sieve shall be known as coarse aggregate; that portion<br />

passing the No. 4 sieve shall be known as fine aggregate.<br />

1. Coarse aggregates shall be angular particles of uniform density.<br />

2. Fine aggregates shall be angular particles of uniform density. Fine aggregate shall consist of screenings,<br />

angular sand, crushed recycled concrete fines, or other finely divided mineral matter processed or naturally<br />

combined with the coarse aggregate.<br />

D. Gradation: Comply with Greenbook requirements for CMB or Caltrans Class 2 Aggregate Base.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Contractor shall verify to the Owner in writing that the subgrade has been inspected, tested, and gradients and<br />

elevations are correct, dry, and properly prepared in accordance with Section 02300.<br />

3.2 CONSTRUCTION<br />

A. Perform base course construction in accordance with the applicable State standard specifications or as shown or<br />

specified.<br />

B. Perform base course construction in a manner that will drain the surface properly and prevent runoff from adjacent<br />

areas from draining onto base course construction.<br />

C. Compact base material to not less than 95 percent of the maximum dry density as determined by ASTM D1557<br />

unless otherwise indicated on the Drawings.<br />

D. Construct to thickness indicated on Construction Drawings. The minimum base thickness as shown on drawings<br />

shall be achieved throughout all pavement areas.<br />

1. Granular Base: Apply in lifts or layers not exceeding 8-inches, measured loose.<br />

3.3 FIELD QUALITY CONTROL<br />

A. Responsibilities: Unless otherwise specified, the quality assurance tests and inspections specified below will be<br />

conducted by the Owner’s Construction Testing Laboratory (CTL) at no cost to the Contractor in accordance with<br />

Section 01458. The Contractor shall perform additional testing or inspection as considered necessary by the<br />

Contractor for assurance of quality control. Field testing, frequency, and methods may vary as determined by and<br />

between the Owner and CTL.<br />

B. Field tests for in-place materials will be performed in accordance with the following:<br />

1. Density: Nuclear Method, ASTM D6938. One test in each lift for each 20,000 sq. ft. of in-place base<br />

material area.<br />

2. Base Material Thickness: One test for each 20,000 sq. ft. of in-place base material area. All areas tested<br />

for thickness shall meet or exceed the base thickness shown on the drawings.<br />

02715-2<br />

Formatted: Bullets and Numbering<br />

Formatted: Indent: Left: 43.2 pt,<br />

Hanging: 28.5 pt, Tabs: 72 pt, Left<br />

Deleted: Aggregate base material<br />

requirements from State or other local<br />

highway agency specifications may be<br />

use for aggregate base course for roads,<br />

streets, or similar use pavements if the<br />

following conditions are met:<br />

Percentage of material by weight<br />

passing the No. 200 sieve will not exceed<br />

10.<br />

Portion of the material passing the<br />

No. 40 sieve must have a liquid limit not<br />

greater than 25 and a plasticity index not<br />

greater than 5.<br />

Formatted: Bullets and Numbering<br />

Deleted: The specified gradation<br />

requirements shall apply to the completed<br />

base course. The aggregates shall have a<br />

maximum size of 2 inches and shall be<br />

continuously well graded within the<br />

following<br />

Deleted: limits:<br />

Formatted: Justified<br />

Deleted: Sieve<br />

Designation No. 1 No. 2 No. 3<br />

2 inch 100 ---- ----<br />

1-1/2 inch 70-100 100 ----<br />

1 inch 45-80 60-100 100<br />

1/2 inch 30-60 30-65 40-70<br />

No. 4 20-50 20-50 20-50<br />

No. 10 15-40 15-40 15-40<br />

No. 40 5-25 5-25 5-25<br />

No. 200 0-10 0-10 0-10<br />

<br />

NOTE: Particles having diameters less<br />

than 0.0008 inch shall not be in excess of<br />

3 percent by weight of the total sample<br />

tested.<br />

Hot-mix Sand Asphalt Bases:<br />

Asphalt Institute Type VI, VII, or VIII<br />

Mixes for Hot-mix Sand Asphalt Bases.<br />

Hot-Mix base shall be used only under<br />

asphaltic concrete surfaces.<br />

Formatted: Bullets and Numbering<br />

Formatted: Bullets and Numbering<br />

Deleted: 98<br />

Deleted: optimum<br />

Deleted: ASTM D698 or 95 percent of<br />

optimum density, as determined by<br />

Deleted: Sand/Shell Base: Apply in<br />

lifts or layers not exceeding 4-inches, ... [1]<br />

Formatted: Bullets and Numbering<br />

Deleted: control<br />

Deleted:<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


3. Verify Contractor’s measurements of base course elevation<br />

C. Prepare and distribute test reports as specified in Section 01458.<br />

D. Contractors Responsibilities:<br />

1. Measure base course tolerances no more than 25 ft on center with a rod and level or stringline.<br />

2. Certify in writing to the Owner that base course placement is in accordance with Contract Document<br />

requirements prior to subsequent work thereon.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02715-3<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


Page 2: [1] Deleted<br />

10/6/2011 2:53:00 PM<br />

Sand/Shell Base: Apply in lifts or layers not exceeding 4-inches, measured loose.<br />

Hot-mix Sand Asphalt Bases: Apply in lifts or layers not exceeding 3-inches, measured<br />

loose.


UniSpec II – Civil (Master Site Specifications) 100711<br />

SECTION 02740 (32 1216) - ASPHALT CONCRETE PAVING<br />

Style Definition: PR2<br />

Formatted: Left: 54 pt, Right: 54<br />

pt, Top: 54 pt, Bottom: 36 pt<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Asphalt concrete binder and surface course.<br />

B. Related Requirements:<br />

1. Section 02300 - Earthwork.<br />

2. Section 02715 - Base Course.<br />

3. Section 02765 - Pavement Markings.<br />

4. Section 02770 - Curbs and Sidewalks.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. The Asphalt Institute (AI):<br />

1. MS-2 - Mix Design Methods For Asphalt Concrete And Other Hot-Mix Types.<br />

C. State of California Department of Transportation (Caltrans)<br />

1. Standard Specifications for Construction and Materials – Local in the state where project is located.<br />

Deleted: Highway Department Standard<br />

Specifications<br />

D. ASTM International (ASTM):<br />

1. ASTM D1188 - Bulk Specific Gravity and Density of Compacted Bituminous Mixtures Using Coated<br />

Samples.<br />

2. ASTM D2041 - Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures.<br />

3. ASTM D2950 - Density of Bituminous Concrete in Place by the Nuclear Methods.<br />

4. ASTM D2726 - Bulk Specific Gravity and Density of Non-Absorptive Compacted Bituminous Mixture.<br />

5. ASTM D5444 - Mechanical Size Analysis of Extracted Aggregate.<br />

E. American Association of State Highway and Transportation Officials (AASHTO):<br />

1. AASHTO M017 - Mineral Filler for Bituminous Paving Mixtures.<br />

2. AASHTO M140 - Emulsified Asphalt.<br />

3. AASHTO M208 - Cationic Emulsified Asphalt.<br />

4. AASHTO M320 - Performance-Graded Asphalt Binder<br />

5. AASHTO M323 - Superpave Volumetric Mix Design<br />

6. AASHTO T164 - Quantitative Extraction of Asphalt Binder from Hot-Mix Asphalt (HMA)<br />

7. AASHTO T166 - Bulk Specific Gravity of Compacted Hot-Mix Asphalt Mixtures Using Saturated Surface-<br />

Dry Specimens<br />

8. AASHTO T209 – Theoretical Maximum Specific Gravity and Density of Hot Mix Asphalt (HMA)<br />

9. AASHTO T245 - Resistance to Plastic Flow of Bituminous Mixtures Using Marshall Apparatus.<br />

10. AASHTO T275 - Bulk Specific Gravity of Compacted Hot-Mix Asphalt Mixtures Using Paraffin-Coated<br />

Specimens<br />

11. AASHTO T308 - Asphalt Content of Hot-Mix Asphalt (HMA) by the Ignition Method.<br />

12. AASHTOT312 - Preparing and Determining the Density of Hot-Mix Asphalt (HMA) Specimens by Means<br />

of the Superpave Gyratory Compactor.<br />

13. AASHTO T331 - Bulk Specific Gravity and Density of Compacted Bituminous Mixtures Using Automatic<br />

Vacuum Sealing Method<br />

F. National Asphalt Pavement Association (NAPA):<br />

1. IS 123 – Recycling Hot-Mix Asphalt Pavements<br />

02740-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


2. IS 128 - HMA Pavement Mix Type Selection Guide<br />

1.3 QUALITY ASSURANCE<br />

A. A Construction Testing Laboratory (CTL) selected and paid by Owner, will be retained to perform construction<br />

testing of in-place asphalt concrete courses for compliance with requirements for thickness, compaction, and surface<br />

smoothness at no cost to the Contractor as specified in Part 3 hereinafter.<br />

B. Pre-installation Meeting: Convene a pre-installation meeting at the site at least two weeks prior to commencing<br />

work of this Section. Require attendance of parties directly affecting work of this Section, including, but not limited<br />

to, the Owner's representative, CTL’s representative and inspector, Contractor, paving sub-contractor and job<br />

foreman.<br />

1. Contact Wal-Mart Construction Manager three weeks prior to pre-installation conference to confirm schedule.<br />

2. Record discussions of meeting and decisions and agreements (or disagreements) reached, and furnish copy<br />

of record to each party attending. Review foreseeable methods and procedures related to paving work, including<br />

the following:<br />

a. Review preparation and installation procedures and coordinating and scheduling required with related<br />

work.<br />

b. Review proposed sources of paving materials, including capabilities and location of plant that will<br />

manufacture hot-mix asphalt.<br />

c. Tour, inspect and discuss condition of subgrade, drainage structures, and other preparatory work.<br />

d. Review requirements for protecting paving work, including restriction of traffic during installation<br />

period and for remainder of construction period.<br />

e. Review and finalize construction schedule and verify availability of materials, installer's personnel,<br />

equipment, and facilities needed to make progress and avoid delays.<br />

f. Review paving requirements (drawings, specifications and other contract documents).<br />

g. Review required submittals, both completed and yet to be completed.<br />

h. Review required inspections, testing procedures.<br />

i. Review weather and forecasted weather conditions, and procedures for coping with unfavorable<br />

conditions.<br />

j. Review safety precautions relating to placement of paving.<br />

Formatted: Hyphenate, Tabs: Not<br />

at 468 pt<br />

1.4 SUBMITTALS<br />

A. Submit mix designs to the Civil Engineering Consultant of Record at least 30 days prior to beginning asphalt paving<br />

operations. Mix designs shall be signed and stamped by a California Registered Civil Engineer. Mix designs<br />

over one year old will not be accepted by Owner. Mix design submittal shall follow the format as recommended<br />

by Asphalt Institutes Manual MS-2 and include the following:<br />

1. Type and Name of mix.<br />

2. Gradation and Laboratory Testing of Aggregates.<br />

3. Optimum asphalt content.<br />

4. Grade of asphalt binder.<br />

5. Volumetric properties.<br />

6. References to local State Highway Department Specification for each material when applicable.<br />

Formatted: Bullets and Numbering<br />

Deleted: Gradation Analysis.<br />

B. Submit approved mix designs and laboratory test results to CTL signed by the materials producer and Contractor<br />

certifying materials and mix ratios conform to the requirements specified herein.<br />

C. The CTL shall submit all certificates furnished with the CTL Reports.<br />

1.5 PROJECT CONDITIONS<br />

A. Weather Limitations:<br />

1. Apply prime and tack coats when ambient or base surface temperature is above 40 F, and when temperature<br />

has been above 35 F for 12 hours immediately prior to application. Do not apply when base is wet, contains<br />

excess moisture, during rain, or when frozen.<br />

02740-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


2. Construct asphalt concrete paving when ambient temperature is above 40 F.<br />

B. Maintain access for vehicular and pedestrian traffic as required for other construction activities. Utilize temporary<br />

striping, flagmen, barricades, warning signs, and warning lights as required.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Aggregate: Use locally available materials and gradations that meet local State Highway Department Specifications<br />

and exhibit satisfactory records of previous installations. All aggregate requirements, including those for<br />

quality, shall meet the requirements of these specifications.<br />

B. Asphalt Binder: Asphalt binder shall be a performance-graded (PG) binder, meeting the requirements of M 320,<br />

which is appropriate for the climate and traffic-loading conditions at the site of the paving project and in compliance<br />

with the local State Highway Department Specifications for that location, or as specified by the contract documents.<br />

1. Design reliability shall be 85% for the high- and low-temperature performance.<br />

2. The minimum required PG binder shall be that which satisfies the required design reliability using the<br />

pavement temperature data determined.<br />

3. The high-temperature grade shall be increased by one grade equivalent to accommodate low traffic speeds.<br />

Deleted: those in AASHTO M323 for<br />

the specified traffic level.<br />

C. Prime Coat: Asphalt emulsion penetrating prime coat consisting of either SS-1h, Asphalt Emulsion Prime (AEP),<br />

or equivalent.<br />

D. Tack Coat: Emulsified asphalt; AASHTO M140 or AASHTO M208, SS-1h, CSS-1, or CSS-1h, may be diluted<br />

with up to 1 part water to 1 part asphalt.<br />

E. Mineral Filler: Rock or slag dust, hydraulic cement, or other inert material complying with AASHTO M17, if recommended<br />

by local State Highway Department Specifications.<br />

F. Reclaimed Asphalt Pavement (RAP): RAP may be used in amounts not to exceed 20% by wt. The mix design<br />

shall contain the percentage of RAP that is to be used in the production. Production procedures using RAP material<br />

shall conform to NAPA IS 123. Additional RAP provisions shall be as follows:<br />

1. Material-handling machinery shall not drive on the RAP stockpiles.<br />

2. RAP maximum top size aggregate introduced into the mix shall be greater than 1-1/2 inches.<br />

3. Dust (fines) in the RAP, when added to the virgin aggregate, shall not exceed the requirements of the virgin<br />

mix design.<br />

4. Moisture content shall be monitored to assure that the material can be thoroughly dried as it is processed.<br />

5. Stockpiles shall be left uncovered or stored under the roof of an open-sided building.<br />

6. Material handling front-end loader operators shall be experienced in handing RAP materials.<br />

7. RAP shall be loaded in the cold feed bins in small consistent quantities without causing the material to<br />

compact in the bin.<br />

8. RAP shall not be held in the bin for extended periods of time, especially on hot, humid days.<br />

9. During production, RAP material shall not be allowed to contact open flame.<br />

2.2 AGGREGATE SIZE REQUIREMENTS - SUPERPAVE MIX<br />

A. Nominal Maximum Size: The combined aggregate shall have a nominal maximum aggregate size of 4.75 to 19.0<br />

mm for surface courses and no larger than 25 mm for subsurface courses in accordance with Table 3 of AASHTO<br />

M323 unless noted otherwise. Selection of the appropriate nominal maximum aggregate size mixture shall be in<br />

accordance with NAPA IS 128.<br />

B. Gradation Classification: The combined aggregate gradation shall be classified as coarse-graded when it passes<br />

below the Primary Control Sieve (PCS) control point as defined in Table 4 of AASHTO M323. All other gradations<br />

shall be classified as fine-graded.<br />

02740-3<br />

Deleted: .<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


2.3 ASPHALT-AGGREGATE MIXTURE<br />

A. Superpave Mix:<br />

1. The initial, design, and maximum number of gyrations shall conform to the following:<br />

Superpave Gyratory Compaction Effort<br />

Design ESALs<br />

Compaction Parameters<br />

(Million) N initial N design N max<br />

< 0.3 6 50 75<br />

0.3 < 3 7 75 115<br />

2. The design, when compacted in accordance with T 312, shall meet the relative density, VMA, VFA, and<br />

dust-to-binder ratio requirements specified in the following table. Air voids at N (design) shall be 4.0 percent.<br />

Superpave HMA Design Requirements<br />

Design<br />

ESALs a<br />

Required Relative<br />

Density, Percent of<br />

Theoretical Maximum<br />

Specific Gravity<br />

Voids in the Mineral Aggregate (VMA)<br />

Percent Minimum<br />

Nominal Maximum Aggregate Size, mm<br />

VFA<br />

Range b ,<br />

Dust-to-<br />

Binder<br />

Ratio<br />

(Million) N initial N design N max 19.0 12.5 9.5 4.75 Percent Range c<br />

Min.<br />

Formatted: Don't keep with next,<br />

Don't keep lines together<br />

Formatted: Indent: Left: 72 pt<br />

Formatted: Indent: Left: 72 pt,<br />

Don't keep with next, Don't keep<br />

lines together<br />

Formatted: Don't keep with next,<br />

Don't keep lines together<br />

B. Marshall Mix:<br />

1. The design shall meet the requirements specified in the following table.<br />

Marshall HMA Design Requirements<br />

02740-4<br />

Formatted: Indent: Left: 72 pt<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


Design<br />

ESALs a<br />

(Million)<br />

Compaction<br />

Effort b<br />

(Blows)<br />

Design<br />

Air<br />

Voids,<br />

Percent<br />

Voids in Mineral Aggregate<br />

(VMA), Percent Minimum<br />

3/4 in. 1/2 in. 3/8 in.<br />

VFA<br />

Range,<br />

Percent<br />

Minimum<br />

Stability,<br />

pounds<br />

Flow, inches<br />

< 0.3 50 3-5 13.0 14.0 15.0 70-82 1000 0.08 – 0.16<br />

0.3 < 3 75 3-5 13.0 14.0 15.0 20-82 1500 0.08 – 0.16<br />

a Design ESALs are the anticipated project traffic level expected on the design project over a 20-year period.<br />

Regardless of the actual design life of the project, determine the design ESALs for 20 years.<br />

b Flat-foot, static base hammer.<br />

2. Aggregate gradation and asphalt content tolerances for acceptance of plant produced mix shall be as follows:<br />

Property Maximum tolerance<br />

for any one<br />

sample<br />

Average of samples<br />

for given mix<br />

for four or more<br />

samples<br />

3/4” (19mm) ±7.0 ±4.0<br />

1/2” (12.5 mm) ±7.0 ±4.0<br />

#4 (4.75mm) ±6.0 ±3.5<br />

#8 (2.36mm) ±6.0 ±3.5<br />

#50 (0.3mm) ±4.0 ±2.3<br />

#200 (0.075mm) ±2.0 ±1.2<br />

Asphalt Content ±0.4 ±0.3<br />

Air Voids ±2.0 ±1.2<br />

VMA > Min. > Min.<br />

C. California Department of Transportation (Caltrans) Design: Hot Mix Asphalt design shall meet the requirements<br />

of a Type B Mix in accordance with Section 39 of the State of California Standard specifications. The base course<br />

shall comply with the requirements of a ¾ inch maximum medium gradation and the top course shall meet the requirements<br />

of a ½ inch maximum medium gradation.<br />

Formatted: Bullets and Numbering<br />

2.4 EQUIPMENT<br />

A. Equipment necessary for the paving of asphalt concrete shall be on the project prior to beginning paving operations.<br />

B. Maintain equipment in satisfactory operating condition and correct breakdowns in manner that will not delay or be<br />

detrimental to the schedule of paving operations.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that the prepared base material has been inspected, tested, and gradients and elevations are correct, dry, and<br />

properly prepared in accordance with Section 02715.<br />

3.2 PREPARATION<br />

A. Proof roll prepared base material surface to check for unstable areas in accordance with Section 02300 including<br />

documentation and re-proof rolling as required. Paving work shall begin only after unsuitable areas have been corrected<br />

and are ready to receive paving.<br />

B. Remove loose material from compacted base material surface immediately before applying prime coat.<br />

C. Establish and maintain required lines and elevations.<br />

02740-5<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. Cover the surfaces of curbs, gutters, manholes and other structures on which the asphalt concrete mixture will be<br />

placed, with a thin, uniform coat of liquid asphalt. Where the asphalt concrete mixture will be placed against the<br />

vertical face of an existing pavement, clean the vertical face to remove foreign substances and apply a coating of<br />

liquid asphalt at a rate of approximately 0.25 gallons per square yard.<br />

E. Density Control Strips:<br />

1. Prior to beginning placement of asphalt, construct asphalt concrete density control strips.<br />

2. Source and type of material, material requirements, and laydown and compaction equipment used for compaction<br />

shall be the same as that to be used in the project.<br />

3. The subgrade or pavement layer upon which the control strip is constructed shall tested by the CTL prior to<br />

construction of the control strip.<br />

4. The control strip shall be a minimum of 250 linear feet long and one paver width wide.<br />

5. Rolling the control strip shall continue until no appreciable increase in density is obtained by additional<br />

coverages.<br />

6. Upon completion of rolling, the Contractor shall use a nuclear testing device to establish the mean density<br />

of the control strip. The mean density will be based on 10 tests taken at randomly selected sites within the<br />

control strip area. The nuclear gauge will be calibrated with the average of 3 cores taken from the same area.<br />

The average of the cores shall meet the specified density requirements. The calibration factor between<br />

the average nuclear density and average core density shall be applied to the Contractor’s nuclear gauge for<br />

Contractor’s density monitoring.<br />

Deleted: .<br />

3.3 APPLICATION<br />

A. Prime Coat:<br />

1. Apply to base material surfaces at least 24 hours in advance.<br />

2. Apply at a rate of 0.25 – 0.30 gal per sq. yd. over compacted base material. Apply to penetrate and seal but<br />

not flood surface.<br />

3. Take necessary precautions to protect adjacent areas from over spray.<br />

4. Cure and dry as long as necessary to attain penetration of compacted base and evaporation of volatile substances.<br />

B. Tack Coat:<br />

1. Apply to contact surfaces of previously constructed asphalt concrete base courses or Portland cement concrete<br />

and surfaces abutting or projecting into asphalt concrete or into asphalt concrete pavement.<br />

2. Apply tack coat to asphalt concrete base course or sand asphalt base course. Apply emulsified asphalt tack<br />

coat between each lift or layer of full depth asphalt concrete and sand asphalt bases and on surface of bases<br />

where asphalt concrete paving will be constructed.<br />

3. Apply at rate which produces a residual of asphalt cement between 0.04 and 0.06 gal per sq. yd of surface.<br />

4. Allow drying until at proper condition to receive paving.<br />

3.4 ASPHALT CONCRETE PLACEMENT<br />

A. Place asphalt concrete mixture on completed, compacted underlying surface, spread, and strike off. Spread mixture<br />

at the minimum ambient temperature that will allow the required density to be achieved.<br />

B. Whenever possible, spread pavement by finishing machine; however, inaccessible or irregular areas may be placed<br />

by hand methods. Spread hot mixture uniformly to required depth with hot shovels and rakes. After spreading,<br />

carefully smooth hot mixture to remove segregated course aggregate and rake marks. Rakes and lutes used for<br />

hand spreading shall be type designed for use on asphalt mixtures. Do not dump loads faster that they can be properly<br />

spread. Workers shall not stand on loose mixture while spreading.<br />

C. Placement and routing of hauling and placing equipment shall be conducted in a manner to avoid tire tracking of<br />

bituminous material onto existing paved surfaces.<br />

D. Paving Machine Placement: Apply successive lifts of asphalt concrete in transverse directions except when placing<br />

within small areas, parallel lifts may be placed when considered more practical. Joints of successive parallel lifts<br />

shall be offset a minimum of 2 feet. Place surface course parallel to flow of traffic. Place asphalt paving in typical<br />

02740-6<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


strips not less than 10'-0" wide. Asphalt concrete pavement, including base and surface course, shall be placed in<br />

two or more lifts as indicated on drawings. Pavement thicknesses shall be thickness shown on the drawings for<br />

each course but not less than 1-1/2 inch nor more than 3 inches for each lift.<br />

3.5 ROLLING AND COMPACTION<br />

A. After being spread, mixture shall be compacted by rolling as soon as it will bear the weight of rollers without undue<br />

displacement. Number, weight, types of rollers, and sequences of rolling operations shall be such that the required<br />

density and surface are consistently attained while the mixture is in workable condition.<br />

B. Compact mixture with hot hand tampers or vibrating plate compactors in areas inaccessible to rollers.<br />

C. Breakdown Rolling: Perform breakdown or initial rolling immediately following rolling of joints and outside edge.<br />

Check surface after breakdown rolling and repair displaced areas by loosening and filling with hot material.<br />

D. Intermediate Rolling: Follow breakdown rolling as soon as possible while mixture is hot. Continue second rolling<br />

until mixture has been thoroughly compacted as follows:<br />

1. Minimum (change from “target”) Average Density: 93 percent of theoretical maximum density according<br />

to AASHTO T209 or ASTM D2041, with no individual test less than 91 percent nor greater than 97 percent.<br />

Formatted: Hyphenate<br />

E. Finish Rolling: Perform finish rolling while mixture is still warm enough for removal of roller marks. Continue<br />

rolling until roller marks are eliminated and course has attained maximum density.<br />

F. Patching: Remove and replace paving areas mixed with foreign materials and defective areas. Cut out such areas<br />

and fill with fresh, hot asphalt concrete. Compact by rolling to maximum surface density and smoothness.<br />

G. Protection: After final rolling, do not permit vehicular traffic on pavement until it has cooled and hardened. Erect<br />

barricades to protect paving from traffic until mixture has cooled enough not to become marked. Any masked or<br />

marred finish surfaces shall be repaired or smoothed.<br />

3.6 JOINTS<br />

A. General: Place each asphalt paving layer as continuous as possible to keep the number of joints to a minimum.<br />

Create joints between old and new pavement, between successive days work, and where the mixture has become<br />

cold (less than 140 degrees F). Make these joints in such a manner as to create a continuous bond between the old<br />

and new pavement construction courses.<br />

B. Construction joints shall have same texture, density, and smoothness as other sections of asphalt concrete course.<br />

C. Transverse Joints: If placing of material is discontinued or if material in place becomes cold, make a joint running<br />

perpendicular to the direction traveled by the paver. Before placement continues, trim the edge of the previously<br />

placed pavement to a straight line perpendicular to the paver and cut back to expose an even vertical surface for<br />

the full thickness of the course. When placement continues, position the paver on the transverse joint so that sufficient<br />

hot mixture will be spread in order to create a joint after rolling that conforms to the required smoothness. If<br />

the temperature of the previously placed pavement material drops below 140 degrees F before paving is resumed,<br />

give the exposed vertical face a thin coat of liquid asphalt just before paving is continued.<br />

D. Longitudinal Joints: Coat longitudinal joints that are not completed before the previously laid mixture has cooled<br />

to a temperature below 140 degrees F, with liquid asphalt just before paving is continued.<br />

3.7 FIELD QUALITY CONTROL<br />

A. Responsibilities: Unless otherwise specified to be performed by the Contractor, the quality assurance tests and inspections<br />

specified below will be conducted by the Owner’s Construction Testing Laboratory (CTL) at no cost to<br />

the Contractor in accordance with Section 01458. Field testing, frequency, and methods may vary as determined<br />

by and between the Owner and CTL. The Contractor shall perform additional testing or inspection as considered<br />

02740-7<br />

Deleted: control<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


necessary by the Contractor for assurance of quality control including use of a nuclear density gauge to establish<br />

rolling patterns and monitor in-place density.<br />

B. Core Sampling and Testing: Asphalt surface and base courses shall be randomly cored at minimum rate of 5 cores<br />

per day’s placement per mix type, but not less than 5 cores in light duty areas and 5 cores in heavy-duty areas shall<br />

be obtained. Asphalt concrete pavement samples shall be tested for conformance with density and thickness requirements.<br />

Cores shall be cut from minimal loading areas representative of project.<br />

C. Coring holes shall be immediately filled by the Contractor with full depth, hot-mix asphalt concrete or non-shrink<br />

grout tinted to match the surrounding pavement.<br />

D. Surface Smoothness Test: In areas of obvious depressions or bumps, suspect areas of each lift shall be checked<br />

with a 10’-0” straightedge both parallel with, and at right angles to, centerline of the paved area. The variation of<br />

the surface between two contact points shall not exceed 1/4-inch.<br />

E. Thickness Test: The Contractor shall measure pavement thickness behind the paver at the beginning of and during<br />

pavement placing operations to assure proper thickness. The CTL will measure thickness of each core sample<br />

taken. At each core location, the thickness of the course shall meet or exceed the thickness shown. If the thickness<br />

of a lower course of asphalt is less than the thickness shown, it shall be identified as a deviation and recorded. The<br />

contractor shall either remove and replace the deficient pavement or increase the thickness of the upper course so<br />

that the total thickness of the pavement meets or exceeds the design thickness, provided that the specified compaction<br />

of the lower lift is achieved. If the Contractor elects to increase the thickness of the upper course, three additional<br />

cores shall be taken in the area after the upper course is laid to verify that the total thickness is achieved.<br />

F. Field density test for in-place materials:<br />

1. Density tests shall be conducted on each core sample taken in accordance with ASTM D1188 or D2726<br />

(AASHTO T166, T275, T331) as applicable.<br />

2. In-place density tests by nuclear method in accordance with ASTM D2950 shall also be taken by the Contractor<br />

as necessary to assure the specified density is obtained. Nuclear density shall be correlated with<br />

ASTM D1188 or D2726 or AASHTO T166, T275, T331 as applicable.<br />

3. Density tests on courses to be overlaid by subsequent courses shall be performed within 48 hours prior to<br />

placement of next lift. If inclement weather occurs after testing, retest prior to placement of next lift.<br />

G. Volumetric Properties: Obtain test samples from the truck at the asphalt plant. Mixture samples shall be taken at<br />

least 2 times for every 8 hour day.<br />

1. Superpave Mix: Compact into specimens in accordance with AASHTO T312. Test each specimen for determination<br />

of relative density, VMA, VFA, and dust-to-binder ratio.<br />

2. Marshall Mix: Compact into specimens using compactive blows equal to mix design per side with the Marshall<br />

hammer as described in AASHTO T245. Temperature shall be equal to temperature at paving machine<br />

with reheating. Test each specimen for determination of laboratory air voids, Marshall stability, and<br />

flow.<br />

3. Hveem Mix: Compact specimens in accordance with CTM 309. Test each specimen for determination of<br />

laboratory air voids, VMA, VFA and stability.<br />

H. Check surface areas as necessary to identify ponding areas.<br />

Formatted: Font color: Auto<br />

Formatted: Bullets and Numbering<br />

I. Asphalt Content and Aggregate Gradation: Asphalt content extraction and gradation of extracted aggregate testing<br />

shall be performed in accordance with AASHTO T 308 or AASHTO T164 and ASTM D5444 respectively and local<br />

State Highway Department Specifications requirements. At least two asphalt content and two gradation tests<br />

shall be taken for each 2000 tons but not less than two tests each for each day pavement is placed.<br />

J. Areas of deficient paving, including compaction, smoothness, thickness, and asphalt mixture, shall be delineated,<br />

removed, and replaced in compliance with specifications requirements. Alternative remedial or corrective measures<br />

for repair of deficient paving may be allowed provided a plan of corrective action is submitted in the form of<br />

a Request For Information (RFI) and the plan is approved by the CEC. Retesting required as a result of failed initial<br />

tests shall be at the Contractor’s expense.<br />

02740-8<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


K. The Contractor shall certify in writing that asphalt placement is in accordance with specification requirements.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02740-9<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec – Civil (Master Site Specifications) 122209<br />

SECTION 02751 (32 1313) - CONCRETE PAVING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Preparation and placement of Portland cement concrete parking areas.<br />

2. Preparation and placement of Portland cement concrete roads and entrances.<br />

3. Aggregate base below Portland cement concrete paving.<br />

Deleted: slab<br />

B. Related Requirements:<br />

1. Section 01330 - Submittal Procedures:<br />

2. Section 01458 - Testing Laboratory Services. Procedures for inspection, testing, and documentation by<br />

Owner furnished testing laboratory.<br />

3. Section 02300 - Earthwork: Excavation, backfill, compaction for subgrades.<br />

4. Section 02765 - Pavement Markings.<br />

5. Section 03310 - Structural Concrete and Exterior Concrete Slabs: Truckwell slab, compactor and compressor<br />

equipment pads, drive-thru pharmacy driveway, and Automotive Center apron.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Concrete Institute (ACI):<br />

1. ACI 117 - Tolerances for Concrete Construction and Materials and Commentary.<br />

2. ACI 301 - Structural Concrete.<br />

3. ACI 305.1- Hot Weather Concreting.<br />

4. ACI 306.1- Cold Weather Concreting.<br />

5. ACI 308.1 - Curing Concrete.<br />

6. ACI 318 - Building Code Requirements for Reinforced Concrete and Commentary.<br />

C. American Society for Testing and Materials (ASTM):<br />

1. ASTM A 36 - Structural Steel.<br />

2. ASTM A185 - Steel Welded Wire Fabric, Plain, for Concrete Reinforcement.<br />

3. ASTM A615 - Deformed and Plain Billet-Steel for Concrete Reinforcement.<br />

4. ASTM C31 - Making and Curing Concrete Test Specimens in the Field.<br />

5. ASTM C33 - Concrete Aggregates.<br />

6. ASTM C 39 - Comprehensive Strength of Cylindrical Concrete Specimens.<br />

7. ASTM C42 - Obtaining and Testing Drilled Cores and Sawed Beams of Concrete.<br />

8. ASTM C94 - Ready-Mixed Concrete.<br />

9. ASTM C138 - Unit Weight, Yield, and Air Content (Gravemetric) of Concrete.<br />

10. ASTM C143 - Slump of Hydraulic Cement Concrete.<br />

11. ASTM C150 - Portland Cement.<br />

12. ASTM C172 - Sampling Freshly Mixed Concrete.<br />

13. ASTM C231 - Air-Content of Freshly Mixed Concrete by the Pressure Method.<br />

14. ASTM C260 - Air-Entraining Admixtures for Concrete.<br />

15. ASTM C309 - Liquid Membrane-Forming Compounds for Curing Concrete.<br />

16. ASTM C403 - Time of Setting of Concrete Mixtures by Penetration Resistance<br />

17. ASTM C618 - Fly Ash and Raw or Calcined Natural Pozzolan for use as a Mineral Admixture in Portland<br />

Cement Concrete.<br />

18. ASTM C920 - Elastomeric Joint Sealants.<br />

19. ASTM C989 - Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars.<br />

20. ASTM C1064 - Temperature of Freshly Mixed Portland Concrete Cement.<br />

21. ASTM C1218 - Water-Soluble Chloride in Mortar and Concrete.<br />

22. ASTM C1602 - Mixing Water used in the Production of Hydraulic Cement Concrete.<br />

02751-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


23. ASTM D98 - Calcium Chloride<br />

24. ASTM D994 - Preformed Expansion Joint Filler for Concrete (Bituminous).<br />

25. ASTM D1241 - Materials for Soil-Aggregate Subbase, Base and Surface Courses<br />

26. ASTM D1557 – Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbs/ft³<br />

(2,700 kN-m/m³))<br />

27. ASTM D1751 - Preformed Expansion Joint Fillers for Concrete Paving and Structural Construction<br />

(Nonextruding and Resilient Bituminous Types).<br />

28. ASTM D1752: Preformed Sponge Rubber and Cork Expansion Joint Fillers for Concrete Paving and<br />

Structural Construction.<br />

29. ASTM D2628 - Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements.<br />

30. ASTM D3575: Standard Test Methods for Flexible Cellular Materials Made From Olefin Polymers.<br />

Deleted: ASTM D 698 - Moisture-<br />

Density Relations of Soils and Soil-<br />

Aggregate Mixtures Using 5.5 lb (2.49<br />

Kg) Hammerand 12-in (305 mm) Drop.<br />

Formatted: Bullets and Numbering<br />

Formatted: Indent: Left: 43.2 pt,<br />

Hanging: 28.8 pt<br />

D. Federal Specifications (FS):<br />

1. FS HH-F-341 - Fillers, Expansion Joint: Bituminous (Asphalt & Tar)<br />

E. International Code Council, Inc.:<br />

1. International Building Code (IBC).<br />

F. State Highway Department Standard Specifications.<br />

G. National Ready-Mixed Concrete Association:<br />

1. NRMCA Inspection Standards<br />

1.3 SUBMITTALS<br />

A. Submittal Procedures: Unless otherwise specified herein, submit in accordance with procedures specified in Section<br />

01330.<br />

B. Obtain CEC approval for Mix Design and Pavement Joint and Placement Plan prior to commencement of work.<br />

C. Submit submittal items required within this section in a single submittal. Do not submit submittals of this section<br />

together with submittals in section 03310 or any other section. Identify submittals explicitly in accordance with<br />

Procedures paragraphs in Section 01330.<br />

D. Laboratory Analysis for Aggregate Base: Submit current sieve analysis, R-value, Durability and Sand Equivalent<br />

report of material sampled and tested within the last 60 days of submittal date for the aggregate base.<br />

E. Concrete Batch Plant Certifications: Submit name and address of the concrete supplier’s batch plant and plant certification(s)<br />

by National Ready-Mix Concrete Association and/or State Department of Transportation.<br />

F. Mix Design: Fill out and submit attached Concrete Mix Design Submittal Form. Submit three copies of each proposed<br />

mix design in accordance with ACI 301, Sections 3.9 "Proportioning on the basis of previous field experience<br />

or trial mixture", or 3.10 "Proportioning based on empirical data". Submit separate mix design for concrete to<br />

be placed by pumping in addition to the mix design for concrete to be placed directly from the truck chute. Submit<br />

mix design to the Civil Engineering Consultant of Record, the Wal-Mart Construction Testing Laboratory, and the<br />

Wal-Mart Assigned Concrete Sub-Consultant. Include all applicable information shown on the Mix Design Submittal<br />

Form including the following:<br />

1. Proportions of cementitious materials, fine and coarse aggregate, and water.<br />

2. Water-cementitious material ratio, 28-day compressive design strength, slump, and air content.<br />

3. Type of cement, fly ash, slag and aggregate.<br />

4. Individual aggregate gradations.<br />

5. Type and dosage of admixtures.<br />

6. Special requirements for pumping.<br />

7. Range of ambient temperature and humidity for which design is valid.<br />

8. Special characteristics of mix which require precautions in mixing, placing, or finishing techniques to<br />

achieve finished product specified.<br />

9. Materials and methods for curing concrete.<br />

02751-2<br />

Deleted: EDITOR NOTE: The CEC<br />

shall coordinate with Wal-Mart Assigned<br />

Concrete Sub-Consultant on Mix Design<br />

and Joint Placement Plan approval.<br />

Formatted: Bullets and Numbering<br />

Formatted: Font color: Auto<br />

Deleted: Sieve Analysis for Aggregate<br />

Base: Submit current sieve analysis<br />

report, sampled and tested within the last<br />

60 days of submittal date, for aggregate<br />

base and choker material.<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


G. Attachments to Concrete Mix Design: Submit the following as attachments to be included with the Concrete Mix<br />

Design:<br />

1. Cementitious materials mill test reports for the following:<br />

a. Portland cement<br />

b. Fly ash<br />

c. Slag<br />

2. Designation, type, quality, and source (natural or manufactured) of coarse and fine aggregate materials.<br />

3. Sieve Analysis Reports: Provide separate sieve analysis of percentages passing for coarse and fine aggregate.<br />

Show values for each sieve size shown on the mix design form. Do not leave any line blank. Sieve<br />

analysis sampling and testing for each aggregate source shall be conducted within 60 days of concrete<br />

submittal date.<br />

4. Aggregate Supplier Statement:<br />

a. Stating if aggregate is possibly alkali-reactive based on tests or past service.<br />

b. Stating if aggregate can possibly cause pop-outs, “D” cracking, or other disruptions due to moisture<br />

gain, freezing, or other mechanisms, based on tests or past service.<br />

5. Product data for the following concrete materials admixtures:<br />

a. Water reducing<br />

b. Set retarding<br />

c. Set accelerating<br />

d. Data indicating chloride ion content information for each admixture<br />

6. Concrete compressive strength data as required by ACI 318.<br />

7. Concrete supplier approval of mix design.<br />

8. Chloride-Ion Content: Measured water-soluble chloride-ion content (percent by weight of cementitious<br />

materials) in accordance with ASTM C1218.<br />

9. Time of Initial Setting: Initial setting time in accordance with ASTM C403.<br />

H. Product Data: Submit certified laboratory test data or manufacturer’s certificates and data for the items listed below<br />

certifying that materials are in conformance requirements specified herein. Submit to the Civil Engineering<br />

Consultant of Record and the Construction Testing Laboratory for review and approval and within 7 calendar days<br />

after receipt of Notice-to-Proceed. In addition, for projects with all-concrete parking lots, submit to the Wal-Mart<br />

Assigned Concrete Sub-Consultant.<br />

1. Portland cement concrete mix design(s)<br />

2. Type and source of Portland cement, fly ash, and slag<br />

3. Aggregate gradations<br />

4. Joint back-up material<br />

5. Soft preformed joint filler<br />

6. Pavement joint sealant<br />

7. Dowel bars<br />

8. Tie bars<br />

9. Reinforcing steel bars<br />

10. Welded wire fabric<br />

11. Air entraining admixtures<br />

12. Water-reducing, set-retarding, and set-accelerating admixtures (if used)<br />

I. Pavement Joint and Placement Plan: For projects with all-concrete parking lots, provide a placement plan identifying<br />

the items listed below. In addition to submission to CEC, submit to Wal-Mart Assigned Concrete Sub-<br />

Consultant.<br />

1. Concrete truck access location.<br />

2. Extent of placements including width, length, slab placement area and volume.<br />

3. Locations of construction joints.<br />

4. Location of sawn contraction joints if different from those shown on the civil drawings.<br />

J. Pre-Slab Installation Meeting:<br />

1. Provide record of notification of pre-slab meeting including company name, persons contacted, and date<br />

and method of contact.<br />

2. Provide meeting minutes to all participants and Wal-Mart Construction Manager including sign-in sheet.<br />

K. Delivery Tickets:<br />

1. Copies of delivery tickets for each load of concrete delivered to site.<br />

02751-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


2. Indicate information required by ASTM C 94 on each ticket including additional information required for<br />

slabs.<br />

3. Information on ticket shall include quantities of material batched including the amount of free water in the<br />

aggregate and the quantity of water that can be added at the site without exceeding the maximum water<br />

cementitious ratio of the approved mix design. Aggregate moisture corrections shall be based on ASTM<br />

definitions of aggregate moisture content and absorption.<br />

4. Mix identification number on ticket shall match number on submitted and approved mix design.<br />

5. Submit copies to Wal-Mart Testing Laboratory with each concrete delivery.<br />

L. Installation Certification: Submit certification in writing that final placement is in accordance with specification<br />

requirements.<br />

M. Statement of Approval of Concrete Supplier: Submit statement with information specified in Quality Assurance<br />

paragraph below.<br />

1.4 TESTING<br />

A. Wal-Mart Construction Testing Laboratory (CTL) will perform concrete testing and inspection specified in Part 3<br />

and elsewhere in this section as specified at no cost to the Contractor in accordance with Section 01458 - Testing<br />

Laboratory Services.<br />

B. CTL is neither authorized to change any specified requirement nor to approve any portion of the work.<br />

C. Failure to detect defective material or Work will neither prevent rejection when defects are discovered later nor<br />

will it obligate Owner to make final acceptance.<br />

D. Responsibilities and Duties of Contractor Relative to Owner Testing:<br />

1. Notify Owner’s agency in advance of concrete placement to allow sufficient time to prepare for required<br />

testing.<br />

2. Assist Owner’s agency in securing field specimens.<br />

3. Provide and maintain for sole use of CTL, facilities for safe storage and proper curing of concrete test cylinders<br />

at project site as required by ASTM C31 and acceptable to Wal-Mart Testing Laboratory.<br />

1.5 QUALITY ASSURANCE<br />

A. Concrete Truck Inspection:<br />

1. Conform to ASTM C94, NRMCA, and Department of Transportation standards in state where project is located.<br />

2. Perform inspections immediately before starting concreting operations.<br />

3. Record acceptable truck numbers.<br />

4. Record the identification numbers of those trucks found to be acceptable on the basis of inspections.<br />

5. Do not bring on site for concreting operations, any truck whose identification numbers are not recorded as<br />

acceptable. Notify Wal-Mart Testing Lab if non-conforming trucks are used to deliver concrete for slabs<br />

and pavements.<br />

B. Tolerances:<br />

1. Conform to most stringent requirements of ACI 117 and ACI 301 except as specified herein.<br />

2. Conform to ACI 117 thickness tolerances for slabs-on-ground.<br />

C. Concrete Supplier Approval:<br />

1. The concrete supplier shall be fully approved and acceptable by the concrete subcontractor as the producer<br />

of concrete for which the subcontractor is to place and finish. Prepare Statement of Approval of Concrete<br />

Supplier stating project name, name of concrete supplier, along with the statement of approval and the signatures<br />

of the Contractor and concrete pavement subcontractor.<br />

D. Workmanship:<br />

1. When directed by the Owner, remove and replace or repair concrete and related Work which does not conform<br />

to specified requirements including strength, tolerances and finishes.<br />

02751-4<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


2. Bear cost of corrections or delays to other work affected by, or resulting from, corrections to concrete<br />

Work.<br />

3. If results of compressive strength tests reveal deficiencies in concrete, meet requirements of ACI 318 and<br />

ACI 301.<br />

4. Establish and maintain required lines and elevations.<br />

5. Check surface areas at intervals necessary to eliminate ponding areas.<br />

E. Pre-installation Meeting: Convene a pre-installation meeting at the site at least two weeks prior to commencing<br />

work of this Section. Require attendance of parties directly affecting work of this Section, including, but not limited<br />

to, the Owner's representative, CTL’s representative and inspector, Contractor, concrete sub-contractor and<br />

job foreman, concrete supplier, and base fine grading contractor.<br />

1. Contact Wal-Mart Construction Manager Thirty days prior to pre-installation conference to confirm schedule.<br />

2. Record discussions of meeting and decisions and agreements (or disagreements) reached, and furnish copy<br />

of record to each party attending. Review foreseeable methods and procedures related to paving work, including<br />

the following:<br />

3. CTL’s testing and inspection procedures.<br />

4. Concrete finishes and finishing.<br />

5. Cold- and hot-weather concreting procedures.<br />

6. Curing procedures.<br />

7. Concrete design mixture and examine procedures for ensuring quality of concrete materials.<br />

8. Proposed sources of concrete materials, including capabilities and location of plant that will manufacture<br />

concrete.<br />

9. Tour, inspect and discuss condition of subgrade, drainage structures, and other preparatory work.<br />

10. Requirements for protecting concrete work, including restriction of traffic during installation period and for<br />

remainder of construction period.<br />

11. Review and finalize construction schedule and verify availability of materials.<br />

12. Concrete paving requirements (drawings, specifications and other contract documents).<br />

13. Required submittals, both completed and yet to be completed.<br />

14. Weather and forecasted weather conditions, and procedures for coping with unfavorable conditions.<br />

15. Safety precautions relating to placement of concrete.<br />

16. Changes to the contract documents from recommendations or discussions at the Pre-Construction meeting<br />

shall be approved in writing by the Wal-Mart Construction Manager prior to implementation.<br />

1.6 ENVIRONMENTAL REQUIREMENTS<br />

A. Concreting in Hot, Dry, or Windy Weather:<br />

1. Employ precautions to avoid cracking when the concrete rate of evaporation exceeds 0.1 pounds per square<br />

foot per hour or when any combination of concrete materials and weather conditions are favorable for the<br />

formation of plastic shrinkage cracks.<br />

2. Maintain an accurate reading thermometer at the job site to check temperature of concrete.<br />

3. Reject concrete if more than one slump adjustment, as defined in ASTM C 94, is required.<br />

4. Do not place concrete when forms, subgrade, aggregate base, or reinforcing bars are more than 120 F or the<br />

temperature differential between the forms, aggregate base, or reinforcing bars and concrete will create<br />

conditions favorable for settlement cracks or thermal cracking.<br />

B. Concreting in Cold Weather:<br />

1. Conform to ACI 306.1 when temperature and other environmental conditions are as noted therein.<br />

2. Subgrade shall be thawed to depth of 12 inches immediately before placing concrete.<br />

3. Measure and record concrete temperature during protection period in each placement at regular time intervals,<br />

but not less than 3 times per 24 hour period.<br />

4. Do not place slabs on subgrade or base that is more than 20F cooler than concrete. Warm subgrade or<br />

base to decrease temperature differential to 20 F or less<br />

1.7 PROJECT CONDITIONS<br />

A. Maintain access for vehicular and pedestrian traffic as required for other construction activities (and Wal-Mart<br />

customers at expansion projects). Utilize temporary striping, flagmen, barricades, warning signs, and warning<br />

lights as required.<br />

02751-5<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Forms: Steel, wood, or other suitable material of size and strength to resist movement during concrete placement<br />

and to retain horizontal and vertical alignment until removal. Use straight forms, free of distortion and defects. Use<br />

flexible spring steel forms or laminated boards to form radius bends as required. Coat forms with nonstaining type<br />

of coating that will not discolor or deface surface of concrete.<br />

B. Aggregate Base and Choker Materials:<br />

1. Aggregate Base Material:<br />

1) Gradation: Refer to Specification 02715 for Aggregate Base Requirements.<br />

2. Aggregate Choker Material: Clean granular fill with less than 3% clay and/or friable particles. Use one of<br />

the following gradations:<br />

a. ASTM 448 No. 10 with 6% to 12% passing No. 200 sieve.<br />

b. Material meeting the following gradation:<br />

Std. Sieve Size<br />

% Passing<br />

No. 4 85-100<br />

No. 8 75-95<br />

No. 16 55-75<br />

No. 50 22-45<br />

No. 100 10-30<br />

No. 200 6-12<br />

C. Reinforcement:<br />

1. Welded Wire Mesh: Welded plain cold-drawn steel wire fabric, ASTM A185. Furnish in flat sheets.<br />

2. Reinforcing Bars: Deformed steel bars, ASTM A615, Grade 60.<br />

3. Joint Dowel Bars: ASTM A615, grade 40 minimum, smooth round plain steel bars, or ASTM A36, smooth<br />

round or square plain steel bars, cut bars true to length with ends square and free of burrs. Epoxy coat per<br />

State Highway Department Standard Specifications.<br />

D. Cementitious Materials:<br />

1. Portland Cement: ASTM C150, Type I or II, Use only one brand throughout project.<br />

2. Fly Ash: ASTM C 618, Class C or F. Use only one type and source throughout project.<br />

E. Pavement Joint Materials:<br />

1. Joint Back-up Material: Polyethylene foam, 100% closed cell<br />

2. Soft Preformed Joint Filler: Flexible closed-cell non-extruding synthetic foam expansion joint strips.<br />

a. Ceramar Flexibe Foam Expansion Joint, by W.R. Meadows.<br />

b. Deck-O-Foam Expansion Joint Filler, by W.R. Meadows<br />

c. Expansion Joint Filler, by BASF Building Systems (Degussa) (Formerly Sonneborn Sonolastic).<br />

3. Sealant:<br />

a. Dow 888, by Dow Corning.<br />

b. 301 NS by Pecora.<br />

c. Spectrum 800 or 900 by Tremco.<br />

F. Concrete Aggregate:<br />

1. Conform to ASTM C33.<br />

2. Aggregate shall contain no coal or lignite in concrete that will not be covered by soil.<br />

3. Fine Aggregate:<br />

a. Conform to fine aggregate grading requirements as defined in section 6.1 of ASTM C 33 unless approved<br />

by the Civil Engineer.<br />

b. If manufactured sand is used, blend with minimum 25% natural sand unless otherwise approved by<br />

Civil Engineer.<br />

4. Coarse Aggregate:<br />

a. Nominal maximum coarse aggregate size shall be 1 inch for slabs ≤ 5-1/2 inch thick.<br />

02751-6<br />

Deleted: Conform to gradation shown<br />

on the Civil Drawings.<br />

Equivalent Gradation: Equivalent<br />

gradations may be used upon approval of<br />

the Civil Engineer of Record. Submit<br />

proposed equivalent gradation to the<br />

Architect for approval within 30 days<br />

after the award of contract. Equivalent<br />

gradation shall be one of the following.<br />

Any state DOT approved road base<br />

material meeting the following gradation:<br />

<br />

Std. Sieve Size % Passing<br />

No. 1-1/2 100<br />

No. 4 15-55<br />

No. 200 5-12<br />

<br />

Material conforming to the General Requirements<br />

and of the Gradation “A”,<br />

”C”, or “D” requirements (with the modified<br />

allowance of 5% to 12% passing the<br />

No. 200 sieve) as defined by ASTM<br />

D1241<br />

Deleted: Slag: ASTM C989, Grade<br />

100 or 120. Use only one type and source<br />

throughout project.<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


. The nominal maximum size of an aggregate is the smallest sieve size through which the major portion<br />

of the aggregate must pass, with a minimal amount retained on the maximum sieve size. Maximum<br />

4% shall be retained on the nominal maximum size sieve.<br />

5. Adjust proportions of combined coarse, intermediate, and fine aggregates to provide the following particle<br />

size distribution characteristics, unless otherwise approved:<br />

a. Coarseness Factor of 60 to 75%.<br />

1) The Coarseness Factor (CF) is the percent of combined aggregate retained on the #8 sieve<br />

that is also retained on the 3/8” sieve.<br />

2) The Coarseness Factor is calculated as follows:<br />

CF = Aggregate retained on 3/8” sieve / Aggregate retained on #8 sieve.<br />

b. Adjusted Workability Factor<br />

1) The Workability Factor (WF) is the percent of combined aggregate that passes the #8 sieve.<br />

2) The Adjusted Workability Factor (Adj-WF) is calculated as follows:<br />

Adj-WF = WF+[(Cementitous Material -564 lbs)/37.6]<br />

3) The range of accepted Adj-WF for a given CF is as follows:<br />

Adj-WF = [(11.25 - .15 CF) + 33] ± 2.5<br />

4) Combined percent retained on any given sieve size shall not exceed 24%.<br />

6. Gradation requirement of ASTM C33 may be waived in order to meet ranges specified.<br />

G. Water: ASTM C 1602.<br />

H. Air Entrainment: ASTM C260.<br />

1. Air-Mix or AEA-92, by Euclid.<br />

2. MB-VR MB-AE 90, or Micro-Air, BASF.<br />

3. Daravair or Darex Series, by W.R. Grace.<br />

4. Equivalent approved products.<br />

I. Evaporation Retardant: Water-based polymer, sprayable.<br />

1. Euco-Bar, by Euclid<br />

2. Confilm, by BASF Admixtures (Master Builders)<br />

3. Aquafilm, by Dayton Superior.<br />

J. Liquid M<br />

PART 1 - GENERAL 1<br />

1.1 SUMMARY 1<br />

A. Section Includes: 1<br />

B. Related Requirements: 1<br />

1.2 REFERENCES 1<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only. 1<br />

B. American Concrete Institute (ACI): 1<br />

C. American Society for Testing and Materials (ASTM): 1<br />

D. Federal Specifications (FS): 2<br />

E. International Code Council, Inc.: 2<br />

F. State Highway Department Standard Specifications. 2<br />

G. National Ready-Mixed Concrete Association: 2<br />

1.3 SUBMITTALS 2<br />

A. Submittal Procedures: Unless otherwise specified herein, submit in accordance with procedures specified in<br />

Section 01330. 2<br />

B. Obtain CEC approval for Mix Design and Pavement Joint and Placement Plan prior to commencement of work. 2<br />

C. Submit submittal items required within this section in a single submittal. Do not submit submittals of this section<br />

together with submittals in section 03310 or any other section. Identify submittals explicitly in accordance with<br />

Procedures paragraphs in Section 01330. 2<br />

D. Laboratory Analysis for Aggregate Base: Submit current sieve analysis, R-value, Durability and Sand Equivalent<br />

report of material sampled and tested within the last 60 days of submittal date for the aggregate base. 2<br />

E. Concrete Batch Plant Certifications: Submit name and address of the concrete supplier’s batch plant and plant<br />

certification(s) by National Ready-Mix Concrete Association and/or State Department of Transportation. 2<br />

F. Mix Design: Fill out and submit attached Concrete Mix Design Submittal Form. Submit three copies of each<br />

proposed mix design in accordance with ACI 301, Sections 3.9 "Proportioning on the basis of previous field experience<br />

02751-7<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


or trial mixture", or 3.10 "Proportioning based on empirical data". Submit separate mix design for concrete to be placed<br />

by pumping in addition to the mix design for concrete to be placed directly from the truck chute. Submit mix design to<br />

the Civil Engineering Consultant of Record, the Wal-Mart Construction Testing Laboratory, and the Wal-Mart Assigned<br />

Concrete Sub-Consultant. Include all applicable information shown on the Mix Design Submittal Form including the<br />

following: 2<br />

G. Attachments to Concrete Mix Design: Submit the following as attachments to be included with the Concrete Mix<br />

Design: 3<br />

H. Product Data: Submit certified laboratory test data or manufacturer’s certificates and data for the items listed<br />

below certifying that materials are in conformance requirements specified herein. Submit to the Civil Engineering<br />

Consultant of Record and the Construction Testing Laboratory for review and approval and within 7 calendar days after<br />

receipt of Notice-to-Proceed. In addition, for projects with all-concrete parking lots, submit to the Wal-Mart Assigned<br />

Concrete Sub-Consultant. 3<br />

I. Pavement Joint and Placement Plan: For projects with all-concrete parking lots, provide a placement plan<br />

identifying the items listed below. In addition to submission to CEC, submit to Wal-Mart Assigned Concrete Sub-<br />

Consultant. 3<br />

J. Pre-Slab Installation Meeting: 3<br />

K. Delivery Tickets: 3<br />

L. Installation Certification: Submit certification in writing that final placement is in accordance with specification<br />

requirements. 4<br />

M. Statement of Approval of Concrete Supplier: Submit statement with information specified in Quality Assurance<br />

paragraph below. 4<br />

1.4 TESTING 4<br />

A. Wal-Mart Construction Testing Laboratory (CTL) will perform concrete testing and inspection specified in Part<br />

3 and elsewhere in this section as specified at no cost to the Contractor in accordance with Section 01458 - Testing<br />

Laboratory Services. 4<br />

B. CTL is neither authorized to change any specified requirement nor to approve any portion of the work. 4<br />

C. Failure to detect defective material or Work will neither prevent rejection when defects are discovered later nor<br />

will it obligate Owner to make final acceptance. 4<br />

D. Responsibilities and Duties of Contractor Relative to Owner Testing: 4<br />

1.5 QUALITY ASSURANCE 4<br />

A. Concrete Truck Inspection: 4<br />

B. Tolerances: 4<br />

C. Concrete Supplier Approval: 4<br />

D. Workmanship: 4<br />

E. Pre-installation Meeting: Convene a pre-installation meeting at the site at least two weeks prior to commencing<br />

work of this Section. Require attendance of parties directly affecting work of this Section, including, but not limited to,<br />

the Owner's representative, CTL’s representative and inspector, Contractor, concrete sub-contractor and job foreman,<br />

concrete supplier, and base fine grading contractor. 5<br />

1.6 ENVIRONMENTAL REQUIREMENTS 5<br />

A. Concreting in Hot, Dry, or Windy Weather: 5<br />

B. Concreting in Cold Weather: 5<br />

1.7 PROJECT CONDITIONS 5<br />

A. Maintain access for vehicular and pedestrian traffic as required for other construction activities (and Wal-Mart<br />

customers at expansion projects). Utilize temporary striping, flagmen, barricades, warning signs, and warning lights as<br />

required. 5<br />

PART 2 - PRODUCTS 6<br />

2.1 MATERIALS 6<br />

A. Forms: Steel, wood, or other suitable material of size and strength to resist movement during concrete placement<br />

and to retain horizontal and vertical alignment until removal. Use straight forms, free of distortion and defects. Use<br />

flexible spring steel forms or laminated boards to form radius bends as required. Coat forms with nonstaining type of<br />

coating that will not discolor or deface surface of concrete. 6<br />

B. Aggregate Base and Choker Materials: 6<br />

C. Reinforcement: 6<br />

D. Cementitious Materials: 6<br />

E. Pavement Joint Materials: 6<br />

F. Concrete Aggregate: 6<br />

G. Water: ASTM C 1602. 7<br />

H. Air Entrainment: ASTM C260. 7<br />

I. Evaporation Retardant: Water-based polymer, sprayable. 7<br />

02751-8<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


J. Liquid Membrane Curing and Sealing Compound: ASTM C 1315, Type I, Class A or B, 25% minimum solids<br />

content, clear non-yellowing with no styrene-butadiene. 7<br />

J. embrane Curing and Sealing Compound: ASTM C 1315, Type I, Class A or B, 25% minimum solids content, clear<br />

non-yellowing with no styrene-butadiene. 10<br />

K. Dissipating Curing Compound (For use below 40F): ASTM C 309 Type 1, Class A or B. 10<br />

2.2 CONCRETE MIX 10<br />

A. Design mix shall produce normal weight concrete consisting of Portland cement, supplementary cementitious<br />

materials, aggregates, admixtures, and water to produce specified requirements. 10<br />

B. Geographical Weather Exposure Classification: Reference IBC Figure 1904.2.2. Uncertainty of classification<br />

due to a project location near a border of a classification shall be referred to Wal-Mart Construction Manager for<br />

clarification. 10<br />

C. Compressive Strength at 28 days, unless otherwise indicated on the Drawings: 10<br />

D. Slump Range: 2”-4” for hand placed concrete, 1-1/4” to 3” for machine placed (slipform) concrete. 10<br />

E. Air Entrainment as shown below: 11<br />

F. Supplementary Cementitious Materials (SCM): 11<br />

G. Calcium Chloride: 11<br />

2.3 MIXING 12<br />

A. Mix concrete and deliver in accordance with ASTM C 94. 12<br />

PART 3 - EXECUTION 12<br />

3.1 PREPARATION 12<br />

A. Proofroll prepared base material surface to check for unstable areas in accordance with Section 02300 including<br />

documentation and re-proof rolling as required. Paving work shall begin only after unsuitable areas have been corrected<br />

and are ready to receive paving. 12<br />

B. Remove loose material from compacted base material surface to produce firm, smooth surface immediately<br />

before placing concrete. 12<br />

3.2 AGGREGATE BASE PLACEMENT 12<br />

A. Unless otherwise specified on the Drawings, place aggregate base as specified herein. 12<br />

B. Aggregate Base: 12<br />

C. Aggregate Base Fine Grading: 12<br />

D. Pavement Aggregate Base Fine Grade Tolerance: +0 inch, -3/4 inch with transition no greater than 3/4 inch<br />

vertically to 8 inches horizontally. 12<br />

3.3 INSTALLATION 12<br />

A. Form Construction 12<br />

B. Reinforcement: Fasten reinforcing bars or welded wire fabric (if required) accurately and securely in place with<br />

suitable supports and ties. Remove from reinforcement all dirt, oil, loose mill scale, rust, and other substances that will<br />

prevent proper bonding of the concrete to the reinforcement. 13<br />

C. Concrete Placement 13<br />

D. Contraction and Construction Joints: Construct contraction and construction joints straight with face<br />

perpendicular to concrete surface. Construct transverse joints perpendicular to centerline, unless otherwise detailed. 13<br />

E. Isolation and Fixed Object Joints: Construct joint at locations and in accordance with details shown. 13<br />

F. Pavement Joint Materials: Place joint fillers, back-up material, and sealants at locations shown and in<br />

accordance with manufacturer’s instructions. 13<br />

3.4 CONCRETE FINISHING 13<br />

A. After initial striking off and consolidating of concrete paving, smooth surface using either magnesium straight<br />

edge, wood, or magnesium channel float. 13<br />

B. Round edges of slabs and formed joints to 1/2-inch radius with edging tool. Eliminate tool marks on concrete<br />

surface. 13<br />

C. After completion of straightedge / floating and when excess moisture or surface sheen has disappeared,<br />

uniformly finish surface to provide a coarse, nonslip finish by scoring surface with stiff-bristled broom perpendicular to<br />

flow of traffic so as to produce regular corrugations not over 1/16 of an inch deep.Initial nonslip finishing shall be<br />

approved by the Wal-Mart Construction Manager. 13<br />

D. Do not remove forms for 24 hours after concrete has been placed. After form removal, clean ends of joints and<br />

point up minor honeycombed areas. Remove and replace areas or sections with major defects, as directed by Owner. 14<br />

3.5 CURING AND PROTECTION 14<br />

A. Protect and cure finished concrete paving using curing compound. Cure for a period not less than 7 days. 14<br />

B. Use solvent based curing compound when compound is applied below 40 F. 14<br />

3.6 CLEANING AND ADJUSTING 14<br />

A. Sweep concrete pavement and wash free of stains, discolorations, dirt, and other foreign material just prior to<br />

final inspection. 14<br />

02751-9<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Protect concrete from damage until acceptance of work. Exclude traffic from pavement for at least 14 days after<br />

placement. When construction traffic is permitted, maintain pavement as clean as possible by removing surface stains<br />

and spillage of materials. 14<br />

3.7 FIELD QUALITY CONTROL 14<br />

A. Field quality control tests specified herein will be conducted by the Owner’s Construction Testing Laboratory at<br />

no cost to the Contractor in accordance with Section 01458. The Contractor shall perform additional testing as<br />

considered necessary by the Contractor for assurance of quality control. Retesting required as a result of failed initial<br />

tests shall be at the Contractor’s expense. 14<br />

B. Field testing, frequency, and methods may vary as determined by and between the Owner and the Owner’s<br />

Testing Laboratory. 14<br />

C. Review the Contractor's proposed materials and mix design for conformance with specifications. 14<br />

D. Perform testing in accordance with ACI 301 and testing standards listed herein. 14<br />

E. Strength Tests: 14<br />

F. Slump Test: Conduct slump test for each cylinder set taken in accordance with ASTM C143. Make additional<br />

slump tests for every other load from a stationary mixer or truck to test consistency. Sampling shall be in accordance<br />

with ASTM C172. 15<br />

G. Air Content: Conduct air content test for each cylinder set for concrete in accordance with ASTM C 231, ASTM<br />

C 173, or ASTM C 138. Indicate test method on report. Make test at same time as slump test. 15<br />

H. Unit Weight: ASTM C 138. 15<br />

I. Temperature Test: Conduct temperature test for each cylinder set taken in accordance with ASTM C1064. Test<br />

hourly when air temperature is 40 F and below or 80 F and above. Determine temperature of concrete sample and<br />

ambient air for each strength test. 15<br />

J. In addition to required information noted previously in this Section, record the following information on concrete<br />

compression reports: 15<br />

K. At the start of each day's mixing, report any significant deviations from approved mix design including<br />

temperature, moisture and condition of aggregate. 15<br />

L. Review each delivery ticket of concrete. Report type of concrete delivered, amount of water added and time at<br />

which cement and aggregate were loaded into truck, and time at which concrete was discharged from truck 15<br />

M. In Place Pavement Testing: Randomly core pavement in low traffic volume areas at minimum rate of 1 core per<br />

20,000 sq. ft of pavement, with minimum of 3 cores . Sample and test cores in accordance with ASTM C42. Core will<br />

be tested for thickness and quality of aggregate distribution. Core holes shall be patched by the Contractor immediately<br />

with Portland cement concrete and shall be finished to provide level surface as specified herein. 16<br />

N. Additional Tests: Additional in-place tests shall be conducted as directed by the Wal-Mart Construction Manager<br />

when specified concrete strengths and other characteristics have not been attained in the structures. 16<br />

K. embrane Curing and Sealing Compound: ASTM C 1315, Type I, Class A or B, 25% minimum solids content, clear<br />

non-yellowing with no styrene-butadiene.<br />

1. Water Based, VOC less than 350 g/l:<br />

a. Super Aqua Cure, by Euclid Chemical Corp.<br />

b. Kure 1315 by BASF.<br />

L. Dissipating Curing Compound (For use below 40F): ASTM C 309 Type 1, Class A or B.<br />

1. Solvent base, VOC less than 350 g/l: Cetri Vex EnvioCure 100 by Vexcon.<br />

2.2 CONCRETE MIX<br />

A. Design mix shall produce normal weight concrete consisting of Portland cement, supplementary cementitious materials,<br />

aggregates, admixtures, and water to produce specified requirements.<br />

B. Geographical Weather Exposure Classification: Reference IBC Figure 1904.2.2. Uncertainty of classification due<br />

to a project location near a border of a classification shall be referred to Wal-Mart Construction Manager for clarification.<br />

C. Compressive Strength at 28 days, unless otherwise indicated on the Drawings:<br />

1. Negligible exposure classification: 3,500 psi with a maximum water-cementitious ratio of 0.53.<br />

2. Moderate exposure classification: 4,000 psi with a maximum water-cementitious ratio of 0.48.<br />

3. Severe exposure classification: 4,500 psi with a maximum water-cementitious ratio of 0.45.<br />

D. Slump Range: 2”-4” for hand placed concrete, 1-1/4” to 3” for machine placed (slipform) concrete.<br />

02751-10<br />

Deleted: [EDITOR NOTE: Delete the<br />

following Solvent Based in AZ, CA, CT,<br />

DE, DC, MA, MD, ME, NH, NJ, NY,<br />

PA, RI, TX, and VA. due to VOC greater<br />

than 350 g/l.]<br />

Solvent Based (For use below 40F)<br />

Super Rez-Seal, by Euclid Chemical<br />

Corp.<br />

Kure-N-Seal 30 by BASF.<br />

[EDITOR NOTE: Use only in AZ, CA,<br />

CT, DE, DC, MA, MD, ME, NH, NJ,<br />

NY, PA, RI, TX, and VA.] <br />

Deleted: u<br />

Deleted: u<br />

Deleted: u<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


E. Air Entrainment as shown below:<br />

Nominal<br />

Maximum Size<br />

Average Air Content (%)<br />

Aggregate (Inch) Negligible Moderate Severe<br />

3/8 4.5 6.0 7.5<br />

1/2 4.0 5.5 7.0<br />

3/4 3.5 5.0 6.0<br />

1 3.0 4.5 6.0<br />

1-1/2 2.5 4.5 5.5<br />

F. Supplementary Cementitious Materials (SCM):<br />

1. Concrete mix shall contain SCM at the amounts specified unless other amounts are approved by the Civil<br />

Engineer. Either fly ash or ground granulated blast furnace slag (GGBFS) may be used for the SCM but<br />

shall not be used together to form a ternary mix. Use of fly ash or GGBFS in the concrete mix is mandatory.<br />

2. Fly Ash: Substitute fly ash for Portland cement at 15% of the total cementitious content.<br />

a. If used to mitigate potential aggregate reactivity, only Type F fly ash may be used and shall have the<br />

following maximum properties: 1.5% available alkali and 8.0% CaO. When a maximum of 25% replacement<br />

is used, up to 10.0% CaO is permitted.<br />

3. Ground Granulated Blast Furnace Slag (GGBFS): Substitute GGBFS for Portland cement at 20% of the total<br />

cementitious content.<br />

a. If required to mitigate potential sulfate exposure or aggregate reactivity, up to 50% substitution of<br />

Portland cement is allowed.<br />

4. Maintain air-entrainment at specified levels.<br />

G. Calcium Chloride:<br />

1. Calcium chloride (Type L) may be used in solution form as part of the mixing water to accelerate concrete<br />

setting and early-strength development.<br />

2. Amount of calcium chloride added shall not be more than necessary to produce the desired results and shall<br />

not exceed 2% by weight of cement.<br />

3. The dosage range for the calcium chloride for the entire project shall not vary by more than 1%. Range is<br />

defined as the difference between the maximum and minimum dosages of calcium chloride for the entire<br />

project.<br />

4. Calcium chloride shall not be used in the following applications unless approved by the Civil Engineer:<br />

a. concrete containing embedded dissimilar metals or aluminum<br />

b. slabs supported on permanent galvanized steel forms<br />

c. concrete exposed to deicing chemicals<br />

d. prestressed or post-tension concrete<br />

e. concrete containing aggregates with potentially deleterious reactivity and concrete exposed to soil<br />

f. concrete exposed to soil or water containing sulfates.<br />

5. Use calcium chloride in accordance with manufacturer’s recommendation.<br />

6. Chloride-ion Concentration: Maximum water-soluble chloride-ion concentrations in hardened concrete at<br />

ages from 28 to 42 days contributed from the ingredients including water, aggregates, cementitious materials,<br />

and admixtures shall not exceed the following limits unless approved by the Civil Engineer:<br />

Type of Member<br />

Maximum water-soluble chloride ion (Cl-) content<br />

in concrete (percent by weight of cement)<br />

Prestressed concrete 0.06<br />

Reinforced concrete exposed<br />

to chloride in service 0.15<br />

Reinforced concrete that will be dry<br />

or protected from moisture in service 1.00<br />

Other reinforced concrete construction 0.30<br />

7. When using calcium chloride or other admixtures containing chlorides, measure water-soluble chloride-ion<br />

content (percent by weight of cement) per ASTM C 1218. Sample shall be from concrete representing the<br />

submitted mix design and maximum chloride dosage anticipated for the project.<br />

02751-11<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


2.3 MIXING<br />

A. Mix concrete and deliver in accordance with ASTM C 94.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Proofroll prepared base material surface to check for unstable areas in accordance with Section 02300 including<br />

documentation and re-proof rolling as required. Paving work shall begin only after unsuitable areas have been corrected<br />

and are ready to receive paving.<br />

B. Remove loose material from compacted base material surface to produce firm, smooth surface immediately before<br />

placing concrete.<br />

3.2 AGGREGATE BASE PLACEMENT<br />

A. Unless otherwise specified on the Drawings, place aggregate base as specified herein.<br />

B. Aggregate Base:<br />

1. Install aggregate base where shown on Drawings.<br />

2. Compact to final thickness shown in layers not exceeding 6 inches with minimum of 2 passes per layer<br />

with vibratory compactor.<br />

3. Compact fill to minimum 95% of aggregate’s Modified Proctor as determined by Method C of ASTM<br />

D1557.<br />

4. Leave base up to 2 inches low until just prior to concrete placement.<br />

C. Aggregate Base Fine Grading:<br />

1. Compact to final thickness shown with 2 passes minimum vibratory compactor to produce smooth, flat,<br />

dense surface.<br />

2. Do not allow excess moisture in or on base at time of placing concrete.<br />

3. Level off aggregate base top surface with a maximum 3/4" thick aggregate choker material to achieve the<br />

following:<br />

a. To reduce surface friction and to meet specified fine grade tolerances specified below.<br />

b. To level areas exposed to rain, traffic, or excavations for buried utilities.<br />

c. At areas where aggregate base material does not have sufficient fine particles to produce a surface<br />

that is free of exposed aggregate or surface voids greater than 3/8” in size at time of slab installation.<br />

4. Wal-Mart Construction Testing Laboratory shall verify adequate fines at surface immediately prior to concrete<br />

slab placement.<br />

5. Provide dry, smooth, flat, dense surface<br />

6. Proof-roll 48 hrs maximum prior to concrete placement. Depression under a fully loaded ready mix truck<br />

shall not exceed 1/2 inch.<br />

Deleted: 8<br />

Deleted: Standard<br />

Deleted: D<br />

Deleted: D698<br />

D. Pavement Aggregate Base Fine Grade Tolerance: +0 inch, -3/4 inch with transition no greater than 3/4 inch vertically<br />

to 8 inches horizontally.<br />

3.3 INSTALLATION<br />

A. Form Construction<br />

1. Set forms to required grades and lines, rigidly braced and secured.<br />

2. Install sufficient quantity of forms to allow continuance of work and so that forms remain in place minimum<br />

of 24 hours after concrete placement.<br />

3. Check completed formwork for grade and alignment to following tolerances:<br />

a. Top of forms not more than 1/8-inch in 10'-0".<br />

b. Vertical face on longitudinal axis, not more than 1/4-inch in 10'-0".<br />

4. Clean forms after each use and coat with form release agent as often as required to ensure separation from<br />

concrete without damage.<br />

02751-12<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Reinforcement: Fasten reinforcing bars or welded wire fabric (if required) accurately and securely in place with<br />

suitable supports and ties. Remove from reinforcement all dirt, oil, loose mill scale, rust, and other substances that<br />

will prevent proper bonding of the concrete to the reinforcement.<br />

C. Concrete Placement<br />

1. Mix and place concrete when the air temperature in the shade and away from artificial heat is a minimum<br />

of 35 degrees F and rising. Hot and cold weather concreting shall be in accordance with ACI 305.1 (hot<br />

weather) and 306.1 (cold weather).<br />

2. Do not place concrete until base material and forms have been checked for alignment and grade. Concrete<br />

shall not be placed around manholes or other structures until they are at required finish elevation and<br />

alignment.<br />

3. Place concrete using methods that prevent segregation of mix. Consolidate concrete along face of forms<br />

and adjacent to transverse joints with internal vibrator. Keep vibrator away from joint assemblies, reinforcement,<br />

or side forms. Consolidate with care to prevent dislocation of reinforcing, dowels, and joint devices.<br />

4. Deposit and spread concrete in continuous operation between transverse joints, as far as possible. If interrupted<br />

for more than 1/2 hour, place construction joint.<br />

D. Contraction and Construction Joints: Construct contraction and construction joints straight with face perpendicular<br />

to concrete surface. Construct transverse joints perpendicular to centerline, unless otherwise detailed.<br />

1. Contraction Joints: Provide joints at spacing of 12'-0" on centers, maximum each way. Construct control<br />

joints for depth equal to at least 1/4 of the concrete thickness, as follows:<br />

a. Form tooled joints in fresh concrete by grooving top with recommended tool and finishing edge<br />

with jointer.<br />

b. Sawed Contraction Joints:<br />

1) Use saws, blades, skid plates, and accessories by Soff-Cut International, Inc. or approved<br />

equal.<br />

2) Start cutting sawed joints as soon as concrete has hardened sufficiently to prevent raveling or<br />

dislodging of aggregates. This will typically be from 1 hour in hot weather to 4 hours in cold<br />

weather after completing finishing of slab in that joint location.<br />

3) Provide at least two “Soff-Cut” saws on site with blades capable of achieving the required<br />

depth of saw cut.<br />

4) Extend sawed joint to the slab boundaries and abutments, including columns, drains, and<br />

other penetrations in the path of a defined joint. Implement methods and timing of the saw<br />

cut beyond the limits of the Soff-Cut saw reach to provide a consistent depth of cut with minimal<br />

raveling of joint edges.<br />

2. Construction Joints: Place construction joints at end of placements and at locations where placement operations<br />

are stopped for period of more than 1/2 hour. Construct joints in accordance with details shown.<br />

E. Isolation and Fixed Object Joints: Construct joint at locations and in accordance with details shown.<br />

F. Pavement Joint Materials: Place joint fillers, back-up material, and sealants at locations shown and in accordance<br />

with manufacturer’s instructions.<br />

1. Soft Preformed Joint Fillers: Extend preformed joint fillers full-width and depth of joint, and not less than<br />

1/2-inch or more than 1-inch below finished surface. Furnish preformed joint fillers in 1-piece lengths for<br />

full width being placed, wherever possible. Where more than 1 length is required, lace or clip preformed<br />

joint filler sections together in a single plane.<br />

3.4 CONCRETE FINISHING<br />

A. After initial striking off and consolidating of concrete paving, smooth surface using either magnesium straight<br />

edge, wood, or magnesium channel float.<br />

B. Round edges of slabs and formed joints to 1/2-inch radius with edging tool. Eliminate tool marks on concrete surface.<br />

C. After completion of straightedge / floating and when excess moisture or surface sheen has disappeared, uniformly<br />

finish surface to provide a coarse, nonslip finish by scoring surface with stiff-bristled broom perpendicular to flow<br />

02751-13<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


of traffic so as to produce regular corrugations not over 1/16 of an inch deep.Initial nonslip finishing shall be approved<br />

by the Wal-Mart Construction Manager.<br />

D. Do not remove forms for 24 hours after concrete has been placed. After form removal, clean ends of joints and<br />

point up minor honeycombed areas. Remove and replace areas or sections with major defects, as directed by Owner.<br />

3.5 CURING AND PROTECTION<br />

A. Protect and cure finished concrete paving using curing compound. Cure for a period not less than 7 days.<br />

B. Use solvent based curing compound when compound is applied below 40 F.<br />

3.6 CLEANING AND ADJUSTING<br />

A. Sweep concrete pavement and wash free of stains, discolorations, dirt, and other foreign material just prior to final<br />

inspection.<br />

B. Protect concrete from damage until acceptance of work. Exclude traffic from pavement for at least 14 days after<br />

placement. When construction traffic is permitted, maintain pavement as clean as possible by removing surface<br />

stains and spillage of materials.<br />

3.7 FIELD QUALITY CONTROL<br />

A. Field quality control tests specified herein will be conducted by the Owner’s Construction Testing Laboratory at<br />

no cost to the Contractor in accordance with Section 01458. The Contractor shall perform additional testing as<br />

considered necessary by the Contractor for assurance of quality control. Retesting required as a result of failed initial<br />

tests shall be at the Contractor’s expense.<br />

B. Field testing, frequency, and methods may vary as determined by and between the Owner and the Owner’s Testing<br />

Laboratory.<br />

C. Review the Contractor's proposed materials and mix design for conformance with specifications.<br />

D. Perform testing in accordance with ACI 301 and testing standards listed herein.<br />

E. Strength Tests:<br />

1. Secure composite samples in accordance with ASTM C172. Sample at regularly spaced intervals from<br />

middle portion of the batch. Sampling time shall not exceed 15 minutes.<br />

2. Mold and cure specimens in accordance with ASTM C31.<br />

a. A minimum of four concrete test cylinders shall be taken for every 100 cubic yards or less of each<br />

class of concrete placed each day and not less than once for each 5000 square feet of paved area.<br />

b. During the initial 24 hours (plus or minus 8 hours) after molding, the temperature immediately adjacent<br />

to the specimens shall be maintained in the range of 60 to 80 degrees F. Control loss of moisture<br />

from the specimens by shielding from the direct rays of the sun and from radiant heating devices.<br />

c. Specimens transported prior to 48 hours after molding shall not be demolded, but shall continue initial<br />

curing at 60 to 80 degrees F until time for transporting.<br />

d. Specimens transported after 48 hours age shall be demolded in 24 hours (plus or minus 8 hours).<br />

Curing shall then be continued but in saturated limewater at 73.4 degrees (plus or minus 3 degrees<br />

F) until the time of transporting.<br />

e. Wet cure cylinders under controlled temperature until testing.<br />

3. Test cylinders in accordance with ASTM C39.<br />

a. Size of specimen test cylinder shall be 6" x 12" or 4” x 8”.<br />

b. Date test cylinders and number consecutively. Give each cylinder of each set an identifying letter<br />

(i.e. A, B, C, D). Prepare a sketch of the site plan for each test set identifying location of placed concrete.<br />

c. Test one cylinder (A) at 7 days for information..<br />

02751-14<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


d. Test two cylinders (B and C) at 28 days and the average of the breaks shall constitute the compressive<br />

strength of the concrete sample.<br />

e. Retain fourth cylinder (D) for further testing if needed, but do not retain cylinder more than 90 days.<br />

4. Evaluation and Acceptance:<br />

a. Strength level of concrete will be considered satisfactory if the average of all sets of three consecutive<br />

strength tests equal or exceed specified strength and no individual strength test (average of two<br />

cylinders) results are below specified compressive strength by more than 500 psi.<br />

b. Complete concrete work will not be accepted unless requirements of ACI 301, have been met, including<br />

dimensional tolerances, appearance, and strength of structure.<br />

c. Where average strength of cylinders, as shown by tests is not satisfactory, Wal-Mart reserves the<br />

right to require Contractor to provide improved curing conditions of temperature and moisture to secure<br />

required strength. If average strength of laboratory control cylinders should fall so low as to<br />

cause portions of structure to be in question by Wal-Mart, follow core procedure set forth in ASTM<br />

C42. If results of core test indicate, in opinion of Wal-Mart, that strength of structure is inadequate,<br />

provide without additional cost to Wal-Mart, replacement, load testing, or strengthening as may be<br />

ordered by Wal-Mart. If core tests are so ordered and results of such tests disclose that strength of<br />

structure is as required, cost of test will be paid by Wal-Mart.<br />

F. Slump Test: Conduct slump test for each cylinder set taken in accordance with ASTM C143. Make additional<br />

slump tests for every other load from a stationary mixer or truck to test consistency. Sampling shall be in accordance<br />

with ASTM C172.<br />

G. Air Content: Conduct air content test for each cylinder set for concrete in accordance with ASTM C 231, ASTM C<br />

173, or ASTM C 138. Indicate test method on report. Make test at same time as slump test.<br />

1. Perform air content test for first and second truck for each class of concrete placed each day. If either test<br />

fails, perform air test on every truck until two consecutive air tests comply with the requirements of the<br />

project specifications.<br />

H. Unit Weight: ASTM C 138.<br />

I. Temperature Test: Conduct temperature test for each cylinder set taken in accordance with ASTM C1064. Test<br />

hourly when air temperature is 40 F and below or 80 F and above. Determine temperature of concrete sample and<br />

ambient air for each strength test.<br />

J. In addition to required information noted previously in this Section, record the following information on concrete<br />

compression reports:<br />

1. Test cylinder number and letter.<br />

2. Specific foundations or structures covered by this test.<br />

3. Proportions of concrete mix or mix identification.<br />

4. Maximum size coarse aggregate.<br />

5. Specified compressive strength.<br />

6. Tested compressive strength.<br />

7. Slump, air-content.<br />

8. Concrete plastic unit weight.<br />

9. Concrete Temperature.<br />

10. Elapsed time from batching at plant to discharge from delivery truck at project.<br />

11. Date and time concrete was placed.<br />

12. Ambient temperature, wind speed, and relative humidity during concrete placement.<br />

13. Name of technician securing samples.<br />

14. Curing conditions for concrete strength test specimens (field and laboratory).<br />

15. Date strength specimens transported to laboratory.<br />

16. Age of strength specimens when tested.<br />

17. Type of fracture during test.<br />

K. At the start of each day's mixing, report any significant deviations from approved mix design including temperature,<br />

moisture and condition of aggregate.<br />

L. Review each delivery ticket of concrete. Report type of concrete delivered, amount of water added and time at<br />

which cement and aggregate were loaded into truck, and time at which concrete was discharged from truck<br />

02751-15<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


M. In Place Pavement Testing: Randomly core pavement in low traffic volume areas at minimum rate of 1 core per<br />

20,000 sq. ft of pavement, with minimum of 3 cores . Sample and test cores in accordance with ASTM C42. Core<br />

will be tested for thickness and quality of aggregate distribution. Core holes shall be patched by the Contractor<br />

immediately with Portland cement concrete and shall be finished to provide level surface as specified herein.<br />

N. Additional Tests: Additional in-place tests shall be conducted as directed by the Wal-Mart Construction Manager<br />

when specified concrete strengths and other characteristics have not been attained in the structures.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02751-16<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


WAL-MART STORES<br />

CONCRETE MIX DESIGN SUBMITTAL FORM<br />

(Section 02751 – Concrete Pavement)<br />

Date<br />

DISCOUNT STORE SUPERCENTER NEIGHBORHOOD MARKET SAM’S CLUB<br />

STORE INFORMATION<br />

STORE #<br />

ADDRESS<br />

CITY, ST<br />

GENERAL CONTRACTOR<br />

COMPANY<br />

JOBSITE PHONE<br />

A. CONCRETE INFORMATION<br />

Supplier Mix Design #<br />

Design Strength (f ’ c)<br />

Water / Cementitious Ratio<br />

psi<br />

Total Air Content %<br />

Total Est. Volume of Concrete<br />

CY<br />

Mix Developed From:<br />

Trial Mix Test Data (attach test data)<br />

Field Experience<br />

Density<br />

Wet pcf Dry pcf<br />

Slump<br />

“ ( ± 1” ) WITHOUT WR Admixture<br />

LEAVE BLANK FOR<br />

STAMP OF<br />

APPROVAL BY<br />

CONCRETE<br />

SUPPLIER AND<br />

ENGINEER OF<br />

RECORD<br />

“ ( ± 1” ) WITH WR Admixture<br />

B. ADMIXTURE INFORMATION<br />

ASTM Designation Product Dosage (ounces)<br />

(Manufacturer/Brand) oz / cy oz / cwt<br />

Water Reducing<br />

Accelerating<br />

Retarding<br />

Air-Entraining<br />

C. MIX DESIGN<br />

02751-17<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


Cement<br />

Fly Ash<br />

Slag<br />

Coarse Aggregate #1<br />

#2<br />

#3<br />

Fine Aggregate #1<br />

#2<br />

Water<br />

Air Content<br />

Mix Proportions (per cubic yard)<br />

Identification<br />

Weight<br />

(Type, size, source, etc.)<br />

(pounds)<br />

TOTALS<br />

Density<br />

(SSD)<br />

Volume<br />

(cubic feet)<br />

% Aggregate<br />

Absorption<br />

Sieve<br />

Size<br />

1-1/2"<br />

1"<br />

3/4"<br />

1/2"<br />

3/8"<br />

# 4<br />

# 8<br />

# 16<br />

# 30<br />

# 50<br />

# 100<br />

# 200<br />

% of Vol<br />

Coarse<br />

Agg. # 1<br />

Coarse & Fine Aggregate Gradation Information<br />

% Passing Each Sieve<br />

(All Sieve Sizes must be entered)<br />

Coarse<br />

Agg. # 2<br />

Coarse<br />

Agg. # 3<br />

Fine<br />

Agg. # 1<br />

Fine<br />

Agg. # 2<br />

Combined % Retained<br />

Combined<br />

% Passing Cumulative Individual<br />

Coarseness Factor =<br />

Aggregate Ratios<br />

Combined % cumulative retained 3/8” sieve<br />

Combined % cumulative retained #8 sieve<br />

=<br />

Workability Factor = Combined % passing #8 sieve =<br />

Adj-Workability Factor = WF + [(Cementitious Material - 564) ÷ 37.6] =<br />

Allowable Adj-WF= Adj-WF = [(11.25 - .15 CF) + 33] ± 2.5 = Low High<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02751-18<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. ATTACHMENTS: Include the following with this Mix Design Report.<br />

Portland Cement mill test reports<br />

Fly ash mill test reports<br />

Slag mill test reports<br />

Designation, type, quality, and source (natural or manufactured) of coarse and fine aggregate materials<br />

Separate aggregate gradation reports including all required sieve sizes<br />

All gradation sieve report tests dated within 60 days of this report<br />

Report for each coarse and fine aggregate material in mix<br />

Statement if possible reactivity of aggregate, based on tests or past service<br />

Statement if possible aggregate pop-outs or their disruptions, based on tests or past service<br />

Product data for the following admixtures:<br />

Chloride ion data and related calculations<br />

Water reducing, set retarding, set accelerating, etc.<br />

Measured water-soluble chloride ion content in concrete (percent by weight of cement).<br />

Concrete compressive strength data used for standard deviation calculations<br />

E. CONCRETE SUPPLIER INFORMATION<br />

Company Name Tel. # ( )<br />

Address<br />

City, ST Zip<br />

Technical Contact Cell # ( )<br />

e-mail<br />

Sales Contact Cell # ( )<br />

PRIMARY PLANT<br />

SECONDARY PLANT<br />

Plant Location:<br />

Miles from Site:<br />

Travel Time to Site:<br />

NRMCA Certified: YES NO YES NO<br />

State DOT Certified: YES NO YES NO<br />

02751-19<br />

Deleted: Anytown<br />

Deleted: ,<br />

Deleted: USA -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


Batch Mixing Type: DRY CENTRAL MIX DRY CENTRAL MIX<br />

Deleted: Anytown<br />

Deleted: ,<br />

Deleted: USA -<br />

Deleted: 11110000<br />

02751-20<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec – Civil (Master Site Specifications) 052711<br />

SECTION 02765 (32 1723) - PAVEMENT MARKINGS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Painting and marking of pavements, curbs, guard posts, and light pole bases.<br />

B. Related Requirements:<br />

1. Section 01743 - Hazardous/Universal Waste Management and Disposal: Hazardous waste management<br />

and disposal related to removal of existing pavement markings.<br />

Deleted: EDITOR NOTE: Use the<br />

following paragraph for Expansion Projects<br />

only. DELETE THIS EDITOR<br />

NOTE PRIOR TO PRINTING.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Association of State Highway and Transportation (AASHTO):<br />

1. AASHTO M247 - Glass Beads Used in Traffic Paints<br />

2. AASHTO M248 - Ready-Mixed White and Yellow Traffic Paints<br />

C. ASTM International (ASTM):<br />

1. ASTM D4414 - Standard Practice for Measurement of Wet Film Thickness by Notched Gauges.<br />

D. Federal Specifications (FS):<br />

1. FS A-A-2886 - Paint, Traffic, Solvent Based (supersedes FS TT-P-85 and FS TT-P-115, Type I)<br />

2. FS TT-B-1325 - Beads (Glass Spheres) Retro-Reflective<br />

3. FS TT-P-1952 - Paint, Traffic And Airfield Marking, Waterborne<br />

1.3 PROJECT CONDITIONS<br />

A. Maintain access for vehicular and pedestrian traffic as required for other construction activities. Utilize flagmen,<br />

barricades, warning signs, and warning lights as required.<br />

1.4 QUALITY ASSURANCE<br />

A. Use trained and experienced personnel in applying the products and operating the equipment required for properly<br />

performed work.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Paint shall be waterborne or solvent borne, colors as shown or specified herein. Pavement marking paints shall<br />

comply with applicable state and local laws enacted to ensure compliance with Federal Clean Air Standards. Paint<br />

materials shall conform to the restrictions of the local Air Pollution Control District.<br />

B. Waterborne Paint: Paints shall conform to FS TT-P-1952.<br />

C. Solvent Borne Paint: Paint shall conform to FS A-A-2886 or AASHTO M248. Paint shall be non-bleeding,<br />

quick-drying, and alkyd petroleum base paint suitable for traffic-bearing surface and be mixed in accordance with<br />

manufacture's instructions before application for colors White, Yellow, Blue, and Red.<br />

D. Glass Beads: AASHTO M 247, Type 1 or FS TT-B-1325, Type 1, Gradation A.<br />

02765-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine the work area and correct conditions detrimental to timely and proper completion of the work. Do not<br />

proceed until unsatisfactory conditions are corrected.<br />

3.2 PREPARATION<br />

A. Sweep and clean surface to eliminate loose material and dust.<br />

B. Where existing pavement markings are indicated on Construction Drawings to be removed or would interfere with<br />

adhesion of new paint, a motorized abrasive device shall be used to remove the markings. Equipment employed<br />

shall not damage existing paving or create surfaces hazardous to vehicle or pedestrian traffic. Within public<br />

rights-of-way, appropriate governing authority shall approve method of marking removal.<br />

3.3 New pavement surfaces shall be allowed to cure for not less than 30 days before application of marking materials.CLEANING<br />

EXISTING PAVEMENT MARKINGS<br />

A. Remove existing pavement markings which are in good condition but interfere or conflict with the newly applied<br />

marking patterns. Deteriorated or obscured markings that are not misleading or confusing or do not interfere with<br />

the adhesion of the new marking material do not require removal. Conduct grinding, scraping, sandblasting or<br />

other operations in such a manner that the finished pavement surface is not damaged or left in a pattern that is misleading<br />

or confusing. Use dust collection system when pavement preparation includes grinding, scraping or sandblasting<br />

of existing pavement markings. Comply with the requirements of Section 01743 for management and<br />

disposal of hazardous wastes.<br />

Formatted: PR1<br />

Deleted: <br />

EDITOR NOTE: Use the following<br />

paragraph for Expansion Projects only.<br />

DELETE THIS EDITOR NOTE PRIOR<br />

TO PRINTING.<br />

Formatted: Hidden<br />

3.4 APPLICATION<br />

A. Apply two coats of same color of paint as specified below, at manufacturer's recommended rate, without addition<br />

of thinner, with maximum of 100 square feet per gallon or as required to provide a minimum wet film thickness of<br />

15 mils and dry film thickness of 7 ½ mils per coat. Paint shall be applied for a total dry film thickness of 15 mils.<br />

Apply with mechanical equipment to produce uniform straight edges. At sidewalk curbs and crosswalks, use<br />

straightedge to ensure uniform, clean, and straight stripe.<br />

B. Install pavement markings according to manufacturer's recommended procedures for the specified material.<br />

C. Following items shall be painted with colors noted below:<br />

1. Pedestrian Crosswalks: White<br />

2. Exterior Sidewalk Curbs, Light Pole Bases, and Guard posts: Yellow<br />

3. Fire Lanes: Red or per local code<br />

4. Lane Striping where separating traffic moving in opposite directions: Yellow<br />

5. Lane Striping where separating traffic moving in the same direction: White<br />

6. ADA Symbols: Blue or per local code<br />

7. ADA parking space markings as shown on the drawings.<br />

8. Parking Stall Striping: Yellow, unless otherwise noted on Construction Drawings<br />

9. Associate Parking Area: White, unless otherwise noted on Construction Drawings<br />

D. Apply glass beads at pedestrian crosswalk striping and at lane striping and arrows at driveways connecting to<br />

public streets. Broadcast glass beads uniformly into wet markings at a rate of 6 lb/gal.<br />

3.5 FIELD QUALITY CONTROL<br />

A. Responsibilities: Unless otherwise specified, the quality control tests and inspections specified below will be conducted<br />

by the Owner’s Construction Testing Laboratory (CTL) at no cost to the Contractor in accordance with<br />

Section 01458. The Contractor shall perform additional testing or inspection as considered necessary by the Con-<br />

02765-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


tractor for assurance of quality control. Field testing, frequency, and methods may vary as determined by and between<br />

the Owner and CTL.<br />

B. Inspection: After the paint has thoroughly dried, visually inspect the entire application and touch up as required to<br />

provide clean, straight lines and surfaces throughout.<br />

C. Testing: Testing of wet film thickness shall be performed a minimum of two times on each parking row (including<br />

striped islands) and pedestrian cross walks, and a minimum of one test on each lane/alignment striping. At least<br />

one test shall be performed after refilling paint striping machine, changing operators of striping machine, and<br />

changing paint types, brands, etc. This shall be performed in addition to the testing stated above. These tests shall<br />

be performed on each coat applied. Testing shall be performed in accordance with ASTM D4414.<br />

3.6 CLEANING<br />

A. Waste materials shall be removed at the end of each workday. Upon completion of the work, all containers and<br />

debris shall be removed from the site. Paint spots upon adjacent surfaces shall be carefully removed by approved<br />

procedures that will not damage the surfaces and the entire job left clean and acceptable.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02765-3<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec II - NP 082710<br />

SECTION 02768 (32 1726) – TACTILE WARNING SYSTEMS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Detectable warning systems.<br />

1.2 SUBMITTALS<br />

A. Refer to Section 01330 for submittal procedures.<br />

B. Manufacturer’s written installation instructions.<br />

C. Manufacturer’s warranty.<br />

1.3 QUALITY ASSURANCE<br />

A. Qualifications: Installer shall have a minimum of five years experience in installations similar to this project and<br />

shall be approved by the detectable warning system manufacturer.<br />

B. Regulatory Requirements: Detectable warning system shall comply with the applicable requirements of the<br />

following:<br />

1. Americans with Disabilities Act (ADA): Title 49 CFR Transportation, Section 4.29.2 Detectable Warnings<br />

on Walking Surfaces.<br />

2. International Building Code, Chapter 11, for detectable warning pavers.<br />

3. American National Standard Institute (ANSI):<br />

a. ICC/ANSI A 117.1-98 Accessible and Useable Buildings and Facilities for Detectable Warning<br />

Pavers.<br />

4. U.S. Architectural and Transportation Barriers Compliance Board Americans with Disabilities Act<br />

Accessibility Guidelines for Buildings and Facilities (ADAAG).<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Reference Section 01600 for general delivery and storage requirements.<br />

B. Deliver materials to project site in manufacturer’s original, unopened containers with labels indicating brand<br />

names, colors and patterns and quality designations legible and intact.<br />

C. Store and protect materials in accordance with manufacturer’s recommendations.<br />

1.5 SITE CONDITIONS<br />

A. Adhere to manufacturer’s printed recommendations for environmental requirements.<br />

B. Work area shall be free of traffic and any work by other trades during, and after installation, and shall be protected<br />

per manufacturer’s printed instructions.<br />

C. Protect finished detectable warning system surfaces from damage by subsequent trades.<br />

1.6 WARRANTY<br />

A. Guarantee product in writing for a period of five years from date of final completion. The guarantee shall include<br />

without limitation, defective work, breakage, deformation, fading and chalking of finishes, and loosening of<br />

materials.<br />

02768 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 DETECTABLE WARNING SYSTEMS<br />

A. Provide tactile cast-in-place panels or tiles or tactile concrete pavers incorporating inline truncated dome pattern<br />

measuring 0.2” in height, 0.9” diameter at the base, and 0.4” diameter at top of dome spaced 2.35” nominal as<br />

measured side by side. Provide one of the following products:<br />

1. Cast-In-Place Panels or Tiles:<br />

a. Cast In Place Armor-Tile Tactile System, by Engineered Plastics Inc., Williamsville, NY (800) 682-<br />

2525, www.armor-tile.com<br />

b. Cast in Place CASTinTACT 3 Concrete Tactile Warning Panels, by Mason Supply Company,<br />

Portland, OR. Contact (503)234-4321, www.castintact.com<br />

c. Cast in Place EZ Set Tile, by Detectable Warning Systems, Inc. Anaheim, CA (866)999-7452,<br />

www.detectable-warning.com<br />

d. Cast in Place Detectable Warning Tile, by ADA Solutions, North Billerica, MA (800) 372-0519,<br />

www.adatile.com<br />

e. Cast in Place Detectable Warning Panels, by Armorcast Products Company, North Hollywood, CA<br />

(818) 982-3600 www.armorcastprod.com/ada.htm<br />

f. Color: Yellow, unless otherwise shown on Drawings. Color shall be contrasting with pavement.<br />

2. Concrete Pavers: By one of the following manufacturers:<br />

a. Hanover Architectural Products, Hanover, PA (800) 426-4242, www.hanoverpavers.com<br />

b. Wausau Tile, Wausau, WI (800) 388-8728, www.wausautile.com<br />

c. Color: Yellow, unless otherwise shown on Drawings. Color shall be contrasting with pavement.<br />

2.2 ACCESSORIES<br />

A. Cleaner: As recommended by manufacturer.<br />

B. Sealer: As recommended by manufacturer.<br />

C. Concrete Paver Accessories:<br />

1. Bedding Sand: Clean, non-plastic, free from deleterious or foreign matter, symmetrically shaped, natural<br />

or manufactured form crushed rock.<br />

2. Joint Sand: Fine, sharp, washed natural sand or crushed stone with 100 percent passing No. 16 sieve and<br />

no more than 10 percent passing No. 200 sieve.<br />

3. Geotextile Fabric: Refer to Section 02340.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces or base materials<br />

conform to product manufacturer's requirements and as indicated on the drawings.<br />

B. Beginning of installation indicates acceptance of substrate conditions.<br />

3.2 PREPARATION<br />

A. Protect utilities, drainage structures, curbs and any other structures within or adjacent to the treatment location<br />

against the application of the surface treatment materials.<br />

3.3 INSTALLATION<br />

A. Install in the locations and pattern as shown on the drawings.<br />

B. Install as shown on the drawings and as recommended by the manufacturer’s written instructions.<br />

02768 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Cut pavers or panels with motor-driven masonry saw equipment to provide pattern indicated and to fit adjoining<br />

work neatly. Use full units without cutting where possible and avoid units cut to less than one quarter of original<br />

size.<br />

D. Tolerances: Do not exceed 1/16-inch unit-to-unit offset from flush (lippage) or 1/8 inch in 10 feet from level, or<br />

indicated slope for finished surface of paving.<br />

E. Install pavers or panels with edges flush with adjacent non-tactile paving.<br />

F. Concrete Pavers:<br />

1. Mix pavers from several pallets or cubes, as they are placed, to produce uniform blend of colors and<br />

textures.<br />

2. Place geotextile fabric over compacted base course.<br />

3. Place bedding sand and screed to a thickness necessary to maintain uniform grade, taking care that moisture<br />

content remains constant and density is loose and constant until pavers are set and compacted.<br />

4. Place pavers hand tight against spacer bars.<br />

5. Vibrate pavers into leveling course with a low-amplitude plate vibrator.<br />

6. Spread dry sand and fill joints immediately after vibrating pavers into leveling course. Vibrate pavers and<br />

add sand until joints are completely filled, then remove excess sand. Leave a slight surplus of sand on the<br />

surface for joint filling.<br />

7. Apply and spread joint sand as necessary until joints remain full.<br />

3.4 CLEANING<br />

A. Thoroughly clean surfaces in a method recommended by manufacturer.<br />

B. Replace discolored materials as required.<br />

END OF SECTION<br />

02768 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec – Civil (Master Site Specifications) 010509<br />

SECTION 02770 (32 1600) - CURBS AND SIDEWALKS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Portland cement concrete curbs, gutters, and sidewalks except sidewalks adjacent to building.<br />

B. Related Requirements:<br />

1. Section 02300 - Earthwork: Preparation of subgrades.<br />

2. Section 03310 - Structural Concrete and Exterior Concrete Slabs: Exterior sidewalks adjacent to building.<br />

Deleted: Requiremnets<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Concrete Institute (ACI):<br />

1. ACI 305R - Hot Weather Concreting<br />

2. ACI 306R - Cold Weather Concreting<br />

3. ACI 306.1 - Cold Weather Concreting.<br />

4. ACI 308 - Curing Concrete<br />

C. ASTM International (ASTM):<br />

1. ASTM A185 - Steel Welded Wire Fabric, Plain, for Concrete Reinforcement.<br />

2. ASTM A615 - Deformed and Plain Billet-Steel for Concrete Reinforcement.<br />

3. ASTM C31 - Making and Curing Concrete Test Specimens in the Field.<br />

4. ASTM C39 - Comprehensive Strength of Cylindrical Concrete Specimens.<br />

5. ASTM C42 - Obtaining and Testing Drilled Cores and Sawed Beams of Concrete.<br />

6. ASTM C94 - Ready-Mixed Concrete.<br />

7. ASTM C138 - Test Method for Unit Weight, Yield, and Air Content (Gravemetric) of Concrete.<br />

8. ASTM C143 - Slump of Hydraulic Cement Concrete.<br />

9. ASTM C231 - Air-Content of Freshly Mixed Concrete by the Pressure Method.<br />

10. ASTM C172 - Sampling Freshly Mixed Concrete.<br />

11. ASTM C173 - Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method.<br />

12. ASTM C260 - Air-Entraining Admixtures for Concrete.<br />

13. ASTM C309 - Liquid Membrane-Forming Compounds for Curing Concrete.<br />

14. ASTM C618 - Fly Ash and Raw or Calcined Natural Pozzolan for use as a Mineral Admixture in Portland<br />

Cement Concrete.<br />

15. ASTM C989 - Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars.<br />

16. ASTM C1064 - Temperature of Freshly Mixed Portland Concrete Cement.<br />

17. ASTM C1218 - Water-Soluble Chloride in Mortar and Concrete.<br />

18. ASTM D98 - Calcium Chloride.<br />

19. ASTM D994 - Preformed Expansion Joint Filler for Concrete (Bituminous).<br />

20. ASTM D1190 - Concrete Joint Sealer, Hot Poured, Elastic Type.<br />

21. ASTM D1751 - Performed Expansion Joint Fillers for Concrete Paving and Structural Construction (Nonextruding<br />

and Resilient Bituminous Types).<br />

22. ASTM D2628 - Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements.<br />

D. Federal Specifications (FS):<br />

1. FS HH-F-341 - Fillers, Expansion Joint: Bituminous (Asphalt & Tar)<br />

E. State Highway Department Standard Specifications<br />

02770-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


1.3 SUBMITTALS<br />

A. Mix Design: Fill out and submit attached Concrete Mix Design Submittal Form. Submit three copies of each proposed<br />

mix design in accordance with ACI 301, Sections 3.9 "Proportioning on the basis of previous field experience<br />

or trial mixture", or 3.10 "Proportioning based on empirical data". Submit separate mix design for concrete to<br />

be placed by pumping in addition to the mix design for concrete to be placed directly from the truck chute. Submit<br />

mix design to the Civil Engineering Consultant of Record, the Wal-Mart Construction Testing Laboratory, and the<br />

Wal-Mart Assigned Concrete Sub-Consultant. Include applicable information shown on the Mix Design Submittal<br />

Form and the following:<br />

1. Proportions of cementitious materials, fine and coarse aggregate, and water.<br />

2. Water-cementitious material ratio, 28-day compressive design strength, slump, and air content.<br />

3. Type of cement, fly ash, slag and aggregate.<br />

4. Aggregate gradation.<br />

5. Type and dosage of admixtures.<br />

6. Special requirements for pumping.<br />

7. Range of ambient temperature and humidity for which design is valid.<br />

8. Special characteristics of mix which require precautions in mixing, placing, or finishing techniques to<br />

achieve finished product specified.<br />

9. Materials and methods for curing concrete.<br />

B. Submit certified laboratory test data or manufacturer’s certificates and data for the items listed below certifying<br />

that materials are in conformance requirements specified herein. Submit to the Engineering Consultant of Record<br />

and the Construction Testing Laboratory for review and approval and within 7 calendar days after receipt of Notice-to-Proceed.<br />

1. Concrete mix design(s)<br />

2. Type and source of Portland cement, fly ash, and slag<br />

3. Aggregate gradations<br />

4. Preformed expansion joint filler<br />

5. Field molded/poured sealant<br />

6. Dowel bars<br />

7. Expansion sleeves<br />

8. Tie bars<br />

9. Reinforcing steel bars<br />

10. Welded wire fabric<br />

11. Air entraining admixtures<br />

12. Water-reducing, set-retarding and set-accelerating admixtures (if used)<br />

C. Test Reports: Submit field quality control test reports.<br />

1.4 QUALITY ASSURANCE<br />

A. Establish and maintain required lines and elevations.<br />

B. Check surface areas at intervals necessary to eliminate ponding areas. Remove and replace unacceptable work as<br />

directed by Owner.<br />

1.5 PROJECT CONDITIONS<br />

A. Maintain access for vehicular and pedestrian traffic as required for other construction activities. Utilize temporary<br />

striping, flagmen, barricades, warning signs, and warning lights as required.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Forms: Steel, wood, or other suitable material of size and strength to resist movement during concrete placement<br />

and to retain horizontal and vertical alignment until removal. Use straight forms, free of distortion and defects. Use<br />

02770-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


flexible spring steel forms or laminated boards to form radius bends as required. Forms shall be of depth equal to<br />

depth of curbing or sidewalk, and so designed as to permit secure fastening together at tops. Coat forms with nonstaining<br />

type of coating that will not discolor or deface surface of concrete.<br />

B. Welded Wire Mesh: Welded plain cold-drawn steel wire fabric, ASTM A185. Furnish in flat sheets.<br />

C. Reinforcing Steel: Deformed steel bars, ASTM A615, Grade 60.<br />

D. Portland Cement: Shall conform to ASTM C150, Type I.<br />

E. Fly Ash: ASTM C618, Class C or F. Use only one type and source throughout project.<br />

F. Slag: ASTM C989, Grade 100 or 120. Use only one type and source throughout project.<br />

G. Exterior Pavement Joint Materials<br />

1. Joint Back-up Material: Polyethylene foam, 100% closed cell.<br />

2. Sealant:<br />

a. Dow 888, by Dow Corning.<br />

b. 301 NS by Pecora.<br />

c. Spectrum 800 or 900 by Tremco.<br />

H. Aggregate: ASTM C33.<br />

I. Water: Clean and potable<br />

J. Dowel Bars: ASTM A615, grade 60, and plain steel bars.<br />

K. Air Entrainment: ASTM C260. .<br />

1. Air-Mix or AEA-92, by Euclid Chemical Corp.<br />

2. MB-VR MB-AE 90, or Micro-Air, by BASF.<br />

3. Daravair or Darex Series, by W.R. Grace.<br />

4. Equivalent approved products.<br />

L. Liquid M<br />

PART 1 - GENERAL 1<br />

1.1 SUMMARY 1<br />

A. Section Includes: 1<br />

B. Related Requirements: 1<br />

1.2 REFERENCES 1<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only. 1<br />

B. American Concrete Institute (ACI): 1<br />

C. ASTM International (ASTM): 1<br />

D. Federal Specifications (FS): 1<br />

E. State Highway Department Standard Specifications 1<br />

1.3 SUBMITTALS 2<br />

A. Mix Design: Fill out and submit attached Concrete Mix Design Submittal Form. Submit three copies of each<br />

proposed mix design in accordance with ACI 301, Sections 3.9 "Proportioning on the basis of previous field experience<br />

or trial mixture", or 3.10 "Proportioning based on empirical data". Submit separate mix design for concrete to be placed<br />

by pumping in addition to the mix design for concrete to be placed directly from the truck chute. Submit mix design to<br />

the Civil Engineering Consultant of Record, the Wal-Mart Construction Testing Laboratory, and the Wal-Mart Assigned<br />

Concrete Sub-Consultant. Include applicable information shown on the Mix Design Submittal Form and the following: 2<br />

B. Submit certified laboratory test data or manufacturer’s certificates and data for the items listed below certifying<br />

that materials are in conformance requirements specified herein. Submit to the Engineering Consultant of Record and<br />

the Construction Testing Laboratory for review and approval and within 7 calendar days after receipt of Notice-to-<br />

Proceed. 2<br />

C. Test Reports: Submit field quality control test reports. 2<br />

02770-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


1.4 QUALITY ASSURANCE 2<br />

A. Establish and maintain required lines and elevations. 2<br />

B. Check surface areas at intervals necessary to eliminate ponding areas. Remove and replace unacceptable work as<br />

directed by Owner. 2<br />

1.5 PROJECT CONDITIONS 2<br />

A. Maintain access for vehicular and pedestrian traffic as required for other construction activities. Utilize<br />

temporary striping, flagmen, barricades, warning signs, and warning lights as required. 2<br />

PART 2 - PRODUCTS 2<br />

2.1 MATERIALS 2<br />

A. Forms: Steel, wood, or other suitable material of size and strength to resist movement during concrete placement<br />

and to retain horizontal and vertical alignment until removal. Use straight forms, free of distortion and defects. Use<br />

flexible spring steel forms or laminated boards to form radius bends as required. Forms shall be of depth equal to depth<br />

of curbing or sidewalk, and so designed as to permit secure fastening together at tops. Coat forms with nonstaining type<br />

of coating that will not discolor or deface surface of concrete. 2<br />

B. Welded Wire Mesh: Welded plain cold-drawn steel wire fabric, ASTM A185. Furnish in flat sheets. 3<br />

C. Reinforcing Steel: Deformed steel bars, ASTM A615, Grade 60. 3<br />

D. Portland Cement: Shall conform to ASTM C150, Type I. 3<br />

E. Fly Ash: ASTM C618, Class C or F. Use only one type and source throughout project. 3<br />

F. Slag: ASTM C989, Grade 100 or 120. Use only one type and source throughout project. 3<br />

G. Exterior Pavement Joint Materials 3<br />

H. Aggregate: ASTM C33. 3<br />

I. Water: Clean and potable 3<br />

J. Dowel Bars: ASTM A615, grade 60, and plain steel bars. 3<br />

K. Air Entrainment: ASTM C260. . 3<br />

L. Liquid Membrane Curing and Sealing Compound: ASTM C1315, Type I, Class A or B, 25% minimum solids<br />

content, clear non-yellowing with no styrene-butadiene. 3<br />

L. embrane Curing and Sealing Compound: ASTM C1315, Type I, Class A or B, 25% minimum solids content,<br />

clear non-yellowing with no styrene-butadiene. 5<br />

M. Dissipating Curing Compound: ASTM C309 Type 1, Class A or B. 5<br />

2.2 CONCRETE MIXING 5<br />

A. Mix concrete and deliver in accordance with ASTM C94. Design mix shall produce normal weight concrete<br />

consisting of Portland cement, supplementary cementitious materials, aggregates, admixtures and water to produce the<br />

following: 5<br />

B. Supplementary Cementitous Materials (SCM): 5<br />

C. Calcium chloride: 6<br />

PART 3 - EXECUTION 6<br />

3.1 PREPARATION 6<br />

A. Begin paving work only after unsuitable areas have been corrected and are ready to receive paving. 6<br />

B. Remove loose material from compacted base material surface to produce firm, smooth surface immediately<br />

before placing concrete. 6<br />

3.2 INSTALLATION 6<br />

A. Form Construction 7<br />

B. Reinforcement: Fasten reinforcing bars or welded wire fabric (if required) accurately and securely in place with<br />

suitable supports and ties. Remove from reinforcement all dirt, oil, loose mill scale, rust, and other substances that will<br />

prevent proper bonding of the concrete to the reinforcement. 7<br />

C. Concrete Placement 7<br />

D. Joint Construction 7<br />

E. Joint Fillers: Extend joint fillers full-width and depth of joint, and not less than 1/2-inch or more than 1-inch<br />

below finished surface where joint sealer is indicated. Furnish joint fillers in 1-piece lengths for full width being placed,<br />

wherever possible. Where more than 1 length is required, lace or clip joint filler sections together. 7<br />

F. Joint Sealants: Install in accordance with manufacturer's recommendations. 7<br />

3.3 CONCRETE FINISHING 7<br />

A. After striking off and consolidating concrete, smooth surface by screeding and floating. Adjust floating to<br />

compact surface and produce uniform texture. After floating, test surface for trueness with 10'-0" straightedge.<br />

Distribute concrete as required to remove surface irregularities, and refloat repaired areas to provide continuous smooth<br />

finish. 7<br />

02770-4<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Work edges of sidewalks, gutters, back top edge of curb, and formed joints with edging tool, rounding edge to<br />

1/2-inch radius. Eliminate tool marks on concrete surface. After completion of floating and trowelling, when excess<br />

moisture or surface sheen has disappeared, complete surface finishing, as follows: 8<br />

C. Do not remove forms for 24 hours after concrete has been placed. After form removal, clean ends of joints and<br />

point up minor honeycombed areas. Remove and replace areas or sections with major defects as directed Owner. 8<br />

3.4 CURING AND PROTECTION 8<br />

A. Protect and cure finished concrete paving using with curing compound or with acceptable moist-curing methods<br />

in accordance with "water-curing" section of ACI 308. Cure for a period not less than 7 days. 8<br />

B. Use solvent based curing compound when compound is applied below 40 F. 8<br />

3.5 BACKFILL 8<br />

A. After concrete has set sufficiently, spaces on either side of concrete curb, combination concrete curb and gutter,<br />

or concrete sidewalk shall be refilled to required elevation with suitable material compacted in accordance with Section<br />

02300. 8<br />

3.6 CLEANING AND PROTECTION 8<br />

A. Sweep concrete pavement and wash free of stains, discolorations, dirt, and other foreign material just prior to<br />

final inspection. 8<br />

B. Protect concrete from damage until acceptance of work. Exclude traffic from pavement for at least 14 days after<br />

placement. When construction traffic is permitted, maintain pavement as clean as possible by removing surface stains<br />

and spillage of materials. 8<br />

3.7 FIELD QUALITY CONTROL 8<br />

A. Field quality control tests specified herein will be conducted by the Owner’s Construction Testing Laboratory at<br />

no cost to the Contractor in accordance with Section 01458. The Contractor shall perform additional testing as<br />

considered necessary by the Contractor for assurance of quality control. Retesting required as a result of failed initial<br />

tests shall be at the Contractor’s expense. 8<br />

B. Field testing, frequency, and methods may vary as determined by and between the Owner and the Owner’s<br />

Testing Laboratory. 8<br />

C. Review the Contractor's proposed materials and mix design for conformance with specifications. 8<br />

D. Perform sampling testing and evaluation in accordance with ASTM C94 and as follows. 8<br />

E. Strength Tests: 8<br />

F. Slump Test: Conduct slump test for each cylinder set taken in accordance with ASTM C143. 9<br />

G. Air Content: Conduct air content test for each cylinder set for concrete exposed to freeze-thaw in accordance<br />

with ASTM C231, ASTM C173, or ASTM C138. 9<br />

M. embrane Curing and Sealing Compound: ASTM C1315, Type I, Class A or B, 25% minimum solids content, clear<br />

non-yellowing with no styrene-butadiene.<br />

1. Water Based, VOC less than 350 g/l:<br />

a. Super Aqua Cure, by Euclid Chemical Corp.<br />

b. Kure 1315 by BASF.<br />

N. Dissipating Curing Compound: ASTM C309 Type 1, Class A or B.<br />

1. Solvent base, VOC less than 350 g/l: Cetri Vex EnvioCure 100 by Vexcon.<br />

2.2 CONCRETE MIXING<br />

A. Mix concrete and deliver in accordance with ASTM C94. Design mix shall produce normal weight concrete consisting<br />

of Portland cement, supplementary cementitious materials, aggregates, admixtures and water to produce the<br />

following:<br />

1. Compressive Strength: 3,500 psi minimum at 28 days unless otherwise indicated on the Drawings.<br />

2. Slump Range: 2”-4” for hand placed concrete, 1-1/4” to 3” for machine placed (slipform) concrete.<br />

3. Air Entrainment: 5 to 8 percent.<br />

B. Supplementary Cementitous Materials (SCM):<br />

1. Concrete mix shall contain SCM at the amounts specified unless other amounts are approved by the Civil<br />

Engineer.<br />

2. Fly Ash: Substitute fly ash for Portland cement at 15% of the total cementitious content. Use of fly ash in<br />

the concrete mix is mandatory.<br />

02770-5<br />

Deleted: [EDITOR NOTE: Delete<br />

Solvent Based in AZ, CA, CT, DE, DC,<br />

MA, MD, ME, NH, NJ, NY, PA, RI, TX,<br />

and VA. due to VOC greater than 350<br />

g/l.]<br />

Solvent Based<br />

Super Rez-Seal, by Euclid Chemical<br />

Corp.<br />

Kure-N-Seal 30 by BASF.<br />

[EDITOR NOTE: Use only in AZ, CA,<br />

CT, DE, DC, MA, MD, ME, NH, NJ,<br />

NY, PA, RI, TX, and VA..] <br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


a. If used to mitigate potential aggregate reactivity, only Type F fly ash may be used and shall have the<br />

following maximum properties: 1.5% available alkali and 8.0% CaO. When a maximum of 30% replacement<br />

is used, up to 10.0% CaO is permitted.<br />

3. Ground Granulated Blast Furnace Slag (GGBFS): GGBFS may be used at the option of the Contractor. If<br />

used, GGBFS shall be substituted for Portland cement at 20% of the total cementitious content. If required<br />

to mitigate potential sulfate exposure or aggregate reactivity, up to 50% substitution of Portland cement is<br />

allowed.<br />

4. Ternary mix (combination of fly ash, GGBFS, and Portland cement): If used, the fly ash and GGBFS combination<br />

shall be substituted for Portland cement at a maximum of 40% or when approved, up to 55% of the<br />

total cementitious content.<br />

5. Maintain air-entrainment at specified levels.<br />

C. Calcium chloride:<br />

1. Calcium chloride (Type L) may be used in solution form as part of the mixing water to accelerate concrete<br />

setting and early-strength development.<br />

a. Amount of calcium chloride added shall not be more than necessary to produce the desired results<br />

and shall not exceed 2% by weight of cement.<br />

b. The dosage range for the calcium chloride for the entire project shall not vary by more than 1%.<br />

Range is defined as the difference between the maximum and minimum dosages of calcium chloride<br />

for the entire project.<br />

c. Calcium chloride shall not be used in the following applications unless approved by the Civil Engineer:<br />

1) concrete containing embedded dissimilar metals or aluminum<br />

2) slabs supported on permanent galvanized steel forms<br />

3) concrete exposed to deicing chemicals<br />

4) prestressed or post-tension concrete<br />

5) concrete containing aggregates with potentially deleterious reactivity and concrete exposed<br />

to soil<br />

6) concrete exposed to soil or water containing sulfates.<br />

2. Use calcium chloride in accordance with manufacturer’s recommendation.<br />

3. Chloride-ion Concentration:<br />

a. Maximum water-soluble chloride-ion concentrations in hardened concrete at ages from 28 to 42<br />

days contributed from the ingredients including water, aggregates, cementitious material, and admixtures<br />

shall not exceed the following limits unless approved by the Civil Engineer:<br />

Type of Member<br />

Maximum water-soluble chloride ion (Cl-) content<br />

in concrete (percent by weight of cement)<br />

Prestressed concrete 0.06<br />

Reinforced concrete exposed<br />

to chloride in service 0.15<br />

Reinforced concrete that will be dry<br />

or protected from moisture in service 1.00<br />

Other reinforced concrete construction 0.30<br />

4. When using calcium chloride or other admixtures containing chlorides, measure water-soluble chloride-ion<br />

content (percent by weight of cementitious materials) per ASTM C1218. Sample shall be from concrete<br />

representing the submitted mix design and maximum chloride dosage anticipated for the project.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Begin paving work only after unsuitable areas have been corrected and are ready to receive paving.<br />

B. Remove loose material from compacted base material surface to produce firm, smooth surface immediately before<br />

placing concrete.<br />

3.2 INSTALLATION<br />

02770-6<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. Form Construction<br />

1. Set forms to required grades and lines, rigidly braced and secured.<br />

2. Install sufficient quantity of forms to allow continuance of work and so that forms remain in place minimum<br />

of 24 hours after concrete placement.<br />

3. Check completed formwork for grade and alignment to following tolerances:<br />

a. Top of forms not more than 1/8-inch in 10'-0".<br />

b. Vertical face on longitudinal axis, not more than 1/4-inch in 10'-0".<br />

4. Clean forms after each use and coat with form release agent as often as required to ensure separation from<br />

concrete without damage.<br />

B. Reinforcement: Fasten reinforcing bars or welded wire fabric (if required) accurately and securely in place with<br />

suitable supports and ties. Remove from reinforcement all dirt, oil, loose mill scale, rust, and other substances that<br />

will prevent proper bonding of the concrete to the reinforcement.<br />

C. Concrete Placement<br />

1. Concrete shall be mixed and placed when the air temperature in the shade and away from artificial heat is a<br />

minimum of 35 degrees F and rising. Hot and cold weather concreting shall be in accordance with ACI<br />

305R (hot weather) and 306.1 and 306R (cold weather).Do not place concrete until base material and forms<br />

have been checked for line and grade. Moisten base material if required to provide uniform dampened condition<br />

at time concrete is placed. Do not place concrete around manholes or other structures until set at required<br />

finish elevation and alignment.<br />

2. Place concrete using methods that prevent segregation of mix. Consolidate concrete along face of forms<br />

and adjacent to transverse joints with internal vibrator. Keep vibrator away from joint assemblies, reinforcement,<br />

or side forms. Consolidate with care to prevent dislocation of reinforcing, dowels, and joint devices.<br />

3. Deposit and spread concrete in continuous operation between transverse joints, as far as possible. If interrupted<br />

for more than 1/2 hour, place construction joint. Automatic machine may be used for curb and gutter<br />

placement. Machine placement shall be at required cross section, line, grade, finish, and jointing as specified<br />

for formed concrete. If results are not acceptable, remove and replace with formed concrete as specified<br />

herein.<br />

D. Joint Construction<br />

1. Contraction Joints: Construct concrete curb or combination concrete curb and gutter, where specified on<br />

Construction Drawings, in uniform sections of length specified on Construction Drawings. Form joints between<br />

sections either by steel templates, 1/8-inch in thickness, of length equal to width of curb and gutter,<br />

and with depth which will penetrate at least 2-inches below surface of curb and gutter; or with 3/4-inch<br />

thick performed expansion joint filler cut to exact cross section of curb and gutter; or by sawing to depth of<br />

at least 2-inches while concrete is between 4 and 24 hours old. If steel templates are used, they shall be left<br />

in place until concrete has set enough to hold its shape, but shall be removed while forms are still in place.<br />

2. Longitudinal Construction Joints: Tie concrete curb or combination concrete curb and gutter, where specified<br />

on Construction Drawings, to concrete pavement with 1/2-inch round deformed reinforcement bars of<br />

length and spacing shown on Construction Drawings.<br />

3. Transverse Expansion Joints: Concrete curb, combination concrete curb and gutter, or concrete sidewalk<br />

shall have filler cut to exact cross section of curb, gutter, or sidewalk. Joints shall be similar to type of expansion<br />

joint used in adjacent pavement.<br />

E. Joint Fillers: Extend joint fillers full-width and depth of joint, and not less than 1/2-inch or more than 1-inch below<br />

finished surface where joint sealer is indicated. Furnish joint fillers in 1-piece lengths for full width being placed,<br />

wherever possible. Where more than 1 length is required, lace or clip joint filler sections together.<br />

F. Joint Sealants: Install in accordance with manufacturer's recommendations.<br />

3.3 CONCRETE FINISHING<br />

A. After striking off and consolidating concrete, smooth surface by screeding and floating. Adjust floating to compact<br />

surface and produce uniform texture. After floating, test surface for trueness with 10'-0" straightedge. Distribute<br />

02770-7<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


concrete as required to remove surface irregularities, and refloat repaired areas to provide continuous smooth finish.<br />

B. Work edges of sidewalks, gutters, back top edge of curb, and formed joints with edging tool, rounding edge to 1/2-<br />

inch radius. Eliminate tool marks on concrete surface. After completion of floating and trowelling, when excess<br />

moisture or surface sheen has disappeared, complete surface finishing, as follows:<br />

1. Curbs, gutters, and sidewalks: Broom finish by drawing fine-hair broom across surface perpendicular to<br />

flow of traffic. Repeat operation as necessary to produce fine line texture.<br />

C. Do not remove forms for 24 hours after concrete has been placed. After form removal, clean ends of joints and<br />

point up minor honeycombed areas. Remove and replace areas or sections with major defects as directed Owner.<br />

3.4 CURING AND PROTECTION<br />

A. Protect and cure finished concrete paving using with curing compound or with acceptable moist-curing methods in<br />

accordance with "water-curing" section of ACI 308. Cure for a period not less than 7 days.<br />

B. Use solvent based curing compound when compound is applied below 40 F.<br />

3.5 BACKFILL<br />

A. After concrete has set sufficiently, spaces on either side of concrete curb, combination concrete curb and gutter, or<br />

concrete sidewalk shall be refilled to required elevation with suitable material compacted in accordance with Section<br />

02300.<br />

3.6 CLEANING AND PROTECTION<br />

A. Sweep concrete pavement and wash free of stains, discolorations, dirt, and other foreign material just prior to final<br />

inspection.<br />

B. Protect concrete from damage until acceptance of work. Exclude traffic from pavement for at least 14 days after<br />

placement. When construction traffic is permitted, maintain pavement as clean as possible by removing surface<br />

stains and spillage of materials.<br />

3.7 FIELD QUALITY CONTROL<br />

A. Field quality control tests specified herein will be conducted by the Owner’s Construction Testing Laboratory at<br />

no cost to the Contractor in accordance with Section 01458. The Contractor shall perform additional testing as<br />

considered necessary by the Contractor for assurance of quality control. Retesting required as a result of failed initial<br />

tests shall be at the Contractor’s expense.<br />

B. Field testing, frequency, and methods may vary as determined by and between the Owner and the Owner’s Testing<br />

Laboratory.<br />

C. Review the Contractor's proposed materials and mix design for conformance with specifications.<br />

D. Perform sampling testing and evaluation in accordance with ASTM C94 and as follows.<br />

E. Strength Tests:<br />

1. Secure composite samples in accordance with ASTM C172. Sample at regularly spaced intervals from<br />

middle portion of the batch. Sampling time shall not exceed 15 minutes.<br />

2. Mold and cure specimens in accordance with ASTM C31.<br />

a. A minimum of four concrete test cylinders shall be taken for every 50 cubic yards or less of concrete<br />

placed each day.<br />

b. Wal-Mart Construction Manager may choose to waive testing requirements on concrete placements<br />

less than 9 cubic yards.<br />

3. Test cylinders in accordance with ASTM C39.<br />

02770-8<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


F. Slump Test: Conduct slump test for each cylinder set taken in accordance with ASTM C143.<br />

G. Air Content: Conduct air content test for each cylinder set for concrete exposed to freeze-thaw in accordance with<br />

ASTM C231, ASTM C173, or ASTM C138.<br />

1. Perform air content test for first and second truck for each class of concrete placed each day. If either test<br />

fails, perform air test on every truck until two consecutive air tests comply with the requirements of the<br />

project specifications.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02770-9<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


WAL-MART STORES<br />

CONCRETE MIX DESIGN SUBMITTAL FORM<br />

(Section 02751 – Concrete Pavement)<br />

Date<br />

DISCOUNT STORE SUPERCENTER NEIGHBORHOOD MARKET SAM’S CLUB<br />

STORE INFORMATION<br />

STORE #<br />

ADDRESS<br />

CITY, ST<br />

GENERAL CONTRACTOR<br />

COMPANY<br />

JOBSITE PHONE<br />

A. CONCRETE INFORMATION<br />

Supplier Mix Design #<br />

Design Strength (f ’ c)<br />

Water / Cementitious Ratio<br />

psi<br />

Total Air Content %<br />

Total Est. Volume of Concrete<br />

CY<br />

Mix Developed From:<br />

Trial Mix Test Data (attach test data)<br />

Field Experience<br />

Density<br />

Wet pcf Dry pcf<br />

Slump<br />

LEAVE<br />

BLANK FOR<br />

ENGINEER’S<br />

STAMP<br />

“ ( ± 1” ) WITHOUT WR Admixture<br />

“ ( ± 1” ) WITH WR Admixture<br />

B. ADMIXTURE INFORMATION<br />

ASTM Designation Product Dosage (ounces)<br />

(Manufacturer/Brand) oz / cy oz / cwt<br />

Water Reducing<br />

Accelerating<br />

Retarding<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

02770-10<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


C. MIX DESIGN<br />

Cement<br />

Fly Ash<br />

Slag<br />

Coarse Aggregate #1<br />

#2<br />

#3<br />

Fine Aggregate #1<br />

#2<br />

Water<br />

Air Content<br />

Mix Proportions (per cubic yard)<br />

Identification<br />

Weight<br />

(Type, size, source, etc.)<br />

(pounds)<br />

TOTALS<br />

Density<br />

(SSD)<br />

Volume<br />

(cubic feet)<br />

% Aggregate<br />

Absorption<br />

Sieve<br />

Size<br />

1-1/2"<br />

1"<br />

3/4"<br />

1/2"<br />

3/8"<br />

# 4<br />

# 8<br />

# 16<br />

# 30<br />

# 50<br />

# 100<br />

# 200<br />

% of Vol<br />

Coarse<br />

Agg. # 1<br />

Coarse & Fine Aggregate Gradation Information<br />

% Passing Each Sieve<br />

(All Sieve Sizes must be entered)<br />

Coarse<br />

Agg. # 2<br />

Coarse<br />

Agg. # 3<br />

Fine<br />

Agg. # 1<br />

Fine<br />

Agg. # 2<br />

Combined % Retained<br />

Combined<br />

% Passing Cumulative Individual<br />

Coarseness Factor =<br />

Aggregate Ratios<br />

Combined % cumulative retained 3/8” sieve<br />

Combined % cumulative retained #8 sieve<br />

=<br />

Workability Factor = Combined % passing #8 sieve =<br />

Adj-Workability Factor = WF + [(Cementitious Material - 564) ÷ 37.6] =<br />

Allowable Adj-WF= Adj-WF = [(11.25 - .15 CF) + 34.5] ± 2.5 = Low High<br />

D. ATTACHMENTS: Include the following with this Mix Design Report.<br />

02770-11<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


Portland Cement mill test reports<br />

Fly ash mill test reports<br />

Slag mill test reports<br />

Designation, type, quality, and source (natural or manufactured) of coarse and fine aggregate materials<br />

Separate aggregate gradation reports including all required sieve sizes<br />

All gradation sieve report tests dated within 60 days of this report<br />

Report for each coarse and fine aggregate material in mix<br />

Statement if possible reactivity of aggregate, based on tests or past service<br />

Statement if possible aggregate pop-outs or their disruptions, based on tests or past service<br />

Product data for the following admixtures:<br />

Chloride ion data and related calculations<br />

Water reducing, set retarding, set accelerating, etc.<br />

Measured water-soluble chloride ion content in concrete (percent by weight of cement)<br />

Concrete compressive strength data used for standard deviation calculations<br />

E. CONCRETE SUPPLIER INFORMATION<br />

Company Name Tel. # ( )<br />

Address<br />

City, ST Zip<br />

Technical Contact Cell # ( )<br />

e-mail<br />

Sales Contact Cell # ( )<br />

PRIMARY PLANT<br />

SECONDARY PLANT<br />

Plant Location:<br />

Miles from Site:<br />

Travel Time to Site:<br />

NRMCA Certified: YES NO YES NO<br />

State DOT Certified: YES NO YES NO<br />

Batch Mixing Type: DRY CENTRAL MIX DRY CENTRAL MIX<br />

02770-12<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec II – Civil (Master Site Specifications) 021511<br />

SECTION 02787 (32 1236) - SEAL COAT<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Seal coats using a polymer-modified asphalt emulsion blended with fine aggregate.<br />

B. Related Requirements:<br />

1. Section 02740 – Asphaltic Concrete Paving.<br />

2. Section 02765 – Pavement Marking<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM)<br />

1. ASTM C 136 – Method of Sieve Analysis of Fine and Coarse Aggregate<br />

2. ASTM D 217 – Method for Cone Penetration of Lubricating Grease<br />

3. ASTM D 244 – Test Methods for Emulsified Asphalts<br />

4. ASTM D 562 – Method for Consistency of Paints Measuring Krebs Unit (KU) Viscosity Using a Stormer-<br />

Type Viscometer<br />

5. ASTM D 977 – Emulsified Asphalt<br />

6. ASTM D 2397 – Cationic Emulsified Asphalt<br />

7. ASTM D 2042 – Method for solubility of Asphalt Materials in Trichloroethylene<br />

8. ASTM D 3910 – Practice for Design, Testing, and Construction of Slurry Seal<br />

9. ASTM D 6690 – Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements<br />

1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-installation Meeting: Convene a pre-installation meeting at the site at least two weeks prior to commencing<br />

work of this Section. Require attendance of parties directly affecting work of this Section, including, but not limited<br />

to, the Owner's representative, CTL’s representative and inspector, Contractor, and job foreman.<br />

1. Contact Wal-Mart Construction Manager three weeks prior to pre-installation conference to confirm schedule.<br />

2. Record discussions of meeting and decisions and agreements reached, and furnish copy of record to each<br />

party attending. Review foreseeable methods and procedures related to paving work, including the following:<br />

a. Review preparation and installation procedures and coordinating and scheduling required with related<br />

work.<br />

b. Review proposed sources of materials.<br />

c. Tour, inspect, and discuss condition of existing pavement and other preparatory work such as<br />

patching, crack sealing, and oil spot priming/repair.<br />

d. Review requirements for protecting paving work, including restriction of traffic during installation<br />

and curing period.<br />

e. Review and finalize construction schedule and verify availability of materials, installer's personnel,<br />

equipment, and facilities needed to make progress and avoid delays.<br />

f. Review paving requirements (drawings, specifications, and other contract documents).<br />

g. Review required submittals, both completed and yet to be completed.<br />

h. Review required inspections, testing procedures.<br />

Deleted: Anytown, USA - 11110000<br />

02787-1<br />

La Habra, CA – 5641-01 11/7/2011


i. Review weather and forecasted weather conditions, and procedures for coping with unfavorable<br />

conditions.<br />

j. Review health and safety precautions relating to handling and placement of seal coat.<br />

1.4 QUALITY ASSURANCE<br />

A. Contractor Qualifications: The seal coat applicator shall have not less than 3 years documented experience in the<br />

application of emulsion seal coats.<br />

1.5 SUBMITTALS<br />

A. Product Data: Submit the manufacturer’s product information for oil spot primer.<br />

B. Certificates:<br />

1. Submit manufacturer's certification that each consignment of emulsion shipped to the project meets the requirements<br />

of the applicable specification for the emulsion specified, except that the water content shall not<br />

exceed 50 percent. The certification shall also indicate the solids content of the emulsion and the date the<br />

tests were conducted.<br />

2. Submit certification of placement in accordance with specification requirements as specified in Part 3 Field<br />

Quality Control.<br />

C. Qualification Statements: Submit contractor qualifications certification.<br />

D. Mix Design:<br />

1. Submit mix design and emulsion properties to the Civil Engineering Consultant of Record at least 30 days<br />

prior to beginning sealing operations. Mix designs over one year old will not be accepted.<br />

2. Submit approved mix designs and laboratory test results to CTL signed by the materials producer and Contractor<br />

certifying materials and mix ratios conform to the requirements specified herein.<br />

E. Calibration Results: Submit report of spreading equipment calibration tests.<br />

1.6 SITE CONDITIONS<br />

A. Weather Limitations: Apply seal coat only under the following weather conditions:<br />

1. The atmospheric temperature is between 50 and 90 F and is expected to remain above 50 F for 24 hours.<br />

2. Pavement temperature is above 55 F.<br />

3. Surface is dry and no moisture is expected within 24 hours.<br />

4. Weather and wind conditions are such that overspray is preventable and will allow proper curing and opening<br />

to traffic within a reasonable time.<br />

Deleted: g<br />

B. Maintain access for vehicular and pedestrian traffic as required by the Wal-Mart Construction Manager. Utilize<br />

temporary striping, flagmen, barricades, warning signs, and warning lights as required.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Aggregate: Aggregate shall be 100 percent passing the No. 16 (1.18 mm) sieve when tested in accordance with<br />

ASTM C 136. Aggregate shall consist of hard, washed, dry natural or manufactured particles free of dust, trash,<br />

clay, organic materials or other contaminants.<br />

B. Asphalt Emulsion: Comply with ASTM D977 or ASTM D2397 for SS-1h or CSS-1h. The penetration of the residue<br />

from the distillation test shall be 20 to 60. Clay stabilized emulsion, with a ph not greater than 7.0, and solids<br />

content not less than 45 percent may be used. The polymer material shall be milled or blended into the asphalt or<br />

emulsifier solution prior to the emulsification process. The minimum amount and type of polymer modifier shall<br />

be determined by the laboratory performing the mix design.<br />

Deleted: Anytown, USA - 11110000<br />

02787-2<br />

La Habra, CA – 5641-01 11/7/2011


C. Coal Tar: Coal tar emulsion or coal tar/asphalt emulsion shall not be used as a substitute for asphalt emulsion.<br />

D. Water: Water shall be potable and free of harmful soluble salts or reactive chemicals and any other contaminants<br />

and at least 50 F.<br />

E. Additives: Additives shall be included and approved as part of the mix design and be compatible with the other<br />

components of the mix.<br />

F. Crack Sealant: Crack sealant shall conform to ASTM D6690 and be certified for compatibility with the specified<br />

emulsion by the manufacturer of the emulsion.<br />

G. Oil Spot Primer: Oil spot primer shall be a quick drying latex emulsion with suitable admixtures manufactured<br />

specifically for the purpose of isolating the asphalt sealcoat from any residual oils, petroleum grease, and gasoline<br />

stained pavement. The oil spot primer shall be certified for compatibility with the specified emulsion by the manufacturer<br />

of the emulsion.<br />

2.2 COMPOSITION<br />

A. Composition. Seal coat shall consist of a mixture of the specified emulsion, water, aggregate, and additives and be<br />

proportioned to meet the requirements shown in the following Table 1.<br />

TABLE 1 – Undiluted Seal Coat Design Properties<br />

Method Minimum Maximum<br />

Weight (per gallon), ASTM D 244, lbs 9.0<br />

Cone Penetration, ASTM D 217, mm 340 700<br />

% Non-Volatile 1 50<br />

% Non-Volatile Residue Soluble in Trichloroethylene, ASTM D 2042 10 35<br />

Wet Track Abrasion Loss, ASTM D 3910, g 35<br />

Viscosity, ASTM D 562, KU 75<br />

Dried Film Color<br />

Black<br />

1 Weigh 10 g of homogeneous product into a previously tarred, small ointment can. Place in an oven at 325°F for<br />

90 minutes. Cool, reweigh and calculate non-volatile residue as a percent of the original mass.<br />

Deleted: EDITOR NOTE: Specify the<br />

following tack coat if necessary due to<br />

the condition of existing pavement as<br />

determined by Engineer. Delete all Editor<br />

Notes prior to printing.<br />

Pavement Primer/Tack Coat: Pavement<br />

primer/tack coat shall consist of one<br />

part SS1h emulsion diluted with four<br />

parts water applied at an undiluted emulsion<br />

rate of 0.05 to 0.10 gal/SY (diluted<br />

emulsion rate of 0.25 to 0.50 gal/SY).<br />

2.3 EQUIPMENT<br />

A. Distributors. Distributors or spray units used for the spray application of the seal coat shall be self propelled and<br />

capable of uniformly applying 0.10 to 0.30 gallons per square yard of material over the required width of application.<br />

Distributors shall be equipped with tachometers, pressure gauges, and volume measuring devices. The mix<br />

tank shall have a mechanically powered, full sweep, mixer with sufficient power to move and homogeneously mix<br />

the entire contents of the tank.<br />

B. Spray Nozzles. Nozzles shall be free from clogs and debris and set at the same angle.<br />

C. Mixing Equipment. The mixing machine shall have a continuous flow mixing unit capable of accurately delivering<br />

a predetermined proportion of aggregate, water, and emulsion, and of discharging the thoroughly mixed product<br />

on a continuous basis. The mixing unit shall be capable of thoroughly blending all ingredients together and<br />

discharging the material without segregation.<br />

D. Spreading Equipment. Spreading equipment shall be a mechanical type squeegee/brush distributor attached to the<br />

mixing machine, equipped with flexible material in contact with the surface to prevent loss of slurry from the<br />

spreader box. It shall be maintained to prevent loss of slurry on varying grades and adjusted to assure uniform<br />

spread. There shall be a lateral control device and a flexible strike off capable of being adjusted to lay the slurry at<br />

the specified rate of application. The spreader box shall have an adjustable width. The box shall be kept clean.<br />

Emulsion and aggregate build up on the box shall not be permitted.<br />

E. Clean equipment with a petroleum solvent if previously used with a different material.<br />

Deleted: Anytown, USA - 11110000<br />

02787-3<br />

La Habra, CA – 5641-01 11/7/2011


F. Hand Squeegee or Brush Application. Hand spreading application shall be used only in places not accessible to<br />

the mechanized equipment or to accommodate neat trim work at curbs, etc. Material that is applied by hand shall<br />

meet the same standards as that applied by machine.<br />

G. Calibration. Spreading equipment shall be provided with a method of calibration by the manufacturer. Equipment<br />

shall be calibrated to assure that it will produce and apply a mix that conforms to the job mix formula. Calibrations<br />

shall be made with the approved job materials prior to application of the seal coat.<br />

2.4 PREPARATION<br />

A. A period of at least 60 days at +70 F daytime temperatures shall elapse between the placement of a hot mixed asphalt<br />

concrete surface course and the application of the seal coat except as permitted for remediation patching below.<br />

B. Remediate distressed areas of existing pavement by saw-cutting and removing existing pavement, regrading and<br />

compacting the underlying base course and replacing with full depth asphalt at locations and as shown on the<br />

drawings.<br />

1. Repairs not specifically shown on the plans but considered necessary by the CEC, the Geotechnical Engineer,<br />

or the CTL shall be identified and submitted as an RFI to the Construction Manager (CM) prior to<br />

commencement of repairs.<br />

2. Repairs submitted by RFI and approved shall be performed as directed by the CEC. Cost for such work directed<br />

and performed will be paid for in accordance with the “Changes in the Work” Clause of the General<br />

Conditions.<br />

3. Repairs shall be completed 30 days prior to the application of the seal coat.<br />

C. Longitudinal and traverse cracks in excess of 0.25 inch, but less than 1 inch shall be sealed with a crack sealing<br />

material compliant with ASTM D6690 Type II or higher, compatible with the specified seal coat emulsion prior to<br />

the seal coat application. Cracks that contain weed or other live vegetable matter shall be treated with a locally approved,<br />

non-oil based sterilant prior to applying the crack filler.<br />

D. Remove oil drippings or grease buildup determined by the CEC to be detrimental to the subsequent seal coat performance<br />

by scraping excessive buildup and by steam cleaning. Prevent oil contaminated water from entering<br />

storm sewer inlets. After cleaning, treat cleaned areas with the oil spot primer.<br />

E. Immediately prior to applying the primer and seal coat, the surface shall be cleared of all loose material, dirt, dust,<br />

grease, oil, vegetation and other objectionable material. If water is used, cracks shall be allowed to dry thoroughly<br />

before applying the seal coat.<br />

F. Protect existing manholes, inlets, vaults, valve boxes, meter boxes, etc. as necessary to maintain free accessibility<br />

upon completion of seal coat application. Surfaces adjacent to seal coat application areas such as sidewalks, curb<br />

and/or gutter, storefronts, etc. shall be protected by use of felt paper anchored with clean aggregate, or by shielding<br />

components with plywood during application.<br />

G. Coordinate limits of seal coat application operations with Owner’s Construction Manager and Store Manager to<br />

avoid interruption to store operations. Protect adjacent areas of the parking lot outside of current seal coat application<br />

limits to avoid tracking onto adjacent areas. Partition off limits of current seal coat operations until surface is<br />

traffic ready.<br />

H. Coordinate with Store Manager to deactivate lawn sprinkler systems least 48 hours prior to placing the seal coat<br />

and remain off for at least 24 hours after the seal coat application.<br />

2.5 APPLICATION<br />

A. Apply seal coat at a total rate (undiluted) of __0.23___gal./SY. Formatted: Underline<br />

02787-4<br />

La Habra, CA – 5641-01 11/7/2011<br />

Deleted: EDITOR NOTE: Specify the<br />

following tack coat if necessary due to<br />

the condition of existing pavement as<br />

determined by Engineer.<br />

Apply a primer/tack coat at a rate of<br />

0.05 to 0.10 gal/sq.yd. Remove loose<br />

gravel by sweeping prior to application of<br />

primer.<br />

Deleted: EDITOR NOTE: Insert application<br />

rate below. Table 2 serves as a<br />

guide for application rates. Delete this<br />

Editor note including Table prior to printing.<br />

TABLE 2 Guidelines for Application<br />

Rate<br />

Existing Pavement Surface ... [1]<br />

Deleted: Anytown, USA - 11110000


B. The Minimum/Maximum application rate shall be between 0.10 and 0.17 gal/SY per application.<br />

C. Dampen pavement with a fog spray of water if ambient temperatures exceed 80°F. No standing water shall remain<br />

on the surface.<br />

D. Apply the first coat uniformly in a manner such that the combined application of the first and second coats equal<br />

the total rate specified above.<br />

E. Suspended application when the distribution tank has less than 100 gallons left and refill to prevent irregular patterns<br />

or misses.<br />

F. Each coat shall be allowed to dry and cure initially a minimum of 2-4 hours before applying any subsequent coats.<br />

The initial drying shall allow evaporation of water of the applied mixture, resulting in the coating being able to<br />

sustain light foot traffic. The initial curing shall enable the mixture to withstand vehicle traffic without damage to<br />

the seal coat.<br />

G. Apply the second coat in the same manner as outlined for the first coat.<br />

H. Apply additional coats if and where necessary as determined by the CEC.<br />

1. Submit an RFI identifying extent of additional coats for approval prior to application.<br />

2. Apply additional coats in accordance with RFI approval. Cost for such additional work directed and performed<br />

will be paid for in accordance with the “Changes in the Work” Clause of the General Conditions.<br />

I. The finished surface shall present a uniform texture with no streaks.<br />

J. The final coat shall be allowed to dry a minimum of eight hours in dry daylight conditions before opening to traffic,<br />

and initially cure enough to support vehicular traffic without damage to the seal coat.<br />

K. Where marginal weather conditions exist during the eight hour drying time, additional drying time shall be allowed.<br />

The length of time shall be as specified by the supplier. The surface shall be checked after the additional<br />

drying time for trafficability before opening the section to vehicle traffic.<br />

2.6 FIELD QUALITY CONTROL<br />

A. Responsibilities: Unless otherwise specified, the quality control tests and inspections specified below will be conducted<br />

by the Owner’s Construction Testing Laboratory (CTL) at no cost to the Contractor in accordance with<br />

Section 01458. The Contractor shall perform additional testing or inspection as considered necessary by the Contractor<br />

for assurance of quality control. Field testing, frequency, and methods may vary as determined by and between<br />

the Owner and CTL.<br />

B. A minimum of one sample per day shall be tested for the properties of Table 1. A random sample of approximately<br />

one-quart of the composite mix will be obtained daily by the Contractor and stored in a glass container.<br />

The containers shall be sealed against contamination and retained in storage by the Owner for a period of six<br />

months. Samples shall be stored at room temperature and not be subjected to freezing temperatures.<br />

C. Certify in writing that the seal coat placement is in accordance with specification requirements.<br />

END OF SECTION<br />

Deleted: Anytown, USA - 11110000<br />

02787-5<br />

La Habra, CA – 5641-01 11/7/2011


Page 4: [1] Deleted Mike Holmes 10/7/2011 4:27:00 PM<br />

EDITOR NOTE: Insert application rate below. Table 2 serves as a guide for application rates.<br />

Delete this Editor note including Table prior to printing.<br />

TABLE 2 Guidelines for Application Rate<br />

Existing Pavement Surface<br />

Total, Undiluted Application Rate, gallons/square yard<br />

Smooth, Dense 0.22 – 0.25<br />

Medium 0.24 – 0.28<br />

Rough Aged 0.26 – 0.30<br />

Excessively Rough, Aged 0.29 – 0.34


UniSpec II – Civil (Master Site Specifications) 012811<br />

Formatted: Left: 54 pt, Right: 54<br />

pt, Top: 54 pt, Bottom: 36 pt<br />

SECTION 02812 (32 8400) – SITE IRRIGATION SYSTEM<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes<br />

1. Underground, automatically controlled lawn and shrub bed irrigation system including electrical connections,<br />

water main connections, and accessories.<br />

B. Related Requirements<br />

1. Section 02300 - Earthwork. Trenching, backfill, and compaction for utilities.<br />

2. Section 02510 - Water Distribution Systems.<br />

3. Section 02900 - Planting. Extended Maintenance Service for Site Irrigation System.<br />

4. Section 02370 -Erosion Control<br />

1.2 REFERENCES<br />

A. ASTM International (ASTM)<br />

1. ASTM D2239 - Polyethylene (PE) Plastic Pipe (SIDR-PR) Based on Controlled Inside Diameter.<br />

2. ASTM D2241 - Poly (Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDR-Series).<br />

3. ASTM D2564 - Solvent Cement for poly (Vinyl Chloride) (PVC) Plastic Pipe and Fittings.<br />

4. ASTM D2609 - Plastic Insert Fittings for Polyethylene (PE) Plastic Pipe.<br />

5. ASTM D2855 - Making Solvent-Cemented Joints with Poly (Vinyl Chloride) (PVC) Pipe and Fittings.<br />

B. National Fire Protection Agency (NFPA)<br />

1. NFPA 70 - National Electrical Code (NEC).<br />

C. American Society of Safety Engineers<br />

1. ASSE 1013 - Performance Requirements for Reduced Pressure Principle Backflow Preventers and Reduced<br />

Pressure Fire Protection Principle Backflow Preventers.<br />

2. ASSE 1015 - Performance Requirements for Double Check Backflow Prevention Assemblies and Double<br />

Check Fire Protection Backflow Prevention Assemblies.<br />

1.3 SUBMITTALS<br />

A. Submittal process: Submit in accordance Section 01330 - Submittal Procedures. Submit required submittals within<br />

30 days after contract award. Submittals shall be available at all times to the Wal-Mart Construction Manager.<br />

B. Quality Assurance Submittals:<br />

1. Irrigation Contractor Qualifications: Provide minimum of 3 references and list of similar projects with<br />

owner's names, addresses, and telephone numbers.<br />

C. Closeout Submittals:<br />

1. As-Built Drawings: Furnish two sets, noting exact locations of elements and changes to Construction<br />

Drawings.<br />

2. Operation Manual: Furnish two copies, bound in 1 inch diameter three ring binders, indexed and tabbed for<br />

easy reference, and labeled on spine and cover. Manual shall include following:<br />

a. Approved submittals as specified herein.<br />

b. Installation instructions including mounting details for control valves.<br />

c. Operating Instructions:<br />

1) Winterization procedures.<br />

2) Recommended operation sequence, frequency, and length of operation cycle, as per relationship<br />

to estimated absorption rate, evaporation rate, and anticipated flow.<br />

d. Maintenance Instructions:<br />

02812-1<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


1) Manufacturers' product data, installation, and maintenance instructions.<br />

2) Copies of completed warranty information. Contractor to complete and mail necessary warranty<br />

registration information to manufacturer keeping copies for Owner.<br />

3. Controller Chart: Prepare color coded chart reduced in size, mounted on the inside of the controller cabinet,<br />

containing same plan information as as-built drawings, and laminated in plastic on both sides, with following<br />

specific information:<br />

a. Note routing of main line, control wires, and controller location.<br />

b. Identify valves as to size, station number shown on controller, and type of irrigation head (e.g. micro<br />

spray head, rotary head) for each valve.<br />

c. Delineate each station's limits of coverage by color-coding, with each station having different color<br />

showing its zone with zone number designation.<br />

d. Size, type, and location of water source.<br />

4. Meetings and Inspections Log.<br />

5. Certification of Conformance: Provide certificate of satisfactory performance of irrigationsystem installation<br />

signed by the Contractor and Landscape Architect or irrigation designer for attachment to CEC Conformance<br />

Letter included at the end of Section 01456.<br />

1.4 QUALITY ASSURANCE<br />

A. Contractor Qualifications:<br />

1. Minimum of 3 consecutive years experience in area of project and having installed other jobs of similar<br />

size and scope including drip irrigation and ET Series Controllers.<br />

B. Pre-Work Meeting and Inspection: Convene a pre-work meeting at the Project site prior to commencing subgrade<br />

preparation for site paving to review conditions of operations, procedures and coordination with related work. Require<br />

attendance of parties directly affecting work of this Section including but not limited to Contractor, irrigation<br />

contractor, site work contractor, Landscape Architect or irrigation designer.<br />

1. Tour, inspect, and discuss conditions of Project site.<br />

2. Review approach and schedule for the following items:<br />

a. Water source.<br />

b. Mainline routing and installation.<br />

c. Zone installation and site preparation.<br />

d. Material availability.<br />

e. Sleeve installation, installation of curb and paving markings for sleeve locations and coordination<br />

with site work contractor.<br />

f. Required Inspections.<br />

C. Irrigation Inspections: Conduct the following inspections during the course of the work in the presence of the<br />

Landscape Architect or irrigation designer to verify conformance to specification requirements. Notify CEC for<br />

observation of inspection by the Landscape Architect or irrigation designer. Correct noted deficiencies during<br />

each inspection prior to proceeding with subsequent work. After each inspection complete Irrigation Inspection<br />

Checklist included at the end of this Section signed by all signitors listed thereon.<br />

1. Pre-Installation Inspection and Static Pressure Test: Perform static pressure test, completed installation of<br />

sleeves, sleeve markings of curbs and paving, status of irrigation schedule and water source, potential conflicts<br />

between irrigation installation and other site utilities.<br />

2. Mainline Inspection: Inspect the installed main line, electronic control valves, wiring prior to backfilling<br />

main line.<br />

3. Substantial Completion Inspection: Inspect all completed irrigation work. Landscape Architect or irrigation<br />

designer will develop a punch list of deficient or incomplete items and deliver to Contractor within 3 calendar<br />

days of inspection date.<br />

4. Final Inspection: Within 30 days of project substantial completion date and subsequent to correction of<br />

punch list deficiencies, convene a final inspection of all irrigation work.<br />

5. Warranty Inspections: Convene a warranty inspection 30 calendars days prior to expiration of warranty period<br />

specified in Part 3 of Section 02900.<br />

D. If additional landscape architect or irrigation designer site visits for observation of inspection are required beyond<br />

those described herein as determined by Wal-Mart to determine correction to non-conforming or incomplete work,<br />

02812-2<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


the Contractor shall reimburse the Owner the sum of $4000 for each additional visit to cover expenses. Additional<br />

site observations will be performed as required until all deviations have been corrected by the Contractor and<br />

closed by the CEC.<br />

E. Meeting and Inspection Log: Maintain log of required meetings and inspections. Record the date; time; weather<br />

conditions; and a brief summary of the discussions, decisions, and agreements reached. Landscape Architect or Irrigation<br />

Designer will review and sign log at the conclusion of the meeting. Furnish copy of log to each party attending.<br />

1.5 MEETING AND EVENT NOTIFICATIONS<br />

A. Provide the following notifications to the Owner’s Civil Engineering Consultant (CEC) within the time period<br />

listed below. CEC will notify Owner, landscape architect or irrigation designer, and other necessary sub consultants:<br />

1. Pre-Work Meeting: Minimum 14 calendar days prior to meeting date.<br />

2. Pre-Installation Inspection and Static Pressure Test: 7 calendar days prior to inspection date.<br />

3. Mainline Inspection and Hydrostatic Test: 7 calendar days prior to inspection date.<br />

4. Substantial Completion Inspection: 7 calendar days prior to irrigation substantial completion.<br />

5. Final Inspection: 7 calendar days prior to irrigation final inspection date.<br />

6. Warranty Inspection: 14 calendar days prior to inspection date.<br />

B. Provide notifications by email or other written means to show proof of delivery.<br />

1.6 PROJECT CONDITIONS<br />

A. Visit site and become familiar with nature and location of work, existing conditions, and conditions that will exist<br />

during installation.<br />

1.7 WARRANTY<br />

A. Guarantee Site Irrigation System for a period of 12-19 months following the Substantial Completion Date in accordance<br />

with the Extended Maintenance/Warranty Chart included Section 02900 and as follows:<br />

1. Defects in material, equipment, and workmanship.<br />

2. Repair of damage to premises resulting from leaks or other defects in material, equipment, and workmanship<br />

to satisfaction of Owner.<br />

1.8 EXTENDED MAINTENANCE SERVICE<br />

A. Extended Maintenance for Site Irrigation System is specified in Section 02900.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Wal-Mart will furnish irrigation products for installation by Contractor as follows:<br />

1. Automatic Controllers.<br />

2. Rainfall / Freeze Sensor.<br />

3. Flow Sensors.<br />

4. Master Valves.<br />

2.2 MANUFACTURERS<br />

A. Acceptable manufacturers shall include:<br />

1. Hunter Industries, Inc., (800) 733-2823 or Alex Bennett, National Accounts Manager (614) 264-2624.<br />

2. Rain Bird Corporation Commercial Turf Division, (800) 724-6247 or Dave Palumbo, Xeriscape Sales<br />

Manager (310) 503-4004.<br />

02812-3<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


2.3 PIPE<br />

3. The Toro Company - Irrigation Division, (888) 384-9939 or Tim Young, Managing Partner (619) 596-<br />

4261.<br />

4. HydroPoint Data Systems, Inc. (707) 769-9696 ext 412, walmart@hydropoint.com; Bill Georgas (972)<br />

618-7745; or Chris Warfield (707) 285-3259.<br />

5. Netafim USA, (888) 638-2346 or Steve McCarter, Sales Manager (972) 569-0545.<br />

6. Ametek - Armor, (800) 348-7558.<br />

7. Data Industrial, (800) 338-0312.<br />

8. Creative Sensor Technology, (508) 763-8100.<br />

9. Superior Controls Company, Inc, (661-257-3533)<br />

A. Polyvinyl Chloride (PVC): Pipe over 1 inch diameter shall conform to ASTM D224, SDR 21, and Class 200.<br />

B. Polyvinyl Chloride (PVC): Pipe 1 inch diameter and under shall conform to ASTM D2241, SDR 13.5, and Class<br />

315.<br />

C. Flexible Polyethylene (PE): Pipe shall conform to ASTM D2239, SDR 11.5, PE23, rated at 100 PSI, National<br />

Sanitation Foundation (NSF) approved. Subject to approval of Owner, PE shall be used for laterals in areas where<br />

ground is subject to freezing for extended periods of time each year.<br />

D. Joints:<br />

1. Pipe sizes 2 1/2 inch or smaller shall have bell and socket joints.<br />

2. Pipe sizes larger than 2 1/2 inch shall have snap connections with rubber gasket joints. Thrust blocking<br />

shall be required in accordance with Section 02510.<br />

E. Pipe used for reclaimed water shall be appropriate color and marked as designated for such use.<br />

F. Fittings:<br />

1. Polyvinyl Chloride (PVC) Fittings: Fittings shall conform to ASTM D2241, Schedule 40, and Molded.<br />

2. Flexible Polyethylene (PE) Lateral Line Fittings: Fittings shall conform to ASTM D2609, Type 1 PVC insert<br />

fittings designed for used with this type of pipe. Pipe and fittings shall be joined with stainless steel<br />

pinch clamps or worm gear clamps, including stainless steel screw.<br />

G. Risers above finished grade shall be black in color or receive 2 coats of black exterior semi-gloss enamel paint if a<br />

color other than black.<br />

2.4 ACCESSORIES<br />

A. Sleeves: Sleeves for pipes passing beneath paving shall conform to ASTM D2241, Schedule 40. Minimum diameter<br />

of 2 inch or 2 sizes larger than pipe scheduled to pass through them.<br />

B. PVC Solvent Cement: Cement shall conform to ASTM D2564.<br />

C. Swing Joint Connections: Connections between heads and laterals shall be thick wall, flexible, polyethylene pipe,<br />

with fittings that have male barbs on one end and either male or female screw ends opposite. Glue fittings and female<br />

barb adapters are not allowed.<br />

2.5 RECLAIMED WATER PRODUCTS AND MATERIALS<br />

A. Irrigation products used with reclaimed water shall be the appropriate color and marked as designated for such use.<br />

2.6 CUTOFF OR ISOLATION VALVES<br />

A. 3 inches or Smaller: Provide full port brass ball valves with 600 WOG rating as manufactured by Red-White<br />

Valve Corporation, Carson, CA.<br />

02812-4<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


B. Larger than 3 inches: Provide cast iron and bronze mechanical joint valves, fusion bonded epoxy coated exterior<br />

and interior, Resilient Wedge Valve as manufactured by Clow Valve Co., Oskaloosa, IA.<br />

C. Provide a valve key and cast iron cylindrical valve box with topwith each valve.<br />

2.7 QUICK COUPLER VALVES<br />

A. Provide one of following if shown on the plans:<br />

1. Rain Bird model 44NP Valve with model 44K Key.<br />

2. Hunter model HQ-44LRC with model HK-44 Key.<br />

3. Toro model 100-SLVLC 470 Series Valve and 100-SLK Coupler Key.<br />

B. Provide each valve with key having 3/4 inch male top pipe threads for hose connection.<br />

2.8 ELECTRIC CONTROL VALVES<br />

A. Provide one of the following:<br />

1. Hunter ICV Series electric remote control valves and ICZ Drip Zone Control Kit.<br />

2. Rain Bird PEB Series electric remote control valves and Medium/Low Flow Control Zone Kit.<br />

3. Netafim Control Valve Kit.<br />

4. Toro P220 Series plastic valves and DZK Drip Zone Valve Kit.<br />

B. Provide 3M DBY watertight connectors.<br />

2.9 SPRINKLER HEADS<br />

A. Full or Part Circle Pop-Up Fixed Spray Sprinkler:<br />

1. Acceptable Products:<br />

a. Hunter PRS40with MP Rotators and check valve (CV) feature.<br />

b. Rain Bird 1800 Series Sprinklers with Rotary Nozzles including PRS and SAM features.<br />

c. Toro 570Z PRX Series with MPR Precision Series Spray Nozzles.<br />

B. Full or Part Circle Pop-up Gear Driven Rotor Sprinkler:<br />

1. Acceptable Products:<br />

a. Rain Bird Rotor, 5000 Series plus MPR rotor nozzle with Seal-A-Matic (SAM) check valve.<br />

b. Toro Super T5P-COM, with check valve or Toro TR-XTP Series with factory installed check valve,<br />

trajectory adjustment, and X Flow Device.<br />

c. Hunter PGP and PGJ series pop-up rotors, with check valve.<br />

C. Pressure Compensating Micro-Spray Nozzles:<br />

1. Acceptable Products:<br />

a. Rain Bird Micro Spray.<br />

b. Hunter Micro Spray.<br />

c. Toro Stream Spray and Stream Bubbler Nozzles with PC.<br />

2.10 LOW VOLUME AND DRIPLINE IRRIGATION<br />

A. Hunter Professional Landscape Dripline with 0.4, 0.6, or 1.0 GPH built-in emitters.<br />

B. Netafim Techline with 0.4, 0.6, or 0.9 GPH dripper.<br />

C. Toro Drip-In PC drip tubing with 0.5 or 1.0 GPH emitter.<br />

2.11 VALVE BOX<br />

Deleted: [Editor Note: Use Toro Drip<br />

line only in groundcover and shrub beds<br />

with mulch]<br />

02812-5<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. Valve boxes shall be manufactured by Ametek, Plymouth Products Division, Sheboygan WI., RainBird Corporation<br />

or equal by acceptable manufacturer. No irrigation valve box shall be placed in pavement areas unless otherwise<br />

shown on the Drawings.<br />

1. When used with single valve, provide Economy Turf Box or Rain Bird model VB-RND with green colored<br />

snap fit cover labeled "Valve Box".<br />

2. When used with 2 or more valves, provide Jumbo Box or Rain Bird model VB-STD with 20 inch x 14 inch<br />

cover opening with cover labeled "Control Valve".<br />

2.12 MANUAL DRAIN VALVES<br />

A. Manual drain valves shall be provided by acceptable manufacturers specified above.<br />

2.13 CONTROL WIRE<br />

A. Number 14-size minimum copper wire, U. L. approved for underground direct burial.<br />

1. Colored wire shall have same color-coding as shown on controller.<br />

2. Provide single wire from controller to each valve.<br />

3. Provide common neutral from controller to each valve.<br />

4. Provide a minimum of two extra sets of wire, 2 control and 1 neutral, to each end of the main for future use.<br />

a. Loop Systems: Provide two spare control wires in each direction to halfway point of loop.<br />

2.14 BACKFLOW PREVENTOR<br />

A. Comply with requirements and codes of local governing authority regarding backflow prevention.<br />

B. Provide the necessary materials, insulation/draining capabilities, and insulated fiberglass enclosure, dark green in<br />

color.<br />

C. Backflow preventers shall be type suitable for use in high hazard cross connection to potable water system as<br />

manufactured by one of the following manufacturer’s: Watts Regulator Company, Febco, or Wilkins.<br />

1. Reduced pressure backflow preventers shall be ASSE # 1013 and labeled accordingly.<br />

2. Double check valve assembly backflow preventers shall be ASSE # 1015 and labeled accordingly.<br />

3. In absence of local codes or requirements, provide double check assembly backflow preventer installed in<br />

strict accordance with manufacturer's written instructions.<br />

2.15 METER<br />

A. Meter and meter box shall conform to requirements of local utility company.<br />

2.16 RAINFALL / FREEZE SENSOR (OWNER FURNISHED / CONTRACTOR INSTALLED)<br />

A. Rainfall Sensor:<br />

1. Irritrol Wireless Rain Sensor, Model RS 1000.<br />

B. Rainfall / Freeze Sensor:<br />

1. Irritrol Wireless Rain/Freeze Sensor, Model RFS 1000.<br />

2.17 FLOW SENSOR (OWNER FURNISHED / CONTRACTOR INSTALLED)<br />

A. Data Industrial – Series 735PV or 228PV.<br />

Deleted: [Editor Note: Specific model<br />

numbers for the flow sensors, master<br />

valve, and controller should be noted on<br />

the plans.]<br />

B. Creative Sensor Technology – Series FSI.<br />

2.18 MASTER VALVE (OWNER FURNISHED / CONTRACTOR INSTALLED)<br />

A. Superior Controls Company, Inc. – Angle or Globe 3100 Series.<br />

02812-6<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


2.19 AUTOMATIC SMART CONTROLLER (OWNER FURNISHED / CONTRACTOR INSTALLED)<br />

A. Controller shall have anintegral weatherproof, lockable stainless steel pedestal cabinet with internal transformer.<br />

1. HydroPoint Weather-TRAK ET Pro2 Central Series with 1 year WT .net service and 5 year hardware warranty.Model:<br />

WtPro2C-XX-SPL where XX is the number of stations.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Pressure/Flow Test: Perform calculations according to the Irrigation Association’s 3-Step Method. Provide written<br />

calculations to the Owner’s CEC including the following site information:<br />

1. Static or residual pressure at the POC.<br />

2. Calculation of pressure for “worst case” sprinkler head.<br />

3. Calculation of GPM per zone.<br />

Deleted: [Editor Note: Use one of the<br />

controllers listed below manufactured by<br />

RainBird or Hunter for the building<br />

planter only when no site irrigation system<br />

exist. Delete the controllers from the<br />

specifications if not used.]<br />

AUTOMATIC CONTROLLER<br />

Hunter XC-200i<br />

RainBird ESP-4Mi<br />

B. Prior to installation, receive approval from General Contractor to proceed with construction.<br />

C. Contractor shall field verify all aboveground and underground utilities prior to start of work.<br />

3.2 EXCAVATION<br />

A. Trenching and Backfilling:<br />

1. Trenching and backfilling shall conform to Section 02300 and 02370.<br />

2. Excavate trench to proper depth as shown or specified.<br />

3. Minimum trench width shall be 3 1/2 inches.<br />

4. Over excavate trenches deeper than required in soils containing rock or other hard material that might damage<br />

pipe and backfill to proper depth with selected fine earth or sand.<br />

5. Backfill and hand tamp over excavation prior to installing piping.<br />

6. Keep trenches free of obstructions and debris that would damage pipe.<br />

7. Irrigation piping shall not be installed in same trench as heating duct, electric ducts, storm and sanitary<br />

sewer lines, water and gas mains.<br />

B. Do not cut sidewalks, paved areas, or curb and gutter when trenching for piping unless otherwise noted on the<br />

Drawings.<br />

1. Provide sleeves as specified in Part 2 above under paving prior to installation of paving.<br />

2. Auger, bore, or tunnel under existing paving without disturbing pavement. Damaged pavement shall be<br />

removed and replaced in accordance with Section 02740 or 02751.<br />

3.3 WATER METER<br />

A. Provide water meter box for irrigation system if required or shown on the Drawings.<br />

3.4 PIPING INSTALLATION<br />

A. Minimum cover from top of piping to finished grade shall be provided as follows:<br />

1. Lawn and planting areas:<br />

a. Mains and Control Valves: 18 inches.<br />

b. Laterals: 12 inches.<br />

2. Drives or parking areas: 24 inches.<br />

B. Clearances: Maintain 3 inch minimum horizontal clearance between parallel lines in same trench or vertical clearance<br />

between lines crossing at angles.<br />

C. Special Requirements - PVC and PE pipe:<br />

1. Snake pipe in trench at least 1 foot per 100 feet of pipe to allow for thermal expansion.<br />

2. Pipe laterals shall be laid to drain to low point drains located at lowest elevations of each zone.<br />

02812-7<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. Rest full length of pipe section on bed of trench, excavating recesses to accommodate joints. Do not lay pipe on<br />

unstable material or blocking, or when in opinion of Owner conditions are unsuitable.<br />

E. Threaded Plastic Pipe Jointing:<br />

1. Do not use solvent cement on threaded joints.<br />

2. Wrap joints with Teflon tape or use virgin Teflon lubricant.<br />

F. Bell and Socket Plastic Pipe Jointing: Cement joints in accordance with ASTM D2855.<br />

3.5 QUICK COUPLER AND AUTOMATIC LOW POINT DRAIN VALVES<br />

A. Provide quick coupler valves as shown on the drawings to accommodate winterization.<br />

B. Provide automatic low point drain valves on all zones. Provide two valves at lowest point of each zone with each<br />

drain installed above a 12 inch by 12 inch by 12 inch deep area of coarse washed gravel.<br />

3.6 SLEEVING<br />

A. Provide sleeves for both piping and control wiring where either passes under paved surfaces.<br />

1. Depths of sleeves shall be same as that required for piping at each location or condition.<br />

2. Extend sleeves 12 inches beyond paving at each end.<br />

3. Install permanent benchmark at top of curbs for reference to sleeve locations.<br />

3.7 VALVES<br />

A. Do not locate beneath paved surfaces.<br />

B. Install plumb to within 1/16 inch.<br />

C. Locate within valve box with 6 inch deep layer of coarse gravel beneath bottom of valve.<br />

D. Top of quick coupler valves shall be 6 inches to top of valve box. Top of gravel layer shall be 3 inches below top<br />

of valve.<br />

E. Master Valve (if required on the Drawings):<br />

1. Locate immediately behind backflow preventer.<br />

2. Valve shall be energized by master valve circuit on automatic controller.<br />

3.8 SPRINKLERS<br />

A. Install plumb to within 1/16 inch with top collar, not nozzle, flush with finish grade.<br />

B. Provide swing joint with each sprinkler except where entire head is raised above grade and/or where rigid riser<br />

piping is required.<br />

C. Heads adjacent to paving and curb: In accordance to the California Model Water Efficient Landscape Ordinance,<br />

overhead irrigation shall not be permitted within 24 inches of any non-permeable surface.<br />

3.9 ELECTRICAL CONNECTIONS AND CONTROL WIRE<br />

A. Conform to the National Electrical Code (NEC) and local electrical codes.<br />

Deleted:<br />

Deleted: Locate between 6 and 12<br />

inches from edge of paving or back of<br />

curb to prevent car overhang to conflict<br />

with a fully extended sprinkler.<br />

B. Provide electrical connection to system as designated on the Drawings and as specified herein.<br />

C. Wire Placement:<br />

1. Do not run control and power supply wiring in same conduit.<br />

02812-8<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


2. Provide continuous runs of wire between controller and valves. Splices shall be made with one of following:<br />

a. Watertight below ground electrical junction boxes.<br />

b. Water-tight connectors, such as utilized for valves, and located within valve box for ease of locating.<br />

c. The location of electrical splices shall be shown on the As-Built drawings.<br />

3. Bury control wire beside pipe in same trench. Bundle and tape together at not more than 10 ft intervals.<br />

D. Expansion Loops: Construct by wrapping wire around 1/2 inch diameter pipe to create coil. A 3 foot section of<br />

wire shall be used to create 12 inch coil with 6 foot section being used to create 24 inch coil.<br />

1. Provide 12 inch coils at each wire splice, not including valves, and at each change of wire direction.<br />

2. Provide 24 inch coils at each control valve and where each valve enters conduit for automatic controller.<br />

3.10 BACKFILLING<br />

A. Sand or fine-grained soils shall be used for initial backfill to sufficient depth to prevent damage to pipe from rocks<br />

or other debris during compaction of subsequent backfill.<br />

B. Fill trench to within 3 inches of finish grade with excavated soil and compact in accordance with Section 02300.<br />

C. Fill top 3 inches with existing topsoil in planting or turf areas and wheel roll until compaction of backfill is same<br />

as surrounding soil.<br />

D. Grade backfilled trench uniform with surrounding grades.<br />

3.11 BACKFLOW PREVENTER<br />

Deleted: O<br />

A. Comply with local codes for installation of backflow preventer. In absence of local codes, install in accordance<br />

with manufacturer's written instructions.<br />

3.12 RAINFALL / FREEZE SENSOR<br />

A. Location and installation shall be as shown on the Drawings and per manufacturer’s written recommendations.<br />

3.13 FLOW SENSOR<br />

A. Location and installation shall be as shown on the Drawings and per manufacturer’s written recommendations.<br />

3.14 MASTER VALVE<br />

A. Location and installation shall be as shown on the Drawings and per manufacturer’s written recommendations.<br />

1. Master valve normal operating position shall be open and shall be electronically actuated.<br />

3.15 AUTOMATIC CONTROLLER<br />

A. Location and installation shall be as shown on the Drawings and approved by Owner prior to installation.<br />

B. Provide rigid conduits for both power supply and control wiring.<br />

1. Control wire conduit shall extend to 18 inches below grade.<br />

2. Pull spare wires for future valves and extend to area outside paved surfaces.<br />

C. Provide electrical grounding for controller in accordance with manufacturer's written instructions.<br />

3.16 FIELD QUALITY CONTROL<br />

A. Inspection and Adjustments: Following installation and prior to Substantial Completion Inspection, make final adjustments<br />

to site irrigation including but not limited to the following:<br />

1. Flush system completely, with nozzles and screens removed and drip lines ends open to extract debris.<br />

02812-9<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


2. Verify sprinkler operation and alignment for direction of throw. Correct as necessary.<br />

3. Check pop-up rotor/rotator nozzling for proper arc of spray with no overthrow onto pavement. Adjust nozzles<br />

as necessary for proper throw and matched precipitation rate.<br />

4. Ensure uniform distribution exists.<br />

5. Ensure proper irrigation head operational after landscaping and/or sod installation.<br />

B. Main Line Inspection and Hydrostatic Tests:<br />

1. Owner’s CTL Inspector and Irrigation Designer will observe testing.<br />

2. Center load Piping with small amount of backfill to prevent arching or slipping under pressure.<br />

3. Install risers and caps on mainline and sub-main lines. Apply continuous and static water pressure of 75 psi<br />

for a minimum of 3 hours when welded plastic joints have cured at least 3 hours.<br />

4. Allowable Leakage:<br />

a. Utilize the following formula to calculate the allowable leakage for O-ring gasket pipe.<br />

L=SD(P) 0.5<br />

133,200<br />

In which: L=Allowable leakage in gallons per hour<br />

S=Length of pipe tested in feet<br />

D=Pipe diameter in inches<br />

P=Average test pressure in PSI gauge<br />

b. No allowable leakage shall be acceptable with solvent based mainline system.<br />

5. Repair leaks and retest.<br />

C. Demonstration: Following final adjustment, operate entire installation to demonstrate complete and successful operation<br />

of equipment.<br />

END OF SECTION<br />

02812-10<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


IRRIGATION INSPECTION CHECKLIST<br />

INSPECTION PROCEDURE<br />

Contractor shall arrange and conduct inspection and complete checklist and identify defects.<br />

Conduct inspections in accordance with the Quality Assurance and QualityControl provisions of the Specifications.<br />

All undersigned parties shall accompany inspection.<br />

Visually identify location of each defect at the site.<br />

After irrigation inspection is complete FAX signed inspection form to Wal-Mart Construction Manager within 24<br />

hours.<br />

COMPLETION OF CHECKLIST AND DEFECTS FORM<br />

Answer each checklist item Yes or No.<br />

Mark “N/A” on checklist items which do not apply.<br />

Identify defects and resolutions on the Wal-Mart Deviation Log. (www.bldgportal.com, enter username and password,<br />

select Deviation Log)<br />

Number each defect as follows:<br />

o Identification Symbol-Checklist Item No.-Defect No. (E.g. ML-1-3)<br />

o The defect number shall be numbered in sequence for each checklist item.<br />

(ML) MAIN LINE INSPECTION:<br />

Piping:<br />

1. Is the correct type and size of pipe installed? YES___ NO___ N/A___<br />

2. Is the pipe installed at the correct depth? YES___ NO___ N/A___<br />

3. Does the trench meet the required minimum width? YES___ NO___ N/A___<br />

4. Is rock present within the trench? YES___ NO___ N/A___<br />

5. If rock is present, has it been properly mitigated? YES___ NO___ N/A___<br />

6. Is minimum 3 inch clearance provided between the main and lateral lines? YES___ NO___ N/A___<br />

7. Are joints primed prior to solvent weld? YES___ NO___ N/A___<br />

8. Is the main line snaked minimum of 1 foot per 100 foot of trench? YES___ NO___ N/A___<br />

9. Are joints cemented in accordance with ASTM standard specified? YES___ NO___ N/A___<br />

10. Does PVC cement conform to ASTM standards specified? YES___ NO___ N/A___<br />

Valves:<br />

1. Is valve box installed plumb and flush with proposed finish grade? YES___ NO___ N/A___<br />

2. Is 6 inch layer of coarse gravel installed beneath base of valve? YES___ NO___ N/A___<br />

3. Is master valve sized to allow proper flow rate? YES___ NO___ N/A___<br />

4. Are splices installed with waterproof connections? YES___ NO___ N/A___<br />

Control Valves:<br />

1. Are continuous wire runs provided between valve boxes and controller? YES___ NO___ N/A___<br />

2. Is control wire placed beside main line? YES___ NO___ N/A___<br />

3. Are control wires bundled and taped at 10 foot intervals? YES___ NO___ N/A___<br />

4. Are expansion loops provided at each valve, wire splice, and each change of direction? YES___ NO___ N/A___<br />

(SC) SUBSTANTIAL COMPLETION INSPECTION<br />

1. Does mainline pressure meet design requirements? YES___ NO___ N/A___<br />

2. Are the backflow prevention/master valve installed as shown on the plans and<br />

functioning properly? YES___ NO___ N/A___<br />

3. If pump station is installed, does it operate at the specified capacity? YES___ NO___ N/A___<br />

4. Does head layout provide 100 percent coverage? YES___ NO___ N/A___<br />

5. Does drip system layout and installation provide 100 percent coverage? YES___ NO___ N/A___<br />

6. Are the controller / flow sensor functioning properly? YES___ NO___ N/A___<br />

7. Is the ET source communicating with the base station? YES___ NO___ N/A___<br />

8. Are rain and freeze sensors installed and functioning properly? YES___ NO___ N/A___<br />

02812-11<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


(F) FINAL INSPECTION<br />

1. Does mainline pressure meet design requirements? YES___ NO___ N/A___<br />

2. Does head layout provide 100 percent coverage? YES___ NO___ N/A___<br />

3. Does drip system layout and installation provide 100 percent coverage? YES___ NO___ N/A___<br />

4. Are the controller / flow sensor functioning properly? YES___ NO___ N/A___<br />

5. Is the ET source communicating with the base station? YES___ NO___ N/A___<br />

(W) WARRANTY INSPECTION<br />

1. Does mainline pressure meet design requirements? YES___ NO___ N/A___<br />

2. Does head layout provide 100 percent coverage? YES___ NO___ N/A___<br />

3. Does drip system layout and installation provide 100 percent coverage? YES___ NO___ N/A___<br />

4. Are the controller / flow sensor functioning properly? YES___ NO___ N/A___<br />

5. Is the ET source communicating with the base station? YES___ NO___ N/A___<br />

(H) HYDROSTATIC TEST:<br />

1. Does the main line hold the specified pressure for the specified length of time? YES___ NO___ N/A___<br />

2. Are leaks present? YES___ NO___ N/A___<br />

3. Were repairs made and line retested? YES___ NO___ N/A___<br />

4. If retesting is required, does retest pass? YES___ NO___ N/A___<br />

5. Does o-ring gasket pipe remain within the calculated allowable leakage? YES___ NO___ N/A___<br />

ATTENDED BY:<br />

GENERAL CONTRACTOR<br />

__________________________________________________<br />

(Signature)<br />

__________________________________________________<br />

(Printed name and title)<br />

IRRIGATION CONTRACTOR<br />

__________________________________________________<br />

(Signature)<br />

__________________________________________________<br />

(Printed name and title)<br />

LANDSCAPE ARCHITECT OR<br />

IRRIGATION DESIGNER<br />

__________________________________________________<br />

(Signature)<br />

__________________________________________________<br />

(Printed name and title)<br />

CIVIL ENGINEERING<br />

CONSULTANT<br />

__________________________________________________<br />

(Signature)<br />

__________________________________________________<br />

(Printed name and title)<br />

02812-12<br />

Deleted: Anytown, USA - 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec II 072911<br />

SECTION 02821 (32 3113) – CHAIN LINK FENCES AND GATES (BUILDING RELATED)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Building related chain link fence.<br />

2. Columns for Garden Center aluminum trusses at shade cloth canopy.<br />

3. Chain link gates.<br />

B. Related Requirements:<br />

1. Section 03310 - Cast-In-Place Structural Concrete: Concrete anchorage for posts.<br />

2. Section 13121 - Fabric Structures: Aluminum trusses and shade cloth canopy at Garden Center.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A 392 - Zinc-Coated Steel Chain-Link Fence Fabric.<br />

2. ASTM F 1043 - Strength and Protective Coatings on Steel Industrial Chain Link Fence Framework.<br />

C. Chain Link Fence Manufacturers Institute (CLFMI): Product Manual.<br />

1.3 QUALITY ASSURANCE<br />

A. Manufacturer Qualifications: Company specializing in manufacturing the products specified in this Section with<br />

minimum 3 years documented experience.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

PART 2 - PRODUCTS<br />

2.1 DESIGN CRITERIA<br />

A. Fencing system and installation engineered to withstand 85 mph minimum windload assuming 50 percent<br />

coverage with hanging plastic banners and signage.<br />

B. Chain link fabric, posts, and components shall conform to the requirements of the CLFMI Product Manual unless<br />

otherwise shown or specified.<br />

2.2 MATERIALS<br />

A. Steel Posts: Type I or II or roll formed "C" Section steel conforming to CLFMI and as specified hereinafter.<br />

B. Fabric: No. 9 gage galvanized steel wire in 2 inch mesh; ASTM A 392, height as shown.<br />

1. Where mini-mesh is shown, provide 1 inch mesh.<br />

2. Fabric height less than 72 inches: Top and bottom selvages knuckled.<br />

3. Fabric height 72 inches and greater: Top selvage twisted, bottom selvage knuckled.<br />

02821 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. PVC Coating (Exterior Fencing):<br />

1. Fabric: Class 1 PVC coating conforming to CLFMI Product Manual. Color: Black.<br />

2. Posts, Rails, and Accessories: Apply thermally fused PVC polymer coating 10 mil min thickness in<br />

accordance with ASTM F 1043. Color shall be black to match PVC coated fabric.<br />

2.3 COMPONENTS<br />

A. End, Corner, and Pull Posts: Minimum sizes and weights as follows unless otherwise shown.<br />

1. Up to 13 Foot Fabric Height: Type I or II in accordance with CLFMI Product Manual.<br />

2. 13 foot and over Fabric Height (If required):<br />

a. Type I Posts: Round; 4.0 inch outside diameter pipe, 9.10 lbs/lin ft.<br />

b. Type II Posts: Round 4.0 inch outside diameter pipe, 6.56 lbs/lin ft.<br />

B. Columns for Garden Center aluminum trusses at shade cloth canopy:<br />

1. Locations and heights as indicated on the Drawings.<br />

2. Type I Posts: Round; 4.0 inch outside diameter pipe, minimum 9.10 lbs/lin ft., designed to support gravity<br />

and wind loads acting on the aluminum truss/shade cloth system, as provided by Walmart’s aluminum truss<br />

supplier (reference Section 13121).<br />

C. Line (Intermediate) Posts: Minimum sizes and weights as follows unless otherwise shown.<br />

1. Up to 8 Foot Fabric Height: Type I, II, or "C" Section in accordance with CLFMI Product Manual.<br />

2. Over 8 Foot Fabric Height:<br />

a. Type I Posts:<br />

1) Round: 2.875 inch outside diameter pipe, 5.79 lbs/lin ft.<br />

2) Square: 2.5 inches x 2.5 inches outside dimension, 5.10 lbs/lin ft.<br />

b. Type II Posts: Round 2.875 inch outside diameter pipe, 4.64 lbs/lin ft.<br />

D. Gate Posts: Type I or II in accordance with CLFMI Product Manual unless otherwise shown.<br />

E. Top, Bottom, and Intermediate Rails: Manufacturer's longest lengths.<br />

1. Type I or II in accordance with CLFMI Product Manual.<br />

2. Couplings: Expansion type, approximately 6 inches long.<br />

3. Attaching Devices: Means of attaching top rail securely to each gate, corner, pull, and end post.<br />

2.4 ACCESSORIES<br />

A. Sleeves: Galvanized steel pipe with inside diameter not less than 1/2 inch greater than outside diameter of fence<br />

posts. Provide steel plate closure welded to bottom of sleeves of width and length not less than 1 inch greater than<br />

outside diameter of sleeve.<br />

1. Up to 6 Foot Fabric Height: Provide sleeve not less than 12 inches long.<br />

2. Over 6 Foot Fabric Height (Not for Partitions Tight to Roof Deck): Provide sleeve not less than 24 inches<br />

long.<br />

3. Fabric Installed Tight to Roof Deck (Posts Braced to Roof Structure): Provide sleeve not less than 12<br />

inches long.<br />

B. Tension Wire: 7 gage steel, metallic-coated coil spring wire, located at bottom of fence fabric.<br />

C. Wire Ties: 11 gage galvanized steel.<br />

D. Post Brace Assembly: Manufacturer's standard adjustable brace at end and gate posts and at both sides of corner<br />

and pull posts, with horizontal brace located at mid-height of fabric. Use same materials as top rail for brace, and<br />

truss to line posts with 0.375 inch diameter rod and adjustable tightener.<br />

E. Post Tops: Galvanized steel, weather tight closure cap for tubular posts, one cap for each post. Furnish cap with<br />

openings to permit passage of top rail.<br />

02821 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


F. Stretcher Bars: Galvanized steel, one piece lengths equal to full height of fabric; with minimum cross section of<br />

3/16 x 3/4 inch. Provide one stretcher bar for each gate and end post, and two for each corner and pull post.<br />

G. Stretcher Bar Bands: Manufacturer's standard.<br />

H. Gate Cross-Bracing: 3/8 inch diameter galvanized steel adjustable length truss rods.<br />

I. Gate Hardware:<br />

1. Swinging Gate Hardware:<br />

a. Hinges:<br />

1) Size and material to suit gate size; offset to permit 180 degree gate opening. Provide 1-1/2<br />

pair of hinges for each leaf over 6 feet nominal height.<br />

b. Latch:<br />

1) Exterior: Forked type or plunger-bar type to permit operation from both sides of gate, with<br />

padlock eye.<br />

2) Interior: Forked type to permit operation from both sides of gate, with padlock link. At<br />

Electrical Room and Sprinkler Room, omit padlock link and substitute standard pin bracket<br />

for attachment of forked latch (gates are not to be padlocked).<br />

2. Double Gate Hardware: In addition to the above, provide gate stops for double gates, consisting of<br />

mushroom type flush plate with anchors set in concrete to engage center drop rod or plunger bar.<br />

Configure for use of one padlock to lock both gate leaves.<br />

2.5 SETTING MIXES<br />

A. Concrete: Specified in Section 03310.<br />

B. Grout: Premixed, factory-packaged, non-staining, non-corrosive grout as specified in Section 03310. Provide<br />

type especially formulated for exterior application.<br />

2.6 SUBSTITUTIONS<br />

A. Reference Section 01600.<br />

2.7 GATE FABRICATION<br />

A. Fabricate gate frames of min. 1.90 inch outside diameter galvanized steel pipe. Provide horizontal and vertical<br />

members to ensure proper gate operation and for attachment of fabric, hardware, and accessories. Space frame<br />

members maximum 8 feet apart.<br />

B. Assemble gate frames rigidly by welding or with special fittings and rivets. Use same fabric as specified for fence.<br />

Install fabric with stretcher bars at vertical edges. Bars may also be used at top and bottom edges. Attach<br />

stretchers to frame at not more than 15 inches on center. Install diagonal cross-bracing on gates as required to<br />

ensure frame rigidity without sag or twist.<br />

C. Attach fabric on sliding gates to maintain bottom clearance as specified below in Installation.<br />

D. Attach hardware to provide security against removal or breakage.<br />

2.8 FINISH<br />

A. Fabric and Framing: Zinc coated in accordance with CLFMI Product Manual.<br />

02821 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install chain link fence including fabric, posts, and components in accordance with CLFMI Product Manual unless<br />

otherwise specified herein.<br />

B. Space line posts 10 feet on center maximum, except as otherwise indicated.<br />

1. Space line posts at 8 feet on center maximum if plastic slats are indicated to be installed in fence fabric.<br />

2. Space interior line posts 8 feet on center maximum.<br />

C. Set posts as close to building walls as practical. Gaps greater than 1 inch between wall and posts shall be closed<br />

with a metal closure panel attached full height to post with Tek screws as shown. Smooth edges and corners of<br />

sheet metal to eliminate sharp or rough edges.<br />

D. Methods for Setting Posts:<br />

1. Grade-Set Posts:<br />

a. Drill or hand excavate to depth and diameter indicated on Drawings. Set post bottom at depth<br />

indicated on Drawings.<br />

b. Hold post in position while placing, consolidating, and finishing concrete.<br />

c. Post shall be set plumb within 1/4 inches in 10 feet.<br />

2. Sleeve-Set Posts In Slabs: Anchor posts in concrete by means of pipe sleeves preset into concrete to depth<br />

not less than 24 inches below finish slab, and anchored into concrete. Insert posts into sleeves and fill<br />

annular space between post and sleeve solid with grout. Mix and place grout in accordance with<br />

manufacturer's published instructions.<br />

E. Intermediate Rails: Provide center and bottom rails where indicated. Install in one piece between posts and flush<br />

with post on fabric side, using offset fittings where necessary. Place intermediate rails a maximum of 6 feet on<br />

center.<br />

F. Brace Assemblies: Install braces so posts are plumb with rod in tension.<br />

G. Tension Wire: Install tension wires through post cap loops before stretching fabric and tie to each post cap with<br />

not less than 6 gage galvanized wire. Fasten fabric to tension wire using 11 gage galvanized steel hog rings spaced<br />

24 inches on center.<br />

H. Fabric: Space between bottom of fabric and finish grade shall be not greater than 2 inches. Space between bottom<br />

of fabric and finish grade shall not be greater the 1/2-inch on sliding gates. Pull fabric taut and tie to posts, rails,<br />

and tension wires. Install fabric on security side of fence, and anchor to framework so fabric remains in tension<br />

after pulling force is released.<br />

I. Stretcher Bars: To secure end, corner, pull, and gate posts, thread through or clamp to fabric 4 inches on center<br />

and secure to posts with metal bands spaced 15 inches on center.<br />

J. Tie Wires:<br />

1. Use U-shaped wire conforming to diameter of pipe to which attached, clasping pipe and fabric firmly with<br />

ends twisted two full turns. Bend wire ends to minimize hazards to persons or clothing.<br />

2. Tie fabric to line posts with wire ties spaced 12 inches on center. Tie fabric to rails and braces with wire<br />

ties spaced 24 inches on center. Manufacturer's standard procedure will be accepted if of equal strength<br />

and durability.<br />

K. Fasteners: Install nuts for tension bands and hardware bolts on side of fence opposite fabric side. Peen ends of<br />

bolts or score threads to prevent removal of nuts.<br />

L. Gates: Install gates plumb, level, and secure for full opening without interference. Install ground-set items in<br />

concrete for anchorage. Adjust hardware for smooth operation.<br />

02821 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


M. Install Columns for Garden Center aluminum trusses at shade cloth canopy at locations indicated on the Drawings.<br />

Construct and set columns plumb in concrete footings as indicated.<br />

3.2 ERECTION TOLERANCES<br />

A. Maximum Variation from Plumb: 1/4 inch.<br />

B. Maximum Offset from True Position: 1 inch.<br />

END OF SECTION<br />

02821 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpeI – Civil (Master Site Specifications) 040103<br />

SECTION 02822 (32 3114) - CHAIN LINK FENCES AND GATES (SITE RELATED)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Chain link fences and gates associated with sitework.<br />

B. Related Requirements:<br />

1. Section 02821 – Chain Link Fences and Gates (Building Related): Fences and gates within or adjacent to<br />

buidling.<br />

1.2 REFERENCES<br />

A. American Society for Testing and Materials (ASTM)<br />

1. ASTM A 392 - Zinc-Coated Steel Chain-Link Fence Fabric<br />

2. ASTM C 94 - Ready-Mixed Concrete<br />

B. Chain Link Fence Manufacturers Institute (CLFMI) latest edition Product Manual<br />

1.3 SUBMITTALS<br />

A. Project Record Documents: Accurately record actual locations of property perimeter posts relative to property<br />

lines and easements.<br />

1.4 QUALITY ASSURANCE<br />

A. Chain link fabric, posts, and components, and installation shall conform to the requirements of the CLFMI Product<br />

Manual unless otherwise shown or specified.<br />

B. Manufacturer Qualifications: Company specializing in manufacturing the products specified in this Section with<br />

minimum 3 years documented experience.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Steel Posts: Type I or II or roll formed "C" Section steel conforming to CLFMI and as specified hereinafter.<br />

B. Fabric: No. 9 gage (0.148 nominal) galvanized steel wire in 2 inch mesh; ASTM A 392, top and bottom selvages<br />

twisted and barbed, height as shown. Furnish 1-piece fabric widths.<br />

Deleted:<br />

C. End, Corner, and Pull Posts: Minimum sizes and weights as follows:<br />

1. Up to 13 Foot Fabric Height: Type I or II in accordance with CLFMI Product Manual.<br />

2. 13 foot and over Fabric Height (If required):<br />

a. Type I Posts: Round; 4.0 inch outside diameter pipe, 9.10 lbs/lin ft.<br />

b. Type II Posts: 4.0 inch outside diameter pipe, 6.56 lbs/lin ft.<br />

D. Line (Intermediate) Posts: Minimum sizes and weights as follows:<br />

1. Up to 8 Foot Fabric Height: Type I, II, or "C" Section in accordance with CLFMI Product Manual.<br />

2. Over 8 Foot Fabric Height:<br />

a. Type I Posts:<br />

1) Round: 2.875 inch outside diameter pipe, 5.79 lbs/lin ft.<br />

2) Square: 2.5" x 2.5" outside dimension, 5.10 lbs/lin ft.<br />

02822-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


. Type II Posts: 2.875 inch outside diameter pipe, 4.64 lbs/lin ft.<br />

E. Gate Posts: Type I or II in accordance with CLFMI Product Manual.<br />

F. Top, Bottom, and Intermediate Rails: Type I or II in accordance with CLFMI Product Manual.<br />

1. Manufacturer's longest lengths.<br />

2. Couplings: Expansion type, approximately 6 inches long.<br />

3. Attaching Devices: Means of attaching top rail securely to each gate, corner, pull, and end post.<br />

G. Sleeves: Galvanized steel pipe not less than 6-inches long with inside diameter not less than ½ inch greater than<br />

outside diameter of pipe. Provide steel plate closure welded to bottom of sleeve of width and length not less than<br />

1 inch greater than outside diameter of sleeve.<br />

H. Tension Wire: 7 gage galvanized steel conforming to CLFMI, Marcelled, located at bottom of fabric.<br />

I. Wire Ties: Class 1 galvanized steel, no less than 9 gage.<br />

J. Post Brace Assembly: Manufacturer's standard adjustable brace at end of gate posts and at both sides of corner<br />

and pull posts, with horizontal brace located at mid-height of fabric. Use same material as top rail for brace, and<br />

truss to line posts with 0.375-inch diameter rod and adjustable tightener.<br />

K. Post Tops: Galvanized steel, weather tight closure cap for each tubular post. Furnish caps with openings to permit<br />

passage of top rail.<br />

L. Stretcher Bars: Galvanized steel, 1 piece lengths equal to full height of fabric, with minimum cross-section of<br />

3/16-inch x 3/4-inch. Provide one stretch bar for each gate and end post, and two for each corner and pull post.<br />

M. Stretch Bar Bands: Manufacturer's standard<br />

N. Gate Cross-bracing: 3/8-inch diameter galvanized steel adjustable length truss rods.<br />

O. Ready Mix Concrete: ASTM C94, mix design as follows:<br />

1. Design mix to produce normal weight concrete consisting of Portland cement, aggregate, water-reducing<br />

admixture, air-entraining admixture, and water to produce following:<br />

a. Compressive Strength: 3,500 psi, minimum at 28 days, unless otherwise indicated on Construction<br />

Drawings.<br />

b. Slump Range: 1 to 3 inches at time of placement<br />

c. Air Entrainment: 5 to 8 percent<br />

P. Swinging Gate Hardware:<br />

1. Hinges: Size and material to suit gate size, non-lift-off type, offset to permit full 180-degree gate opening.<br />

Provide a pair of 1 1/2-inch hinges for each leaf over 6'-0" nominal height.<br />

2. Latch: Forked type or plunger-bar type to permit operation from either side of gate, with padlock eye as integral<br />

part of latch.<br />

Q. Double Gates Hardware: Provide gate stops for double gates, consisting of mushroom type of flush plate with anchors<br />

set in concrete, to engage center drop rod or plunger bar. Include locking device and padlock eye as integral<br />

part of latch, using 1 padlock for locking both gate leaves.<br />

R. Sliding Gate Hardware: Provide manufacturer's standard heavy-duty track, ball-bearing hanger sheaves, overhead<br />

framing and supports, guides, stays, bracing, and accessories as required.<br />

2.2 GATE FABRICATION<br />

A. Fabricate swing gate perimeter frames of 1.90-inch OD pipe, galvanized steel. Provide horizontal and vertical<br />

members to ensure proper gate operation and attachment of fabric, hardware, and accessories. Space frame members<br />

maximum of 8'-0" apart.<br />

02822-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


B. Assemble gate frames by welding or special fittings and rivets, for rigid connections. Install same fabric as for<br />

fence with stretcher bars at vertical edges. Install diagonal cross-bracing on gates as required ensuring rigid frame<br />

without sag or twist. Bars may be used at top and bottom edges. Attach stretchers to gate frame at 15 inches o.c.<br />

maximum.<br />

C. Attach hardware to provide security against removal or breakage.<br />

2.3 FINISH<br />

A. Fabric, Framing, and Other Iron Parts: Hot dip zinc coated in accordance with CLFMI Product Manual.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install chain link fence in accordance with CLFMI Product Manual unless otherwise specified herein.<br />

B. Comply with recommended procedures and instructions of fencing manufacturer. Provide secure, aligned installation<br />

with line posts spaced at 10'-0" o.c. maximum.<br />

C. Methods for Setting Posts:<br />

1. Grade-Set Posts:<br />

a. Drill or hand excavate to a depth approximately 3 inches lower than post bottom. Set post bottom<br />

not less than 36 inches below finish grade.<br />

b. Excavate each post hole to 12 inch diameter, or not less than four times diameter of post.<br />

c. Place concrete around posts and vibrate or tamp for consolidation. Check each post for vertical and<br />

top alignment, and hold in position during placement and finishing operations. Extend concrete<br />

footing 2-inches above grade and trowel crown to shed water.<br />

d. Post shall be set plumb within 1/4" in 10 feet.<br />

2. Sleeve Set Posts: Anchor posts by means of pipe sleeves preset and anchored into concrete. After posts<br />

have been inserted into sleeves, fill annular space between post and sleeve solid with nonshrink,<br />

non-metallic grout, mixed and placed to comply with grout manufacturer's directions.<br />

D. Top Rails: Run rail continuously, bending to form radius for curved runs. Provide expansion couplings as recommended<br />

by manufacturer.<br />

E. Center Rails: Provide center rails where indicated. Install in 1 piece between posts and flush with post on fabric<br />

side, using special offset fittings where necessary.<br />

F. Brace Assemblies: Install braces so posts are plumb when diagonal rod are under proper tension.<br />

G. Tension Wire: Install tension wires through post cap loops before stretching fabric and tie to each post cap with<br />

not less than 6 gauge galvanized wire. Fasten fabric to tension wire using 11 gauge galvanized steel hog rings<br />

spaced 24-inches o.c.<br />

H. Fabric: Leave approximately 2 inches between finish grade and bottom selvage. Pull fabric taut and tie to posts,<br />

rails, and tension wires. Install fabric on security side of fence, and anchor to framework so that fabric remains in<br />

tension after pulling force is released.<br />

I. Stretcher Bars: Secure at end, corner, pull, and gate posts by threading through or clamping to fabric at 4 inches<br />

o.c. and secure to posts with metal bands spaced at 15 inches o.c.<br />

J. Tie Wires:<br />

1. Use U-shaped wire, conforming to diameter of pipe to which attached, clasping pipe and fabric firmly<br />

when ends twisted at least 2 full turns. Bend ends of wire to minimize hazard to persons or clothing.<br />

2. Tie fabric to line posts with wire ties spaced 12 inches o.c. Tie fabric to rails and braces with wire ties<br />

spaced 24 inches o.c. Tie fabric to tension wires with hog rings spaced 24-inches o.c.<br />

02822-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


3. Manufacturer's standard procedure will be accepted if of equal strength and durability.<br />

K. Fasteners: Install nuts for tension bands and hardware bolts on side of fence opposite fabric side. Peen ends of<br />

bolts or score threads to prevent removal of nuts.<br />

L. Gates: Install gates plumb, level, and secure for full opening without interference. Install ground-set items in concrete<br />

for anchorage. Adjust hardware for smooth operation and lubrication.<br />

3.2 ADDITIONAL INSTALLATION PROVISIONS<br />

A. Use U-shape tie wires, conforming to the diameters of pipe, that clasp the pipe and fabric firmly with ends twisted<br />

at least 2 full turns.<br />

B. Bend ends of exposed wires to minimize hazards to persons or clothing.<br />

C. Install nuts for fasteners on tension bands and hardware bolts on the side of the fence opposite the fabric. The<br />

ends of bolts, once secure and checked for smooth operation, shall be peened to prevent removal of nuts.<br />

D. Repair coatings damaged in the field with methods and techniques as recommended by the manufacturer.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

02822-4<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec II 012811<br />

SECTION 02823 (32 3119) – ORNAMENTAL METAL FENCES AND GATES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Fence framework and accessories.<br />

2. Gates and related hardware.<br />

3. Screening mesh.<br />

4. Columns for Garden Center aluminum trusses at shade cloth canopy.<br />

5. Shade cloth visual screen.<br />

B. Related Requirements:<br />

1. Division 3 - Concrete for post anchorage.<br />

2. Section 04200 - Unit Masonry Assemblies: Anchorage to Masonry.<br />

3. Section 10675 - Modular Rack and Fence System: Garden Center Modular Rack and Fence System.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Fence Association (AFA):<br />

1. Installation Standards.<br />

C. ASTM International (ASTM):<br />

1. ASTM A123 - Zinc (Hot-Dip Galvanized) Coating on Iron and Steel Products.<br />

2. ASTM A500 - Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes.<br />

3. ASTM A501- Hot-Formed Welded and Seamless Carbon Steel Structural Tubing.<br />

4. ASTM A513 - Electric-Resistance-Welded Carbon and Alloy Steel Mechanical Tubing.<br />

5. ASTM D 523 - Standard Test Method for Specular Gloss.<br />

6. ASTM A 641 - Zinc-Coated (Galvanized) Carbon Steel Wire.<br />

7. ASTM A653 - Steel Sheet, Zinc-Coated (Galvanized) by the Hot-Dip Process.<br />

8. ASTM B 117 - Salt Spray (Fog) Testing.<br />

9. ASTM D 2794 - Standard Test Method for Resistance of Organic Coatings to the Effects of Rapid<br />

Deformation (Impact).<br />

10. ASTM D 3359 - Standard Test Methods for Measuring Adhesion by Tape Test.<br />

11. ASTM D 3363 - Standard Test Method for Film Hardness by Pencil Test.<br />

12. ASTM E 2016 - Industrial Woven Wire Cloth.<br />

1.3 SUBMITTALS<br />

A. Shop Drawings: Show layout, locations, components, materials, dimensions, sizes, weights, finishes of<br />

components, installation, and operational clearances, gate swings, member sizes, member spacing, screening mesh<br />

type, gate details/dimensions, details of post anchorage, and post attachment/bracing.<br />

B. Fence system design and shop drawings shall be sealed by a Registered Professional Engineer, licensed in the<br />

jurisdiction of the project, certifying conformance to design requirements specified herein.<br />

C. Closeout Submittals: Submit the following as part of closeout documents in accordance with the requirements of<br />

Section 01770.<br />

1. Warranty Certificate.<br />

02823 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

1.5 WARRANTY<br />

A. Material: Provide manufacturer’s 25-year finish coating material warranty, including labor for re-finishing, to<br />

cover corrosion, bonding, delaminating, abrasion, weathering and color retention.<br />

B. Workmanship: Provide manufacturer’s 10-year workmanship warranty to cover workmanship, operation, and<br />

installation and for replacement or repair of deficient components and the removal and re-installation thereof.<br />

C. Prepare "Application for Limited Warranty" included at the end of this Section for submission to fence<br />

manufacturer. Follow instructions on form.<br />

D. Obtain Intent-to-Warrant statement from fence manufacturer prior to fabrication.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURER<br />

A. Provide fence by one of the following manufacturers:<br />

1. BetaFence USA, Ennis, TX (888) 650-4766.<br />

2. Ameristar Fencing Products, Tulsa, OK (800) 321-8724.<br />

B. Provide shade cloth visual screen by the following manufacturer:<br />

1. Hendee Enterprises Incorporated, Houston, TX (800) 231-7275. Contact: Crystal Genovese<br />

walmart@hendee.com (713) 796-6119.<br />

C. Substitutions: Not permitted.<br />

2.2 DESIGN REQUIREMENTS<br />

A. Fencing system and installation shall be engineered to withstand 85 mph minimum windload assuming 50 percent<br />

coverage with hanging plastic banners and signage and/or windscreen where required.<br />

2.3 MATERIALS<br />

A. Fencing System: Provide one of the following models:<br />

1. Commercial Rail Fencing, 5522-6 by BetaFence USA.<br />

2. Aegis II, Majestic 3-Rail Style by Ameristar.<br />

B. Fence Pickets, Rails, Posts, and Columns: Formed from coil steel with minimum yield of 50,000 psi; ASTM<br />

A653. Posts over 11 gage wall thickness shall be per ASTM A500, A501 or A513 with galvanization per ASTM<br />

A123.<br />

C. Fabrication:<br />

1. Bottom of pickets shall not extend below bottom rail or above top rail.<br />

2. Space pickets at approximately 5 inches on center.<br />

3. Bottom rail shall be fabricated to allow for maximum space of 2 inches between bottom rail and finish<br />

grade.<br />

4. Intermediate rail shall be located between 3 ft. below top rail and 4 ft. above bottom rail.<br />

02823 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Member Sizes: Provide member sizes and thickness gages as required to meet windload as specified above.<br />

Contact manufacturer to obtain actual required calculated member sizes for each specific project. Minimum<br />

member sizes shall be as follows:<br />

1. Pickets: Minimum 1 inch x 1 inch x 16 gage.<br />

2. Rails: Minimum 1-3/4 inches x 1-3/4 inches x 14 gage.<br />

3. Posts: Minimum 3 inches x 3 inches x 12 gage or as required by manufacturer.<br />

4. Columns: Minimum 4 inches x 4 inches x .121 inch thick wall or as required by manufacturer.<br />

5. Columns for Garden Center: Minimum 4 inches x 4 inches x .121 inch thick wall, designed to support<br />

gravity and wind loads acting on aluminum truss / shade cloth system, as specified in Section 13121 and<br />

provided by Wal-Mart’s Aluminum Truss Supplier.<br />

E. Option: Picket, rail, post, and column sizes may vary depending on standard and stock members utilized by the<br />

manufacturer. Alternate sizes of members shall provide equivalent structural characteristics in each member and<br />

the equivalent Moment of Inertia, I, about the principal axis of the component member as that of the minimum<br />

specified or calculated sizes.<br />

F. Fasteners: Self-drilling steel hex head, zinc-plated and polymer coated to match fencing system and having a pullout<br />

value from 500 to 700 pounds.<br />

G. Post and Column Caps: Square caps firmly affixed on extending end.<br />

H. Steel Overhead Sliding Gate:<br />

1. Prefabricated steel gate panels.<br />

2. Aluminum track extruded top rail with two truck assemblies.<br />

3. Guide roller assembly at bottom rail.<br />

4. Two lockable cantilever gate latches. One at 18” above grade and one at 46” above grade, inside face.<br />

I. Cantilever Sliding Gate (If shown on Drawings): Manufacturer's standard cantilever sliding gates including the<br />

following:<br />

1. Track/rail and guide assembly.<br />

2. Gate hangers, latches, brackets, bracing, and stops.<br />

3. Suspension and guide roller assemblies.<br />

J. Steel Swing Gate:<br />

1. Prefabricated steel fence panels with all hardware and steel plate pre- installed by manufacturer.<br />

2. Steel plate, size as indicated on Drawings, welded to gate panel frame for mounting of exit device<br />

hardware.<br />

3. Two 6” min. heavy dutybutt or ball bearing barrel hinges.<br />

K. Door Surround Mesh: PVC-coated 1-inch mini mesh chain link fabric as specified in Section 02821.<br />

L. Screening Mesh:<br />

1. Provide screening mesh by one of the following:<br />

a. Guardian Security Fence System security mesh and attachment hardware by BetaFence USA.<br />

b. Matrix SPEC System security mesh and attachment hardware by Ameristar.<br />

c. Screening mesh and attachment hardware products by other manufacturers which are an approved<br />

equivalent to the Guardian or Matrix system specified above and which conform to requirements<br />

specified herein may be provided.<br />

2. Provide attachment hardware as required for attachment to the posts, rails, and gates of the ornamental<br />

fence members.<br />

3. Provide the following mesh type:<br />

a. 1” x 1” x 0.162 woven wire flattened mesh by BetaFence USA, height as shown.<br />

4. Apply polyester powder coated factory finish coating to screening mesh and components.<br />

M. Gate Bottom Sweep: Type C607DkB by National Guard Products or equivalent, anodized aluminum, dark bronze<br />

finish nylon brush sweep. Supply with #6 x 3/4” stainless steel sheet metal screws.<br />

02823 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 FABRICATION<br />

A. Shop fabricate fence components in accordance with manufacturer’s standard details for the model specified.<br />

2.5 POWDER COATED FACTORY FINISH<br />

A. Coating Material: Posts, Post Caps, Rails and screening mesh shall be a factory electrostatically applied TGIC<br />

polyester powder coating of the “Super Durable TGIC” class. Powder coated finish shall meet or exceed the<br />

following:<br />

1. ASTM B 117: 5% salt spray at 95° F and 95% relative humidity, 2,000 hour test without loss of adhesion.<br />

2. ASTM D 3359: Method B, coating retention of not less than 95%.<br />

3. ASTM D 2794: Minimum resistance to impact not less than 120 in. /lb.<br />

4. South Florida Weatherability testing, no film failure and 65% gloss retention as measured by ASTM D 523<br />

after 60 months of 45 degree South Florida Exposure Testing.<br />

5. ASTM D 3363: Minimum hardness 2H.<br />

B. Thickness: Minimum film thickness of 2-3 mils as measured by manufacturer’s standard powder coat<br />

measurement and inspection procedures.<br />

C. Pretreatment: The fence framework shall be prepared using a pre-treatment cleaning system to remove foreign<br />

material and to properly prepare the surface to achieve the coating system requirements specified above.<br />

D. Zinc Coating: Wire fabric shall be zinc coated with a “regular coating” classification in accordance with ASTM<br />

A641 prior to powder coating.<br />

E. Curing: Heat cure in accordance with powder manufacturer’s prescribed cure schedule to bond finish to metal<br />

substrate.<br />

F. Color: Black.<br />

G. Visual Screening Fabric: Vinyl impregnated woven polyester yarn, heat set for stability.<br />

1. Color: Black.<br />

2. Shade Factor: 80%.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION - FENCING SYSTEM<br />

A. Install framework, fencing, gates and accessories in accordance with manufacturer's published instructions and<br />

installation drawings. Install fencing to withstand windload specified.<br />

B. Set system plumb, in footings with top of footing and fence height as shown on Drawings. Slope top of concrete<br />

for water runoff.<br />

C. Brace each gate and corner post to adjacent line post with horizontal center brace rail or diagonal truss rods as<br />

recommended by manufacturer.<br />

D. Attach rail ends into posts and pickets into rails using pre-punched holes or brackets and fasten in accordance with<br />

manufacturer’s standard methods.<br />

E. Install swinging gate by attaching hinges of gate assembly to gate post and exit device strike to opposite gate post<br />

to align with exit device latch bolt.<br />

F. Set posts as close to building walls as practical. Gaps greater than 1 inch between wall and posts shall be closed<br />

with a metal closure panel attached full height to post with Tek screws as shown. Smooth edges and corners of<br />

sheet metal to eliminate sharp or rough edges.<br />

02823 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


G. Install ornamental metal fencing and accessories in accordance with installation instructions and in accordance<br />

with American Fence Association (AFA) standards.<br />

H. Install screening mesh and components in accordance with manufacturer’s instructions. Attach mesh to<br />

ornamental fence members with hardware furnished by screening mesh supplier.<br />

I. Install Columns for Garden Center aluminum trusses at shade cloth canopy at locations indicated on the Drawings.<br />

Construct and set columns plumb in concrete footings as indicated.<br />

J. Install visual screen to the inside face of the fence system in accordance with manufacturer’s published<br />

instructions, in locations shown on Drawings.<br />

3.2 INTERFACE WITH OTHER WORK<br />

A. Coordinate installation of light fixtures to aluminum trusses at locations indicated on Drawings.<br />

3.3 FIELD QUALITY CONTROL<br />

A. Inspect fencing system installation and attachment to building structure.<br />

B. Inspect gate operation and hardware installation.<br />

C. Inspect aluminum truss, shade cloth installation and attachments.<br />

END OF SECTION<br />

02823 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Application for Limited Warranty<br />

(Ornamental Fence)<br />

(To be completed by General Contractor)<br />

Wal-Mart Store____Supercenter____Store #________Prototype __________<br />

Store Address:<br />

City___________________________State____________________ Zip___________________________________________<br />

Installer Contractor___________________________________________________________________________<br />

Installer Contractor’s Address__________________________________________________________________<br />

City____________________________State___________________________________Zip___________________________<br />

Phone No.________________________Fax No.<br />

____________<br />

General Contractor___________________________________________________________________________<br />

General Contractor Contact___________________________________________Job Site Phone _______________________<br />

Installer acknowledges completion of work related to the installation of the fence system, including gates and hardware, in<br />

accordance with manufacturer’s instructions.<br />

Date job completed:___________________________Installer’s Signature:<br />

This Application for Limited Warranty will not be accepted unless complete information is provided. Any deceptive<br />

information contained in this application for Limited Warranty is grounds for voiding the Limited Warranty.<br />

Upon completion of this application form, submit to fence manufacturer for processing. When approved, the manufacturer<br />

will submit a 25 yr. material and 10 yr. workmanship Limited Warranty Certificate to be included in the closeout documents<br />

specified in Specifications Section 01770.<br />

02823 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 02845 (10 8500) – CART CORRAL<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Wal-Mart furnished parking lot cart storage corrals for installation by Contractor.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Wal-Mart furnished products.<br />

2. Section 02765 - Pavement Marking: Painted pavement markings surrounding corral.<br />

1.2 DELIVERY, STORAGE AND HANDLING<br />

A. Receive Owner Furnished products in compliance with the requirements of Section 01640.<br />

B. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's Cart Corral Supplier will furnish cart corrals for installation by<br />

Contractor. Descriptions and specifications of Owner furnished products are included as information to Contractor<br />

only and are not to be considered as Contractor requirements unless otherwise stated.<br />

B. Owner’s Cart Corral Supplier: One of the following as determined by Wal-Mart:<br />

1. National Cart Co. St. Charles, MO (800) 455-3802.<br />

2. Win-Holt Equipment Group, Syosset, NY (800) 444-3595.<br />

C. Contractor shall notify Wal-Mart Procurement to provide required quantities of Owner Furnished Products as<br />

shown on Drawings.<br />

2.2 CART CORRAL (Wal-Mart Furnished, Contractor Installed)<br />

A. Description: Steel post and rail cart storage corral of welded galvanized pipe components.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION BY CONTRACTOR<br />

A. Assemble and install corral as indicated and at locations shown on Drawings and as shown on manufacturer’s<br />

assembly drawings.<br />

3.2 ADJUSTING AND CLEANING BY CONTRACTOR<br />

A. After completing installation, inspect exposed finishes and repair damaged finishes.<br />

END OF SECTION<br />

02845 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 02870 – SITE FURNISHINGS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Metal lighted bollard.<br />

2. Metal bench.<br />

3. Metal waste container.<br />

4. Metal bicycle parking rack.<br />

5. Metal tree grate.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Wal-Mart will furnish the following products for installation by Contractor as<br />

described within this Section.<br />

1. Metal bench.<br />

2. Metal waste container.<br />

3. Metal bicycle parking rack.<br />

B. Descriptions and related provisions of products by Wal-Mart’s supplier as specified herein are included as<br />

requirements by the supplier of equipment to be furnished by Wal-Mart and are included as information only to<br />

the Contractor.<br />

2.2 METAL LIGHTED BOLLARD<br />

A. Manufacturer: Gardco Lighting, San Marcos, TX (800) 227-0758.<br />

1. Supplier: Haines, Jones & Cadbury, Inc. Contact: Customer Service, (800) 459-7099, Fax (479) 756-<br />

8998, Email info@hjcinc.com<br />

B. Model: BRM832 LED Dome Top School Bollard by Gardco.<br />

C. Description: Aluminum cylindrical bollard with LED lighting and louverd lens.<br />

1. Upper Housing: Diecast aluminum dome top secured to a one-piece diecast zinc louver assembly.<br />

2. Lower Housing: .125 inch wall 6063-T5 extruded aluminum.<br />

3. Dimensions: 8 inch diameter by 42 inches high.<br />

4. Lens & Optical System: Constant wattage full light output, 41 total watts, Cree nuetral white luminare,<br />

with 360 degree light coverage.<br />

5. Anchorage: Galvanized steel mounting tenon, secured and double-nut leveled to concrete footing with<br />

anchor bolts supplied by manufacturer.<br />

6. Finish: Electrostatically applied, thermally cured textured polyester powdercoat finish. Color: RAL5015.<br />

7. Electrical: 120 Volts through 240 Volts.<br />

2.3 METAL BENCH (WAL-MART FURNISHED/CONTRACTOR INSTALLED)<br />

A. Manufacturer: Wausau Tile Site Furnishings, Wausau, WI (800) 388-8728.<br />

B. Description: Model MF 2209 Backless Bench by Wausau.<br />

1. Size: 60 x 26 x 24 inch.<br />

2. Construction: Hot rolled steel backless dual side configuration.<br />

3. Finish: Polyethylene copolymer coating. Color: Black.<br />

4. Anchors: Zink plated anchor kit, MF7200 by manufacturer.<br />

02870 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 METAL WASTE CONTAINER (WAL-MART FURNISHED/CONTRACTOR INSTALLED)<br />

A. Manufacturer: Wausau Tile Site Furnishings, Wausau, WI (800) 388-8728.<br />

B. Description: Model MF 3228 Waste Container by Wausau.<br />

1. Size: 26 inch diameter x 51 inches, 41 gallon capacity.<br />

2. Construction: Hot rolled steel body with cast aluminum funnel top w/ rain cover and security cable.<br />

3. Liner: Polyethylene reusable liner.<br />

4. Finish: Polyethylene copolymer coating. Color: Black.<br />

5. Anchors: Zink plated anchor kit, MF7200 by manufacturer.<br />

2.5 METAL BICYCLE PARKING RACKS (WAL-MART FURNISHED/CONTRACTOR INSTALLED)<br />

A. Manufacturer: Wausau Tile Site Furnishings, Wausau, WI (800) 388-8728.<br />

B. Description: Model MF9009-BLACK Wave Bike Rack Surface Mount.<br />

1. Size: 78 1/2 inches wide x 36 inches high, 7 bike capacity.<br />

2. Construction: 2 inch O.D. x 11 gage hot-dipped galvanized wall tube.<br />

3. Color: Black.<br />

4. Anchors: Six concrete anchors by manufacturer.<br />

2.6 METAL TREE GRATE<br />

A. Manufacturers:<br />

1. Neenah Foundry Company, Neenah, WI (414) 725-7000.<br />

2. Alhambra Foundry Company, Alhambra, CA (818) 289-4294.<br />

B. Tree Grate: Cast iron 48 inches square, cast in 2 half sections, radial pattern, with cast iron angle frame. Color:<br />

Black.<br />

1. No. R-8742 by Neenah.<br />

2. No. A-2326 by Alhambra.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that conditions conform to<br />

product manufacturer's requirements for installation. Do not proceed until unsatisfactory conditions have been<br />

corrected.<br />

B. Beginning of installation indicates acceptance of existing conditions.<br />

3.2 INSTALLATION<br />

A. Install items at locations as indicated on Drawings in accordance with manufacturer's published instructions.<br />

END OF SECTION<br />

02870 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec – Civil (Master Site Specifications) 021511<br />

SECTION 02890 (34 4113) - TRAFFIC SIGNS AND SIGNALS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Traffic control signs.<br />

B. Related Requirements:<br />

1. Section 09900 - Painting. Painting for painted posts where shown on the Drawings.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A53 - Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless.<br />

2. ASTM C94 - Ready Mix Concrete<br />

3. ASTM D4956 - Retroreflective Sheeting for Traffic Control.<br />

C. US Department of Transportation, Federal Highway Administration:<br />

1. Manual on Uniform Traffic Control Devices (MUTCD).<br />

PART 2 - PRODUCTS<br />

2.1 SIGNS<br />

A. Conform to US Department of Transportation MUTCD. Sign classification, type, size, and color shall be as shown<br />

on the drawings<br />

B. Retroreflectivity: Microprismatic type sheeting conforming to ASTM D 4956, Type VIII, IX, or XI.<br />

2.2 POSTS<br />

A. Square Post: Square tubular steel sign post, galvanized, 12 ga, perforated full-length with 7/16 inch holes on four<br />

sides. Post size shall be as shown on the Drawings.<br />

B. Steel Pipe: ASTM A 53, Type E (electric-resistance welded) or Type S (seamless), Grade B, Schedule 40, size as<br />

shown on the Drawings.<br />

2.3 CONCRETE<br />

A. Mix concrete and deliver in accordance with ASTM C 94.<br />

B. Design mix to produce normal weight concrete consisting of Portland cement, aggregate, water-reducing admixture,<br />

air-entraining admixture, and water to produce following:<br />

1. Compressive Strength: 3,500 psi, minimum at 28 days, unless otherwise indicated on the Drawings.<br />

2. Slump Range: 1 to 3-inches at time of placement<br />

3. Air Entrainment: 5 to 8 percent<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

02890-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


A. Field verify underground utilities prior to sign installation. Primary utilities of concern of shallow depths are lawn<br />

sprinkler systems, electric, telephone, fiber optic, cable and gas.<br />

3.2 INSTALLATION<br />

A. Install signs as shown on the Drawings and in accordance with MUTCD and manufacturer's instructions.<br />

B. Install signs of the type and at locations shown on the Drawings.<br />

C. Install posts of the type as shown on the drawing.<br />

D. Where shown as painted, field paint steel pipe posts in accordance with Section 09900.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

02890-2<br />

Deleted: Revision Date:<br />

La Habra, CA – 5641-01 10/15/11


UniSpec II – Civil (Master Site Specifications) 100710<br />

SECTION 02900 (32 9300) – PLANTING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Planting of drought tolerant trees, shrubs, sod, seed, groundcover, and associated materials.<br />

B. Related Requirements:<br />

1. Section 02300 - Earthwork.<br />

2. Section 02370 - Erosion and Sedimentation Control.<br />

3. Section 02812 - Site Irrigation System.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI Z60.1 - American Standard for Nursery Stock.<br />

C. ASTM International (ASTM):<br />

1. ASTM D5268 - Topsoil used for Landscaping Purposes.<br />

2. ASTM C602 - Agricultural Liming Materials.<br />

D. Erosion Control Technology Council (ECTC):<br />

1. Standard Specification for Rolled Erosion Control Products.<br />

1.3 SUBMITTALS<br />

A. Submittal Process: Submit in accordance with Section 01330 - Submittal Procedures.<br />

B. Submittals shall be available at all times to the Wal-Mart Construction Manager.<br />

C. Grower / Nursery Information: Submit name, address, phone number and contact person for each Grower / Nursery<br />

30 days prior to plant material selection meeting.<br />

D. Materials Test Reports: Submit topsoil borrow area test reports to Owner’s Civil Engineering Consultant (CEC)<br />

minimum 6 weeks prior to delivery to site.<br />

1. Provide location of topsoil borrow area.<br />

2. Provide name of independent soil testing laboratory.<br />

3. Provide date of sampling and testing.<br />

E. Product Data:<br />

1. Submit certification tags from trees, shrubs, sod, and seed verifying type and purity to Owner’s CEC.<br />

2. Submit photographs of each species of tree specified. Photographs shall be taken at grower’s nursery prior<br />

to digging. Photographs shall contain tree with measuring rod in vertical position 30 days prior to plant<br />

material selection meeting.<br />

F. Sample: Submit minimum one cubic foot representative sample of wood or mineral mulch to Owner’s CEC.<br />

G. Quality Assurance Submittals:<br />

02900-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


1. Submit to Owner and Owner’s CEC a copy of the invoice for each shipment of plant materials to the Project<br />

site. Invoice shall include name and size of each type of plant material.<br />

2. Tree Transplanting Contractor Qualifications:<br />

a. Provide statement of required qualifications of tree transplanting contractor.<br />

b. Provide Owner project names, addresses, project owner’s names and phone numbers for completed<br />

projects of similar scope.<br />

c. Provide progress photographs of the tree transplanting process and final photographs taken at least 2<br />

years after establishment.<br />

d. Provide evidence of the health of at least 10 trees transplanted 3 or more years ago on at least 3 different<br />

projects. Trees shall be of similar size, species, and conditions of the trees indicated on the<br />

Plans.<br />

H. Closeout Submittals:<br />

1. Submit Meetings and Inspections Log prior to Final Completion of the Project.<br />

2. Certification of Conformance: Provide certificate of satisfactory performance of planting operations signed<br />

by the Contractor and Landscape Architect for attachment to CEC Conformance Letter included at the end<br />

of Section 01456.<br />

1.4 QUALITY ASSURANCE<br />

A. Pre-Work Meeting: Convene a pre-work meeting minimum 30 days prior to commencing work on this Section.<br />

Review conditions of operations, procedures and coordination with related work. The pre-work meeting may be<br />

combined with the plant material selection trip.<br />

1. Review planting schedule and maintenance.<br />

2. Review required inspections, schedule of topsoil testing, and environmental procedures.<br />

B. A Construction Testing Laboratory (CTL) selected and paid for by the Owner, will be retained to perform testing<br />

and analysis on in-place topsoil.<br />

1. The CTL shall prepare test reports that indicate test location and test results. Civil Engineering Consultant,<br />

and Contractor shall be provided with copies of reports as follows:<br />

a. Topsoil Analysis – within 10 calendar days of sampling date.<br />

b. Topsoil Depth Inspection – within 3 working days of test completion.<br />

2. In event that test performed fails to meet Specifications, the (CTL) shall notify Owner and Contractor immediately<br />

and record the deviations on the Observation Log.<br />

3. Contractor shall provide free access to site for testing activities.<br />

C. Tree Transplanting Contractor Qualifications: Tree transplanting contractor shall meet the following qualifications:<br />

1. Certified Arborist on staff.<br />

2. Local representation and offices in the state or an adjoining state where the work is to be performed.<br />

3. Minimum five years of experience transplanting and establishing trees of the same size, species, and quantity<br />

as shown on the plans.<br />

D. Plant Material Selection:<br />

1. Trees: Trees will be tagged by the landscape architect at the tree grower nursery prior to purchase and delivery<br />

to site.<br />

2. Shrubs: Deliver representative samples of each shrub variety and size to the Project site for verification of<br />

specification compliance. Mark shrubs with size, genus, species, cultivar, and variety.<br />

3. Schedule and arrange meeting of landscape contractor and landscape architect for observation of plant material<br />

at the tree grower nursery. Tagging and observation will be based on compliance with requirements<br />

for genus, species, variety, cultivar, size, and quality.<br />

4. Owner and landscape architect may observe trees and shrubs further for size and condition of balls and root<br />

systems, pests, disease symptoms, injuries, and latent defects.<br />

5. Remove rejected trees or shrubs immediately from Project site.<br />

02900-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


E. Plant Measurements: Measure according to ANSI Z60.1. Spread, height, or container sizes shown on the drawings<br />

are minimum acceptable sizes. Do not prune to obtain required sizes. If range of sizes is given, no plant shall<br />

be less than minimum size, and at least 50 percent of plants shall be as large as upper half of range specified.<br />

1. Trees and Shrubs: Measure with branches and trunks or canes in their normal position. Take height measurements<br />

from or near the top of the root flare for field-grown stock and container grown stock. Measure<br />

main body of tree or shrub for height and spread. Do not measure branches or roots tip to tip. Take caliper<br />

measurements 6 inches above the root flare for trees up to 4-inch caliper size, and 12 inches above the root<br />

flare for larger sizes.<br />

2. Other Plants: Measure with stems, petioles, and foliage in their normal position.<br />

F. Soil-Testing Laboratory Qualifications:<br />

1. Multiresidue Herbicide/Pesticide Screen: A NELAC (National Environmental Laboratory Accreditation<br />

Conference) certified independent soil testing laboratory with the experience and capability to conduct the<br />

testing indicated based on local conditions.<br />

2. Topsoil Analysis: Independent soil testing laboratory employing a landscape or soil agronomist familiar<br />

with the final use of the material and construction practices for large earthwork sites.<br />

G. Quality Assurance Inspections: Conduct the following inspections during the course of the work in the presence of<br />

the Landscape Architect to verify conformance to specification requirements. Notify CEC for observation of inspection<br />

by the Landscape Architect. Correct noted deficiencies during each inspection prior to proceeding with<br />

subsequent work.<br />

1. Island Inspection: Inspect parking islands for excavation depth and soil conditions prior to installation of<br />

planting or irrigation. Obtain sample of planting soil mix.<br />

2. Substantial Completion Inspection: Convene a substantial completion inspection to observe completed<br />

work. Landscape Architect will record the deficient or incomplete items on the deviation log within 3 calendar<br />

days of inspection date.<br />

3. Final Inspection: Within 30 days of substantial completion date, convene a final inspection to observe that<br />

all work is completed as specified and shown on the drawings.<br />

4. Warranty Inspections: Convene a warranty inspection 60 calendars days prior to expiration of warranty period<br />

specified in Part 3 herein.<br />

H. Meeting and Inspection Log: Maintain log of required meetings and inspections. Record the date; time; weather<br />

conditions; and a brief summary of the discussions, decisions, agreements (or disagreements) reached. Provide log<br />

to CEC for signature and review by Landscape Architect at the conclusion of each meeting. Furnish copy of log to<br />

each party attending.<br />

1.5 MEETING AND EVENT NOTIFICATIONS<br />

A. Provide the following notifications to the Owner’s Civil Engineering Consultant (CEC) within the time period<br />

listed below. CEC will notify Owner, landscape architect, and other necessary sub consultants:<br />

1. Pre-Work Meeting: Minimum 14 calendar days prior to meeting date.<br />

2. Plant Material Selection Meeting at Grower: Minimum 14 calendar days prior to meeting date.<br />

3. Planting Operations: 14 calendar days prior to commencing planting operations.<br />

4. Island Inspection: 7 calendar days prior to inspection date.<br />

5. Tree Transplanting: Minimum 7 calendar days in advance for transplanting of trees 8 inches in caliper or<br />

greater.<br />

6. Substantial Completion Inspection: 7 calendar days prior to substantial completion date.<br />

7. Final Inspection: 7 calendar days prior to Grand Opening.<br />

8. Warranty Inspection: 14 calendar days prior to inspection date.<br />

B. Provide notifications by email or other written means to show proof of delivery.<br />

1.6 PROJECT CONDITIONS<br />

A. Perform work only during weather conditions favorable to landscape construction and to health and welfare of<br />

plants. Owner shall determine suitability of such weather conditions.<br />

02900-3<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


1.7 WARRANTY<br />

A. Guarantee plant material for a period of 12-19 months following the Substantial Completion Date in accordance<br />

with the Extended Maintenance/Warranty Chart included in Part 3 hereinafter.<br />

1. A limit of one replacement of each plant shall be required, except for losses or replacements due to failure<br />

to comply with requirements.<br />

2. Remove from site any plant that is dead or unsatisfactory to Owner, Jurisdiction having Authority, or Landscape<br />

Architect. Replace plants during normal planting season.<br />

1.8 EXTENDED MAINTENANCE SERVICE<br />

A. Provide extended landscape maintenance beyond Substantial Completion as specified in Part 3 Paragraph “Extended<br />

Maintenance” for a period as stated in the Extended Maintenance/Warranty Chart included therein. Pursuant<br />

to Paragraph 20.5 of the General Conditions, and the associated Performance Bond (Exhibit A) therein, the extended<br />

maintenance specified in this section shall be considered within the maintenance obligation of the bond.<br />

PART 2 - PRODUCT<br />

2.1 WOODY PLANT MATERIALS<br />

A. Furnish nursery-grown trees and shrubs complying with ANSI Z60.1 and the following requirements:<br />

1. Provide plants with healthy root systems developed by transplanting or root pruning.<br />

2. Provide well-shaped, fully branched, healthy, vigorous stock free of disease, insects, eggs, larvae, and defects<br />

such as disfiguring knots, sun scald, injuries, abrasions, and disfigurement.<br />

3. Provide selected specimen quality plants being exceptionally heavy, symmetrical, tight knit, so trained or<br />

favored in their development and appearance as to be superior in form, number of branches, compactness<br />

and symmetry.<br />

4. Do not prune plants before delivery.<br />

5. Trees with fresh cuts of limbs over 1 1/4-inch, which have not completely calloused, shall be rejected.<br />

6. Provide plants typical of their species or variety and exhibiting a normal habit of growth and be legibly<br />

tagged with proper name. Provide plants grown under climatic conditions similar to those of site or have<br />

been acclimated to such condition for at least 2 years.<br />

7. Root system of each plant shall be well-provided with fibrous roots. Parts shall be sound, healthy, vigorous,<br />

well-branched, and densely foliated when in leaf.<br />

8. Plants designated ball and burlap shall be moved with root systems as solid units with balls of earth firmly<br />

wrapped with burlap and comply with the following:<br />

a. Diameter and depth of balls of earth shall be sufficient to encompass fibrous root feeding systems<br />

necessary for healthy development of plant.<br />

b. No plant shall be accepted when ball of earth surrounding its roots has been cracked or broken preparatory<br />

to or during process of planting. Balls shall remain intact during all operations.<br />

c. Heel-in plants that cannot be planted immediately by setting in ground and covering balls with soil<br />

or mulch and then watering.<br />

d. Hemp burlap and twine is preferable to treated. If treated burlap is used, twine shall be cut from<br />

around trunk and burlap shall be removed.<br />

9. Provide single trunk trees growing from single unmutilated crown of roots. No part of trunk shall be conspicuously<br />

crooked as compared with normal trees of same variety.<br />

10. Provide shrubs with thickness corresponding to trade classification "No.1". Single-stemmed or thin plants<br />

shall not be accepted. Side branches shall be generous, well-twigged, and plant as whole well-branched to<br />

ground. Plants shall be in moist condition, free from dead wood, bruises, or other root or branch injuries.<br />

2.2 LAWN SEED<br />

A. Provide fresh, clean, new crop lawn seed mixture. Furnish to Owner dealers guaranteed statement of composition<br />

of mixture and percentage of purity and germination of each variety.<br />

02900-4<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


B. Seed Mixture: Provide seed of grass species and varieties, proportions by weight and minimum percentages of purity,<br />

germination, and maximum percentage of weed seed. Seed mixtures vary by region and season and shall<br />

comply with State DOT and Local Soil Conservation Service Standards for lawn turf.<br />

2.3 SOD<br />

A. Provide sod species suitable as lawn turf for the region. Sod shall be strongly rooted, weed, disease, pest free and<br />

uniform in thickness.<br />

2.4 GROUNDCOVER<br />

A. Provide groundcover established and well rooted in pots or similar containers and comply with ANSI Z60.1.<br />

Slopes steeper than a 3:1 shall receive groundcovers as shown on the drawings.<br />

2.5 TOPSOIL<br />

A. ASTM D5268, natural, friable, fertile, fine loamy soil possessing characteristics of representative topsoil in the vicinity<br />

that produces heavy growth. Topsoil shall have a pH range of 5.5 to 7.4 percent, free from subsoil, objectionable<br />

weeds, litter, sods, stiff clay, stones larger than 1-inch in diameter, stumps, roots, trash, herbicides, toxic<br />

substances, or any other material which may be harmful to plant growth or hinder planting operations. Top soil<br />

shall contain a minimum of three percent organic material.<br />

Deleted: [Editor Note: Groundcover<br />

may be plant varieties listed or may be<br />

equivalent groundcover as selected by the<br />

landscape architect and shown on the<br />

drawing planting plan. Edit listing to<br />

select only the applicable region.<br />

DELETE THESE EDITOR NOTES<br />

PRIOR TO ISSUE.]<br />

Deleted: one or more of the specific<br />

regional<br />

Deleted: listed below or<br />

Deleted: NORTHEAST<br />

Coronilla varia<br />

... [1]<br />

Formatted: Bullets and Numbering<br />

B. Topsoil shall be tested in accordance with part 3 below.<br />

C. Salvaged or Existing Topsoil: Reuse suitable topsoil stockpiled on-site or existing topsoil undisturbed by grading<br />

or excavation operations. Clean topsoil of roots, plants, sod, stones, clay lumps, and other extraneous materials<br />

harmful to plant growth.<br />

D. Verify amount of suitable topsoil stockpiled if any, and supply additional imported topsoil as needed.<br />

E. Imported Topsoil: Supplement salvaged topsoil with imported topsoil from off-site sources when existing quantities<br />

are insufficient.<br />

1. Obtain topsoil displaced from naturally well-drained sites where topsoil occurs at least 6 inches deep; do<br />

not obtain from agricultural land, bogs, or marshes.<br />

2. Verify borrow and disposal sites are permitted as required by state and local regulations. Obtain written<br />

confirmation that permits are current and active.<br />

3. Obtain permits required by state and local regulations for transporting topsoil. Permits shall be current and<br />

active.<br />

F. Amend existing and imported topsoil as indicated in part 3 below.<br />

2.6 ORGANIC SOIL AMENDMENTS<br />

A. Manure: Well-rotted, unleached, stable or cattle manure containing not more than 25 percent by volume of straw,<br />

sawdust, or other bedding materials; free of toxic substances, stones, sticks, soil, weed seed, and material harmful<br />

to plant growth.<br />

B. Back to Nature Cotton Burr Compost or approved equivalent.<br />

02900-5<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


C. Compost: Decomposed organic material including leaf litter, manure, sawdust, plant trimmings and/or hay, mixed<br />

with soil.<br />

D. Pecan Hulls: Composted pecan hulls for local source.<br />

E. Biosolids: Use Grade 1 containing lower pathogen levels.<br />

F. Worm Castings: Earthworms.<br />

2.7 INORGANIC SOIL AMENDMENTS<br />

A. Lime: ASTM C602, Class O agricultural limestone containing a minimum of 80 percent calcium carbonate equivalent<br />

with a minimum of 95 percent passing No. 8 sieve and minimum of 55 percent passing No. 60 sieve.<br />

B. Sulfur: Granular, biodegradable, containing a minimum of 90 percent sulfur, with a minimum of 99 percent passing<br />

No. 6 sieve and a maximum of 10 percent passing No. 40 sieve.<br />

C. Iron Sulfate: Granulated ferrous sulfate containing a minimum of 20 percent iron and 10 percent sulfur.<br />

D. Agricultural Gypsum: Finely ground, containing a minimum of 90 percent calcium sulfate.<br />

E. Sand: Clean, washed, natural or manufactured, free of toxic materials.<br />

2.8 PLANTING ACCESSORIES<br />

A. Non Selective Herbicide: Roundup-Pro, Finale or equivalent.<br />

B. Selective Post Emergent Herbicide: EPA registered and approved, of type recommended by manufacturer for application.<br />

C. Selective Pre-Emergent Herbicide: EPA registered and approved, of type recommended by manufacturer for application.<br />

2.9 PLANTING SOIL MIX<br />

A. Planting medium containing 75 percent specified topsoil mixed with 15 percent organic soil amendments and 10<br />

percent sharp washed sand.<br />

2.10 FERTILIZER<br />

A. Commercial Fertilizer: Commercial-grade complete fertilizer of neutral character, consisting of fast- and slowrelease<br />

nitrogen, 50 percent derived from natural organic sources of urea formaldehyde, phosphorous, and potassium.<br />

1. Composition: Nitrogen, phosphorous, and potassium in amount required to remedy deficiencies identified<br />

in the results of the existing topsoil and in-place topsoil test performed by the geotechnical engineering<br />

company and the CTL.<br />

B. Slow-Release Fertilizer: Use one of the following:<br />

1. Osmocote Standard Granular fertilizer by Scotts Company composed of 13 percent nitrogen, 13 percent<br />

phosphorous, and 13 percent potassium, by weight.<br />

2. Multi-Cote All Purpose by Schultz composed of 17 percent nitrogen, 17 percent phosphorous, and 17 percent<br />

potassium, by weight.<br />

C. Deliver fertilizer, mixed as specified, in original unopened standard size bags showing weight, analysis and name<br />

of manufacturer. Containers shall bear manufacturer's guaranteed statement of analysis, or manufacturer's certifi-<br />

02900-6<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


2.11 MULCH<br />

cate of compliance covering analysis shall be furnished to Owner. Store fertilizer in such manner that it shall be<br />

kept dry.<br />

A. Straw Mulch: Straw mulch shall used for seeding purposes only and shall be air-dry, clean, mildew and seed free,<br />

salt hay or threshed straw of wheat, rye, oats, or barley.<br />

B. Wood Mulch: Wood mulch shall be shredded hardwood or softwood mulch obtained from a local source harvested<br />

in a sustainable manner and salt free and free from deleterious materials and suitable as a top dressing of<br />

trees and shrubs. Mulch shall have the characteristics of retaining moisture, forming a mat not susceptible to<br />

spreading by wind or rain, and providing a suitable growth medium for plants and shall be free of soil, rocks,<br />

weeds, sawdust, dirt, garbage, or other debris.<br />

1. Hardwood Mulch: Shredded hardwood mulch shall consist of long fibrous interlocking strands.<br />

2. Softwood Mulch: Softwood mulch shall be medium sized softwood material 1/2 to 3 inches with fines of<br />

1/2 inches and below produced from douglas fir, hemlock, or red cedar.<br />

3. Color: Natural.<br />

C. Mineral Mulch: Mineral mulch shall consist of decomposed granite, crushed rock, or gravel. Mulch shall be hard,<br />

durable stone, washed free of loam, sand, clay, and other foreign substances.<br />

1. Where wood mulch is shown or specified, mineral mulch shall be used where regionally appropriate or<br />

where wood mulch is not readily available.<br />

2. Size Range: 3/4 inch maximum 1/4 inch minimum.<br />

3. Color: Readily available natural gravel color range.<br />

D. Pine Bark or Pine Needle Mulch shall not be used.<br />

2.12 TREE STAKING<br />

A. Stakes shall be of lodgepole pine and shall be straight shafts, shaved and cut clean and bare of branches and stubs,<br />

free of loose knots, splits or bends, of uniform thickness and with a minimum diameter of 2 inches. Stakes shall be<br />

no less than ten (10’) feet in length.<br />

Formatted: PR1<br />

Formatted: Bullets and Numbering<br />

B. Tree ties shall be V.I.T. Cinch-Tie or approved equal.<br />

C. Hose chafing guard. Reinforced rubber or plastic hose at least 4 inch in diameter, black, cut to lengths required to<br />

protect tree trunks from damage.<br />

2.13 WATER<br />

A. Potable water, hose, and other watering equipment.<br />

Deleted: Tomahawk Tree Stabilizer<br />

and Fertilization System manufactured by<br />

Border Concepts, Inc. (800)845-3343.<br />

Part # 82100 – 42 inch Tomahawk<br />

Part # 82101 – 32 inch Tomahawk<br />

2.14 WEED MAT<br />

A. 4.1 oz., woven polypropylene, needle-punched fabric, weed barrier.<br />

2.15 STEEL EDGING<br />

A. 1/8-inch x 4-inch interlocking steel edging, staked with metal stakes sufficiently to hold in place.<br />

2.16 EROSION CONTROL BLANKET<br />

A. Rolled Erosion Control Products shall have current QDOR TM (Quality Data Oversight and Review) status issued<br />

by the Erosion Control Technology Council and shall meet state or agency specific requirements. Evidence of<br />

QDOR TM approval shall accompany the product shipped to the job site for ready identification by the contractor or<br />

an agency inspector.<br />

02900-7<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. If project completion date prohibits in-season planting, prepare for out-of-season seeding or sodding so that lawns<br />

shall be completed and ready for acceptance at time of project completion.<br />

B. Unsuitable Subsoils: Locations containing unsuitable subsoil shall be treated by one or more of the following:<br />

1. Where unsuitability is deemed by Owner to be due to excessive compaction caused by heavy equipment<br />

and where natural subsoil is other than AASHTO classification of A6 or A7, loosen such areas with spikes,<br />

discing, or other means to loosen soil to condition acceptable to Owner. Loosen soil to minimum depth of<br />

12 inches with additional loosening as required to obtain adequate drainage. Contractor may introduce peat<br />

moss, sand, or organic matter into the subsoil to obtain adequate drainage. Such remedial measures shall<br />

be considered as incidental, without additional cost to Owner.<br />

2. Where unsuitability is deemed by Owner to be due to presence of boards, mortar, concrete, or other construction<br />

materials in sub-grade and where natural subsoil is other than AASHTO classification of A6 or<br />

A7, remove debris and objectionable material. Such remedial measures shall be considered as incidental,<br />

without additional cost to Owner.<br />

3. Where unsuitability is deemed by Owner to be because natural subsoil falls into AASHTO classification of<br />

A6 or A7 and contains moisture in excess of 30 percent, then installation of sub-drainage system or other<br />

means described elsewhere in Specifications shall be used. Where such conditions have not been known or<br />

revealed prior to planting time and they have not been recognized in preparation of The Drawings and<br />

Specifications, then Owner shall issue pricing order to install proper remedial measures.<br />

C. Unsuitable Topsoil: Locations containing unsuitable topsoil shall be treated by one or more of the following:<br />

1. Where unsuitability is deemed by Owner to be because of presence of objectionable weeds; litter; sods;<br />

stiff clay; toxic substances; herbicides or other material which may be harmful to plant growth, then topsoil<br />

shall be removed from the site and disposed of in a legal manner.<br />

2. Where unsuitability is deemed by Owner to be because of presence of the stumps, roots; stones larger than<br />

1 inch in diameter; less than 3 percent organic material; low or high pH range, remove objectionable material<br />

and amend topsoil to meet the requirements specified in part 2 above. Such remedial measures shall be<br />

considered as incidental, without additional cost to Owner.<br />

D. Perform planting operations at steady rate of work unless weather conditions make it impossible to work. No plant<br />

material shall be planted in frozen ground.<br />

E. Tree and Shrub Preparation<br />

1. Dig bare-rooted shrubs with adequate fibrous roots. Cover roots with uniformly thick coating of mud by<br />

being puddled immediately after they are dug, or packed in moist straw or moss.<br />

2. Dig ball and burlap plants with firm natural balls of earth of diameter and depth to include fibrous roots.<br />

3. Protect roots or balls of plants at all times from sun and drying winds.<br />

4. Ball and burlap plants which cannot be planted immediately upon delivery shall be set on ground and protected<br />

with soil, wet moss, or other acceptable material. Heel-in bare rooted plants that cannot be planted<br />

immediately upon delivery. All shall be kept moist.<br />

5. Open and separate bundles of plants before roots are covered. Prevent air pockets among roots. During<br />

planting operations, cover bare roots with canvas, hay, or other suitable material. Plants shall not be bound<br />

with wire or rope which will result in damage to bark or branches.<br />

F. Sod and Seed Bed Preparation<br />

1. Newly Graded Subgrades:<br />

a. Do not place topsoil until subgrade has been approved in accordance with Section 02300.<br />

b. Before placing topsoil, rake subsoil surface clear of stones, debris, and roots. Disk, drag, harrow, or<br />

hand rake subgrade to depth of 4 inches and remove stones larger than 1-1/2 inches to provide bond<br />

for topsoil.<br />

c. Spread topsoil to a depth of 4 inches but not less than required to meet finish grades after light rolling<br />

and natural settlement. Adjust depth of topsoil in areas adjacent to paved surfaces or curbs to allow<br />

for the placement of sod or seed.<br />

02900-8<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


2. Unchanged Subgrades: If lawns are to be planted in areas unaltered or undisturbed by excavating, grading,<br />

or surface-soil stripping operations, prepare surface as follows:<br />

a. Remove existing grass, vegetation, and turf. Do not mix into surface soil.<br />

b. Disk, drag, or harrow surface soil to a depth of at least 6 inches.<br />

c. Remove stones larger that 1-1/2 inch in any dimension and sticks, roots, trash, and other extraneous<br />

matter.<br />

d. Legally dispose of waste material, including grass, vegetation, and turf.<br />

e. Adjust depth of topsoil in areas adjacent to paved surfaces or curbs to allow for the placement of sod<br />

or seed.<br />

3. Incorporate soil amendments and commercial fertilizer into the top 4 inches of topsoil to achieve the specified<br />

topsoil requirements. Till soil to a homogenous mixture of fine texture.<br />

4. Grade areas to finish grades, filling as needed or removing surplus topsoil. Float areas to smooth, uniform<br />

grade as indicated on the Drawings. Lawn areas shall slope to drain.<br />

5. Where no grades are shown, areas shall have a smooth and continual grade between existing or fixed controls,<br />

such as walks, curbs, catch basin, steps, or buildings. Roll, scarify, rake, and level as necessary to obtain<br />

true, even lawn surfaces. Finish grades shall meet approval of Owner.<br />

6. Sod and seed beds shall be firmed by rolling before seeding begins.<br />

G. Groundcover Bed Preparation:<br />

1. Grade areas to finish grades, filling as needed or removing surplus topsoil. Float areas to smooth, uniform<br />

grade as indicated on the Drawings.<br />

2. Set out and space groundcover 12 inches apart maximum.<br />

3. Dig holes large enough to allow spreading of roots, and backfill with planting soil.<br />

4. Remove groundcover from pots.<br />

5. Work soil around roots to eliminate air pockets and leave a slight saucer indention around plants to hold<br />

water.<br />

6. Water thoroughly after planting taking care not to cover plant crowns with wet soil.<br />

7. Protect plants from hot sun and wind; remove protection when plants show evidence of recovery from<br />

transplanting shock.<br />

H. Island Preparation:<br />

1. Excavate compacted soil to a depth of 24 inches.<br />

2. Maintain required angles of repose of adjacent materials as shown on the Drawings. Do not excavate subgrades<br />

of adjacent paving, structures, hardscapes, or other new or existing improvements.<br />

3. Scarify sides of excavation pit smeared or smoothed during excavation.<br />

4. Subsoil or topsoil removed from islands shall not be used in planting soil mix.<br />

5. Notify Owner’s CEC if subsoil conditions evidence unexpected water seepage or retention within excavation<br />

area.<br />

6. Backfill islands in 9 inch lifts with planting soil mix specified herein. Tamp each lift lightly to prevent settling.<br />

7. Grade areas to finish grades, filling as needed to allow positive drainage. Float areas to a smooth, uniform<br />

grade as indicated on the Drawings.<br />

I. Raised Planter Preparation:<br />

1. Excavate compacted soil and construction debris within raised planter to minimum 12 inches below finish<br />

grade of adjacent sidewalk.<br />

2. Notify Owner’s CEC if subsoil conditions evidence unexpected water seepage or retention with the excavation<br />

area.<br />

3. Scarify bottom of excavation and provide positive drainage to drainage pipe.<br />

4. Install drainage pipe as shown in the drawings.<br />

5. Backfill raised planter in 9 inch lifts with specified planting soil mix to within 1 inch of bottom edge of<br />

wall cap. Tamp each lift lightly to prevent settling. If settling occurs prior to planting add additional planting<br />

soil mix.<br />

6. Grade areas to finish grades, filling as needed to allow positive drainage. Float areas to a smooth, uniform<br />

grade as indicated on the Drawings.<br />

3.2 PROTECTION<br />

02900-9<br />

Deleted: [Editor Note: Island<br />

drainage systems may be required in<br />

some regions. Refer to the Geotechnical<br />

Report and include appropriate design on<br />

the plans and details and coordinate with<br />

paragraph below. Coordinate Island<br />

Preparation paragraph with the Wal-Mart<br />

Bio-Swale and Bio-island Guidelines.<br />

Formatted: Bullets and Numbering<br />

Formatted: Bullets and Numbering<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


A. Topsoil which must be transported across finished sidewalks shall be delivered in such manner that no damage<br />

will be done to sidewalks.<br />

B. Before commencing work, trees and shrubs that are to be saved shall be protected from damage by placement of<br />

fencing flagged for visibility or some other suitable protective procedure approved by Owner.<br />

C. Trucks or other equipment shall not be driven or parked within drip line of any tree unless tree overspreads paved<br />

area.<br />

D. Use precautionary measures when performing work around trees, sidewalks, pavements, utilities, and other features<br />

either existing or previously installed.<br />

E. Adjust depth of earthwork and topsoil when working immediately adjacent to aforementioned features in order to<br />

prevent disturbing tree roots, undermining sidewalks and pavements, and damage in general to other features either<br />

existing or previously installed.<br />

F. Cover plants transported to project in open vehicles with tarpaulins or other suitable covers securely fastened to<br />

body of vehicle to prevent injury to plants. Closed vehicles shall be adequately ventilated to prevent overheating of<br />

plants. Evidence of inadequate protection following digging, carelessness while in transit, or improper handling or<br />

storage shall be cause for rejection. Plants shall be kept moist, fresh, and protected. Such protection shall encompass<br />

entire period during which plants are in transit, being handled, or are in temporary storage.<br />

G. Plants shall not be delivered to the site more than seven days prior to planting. Plants not planted within 48 hours<br />

of delivery, shall be healed in (covered with sawdust, soil or mulch), and the containers or balls protected from<br />

wind and temperature and kept moist until planting.<br />

H. Where excavation, fill, or grading is required within drip line of trees that are to remain, work shall be performed<br />

as follows:<br />

1. Trenching: When trenching occurs around trees to remain, tree roots shall not be cut but trench shall be<br />

tunneled under or around roots by careful hand digging without injury to roots.<br />

2. Raising Grades:<br />

a. Where fill not exceeding 16 inches is required, clean, washed gravel graded from 1 inch to 2 inches<br />

in size shall be placed directly around tree trunk. Extend gravel out from trunk on all sides minimum<br />

of 18 inches and finish approximately 2 inches above finished grade at tree. Install gravel before<br />

any earth fill is placed. New earth fill shall not be left in contact with trunks of trees requiring<br />

fill.<br />

b. Where fill exceeding 16 inches is required, construct dry-laid tree well around trunk of tree. Tree<br />

well shall extend out from trunk on all sides minimum of 3 feet and to 3 inches above finish grade.<br />

Place coarse-graded rock directly around tree well extending out to drip line of tree. Place clean,<br />

washed gravel graded from 1 inch to 2 inches in size directly over coarse rock to depth of 3 inches.<br />

Place approved backfill material directly over washed gravel to desired finish grade.<br />

3. Lowering Grades: Existing trees in areas where new finish grade is to be lowered shall have regrading<br />

work done by hand to elevation indicated on The Drawings. Roots as required shall be cut cleanly 3 inches<br />

below finished grade and scars covered with tree paint.<br />

4. Trees marked for preservation that are more than 6 inches above proposed grades shall stand on broad<br />

rounded mounds and graded smoothly into lower level. Trees located more than 16 inches above proposed<br />

grades shall have dry-laid stone wall or other retaining structure as detailed on The Drawings constructed<br />

minimum of 5 feet from trunk. Exposed or broken roots shall be cut clean and covered with topsoil.<br />

3.3 PLANTING BED ESTABLISHMENT<br />

A. Prior to preparing planting beds, the area shall conform to the lines and grades shown on the plans and the condition<br />

of the subsoil shall be approved by the Owner.<br />

B. Contractor shall verify the location of any underground utilities on site.<br />

02900-10<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


C. Planting beds where existing subsoil is determined by Owner to be unsuitable for plant growth in accordance paragraph<br />

Unsuitable Subsoil herein shall be excavated to a depth of 24 inches or as needed to provide adequate drainage.<br />

Replace excavated soil with planting soil mix.<br />

D. Planting beds where existing subsoil is acceptable by Owner shall be prepared as follows:<br />

1. Seven days prior to commencing establishment of the planting areas, apply non selective herbicide. Remove<br />

dead vegetation.<br />

2. Loosen subsoil to a depth of 12 inches. Remove stones larger than 1 inch in any dimension, sticks, roots,<br />

rubbish, and other extraneous matter and legally dispose of them off site.<br />

3. Spread 3 inches of soil conditioner over the surface of the planting area and incorporate into the top 12<br />

inches of the soil. Prior to spreading soil conditioner, add or remove topsoil as needed to accommodate addition<br />

of soil conditioner and to achieve finish grade.<br />

4. Till planting soil mix to a homogenous mixture of fine texture.<br />

5. Float areas to smooth, uniform grade providing positive drainage out of planting beds and away from structures<br />

or as indicated on the Drawings.<br />

E. Apply slow release fertilizer at a rate of 1-1/2 pounds per 100 square feet for beds areas or as recommended by<br />

manufacturer and incorporate into the top 8 inches.<br />

3.4 TREE AND SHRUB PLANTING<br />

A. Plants too large for 2 persons to lift in and out of holes shall be placed with sling. Do not rock trees in holes to<br />

raise.<br />

B. If rock or other underground obstruction is encountered, Owner may require plant pits to be relocated, pits enlarged,<br />

or plants deleted from project.<br />

C. Make adjustments in locations as directed. In event that pits or areas for planting are prepared and backfilled with<br />

planting soil mix or topsoil to grade prior to commencement of lawn operations, they shall be so marked that when<br />

planting proceeds, they can be readily located. In case underground obstructions such as ledges or utilities are encountered,<br />

change location under direction of Owner without charge.<br />

D. Holes for trees shall be at least 2 feet greater in diameter than spread of root system and at least 6 inches deeper<br />

than root ball or as shown on the Drawings. Holes for shrubs shall be at least 2 feet greater in diameter than the<br />

spread of root system and at least 2 feet deep or as shown on the Drawings. Holes for vines shall be at least 12<br />

inches greater in diameter than the spread of rootball at least 12 inches deep.<br />

E. Backfill tree holes and shrub beds with planting soil mix. Apply slow release fertilizer at a rate of 1/4 pounds per<br />

caliper inch for trees. Incorporate fertilizer into the planting soil mix.<br />

F. Plants shall be planted at same depth as they had previously grown or as shown on the drawings. Backfill planting<br />

soil mix in layers of not more than 8 inches and each layer watered sufficiently to settle before next layer is placed.<br />

Tamp planting soil mix under edges of balled plants. Use enough planting soil mix to bring surfaces to finish<br />

grade when settled.<br />

1. Provide saucer around each plant as shown on The Drawings.<br />

2. Soak plants with water twice within first 24 hours after time of planting. Apply water with low pressure so<br />

as to soak in thoroughly without dislodging topsoil.<br />

G. Tree Staking: Install Tomahawk Tree Stabilizer and Fertilization System as shown on the drawings. Use one size<br />

larger than required by manufacturer.<br />

3.5 MISCELLANEOUS INSTALLATIONS<br />

A. Weed Mat: Place weed mat under planting areas that will not be seeded and in any other locations as shown on the<br />

Drawings. Cover weed mat with 4 inches of mulch and secure in place with soil staples.<br />

02900-11<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


B. Mulch: Place 4 inches of mulch as a top dressing in planting beds. Mulch single trees or shrubs to outside edge of<br />

saucer.<br />

C. Peg sodded slopes greater than 3:1 to hold in place.<br />

D. Areas to be covered with erosion control blankets shall be properly prepared, fertilized, and seeded before blanket<br />

is applied. When blanket is unrolled, netting shall be on top and fibers in contact with soil. In ditches, apply blanket<br />

in direction of flow of water. On slopes, apply blankets vertically on slope. Overlap ends and sides 6 inches<br />

and staple per manufacturer's written instructions.<br />

3.6 AREAS TO BE TURFED<br />

A. Unless otherwise shown on the plans, disturbed areas including out-lots shall be permanently sodded and seeded.<br />

B. Place 16-24 inch wide strip of solid slab sod adjacent to paved surfaces including sidewalks, curbs, walls, drainage<br />

structures, and vehicular pavement as shown on the drawings.<br />

C. Continually seed remaining disturbed areas until fully turfed with no bare spots.<br />

3.7 SOIL STABILIZATION<br />

A. Provide one or more of the following techniques to prevent soil eroding from denuded areas and leaving the site.<br />

Refer to stabilization requirements in Section 02370.<br />

1. Temporary Seeding or Stabilization.<br />

2. Permanent Seeding, Sodding, or Mulching.<br />

3.8 SEEDING<br />

A. Do not perform seeding in windy conditions.<br />

B. Seeding shall be dispersed in 2 directions at right angles to each other.<br />

C. Permanently seed and mulch cut and fill slopes as construction proceeds to extent considered desirable and practical.<br />

In the event it is not practical to seed areas, slopes shall be stabilized with straw mulch and tackifier, bonded<br />

fiber matrix, netting, blankets or other means to reduce the erosive potential of the area.<br />

D. Seed lawn areas by sowing evenly with approved mechanical seeder at rate of minimum of 3 pounds per 1,000<br />

square feet. Culti-packer or approved similar equipment may be used to cover seed and to form seedbed in one<br />

operation. In areas inaccessible to culti-packer, lightly rake seeded ground with flexible rakes and roll with water<br />

ballast roller. After rolling mulch with straw mulch at the rate of 2 tons per acre.<br />

E. Surface layer of soil for seeded areas shall be kept moist during germination period. Water seeded areas twice first<br />

week to minimum depth of 6 inches with fine spray and once per week thereafter as necessary to supplement natural<br />

rain to equivalent of 6 inches depth.<br />

3.9 SODDING<br />

A. Cut and lay sod on same day. Only healthy vigorous growing sod shall be laid.<br />

B. Lay sod across slope and tightly together to result in solid coverage free of gaps.<br />

C. Roll or firmly but lightly tamp new sod with suitable wooden or metal tamper sufficiently to set or press sod into<br />

underlying soil.<br />

D. All finished sodding shall be smooth and free of lumps and depressions.<br />

02900-12<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


E. After sodding has been completed, clean up and thoroughly water newly-sodded areas.<br />

3.10 MAINTENANCE DURING CONSTRUCTION<br />

A. Begin maintenance operations immediately after each plant is planted and continue as required until acceptance.<br />

Water, mulch, weed, prune, spray, fertilize, cultivate, and otherwise maintain and protect plants. Reset settled<br />

plants to proper grade and position, restore planting saucers, and remove dead, diseased, or unhealthy plant material.<br />

Tighten and repair stakes and wires. Correct defective work as soon as possible after it becomes apparent<br />

and weather and season permit.<br />

B. Upon completion of the planting operations, clean up landscaped areas to be free of stones, containers, trash, and<br />

other waste and debris to leave area in a neat and well groomed appearance.<br />

C. Supplement rainfall as required to provide an equivalent of 1 inch of water per week until the plants have rooted<br />

and are established.<br />

D. Maintain all plant material in a healthy, vigorous growing condition.<br />

E. Make weekly inspections to determine moisture content of soil and adjust watering schedule established by irrigation<br />

system installer to fit conditions.<br />

F. After grass growth has started, reseed or sod areas that fail to show uniform stand of grass in accordance with The<br />

Drawings and as specified herein. Continue Reseeding and sodding such areas repeatedly until areas are covered<br />

with satisfactory growth of grass. Perform removal and replacement or topsoil conditioning if required to facilitate<br />

establishment of grass.<br />

G. Water in such manner and as frequently as is deemed necessary by Owner to assure continued growth of healthy<br />

grass. Water areas of site in such a manner as to prevent erosion due to excessive quantities applied over small areas<br />

and to avoid damage to finished surface due to watering equipment.<br />

H. Provide water for execution and maintenance at no expense to Owner. Furnish portable tanks, pumps, hose, pipe,<br />

connections, nozzles, and any other equipment required to transport water from available outlets and apply it to<br />

seeded areas in approved manner.<br />

I. Mowing:<br />

1. Initiate mowing of turf grass areas when grass has attained height of 3 inches and roots are firmly established.<br />

Maintain turf grass height at 2 1/2 to 3 inches at subsequent cuttings depending on time of year.<br />

Remove no more than 1/3 of grass leaf at any cutting and cutting shall not occur more than 10 days apart.<br />

2. Mow native grass areas no more than 3 times per year to a height of no less than 4 inches.<br />

J. Remove heavy cuttings to prevent destruction of underlying turf. If weeds or other undesirable vegetation threaten<br />

to smother planted species, such vegetation shall be mowed or, in case of rank growths, shall be uprooted, raked<br />

and removed from area by methods approved by Owner.<br />

K. Remove weeds and other undesirable vegetation by applying herbicides as recommended by the manufacturer or<br />

by uprooting. Rake and remove uprooted vegetation from area by methods approved by Owner.<br />

L. Protect seeded area from pedestrian or vehicular trespassing while grass is germinating. Provide fences, signs,<br />

barriers, or other necessary temporary protective devices. Repair damage resulting from trespass, erosion, washout,<br />

settlement, or other causes.<br />

M. Remove fences, signs, barriers, or other temporary protective devices after final acceptance.<br />

N. Remove and replace diseased, distressed, dead, or rejected plants prior to Substantial Completion Date.<br />

02900-13<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


O. Replacements shall be plants of same variety and size specified on The Drawings. Furnish and plant as specified<br />

herein. Replacements resulting from removal, loss, or damage due to occupancy of project in any part, vandalism,<br />

physical damage by animals, vehicles, etc., and losses due to curtailment of water by local authorities will be approved<br />

and paid for by Owner.<br />

P. Grassed areas damaged during process of work shall be restored or repaired to condition satisfactory to the Owner.<br />

Fill, grade, re-fertilize, replant, or mulch as required to restore to contract requirements.<br />

3.11 QUALITY CONTROL<br />

A. Construction Testing Laboratory Quality Control: A Construction Testing Laboratory (CTL) selected and paid for<br />

by the Owner, will be retained to perform topsoil testing and analysis of in-place topsoil during topsoil placement<br />

operations.<br />

1. Topsoil Analysis: Collect 5 random representative samples from the in-place topsoil. Combine samples and<br />

test as a composite for percentages of organic matter; presence of herbicides, percentage of sand, silt, and<br />

clay content; deleterious material; pH; micro and macro nutrient content; and mineral and plant-nutrient<br />

content of topsoil.<br />

2. Multiresidue Herbicide/Pesticide Screen: Perform a multiresidue herbicide/pesticide screen that includes<br />

the following herbicides and pesticides: Acetochlor, Alachlor, Atrazine, Butylate, Carbofuran, Clomazone,<br />

Cyanazine, Diazinon, Ethyl Chlorpyrifos, Ethyl Parathion, EPTC, Ethalfluralin, Fluchloralin, Fonofos,<br />

Isofenphos, Malathion, Methyl Parathion, Metolachlor, Metribuzin, Pebulate, Propachlor, Pramitol, Propazine,<br />

Pendimethalin, Simazine, Trifluralin, and Vernolate.<br />

3. Topsoil Depth Inspection: Verify depth of topsoil placement as follows:<br />

a. Open Lawn Areas: 50 feet on center, minimum 1 inspection per area<br />

b. Parking Islands: One inspection per 200 square feet of sod and seed bed preparation area, minimum<br />

one per island.<br />

4. Submit test reports in accordance with Section 01458.<br />

B. Contractor Quality Control: Retain an independent soil testing laboratory to sample and test imported topsoil. The<br />

testing lab for the Multiresidue Herbicide/Pesticide Screen shall be NELAC certified.<br />

1. Topsoil Analysis: Collect 5 random samples from the topsoil borrow area or areas. Combine samples and<br />

test as a composite for percentages of organic matter; presence of herbicides; percentage of sand, silt, and<br />

clay content; deleterious material; pH; and mineral and plant-nutrient content of topsoil.<br />

2. Multiresidue Herbicide/Pesticide Screen: Perform a multiresidue herbicide/pesticide screen that includes<br />

the following herbicides and pesticides: Acetochlor, Alachlor, Atrazine, Butylate, Carbofuran, Clomazone,<br />

Cyanazine, Diazinon, Ethyl Chlorpyrifos, Ethyl Parathion, EPTC, Ethalfluralin, Fluchloralin, Fonofos,<br />

Isofenphos, Malathion, Methyl Parathion, Metolachlor, Metribuzin, Pebulate, Propachlor, Pramitol, Propazine,<br />

Pendimethalin, Simazine, Trifluralin, and Vernolate.<br />

3. Submit topsoil borrow area test reports to Owner’s Civil Engineering Consultant (CEC) minimum 6 weeks<br />

prior to delivery to site.<br />

3.12 EXTENDED MAINTENANCE<br />

A. Provide landscape maintenance for the site including stormwater conveyance systems as specified below.<br />

B. Contractor shall provide warranty and maintenance for the entire site including existing lawns and landscape materials<br />

not installed as part this contract, but remaining in place during and after completion of the project.<br />

C. Comply with Federal, State, Local or other governmental requirements relating to the general upkeep and maintenance<br />

of Stormwater Conveyance Systems, Natural Areas, Natural and Created Wetlands. Failure to follow these<br />

standards will fall to the liability of the Contractor<br />

D. Commence Extended Maintenance immediately after Substantial Completion Date and continue as indicated on<br />

the following chart:<br />

E.<br />

02900-14<br />

Deleted: [Editor Note: Extended maintenance<br />

applies to all projects including<br />

new stores, expansions, and take-overs.]<br />

Formatted: Bullets and Numbering<br />

Deleted: [Editor Note: Include the<br />

bracketed text below for Expansion and<br />

Take-Over projects only. Delete the text<br />

for New Store Projects]<br />

[<br />

Formatted: Bullets and Numbering<br />

Deleted: ]<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


EXTENDED MAINTENANCE / WARRANTY CHART<br />

Extended Maintenance / Warranty<br />

Substantial Completion Date Expiration<br />

Duration<br />

December July 19 months<br />

January July 18 months<br />

February July 17 months<br />

March July 16 months<br />

April July 15 months<br />

May July 14 months<br />

June July 13 months<br />

July July 12 months<br />

August August 12 months<br />

September September 12 months<br />

October October 12 months<br />

November November 12 months<br />

F. General Landscaping: Landscape maintenance shall include necessary watering, cultivation, weeding, pruning,<br />

wound dressing, disease and insect pest control, protective spraying, straightening plants which lean or sag, adjustments<br />

of plants which settle or are planted too low, mowing, replacement of mulch that has been displaced, repairing<br />

and reshaping of saucers, and reseeding or replanting of those areas affected. Remove rubbish, waste,<br />

tools, and equipment used at end of each workday.<br />

G. Watering<br />

1. Utilize the Owner’s irrigation system for watering. Failure of system does not relieve Contractor's responsibility<br />

of maintaining desired level of moisture necessary to maintain vigorous, healthy growth.<br />

2. Apply water in quantities sufficient to penetrate soil to minimum depth of 8-inches in shrub beds and 6-<br />

inches in turf areas at rate that will prevent saturation of soil.<br />

3. Supplemental on-site water will be furnished by Owner. Contractor shall furnish hose and other watering<br />

equipment as required for supplemental watering. If on-site water is not available, immediately notify Wal-<br />

Mart Warranty and Landscape Departments by email at warrantynewconstruction@wal-mart.com and<br />

landscape@wal-mart.com.<br />

H. Weeding: Maintain all shrub and groundcover areas free from weeds and undesirable grasses.<br />

I. Disease and insect pest control: Inspect plant material at least once each month to locate any disease or insect pest<br />

infestations. Upon discovery of infestation, nature or species of infestation shall be identified. Spray or treat as<br />

required to keep trees and shrubs free of insects and disease.<br />

J. Supplement rainfall and irrigation system as required to provide adequate water for vigorous and healthy growth<br />

of trees.<br />

K. Pruning and Repair: Prune as required to remove dead or injured branches, to compensate for loss of roots as result<br />

of transplanting operations, and to maintain safety in traveled areas. Pruning shall not change the natural habit<br />

or attractive, balanced shape of plant. Cuts shall be made at the outside edge of the branch collar.<br />

L. Turf Maintenance: Maintain an establish lawn by watering, fertilizing, weeding, mowing, trimming, edging, replanting<br />

and operations required to maintain full turf coverage. Roll, re-grade, re-mulch, and replant bare or eroded<br />

areas greater 1 square foot to produce a uniformly smooth lawn. Provide materials and installation techniques<br />

the same as those used in the original installation.<br />

1. Mowing:<br />

a. Mow turf grass areas at regular intervals to keep turf height from exceeding 3-inches. Maintain turf<br />

grass height at 2-1/2 to 3-1/2 inches at subsequent cuttings depending on time of year. Remove no<br />

more than 1/3 of grass leaf at any cutting. Mow turf grass at intervals of not more than 10 days dur-<br />

02900-15<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


ing growing season. Mow in such manner as to prevent clippings from blowing onto paved areas<br />

and sidewalks. Cleanup after mowing shall include sweeping or blowing to clear mowing debris.<br />

b. Mow native grass areas no more than 3 times per year to a height of no less than 4 inches.<br />

2. Edging: Mechanically edge turf areas adjacent to sidewalks, curbs and other paved surfaces with a blade<br />

type edger. Perform edging with each mowing interval.<br />

3. Trimming: Trim grass around valve boxes, poles and other structures with string type trimmers. Do not<br />

trim grass around tree trunks with mechanical trimmer. Remove grass adjacent to tree trunk by methods<br />

that will not cause damage to trees.<br />

4. Turf Fertilization: Apply balanced commercial grade fertilizer minimum 4 times annually. Adjust type,<br />

frequency, and quantity of fertilizer to provide lush and healthy turf at all times. Spilled or excess fertilizer<br />

shall be swept and properly disposed. Flushing into storm sewer is prohibited.<br />

5. Turf Weed Control: Develop and maintain a broadleaf weed and foreign grass control program consisting<br />

of both post and pre-emergent chemical control. Maintain turf in a weed-free condition.<br />

M. Clean up: During course of maintenance, excess and waste materials shall be continuously and promptly removed<br />

at end of each workday.<br />

N. Maintenance report and schedule of activities: Utilizing the online Evoco Quickbase Landscape tracking application<br />

to provide monthly schedules and reports to Owner detailing previous and subsequent planned maintenance<br />

activities. Use the report form located at the end of this section. Include dated digital photographs in PDF format<br />

with each monthly report showing current and full clear views of entire landscaped and turf areas. Upload maintenance<br />

report and photos to the Quickbase Landscape tracking application each month.<br />

O. General Irrigation:<br />

1. Contractor shall maintain the irrigation system in good operating condition and coordinate the operation of<br />

the system with the store manager through monthly inspections of system components and make repairs or<br />

replacement of parts as necessary. This includes checking and verifying operation in each zone including<br />

but limited to the following: head alignment, rain sensors, controller, cleaning and replacing filters, observe<br />

drip emitters and tubing for problems, calibrate on-site weather station, and leak detection.<br />

2. Optimize water usage and water conservation by adjusting programming to allow for weather changes and<br />

growth seasons. Irrigation shall be conducted between 2:00 a.m. and 6:00 a.m. unless requested by Owner.<br />

Immediately notify Wal-Mart Warranty and Landscape departments by email at warrantynewconstruction@wal-mart.com<br />

and landscape@wal-mart.com if normal irrigation programming is discontinued or disrupted<br />

by store employees.<br />

3. In the event of irrigation system failure, provide manual watering to keep the plant material in a vigorous,<br />

healthy condition until system is restored.<br />

4. Comply with water rationing ordinances mandated by the jurisdictional authorities. Immediately notify<br />

Wal-Mart Warranty and Landscape Departments by email at warrantynewconstruction@wal-mart.com and<br />

landscape@wal-mart.com when rationing ordinances are implemented.<br />

P. Winterization:<br />

1. When cold weather approaches and chance for freezing conditions exist, the irrigation system shall be<br />

drained after each use.<br />

2. Winterization procedure shall include the following:<br />

a. Shut water off at main gate valve<br />

b. Open manual drain valves<br />

c. Blow out each section twice with compressed air<br />

d. Set controller to cycle through each section minimum time available, once each day through winter<br />

months.<br />

e. If backflow preventer is installed with unions, remove and store out of weather.<br />

Q. Spring Start-up: Spring start-up procedure shall include the following:<br />

1. Reinstall backflow prevention device.<br />

2. Close manual drain valves.<br />

3. Slowly turn water on.<br />

4. Check for leaks and proper alignment of heads.<br />

5. Check drip line and emitters for damage.<br />

02900-16<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


6. Repair and adjust system as required for proper operation.<br />

R. Stormwater Conveyance Systems Maintenance:<br />

1. 30 days prior to substantial completion, Contractor shall call (479) 204-1195 to arrange an onsite meeting<br />

with Walmart’s Stormwater Compliance Contractor to review and identify areas of responsibility prior to<br />

initiating extended maintenance service. Stormwater Compliance Contractor’s contact information will be<br />

provided by Walmart.<br />

a. Wal-Mart’s Stormwater Compliance Contractors maintenance areas shall be identified as shown on<br />

the drawings and as defined below.<br />

S. Wal-Mart’s Stormwater Compliance Contractor Maintenance Responsibility: Areas that are machine maintained<br />

where damages could result to landscaping materials if maintenance occurred with soils in a saturated condition<br />

will be maintained under a separate contract by Wal-Mart’s Stormwater Compliance Contactor. The areas are defined<br />

as follows:<br />

1. Swales<br />

2. Ditches<br />

3. Channels<br />

4. Turf vegetation within the sloped bank perimeter of dry and wet detention basins.<br />

Deleted: [Editor Note: Delineate areas<br />

of responsibility for Wal-Mart’s Stormwater<br />

Compliance Contractor’s landscape<br />

maintenance on the plans based on the<br />

requirements below and guidance in the<br />

Anytown Plans. Edit stormwater conveyance<br />

maintenance requirements to add<br />

additional maintenance obligations for<br />

the Contractor as required by wetlands<br />

permit. The term Contractor refers to the<br />

General Contractor only.]<br />

Formatted: Bullets and Numbering<br />

T. Wal-Mart’s Stormwater Compliance Contractor will provide limited maintenance including trash and debris removal<br />

only from wetlands and bio-retention areas.<br />

U. Contractor’s Responsibility: Landscaped areas not identified as Wal-Mart’s Stormwater Compliance Contractors<br />

responsibility above shall be maintained by Contractor:<br />

1. Maintain areas adjacent to stormwater conveyances and collection areas as follows:<br />

a. Mow only to the top of bank, top of side slope, or the perimeter fence.<br />

2. Perform limited maintenance including trash and debris removal only from stormwater conveyance systems<br />

including swales, ditches, channels, dry detention and wet detention (retention) basins except for within<br />

open water areas.<br />

3. Contractor shall not operate motorized equipment or perform maintenance activities including mowing,<br />

trimming, herbicide, pesticide or fertilizer applications within areas identified as stormwater conveyance or<br />

collection areas.<br />

4. Evaluate and report overall condition of wetland areas and plant material on the monthly maintenance report<br />

provided below. Compliance testing, sampling and reporting including, but not limited to water samples<br />

and photos will be provided by others.<br />

5. Determine applicable environmental laws and regulations regarding the use of chemicals adjacent to these<br />

areas and complying with all such applicable laws and regulations. Contractor shall not apply any chemicals<br />

directly or indirectly into stormwater conveyance or collection areas.<br />

6. Comply with all Federal, state, local or other governmental requirements relating to the general upkeep of<br />

these areas. Failure to follow these standards will fall to the liability of the Contractor.<br />

V. No-Fault Repair and Correction: No fault repair and correction work shall consist of work to correct faults or repair<br />

damage existing through no fault of the Contractor, but which is necessary for the continued proper maintenance<br />

and operation of the landscape system including correction of sprinkler system, on-site utilities, equipment,<br />

landscape plants or materials damage, or other corrections necessary for the duration of the Extended Maintenance/Warranty<br />

Period specified above. No fault repair and correction shall not include work as otherwise defined<br />

within the scope of Extended Maintenance. The Contractor shall perform such necessary work and shall bear costs<br />

up to an amount of $300 per month. This amount, multiplied by number of months of anticipated warranty period,<br />

shall be included in the bid price. When similar necessary repair work in excess of $300 per month occurs, the<br />

Contractor shall Immediately notify Wal-Mart Warranty and Landscape departments by email at warrantynewconstruction@wal-mart.com<br />

and landscape@wal-mart.com and perform such excess work only upon their direction.<br />

Payment for work directed and performed exceeding $300 per month will be made to the Contractor by Wal-Mart.<br />

END OF SECTION<br />

02900-17<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 Revision Date: 10-21-2011


MONTHLY MAINTENANCE REPORT AND SCHEDULE OF ACTIVITIES<br />

Project Location:<br />

Date:<br />

(City)<br />

(State)<br />

Project Number: ___________ Store Number: _________________________<br />

Reporting Period (month/day/year – month/day/year): _____________________________________________________<br />

Substantial Completion Date: ________________________________________________________________________<br />

Extended Maintenance / Warranty Expiration Date: _______________________________________________________<br />

Maintenance Activities Completed during this Reporting Period:<br />

Was lawn mowing performed? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): ____________________________________________________________________<br />

Were trees pruned? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): _____________________________________________________________________<br />

Were shrubs pruned? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): _____________________________________________________________________<br />

Was supplemental watering performed? YES___ NO___<br />

Trees YES___ NO___<br />

Shrubs YES___ NO___<br />

Lawn YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): _____________________________________________________________________<br />

Were post / pre-emergent herbicides, insecticides, or fungicides applied? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): _____________________________________________________________________<br />

Types: ______________________________________________________________________<br />

______________________________________________________________________<br />

Rate of application: ____________________________________________________________<br />

Was fertilizer applied to the lawn? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): ____________________________________________________________________<br />

Types: _____________________________________________________________________<br />

02900-18<br />

Anytown, USA - 11110000 11/7/2011


Rate of application: ___________________________________________________________<br />

Were any plant materials adjusted or replaced? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

List species, location and date of each adjustment / replacement:<br />

1. ________________________________________________________________________<br />

2. ________________________________________________________________________<br />

3. ________________________________________________________________________<br />

4. ________________________________________________________________________<br />

5. ________________________________________________________________________<br />

Was mulch added to the trees or shrub planting area? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

Date(s): ____________________________________________________________________<br />

Number of bags: _____________________________________________________________<br />

Were repairs on the landscaping or irrigation system performed? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

List repairs, locations and dates:<br />

1. __________________________________________________________________________<br />

2. __________________________________________________________________________<br />

3. __________________________________________________________________________<br />

4. __________________________________________________________________________<br />

5. __________________________________________________________________________<br />

No Fault Repairs and Corrections completed during the Reporting Period.<br />

Performed by: ______________________________________________________________________<br />

(company)<br />

(supervisor)<br />

List details of repairs, locations and dates:<br />

1. ___________________________________________________________________________<br />

2. ___________________________________________________________________________<br />

3. ___________________________________________________________________________<br />

4. ___________________________________________________________________________<br />

5. ___________________________________________________________________________<br />

Wetlands and Bio-Retention Maintenance during this Reporting Period<br />

Does the site contain natural or created wetlands? YES___ NO___<br />

Does the site contain bio-retention areas? YES___ NO___<br />

Report overall condition of wetland and bio-retention areas and condition of plant material.<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_______________<br />

Were any plant materials adjusted or replaced? YES___ NO___<br />

Performed by: ______________________________________________________________________<br />

02900-19<br />

Anytown, USA - 11110000 11/7/2011


(company)<br />

(supervisor)<br />

List species, location and date of each adjustment / replacement:<br />

1. ________________________________________________________________________<br />

2. ________________________________________________________________________<br />

3. ________________________________________________________________________<br />

4. ________________________________________________________________________<br />

5. ________________________________________________________________________<br />

• Report overall condition of other storm water conveyance systems:<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

_____________________________________________________________________________________________<br />

Planned Maintenance Activities for the Upcoming Month:<br />

Week #1 (1 st – 7 th ):<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

Week #2 (8th – 14 th ):<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

Week #3 (15 th – 21 st ):<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

Week #4 (22 nd – End of the Month):<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

02900-20<br />

Anytown, USA - 11110000 11/7/2011


____________________________________________________________________________________________________<br />

____________________________________________________________________________________________________<br />

General Contractor: ________________________________________________<br />

(Signature)<br />

________________________________________________<br />

(Print Name and Title)<br />

Landscape/Maintenance Contractor: ___________________________________<br />

(Signature)<br />

________________________________________________<br />

(Print Name and Title)<br />

___________________________<br />

(Date)<br />

___________________________<br />

(Date)<br />

02900-21<br />

Anytown, USA - 11110000 11/7/2011


CONTRACTOR WORK COMPLETION REPORT<br />

(Form to be completed by the store manager and submitted with the Monthly Maintenance Report and Schedule of Activities).<br />

STORE MANAGER: Please initial on the appropriate blanks.<br />

Yes<br />

No<br />

Was quality of work satisfactory? _____ _____<br />

Did the contractor’s employees cooperate with you satisfactorily? _____ _____<br />

Was clean up after work completion satisfactory? _____ _____<br />

Did the contractor’s employees complete all specified work? _____ _____<br />

Did you personally inspect completed work? _____ _____<br />

Overall performance: EXCELLENT GOOD POOR<br />

Other Comments: ______________________________________________________________<br />

Managers Signature:______________________________________DATE:__________________________<br />

PRINT NAME AND TITLE:________________________________________________________<br />

Store/Club#: _ Location: . W/O # ________.<br />

STORE STAMP (must have)<br />

STORE STAMP<br />

02900-22<br />

Anytown, USA - 11110000 11/7/2011


Page 5: [1] Deleted kkoethe 10/13/2011 1:59:00 PM<br />

NORTHEAST<br />

Coronilla varia Crown Vetch<br />

Hedera helix English Ivy<br />

Parthenocissus Virginia Creeper<br />

quinquefolia<br />

MIDWEST<br />

Coronilla varia Crown Vetch<br />

Hedera helix English Ivy<br />

Vinca minor Periwinkle<br />

SOUTHEAST<br />

Coronilla varia Crown Vetch<br />

Euonymous Wintercreeper<br />

fortunei<br />

Vinca minor Periwinkle<br />

NORTHWEST<br />

Hypericum St. John's Wart<br />

Euonymous Wintercreeper<br />

fortunei<br />

Vinca minor Periwinkle<br />

SOUTHWEST<br />

Oenothera berlandiera<br />

Mexican Evening Primrose<br />

Dalea greggii Trailize Indigo Bush<br />

Merremia aurea Yellow Morning Glory<br />

SOUTH FLORIDA AND SOUTH TEXAS<br />

Ajuga reptans Carpet Bugle<br />

Euonymous Wintercreeper<br />

fortunei<br />

Hypericum St. John's Wart


UniSpec II 093011<br />

SECTION 03310 (03 3100) – STRUCTURAL CONCRETE AND EXTERIOR CONCRETE SLABS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Cast-in-place structural concrete for concrete structures and exterior slabs on grade including the following:<br />

a. Footing and stemwalls.<br />

b. Dock walls.<br />

c. Truckwell retaining wall.<br />

d. Dock leveler pit.<br />

e. Steps.<br />

f. Interior curbs.<br />

g. Chase wall pit.<br />

h. Truckwell.<br />

i. Door stoops.<br />

j. Exterior sidewalks adjacent to building and entry slab.<br />

k. Compactor and compressor equipment pads.<br />

l. Garden center (exterior slabs).<br />

2. Aggregate base below slab.<br />

3. Formwork, shoring, bracing, and anchorage.<br />

4. Reinforcement and accessories.<br />

5. Curing and finishing.<br />

B. Related Requirements:<br />

1. Section 01458 - Laboratory Testing Services: Procedures for inspection, testing, and documentation by<br />

Owner furnished testing laboratory.<br />

2. Section 02715 - Base Course: Base for exterior concrete slabs except as otherwise specified herein.<br />

3. Section 03312 - Cast-In-Place Concrete Slabs: Concrete for interior slabs on ground.<br />

4. Section 03362 - Burnished Concrete Floor Finishes.<br />

5. Section 05120 - Structural Steel: Column anchor bolts.<br />

6. Section 05500 - Metal Fabrications: Other metal components cast into concrete.<br />

7. Section 07900 - Joint Sealers. Expansion, contraction, and construction joint fillers and sealants.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. Mandatory Provisions: In publications referred to herein, advisory provisions shall be considered to be<br />

mandatory.<br />

C. American Association of State Highway and Transportation Officials (AASHTO): Standard Specification For<br />

Transportation Materials And Methods Of Sampling and Testing.<br />

1. AASHTO T318 - Water Content of Freshly Mixed Concrete Using Microwave Oven Drying (Formerly<br />

AASHTO TP 23).<br />

D. American Concrete Institute (ACI):<br />

1. ACI 117 - Standard Tolerances for Concrete Construction and Materials.<br />

2. ACI 301 - Structural Concrete.<br />

3. ACI 304R - Guide for Measuring, Mixing, Transporting, and Placing Concrete.<br />

4. ACI 304.2R - Placing Concrete By Pumping Methods.<br />

5. ACI 305.1 - Specifications for Hot Weather Concreting.<br />

6. ACI 306.1 - Cold Weather Concreting.<br />

03310 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


7. ACI 308.1 - Standard Specification for Curing Concrete.<br />

8. ACI 308R - Guide To Curing Concrete.<br />

9. ACI 315 - Details and Detailing of Concrete Reinforcement.<br />

10. ACI 318 - Building Code Requirements for Reinforced Concrete and Commentary.<br />

11. ACI 347 - Guide To Formwork For Concrete.<br />

12. ACI 347R - Formwork for Concrete.<br />

13. ACI SP66 - ACI Detailing Manual.<br />

E. ASTM International (ASTM):<br />

1. ASTM A 36 - Carbon Structural Steel.<br />

2. ASTM A 185 - Steel Welded Wire Fabric, Plain, for Carbon Steel, 60,000 PSI Tensile Strength Concrete<br />

Reinforcement.<br />

3. ASTM A 615 - Deformed and Plain Billet-Steel Bars for Concrete Reinforcement.<br />

4. ASTM A 706 - Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement.<br />

5. ASTM C 31 - Making and Curing Concrete Test Specimens in the Field.<br />

6. ASTM C 33 - Concrete Aggregates.<br />

7. ASTM C 39 - Concrete Specimens, Compressive Strength of.<br />

8. ASTM C 42 - Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of<br />

Concrete.<br />

9. ASTM C 94 - Ready-Mixed Concrete.<br />

10. ASTM C 136 - Sieve Analysis of Fine and Coarse Aggregates.<br />

11. ASTM C 138 - Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of<br />

Concrete.<br />

12. ASTM C 143 - Standard Test Method for Slump of Hydraulic Cement Concrete.<br />

13. ASTM C 150 - Portland Cement.<br />

14. ASTM C 171 - Sheet Materials for Curing Concrete.<br />

15. ASTM C 172 - Sampling Freshly Mixed Concrete.<br />

16. ASTM C 173 - Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric<br />

Method.<br />

17. ASTM C 231 - Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method.<br />

18. ASTM C 260 - Air-Entraining Admixtures for Concrete.<br />

19. ASTM C 309 - Liquid Membrane-Forming Compounds for Curing Concrete.<br />

20. ASTM C 494 - Chemical Admixtures for Concrete.<br />

21. ASTM C 618 - Fly Ash and Raw or Calcined Natural Pozzolan for use as a Mineral Admixture in Portland<br />

Cement Concrete.<br />

22. ASTM C 881 - Epoxy-Resin-Base Bonding Systems For Concrete.<br />

23. ASTM C 989 - Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars.<br />

24. ASTM C 1064 - Standard Test Method for Temperature of Freshly Mixed Hydraulic Cement Concrete.<br />

25. ASTM C 1218 - Water-Soluble Chloride in Mortar and Concrete.<br />

26. ASTM C 1315 - Liquid Membrane Forming Compounds Having Special Properties for Curing and Sealing<br />

Concrete.<br />

27. ASTM D 98 - Calcium Chloride.<br />

28. ASTM D 226 - Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing.<br />

29. ASTM D 448 - Sizes of Aggregate for Road and Bridge Construction.<br />

30. ASTM D 698 - Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 5.5 lb (2.49 Kg)<br />

Hammerand 12-in (305 mm) Drop.<br />

31. ASTM D 1241 - Materials for Soil-Aggregate Subbase, Base and Surface Courses.<br />

F. America Plywood Association (APA):<br />

1. Grading Rules.<br />

G. American Welding Society (AWS):<br />

1. AWS D1.4 - Structural Welding Code Reinforcing Steel.<br />

H. Concrete Reinforcing Steel Institute (CRSI):<br />

1. CRSI Manual of Standard Practice.<br />

2. CRSI Placing Reinforcing Bars.<br />

03310 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


I. Department of Commerce (National Institute of Standards and Technology) - Product Standard (DOC):<br />

1. DOC PS 1 - Construction and Industrial Plywood.<br />

J. International Code Council, Inc.:<br />

1. International Building Code (IBC).<br />

K. National Ready Mixed Concrete Association:<br />

1. NRMCA Inspection Standards.<br />

1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre installation Meeting: Convene Pre-installation Meeting at Site at least two weeks prior to commencing work<br />

of this Section.<br />

1. Require attendance of parties directly affecting work of this Section, including, but not limited to, the<br />

following:<br />

a. Owner’s Representative.<br />

b. CTL’s Representative and Inspector.<br />

c. Contractor.<br />

d. Concrete sub-contractor.<br />

e. Concrete job foreman.<br />

f. Concrete supplier.<br />

g. Base fine grading contractor.<br />

2. Contact Wal Mart Construction Manager 30 days prior to pre installation conference to confirm schedule.<br />

3. Review foreseeable methods and procedures related to paving work, including the following:<br />

a. CTL’s testing and inspection procedures.<br />

b. Concrete finishes and finishing.<br />

c. Cold- and hot-weather concreting procedures.<br />

d. Curing procedures.<br />

e. Concrete design mixture and examine procedures for ensuring quality of concrete materials.<br />

f. Proposed sources of concrete materials, including capabilities and location of plant that will<br />

manufacture concrete.<br />

g. Tour, inspect and discuss condition of subgrade, drainage structures, and other preparatory work.<br />

h. Requirements for protecting concrete work, including restriction of traffic during installation period<br />

and for remainder of construction period.<br />

i. Review and finalize construction schedule and verify availability of materials.<br />

j. Concrete paving requirements (drawings, specifications and other contract documents).<br />

k. Required submittals, both completed and yet to be completed.<br />

l. Weather and forecasted weather conditions, and procedures for coping with unfavorable conditions.<br />

m. Safety precautions relating to placement of concrete.<br />

4. Record discussions of meeting and decisions and agreements reached. Submit in accordance with the<br />

requirements of Submittals paragraph.<br />

5. Changes to Contract Documents from recommendations or discussions at the Pre-installation Meeting shall<br />

be approved in writing by Wal-Mart Construction Manager prior to implementation.<br />

1.4 SUBMITTALS<br />

A. Submittal Procedures: Unless otherwise specified herein, comply with the requirements of Section 01330.<br />

B. Submit submittal items required within this Section concurrently. Do not submit submittals of this Section<br />

together with submittals in Section 03312 or any other section. Identify submittals explicitly in accordance with<br />

the requirements of Section 01330. Submit required submittals within 5 working days of Contract date unless<br />

otherwise specified in this Section.<br />

C. Sieve Analysis for Aggregate Base: Submit current sieve analysis report for aggregate base and choker material.<br />

D. Concrete Batch Plant Certification: Submit name and address of the concrete supplier’s batch plant and plant<br />

certification(s) by National Ready-Mix Concrete Association or State Department of Transportation.<br />

03310 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Shop Drawings: Submit shop drawings within 5 working days of Contract Date. Do not use reproductions of<br />

Contract Documents as shop drawings. Prepare shop drawings in accordance with Part B, Chapter 3, ACI 315.<br />

1. Reinforcement:<br />

a. Include concrete notes on shop drawings that relate to proper placing of reinforcing.<br />

b. Show all reinforcing steel including dowels, embedded steel items, and anchor bolts.<br />

c. Include number, grade, size, length, mark, location, splice lengths, and bending diagrams for<br />

reinforcing steel and related products.<br />

2. Placement Drawings:<br />

a. Submit reinforcement placement drawings with bar lists. Include walls, grade beams, and plans of<br />

footings and slabs.<br />

b. Show section cuts, details with piece marks, and control joint locations. Show reinforcing size,<br />

quantity, spacing, location, length, and required schedules.<br />

F. Samples: Materials as requested by the Structural Engineer of Record (SER), including names, sources, and<br />

descriptions.<br />

G. Mix Design: Submit Concrete Mix Design Submittal Form included at end of this Section.<br />

1. Submit proposed mix design in accordance with ACI 301, Sections 3.9 "Proportioning on the basis of<br />

previous field experience or trial mixture", or 3.10 "Proportioning based on empirical data".<br />

2. Submit separate mix design for concrete to be placed by pumping in addition to the mix design for concrete<br />

to be placed directly from the truck chute.<br />

3. Submit mix design by email to Architect and the Wal-Mart Construction Testing Laboratory (CTL).<br />

Include applicable information shown on the Mix Design Submittal Form including the following:<br />

a. Proportions of cementitious materials, fine and coarse aggregate, and water.<br />

b. Water-cementitious material ratio, 28-day compressive design strength, slump, and air content.<br />

c. Type of cement, fly ash, slag, and aggregate.<br />

d. Individual aggregate gradation.<br />

e. Type and dosage of admixtures.<br />

f. Special requirements for pumping.<br />

g. Range of ambient temperature and humidity for which design is valid.<br />

h. Special characteristics of mix which require precautions in mixing, placing, or finishing techniques<br />

to achieve finished product specified.<br />

H. Attachments to Concrete Mix Design: Submit the following as attachments to be included with the Concrete Mix<br />

Design:<br />

1. Cementitious materials mill test reports for the following:<br />

a. Portland cement.<br />

b. Fly ash.<br />

c. Slag.<br />

2. Designation, type, quality, and source (natural or manufactured) of coarse and fine aggregate materials.<br />

3. Sieve Analysis Reports for Concrete Aggregate: Provide separate reports of particle distribution,<br />

calculating cumulated percentages passing for all individual aggregates required on the mix form. Sieve<br />

analysis sampling and testing for each aggregate source shall be conducted within 60 days of concrete<br />

submittal date.<br />

4. Aggregate Supplier Statement:<br />

a. Stating if aggregate is possibly alkali-reactive based on tests or past service.<br />

b. Stating if aggregate can possibly cause pop-outs, “D” cracking, or other disruptions due to moisture<br />

gain, freezing, or other mechanisms, based on tests or past service.<br />

5. Product data for the following concrete materials admixtures:<br />

a. Air entraining.<br />

b. Water reducing.<br />

c. Water reducing and retarding.<br />

d. Accelerating.<br />

e. Evaporation retarding.<br />

f. High-range water reducing.<br />

g. Chloride ion content for each admixture.<br />

03310 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


6. Chloride-Ion Content: Measured water-soluble chloride-ion content (percent by weight of cementitious<br />

materials) in accordance with ASTM C 1218.<br />

7. Concrete compressive strength data as required by ACI 318.<br />

I. Concrete Supplier Approval. Statement of Acceptance of Concrete Supplier as described in Quality Assurance<br />

paragraph.<br />

J. Product Data: Submit certified laboratory test data or manufacturer’s certificates and data for the items listed<br />

below certifying that materials are in conformance requirements specified herein. Submit to the Architect of<br />

Record and the CTL within 5 working days of Contract Date.<br />

K. Soft Preformed Joint Filler:<br />

1. Pavement joint sealant.<br />

2. Dowel bars.<br />

3. Reinforcing bars.<br />

4. Welded wire fabric.<br />

5. Waterstops.<br />

L. Pavement Joint and Placement Plan: Provide a placement plan identifying the following:<br />

1. Concrete truck access location.<br />

2. Extent of placements including width, length, slab placement area and volume.<br />

3. Locations of construction joints.<br />

4. Location of sawn contraction joints if different from those shown on the civil drawings.<br />

M. Pre-Slab Installation Meeting Documents:<br />

1. Record of Notification of Pre-slab Meeting including company name, persons contacted, and date and<br />

method of contact.<br />

2. Provide Meeting Minutes including attendance record to all participants and Wal-Mart Construction<br />

Manager.<br />

N. Delivery Tickets:<br />

1. Copies of delivery tickets for each load of concrete delivered to site.<br />

2. Indicate information required by ASTM C 94 on each ticket including additional information required for<br />

slabs.<br />

3. Information on ticket shall include quantities of material batched including the amount of free water in the<br />

aggregate and the quantity of water that can be added at the site without exceeding the maximum water<br />

cementitious ratio of the approved mix design. Aggregate moisture corrections shall be based on ASTM<br />

definitions of aggregate moisture content and absorption.<br />

4. Mix identification number on ticket shall match number on submitted and approved mix design.<br />

5. Submit copies to CTL with each concrete delivery.<br />

O. Installation Certification: Submit certification in writing that final placement is in accordance with specified<br />

requirements.<br />

1.5 QUALITY ASSURANCE<br />

A. Codes and Standards: Comply with ACI 301, ACI 318, and CRSI Manual of Standard Practice provisions except<br />

where more stringent requirements are shown or specified:<br />

B. Pumped Concrete:<br />

1. Perform mix design, proportioning, and placement in accordance with ACI 304.2R.<br />

2. Submit documented evidence of experience in placing concrete by pumping on not less than three projects<br />

of similar size and complexity. List available pump size, standby pump size, piping, and other equipment.<br />

3. Submit documented evidence of concrete supplier's ability to dedicate sufficient mixing and delivery<br />

equipment to supply the concrete continuously for the volumes to be placed by pumping.<br />

03310 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Chemical Admixtures: Accelerating and retarding admixtures may be used only when adverse weather conditions<br />

are anticipated. Use of admixtures is subject to Wal-Mart approval.<br />

1. Provide Wal-Mart Construction Manager with proposed Construction Schedule identifying anticipated<br />

adverse weather conditions justifying use of admixtures.<br />

2. Mix design shall indicate ingredients including the admixtures to be used and the slump and air content<br />

range for the project.<br />

D. Concrete Truck Inspection:<br />

1. Conform to ASTM C 94, NRMCA, and Department of Transportation standards in state where project is<br />

located with respect to truck mixer requirements.<br />

2. Perform inspections immediately before starting concreting operations.<br />

3. Record the identification numbers of those trucks found to be acceptable on the basis of inspections.<br />

4. Do not bring on site for concreting operations, any truck whose identification numbers are not recorded as<br />

acceptable. Notify CTL if non-conforming trucks are used to deliver concrete for slabs and pavements.<br />

E. Concrete Supplier Approval: Concrete Supplier and materials provided shall be fully approved by and acceptable<br />

to Concrete Subcontractor as the producer of concrete which Subcontractor is to place and finish. Prepare<br />

Statement of Approval of Concrete Supplier stating project name, name of concrete supplier, along with the<br />

statement of approval and the signatures of Contractor and Concrete Pavement Subcontractor. Submit statement<br />

as specified in Submittals paragraph.<br />

1.6 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Deliver materials in unopened containers with labels identifying contents. Keep containers closed and upright to<br />

prevent leakage.<br />

C. Mark reinforcing, accessories and embedded items for proper identification and placement location.<br />

D. Store materials, except aggregate, off ground in dry area and in manner to prevent damage. Protect liquid<br />

materials from freezing.<br />

E. Stockpile aggregate in manner to prevent contamination with other materials or with other sizes of aggregates. Do<br />

not use bottom 6 inches of aggregate piles in contact with ground. Allow sand to drain until it has reached a<br />

uniform moisture content before it is used.<br />

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.<br />

G. Store admixtures in manner to prevent contamination. Protect admixtures from extreme temperatures which<br />

would adversely affect their characteristics.<br />

1.7 ENVIRONMENTAL REQUIREMENTS<br />

A. Hot and cold weather concreting shall be in accordance with ACI 305.1 (hot weather) and 306.1 (cold weather).<br />

B. Concreting in Hot, Dry, or Windy Weather:<br />

1. Determine rate of evaporation in accordance with ACI 305.1.<br />

03310 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Employ precautions as required to protect fresh concrete before and during finishing when the concrete rate<br />

of evaporation exceeds 0.1 pounds per square foot per hour or when any combination of concrete materials<br />

and weather conditions are favorable for the formation of plastic shrinkage cracks.<br />

a. Cool ingredients before mixing to reduce concrete temperature at time of placement. Mixing water<br />

may be chilled, or chopped ice may be used to control the concrete temperature provided the water<br />

equivalent of the ice is calculated to the total amount of mixing water.<br />

b. Dampen subgrade and forms.<br />

c. Cover reinforcing steel with water soaked burlap so the steel temperature will not exceed the<br />

ambient air temperature immediately before embedment in concrete.<br />

3. Maintain an accurate reading thermometer at the Site to check temperature of concrete.<br />

4. Temperature of concrete at time of placing: Not to exceed 95 degrees F.<br />

5. Reject concrete if more than one slump adjustment, as defined in ASTM C 94, is required.<br />

6. Do not place concrete when forms, subgrade, aggregate base, or reinforcing bars are more than 120 degrees<br />

F or the temperature differential between the forms, aggregate base, or reinforcing bars and concrete will<br />

create conditions favorable for settlement cracks or thermal cracking.<br />

7. When high temperature and placing conditions dictate, the concrete supplier may request use of waterreducing<br />

retarding admixture (Type D) in lieu of water-reducing admixture (Type A), subject to approval<br />

from the Wal-Mart Construction Manager.<br />

C. Concreting in Cold Weather:<br />

1. Thaw subgrade to depth of 12 inches immediately before placing concrete.<br />

2. Measure and record concrete temperature during protection period in each placement at regular time<br />

intervals, but not less than 3 times per 24 hour period.<br />

3. Minimum temperature requirements for concrete delivered to Site:<br />

a. Air Temperature 30 to 45 degrees F: Concrete temperature 60 degrees F minimum.<br />

b. Air Temperature 0 to 30 degrees F: Concrete temperature 65 degrees F minimum.<br />

c. Air Temperature below 0 degrees F: Concrete temperature 70 degrees F minimum.<br />

d. Maximum Concrete Temperature: Not to exceed the minimum required temperature by more than<br />

10 degrees F.<br />

4. Do not place slabs on subgrade or base that is more than 20 degrees F cooler than concrete. Warm<br />

subgrade or base to decrease temperature differential to 20 degrees F or less.<br />

5. When temperatures of 40 degrees F or lower occur during the placing and curing of concrete, maintain<br />

temperature of concrete at not less than 50 degrees F for at least 7 days for conventional concrete or at least<br />

3 days for high early strength concrete.<br />

a. Make arrangements before placement to maintain required temperature without damage from<br />

excessive heat.<br />

b. Do not use combustion heaters during first 48 hours without precautions to prevent exposure of<br />

concrete to exhaust gases containing carbon dioxide and carbon monoxide.<br />

c. Provide temporary housings or coverings including tarpaulins or plastic film. Keep protection in<br />

place and intact at least 24 hours after artificial heat is discontinued. Avoid rapid drying of concrete<br />

due to overheating, and avoid thermal shock due to sudden cooling or heating.<br />

6. Protect concrete work from physical damage or reduced strength which could be caused by frost, freezing<br />

actions, or low temperatures, in compliance with the requirements of ACI 306R and 306.1 and as specified<br />

in this Section.<br />

7. Do not use frozen materials containing ice or snow. Do not place concrete on frozen subgrade or on<br />

subgrade containing frozen materials. Verify that forms, reinforcing steel, and adjacent concrete surfaces<br />

are free of frost, snow, and ice and that temperature of these materials is above 32 degrees F before placing<br />

concrete.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with project requirements, provide products as manufactured by the following to the extent<br />

as specified hereinafter for the specific product:<br />

1. Ardex Engineered Cements, Aliquippa, PA (888) 512-7339. Contact: Ben Mack.<br />

2. BASF Admixtures, Inc., Cleveland, OH (800) 628-9990.<br />

03310 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. BASF Building Systems, Shakopee, MN (800) 433-9517.<br />

4. Chase Construction Products, Bridgwater, MA 508-341-4961.<br />

5. Colloid Environmental Technologies Co. (CETCO), Hoffman Estates, IL (800) 527-9948.<br />

6. Dayton Superior/Conspec, Dayton, OH (888) 977-9600.<br />

7. Euclid Chemical Co., Cleveland, OH (800) 321-7628.<br />

8. Henry Company (Synko-Flex Products Division) (800) 231-4551.<br />

9. Master Builders, Inc.: See BASF Admixtures.<br />

10. Sika Corp., (800) 933-7452.<br />

11. Sonneborn Building Products: See BASF Building Products.<br />

12. Thoro System Products: See BASF Building Products.<br />

13. Unitex, Kansas City, MO (816) 231-7700 or (800) 821-5846.<br />

14. W.R. Grace and Co., (713) 223-8353.<br />

15. Vexcon Chemicals, Inc., Philadelphia, PA (888) 839-2661.<br />

B. Substitutions: Comply with the requirements of Section 01600 unless specified otherwise in this Section.<br />

2.2 AGGREGATE BASE MATERIALS<br />

A. Exterior pavement areas shown on the Drawings referencing the “Foundation Subsurface Preparation” for base<br />

preparation shall receive aggregate base materials as specified herein unless otherwise shown on the Foundation<br />

Subsurface Preparation.<br />

B. Aggregate Base: Use one of the following gradations:<br />

1. Any state DOT approved road base material meeting the following gradation:<br />

Standard Sieve Size<br />

% Passing<br />

No. 1-1/2 100<br />

No. 4 15-55<br />

No. 200 5-12<br />

2. Material conforming to the General Requirements and of the Gradation “A”, ”C”, or “D” requirements<br />

(with the modified allowance of 5% to 12% passing the No. 200 sieve) as defined by ASTM D 1241.<br />

3. Material passing the No. 200 shall be clean granular fill with less than 3% clay and/or friable particles.<br />

C. Aggregate Choker Course: Clean granular fill with less than 3% clay and/or friable particles. Use one of the<br />

following gradations:<br />

1. ASTM D 448 No. 10 with 6% to 12% passing No. 200 sieve.<br />

2. Material that meets the following gradation:<br />

Standard Sieve Size<br />

% Passing<br />

No. 4 85-100<br />

No. 8 75-95<br />

No. 16 55-75<br />

No. 50 22-45<br />

No. 100 10-30<br />

No. 200 6-12<br />

D. Refer to Section 02715 for base materials not subject to the Foundation Subsurface Preparation requirements.<br />

03310 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.3 FORMWORK<br />

A. Forms: Design, engineer, and construct forms, shores, bracing, and other temporary supports to support loads<br />

imposed during construction in accordance with ACI 347. Design under the direct supervision of a licensed<br />

Professional Engineer experienced in design of this Work.<br />

1. Plywood: APA Plyform Class 1, complying with DOC PS 1, exterior-grade plywood panels, suitable for<br />

concrete forms, 5/8 inch minimum thickness unless otherwise shown or specified, and as follows:<br />

a. Plywood For Concrete Surfaces Not To Be Exposed After Construction Is Complete: APA B-B<br />

Plyform.<br />

b. Plywood For Concrete Surfaces To Be Exposed After Construction Is Complete: APA HDO (High<br />

Density Overlay) Plyform, with straight, sealed edges.<br />

2. Lumber: Dressed, tongue and grooved, free from loose knots.<br />

3. Metal: Smooth, clean, corrosion-free, without dents or holes and with closely-matching edges.<br />

4. Fiberglass: Smooth, clean, without dents or holes and with closely-matching edges.<br />

5. Laminated Round Fiber Tubes: Spirally laminated paper fiber, wax impregnated on exterior surfaces and<br />

interior ply allowing uniform moisture penetration.<br />

B. Form Release Agent:<br />

1. 100% biodegradable, non-toxic, 100% natural organic chemical release agent. Will not cause surface<br />

imperfections, non-staining, and compatible with field applied paints, toppings, curing compounds, and<br />

other coatings. Use same brand form release agent for all forms. Provide one of the following:<br />

a. Form-EZE Natural by Euclid.<br />

b. Bio-Release EF by Dayton Superior.<br />

c. Star Seal EF V Release by Vexcon.<br />

d. Farm Fresh by Unitex.<br />

e. Reaxion WB by SpecChem.<br />

C. Form Ties and Accessories:<br />

1. Provide form ties, anchors, and hangers of sufficient strength to resist displacement of forms due to<br />

construction loads and depositing of concrete.<br />

2. Provide ties and spreader form ties designed so no metal will be within 1 inch of surface when forms are<br />

removed.<br />

3. Where concrete surfaces are exposed to view, use form ties that will leave a depression not more than 1<br />

inch in diameter when removed.<br />

D. Waterstops: Provide one of the following.<br />

1. Volclay Waterstop RX-101 Bentonite Waterstop by CETCO (Colloid Environmental Technologies Co.).<br />

2. SF302-Synko-Flex Waterstop by Henry Co.<br />

2.4 REINFORCEMENT<br />

A. Reinforcing Bars:<br />

1. ASTM A 615, deformed, Grade 60.<br />

2. ASTM A 706, deformed, Grade 60.<br />

B. Joint Dowel Bars: ASTM A 615, grade 40 minimum, or ASTM A 36, smooth round plain steel bars, cut bars true<br />

to length with ends square and free of burrs. Epoxy coat per State Highway Department Standard Specifications.<br />

C. Welded Wire Mesh: Welded plain cold-drawn steel wire fabric, ASTM A 185. Furnish in flat sheets.<br />

2.5 REINFORCEMENT ACCESSORY MATERIALS<br />

A. Tie Wire: Minimum 16 gage annealed type.<br />

B. Reinforcing Support Devices:<br />

1. Manufactured support devices of metal (wire bar), concrete, or recycled plastic devices conforming to<br />

CRSI Manual of Standard Practice.<br />

03310 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Precast concrete bar supports shall have minimum compressive strength of 3500 psi.<br />

3. Plastic accessories shall have a minimum of 50% recycled content.<br />

4. Do not use wood, clay brick, and other devices that can expand due to moisture gain.<br />

5. For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1<br />

plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.<br />

6. When precast concrete bar supports are used over aggregate base, or over waterproof membranes and<br />

vapor retarders, properly embed tie wires to prevent penetration of substrate.<br />

7. Properly size foot of bar supports or similar devices to prevent settlement on base material or prevent<br />

puncture on vapor barrier.<br />

8. When supporting multiple layers of reinforcement, provide the proper size and spacing of bar supports or<br />

similar devices to prevent deformation of plastic and to retain rebar within position tolerances.<br />

2.6 CONCRETE MATERIALS<br />

A. Cement: ASTM C 150 – Type I. If reactive aggregates are present in the area, use low alkali cement containing<br />

less than 0.6 percent alkalis. Use only one brand throughout project.<br />

B. Concrete Aggregate:<br />

1. Conform to ASTM C 33.<br />

2. Aggregate shall contain no coal or lignite in concrete that will not be covered by soil.<br />

3. Fine Aggregate:<br />

a. Conform to fine aggregate grading requirements as defined in Section 6.1 of ASTM C 33 unless<br />

approved by the SER.<br />

b. If manufactured fine aggregate is used, blend with minimum 25% natural materials unless otherwise<br />

approved by the SER.<br />

4. Coarse Aggregate:<br />

a. Nominal maximum coarse aggregate size shall be 1 inch for slabs ≤ 5-1/2 inch thick.<br />

b. The nominal maximum size of an aggregate is the smallest sieve size through which the major<br />

portion of the aggregate must pass, with a minimal amount retained on the maximum sieve size.<br />

Maximum 4% shall be retained on the nominal maximum size sieve.<br />

5. Adjust proportions of combined coarse, intermediate, and fine aggregates to provide the following particle<br />

size distribution characteristics, unless otherwise approved:<br />

a. Coarseness Factor of 60 to 75%.<br />

1) The Coarseness Factor (CF) is the percent of combined aggregate retained on the #8 sieve<br />

that is also retained on the 3/8 inch sieve.<br />

2) The Coarseness Factor is calculated as follows:<br />

CF = Aggregate retained on 3/8 inch sieve / Aggregate retained on #8 sieve.<br />

b. Adjusted Workability Factor.<br />

1) The Workability Factor (WF) is the percent of combined aggregate that passes the #8 sieve.<br />

2) The Adjusted Workability Factor (Adj-WF) is calculated as follows:<br />

Adj-WF = WF+[(Cementitious Material -564 lbs)/37.6].<br />

3) The range of accepted Adj-WF for a given CF is as follows:<br />

Adj-WF = [(11.25 - .15 CF) + 36] ± 2.5.<br />

4) Combined percent retained on any given sieve size shall not exceed 24%.<br />

6. Aggregate gradation requirements of ASTM C 33 may be waived in order to meet ranges specified.<br />

C. Fly Ash: ASTM C 618, Class C or F. Use only one type and source throughout project.<br />

D. Slag: ASTM C 989, Grade 100 or 120. Use only one type and source throughout project.<br />

E. Water: Clean potable water, not detrimental to concrete.<br />

2.7 CHEMICAL ADMIXTURES<br />

A. Air Entrainment: ASTM C 260.<br />

1. Air-Mix or AEA-92 by Euclid.<br />

2. MB-VR, MB-AE 90, or Micro-Air by BASF.<br />

03310 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Daravair or Darex Series by W.R. Grace.<br />

4. Sika Air Series or AEA Series by Sika.<br />

5. Equivalent approved products.<br />

B. Water Reducing Admixture: ASTM C494, Type A.<br />

1. Eucon or Plastol Series by Euclid.<br />

2. Pozzolith, PolyHeed or Glemium Series by BASF Admixtures.<br />

3. WRDA, Daracem, Mira, Zyla or Adva Series by W.R. Grace.<br />

4. Plastiment, Plastocrete, or Sikament Series by Sika Corp.<br />

5. Equivalent approved products.<br />

C. Water Reducing and Retarding Admixture: ASTM C494, Type B or D.<br />

1. Eucon Retarder 75 by Euclid.<br />

2. Pozzolith Series or Delvo by BASF Admixtures.<br />

3. Recover or Daratard 17 by W.R. Grace.<br />

4. Plastiment or Plastocrete Series by Sika Corp.<br />

5. Equivalent approved products.<br />

D. Accelerating Admixture: ASTM C494, Type C or E.<br />

1. Accelguard 80 by Euclid.<br />

2. Daraset Series, Daracel, Lubricon, Polarset, or DCI by W.R. Grace.<br />

3. Pozzolith or Pozzutec Series by BASF Admixtures.<br />

4. Plastocrete 161 FL, Plastocrete 161 HE, Sikaset NC, or Sikaset HE by Sika Corp.<br />

5. Calcium Chloride (Type L) in solution form.<br />

6. Equivalent approved products.<br />

E. Evaporation Retardant: Water-based polymer, sprayable.<br />

1. EucoBar by Euclid.<br />

2. Confilm by BASF Admixtures.<br />

3. Conspec Aquafilm by Dayton Superior.<br />

F. High-Range Water Reducing Admixture: ASTM C 494, Type F or G.<br />

1. Type F:<br />

a. Eucon 37 by Euclid.<br />

b. Daracem 100 by W.R. Grace.<br />

c. Rheobuild 1000 or Glenium Series by BASF.<br />

d. ViscoCrete, Sikament, or Sikaplast by Sika.<br />

e. Equivalent approved products.<br />

2. Type G:<br />

a. Eucon 537, by Euclid.<br />

b. Daracem 100 by W.R. Grace.<br />

c. Rheobuild 716 by BASF.<br />

d. Equivalent approved products.<br />

2.8 RELATED MATERIALS<br />

A. Joint Materials: Specified in Section 07900.<br />

B. Epoxy Bonding Agent: ASTM C 881.<br />

1. Euco #452 by Euclid.<br />

2. EVA-POX Epoxy Paste No. 22 by Chase Construction Products.<br />

3. Concresive Liquid LPL by BASF Admixtures.<br />

4. Sikadur 32 Hi-Mod LPL by Sika.<br />

C. Bond Breaker: ASTM D 226, No. 15, unperforated asphalt saturated felt.<br />

03310 - 11<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Patching Mortar:<br />

1. FDM by Ardex for vertical or horizontal placement, formed and poured.<br />

2. B20 by Ardex for vertical or overhead placement, hand packed.<br />

3. ERM by Ardex for exterior horizontal applications.<br />

4. Approved equivalent products.<br />

E. Concrete Sealer: Solvent based concrete sealer low VOC (


3. Air Entrainment shall be as follows:<br />

Nominal<br />

Maximum Size<br />

Average Air Content (%) +/- 1.5%<br />

By Exposure Classification<br />

Aggregate (Inch) Negligible Moderate Severe<br />

3/8 4.5 6.0 7.5<br />

1/2 4.0 5.5 7.0<br />

3/4 3.5 5.0 6.0<br />

1 3.0 4.5 6.0<br />

1-1/2 2.5 4.5 5.5<br />

D. Interior Concrete and Exterior Structural Concrete:<br />

1. Compressive Strength: Strength at 28 days shall be 3000 psi unless otherwise shown or specified.<br />

2. Maximum Water-Cementitious Material Ratio (Cement Quantity Includes Fly Ash or slag):<br />

a. Exterior Structural Concrete: 0.50 by wt.<br />

b. Interior Concrete: 0.55 by wt.<br />

3. Slump: Slump at the point of placement shall not exceed 5 inches subject to the requirement that concrete<br />

shall be of a consistency to be worked readily into forms and around reinforcement without segregation,<br />

voids, or excessive bleeding. Maximum slump variance shall be 2 inches.<br />

4. Air Content: As listed below plus or minus 1.5 percent.<br />

a. For Concrete Exposed to Weather:<br />

1) Negligible Exposure: 4.0 percent.<br />

2) Moderate Exposure: 5.0 percent.<br />

3) Severe Exposure: 6.0 percent.<br />

b. For Concrete Not Exposed to Weather: Not to exceed 5.0 percent.<br />

5. Concrete to be Placed by Pumping Methods:<br />

a. The minimum quantity of constituent materials passing the No. 50 sieve (fine aggregate and<br />

cementitious materials) shall be 600 pounds per cubic yard.<br />

b. The particle size distribution of the combined fine and coarse aggregate shall be uniform from the<br />

largest to the smallest particles.<br />

E. Admixtures:<br />

1. Use water-reducing admixture in concrete as required for placement and workability. Unless otherwise<br />

permitted herein, chemical admixtures shall be dispensed at the batch plant.<br />

2. Use air-entraining admixture in exterior concrete exposed to weather. Add air-entraining admixture at<br />

manufacturer's prescribed rate to result in concrete at point of placement having total air content specified<br />

above.<br />

3. Use admixtures for water reduction and set control (accelerators and retarders) in strict compliance with<br />

manufacturer's directions.<br />

4. Verify with the admixture manufacturer the following:<br />

a. The compatibility of the individual admixtures when combined in the concrete mix.<br />

b. The compatibility of the individual admixtures with the concrete materials.<br />

c. The compatibility of the individual admixtures with the coloring admixture.<br />

F. Supplementary Cementitious Materials (SCM):<br />

1. Concrete mix shall contain SCM at the amounts specified unless other amounts are approved by SER.<br />

Either fly ash or ground granulated blast furnace slag (GGBFS) may be used for the SCM but shall not be<br />

used together to form a ternary mix. Use of fly ash or GGBFS in the concrete mix is mandatory.<br />

2. Fly Ash: Substitute fly ash for Portland cement at 20% of the total cementitious content.<br />

a. If used to mitigate potential aggregate reactivity, only Type F fly ash may be used and shall have the<br />

following maximum properties: 1.5% available alkali and 8.0% CaO. When a maximum of 30%<br />

replacement is used, up to 10.0% CaO is permitted.<br />

3. Ground Granulated Blast Furnace Slag (GGBFS): Substitute GGBFS for Portland cement at 25% of the<br />

total cementitious content. If required to mitigate potential sulfate exposure or aggregate reactivity, up to<br />

50% GGBFS substitution for Portland cement may be used.<br />

4. Maintain air-entrainment at specified levels.<br />

03310 - 13<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. In cold weather, provide adequate concrete strength gain so concrete will not be damaged from traffic and<br />

loads of use.<br />

G. Calcium Chloride Admixture:<br />

1. Calcium chloride (Type L) conforming to ASTM D 98 may be used in solution form as part of the mixing<br />

water to accelerate concrete setting and early-strength development.<br />

2. Amount of calcium chloride added shall not be more than necessary to produce the desired results and shall<br />

not exceed 2% by weight of cement.<br />

3. The dosage range for the calcium chloride for the entire project shall not vary by more than 1%. Range is<br />

defined as the difference between the maximum and minimum dosages of calcium chloride for the entire<br />

project.<br />

4. Calcium chloride shall not be used in the following applications unless approved by SER:<br />

a. Concrete containing embedded dissimilar metals or aluminum.<br />

b. Slabs supported on permanent galvanized steel forms.<br />

c. Concrete exposed to deicing chemicals.<br />

d. Prestressed or post-tensioned concrete.<br />

e. Concrete containing aggregates with potentially deleterious reactivity.<br />

f. Concrete exposed to soil or water containing sulfates.<br />

5. Use calcium chloride in accordance with manufacturer’s recommendation.<br />

6. Chloride-ion Concentration: Maximum water-soluble chloride-ion concentrations in hardened concrete at<br />

ages from 28 to 42 days contributed from the ingredients including water, aggregates, cementitious<br />

materials, and admixtures shall not exceed the following limits unless approved by SER:<br />

Maximum water-soluble chloride ion (Cl-) content in<br />

Type of Member<br />

concrete<br />

(percent by weight of cement)<br />

Prestressed Concrete .06<br />

Reinforced concrete exposed to chloride<br />

in service<br />

Reinforced concrete that will be dry or<br />

protected from moisture in service<br />

.15<br />

1.00<br />

Other reinforced concrete construction .30<br />

2.11 MIXING<br />

7. When using calcium chloride or other admixtures containing chlorides, measure water-soluble chloride-ion<br />

content (percent by weight of cementitious materials) per ASTM C 1218. Sample shall be from concrete<br />

representing the submitted mix design and maximum chloride dosage anticipated for the project.<br />

A. Ready-Mixed Concrete:<br />

1. Mix and transport in accordance with ASTM C 94 and ACI 301 except as specified.<br />

2. Reset drum revolution counter to zero on concrete truck when water is added to drum.<br />

B. Site-Mixed Concrete:<br />

1. Conform to ACI 301.<br />

2. Use central-mix type batch plant.<br />

C. Proportion concrete materials on basis of field experience or by laboratory trial batches in accordance with ACI<br />

318.<br />

D. Ready-mix concrete supplier may proportion materials by field experience, per ACI 318.<br />

E. Proportioning by Water-Cement ratio per ACI 318 is not acceptable.<br />

03310 - 14<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify anchors, seats, plates, reinforcement, and other items to be cast into concrete are accurately placed, held<br />

securely, and will not cause hardship in placing concrete.<br />

3.2 PREPARATION<br />

A. Prepare previously placed concrete by cleaning with steel brush and applying bonding agent. Apply bonding<br />

agent in accordance with manufacturer's instructions.<br />

B. Preplacement Inspection: All trades and participants involved shall verify that preparations are in conformance<br />

with Contract Documents. Inspect reinforcement, inserts, and embedded parts before beginning concrete<br />

placement to ensure accurate size and location. Use approved sign-off forms.<br />

C. Notify CTL minimum 48 hours prior to commencement of concreting operations.<br />

D. Cleaning Equipment: Remove hardened concrete and foreign materials from mixing and conveying equipment.<br />

E. Ensure that all work is properly coordinated:<br />

1. Structural Drawings and Specifications with those of other disciplines.<br />

2. Use final corrected submittals.<br />

3.3 INSTALLATION - GENERAL<br />

A. Establish and maintain required lines and elevations.<br />

B. Check surface areas at intervals necessary to eliminate ponding areas.<br />

3.4 AGGREGATE BASE PLACEMENT<br />

A. Where exterior pavement areas are shown on the Drawings referencing the “Foundation Subsurface Preparation”<br />

for base preparation, place aggregate base in accordance with requirements herein.<br />

B. Aggregate Base:<br />

1. Install aggregate base where shown on Drawings.<br />

2. Compact to final thickness shown on the Drawings in layers not exceeding 6 inches with minimum of 2<br />

passes per layer with vibratory compactor.<br />

3. Compact fill to 98% of aggregate’s Standard Proctor as determined by Method D of ASTM D 698.<br />

4. Leave pad up to 2 inches low until just prior to concrete placement.<br />

C. Aggregate Base Fine Grading:<br />

1. Compact to final thickness noted with 2 passes minimum vibratory compactor to produce smooth, flat,<br />

dense surface.<br />

2. Aggregate choker course shall be placed dry immediately before placing concrete.<br />

3. Do not allow excess moisture or soft soil beneath vapor retarder at time of placing concrete.<br />

4. Thickness shall not exceed 2 inches.<br />

5. Level off aggregate base top surface with aggregate choker course material as necessary as follows:<br />

a. To reduce surface friction and to meet specified fine grade tolerances specified below. Typically<br />

required up to 3/4 inch thick in areas exposed to rain, traffic, or excavation for pits and buried<br />

utilities.<br />

b. Where aggregate base material does not have sufficient fine particles to produce a surface that is<br />

free of exposed aggregate or surface voids greater than 3/8 inch in size at time of slab installation.<br />

6. Use laser guided equipment used to establish specified base elevation.<br />

7. Provide dry, smooth, flat, dense surface. Take corrective action if rutting or pumping is evident during the<br />

preparation of the soil support system.<br />

03310 - 15<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


8. Proofroll 48 hrs maximum prior to concrete placement. Depression under a fully loaded concrete truck<br />

shall not exceed 1/2 inch.<br />

D. Pavement Aggregate Base Fine Grade Tolerance: +0 inch, -3/4 inch with transition no greater than 3/4 inch<br />

vertically to 8 inches horizontally for level slab.<br />

3.5 FORMWORK<br />

A. Form vertical surfaces of concrete work.<br />

B. Design, construct, erect, support, and remove formwork and related items in accordance with most stringent<br />

requirements of ACI 117, 301, 304R, 318 and 347R.<br />

1. Camber forms to allow for deflection due to weight of fresh concrete.<br />

C. Formwork for concrete surfaces to be painted or exposed to view after completion of project shall conform to the<br />

following:<br />

1. Do not use forms with dents, holes or patches.<br />

2. Individual formwork elements shall be as large as possible.<br />

3. Position individual formwork elements in regular, uniform pattern with joints aligned.<br />

4. Uniformly space and align form ties in horizontal and vertical rows.<br />

5. Construct forms for removal without hammering or prying against concrete.<br />

6. Temporary formwork openings (for cleaning, inspecting, etc.) shall be placed on unexposed side or<br />

constructed so that concrete surface at opening will match adjacent concrete in appearance.<br />

D. Form Preparation:<br />

1. Clean formwork.<br />

2. Remove rust from steel formwork.<br />

E. Erecting Forms:<br />

1. Solidly butt joints and provide backup at joints as required to prevent leakage of cement paste.<br />

2. Do not tape formwork joints.<br />

3. Just before placing concrete, clean forms and adjacent surfaces again as necessary. Remove wood,<br />

sawdust, chips dirt and other debris.<br />

4. If necessary to grease tie threads, do not allow grease to contact remainder of tie when wall will be exposed<br />

to hydrostatic pressure.<br />

F. Form Release Agent:<br />

1. Before placing reinforcing steel, thoroughly coat contact surfaces of forms with form release agent.<br />

2. Apply form release agent evenly without excess drip.<br />

3. Do not allow form release agent to come into contact with concrete surfaces against which fresh concrete<br />

will be placed.<br />

4. Moisten wood forms immediately before placing concrete where form release agents are not used.<br />

G. Form Construction for Paving:<br />

1. Set forms to required grades and lines, rigidly braced and secured.<br />

2. Install sufficient quantity of forms to allow continuance of work and so that forms remain in place<br />

minimum of 24 hours after concrete placement.<br />

3. Check completed formwork for grade and alignment to following tolerances:<br />

a. Top of forms not more than 1/8-inch in 10 feet.<br />

b. Vertical face on longitudinal axis, not more than 1/4-inch in 10 feet.<br />

4. Clean forms after each use and coat with form release agent as often as required to ensure separation from<br />

concrete without damage.<br />

3.6 PLACING REINFORCEMENT<br />

A. Place reinforcing in accordance with ACI 117, ACI 301, ACI 308, and CRSI Manual of Standard Practice and<br />

Placing Reinforcing Bars.<br />

03310 - 16<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Accurately place and secure reinforcement against displacement by firmly wiring at intersections and splices.<br />

C. Perform concrete reinforcement work in accordance with CRSI Manual of Standard Practice, Documents 63 and<br />

65. Detailing practices and fabrication shall conform to ACI SP66.<br />

1. Place and secure saddle ties at every other intersection with wire; hold in place with metal chairs or spacers<br />

during placing of concrete.<br />

2. Hold bars in beams and slabs to exact location during concrete placement. Use spacers, chairs, or other<br />

necessary supports with the following tolerances:<br />

a. Bars in Slabs and Beams:<br />

1) Members 8 Inches Deep or Less: ± 1/4 inch.<br />

2) Members 8 Inches to 2 Feet Deep: ± 1/2 inch.<br />

3) Members more than 2 Feet Deep: ± 1 inch.<br />

b. Lengthwise of Member: ± 2 inches.<br />

c. Concrete Cover to Formed Surfaces: ± 1/4 inch.<br />

d. Minimum Spacing Between Bars: ± 1/4 inch.<br />

D. Turn wire ends away from concrete exterior.<br />

E. Ensure reinforcing is clean, free from defects and kinks, loose mill or rust scale or coatings that will reduce bond.<br />

F. Protect exposed reinforcing bars, inserts and plates intended for bonding with future expansion from corrosion.<br />

G. When welding of reinforcement is specified, comply with AWS D1.4. Do not tack weld crossing bars for<br />

assembly of reinforcement, supports or embedded items.<br />

H. Exterior Slab on Ground and Pavement Dowels:<br />

1. Install round smooth dowels within ± 1/4 inch alignment in vertical and horizontal planes.<br />

2. Secure dowels and sleeves perpendicular to joint and parallel to finished concrete surface.<br />

3. Use prefabricated dowel supports at ends of dowels to maintain alignment.<br />

4. Dowel alignment shall be within specified tolerances.<br />

5. Lightly grease round smooth dowels to prevent bond to concrete.<br />

6. Do not grease plate dowels.<br />

3.7 EMBEDMENTS<br />

A. Install anchor bolts and embedded bearing devices provided by others.<br />

B. Provide other anchor bolts and bearing devices shown on Drawings or anchor bolt setting plans or required<br />

equipment installation.<br />

C. Use templates as required for spacing between anchor bolts and set elevations with surveying equipment.<br />

D. Position and anchor steel shapes, anchor bolts, casings, conduit sleeves, masonry anchorages and other materials<br />

embedded in concrete.<br />

E. Place and secure against displacement miscellaneous steel, pipe sleeves, inserts, anchors, stair abrasive nosings,<br />

preformed joint filler, vapor retarders and miscellaneous embedded items.<br />

F. Secure embedments to formwork when possible.<br />

G. Install clean embedments. After concrete placement, clean embedment exposed surfaces of concrete splatter and<br />

other foreign substances.<br />

H. Unless noted otherwise on the Drawings, ensure corner protection angles, bars and other similar embedded metal<br />

items are continuous between concrete joints. If shorter lengths are required for metal items, connect the ends by<br />

butt-welding entire joint and grinding smooth exposed surface. Ensure embedded metal items are discontinued at<br />

construction, contraction and isolation joints.<br />

03310 - 17<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


I. Temporarily fill voids in sleeves and inserts with easily removable materials.<br />

J. Before placing concrete on grade, piping and other utilities under concrete shall be inspected, tested, and<br />

excavations backfilled and properly compacted to solid bearing.<br />

K. Allow sufficient time between erection of forms and placing concrete for other trades to install and test their work.<br />

3.8 JOINTS<br />

A. Joints:<br />

1. Provide construction, isolation and contraction joints as indicated on Drawings and as noted below.<br />

2. Bulkheads for construction joints shall be 1-1/2 inch minimum lumber. Do not use permanent preformed<br />

metal bulkheads.<br />

3. Provide bulkheads full depth of member.<br />

4. Space joints to allow one continuous placement between bulkheads.<br />

5. Unless otherwise shown on the Drawings, do not extend reinforcement, corner protection angles, bars or<br />

other fixed metal items through construction joints or contraction joints in slabs on ground or pavements or<br />

through joints between slabs on ground and vertical surfaces.<br />

6. Match joints in walls and curbs with joints in slabs on ground and pavements.<br />

7. Extend joints across tops of walls and curbs unless noted otherwise on Drawings.<br />

B. Pavement Joint Construction: Construct weakened-plane control (contraction), and construction joints straight<br />

with face perpendicular to concrete surface. Construct transverse joints perpendicular to centerline, unless<br />

otherwise detailed.<br />

1. Weakened-Plane Control or Contraction Joints: Provide joints at spacing of 12 feet on center, maximum<br />

each way. Construct control joints for depth equal to at least 1/4 of the concrete thickness, as follows:<br />

a. Form tooled joints in fresh concrete by grooving top with recommended tool and finishing edge<br />

with jointer.<br />

b. Sawed Contraction Joints:<br />

1) Use saws, blades, skid plates, and accessories by Soff-Cut International, Inc., Memphis, TN,<br />

(901)368-3753, or approved equal.<br />

2) Start cutting sawed joints as soon as concrete has hardened sufficiently to prevent raveling or<br />

dislodging of aggregates. This will typically be from 1 hour in hot weather to 4 hours in cold<br />

weather after completing finishing of slab in that joint location.<br />

3) Provide at least two Soff-Cut saws on site with blades capable of achieving the required<br />

depth of saw cut.<br />

4) Extend sawed joint to the slab boundaries and abutments, including columns, drains, and<br />

other penetrations in the path of a defined joint. Implement methods and timing of the saw<br />

cut beyond the limits of the Soff-Cut saw reach to provide a consistent depth of cut with<br />

minimal raveling of joint edges.<br />

2. Construction Joints: Place construction joints at end of placements and at locations where placement<br />

operations are stopped for period of more than 1/2 hour. Construct joints in accordance with details shown.<br />

C. Doweled Joints: Install dowel bars and support assemblies at joints as indicated. Make provision to prevent<br />

concrete bonding to one side of joint by methods shown on the Drawings.<br />

D. Joint filling and sealing is specified in Section 07900.<br />

3.9 CONVEYING<br />

A. Handle concrete from mixer to place of final deposit as rapidly as practicable and in manner which will assure<br />

obtaining specified quality of concrete.<br />

B. Retempering: Discard concrete which has already begun to set. Do not retemper with water.<br />

03310 - 18<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Equipment: Provide mixing and conveying equipment of proper size and design to ensure a continuous flow of<br />

concrete to delivery end. Do not use aluminum pipe or equipment in contact with concrete.<br />

1. Mixers, Agitators and Non-agitating Units: Conform to ASTM C 94 and current certification requirements<br />

of Department of Transportation in state where concrete plant is located.<br />

2. Belt Conveyers:<br />

a. Use only types which will not cause segregation.<br />

b. Discharge runs over 30 feet into hopper.<br />

3. Chutes: Metal or metal lined not to be installed at slopes greater than 1 vertical to 3 horizontal.<br />

4. Runways:<br />

a. Provide runways or other means above finished concrete level for wheeled conveying equipment.<br />

b. Do not support runways on reinforcing.<br />

c. Do not wheel equipment directly over reinforcing or metal deck.<br />

5. Pumps:<br />

a. Use pump hoses and other slickline components with 5 inch minimum inside diameter.<br />

b. For slickline reducers, reduction in diameter shall not exceed 1 inch over a 5 foot length.<br />

3.10 PLACING CONCRETE<br />

A. Place concrete in accordance with ACI 301.<br />

B. Inspect reinforcement, inserts, and embedded parts before beginning concrete placement to verify accurate size<br />

and location.<br />

C. Ensure reinforcement, inserts, embedded parts and formed joints are not disturbed during concrete placement.<br />

D. Place concrete in uniform layers, horizontal, 12 to 18 inches thick, exercising care to avoid vertical joints or<br />

inclined planes. Place concrete continuously between predetermined construction joints shown on structural<br />

drawings. Piling up of concrete in forms to cause separation or loss of ingredients is not permitted.<br />

E. Do not deposit concrete which has partially set or hardened. Do not deposit initial lubricating mortar when<br />

pumping concrete. Remove hardened or partially hardened concrete which has accumulated on forms or<br />

reinforcement. Do not place concrete on previously deposited concrete which has hardened sufficiently to cause<br />

formation of seams or planes of weakness within respective member or section except as specified.<br />

F. Deposit concrete as nearly in final position as practical to avoid rehandling. Exercise care to prevent splashing<br />

forms or reinforcing with concrete. Do not permit concrete to drop freely a distance greater than 3 feet. Where<br />

longer drops are necessary, use chute, tremie, or other conveyance to help avoid separation.<br />

G. Do not deposit concrete into excavation where water is standing. If place of deposit cannot be successfully<br />

pumped dry, place through tremie with outlet end near bottom of place of deposit.<br />

H. Do not deposit concrete when plasticity, measured by slump test, is outside specified limits. The addition of water<br />

to increase slump will not be permitted.<br />

I. Vibration: As soon as concrete is deposited, thoroughly agitate with mechanical vibrators and suitable hand tools<br />

to work mixture into corners of forms and around reinforcing and embedded items. Use mechanical vibrators<br />

with minimum frequency of 9000 revolutions/minute. Do not over vibrate or use vibrators to transport concrete<br />

within forms. Insert and withdraw vibrators at approximately 18 inches apart. At each insertion, vibrate generally<br />

5-15 seconds, sufficient to consolidate concrete but not long enough to cause segregation. Keep spare vibrator on<br />

job site during concrete placement operations. Do not insert vibrator into lower courses that have begun to set.<br />

J. Pumping: Maintain controls for proportioning, mixing, adjustment of mix, and placement in accordance with ACI<br />

301 and ACI 304.2R.<br />

03310 - 19<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.11 CONCRETE FINISHING<br />

A. Formed Surfaces:<br />

1. Rough-Form Finish:<br />

a. Patch tie holes and defects. Clip or rub off fins exceeding 1/2 inch in height. Leave surfaces with<br />

texture imparted by forms.<br />

b. Apply on concrete surfaces not exposed to public view and where noted on Drawings.<br />

2. Smooth-Form Finish:<br />

a. Patch tie holes and defects. Remove fins exceeding 1/8 inch in height.<br />

b. Apply on concrete surfaces exposed to public view and where noted on Drawings.<br />

B. Initial Finishing:<br />

1. Re-straighten surface irregularities with a 10 ft highway screed in two directions as close to perpendicular<br />

as possible before water appears on concrete surface.<br />

2. Do no further working of surface until time for floating; do not work surface while water is present.<br />

3. "Dry Sprinkle" method finishing is not acceptable and will be cause for rejection.<br />

C. Floating:<br />

1. Begin float operations when bleed water sheen has disappeared and concrete has stiffened sufficiently to<br />

allow walking on surface without leaving heel prints more than 1/4 inch deep. Check and level the surface<br />

lane to an initial tolerance not exceeding 1/4 inch in ten feet when tested with a ten foot straight edge.<br />

Immediately after leveling, refloat surface to a uniform smooth granular surface. Use magnesium or<br />

aluminum power float unless otherwise specified.<br />

2. Avoid premature finishing that brings excessive fines to surface causing finished slab to have soft surface<br />

which will dust.<br />

D. Troweling:<br />

1. Delay troweling as long as possible to prevent working excess fines and water to surface. Do not begin<br />

until surface moisture film and shine remaining after floating have disappeared. Trowel in alternate pass<br />

directions.<br />

2. Power trowel using riding trowel where possible. Use hand trowel in inaccessible areas.<br />

3. Do not over trowel floors scheduled to receive curing/sealing compound unless specified otherwise.<br />

4. Do not re-wet surface to trowel.<br />

5. Final hand finish passes shall be done in the same direction. Finish all surfaces within a reasonable time<br />

period to provide uniformity of appearance.<br />

E. Broom Finish:<br />

1. Provide a floated finish, then finish with broom.<br />

a. Heavy Boom Finish: Steel wire or stiff, coarse, fiber broom.<br />

b. Light Broom Finish: Soft-bristled fiber broom.<br />

2. Allow surface to harden sufficiently to retain scoring or ridges.<br />

3. Broom transverse to traffic or at right angles to slope of slab.<br />

F. Sealing: Apply concrete sealer to interior concrete curbs in cart storage area.<br />

G. Finish Schedule:<br />

1. Unexposed Exterior Formed Surfaces: Rough form finish.<br />

2. Exposed Exterior Formed Surfaces: Smooth form finish, stone rubbed.<br />

3. Equipment Pads: Troweled.<br />

4. Dock: Light Broom.<br />

5. Curbs: Troweled.<br />

6. Stair Treads: Heavy Broom.<br />

7. Sidewalks: Light broom.<br />

8. Ramps and Steps: Heavy broom.<br />

9. Exterior Garden Center Slab: Light broom.<br />

10. Exposed exterior slabs, unless otherwise noted in this Section or on Drawings: Light Broom Finish.<br />

03310 - 20<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.12 CURING<br />

A. General:<br />

1. Cure concrete in accordance with ACI 301, ACI 308R and ACI 308.1, except as noted.<br />

2. Start curing as soon as concrete surface will not be damaged by curing operations.<br />

3. Continuously cure concrete for at least 7 consecutive days.<br />

4. During curing period, do not allow any part of the concrete to become dry.<br />

5. If using forms for curing, keep forms in contact with concrete wet during curing period unless type of form<br />

is impervious to water, such as metal or fiberglass.<br />

6. If forms are removed before curing period is complete, continue curing immediately with other approved<br />

methods.<br />

B. Methods of Curing:<br />

1. Impervious Sheet Cure: Wet exposed surfaces of concrete after completing finishing and then apply<br />

prewetted sheet with edges lapped 6 inches minimum and sealed & secured in such manner as to prevent<br />

moisture from escaping from concrete from laps or edges. Remove sheets after 7 day curing period.<br />

2. Curing Compound:<br />

a. Apply curing compounds by spraying or rolling uniformly in a single coat on surfaces immediately<br />

following final finishing operation.<br />

b. Apply curing compound in accordance with manufacturer’s recommendations.<br />

c. Do not use curing compound on surface against which additional concrete, other finishing materials,<br />

or coatings are to be bonded if their bond will be affected by curing compound.<br />

d. Spraying shall be by power sprayer.<br />

e. Immediately recoat, at the rate specified above, surfaces subjected to rainfall within 3 hours after<br />

compound has been applied or surfaces damaged by subsequent construction operations within the<br />

curing period.<br />

f. Use solvent based curing compounds when compound is applied below 40 F.<br />

3. Curing Schedule:<br />

a. Unformed surfaces shall receive an impervious sheet cure or curing compound as appropriate except<br />

as follows:<br />

b. Use impervious sheet cure for exterior colored concrete surfaces.<br />

c. Protect and cure finished concrete paving using curing compound.<br />

3.13 FORM REMOVAL<br />

A. Do not remove forms until concrete has hardened sufficiently to support its own weight and imposed construction<br />

loads.<br />

B. Remove forms in manner to avoid damage to concrete.<br />

C. Formwork for slabs and pavements, curbs and other parts not supporting vertical load of concrete may be removed<br />

as soon as concrete has hardened sufficiently to resist damage from removal operations, but in no case sooner than<br />

12 hours.<br />

D. Remove wood forms from under floors, ramps, steps, and similar places (through temporary openings if<br />

necessary) so no material will be left to rot or to be infested by termites.<br />

3.14 TOLERANCES<br />

A. Conform to requirements of ACI 117 and ACI 301 except as specified herein.<br />

B. Conform to ACI 117 thickness tolerances for slabs-on-ground.<br />

3.15 QUALITY CONTROL BY OWNER<br />

A. Wal-Mart Construction Testing Laboratory (CTL) will perform concrete testing and inspection specified herein at<br />

no cost to the Contractor in accordance with Section 01458.<br />

03310 - 21<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. CTL is neither authorized to change any specified requirement nor to approve any portion of the work.<br />

C. Failure to detect defective material or Work will neither prevent rejection when defects are discovered later nor<br />

will it obligate Owner to make final acceptance.<br />

D. Responsibilities and Duties of Contractor Relative to Owner Testing:<br />

1. Notify CTL not less than 3 working days prior to placing concrete to allow time for observation of installed<br />

work.<br />

2. Assist CTL in securing field specimens.<br />

3. Provide and maintain for sole use of CTL, facilities for safe storage and proper curing of concrete test<br />

cylinders at project site as required by ASTM C 31 and acceptable to CTL.<br />

E. General:<br />

1. CTL will perform tests and inspections as specified in this Section and as indicated in Table A - Testing<br />

and Inspection Schedule, at the end of this Section. CTL will keep records of the testing and inspections.<br />

F. Qualifications: Unless otherwise specified, work shall be performed by a Special Inspector - Technical II or<br />

Special Inspector - Structural I. In addition to the Inspector and CTL qualifications specified in Section 01458,<br />

the following qualifications shall apply for all Cast-in-Place Concrete inspections.<br />

1. Technical I: ACI Certified Grade I inspector.<br />

2. Technical II: ACI Certified Grade II inspector.<br />

3. CTL: C.C.R.L. certification at the National Bureau of Standards (For multi-story projects only).<br />

4. Lead technician shall have at least five years experience in projects of this size and complexity.<br />

5. Other technicians shall have at least two years experience.<br />

G. Review the Contractor's proposed materials and mix design for conformance with specifications.<br />

H. Perform testing in accordance with ACI 301 and testing standards listed in this Section.<br />

I. Field Testing:<br />

1. At the start of each day's mixing, report any significant deviations from approved mix design including<br />

temperature, moisture and condition of aggregate.<br />

2. When pumping concrete, take samples for tests at point of delivery from pumping line in addition to first<br />

slump test noted above for concrete with mid-range or high-range water-reducer.<br />

3. Stockpile Sieve Analysis: During first day of concrete placement and later as directed by Wal-Mart<br />

Construction Manager, take concrete sample at point of final placement to verify mix design submittals.<br />

Washout sample to remove material finer than no. 200 sieve and perform combined sieve analysis, using<br />

sieve sizes specified herein, furnishing percent retained on each sieve. Concrete sample shall be large<br />

enough to be representative but is not less than 70 pounds. Conform to ASTM C 136. Tolerance for<br />

material retained on any 1 sieve shall be -3% and +4% of approved mix design for total combined coarse<br />

and fine aggregates except tolerance for material retained on 100 sieve shall be + or -2%.<br />

4. Determine concrete mix water content for first placement of slabs. This test is to be done first by the<br />

concrete supplier then at the project Site by the CTL.<br />

a. Conform to AASHTO T318.<br />

b. Sample size shall be a minimum of 2500g.<br />

c. Give verbal results as soon as possible but not later than end of same day.<br />

d. Submit written report by electronic means or hand deliver within 36 hours or next regularly<br />

scheduled working day after placement.<br />

5. Make cylinder sets for compressive strength testing as specified below at the following frequency: Once<br />

each day a given mix is placed, and not less than once for each 100 cubic yards of each mix placed each<br />

day, nor less then once for each 5,000 square feet of each mix for slab or wall surface area placed each day.<br />

Only one side of the slab or wall shall be considered when calculating surface area.<br />

6. When specified schedule of testing provides less than 5 tests for a given mix of concrete for all placements,<br />

conduct tests for at least 5 randomly selected batches; if fewer than 5 batches are used, conduct tests for<br />

each batch.<br />

7. Conduct slump, air content and temperature tests as specified herein at the time each cylinder set is made.<br />

Determine temperature of concrete sample and ambient air for each strength test.<br />

03310 - 22<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


8. In addition to slump tests conducted for cylinder sets, conduct slump tests for first truckload of concrete<br />

and every 50 cubic yards minimum thereafter in accordance with ASTM C 143. If initial slump test fails,<br />

make additional slump tests for every other load from a stationary mixer or truck to test consistency.<br />

Sampling shall be in accordance with ASTM C 172.<br />

9. In addition to air content tests conducted for cylinder sets, conduct air content test for first truckload and<br />

every 100 cubic yards minimum thereafter of concrete exposed to freeze-thaw in accordance with ASTM C<br />

231, ASTM C 173, or ASTM C 138. Indicate test method on report. Make test at same time as slump test.<br />

If initial test fails, perform air content test on every other truckload to insure consistency. When Type F fly<br />

ash is used and concrete is exposed to weather, perform air content test for first and second truck for each<br />

mix of concrete placed each day. If either test fails, perform air content test on every truckload until two<br />

consecutive air content tests comply with specified requirements.<br />

10. In addition to temperature tests conducted for cylinder sets, conduct temperature test for first truckload of<br />

concrete and every 50 cubic yards minimum thereafter in accordance with ASTM C 1064. If the initial<br />

temperature test fails, make additional temperature tests for every other load from a stationary mixer or<br />

truck to test consistency. Test hourly when air temperature is 40 degrees F and below or 80 degrees F and<br />

above.<br />

11. Note trends of decreasing quality in concrete due to changing seasons, conditions of curing, or other causes<br />

and bring to attention of the Wal-Mart Construction Manager. Report and log comments on Non-<br />

Conformance Correction Log.<br />

12. Certify each delivery ticket of concrete. Report type of concrete delivered, amount of water added and time<br />

at which cement and aggregate were loaded into truck, and time at which concrete was discharged from<br />

truck.<br />

J. Laboratory Testing Requirements:<br />

1. Test items such as reinforcing steel, aggregates, and other products suspected of not meeting specified<br />

requirement as directed by Wal-Mart Construction Manager to verify compliance. Provide test report to<br />

Wal-Mart Construction Manager. In-place tests in accordance with ASTM C 42 shall be conducted as<br />

directed by the Wal-Mart Construction Manager when specified concrete strengths and other characteristics<br />

have not been attained in the structures.<br />

2. Conduct Strength Tests:<br />

a. Secure composite samples in accordance with ASTM C 172. Sample at regularly spaced intervals<br />

from middle portion of the batch. Sampling time shall not exceed 15 minutes.<br />

b. Mold and cure specimens in accordance with ASTM C 31.<br />

1) During the initial 24 hours (plus or minus 8 hours) after molding, the temperature<br />

immediately adjacent to the specimens shall be maintained in the range of 60 to 80 degrees<br />

F. Control loss of moisture from the specimens by shielding from the direct rays of the sun<br />

and from radiant heating devices.<br />

2) Specimens transported prior to 48 hours after molding shall not be demolded, but shall<br />

continue initial curing at 60 to 80 degrees F until time for transporting.<br />

3) Specimens transported after 48 hours age shall be demolded in 24 hours (plus or minus 8<br />

hours). Curing shall then be continued but in saturated limewater at 73.4 degrees (plus or<br />

minus 3 degrees F) until the time of transporting.<br />

4) During transportation, protect the specimens with suitable cushioning material to prevent<br />

damage from jarring. During cold weather, protect specimens from freezing with suitable<br />

insulation material. Transportation time shall not exceed four hours.<br />

5) Date test cylinders and number consecutively. Give each cylinder of each set an identifying<br />

letter (i.e., A, B, C, D). Prepare a sketch of the building plan for each test set identifying<br />

location of placed concrete.<br />

c. Test cylinders in accordance with ASTM C 39.<br />

1) Test one cylinder (A) at 7 days for information. If the compressive strength of the concrete<br />

sample is equal to or above the 28 day specified strength, test another cylinder (B) at 7 days.<br />

The average of the breaks shall constitute the compressive strength of the concrete sample.<br />

2) Test two cylinders (B and C) at 28 days and the average of the breaks shall constitute the<br />

compressive strength of the concrete sample.<br />

3) Retain fourth cylinder (D) for further testing if needed, but do not retain cylinder more than<br />

60 days.<br />

03310 - 23<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


K. Reporting:<br />

1. Strength Tests: Record the following information on concrete compression reports and submit to Wal-Mart<br />

Construction Manager and others as specified in Section 01458:<br />

a. Test cylinder number and letter.<br />

b. Specific foundations or structures covered by this test.<br />

c. Proportions of concrete mix or mix identification.<br />

d. Maximum size coarse aggregate.<br />

e. Specified compressive strength.<br />

f. Tested compressive strength.<br />

g. Slump.<br />

h. Air content.<br />

i. Concrete temperature.<br />

j. Concrete plastic unit weight.<br />

k. Elapsed time from batching at plant to discharge from delivery truck at project.<br />

l. Date and time concrete was placed.<br />

m. Ambient temperature, wind speed, and relative humidity during concrete placement.<br />

n. Name of technician securing samples.<br />

o. Curing conditions for concrete strength test specimens (field and laboratory).<br />

p. Date strength specimens transported to laboratory.<br />

q. Age of strength specimens when tested.<br />

r. Type of fracture during test.<br />

2. Field Test Reports: Submit reports of field tests and inspections to Wal-Mart Construction Manager and<br />

others as specified in Section 01458.<br />

L. Inspections:<br />

1. Concrete Form Work: Verify formwork dimensions will result in member size and configuration shown.<br />

Structural adequacy of formwork is the sole responsibility of the Contractor.<br />

2. Concrete Reinforcement:<br />

a. Verify reinforcing bar grade.<br />

b. Verify reinforcing bars are free of dirt, excessive rust, and damage.<br />

c. Verify reinforcing bars are adequately tied, chaired, and supported to prevent displacement during<br />

concrete placement.<br />

d. Verify proper clear distances between bars and to surfaces of concrete.<br />

e. Verify reinforcing bar size and placement.<br />

f. Verify bar laps for proper length and stagger.<br />

3. Embedded Items:<br />

a. Verify specified size, type, spacing, configuration, embedment length, and quantity of anchor bolts<br />

and embedded items.<br />

b. Verify proper concrete placement and means have been taken to achieve consolidation around bolts<br />

and embedded items.<br />

4. Concrete Foundations Structural Inspections: Inspect foundations. Report on the following:<br />

a. Concrete footing size and depth.<br />

b. Footing bar size, spacing, and placement (cover).<br />

c. Placement and vibration of concrete.<br />

d. Dowel bar size, orientation, embedment, and spacing.<br />

5. Slab-on-Grade Structural Inspection: Inspect slabs-on-grade. Report on the following:<br />

a. Preparation of subgrade.<br />

b. Slab thickness.<br />

c. Size, spacing, placement (cover), and lap of reinforcement.<br />

d. Size, spacing, and placement of joint dowels.<br />

e. Placement and finishing of concrete.<br />

f. Time of saw cuts after placement of concrete.<br />

6. Concrete Mix:<br />

a. Verify mixer truck trip ticket conforms to approved mix design.<br />

b. Verify that total water added to mix on site does not exceed that allowed by concrete mix design.<br />

c. Verify that concrete quality is indicative of adequate mixing time, consistency, and relevant time<br />

limits.<br />

d. Work shall be performed by a Special Inspector - Technical I. Report of results shall be made daily.<br />

03310 - 24<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


7. Preparation and Placement: Inspect preparation and placement of concrete.<br />

a. Verify acceptable general condition of concrete base prior to placement.<br />

b. Verify that concrete conveyance and depositing avoids segregation and contamination.<br />

c. Verify that concrete is properly consolidated.<br />

d. Verify reinforcement remains at proper location.<br />

8. Protection and Curing: Observe protection and curing methods.<br />

a. Verify specified curing procedures are followed.<br />

b. Verify that specified hot and cold weather procedures are followed.<br />

9. Slab Joint Filler: Inspect floor slab joint filler installation at beginning of installation and periodically<br />

thereafter for proper installation including cleaning, joint prep, and depth of fill.<br />

3.16 NON-CONFORMING WORK<br />

A. When directed by Owner, repair concrete and related Work which does not conform to specified requirements<br />

including strength, durability, tolerances and finishes. Remove and replace defective concrete if repair cannot be<br />

accomplished to the satisfaction of Wal-Mart Construction Manager.<br />

B. Notify Wal-Mart Construction Manager immediately upon discovery of non-conforming Work. Excessive<br />

honeycomb or embedded debris in concrete is not acceptable.<br />

C. Patching: Cut out honeycomb, rock pockets, voids over 1/4 inch in any dimension, surface imperfections and<br />

holes left by tie rods and bolts down to solid concrete, but in no case, to a depth of not less than one inch. Make<br />

edges of cut perpendicular to the concrete surface. Thoroughly clean, dampen with water and brush-coat the area<br />

to be patched with specified bonding agent. Place patching mortar after bonding compound has dried.<br />

D. Work on which tests have failed shall be corrected as directed by Wal-Mart Construction Manager.<br />

3.17 PROTECTION<br />

A. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and<br />

damage.<br />

B. Protect wet cured or impervious sheet cured surfaces as follows:<br />

1. Barricade concrete surfaces immediately after finishing.<br />

2. Do not allow light traffic, except for curing purposes, on concrete surfaces until concrete has obtained 1800<br />

psi (approx. 3 days).<br />

3. Do not allow heavy traffic on concrete surface until concrete has obtained, by test, its design strength as<br />

noted on drawings, but not sooner than 9 days after placement.<br />

4. Permit concrete to dry minimum of 2 additional days after curing is completed before removing barricades.<br />

C. Protect surfaces cured with curing compound as follows:<br />

1. Barricade concrete surfaces immediately after application of curing compound.<br />

2. Do not allow traffic on concrete surfaces sooner than 3 days after placement.<br />

3.18 CLEANING<br />

A. Remove forms, equipment, protective coverings, and rubbish resulting from concreting operations. Leave<br />

finished concrete surfaces in clean conditions. After sweeping with ordinary broom and removing mortar,<br />

concrete droppings, loose dirt and mud, wash concrete floors and platforms with soapy water and rinse with clean<br />

water.<br />

END OF SECTION<br />

03310 - 25<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


TABLE A<br />

TESTING AND INSPECTION SCHEDULE<br />

Description of Verification and Inspection Inspection Frequency<br />

Work<br />

Referenced Standard<br />

Inspect formwork for shape, location, and<br />

dimensions of the concrete member being formed.<br />

Periodic ACI 318: 6.1.1<br />

Inspect reinforcing steel and placement. Periodic ACI 318: Ch 3.5, 7.1-7.7<br />

Inspect bolts to be installed in concrete prior to<br />

and during placement of concrete.<br />

Foundation Structural Inspection.<br />

Continuous<br />

Continuous<br />

Slab on Grade Structural Inspection.<br />

Verify use of approved design mix.<br />

Inspect concrete placement for proper application<br />

techniques.<br />

Inspect maintenance of specified curing<br />

temperature and techniques.<br />

Continuous<br />

Periodic<br />

ACI 318:<br />

Ch 4, 5.2-5.4<br />

Continuous ACI 318: Ch 5.9, 5.10<br />

Periodic ACI 318: Ch 5.11-5.13<br />

Inspect slab joint filler.<br />

Test concrete materials for compressive strength,<br />

air content, temperature, slump and plastic unit<br />

weight<br />

Periodic<br />

ASTM C 31<br />

ASTM C 39<br />

ASTM C 138<br />

ASTM C 143<br />

ASTM C 172<br />

ASTM C 1064<br />

ACI 318: Ch 5.6, 5.8<br />

03310 - 26<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


WAL-MART STORES<br />

CONCRETE MIX DESIGN SUBMITTAL FORM<br />

(Section 03310 – Structural Concrete and Exterior Concrete Slabs)<br />

Date ________________________<br />

DISCOUNT STORE SUPERCENTER MARKET SAM’S CLUB<br />

STORE INFORMATION<br />

STORE #<br />

ADDRESS<br />

CITY, STATE<br />

GENERAL CONTRACTOR<br />

COMPANY<br />

JOB SITE PHONE<br />

A. CONCRETE INFORMATION<br />

Supplier Mix Design #<br />

Design Strength (f ’ c)<br />

Water / Cementitious Ratio<br />

psi<br />

Total Air Content %<br />

Total Est. Volume of Concrete<br />

CY<br />

LEAVE<br />

BLANK FOR<br />

ENGINEER’S<br />

STAMP<br />

Mix Developed From:<br />

Trial Mix Test Data (attach test data)<br />

Field Experience<br />

Density<br />

Wet pcf Dry pcf<br />

Slump<br />

“ ( ± 1” ) WITHOUT WR Admixture<br />

“ ( ± 1” ) WITH WR Admixture<br />

Ambient Conditions for which mix is valid<br />

Temperature Min. __________ Max. __________<br />

Special requirements for pumping:<br />

Special characteristics of mix which require precautions<br />

in mixing, placing, or finishing techniques to achieve<br />

finished product specified:<br />

Humidity Min. __________ Max. __________<br />

B. ADMIXTURE INFORMATION<br />

ASTM Designation Product (Manufacturer/Brand) Dosage (ounces)<br />

oz / cy oz / cwt<br />

Air Entraining<br />

Water Reducing<br />

Water Reducing and Retarding<br />

Accelerating<br />

Evaporation Retarding<br />

High-range Water Reducing<br />

03310 - 27<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. MIX DESIGN<br />

Cement<br />

Fly Ash<br />

Slag (GGBFS)<br />

Coarse Aggregate #1<br />

Mix Proportions (per cubic yard)<br />

Identification<br />

Weight<br />

(Type, size, source, etc.)<br />

(pounds)<br />

Density<br />

(SSD)<br />

Volume<br />

(cubic feet)<br />

% Aggregate<br />

Absorption<br />

#2<br />

#3<br />

Fine Aggregate #1<br />

#2<br />

Water<br />

Air Content<br />

TOTALS<br />

Sieve<br />

Size<br />

1-1/2"<br />

1"<br />

3/4"<br />

1/2"<br />

3/8"<br />

# 4<br />

# 8<br />

# 16<br />

# 30<br />

# 50<br />

# 100<br />

# 200<br />

% of Vol<br />

Coarse<br />

Agg. # 1<br />

Coarse & Fine Aggregate Gradation Information<br />

% Passing Each Sieve<br />

(All Sieve Sizes must be entered)<br />

Coarse<br />

Agg. # 2<br />

Coarse<br />

Agg. # 3<br />

Fine<br />

Agg. # 1<br />

Combined % Retained<br />

Fine<br />

Agg. # 2<br />

Combined<br />

% Passing Cumulative Individual<br />

Aggregate Ratios<br />

Coarseness Factor =<br />

Combined % cumulative retained 3/8” sieve<br />

Combined % cumulative retained #8 sieve<br />

=<br />

Workability Factor = Combined % passing #8 sieve =<br />

Adj-Workability Factor = WF + [(Cementitious Material - 564) ÷ 37.6] =<br />

Allowable Adj-WF= Adj-WF = [(11.25 - .15 CF) + 36] ± 2.5 = Low High<br />

03310 - 28<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. ATTACHMENTS: Include the following with this Mix Design Report.<br />

Portland Cement mill test reports<br />

Fly ash mill test reports<br />

Slag mill test reports<br />

Designation, type, quality, and source (natural or manufactured) of coarse and fine aggregate materials<br />

Separate aggregate gradation reports including all required sieve sizes<br />

• All gradation sieve report tests dated within 60 days of this report<br />

• Report for each coarse and fine aggregate material in mix<br />

Statement if possible reactivity of aggregate, based on tests or past service<br />

Statement if possible aggregate pop-outs or their disruptions, based on tests or past service<br />

Product data for the following admixtures:<br />

• Chloride ion data and related calculations<br />

• Air entraining<br />

• Water reducing<br />

• Water reducing and retarding<br />

• Accelerating<br />

• Evaporation retarding<br />

• High-range water reducing<br />

Measured water-soluble chloride ion content in concrete (percent by weight of cement)<br />

Concrete compressive strength data used for standard deviation calculations<br />

E. CONCRETE SUPPLIER INFORMATION<br />

Company Name Tel. # ( )<br />

Address<br />

City, ST Zip<br />

Technical Contact Cell # ( )<br />

e-mail<br />

Sales Contact Cell # ( )<br />

PRIMARY PLANT<br />

SECONDARY PLANT<br />

Plant Location:<br />

Miles from Site:<br />

Travel Time to Site:<br />

NRMCA Certified: YES NO YES NO<br />

State DOT Certified: YES NO YES NO<br />

Batch Mixing Type: DRY CENTRAL MIX DRY CENTRAL MIX<br />

03310 - 29<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


BLANK PAGE<br />

03310 - 30<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 03312 (03 3012) – CAST-IN-PLACE CONCRETE SLABS (INTERIOR)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Cast-in-place concrete slabs including the following:<br />

a. Interior floor slabs on ground.<br />

b. Suspended slabs.<br />

c. Freezer floors.<br />

d. Garden center floor slabs (Inside Sales and Canopy areas).<br />

2. Aggregate base below slab.<br />

3. Reinforcement and accessories.<br />

B. Related Requirements:<br />

1. Section 01458 - Laboratory Testing Services: Procedures for inspection, testing, and documentation by<br />

Owner furnished testing laboratory.<br />

2. Section 03310 - Structural Concrete and Exterior Concrete Slabs: All concrete not included in this Section<br />

including structural concrete work and exterior slabs including exterior sidewalks, truck wells, door stoops,<br />

compactor pads, compressor house equipment pads, and Garden Center exterior slabs.<br />

3. Section 03362 - Burnished Concrete Floor Finishes: Cleaning, application of densifier and burnishing of<br />

floor slabs.<br />

4. Section 03930 - Concrete Rehabilitation.<br />

5. Section 05120 - Structural Steel: Column anchor bolts.<br />

6. Section 05500 - Metal Fabrications: Metal components cast into concrete.<br />

7. Section 07900 - Joint Sealers: Joint fillers and sealants for floor slabs.<br />

8. Section 09650 - Resilient Flooring:<br />

a. Joint subfloor filler for contraction and construction joints concealed by floor finish material.<br />

b. Concrete slab moisture & pH testing.<br />

9. Section 09680 - Carpet: Joint subfloor filler for contraction and construction joints concealed by floor<br />

finish material.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Association of State Highway and Transportation Officials (AASHTO):<br />

1. Standard Specification For Transportation Materials And Methods Of Sampling and Testing:<br />

a. AASHTO T318 - Water Content of Freshly Mixed Concrete Using Microwave Oven Drying<br />

(Formerly AASHTO TP 23).<br />

C. American Concrete Institute (ACI):<br />

1. ACI 117 - Tolerances for Concrete Construction and Materials and Commentary.<br />

2. ACI 301 - Structural Concrete.<br />

3. ACI 305.1 - Hot Weather Concreting.<br />

4. ACI 306.1 - Cold Weather Concreting.<br />

5. ACI 318 - Building Code Requirements for Reinforced Concrete and Commentary.<br />

6. ACI 347 - Formwork for Concrete.<br />

7. ACI SP66 - ACI Detailing Manual.<br />

D. ASTM International (ASTM):<br />

1. ASTM A 36 - Carbon Structural Steel.<br />

2. ASTM A 615 - Deformed and Plain Billet-Steel Bars for Concrete Reinforcement.<br />

3. ASTM A 706 - Low-Alloy Steel deformed and Plain Bars for Concrete Reinforcement.<br />

4. ASTM C 31 - Making and Curing Concrete Test Specimens in the Field.<br />

03312 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. ASTM C 33 - Concrete Aggregates.<br />

6. ASTM C 39 - Compressive Strength of Cylindrical Concrete Specimens.<br />

7. ASTM C 94 - Ready-Mixed Concrete.<br />

8. ASTM C 136 - Sieve Analysis of Fine and Coarse Aggregates<br />

9. ASTM C 150 - Portland Cement.<br />

10. ASTM C 172 - Sampling Freshly Mixed Concrete.<br />

11. ASTM C 403 - Time of Setting of Concrete Mixtures by Penetration Resistance.<br />

12. ASTM C 494 - Chemical Admixtures for Concrete.<br />

13. ASTM C 618 - Fly Ash and Raw or Calcined Natural Pozzolan for use as a Mineral Admixture in Portland<br />

Cement Concrete.<br />

14. ASTM C 702 - Reducing Field Samples of Aggregate to Testing Size.<br />

15. ASTM C 881 - Epoxy-Resin-Base Bonding Systems for Concrete.<br />

16. ASTM C 989 - Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars.<br />

17. ASTM C 1218 - Water-Soluble Chloride in Mortar and Concrete.<br />

18. ASTM C 1602 - Mixing Water used in the Production of Hydraulic Cement Concrete.<br />

19. ASTM D 75 - Sampling Aggregates.<br />

20. ASTM D 98 - Calcium Chloride.<br />

21. ASTM D 448 - Classification for Sizes of Aggregate for Road and Bridge Construction.<br />

22. ASTM D 698 - Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 5.5 lb (2.49 Kg)<br />

Hammer and 12-in (305 mm) Drop.<br />

23. ASTM D 1241 - Materials for Soil-Aggregate Subbase, Base and Surface Courses.<br />

24. ASTM E 1155 - Determining Floor Flatness and Levelness Using the F-Number System (Inch-Pound<br />

Units).<br />

25. ASTM E 1643 - Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor<br />

Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs.<br />

26. ASTM E 1745 - Plastic Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete<br />

Slabs.<br />

E. American Welding Society (AWS):<br />

1. AWS D1.4 - Structural Welding Code Reinforcing Steel.<br />

F. Concrete Reinforcing Steel Institute (CRSI):<br />

1. CRSI Manual of Standard Practice.<br />

2. CRSI Placing Reinforcing Bars.<br />

G. National Ready-Mixed Concrete Association:<br />

1. NRMCA Inspection Standards.<br />

1.3 ADMINSTRATIVE REQUIREMENTS<br />

A. Pursuant to Article 15 of the General Conditions, the Owner has the right to perform construction work and to<br />

award separate contracts on the Site.<br />

B. The construction work and separate contracts on the Site associated with the floor slab construction may include<br />

but are not limited to energy management cabling, LP cabling, CCTV cabling, HVAC testing and balancing,<br />

telecommunications, data cabling, alarms, and refrigeration.<br />

C. Owner or Separate Contractor Responsibilities: The following provisions are provided as information to<br />

Contractor with respect to the responsibilities of the Owner or separate contractors doing work on, or related to,<br />

the building floor slab construction. The Owner or separate contractors must:<br />

1. Notify Contractor’s superintendent 1 week prior to the start of the work at Site. Provide names and contact<br />

phone numbers to Contractor’s superintendent.<br />

2. Require workers who will be working on or around the floor slab to view Owners Contractors Training and<br />

Instructional Video and Pre-Slab Meeting Video prior to start of work or installation.<br />

3. Coordinate work and schedule activities with floor slab construction to avoid interference and to minimize<br />

detrimental effects to floor finish.<br />

4. Comply with floor protection measures as specified in this Section and as described in Contractor’s<br />

Concrete Floor Protection Plan.<br />

03312 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. Damage to concrete floor finish determined by Wal-Mart to be the responsibility of Owner or separate<br />

contractor will be repaired in accordance with approved methods, materials, and personnel at the expense<br />

of Owner or separate contractor.<br />

D. Pre-Slab Installation Meeting:<br />

1. Plan, host, and attend Pre-slab Installation Meeting to be conducted at Site by Wal-Mart Concrete<br />

Consultant via teleconference.<br />

2. Schedule meeting between 7 and 14 days prior to first concrete slab placement of 10,000 SF or greater and<br />

after placement of test slab and after concrete submittals have been approved.<br />

3. Obtain Pre-slab Installation Meeting agenda from Wal-Mart Concrete Consultant (Structural Services, Inc.<br />

(SSI), (877) 774-2677.<br />

4. Require responsible representatives of each party involved with the interior concrete slab work to attend the<br />

meeting. Representatives to be present shall include personnel who are directly involved in overseeing the<br />

work for each placement and who have authority to control the concreting work.<br />

5. Notify all required attendees in writing of scheduled time and place at least two weeks in advance of<br />

meeting. Include copy of agenda with invitation.<br />

6. The meeting shall convene only when all parties are present.<br />

7. Attendees shall include, but not be limited to the following:<br />

a. Wal-Mart Construction Manager.<br />

b. Wal-Mart Concrete Consultant.<br />

c. Contractor.<br />

1) Project Manager.<br />

2) Superintendent.<br />

d. Concrete Subcontractor.<br />

1) Project Manager.<br />

2) Finish Foreman.<br />

e. Concrete Supplier.<br />

1) Quality Assurance Representative.<br />

f. Base Fine Grading Contractor.<br />

g. Wal-Mart Construction Testing Laboratory.<br />

h. Densifier Manufacturer’s Representative.<br />

i. Densifier Applicator and Burnished Floor Surface Installer.<br />

j. Polyurea Joint Filler Manufacturer’s Representative.<br />

k. Polyurea Joint Filler Subcontractor.<br />

l. Semi-Rigid Epoxy Joint Filler Manufacturer’s Representative.<br />

m. Semi-Rigid Epoxy Joint Filler Subcontractor.<br />

8. Meeting Minutes: Record discussions of meeting and decisions and agreements reached. Submit in<br />

accordance with the requirements of Submittals paragraph.<br />

9. Changes to Contract Documents from recommendations or discussions at the Pre-slab Installation Meeting<br />

shall be approved in writing by Wal-Mart Construction Manager prior to implementation. Wal-Mart<br />

Concrete Consultant is not authorized to change any specified requirement or to approve execution of any<br />

portion of the work.<br />

1.4 SUBMITTALS<br />

A. Submittal Procedures: Unless otherwise specified herein, submit in accordance with procedures specified in<br />

Section 01330.<br />

B. Submit submittal items concurrently for submittals shown with the same submittal date specified in the Concrete<br />

Submittal Register included at the end of this Section. Do not submit submittals of this section together with<br />

submittals in Section 03310 or any other Section. Identify submittals explicitly in accordance with the<br />

requirements of Section 01330.<br />

C. Submit to designated parties in the Concrete Submittal Register included at the end of this Section.<br />

D. Sieve Analysis for Aggregate Base System: Submit current sieve analysis report for aggregate base and choker<br />

material.<br />

03312 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Concrete Finishing Sub-contractor's Qualification Statement: Submit Concrete Finishing Sub-Contractor’s<br />

Qualifications Statement form included at the end of this Section including Floor Finisher Qualifications as<br />

required in Quality Assurance paragraph.<br />

1. Provide ACI certification documents for at least three finishers who will install interior slabs.<br />

F. Concrete Batch Plant Certification: Submit name and address of concrete supplier’s batch plant and plant<br />

certification(s) by National Ready-Mix Concrete Association or State Department of Transportation.<br />

G. Slab Reinforcing Bar Shop Drawings:<br />

1. Complete information for installing reinforcing, including placement plans, bar bending diagrams, splice<br />

lengths and locations, bar spacing, concrete cover, and support devices and accessories.<br />

2. Detail in accordance with ACI SP 66.<br />

3. Perimeter foundation tie reinforcing submittals is specified in Section 03310.<br />

H. Mix Design: Submit Concrete Slab Mix Design Submittal Form at the end of this Section.<br />

1. Submit only one form indicating same mix design proportions for all interior slab concrete.<br />

2. Include applicable information shown on the Mix Design Submittal Form including the following:<br />

a. Proportions of cementitious materials, fine and coarse aggregate, and water.<br />

b. Water cementitious material ratio, 28-day compressive design strength, slump, and air content.<br />

c. Type of cement, fly ash, slag, and aggregate.<br />

d. Individual aggregate gradation.<br />

e. Type and dosage of admixtures.<br />

f. Special requirements for pumping.<br />

g. Range of ambient temperature and humidity for which design is valid.<br />

h. Special characteristics of mix which require precautions in mixing, placing, or finishing techniques<br />

to achieve finished product specified.<br />

I. Attachments to Concrete Mix Design: Submit the following as attachments to be included with the Concrete Mix<br />

Design:<br />

1. Cementitious materials mill test reports for the following:<br />

a. Portland cement.<br />

b. Fly ash.<br />

c. Slag.<br />

2. Designation, type, quality, and source (natural or manufactured) of coarse and fine concrete aggregate<br />

materials.<br />

3. Sieve Analysis Reports for Concrete Aggregate: Provide separate reports of particle distribution,<br />

calculating cumulated percentages passing for all individual aggregates required on the mix form. Sieve<br />

analysis sampling and testing for each aggregate source shall be conducted within 60 days of concrete<br />

submittal date.<br />

4. Concrete Aggregate Supplier Statement:<br />

a. Stating if aggregate is possibly alkali-reactive, based on tests or past service.<br />

b. Stating if aggregate can possibly cause pop-outs, “D” cracking, or other disruptions due to moisture<br />

gain, freezing, or other mechanisms, based on tests or past service.<br />

5. Product data for the following concrete materials admixtures:<br />

a. Water reducing.<br />

b. Water reducing and retarding.<br />

c. Accelerating.<br />

d. Chloride ion content for each admixture.<br />

6. Chloride-Ion Content: Measured water-soluble chloride-ion content (percent by weight of cementitious<br />

materials) in accordance with ASTM C 1218.<br />

7. Concrete compressive strength data as required by ACI 318.<br />

8. Time of Initial Setting: Initial setting time in accordance with ASTM C 403.<br />

J. Concrete Supplier Approval. Statement of Acceptance of Concrete Supplier as described in Quality Assurance<br />

paragraph.<br />

K. Product Data: Brand name, chemical composition, installation directions and certificates of compliance with<br />

required standards for the following products:<br />

1. Doweling system for construction joints.<br />

03312 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Vapor retarder and tape.<br />

3. Curing compound.<br />

L. Slab Joint and Placement Plan:<br />

1. Develop and submit slab joint and placement plan on a copy of Sheet S1.1.<br />

2. Plan shall identify the following:<br />

a. Exterior walls and column grid locations.<br />

b. Truck access location.<br />

c. Extent of pours including width, length, slab placement area and volume.<br />

d. Sequence of placement.<br />

e. Location of test slab placement.<br />

f. Locations of construction joints.<br />

g. Location of sawn contraction joints if different from those shown on the structural drawings.<br />

M. Concrete Floor Protection Plan. Submit Concrete Floor Protection Plan addressing procedures specified in Part 3<br />

of this Section.<br />

N. Pre-Slab Installation Meeting Documents:<br />

1. Record of Notification of pre-slab meeting including company name, persons contacted, and date and<br />

method of contact.<br />

2. Meeting Agenda.<br />

3. Meeting Minutes. Submit meeting minutes including attendance record to participants and Wal-Mart<br />

Construction Manager. Minutes of the meeting shall be distributed to parties in attendance by the<br />

Contractor within 5 days of the meeting. One copy of the minutes shall also be transmitted to the Walmart<br />

Construction Manager for information purposes.<br />

O. Delivery Tickets:<br />

1. Copies of delivery tickets for each load of concrete delivered to site.<br />

2. Indicate information required by ASTM C 94 on each ticket including additional information required for<br />

slabs.<br />

3. Information on ticket shall include quantities of all material batched including the amount of free water in<br />

the aggregate and the quantity of water that can be added at the site without exceeding the maximum water<br />

cement ratio of the approved mix design. Aggregate moisture corrections shall be based on ASTM<br />

definitions of aggregate moisture content and absorption.<br />

4. Mix identification number on ticket shall match number on submitted and approved mix design.<br />

1.5 QUALITY ASSURANCE<br />

A. Concrete Truck Inspection:<br />

1. Conform to ASTM C 94, NRMCA and Department of Transportation standards in state where project is<br />

located with respect to truck mixer requirements.<br />

2. Perform inspections immediately before starting concreting operations.<br />

3. Record the identification numbers of those trucks found to be acceptable on the basis of inspections.<br />

4. Do not bring on site for concreting operations, any truck whose identification numbers are not recorded as<br />

acceptable. Notify CTL if non-conforming trucks are used to deliver concrete for interior.<br />

B. Concrete Supplier Approval: Concrete Supplier and materials provided shall be fully approved by and acceptable<br />

to Concrete Subcontractor as the producer of concrete which Sub-contractor is to place and finish. Prepare<br />

Statement of Approval of Concrete Supplier stating project name, name of concrete supplier, along with the<br />

statement of approval and signatures of the Contractor and Concrete Floor Sub-contractor. Submit statement as<br />

specified in Submittals paragraph.<br />

C. Batch Plant Quality Control: Quality control of materials and batching operations during batching operations shall<br />

be the full responsibility of the batch plant operators. CTL or Wal-Mart Concrete Consultant will not be required<br />

to perform observation, testing, or inspection at the batch plant during batching operations.<br />

03312 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Floor Finisher Qualifications:<br />

1. The concrete floor finishing subcontractor lead finisher and at least two additional members of the finishing<br />

crew shall be certified under the Concrete Flatwork Finisher Training and Certification Program as granted<br />

by the American Concrete Institute and shall be present during finishing of interior floor slab concrete.<br />

Certified individuals executing finish operations shall have documentation of current certification available<br />

for inspection on Site.<br />

2. The concrete floor finisher subcontractor shall have experience in finishing interior floors of similar size<br />

and scope in at least 5 previous projects.<br />

E. Floor Test Slabs:<br />

1. Prior to the Pre-Slab Installation Meeting construct permanent test slab with approved mix design as<br />

indicated on the Slab Plan of the Structural Drawings.<br />

2. Wal-Mart Construction Manager will evaluate the test slab and indicate Owner’s acceptance, corrections<br />

noted, or rejection to establish a minimum basis for acceptance of final slabs.<br />

3. Work shall not begin on final areas until an ability to satisfy specified tolerances and other requirements<br />

routinely in test areas has been demonstrated.<br />

4. Use same materials, tools, and methods for finishing and curing final slab work as used for test slab.<br />

5. Replace final slab work that does not meet or exceed accepted established test slab standard.<br />

1.6 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Deliver materials in unopened containers with labels identifying contents. Keep containers closed and upright to<br />

prevent leakage.<br />

C. Mark reinforcing, accessories and embedded items for proper identification and placement location.<br />

D. Store materials, except aggregate, off ground in dry area and in manner to prevent damage. Protect liquid<br />

materials from freezing.<br />

E. Stockpile aggregate in manner to prevent contamination with other materials or with other sizes of aggregates. Do<br />

not use bottom 6 inches of aggregate piles in contact with ground. Allow sand to drain until it has reached<br />

uniform moisture content before it is used.<br />

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.<br />

G. Store admixtures in manner to prevent contamination. Protect admixtures from extreme temperatures which<br />

would adversely affect their characteristics.<br />

1.7 ENVIRONMENTAL REQUIREMENTS<br />

A. Hot and cold weather concreting shall be in accordance with ACI 305.1 (hot weather) and 306.1 (cold weather).<br />

B. Concreting in Hot, Dry or Windy Weather:<br />

1. Determine rate of evaporation in accordance with ACI 305.1.<br />

2. Employ precautions as required to protect fresh concrete before and during finishing when the concrete rate<br />

of evaporation exceeds 0.1 pounds per square foot per hour or when any combination of concrete materials<br />

and weather conditions are favorable for the formation of plastic shrinkage cracks.<br />

a. Cool ingredients before mixing to reduce concrete temperature at time of placement. Mixing water<br />

may be chilled, or chopped ice may be used to control the concrete temperature provided the water<br />

equivalent of the ice is calculated to the total amount of mixing water.<br />

b. Dampen subgrade and forms.<br />

c. Cover reinforcing steel with water soaked burlap so the steel temperature will not exceed the<br />

ambient air temperature immediately before embedment in concrete.<br />

3. Maintain an accurate reading thermometer at the Site to check temperature of concrete.<br />

4. Temperature of concrete at time of placing: Not to exceed 95 degrees F.<br />

5. Reject concrete if more than one slump adjustment, as defined in ASTM C 94, is required.<br />

03312 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


6. Do not place concrete when forms, subgrade, aggregate base or reinforcing bars are more than 120 degrees<br />

F or the temperature differential between the forms, aggregate base, or reinforcing bars and concrete will<br />

create conditions favorable for settlement cracks or thermal cracking.<br />

C. Concreting in Cold Weather:<br />

1. Minimum base surface temperature and ambient building air temperature shall be 55 degrees F during<br />

placement and throughout curing period. Measure and record concrete temperature during protection<br />

period at regular time intervals, but not less than 3 times per 24 hours.<br />

2. Do not place slabs on subgrade, or base that is more than 20 degrees F cooler than concrete. Warm<br />

subgrade, or base to decrease temperature differential to 20 degrees F or less.<br />

3. Minimum concrete temperature as measured at the point of discharge shall be 65 F.<br />

4. Do not use unvented combustion heaters during concrete placement so as to prevent exposure of concrete<br />

to excessive exhaust gases containing carbon dioxide (CO 2 ) or carbon monoxide (CO). During slab<br />

placement and curing periods, maximum CO 2 levels shall be 4,500 parts per million and maximum CO<br />

levels shall be 15 parts per million at concrete surface within 5 feet of any source of exhaust gases to<br />

minimize potential damage to concrete.<br />

D. Placing Environment:<br />

1. Sales floor concrete shall be placed within a completely enclosed structure, after the roof membrane is<br />

completely installed and watertight.<br />

2. Roof construction, RTUs, skylight installation, overhead painting, and roof drainage system shall be<br />

complete and weathertight prior to placement of slabs.<br />

3. Non-sales floor concrete shall be protected from precipitation until adequate strength is gained to prevent<br />

damage.<br />

4. Lighting: Permanent lighting shall be operational during all slab placements.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Subject to compliance with project requirements, provide products as manufactured by the following to the extent<br />

as specified hereinafter for the specific product:<br />

1. BASF Admixtures, Inc., Cleveland, OH (Formerly Master Builders) (800) 628-9990.<br />

2. BASF Building Systems, Shakopee, MN (Formerly Degussa Building Products) (800) 433-9517.<br />

3. Chase Construction Products, Bridgwater, MA 508-341-4961.<br />

4. Commercial Metals Company (214) 689-4300.<br />

5. Dayton Superior Dayton, OH (913) 287-1700 or (877) 416-3439.<br />

6. Davis Colors, (800) 800-6856.<br />

7. Euclid Chemical Co., (877) 438-3826.<br />

8. Fortifiber Building Systems Group, Fernley, NV (800) 773-4777.<br />

9. Greenstreak Group, Inc., St. Louis, MO (800) 325-9504.<br />

10. L.M. Scofield, (800) 800-9900.<br />

11. Master Builders, Inc.: See BASF Admixtures, Inc. (Formerly Degussa).<br />

12. MBT: See BASF Building Systems (Formerly Master Builders and Degussa).<br />

13. McTech Group, Steve McDonald, (866) 913-8363.<br />

14. PNA Construction Technologies, (800) 542-0214.<br />

15. Raven Industries, Inc., Sioux Falls, SD (800) 635-3456.<br />

16. Seal Source (800) 305-9144, www.sealsource.com<br />

17. Sika Corp., (800) 933-7452.<br />

18. Soff-Cut (951) 272-2330.<br />

19. Solomon Colors, Springfield, IL (800) 624-0261.<br />

20. SpecChem (866) 791-8700.<br />

21. Stego Industries, LLC, San Clemente, CA (877) 464-7834.<br />

22. Unitex, Kansas City, MO, (816) 231-7700 or (800) 821-5846.<br />

23. W.R. Grace and Co., (713) 223-8353.<br />

24. W.R. Meadows, Inc., (847) 214-2100.<br />

25. Vexcon Chemicals, Inc., Philadelphia, PA (888) 839-2661.<br />

B. Substitutions: Comply with the requirements of Section 01600 unless specified otherwise herein.<br />

03312 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 AGGREGATE BASE AND CHOKER MATERIALS<br />

A. Aggregate Base Material:<br />

1. Gradation: Conform to gradation shown on the Structural Drawings.<br />

2. Equivalent Gradation: Equivalent gradations may be used upon approval of the Structural Engineer of<br />

Record (SER). Submit proposed equivalent gradation to the Architect for approval within 30 days after the<br />

award of contract. Equivalent gradation shall be one of the following.<br />

a. Any state DOT approved road base material meeting the following gradation:<br />

Standard Sieve Size<br />

% Passing<br />

1-1/2” 100<br />

No. 4 15-55<br />

No. 200 3-12<br />

b. Material conforming to the General Requirements and of the Gradation “A”, ”C”, or “D”<br />

requirements (with the modified allowance of 5% to 12% passing the No. 200 sieve) as defined by<br />

ASTM D 1241.<br />

3. Material passing the No. 200 sieve shall be clean granular fill with less than 3% clay and/or friable<br />

particles.<br />

B. Aggregate Choker Material: Clean granular fill with less than 3% clay and/or friable particles. Use one of the<br />

following gradations:<br />

1. ASTM D 448 No. 10 with 6% to 12% passing No. 200 sieve.<br />

2. Material meeting the following gradation:<br />

2.3 FORMWORK<br />

Standard Sieve Size<br />

% Passing<br />

No. 4 85-100<br />

No. 8 75-95<br />

No. 16 55-75<br />

No. 50 22-45<br />

No. 100 10-30<br />

No. 200 6-12<br />

A. Forms:<br />

1. Plywood, metal, metal-framed plywood faced, or other acceptable panel-type materials to provide<br />

continuous, straight, smooth, exposed surfaces.<br />

2. Furnish forms in largest practicable sizes to minimize number of joints and to conform to joint system<br />

shown on Drawings.<br />

3. Provide lumber dressed on at least two edges and one side for tight fit.<br />

4. Bevel top outside edge of form.<br />

5. Do not use partial depth forms.<br />

B. Form Release Agent:<br />

1. 100% biodegradable, non-toxic, 100% natural organic chemical release agent. Will not cause surface<br />

imperfections, non-staining, and compatible with field applied paints, toppings, curing compounds, and<br />

other coatings. Use same brand form release agent for all forms. Provide one of the following:<br />

a. Form-EZE Natural by Euclid.<br />

b. Bio-Release EF by Dayton Superior.<br />

c. Star Seal EF V Release by Vexcon.<br />

d. Farm Fresh by Unitex.<br />

e. Reaxion WB by SpecChem.<br />

03312 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Prefabricated Access Pit Form: Pit form at Refrigeration Pit shall be Model POL Prefabricated Fiberglass Access<br />

Pit and Anchoring Assembly as manufactured by Craigg Manufacturing Corp., Reinholds, PA (717) 733-1412,<br />

Fax (717) 733-6132, Email CraiggMFG@Criagg.com.<br />

2.4 REINFORCEMENT<br />

A. Reinforcing Bars:<br />

1. ASTM A 615, deformed, Grade 60.<br />

2. ASTM A 706, deformed, Grade 60.<br />

B. Tie Wire:<br />

1. Minimum 16 gage annealed type.<br />

C. Reinforcing Support Devices:<br />

1. Manufactured support devices of metal (wire bar), concrete, or recycled plastic devices conforming to<br />

CRSI Manual of Standard Practice.<br />

2. Precast concrete bar supports shall have minimum compressive strength of 3500 psi.<br />

3. Plastic accessories shall have a minimum of 50% recycled content.<br />

4. Do not use wood, clay brick, and other devices that can expand due to moisture gain.<br />

5. For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1<br />

plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.<br />

6. When precast concrete bar supports are used over aggregate base, or over waterproof membranes and vapor<br />

retarders, properly embed tie wires to prevent penetration of substrate.<br />

7. Properly size foot of bar supports or similar devices to prevent settlement on base material or prevent<br />

puncture on vapor barrier.<br />

8. When supporting multiple layers of reinforcement, provide the proper size and spacing of bar supports or<br />

similar devices to prevent deformation of plastic and to retain rebar within position tolerances.<br />

D. Plate Dowels - Construction Joints:<br />

1. Provide plate dowels consisting of smooth steel plate bars, ASTM A 36 steel. Provide one of the<br />

following:<br />

a. Diamond Dowel System by PNA Construction Technologies, size 1/4 inch x 4-1/2 inch dowels.<br />

b. EZform EZdowel (including EZform Board) by McTech, Inc., size 6-1/4 inch x 3-1/2 inch x 1/4inch<br />

dowels.<br />

c. Speed Plate System by Greenstreak, size 1/4 inch x 4 inch x 6 inch dowels.<br />

2.5 CONCRETE MATERIALS<br />

A. Cement: ASTM C 150 – Type I. Use only one brand throughout project.<br />

B. Fly Ash: ASTM C 618, Class C or F. Use only one type and source throughout project.<br />

C. Slag: ASTM C 989, Grade 100 or 120. Use only one type and source throughout project.<br />

D. Concrete Aggregate:<br />

1. Conform to ASTM C 33:<br />

a. No coal or lignite in concrete that will not be covered by building materials or soil.<br />

b. Fine aggregate grading requirements as defined in Section 6.1 of ASTM C 33 shall be strictly met<br />

without deviation.<br />

2. If manufactured fine aggregate is used, blend with minimum 25% natural materials.<br />

3. Coarse Aggregate:<br />

a. Nominal maximum coarse aggregate size shall be 1-1/2 inch for slabs > 5-1/2 inch thick.<br />

b. Nominal maximum coarse aggregate size shall be 1 inch for slabs ≤ 5-1/2 inch thick.<br />

c. The nominal maximum size of an aggregate is the smallest sieve size through which the major<br />

portion of the aggregate must pass, with 1% to 5% retained on the nominal maximum size sieve.<br />

03312 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Adjust proportions of combined coarse, intermediate, and fine aggregates to provide the following particle<br />

size distribution characteristics, unless otherwise approved:<br />

1) Coarseness Factor of 60 to 75%.<br />

a) The Coarseness Factor (CF) is the percent of combined aggregate retained on the #8<br />

sieve that is also retained on the 3/8 inch sieve.<br />

b) The Coarseness Factor is calculated as follows: CF=Aggregate retained on 3/8” sieve<br />

/ Aggregate retained on #8 sieve.<br />

2) Adjusted Workability Factor:<br />

a) The Workability Factor (WF) is the percent of combined aggregate that passes the #8<br />

sieve.<br />

b) The Adjusted Workability Factor (Adj-WF) is calculated as follows:<br />

Adj-WF =WF+[(Cementitious Material -564 lbs)/37.6]<br />

c) The range of accepted Adj-WF for a given CF is as follows:<br />

Adj-WF = [(11.25 - .15 CF) + 36] ± 2.5.<br />

3) Combined percent retained on any given sieve size shall not exceed 24%.<br />

4) See Coarseness Factor Chart at the end of this Section.<br />

5. Aggregate gradation requirements of ASTM C 33 may be waived in order to meet ranges specified.<br />

E. Water: ASTM C 1602.<br />

2.6 CHEMICAL ADMIXTURES<br />

A. Provide admixture products as specified below. Within each product listing, provide one of the products specified.<br />

When specifically allowed within each product listing, equivalent admixture products by other manufacturers<br />

meeting the specified ASTM standards may be used upon submittal of product data and approval by SER.<br />

B. Water Reducing Admixture: ASTM C 494, Type A.<br />

1. Eucon or Plastol Series by Euclid.<br />

2. Pozzolith, PolyHeed or Glenium Series by BASF Admixtures.<br />

3. WRDA, Daracem, Mira, Zyla or Adva Series by W.R. Grace.<br />

4. Plastiment, Plastocrete, ViscoCrete, Sikaplast, or Sikament Series by Sika Corp.<br />

5. Equivalent approved products.<br />

C. Water Reducing and Retarding Admixture: ASTM C 494, Type B or D.<br />

1. Eucon Retarder 75 by Euclid.<br />

2. Pozzolith Series or Delvo by BASF Admixtures.<br />

3. Recover or Daratard 17 by W.R. Grace.<br />

4. Plastiment or Plastocrete Series by Sika Corp.<br />

5. Equivalent approved products.<br />

D. Accelerating Admixture: ASTM C 494, Type C or E.<br />

1. Accelguard 80 by Euclid.<br />

2. Daraset Series, Daracel, Lubricon, Polarset, or DCI by W.R. Grace.<br />

3. Pozzolith or Pozzutec Series by BASF Admixtures.<br />

4. Plastocrete 161 FL, Plastocrete 161 HE, Sikaset NC, Sika Rapid 1, or Sikaset HE by Sika Corp.<br />

5. Calcium Chloride (Type L) in solution form.<br />

6. Equivalent approved products.<br />

E. Water Reducing Admixture: ASTM C 494, Type F. Do not use high range, Type F, or all range water reducing<br />

admixture at Type F dosage rates.<br />

F. Evaporation Retardant: Water-based polymer, sprayable.<br />

1. EucoBar by Euclid.<br />

2. Confilm by BASF Admixtures.<br />

3. Conspec Aquafilm by Dayton Superior.<br />

4. SpecFilm RTU by SpecChem.<br />

03312 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.7 RELATED MATERIALS<br />

A. Screed Chairs: Metal.<br />

B. Vapor Retarder: ASTM E 1745, Class A, sheet membrane material, not less than 10 mils thick unless otherwise<br />

shown on Drawings.<br />

1. Stego Wrap by Stego Industries.<br />

2. Moistop Ultra 10 by Fortifiber.<br />

3. Perminator 10 mil, by W.R. Meadows.<br />

4. Vapor Block 10 mil, by Raven Industries.<br />

C. Vapor Retarder Tape and Adhesive: Tape and adhesives for sealing laps, punctures, tears and penetrations shall be<br />

pressure-sensitive, waterproof adhesive tape, 2 inches minimum width and compatible with retarder.<br />

D. Epoxy Bonding Agent: ASTM C 881.<br />

1. Euco #452 by Euclid.<br />

2. E-Poxy Eva-Pox Fresh Concrete Bonder 2 by Chase Construction Products.<br />

3. Concresive Liquid LPL by BASF Building Systems.<br />

4. Sikadur 32 Hi-Mod LPL by Sika.<br />

2.8 CONCRETE CURING MATERIALS<br />

A. Curing Compound: Temporary film forming type curing compound.<br />

1. SC Cure 500 by SpecChem.<br />

B. Concrete Epoxy Resin Sealer: One-coat system, by Concrete Curative Systems, LLC, (877) 227-8003,<br />

http://www.concretecurative.com/<br />

1. Product: CCS-S1.<br />

a. Performance: ASTM D 1308, ASTM D 2240, ASTM D 4145, ASTM F 2170.<br />

b. VOC: None.<br />

2. Surface preparation, application and testing shall be per manufacturer’s published specifications.<br />

2.9 CONCRETE MIX<br />

A. General:<br />

1. Use only materials and their proportions included in approved Concrete Mix Design.<br />

2. Measure and mix ingredients in accordance of ASTM C 94.<br />

3. Concrete supplier may proportion materials by field experience or proportion concrete materials by<br />

laboratory trial batches per ACI 318 for strength compliance.<br />

B. Strength: As indicated on Drawings.<br />

C. Workability: Concrete shall be of a consistency to be worked readily into forms and around reinforcement without<br />

segregation, voids, or excessive bleeding.<br />

D. Supplementary Cementitious Materials (SCM):<br />

1. Use of SCM in the concrete mix is mandatory.<br />

2. Ternary blended materials are not acceptable. Concrete mix shall contain either fly ash or ground<br />

granulated blast furnace slag (GGBFS) but not both.<br />

3. Fly Ash: Substitute fly ash for Portland cement at a minimum of 15% to a maximum of 20% of the total<br />

cementitious content.<br />

a. If used to mitigate potential aggregate reactivity, only Type F fly ash may be used and shall have the<br />

following maximum properties: 1.5% available alkali and 8.0% CaO.<br />

4. Ground Granulated Blast Furnace Slag (GGBFS): Substitute GGBFS for Portland cement at a minimum of<br />

25% to a maximum of 30% of the total cementitious content. If required to mitigate potential sulfate<br />

exposure or aggregate reactivity, up to 50% GGBFS substitution for Portland cement may be used.<br />

E. Cementitious Materials Content (Portland Cement + SCM): Use 520 pounds minimum for all interior slab mixes.<br />

03312 - 11<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


F. Water/Cementitious Materials Ratio: Interior Floor Slabs: 0.53 maximum.<br />

G. Air-Entraining Admixture: Do not air-entrain interior floor slabs with troweled finish.<br />

H. Time of Setting: Initial setting time shall not exceed 400 minutes as determined by ASTM C 403 for a laboratory<br />

sample representing the submitted mix design, admixture dosages, and concrete temperature of 60°F ± 5°F. Only<br />

one specimen or time of setting test is required per sample. If more than one test is performed per sample, report<br />

average times of initial setting. Test shall be performed by an independent testing agency selected by, and as a<br />

responsibility of, the Concrete Supplier.<br />

I. Slump: Slump at the point of placement shall not exceed 6 inches subject to the requirement that concrete shall be<br />

of a consistency to be worked readily into forms and around reinforcement without segregation, voids, or<br />

excessive bleeding. Maximum slump variance shall be 2 inches.<br />

J. Admixtures:<br />

1. Water-reducing admixture may be added to improve workability beyond 2 inches to 3 inches initial water<br />

slump. Mix shall have adequate water to produce consistent plastic material properties.<br />

2. Concrete slab mix shall contain only one water reducing admixture.<br />

3. Use admixtures in accordance with manufacturer’s recommendation.<br />

K. Calcium Chloride Admixture:<br />

1. Calcium chloride (Type L) conforming to ASTM D 98 may be used in solution form as part of the mixing<br />

water to accelerate concrete setting and early-strength development.<br />

2. Amount of calcium chloride added shall not be more than necessary to produce the desired results and shall<br />

not exceed 1.5% by weight of cement.<br />

3. The dosage range for the calcium chloride for the entire project shall not vary by more than 1%. Range is<br />

defined as the difference between the maximum and minimum dosages of calcium chloride for the entire<br />

project.<br />

4. Calcium chloride shall not be used in the following applications unless approved by SER:<br />

a. Concrete containing embedded dissimilar metals or aluminum.<br />

b. Slabs supported on permanent galvanized steel forms.<br />

c. Concrete exposed to deicing chemicals.<br />

d. Prestressed or post-tensioned concrete.<br />

e. Concrete containing aggregates with potentially deleterious reactivity.<br />

f. Concrete exposed to soil or water containing sulfates.<br />

5. Use calcium chloride in accordance with manufacturer’s recommendation.<br />

6. Chloride-Ion Concentration: Maximum water-soluble chloride-ion concentrations in hardened concrete at<br />

ages from 28 to 42 days contributed from the ingredients including water, aggregates, cementitious<br />

materials, and admixtures shall not exceed the following limits unless approved by SER:<br />

Maximum water-soluble chloride ion (Cl-) content in<br />

Type of Member<br />

concrete<br />

(percent by weight of cement)<br />

Prestressed Concrete .06<br />

Reinforced concrete exposed to chloride<br />

in service<br />

Reinforced concrete that will be dry or<br />

protected from moisture in service<br />

.15<br />

1.00<br />

Other reinforced concrete construction .30<br />

7. When using calcium chloride or other admixtures containing chlorides, measure water-soluble chloride-ion<br />

content (percent by weight of cementitious materials) per ASTM C 1218. Sample shall be from concrete<br />

representing the submitted mix design and maximum chloride dosage anticipated for the project.<br />

03312 - 12<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.10 MIXING<br />

A. Ready-Mixed Concrete:<br />

1. Mix and transport in accordance with ASTM C 94 and ACI 301 except as specified.<br />

2. Reset drum revolution counter to zero on concrete truck when water is added to drum.<br />

B. Site-Mixed Concrete:<br />

1. Conform to ACI 301.<br />

2. Use central-mix type batch plant.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Conform to manufacturer’s printed instructions for materials and equipment.<br />

B. Verify anchors, seats, plates, reinforcement, and other items to be cast into concrete are accurately placed, held<br />

securely, and will not cause difficulty in placing concrete.<br />

3.2 PREPARATION<br />

A. Preplacement Inspection: All trades and participants involved shall verify that preparations are in conformance<br />

with Contract Documents.<br />

B. Cleaning Equipment: Remove hardened concrete and foreign materials from mixing and conveying equipment.<br />

C. Ensure that all work is properly coordinated:<br />

1. Structural Drawings and Specifications with those of other disciplines.<br />

2. Use final corrected submittals.<br />

3.3 AGGREGATE BASE PLACEMENT<br />

A. Unless otherwise indicated on the Drawings, place aggregate base as specified herein.<br />

B. Aggregate Base:<br />

1. Install aggregate base where shown on Drawings.<br />

2. Compact to final thickness shown on Drawings in layers not exceeding 6 inches with minimum of 2 passes<br />

per layer with vibratory compactor.<br />

3. Compact fill to 98% of aggregate’s Standard Proctor as determined by Method D of ASTM D 698.<br />

4. Leave pad up to 2 inches low until just prior to concrete placement.<br />

C. Aggregate Base Fine Grading:<br />

1. Compact to final thickness noted with 2 passes minimum vibratory compactor to produce smooth, flat,<br />

dense surface.<br />

2. Do not allow excess moisture or soft soil beneath vapor retarder at time of placing concrete.<br />

3. Level off aggregate base top surface with aggregate choker material as necessary as follows:<br />

a. To reduce surface friction and to meet specified fine grade tolerances specified below. Typically<br />

required up to 3/4 inch thick in areas exposed to rain, traffic, or excavation for pits and buried<br />

utilities.<br />

b. Where aggregate base material does not have sufficient fine particles to produce a surface that is<br />

free of exposed aggregate or surface voids greater than 3/8 inch in size at time of slab installation.<br />

4. Wal-Mart Construction Testing Laboratory shall verify adequate fines at surface prior to concrete slab<br />

placement.<br />

5. Use laser guided equipment to establish specified base elevation.<br />

6. Provide dry, smooth, flat, dense surface. Take corrective action if rutting or pumping is evident during the<br />

preparation of the soil support system.<br />

7. Proof-roll 48 hrs maximum prior to concrete placement. Depression under a fully loaded concrete truck<br />

shall not exceed 1/2 inch.<br />

03312 - 13<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Slab on Ground Aggregate Base Fine Grade Tolerance: +0 inch, -3/4 inch with transition no greater than 3/4 inch<br />

vertically to 8 inches horizontally for level slab.<br />

3.4 FORMWORK<br />

A. Form vertical surfaces of concrete work.<br />

B. Design, construct, and remove formwork and related items in accordance with most stringent requirements of ACI<br />

117 and 347.<br />

C. Form Preparation:<br />

1. Clean formwork.<br />

2. Remove rust from steel formwork.<br />

D. Erecting Forms:<br />

1. Butt joints and provide backup splice at joints as required to prevent faulting at form.<br />

2. Do not tape formwork joints.<br />

3. Just before placing concrete, clean forms and adjacent surfaces again as necessary. Remove wood,<br />

sawdust, chips dirt and other debris.<br />

4. If necessary to grease tie threads, do not allow grease to contact remainder of tie when wall will be exposed<br />

to hydrostatic pressure.<br />

E. Form Release Agent:<br />

1. Before placing reinforcing steel, thoroughly coat contact surfaces of forms with form release agent.<br />

2. Apply form release agent evenly without excess drip.<br />

3. Do not allow form release agent to come into contact with concrete surfaces against which fresh concrete<br />

will be placed.<br />

4. Moisten wood forms immediately before placing concrete where form release agents are not used.<br />

F. Provide slab side forms, of form materials specified, full depth, with beveled, level, and smooth top surface for all<br />

slabs on ground where SOV is greater than FF 35 / FL 25.<br />

G. Provide slab side forms such that by placing a 10-foot straightedge, form does not exceed 1/8 inch variation.<br />

H. Prefabricated Access Pit Form: Install in accordance with manufacturer’s instructions.<br />

3.5 VAPOR RETARDER INSTALLATION<br />

A. Install vapor retarder in accordance with ASTM E 1643 except that Paragraph 10 - Slab Moisture Content<br />

provisions shall not apply.<br />

B. Install vapor retarder directly under slabs where shown on Drawings.<br />

C. Following leveling and tamping of prepared base for slabs, place vapor retarder sheeting with longest dimension<br />

parallel with direction of placement.<br />

D. Lap joints 6 inches minimum and seal continuously with specified tape.<br />

E. Seal punctures and tears in membrane caused by bar chair feet, screed anchors, or utility penetrations with<br />

specified tape.<br />

F. Sequence installation of vapor retarder no more than 40 feet in advance of laser screed strike-off.<br />

G. Do not disturb or damage vapor retarder while placing granular fill. If damage occurs, repair prior to concrete<br />

placement.<br />

03312 - 14<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.6 PLACING REINFORCEMENT<br />

A. Place reinforcing in accordance with of ACI 117, ACI 301, ACI 318 and CRSI Manual of Standard Practice and<br />

Placing Reinforcing Bars.<br />

B. Accurately place and secure reinforcement against displacement by firmly wiring at intersections and splices.<br />

C. Turn wire ends away from concrete exterior.<br />

D. Ensure reinforcing is clean, free from defects and kinks, loose mill or rust scale or coatings that will reduce bond.<br />

E. Protect exposed reinforcing bars, inserts and plates intended for bonding with future expansion from corrosion.<br />

F. When welding of reinforcement is specified, comply with AWS D1.4. Do not tack weld crossing bars for<br />

assembly of reinforcement, supports or embedded items.<br />

G. Slab on Ground and Pavement Dowels:<br />

1. Secure dowels and sleeves (if required) perpendicular to joint and parallel to finished concrete surface.<br />

2. Use prefabricated dowel supports at ends of dowels to maintain alignment, if necessary.<br />

3. Dowel alignment shall be within specified tolerances.<br />

4. Dowels shall be manufactured to provide bond break between steel and concrete.<br />

5. Do not grease dowels.<br />

6. Install dowels at construction joints in accordance with manufacturer’s recommendations.<br />

7. Install slab on ground plate dowels within +/- 1/8 inch in dowel alignment in vertical and horizontal planes.<br />

8. Install slab on ground plate dowels horizontally on the bulkhead at the greater depth of either mid-slab or 2-<br />

1/4 inch from slab surface to center line of the plate.<br />

3.7 EMBEDMENTS<br />

A. Install anchor bolts and embedded bearing devices provided by others.<br />

B. Provide other anchor bolts and bearing devices shown on Drawings or anchor bolt setting plans or required<br />

equipment installation.<br />

C. Use templates as required for spacing between anchor bolts and set elevations with surveying equipment.<br />

D. Position and anchor steel shapes, anchor bolts, casings, conduit sleeves, masonry anchorages and other materials<br />

embedded in concrete.<br />

E. Place and secure against displacement miscellaneous steel, pipe sleeves, inserts, anchors, stair abrasive nosings,<br />

preformed joint filler, vapor retarders and miscellaneous embedded items.<br />

F. Secure embedments to formwork when possible.<br />

G. Install clean embedments. After concrete placement, clean embedment exposed surfaces of concrete splatter and<br />

other foreign substances.<br />

H. Unless noted otherwise on the Drawings, ensure corner protection angles, bars and other similar embedded metal<br />

items are continuous between concrete joints. If shorter lengths are required for metal items, connect the ends by<br />

butt-welding entire joint and grinding smooth exposed surface. Ensure embedded metal items are discontinued at<br />

construction, contraction and isolation joints.<br />

I. Temporarily fill voids in sleeves and inserts with easily removable materials.<br />

J. Allow sufficient time between erection of forms and placing concrete for other trades to install and test their work.<br />

K. Before placing concrete on grade, piping and other utilities under concrete shall be inspected, tested, and<br />

excavations backfilled and properly compacted to solid bearing.<br />

03312 - 15<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.8 CONVEYING<br />

A. Handle concrete from mixer to place of final deposit as rapidly as practicable and in manner which will assure<br />

obtaining specified quality of concrete.<br />

B. Re-tempering: Discard concrete which has already begun to set. Do not re-temper with water.<br />

C. Equipment: Provide mixing and conveying equipment of proper size and design to ensure a continuous flow of<br />

concrete to delivery end. Do not use aluminum pipe or equipment in contact with concrete.<br />

1. Mixers, agitators and non-agitating units: Conform to ASTM C 94 and current certification requirements<br />

of Department of Transportation in state where concrete plant is located.<br />

2. Belt Conveyers:<br />

a. Use only types which will not cause segregation.<br />

b. Discharge runs over 30 feet into hopper.<br />

3. Chutes: Metal or metal lined not to be installed at slopes greater than 1 vertical to 3 horizontal.<br />

4. Runways:<br />

a. Provide runways or other means above finished concrete level for wheeled conveying equipment.<br />

b. Do not support runways on reinforcing.<br />

c. Do not wheel equipment directly over reinforcing or metal deck.<br />

5. Pumps:<br />

a. Use pump hoses and other slickline components with 5 inch minimum inside diameter.<br />

b. For slickline reducers, reduction in diameter shall not exceed 1 inch over a 5 foot length.<br />

3.9 PLACING CONCRETE<br />

A. Unless otherwise specified, place concrete in accordance with the requirements of ACI 301.<br />

B. The following personnel shall be present during all slab placements: Contractor’s Superintendent, Concrete<br />

Subcontractor’s Finish Foreman, Concrete Supplier’s Quality Assurance Representative, and Wal-Mart<br />

Construction Testing Laboratory.<br />

C. Depositing:<br />

1. Do not deposit concrete which has partially hardened or has been contaminated by foreign matter.<br />

2. Deposit concrete continuously in layers of such thickness that no concrete will be deposited on concrete<br />

which has hardened sufficiently to cause seams or planes of weakness.<br />

3. Between construction joints, place concrete in a continuous operation such that concrete is plastic at all<br />

times and flows readily into spaces between reinforcement.<br />

4. Use placement procedures to avoid segregation.<br />

5. Deposit concrete as near as possible to its final position.<br />

6. Densified Floor Slabs: Place concrete in one continuous placement up to a maximum of 20,000 square<br />

feet. Placement over 20,000 sq ft may be performed provided written approval by Wal-Mart is obtained<br />

contingent upon the Contractor’s demonstration of ability, equipment, and personnel to handle the<br />

increased areas.<br />

7. Do not place concrete over standing water, mud, frost, ice or snow.<br />

8. Do not use wet screeds.<br />

D. Consolidation:<br />

1. Consolidate concrete complying with ACI 301 by vibrating, spading or rodding so that concrete is<br />

thoroughly worked around reinforcing, embedded items and into the corner of forms.<br />

2. Consolidate each layer of concrete with previously placed layers in manner that will eliminate air or stone<br />

pockets which may cause honeycombing, pitting or places of weakness.<br />

3. Do not insert vibrator into portions of concrete that have begun to set.<br />

4. Do not use vibrators to transport concrete.<br />

5. Keep spare vibrator on job site during concrete operations.<br />

6. Use internal vibrator for formed elements, not form vibrators.<br />

03312 - 16<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


7. Slabs:<br />

a. Consolidate and screed concrete slabs-on-ground to allow construction joint pattern as indicated on<br />

Structural Drawings and as specified. Consolidate concrete by vibrating laser screeds. Other<br />

vibratory screeding methods are acceptable only in areas where laser screed is not accessible.<br />

1) Check laser screed level head a minimum of 3 times during each pour. Use feeler gauge to<br />

measure deviations. If deviations are present, replace head with a new straight one.<br />

b. Use internal vibration along construction joints at both formed and slab abutments. Vibrate under<br />

plate dowels. Mark forms before concreting to properly locate dowels after concreting.<br />

c. Do not use grate tampers, jitterbugs, or mesh rollers.<br />

E. After concrete placement, adjust forms and bracing as necessary to maintain proper alignment and eliminate<br />

leakage of cement paste.<br />

3.10 FLOOR SLAB FINISHING<br />

A. General:<br />

1. Do not add water to any slab surface during finishing operations.<br />

2. Do not add cement to any slab surface during finishing operations.<br />

3. Perform no finishing operation while water is present on slab surface.<br />

B. Initial Leveling:<br />

1. Complete bull floating, darbying and straight-edging before any bleed water is present on slab surface.<br />

2. Use a checkrod or highway straightedge 10 feet wide minimum for initial and later leveling instead of bull<br />

float where overall floor tolerances specified are greater than FF 20 / FL15.<br />

C. Hand and Power Floating:<br />

1. Do not start floating until following conditions are met:<br />

a. Bleeding is complete and water is gone, including water sheen on slab surface.<br />

b. Concrete will sustain the weight of finishers without creating more than 1/8 to 1/4 inch indentations.<br />

c. Mortar is not thrown by rotating blades of power float.<br />

2. The finisher shall determine the proper time to start finishing procedures for interior slab placements on the<br />

basis the above conditions. It is noted for advisory purposes, however, that typical setting characteristics of<br />

concrete materials will allow for initial power floating to begin 3-1/2 hour’s ± 1 hour after initial strike-off<br />

(screeding), at which time the concrete should support a finisher on foot without more than approximately a<br />

1/4 inch indentation in the slab surface. Variations in concrete materials, nature and proportion of<br />

supplementary cementing materials, and concrete temperature will cause setting behavior to vary.<br />

3. Do not use following tools for floating:<br />

a. Power troweling machines with trowel blades.<br />

b. Fresno or other type of wide metal trowel.<br />

c. Power floating machine with water attachment for wetting concrete.<br />

4. Float three times minimum with each floating at right angles to previous floating, and final pass at 45<br />

degrees to previous pass.<br />

D. Troweling for Interior Slabs:<br />

1. Hand or power float floor before starting troweling.<br />

2. For first troweling, keep blade as flat as possible and use low speed, minimizing “washboard” or “chatter<br />

marks” and “pitting”.<br />

3. Trowel two times minimum with first two trowelings at right angles. Some burn marks are acceptable as<br />

determined in review of the test slab. Cease troweling before trowel blades scratch surface.<br />

4. Allow time between trowelings for concrete to stiffen and water sheen to disappear.<br />

5. Do not add water to slab surface during troweling.<br />

6. Do not ride trowels on existing hardened concrete slabs. Trowels shall be carried off of slab surfaces.<br />

When parking power trowels on fresh concrete, place on top of plywood or spray area with evaporation<br />

retarder before placing trowel on top of slab.<br />

E. Pitch to Drains: Form 18 inch radius around floor drains and pitch concrete surface to drains at rate of 1/4 inch per<br />

foot nominal, unless noted otherwise on the Drawings.<br />

03312 - 17<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.11 CONCRETE FINISHES<br />

A. Formed Surfaces:<br />

1. As-Cast Finish:<br />

a. Apply on concrete surfaces not exposed to public view and where noted on Drawings.<br />

b. Clip or rub off fins exceeding 1/2 inch in height. Leave surfaces with texture imparted by forms.<br />

2. Smooth-Form Finish:<br />

a. Apply on concrete surfaces exposed to public view and where noted on Drawings.<br />

b. Remove fins exceeding 1/8 inch in height.<br />

B. Unformed Finishes:<br />

1. Scratched Finish: After floating lightly scratch surface with stiff brush.<br />

C. Troweled Finish:<br />

1. After floating, power trowel or hand trowel surface.<br />

2. Ensure kneeboard impressions, trowel marks or chattered areas are not evident after floor is finished.<br />

3. Provide dense, smooth trowel surface, uniform in texture. Random, mottled burn marks are desired and<br />

acceptable. Refer to approved permanent test panel.<br />

4. Finish surface to produce maximum sheen free of scratches and trowel marks.<br />

D. Floor Finish Schedule:<br />

1. Scratched Finish: Use for surfaces to receive mortar setting beds for tile and other bonded applied<br />

cementitious finish flooring materials, except bonded concrete floor toppings.<br />

2. Troweled Finish:<br />

a. Use for exposed interior walking surfaces and surfaces to be covered with carpet, resilient flooring<br />

and other thin film finish coating systems.<br />

E. Use the following bonding procedure for bonding new concrete to existing concrete and as noted on Drawings:<br />

1. Roughen surface until coarse aggregate is exposed.<br />

2. Clean surface.<br />

3. Immediately before placing concrete, clean surface again as necessary, dampen surface and remove free<br />

water. \<br />

4. Apply a commercial epoxy bonding agent or a bonding grout composed of one part cement, 1.5 parts fine<br />

sand with 100% passing No. 8 sieve, and a 50:50 bonding admixture with water to achieve the consistency<br />

of thick paint. The water/cement ratio for bonding grout shall not exceed that of the new concrete being<br />

placed on it.<br />

3.12 JOINTS<br />

A. Provide construction, isolation, and contraction joints as indicated on Drawings and as noted below.<br />

1. Bulkheads for construction joints shall be 1-1/2 inch minimum lumber with top outside edge beveled 30<br />

degrees minimum, leaving 1/2 inch to 3/4 inch level surface. Do not use permanent preformed metal<br />

bulkheads.<br />

2. Provide bulkheads full depth of member.<br />

3. Space joints to allow one continuous placement between bulkheads.<br />

4. Maximum length-to-width ratio for concrete panels defined by walls or joints shall be 1-1/2:1.<br />

5. Do not locate longitudinal construction joints in action alleys.<br />

6. Unless otherwise shown on the Drawings, do not extend reinforcement, corner protection angles, bars, or<br />

other fixed metal items through joints in slabs or through joints between slabs on ground and vertical<br />

surfaces.<br />

7. Match joints in walls and curbs with joints in slabs on ground and pavements.<br />

8. Extend joints across tops of walls and curbs unless noted otherwise on Drawings.<br />

9. Isolation Joints: Form isolation joints in accordance with Section 07900.<br />

B. Provide contraction slab joints as indicated on Drawings.<br />

1. After saw cutting with attached vacuum system, immediately clean slab surface of all sawing residues.<br />

2. See Drawings for additional requirements.<br />

3. Saw cut to width of 1/8 inch by 1/4 the slab depth, unless noted otherwise on Drawings.<br />

03312 - 18<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Use saws, blades, skid plates, and accessories by Soff-Cut International, Inc., (951) 272-2330 or approved<br />

equal.<br />

5. Start cutting sawed joints as soon as concrete has hardened sufficiently to prevent raveling or dislodging of<br />

aggregates. This will typically be from 1 hour in hot weather to 4 hours in cold weather after completing<br />

finishing of slab in that joint location.<br />

6. Employ sufficient number of saws and workers to complete cutting saw joints before shrinkage produces<br />

cracking.<br />

7. Provide at least two Soff-Cut saws with specified vacuums on Site with blades capable of achieving the<br />

required depth of saw cut.<br />

8. Extend sawed joint to the slab boundaries and abutments, including columns, drains, and other penetrations<br />

in the path of a defined joint. Implement methods and timing of the saw cut beyond the limits of the Soff-<br />

Cut saw reach to provide a consistent depth of cut with minimal raveling of joint edges.<br />

C. Saw-Cut Control Joint Dust Collection:<br />

1. Connect a dust collection system directly to each Soff-Cut saw being used.<br />

2. Dust Collection System:<br />

a. ProVac Dust Collection System by GladTech, Inc., Nashville, TN (614) 251-8111.<br />

b. SoffVac by Soff-Cut International, Inc.<br />

D. Joint filling and sealing of concrete floors is specified in Section 07900. Joint filling of concrete floors under<br />

resilient tile and carpet floor covering is specified in Sections 09650 and 09680 respectively.<br />

3.13 CURING<br />

A. Curing Compound (Temporary Film Forming):<br />

1. Apply curing compound after saw joints have been cut and as soon as concrete surface will not be damaged<br />

by curing operations.<br />

2. Clean slab surface and joints and remove loose or compacted saw debris prior to curing compound<br />

application.<br />

3. Apply compound at a rate of 700 to 1000 square feet per gallon with high volume, low pressure, atomized<br />

sprayer in accordance with manufacturer recommendations. Prevent over-application in excess of specified<br />

rate.<br />

4. Spread compound evenly using mopping pads. Mopping pads shall be Rubbermaid 24 inch Microfiber<br />

Wet Room Pad or equivalent.<br />

5. If whitening from over application occurs, consult manufacturer for removal of product with hot water and<br />

aggressive scrubbing.<br />

6. Do not allow compound to accumulate and puddle.<br />

7. Do not use polyethylene sheets or other impervious covers on exposed interior floors.<br />

3.14 FORM REMOVAL<br />

A. Do not remove forms until concrete has hardened sufficiently to support its own weight and imposed construction<br />

loads.<br />

B. Remove forms in manner to avoid damage to concrete.<br />

C. Formwork for slabs, curbs and other parts not supporting vertical load of concrete may be removed as soon as<br />

concrete has hardened sufficiently to resist damage from removal operations, but in no case sooner than 12 hours.<br />

3.15 DENSIFIER TREATMENT<br />

A. Densifier for concrete floor slabs is specified in Section 03362.<br />

3.16 CONCRETE FLOOR POLISHING (BURNISHING)<br />

A. Burnishing concrete floor slabs which have received densifier is specified in Section 03362.<br />

03312 - 19<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.17 TOLERANCES<br />

A. Conform to most stringent requirements of ACI 117 and ACI 301 except as specified herein.<br />

B. Floor Flatness (FF) and Floor Levelness (FL): Tolerances for trowel finished slabs shall be in accordance with<br />

ACI 117 as follows:<br />

1. The minimum local area shall be bound on each side by column lines.<br />

2. Interior Slabs on Ground (Sales): Specified Overall Value (SOV) FF 50 / FL 35 and Minimum Local Value<br />

(MLV) FF 33 / FL 24.<br />

3. Interior Slabs on Ground (Non-Sales): Specified Overall Value (SOV) FF 35 / FL 25 and Minimum Local<br />

Value (MLV) FF 24 / FL 17.<br />

4. Suspended Floor Slabs: Specified Overall Value (SOV) FF 25 and Minimum Local Value (MLV) FF 20.<br />

3.18 QUALITY CONTROL BY OWNER<br />

A. Wal-Mart Construction Testing Laboratory (CTL) will perform concrete testing and inspection as specified herein<br />

at no cost to the Contractor in accordance with Section 01458.<br />

B. CTL is neither authorized to change any specified requirement nor to approve any portion of the work.<br />

C. Failure to detect defective material or Work will neither prevent rejection when defects are discovered later nor<br />

will it obligate Owner to make final acceptance.<br />

D. Responsibilities and Duties of Contractor Relative to Owner Testing:<br />

1. Notify CTL not less than 3 working days prior to placing concrete.<br />

2. Assist Owner’s agency in securing field specimens.<br />

3. Provide and maintain for sole use of CTL, facilities for safe storage and proper curing of concrete test<br />

cylinders at project site as required by ASTM C 31 and acceptable to Wal-Mart Testing Laboratory.<br />

4. Concrete Supplier and Aggregate Supplier shall have representatives available to assist CTL in obtaining<br />

representative samples.<br />

E. General:<br />

1. CTL will perform tests and inspections as specified in this Section and as indicated in Table A - Testing<br />

and Inspection Schedule at the end of this Section. CTL will keep records of the testing and inspections.<br />

F. Qualifications: Unless otherwise specified, work shall be performed by a Special Inspector - Technical II or<br />

Special Inspector - Structural I. In addition to the Inspector and CTL qualifications specified in Section 01458, the<br />

following qualifications shall apply for all Cast-in-Place Concrete inspection.<br />

1. Technical I: ACI Certified Grade I inspector.<br />

2. Technical II: ACI Certified Grade II inspector.<br />

3. CTL: C.C.R.L. certification at the National Bureau of Standards (For multi-story projects only).<br />

4. Lead technician shall have at least five years experience in projects of this size and complexity.<br />

5. Other technicians shall have at least two years experience.<br />

G. Review the Contractor's proposed materials and mix design for conformance with specifications.<br />

H. Perform testing in accordance with ACI 301 and testing standards listed in this Section.<br />

I. Field Testing:<br />

1. CTL shall notify Contractor to reject concrete if air content is over 3%.<br />

2. When pumping concrete, take additional samples for slump tests at point of delivery from pumping line.<br />

3. Stockpile Sieve Analysis: Immediately before first concrete production and later as directed by Wal-Mart<br />

Construction Manager, obtain samples at concrete plant of aggregate size groups used in pertinent mix to<br />

verify mix design submittals. Samples shall be obtained from bins as close as possible in time and space to<br />

their introduction into mixer. Perform sieve analysis on each aggregate size group, using sieve sizes<br />

specified herein. Provide following test data: percent passing each sieve, cumulative percent retained on<br />

each sieve, percent retained on each sieve, fineness modulus, and combined sieve analysis of material<br />

retained on each sieve for aggregates. Conform to ASTM C 136, C 702 and D 75. Record and report<br />

results to SER, Wal-Mart Concrete Consultant, and Wal-Mart Construction Manager.<br />

03312 - 20<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Make cylinder sets for strength testing and test concrete materials for slump, concrete temperature, air<br />

content, and platic unit weight in accordance with ASTM C 31 and ASTM C 39. Frequency of testing shall<br />

be as follows:<br />

a. All of the above sampling and testing for the first truck placement of each day a given interior slab<br />

is placed, but not less than one slump and one concrete temperature test for each 5 trucks of each<br />

interior slab placed each day, nor less than one set of cylinders, air content, and plastic unit weight<br />

test for each 15 trucks of each interior slab placed each day.<br />

b. When specified schedule of testing provides less than 5 sets of tests for a given class of concrete for<br />

all placements, test at least 5 randomly selected batches; if fewer than 5 batches are used, test each<br />

batch.<br />

c. If any test fails, repeat failed test for each following truck until compliance is met.<br />

d. Test concrete temperature hourly when air temperature is 40 F and below or 80 F and above.<br />

5. Flatness and Levelness Testing:<br />

a. Test floor slab finished surface areas shown on drawings for flatness and levelness in accordance<br />

with ASTM E 1155, except as specified herein.<br />

b. Perform testing at random on the first placement of the exposed sales floor slab and randomly on<br />

other placements as directed by the Wal-Mart Construction Manager or as directed by Owner.<br />

c. F-Number requirements shall be as follows for all interior floor slabs.<br />

1) FF /FL minimum overall for composite of measured values (SOV) for entire day’s concrete<br />

placement; FF /FL minimum for any individual floor section (MLV) as specified in<br />

Tolerances paragraph.<br />

d. Bound individual floor sections for testing purposes by the following that provide the smallest<br />

sections: Construction joints, contraction joints or column and half-column lines.<br />

e. Conform to F-numbers specified for floor areas within 2 feet of construction and isolation joints, in<br />

lieu of ASTM E 1155 requirements that exclude these areas.<br />

f. Ensure top of entire floor falls within tolerances specified in Quality Assurance Tolerances<br />

paragraph for finished floor elevation.<br />

6. Complete testing, identify defective areas, and give verbal report to Wal-Mart Construction Manager within<br />

24 hours after placement.<br />

7. Submit written report by electronic means or hand deliver to parties concerned within 36 hours or next<br />

regularly scheduled working day (Mon-Sat), after placement. Include costs for retesting replaced or<br />

repaired defective areas.<br />

8. Note trends of decreasing quality in concrete due to changing seasons, conditions of curing, or other causes<br />

and bring to attention of the Wal-Mart Construction Manager. Report and log comments on Non-<br />

Conformance Correction Log.<br />

9. Verify each delivery ticket of concrete. Report type of concrete delivered, amount of water added and time<br />

at which cement and aggregate were loaded into truck, and time at which concrete was discharged from<br />

truck.<br />

10. Verify that the proper amount of densifier has been applied to the concrete floor slab surface.<br />

J. Laboratory Testing Requirements:<br />

1. Test items such as reinforcing steel, aggregates, and other products suspected of not meeting specified<br />

requirement as directed by Wal-Mart Construction Manager to verify compliance. Provide test report to<br />

Wal-Mart Construction Manager.<br />

03312 - 21<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Conduct Strength Tests:<br />

a. Secure composite samples in accordance with ASTM C 172. Sample at regularly spaced intervals<br />

from middle portion of the batch. Sampling time shall not exceed 15 minutes.<br />

b. Make and cure concrete test specimens in conformance with ASTM C 31.<br />

c. During the initial 24 hours (plus or minus 8 hours) after molding, the temperature immediately<br />

adjacent to the specimens shall be maintained in the range of 60 to 80 degrees F. Control loss of<br />

moisture from the specimens by shielding from the direct rays of the sun and from radiant heating<br />

devices.<br />

d. Specimens transported prior to 48 hours after molding shall not be demolded, but shall continue<br />

initial curing at 60 to 80 degrees F until time for transporting.<br />

e. Specimens transported after 48 hours age shall be demolded in 24 hours (plus or minus 8 hours).<br />

Curing shall then be continued but in saturated limewater at 73 degrees (plus or minus 3 degrees F)<br />

until the time of transporting.<br />

f. During transportation, protect the specimens with suitable cushioning material to prevent damage<br />

from jarring. During cold weather, protect specimens from freezing with suitable insulation<br />

material. Transportation time shall not exceed four hours.<br />

g. Date test cylinders and number consecutively. Give each cylinder of each set an identifying letter<br />

(i.e., A, B, C, and D). Prepare a sketch of the building plan for each test set identifying location of<br />

placed concrete.<br />

3. Test cylinders in accordance with ASTM C 39.<br />

a. Test one cylinder (A) at 7 days for information. If the compressive strength of the concrete sample<br />

is equal to or above the 28 day specified strength, test another cylinder (B) at 7 days. The average<br />

of the breaks shall constitute the compressive strength of the concrete sample.<br />

b. Test two cylinders (B and C) at 28 days and the average of the breaks shall constitute the<br />

compressive strength of the concrete sample.<br />

c. Retain fourth cylinder (D) for further testing if needed, but do not retain cylinder more than 60 days.<br />

K. Reporting:<br />

1. Strength Tests: Record the following information on concrete compressive strength reports and submit to<br />

Wal-Mart Construction Manager and others as specified in Section 01458:<br />

a. Test cylinder number and letter.<br />

b. Specific foundations or structures covered by this test.<br />

c. Proportions of concrete mix or mix identification.<br />

d. Maximum size coarse aggregate.<br />

e. Measure uncapped concrete cylinder weight.<br />

f. Specified compressive strength.<br />

g. Tested compressive strength.<br />

h. Slump.<br />

i. Air content.<br />

j. Concrete temperature.<br />

k. Concrete plastic unit weight.<br />

l. Elapsed time from batching at plant to discharge from delivery truck at project.<br />

m. Date and time concrete was placed.<br />

n. Ambient temperature, wind speed, and relative humidity during concrete placement.<br />

o. Name of technician securing samples.<br />

p. Curing conditions for concrete strength test specimens (field and laboratory).<br />

q. Date strength specimens transported to laboratory.<br />

r. Age of strength specimens when tested.<br />

s. Type of fracture during test.<br />

03312 - 22<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Field Test Reports: Submit reports of field tests and inspections to Wal-Mart Construction Manager and<br />

others as specified in Section 01458. In addition to other required information noted in this Section, record<br />

the following concrete materials information on “Wal-Mart Interior Slabs on Ground Observation Report”:<br />

a. Date and time concrete was placed.<br />

b. Time of batching at plant.<br />

c. Relative humidity, ambient temperature, and base temperature during concrete placement in<br />

accordance with ACI 305.1.<br />

d. Time of placing and finishing tasks at location where sampled concrete is placed.<br />

1) Batching at plant.<br />

2) Discharge from delivery.<br />

3) Start of initial floating.<br />

4) Start of initial troweling.<br />

5) Completion of finishing.<br />

6) Start of joint sawing.<br />

7) Start of application of curing compound.<br />

L. Inspection:<br />

1. Concrete Form Work: Verify formwork dimensions will result in member size and configuration shown.<br />

Structural adequacy of formwork is the sole responsibility of the Contractor.<br />

2. Concrete Reinforcement:<br />

a. Verify reinforcing bar grade.<br />

b. Verify reinforcing bars are free of dirt, excessive rust, and damage.<br />

c. Verify reinforcing bars are adequately tied, chaired, and supported to prevent displacement during<br />

concrete placement.<br />

d. Verify proper clear distances between bars and to surfaces of concrete.<br />

e. Verify reinforcing bar size and placement.<br />

f. Verify bar laps for proper length and stagger.<br />

3. Embedded Items:<br />

a. Verify specified size, type, spacing, configuration, embedment length, and quantity of anchor bolts<br />

and embedded items.<br />

b. Verify proper concrete placement and means have been taken to achieve consolidation around bolts<br />

and embedded items.<br />

4. Slab-on-Grade Structural Inspection: Inspect slabs-on-grade. Report on the following:<br />

a. Preparation of subgrade.<br />

b. Slab thickness.<br />

c. Size, spacing, placement (cover), and lap of reinforcement.<br />

d. Size, spacing, and placement of joint dowels.<br />

e. Placement and finishing of concrete.<br />

f. Time of saw cuts after placement of concrete.<br />

5. Concrete Mix:<br />

a. Verify mixer truck trip ticket conforms to approved mix design.<br />

b. Verify that total water added to mix on site does not exceed that allowed by concrete mix design<br />

based on the concrete company having calibrated or verified the accuracy of the water meters on<br />

each truck and the available water indicated on the ticket by the concrete supplier.<br />

c. Verify that concrete quality is indicative of adequate mixing time, consistency, and relevant time<br />

limits.<br />

d. Work shall be performed by a Special Inspector – Technical I. Report of results shall be made daily.<br />

6. Preparation and Placement: Inspect preparation and placement of concrete.<br />

a. Verify acceptable general condition of concrete base prior to placement.<br />

b. Verify that concrete conveyance and depositing avoids segregation and contamination.<br />

c. Verify that concrete is properly consolidated.<br />

d. Verify reinforcement remains at proper location.<br />

e. Inspections shall be continuous.<br />

7. Protection and Curing: Observe protection and curing methods for all concrete.<br />

a. Verify specified curing procedures are followed.<br />

b. Verify that specified hot and cold weather procedures are followed.<br />

03312 - 23<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


8. Slab Joint Filler: Inspect floor slab joint filler installation at beginning of installation and periodically<br />

thereafter for proper installation including cleaning, joint prep, and depth of fill. Randomly check depth of<br />

filled joints at intervals of approximately every 1000 linear ft of joint. Document and report discrepancies<br />

to Wal-Mart Construction Manager and Contractor.<br />

3.19 NON CONFORMING WORK<br />

A. When directed by Owner, remove and replace or repair concrete related Work which does not conform to specified<br />

requirements including strength, tolerances and finishes.<br />

B. When directed by Owner, remove and replace slabs-on-ground with surfaces measuring below either specified Ff<br />

and Fl minimum local values.<br />

C. At option of Owner, Contractor may be allowed to submit alternatives for remediation to slabs-on-ground<br />

measuring below either or both specified Ff and Fl minimum local values.<br />

D. Costs for corrective work, remedies for out-of-tolerance work, and extra testing as required by defective work<br />

shall be borne by Contractor.<br />

3.20 PROTECTION<br />

A. Slab Protection:<br />

1. Protect slabs from staining prior to application of densifier specified in Section 03362.<br />

2. Protect finished floors to prevent damage including staining, gouges and scratching by construction traffic<br />

and activities until Owner possession.<br />

a. Barricade concrete surfaces immediately after placing and finishing.<br />

b. 3 days after placement: Foot traffic permitted. No construction materials in contact with slab<br />

surface.<br />

c. 5 days after placement: Scissor lift traffic permitted.<br />

d. 9 days after placement: Heavy traffic permitted but not before concrete has obtained, by test, its<br />

design strength as noted on Drawings.<br />

3. Keep slabs free from dirt and grime.<br />

4. Provide impact protection to slab with approved sheet materials. Remove or consolidate impact protection<br />

materials on a regular basis to prevent discoloring. The use of plastic sheets for impact protection is<br />

prohibited.<br />

5. Prohibit foot traffic by workers and others not involved in floor construction or finishing operations in<br />

areas where floor construction or finishing operations are being performed.<br />

6. Vehicles and equipment may be driven on concrete surface within building line only if the slab is protected<br />

by the following:<br />

a. Diaper hydraulically-powered equipment.<br />

b. Place non-absorbent drop cloths or other breathable slab protection that will not stain slab surface<br />

under parked vehicles.<br />

c. Vehicles and equipment are equipped with non-marking tires.<br />

d. Tire treads are inspected for debris prior to use on slab and a least once per day. Remove embedded<br />

items which may cause damage to floor slab.<br />

7. Clean up spills on slab immediately. Provide cleaning chemicals and absorptive materials.<br />

8. Storage of structural steel or metal fabrications is prohibited on concrete surface within building line.<br />

9. Storage of construction materials is prohibited on sales floor surface.<br />

10. Pipe cutting machinery is prohibited on concrete surface within building line.<br />

11. Adequately protect concrete inserts and other embedded items from movement, mechanical injury, or from<br />

damage by elements.<br />

12. Provide access ramps of compacted earth or other means along exposed concrete edges of floor slabs to<br />

prevent equipment and machinery from impacting edges. Barricade other exposed edges to vehicular<br />

traffic which may damage edges.<br />

B. Concrete Floor Protection Plan: Develop Concrete Floor Protection Plan that addresses the following procedures:<br />

1. Communication of protection plan to subcontractors and vendors, including those directly contracted by the<br />

Owner.<br />

2. Procedures for compliance with slab protection requirements specified in this Section.<br />

03312 - 24<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. When and how floor covering protection will be provided in high traffic areas.<br />

4. Condition, inspection, and operational procedures for construction equipment allowed on the slab surface.<br />

5. Procedures for cleaning up slab spills, including use of and availability of cleaning chemicals and<br />

absorptive materials at Site.<br />

C. Submit Concrete Floor Protection Plan as specified in Part 1 of this Section. Comply with the requirements of<br />

approved Concrete Floor Protection Plan.<br />

3.21 CLEANING<br />

A. Provide daily scrubbing, using only water, of the entire exposed concrete slab surface with fuel powered riding<br />

equipment from time of dried initial application of surface densifier until time of store turnover.<br />

END OF SECTION<br />

03312 - 25<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


WAL-MART STORES<br />

CONCRETE SLAB MIX DESIGN SUBMITTAL FORM<br />

(Section 03312 – Cast-in-Place Concrete Slabs)<br />

Date ________________________<br />

DISCOUNT STORE SUPERCENTER MARKET SAM’S CLUB<br />

SUBMITTED MIX DESIGN<br />

Interior Building Slabs STORE #<br />

03312-SLN Natural Concrete (gray) ADDRESS<br />

Mix ID # ____________________________ CITY, ST<br />

STORE INFORMATION<br />

03312-SLC Integrally Colored Concrete GENERAL CONTRACTOR<br />

Mix ID # ____________________________ COMPANY<br />

* Same basic proportions for all interior slab concrete JOBSITE PHONE<br />

A. CONCRETE INFORMATION<br />

Design Strength (f ’ c)<br />

psi<br />

Water / Cementitious Ratio<br />

Total Air Content %<br />

Mix Developed From<br />

Trial Mix Test Data (attach test data)<br />

Field Experience (attach data)<br />

Density<br />

Wet pcf Dry pcf<br />

Slump<br />

“ ( ± 1” ) WITHOUT WR Admixture<br />

“ ( ± 1” ) WITH WR Admixture<br />

Ambient Conditions for which mix is valid<br />

Temperature Min. __________ Max. __________<br />

Special requirements for pumping:<br />

Special characteristics of mix which require precautions in<br />

mixing, placing, or finishing techniques to achieve finished<br />

product specified:<br />

Humidity Min. __________ Max. __________<br />

B. ADMIXTURE INFORMATION<br />

ASTM Designation Product Dosage (ounces)<br />

(Manufacturer/Brand) oz / cy oz / cwt<br />

Water Reducing<br />

Water Reducing and Retarding<br />

Accelerating<br />

Integral Color<br />

03312 - 26<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. MIX DESIGN<br />

Cement<br />

Fly Ash<br />

Slag (GGBFS)<br />

Coarse Aggregate #1<br />

Mix Proportions (per cubic yard)<br />

Identification<br />

Weight<br />

(Type, size, source, etc.)<br />

(pounds)<br />

Density<br />

(SSD)<br />

Volume<br />

(cubic feet)<br />

% Aggregate<br />

Absorption<br />

#2<br />

#3<br />

Fine Aggregate #1<br />

#2<br />

Water<br />

Air Content<br />

Liquid Color<br />

TOTALS<br />

Sieve<br />

Size<br />

1-1/2"<br />

1"<br />

3/4"<br />

1/2"<br />

3/8"<br />

# 4<br />

# 8<br />

# 16<br />

# 30<br />

# 50<br />

# 100<br />

# 200<br />

% of Vol<br />

Coarse<br />

Agg. # 1<br />

Coarse & Fine Aggregate Gradation Information<br />

% Passing Each Sieve<br />

(All Sieve Sizes must be entered)<br />

Coarse<br />

Agg. # 2<br />

Coarse<br />

Agg. # 3<br />

Fine<br />

Agg. # 1<br />

Combined % Retained<br />

Fine<br />

Agg. # 2<br />

Combined<br />

% Passing Cumulative Individual<br />

Aggregate Ratios<br />

Coarseness Factor =<br />

Combined % cumulative retained 3/8” sieve<br />

Combined % cumulative retained #8 sieve<br />

=<br />

Workability Factor = Combined % passing #8 sieve =<br />

Adj-Workability Factor = WF + [(Cementitious Material - 564) ÷ 37.6] =<br />

Allowable Adj-WF= Adj-WF = [(11.25 - .15 CF) + 36] ± 2.5 = Low High<br />

03312 - 27<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. ATTACHMENTS: Include the following with this Mix Design Report.<br />

Mill test reports for Portland cement, fly ash, and ground granulated blast furnace slag materials<br />

Designation, type, quality, and source (natural or manufactured) of coarse and fine aggregate materials<br />

Separate aggregate gradation reports including all required sieve sizes<br />

• Gradation sieve report tests dated within 60 days of this report<br />

• Report for each coarse and fine aggregate material in mix<br />

Statement if possible reactivity of aggregate, based on tests or past service<br />

Statement if possible aggregate pop-outs or their disruptions, based on tests or past service<br />

Product data for the following admixtures:<br />

• Chloride ion data and related calculations<br />

• Water reducing<br />

• Water reducing and retarding<br />

• Accelerating<br />

• Integral color<br />

Concrete compressive strength data used for standard deviation calculations<br />

Measured water-soluble chloride ion content. (percent by weight of cement)<br />

Time of initial setting per ASTM C 403.<br />

E. CONCRETE SUPPLIER INFORMATION<br />

Company Name Tel. # ( )<br />

Address<br />

City, ST Zip<br />

Technical Contact Cell # ( )<br />

e-mail<br />

Sales Contact Cell # ( )<br />

PRIMARY PLANT<br />

SECONDARY PLANT<br />

Plant Location:<br />

Miles from Site:<br />

Travel Time to Site:<br />

NRMCA Certified: YES NO YES NO<br />

State DOT Certified: YES NO YES NO<br />

Batch Mixing Type: DRY CENTRAL MIX DRY CENTRAL MIX<br />

03312 - 28<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CONCRETE FINISHING SUBCONTRACTOR'S QUALIFICATION STATEMENT<br />

SECTION 03312<br />

CAST-IN-PLACE CONCRETE SLAB<br />

Project Location:_______________________________________________Date:<br />

Project Number:____________________________Store Number:<br />

By signing below Contractor confirms that the concrete finishing subcontractor meets the following requirements:<br />

The concrete finishing subcontractor lead finisher and two additional members of the finishing crew are certified under the<br />

Concrete Flatwork Finisher Training and Certification Program as granted by the American Concrete Institute.<br />

The concrete floor finishing subcontractor has experience in finishing interior floors of similar size and scope in at least 5<br />

previous projects. The names and locations of these projects are as follows:<br />

1. ___________________________________________________________________<br />

2. ___________________________________________________________________<br />

3. ___________________________________________________________________<br />

4. ___________________________________________________________________<br />

5. ___________________________________________________________________<br />

Concrete Finishing Subcontractor Company Name and Address:<br />

__________________________________________<br />

__________________________________________<br />

__________________________________________<br />

Signature of Responsible Officer: _________________________<br />

Typed Name and Title of Officer: _________________________<br />

Telephone Number: ( ______ ) ___________________________<br />

Contractor Company Name and Address:<br />

_______________________________________<br />

_______________________________________<br />

Signed by:<br />

______________________________________ Date:_________________<br />

Attach certificates from the Concrete Flatwork Finisher Training and Certification Program for lead finisher and two<br />

additional members of the finishing crew.<br />

Submit one copy of this Statement to the Architect.<br />

03312 - 29<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CONCRETE SUBMITTAL REGISTER SUMMARY<br />

(Reference Submittals paragraph in Part 1 for submittal details.)<br />

SUBMITTAL SUBMIT TO SUBMITTAL DUE<br />

Concrete Finishing Subcontractor’s Qualification<br />

Statement<br />

• 3 ACI Finisher Certifications<br />

Architect<br />

30 days prior to first pour<br />

Concrete Batch Plant Certification<br />

• NRMCA Certification<br />

• DOT Certification<br />

Sieve Analysis for Aggregate Base System<br />

• Aggregate Base Material<br />

• Choker Material<br />

Mix Design<br />

• One mix for all interior slabs<br />

• Submit on form provided<br />

Attachments to Concrete Mix Design<br />

• Mill test reports<br />

• Concrete aggregate designation, type,<br />

type, quality, & source<br />

• Sieve analysis for concrete aggregate<br />

• Concrete Aggregate Supplier Statement<br />

• Product data for concrete admixtures<br />

• Concrete compressive strength data<br />

• Chloride-Ion content<br />

• Time of initial setting<br />

Architect<br />

Architect (by email)<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL) (by email)<br />

Architect (by email)<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL) (by email)<br />

Structural Engineer of Record (by<br />

email)<br />

Wal-Mart Construction Manager<br />

(by email)<br />

Architect (by email)<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL) (by email)<br />

Structural Engineer of Record (by<br />

email)<br />

Wal-Mart Construction Manager<br />

(by email)<br />

30 days prior to first pour<br />

30 days after award of<br />

Contract<br />

30 days prior to first pour<br />

30 days prior to first pour<br />

Concrete Supplier Approval<br />

Slab Reinforcing Bar Shop Drawings<br />

• Installation details<br />

Perimeter foundation tie reinforcing submittals are<br />

submitted under Section 03310.<br />

Architect (by email)<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL) (by email)<br />

Submit to Wal-Mart Concrete<br />

Consultant at or prior to Pre-Slab<br />

meeting.<br />

Architect<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL)<br />

30 days prior to first pour<br />

30 days prior to first pour<br />

03312 - 30<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CONCRETE SUBMITTAL REGISTER SUMMARY<br />

(Reference Submittals paragraph in Part 1 for submittal details.)<br />

SUBMITTAL SUBMIT TO SUBMITTAL DUE<br />

Product Data<br />

• Dowels at construction joints.<br />

• Dowels at sawed joints<br />

• Vapor retarder<br />

• Curing compound<br />

Architect<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL)<br />

30 days prior to first pour<br />

Slab Joint and Placement Plan<br />

Pre-slab Installation Meeting<br />

• Record of notification<br />

Meeting agenda<br />

• Meeting minutes<br />

Architect<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL)<br />

Wal-Mart Concrete Consultant<br />

Wal-Mart Construction Manager<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL)<br />

30 days prior to first pour<br />

3 days after meeting.<br />

Concrete Floor Protection Plan Wal-Mart Construction Manager Prior to first pour<br />

Delivery Tickets<br />

Wal-Mart Construction Testing<br />

Laboratory (CTL)<br />

With delivery of each load<br />

03312 - 31<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


TABLE A<br />

TESTING AND INSPECTION SCHEDULE<br />

Description of Verification and Inspection Work Inspection Frequency Referenced Standard<br />

Inspect formwork for shape, location, and dimensions<br />

of the concrete member being formed.<br />

Periodic ACI 318: Ch 6.1.1<br />

Inspect of reinforcing steel and placement. Periodic ACI 318: Ch 3.5, 7.1-7.7<br />

Inspect bolts to be installed in concrete prior to and<br />

during placement of concrete.<br />

Slab on Grade Structural Inspection.<br />

Continuous<br />

Continuous<br />

Verify use of approved design mix Periodic ACI 318:<br />

Ch 4, 5.2-5.4<br />

Inspect concrete placement for proper application<br />

techniques.<br />

Inspect maintenance of specified curing temperature<br />

and techniques.<br />

Continuous ACI 318: Ch 5.9, 5.10<br />

Periodic ACI 318: Ch 5.11-5.13<br />

Inspect slab joint filler.<br />

Test concrete materials for slump, concrete<br />

temperature, air content, compressive strength, and<br />

plastic unit weight<br />

Periodic<br />

ASTM C 172<br />

ASTM C 31 & C 39<br />

ACI 318: Ch 5.6, 5.8<br />

AASHTO T318<br />

03312 - 32<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


03312 - 33<br />

Walmart SC #5641 – La Habra, CA<br />

PWO – 04/11/11


03312 - 34<br />

Walmart SC #5641 – La Habra, CA<br />

PWO – 04/11/11


Unispec 093011<br />

SECTION 03362 (03 3562) – BURNISHED CONCRETE FLOOR FINISHES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Application of densifier and burnishing of concrete floor slabs.<br />

B. Related Requirements:<br />

1. Section 03312 - Cast-In-Place Concrete Slabs (Interior): Concrete for interior slabs on grade.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C1028 - Standard Test Method for Determining the Static Coefficient of Friction (SCOF) of<br />

Ceramic Tile and Other Like Surfaces by the Horizontal Dynamometer Pull-Meter Method.<br />

1.3 SUBMITTALS<br />

A. Submittals: Comply with the requirements of Section 01330.<br />

B. Submit to Architect specified in Section 01330 and to the Wal-Mart Construction Testing Laboratory specified in<br />

Section 01458.<br />

C. Product Data:<br />

1. Densifier: Brand name, chemical composition, installation directions and certificates of compliance with<br />

required standards. Submit 30 days prior to first concrete placement.<br />

2. Burnishing Pads: Submit product data for burnishing pads prior to beginning burnishing operations to<br />

verify pad texture.<br />

D. Applicator Qualifications:<br />

1. Provide documentation showing densifier applicator is certified by the densifier manufacturer.<br />

2. Letter shall be from the product manufacturer stating that the installer is qualified and certified by the<br />

manufacturer to install the material to be used, citing the specific project and location.<br />

3. Provide list of a minimum of 5 projects performed within the last 3 years of similar type, size and<br />

complexity as this contract.<br />

4. Submit 30 days prior to first concrete placement.<br />

E. Provide name of technically qualified densifier manufacturer’s field representative.<br />

1.4 QUALITY ASSURANCE<br />

A. A technically qualified manufacturer’s field representative of the densifier product shall be on site during the<br />

initial application of the densifier and occasional observations during remainder of the applications.<br />

B. Ensure that the correct amount of densifier is onsite and in numbered containers prior to commencement of work.<br />

1.5 PRODUCT DELIVERY, STORAGE AND HANDLING<br />

A. Dispense densifier material from factory numbered and sealed drums. Maintain record of drum numbers.<br />

03362 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.6 ENVIRONMENTAL REQUIREMENTS<br />

A. Limit and control damage from excessive dust caused by burnishing.<br />

B. Limit and control damage from moisture. Remove standing moisture from floor after densifier application.<br />

1.7 WARRANTY<br />

A. Provide manufacturer’s standard warranty for replacement of defective densifier products.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with project requirements, provide products as manufactured by the following to the extent<br />

as specified hereinafter for the specific product:<br />

1. 3M (888) 364-3577.<br />

2. Concrete Polishing Solutions (CPS) (877) 472-8200.<br />

3. Convergent Concrete Technologies, Orem, UT (866) 375-2280.<br />

4. Stonekor LLC (800) 633-0519.<br />

5. ETC of Henderson, Inc. (800) 334-6651.<br />

6. HTC (877) 482-8700.<br />

7. Norton (Saint-Gobain Abrasives).<br />

8. Pioneer Eclipse (800) 367-3550.<br />

9. Prosoco, Lawrence, KS, (866) 363-4567.<br />

10. SealSource International, Orem, Utah, (800) 305-9144.<br />

11. VIC International Corporation (800) 423-1634.<br />

2.2 DENSIFIER PRODUCTS<br />

A. Pre-Densifier Floor Cleaner: As recommended by densifier manufacturer.<br />

B. Densifier: Concrete lithium based chemical densifier specifically for concrete surface treatment which reacts<br />

chemically to the concrete surface forming a clear, dense, durable, hard, abrasion-resistant surface. Product shall<br />

be a colorless, odorless, water-based solution that is less than 50 g/L VOC.<br />

1. Prentra-Sil (NL) by Convergent.<br />

2. Consolideck LS by Prosoco.<br />

3. SS Harden X by SealSource.<br />

C. Sprayer: Manufacturer approved high volume, low pressure sprayer and sprayer tip.<br />

2.3 POLISHING PRODUCTS<br />

A. Burnishing Pads: Pads as follows or equivalent as required to produce specified results:<br />

1. Diamond Impregnated Pads:<br />

a. Twister Diamond Cleaning System Pads by HTC.<br />

b. Diamond Polishing Pads by Norton.<br />

c. SpinFlex Diamond Polishing Pads by CPS.<br />

d. Scotch-Brite Diamond Floor Pads Plus by 3M.<br />

e. Optima pad system by VIC.<br />

2. Hogs Hair Pads:<br />

a. Niagra Super Hogs Hair Floor Pad 3700N by 3M.<br />

b. Ultra Grizzly Bear by Norton.<br />

c. Consolideck Heat Pad by Prosoco.<br />

03362 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 EQUIPMENT<br />

A. Scrubber Machines: Equipment used for cleaning operations shall be Clark Encore Max38 or L38 with a head<br />

pressure of 150 lbs. or similar equipment as required to produce the specified results.<br />

B. Burnishing Machine: High speed propane burnisher, with a minimum 27 inch head generating pad speeds of<br />

1,500 RPM or higher as verified with tachometer.<br />

PART 3 - EXECUTION<br />

3.1 GENERAL CLEANING AND BURNISHING REQUIREMENTS<br />

A. Coordinate with joint filling operations. Do not perform wet cleaning within 72 hrs prior to joint filling.<br />

B. Do not use stain or scuff removing agents such as “crete-strip”.<br />

C. Clean floors as specified hereinafter prior to application of densifier.<br />

D. Burnish floors as specified hereinafter after application of densifier.<br />

E. Utilize riding machines to the maximum extent practical to achieve optimum efficiency.<br />

F. Final finish sheen shall be equivalent to that as accepted on the Floor Test Slab as specified in Section 03312 and<br />

in this Section.<br />

3.2 CLEANING<br />

A. Use sweeping compound to control airborne dust. Scrape floor to remove remaining saw cut residue and paint<br />

droppings. Remove paint droppings with soft, damp cloth and solvent stripper. Do not use stripper with an acidic<br />

pH.<br />

B. Treat oil spots with oil emulsifier and oil absorber materials.<br />

C. Double scrub floor with scrubber machine and appropriate brushes or pads and pH compatible detergent.<br />

3.3 DENSIFIER APPLICATION<br />

A. Area to be Treated: Apply densifier to all interior concrete floors except floors to receive resilient flooring.<br />

B. Examination and Preparation:<br />

1. Examine surfaces receiving densifier. Verify that surfaces conform to product manufacturer's requirements<br />

for substrate conditions.<br />

2. Vacuum and clean saw cut joints and surrounding area so that no dust remains to react with concrete finish<br />

material.<br />

3. Remove remnant of temporary film forming curing compound prior to application of densifier. Remove<br />

compound by cleaning and scrubbing in accordance with manufacturer’s instructions.<br />

4. Scrub floor with pre-densifier floor cleaner to remove latent salts.<br />

5. Verify floor is free of curing membrane, bond-breaker, and construction laitance.<br />

6. Do not proceed until unsatisfactory conditions have been corrected.<br />

C. Application:<br />

1. Application shall be performed by certified applicator in accordance with manufacturers published<br />

instructions.<br />

2. Schedule to begin 7 days after floor slab placement.<br />

3. Employ methods to ensure concrete surface is not damaged during application, including discoloration.<br />

4. Apply densifier finish at the rate of 500 square feet per gallon.<br />

03362 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. Apply with low pressure sprayer with enough coverage to keep concrete surface wet for minimum 20<br />

minute period.<br />

6. Apply second coat of densifier 2 weeks prior to Owner Possession, apply over surfaces to which densifier<br />

has been applied.<br />

7. Apply densifier finish at the rate of 1000 square feet per gallon.<br />

8. Apply with low pressure sprayer with enough coverage to keep concrete surface wet for minimum 20<br />

minute period.<br />

3.4 BURNISHING PROCEDURE<br />

A. Allow second coat of densifier to dry.<br />

B. Burnish at a slow movement pace using burnishing machine with 800 grit diamond impregnated or hogs hair<br />

burnishing pads.<br />

C. Continue burnishing operations until the specified gloss is attained. Achieve specified gloss not later than two<br />

weeks prior to Owner Possession and maintain specified gloss levels until Owner Possession.<br />

D. Provide final burnishing prior to Owner Possession to eliminate any scratches resulting from construction<br />

operations.<br />

3.5 FINISH REQUIREMENTS<br />

A. Gloss: Final surface gloss shall be a Specified Overall Gloss Value (SOGV) of not less than 40 and a Minimum<br />

Local Gloss Value (MLGV) of 30 as measured using a Horiba IG-320 Gloss Checker.<br />

B. Slip Resistance: Measured static coefficient of friction (SCOF) shall be not less than 0.50 as measured in<br />

accordance with ASTM C 1028, at time of Owner Possession.<br />

3.6 FLOOR PROTECTION<br />

A. Protect finished floor from construction traffic and weather until time of Owner Possession.<br />

B. Prohibit acids and acidic detergents to come in contact with slab.<br />

3.7 PRODUCT DISPOSAL<br />

A. Upon completion of densifier application, dispose of excess material as required by local Authority Having<br />

Jurisdiction.<br />

B. Certified applicator shall remove densifier product containers from job site immediately upon completion of<br />

treatment.<br />

3.8 QUALITY CONTROL TESTING (BY OWNER)<br />

A. Testing will be performed by Wal-Mart’s Construction Testing Laboratory (CTL) at no expense to the Contractor.<br />

A test report of all measurements and a plan and table of the measurements taken will be prepared by the CTL for<br />

submission.<br />

B. Gloss measurements will be taken at 2 weeks prior to Owner Possession and at time of Possession. Contractor<br />

shall notify CTL when floors are ready for testing.<br />

C. Measurement and reporting of SOGV and MLGV by CTL shall be as follows:<br />

1. Collect a minimum of three samples per each bay in random, evenly distributed locations.<br />

2. Record measurement locations on copy of sheet S1.1.<br />

3.<br />

03362 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. The average of all samples collected in each bay shall meet or exceed the SOGV.<br />

a. If the average of samples collected do not meet the SOGV, collect an additional 3 samples in each<br />

bay for each deficient result unless the individual samples fail to meet the MLGV or the average of<br />

all collected samples in each bay fail to meet the SOGV.<br />

b. If samples fail to meet the SOGV, Contractor shall continue burnishing operations until the SOGV<br />

is achieved.<br />

5. No single measured value shall be less than MLGV.<br />

a. If one or more samples fall below the MLGV, continue burnishing operations until all samples<br />

comply with Specified MLGV and SOGV.<br />

6. Collect and certify final gloss measurements.<br />

D. Slip resistance measurements will be taken at 2 weeks prior to Owner Possession and at time of Possession.<br />

Contractor shall notify CTL when floors are ready for testing. Measurement and reporting shall be in accordance<br />

with ASTM C1028.<br />

END OF SECTION<br />

03362 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 092410<br />

SECTION 03363 (03 3563) – BURNISHED CONCRETE FLOOR FINISHES (EXISTING FLOORS)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Removal of existing floor finishes (sealers, coatings, tile, etc.) and underlayments,as necessary.<br />

2. Grinding of slab surface to receive densifier treatment.<br />

3. Application of densifier.<br />

4. Progressive burnishing of slab surface to achieve required gloss values.<br />

B. Related Requirements:<br />

1. Section 03312 - Cast in Place Concrete Slabs (Interior): Concrete for new floors and control joint filler.<br />

2. Section 03362 - Burnished Concrete Floor Finishes: Burnished concrete floor finishes for new floors.<br />

3. Section 03930 - Concrete Rehabilitation.<br />

1.2 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-installation Meeting:<br />

1. Schedule Pre-installation Meeting to be conducted a minimum of one day prior to first burnishing of<br />

existing concrete slab and after installation of mockup and required submittals have been approved.<br />

2. Obtain meeting agenda from Wal-Mart Concrete Consultant Structural Services, Inc., (214) 522-6438.<br />

3. Notify required attendees in writing of scheduled time and meeting location a minimum of 14 days in<br />

advance of Pre-installation Meeting. Include copy of agenda with invitation.<br />

4. Attendees shall include personnel directly involved in overseeing the work, including but not limited to the<br />

following:<br />

a. Wal-Mart Construction Manager.<br />

b. Wal-Mart Store Manager.<br />

c. Wal-Mart Concrete Consultant.<br />

d. General Contractor.<br />

1) Project Manager.<br />

2) Superintendent (overseeing burnishing work).<br />

e. Concrete Burnishing Subcontractor.<br />

1) Project Manager.<br />

2) Foreman (representative that will be present during all phases of work).<br />

f. Joint Filler Replacement and Slab Repair Subcontractor (if separate).<br />

g. Wal-Mart Construction Testing Laboratory representative.<br />

h. Manufacturers’ representatives for products specified in this Section.<br />

5. Convene meeting only when all required parties are in attendance.<br />

6. Review the following:<br />

a. Expectations of finished work specified.<br />

b. Scheduling and phasing of work.<br />

c. Coordination with other work and personnel.<br />

d. Environmental requirements (store working conditions).<br />

e. Existing joint filler replacement.<br />

f. Repair of existing slab defects.<br />

g. Grinding and burnishing procedures, including application of liquid densifier system.<br />

h. Field quality control requirements.<br />

i. Slab protection after completion of work.<br />

j. Protection of adjacent surfaces.<br />

k. Surface preparation.<br />

l. Repair of defective work.<br />

m. Cleaning.<br />

n. Application of floor finish.<br />

03363 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


7. Record and distribute minutes to all parties in attendance within 2 days of the meeting via e-mail in .pdf<br />

format. Completed pre-installation meeting agenda is acceptable.<br />

B. Coordination, Sequencing and Scheduling:<br />

1. Floor Burnishing Plan Schedule: Provide detailed written schedule for sequence of work to ensure<br />

uninterrupted progress of Owner's on-site operations.<br />

2. Coordinate project phasing and relocation of racking, shelving, or merchandise to ensure minimum<br />

interference with other aspects of the Work. This may require Applicator to mobilize multiple times on a<br />

given project.<br />

3. Conduct grinding and burnishing work in manner to minimize disruption of Owner's normal operations.<br />

Work shall be performed after normal hours of operation and shall be completed (including cleanup) each<br />

day prior to start of normal store operations.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Product Data:<br />

1. Manufacturer and model of equipment to be used, including all types of grinding heads, saws, and dust<br />

extraction systems for burnishing, joint filler replacement, and slab defect repairs.<br />

2. Reactive surface densifying system including stain guard treatment.<br />

C. Applicator Qualifications:<br />

1. At least 5 projects of similar type, size, and complexity to Project performed by Applicator within last three<br />

years. Submit project names, addresses, contacts, and phone numbers for each project.<br />

2. Manufacturer’s certification, identifying the individuals that are currently certified applicators of the system<br />

and are familiar with proper procedures and installation methods as required by the manufacturer for:<br />

a. Surface densifier system.<br />

b. Joint filler replacement materials (specified in Section 03930).<br />

c. Surface defect repair materials (specified in Section 03930).<br />

3. At least one installer for work requiring certification, possessing manufacturer’s documents that<br />

state this individual has been specifically trained and certified, shall be present during all installations of<br />

such work.<br />

D. Floor Burnishing Plan:<br />

1. Prior to commencement of work, submitFloor BurnishingPlan (developed from Sheet A-1 “Floor Plan”)<br />

including:<br />

a. Size, locationand anticipated progression of individual nightly work areas.<br />

b. Location of cracks, spalls and other surface defects requiring repairs.<br />

c. Electrical supply locations, including exterior access if generators are utilized.<br />

2. Use plan to document gloss value measurements, as reported weekly from CTL.<br />

3. Floor Burnishing Plan shall be reviewed and accepted by Wal-Mart Construction Manager and Store<br />

Manager prior to start of work.<br />

E. Test Results:<br />

1. Submit final floor gloss and slip resistance test reports (prepared by Wal-Mart’s Construction Testing<br />

Laboratory (CTL)) to Wal-Mart Concrete Consultant and Wal-Mart Construction Manager.<br />

1.4 CLOSEOUT SUBMITTALS<br />

A. Comply with the requirements of Section 01770.<br />

B. Maintenance Data: Submit 7 sets of maintenance data as follows:<br />

1. Manufacturer’s technical product data and literature.<br />

2. Storage and handling requirements and recommendations.<br />

3. Manufacturer’s safety data sheets and related safety requirements.<br />

4. As-built Floor Burnishing Plan.<br />

03363 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. Methods of maintaining burnished concrete, including a listing of approved cleaning and stain removal<br />

products and procedures.<br />

6. Manufacturer’s recommended maintenance schedule.<br />

7. Precautions for cleaning materials and methods that could be detrimental to burnished concrete.<br />

1.5 QUALITY ASSURANCE<br />

A. Mock-Up: Prior to commencement of work, prepare mock-up for evaluation of surface preparation techniques and<br />

application workmanship.<br />

1. Designate250 square feet for mock-up of system specified, using same materials, tools, equipment, and<br />

procedures intended for actual surface preparation in Sales floor at location determined by the Wal-Mart<br />

Construction Manager. Include properly prepared slab joints, surface spalls and crack repairs if available.<br />

Include slab edges adjoining existing partitions/walls.<br />

2. Notify Wal-Mart Construction Manager minimum 7 days prior to date and time when mock-ups will be<br />

performed and completed.<br />

3. Choose mock-up location that demonstrates proposed range of aesthetic effects and workmanship.<br />

4. Obtain Wal-Mart Construction Manager’s approval of mock-ups before proceeding with work.<br />

5. Maintain mock-ups during construction in undisturbed condition as a standard for judging completed work.<br />

6. Approved mock-ups installed in sales areas may become part of the completed work if acceptable to Wal-<br />

Mart Construction Manager.<br />

1.6 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Deliver materials to site in original, factory sealed, unopened, new containers (drums) bearing manufacturer’s<br />

name and label intact and legible, with the following information:<br />

1. Name or title of material.<br />

2. Manufacturer’s standard container (drum) numbers.<br />

3. Application instructions.<br />

C. Storage:<br />

1. Store materials in protected and well-ventilated area at temperatures between 40 and 90 degrees F unless<br />

otherwise required by manufacturer.<br />

2. Keep containers sealed until ready for use.<br />

3. Do not use materials beyond manufacturer’s shelf life limits.<br />

D. Handling:Protect materials during handling and application to prevent damage or contamination.<br />

1. Dispense penetrating liquid densifier only from factory sealed and numbered containers (drums).<br />

2. Maintain record of container (drum) numbers received and used during floor treatment.<br />

1.7 ENVIRONMENTAL REQUIREMENTS<br />

A. Limit and control damage from excessive dust and moisture caused by surface preparation and burnishing.<br />

B. Comply with manufacturer's written instructions for substrate temperature and moisture content, ambient<br />

temperature and humidity, ventilation and other conditions affecting product performance.<br />

C. Replaced concrete shall be cured a minimum of 28 days or until such point equipment can be put on slab without<br />

displacing aggregate.<br />

D. Air and Surface Temperatures: Prepare surfaces and apply and cure coatings within air and surface temperature<br />

range in accordance with densifier manufacturer’s instructions.<br />

E. Comply with manufacturer’s written instructions for substrate temperature and moisture content, ambient<br />

temperature and humidity, ventilation, and other conditions affecting densifier performance.<br />

03363 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.8 WARRANTY<br />

A. Provide manufacturer’s standard warranty for replacement of defective densifier products.<br />

PART 2 - PRODUCTS<br />

2.1 REGULATORY REQUIREMENTS<br />

A. Accessibility Requirements: Comply with applicable requirements of the Americans with Disabilities Act<br />

Accessibility Guidelines (ADAAGs) for Buildings and Facilities; Final Guidelines, revisions, and updates for<br />

static coefficient of friction for walkway surfaces.<br />

B. Environmental Requirements: Comply with current Federal and local toxicity and air quality regulations and with<br />

Federal requirements on content of lead, mercury, and other heavy metals. Do not use solvents in floor polish<br />

products that contribute to air pollution.<br />

2.2 MANUFACTURERS<br />

A. Subject to compliance with project requirements, provide products and equipment by the following:<br />

1. 3M (888) 364-3577 www.3m.com<br />

2. Concrete Polishing Solutions (877) 472-8200 www.go2cps.com<br />

3. Convergent Concrete Technologies (866) 375-2280 www.convergentconcrete.com<br />

4. Stonekor LLC (800) 633-0519 http://stonekor.com<br />

5. HTC (877) 482-8700 www.htc-america.com<br />

6. Innovatech (800) 267-6682 www.innovatechproducts.com<br />

7. Norton Abrasives (800) 331-3604 www.nortonprocleaning.com<br />

8. Pioneer Eclipse (800) 367-3550 www.pioneer-eclipse.com<br />

9. Prosoco (800) 255-4255 www.prosoco.com<br />

10. Pullman-Ermator (800) 232-2635 www.pullman-ermator.com<br />

11. Rubbermaid Commercial Products (540) 667-8700.<br />

12. SASE Company, Inc. (800) 522-2606 www.sasecompany.com<br />

13. Seal Source (800) 305-9144 www.sealsource.com<br />

14. Substrate Technology, Inc. (815) 941-4800 www.substratetechnology.com<br />

15. VIC International Corporation (800) 423-1634 www.vicintl.com<br />

16. VMC Technical Assistance Corp. (800) 460-4862 www.vmctac.com<br />

B. Substitutions: Comply with the requirements of Section 01600.<br />

2.3 PRODUCTS<br />

A. Joint Filler: Polyurea joint filler as specified in Section 03930.<br />

B. Densifier: Clear, lithium-silicate based liquid.<br />

1. Pentra-Sil (NL) by Convergent Concrete Technologies.<br />

2. Consolideck LS by Prosoco.<br />

3. SS Harden X by SealSource.<br />

C. Breathable Surface Protective Material: Provide one of the following products:<br />

1. EZ-Cover by McTech Group, Loganville, GA (866) 913-8363.<br />

2. Ram Board byRam Board, Burbank, CA (818) 848-0400.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine concrete slab in the presence of certified applicator and Wal-Mart Construction Manager. Identify and<br />

note joint filler replacement and repairs required for existing slab defects on as-built Floor Burnishing Plan.<br />

03363 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.2 PREPARATION<br />

A. Close areas to traffic during and after floor finish application for time period recommended by product<br />

manufacturer.<br />

B. Cover and protect merchandise and racking to prevent damage or contamination of stored products. Provide dust<br />

drapes as required to protect merchandise from dust or debris.<br />

C. Clean Substrate: Remove surface contaminants to ensure penetration of reactive surface densifier. No hazardous,<br />

flammable, toxic or solvent based cleaning materials are permitted.<br />

1. Remove dust and loose material by brushing, sweeping, vacuuming, and blowing with high pressure air.<br />

2. Remove all curing or sealing compounds, coatings (including epoxy resins), and wax by mechanical means<br />

that will not expose concrete slab coarse aggregate.<br />

3. Remove deep-set oil and grease stains.<br />

4. Remove paint residue with solvent/stripper provided the stripper does not have an acidic pH.<br />

5. Remove grease and general soiling with cleaner/degreaser diluted as recommended by manufacturer in an<br />

auto scrubber.<br />

6. Remove mildew by scrubbing with solution of trisodium phosphate and bleach. Rinse with clean water.<br />

7. Remove tire marks and residue with recommended non-acidic cleaning agents.<br />

a. Comply with manufacturer’s detailed instructions prior to mixing and removal.<br />

b. Dilute cleaning agent in recommended proportions to avoid etching concrete and opening of<br />

concrete pores.<br />

8. Power scrub and thoroughly rinse floor surface to remove soap residue and contaminants.<br />

9. Squeegee dry.<br />

10. No hazardous, flammable, toxic or solvent based cleaning materials are permitted.<br />

D. Remove existing joint filler and replacewith specified filler at slab joints within the limits of required slab<br />

burnishing,in accordance with Section 03930.<br />

E. Grind protrusions flush with surface.<br />

F. Ensure surfaces are clean, dry, and free of oil, grease, dirt, dust, and contaminants.<br />

G. Protect surrounding and adjacent surfaces in accordance with floor finish manufacturer’s written<br />

recommendations. Do not apply tape to floor. If floor is damaged by tape installation or removal, repair damage<br />

to satisfaction of Wal-Mart Construction Manager.<br />

H. Repair slab defects within the limits of required slab burnishingin accordance with Section 03930, including<br />

previously repaired defects that do not conform to 03930 requirements.<br />

3.3 INSTALLATION/APPLICATION EQUIPMENT<br />

A. Furnish minimum three grinding/burnishing machines in full operating condition during the duration of work.<br />

1. Planetary, counter rotating variable speed floor grinder (3 or 4 head).<br />

2. Minimum 600 pounds of downward pressure.<br />

B. Dust extraction system and pre-separator for grinding and burnishing.<br />

1. Heavy-duty industrial HEPA filtration vacuum system, suitable for extracting and containing large<br />

quantities of fine concrete dust (minimum 350CFM air flow) in conjunction with manufacturer<br />

recommended pre-separator.<br />

2. Provide one of the following:<br />

a. 86D by HTC.<br />

b. T8600 by Pullman-Ermator.<br />

c. Bull 1250 by SASE Company, Inc.<br />

d. Approved equal.<br />

C. Hand grinder with dust extraction attachment and pads for edge grinding/burnishing.<br />

03363 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. High Speed Propane Burnisher:<br />

1. Minimum 27 inch head generating pad speeds of 1,500 RPM or higher, as verified with tachometer.<br />

E. Diamond Grinding Heads:<br />

1. Use diamond grinding heads from approved manufacturers only.<br />

2. Grinding Diamonds (or approved equivalents):<br />

a. Metal Bonded Diamond Grit Sizes 40, 80, and 150.<br />

b. Resin Bonded, Phenolic Diamond Grit Sizes: 100, 200, 400, 800 and 1,500.<br />

3. Grinding/Burnishing Pads for Edges (or approved equivalents):<br />

a. Grit Size: 60, 100, 120, 200, 400, 800, 1500, and 3000.<br />

F. Diamond Impregnated Pads (800 and 1500 grit):<br />

1. Twister Diamond Cleaning System Pads by HTC.<br />

2. Diamond Polishing Pads by Norton.<br />

3. SpinFlex Diamond Polishing Pads by CPS.<br />

4. Scotch-Brite Diamond Floor Pads Plus by 3M.<br />

5. Optima pad system by VIC.<br />

G. Natural Hair Pads:<br />

1. Niagra Super Hogs Hair Floor Pad 3700N by 3M.<br />

2. Ultra Grizzly Bear by Norton.<br />

3. Consolideck Heat Pad by Prosoco.<br />

H. Applicator Pad: Minimum 24" Microfiber Wet Room Pad by Rubbermaid.<br />

3.4 SURFACE BURNISHING AND DENSIFIER APPLICATION<br />

A. Application shall be performed by certified applicator in accordance with manufacturers published instructions.<br />

B. Employ methods to ensure concrete surface is not damaged during application, including discoloration.<br />

C. Open slab surface by progressively grindingwith 40, 80, or 150-grit metal-bonded diamond heads. Start with<br />

initial grinding grit necessary to produce required gloss values in a surface free of pits and scratches. Do not<br />

expose coarse aggregate.<br />

1. Use of more aggressive metal bonded diamond grits for removal of existing surface imperfections, sealers<br />

or coatings shall be approved in writing by the Wal-Mart Construction Manager prior to use.<br />

2. Sequential progression of diamond grinding shall be no more than double the grit value of the previous<br />

diamonds used.<br />

D. Clean slab with wet auto scrubber between grinding passes.<br />

E. Progressively polish slab surface with 100, 200, 400 and 800-grit resin-bonded, phenolic diamond heads. Clean<br />

slab with wet auto scrubber between burnishing passes. Use of 100/200 combination diamond heads will be<br />

acceptable if required to produce less scratching in the slab surface.<br />

F. Apply reactive surface densifier at 500 sq. ft. per gallon, one time after 100-grit resin diamond pass,according to<br />

manufacturer's instructions. Allow to dry 30 to 60 minutes.<br />

G. Progressively diamond grind and polish edges along and around all vertical abutments, including walls, columns,<br />

cases, and racking systems as shown on Drawings. Use same progression of grinding/burnishing diamonds as<br />

noted above and include application of reactive surface densifier after initial grinding.<br />

H. Apply second of densifier at the rate of 1000 SF per gallon to clean and dry slab surface.<br />

I. Burnish at a slow movement pace using burnishing machine with 800 grit diamond impregnated or hogs hair<br />

burnishing pads.<br />

03363 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


J. Continue burnishing operations until the specified gloss is attained.<br />

3.5 FINAL BURNISHING PROCEDURE<br />

A. Burnish at a slow movement pace using burnishing machine with 800 grit diamond impregnated or hogs hair<br />

burnishing pads two weeks prior to Owner Possession.<br />

B. Achieve specified gloss not later than twoweeks prior to Owner Possession and maintain specified gloss levels<br />

until Owner Possession.<br />

C. Provide final burnishing prior to Owner Possession to eliminate any scratches resulting from construction<br />

operations<br />

3.6 FINISH REQUIREMENTS<br />

A. Gloss: Final surface gloss shall be a Specified Overall Gloss Value (SOGV) of not less than 50 and Minimum<br />

Local Gloss Value (MLGV) of 40 as measured using a Horiba IG-320 Gloss Checker.<br />

B. Slip Resistance: Measured static coefficient of friction (SCOF) shall be not less than 0.50 at time of Re-Grand<br />

Opening as measured using an American Slip Meter ASM 825 Digital Meter, Regan Scientific Instruments BOT-<br />

3000 Tribometer, or approved equal.<br />

3.7 PROTECTION<br />

A. Protect areas to receive polished concrete finish at all times during construction to prevent oils, dirt, metal,<br />

excessive water, paint and other potentially damaging materials from affecting the finished concrete surface.<br />

Protective measures listed below shall begin immediately after completion of grinding and burnishing.<br />

1. Communicate to Store/Club Manager and subcontractors, vendors, and trades importance of maintaining<br />

slab protection. Each day, inspect equipment used over completed slab surface, to insure:<br />

a. Equipment is without leaking hydraulic lines and is diapered to avoid staining. Remove equipment<br />

with hydraulic fluid leaks from store site.<br />

b. Equipment is without tire embedment’s (rocks, nails, screws, etc.) that will scratch or pit slab<br />

surface.<br />

c. Operational HEPA vacuum filtration system is attached to grinding and polishing equipment.<br />

2. Do not allow pipe cutting on the finished slab.<br />

3. Do not place steel on the finished slab to avoid rust staining.<br />

4. Prevent contact with acids and acidic detergents.<br />

5. Use breathable surface protective materialsfor high traffic areas.<br />

6. Use breathable drop cloths during all painting. Immediately wipe clean spilled paint.<br />

3.8 FIELD QUALITY CONTROL BY OWNER<br />

A. Testing will be performed by Wal-Mart Construction Testing Laboratory (CTL) at no expense to Contractor. A<br />

test report including plan and table of measurements taken shall be prepared by CTL for submittal by Contractor<br />

as required in Part 1.<br />

B. Contractor shall notify CTL when slab is ready for testing.<br />

C. CTL shall take gloss measurements once weekly. Gloss shall be considered as a quantitative value that expresses<br />

the degree of reflection when light hits the concrete floor surface. Gloss measurements will be taken independent<br />

of ambient lighting and within a sealed measurement window located beneath the testing equipment.<br />

Measurement and reporting of SOGV and MLGV by CTL shall be as follows:<br />

1. Collect a minimum of five samples per each bay, in random, evenly distributed locations. Record<br />

measurement locations on copy of Floor BurnishingPlan. Discard the high and low values measured in<br />

each bay.<br />

03363 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. The average of all samples collected in each bay shall meet SOGV.<br />

a. If the average of samples collected do not meet the SOGV, collect an additional 3 samples in each<br />

bay for each deficient result unless the individual samples fail to meet the MLGV or the average of<br />

all collected samples in each bay fail to meet the SOGV.<br />

b. If samples fail to meet the SOGV, Contractor shall continue sweeping, scrubbing and burnishing<br />

until the SOGV is achieved.<br />

3. No single measured value shall be less than MLGV.<br />

a. If one or more samples fall below the MLGV, Contractor shall continue sweeping, scrubbing and<br />

burnishing until all samples comply with Specified MLGV and SOGV.<br />

4. Collect and certify final gloss measurements.<br />

D. Slip Resistance Measurements:<br />

1. CTL shall take slip resistance measurements 2 weeks prior to Re-Grand Opening and at time of Re-Grand<br />

Opening. Contractor shall notify CTL when floors are ready for testing.<br />

2. Four slip resistance measurements will be required within the areas of the two highest and two lowest<br />

SOGV measurements.<br />

3. Correlate single re-measured gloss value at each location in floor slab where slip resistance is measured.<br />

3.9 FIELD QUALITY CONTROL BY CONTRACTOR<br />

A. At the request of the Wal-Mart Construction Manager or Concrete Consultant, Manufacturer’s Technical<br />

Representative shall be on Site to oversee the installation of the densifier system, joint filler, or surface defect<br />

repairs to verify proper installation of product.<br />

B. A technically qualified manufacturer’s field representative of the densifier product shall be on Site during the<br />

initial application of the densifier and occasional observations during remainder of the applications.<br />

C. The densifier representative shall ensure that the correct amount of densifier is onsite and in numbered containers<br />

prior to commencement of work.<br />

3.10 CLEANING AND PROTECTION<br />

A. Remove spilled, splashed, or splattered finish material from surfaces.<br />

B. Prohibit traffic until floor has achieved full cure.<br />

END OF SECTION<br />

03363 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 022511<br />

SECTION 03450 (03 4500) – PLANT-PRECAST ARCHITECTURAL CONCRETE<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Precast concrete units in the following applications:<br />

1. Sill.<br />

2. Cap.<br />

3. Trim.<br />

4. Precast integral color concrete pavers.<br />

B. Related Requirements:<br />

1. Section 07711 - Gutters and Downspouts: Precast concrete splash blocks.<br />

1.2 SUBMITTALS<br />

A. Precast Integrally Colored Concrete: Refer to Section 01330 for submittal requirements.<br />

1. Manufacturer’s published product and material data and installation instructions, as applicable.<br />

2. Shop drawings.<br />

3. Samples for Architect’s approval.<br />

a. Samples shall show full range of colors and textures shown on Drawings.<br />

1.3 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A 82 - Steel Wire, Plain, for Concrete Reinforcement.<br />

2. ASTM A 496 - Steel Wire, Deformed for Concrete Reinforcement.<br />

3. ASTM A 615 - Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement.<br />

4. ASTM C 33 - Concrete Aggregates.<br />

5. ASTM C 144 - Aggregate for Masonry Mortar.<br />

6. ASTM C 150 -Portland Cement.<br />

7. ASTM C 260 - Air-Entraining Admixtures for Concrete.<br />

C. American Concrete Institute (ACI):<br />

1. ACI 211.1 - Standard Practice for Selecting proportions for Normal, Heavyweight and Mass Concrete.<br />

2. ACI 318 - Building Code Requirements for Structural Concrete.<br />

D. Concrete Reinforcing Steel Institute (CRSI):<br />

1. CRSI - Manual of Standard Practice.<br />

E. Precast / Prestressed Concrete Institute (PCI):<br />

1. PCI MNL 117 - Manual for Quality Control for Plants and Production of Architectural Precast Concrete<br />

Products.<br />

2. PCI MNL 120 - Design Handbook - Precast and Prestressed Concrete.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect plant-precast architectural concrete products in compliance with the<br />

requirements of Section 01600 and manufacturer's recommendations.<br />

03450 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Store units at Site to prevent cracking, distorting, warping, staining, or other physical damage, and so markings are<br />

visible.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Steel Reinforcing:<br />

1. Reinforcing Bars: ASTM A 615, Grade 60, deformed.<br />

2. Plain-Steel Wire: ASTM A 82, as drawn.<br />

3. Deformed-Steel Wire: ASTM A 496.<br />

B. Concrete: Portland Cement: ASTM C 150, Type I or Type III of same type, brand, and source.<br />

C. Normal-Weight Aggregates: Except as modified by PCI MNL 117, ASTM C 33, with coarse aggregates<br />

complying with Class 5S.<br />

D. Air-Entraining Admixture: ASTM C 260.<br />

E. Sand-Cement Grout: Portland cement, ASTM C 150, Type I, and clean, natural sand, ASTM C 144. Mix at ratio<br />

of 1 part cement to 2-1/2 parts sand, by volume, with minimum water required for placement and hydration.<br />

2.2 PRECAST INTEGRAL COLOR CONCRETE PAVERS<br />

A. Manufacturer: Concrete Designs, Inc. Tucson, AZ (800) 279-2278, http://www.concrete-designs.com/<br />

1. Paver and Color: As shown on Drawings.<br />

2. Refer to Drawings for locations and additional information.<br />

2.3 CONCRETE MIXES<br />

A. Proportion mixes by either laboratory trial batch or field test data methods according to ACI 211.1, with materials<br />

to be used on Project, to provide normal-weight concrete with the following properties:<br />

1. Compressive Strength (28 Days): 5000 psi.<br />

2. Maximum Water-Cementitious Materials Ratio: 0.45.<br />

B. Water Absorption: 12 to 14 percent by volume, tested according to PCI MNL 117.<br />

C. Add air-entraining admixture at manufacturer's prescribed rate to result in concrete at point of placement having an<br />

air content complying with PCI MNL 117.<br />

2.4 FABRICATION<br />

A. Design Standards: Comply with ACI 318 and the design recommendations in PCI MNL 120.<br />

B. Quality-Control Standard: Comply with PCI MNL 117.<br />

C. Cast concrete units in size and shape as indicted.<br />

D. Reinforcement: Comply with recommendations in CRSI's "Manual of Standard Practice" and PCI MNL 117 for<br />

fabricating, placing, and supporting reinforcement.<br />

E. Reinforce precast architectural concrete units to resist handling, transportation, and erection stresses.<br />

F. Mix concrete according to PCI MNL 117 and requirements in this Section. After concrete batching, no additional<br />

water may be added.<br />

03450 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


G. Thoroughly consolidate placed concrete by internal and external vibration without dislocating or damaging<br />

reinforcement and built-in items. Use equipment and procedures complying with PCI MNL 117.<br />

H. Cure concrete, according to requirements in PCI MNL 117, by moisture retention without heat or by accelerated<br />

heat curing using low-pressure live steam or radiant heat and moisture.<br />

I. Discard precast architectural concrete units that are warped, cracked, broken, spalled, stained, or otherwise<br />

defective unless repairs are approved by Architect.<br />

J. Fabricate precast architectural concrete units straight and true to size and shape with exposed edges and corners<br />

precise and true so each finished panel complies with PCI MNL 117 product tolerances as well as position<br />

tolerances for cast-in items.<br />

K. Fabricate sill and wall cap in nominal dimensions, allowing for 3/8 inch mortar joints.<br />

2.5 FINISHES<br />

A. Finish exposed surfaces of precast architectural concrete units to a smooth surface finish free of pockets, sand<br />

streaks, and honeycombs, with uniform color and texture. Chamfer exposed edges of wall cap and sills.<br />

B. Color: Standard gray (no pigment added), unless noted otherwise.<br />

2.6 SOURCE QUALITY CONTROL<br />

A. Quality-Control Testing: Test and inspect precast concrete according to PCI MNL 117 requirements.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Lay units with completely filled bed and head joints; butter ends with sufficient mortar to fill head joints and shove<br />

into place. Do not slush head joints. Remove excess mortar.<br />

B. Dowel units into place as shown on the Drawings.<br />

C. Maintain courses to uniform width. Align vertical joints. Provide joints equal and of uniform thickness.<br />

D. Tool head and bed joints concave. Use tool with large enough radius that joint is not raked free of mortar.<br />

E. Install precast architectural concrete units level, plumb, square, true, and in alignment without exceeding the noncumulative<br />

erection tolerances of PCI MNL 117, Appendix I.<br />

F. Seal sill units as shown in accordance with Section 07900 with sealant color to match mortar.<br />

G. Clean exposed surfaces of precast concrete units after erection to remove markings, dirt, and stains.<br />

END OF SECTION<br />

03450 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 042911<br />

SECTION 03930 (03 9050) – CONCRETE REHABILITATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Concrete rehabilitation for interior concrete floors including the following:<br />

a. Joint edge spall repair.<br />

b. Crack repair.<br />

c. Surface defect repair, including pop-outs, chips, spalls, and pitting.<br />

B. Related Requirements:<br />

1. Section 03363 - Burnished Concrete Floor Finishes (Existing Floors).<br />

1.2 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-installation Meeting specified in Section 03363.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Product Data:<br />

1. Polyurea Joint Filler.<br />

2. Low Viscosity Rigid Urethane.<br />

3. Polymerized Portland Cement Compound.<br />

4. Manufacturer and model of equipment to be used as specified in Part 3:<br />

a. Joint Filler Removal and Preparation Equipment.<br />

b. Dust Extraction System.<br />

c. Crack Repair Equipment.<br />

d. Surface Grinder.<br />

C. Samples: Submit one dry sample of polyurea joint filler for each color required to Wal-Mart Construction<br />

Manager.<br />

D. Floor Burnishing Plan specified in Section 03363.<br />

1.4 QUALITY ASSURANCE<br />

A. Wal-Mart Concrete Consultant: Structural Services, Inc. (SSI), (214) 522-6438.<br />

1.5 DELIVERY, STORAGE AND HANDING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

1.6 ENVIRONMENTAL REQUIREMENTS<br />

A. Cure replaced concrete a minimum of 28 days prior to joint filler installation.<br />

B. Close concrete repair area to traffic during preparation and repair for a time as recommended by repair material<br />

manufacturer.<br />

03930 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 PRODUCTS AND MATERIALS<br />

A. Subject to compliance with project requirements, provide products as manufactured by the following to the extent<br />

as specified hereinafter:<br />

1. Ardex Engineered Cements, Aliquippa, PA (888) 512-7339.<br />

2. Euclid Chemical Co., Cleveland, OH (877) 438-3826.<br />

3. Mapei Corp. (800) 426-2734.<br />

4. Metzger/McGuire, Concord, NH (800) 223-6680.<br />

5. SpecChem, LLC, Kansas City, MO (866) 791-8700.<br />

6. VersaFlex, Inc., Kansas City, MO (913) 321-1416.<br />

B. Polyurea Joint Filler: Rapid setting, two-component polyurea polymer liquid of 100% solids content, Shore<br />

hardness 85-90, compatible with construction materials in contact.<br />

1. Spal-Pro RS 88 by Metzger/McGuire.<br />

2. VersaFlex SL/85 by VersaFlex.<br />

3. Match color of adjacent exposed concrete slab surface.<br />

C. Low Viscosity Rigid Urethane:<br />

1. Rapid ReFloor by Metzger/McGuire.<br />

2. Quick Mender by VersaFlex.<br />

3. Match color of adjacent exposed concrete slab surface.<br />

D. Silica Sand:<br />

1. Dry 00 Sandblasting sand.<br />

E. Polymerized Portland Cement Compound:<br />

1. Fast Top Supreme by Euclid Chemical.<br />

2. Planitop X by Mapei.<br />

3. Ardex CD by Ardex.<br />

4. RepCon 928 by SpecChem.<br />

2.2 SUBSTITUTIONS<br />

A. Substitutions: Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 GENERAL<br />

A. Concrete rehabilitation work specified shall be performed within the limits of the Grind and Polish area of the<br />

sales floor shown on Drawings.<br />

B. Installation of specified products shall be in accordance with product manufacturer’s written instructions.<br />

3.2 EXAMINATION<br />

A. Evaluate existing floor slab, identifying defects to be repaired. Scope of repairs shall be agreed to by Wal-Mart<br />

Construction Manager prior to commencement of work. Identify scope of work on Floor Burnishing Plan<br />

specified in Section 03363.<br />

B. Repairs shall be approved by Wal-Mart Construction Manager or Architect of Record. Wal-Mart Concrete<br />

Consultant is not authorized to change any specified requirement or to approve execution of any portion of the<br />

Work.<br />

03930 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 PREPARATION<br />

A. Protect existing construction from dust and moisture damage caused by demolition, preparation and installation of<br />

slab repair.<br />

B. Protect surface of slab immediately adjacent to defect under repair.<br />

3.4 EQUIPMENT<br />

A. Manufacturers: Subject to compliance with project requirements, provide equipment by the following:<br />

1. HTC, Inc., Knoxville, TN (877) 482-8700.<br />

2. Joe Due Blades and Equipment, Mauston, WI (877) 563-3833.<br />

3. Pulman-Ermator, Tampa, FL (800) 232-2635.<br />

4. SASE Company, Inc., Kent, WA (800) 522-2606.<br />

5. U.S. Saws, Santa Ana, CA (866) 987-7297.<br />

B. Use equipment as specified below. Within each equipment listing, provide one of the models specified. When<br />

specifically allowed within each product listing, equivalent products by other manufacturers meeting the specified<br />

requirements may be used upon submittal of product data and approval by Wal-Mart Concrete Consultant.<br />

C. Dust extraction system for grinding/sawing. HEPA filtration vacuum, designed for use with hand tools when<br />

grinding or sawing concrete (minimum 125CFM air flow). Provide one of the following:<br />

1. 26D by HTC.<br />

2. S2400 by Pullman-Ermator.<br />

3. Bull 50 by SASE Company, Inc.<br />

4. Similar equipment as required to produce the specified results.<br />

D. Joint Filler Removal and Preparation Equipment. Provide one of the following:<br />

1. Humpback Cutter Complete, by Joe Due.<br />

2. Dust Buggy by U.S. Saws.<br />

3. Similar equipment as required to produce the specified results.<br />

E. Crack Repair Equipment. Provide one of the following:<br />

1. 5” Dustmizer 007, by Joe Due.<br />

2. 5” Crack Attacker, by Joe Due.<br />

3. 7” Handheld Crack Chaser, by Joe Due.<br />

4. SawTec 5” Tile Vac, by U.S. Saws.<br />

5. SawTec 7” Crac-Vac, by U.S. Saws.<br />

6. Similar equipment as required to produce the specified results.<br />

F. Surface Grinder. Handheld 5”-7” electric surface grinder with dustless shroud/housing. Provide one of the<br />

following:<br />

1. Dust Avenger 5, by Joe Due.<br />

2. Dust Avenger 7, by Joe Due.<br />

3. SawTec 5” Grinder Vac, by U.S. Saws.<br />

4. SawTec 7” Grinder Vac, by U.S. Saws.<br />

5. Similar equipment as required to produce the specified results.<br />

03930 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.5 JOINT MILLING AND CAP FILLER REPLACEMENT<br />

1/2" min.<br />

new filler<br />

Before<br />

Orginal material<br />

bearing on<br />

saw cut shelf<br />

After<br />

A. If existing joint filler is sound and resting on top of saw cut shelf, mill top 1/2" of material and refill with specified<br />

polyurea joint filler.<br />

B. Re-saw the joint to a minimum depth of 1/2 inch with a dry-cut, vacuum-equipped saw using a slightly oversized<br />

blade. Use blade of sufficient width to encapsulate the widest spall along a given contraction joint segment to<br />

produce a sharp corner on each side of the joint with a minimum of two passes through the joint.<br />

C. Refill with polyurea joint filler material from the bottom up. Avoid trapping large air bubbles. Slightly overfill<br />

and shave flush to the surface prior to grinding process.<br />

D. After grinding, joint shall be smooth and flush with finish floor surface without concave or intermittent darkened<br />

profile.<br />

3.6 FULL DEPTH JOINT FILLER REPLACEMENT<br />

Fill to Bottom<br />

of Original<br />

Saw Cut<br />

Before<br />

Saw cut shelf<br />

After<br />

A. If existing joint filler is loose, easily removed, or able to be forced downward with a hand tool, remove filler<br />

material from joint and refill.<br />

B. Re-saw joint full depth with a dry-cut, vacuum-equipped saw using a slightly oversized blade. Use blade of<br />

sufficient width to encapsulate the widest spall along a given contraction joint segment to produce a sharp corner<br />

on each side of the joint with a minimum of two passes through the joint. Remove filler material, debris, and<br />

laitance.<br />

C. If shelf width at base of saw cut is less than 1/4 inch on either side of joint, fill joint with compressible backer rod<br />

or bagged silica sand to not more than 2 inches below slab surface.<br />

03930 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Refill with polyurea joint filler material from the bottom up. Avoid trapping large air bubbles. Slightly overfill<br />

and shave flush to the surface prior to grinding process.<br />

E. After grinding, joint shall be smooth and flush with finish floor surface without concave or intermittent darkened<br />

profile.<br />

3.7 SPALLED JOINT REPAIR (LESS THAN 1”)<br />

Spalled<br />

or tooled<br />

radiud edge<br />

Original<br />

Joint<br />

3/4" min.<br />

depth<br />

Sawcut and<br />

Remove<br />

Concrete<br />

As required<br />

1" maximum<br />

A. For joints that are spalled or have radius tooled edges not exceeding 1 inch in width at slab surface, re-saw the<br />

joint edge to a minimum depth of 3/4 inch with a dry-cut, vacuum-equipped saw allowing removal of the widest<br />

spall (or top of radius) along a given joint segment to produce a sharp corner on each side of the joint with a<br />

minimum of two passes through joint.<br />

B. Clean joint of loose concrete, joint filler, laitance, dirt, debris, backer rod, etc.<br />

C. Joints shall be free of visible moisture.<br />

Repair Cavity < 1"<br />

Overfill and<br />

Shave Flush<br />

Re-establish Aggregate<br />

Interlock with Polyurea<br />

D. Gravity feed a trace amount (1/8 inch) of silica sand into joint to prevent 3-sided bonding of joint filler.<br />

03930 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Fill joint cavity, avoiding trapping large air bubbles. Install filler so that it penetrates the irregular aggregate<br />

interlock portion of the sawn contraction joint as shown above, re-establishing the aggregate interlock that may<br />

have been lost due to shrinkage, curling, and lack of reinforcement. Overfill joint slightly and shave flush to slab<br />

surface prior to grinding process.<br />

3.8 CONSTRUCTION JOINT REPAIR (GREATER THAN 1”)<br />

Saw cut patch material<br />

and refill to match<br />

original joint<br />

Rebuild joint edge with<br />

cementitious patch material<br />

3/4" min.<br />

Repair Cavity > 1"<br />

Polyurea<br />

Material<br />

A. For construction joints exceeding 1inch in width at slab surface or greater than 1/4 inch height differential at<br />

abutting joint edges, re-saw the construction joint edge to a minimum depth of 3/4 inch with a dry-cut, vacuumequipped<br />

saw allowing removal of the widest spall along a given joint segment to produce a sharp corner on each<br />

side of the joint with a minimum of two passes through joint. Maintain consistent width of repair to within 1/2<br />

inch in 10 feet.<br />

1. For construction joints of 1/4 inch or greater height differential at abutting joint edges, slope repair material<br />

1/4 inch per foot at floor surface with consistent depth of material at 1/2 inch below repair surface.<br />

B. Overfill repair cavity with cementitious patch material and grind flush to slab surface.<br />

C. After cementitious patch material has cured and prior to traffic on patched surface, re-saw original slab joints and<br />

fill with polyurea joint filler.<br />

D. Burnish repair material to match adjacent slab surface color after material has cured.<br />

E. Do not repair cracks less than 1/32 inch in width without surface spalling.<br />

03930 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.9 CRACK REPAIR<br />

A. Cracks From 1/32 Inch to 1/4 Inch in Width:<br />

1. Clean crack cavity.<br />

a. Clean sidewall by removing loose concrete, dirt and debris from crack with a wire brush or hand<br />

grinder with twisted wire wheel attachment, 1/2 inch minimum depth.<br />

b. Remove loose segments, including islands formed by crack, with sharp tool.<br />

c. Use methods that will not widen existing crack.<br />

d. Vacuum crack to remove dirt, debris and other laitance.<br />

2. Mask slab surface along crack as necessary to minimize overfill.<br />

3. Install low viscosity rigid urethane repair material.<br />

4. Repeat until voids are filled and material crowns slab surface.<br />

a. Do not flood area around crack.<br />

b. Avoid bubble formation and out gassing.<br />

c. Do not allow material to gel before adding additional material.<br />

5. Shave or grind material flush to surface.<br />

B. Cracks From 1/4 Inch to 1 Inch in Width:<br />

1. Saw top or edge of crack to provide square edge, minimum ¾” in depth.<br />

a. Use small hand grinder with maximum 5” diameter blade, minimizing eventual crack width while<br />

maintaining uniformity of shape.<br />

2. Clean crack cavity.<br />

a. Vacuum crack to remove dirt, debris and other laitance.<br />

b. Remove visible moisture.<br />

3. Mask slab surface along crack as necessary to minimize overfill.<br />

4. Install polyurea joint filler.<br />

a. Dispense sample into small bucket to test blending of material.<br />

b. Prime crack with repair material.<br />

c. Dispense material, dragging dispenser tip along crack, until it flows over the slab.<br />

5. Wait approximately 10 minutes, periodically checking for material cure.<br />

a. Check condition of material by shaving with razor scraper.<br />

6. Shave material flush to slab surface.<br />

03930 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.10 SURFACE SPALLING REPAIR<br />

FLOOR JOINT<br />

SLAB SURFACE SPALL<br />

A. Route edge of spall to provide 1/2 inch deep square edge.<br />

1. Use small hand grinder with maximum 5 inch diameter dry diamond blade and vacuum system attachment.<br />

2. Do not overcut slots into existing slab surface.<br />

B. Clean and prep spalled cavity.<br />

1. Wire brush spalled surface to remove dirt and laitance.<br />

2. Mask slab at perimeter of spall with tape.<br />

C. Install low viscosity rigid urethane repair material using tube cartridge without flow restrictor.<br />

D. Polish repair area with diamond disks to blend surface.<br />

1. Feather filler material into the adjacent concrete floor surface.<br />

2. With 2000 grit disk and firm pressure, add a few burn marks to mottle surface to blend with adjacent floor<br />

surface.<br />

E. For spalled joints, use form material if required to temporarily support vertical face of spalled joint edge. Prevent<br />

repair material from adhering to form.<br />

3.11 HIGH RACK BOLT HOLE/SPALL REPAIR<br />

A. Recess steel bolt a minimum of 1/2 inch below finish floor by either punching or cutting.<br />

B. For spall fracture edge less than 30 degrees, square edge to a minimum 3/8 inch depth with either a drill bit or<br />

chisel.<br />

C. Clean cavity of debris and laitance with drill activated, brass wire wheel. Vacuum hole to remove dirt, debris and<br />

other laitance.<br />

D. Dispense low viscosity rigid urethane at moderate pace using steady pressure. Dispense material into void,<br />

refilling as necessary to produce slight crown.<br />

E. Grind material flush to slab surface.<br />

3.12 LARGE SURFACE REPAIR<br />

A. Edge perimeter with diamond masonry wheel to produce sharp edge at least 3/8 inch deep.<br />

B. Roughen base surface and vacuum clean. Wire brush to remove any small loose material and vacuum again.<br />

03930 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Protect adjacent slab surface with tape at perimeter of repair area, width as required to prevent scratching during<br />

troweling operations.<br />

D. Mist floor surface until damp but without standing water.<br />

E. Prepare slurry prime coat of polymerized Portland cement compound and scrub into repair surface with stiff bristle<br />

brush. Do not allow to dry before placing pigmented repair material. Use concrete bonding agent if required.<br />

F. Mix repair material in accordance with manufacturer’s instructions.<br />

G. Place repair material in floor surface defect and float level. Use float on edge.<br />

H. Lightly mist floated repair material with the finishing aid once and perform first troweling pass to smooth surface<br />

without over-working. Do not reapply finishing aid during any other troweling operations.<br />

I. Wait until material begins to set and can be indented with finger about 1/8 inch. Perform second troweling pass<br />

approximately two hours after initial placement.<br />

J. Using a fine sharp edged cutting tool, cut along edge of repair material and adjacent slab to prevent raveling of<br />

edge during tape removal.<br />

K. When material has become stiff and can be slightly indented with hard finger pressure, final trowel using firm<br />

pressure until mottling and shine has become apparent. Do not allow trowels to be positioned on surface flat, as<br />

surface will tear. Use circular sweeping motions.<br />

L. Keep surface clean during troweling operations to prevent laitance from coming in contact with repair material and<br />

marring surface.<br />

M. Check material set after 30 minutes to 1 hour. Surface should not dent with fingernail under hard hand pressure.<br />

N. Troweled surface shall be tight, level and smooth without surface defects.<br />

O. After repair material has cured, burnish repair material to match adjacent slab surface in accordance with the<br />

requirements of Section 03363.<br />

P. Remove tape and clean area of particles on repair surface and adjacent floor surface.<br />

Q. Re-establish original concrete slab joints by sawing completely through patch and re-filling with polyurea joint<br />

filler prior to exposure to traffic.<br />

03930 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.13 SURFACE PITTING REPAIR<br />

SLAB SURFACE PITTING<br />

A. Clean pitted sections with 90-degree angle grinder equipped with wire wheel to remove dirt and laitance. Pass<br />

grinding wheel over defect in multiple directions.<br />

B. Vacuum prepared pitted sections.<br />

C. Dispense low viscosity rigid urethane repair material generously in and around pitted areas.<br />

D. Immediately trowel repair material flush with slab surface and repeat troweling in opposite directions until<br />

material begins to thicken (approximately 2 minutes). If material sticks to trowel, wipe with denatured alcohol.<br />

1. Provide thin, uniform layer of repair material over pitted areas. Refill low spots as needed.<br />

E. Allow repair material to fully cure (approximately 90-120 minutes for thin film).<br />

F. Grind overfill with 80-grit metal-bond pads until repair material is flush with slab surface.<br />

G. Repeat repairs in areas as required if repair material pulls out of defects. Extend curing time as necessary to<br />

minimize material pull out.<br />

3.14 PROTECTION<br />

A. Protect surfaces of finished floor.<br />

B. Prohibit traffic until floor repairs have received final approval by Owner.<br />

END OF SECTION<br />

03930 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II - NON PROTO 093011<br />

SECTION 04711 (04 7300) – MANUFACTURED STONE VENEERS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Manufactured stone veneers.<br />

B. Related Requirements:<br />

1. Section 07190 - Water Repellents: Water repellent coating applied to exterior manufactured stone veneer<br />

surfaces.<br />

2. Section 07620 - Sheet Metal Flashing and Trim: Veneer Flashing.<br />

3. Section 07900 - Joint Sealers: Perimeter Sealing at Openings.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C 67 - Standard Test Methods for Sampling and Testing Brick and Structural Clay Tile.<br />

2. ASTM C 270 - Mortar for Unit Masonry.<br />

3. ASTM C 847 - Metal Lath.<br />

4. ASTM C 1032 - Woven Wire Plaster Base.<br />

5. ASTM D 226 - Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing.<br />

C. ICC-Evaluation Service (ICC-ES):<br />

1. ICC-ES AC38 - Acceptance Criteria for Water-Resistive Barriers.<br />

2. ICC-ES AC51 - Acceptance Criteria for Precast Stone Veneer.<br />

D. Underwriters Laboratories (UL):<br />

1. UL 723 - Surface Burning Characteristics of Building Materials.<br />

1.3 SUBMITTALS<br />

A. Submittals: Comply with the requirements of Section 01330.<br />

B. Product Data:<br />

1. Manufactured masonry.<br />

2. Application materials.<br />

3. Mortar color charts.<br />

4. Weather resistant barrier.<br />

C. Manufacturer's Installation Instructions.<br />

D. Installer Qualifications.<br />

E. Samples:<br />

1. Submit sample boards of manufactured stone veneer.<br />

2. Obtain Architect's approval prior to installation of manufactured stone veneer.<br />

F. Certifications:<br />

1. ICBO Evaluation Service - Evaluation Reports.<br />

04711 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 CLOSEOUT SUBMITTALS<br />

A. Submit the following in compliance with the requirements of Section 01770.<br />

1. Maintenance Instructions.<br />

2. Warranty.<br />

1.5 QUALITY ASSURANCE<br />

A. Installer Qualifications: Company with documented experience in installation of manufactured masonry including<br />

minimum 5 projects within 400 mile radius of this project.<br />

B. Conform to ICC-ES AC51 acceptance criteria for pre-cast stone veneer.<br />

C. Conform to ICC-ES AC38 acceptance criteria for water resistive barrier.<br />

D. Mock-Up:<br />

1. Prepare 4 foot by 4 foot field mock-up at a location on the structure as selected by the Wal-Mart<br />

Construction Manager. Use approved materials and colors. Include corners and mortar joints utilizing of<br />

stone veneer specified.<br />

2. Obtain approval of Wal-Mart Construction Manager.<br />

3. Protect and retain mock-up as a basis for approval of completed manufactured stone work. Approved<br />

mock-up may be incorporated into completed work.<br />

1.6 EXTRA STOCK MATERIALS<br />

A. Extra Materials: Furnish extra manufactured stone material in a variety of shapes and sizes in quantity equal to<br />

three percent of the installed stone.<br />

1.7 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Prevent damage or contamination to materials by water, freezing, foreign matter, and other causes.<br />

1.8 SITE CONDITIONS<br />

A. Maintain materials and ambient temperature in area of installation at minimum 40º F prior to, during, and for 48<br />

hours following installation.<br />

B. In hot weather, maintain scratch coat below 120º F by misting the work area with clean water every 4 to 6 hours<br />

during daylight as required.<br />

1.9 WARRANTY<br />

A. Provide manufacturer's standard warranty.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with requirements, provide manufactured stone veneer of the following:<br />

1. Coronado Stone Products, Fontana, CA (800) 847-8663. Contact: Kevin McNally (775) 412-3181.<br />

B. Manufacturing Plant Locations: Provide stone from a plant or distribution center nearest the project site for<br />

manufacturer selected.<br />

04711 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Substitutions: Comply with the requirements of Section 01600.<br />

2.2 STONE MATERIAL<br />

A. Veneer Units: Precast veneer units consisting of Portland cement, sand, lightweight aggregates, and mineral oxide<br />

pigments.<br />

B. Physical Properties:<br />

1. Maximum Veneer Unit Weight: 15 psf.<br />

2. Compressive Strength: 5 sample avg. 2,200 psi. 1500 psi minimum for individual unit.<br />

3. Bond Between Stone Unit, Type N Mortar, and Backing: ASTM C 270, 50 psi.<br />

4. Thermal Resistance: R = 0.355 per inch of thickness.<br />

5. Freeze/Thaw: ASTM C 67, no disintegration and less than 3 percent weight loss.<br />

6. Fire Hazard Test, UL 723:<br />

a. Flame spread: 0.<br />

b. Smoke Development: 0.<br />

C. Color and Texture: As shown on Drawings.<br />

2.3 RELATED MATERIALS<br />

A. Mortar Components: Mixed using components and proportions following manufactured masonry manufacturer’s<br />

installation instructions.<br />

1. Premixed: Type N or S mortar, ASTM C 270.<br />

2. Mortar Color: Iron oxide pigments.<br />

3. Water: Potable water.<br />

B. Water-Resistant Barrier: 60 minute, Grade D, Kraft waterproof building paper or No. 15, Type I, asphalt saturated<br />

felt, ASTM D 226.<br />

C. Flashing: Rigid, corrosion-resistant.<br />

D. Metal Lath: Self-furred 2.5 lb. galvanized expanded metal lath (diamond mesh) meeting the requirements of<br />

ASTM C 847, or min. 18-gauge galvanized self-furring woven wire mesh meeting the requirements of ASTM C<br />

1032.<br />

E. Scratch Coat: Type N or S mortar, ASTM C 270.<br />

F. Fasteners:<br />

1. Concrete or Masonry: Galvanized concrete nails or screws.<br />

2. Sheathing Over Metal Studs: Corrosion-resistant, self-drilling, self-tapping pancake-head screw with<br />

minimum 7/16 inch diameter head, of 1-1/4 inch length or suitable to obtain 3/8 inch penetration beyond<br />

inside surface of metal, or as recommended by manufacturer.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine substrates upon which veneer will be installed.<br />

B. Coordinate with responsible entity to correct unsatisfactory conditions.<br />

3.2 PREPARATION<br />

A. Protection: Prevent work from occurring on the opposite of walls to which manufactured masonry is applied<br />

during and for 48 hours following installation of the stone.<br />

04711 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Precast Concrete Substrate Surfaces:<br />

1. Finished surface containing releasing agents or form oil shall be etched with muriatic acid or scored with a<br />

wire brush and rinsed thoroughly.<br />

2. Bead blast or sand blast to produce a sandpaper-like texture without slick surfaces.<br />

3. Spray water on the surface to test for beading. Repeat bead or sand blasting where beading occurs.<br />

4. Allow surface to dry before proceeding with installation.<br />

5. Apply a coat of bonding agent if required.<br />

C. Concrete Masonry Unit Substrate Surfaces:<br />

1. Examine the surface to ensure it is solid with no sign of deterioration.<br />

2. The clean surface should not be painted, sealed or have other coatings that may prevent adequate bond of<br />

the scratch coat to the substrate.<br />

3. Spray water on the wall to test for beading. Bead blast or sand blast where beading occurs.<br />

4. Allow surface to dry before proceeding with installation.<br />

5. Apply a coat of bonding agent if required.<br />

3.3 INSTALLATION<br />

A. Install as shown on Drawings and as specified in this Section or in accordance with manufacturer’s installation<br />

instructions.<br />

B. Weather-Resistant Barrier:<br />

1. Install two layers per manufacturer’s installation instructions.<br />

2. Weather-resistant barrier shall be free of tears.<br />

C. Metal Lath:<br />

1. Install lath with diamond pattern facing up.<br />

2. Concrete or Masonry Installation: Install metal lath on concrete or masonry using concrete nails or screws<br />

at a maximum spacing of 6 inches vertically and 16 inches horizontally with a minimum penetration into<br />

concrete surface of 3/4 inch.<br />

3. Sheathing over Metal Studs:<br />

a. Apply perpendicular to framing. Overlap the lath sides and ends a minimum of 1 inch. Attach<br />

metal lath with small cups pointing upwards and verify the lath is pulled tight before fastening to<br />

avoid lath or mortar sag. The ends of adjoining metal lath shall be staggered.<br />

b. Space screws 6 inches on stud center vertically and 16 inches on stud center horizontally, or to<br />

match wall construction. Do not use fasteners in between framing.<br />

4. Corners: Wrap inside and outside corners with double layer of lath. Extend lath at least 16 inches on both<br />

sides of a corner.<br />

D. Scratch Coat:<br />

1. Apply a nominal 1/2 inch thick coat of mortar with sufficient pressure to fully embed the lath.<br />

2. Score the surface horizontally with a notched trowel or scarifier when the mortar has become thumbprintdry.<br />

3. Allow the scratch coat to moist cure for at least 48 hours before installing stone.<br />

E. Select and mix pieces from different boxes throughout the installation to produce a balanced pattern of shapes,<br />

sizes, colors, thicknesses and textures.<br />

F. Immediately prior to stone installation, moisten scratch coat and back side of stone. Remove excess free water.<br />

G. Flashing: Install flashing as shown.<br />

1. Install flashing around penetrations and terminations of the veneer application.<br />

2. Install flashing to divert water run-off away from the finished surface area.<br />

H. Grouted Installations: Install per manufacturer’s recommended installation for selected product.<br />

1. Install veneer with uniform size grout joints.<br />

2. After the veneer has been applied to the wall surface, fill joints with grout.<br />

04711 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Avoid smearing grout onto the face of the veneer.<br />

4. Allow mortar that gets on the veneer to dry until dry and crumbly. Brush off with a dry whisk broom.<br />

Remove loose mortar and spots within a few hours. Do not allow to set up overnight.<br />

I. Dry-Stack Installations: Install per manufacturer’s recommended installation for selected product.<br />

1. Apply mortar generously to the back of each piece to allow ample mortar to squeeze out around edges as it<br />

is pressed onto the wall surface.<br />

2. Apply mortar, completely covering the back of each piece and use a trowel to work the mortar into<br />

depressions.<br />

3. Immediately after setting each piece, use a masonry trowel to remove excess mortar and fill voids along the<br />

exposed edges. Use a metal striking tool to smooth mortar around the perimeter.<br />

4. Just prior to setting each piece, apply a thin bead of mortar with a grout bag to the edges of previously<br />

installed adjacent veneer pieces.<br />

5. If the scratch coat is visible or if the perimeter of the veneer pieces is not sealed with mortar, grout as<br />

needed.<br />

3.4 CLEANING<br />

A. Cleaning Veneer Units:<br />

1. Wash with soft bristle brush and water/granulated detergent solution.<br />

2. Rinse immediately with clean water.<br />

B. Removing Efflorescence:<br />

1. Allow veneer to dry thoroughly.<br />

2. Scrub with soft bristle brush and clean water.<br />

3. Rinse immediately with clean water; allow to dry.<br />

4. If efflorescence is still visible, repeat above procedure using a solution of 1 part household vinegar and 5<br />

parts water.<br />

5. Rinse immediately with clean water.<br />

3.5 PROTECTION<br />

A. Protect finished work from rain during and for 48 hours following installation.<br />

END OF SECTION<br />

04711 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082710<br />

SECTION 05090 – POST-INSTALLED CONCRETE AND MASONRY ANCHORS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Post-installed mechanical and adhesive type anchors for structural members and equipment<br />

support.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C 881 - Epoxy-Resin-Based Bonding Systems for Concrete.<br />

1.3 QUALITY ASSURANCE<br />

A. Reports showing evidence of published performance data for each anchor used shall be available for review by the<br />

Structural Engineer of Record (SER) upon request. Evidence may be in the form of current ICC-ER report or a<br />

report by an independent testing laboratory.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Provide products from one of the following manufacturers:<br />

1. Hilti, Inc. (800) 879-8000.<br />

2. ITW Red Head (800) 899-7890.<br />

3. Simpson Strong Tie Co., Inc. (800) 999-5099.<br />

4. Powers Fasteners, Inc. (800) 524-3244.<br />

2.2 MATERIALS<br />

A. Substitutions: Substitutions of products from manufacturers not listed are not permitted.<br />

B. Alternate Products: Alternate products from the manufacturers listed may be used upon approval based upon<br />

suitability for the installation involved as determined by the SER.<br />

C. Provide proprietary anchor products as specified below unless otherwise shown on the drawings or specified in<br />

other sections. Anchors may be any one of the products listed for the type specified unless otherwise shown or<br />

specified.<br />

D. Manufacturer’s Instructions: Provide complete installation instructions with items furnished to the field.<br />

2.3 MECHANICAL ANCHORS<br />

A. Interior Use Anchors: Zinc plated carbon steel anchors.<br />

B. Exterior Use Anchors: Stainless steel with stainless steel nuts and washers of matching alloy group and minimum<br />

proof stress equal to or greater than the specified minimum full-size tensile strength of the externally threaded<br />

fastener.<br />

05090 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Wedge Expansion Anchors: Torque-controlled, with impact section to prevent thread damage complete with<br />

required nuts and washers. Type and size as indicated on Drawings. Provide one of the following:<br />

1. Hilti Kwik Bolt 3.<br />

2. Simpson Wedge All.<br />

3. ITW Red Head Trubolt.<br />

4. Powers Power-Stud.<br />

D. Sleeve Anchors: Torque controlled, exhibiting follow-up expansion under load, with provision for rotation<br />

prevention during installation. Provide one of the following:<br />

1. Hilti HLC Sleeve Anchor.<br />

2. Simpson Sleeve-All Sleeve Anchor.<br />

3. ITW Red Head Dynabolt Sleeve Anchor.<br />

4. Powers Power-Bolt Sleeve Anchor.<br />

E. Screw Anchors: Single piece anchor installed in a pre-drilled hole using a bit matching manufacuturer tolerances.<br />

Anchors shall have 360-degree contact with the base material and shall not require oversized or undersized holes<br />

for installation. Provide one of the following:<br />

1. Hilti HUS-H or KWIK-CON II Screw Anchor.<br />

2. Simpson Titen HD or Titen HD Mini Screw Anchor.<br />

3. ITW Red Head Tapcon or Large Diameter Tapcon (LDT) Screw Anchor.<br />

4. Powers Wedge-Bolt or Tapper Screw Anchor.<br />

2.4 ADHESIVE ANCHORS<br />

A. Adhesive Anchor Bolts: Stud-type anchors consisting of threaded steel rod, nut, and washer or deformed<br />

reinforcing bar, and anchor adhesive. Use type and size as indicated on Drawings. Use stainless steel or zinc<br />

coated carbon steel for exterior exposure.<br />

B. Epoxy Adhesive: ASTM C881 Type I, II, IV and V, Grade 3, Class B and C. Adhesive shall be a cartridge type,<br />

two-component, solid epoxy based system dispensed and mixed through a static mixing nozzle supplied by the<br />

manufacturer. Acceptable installation and performance temperature ranges shall be verified with manufacturer’s<br />

literature prior to installation. Provide one of the following:<br />

1. Hilti HIT HY 150 or HIT RE 500 Epoxy Adhesive.<br />

2. Simpson Epoxy-Tie (ET) Adhesive, High Strength Epoxy-Tie (SET) Adhesive or Structural Epoxy-Tie<br />

(SET-XP) Adhesive.<br />

3. ITW Red Head Epcon C6 Epoxy or Epcon G5 High Strength Epoxy Adhesive.<br />

C. Acrylic Adhesive: ASTM C881 Type I and IV, Grade 3, Class A, B, and C. Adhesive shall be a cartridge type,<br />

two-component, acrylic based system dispensed and mixed through a static mixing nozzle supplied by the<br />

manufacturer. Provide one of the following:<br />

a. Hilti HIT HY-ICE or HIT HY-150 MAX Acrylic Adhesive.<br />

b. Simpson Acrylic-Tie (AT) Adhesive.<br />

c. ITW Red Head Epcon A7 Acrylic Adhesive.<br />

d. Powers AC100 Plus Acrylic Adhesive.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine conditions and adjacent areas where products and materials will be installed and verify that conditions<br />

conform to product manufacturer's requirements. Verify that structural components are ready to receive Work.<br />

Do not proceed until unsatisfactory conditions have been corrected.<br />

B. Beginning of installation indicates acceptance of existing conditions.<br />

05090 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.2 INSTALLATION<br />

A. Post-installed anchors installed for missing or misplaced cast-in-place anchors shall be approved by the SER.<br />

B. Where manufacturer recommends use of special tools for installation of anchors, such tools shall be used, unless<br />

otherwise permitted specifically by the SER.<br />

C. Where holes are drilled in concrete or masonry, holes shall be accurately and squarely drilled, and the holes shall<br />

be cleaned in accordance with the manufacturer’s recommendations.<br />

D. Post-installed Anchor Installation (General):<br />

1. Install post-installed anchors where shown on the drawings.<br />

2. Perform anchor installation in accordance with manufacturer instructions. Install anchors at not less than<br />

the minimum embedment, edge distance, and spacing recommended by the manufacturer.<br />

3. Drill holes with rotary impact hammer drills using carbide-tipped bits. Drill bits shall be of diameters as<br />

specified by the anchor manufacturer. Unless otherwise shown on the Drawings, all holes shall be drilled<br />

perpendicular to the concrete surface.<br />

a. Cored Holes: Where anchors are to be installed in cored holes, use core bits with matched<br />

tolerances as specified by the manufacturer.<br />

b. Embedded Items: Identify position of reinforcing steel and other embedded items prior to drilling<br />

holes for anchors. Avoid damage to existing reinforcing or embedded items during coring or<br />

drilling. Avoid damaging electrical and telecommunications conduit and gas lines. Notify the SER<br />

if reinforcing steel or other embedded items are encountered during drilling.<br />

c. Base Material Strength: Unless otherwise specified, do not drill holes in concrete or masonry until<br />

concrete, mortar, or grout has achieved full design strength.<br />

4. Use anchors of the same anchor manufacturer for anchors of the same type.<br />

E. Mechanical Anchor Installation: Protect threads from damage during anchor installation. Sleeve anchors shall be<br />

installed with sleeve fully engaged in part to be fastened. Set anchors to manufacturer’s recommended torque,<br />

using a torque wrench.<br />

F. Adhesive Anchor Installation:<br />

1. When the base material temperature drops below 40 degrees F, use only acrylic adhesive. See<br />

manufacturer’s instructions for additional minimum temperature requirements. Maintain environmental<br />

conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for<br />

optimum results. Do not install under environmental conditions outside manufacturer’s absolute limits.<br />

2. Hollow Substrates: Anchorage into hollow substrates is not allowed unless specifically indicated on the<br />

contract documents. Where applicable, the adhesive manufacturer’s screen tubes shall be used for adhesive<br />

installation into hollow substrate applications.<br />

3. Oversized Holes: Refer to manufacturer’s information if drilled hole size is larger than what is<br />

recommended.<br />

4. Core Drilled Holes: Refer to manufacturer’s information if holes are drilled with a core-drill bit.<br />

5. Clean holes per manufacturer instructions to remove loose material and drilling dust prior to installation of<br />

adhesive. Inject adhesive into holes proceeding from the bottom of the hole and progressing toward the<br />

surface in such a manner as to avoid introduction of air pockets in the adhesive. Follow manufacturer<br />

recommendations to ensure proper mixing of adhesive components. Sufficient adhesive shall be injected in<br />

the hole to ensure that the annular gap is filled to the surface. Remove excess adhesive from the surface.<br />

Shim anchors with suitable device to center the anchor in the hole. Do not disturb or load anchors before<br />

manufacturer specified cure time has elapsed.<br />

3.3 REPAIR OF DEFECTIVE WORK<br />

A. Remove and replace misplaced, defective, or malfunctioning anchors. Anchors that fail a sheer or pullout test, if<br />

directed or installation torque requirements shall be regarded as malfunctioning. Fill empty anchor holes and<br />

patch failed anchor locations with high-strength non-shrink, nonmetallic grout.<br />

05090 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.4 QUALITY ASSURANCE TESTING AND INSPECTION<br />

A. Unless otherwise specified, quality control tests and inspection specified below will be conducted by the Owner’s<br />

Construction Testing Laboratory (CTL) at no cost to the Contractor in accordance with Section 01458. The<br />

Contractor shall perform additional testing or inspection as considered necessary by the Contractor for assurance<br />

of quality control.<br />

1. Work shall be performed by a Special Inspector - Technical II or Special Inspector - Structural I.<br />

B. Mechanical and Adhesive Anchors:<br />

1. Periodically verify the following:<br />

a. General compliance with manufacturer’s published instructions.<br />

b. Product name and description.<br />

c. Adhesive expiration date for adhesive anchors.<br />

d. Compliance of drill bit with manufacturer’s specifications.<br />

e. Adhesive application technique for adhesive anchors.<br />

2. Continuously inspect and verify the following:<br />

a. Hole diameter, depth, location, and edge distance.<br />

b. Cleanliness of hole and anchor.<br />

c. Anchor diameter, length, and steel grade.<br />

d. Anchor embedment and spacing.<br />

e. Required tightening torque for mechanical anchors.<br />

C. Additional Testing: Perform pullout or shear tests to determine adequacy of suspected malfunctioning anchors<br />

when directed to do so by the Wal-Mart Construction manager upon recommendation by the CTL.<br />

END OF SECTION<br />

05090 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 05120 (05 1200) – STRUCTURAL STEEL<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Structural steel framing members, structural steel support members, struts, with required bracing, welds,<br />

and fasteners.<br />

2. Base plates and shear stud connectors.<br />

3. Teflon coated slide bearing pads.<br />

4. Grout, for setting and anchoring items in masonry and concrete.<br />

B. Related Requirements:<br />

1. Division 3 -Concrete: Anchorages cast in concrete.<br />

2. Section 05090 - Post Installed Concrete and Masonry Anchors: Mechanical and adhesive type anchor<br />

studs, expansion bolts, sleeve anchors, adhesive anchors, and anchor bolts embedded in concrete and<br />

masonry for anchoring and supporting structural members.<br />

3. Section 05500 - Metal Fabrications: Miscellaneous steel components.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Institute of Steel Construction (AISC):<br />

1. AISC 303 - Code of Standard Practice for Steel Buildings and Bridges.<br />

2. AISC 360 - Structural Steel Buildings.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 36 - Structural Steel.<br />

2. ASTM A 53 - Pipe, Steel, Black and Galvanized, Seamless and Welded.<br />

3. ASTM A 108 - Steel Bars, Carbon And Alloy, Cold- Finished.<br />

4. ASTM A 123 - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.<br />

5. ASTM A 307 - Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength.<br />

6. ASTM A 325 - Structural Bolts, Heat Treated, 120/105 ksi Minimum Tensile Strength.<br />

7. ASTM A 490 - Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength.<br />

8. ASTM A500 - Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes.<br />

9. ASTM A 501 - Hot-Formed Welded and Seamless Carbon Steel Structural Tubing.<br />

10. ASTM A 992 - Structural Steel Shapes.<br />

11. ASTM C 1107 - Packaged Dry, Hydraulic-Cement Grout (Non-Shrink).<br />

12. ASTM D 1187 - Asphalt-Base Emulsions for Use as Protective Coatings for Metal.<br />

13. ASTM E 709 - Standard Guide for Magnetic Particle Testing.<br />

D. American Welding Society (AWS):<br />

1. AWS D1.1 - Structural Welding Code.<br />

2. AWS D1.3 - Structural Welding Code - Sheet Steel.<br />

E. Research Council on Structural Connections (RCSC):<br />

1. Specification for Structural Joints Using ASTM A 325 or A 490 Bolts.<br />

F. Steel Structures Painting Council (SSPC):<br />

1. SSPC-SP 2 - Hand Tool Cleaning.<br />

05120 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-installation Meeting:<br />

1. Convene Pre-installation Meeting at Site one week prior to commencing work of this Section. Require<br />

attendance of parties directly affecting work of this Section, including, but not limited to, the Owner's<br />

representative, Contractor, steel erector sub-contractor and foreman, and Owner’s Construction Testing<br />

Laboratory.<br />

2. Notify all attendees at least two weeks prior to the meeting.<br />

3. Review preparation and installation procedures and coordinating and scheduling required with related<br />

work.<br />

4. Review foreseeable methods and procedures related to the work, including the following:<br />

a. Tour, inspect, and discuss condition of preparatory work performed by other trades.<br />

b. Review structural loading limitations and bracing requirements.<br />

c. Review drawings, specifications and other contract documents including submittals.<br />

d. Review and finalize construction schedule related to work and verify availability of materials,<br />

installer's personnel, equipment, and facilities needed to make progress and avoid delays.<br />

e. Review required inspections, testing, certifying, and material usage accounting procedures.<br />

f. Review weather and forecasted weather conditions, and procedures for coping with unfavorable<br />

conditions.<br />

5. Record discussions of the meeting and decisions and agreements (or disagreements) reached, and furnish<br />

copy of record to each party attending.<br />

1.4 SUBMITTALS<br />

A. Submittals: Comply with the requirements of Section 01330.<br />

B. Shop Drawings: Submit within 10 working days of Contract Date.<br />

1. Indicate profiles, sizes, spacing, and locations of structural members, connections, attachments, and<br />

fasteners.<br />

2. Include supplementary parts and members necessary to complete structural steel work, regardless of<br />

whether parts are definitely shown or specified, and furnish bolts, gussets, plates, and related items as<br />

required for proper assembly of items.<br />

3. Include miscellaneous deck support angles as required for proper support of metal deck around columns,<br />

gussets, openings, and obstructions.<br />

4. Indicate welded connections using standard AWS welding symbols.Indicate net weld lengths.<br />

5. Provide setting drawings, templates, and directions for installation of anchor bolts and other anchorages to<br />

be installed by other trades.<br />

6. Indicate top of bearing plate elevations, and elevations above finish floor to the centerlines of embedded<br />

plate, anchor bolts, and all control joint locations.<br />

7. Templates shall be furnished by fabricator with instructions for setting of anchor bolts and bearing plates.<br />

8. Prepare shop drawings under seal of a Professional Structural Engineer registered in the State in which<br />

Project is located.<br />

9. Omission from shop drawings of materials required by Contract Documents does not relieve Contractor of<br />

responsibility of furnishing and installing such materials even though shop drawings may have been<br />

returned and reviewed.<br />

C. Quality Control Submittals: Within 10 days of Contract Date, submit design calculations for structural steel<br />

connections not detailed on Contract Documents or proposed differently than as shown on Contract Documents,<br />

signed and sealed by Professional Structural Engineer registered in State in which Project is located.<br />

D. Substitutions: Submit substitutions of sections or modifications of details, or both, and reasons for proposal, with<br />

shop drawings. Clearly identify substitutions as such. Accepted substitutions, modifications, and necessary<br />

changes in related portions of Work shall be coordinated by fabricator and shall be accomplished at no additional<br />

cost to Wal-Mart.<br />

05120 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 QUALITY ASSURANCE<br />

A. Welder Qualifications: Qualify welding operators in accordance with Standard Qualification Procedures as<br />

required by AWS D1.1.<br />

B. Comply with applicable provisions of the following specifications and documents:<br />

1. AISC 303.<br />

2. AISC 360.<br />

3. RCSC Specification for Structural Joints Using ASTM A 325 or A 490 Bolts.<br />

C. Design connections not detailed on Drawings under direct supervision of a Professional Structural Engineer<br />

experienced in the design of this Work registered in State in which the project is located.<br />

1.6 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in accordance with the requirements of Section 01600.<br />

B. Store materials to permit easy access for inspection and identification.<br />

C. Keep steel members off ground by using pallets, platforms, or other supports.<br />

D. Protect steel members and packaged materials from erosion and deterioration.<br />

1. Store fasteners in a protected place. Clean and relubricate bolts and nuts that become dry or rusty before<br />

use.<br />

2. Do not store materials on structure in a manner that might cause distortion or damage members or<br />

supporting structures.<br />

3. Remove salt residue from steel members by power spraying when present as a result of salted roads during<br />

winter weather transport.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Structural Steel:<br />

1. Wide Flange Steel Shapes: ASTM A 992.<br />

2. Steel Channels, Angles, Anchor Bolts, Plates and Bars: ASTM A 36.<br />

B. Structural Tubing: ASTM A 500, Grade B.<br />

C. Structural Steel Pipe: ASTM A53, Grade B; ASTM A500, Grade B; or ASTM A 501 as shown on the drawings.<br />

D. Bolts, Nuts, and Washers: ASTM A 325 or A 307 as shown on Drawings.<br />

E. Welding Materials: AWS D1.1; type required for materials being welded or as shown on Drawings.E7024<br />

electrodes ("Jet Weld" rods) are not permitted; use only "All Position" rods (7018LH).<br />

F. Headed Stud Anchors: ASTM A 108, Grades 1010 through 1020, headed-stud type, cold-finished carbon steel;<br />

AWS D1.1, Type B.<br />

G. Adhesive Anchors: Specified in Section 05090.<br />

H. Alkyd Primer: Gray color.<br />

1. B50AV11 by Sherwin-Williams (800) 474-3794.<br />

I. Asphaltic Mastic: Cold-applied asphalt emulsion complying with ASTM D 1187.<br />

05120 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


J. Teflon Coated Slide Bearing Pads: Provide one of the following products:<br />

1. Fluorogold by Seismic Energy Products, LP (formerly Furon), Athens, TX (903) 675-8571.<br />

2. Dura-Slide by Tobi Engineering, Glenview, IL (847) 724-7880.<br />

3. Type CSA by Con-Serv, Inc., Georgetown, SC (843) 546-1044.<br />

K. Non-shrink Grout: Pre-mixed non-shrinking, high strength grout, ASTM C1107, Type A, B, or C; compressive<br />

strength of 5,000 psi in 28 days. Provide one of the following products:<br />

1. NS Grout by Euclid Chemical, Cleveland, OH (800) 321-7628.<br />

2. Construction Grout by BASF Building Systems.<br />

3. Certi-Vex Grout 1000 by Vexcon Chemicals, Philadelphia, PA (888) 839-2661.<br />

4. Conspec Enduro 50 by Dayton Superior, Miamisburg, OH (888) 977-9600.<br />

2.2 FABRICATION<br />

A. Fabricate and assemble structural steel in shop to greatest extent possible. Fabricate according to AISC 360.<br />

B. Do not splice structural steel members unless otherwise shown on Drawings.<br />

2.3 FINISH<br />

A. Clean, prepare, and shop prime structural steel members.<br />

B. Do not paint surfaces in contact with concrete, or surfaces specified to be galvanized.<br />

C. Galvanized Finish: Minimum 1.25 oz/sq ft zinc (hot-dipped galvanized) coating complying with ASTM A 123.<br />

Galvanize the following items:<br />

1. Structural steel angles and plates, exposed to weather and in contact with or embedded in concrete or<br />

masonry.<br />

2. Anchor bolts exposed to weather and in contact with or embedded in concrete or masonry.<br />

D. Alkyd Primer Finish: Prepare structural steel items scheduled to recieve alkyd primer by SSPC-SP 2 (Hand Tool<br />

Cleaning) method. Prime steel with alkyd primer; minimum dry mil thickness of 2 mils. Apply alkyd primer to<br />

the following items:<br />

1. Structural steel items not specified as galvanized.<br />

2. Garden Center canopy framing (excluding wall angles, which are galvanized as specified herein).<br />

3. Satellite dish support (from bottom of deck to top of support).<br />

4. Exposed rooftop refrigeration and HVAC support framing.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine conditions and adjacent areas where products and materials will be installed and verify that conditions<br />

conform to product manufacturer's requirements. Verify elevations of concrete and masonry bearing surfaces and<br />

locations of anchorage. Verify that all conditions are ready to receive Work. Do not proceed until unsatisfactory<br />

conditions have been corrected.<br />

3.2 PREPARATION<br />

A. Supply items required to be cast into concrete or embedded in masonry with setting diagrams.<br />

05120 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 SURVEY<br />

A. Employ Professional Engineer or Land Surveyor registered in State in which Project is located, experienced in<br />

survey work, to establish permanent bench marks as shown and as necessary for accurate erection of structural<br />

steel. Check elevations of concrete and masonry bearing surfaces, and locations of anchor bolts and similar<br />

devices, before erection work proceeds, and report discrepancies to Wal-Mart Construction Manager. Do not<br />

proceed with erection until corrections have been made, or until compensating adjustments to structural steel work<br />

have been agreed upon with Wal-Mart.<br />

3.4 ERECTION<br />

A. Set structural steel accurately in locations and to elevations indicated and according to AISC 303 and AISC 360.<br />

B. Make provision for erection loads, and for sufficient temporary bracing to maintain structure safe, plumb, and in<br />

true alignment until completion of erection and installation of permanent bracing.<br />

C. Do not field cut or alter structural members.<br />

D. After erection, paint surfaces not shop painted that are to receive finish painting, except surfaces to be in contact<br />

with concrete. Use a primer consistent with shop coat.<br />

E. Anchor Bolts: Install anchor bolts and other connectors required for securing structural steel to foundations and<br />

other in-place work. Furnish templates and other devices as necessary for presetting bolts and other anchors to<br />

accurate locations. Provide post installed anchors in accordance with Section 05090.<br />

F. Setting Bases and Bearing Plates: Clean concrete and masonry bearing surfaces of bond-reducing materials and<br />

roughen to improve bond to surfaces. Clean bottom surfaces of base and bearing plates.<br />

1. Set loose and attached base plates and bearing plates for structural members on adjusting nuts.<br />

2. Tighten anchor bolts after the supported members have been positioned and plumbed.<br />

3. Grout solidly between bearing surfaces and bases of plates. Finish exposed surfaces, protect installed<br />

materials, and allow to cure. For proprietary grout materials, comply with manufacturer's installation<br />

instructions.<br />

4. Slide Bearing Pads: Permanently affixed to member and support, respectively, by welding or bolting as<br />

indicated. Align and level member faces to maintain full contact between surfaces before completing<br />

installation.<br />

G. High Strength Bolting: Install high-strength bolts according to RCSC Specification for Structural Joints Using<br />

ASTM A 325 or A 490 Bolts for type of bolt and type of joint shown or specified.<br />

H. Erection Bolts:<br />

1. Comply with ASTM A 307.<br />

2. Hand tighten nut to minimum depth of nut.<br />

I. Field Welding: Perform field welding in accordance with AWS D1.1 or D1.3, as applicable. After installation,<br />

grind sight-exposed field welds smooth, touch-up welds, scratched, or damaged surfaces with primer.<br />

J. Touch-up Painting: Immediately after erection, clean exposed field welds, bolted connections, and abraded areas<br />

of shop paint. Apply paint to exposed areas with same material as used for shop painting. Apply by brush or<br />

spray to provide a minimum dry film thickness of 2.0 mils.<br />

K. Protective Coating: Apply heavy coat of asphatic mastic bituminous coating to anchor bolts, base plates, and<br />

columns below finished floor where shown on the drawings.<br />

L. Field Painting: Specified in Section 09900.<br />

05120 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.5 QUALITY ASSURANCE TESTING AND INSPECTION<br />

A. Responsibilities: Unless otherwise specified, quality control tests and inspection specified below will be<br />

conducted by the Wal-Mart Construction Testing Laboratory (CTL) at no cost to Contractor in accordance with<br />

Section 01458. Contractor shall perform additional testing or inspection as considered necessary by the Contractor<br />

for assurance of quality control.<br />

1. Work shall be performed by a Special Inspector - Technical II or Special Inspector - Structural I.<br />

a. In addition to the Special Inspector qualification stated in Section 01458, the Technical II Inspector<br />

shall be anAmerican Society for Non-destructive Testing (ASNT), Non-destructive Testing<br />

Technician, TC-1A Level I, or an American Welding Society (AWS) Certified Associate Weld<br />

Inspector (C.A.W.I.).<br />

2. CTL shall report results shall be made after each observation visit.<br />

B. High Strength Bolting (Field Installed):<br />

1. General:<br />

a. Visually inspect mating surfaces and bolt type for all slip-critical bolted connections for general<br />

conformance with the contract documents prior to bolting.<br />

b. Verify that requirements for bolts, nuts, washers, paint and installation/tightening standards are met.<br />

c. Observe calibration procedures and verify that selected procedure is used to tighten bolts.<br />

d. Test High Strength bolted connections in accordance with bolting standard specified above.<br />

2. Slip Critical and Tension Bolts: Test bolt tightening in 100% of all bolts.Verify that all surfaces of<br />

connected elements have been brought into contact at 100% of connections. Verify all tips are removed<br />

from twist-off bolts.<br />

3. Bearing Bolts: Visually inspect to confirm all surfaces of connected elements have been brought into<br />

contact, at 100% of connections. This shall apply only to bolts designed for values not requiring exclusion<br />

of threads from failure plane. All other bolts shall be tested as for tension bolts.<br />

C. High Strength Bolting (Shop Installed): For shop fabricated work, perform tests required for field installation,<br />

except that bolt testing may be reduced or deleted if fabrication shop satisfies AISC Quality Certification Program<br />

Category STD (Standard for Steel Building Structures), or more stringent criteria, or is approved by Building<br />

Official and SER.<br />

D. Welding (General):<br />

1. Prior to start of fabrication, determine if fabrication shop meets the criteria for exempting shop welds from<br />

inspection and confirm in writing to Building Official and SER.<br />

2. Verify qualifications of welders as AWS certified.<br />

3. Verify proposed welding procedures and materials.<br />

4. Verify adequate preparation of faying surfaces.<br />

5. Verify preheat and interpass temperatures of steel, proper technique and sequence of welding, and cleaning<br />

and number of passes are provided as required.<br />

E. Welding (Field):<br />

1. Single Pass Fillet Welds less than or equal to 5/16 inch: Visually inspect 100% of all fillet welds for size,<br />

length, and quality, per AWS D1.1.<br />

2. Single Pass Fillet Welds greater than 5/16 inch: Continuously inspect 100% of all fillet welds for size,<br />

length, and quality, per AWS D1.1.<br />

3. Multi-pass Fillet Welds: Continuously inspect 100% of all fillet welds for size, length, and quality, per<br />

AWS D1.1.<br />

4. Partial Penetration Welds: Test 100% of all partial penetration welds exceeding 5/16 inch, using Ultrasonic<br />

Testing per AWS. D1.1. Test 100% of all partial penetration welds less than 5/16 inch, using Magnetic<br />

Particle Testing per ASTM E 709, performed on root pass and on finished weld.<br />

5. Complete Penetration Welds: Test 100% of all complete penetration welds exceeding 5/16 inch, using<br />

Ultrasonic Testing per A.W.S. D1.1. Test 100% of all complete penetration welds less than 5/16 inch,<br />

using Magnetic Particle Testing per ASTM E 709, performed on root pass and on finished weld.<br />

6. Miscellaneous Metals, Inserts and Prefabricated Components: Where integrity of the connections impact<br />

life safety or performance of the building structure, provide testing and inspection as for typical welds<br />

previously specified.<br />

05120 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


F. Welding (Shop): Perform inspections as for field welding except weld testing may be reduced or deleted if<br />

fabrication shop satisfies AISC Quality Certification Program - Category I, or more stringent criteria, and is<br />

approved by Building Official and SER.<br />

G. Submittal Verification: Verify mill test reports and other submitted documentation for compliance with Contract<br />

Documents.<br />

H. Materials Verification: Verify materials delivered to Site comply with Contract Documents and approved shop<br />

drawings. Materials and verifications include:<br />

1. Structural Steel:<br />

a. Identification markings to conform to ASTM standards.<br />

b. Manufacturer’s certified mill test reports.<br />

2. High Strength Bolts, Nuts, and Washers:<br />

a. Identification markings to conform to ASTM standards.<br />

b. Manufacturer’s certificate of compliance.<br />

3. Welding Electrodes:<br />

a. Identification markings to conform to AWS specification.<br />

b. Manufacturer’s certificate of compliance.<br />

I. Verification of Detail Compatibility:<br />

1. Inspect on a periodic basis.<br />

2. Review project documents affecting integrity of the structure, including Contract Documents and pertinent<br />

submittals includingapproved shop drawings.<br />

3. Visit Site at intervals appropriate to the stage of construction to perform review of the structure and visually<br />

confirm general compliance with Contract Documents.<br />

4. Inspect the following to verify member orientation, configuration, type, and size comply with details<br />

indicated in Contract Documents and approved shop drawings:<br />

a. Bracing and stiffening members.<br />

b. Structural member locations.<br />

c. Proper applications of joint details at connections for structural members.<br />

d. Other work critical to the integrity of the building structure.<br />

END OF SECTION<br />

05120 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 05400 (05 4000) – COLD FORMED METAL FRAMING<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Cold formed steel stud exterior and interior framing 20 gage and heavier.<br />

B. Related Requirements:<br />

1. Section 05090 - Post-installed Concrete and Masonry Anchors: Mechanical and adhesive anchors drilled<br />

into concrete or masonry.<br />

2. Section 05120 - Structural Steel: Connecting to structural building framing.<br />

3. Section 06100 - Rough Carpentry: Wood deck, furring strips, plywood, and blocking.<br />

4. Section 07210 - Building Insulation: Thermal insulation installed in exterior framing.<br />

5. Section 09100 - Lath and Plaster (Stucco).<br />

6. Section 09250 - Gypsum Board: Non-load bearing steel stud partition framing lighter than 20 gage.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Iron and Steel Institute (AISI):<br />

1. North American Specification for the Design of Cold-Formed Steel Structural Members.<br />

2. Standard for Cold-Formed Steel Framing.<br />

C. ASTM International (ASTM):<br />

3. ASTM A 36 - Carbon Structural Steel.<br />

4. ASTM A 123 - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.<br />

5. ASTM A 1003 - Steel Sheet, Carbon, Metallic- and Nonmetallic-Coated for Cold-Formed Framing<br />

Members.<br />

6. ASTM C 1007 - Installation of Load Bearing (Transverse and Axial) Steel Studs and Related Accessories.<br />

7. ASTM C 1513 - Steel Tapping Screws for Cold-Formed Steel Framing Connections.<br />

D. American Welding Society (AWS):<br />

8. AWS D1.1 - Structural Welding Code - Steel.<br />

9. AWS D1.3 - Structural Welding Code - Steel Sheet.<br />

E. Gypsum Association (GA):<br />

1. GA-216 - Application and Finishing of Gypsum Board.<br />

F. Steel Structures Painting Council (SSPC):<br />

1. SSPC-Paint 20 - Zinc-Rich Coating Type I Inorganic And Type II Organic.<br />

1.3 QUALITY ASSURANCE<br />

A. Installer Qualifications: Company specializing in the installation of cold formed metal framing components with<br />

minimum five years documented experience.<br />

B. Qualifications for Welding Work: Qualify welding operators in accordance with Standard Qualification<br />

Procedures as required by AWS D1.1.<br />

05400 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Protect metal framing from corrosion, deformation, and other damage during delivery, storage, and handling.<br />

C. Store and protect metal framing products with waterproof covering; ventilate to avoid condensation.<br />

D. Where framing is stored outdoors, stack materials off ground, supported on level platform, fully protected from<br />

weather.<br />

PART 2 PRODUCTS<br />

2.1 MATERIALS<br />

A. Comply with AISI North American Specification for the Design of Cold-Formed Steel Structural Members and<br />

Standard for Cold-Formed Steel Framing.<br />

B. Steel Sheet: ASTM A 1003, Structural Grade, Type H, metallic coated, Grade: ST33H (33 ksi) unless otherwise<br />

indicated, Coating G60.<br />

C. Material Thickness: Gage shown on Drawings shall have the following minimum base metal thickness.<br />

1. 20 gage: 33 mils.<br />

2. 18 gage: 43 mils.<br />

3. 16 gage: 53 mils.<br />

2.2 FRAMING AND ACCESSORIES<br />

A. Interior and Exterior Load-Bearing Studs: Manufacturer's standard C-shaped steel studs, of web depths indicated,<br />

punched, with stiffened flanges, depth, flange width, and gage as indicated on Drawings.<br />

B. Interior and Exterior Load-Bearing Steel Joists: Manufacturer's standard C-shaped steel joists, of web depths<br />

indicated, with stiffened flanges.<br />

C. Partition Floor Tracks and Runners: Galvanized sheet steel, C-shaped; same depth and gage as studs; tight fit;<br />

solid web.<br />

D. Steel Track: Manufacturer's standard U-shaped steel track, of web depths indicated, unpunched, with unstiffened<br />

flanges, and same minimum base-metal thickness as steel studs.<br />

E. Deflection (Capture) Track: Deep-leg, U-shaped steel track; unpunched, with unstiffened flanges, of web depth as<br />

shown to contain studs while allowing free vertical movement, with flanges or legs as shown designed to support<br />

horizontal and lateral loads. Provide fasteners as indicated on Drawings.<br />

1. Contractor's Option: Manufacturer’s standard double or single deflection track as follows:<br />

a. VertiClip or VertiTrack by The Steel Network, Raleigh, NC (888) 474-4876. If this option is used,<br />

track may be 20 gauge for all stud sizes.<br />

b. FastTop Clip by ClarkDietrich Building Systems, West Chester, OH (513) 870-1100.<br />

c. SLP-TRK by Brady Innovations as distributed by ClarkDietrich.<br />

F. Vertical Deflection Clip (Slide Clip): VertiClip SLB by The Steel Network as shown on Drawings.<br />

G. Load-Bearing Wall Furring and Partition Bracing: Galvanized sheet steel.<br />

1. Cold-Formed Channels: 3/4 inch x 1/2 inch and 1-1/2 inch x 17/32 inch or as shown on Drawings.<br />

2. Clip Angles: 2 inches x 2 inches x 16 gage x 1/4 inch less than stud width or<br />

a. Bridge Clip by The Steel Network.<br />

b. EasyClip U-Series Clip Angles 1-1/2” x 1-1/2” x 16 gage x 1/4 inch less than stud width by<br />

ClarkDietrich.<br />

05400 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Contractor’s Option: In lieu of cold-formed channels and clip angles for horizontal bridging, provide one<br />

of the following:<br />

a. Bridge Bar by The Steel Network.<br />

b. TradeReady Spazzer 5400 spacing bar by ClarkDietrich.<br />

H. Steel Shapes and Clips: ASTM A 36, zinc coated by hot-dip process according to ASTM A 123.<br />

I. Framing Attachment Angles: Galvanized sheet steel, size, shape and configuration as indicated on Drawings, 14<br />

gage, unless indicated otherwise on Drawings.<br />

1. Contractor’s Option: Contact ClarkDietrich (866) 638-1908 for alternative selections.<br />

J. Ceiling Joists and Runners: Galvanized sheet steel, C-shaped.<br />

K. Flat Metal Straps and Plates: Galvanized sheet steel, gage, shape, and configuration as indicated on Drawings.<br />

1. Contractor's Option: In lieu of 2-inch continuous metal strap at deflection (capture) tracks, Contractor may<br />

provide one of the following:<br />

a. Bridge Bar by The Steel Network.<br />

b. TradeReady Spazzer 5400 bridging and spacing bar by ClarkDietrich.<br />

2.3 FASTENERS<br />

A. Power-Actuated Anchors: Fastener system of type suitable for application indicated, fabricated from corrosionresistant<br />

materials, with capability to sustain, without failure, a load equal to 10 times design load.<br />

B. Mechanical Fasteners: ASTM C 1513, corrosion-resistant-coated, self-drilling, self-tapping steel drill screws.<br />

C. Framing to Framing: ASTM C 1513; 5/8 inch Type S-12 low-profile head corrosion-resistant self-drilling selftapping<br />

steel screws.<br />

D. Framing to Attachment Angle Fasteners: #12 diameter pan head corrosion-resistant self-drilling self-tapping steel<br />

screws.<br />

E. Wall Floor Track Anchorage Device: Carbon steel wedge type expansion anchor; minimum 3/8 inch diameter x<br />

minimum 1-1/2 inch embedment unless noted otherwise on Drawings. Refer to Section 05090 for approved<br />

anchors.<br />

F. Wall Furring to Concrete or Masonry Wall Fasteners: Hex head screw anchors; minimum 1/4 inch diameter x<br />

minimum 1-1/8 inch embedment unless noted otherwise on Drawings. Refer to Section 05090 for approved<br />

anchors.<br />

G. Furring Channel to Masonry or Concrete Surface Fasteners: Low velocity powder-actuated drive pins of size to<br />

suit application.<br />

H. Welding Materials: AWS D1.3.<br />

I. Wood Furring, Blocking, and Plywood, Attached to Framing Fasteners: Specified in Section 06100.<br />

2.4 FINISHES<br />

A. Galvanizing: G60 coating class.<br />

B. Galvanizing Repair Paint: SSPC-Paint 20, Type II - organic.<br />

2.5 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

05400 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine existing conditions and adjacent areas where products will be installed and verify that conditions<br />

conform to product manufacturer's requirements. Verify that building framing components are ready to receive<br />

work. Verify that rough-in utilities are in-place and located where required. Do not proceed until unsatisfactory<br />

conditions have been corrected.<br />

3.2 INSTALLATION - GENERAL<br />

A. Install cold-formed metal framing in accordance with AISI North American Standard for Cold-Formed Steel<br />

Framing and to manufacturer's written instructions unless more stringent requirements are shown or specified.<br />

B. Install system to provide for movement of components without damage, failure of joint seals, undue stress on<br />

fasteners, or other detrimental effects when subject to seasonal or cyclic day/night temperature ranges.<br />

C. Install system to accommodate construction tolerances, deflection of building structural members, and clearances<br />

of intended openings.<br />

D. Install cold-formed metal framing and accessories plumb, square, and true to line, and with connections securely<br />

fastened.<br />

E. Install framing members in one-piece lengths.<br />

F. Perform field welding in accordance with AWS D1.3.<br />

3.3 INSTALLATION - STUD FRAMING<br />

A. Install studs and fasteners in accordance with manufacturer's published instructions and, where gypsum board is<br />

attached to studs, install studs in accordance with GA-216 and ASTM C 1007.<br />

B. Metal Stud Spacing: 16 inches on center, maximum, unless otherwise shown on Drawings.<br />

C. Align stud web openings horizontally.<br />

D. Construct corners using minimum three studs.<br />

E. Place studs as indicated on Drawings, minimum 2 inches from abutting walls.<br />

F. Erect studs one piece full length. Splicing of studs not permitted.<br />

G. Erect studs, brace, and reinforce to develop full strength to meet design requirements.<br />

H. Install headers at partition openings using load-bearing C-shaped joists.<br />

I. Install framing between studs for attachment of mechanical and electrical items.<br />

J. Coordinate placement of insulation in multiple stud spaces made inaccessible after erection.<br />

K. Install intermediate studs above and below openings to match wall stud spacing.<br />

L. Fasten studs adjacent to door and window frames, partition intersections, and corners to top and bottom runner<br />

flanges in double-stud fashion with metal lock fastener tools.<br />

1. Securely fasten studs to jamb and head anchor clips of door and borrowed-light frames.<br />

2. Place horizontally a cut-to-length section of runner with web-flange bent at each end, fasten with minimum<br />

one screw per flange.<br />

05400 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Position a cut-to-length stud (extending to top runner) at vertical panel joints over door frame header.<br />

M. Install bridging for stud partitions over 8 feet high at mid-height with 1-1/2 inch rolled channels through studs and<br />

screw attach in place using clip angles. Lap channels by nesting one inside the other to a length of at least 8 inches<br />

and wire fasten together.<br />

N. Blocking: Screw attach wood blocking between studs. Install blocking for support of plumbing fixtures, toilet<br />

partitions, wall cabinets, toilet accessories, and hardware.<br />

O. Where optional framing products by the named manufacturers are specified in Part 2 above in lieu of conventional<br />

components specified, install in accordance with manufacturers recommendations.<br />

P. Touch up field welds and damaged galvanized surfaces with primer.<br />

Q. Fastening: Fasten framing in accordance with manufacturer's published instructions and schedule below unless<br />

indicated otherwise on Drawings.<br />

FASTENERS<br />

Floor Track to Concrete<br />

Partition Stud to Floor Track<br />

Stud Web to Stud Web<br />

Plates and Straps to Studs<br />

Lateral Bracing to Partition Stud Using clip Angles<br />

Runner to Header<br />

Welded Connections<br />

MINIMUM CONNECTION<br />

1 Anchor at 36 inches on center.<br />

1 Screw each side at flange.<br />

2 Screws.<br />

2 Screws.<br />

2 Screws to stud and 2 Screws to cold rolled channel.<br />

1 Screw at 16 inches on center, maximum 6 inches<br />

from each end.<br />

Indicated on Drawings.<br />

3.4 INSTALLATION - JOIST FRAMING<br />

A. Install joists and fasteners in accordance with manufacturer's published instructions.<br />

B. Make provisions for erection stresses. Provide temporary alignment and bracing.<br />

C. Place joists at locations and spacing as indicated on Drawings.<br />

D. Touch-up field welds and damaged galvanized surfaces with primer.<br />

E. Fastening: Indicated on Drawings.<br />

3.5 INSTALLATION - CEILING JOISTS<br />

A. Install joists and fasteners in accordance with manufacturer's published instructions and, where gypsum board is<br />

attached to joists, install joists in accordance with GA-216, and ASTM C 1007.<br />

B. Ceiling Joist Spacing: 16 inches on center beginning from center of room unless otherwise shown on Drawings.<br />

C. Install joists in direction of shortest span, parallel and level, with lateral bracing and bridging.<br />

D. Install joists in one piece full length. Splicing of joists not permitted.<br />

E. Install perimeter joist runner track sized to match joists. Attach joist runner track to wall framing with minimum 2<br />

screws per stud and at corners and ends.<br />

F. Attach joist ends to joist runner tracks with minimum 1 screw each side at each flange.<br />

05400 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


G. Install bridging at 48 inches on center beginning from center of room with 1-1/2 inch rolled channels screw<br />

attached to joists.<br />

1. Stagger bridging at light fixture locations as required.<br />

3.6 INSTALLATION - FURRING<br />

A. Furring Channels: Attach vertically spaced at maximum 16 inches on center, unless otherwise shown on<br />

Drawings, to masonry and concrete surfaces with specified powder driven fasteners staggered 24 inches on center<br />

on opposite flanges.<br />

B. Wall Furring:<br />

1. Secure top and bottom runners to structure.<br />

2. Space metal furring at maximum 16 inches on center unless otherwise shown on Drawings.<br />

3.7 INTERFACE WITH OTHER WORK<br />

A. Coordinate erection of studs with hollow metal door frames and overhead coiling door frames.<br />

B. Coordinate installation of anchors, supports, and blocking for mechanical, electrical, and building accessory items<br />

installed within framing.<br />

3.8 FIELD TESTS AND INSPECTIONS BY OWNER<br />

A. Unless otherwise specified, quality control tests and inspection specified below will be conducted by Owner’s<br />

Construction Testing Laboratory (CTL) at no cost to Contractor in accordance with Section 01458. Contractor<br />

shall perform additional testing or inspection as considered necessary by Contractor for assurance of quality<br />

control.<br />

1. Work shall be preformed by a Special Inspector - Technical II or Special Inspector - Structural I.<br />

B. Welding (General):<br />

1. Prior to start of fabrication, determine if fabrication shop meets the criteria for exempting shop welds from<br />

inspection and confirm in writing to building official and SER.<br />

2. Verify qualifications of all welders as AWS certified.<br />

3. Verify proposed welding procedures and materials.<br />

4. Verify adequate preparation of faying surfaces.<br />

5. Verify preheat and interpass temperatures of steel, proper technique and sequence of welding, and cleaning<br />

and number of passes are provided as required.<br />

C. Welding (Field):<br />

1. Cold Formed Metal Framing Welds: Visually inspect 100% of welds for specified length, size, and<br />

continuity in accordance with AWS D1.3 for metal less than 1/8" in thickness, for work designed as a<br />

structural element.<br />

2. Miscellaneous Metals, Inserts and Prefabricated Components: Where integrity of the connections impact<br />

life safety or performance of the building structure, provide testing and inspection as for typical welds<br />

previously specified.<br />

D. Miscellaneous Mechanical Fasteners: Visually inspect fasteners that are part of the building structural system for<br />

specified size, spacing, and location.<br />

E. Submittal Verification: Verify submitted documentation for compliance with Contract Documents.<br />

F. Material Verification: Verify materials delivered to site comply with Contract Documents and approved shop<br />

drawings. Materials include:<br />

1. Welding Electrodes.<br />

a. Identification markings to conform to AWS specifications.<br />

b. Manufacturer’s certificate of compliance.<br />

2. Mechanical fasteners.<br />

05400 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


G. Verification of Detail Compatibility:<br />

1. Inspect on a periodic basis.<br />

2. Review project documents affecting integrity of the structure including Contract Documents and approved<br />

shop drawings.<br />

3. Visit Site at intervals appropriate to the stage of construction to perform review of the structure and visually<br />

confirm general compliance with Contract Documents.<br />

4. Inspect the following to verify that member orientation, configuration, type, and size comply with details<br />

indicated on Contract Documents and approved shop drawings:<br />

a. Bracing and stiffening members.<br />

b. Structural member locations.<br />

c. Proper applications of joint details at connections for structural members.<br />

d. Other work critical to the integrity of the building structure.<br />

END OF SECTION<br />

05400 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 05500 (05 5000) – METAL FABRICATIONS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Shop fabricated ferrous metal items, galvanized and prime painted.<br />

2. Wal-Mart furnished fabricated metal items.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Wal-Mart furnished products.<br />

2. Section 05090 - Post-installed Concrete and Masonry Anchors: Mechanical and adhesive anchors drilled<br />

into concrete or masonry.<br />

3. Section 05120 - Structural Steel: Connection of miscellaneous framing and supports to structural steel.<br />

4. Section 06065 - Plastic Materials: Plastic sleeves for steel pipe bollards.<br />

5. Section 09900 - Paints and Coatings: Field painted finishes.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI A 14.3 - Ladders, Fixed, Safety Requirements.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 36 - Carbon Structural Steel.<br />

2. ASTM A 53 - Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless.<br />

3. ASTM A 123 - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.<br />

4. ASTM A 153 - Zinc Coating (Hot-Dip) on Iron and Steel Hardware.<br />

5. ASTM A 240 - Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels<br />

and for General Applications.<br />

6. ASTM A 307 - Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength.<br />

7. ASTM A 325 - Structural Bolts, Heat Treated, 120/105 ksi Minimum Tensile Strength.<br />

8. ASTM A 500 - Cold-formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes.<br />

9. ASTM A 591 - Steel Sheet, Electrolytic Zinc-Coated, for Light Coating Mass Applications.<br />

10. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

11. ASTM A 666 - Annealed or Cold-Worked Austenitic Stainless Steel Sheet, Strip, Plate, and Flat Bar.<br />

12. ASTM A 1008 - Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength<br />

Low-Alloy with Improved Formability, Solution Hardened, Baked Hardenable.<br />

13. ASTM A 1011 - Steel, Sheet and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy and<br />

High-Strength Low-Alloy with Improved Formability.<br />

D. American Welding Society (AWS):<br />

1. AWS D1.1 - Structural Welding Code.<br />

2. AWS D1.3 - Structural Welding Code - Sheet Steel.<br />

E. National Association of Architectural Metal Manufacturers (NAAMM):<br />

1. Metal Finishes Manual for Architectural and Metal Products.<br />

F. Steel Structures Painting Council (SSPC):<br />

1. SSPC-Paint 20 - Zinc-Rich Coating Type I - Inorganic and Type II - Organic.<br />

05500 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. SSPC-Paint 25 - Zinc Oxide, Alkyd, Linseed Oil Primer for Use Over Hand Cleaned Steel Type I And Type<br />

II.<br />

3. SSPC-SP 3 - Power Tool Cleaning.<br />

4. SSPC-PA 1 - Shop, Field, and Maintenance Painting of Steel.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Shop Drawings: Submit within 10 working days of Contract Date for Contractor furnished items only.<br />

1. Indicate profiles, sizes, connection attachments, reinforcing, anchorage, size and type of fasteners, and<br />

accessories.<br />

2. Include erection drawings, elevations, and details where applicable.<br />

3. Indicate welded connections using standard AWS welding symbols. Indicate net weld lengths.<br />

4. Prepare shop drawings under the supervision of a licensed structural Professional Engineer.<br />

1.4 QUALITY ASSURANCE<br />

A. Welder Qualifications: Qualify welding operators in accordance with Standard Qualification Procedures as<br />

required by AWS D1.1.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Delivery And Handling of Wal-Mart Furnished, Contractor Installed Items:<br />

1. Product Delivery: Wal-Mart Supplier will deliver products to Site. Contact Wal-Mart Supplier to establish<br />

product delivery date.<br />

2. Product Packaging: Products will be packaged in manufacturer's standard packaging on shipping pallets.<br />

Installation Drawings will be included with products.<br />

3. Acceptance at Site: Receive products as specified in Section 01640.<br />

a. Verify quantity of products furnished with Bill of Materials provided with Wal-Mart furnished<br />

products.<br />

b. Report discrepancies in product quantity delivered, or damage to products delivered to Wal-Mart<br />

Construction Manager, Wal-Mart Indirect Sourcing at (479) 204-0684 (select option 1) or<br />

construction.buyouts@wal-mart.comand Wal-Mart Supplier.<br />

c. Note product quantity discrepancies and/or product damage on Bill of Materials.<br />

d. Upon notification by Contractor, Wal-Mart will arrange for delivery of replacement products.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Wal-Mart's Suppliers will furnish the following fabricated metal items for<br />

installation by Contractor.<br />

1. Jib crane hoist arm.<br />

2. LP Monitor support assembly - wall and ceiling mounting.<br />

3. Interior Steel Pipe Bollards as specified.<br />

B. Wal-Mart Supplier: Wylie Welding, Gravette, AR (479) 787-9929, unless otherwise specified.<br />

1. Contact: Cheryl Hooten hwylie@specent.com or Glenda Herron hwyliewelding@hughes.net<br />

C. Descriptions and related provisions of products by Wal-Marts’s Supplier as specified herein are included as<br />

requirements by the supplier of equipment to be furnished by Wal-Mart and are included as information only to<br />

the Contractor.<br />

05500 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 MATERIALS<br />

A. Steel Plates, Shapes and Bars: ASTM A 36.<br />

B. Bolts, Nuts, and Washers: ASTM A 325 and ASTM A 307.<br />

C. Cold Rolled Steel Sheet: ASTM A 1008.<br />

D. Hot Rolled Steel Sheet: ASTM A 1011.<br />

E. Galvanized Steel Sheets:<br />

1. Structural: ASTM A 653 Structural Quality, G90.<br />

2. Galvanized Sheet Steel: ASTM A 591, Class C.<br />

F. Stainless-Steel Sheet, Strip, and Plate: ASTM A 240 or ASTM A 666, Type 304.<br />

G. Steel Tubing: ASTM A 500, Grade B.<br />

H. Steel Piping: ASTM A 53.<br />

I. Welding Materials: AWS D1.1 and AWS D1.3 type required for materials being welded.<br />

J. Primers:<br />

1. Shop Application and Field Touch-up: SSPC Paint 25.<br />

2. Touch-up Primer for Galvanized Surfaces: SSPC Paint 20.<br />

3. Color: To match primer used on steel roof deck and joists.<br />

K. Concrete Inserts: Cast steel or malleable bolts, washers, and shims; galvanized.<br />

L. Grout: Specified in Section 05120.<br />

2.3 FABRICATION<br />

A. Verify dimensions on site prior to shop fabrication.<br />

B. Fabricate items with joints tightly fitted and secured.<br />

C. Fit and shop assemble in largest practical sections for delivery to Site.<br />

D. Grind exposed welds flush and smooth with adjacent finished surface. Ease exposed edges to small uniform<br />

radius.<br />

E. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners where possible. Use<br />

exposed fasteners of type indicated or, if not indicated, Phillips flat-head (countersunk) screws or bolts. Locate<br />

joints where least conspicuous.<br />

F. Supply components required for anchorage of metal fabrications. Fabricate anchorage and related components of<br />

same material and finish as metal fabrication, except where specifically noted otherwise.<br />

2.4 FINISHES<br />

A. Finish metal fabrications after assembly. Comply with NAAMM's "Metal Finishes Manual for Architectural and<br />

Metal Products" recommendations for applying and designating finishes. Shop prime ferrous metal items not<br />

indicated to be galvanized.<br />

B. Prime Painting:<br />

1. Prime paint in shop as scheduled.<br />

05500 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Prepare uncoated ferrous-metal surfaces to comply with SSPC-SP 3, "Power Tool Cleaning".<br />

3. Apply shop primer to comply with SSPC-PA 1 for shop painting.<br />

4. Do not prime surfaces in direct contact bond with concrete or where field welding is required.<br />

5. Prime paint items scheduled with one coat. Touch-up with same primer.<br />

C. Galvanizing: Hot-dip galvanize items indicated to be galvanized to comply with ASTM A 123 or ASTM A 153 as<br />

applicable. Galvanize exterior items and those items indicated on Drawings and specified herein to be galvanized<br />

to minimum 2.0 oz./sq. ft. zinc coating.<br />

D. Finish Painting: Finish paint after installation as shown on Drawings or specified herein in accordance with<br />

Section 09900.<br />

2.5 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Obtain Wal-Mart Construction Manager approval prior to field cutting or making adjustments not scheduled.<br />

B. Clean and strip field-primed steel items to bare metal where field welding is scheduled.<br />

C. Make provision for erection loads with temporary bracing. Keep work in alignment.<br />

3.2 INSTALLATION<br />

A. Install items plumb and level, accurately fitted, free from distortion or defects.<br />

B. Use grout for setting metal fabrications.<br />

C. Perform field welding in accordance with AWS D1.1 or D1.3, as applicable. After installation, grind sightexposed<br />

field welds smooth, touch-up welds, scratched, or damaged surfaces with primer.<br />

3.3 SCHEDULE<br />

A. Provide items as scheduled herein and as indicated on Drawings.<br />

B. Miscellaneous Framing and Supports: Furnish steel framing and supports not specified under Section 05120.<br />

Fabricate welded construction in as large units as possible. Drill and tap for hardware and other items. Include<br />

anchors required for building into work of other Sections.<br />

1. Interior: Prime paint finish, gray.<br />

2. Exterior: Galvanized.<br />

C. Rough Hardware: Custom fabricated bolts, plates, anchors, hanger, dowels, and other miscellaneous steel and iron<br />

shapes required for framing, supporting, and anchoring other construction. Galvanized unless otherwise indicated<br />

on Drawings.<br />

D. Steel Columns Bearing on Slab: Provide steel columns, base plates, and attachment hardware bearing on floor<br />

slab where shown on Architectural Drawings or specifically noted on Structural Drawings.<br />

1. Interior: Prime paint finish.<br />

2. Exterior: Galvanized.<br />

E. Field Strut Angles: Provide L 2 x 2 x 3/16 field struts at joist panel points as required on Structural Drawings.<br />

05500 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


F. Deck Reinforcing at Skylights: Provide L 1-1/2 x 1-1/2 x 1/16 deck reinforcing at skylights as required on<br />

Structural Drawings.<br />

G. Miscellaneous Steel Trim: Profiles and sizes as indicated on Drawings with continuously welded joints and<br />

smooth exposed edges. Use concealed field splices where possible. Provide cutouts, fittings, and anchorages.<br />

Coordinate assembly and installation into work of other Sections.<br />

1. Interior: Prime paint finish.<br />

2. Exterior: Galvanized.<br />

H. Exterior Steel Pipe Bollards (Footing Mounted): ASTM A 53, Type E (electric-resistance welded) or Type S<br />

(seamless), Grade B.<br />

1. Pipe Schedule No.:<br />

a. Public Entrances (at Detail 10-SP2.1): Schedule 80.<br />

b. All Other Locations: Schedule 40.<br />

2. Size: Height and diameter as shown on Drawings.<br />

3. Fill bollard as indicated on Drawings.<br />

4. Finish:<br />

a. Painted Bollards: Field prime and finish coated in accordance with Section 09900.<br />

b. Covered Bollards: Galvanized.<br />

5. Installation: Install in concrete footing as shown on Drawings.<br />

6. Plastic Sleeves: Install polyethylene thermoplastic pipe sleeves on bollards as specified in Section 06065.<br />

I. Interior Galvanized Steel Pipe Bollards - Core Drilled: ASTM A 53, Type E (electric-resistance welded) or Type<br />

S (seamless), Grade B, Schedule 40.<br />

1. Size: Height and nominal diameter as shown on Drawings.<br />

2. Fill bollard as indicated on Drawings.<br />

3. Finish: Hot dip galvanized.<br />

J. Interior Stainless Steel Pipe Bollards - Floor Mounted (Wal-Mart Furnished, Contractor Installed):<br />

1. Wal-Mart Supplier: As selected by Wal-Mart.<br />

2. Size: Height and nominal diameter as shown on the drawings.<br />

3. Fasteners: 5/8 inch x 5 inch Titan-HD anchor bolts and socket head set screw.<br />

K. Interior Galvanized Steel Pipe Bollards - Floor Mounted (Wal-Mart Furnished, Contractor Installed): 10 gage<br />

CRS tubing with rounded cap and floor mounted support.<br />

1. Wal-Mart Supplier: As selected by Wal-Mart.<br />

2. Size: Height and nominal diameter as shown on the drawings.<br />

3. Fasteners: 5/8 inch x 5 inch Titan-HD anchor bolts and socket head set screw.<br />

4. Finish: Hot dip galvanized.<br />

L. Interior Galvanized Steel Pipe Bollards - Plate Mounted Inside Freezer (Wal-Mart Furnished, Contractor<br />

Installed): 10 gage CRS tubing with rounded cap.<br />

1. Wal-Mart Supplier: As selected by Wal-Mart.<br />

2. Size: Height and nominal diameter as shown on the drawings.<br />

3. Finish: Hot dip galvanized.<br />

M. Bollard Base Plate (For Wal-Mart Furnished/ Contractor Installed Bollards Inside Freezer): Provide steel bollard<br />

mounting base plate to be cast in concrete floor as shown.<br />

1. Wal-Mart Supplier: PNA Construction Technologies, Inc. Contact: Marva Wilkerson (800) 542-0214.<br />

2. Fabricate base plate assembly as detailed on Drawings.<br />

05500 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


N. Steel Pipe Guardrails, Handrails and Railing Posts: ASTM A53, Type E (electric-resistance welded) or Type S<br />

(seamless), Grade B, Schedule 40, 1 1/2 inch outside diameter unless otherwise indicated on Drawings. Fabricate<br />

to dimensions indicated on Drawings. Cope horizontal railings intersecting vertical members. Provide radius<br />

bends at changes in direction.<br />

1. Finish as follows:<br />

a. Interior: Prime paint finish.<br />

b. Exterior: Galvanized.<br />

2. Pipe Sleeves: For railing posts set in concrete, provide 3 inch outside diameter galvanized steel pipe sleeves<br />

not less than 6 inches long with metal plate forming bottom closure, unless otherwise indicated on<br />

Drawings.<br />

a. Use metal sleeves preset and anchored into concrete for installing posts. After posts have been<br />

inserted into sleeves, fill annular space between post and sleeve with nonshrink, nonmetallic grout.<br />

Install sealant at top of pipe sleeves as specified in Section 07900.<br />

3. Secure railings to other construction as indicated on Drawings.<br />

4. Handrails and Top Rails: Design point load 200 lbs, downward or horizontal, and uniform load of 50 lb/lin<br />

ft applied simultaneously in both vertical and horizontal directions. Concentrated and uniform loads need<br />

not be assumed to act concurrently.<br />

5. Intermediate Rails: Uniform load of 25 lbs/sq ft of gross area of railing system including open area.<br />

6. Shopping Cart Railings (If Indicated on Drawings): 1-1/2 x 1-1/2 inches by 11 gage tube steel. Weld all<br />

connections. No finish required. Coordinate installation with Store Manager.<br />

7. Steel Balusters: Provide steel bar balusters, 1/2 inch square.<br />

O. Handrail Brackets: Cast iron with not less than 3 inch projection from wall surface to centerline of handrail.<br />

Finish as indicated below.<br />

1. Interior: Prime paint finish.<br />

2. Exterior: Galvanized.<br />

P. Steel Supports for Overhead Doors, Closures, and Grilles: Channels, tubes and angles as indicated on Drawings<br />

for overhead coiling doors, rolling closures, and overhead coiling grilles. Coordinate fabrication with respective<br />

section of work.<br />

Q. Jib Crane Hoist Arm (Wal-Mart Furnished Contractor Installed):<br />

1. Factory fabricated welded steel tube with steel support bracket plates of size and configuration indicated on<br />

Drawings, factory finished OSHA Yellow.<br />

2. Install jib crane hoist arm assembly using threaded rods through masonry wall with nuts each side to<br />

attachment plates and backing plates in accordance with manufacturer's installation drawings at locations<br />

indicated on Drawings.<br />

3. Seal threaded rod penetrations of masonry wall using sealant. Provide a watertight condition. Set support<br />

bracket plate in full bed of sealant and seal edge of plate to prevent infiltration of moisture behind plate.<br />

4. Anchor frame assembly for seismic protection as shown on Drawings. Provide penetration seals as specified<br />

in Section 07500.<br />

R. LP Monitor Support Assembly - Ceiling Mounted (Wal-Mart Furnished Contractor Installed):<br />

1. Support Assembly: Factory fabricated steel assembly consisting of threaded pipe hanger, support angle, and<br />

attachment fasteners. Factory prime finish ready for field painting.<br />

a. Install support assembly spanning across steel roof joist bottom chords and attach to structure as<br />

indicated on the Drawings.<br />

b. Install support assemblies at locations indicated on Electrical Drawings and as approved by Wal-<br />

Mart.<br />

2. Seismic Bracing: Provide seismic bracing when required by Authority Having Jurisdiction.<br />

a. Fabricate and install seismic bracing in accordance with details provided by Architect.<br />

b. Costs for additional work to provide seismic support will be paid for in accordance with Changes in<br />

the Work of the General Conditions.<br />

c. Wal-Mart Supplier of Seismic Bracing: Wal-Mart Supplier specified in this Section.<br />

05500 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


S. LP Monitor Bracket Support Assembly - Wall Mounted (Wal-Mart Furnished Contractor Installed):<br />

1. Manufacturer: Ultrak, Lewisville, TX, (800) 796-2288.<br />

a. Monitor Mounting Bracket: Ultrak Model # MA21MMGR.<br />

b. Wall Mount Bracket: Ultrak Model # MAWB180G.<br />

T. Steel Ladder (Interior):<br />

1. Comply with ANSI A14.3 unless otherwise indicated.<br />

2. Side Rails: Steel bars size as shown.<br />

3. Rungs: Solid steel rods size and spacing as shown.<br />

4. Fit rungs in centerline of siderails. Plug-weld and grind smooth on outer rail faces.<br />

5. Provide nonslip surfaces on top of each rung by one of the following methods:<br />

a. Coating rung with aluminum-oxide granules set in epoxy-resin adhesive.<br />

b. Coating rung with abrasive material metallically bonded to rung.<br />

c. Use of manufactured rung filled with aluminum-oxide grout.<br />

6. Finish: Prime paint finish.<br />

7. Attach ladder to structure with steel mounting brackets.<br />

U. Ladder Safety Extension (For Roof Hatch): Hatch-Grip by PS Doors, Grand Forks, ND (800) 284-0623.<br />

1. Ladder rung continuation grip safety extension above ladder roof hatch opening.<br />

2. Provide fasteners with neoprene washers for attachment to roof hatch curb.<br />

3. Finish: Powder coat grey stipple finish.<br />

4. Assemble and install in accordance with manufacturer’s instructions.<br />

5. Substitutions: Not permitted.<br />

V. Ladder Cage at Roof Hatch: Provide at location and height shown on the drawings. Fabricate cage in<br />

conformance with ANSI A14.3 or OSHA requirements.<br />

W. Truck Well Curb Drain: 12 inch square cast iron grate, factory finished black.<br />

1. Model No. 1213 by National Diversified Sales, Inc. (800) 726-1994.<br />

X. Pit Angles and Channels: Provide perimeter steel angles and channels with welded studs for dock leveler pits as<br />

required for installation of equipment. Coordinate fabrication with respective section of work.<br />

1. Galvanize after fabrications.<br />

a.<br />

Y. Water Heater Support Frames: Fabricate support frames and floor-to-roof steel tube bracing as indicated on<br />

Drawings for overhead water heater platforms. Provide welded connections, ground smooth.<br />

Z. Closure Panel at Refrigerated Cases: Fabricate and install closure panels as shown on Drawings. Fabricate from<br />

stainless steel or galvanized steel sheet as shown.<br />

AA.<br />

Exterior WALMART Sign Post: Round steel post for pylon or monument sign constructed and installed as shown<br />

on Drawings.<br />

END OF SECTION<br />

05500 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052810<br />

SECTION 06065 (06 6000) – PLASTIC MATERIALS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Thermoplastic polyethylene plastic sleeves for steel pipe bollards furnished by Owner for installation by<br />

Contractor.<br />

2. Plastic transition strip at walk-in freezer.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Wal-Mart furnished products.<br />

2. Section 05500 - Metal Fabrications: Steel pipe bollards to receive plastic sleeves.<br />

1.2 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Receive Owner Furnished products in compliance with the requirements of Section 01640.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's Supplier will furnish plastic sleeves for installation by Contractor.<br />

Descriptions and specifications of Owner furnished products are included as information to Contractor only and<br />

are not to be considered as Contractor requirements unless otherwise stated.<br />

B. Owner’s Plastic Sleeve Supplier: One of the following depending on location of Project.<br />

1. Ideal Shield, Detroit, MI. Chris Parenti, (313) 551-2281, cparenti@idealshield.com.<br />

2. Post Guard by Encore, Southfield, MI. Suzanne Fitzpatrick, (866) 737-8900, suzanne@postguard.com.<br />

2.2 PLASTIC SLEEVES<br />

A. Polyethylene thermoplastic (HDPE) molded plastic bollard sleeve. Color and size as shown on Drawings.<br />

2.3 PLASTIC TRANSITION STRIP AT WALK-IN FREEZER<br />

A. Korlyte S-2-S by Parkland Plastics Inc., Middlebury, IN (574) 825-4336 or (800) 835-4110.<br />

1. Parkland Part Number PVC 1901M.<br />

2. Factory cut to size: 3 inches x 3/4 inch x 8 feet.<br />

3. Color: Tan.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install plastic sleeves on steel bollards in accordance with manufacturer's published instructions at locations shown<br />

on Drawings.<br />

B. Install plastic transition strip at locations and as shown on Drawings.<br />

END OF SECTION<br />

06065 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II<br />

093011a<br />

SECTION 06100 (06 1000) – ROUGH CARPENTRY<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Blocking and nailers for roofing system and related metal flashings.<br />

2. Preservative and fire resistive treatment.<br />

3. Concealed blocking behind wall mounted items.<br />

4. Structural panel products.<br />

5. Non-structural panel products including the following:<br />

a. Backing for electrical and telephone equipment.<br />

b. Panels concealed within gypsum board and metal stud partitions.<br />

c. Panels used as finish material; walls, ceilings, wainscots, and bases.<br />

B. Related Requirements:<br />

1. Section 06616 - Simulated Stone Fabrications: Plywood substrate for countertops.<br />

2. Section 07243 - Water-Drainage Exterior Insulation and Finish System: Finish over plywood sheathing at<br />

exterior signage.<br />

3. Section 07620 - Sheet Metal Flashing and Trim.<br />

4. Section 09100 - Lath and Plaster (Stucco).<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Lumber Standards Committee (ALSC):<br />

1. Softwood Lumber Standards.<br />

C. American Plywood Association (APA):<br />

1. Grades and Standards.<br />

D. ASTM International (ASTM):<br />

1. ASTM A 123/A - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.<br />

2. ASTM A 153 - Zinc Coating (Hot-Dip) on Iron and Steel Hardware.<br />

3. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

4. ASTM A 307 - Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength.<br />

5. ASTM B 117 - Standard Practice for Operating Salt Spray (Fog) Apparatus.<br />

6. ASTM E 1333 - Test Method for Determining Formaldehyde Concentrations in Air and Emission Rates<br />

from Wood Products Using a Large Chamber.<br />

E. American Society of Mechanical Engineers (ASME):<br />

1. ASME B18.6.1 - Wood Screws (Inch Series).<br />

F. American Wood Protection Association (AWPA):<br />

1. AWPA U1 - User Specification for Treated Wood.<br />

2. AWPA M4 - Care of Preservative Treated Wood Products.<br />

G. Department of Commerce (National Institute of Standards and Technology) - Product Standard (DOC):<br />

1. DOC PS 1 - Construction and Industrial Plywood.<br />

2. DOC PS 2 - Performance Standard for Wood Based Structural Use Panels.<br />

3. DOC PS 20 - American Softwood Lumber Standard.<br />

06100 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


H. Southern Pine Inspection Bureau (SPIB):<br />

1. Grading Rules.<br />

I. Western Wood Products Association (WWPA):<br />

1. Western Lumber Grading Rules.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Closeout Submittals: Submit Certifications in compliance with the requirements of Section 01770.<br />

1.4 QUALITY ASSURANCE<br />

A. Lumber Grading Agency: Lumber to be grade stamped by an agency certified by the Board of Review of the<br />

American Lumber Standards Committee (ALSC).<br />

B. Plywood Grading Agency: Certified by APA.<br />

C. Regulatory Requirements: Conform to applicable codes for fire retardant treatment of wood surfaces for<br />

flame/smoke ratings.<br />

D. Certifications:<br />

1. Preservatives Treatment: For type specified, include certification by treating plant stating chemicals and<br />

process used, net amount of preservative retained and conformance with AWPA U1.<br />

a. For water-borne preservatives, include statement that moisture content of treated materials was<br />

reduced to a maximum of 15-19% for treated materials prior to shipment to project site.<br />

2. Fire Retardant Treatment: For type specified, include certification by treating plant stating chemicals and<br />

process used, net amount of retardant retained and conformance with AWPA U1.<br />

a. For water-borne preservatives, include statement that moisture content of treated materials was<br />

reduced to a maximum of 15-19% for treated materials prior to shipment to project site.<br />

E. Composite Wood Products: Hardwood plywood, particleboard, and medium density fiberboard composite wood<br />

products specified herein for exterior or interior applications shall meet the requirements for formaldehyde as<br />

specified by the California Air Resources Board, Air Toxics Control Measure for Composite Wood as tested in<br />

accordance with ASTM E 1333, and Chap. 5 of the CALGreen requirements.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Provide proper facilities for handling and storage of materials to prevent damage to edges, ends and surfaces.<br />

C. Keep materials dry. Stack materials off ground a minimum of 12 inches or if on concrete slab-on-grade a<br />

minimum of 1-1/2 inches, fully protected from weather. Provide for air circulation around stacks and under<br />

coverings.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS AND PRODUCTS<br />

A. Lumber: PS 20; S4S. Maximum of 19 percent moisture content, surfaced dry, No. 2 any species graded under<br />

WWPA grading rules or No. 3 Grade Southern Pine graded under SPIB grading rules.<br />

B. Nonstructural Panel: DOC PS 1 or PS 2.<br />

1. Type 1 (Interior): Grade C-D Plugged veneer plywood, Exposure I, locations and thickness indicated on<br />

the Drawings.<br />

06100 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Type 2 (Exterior): Grade B-B veneer plywood, Exterior, locations and thickness as indicated on the<br />

Drawings.<br />

C. Structural Panels: DOC PS 1 or PS 2.<br />

1. Plywood Wall Sheathing: Grade B-B veneer plywood, Exterior for exterior, Exposure 1 for interior, span<br />

rating required to support spacing indicated on Drawings. Thickness: Indicated on Drawings.<br />

2. Plywood Roof Sheathing: Grade B-B veneer plywood, Exposure 1, Structural I, span rating as required to<br />

suit support spacing indicated on Drawings. Thickness: As indicated on Drawings.<br />

D. High Density Wood Fiber Panel Products: Provide one of the following panels with span rating as required to suit<br />

support spacing indicated on Drawings. Thickness: As indicated on Drawings.<br />

1. EnergyGuard High Density Fiberboard, by GAF, (800) 766-3411.<br />

2. Huebert Fiberboard Roof Insulation, by Huebert Brothers Products, LLC; Booneville, MO, (816) 882-2704.<br />

2.2 FASTENERS<br />

A. Where rough carpentry is exposed to weather, in ground contact, pressure-preservative treated, or in area of high<br />

relative humidity: Comply with the treated lumber manufacturer’s recommendations for fasteners and metal<br />

components in contact with treated lumber.<br />

1. Fasteners: ASTM A 153, class D for hot dip galvanized fasteners or type 304 or type 316 stainless steel.<br />

2. Other components: ASTM A 653, G-185, with minimum of 1.85 ounces of zinc coating per square foot<br />

coverage or type 304 or type 316 stainless steel.<br />

B. At no time shall any galvanized metal, stainless steel, or other dissimilar metals be in contact with one another.<br />

C. Nails, Brads and Staples:<br />

1. ASTM F 1667 galvanized for exterior locations and high-humidity areas and for treated wood.<br />

2. ASTM A 123 plain finish for other interior locations.<br />

3. Size and type to suit application, unless otherwise noted.<br />

D. Bolts, Nuts, Washers, and Lag Screws: ASTM A 307, Medium carbon steel; size and type to suit application;<br />

galvanized for exterior locations, high humidity areas, and treated wood; plain finish for other interior locations, of<br />

size and type to suit application, unless otherwise noted.<br />

E. Wood Screws: ASME B18.6.1.<br />

F. Toggle Bolt Fasteners: For anchorage of non-structural items to hollow masonry.<br />

G. Expansion Shield Fasteners: For anchorage of non-structural items to solid masonry and concrete.<br />

H. Powder Actuated Fasteners: For anchorage of non-structural items to steel.<br />

I. Fasteners for Wood and Plywood to Light Gage Metal Framing and Metal Deck (up to 10 gage, 0.1345 inch):<br />

Self-drilling flat head wood-to-metal screws.<br />

1. Manufacturers:<br />

a. Hilti, Tulsa, OK (800) 879-6000.<br />

b. ITW Buildex, Itasca, IL (800) 323-0720.<br />

2. Wood and Plywood Up to 3/4 Inch Thick:<br />

a. Hilti: S-WD 8-18 x 1-15/16 PFH #3 Black Phosphated.<br />

b. ITW: Traxx 10-16 #3 point.<br />

c. Pre-drill wood if wood thickness is greater than 1/2 inch or use heavier fastener specified below.<br />

3. Wood less than or equal to 1-1/8 inch thickness to 18 Gage (0.0478 inch) and 20 Gage (0.0359 inch) Metal:<br />

a. Hilti: S-WD 10-24 x 1-1/2 PWH #3 wafer head screw.<br />

b. ITW: Traxx 10-16 #3 point.<br />

c. Pre-drill wood if wood thickness is greater than 1/2 inch.<br />

06100 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Wood less than or equal to 1-3/4 inch thickness to 16 Gage (0.598 inch) and Heavier Metal (less than or<br />

equal to 0.232 inches):<br />

a. Hilti: S-WW 12-24 x 2-1/2 PFH #4 Wings.<br />

b. ITW: Traxx 12-24 #4 Point with Wings.<br />

5. Wood less than or equal to 2-inch thickness to 16 Gage (0.598 inch) and heavier metal (less than or equal to<br />

1/4 inch):<br />

a. Hilti: S-WW 1/4-20 x 2-3/4 PFH #4 Wings.<br />

J. For wall and roof sheathing panels, provide screws with organic-polymer or other corrosion-protective coating<br />

having a salt-spray resistance of more than 800 hours according to ASTM B 117 with wafer heads or reamer wings<br />

as specified above, length as shown or as recommended by screw manufacturer for material being fastened.<br />

K. Fasteners for Structural Wood Members to Solid Grouted Masonry: Adhesive anchors, size and length as<br />

indicated on Drawings.<br />

1. Anchor adhesive: Cartridge type two-component adhesive for embedding anchors.<br />

a. HIT HY-150 by Hilti Corp.<br />

b. Epcon System, Ceramic 6 by ITW Ramset/Red Head.<br />

c. Epoxy-Tie SET by Simpson Strong Tie Co., Inc., Pleasanton, CA (800) 925-5099.<br />

d. Substitutions: Not permitted.<br />

L. Fasteners for Non-Structural Wood Members to Masonry: Masonry screw anchor with Phillips or Torx flat head,<br />

size and length as shown on the drawings.<br />

1. Hilti: Kwik-Con II fastener.<br />

2. ITW: Tapcon masonry anchor.<br />

M. Alternate Manufacturers: Subject to compliance with project requirements, fasteners by alternate manufacturers of<br />

equal types to those specified may be provided, except where substitutions specifically prohibited.<br />

2.3 WOOD TREATMENT<br />

A. Preservative Pressure Treated Lumber Treatment:<br />

1. Products and Manufacturers: Provide any of the following:<br />

a. Wolman CCA by Arch Wood Protection, Smyrna, GA, (770) 801-6600.<br />

b. CCA Pressure Treatment by Hoover Treated Wood Products Inc., Thomson, GA, (800) 832-9663.<br />

c. SupaTimber by Viance, Charlotte, NC, (800) 421-8661.<br />

2. Treat lumber in accordance with AWPA U1. Use Category UC2 for interior construction not in contact<br />

with the ground. Use Category UC3b for exterior construction not in contact with the ground. Use<br />

Category UC4a for items in contact with the ground.<br />

3. Preservative chemicals shall be acceptable to Authorities Having Jurisdiction and contain no arsenic or<br />

chromium where prohibited.<br />

4. Kiln dry lumber after treatment to 15-19 percent moisture content. Do not use warped material or materials<br />

that do not comply with requirements for untreated material. Material to be painted or stained shall have<br />

knots and pitch streaks sealed as with untreated wood.<br />

5. Mark lumber with treatment quality mark of an inspection agency approved by the ALSC Board of Review<br />

and acceptable to Authorities Having Jurisdiction.<br />

B. Field-Applied Lumber Preservative:<br />

1. Provide the following:<br />

a. Inorganic boron.<br />

b. Copper naphthenate.<br />

C. Fire Retardant Treatment:<br />

1. Products and Manufacturers: Provide any of the following:<br />

a. Dricon FRT (exterior and interior), by Arch Wood Protection, Smyrna, GA, (770) 801-6600.<br />

b. Exterior X (exterior) and Pyro-Guard (interior) by Hoover Treated Wood Products Inc., Thomson,<br />

GA, (800) 832-9663.<br />

c. D-Blaze (interior) by Viance, Charlotte, NC, (800) 421-8661.<br />

06100 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Identify fire retardant treated wood with appropriate classification marking of testing and inspecting agency<br />

acceptable to Authorities Having Jurisdiction.<br />

3. For exposed items indicated to receive a stained or natural finish, use chemical formulations that do not<br />

bleed through, contain colorants, or otherwise adversely affect finishes.<br />

4. Kiln dry lumber after treatment to an average moisture content of 19 percent or less.<br />

5. Kiln dry plywood after treatment to an average moisture content of 15 percent or less.<br />

6. Chemicals used to treat material shall be free of halogens, sulfates, ammonium phosphate and<br />

formaldehyde.<br />

7. Treatment material shall provide protection against termites and fungal decay and shall be registered for<br />

use as a wood preservative by the U. S. Environmental Protection Agency.<br />

D. Wood Requiring Treatment:<br />

1. Lumber, Preservative Treated:<br />

a. Nailers, blocking, stripping, and similar items in conjunction with roofing, flashing, and other<br />

construction.<br />

b. Sills, blocking, furring, stripping, and similar items in contact with masonry or concrete.<br />

2. Lumber, Fire Retardant Treated:<br />

a. Wood in concealed spaces.<br />

b. Wood exposed within the roof/ceiling assembly.<br />

3. Interior Plywood, Fire Retardant Treated:<br />

a. Plywood used as finish material, walls, wainscots, and bases in fire-rated corridors.<br />

b. Plywood backing for electrical and telephone equipment.<br />

c. Non-structural plywood wall sheathing in concealed spaces.<br />

4. Plywood Not to be Fire Retardant Treated:<br />

a. Structural plywood performing a structural function, such as a component of roof, floors or shear<br />

walls.<br />

b. Exterior plywood used as non-structural sheathing, substrate, or parapet cap assembly.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine areas to receive rough carpentry work and verify following:<br />

1. That installation of building components to receive rough carpentry work is complete.<br />

2. That surfaces are satisfactory to receive work.<br />

3. That spacing, direction and details of supports are correct to accommodate installation of blocking,<br />

backing, stripping, furring and nailing strips.<br />

3.2 SITE TREATMENT OF WOOD MATERIALS<br />

A. Wood Treatment at Site: Comply with AWPA M4 for applying field treatment to cut surfaces of preservative<br />

treated lumber.<br />

1. Use inorganic boron for items continuously protected from liquid water.<br />

2. Use copper naphthenate for items not continuously protected from liquid water.<br />

3.3 INSTALLATION<br />

A. Set rough carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit rough<br />

carpentry to other construction; scribe and cope as needed for accurate fit. Locate furring, nailers, blocking,<br />

grounds, and similar supports to comply with requirements for attaching other construction.<br />

1. Construct members of continuous pieces of longest possible lengths.<br />

2. Do not splice structural members between supports, unless otherwise indicated.<br />

B. Provide blocking and framing indicated and necessary to support facing materials, fixtures, specialty items, and<br />

trim.<br />

1. Provide metal clips for fastening gypsum board or lath at corners and intersections where framing or<br />

blocking does not provide a surface for fastening edges of panels. Space clips not more than 16 inches o.c.<br />

06100 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Secure members in place with specified fastener. Select fasteners of size that will not fully penetrate members<br />

where opposite side will be exposed to view or will receive finish materials. Make tight connections between<br />

members. Install fasteners without splitting wood. Do not countersink nail heads unless otherwise indicated.<br />

D. Wood Ground, Sleeper, Blocking, and Nailer: Install where indicated and where required for screeding or<br />

attaching other work. Form to shapes indicated and cut as required for true line and level of attached work.<br />

Coordinate locations with other work involved.<br />

1. Attach items to substrates to support applied loading. Recess bolts and nuts flush with surfaces, unless<br />

otherwise indicated.<br />

2. Recess heads of fasteners below surface of wood members.<br />

E. Wood Furring: Install level and plumb with closure strips at edges and openings. Shim with wood as required for<br />

tolerance of finish work.<br />

F. Install firestopping complying with Section 07840 in concealed spaces with wood blocking, horizontally and<br />

vertically in accordance with drawings, minimum 2 inches thick where space is not blocked by framing members.<br />

G. Tapered Wood Shim (edge strip) at Parapet Cap:<br />

1. Provide shaped high density wood fiber or wood material as indicated at the optional Parapet Detail.<br />

2. Shape wood material for continuous support of metal coping.<br />

H. Fasteners: Install fasteners with manufacturer’s recommended power tool for each type of fastener.<br />

3.4 PROTECTION<br />

A. Protect rough carpentry from weather throughout construction period.<br />

END OF SECTION<br />

06100 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 042707<br />

SECTION 06200 – FINISH CARPENTRY<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Interior standing and running trim.<br />

2. Shelving.<br />

B. Related Sections:<br />

1. Section 06100 - Rough Carpentry: Panel product used as finish material on walls, ceilings, wainscots, and<br />

bases.<br />

2. Section 06400 - Architectural Woodwork: Plastic and simulated wood trim and custom wood trim.<br />

3. Section 09900 - Paints and Coatings: Opaque and transparent finishes.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Woodworking Institute (AWI):<br />

1. AWI - Quality Standards.<br />

C. American Plywood Association (APA):<br />

1. APA - Grades & Specifications.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Section 01600 - Material and Equipment: Transport, handle, store, and protect products.<br />

PART 2 - PRODUCTS<br />

2.1 WOOD MATERIALS<br />

A. Interior Standing and Running Trim: AWI Custom Grade; plain sawn, Grade II lumber.<br />

1. Painted Finish: Closed-grain hardwood, any species.<br />

2. Clear Sealed Hardwood: One of the following hardwood species. Use one species throughout.<br />

a. Ash.<br />

b. Birch.<br />

c. Oak.<br />

B. Shelving - Clear Sealer Finish: Fir or birch plywood with veneer core and sanded edges.<br />

1. APA 5-ply A/C, 3/4 inch thickness at Stockroom shelving.<br />

2. APA 5-ply A/B at other locations.<br />

C. Panel Product for Finish Material on Walls, Ceilings, Wainscots, and Bases: See Section 06100.<br />

2.2 HARDWARE<br />

A. Fasteners: Size and type to suit application; galvanized for exterior and high humidity locations; plain finish at<br />

other locations.<br />

06200 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.3 FABRICATION<br />

A. Fabricate to AWI Standards.<br />

1. Standing and Running Trim: Custom Grade.<br />

2. Wood Shelving with Clear Sealer: Economy Grade.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install woodwork plumb, level, and straight without distortion; use concealed shims. Scribe and cut woodwork to<br />

fit adjoining work. Anchor woodwork items to nailers or blocking or directly to substrate using concealed<br />

fasteners.<br />

B. Standing and Running Trim: Install with minimum joints, using maximum lumber lengths possible. Cope at<br />

returns; miter at corner.<br />

C. Wood Shelving: Assemble units and install as indicated on Drawings.<br />

D. Site Finishing: Refer to Section 09900.<br />

END OF SECTION<br />

06200 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II<br />

093011a<br />

SECTION 06400 (06 4000) – ARCHITECTURAL WOODWORK<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Plastic Laminate Casework.<br />

2. Molded Laminate Countertop.<br />

3. Thermofused Melamine Panel (TFM).<br />

4. High Pressure Laminate (HPL) Wainscoting.<br />

5. Metal Edge Trim.<br />

B. Related Requirements:<br />

1. Section 06424 - Protective Surfacing: Polyester blend compound, high impact, rigid sheet wall covering.<br />

2. Section 06616 - Simulated Stone Fabrications: Countertops.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI A208.1 - Particleboard.<br />

2. ANSI A208.2 - Medium Density Fiberboard For Interior Use.<br />

C. American National Standards Institute (ANSI) / Builders Hardware Manufacturers Association (BHMA):<br />

1. ANSI/BHMA 156.9 - Cabinet Hardware.<br />

2. ANSI/BHMA 156.11 - Cabinet Locks.<br />

3. ANSI/BHMA 156.18 - Materials & Finishes.<br />

D. Architectural Woodwork Institute (AWI) / Architectural Woodwork Manufacturers Association of Canada<br />

(AWMAC) / Woodwork Institute (WI) - Joint Publication:<br />

1. AWI/AWMAC/WI - Architectural Woodwork Standards.<br />

E. American Plywood Association (APA): APA - Grades & Specifications.<br />

F. National Electrical Manufacturer's Association (NEMA):<br />

1. NEMA LD3 - High-Pressure Decorative Laminates.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Inspect materials delivered and reject those not qualifying with requirements, those damaged in transit, or those<br />

that appear otherwise unsatisfactory.<br />

C. Schedule delivery of items to installation areas that are in proper condition to receive them. Place items neatly<br />

and systematically to avoid damage, store in clean, dry, enclosed, and secure storage area.<br />

1.4 PROJECT CONDITIONS<br />

A. Environmental Limitations: Do not deliver or install architectural woodwork until building is enclosed, wet work<br />

is complete, and HVAC system is operating and maintaining temperature and relative humidity at occupancy<br />

levels during the remainder of the construction period.<br />

06400 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 LAMINATE MATERIALS<br />

A. High Pressure Laminate (HPL): NEMA LD3: Color, pattern, and finish as indicated in this Section. Exposed<br />

Horizontal and Vertical Surfaces: GP-50. Postformed Surfaces: PF-42. Provide HPL products as manufactured<br />

by the following as specified in the Color/Pattern Schedule below:<br />

1. Formica Corporation, Indianapolis, IN, Megan Shaughnessy, (513) 786-3039.<br />

2. Wilsonart, Temple, TX, Mark Kieckhafer, (254) 207-2381.<br />

3. Nevamar Decorative Surfaces, Hampton, SC, (800) 638-4380.<br />

4. Panolam Industries, Shelton, CT (800) 241-4915.<br />

5. Pionite Decorative Surfaces, Auburn, ME (800) 746-6483.<br />

B. Thermofused Melamine Panel (TFM): Particleboard or medium density fiberboard (MDF) finished with<br />

thermally fused, melamine-impregnated decorative paper. Provide products by one of the following<br />

manufacturers:<br />

1. Panolam Industries.<br />

2. Funder America, Inc., Mocksville, NC (336) 751-3501.<br />

3. Roseburg Forest Products, Roseburg, OR (800) 245-1115.<br />

2.2 ACCESSORIES<br />

A. Adhesives: Low VOC adhesive, as recommended by laminate manufacturer and suitable for shop or field<br />

application.<br />

1. Toxicity / IEQ:<br />

a. Comply with applicable regulations regarding toxic and hazardous materials.<br />

b. Comply with Green Seal Standard GS-36 for commercial aerosol adhesives.<br />

c. Comply with California’s South Coast Air Quality Management District (SCAQMD) Rule No. 1168<br />

in areas where exposure to freeze/thaw conditions and direct exposure to moisture will not occur. In<br />

areas where freeze/thaw conditions exist or direct exposure to moisture can occur, comply with<br />

California’s Bay Area AQMD Regulation 8, Rule 51 for containers larger than 16 oz. and with<br />

California Air Resource Board (CARB) for containers 16 oz. or less.<br />

2. Provide one of the following products or equivalent as recommended by laminate manufacturer.<br />

a. Wilsonart 3000 Adhesive Series.<br />

b. Sta’-Put SP80.<br />

c. Titebond.<br />

B. Fasteners: Unless otherwise recommended by manufacturer, use size and type to suit application. Use galvanized<br />

or stainless for exterior and high humidity locations. Use plain finish at other locations.<br />

C. Metal Edge Trim:<br />

1. Manufacturers:<br />

a. Macklanburg-Duncan, Oklahoma City, OK (800) 654-8454.<br />

b. Outwater Plastics Industries, Inc.<br />

1) East Coast: Bogota, NJ (800) 631-8375.<br />

2) West Coast: Phoenix, AZ (800) 248-2067.<br />

c. Loxcreen, West Columbia, SC (817) 640-4456<br />

d. Stylmark, Minneapolis, MN (800) 328-2495.<br />

e. Alternate Manufacturers: As approved by the Wal-Mart Construction Manager.<br />

2. Description: Extruded aluminum shapes, smooth surface, anodized finish. Size and type to suit application.<br />

a. 3/4 inch x 3/4 inch as indicated on Drawings.<br />

b. 1-1/2 inch x 1-1/2 inch as indicated on Drawings.<br />

2.3 PANEL PRODUCT<br />

A. Medium Density Fiberboard (MDF), ANSI A208.2, Grade MD, made with binder containing no urea<br />

formaldehyde resin.<br />

06400 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Particleboard, density 45 lb., ANSI A208.1, Grade M-2, made with binder containing no urea formaldehyde resin.<br />

C. Provide MDF or Particleboard specified above as manufactured by one of the following:<br />

1. Flakeboard Company.<br />

2. Homasote.<br />

3. Panel Source International.<br />

4. Sierra Pine.<br />

5. Roseburg Forest Products.<br />

6. Temple Inland.<br />

2.4 COLOR/PATTERN SCHEDULE<br />

A. Provide one color where two or more are specified. Provide laminate specified below as applicable as shown or<br />

scheduled on the Drawings. All PL designations are for HPL unless otherwise indicated. Colors shown in<br />

parenthesis are generic color names.<br />

1. PL-1 (Light Gray):<br />

a. No. 692 Folkstone Celesta, by Formica.<br />

b. No. 4142-6 Grey Glace, by Wilsonart.<br />

2. PL-2 (White): No. D354-60 Designer White, matte finish, by Wilsonart.<br />

3. PL-4 (Maple): Grain oriented parallel to long axis of sheet.<br />

a. No. WM791 Hardrock Maple, by Pionite.<br />

b. No. 10776-60 Kensington Maple, by Wilsonart.<br />

c. No. W290 Hardrock Maple, by Panolam (TFM).<br />

4. PL-5 (Dark Gray):<br />

a. No. D92-6 Dove Grey, by Wilsonart.<br />

5. PL-6 (Light Tan): No. 4143-60 Neutral Glace, by Wilsonart.<br />

6. PL-7 (Dark Gray): No. D96-60 Shadow, by Wilsonart.<br />

7. PL-8 (Sand):<br />

a. No. AG381 Mineral Talc, by Pionite.<br />

b. No. 1763-60 Brune Slate, by Wilsonart.<br />

8. PL-9: No. 4762-60 Mistique Dawn, by Wilsonart.<br />

9. PL-10: No. D436-60 Fleece, by Wilsonart.<br />

10. PL-13: No. ST622-S Caramel, by Pionite.<br />

11. PL-14: No. 4680 Lodestone, by Wilsonart.<br />

12. PL-15 (Brown):<br />

a. No. MKT-001T Golden Iron Moonrock, by Nevamar.<br />

b. No. 13041HW-60 Bronze Terra, by Wilsonart.<br />

13. PL-16: No. #4745-60 Maroochy Brush, by Wilsonart.<br />

14. PL-18 (Medium Tan):<br />

a. No. PON-003T Painted Desert, by Nevamar.<br />

b. No. 13042HW-60 Artistry Gold, by Wilsonart.<br />

15. PL-19 (Champagne):<br />

a. No. ARP S-2-003T Champaign, by Nevamar.<br />

b. No. D456-60 Café Crème, by Wilsonart.<br />

c. No. S463 Antique White, by Panolam (TFM).<br />

16. PL-20 (Aloe): No. 7962K-18 Aloe, by Wilsonart.<br />

17. PL-21: No. 10745-60 Fonthill Pear, by Wilsonart.<br />

18. PL-22: No. 4638 Monterey Sun by Wilsonart.<br />

19. PL-23: No 4830K-18 Satin Stainless by Wilsonart.<br />

B. Substitutions: Not permitted. Comply with the requirements of Section 01600.<br />

2.5 PLASTIC LAMINATE CASEWORK<br />

A. Fabricate casework in compliance with AWI/AWMAC/WI - Architectural Woodwork Standards, Custom Grade.<br />

1. Flush overlay construction.<br />

06400 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Fabricate using following materials for listed surfaces as defined in AWI/AWMAC/WI - Architectural Woodwork<br />

Standards.<br />

1. Plastic Laminates and Thermofused Melamine (TFM) panels with woodgrain patterns:<br />

a. Grain direction to run vertical on vertical exposed millwork surfaces, including but not limited to<br />

cabinet faces, end panels, doors, drawer fronts, dividers and fillers, unless noted otherwise.<br />

b. Grain direction to run parallel to face or exposed edges on horizontal surfaces including but not<br />

limited to cabinet bottoms, shelving and horizontal partitions.<br />

2. Exterior Exposed Surfaces (cabinet faces, ends and finished backs, doors, drawer fronts): High pressure or<br />

thermoplastic laminate as shown. Colors as indicated on Drawings.<br />

3. Interior Exposed Surfaces (open shelving storage or shelving areas): Thermofused Melamine (TFM) as<br />

shown. Color as indicated on the Drawings.<br />

4. Semi-Exposed Surfaces (spaces behind doors, drawer boxes): Thermofused Melamine (TFM) as shown.<br />

Color as indicated on Drawings.<br />

5. Concealed Surfaces: Mill option using materials specified in this Section.<br />

6. Base: 3/4” plywood or 2x wood blocking as indicated on Drawings.<br />

7. Hardwood Edge Trim: Solid hardwood, optional species, for countertop edges as indicated on Drawings.<br />

8. Panel Product Substrate for Laminate Clad Casework: Medium Density Fiberboard (MDF) or<br />

Particleboard as specified in Panel Product paragraph above.<br />

2.6 CABINET HARDWARE AND ACCESSORIES<br />

A. Provide cabinet hardware as specified by the following manufacturers:<br />

1. Knape & Vogt (KV), 2700 Oak Industrial Drive NE, Grand Rapids, MI 49505, (616) 459-3311.<br />

2. Hafele, 3901 Cheyenne Drive, Archdale, NC 27263, (800) 423-3531.<br />

3. Ives, 2720 Tobey Drive, Indianapolis, IN 46219, (877) 613-8766.<br />

4. Rockford Process Control, Inc., 2020 Seventh Street, Rockford, IL 61104, (815) 966-2000.<br />

5. Blum, Inc., 7733 Old Plank Road, Stanley, NC 28164, (800) 438-6788.<br />

6. Grass, 1202 Highway 66 South, Kernersville, NC 27284, (336) 423-5226.<br />

B. Cabinet Hardware:<br />

1. Wire Drawer and Door Pulls: ANSI/BHMA A156.9, B02011, solid metal, 4 inches long, 5/16 inch in<br />

diameter.<br />

2. Drawer Slides: ANSI/BHMA A156.9, B05091. Slides shall include an integral positive stop to avoid<br />

accidental drawer removal.<br />

a. Box Drawer Slides: Grade 1HD-100; side mounted; full-extension type; zinc-plated steel ballbearing<br />

slides for drawers not more than 6 inches high and 24 inches wide.<br />

b. File Drawer Slides: Grade 1HD-100; side mounted; full-extension type; zinc-plated steel ballbearing<br />

slides for drawers more than 6 inches high or 24 inches wide.<br />

c. Pencil Drawer Slides: Grade 1; side mounted; full-extension type; zinc-plated steel or epoxy-coated<br />

steel with polymer rollers for drawers not more than 3 inches high and 24 inches wide.<br />

3. Drawer Locks: ANSI/BHMA A156.11, E07041.<br />

4. Shelf Rests: ANSI/BHMA A156.9, B04013; metal.<br />

a. Place rests in drilled 5mm diameter holes, spaced vertically at 1 1/4” centers. Minimum of four rests<br />

per shelf.<br />

b. Shelf span per AWI/AWMAC/WI standards.<br />

5. Door Locks: ANSI/BHMA A156.11, E07121.<br />

6. Frameless Concealed Hinges (European Type): ANSI/BHMA A156.9, B01602, 100 degrees of opening,<br />

self-closing.<br />

C. Cabinet Accessories: Provide cabinet accessories by the manufacturers specified below or equivalent products of<br />

same function, style, material, and finish from manufacturers specified above.<br />

1. Keyboard Tray: Knape and Vogt: 1805 (left and right) 3/4 inch PTBD with Black LPL 2-S.<br />

06400 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Grommets:<br />

a. Doug Mockett & Company: EDP-3 Round Plastic Grommets, removable caps with flip-down tabs.<br />

LO-2 Oval.<br />

1) Size as noted on Drawings.<br />

2) Color as noted on Drawings.<br />

b. Hardware Concepts: 6249.<br />

1) Size as noted on Drawings.<br />

2) Color as noted on Drawings.<br />

c. Bainbridge Manufacturing: 2 1/2 inch Round 1031BK-52.<br />

3. Finger Pull (Black): Hardware Concepts.<br />

4. Cubby Latches: Southco M1-64 Flush Pull Latch, Black, as distributed by Bisco Industries, Inc.<br />

5. Cubby Hinge:<br />

a. Lawson & Shaw: Piano Hinge HGE1000.<br />

b. Stocker: Hinge 1-95352475-7200.<br />

c. Terry: Hinge CP2-2203S, Nickel/chrome.<br />

6. Vision Center Door and Drawer Pulls: Taco Metals F50-2876 BKA. Flush Mount 4-3/8 inches x 1-1/4<br />

inches, Black.<br />

7. Vision Center Shelf Brackets:<br />

a. Knape and Vogt: #208 Heavy Duty Utility L-Bracket 20 inches, White.<br />

b. Knape and Vogt: #208 Heavy Duty Utility L-Bracket 12 inches, White.<br />

8. Metal Support Leg: 3 inches x 29-7/8 inches with leveler.<br />

9. Adjustable Shelf Pin: Hafele #282.40.708 5mm.<br />

10. T-Molding (Photo Lab):<br />

a. Outwater Plastics 1 1/4 inch Almond Gloss: #303-1032-AL.<br />

b. Outwater Plastics 1 1/4 inch Black Gloss: #303-1032-BK.<br />

D. Exposed Hardware Finishes: For exposed hardware, provide finish that complies with ANSI/BHMA A156.18 for<br />

BHMA finish number indicated, except where indicated otherwise.<br />

1. Satin Chromium Plated: BHMA 626 for brass base; BHMA 652 for steel base; BHMA 682 for zinc base.<br />

E. For concealed hardware, provide manufacturer's standard finish that complies with product class requirements in<br />

ANSI/BHMA A156.9.<br />

2.7 MOLDED LAMINATE COUNTERTOP<br />

A. Postformed plastic laminate on 3/4 inch particle core with waterfall edge trim and integral backsplash, all onepiece<br />

design, length and width as shown.<br />

B. Manufacturer: Belanger Laminates VT Inc. (800) 264-3440, similar to Belanger style 1000, 1100, or 2100. As<br />

distributed by Lowes (Model # 3526118) or Home Depot or equivalent by other manufacturers.<br />

C. Color: Travertine or Sandstone.<br />

2.8 LAMINATE WAINSCOT PANELS<br />

A. Provide wainscot from high pressure laminate (HPL) materials specified above as shown on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 PLASTIC LAMINATE CASEWORK<br />

A. Install woodwork plumb, level, and straight without distortion; use concealed shims. Scribe and cut woodwork to<br />

fit adjoining work. Anchor woodwork items to nailers or blocking or directly to substrate using concealed<br />

fasteners.<br />

B. Casework: Provide well-fitting and smooth operating doors and drawers.<br />

06400 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Countertops: Anchor plastic laminate countertops securely to base units.<br />

D. Install laminate with directional pattern or grain oriented vertically.<br />

3.2 LAMINATE WAINSCOT<br />

A. Examine surfaces and adjacent areas where wainscot will be installed and verify that substrates are flat, clean, dry,<br />

solid, and free from coatings and defects detrimental to installation. Verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions unless otherwise shown or specified.<br />

B. Remove existing finishes at areas to receive laminate wainscot.<br />

C. Prepare substrate for laminate wainscot installation in accordance with manufacturer's published instructions and<br />

recommendations unless otherwise shown or specified.<br />

D. Lay out laminate wainscot before installing.<br />

E. Securely attach wainscot panels to substrate at locations shown on Drawings with adhesive specified in this<br />

Section.<br />

F. Provide extruded aluminum trim at exposed vertical and horizontal edges of high pressure laminate (HPL).<br />

G. Install woodgrain laminate with grain oriented vertically.<br />

END OF SECTION<br />

06400 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 062411<br />

SECTION 06424(06 4240) – PROTECTIVE SURFACING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Interior rigid sheet protective wall covering.<br />

B. Related Requirements:<br />

1. Section 09250 - Gypsum Board: Substrate for protective surfacing.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 84 - Test Method for Surface Burning Characteristics of Building Materials.<br />

2. ASTM D1308 - Standard Test Method for Effect of Household Chemicals on Clear and Pigmented Organic<br />

Finishes.<br />

3. ASTM F476 - Standard Test Methods for Security of Swinging Door Assemblies.<br />

1.3 QUALITY ASSURANCE<br />

A. Manufacturer’s Qualifications: Not less than 5 years experience in the production of specified product.<br />

B. Installer Qualifications: Not less than 3years experience in installation of similar product/system, as required for<br />

this project.<br />

C. Fire Performance Requirements:<br />

1. Surface Burning Characteristics: Conform to the following in accordance with ASTM E 84.<br />

a. Flame Spread: Less than 25 or less.<br />

b. Smoke Density: 450 or less.<br />

D. Impact Strength Requirements:<br />

1. Tested in accordance with and meets or exceeds the applicable provisions of ASTM F 476.<br />

E. Chemical and Stain Resistance Requirements:<br />

1. Tested in accordance with and meets or exceeds ASTM D 1308.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Store in clean, dry, enclosed, and secure storage area. Store flat and in accordance with manufacturer’s published<br />

requirements.<br />

C. Protect protective surfacing products and accessories, especially adhesive, from freezing temperatures, excessive<br />

heat, temperature fluctuations, humidity and moisture penetration.<br />

1.5 PROJECT CONDITIONS<br />

A. Enclose and weatherproof installation areasprior to beginning installation.<br />

06424 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Maintain panel and adhesive material in an environment of a minimum of 68° F and within humidity range<br />

recommended by panel manufacturer for at least 24 hours prior to beginning the installation.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURER<br />

A. Grand Entrance, Frederick, MD. Contact: Wal-Mart National Account (888) 424-6287, georders@c-sgroup.com<br />

2.2 PRODUCTS<br />

A. Protective surfacing wall covering panel shall be EcoShield by Grand Entrance.<br />

B. Description:<br />

1. PVC-free polyester blend compound, high impact, rigid sheet.<br />

2. Thickness: .040 inches.<br />

3. Sheet Size: 48 inches by 96 inches.<br />

4. Texture: Suede.<br />

5. Color: Provide color specified below as shown or scheduled on the Drawings.<br />

a. PS-1: Walmart Blue. Grand Entrance Part No.WMWC40ES410S601.<br />

b. PS-2: Pearl Gray. Grand Entrance Part No. CSWC4048S934N.<br />

c. PS-3: Brushed Silver. Grand Entrance Part No. CSCW40410378N.<br />

2.3 ACCESSORIES<br />

A. Adhesive: Spray-Lock Wall Panel Adhesive, as manufactured by Interlock Industries, Inc., Chattanooga, TN<br />

(479) 721-5431.<br />

B. Corner Trim: Ecoshield extrusions by Grand Entrance. Color to match wall covering panel.<br />

1. Inside Corner: Manufacturer’s standard.<br />

a. Grand Entrance Part No. WMWC40IS601 (Walmart Blue).<br />

b. Grand Entrance Part No. CSWC401S934N (Pearl Gray).<br />

c. Grand Entrance Part No. CSWC40IS378N (Brushed Silver).<br />

2. High Impact Outside Corner: SSM-20 Suede Texture, 4feet 1inch long with caps (includes retainer and<br />

fasteners).<br />

a. Grand Entrance Part No. WMSSM20ESS601 (Walmart Blue).<br />

b. Grand Entrance Part No. CSSSM2041934S (Pearl Gray).<br />

c. Grand Entrance Part No. CSSSM204F374N (Brushed Silver).<br />

3. Low Impact Outside Corner: VA-200, 4 feet 1 inch long.<br />

a. Grand Entrance Part No. CSVA2004FNT601N (Walmart Blue).<br />

b. Grand Entrance Part No. CSVA2004FNT136N (Pearl Gray).<br />

C. Caulk: Color-matched and furnished by manufacturer.<br />

1. Grand Entrance Part No. WMCAULK601 (Walmart Blue).<br />

2. Grand Entrance Part No. CSCAULK934 (Pearl Gray).<br />

3. Grand Entrance Part No. CSCAULK374 (Brushed Silver).<br />

2.4 SUBSTITUTIONS<br />

A. Reference Section 01600.<br />

06424 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where protective wall covering will be installed and verify that substrates are<br />

flat, clean, dry, solid, and free from coatings and defects detrimental to installation. Verify that surfaces conform<br />

to product manufacturer's requirements for substrate conditions.<br />

3.2 PREPARATION<br />

A. Remove existing finishes at areas to receive protective surfacing.<br />

B. Prepare substrate for protective wall covering installation in accordance with manufacturer's published instructions<br />

and recommendations.<br />

C. View adhesive manufacturer’s installation video at http://www.spraylock.com/world/walmart_installers.html prior<br />

to start of installation.<br />

D. Lay out paneling before installing.<br />

3.3 INSTALLATION<br />

A. Install protective wall covering and accessories, including trim, in accordance with panel manufacturer's published<br />

instructions. Follow adhesive manufacturer’s installation video except as otherwise instructed by panel<br />

manufacturer.<br />

1. Install inside corner guards using included adhesive tape.<br />

2. Install high impact outside corner guards using included retainers, fasteners and end caps.<br />

3. Install low impact outside corner guards using included adhesive tape.<br />

B. Assure HVAC is in operation and a minimum temperature of 68° F and a maximum relative humidity of 80% is<br />

maintained at time of installation and 48 hours subsequent to installationtion in accordance with manufacturer’s<br />

installation instructions.<br />

C. Apply protective wall covering using adhesive specified.<br />

D. Apply sealant at butt joints as required to fill gaps.<br />

E. Remove excess sealant and smears as paneling is installed. Clean with solvent recommended by sealant<br />

manufacturer and then wipe with clean dry cloths until no residue remains.<br />

3.4 CLEANING<br />

A. Immediately upon completion of installation, clean protective surfacing and accessories in accordance with panel<br />

and adhesive manufacturers' recommended cleaning method.<br />

B. Remove surplus materials, rubbish, and debris resulting from installation as work progresses and upon completion<br />

of work.<br />

3.5 PROTECTION<br />

A. Protect protective wall covering from expsoure to direct sunlight before, during,and after installation.<br />

B. Protect installed protective surfacing from subsequent construction activities. Use materials that may be easily<br />

removed without leaving residue or permanent stains.<br />

END OF SECTION<br />

06424 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 062510<br />

SECTION 06615 (06 6415) – NON-FIBERGLASS REINFORCED PLASTIC PANELS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Non-fiberglass reinforced plastic (NRP) coated panels and accessories.<br />

B. Related Requirements:<br />

1. Section 01600 - Product Requirements: Direct Purchase Products.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM D570 - Standard Test Method For Water Absorption Of Plastics.<br />

2. ASTM D648 - Standard Test Method For Deflection Temperature Of Plastics Under Flexural Load In The<br />

Edgewise Position.<br />

3. ASTM D695 - Standard Test Method For Compressive Properties Of Rigid Plastics.<br />

4. ASTM D732 - Standard Test Method For Shear Strength Of Plastics By Punch Tool.<br />

5. ASTM D2240 - Standard Test Method For Rubber Property - Durometer Hardness.<br />

6. ASTM D5420 - Standard Test Method for Impact Resistance of Flat, Rigid Plastic Specimen by Means of a<br />

Striker Impacted by a Falling Weight (Gardner Impact).<br />

7. ASTM E 84 - Test Method for Surface Burning Characteristics of Building Materials.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Store in clean, dry, enclosed, and secure storage area. Store flat and in accordance with manufacturer’s published<br />

requirements.<br />

C. Protect non-fiberglass reinforced plastic products and accessories, especially adhesive, from freezing temperatures,<br />

excessive heat, temperature fluctuations, humidity and moisture penetration.<br />

1.4 PROJECT CONDITIONS<br />

A. Enclose and weatherproof installation areas prior to beginning installation.<br />

B. Environmental Requirements: Maintain uniform temperature and humidity within ranges recommended by panel<br />

manufacturer for at least 24 hours prior to installation, during installation, and after installation.<br />

C. Maintain panel and adhesive material in an environment of a minimum of 68° F and within humidity range<br />

recommended by panel manufacturer for at least 24 hours prior to beginning the installation.<br />

PART 2 - PRODUCTS<br />

2.1 PRODUCT PROCUREMENT REQUIREMENTS<br />

A. Purchase Non-fiberglass Reinforced Plastic panels and accessories specified herein direct from Owner’s prenegotiated<br />

supplier as follows:<br />

1. Haines, Jones & Cadbury. Contact: Customer Service (800) 459-7099, info@hjcinc.com.<br />

06615 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Reference paragraph Direct Purchase Products in Section 01600.<br />

2.2 MANUFACTURER<br />

A. Manufacturer of NRP products and accessories specified herein shall be by the following unless otherwise<br />

specified:<br />

1. Parkland Plastics, Inc., Middlebury, Indiana (800) 835-4110.<br />

2.3 PANELS<br />

A. Description: Plas-Tex NRP by Parkland Plastics. Waterproof, mineral reinforced, sanitary wall covering sheets<br />

fabricated from recycled polyethylene and polypropylene resins mixed with calcium carbonate and extruded to<br />

form a chemically inert sheet. Sheets with fiberglass reinforcement are not acceptable.<br />

1. Recycled Content: 90 percent minimum.<br />

2. Recyclable Content: 100 percent.<br />

3. Panel Thickness: 3/32 inch thick.<br />

B. Physical Characteristics: Meet the following minimum characteristics:<br />

1. Resistant to fungi and bacteria growth, cleaning agents, acids, and other chemicals.<br />

2. No yellowing or color change with corrosive environments.<br />

3. Fire Rating (ASTM E84): Class C.<br />

a. Flame spread: 105 maximum.<br />

b. Smoke development: 435 maximum.<br />

4. Water Absorption (ASTM D570): 0.055 percent maximum.<br />

5. Shear Strength (ASTM D732): 970 psi minimum.<br />

6. Hardness (ASTM D2240): 51 Shore D minimum.<br />

7. Compressive Strength (ASTM D695): 5293 psi minimum.<br />

8. Impact Resistance (ASTM D5420):<br />

a. 22.6 inch pounds minimum at 73 degrees F.<br />

b. 5.9 inch pounds minimum at minus 4 degrees F.<br />

9. Heat Deflection Temperature (ASTM D648): 124° F.<br />

10. United States Department of Agriculture (USDA): Approved for incidental food contact.<br />

C. Finish: Matte.<br />

D. Color:<br />

1. NRP1 (White): Bright White by Parkland.<br />

2. NRP2 (Almond): Almond by Parkland.<br />

2.4 ACCESSORIES<br />

A. Adhesive: Pressure sensitive, low VOC adhesive. One of the following as determined by the pre-negotiated<br />

supplier:<br />

1. X7029 Parkland Panel Adhesive by Parkland.<br />

2. Spray-Lock by Interlock Industries, Inc. Chattanooga, TN; Contact: Wal-Mart Coordinator (706) 517-8989.<br />

B. Anchors: Smooth-head mechanical anchors consisting of one piece or two piece nylon rivets as recommended by<br />

manufacturer. Anchors shall be furnished and shipped with delivered panels by the panel manufacturer.<br />

C. Moldings: Extruded polyvinyl chloride (PVC) channel type moldings with flanges to fit beneath wall sheets.<br />

Shapes for panel division, inside and outside corners, and edge caps. Color: Match NRP panel color.<br />

D. Sealant: Silicone type as specified in Section 07900 and approved by NRP manufacturer for this application.<br />

06615 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.5 SUBSTITUTIONS<br />

A. Reference Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that substrates to receive panels<br />

are flat, clean, dry, solid, and free from coatings and defects detrimental to installation. Verify that surfaces<br />

conform to product manufacturer's requirements for substrate conditions.<br />

3.2 PREPARATION<br />

A. Prepare substrate for product installation in accordance with manufacturer's published instructions.<br />

3.3 INSTALLATION<br />

A. Install NRP panels in accordance with manufacturer's instructions. Follow the Plas-Tex installation online video<br />

for installation instructions except as may be otherwise instructed by the adhesive manufacturer<br />

http://www.parklandplastics.com/install-nrp-polywall.shtml<br />

B. Assure HVAC is in operation and a minimum temperature of 68° F and a maximum relative humidity of 80% is<br />

maintained at time of installation and 48 hours subsequent to installation in accordance with manufacturer’s<br />

installation instructions.<br />

C. Install sheets vertically with adhesive and anchors as shown.<br />

D. Cut sheets by scoring and snapping, with sheet metal shears, or sawing with fine toothed blade.<br />

E. Position sheet against wall. Allow recommended gap at top, bottom, and sides of sheets. Secure sheet by applying<br />

pressure with roller over entire surface. Ensure adhesive contact is even and complete.<br />

F. Penetrations and openings: Drill round openings. For rectangular cutouts, first drill hole at each corner to relieve<br />

stress. Provide minimum 1/8 inch space around pipes, electrical fittings, obstructions and other items penetrating<br />

panels.<br />

G. Install panels with edges vertical and plumb. Use maximum length pieces to provide minimum number of end<br />

joints.<br />

1. Align panel to panel vertical joints at inside and outside corner conditions.<br />

H. Adhesive: Apply in accordance with manufactures application instructions for substrates listed below:<br />

1. CMU: Parkland Adhesive. Follow on-line video installation instructions referenced above.<br />

2. Gypsum Board, Plywood And Glass-Mat Faced Gypsum Backing Board: Spray-Lock Adhesive. Follow<br />

on-line video instructions as follows: http://www.spraylock.com/world/walmart_installers.html<br />

I. Anchors: Apply as shown and in accordance with panel manufacturer’s instructions.<br />

J. Moldings: Install accessory panel trim pieces concurrently with installation of panels. Miter cut accessory panel<br />

trim at corners to provide smooth transition.<br />

1. Provide moldings for wall covering joints, perimeter edges, and corners. Neatly cut molding to required<br />

lengths. Ensure moldings are straight and correctly aligned.<br />

2. Allow space in molding channels as recommended by manufacturer for wall covering expansion.<br />

K. Apply continuous bead of sealant in all molding channels.<br />

1. Seal corner seams, base and ceiling junctures, and junctures between panels and wall with sealant.<br />

2. Provide sealant around all openings, corners, and joints.<br />

06615 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


L. Immediately remove excess adhesive and sealant from wall covering and moldings.<br />

M. Adhesive and sealant should not be visible in completed system.<br />

3.4 PROTECTION<br />

A. Protect installed panels from subsequent construction activities.<br />

END OF SECTION<br />

06615 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II<br />

093011a<br />

SECTION 06616 (06 6100) – SIMULATED STONE FABRICATIONS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Solid surfacing material.<br />

2. Quartz agglomerate.<br />

3. Substrate for solid surfacing and quartz agglomerate countertops.<br />

1.2 RELATED REQUIREMENTS<br />

A. Section 06100 - Rough Carpentry: Fire retardant treatment for plywood countertop substrate.<br />

1.3 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 84 - Test Method for Surface Burning Characteristics of Building Materials.<br />

C. Department of Commerce (National Institute of Standards and Technology) - Product Standard (DOC):<br />

1. DOC PS 1 - Construction and Industrial Plywood.<br />

D. National Sanitation Foundation / American National Standards Institute (NSF/ANSI):<br />

1. NSF/ANSI 51 - Food Equipment Materials.<br />

1.4 INSTALLER QUALIFICATIONS<br />

A. Installers of simulated stone countertops shall be factory-trained.<br />

B. Installers of quartz agglomerate countertops shall have no less than 2 years of prior experience in the installation<br />

of simulated stone materials.<br />

1.5 SUBMITTALS<br />

A. Shop Drawings: Require quartz agglomerate countertop supplier to provide Shop Drawings including countertop<br />

layout, dimensions, edge treatments, materials, finishes, cutouts, attachments and supporting structure.<br />

B. Certifications: Fire Retardant Treatment: For type of fire retardant treatment specified, provide certification by<br />

treating plant stating chemicals and process used, net amount of retardant retained and conformance with AWPA<br />

U1.<br />

1.6 DELIVERY, STORAGE, AND HANDLING<br />

A. Deliver, store, protect, and handle products in accordance with provisions of Section 01600.<br />

B. Require simulated stone countertop supplier to provide Shipping List of countertops and related items shipped and<br />

including store number and project location (city and state) and installed location of each countertop (room name<br />

and number).<br />

C. Store simulated stone materials to prevent breakage and marring of surfaces in accordance with manufacturer’s<br />

printed instructions.<br />

06616 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Provide protective coverings to prevent physical damage or staining following installation for duration of project.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURER<br />

A. Provide simulated stone materials by the following manufacturer:<br />

1. Levantina USA, Inc., Dallas, TX, (214) 736-9895. Contact: Austin Lowrie alowrie@levantinausa.com.<br />

B. Substitutions: Comply with the requirements of Section 01600.<br />

2.2 REGULATORY REQUIREMENTS<br />

A. Provide simulated stone countertops complying with the following requirements:<br />

1. ASTM E 84: Class A.<br />

2. United States Department of Agriculture (USDA): Approved for incidental food contact.<br />

3. NSF/ANSI 51.<br />

2.3 QUARTZ AGGLOMERATE<br />

A. Product Description: Quartzia by Levantina. Solid sheets consisting of quartz aggregates bound together with a<br />

matrix of filled plastic resin.<br />

1. Finish: Polished.<br />

2. Thickness: As indicated on Drawings.<br />

B. Colors as follows as indicated on Drawings:<br />

1. SST4: Alpine Line Tuscany Canyon.<br />

C. Profiles as indicated on Drawings.<br />

D. Vendors: Purchase Quartzia products from one of the following suppliers:<br />

1. Levantina as indicated under Manufacturers listed in this Section.<br />

2. Haines, Jones and Cadbury, Inc. Contact: Customer Service, (800) 459-7099, Fax (479) 756-8998, Email<br />

info@hjcinc.com.<br />

2.4 COUNTERTOP SUBSTRATE<br />

A. Provide the following substrate for simulated stone countertops at locations indicated on Drawings:<br />

1. Plywood DOC PS 1 Type 1 (Interior): Grade C-D Plugged veneer plywood, Exposure I.<br />

2. Thickness as indicated on the Drawings.<br />

3. Provide plywood treated with fire retardant specified in Section 06100.<br />

2.5 ACCESSORIES<br />

A. Supply materials for installation of products as specified in manufacturer’s printed installation instructions<br />

including color matched silicone sealant and adhesives where applicable.<br />

2.6 FABRICATION<br />

A. Fabricate components in shop to the greatest extent practical to sizes and shapes indicated.<br />

B. Form joints between components using manufacturer’s recommended joint adhesive. Joints shall be flush, tight<br />

fitting, level, without voids and inconspicuous in appearance.<br />

C. Provide holes and cutouts for plumbing and bath accessories as indicated on Drawings.<br />

D. Rout and finish component edges to a smooth, uniform finish.<br />

06616 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Surfaces shall have a uniform finish.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions.<br />

3.2 PREPARATION<br />

A. View Levantina Quartzia Technical Video at http://www.levantina.com/us/seccion.asp?idseccion=6265 prior to<br />

start of installation.<br />

B. Read Levantina Quartzia Technical Guide at http://www.levantina.com/us/seccion.asp?idseccion=6265 prior to<br />

start of installation.<br />

C. Precondition simulated stone materials and surfaces to receive simulated stone materials in accordance with<br />

manufacturer’s printed instructions.<br />

3.3 INSTALLATION<br />

A. Use tools, techniques and procedures recommended by quartz agglomerate countertop manufacturer for field<br />

fabrication and installation of quartz agglomerate countertops.<br />

B. Install components plumb and level in accordance with manufacturer’s printed installation instructions.<br />

C. Fabricate seams and fixture mounting in accordance with factory fabrication manual.<br />

D. Form field joints using manufacturer’s recommended adhesive, with joints inconspicuous in finished work.<br />

E. Provide backsplashes and end splashes as indicated on Drawings. Adhere to countertop using manufacturers<br />

standard color matched silicone sealant.<br />

F. At backsplashes provide a smooth continuous cove of sealant free of voids and neat in appearance at bottom, top<br />

and vertical corners.<br />

G. Remove adhesives, sealants, and other stains upon completion of installation per manufactures written<br />

instructions.<br />

END OF SECTION<br />

06616 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 07190 (07 1900) – WATER REPELLENTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Water repellent coating applied to exterior masonry surfaces.<br />

B. Related Requirements:<br />

1. Section 04711 - Manufactured Stone Veneers: Substrate for application of water repellent.<br />

1.2 SUBMITTALS<br />

A. Certifications: Submit manufacturer’s certification of conformance to specified surface preparation and<br />

application rates.<br />

B. Test Results: Submit test results of initial and final RILEM test and final spray test.<br />

C. Contract Closeout Submittals: Submit Letter of Certification under provisions of Section 01770.<br />

1.3 QUALITY ASSURANCE<br />

A. Qualifications:<br />

1. Manufacturer: Company specializing in manufacturing Products specified with minimum 5 years<br />

documented experience.<br />

2. Applicator: Company specializing in performing the work of this Section with minimum 5 years<br />

documented experience.<br />

B. Regulatory Requirements: Comply with applicable rules and regulations of Pollution-Control Regulatory Agency<br />

having jurisdiction regarding volatile organic compounds (VOC) and use of hydrocarbon solvents.<br />

C. Field Samples:<br />

1. Prior to water repellent application, apply water repellent coating to field mock-up sample specified in<br />

Section 04200 for determination of coverage rate.<br />

2. Apply water repellent at an initial rate of application as determined by the manufacturer as presumed<br />

necessary to pass the RILEM water tube uptake test results specified.<br />

3. Allow five days for the sample to cure. Perform a RILEM water tube uptake test on the treated area<br />

conducted by or supervised by the manufacturer’s representative. Place one tube on the block surface and<br />

one tube on a mortar joint.<br />

4. Results: Absorption shall be not more than 1.0 milliliter of water using a RILEM water uptake tube at 60<br />

mph wind driven rain equivalent. Apply additional repellent when tests results indicate failing results and<br />

retest until passing tests are achieved.<br />

5. Coverage rate for entire project shall be that which is used to for the mock-up sample passing test.<br />

6. Provide test report and application rates to the Wal-Mart Construction Manager.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Section 01600 - Materials and Equipment: Transport, handle, store, and protect products.<br />

B. Protect coating liquid from freezing.<br />

07190 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 PROJECT CONDITIONS<br />

A. Environmental Requirements: Do not apply Product during the following conditions:<br />

1. Ambient temperature below 40 degrees F.<br />

2. Substrate surfaces have cured less than 30 days.<br />

3. Rain or temperatures below 40 degrees F are predicted for a period of 24 hours.<br />

4. Surfaces not dry for minimum 24 hours.<br />

5. Substrate frozen or surface temperature is below 40 degrees F.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with project requirements, manufacturer's offering Products which may be incorporated in<br />

the Work include the following:<br />

1. BASF Building Systems, Shakopee, MN (800) 433-9517.<br />

2. ChemRex: See BASF Building Systems.<br />

3. Chemprobe Coating Systems, Garland, TX (800) 760-6776.<br />

4. Evonik Degussa Corp., Parsippany, NJ (800) 828-0919.<br />

5. L&M Construction Chemicals, Incorporated, Omaha, NE (800) 362-3331.<br />

6. Modac Products Co., Broomall, PA (800) 626-0322.<br />

7. ProSoCo, Incorporated, Kansas City, MO (800) 255-4255.<br />

8. Rainguard International Products Company, Corona del Mar, CA (949) 675-2811.<br />

2.2 MATERIALS<br />

A. Description: Clear penetrating water repellent. Siloxanes, silane or siloxane/silane blend, waterborne and VOC<br />

compliant.<br />

B. Products:<br />

1. Chemprobe: Prime-a-Pell H2O.<br />

2. BASF (ChemRex): Enviroseal PBT.<br />

3. Evonik Degussa: Protectosil Aqua-Trete Concentrate.<br />

4. L&M: Hydroblock.<br />

5. Modac: Siloxane 20.<br />

6. ProSoCo: Weather Seal Siloxane WB Concentrate.<br />

7. Rainguard: Blok-Lok.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be applied and verify that surfaces conform to<br />

specifications and manufacturer's requirements for substrate conditions. Do not proceed until satisfactory<br />

conditions have been corrected.<br />

B. Verify joint sealants are installed and cured.<br />

C. Beginning of application indicates acceptance of substrate conditions.<br />

3.2 PREPARATION<br />

A. Surface cracks, holes, or other imperfections that exceed 1/64 of an inch shall be filled with pointing mortar.<br />

Masonry joints found to be unsound, hollow, or otherwise defective shall be raked out to a depth of 1/2 inch and<br />

pointed with mortar.<br />

07190 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Remove loose particles and foreign matter. Remove oil or foreign substance with a cleaning agent which will not<br />

affect coating.<br />

C. Scrub and rinse surfaces with water, and let dry.<br />

D. Protect adjacent surfaces not scheduled to receive coating. If applied on unscheduled surfaces, remove<br />

immediately, by approved method.<br />

E. Protect landscaping, property, and vehicles from over spray and drift.<br />

3.3 APPLICATION<br />

A. Apply water repellent coating to exterior integrally colored manufactured stone veneer exposed-to-weather<br />

surfaces.<br />

B. Apply after masonry mortar is cured for not less than seven days.<br />

C. Apply coating in accordance with manufacturer's published instructions, using appropriate method and coverage<br />

rate.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Manufacturer's Field Services: Provide services of a manufacturer-authorized technical service representative to<br />

inspect and approve the substrate before application, to instruct the applicator on the product and application<br />

method to be used, and to field test the in-place surfaces after application.<br />

B. Spray Test: After water repellent has dried, spray coated surfaces with water. After surfaces have adequately<br />

dried, recoat surfaces that show water absorption.<br />

C. Water Uptake Test: Perform a RILEM Water Uptake test on a minimum of 10 location on the completed project<br />

to confirm conformance to minimum results stated in Part 1 hereinbefore. Conduct test on upper and lower<br />

portions of the masonry surfaces and on an equal number of joints and block surfaces. Tests shall be conducted by<br />

the manufacturer’s representative.<br />

D. Furnish written certification that surface preparation and rate of application is completed in accordance with<br />

specification requirements and the manufacturer’s recommendations. Furnish results of in-place RILEM and<br />

spray test.<br />

3.5 CLEANING<br />

A. Immediately clean water repellent from adjoining surfaces soiled or damaged by water repellent application as<br />

work progresses.<br />

B. Repair damage caused by water repellent application.<br />

C. Comply with manufacturer's published instructions for cleaning.<br />

END OF SECTION<br />

07190 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 07210 (07 2100) – BUILDING INSULATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Batt Insulation.<br />

2. Board Insulation.<br />

B. Related Requirements:<br />

1. Section 07840 - Firestopping: Safing insulation used in conjunction with fire stop material.<br />

2. Section 09250 - Gypsum Board: Metal furring.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 84 - Test Method for Surface Burning Characteristics of Building Materials.<br />

2. ASTM C 578 - Rigid, Cellular Polystyrene Thermal Insulation.<br />

3. ASTM C 665 - Mineral-Fiber Blanket Thermal Insulation for Light Frame Construction and Manufactured<br />

Housing.<br />

4. ASTM E 136 - Behavior of Materials in a Vertical Tube furnace at 750 C.<br />

1.3 DEFINITIONS<br />

A. Concealed Insulation: Insulation concealed within framing system, both faces protected by finish material.<br />

B. Exposed Insulation: Insulation exposed within framing system, one or both faces unprotected.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Provide products from one of the following manufacturers as specified in the Materials paragraph below:<br />

1. Atlas Roofing Corp., Atlanta, GA (800) 933-1476.<br />

2. CertainTeed Corporation, Valley Forge, PA (800) 523-7844.<br />

3. Dow Chemical Company, Midland, MI (800) 232-2436.<br />

4. Firestone Building Products Company, Carmel, IN (800) 428-4442.<br />

5. Guardian Fiberglass Incorporated, Albion, MI (800) 748-0035.<br />

6. Johns Manville Insulations, Denver, CO (877) 766-3295.<br />

7. Owens-Corning, Toledo, OH (800) 438-7465.<br />

8. Pactiv Building Products, Smyrna, GA (800) 241-4402.<br />

07210 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 REGULATORY REQUIREMENTS<br />

A. Fire-Test-Response Characteristics: Provide insulation and related materials with the fire-test-response<br />

characteristics indicated, as determined by testing identical products per ASTM E 84 for surface-burning<br />

characteristics and other methods specified. Identify materials with appropriate markings of applicable testing and<br />

inspecting agency.<br />

2.3 MATERIALS<br />

A. Batt Insulation: ASTM C 665 mineral fiber blanket insulation.<br />

1. Unfaced Glass Fiber: Type I (blankets without membrane facing); with maximum flame-spread and<br />

smoke-developed indexes of 25 and 50, respectively passing ASTM E 136 for combustion characteristics.<br />

2. Faced, Glass Fiber: Type III (blankets with reflective membrane facing), Class A (membrane-faced surface<br />

with a flame-spread index of 25 or less); Category 1 (membrane is a vapor barrier), faced with vaporretarder<br />

membrane on 1 face.<br />

3. Sound Attenuation Insulation (Sound Batts): Unfaced glass fiber batt insulation as specified above.<br />

4. Provide batt insulation by one of the following manufacturers:<br />

a. CertainTeed Corporation.<br />

b. Guardian Fiberglass, Inc.<br />

c. Johns Manville.<br />

d. Owens Corning.<br />

B. Board Insulation:<br />

1. Extruded Polystyrene:<br />

a. Type VI: ASTM C 578, Type VI (density 1.8 pcf minimum); square edges. Provide one of the<br />

following:<br />

1) Styrofoam 40 High Load by Dow.<br />

2) Foamular 400 by Owens Corning.<br />

C. Substitutions: Comply with the requirements of Section 01600.<br />

2.4 ACCESSORIES<br />

A. Tape: Polyethylene or polyester self-adhering type; two inches wide.<br />

B. Adhesive: Waterproof type, acceptable to manufacturer of insulation board. Adhesive VOC shall be within the<br />

limits of not greater than 70 g/L in accordance with the California’s South Coast Air Quality Management District<br />

(SCAQMD) Rule No. 1168.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Batt Insulation:<br />

1. Verify adjacent materials are dry and ready to receive installation.<br />

2. Verify mechanical and electrical services within walls have been installed and tested.<br />

B. Board Insulation:<br />

1. Verify substrate and adjacent materials and insulation boards are dry and ready to receive insulation and<br />

adhesive.<br />

2. Verify insulation boards are unbroken, free of damage.<br />

3.2 INSTALLATION - BATT INSULATION<br />

A. Install batt insulation in accordance with manufacturer's instructions, without gaps or voids.<br />

07210 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Trim insulation neatly to fit spaces. Use batts free of damage. Fit insulation tight in spaces and tight to exterior<br />

side of mechanical and electrical services within the plane of insulation.<br />

C. Install insulation with factory applied membrane facing warm side in winter of building spaces. Lap ends and side<br />

flanges of membrane. Attach insulation in place to framing; tape seal butt ends and lapped side flanges. Tape seal<br />

tears or cuts in membrane.<br />

3.3 INSTALLATION - BOARD INSULATION BENEATH FREEZER<br />

A. Coordinate with concrete Sections in Division 3 of the specifications for timely placement of insulation board.<br />

B. Install two layers of insulation board in areas beneath freezers. Refer to Drawings for locations and details.<br />

3.4 SCHEDULES<br />

A. Provide insulation types as scheduled below and as indicated on Drawings.<br />

CONDITION TYPE OF INSULATION THICKNESS<br />

3-1/2 inches (R=11) or 6 inches (R=19)<br />

Exterior Wall, Soffits, &<br />

Faced Batt Insulation<br />

or 8 inches (R-25) as shown; or as<br />

Ceiling<br />

required to fill cavity.<br />

Interior Partitions Unfaced Batt Insulation 3-1/2 inches or 6 inches as Shown.<br />

Sound Attenuation Unfaced Batt Insulation 3-1/2 inches or 6 inches as Shown.<br />

Freezer Slab Insulation Extruded Polystyrene, Type VI 6.0 inches<br />

END OF SECTION<br />

07210 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 07243 (07 2419) – WATER-DRAINAGE EXTERIOR INSULATION AND FINISH SYSTEM (EIFS)<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Field applied water-drainage exterior insulation and finish system (EIFS) applied over<br />

sheathing or masonry units.<br />

B. Related Requirements:<br />

1. Section 05400 - Cold Formed Metal Framing: Framing for gypsum sheathing substrate.<br />

2. Section 06100 - Rough Carpentry: Non-structural plywood panels used for sheathing.<br />

3. Section 07900 - Joint Sealers: Joint sealants used in conjunction with exterior insulation and finish system.<br />

4. Section 09250 - Gypsum Board: Gypsum sheathing.<br />

5. Section 09900 - Paint and Coatings: Field applied paint finish.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C 578 - Rigid, Cellular Polystyrene Thermal Insulation.<br />

2. ASTM C 1063 - Installation of Lathing and Furring to Receive Interior and Exterior Portland Cement-<br />

Based Plaster.<br />

3. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

4. ASTM D 1784 - Rigid Poly (Vinyl Chloride) (PVC) Compounds and Chlorinated Poly (Vinyl Chloride)<br />

(CPVC) Compounds.<br />

5. ASTM E 2430 - Expanded Polystyrene ("EPS") Thermal Insulation Boards For Use In Exterior Insulation<br />

and Finish Systems ("EIFS").<br />

6. ASTM E 2568 - PB Exterior Insulation and Finish Systems.<br />

C. ICC Evaluation Service, Inc. (ICC-ES):<br />

1. ICC-ES AC212 - Acceptance Criteria For Water-Resistive Coatings Used As Water-Resistive Barriers<br />

Over Exterior Sheathing.<br />

2. ICC-ES AC235 - Acceptance Criteria For EIFS Clad Drainage Wall Assemblies.<br />

D. National Fire Protection Association (NFPA):<br />

1. NFPA 268 - Standard Test Method For Determining Ignitibility Of Exterior Wall Assemblies Using A<br />

Radiant Heat Energy Source.<br />

2. NFPA 259 - Standard Test Method For Potential Heat Of Building Materials.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Evaluation Reports: Submit current ICC-ER report specified in Part 2 of this Section.<br />

1.4 CLOSEOUT SUBMITTALS<br />

A. Comply with the requirements of Section 01770.<br />

B. Letter of Certification.<br />

07243 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Contractor Installation Declaration Forms: Include completed Exhibit A and Exhibit B forms (included at the end<br />

of this section) signed by EIFS Contractor and Sealant Installer.<br />

D. Manufacturer's Observation Reports: Submit report signed by EIFS manufacturer of observations during site visit<br />

by manufacturer’s representative.<br />

1.5 QUALITY ASSURANCE<br />

A. Installer Qualifications: Single firm, approved in writing by EIFS manufacturer, employing trained workers<br />

familiar with current installation methods and materials. Installer shall have not less than 2 years documented<br />

experience in the installation of the specific drainable system to be installed.<br />

B. Source Limitations: Obtain EIFS from single source from single EIFS manufacturer and from sources approved<br />

by EIFS manufacturer as compatible with system components.<br />

PART 2 PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Manufacturers: Subject to compliance with requirements, provide EIFS by the following:<br />

B. Manufacturers: Subject to compliance with requirements, provide EIFS by one of the following:<br />

1. BASF Wall Systems, Inc., Jacksonville, FL (Formerly Senergy, Inc & Degussa Wall Systems), (800) 221-<br />

9255. Contact: Steve DonFrancesco (770) 335-5260.<br />

2. Dryvit Systems, Inc., Warwick, RI (800) 556-7752.<br />

3. Omega Products International, Inc., Los Angeles, CA (800) 600-6634.<br />

4. Parex, Inc., Redan, GA, (800) 537-2739.<br />

5. Sto Corp., Atlanta, GA. Contact Strategic Accounts (888) 786-3437.<br />

2.2 PRODUCTS<br />

A. Products: Drainable, Class PB EIFS System. Provide one of the following products:<br />

1. One of the following brands by BASF:<br />

a. Senerflex Channeled Adhesive or Senerflex Channeled Insulation Board by Senergy.<br />

b. Pebbletex-DCA System by Finestone.<br />

c. FlexWall WM System by SonoWall.<br />

d. Acrowall-ES Plus by Acrocrete.<br />

2. Outsulation Plus by Dryvit.<br />

3. Akroflex Water Managed Drainage Board System, Class PB by Omega.<br />

4. Standard Water Master (formerly Commercial Water Master VR) by Parex.<br />

5. Sto Essence NexT by Sto.<br />

B. Substitutions: Comply with the requirements of Section 01600.<br />

2.3 PERFORMANCE REQUIREMENTS<br />

A. Bond Integrity: System shall be free from bond failure within EIFS components or between system and<br />

supporting wall construction, resulting from exposure to wind loads, weather, or other in-service conditions.<br />

B. Weathertightness: System shall be resistant to water penetration from exterior into water-drainage EIFS and<br />

assemblies behind it or through them into interior of building that results in deterioration of thermal-insulating<br />

effectiveness or other degradation of EIFS and assemblies behind it, including substrates, supporting wall<br />

construction, and interior finish, and including a means that allows water entering into an EIFS assembly to drain<br />

to the exterior.<br />

C. Physical Properties, Structural Performance, and Drainage Provisions: Comply with ICC-ES AC235 or ASTM<br />

E2568.<br />

07243 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Fire-Test-Response Characteristics: Provide EIFS and system components with the following fire-test-response<br />

characteristics as determined by testing identical EIFS and system components per test method indicated below by<br />

UL or another testing and inspecting agency acceptable to Authorities Having Jurisdiction. Identify products with<br />

appropriate markings of applicable testing agency.<br />

1. Radiant Heat Exposure: No ignition of EIFS per NFPA 268.<br />

2. Potential Heat: Acceptable level per NFPA 259.<br />

3. Surface-Burning Characteristics: Insulation board, adhesives, base coats, and finish coats with flame<br />

spread index of 25 or less and smoke developed index of 450 or less, per ASTM E 84.<br />

E. Evaluation Report: The system proposed for use from the specified products shall have a current Evaluation<br />

Report (ICC-ER) by the International Code Council Evaluation Service (ICC-ES) showing compliance with the<br />

International Building Code or the model code within the jurisdiction of the project and as required by the<br />

Authority Having Jurisdiction.<br />

2.4 MATERIALS<br />

A. Applicability: Provide materials and EIFS components standard with the manufacturer for the product systems<br />

listed and selected for the project. Products listed below shall apply to the extent applicable to the system to be<br />

installed.<br />

B. Compatibility: Provide water-resistive coating, adhesive, fasteners, board insulation, reinforcing meshes, baseand<br />

finish-coat systems, sealants, and accessories that are compatible with one another and with substrates and<br />

approved for use by EIFS manufacturer for Project.<br />

C. Water-Resistive Coatings: EIFS manufacturer's standard formulation and accessories for use as water/weatherresistive<br />

barriers, compatible with substrate, and complying with physical and performance criteria of ICC-ES<br />

AC212.<br />

D. Flexible-Membrane Flashing: Cold-applied, fully self-adhering, self-healing, rubberized-asphalt and<br />

polyethylene-film composite sheet or tape and primer; EIFS manufacturer's standard or product recommended in<br />

writing by EIFS manufacturer.<br />

E. Drainage Mat: Three-dimensional, nonwoven, entangled filament, nylon or plastic; or woven or fused, selffurring,<br />

PVC mesh lath mat designed to drain incidental moisture by gravity; EIFS manufacturer's standard or<br />

product recommended in writing by EIFS manufacturer with manufacturer's standard application method suitable<br />

for intended substrate.<br />

F. Spacers: Closed-cell polyethylene or woven or fused, self-furring, PVC mesh lath furring strips; EIFS<br />

manufacturer's standard or product recommended in writing by EIFS manufacturer with manufacturer's standard<br />

application method suitable for intended substrate.<br />

G. Insulation Adhesive: Standard formulation for EIFS system used. Adhesive VOC shall be not greater than 50 g/L<br />

as set forth in the California’s South Coast Air Quality Management District (SCAQMD) Rule No. 1168.<br />

H. Molded, Rigid Cellular Polystyrene Board Insulation: Comply with ASTM C 578, Type I, and EIFS<br />

manufacturer's requirements.<br />

1. Channeled Board Insulation: EIFS manufacturer's standard factory-fabricated profile with linear, vertical<br />

drainage channels, slots, or waves on the back side of board.<br />

2. EIFS Cornice (Foam Shapes): Pre-Manufactured EIFS extrusion Expanded Polystyrene (EPS) as specified<br />

above for insulation. Cut and form to profile as indicated on Drawings.<br />

a. Adhesive: As recommended by the molding manufacturer.<br />

I. Reinforcing Mesh: Balanced, alkali-resistant, open-weave, glass-fiber mesh; complying with ASTM D 578 and<br />

the following:<br />

1. Standard-Impact Reinforcing Mesh: Not less than 4.0 oz./sq. yd.<br />

2. Heavy-Duty Reinforcing Mesh: Not less than 20 oz./sq. yd.<br />

3. Strip Reinforcing Mesh: Not less than 3.75 oz./sq. yd.<br />

07243 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Detail Reinforcing Mesh: Not less than 4.0 oz./sq. yd.<br />

5. Corner Reinforcing Mesh: Not less than 7.2 oz./sq. yd.<br />

J. Base-Coat Materials: Standard formulation.<br />

K. Primer: Factory-mixed, elastomeric-polymer primer.<br />

L. Finish-Coat Materials: Factory-mixed, standard acrylic-based coating.<br />

1. Integral Color: Dryvit standard #310 "China White".<br />

2. Paint Finish: Field applied paint finish as specified in Section 09900. Color as shown on the drawings and<br />

as defined within Section 09900.<br />

a. Texture: Dryvit standard "Sandblast". If new Exterior Insulation and Finish System is installed<br />

adjacent to existing Exterior Insulation and Finish System with finish coat texture other than that<br />

specified, consult with the Wal-Mart Construction Manager for finish coat to be installed at new<br />

adjacent Exterior Insulation and Finish System.<br />

M. Mechanical Fasteners: Corrosion-resistant fasteners consisting of thermal cap, standard washer and shaft<br />

attachments, and fastener suitable for substrate.<br />

N. Trim Accessories: Manufactured from UV-stabilized PVC and complying with ASTM D1784 and ASTM C1063.<br />

O. Joint Sealant: Joint sealant shall be as specified in Section 07900 unless otherwise required by the EIFS<br />

manufacturer.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation<br />

tolerances and other conditions affecting performance of EIFS.<br />

B. Proceed with installation only after unsatisfactory conditions have been corrected.<br />

C. Begin coating application only after surfaces are dry.<br />

3.2 PREPARATION<br />

A. Protect contiguous work from moisture deterioration and soiling caused by application of EIFS. Provide<br />

temporary covering and other protection needed to prevent spattering of exterior finish coats on other work.<br />

B. Protect EIFS, substrates, and wall construction behind them from inclement weather during installation. Prevent<br />

penetration of moisture behind drainage plane of EIFS and deterioration of substrates.<br />

C. Prepare and clean substrates to comply with EIFS manufacturer's written instructions to obtain optimum bond<br />

between substrate and adhesive for insulation.<br />

3.3 INSTALLATION<br />

A. Comply with EIFS manufacturer's written instructions for installation of EIFS as applicable to type of substrate<br />

indicated.<br />

B. Water-Resistive Coatings: Apply over substrates to protect substrates from degradation and to provide<br />

water/weather-resistive barrier.<br />

07243 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Flexible-Membrane Flashing: Install over weather-resistive barrier, applied and lapped to shed water; seal at<br />

openings, penetrations, terminations, and where indicated by EIFS manufacturer's written instructions to protect<br />

wall assembly from degradation. Prime substrates, if required, and install flashing to comply with EIFS<br />

manufacturer's written instructions and details.<br />

D. Trim: Apply trim accessories at locations indicated on Drawings.<br />

E. Drainage Mat: Apply wrinkle free, continuously, with edges over water-/weather-resistive barrier according to<br />

manufacturer's written instructions.<br />

F. Board Insulation: Attach to substrate.<br />

G. Expansion Joints: Install at locations indicated, where required by EIFS manufacturer, where expansion joints or<br />

control joints are indicated in substrates behind EIFS; where EIFS adjoin dissimilar substrates, materials, and<br />

construction; and where wall height changes.<br />

1. Do not exceed manufacturer's maximum recommended area.<br />

2. Coordinate placement of additional joints with Wal-Mart Construction Manager.<br />

H. Base Coat: Apply to exposed surfaces of insulation and foam shapes in minimum thickness recommended in<br />

writing by EIFS manufacturer, but not less than 1/16-inch dry-coat thickness.<br />

I. Reinforcing Mesh:<br />

1. Place reinforcing mesh over insulation and secure in place with base coating.<br />

2. Completely embed mesh in wet base coat, applying additional base-coat material if necessary, so<br />

reinforcing-mesh color and pattern are not visible.<br />

3. Apply heavy weight mesh in conjunction with standard weight mesh in areas below 8 feet above ground<br />

level.<br />

J. Finish Coat: Apply over dry base coat, maintaining a wet edge at all times for uniform appearance, in thickness<br />

required by EIFS manufacturer to produce a uniform finish of color and texture matching approved sample and<br />

free of cold joints, shadow lines, and texture variations.<br />

K. Form 3/4 inch drip rustication joints straight and true to line, as indicated on Drawings.<br />

3.4 JOINTS<br />

A. Install sealant at joints within system and where system abuts dissimilar materials. Apply joint sealant using<br />

sealant type, application method, and installation procedures in accordance with manufacturer’s recommendation<br />

and Section 07900 and the EIFS manufacturers evaluation report. Do not seal drainage weep holes or outlets.<br />

3.5 REPAIR OF DAMAGED OR NON-CONFORMING WORK<br />

A. Repair or correct installed work which is damaged during construction or is otherwise incomplete or not<br />

conforming to specification requirements. Repair and correction shall be in accordance with manufacturer’s<br />

written and published instructions.<br />

3.6 FIELD QUALITY CONTROL<br />

A. Unless otherwise specified, quality control tests and inspection specified below will be conducted by the Owner’s<br />

Construction Testing Laboratory at no cost to the Contractor in accordance with Section 01458. The Contractor<br />

shall perform additional testing or inspection as considered necessary by the Contractor for assurance of quality<br />

control.<br />

B. Special Inspections: CTL shall perform special inspections of water-resistive barrier and EIFS and prepare<br />

reports according to ICC-ES AC 212 and AC235.<br />

07243 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Manufacturer Services: A representative of the manufacturer shall visit the site prior to installation of EIFS,<br />

during installation, and upon completion of installation of EIFS to become familiar with material and methods<br />

being applied. Site visits shall include inspection of substrate, installation, and verification of proper procedure to<br />

the extent observed. Manufacturer’s Representative shall prepare observation report stating conformance or<br />

deficiencies noted.<br />

END OF SECTION<br />

07243 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


EXHIBIT A<br />

EIFS Contractor Installation Declaration Form<br />

EIFS Contractor Name:<br />

Completion Date:<br />

THE EXTERIOR INSULATION AND FINISH SYSTEM (EIFS) INSTALLED ON THE STRUCTURE LOCATED AT<br />

THE ADDRESS INDICATED BELOW CONFORMS:<br />

TO<br />

(Insert EIFS Manufacturer Name Here)<br />

RECOMMENDED INSTALLATION PRACTICES AND<br />

FOR_________________________________ AND SECTION(S)<br />

(Insert EIFS System name here)<br />

EVALUATION REPORT NO. _____________________________<br />

(Insert Applicable Report Number Here)<br />

Address of Structure:<br />

(Insert Appropriate Section Numbers Here)<br />

Product Component Names:<br />

Adhesive(s):<br />

Fasteners (Mech.):<br />

Base Coat:<br />

Reinforcing Fabric:<br />

Finish Coat (s):<br />

OF ICC<br />

INSTALLATION<br />

CONFORMS<br />

A. Substrate Type and Tolerance<br />

B. EIFS<br />

1. Adhesive and/or Fasteners<br />

2. Insulation<br />

3. Reinforcing Fabric<br />

4. Base Coat<br />

5. Finish<br />

C. The information entered above is offered in testimony that the EIFS installation conforms with the<br />

EIFS manufacturer's installation methods and procedures, and the EIFS manufacturers ES report.<br />

D. An installation card shall be received from the Sealant Installer indicating that the sealant installation conforms with<br />

the EIFS evaluation report and sealant manufacturer's installation methods and procedures must accompany this<br />

declaration.<br />

EIFS Contractor Company Name and Address:<br />

_____________________________________<br />

_____________________________________<br />

_____________________________________<br />

Signature of Responsible Officer:<br />

_____________________________________<br />

Typed Name and Title of Officer:<br />

_____________________________________<br />

Telephone Number:_____________________<br />

cc: Original: Building Department (Must be submitted with sealant installer declaration.)<br />

Copies: EIFS Manufacturer<br />

Owner (include in Final Closeout Submittals)<br />

07243 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


EXHIBIT B<br />

EIFS Sealant Contractor Installation Declaration Form<br />

Sealant Installer Name:<br />

Completion Date:<br />

THE SEALANT INSTALLED IN CONJUNCTION WITH AN EXTERIOR INSULATION AND FINISH SYSTEM (EIFS)<br />

INSTALLED ON THE STRUCTURE LOCATED AT THE ADDRESS INDICATED BELOW CONFORMS:<br />

TO and RECOMMENDED<br />

(Insert EIFS Manufacturer Name Here)<br />

(Insert Sealant Manufacturer Name Here)<br />

INSTALLATION PRACTICES AND SECTION(S)<br />

EVALUATION REPORT NO. .<br />

(Insert Applicable Report Number Here)<br />

(Insert Appropriate Section Numbers Here)<br />

OF ICC<br />

Address of Structure:<br />

Product Component Names:<br />

Primer(s):<br />

Sealers:<br />

Bond Breakers:<br />

Sealant Materials:<br />

INSTALLATION<br />

CONFORMS<br />

A. Designer's requirements, details<br />

and instructions<br />

B. Sealant Manufacturer's details<br />

and Requirements<br />

C. Exterior Insulation Manufacturer's<br />

Requirements<br />

D. The information entered above is offered in testimony that the Sealant installation conforms with the<br />

Sealant manufacturer's installation methods and procedures, and the EIFS manufacturers evaluation report.<br />

Sealant Installer Company Name and Address:<br />

Signature of Responsible Officer:<br />

Typed Name and Title of Officer:<br />

Telephone Number: ( )<br />

cc: Original: Building Department (Must be submitted with EIFS contractor declaration.)<br />

Copies: EIFS Manufacturer<br />

EIFS Contractor<br />

Sealant Manufacturer<br />

Owner (include in Final Closeout Submittals)<br />

07243 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II - NP 062711<br />

SECTION 07411 (07 4213) – METAL WALL PANELS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Exterior metal wall panels and accessories.<br />

B. Related Requirements:<br />

1. Section 07525 - Fluid Applied Air Barrier: Membrane air barrier for application to substrate behind metal<br />

wall panels.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA):<br />

1. Architectural Sheet Metal Manual.<br />

C. ASTM International (ASTM):<br />

1. ASTM A653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

1.3 SUBMITTALS<br />

A. Shop Drawings: Provide shop drawings showing metal panel wall system, including fastening (attachment)<br />

methods, joinery, sealing methods, accommodations of thermal movement, accessories required and erection<br />

procedures.<br />

1.4 QUALITY ASSURANCE<br />

A. Applicator Qualifications:<br />

1. Three years minimum experience in application of metal wall systems of this nature.<br />

2. Approved installer, certified by the manufacturer.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Section 01600 - Product Requirements: Transport, handle, store, and protect products.<br />

B. Stack preformed and prefinished material to prevent twisting, bending, or abrasion, and to provide ventilation.<br />

Comply with manufacturer's recommendations for job site storage, handling, and protection.<br />

C. Prevent contact with materials during storage which may cause discoloration or staining.<br />

D. Store panels in a clean, dry place. One end should be elevated to allow moisture to run off.<br />

E. Store panels with strippable film away from direct exposure to the sun.<br />

F. Stack materials to prevent damage and to allow for adequate ventilation.<br />

G. Prevent prolonged storage of bundled panels.<br />

07411 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.6 WARRANTY<br />

A. Material Warranty: Provide manufacturer’s twenty year standard warranty against failure due to corrosion, rupture<br />

or perforation.<br />

B. Installation Warranty: Provide labor warranty to repair or replace metal wall panel assemblies that fail in materials<br />

and workmanship within two years from date of Substantial Completion.<br />

PART 2 - PRODUCT<br />

2.1 MATERIALS<br />

A. Prefinished Metal Wall Panel:<br />

1. Manufacturer: Centria Architectural Systems, Moon Township, PA, Phone (800) 759-7474.<br />

2. Material: 22 gage zinc coated steel conforming to ASTM A 653 SS Grade 37, G90 coating.4b.<br />

3. Provide the following as shown on the drawings:<br />

a. CS-260 Profile:<br />

1) Concept Series, CS-260 Profile.<br />

2) Panel Size: 12” H x 7/8” D x Length.<br />

3) Fasteners: Concealed.<br />

4) Finish: Smooth or embossed.<br />

b. Econolap 3/4” Profile:<br />

1) Econolap 3/4” Exposed Fastener Panels.<br />

2) Panel Size: 34 2/3” H x 3/4” D x Length.<br />

3) Fasteners: Exposed.<br />

4) Finish: Smooth or embossed.<br />

B. Finish: Full strength Kynar 500 Fluoropolymer coating, applied by the manufacturer on a continuous coil coating<br />

line, with a prime coat of 0.20 - 0.30 mils DFT and topcoat of 0.70 - 0.90 mils DFT. Metallic Colors: Provide a 3-<br />

coat metallic, with additional 0.4 - 0.6 mil top coat. Bottom side shall be coated with manufacturer’s standard<br />

wash coating. Finish shall conform to all tests for adhesion, flexibility, and longevity as specified by the Kynar<br />

500 finish supplier.<br />

1. Color: As shown on the Drawings.<br />

C. Strippable film shall be applied to the top side of the painted coil to protect the finish during fabrication, shipping<br />

and field handling.<br />

2.2 ACCESSORY MATERIALS<br />

A. Provide manufacturer's standard accessories and other special items required for sheet metal wall system<br />

installation. Provide accessories with same finish and color as sheet metal panels.<br />

1. Trim Items: Same material and finish as wall panels.<br />

2. Fasteners: Recommended by panel manufacturer for intended purpose.<br />

3. Mastic Tape: Manufacturer's standard.<br />

4. Sealants: Color coordinated primerless silicone, or high grade, non-drying butyl recommended by panel<br />

manufacturer.<br />

5. Hem exposed edges of flashing on underside 1/2 inch.<br />

B. Protective Backing Paint: Bituminous.<br />

2.3 AIR BARRIER<br />

A. Liquid applied air barrier for application behind wall panels is specified in section 07525.<br />

07411 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions.<br />

3.2 INSTALLATION<br />

A. Install weather barrier and support channels as shown on the drawings.<br />

B. Comply with manufacturers standard instructions and conform to standards set forth in the Architectural Sheet<br />

Metal Manual published by SMACNA to achieve a watertight installation.<br />

C. Metal panel and accessory erection shall be in accordance with shop drawings.<br />

D. Install panels with horizontal lines true and level and vertical lines plumb.<br />

E. Attach panels using manufacturer's standard fasteners, spaced in accordance with approved shop drawings.<br />

F. Dissimilar Metals: Where aluminum materials come in contact with dissimilar materials, a bituminous paint or<br />

caulking tape shall be installed to insulate between the dissimilar materials. Factory applied protective paint<br />

coatings are considered adequate insulation.<br />

G. Apply sealant to penetrations, transitions, and other locations necessary for airtight, waterproof installation.<br />

3.3 CLEANING<br />

A. Clean exposed surfaces immediately after completion of installation.<br />

B. Clean exposed surfaces 24 hours prior to date of Substantial Completion.<br />

C. Clean grease, finger marks, or stains from the panels per manufacturer's recommendations.<br />

3.4 PROTECTION<br />

A. Provide protection and maintain manufacturer’s recommended conditions to prevent damage or deterioration of<br />

sheet metal panels until date of Substantial Completion.<br />

END OF SECTION<br />

07411 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 07500 (07 5000) – MEMBRANE ROOFING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. TPO Membrane Roofing System including insulation.<br />

2. Underlayment: DensDeck® board.<br />

B. Related Requirements:<br />

1. Section 06100 - Rough Carpentry: Wood deck, blocking and nailers.<br />

2. Section 07620 - Sheet Metal Flashing and Trim: Sheet metal fascia and edge trim, counter<br />

flashings, and other sheet metal.<br />

3. Section 07711 - Gutters and Downspouts: Interface of gutters with roofing and metal flashings.<br />

4. Section 07900 - Joint Sealers.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C 578 - Rigid, Cellular Polystyrene Thermal Insulation.<br />

2. ASTM C 1289 - Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board.<br />

3. ASTM C 1303 - Standard Test Method for Predicting Long-Term Thermal Resistance of Closed-<br />

Cell Foam Insulation.<br />

4. ASTM D 6878 - Thermoplastic Polyolefin Based Sheet Roofing.<br />

C. Factory Mutual Research Corporation (FM):<br />

1. FM Approvals Building Materials Approval Guide, Chapter 3 - Approved Combinations and<br />

Assemblies.<br />

2. FM Global Loss Prevention Data Sheet 1-28 - Design Wind Loads.<br />

3. FM Global Loss Prevention Data Sheet 1-29 - Roof Deck Securement and Above-Deck<br />

Components.<br />

4. FM Approval Standard 4450 - Class 1 Insulated Steel Deck Roofs.<br />

5. FM Approval Standard 4470 - Class 1 Roof Covers.<br />

D. Underwriters Laboratories, Inc. (UL):<br />

1. UL - Roofing Materials and Systems Directory.<br />

2. UL 1256 - Fire Test of Roof Deck Construction.<br />

1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-installation Conference:<br />

1. Convene Pre-installation Conference at Site one week prior to commencing work of this Section.<br />

Require attendance of parties directly affecting work of this Section, including, but not limited to<br />

the following:<br />

a. Architect.<br />

b. Wal-Mart Construction Manager.<br />

c. General Contractor.<br />

d. Roofing sub-contractor (Roofing Applicator and job foreman).<br />

e. Mechanical and Plumbing sub-contractors.<br />

f. Owner’s Independent Roofing Inspector.<br />

g. Roofing Manufacturer's Representative.<br />

07500 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 SUBMITTALS<br />

2. Notify attendees at least two weeks prior to the conference.<br />

3. Review preparation and installation procedures and coordinating and scheduling required with<br />

related work.<br />

4. Review foreseeable methods and procedures related to roofing work, including the following:<br />

a. Tour, inspect and discuss condition of substrate, roof drains, roof drain final locations,<br />

curbs, penetrations and other preparatory work performed by other trades.<br />

b. Review structural loading limitations of deck as defined below and inspect deck for loss<br />

of flatness and for required mechanical fastening.<br />

c. Review roofing system requirements (drawings, specifications and other contract<br />

documents including submittals).<br />

d. Review required submittals.<br />

e. Review and finalize construction schedule related to roofing work and verify availability<br />

of materials, installer's personnel, equipment, and facilities needed to make progress and<br />

avoid delays.<br />

f. Review required inspections, testing, certifying, and material usage accounting<br />

procedures.<br />

g. Review weather and forecasted weather conditions, and procedures for coping with<br />

unfavorable conditions, including possibility of temporary roofing (if not a mandatory<br />

requirement).<br />

5. Record discussions of conference and decisions and agreements (or disagreements) reached, and<br />

furnish copy of record to each party attending.<br />

A. Comply with the requirements of Section 01330. Submit required submittals within 30 days after contract<br />

award. Submittals shall be available at all times to the Wal-Mart Construction Manager.<br />

B. Product Data: Submit Product Data and MSDS sheets for accepted system showing compliance with the<br />

specified physical properties.<br />

C. Regulatory Requirements Documentation:<br />

1. Submit Factory Mutual and UL data and assembly drawings showing compliance with Quality<br />

Assurance requirements specified below.<br />

2. Submit letter of compliance from the manufacturer certifying compliance with referenced FM and<br />

UL roofing system requirements.<br />

D. Shop Drawings: Submit Shop Drawings showing:<br />

1. Fastener patterns to meet uplift requirements.<br />

2. Layouts for Crickets and saddles.<br />

3. Walk pad layouts.<br />

4. Details required for completion but not shown on Drawings.<br />

5. Techniques for nighttime or weather tie offs.<br />

E. Quality Assurance Submittals: Copy of Certified Applicator Statement from system manufacturer<br />

showing:<br />

1. Job names, size, scope, letters from owner contact, present owner contact name and phone number<br />

to verify logistical and system experience.<br />

F. Closeout Submittals: Comply with the requirements of Section 01770.<br />

1. Record Letter of Conformance included at the end of this Section.<br />

2. Letter of Certification of installer’s qualifications and conformance with specified tests and<br />

criteria.<br />

3. Manufacturer's Technical Representative Site Inspection Reports.<br />

4. Manufacturer’s Certificate of Acceptance.<br />

07500 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. Roof Inspection Form included at the end of this Section. Submit at Final Inspection. Parties in<br />

attendance shall include Contractor, Roofing subcontractor, Owner’s Independent Roofing<br />

Inspector, Manufacturer’s Technical Representative, Wal-Mart Construction Manager, and Wal-<br />

Mart Store Manager. Form shall be completed by the Independent Roofing Inspector and signed<br />

by the applicable parties. Provide copies to all parties in attendance.<br />

6. Roofing System Warranty Form included at the end of this Section.<br />

1.5 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Deliver materials in manufacturer's original unopened containers, dry and undamaged with seals and labels<br />

intact.<br />

C. Store materials in weather-protected environment, clear of ground and moisture. Storage requirements for<br />

insulation are as follows:<br />

1. Cut or remove plastic shipping wrap from insulation.<br />

2. Cover with tarpaulin, shield from moistures and ultraviolet rays.<br />

3. Elevate minimum of 4 inches above substrate.<br />

4. Secure to resist high winds.<br />

5. Distribute insulation stored on roof deck to prevent concentrated loads.<br />

6. Do not install wet insulation. Insulation shall be thoroughly dry prior to installation.<br />

D. Store cements, primers, and caulks in heated area above 40 degrees F during cold weather and in area<br />

below 80 degrees F in warm weather.<br />

E. Do not store materials on completed roofing.<br />

1.6 PROJECT CONDITIONS<br />

A. Follow industry standards for environment requirements including, but not limited to, the following:<br />

1. Do not apply roofing membrane during inclement weather. When air temperature is expected to<br />

fall below 40 degrees F, follow specified Cold Weather Application Procedures as specified<br />

herein.<br />

2. Do not apply finished roofing system to wet, damp or frozen deck surface or when precipitation is<br />

occurring.<br />

3. Do not expose materials vulnerable to water or sun damage in quantities greater than can be<br />

weatherproofed during same day.<br />

1.7 WARRANTY<br />

A. Provide Warranty commencing at date of Grand Opening, on form provided at the end of this Section that<br />

includes cost of labor and materials for loss of weather tightness without financial limit for a period of 15<br />

years.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Manufacturers: Subject to compliance with requirements and to the extent specified hereinafter, provide<br />

products by the following manufacturers:<br />

1. Carlisle SynTec, Steve Benjamin, Technical Manager, Strategic Accounts Group, (413) 262-8928,<br />

steven.benjamin@syntec.carlisle.com.<br />

2. Firestone Building Products Company, Indianapolis, IN, Chris Mincey, National Accounts<br />

Representative, (800) 4442 x53236.<br />

07500 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 SYSTEM DESCRIPTION<br />

3. Johns Manville Roofing Systems, A. J. Maijala, Manager, Preferred Accounts, (303) 978-2176 or<br />

(303) 898-0027, aj.maijala@jm.com<br />

A. Single Ply Membrane Roofing System over Wood Deck: Single ply membrane roofing system consisting<br />

of insulation on existing wood deck over fire resistive Underlayment, with reinforced membrane<br />

mechanically fastened.<br />

B. Flashing and Waterproofing Membranes: Reinforced membrane and unreinforced, fully adhered, as<br />

defined herein and indicated on Drawings.<br />

2.3 REGULATORY REQUIREMENTS<br />

A. Regulatory Requirements for Roof Assembly: Comply with FM Approvals Building Materials Approval<br />

Guide or Underwriters Laboratories, Inc. Roofing Materials and Systems Directory as specified:<br />

1. Factory Mutual: Provide roofing assembly meeting Class 1A-90 requirements for fire resistance<br />

and wind uplift in accordance with FM Approvals Standard 4470 and FM Global Loss Prevention<br />

Data Sheet 1-28 and FM Global Loss Prevention Data Sheet 1-29.<br />

2. Provide roof assembly meeting requirements of UL 1256 for Flame Spread developed from<br />

underside of deck and roof assembly meeting requirements of FM Approvals Standard 4450 for<br />

Class 1 Insulated Steel Deck Roofs (construction materials calorimeter).<br />

2.4 ROOFING SYSTEMS<br />

A. Single Ply Mechanically Attached TPO Membrane Roofing System. Subject to compliance with<br />

requirements, provide one of the following products:<br />

1. Sure-Weld Roofing System by Carlisle.<br />

2. UltraPly TPO Roofing System by Firestone.<br />

3. JM TPO Mechanically Fastened Roofing System by Johns Manville.<br />

B. Substitutions: Comply with the requirements of Section 01600.<br />

2.5 ROOF MEMBRANE<br />

A. Roof Membrane: Single ply membrane composed of thermoplastic polyolefin (TPO) sheet as specified for<br />

the specific product hereinbefore and reinforced with polyester scrim conforming to ASTM D 6878.<br />

1. Membrane Type: Reinforced, 60 mil thickness, white U.N.O., 10 ft. maximum sheet width.<br />

B. Flashing Membrane: Reinforced and non-reinforced TPO membrane and pressure-sensitive flashing by<br />

Roofing System manufacturer, thickness to match roofing membrane, specifically designed for use in<br />

flashing at perimeters and around projections through roofing system.<br />

2.6 FIRE RESISTIVE UNDERLAYMENT<br />

A. Manufacturer: Georgia-Pacific, (800) 284-5347 http://www.gp.com/BUILD/index.aspx<br />

B. Underlayment: UL listed Class A (UL 790), ¼” thick DensDeck® board over wood deck, for Class I Roofing<br />

System.<br />

1. Flame spread 0, smoke developed 0, when tested in accordance with ASTM E84; noncombustible when<br />

tested in accordance with ASTM E136.<br />

C. No Substitutions.<br />

D. Refer to Drawings for UL assembly design number, details, and additional information.<br />

07500 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.7 WATERPROOFING MEMBRANE<br />

A. At Contractor’s option, use TPO or EPDM waterproofing membrane and flashing as specified below.<br />

B. TPO System:<br />

1. Waterproofing Membrane: Membrane waterproofing composed of thermoplastic polyolefin<br />

(TPO) formed into uniform, flexible sheets by Roofing System manufacturer, thickness to match<br />

roof membrane.<br />

2. Waterproofing Flashing: Reinforced and non-reinforced TPO membrane and pressure-sensitive<br />

flashing by Roofing System manufacturer, thickness to match membrane, specifically designed for<br />

use in flashing at perimeters and wall, and around projections through roofing system.<br />

C. EPDM System:<br />

1. Waterproofing Membrane: Unreinforced cured single ply membrane composed of ethylene<br />

propylene diene monomer (EPDM) sheet as specified for the specific product hereinbefore.<br />

a. Membrane Type: 60 mil thickness, black.<br />

2. Waterproofing Flashing: Reinforced and non-reinforced EPDM membrane and pressure-sensitive<br />

flashing by roofing system manufacturer, thickness to match membrane, specifically designed for<br />

use in flashing at wall.<br />

2.8 ROOF INSULATION<br />

A. Isocyanurate Foam Insulation: Polyisocyanurate board insulation, ASTM C 1289, Type II, felt or glassfiber<br />

mat facer on both major surfaces, with an LTTR (Long Term Thermal Resistance) value of 17.2 based<br />

on ASTM C 1303.<br />

1. Subject to compliance with requirements, provide one of the following products:<br />

a. HPH by Carlisle.<br />

b. ISO 95+ GL, by Firestone.<br />

c. E'NRG'Y 3 or ISO 3 by Johns Manville.<br />

d. Products meeting the specified requirements by other manufacturers as recommended by<br />

the roofing membrane manufacturer.<br />

2. Thickness: 2.8 inches min.<br />

B. Prefabricated EPS Tapered Insulation: Rigid expanded polystyrene (EPS) foam insulation, ASTM C 578,<br />

Type VIII (1.15 pcf minimum) or Type II (1.5 pcf minimum), flame retardant additive, with an LTTR<br />

(Long Term Thermal Resistance) value of 20.0 based on ASTM C 1303.<br />

1. Provide products meeting the specified requirements by one of the manufacturers specified above<br />

as applicable.<br />

C. Roof Curb Insulation: Polyisocyanurate Foam; both faces covered with glass fiber felt; thickness to match<br />

wood nailer.<br />

2.9 COVER BOARD<br />

A. Cover Board for Application over Prefabricated EPS Tapered Insulation: Glass-mat, water-resistant<br />

gypsum roof board, 1/4 inch thick conforming to ASTM C 1177.<br />

1. Product: Dens Deck Roof Board by Georgia-Pacific.<br />

2.10 ROOF PENETRATION FLASHING AND SEALS<br />

A. Molded Pipe Flashing: Pre-molded flexible pipe flashing as recommended and supplied by the roofing<br />

manufacturer.<br />

B. Urethane Rubber Seal System: Manufacturer’s standard elastomeric pourable sealer pockets including<br />

two-part pourable urethane sealer.<br />

07500 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.11 ACCESSORIES<br />

A. Provide accessories as shown on the drawings and manufacturer’s system accessories for a complete and<br />

warranted Roofing System, including, but not limited to, the following:<br />

1. Weathered Membrane Cleaner.<br />

2. Lap Sealant.<br />

3. Bonding Adhesive.<br />

4. Membrane Fasteners.<br />

5. Termination Bar.<br />

6. Insulation Fasteners.<br />

7. Walkway / Isolation Pads.<br />

8. Preformed Accessories including pipe flashings.<br />

9. Preformed Corner Patching.<br />

10. Draw Bands.<br />

11. Foam Filler Insulation: Polyurethane Expanding Foam as specified in Section 07900.<br />

12. Pressure-sensitive Flashing.<br />

13. Primer.<br />

14. Insulation and Membrane Fasteners.<br />

15. In-seam Plates.<br />

16. Splice Tape.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify wood deck is clean and smooth, free of depressions, waves, or projections, properly sloped to drains,<br />

valleys, and eaves. Defects in the substrate surface shall be reported and documented.<br />

B. Verify roof openings, curbs, pipes, sleeves, ducts, or vents through roof are solidly set, cant strips, nailing<br />

strips, and reglets are in place. Verify deck is supported and tightly secured.<br />

C. Verify deck surfaces are dry and free of water, snow, and ice.<br />

3.2 PREPARATION<br />

A. Provide covers and other means of protection as necessary to protect building surfaces against damage<br />

during roofing work.<br />

B. Where Work shall continue over finished roof membrane, protect roof system from damage.<br />

3.3 INSTALLATION<br />

A. Comply with membrane roofing system and insulation manufacturer's written instructions for installing<br />

roof insulation.<br />

3.4 ROOF INSULATION INSTALLATION<br />

A. Insulation over Wood Deck: Lay Polyisocyanurate board insulation units over DensDeck® board, with end<br />

joints staggered, per manufacturer’s published instructions. Mechanically fasten insulation, through<br />

DensDeck® board to wood deck with FM approved fasteners in accordance with requirements of FM.<br />

1. In no case shall the number of fasteners be less than indicated in approved submittals.<br />

B. Lay insulation boards to moderate contact without forcing joints. Cut insulation to fit neatly around<br />

protrusions through roof. At parapet walls, cope insulation around protrusions and embed plates; butt tight<br />

to wall, sealing conditioned building.<br />

1. Fill gaps over 1/4 inch wide with Foam Filler Insulation. After foam sets and before installation<br />

of membrane, trim foam flush with insulation surface.<br />

07500 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Tapered Insulation: Install tapered insulation in accordance with manufacturer’s instructions and the<br />

following:<br />

1. Skylight Saddles: Install prefabricated EPS tapered insulation to achieve slope as shown on<br />

Drawings but not less than 1/4 inch per foot finished slope.<br />

a. Install cover boards over insulation. Loosely butt cover boards together and fasten to<br />

roof deck.<br />

2. Mechanical Unit Crickets and Saddles: Install field-fabricated tapered isocyanurate foam<br />

insulation to achieve slope as shown on Drawings but not less than 1/4 inch per foot finished<br />

slope.<br />

3. Roof Counterslope: Where tapered insulation is indicated to counter roof slope, install fieldfabricated<br />

tapered isocyanurate foam insulation to achieve 1/4 inch per foot min. finished slope.<br />

4. Edge Taper Insulation: Adjacent to gutter assembly, slope field-fabricated tapered isocyanurate<br />

foam insulation at minimum rate of 1/2 inch per foot. Provide insulation having a starting<br />

thickness of one inch, tapering insulation up to match nominal roof insulation thickness.<br />

D. Apply no more insulation than can be sealed with membrane in same day.<br />

E. Adhere a single layer of insulation to manufactured metal curbs with bonding cement.<br />

3.5 ROOF MEMBRANE INSTALLATION<br />

A. Mechanically Fastened Membrane:<br />

1. Unroll membrane over prepared wood deck substrate, lapping adjoining sheets as recommended<br />

by manufacturer.<br />

2. Mechanically fasten membrane using manufacturer's fastening system. Install fasteners in<br />

accordance with submitted engineered layout pattern to resist specified wind uplift.<br />

3. Install fasteners using drill depth sensing or torque limiting screw guns to limit under / over drive<br />

of fasteners. Drill motors and other non-limiting drivers shall not be used.<br />

4. Seam Sealing: Heat-weld seams according to the system manufacturer’s recommendations, and<br />

with a minimum weld width of 1-1/2 inches.<br />

B. Cold Weather Application Procedures: When air temperature is expected to fall below 40 degrees F,<br />

follow Cold Weather Application Procedures as follows:<br />

1. Store materials in heated storage units prior to installation. Rotate adhesive, cement, and sealant<br />

containers to maintain their temperature above 40 degrees F.<br />

2. Allow membrane to relax until no wrinkles are visible.<br />

3. Allow adequate time for solvents in cements to flash off. Check dryness of applied cements<br />

before sealing joints.<br />

4. Verify that frost, dew, and other forms of moisture have evaporated prior to covering insulation<br />

with membrane to prevent entrapment of moisture within finished roof system.<br />

3.6 WATER CUTOFFS AND WEATHER PROTECTION<br />

A. Install water cut-offs at end of day's operation to seal insulation and edge of roof membrane from moisture<br />

entry. If inclement weather appears imminent during roofing application, cease operations and protect<br />

deck, insulation, flashings, penetrations and membrane from moisture infiltration with water cutoffs.<br />

Insulation and roofing materials not so protected prior to inclement weather will be considered damaged<br />

and will be cause for rejection.<br />

B. Remove water cut-offs and other temporary weather protections prior to continuing roofing work. Remove<br />

materials that have been subject to moisture damage and return deck to a clean, dry condition before<br />

proceeding with roofing operations. Remove damaged materials from job site.<br />

C. The water cut-offs and weather protection shall not be considered a part of the final roof system specified.<br />

07500 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.7 FLASHING MEMBRANE AND ACCESSORIES INSTALLATION<br />

A. Flashing Membrane: Apply flexible flashings to seal membrane to vertical elements using manufacturer's<br />

standard peel and stick flashing.<br />

1. Reinforced Flashing Membrane: Where conditions permit, flash penetrations and walls with<br />

reinforced flashing membrane.<br />

2. Uncured Flashing: Limit use of uncured flashing to overlay vertical seams as required at angle<br />

changes, to flash inside and outside corners, scuppers, and other penetrations or unusually shaped<br />

walls as approved by the manufacturer.<br />

B. Roof Penetrations:<br />

1. Molded Pipe Flashing: Install where configuration of penetration will permit.<br />

2. Urethane Rubber Seal System: Install where molded pipe flashing cannot be installed due to<br />

configuration of penetration. Install at locations shown including electrical penetrations, gas line<br />

penetrations, flues, and satellite dish location.<br />

a. Install per manufacturers application instructions.<br />

C. Seal flashings and flanges of items penetrating membrane.<br />

D. Fasten termination bars at 12 inches on center or less to maintain constant compression.<br />

E. Isolation Pads: Install isolation pads at pipe supports.<br />

F. Walkway Pads: Install walkway pads as shown on Drawings. Maximum pad section length shall be 10 ft<br />

with three inch spacing between pad sections, unless indicated otherwise on Drawings. Adhere pads to<br />

roofing system to prevent displacement in maximum anticipated design wind velocity and to allow<br />

drainage of moisture from beneath pads. Install pads to allow roof surface drainage without ponding water.<br />

Install pads after adjacent equipment installation.<br />

3.8 WATERPROOFING MEMBRANE INSTALLATION<br />

A. Waterproofing Membrane: Install waterproofing membrane to be fully adhered to parapet using bonding<br />

adhesive as recommended by membrane manufacturer. Run membrane waterproofing over top of parapet<br />

and turn down front side of parapet 3 inches.<br />

1. Provide continuous weather tight seal from 3 inches below parapet cap, over parapet, down<br />

interior face, and onto roof surface.<br />

2. Conceal adhesive on exterior face of parapet with waterproofing.<br />

3. When EPDM waterproofing membrane is used, lap waterproofing membrane over roof membrane<br />

and secure with splice tape and pressure sensitive flashing as indicated on Drawings and as<br />

recommended by roofing system manufacturer.<br />

3.9 WATERPROOFING FLASHING INSTALLATION<br />

A. Waterproofing Flashing: Apply waterproofing flashing to seal membrane to vertical elements using<br />

manufacturer's peel and stick flashing.<br />

B. Comply with the following requirements when using TPO waterproofing flashing:<br />

1. Reinforced Waterproofing Flashing: Where conditions permit, flash walls with reinforced<br />

waterproofing flashing or as required by the manufacturer.<br />

2. Uncured Flashing: Limit use of uncured flashing to overlay vertical seams as required at angle<br />

changes, to flash inside and outside corners, scuppers, and other penetrations or unusually shaped<br />

walls where use of reinforced waterproofing flashing is not practical or as required by the<br />

manufacturer.<br />

07500 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.10 INTERFACE WITH OTHER WORK<br />

A. Coordinate Work with installation of associated metal counterflashings specified under other sections as the<br />

Work of this Section proceeds.<br />

B. Complete installation of base flashing at roof curbs prior to setting roof top equipment.<br />

3.11 FIELD QUALITY CONTROL<br />

A. Roofing Inspection:<br />

1. The Owner’s Independent Roofing Inspector (IRI) will conduct roof construction inspections at no<br />

cost to the Contractor. The IRI shall be the responsible person in charge of overall supervision<br />

and implementation of Roof Observation Program in accordance with Section 01458. Inspection<br />

includes the following:<br />

a. Training and supervision of CTL Roofing Technicians.<br />

b. Site visits during the roof installation at least once and as many times as necessary to<br />

ensure adequate observations and proper installation.<br />

c. Field reports.<br />

d. Periodic roof installation observation.<br />

e. Field testing recommendations.<br />

f. Oversight of remedial repairs in the field.<br />

g. Administration and maintenance of the online Wal-Mart Observation Log with respect to<br />

roofing defects and repairs.<br />

h. Verification of completion of magnetic sweeping prior to Grand Opening.<br />

i. Conducting comprehensive roof inspection upon completion of roofing together with all<br />

parties to be signators to Roof Inspection Checklist.<br />

j. Issuance of Certification of Quality of Roof Construction upon completion of roof<br />

installation.<br />

k. Full time observation during inspection, removal, and replacement of existing roof.<br />

2. The activities and responsibilities of the IRI shall not preclude any quality control responsibilities<br />

by the Contractor, the Roofing Contractor, or the Manufacturer as specified herein.<br />

3. The Contractor shall be responsible for sampling and testing specified herein.<br />

4. The Roof Inspection Checklist included herein shall be used by the Contractor as a tool to measure<br />

quality roofing work as the work progresses.<br />

B. Core samples shall be taken only when required to evaluate problems observed during quality-assurance<br />

inspections of roofing membrane as follows:<br />

1. Sample cutting and patching shall be by and at the expense of the Contractor.<br />

2. Cut samples shall be taken when and as recommended by the IRI, and approved by the Wal-Mart<br />

Construction Manager, when determined necessary for quality assurance validation or to<br />

determine the extent of deficiencies discovered during construction or during final roofing<br />

inspection. Except where cut samples are taken to investigate deficiencies, no more than two cut<br />

samples per 100 squares or one cut sample from each day's work shall be required. Cut samples at<br />

locations identified by the IRI.<br />

3. Submit core samples to the IRI for examination. Deficiencies shall be reported by the IRI.<br />

C. Manufacturer Services:<br />

1. Provide site inspection and reports by Manufacturer's Technical Representative at the following<br />

periods:<br />

a. After 30% but prior to 50% of roof installation.<br />

b. At 100% completion of roof installation.<br />

c. Final Inspection: Two weeks prior to Grand Opening.<br />

2. Inspection shall conform to the inspection requirements specified herein.<br />

3. Prepare Certificate of Acceptance of completed roof installation by the Manufacturer.<br />

4. Perform a final audit 10 months after acceptance with Wal-Mart representative as scheduled by<br />

Wal-Mart.<br />

07500 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.12 CLEANING<br />

A. Replace defaced or disfigured finishes caused by Work of this Section.<br />

B. One week prior to Grand Opening, sweep entire roof surface with a magnetic sweeper to remove nails,<br />

screws and other metal items which may cause subsequent damage to the roof.<br />

3.13 PROTECTION<br />

A. Where construction traffic must continue over finished roof installation, protect roof surfaces as<br />

recommended by roofing system manufacturer to protect manufacturer's warranty.<br />

3.14 MAINTENANCE AND REPAIR DURING CONSTRUCTION<br />

A. Maintain roofing system and related work from time of roofing completion until store Grand Opening.<br />

Repair material or installation defects or damage resulting from any subsequent work on the roof or from<br />

any weather-related damage. Maintain roof system in watertight condition including repair of conditions<br />

that show signs of inferior workmanship that may result in potential leaks. Repair leaks occurring prior to<br />

Grand Opening in accordance with good roofing practice and the requirements specified herein. Remove<br />

and replace wet insulation caused by water leaks and repair the roofing system.<br />

END OF SECTION<br />

07500 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 07500<br />

MEMBRANE ROOFING<br />

Project Location:<br />

Date:<br />

(City)<br />

(State)<br />

Project Number:<br />

Store Number:<br />

Regulatory Requirements for Roof Assembly: The roof assembly meets the following FM & UL requirements:<br />

Roof assembly meets Class 1A-90 requirements for fire resistance and wind uplift in accordance with FM<br />

Approvals Standard 4470 and FM Global Loss Prevention Data Sheet 1-28 and FM Global Loss Prevention<br />

Data Sheet 1-29 (Insert UL Classification)<br />

Roof assembly meets Fire Classification UL 1256 for Flame Spread developed from underside of deck and<br />

meets approval standard of FM Standard 4450 for Class 1 Insulated Steel Deck.<br />

The following product has been selected for use in this project from the list of acceptable products specified.<br />

Quality Assurance: Roofing Applicator: In accordance with this specification, the applicator is qualified to install the<br />

indicated Roofing System.<br />

Carlisle SynTec Systems, Authorized Applicator<br />

Firestone Red Shield Licensed Contractor.<br />

Johns Manville Approved Roofing Contractors.<br />

Roofing System Manufacturer: Indicate System provided below:<br />

Single Ply TPO Membrane Roofing<br />

Sure-Weld Roofing System by Carlisle.<br />

UltraPly TPO Roofing System, by Firestone.<br />

JM TPO Mechanically Fastened Roofing System by Johns Manville.<br />

Roofing System Accessories: The following accessories are compatible with the indicated Roofing System Warranty.<br />

Sheet Seaming System:<br />

Cleaner: .<br />

Primer: .<br />

Lap Sealant: .<br />

Bonding Adhesive: ___________________________________________ .<br />

Mechanical Fasteners for Membrane:<br />

Manufacturer: .<br />

Termination Bar:<br />

Manufacturer: .<br />

Mechanical Fasteners for Insulation:<br />

Coated mechanical fasteners; proper length and acceptable for defined wind uplift.<br />

Manufacturer: .<br />

Walkway/Isolation Pads:<br />

Manufacturer: .<br />

Urethane Rubber Seal System:<br />

Manufacturer: .<br />

07500 - 11<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Molded Pipe Flashing:<br />

Manufacturer: .<br />

Draw Band: Stainless steel.<br />

Roof Insulation: Check insulation system and those products to be provided; give thicknesses.<br />

Insulation Boards: Indicate boards used in insulation assembly:<br />

Isocyanurate Foam Insulation:<br />

HPH, by Carlisle:<br />

Thickness: .<br />

ISO 95+ GL by Firestone:<br />

Thickness: .<br />

E'NRG'Y 3 or ISO 3 by Johns Manville:<br />

Thickness: .<br />

Other: ______________________________:<br />

Thickness: .<br />

Roof Curb Insulation:<br />

Polyisocyanurate Foam:<br />

Thickness: .<br />

Tapered Roof Insulation:<br />

EPS Insulation: ____________________________________.<br />

Brand name and manufacturer of EPS<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 - Contract<br />

Closeout. The undersigned hereby declares that the Product identified above by manufacturer's name and model number is<br />

(one of) the product(s) specified and is suitable for the intended use as defined within the Contract Documents and has been<br />

provided and placed in operational condition in accordance with the manufacturer's published instructions and the Contract<br />

Documents.<br />

SUPPLIER:<br />

(Contact name of supplier offering above product)<br />

Phone Number: ( )<br />

(Supplier name and address)<br />

SUBCONTRACTOR:<br />

(Contact name of subcontractor offering above product)<br />

Phone Number: ( )<br />

(Subcontractor name and address)<br />

CONTRACTOR:<br />

(Contact name of Contractor)<br />

(Contractor signature and Title of Signatory)<br />

07500 - 12<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


ROOFING SYSTEM WARRANTY<br />

Owner:<br />

Address of Owner:<br />

Type and Name of Building:<br />

Location:<br />

Roofing System Specification Number:<br />

Date of Store Grand Opening:<br />

Manufacturer’s 24 hour Emergency Telephone: (____)<br />

Area of Roof System:<br />

Date Warranty Expires:<br />

(no answering machines or message Center)<br />

Contact Name:<br />

Contractor’s Telephone: (_______)<br />

(no answering machines or message center)<br />

Contact Name:<br />

Upon completion of and after inspection by the Manufacturer of such Work, Manufacturer agrees to warrantee the aforesaid<br />

Roofing System for a limited period and subject to the conditions herein set forth:<br />

Manufacturer Warrantees, subject to the conditions herein set forth, that during a period of 15 years from the date of store<br />

Grand Opening, it will, at its own cost and expense, make or cause to be made such repairs to said Roofing System resulting<br />

solely from faults or defects in materials and/or workmanship applied by or through the Roofing System Contractor as may<br />

be necessary to maintain said Roofing system in watertight condition. Owner’s remedies and manufacturer’s liability shall<br />

include cost of labor and materials for loss of weather tightness without financial limit. In accordance with good roofing<br />

practice, the Manufacturer shall remove and replace all wet insulation (as defined in specifications) caused by water leaks<br />

covered under this Warranty (i.e. leaks resulting from circumstances other than those listed in the exclusions) and repair the<br />

Roofing System at no cost to the Owner. Should the investigation reveal that the leak is the result of something other than a<br />

defect in materials and/or workmanship applied by or through the Roofing System Contractor, the reasonable investigative<br />

work and reasonable repair costs shall be paid by the Owner. Failure by the Owner to pay these costs shall render this<br />

warranty null and void.<br />

Warranty shall include materials and workmanship from the following items:<br />

1. Membranes (including parapet waterproofing).<br />

2. Membrane flashings including attachment to sheet metal flashings and trim.<br />

3. Fasteners, cements, and adhesives.<br />

This warranty is made subject to the following conditions:<br />

1. The Owner shall notify Manufacturer within 24 hours of notice by the Wal-Mart Roof Maintenance Department of leaks.<br />

The Manufacturer will respond with service within 24 hours of notice from owner (if not possible, than no later than 48<br />

hours, however Wal-Mart retains the right to make repairs at Warrantor’s expense to mitigate damages).<br />

2. Specifically excluded from this Warranty is any and all damage to said roof system, the building, or contents caused by<br />

natural disasters, including, but not limited to: earthquake, hail, lightning, hurricane, tornado, strong gale wind force (72<br />

MPH or greater), or structural failure of the building or of the roof deck (as defined by a licensed Structural Engineer and<br />

except that caused by the Manufacturer), fire, and acts of war. If the roof system is damaged by reason of any of the<br />

foregoing, this warranty shall become null and void (AFFECTED AREAS ONLY) for the balance of the warranty period<br />

unless such damage is repaired at the expense of the owner.<br />

3. Manufacturer is not liable for consequential damages to the building or contents resulting from any defects in said roof<br />

system, including, but without limitation, any interruption of business experienced by Owner or occupants of the<br />

building.<br />

07500 - 13<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. All additions and/or alterations to the roof system shall be installed in accordance with the manufacturer’s written<br />

recommendations and the manufacturer should provide prior to acceptance to said additions or alterations. Should<br />

unauthorized additions/alterations be discovered by the Wal-Mart Roof Maintenance Department, the manufacturer will<br />

be notified in writing within fourteen days of such discovery. Provide at manufacturer’s discretion an inspection of the<br />

unauthorized additions/alterations and notify the Owner in writing of any remedy required by the manufacturer within<br />

fourteen days. This Installation/Inspection by the Manufacturer is to be done at a cost to Owner of not more than $500.00<br />

to cover travel and time for the inspector. Provide inspection of said roof during business hours. Failure to notify the<br />

Owner of any required remedy shall deem the addition/alteration acceptable to the Manufacturer and the warranty will<br />

remain in effect.<br />

5. The area of additions and/or alterations shall be the only area of the roof system where warranty is suspended. All other<br />

roof system areas will have continual coverage under the roof warranty.<br />

6. This Warranty is transferable within the 15-year warranty period, subject to Manufacturer’s inspection, written approval<br />

and transfer fee payment.<br />

7. During the term of this warranty, the manufacturer, its agents and employees, shall have free and unlimited access to the<br />

roof during the hours of store operation.<br />

8. The terms and conditions of this warranty are controlling. Any other warranty conditions attached or referenced that are<br />

in conflict with this warranty are ineffective and invalid.<br />

9. This limited warranty shall be governed and construed in accordance with the laws of the State of Arkansas without<br />

regard to conflict of laws.<br />

10. The Manufacturer does not warrant products incorporated or utilized in this installation that it has not furnished. The<br />

Manufacturer specifically disclaims liability under any theory of law arising out of the installation or performance of, or<br />

damages sustained by or caused by, products not furnished by the Manufacturer.<br />

IN WITNESS WHEREOF, this instrument has been duly executed this ____day of ____________, _____________.<br />

__________________________________<br />

By ____________________________________<br />

END OF WARRANTY<br />

07500 - 14<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


ROOF INSPECTION INSTRUCTIONS<br />

TOOLS AND SUPPLIES: Provide the following during inspections:<br />

• Copy of roof plan and copy and specifications.<br />

• Tape measure, metal thickness gauge, paint for marking defects on roof, roof coring tools and repair materials, and<br />

seam probe (to be supplied by Roofing Contractor).<br />

INSPECTION PROCEDURE<br />

• Owner’s Independent Roofing Inspector shall arrange and conduct inspection and complete checklist and identify<br />

defects.<br />

• All undersigned parties shall accompany inspection.<br />

• Inspect underside of decking from inside of building for proper insulation fastener spacing and sheet fastener<br />

spacing.<br />

• Roof Inspection shall start at the parapet wall on the GM side of the building, at the back corner.<br />

• Proceed around perimeter, (including Auto Center, Garden Center, etc).<br />

• Continue across front wall and down sidewall at GR.<br />

• Inspect all metal flashings, base and wall flashings, perimeter attachments, perimeter membrane sheet layout,<br />

parapet waterproofing membrane, and all accessories.<br />

• Inspect condition of paint on exterior walls. Inspect CMU for proper paint coverage.<br />

• Inspect all painted metals for proper coverage.<br />

• Inspect back wall gutter or internal drainage system.<br />

• Inspect field of roof system, beginning approx. 10' from back wall, walking side to side of building.<br />

• Inspect roof area no more than 10 feet on each side of walking paths, from back, to front of building.<br />

• Inspect all checklist items at field seams, flashings, RTUs, mechanical equipment, skylights, refrigeration units, gas<br />

lines, expansion joints, crickets, walkpads, and other roof accessories.<br />

• Mark defects on roof by paint markings and identify each defect using corresponding defect number.<br />

• After roof inspection is complete FAX signed inspection form to Wal-Mart Construction Manager within 24 hours.<br />

COMPLETION OF CHECKLIST AND DEFECTS FORM<br />

• Answer each checklist item Yes or No.<br />

• Mark “N/A” on checklist items which do not apply.<br />

• Identify defects on the Wal-Mart Observation Log. (www.bldgportal.com, enter username and password, select<br />

Observation Log)<br />

• Number each defect as follows:<br />

o Identification Symbol-Checklist Item No.-Defect No. (E.g. MF-1-3)<br />

o Identification symbol and checklist item number shall correspond to the Roof Inspection Checklist. The<br />

defect number shall be numbered in sequence for each checklist item.<br />

• Complete all applicable information in the Observation Log including the resolution of each item.<br />

07500 - 15<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


ROOF INSPECTION CHECKLIST<br />

(GI) GENERAL:<br />

1. Is specified roof system installed? YES___ NO___ N/A___<br />

2. Is construction materials, trash, and other debris removed from the roof? YES___ NO___ N/A___<br />

3. Are all punch list items addressed and signed off? YES___ NO___ N/A___<br />

4. Is there any visible physical damage to roof? YES___ NO___ N/A___<br />

5. Are RTU's numbered so they can be seen from the roof hatch? YES___ NO___ N/A___<br />

6. Is roof hatch painted? YES___ NO___ N/A___<br />

7. Is there roofing mastic or other foreign substance on roof membrane? YES___ NO___N/A___<br />

(MF) MECHANICAL FASTENERS: (Check from inside building)<br />

1. Is insulation attachment pattern installed per manufacturers required spacing and pattern? YES___ NO___N/A___<br />

2. Is membrane sheet attachment in the seams at minimum 12” inches o.c.<br />

or per manufacturers required spacing? YES___ NO___N/A___<br />

3. Are all seams mechanically attached? YES___ NO___N/A___<br />

(PF) PERIMETER WALL FLASHING<br />

Metal Flashing Types (Check all that apply)<br />

[ ] Embedded edge metal<br />

[ ] Metal cap flashing<br />

[ ] Wall/Parapet<br />

[ ] Coping<br />

[ ] Other<br />

[ ] Pre-finished metal<br />

[ ] Painted metal. Paint condition:<br />

1. Is edge metal fascia attached with fastener spacing at 3” o.c. staggered? YES___ NO___N/A___<br />

2. Is edge metal fascia continuously attached to the cleat? YES___ NO___N/A___<br />

3. Is edge metal lapped a minimum of 4”? YES___ NO___N/A___<br />

4. Are laps sealed? YES___ NO___N/A___<br />

5. Is edge metal properly stripped into roof system? YES___ NO___N/A___<br />

6. Is metal sealed at the flashing? YES___ NO___N/A___<br />

7. Is metal coping fastened with neoprene gasket fasteners at 12” o.c.? YES___ NO___N/A___<br />

(PW) PARAPET WALL MEMBRANE<br />

1. Is membrane fully adhered in all areas to the parapet walls? YES___ NO___N/A___<br />

2. Are there any voids, wrinkles, or disbonded areas? YES___ NO___N/A___<br />

3. Is termination bar installed at the base flashing? YES___ NO___N/A___<br />

4. Is base flashing run onto the roof membrane and seam sealant used? YES___ NO___N/A___<br />

5. Are corner flashings installed? YES___ NO___N/A___<br />

6. Are there any open seams? YES___ NO___N/A___<br />

7. Is membrane terminated and sealed at parapet end wall conditions? YES___ NO___N/A___<br />

8. Are all parapet end walls fully painted or flashed? YES___ NO___N/A___<br />

(PA) PERIMETER MEMBRANE SHEETS ATTACHMENT<br />

1. Are the required number perimeter sheets per system specification installed? YES___ NO___N/A___<br />

2. Are fasteners spaced per the manufacturers requirements? YES___ NO___N/A___<br />

3. Are T-Lap patches installed at all T-joints? YES___ NO___N/A___<br />

4. Are seams properly sealed? YES___ NO___N/A___<br />

(EW) EXTERIOR WALL PAINT (Inspect every 25’ minimum.)<br />

1. Is wall painted/sealed? YES___ NO___N/A___<br />

2. Are there visible voids in the paint? YES___ NO___N/A___<br />

3. Are there cracks in blocks or open mortar joints? YES___ NO___N/A___<br />

4. Are walls painted behind downspouts? YES___ NO___N/A___<br />

07500 - 16<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


DRAINAGE SYSTEM (Check all that apply)<br />

[ ] Gutters and downspouts<br />

[ ] Interior drains [ ] Overflow drains [ ] Overflow scuppers<br />

[ ] Scuppers with leaders & downspouts [ ] Overflow scuppers<br />

Specified gauge (Check all areas with gauge)<br />

• Main roof area gauge<br />

• Auto Center gauge<br />

• Garden Center gauge<br />

• Receiving gauge<br />

• Other gauge<br />

(GD) GUTTERS AND DOWNSPOUTS<br />

1. Is specified type of metal installed? YES___ NO___N/A___<br />

2. Is gutter sized as indicated on the drawings? YES___ NO___N/A___<br />

3. Is gutter holding water? YES___ NO___N/A___<br />

4. Is gutter painted inside? YES___ NO___N/A___<br />

5. Are gutter straps installed every 36” o.c.? YES___ NO___N/A___<br />

6. Are gutter expansion joints installed every 40’ maximum? YES___ NO___N/A___<br />

7. Are gutter outlets soldiered to the gutter? YES___ NO___N/A___<br />

9. Are gutter brackets installed every 36” o.c.? (Inspect from the ground level) YES___ NO ___N/A___<br />

10. Are downspouts the specified size and configuration? YES___ NO___N/A___<br />

11. Are downspout straps installed at top, center, and bottom? YES___ NO___N/A___<br />

12. Are downspouts spaced as called out in the documents? YES___ NO___N/A___<br />

13. Are splash blocks installed? YES___ NO___N/A___<br />

14. Are downspouts properly tied to the storm sewer? YES___ NO___N/A___<br />

15. Are joints in gutter leaking? YES___ NO___N/A___<br />

16. Are outlets in gutter leaking? YES___ NO___N/A___<br />

(RE) ROOF EDGE<br />

1. Is gravel guard properly installed? YES___ NO___N/A___<br />

2. Is gravel guard properly stripped into roof system? YES___ NO___N/A___<br />

3. Is gravel guard prefinished or painted? YES___ NO___N/A___<br />

4. Is gravel guard nailed at 3”o.c. staggered? YES___ NO___N/A___<br />

6. Is roof edge ponding water? YES___ NO___N/A___<br />

(DR) INTERIOR DRAINS<br />

1. Are roof drains the specified diameter? YES___ NO___N/A___<br />

2. Are overflow drains the specified diameter? YES___ NO___N/A___<br />

3. Does the roof drain outlet diameter match the diameter of the leader pipe? YES___ NO___N/A___<br />

4. Is roof membrane properly trimmed inside the roof drain? YES___ NO___N/A___<br />

5. Is roof drain free of debris and draining properly? YES___ NO___N/A___<br />

6. Is insulation tapered around the roof drains? YES___ NO___N/A___<br />

7. Are roof drains checked for leaks inside the store? YES___ NO___N/A___<br />

9. Are roof drain strainers in place? YES___ NO___N/A___<br />

10. Does ponding exist? YES___ NO___N/A___<br />

(SC) SCUPPERS<br />

1. Are scuppers the specified height and width? YES___ NO___N/A___<br />

2. Are scuppers located directly in line with the primary and over flow drains? YES___ NO___N/A___<br />

3. Are scuppers flush with the roof? YES___ NO___N/A___<br />

4. Does ponding exist? YES___ NO___N/A___<br />

5. Is scupper box installed and sealed to the wall? YES___ NO___N/A___<br />

6. Are scuppers properly flashed to roof system? YES___ NO___N/A___<br />

07500 - 17<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


(JC) JIB CRANE<br />

1. Is jib crane located with unobstructed clear space below? YES___ NO___N/A___<br />

2. Is jib crane usable in a safe manner? YES___ NO___N/A___<br />

3. Is safety chain installed? YES___ NO___N/A___<br />

4. Is ladder safety chain installed? YES___ NO___N/A___<br />

5. Is GFI outlet installed within 6’ reach of the jib hoist arm? YES___ NO___N/A___<br />

6. Are walkway protection pads installed? YES___ NO___N/A___<br />

7. Is parapet door in place (on raised parapet projects)? YES___ NO___N/A___<br />

(RM) ROOF FIELD MEMBRANE:<br />

(Seams should be checked in random areas for proper seals and voids. No wrinkles in seams will be acceptable.)<br />

1. Is maximum width field sheet used? YES___ NO___N/A___<br />

2. Are all seams properly lapped and sealed? YES___ NO___N/A___<br />

3. Are T-lap patches in place at all T-Laps? YES___ NO___N/A___<br />

4. Are all edges of cut sheet sealed? YES___ NO___N/A___<br />

5. Are there wrinkles in any laps? YES___ NO___N/A___<br />

6. Does any ponding exist in roof area? YES___ NO___N/A___<br />

7. Is membrane shingled properly with the slope of the roof? YES___ NO___N/A___<br />

(RI) ROOF INSULATION<br />

1. Is insulation the specified thickness? (Verify by roof cores if necessary) YES___ NO___N/A___<br />

2. Are there visible gaps in the insulation boards? YES___ NO___N/A___<br />

3. Is there ponding along horizontal insulation joints? YES___ NO___N/A___<br />

4. Are there voids or missing insulation? YES___ NO___N/A___<br />

(RTU) ROOF TOP UNITS & REFRIGERATION UNITS FLASHINGS:<br />

1. Are base flashings fully adhered to curb? YES___ NO___N/A___<br />

2. Are corner flashings on curbs installed? YES___ NO___N/A___<br />

3. Are seams to roof membrane sealed with no voids or wrinkles? YES___ NO___N/A___<br />

4. Are crickets installed to divert water around unit? YES___ NO___N/A___<br />

5. Are counterflashings installed and properly attached? YES___ NO___N/A___<br />

6. Are walkpads installed as per the documents? YES___ NO___N/A___<br />

7. Are condensation P-traps installed on all units? YES___ NO___N/A___<br />

(SK) SKYLIGHTS:<br />

1. Are base flashings fully adhered to curb? YES___ NO___N/A___<br />

2. Are corner flashings on curbs installed? YES___ NO___N/A___<br />

3. Are seams to roof membrane sealed with no voids or wrinkles? YES___ NO___N/A___<br />

4. Are crickets installed to divert water around unit? YES___ NO___N/A___<br />

5. Are counterflashings installed and properly attached? YES___ NO___N/A___<br />

6. Are skylights attached to curbs at 12”o.c.? YES___ NO___N/A___<br />

7. Do screws have neoprene washers? YES___ NO___N/A___<br />

8. Are cracks visible in domes? YES___ NO___N/A___<br />

9. Is there moisture between domes? YES___ NO___N/A___<br />

10. Are any of the units damaged? YES___ NO___N/A___<br />

11. Are any of the corners open? YES___ NO___N/A___<br />

07500 - 18<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


(GL) GAS LINES:<br />

1. Are gas lines painted? YES___ NO___N/A___<br />

2. Is blocking spaced under line at 8’ o.c max.? YES___ NO___N/A___<br />

3. Is blocking located within 2’ of RTU? YES___ NO___N/A___<br />

4. Is blocking located within 1’-6” of each corner? YES___ NO___N/A___<br />

5. Are protection pads under each block? YES___ NO___N/A___<br />

6. Are protection pads the correct size and fully adhered? YES___ NO___N/A___<br />

7. Are pipe clamps correct sizes and installed per the documents? YES___ NO___N/A___<br />

8. Are gas pipe dirt legs touching roof? YES___ NO___N/A___<br />

(EJ) ROOF EXPANSION JOINTS<br />

1. Is expansion joint installed? YES___ NO___N/A___<br />

2. Is joint properly terminated at the parapet at the front? YES___ NO___N/A___<br />

3. Is joint properly terminated at the rear? YES___ NO___N/A___<br />

4. Is joint properly flashed to roof system? YES___ NO___N/A___<br />

5. Are there any open seams? YES___ NO___N/A___<br />

(MI) MISCELLANEOUS ITEMS<br />

1. Are soil stacks properly flashed and clamps installed? YES___ NO___N/A___<br />

2. Are roof jacks properly flashed and collars sealed? YES___ NO___N/A___<br />

3. Are protection pads under support? YES___ NO___N/A___<br />

07500 - 19<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


ATTENDED BY:<br />

GENERAL CONTRACTOR<br />

__________________________________________________<br />

__________________________________________________<br />

(Printed name and title)<br />

ROOFING CONTRACTOR<br />

__________________________________________________<br />

__________________________________________________<br />

(Printed name and title)<br />

MANUFACTURERS REP.<br />

__________________________________________________<br />

__________________________________________________<br />

(Printed name and title)<br />

WAL-MART CONST MGR.<br />

_________________________________________________<br />

_________________________________________________<br />

(Printed name and title)<br />

WAL-MART STORE MGR<br />

_________________________________________________<br />

_________________________________________________<br />

(Printed name and title)<br />

INDEPENDENT ROOFING INSPECTOR<br />

__________________________________________<br />

__________________________________________<br />

(Printed name and title)<br />

07500 - 20<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II - NP 062411<br />

SECTION 07525 (07 2726) – FLUID-APPLIED MEMBRANE AIR BARRIER<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Fluid applied, vapor permeable air barrier membrane system for installation on substrate behind<br />

exterior metal wall panels.<br />

B. Related Requirements:<br />

1. Section 07411 - Metal Wall Panels. Exterior wall panels under which air barrier is applied.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C 920 - Elastomeric Joint Sealants.<br />

2. ASTM C 1193 - Guide for Use of Joint Sealants.<br />

3. ASTM D 4258 - Practice for Surface Cleaning Concrete for Coating.<br />

4. ASTM D 4263 -Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method.<br />

5. ASTM E 162 - Test Method for Surface Flammability of Materials Using a Radiant Heat Source.<br />

6. ASTM E 1186 - Practice for Air Leakage Site Detection in Building Envelopes and Air Retarder Systems.<br />

1.3 DEFINITIONS<br />

A. Air Barrier Assembly: The collection of air barrier materials and auxiliary materials applied to exterior wall,<br />

including joints and junctions to abutting construction, to control air movement through the wall.<br />

B. QUALITY ASSURANCE<br />

C. Manufacturer’s Qualifications: Air barrier systems shall be manufactured and marketed by a firm with a minimum<br />

of 20 years experience in the production and sales of waterproofing and air barriers.<br />

D. Applicator Qualifications: A firm experienced in applying air barrier materials similar in material, design, and<br />

extent to those indicated for this Project, whose work has resulted in applications with a record of successful inservice<br />

performance.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Deliver materials and products in labeled packages. Protect products from damage due to sunlight, weather,<br />

excessive temperatures and construction operations.<br />

C. Do not double-stack pallets of fluid applied membrane components on the job site. Provide cover on top and all<br />

sides, allowing for adequate ventilation.<br />

D. Protect fluid-applied membrane components from freezing and extreme heat.<br />

07525 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 PROJECT CONDITIONS<br />

A. Environmental Limitations: Apply air barrier within the range of ambient and substrate temperatures<br />

recommended by air barrier manufacturer. Protect substrates from environmental conditions that affect<br />

performance of air barrier. Do not apply air barrier to a wet substrate or during snow, rain, fog, or mist.<br />

PART 2 - PRODUCTS<br />

2.1 AIR BARRIER<br />

A. Manufacturer and Product: Perm-A-Barrier VP as manufactured by Grace Construction Products, Cambridge,<br />

MA.<br />

B. Source Limitations: Obtain primary air-barrier material and through wall flashing through one source from a<br />

single manufacturer.<br />

C. Description: Air barrier shall be fluid-applied, fully-adhered, vapor-permeable, single component acrylic<br />

membrane air barrier.<br />

D. Performance Criteria: Air barrier shall be capable of performing as a continuous vapor-permeable air barrier and<br />

as a liquid-water drainage plane flashed to discharge to the exterior incidental condensation or water penetration.<br />

Air barrier assemblies shall be capable of accommodating substrate movement and of sealing substrate expansion<br />

and control joints, construction material changes, and transitions at perimeter conditions without deterioration and<br />

air leakage.<br />

2.2 AUXILIARY MATERIALS<br />

A. General: Auxiliary materials recommended by air barrier manufacturer for intended use and compatible with air<br />

barrier membrane. Liquid-type auxiliary materials shall comply with VOC limits of Authorities Having<br />

Jurisdiction.<br />

B. Liquid Membrane for Details and Terminations: Bituthene Liquid Membrane by Grace.<br />

C. Wall Primer (for Use with Throughwall Flashing and Tapes Applied to Substrate): Liquid waterborne primer.<br />

1. Product: Perm-A-Barrier WB Primer by Grace.<br />

D. Flexible Membrane Wall Flashing: 32 mils of self-adhesive rubberized asphalt integrally bonded to 8 mil of crosslaminated,<br />

high-density polyethylene film to provide a min. 40 mil thick membrane. Membrane shall be<br />

interleaved with disposable silicone-coated release paper until installed.<br />

1. Product: Perm-A-Barrier Wall Flashing by Grace.<br />

E. Joint Reinforcing Strip: Air barrier manufacturer's approved tape.<br />

F. Transition Membrane: 32 mils of self-adhesive rubberized asphalt integrally bonded to 8 mil of cross-laminated,<br />

high-density polyethylene film to provide a min. 40 mil thick membrane. Membrane shall be interleaved with<br />

disposable silicone-coated release paper until installed.<br />

1. Product: Perm-A-Barrier Wall Flashing Grace.<br />

G. Substrate Patching Membrane: Manufacturer's standard trowel-grade substrate filler.<br />

1. Product: Bituthene Liquid Membrane by Grace.<br />

H. Sprayed Polyurethane Foam Sealant: 1- or 2-component, foamed-in-place, polyurethane foam sealant, 1.5 to 2.0<br />

lb/cu. ft density; flame spread index of 25 or less according to ASTM E 162; with primer and noncorrosive<br />

substrate cleaner recommended by foam sealant manufacturer.<br />

I. Joint Sealant: ASTM C 920, single-component, neutral-curing silicone; Class 100/50 (low-modulus), Grade NS,<br />

Use NT related to exposure, and, as applicable to joint substrates indicated, Use O.<br />

07525 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.3 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine substrates, areas, and conditions, with installer present, for compliance with requirements and other<br />

conditions affecting performance.<br />

1. Verify that substrates are sound and free of oil, grease, dirt, excess mortar, or other contaminants.<br />

2. Verify that concrete has cured and aged for minimum time period recommended by air barrier<br />

manufacturer.<br />

3. Verify that concrete is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method<br />

according to ASTM D 4263.<br />

4. Verify that masonry joints are struck flush and completely filled with mortar.<br />

5. Proceed with installation only after unsatisfactory conditions have been corrected.<br />

3.2 SURFACE PREPARATION<br />

A. Refer to manufacturer’s literature for requirements for preparation of substrates. Surfaces shall be sound and free<br />

of voids, spalled areas, loose aggregate and sharp protrusions. Remove contaminants such as grease, oil and wax<br />

from exposed surfaces. Remove dust, dirt, loose stone and debris. Use repair materials and methods that are<br />

acceptable to manufacturer of the fluid-applied air barrier system.<br />

B. Exterior Sheathing Panels: Stabilize panels with corners and edges fastened with appropriate screws. Pre-treat<br />

board joints with 2-3 in. wide, manufacturer's recommended self-adhesive tape. Fill gaps greater than 1/4 in. with<br />

mastic or caulk, allowing sufficient time to fully cure before application of the tape and fluid applied air barrier<br />

system.<br />

C. Masonry Substrates: Apply air barrier over concrete block and brick with smooth trowel-cut mortar joints, struck<br />

full and flush. Fill voids and holes, particularly in the mortar joints, with a lean mortar mix, non-shrinking grout,<br />

or parge coat.<br />

D. Treat construction joints and install flashing as recommended by manufacturer.<br />

E. Clean, prepare, treat, and seal substrate according to manufacturer's written instructions. Provide clean, dust-free,<br />

and dry substrate for air barrier application.<br />

F. Mask off adjoining surfaces not covered by air barrier to prevent spillage and overspray affecting other<br />

construction.<br />

G. Remove grease, oil, bitumen, form-release agents, paints, curing compounds, and other penetrating contaminants<br />

or film-forming coatings from concrete.<br />

H. Remove fins, ridges, mortar, and other projections and fill honeycomb, aggregate pockets, holes, and other voids<br />

in concrete with substrate patching membrane.<br />

I. Remove excess mortar from masonry ties, shelf angles, and other obstructions.<br />

J. At changes in substrate plane, apply sealant or Bituthene Liquid Membrane at sharp corners and edges to form a<br />

smooth transition from one plane to another.<br />

K. Cover gaps in substrate plane and form a smooth transition from one substrate plane to another with stainless-steel<br />

sheet mechanically fastened to structural framing to provide continuous support for air barrier.<br />

07525 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 JOINT TREATMENT<br />

A. Concrete and Masonry: Prepare, treat, rout, and fill joints and cracks in substrate according to ASTM C 1193 and<br />

air barrier manufacturer's written instructions. Remove dust and dirt from joints and cracks complying with<br />

ASTM D 4258 before coating surfaces. Prime substrate as required.<br />

B. Gypsum Sheathing: Fill joints greater than 1/4 inch with sealant according to ASTM C 1193 and with air barrier<br />

manufacturer's written instructions. Apply tape to joint prior to installing fluid air barrier membrane.<br />

3.4 AIR BARRIER MEMBRANE INSTALLATION<br />

A. Apply air barrier membrane to achieve a continuous air barrier according to air barrier manufacturer's written<br />

instructions.<br />

B. Apply a continuous unbroken air barrier to substrates according to the following minimum thickness. Apply<br />

membrane in full contact around protrusions such as masonry ties.<br />

1. 90-mil wet film thickness, 45-mil dry film thickness.<br />

C. Do not cover air barrier until it has been tested and inspected by Owner's Construction Testing Laboratory.<br />

3.5 TRANSITION MEMBRANE INSTALLATION<br />

A. Install strips, transition membrane, and auxiliary materials according to air barrier manufacturer's written<br />

instructions to form a seal with adjacent construction and maintain a continuous air barrier.<br />

1. Coordinate the installation of air barrier with installation of roofing membrane and base flashing to ensure<br />

continuity of air barrier with roofing membrane.<br />

2. Install strip on roofing membrane or base flashing so that a minimum of 3 inches of coverage is achieved<br />

over both substrates.<br />

3. Install all flashings only after application of air barrier.<br />

B. Apply primer to substrates to receive transition membrane at required rate and allow to dry. Limit priming to<br />

areas that will be covered by transition tape in same day. Reprime areas exposed for more than 24 hours.<br />

1. Prime glass-fiber-surfaced gypsum sheathing not covered with air membrane material with number of<br />

prime coats needed to achieve required bond, with adequate drying time between coats.<br />

C. Connect and seal exterior wall air barrier membrane continuously to roofing membrane air barrier, concrete<br />

below-grade structures, floor-to floor construction, exterior glazing and window systems, storefront systems,<br />

exterior louvers, exterior door framing, and other construction used in exterior wall openings, using accessory<br />

materials.<br />

D. At end of each working day, seal top edge of strips and transition strips to substrate with termination mastic.<br />

E. Apply joint sealants forming part of air barrier assembly within manufacturer's recommended application<br />

temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges.<br />

F. Wall Openings: Prime concealed perimeter frame surfaces of storefronts, and doors. Apply transition strip so that<br />

a minimum of 3 inches of coverage is achieved over both substrates. Maintain 3 inches) of full contact over firm<br />

bearing to perimeter frames with not less than 1 inch of full contact.<br />

1. Transition Membrane: Roll firmly to enhance adhesion.<br />

G. Fill gaps in perimeter frame surfaces of windows, curtain walls, storefronts, and doors, and miscellaneous<br />

penetrations of air barrier membrane with foam sealant.<br />

H. Repair punctures, voids, and deficient lapped seams in strips and transition strips. Slit and flatten fishmouths and<br />

blisters. Patch with transition strips extending 6 inches beyond repaired areas in strip direction.<br />

07525 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.6 FIELD QUALITY CONTROL<br />

A. Unless otherwise specified, quality control tests and inspection specified below will be conducted by the Owner’s<br />

Construction Testing Laboratory at no cost to the Contractor in accordance with Section 01458. The Contractor<br />

shall perform additional testing or inspection as considered necessary by the Contractor for assurance of quality<br />

control.<br />

B. Inspections: Air barrier materials and installation are subject to inspection for compliance with requirements.<br />

Inspections may include the following:<br />

1. Continuity of air barrier system has been achieved throughout the building envelope with no gaps or holes.<br />

2. Continuous structural support of air barrier system has been provided.<br />

3. Masonry and concrete surfaces are smooth, clean and free of cavities, protrusions, and mortar droppings.<br />

4. Site conditions for application temperature and dryness of substrates have been maintained.<br />

5. Maximum exposure time of materials to UV deterioration has not been exceeded.<br />

6. Surfaces have been primed, if applicable.<br />

7. Laps in strips and transition strips have complied with minimum requirements and have been shingled in<br />

the correct direction (or mastic has been applied on exposed edges), with no fishmouths.<br />

8. Termination mastic has been applied on cut edges.<br />

9. Strips and transition strips have been firmly adhered to substrate.<br />

10. Compatible materials have been used.<br />

11. Transitions at changes in direction and structural support at gaps have been provided.<br />

12. Connections between assemblies (membrane and sealants) have complied with requirements for<br />

cleanliness, preparation and priming of surfaces, structural support, integrity, and continuity of seal.<br />

13. All penetrations have been sealed.<br />

C. Tests: Testing to be performed will be determined by Owner's Construction Testing Laboratory from among the<br />

following tests:<br />

1. Qualitative Testing: Air barrier assemblies will be tested for evidence of air leakage according to ASTM<br />

E1186, smoke pencil with pressurization or depressurization.<br />

3.7 CLEANING AND PROTECTION<br />

A. Protect air barrier system from damage during application and remainder of construction period, according to<br />

manufacturer's written instructions.<br />

B. Protect air barrier from exposure to UV light and harmful weather exposure as required by manufacturer. Remove<br />

and replace air barrier exposed for more than 150 days.<br />

C. Clean spills, stains, and soiling from construction that would be exposed in the completed work using cleaning<br />

agents and procedures recommended by manufacturer of affected construction.<br />

D. Remove masking materials after installation.<br />

END OF SECTION<br />

07525 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 042911<br />

SECTION 07611 (07 4116) – SHEET METAL SOFFIT<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Preformed metal soffit panels.<br />

B. Related Requirements:<br />

1. Section 05400 - Cold Formed Metal Framing: Steel framing supporting metal soffit.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Architectural Manufacturer's Association (AAMA):<br />

1. AAMA 2605 - Specifications, Performance Requirements And Test Procedures For Superior Performing<br />

Organic Coatings And Aluminum Extrusions And Panels.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 755/A - Steel Sheet, Metallic Coated by the Hot-Dip Process and Prepainted by the Coil-Coating<br />

Process for Exterior Exposed Building Products.<br />

2. ASTM A 792/A - Steel Sheet, 55% Aluminum-Zinc Alloy-Coated by the Hot-Dip Process.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Section 01600 - Product Requirements: Transport, handle, store, and protect products.<br />

B. Protect panels from accelerated weathering by removing or venting sheet plastic shipping wrap.<br />

C. Deliver panels to site in dry and undamaged condition. Unload and handle in accordance with manufacturer's<br />

published instructions.<br />

D. Store panels off ground protected from weather, to prevent twisting, bending, or abrasion, and to provide<br />

ventilation.<br />

PART 2 - PRODUCTS<br />

2.1 METAL SOFFIT<br />

A. Metallic-Coated Steel Sheet:<br />

1. Steel Sheet with Organic Coating Finish: Steel sheet metallic coated by the hot-dip process and prepainted<br />

by the coil-coating process to comply with ASTM A755.<br />

2. Steel Sheet with Aluminum or Galvalume Finish: Aluminum-Zinc Alloy-Coated Steel Sheet, ASTM<br />

A792, Class AZ50 coating designation, Grade 40; structural quality.<br />

B. Manufacturer: Subject to compliance with requirements, provide product equivalent to those specified by any one<br />

of the following manufacturers:<br />

1. AEP-SPAN, Dallas, TX (800) 527-2503.<br />

2. Berridge Manufacturing Co., Houston, TX (800) 231-8127.<br />

3. Fabral Metal Roof and Wall Systems, Lancaster, PA (800) 884-4484.<br />

4. MBCI, Houston, TX (800) 861-6224.<br />

5. McElroy Metal, Bossier City, LA (800) 950-6531.<br />

07611 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


6. PAC-CLAD, Petersen Aluminum Corporation, Elk Grove Village, IL (800) 722--2523.<br />

C. Description:<br />

1. Exterior Soffit (Prefinished Metal Soffit Panels): L-Panel by Berridge, 24 gage steel grooved panels,<br />

concealed fasteners. Panel profile shall be approximately 12” panel width, 1” panel depth, 3” groove<br />

spacing or similar panel profile by any named manufacturer.<br />

2.2 ACCESSORIES<br />

A. Provide manufacturer's standard accessories and other special items required and essential to completeness of<br />

soffit installation. Sight-exposed accessories shall match finish of metal soffit system.<br />

1. Trim Items: Of same material and finish as soffit sheets.<br />

2. Fasteners: As recommended by soffit system manufacturer for intended purpose.<br />

3. Sealants: Color coordinated primerless silicone or high grade non-drying butyl, recommended by panel<br />

manufacturer.<br />

2.3 FABRICATION<br />

A. Factory fabricate and finish panels and accessories ready for field assembly.<br />

B. Form sections true to shape, accurate in size, square, and free from distortion.<br />

C. Fabricate panels in one piece. In areas where one piece is impractical, fabricate panels in minimum number<br />

possible of equal lengths. Fabricate accessories in longest practicable lengths.<br />

2.4 FINISHES<br />

A. Exterior Soffit: Factory finish surfaces with high performance pigmented organic coating. Prepare, pretreat, and<br />

apply coating to exposed metal surfaces in conformance with coating and resin manufacturer's instructions<br />

providing finish free of scratches and other blemishes.<br />

1. Finish: Manufacturer's standard 2-coat, thermocured system composed of specially formulated inhibitive<br />

primer and fluoropolymer color topcoat containing minimum of 70 percent Penwalt Kynar 500 resin by<br />

weight with total minimum dry film thickness of 1.0 mil and 30 percent reflective gloss when tested in<br />

accordance with ASTM D 523 and complying with physical properties and coating performance<br />

requirements of AAMA 2605, except Humidity Resistance and Salt Spray Resistance shall be 2000 hours.<br />

2. Color as shown on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine building structure and adjacent areas where panels will be installed. Do not proceed with Work until<br />

unsatisfactory conditions have been corrected.<br />

1. Examine soffit structure to verify that structure is ready for soffit panel installation.<br />

2. Verify field dimensions to determine compliance with panel manufacturer's tolerances.<br />

B. Beginning of installation indicates acceptance of existing conditions.<br />

3.2 INSTALLATION<br />

A. Install soffit panels in accordance with manufacturer's published instructions.<br />

B. Secure panel in place with concealed fasteners.<br />

C. Interlock panels and secure in place to prevent warping and wracking.<br />

D. Back paint surfaces in contact with dissimilar materials.<br />

07611 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 FIELD QUALITY CONTROL<br />

A. Inspect soffit panel installation, alignment, attachments, trim, and accessories.<br />

3.4 CLEANING<br />

A. Wipe clean each soffit panel after erection.<br />

B. Replace damaged panels and other components of Work which cannot be repaired by finish touch-up or similar<br />

minor repairs.<br />

C. Remove from finished surface, filing caused by drilling and cutting of panels.<br />

END OF SECTION<br />

07611 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 07620 (07 6200) – SHEET METAL FLASHING AND TRIM<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Fascia and roof edge trim.<br />

2. Counterflashing over base flashing.<br />

3. Metal parapet cap.<br />

4. Door hoods.<br />

5. Refrigeration line hood.<br />

B. Related Requirements:<br />

1. Section 06100 - Rough Carpentry: Wood blocking and nailers.<br />

2. Section 07500 - Membrane Roofing: Roof penetration flashing and seals.<br />

3. Section 07611 - Sheet Metal Soffit: Preformed and prefinished soffits and soffit panels used for fascia.<br />

4. Section 07711 - Gutters and Downspouts.<br />

5. Section 07900 - Joint Sealers.<br />

6. Section 09900 - Paints and Coatings.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Architectural Manufacturers Association (AAMA):<br />

1. AAMA 621 - Voluntary Specifications for High Performance Organic Coatings on Coil Coated<br />

Architectural Hot Dipped Galvanized (HDG) and Zinc-Aluminum Coated Steel Substrates.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

2. ASTM A 755/A - Steel Sheet, Metallic Coated by the Hot-Dip Process and Prepainted by the Coil-Coating<br />

Process for Exterior Exposed Building Products.<br />

3. ASTM A 792/A - Steel Sheet, 55% Aluminum-Zinc Alloy-Coated by the Hot-Dip Process.<br />

4. ASTM B 749 - Lead and Lead Alloy Strip, Sheet, and Plate Products.<br />

5. ASTM D 523 - Standard Test Method for Specular Gloss.<br />

6. ASTM D 4586 - Asphalt Roof Cement, Asbestos Free.<br />

D. National Roofing Contractors Association (NRCA):<br />

1. NRCA - Low Slope Roofing Manual.<br />

E. Sheet Metal and Air Conditioning Contractors National Association (SMACNA):<br />

1. SMACNA - Architectural Sheet Metal Manual, Fifth Edition, 1993.<br />

F. Steel Structures Painting Council (SSPC):<br />

1. SSPC-Paint 12 - Cold-Applied Asphalt Mastic (Extra Thick Film).<br />

1.3 SUBMITTALS<br />

A. Contract Closeout Submittals: Submit the following under provisions of Section 01770.<br />

1. Letter of Certification: Submit certification from sheet metal supplier verifying quality of galvanized steel<br />

sheet materials.<br />

07620 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 QUALITY ASSURANCE<br />

A. Perform work in accordance with SMACNA "Architectural Sheet Metal Manual" and NRCA "Low Slope Roofing<br />

Manual" standard details and requirements.<br />

B. Supplier Certification: Provide certification from galvanized sheet steel supplier stating that materials conform to<br />

ATSM A 653, G90 hot-dipped galvanized steel.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Stack preformed material to prevent twisting, bending, or abrasion, and to provide ventilation.<br />

B. Prevent contact with materials during storage that may cause discoloration, staining, or damage.<br />

PART 2 - PRODUCTS<br />

2.1 SHEET MATERIALS<br />

A. Galvanized Steel: ASTM A 653 Commercial Quality and Lock-Forming Quality, G90 coating designation hot-dip<br />

galvanized, mill phosphatized for painting where exposed to view from ground level. Sheet metal gages shall be<br />

as shown or as follows where not shown:<br />

1. Flashing and Counter Flashing: 24 gage.<br />

2. Fascia and Edge Trim: 24 gage.<br />

3. Door Hood: 18 gage.<br />

4. Refrigeration Line Hood: 18 gage.<br />

B. Prefinished Sheet Metal: 24 gage; Aluminum-Zinc Alloy-Coated Steel Sheet, ASTM A 792/A, Class AZ50<br />

coating designation, Grade 40, structural quality, UL 90 rated panels, and prepainted by the coil-coating process to<br />

comply with ASTM A 755/A.<br />

1. Finish: Smooth panel with factory finished baked-on flouropolymer 2-coat coating system.<br />

a. Manufacturer's standard 2-Coat Fluoropolymer conforming to AAMA 621. Fluoropolymer finish<br />

containing not less than 70 percent Kynar 500 PVDF resin by weight in color coat with a minimum<br />

of 0.9 mil dry film thickness. Prepare, pretreat, and apply coating to exposed metal surfaces to<br />

comply with coating and resin manufacturers' written instructions.<br />

b. Unexposed side finish shall consist of not less than a 0.5 mil dry film thickness backer coat.<br />

c. Color: As shown on Drawings.<br />

2.2 ACCESSORIES<br />

A. Fasteners: Galvanized steel finish exposed fasteners to match flashing metal. Furnish exposed fasteners with soft<br />

EPDM washers as manufactured by the following:<br />

1. Kwik-Pro Screws, by Hilti.<br />

2. Trugrip GT, by ITW Buildex.<br />

B. Sealant: Specified in Section 07900.<br />

C. Sealing Mastic: Single component gun grade butyl or polyurethane sealant as recommended by roofing<br />

manufacturer.<br />

D. Bituminous Coating: SSPC - Paint 12, solvent-type bituminous mastic, nominally free of sulfur, compounded for<br />

15 mil dry film thickness per coat.<br />

E. Draw Band: Stainless steel.<br />

2.3 FABRICATION<br />

A. Form sections true to shape, accurate in size, square, and free from distortion or defects.<br />

07620 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Fabricate cleats of same material as sheet, interlockable with sheet.<br />

C. Form pieces in longest possible lengths.<br />

D. Hem exposed edges on underside 1/2 inch; miter and seam corners.<br />

E. Fabricate corners to form one piece with minimum 18 inches long legs; rivet for rigidity.<br />

F. Fabricate vertical faces with bottom edge formed outward 1/4 inch and hemmed to form drip.<br />

G. Fabricate flashings to allow toe to extend 4 inches over roofing. Return and brake edges.<br />

H. Fabricate exposed sheet metal components with provisions for thermal expansion.<br />

2.4 FINISH<br />

A. Sheet metal finish shall be as shown on Drawings.<br />

B. Where paint finish is shown, field paint in accordance with Section 09900.<br />

C. Paint metal surfaces exposed to view from ground level in accordance with Section 09900, and as indicated on<br />

Drawings, unless otherwise shown to be prefinished.<br />

D. Sheet metal surfaces not designated or specified to receive a finish shall remain uncoated.<br />

PART 3 - EXECUTION<br />

3.1 INSPECTION<br />

A. Verify roof openings, curbs, pipes, sleeves, ducts, or vents through roof are solidly set.<br />

B. Verify roofing membrane termination and base flashings are in place, sealed, and secure.<br />

C. Beginning of installation means acceptance of existing conditions.<br />

3.2 PREPARATION<br />

A. Field measure site conditions prior to fabricating work.<br />

B. Install starter and edge strips, and cleats before starting installation.<br />

3.3 INSTALLATION<br />

A. Install sheet metal flashing and trim in accordance with applicable details of SMACNA "Architectural Sheet Metal<br />

Manual" and NRCA "Low Slope Roofing Manual". Anchor units of work securely in place by methods indicated,<br />

providing for thermal expansion of metal units; conceal fasteners where possible, and set units true to line and<br />

level. Install work with laps, joints, and seams that will be permanently watertight and weatherproof.<br />

B. Bed flanges of metal flashings in plastic cement or sealing mastic where required for waterproof performance.<br />

C. Apply bituminous coating on surfaces in contact with dissimilar materials including the following:<br />

1. Dissimilar metals as defined in SMACNA Appendix A-3.<br />

2. Preservative treated wood.<br />

D. Roof Edge Trim:<br />

1. Install sheet metal edge trim in accordance with SMACNA Figure 2-1, profile as indicated on Drawings.<br />

Nail edge trim flange at 3 inches on center, in staggered pattern.<br />

07620 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Thermal Expansion Joints: Install roof edge trim in 10 foot lengths with a 1/4 inch gap joint with a 6 inch<br />

cover plate in accordance with SMACNA Figure 2-5A. Set the cover plate in sealant, nail through opening<br />

in edge trim, and loose lock to the drip edge.<br />

3. Corner Joints: Notch and lap. Set laps in sealant and rivet for rigidity. Space rivets at 1 inch on center.<br />

E. Parapet Cap Flashing:<br />

1. Install sheet metal coping with continuous cleat in accordance with SMACNA requirements, profiles as<br />

indicated.<br />

a. Set cleat in full bed of sealant, overlaying and concealing continuous parapet waterproofing<br />

membrane.<br />

b. Secure cleat at 6 inches on center to nailer.<br />

2. Install coping in accordance with SMACNA Figure 3-1 over shaped fiber board; secure roof side edge<br />

using washered screws in staggered pattern through slotted or oversized holes located at maximum 12" on<br />

center.<br />

3. Provide coping in minimum 10 to maximum 25 foot lengths.<br />

4. Provide thermal expansion joints using joints in accordance with SMACNA Figure 3-3, Covered Plate<br />

Seam. Set lap in beds of sealant.<br />

F. Door Hood: Install galvanized sheet metal hood with 3/8-inch expansion bolts at 16 inches on center and as<br />

indicated on Drawings.<br />

G. Refrigeration Line Hood: Install galvanized sheet metal hoods with 3/8 inch expansion bolts at 16 inches on<br />

center and as indicated on Drawings.<br />

H. Reglet and Counterflashing System:<br />

1. Surfaced Mounted Reglet:<br />

a. Set reglet parallel to roof line in full bed of sealant. Provide minimum 2 inch end lap at continuous<br />

elevations.<br />

b. Secure to wall with neoprene/stainless steel washers and drive pins at maximum 16 inches on<br />

center.<br />

c. Provide a continuous, full bead of sealant at top edge of reglet between flashing and wall. Sealant<br />

bead shall be of sufficient width to provide a 45 degree angle with vertical surface.<br />

2. Counterflashing: Provide counterflashing of the type indicated or required to match reglet system. Insert<br />

counterflashings into reglets to form tight fit. Counterflashing shall be installed in such a manner as to<br />

provide for continuous contact at base flashing with sufficient pressure at point of contact to prevent<br />

dislocation. Lap inside corners. Notch and hook-seam outside corners. Set laps and seams in sealant.<br />

a. Provide minimum 2 inch end lap at continuous elevations.<br />

b. Change in elevation of 4 inches, provide 8 inch end lap.<br />

c. Change in elevation of 8 inches, provide 12 inch end lap.<br />

END OF SECTION<br />

07620 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 022511<br />

SECTION 07711 (07 7113) – GUTTERS AND DOWNSPOUTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Gutters and downspouts, with expansion joints.<br />

2. Downspout collectors.<br />

3. Scuppers.<br />

4. Conductor heads.<br />

B. Related Requirements:<br />

1. Section 07620 - Sheet Metal Flashings and Trim.<br />

2. Section 07900 - Joint Sealers.<br />

3. Section 09900 - Paints and Coatings: Field painting of metal surfaces.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Architectural Manufacturers Association (AAMA):<br />

1. AAMA 621 - High Performance Organic Coatings on Coil Coated Architectural Hot Dipped Galvanized<br />

(HDG) & Zinc-Aluminum Coated Steel Substrates.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

2. ASTM A 755 - Steel Sheet, Metallic Coated by the Hot-Dip Process and Prepainted by the Coil-Coating<br />

Process for Exterior Exposed Building Products.<br />

3. ASTM A 792 - Steel Sheet, 55 % Aluminum-Zinc Alloy-Coated by the Hot-Dip Process.<br />

D. Sheet Metal and Air Conditioning Contractors National Association (SMACNA):<br />

1. Architectural Sheet Metal Manual.<br />

E. Steel Structures Painting Council (SSPC):<br />

1. SSPC - Paint 12 - Cold-Applied Asphalt Mastic (Extra Thick Film).<br />

1.3 QUALITY ASSURANCE<br />

A. Nominal sizing of components for rainfall intensity determined by a storm occurrence of 1 in 5 years shall be as<br />

indicated on Drawings.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Stack preformed materials to prevent twisting, bending, or abrasion, and to aid ventilation. Slope to drain.<br />

B. Prevent contact with materials during storage which may cause discoloration, staining, or damage.<br />

07711 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Galvanized Steel Sheet: ASTM A 653 Structural Quality, Grade 33, G90 zinc coating. Sheet metal components<br />

shall be galvanized steel sheet unless otherwise specified.<br />

2.2 COMPONENTS<br />

A. Hanging Gutters: Fabricate to cross section indicated, complete with end pieces, outlet tubes, and other<br />

accessories as required. Fabricate in minimum 96-inch long sections. Furnish flat-stock gutter spacers and gutter<br />

brackets fabricated from same metal as gutters, of size recommended by SMACNA but not less than twice the<br />

gutter thickness. Fabricate expansion joints, expansion-joint covers, and gutter accessories from same metal as<br />

gutters. SMACNA rectangular profile, Figure 1-2, Style D, gauge as follows:<br />

1. 12 inches x 12 inches: 22 gauge.<br />

2. 8 inches x 8 inches: 22 gauge.<br />

3. 5 inches x 5inches: 24 gauge.<br />

4. 4 inches x 4 inches: 24 gauge.<br />

B. Prefinished Metal Gutters: 24 gage; Aluminum-Zinc Alloy-Coated Steel Sheet, ASTM A 792/A, Class AZ50<br />

coating designation, Grade 40, structural quality, UL 90 rated panels, and prepainted by the coil-coating process to<br />

comply with ASTM A 755/A.<br />

1. Finish: Smooth panel with factory finished baked-on flouropolymer 2-coat coating system consisting of<br />

manufacturer's standard 2-Coat Fluoropolymer conforming to AAMA 621. Fluoropolymer finish<br />

containing not less than 70 percent Kynar 500 PVDF resin by weight in color coat with a minimum of 0.9<br />

mil dry film thickness. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with<br />

coating and resin manufacturers' written instructions.<br />

a. Color: As shown on Drawings.<br />

C. Downspouts: 22 gauge, SMACNA rectangular unless otherwise indicated. Fabricate downspouts complete with<br />

mitered elbows. Downspouts shall be fully enclosed profile, SMACNA Figure 1-32B:<br />

D. Conductor Head: SMACNA Figure 1-25F.<br />

E. Through-Wall Scuppers: SMACNA Figure 1-26.<br />

F. Overflow Scuppers: SMACNA Figure 1-30.<br />

2.3 ACCESSORIES<br />

A. Gutter Brackets: Galvanized steel plate, 3/16 inch thick by 2 inches wide bent plate.<br />

B. Gutter Spacer Clip: Galvanized steel sheet, gauge to match gutter.<br />

C. Gutter Strap: Galvanized steel sheet size and spacing as shown.<br />

D. Downspout/Gutter Connections: Match gauge and profile of gutter, SMACNA Figure 1-33B, Detail 1.<br />

E. Downspout Straps: Match downspout material, minimum 20 gauge, SMACNA Figure 1-35G.<br />

F. Bituminous Coating: SSPC - Paint 12, solvent-type bituminous mastic, nominally free of sulfur, compounded for<br />

15 mil dry film thickness per coat.<br />

G. Sealant: Specified in Section 07900.<br />

H. Splash Blocks (if indicated on Drawings): Precast concrete units, minimum 3000 psi at 28 days, with 5 percent air<br />

entrainment, size and profile to suit application.<br />

07711 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


I. Downspout Collectors (if indicated on Drawings): Pipe material, sizes, connections, dimensions and profiles to<br />

suit downspouts and underground storm drainage system as indicated on drawings.<br />

2.4 FABRICATION<br />

A. Form gutters and downspouts of size as indicated on Drawings.<br />

B. Form scuppers of size indicated on Drawings.<br />

C. Fabricate in accordance with SMACNA details unless otherwise shown.<br />

D. Provide gutter spacers at spacing shown. Fasten to front and back of gutter.<br />

E. Field measure site conditions prior to fabricating work.<br />

F. Form sections square, true, and accurate in size, in maximum possible lengths and free of distortion or defects<br />

detrimental to appearance or performance. Allow for expansion at joints.<br />

G. Hem exposed edges of metal.<br />

H. Field Finishing: Field paint gutters, downspouts, and accessories surfaces exposed to view from ground surface<br />

unless noted as prefinished or unpainted on Drawings. Paint in accordance with Section 09900.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that surfaces are ready to receive work and conditions are acceptable.<br />

B. Verify surfaces behind gutters and downspouts are painted prior to installation. Gutters, downspouts, and<br />

conductor heads shall not be in place while surfaces behind such items are being painted.<br />

3.2 INSTALLATION<br />

A. Install gutters, brackets, and accessories in accordance with SMACNA Figure 1-12 and as shown on the Drawings.<br />

1. Install gutters level without sags or dips to prevent ponding.<br />

2. Gutter Brackets: Space alternately with gutter spacers at 36 inches on center.<br />

a. Attachment to Masonry: Anchor to masonry bond beam as shown. Space anchor bolts minimum of<br />

3 inches apart.<br />

b. Attachment to Steel: Weld to steel tube section with 3/16 inch by 2 inches fillet weld, both sides of<br />

bracket. Begin weld at top of bracket.<br />

3. Lap gutter joints 2 inches, set laps in bead of sealant, and rivet at 1 inch on center.<br />

4. Provide lap type gutter expansion joint in accordance with SMACNA Figure 1-6. Locate joints at a<br />

maximum spacing of 40 feet with at least one expansion joints in each segment of gutter between ends<br />

and/or downspouts.<br />

B. Install downspouts in accordance with SMACNA Figure 1-35G, space straps at 48 inches on center.<br />

C. Install conductor heads and downspouts after application of exterior wall coating.<br />

D. Install scuppers in accordance with SMACNA Figure 1-26 or Figure 1-30, as applicable, except as otherwise<br />

shown on the drawings. Install scuppers before installation of roofing membrane.<br />

07711 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Apply bituminous coating on surfaces in contact with dissimilar materials including the following:<br />

1. Dissimilar metals as defined in SMACNA Appendix A-3 and backside of conductor heads, gutters and<br />

downspouts.<br />

2. Preservative treated wood.<br />

END OF SECTION<br />

07711 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 07721 (07 7213) – MANUFACTURED CURBS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished manufactured structural metal roof curbs and adapter curbs for installation by Contractor.<br />

2. Manufactured non-structural metal roof curbs furnished and installed by Contractor.<br />

B. Related Requirements:<br />

1. Section 05120 - Structural Steel: Roof opening frames and headers.<br />

2. Section 07500 - Membrane Roofing: Board insulation for roof curbs.<br />

3. Section 07620 - Sheet Metal Flashing Trim: Sheet metal flashing installed in conjunction with roof<br />

penetration curbs.<br />

4. Section 07722 - Roof Hatches.<br />

5. Section 15600 - Refrigeration Systems.<br />

6. Section 15700 - Heating, Ventilating and Air Conditioning Equipment.<br />

7. Section 15800 - Air Distribution: Grease duct exhaust fan curbs.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Welding Society (AWS): AWS D1.1 - Structural Welding Code.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 463 - Steel Sheet, Aluminum Coated by the Hot-Dip Process.<br />

2. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

3. ASTM A 792 - Steel Sheet, 55% Aluminum-Zinc Alloy-Coated by the Hot-Dip Process.<br />

D. Steel Structures Painting Council (SSPC):<br />

1. SSPC-Paint 20 - Zinc-Rich Coating Type I - Inorganic And Type II- Organic.<br />

1.3 DEFINITIONS<br />

A. Structural Roof Curb: Manufactured square or rectangular roof curb, bearing on structural steel joists or headers,<br />

designed to support equipment dead load and roof dead and live loads.<br />

B. Non-Structural Roof Curb:<br />

1. Deck Penetrations - 10 Inches by 10 Inches or Less: Manufactured square or rectangular roof curb, bearing<br />

on top of metal roof deck, designed to receive sheet metal flashing skirt, not used for support of equipment.<br />

2. Deck Penetrations - Greater Than 10 Inches by 10 Inches: Manufactured square or rectangular roof curb<br />

bearing on structural steel angle frame, designed to support equipment dead load. Roof dead and live load<br />

supported by structural angle frame.<br />

1.4 QUALITY ASSURANCE<br />

A. Qualifications for Welding Work: Qualify field welding operators in accordance with AWS Standard<br />

Qualification Procedures. Provide certification that field welders have satisfactorily passed AWS qualification<br />

tests within previous 12 months.<br />

1. If recertification of welders is required, provide without additional cost to Owner.<br />

07721 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations. Receive Owner Furnished products in compliance with the requirements of<br />

Section 01640.<br />

B. Ship curbs to site palletized and banded.<br />

C. Curb Manufacturer shall furnish Curb Schedule to Contractor identifying curb "Type" and roof penetration for<br />

which curb is to be used. Curb Schedule shall identify identical curbs as single "Type" (i.e., Type A - 10 ton<br />

RTU's, Type B - 5 ton RTU's, Type C - skylights, Type D - satellite dish, Type E - expansion joints, etc.). Identify<br />

each curb with "Type" designation painted in 1 inch high letters on outside face of curb.<br />

D. Stack curbs at site to prevent twisting, bending or permanent deformation.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's supplier will furnish structural roof curbs, adapter curbs and<br />

associated wind seismic restraint brackets (when required) for installation by the Contractor.<br />

1. Non-structural roof curbs shall be Contractor furnished and installed.<br />

2. Descriptions and specifications of Owner furnished items and equipment hereinafter are included as<br />

information to the Contractor only and not to be considered as Contractor requirements unless otherwise<br />

stated.<br />

2.2 MANUFACTURERS<br />

A. Structural Roof Curbs: Owner’s supplier for structural roof curbs and adapter curbs will be as follows:<br />

1. AES Industries, Tallassee, AL. Contact: Chad Burt (800) 786-0402.<br />

B. Non-Structural Roof Curbs: Subject to compliance with project requirements, provide prefabricated metal roof<br />

curbs manufactured by one of the following:<br />

1. AES Industries, Tallassee, AL. Contact: Chad Burt (800) 786-0402.<br />

2. Curbs Plus, Rossville, GA. Contact: Marc Brower (888) 639-2872.<br />

2.3 MATERIALS<br />

A. Sheet Steel: One of the following:<br />

1. Galvanized Steel Sheet: ASTM A 653, SS (Structural Steel) Classification, Grade 33, G60 hot-dip zinc<br />

coating.<br />

2. Aluminum-Coated Steel Sheet: ASTM A 463, SS (Structural Steel) Classification, Grade 33, Type 2, T2<br />

100 aluminum coating.<br />

3. Aluminum Zinc Alloy-Coated Steel Sheet (GAVALUME): ASTM A 792, AZ55 aluminum zinc alloy<br />

coating.<br />

B. Board Insulation: Specified in Section 07500.<br />

C. Wood Nailers: CCA Pressure Treated Lumber Type C, "Standard" grade lumber of any species.<br />

D. Zinc-Rich Primer: SSPC-Paint 20 Type II.<br />

E. Deck Support Clip: Galvanized steel sheet, gauge as shown.<br />

F. Finish Paint:<br />

1. Primer: One coat Speedhide Super Tech Dry-Fog Epoxy Ester #6-157 by PPG.<br />

2. Finish: One coat Speedhide Super Tech Alkyd Dry-Fog Enamel, Eggshell # 6-151 by PPG.<br />

07721 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 STRUCTURAL ROOF CURBS (OWNER FURNISHED - CONTRACTOR INSTALLED)<br />

A. Fabrication, General: Coated 14 gauge steel sheet curb sections, corners fully mitered and welded; 2 inch by 4<br />

inch (nominal dimension) pressure treated continuous wood nailers mechanically fastened with corrosion resistant<br />

fasteners at 12 inches on center to exterior face of curb. Shop prime welded connections with zinc-rich paint<br />

complying with SSPC-Paint 20.<br />

B. Adapter Curbs: Curbs shall be fully welded and insulated. Blank off open areas not used for supply and return air<br />

to prevent air mixing. Construct adapter curbs with the minimum height required to achieve proper airflow.<br />

Verify curb type, size, and unit prior to fabrication.<br />

C. Curb Height: Unless otherwise required by local codes, minimum curb height from top of bar joist to top of curb<br />

shall be as specified below but in no case less than 8 inches from top of roof membrane to top of curb:<br />

1. All Rooftop Unit Curbs Unless Otherwise Shown or Specified: 18 inches.<br />

D. Reinforce curb sections as required for design loads indicated on Drawings.<br />

E. Welding: AWS D1.1.<br />

F. Mechanical Unit Curbs: Label curbs with “FRONT” designating the curb orientation to the front of store prior to<br />

shipment. Mechanical curbs will be provided as follows as applicable:<br />

1. Roof Top Unit (RTU) Curbs: Provide continuous height rail curbs. It is acceptable for units to follow roof<br />

slopes not exceeding 3/8 inch per foot only if the unit outdoor air intake (return air end) is oriented toward<br />

the high side of the roof pitch.<br />

2. Air Handling Unit (AHU) Curbs: Provide tapered rail curbs. Construct curb for AHU to be level (verify<br />

roof slope).<br />

3. Double Cross-Sloped and Side-Sloped Curbs: Provide tapered rail curbs for level mounting of RTUs when<br />

located in a cross-sloped or side-sloped section of roof as shown on the structural roof plan. Curbs<br />

fabricated for cross-sloped or side-sloped installation shall be clearly marked by the manufacturer to<br />

indicate for special application.<br />

G. Shop Painting: Shop finish interior surfaces of curbs including safety screen and hardware kit of items that will be<br />

exposed to the public after installation. Use PPG dry fog coating as specified; color to match Sherwin-Williams<br />

#SW6385 “Dover White”.<br />

2.5 NON-STRUCTURAL ROOF CURBS (CONTRACTOR FURNISHED AND INSTALLED)<br />

A. Coated 18 gauge steel sheet curb sections, corners fully mitered and welded; 2 inch by 4 inch (nominal dimension)<br />

pressure treated continuous wood nailers mechanically fastened at 12 inches on center to exterior face of curb.<br />

Shop prime welded connections with zinc-rich paint complying with SSPC-Paint 20. Profile and dimensions shall<br />

be as shown.<br />

1. Web Height: Comply with local code requirements for minimum curb height, but in no case shall curb<br />

height be less than 18 inches for deck penetrations greater than 10 inches by 10 inches and not less than 14<br />

inches for deck penetrations 10 inches by 10 inches or less as measured from top of steel roof deck to top of<br />

curb, nor shall curb height be less than 8 inches as measured from top of roof membrane to top of curb.<br />

B. Grease Duct Exhaust Fan Curbs:<br />

1. Grease duct curbs shall be manufactured as a part of the 4G Grease Duct System by Metal-Fab, Wichita,<br />

KS, as specified in Section 15800. Contact: CVP Customer Service, (800) 835-2830.<br />

2. Coordinate delivery of grease duct curbs with mechanical contractor and grease duct curb supplier such that<br />

grease duct curbs are installed concurrent with curbs specified herein.<br />

2.6 WIND/SEISMIC RESTRAINT BRACKETS (OWNER FURNISHED - CONTRACTOR INSTALLED)<br />

A. When noted on the Mechanical Rooftop Unit or Air Handling Unit Schedules, or Refrigeration Drawings, install<br />

wind and seismic restraint brackets furnished by Owner with curbs for anchorage of rooftop equipment to curbs.<br />

07721 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.7 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install curbs in accordance with manufacturer's instructions and as indicated on Drawings. Coordinate installation<br />

with roof membrane installation requirements specified under other Sections.<br />

B. Roof Curbs Bearing on Steel Angles, Joists, and Headers:<br />

1. Set units in place and secure base to roof structure by welding to top chord of structural member.<br />

2. Secure metal deck to perimeter of curb as indicated on Drawings.<br />

C. Roof Curbs Bearing on Roof Deck:<br />

1. Set units in place and secure base to steel roof deck by self-tapping screw fasteners spaced at a maximum<br />

of 12 inches on center, staggered.<br />

D. Install wind/seismic restraint brackets prior to installation of HVAC equipment in accordance with manufacturer’s<br />

recommendations.<br />

3.2 INTERFACE WITH OTHER WORK<br />

A. Coordinate project requirements for custom adapting and connecting to roof curbs with manufacturers and<br />

suppliers of curb mounted items and equipment.<br />

3.3 ROOF CURB SCHEDULE<br />

A. Structural Curbs: Owner furnished structural curbs and adapter curbs will be provided for the following items:<br />

1. HVAC Roof Top Units (RTU).<br />

2. Air Handling Units (AHU).<br />

B. Non-Structural Curbs: Provide non-structural roof curbs for the following items:<br />

1. Exhaust fans unless otherwise shown to be provided by others.<br />

END OF SECTION<br />

07721 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 07722 – ROOF HATCHES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Prefabricated roof hatch, with integral support curbs, operable hardware, and counterflashings.<br />

B. Related Requirements:<br />

1. Section 05500 - Metal Fabrications: Shop fabricated roof hatch ladders, Hatch Grip ladder safety<br />

extension, and other ferrous metal items.<br />

2. Section 09900 - Paints and Coatings: Exterior field painting of roof hatch.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with project requirements, provide specified items by one of the following manufacturers:<br />

1. Babcock Davis, Brooklyn Park, MN (888) 412-3726.<br />

2. The Bilco Company, New Haven, CT (800)366-6530.<br />

3. Milcor, Carol Stream, IL (800) 624-8642.<br />

4. Precision Ladders, LLC, Morristown, TN (800) 225-7814.<br />

2.2 ROOF HATCHES<br />

A. Model:<br />

1. Personnel Series Ladder Access Model B-RHG by Babcock-Davis.<br />

2. Model S-20 by Bilco.<br />

3. Model M-1 by Milcor.<br />

4. Model PLH-G by Precision.<br />

5. Description:<br />

a. Size: 2 feet 6 inches by 3 feet.<br />

b. Curb: 14 gage galvanized G60 steel; 1 inch rigid insulation; integral cap flashing to receive roof<br />

flashing system; extended flange for mounting.<br />

c. Cover: 14 gage galvanized G60 steel with one inch glass fiber insulation retained by 22 gage steel<br />

inner liner. Continuous gasket to provide weatherproof seal.<br />

d. Hardware: Manufacturer's standard manually operated type with compression spring operators,<br />

positive snap latch with turn handles inside and out and padlock hasp inside; automatic hold-open<br />

arm with vinyl covered grip handle for easy release; cadmium plated finish.<br />

e. Hinges: Heavy duty pintle type.<br />

f. Fasteners: Corrosive resistant fasteners recommended by roof hatch manufacturer.<br />

B. Model: Equipment Series by Babcock-Davis http://www.babcockdavis.com/roof-hatches/equipment-series/<br />

1. Size: 4 feet by 8 feet.<br />

2. Materials and Finishes: Match Personnel Series specified above, as provided by the manufacturer.<br />

3. Refer to Drawings for locations and additional information.<br />

2.3 FABRICATION<br />

A. Fabricate roof hatches free of visual distortions and defects. Weld corners and joints.<br />

B. Fabricate roof hatches weathertight with integral capflashing, providing for removal of condensation.<br />

07722 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Finish:<br />

1. Galvanized Steel: Prime paint, one coat for field finish painting or shop powder coated.<br />

2. Aluminum: Unpainted mill finish.<br />

D. Spot weld hasp, latch and hinges to prevent removal from interior.<br />

2.4 ROOF HATCH LADDER<br />

A. Steel Wall Ladder: As specified in Section 05500 - Metal Fabrications.<br />

B. Ladder Safety Extension: Hatch Grip safety extension as specified in Section 05500 - Metal Fabrications.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install in accordance with manufacturer's instructions. Coordinate with installation of roofing system and related<br />

flashings. Provide weathertight installation.<br />

B. Apply bituminous paint on metal surfaces of units in contact with cementitious materials and dissimilar metals.<br />

C. Field paint exterior exposed areas of hatch as specified in Section 09900.<br />

D. Interface with Other Work:<br />

1. Coordinate location and required clear dimensions of roof deck opening.<br />

2. Coordinate locations of steel roof structure members for attachment of roof hatch curbs.<br />

3. Coordinate with installation of roof insulation, roof membrane and related flashings.<br />

3.2 FIELD QUALITY CONTROL<br />

A. Inspect roof hatch installation and attachment to structure.<br />

B. Adjust hatch hinge and hold-open arm for smooth operation.<br />

END OF SECTION<br />

07722 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 103009<br />

SECTION 07815 (07 8133) – MINERAL FIBER FIREPROOFING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Mineral fiber blanket fireproofing.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

2. ASTM E 119 - Fire Tests of Building Construction and Materials.<br />

3. ASTM E 2336 - Standard Test Methods for Fire Resistive Grease Duct Enclosure Systems.<br />

1.3 SEQUENCING<br />

A. Sequence and coordinate installation of mineral fiber blanket fireproofing with other, related construction<br />

specified in other sections to comply the following requirements:<br />

1. Avoid unnecessary exposure of mineral fiber blanket fireproofing to abrasion and other damage likely to<br />

occur during construction operations subsequent to its application.<br />

2. Do not install enclosing or concealing construction until after mineral fiber blanket fireproofing has been<br />

applied and inspected by authorities having jurisdiction.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with requirements of this Section, provide mineral fiber fireproofing as manufactured by<br />

one of the following:<br />

1. Unifrax, Niagara Falls, NY, (716) 278-3800.<br />

2. 3M Corporation, Building and Commercial Services Division, St. Paul, MN, (800) 328-1687.<br />

3. Thermal Ceramics, Atlanta GA, (706) 796-4200.<br />

2.2 PERFORMANCE CRITERIA<br />

A. Fire Performance Characteristics:<br />

1. Surface Burning Characteristics: ASTM E 84.<br />

a. Flame Spread (Max): 25.<br />

b. Smoke Developed (Max): 50.<br />

B. Grease Duct Fire Resistance: Duct wrap shall meet the fire resistance standards for a two-layer grease duct<br />

enclosure system when tested in accordance with ASTM E 2336.<br />

2.3 MATERIALS<br />

A. Mineral Fiber Blanket Fireproofing: Ceramic or glass fiber blanket covered with polypropylene or fiberglass<br />

scrim foil facing. Provide one of the following products:<br />

1. 3M Fire Barrier Duct Wrap 15A, by 3M.<br />

2. FyreWrap Elite 1.5, by Unifrax.<br />

3. FireMaster Fast Wrap XL, by Thermal Ceramics.<br />

07815 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. System Thickness: 2 layers of 1-1/2 inch blanket.<br />

C. Nominal Density/Thermal Resistivity: 8 pcf/4.15 at 70 deg F.<br />

D. Anchorage Accessories: For each fire resistive assembly in which mineral fiber blanket serves as fireproofing,<br />

provide manufacturer's standard blanket-anchorage system complying with related design of UL or other testing<br />

and inspecting organization acceptable to authorities having jurisdiction.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas in which Work under this Section is to be performed. Report in writing to the<br />

Construction Manager prevailing conditions that may adversely affect satisfactory execution of Work. Do not<br />

proceed with Work until unsatisfactory conditions have been corrected.<br />

B. Starting Work constitutes acceptance of the existing conditions and this Contractor shall then, at his expense, be<br />

responsible for correcting all unsatisfactory and defective Work encountered.<br />

3.2 INSTALLATION<br />

A. Comply with manufacturer's instructions for particular conditions of installation in each case. Consult with<br />

manufacturer's technical representative for conditions not covered by printed instructions.<br />

B. Install fireproofing blanket to comply with requirements for thicknesses, number of courses (layers), construction<br />

of joints and corners, and anchorage methods that apply to fire resistance systems specified.<br />

3.3 PROTECTION<br />

A. Coordinate installation of fireproofing with other construction to minimize cutting into, or removal of, installed<br />

fireproofing. As other construction is successively completed, replace or repair fireproofing installations which<br />

have been cut away to facilitate this other construction. Maintain complete coverages of full thickness on<br />

members and substrates protected by fireproofing.<br />

B. Provide final protection and maintain conditions in a manner acceptable to Installer, Manufacturer, and authorities<br />

having jurisdiction that ensures mineral fiber blanket fireproofing being without damage or deterioration at time of<br />

Substantial Completion.<br />

END OF SECTION<br />

07815 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082710<br />

SECTION 07840 (07 8400) – FIRESTOPPING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Firestopping in rated assemblies.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 814 - Fire Tests of Through Penetration Fire Stops.<br />

C. FM Global (FM):<br />

1. FM 4991 - Standard for the Approval of Firestop Contractors.<br />

D. Underwriters' Laboratories, Inc. (UL):<br />

1. UL 1479 - Fire Tests of Through-Penetration Firestops.<br />

2. UL 2079 – Tests for Fire Resistance of Building Joint Systems.<br />

3. UL Fire Resistance Directory.<br />

1.3 SUBMITTALS<br />

A. Submittals: Comply with the requirements of Section 01330.<br />

B. Certifications:<br />

1. Installer Qualifications: Submit documentation of DRI or letter from firestop manufacturer naming<br />

approved installer to Architect prior to commencement of firestop work.<br />

2. Manufacturer’s Inspection: Submit written certification from firestop manufacturer that Manufacturer’s<br />

Representative has visited Site as specified in Part 3 and Work is in accordance with manufacturer’s<br />

requirements and published instructions.<br />

1.4 QUALITY ASSURANCE<br />

A. Installer Qualifications: Installation of firestopping shall be by a Designated Responsible Individual (DRI) in<br />

accordance with FM 4991 or shall be by an approved installer of firestop manufacturer.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with requirements, provide firestopping products as manufactured by one of the following:<br />

1. Nelson Firestop Products (800) 331-7325.<br />

2. Hilti, Inc. (800) 879-8000.<br />

3. RectorSeal Corporation (800) 231-3345.<br />

4. Specified Technologies, Inc. (STI), (800) 992-1180.<br />

07840 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. 3M Fire Protection Products (800) 376-0964.<br />

6. Tremco Firestop System (800) 852-8173.<br />

2.2 REGULATORY REQUIREMENTS<br />

A. Firestop materials shall have been tested with and shall be in compliance with the minimum requirements of<br />

ASTM E 814, UL 1479, and UL 2079 as applicable. Products used shall be as listed below as suitable for the<br />

intended application and as required to produce the fire rating as shown on Drawings and to conform to the<br />

Firestopping Schedule of UL assemblies included at the end of this Section.<br />

2.3 MATERIALS<br />

A. Intumescent Latex or Acrylic Sealant: Single-component, intumescent, latex or acrylic formulation.<br />

1. LBS by Nelson Firestop Products.<br />

2. FS ONE or CP 606 by Hilti.<br />

3. Metacaulk 950 or 1000 by RectorSeal.<br />

4. SpecSeal SSS100 by STI.<br />

5. CP 25WB+, IC 15WB, or 3000WT by 3M.<br />

6. TREMstop Intumescent Acrylic (IA) or Acrylic (A) by Tremco.<br />

B. Intumescent Solvent-Release-Curing Sealant: Single component, intumescent, synthetic-polymer based, non-sag<br />

grade.<br />

1. CP 25N/S by 3M.<br />

C. Intumescent Wrap/Strip: Single-component, elastomeric sheet with aluminum foil on one face.<br />

1. WRS by Nelson Firestop Products.<br />

2. CP 645 Wrap Strip by Hilti.<br />

3. Metacaulk Wrap Strip by RectorSeal.<br />

4. SpecSeal SSWRED Wrapstrip by STI.<br />

5. FS-195+ Wrap/Strip or Ultra GS by 3M.<br />

6. TREMstop WS by Tremco.<br />

D. Intumescent Putty: Single-component, non-hardening, dielectric, intumescent putty.<br />

1. FSP by Nelson Firestop Products.<br />

2. CP 618 Putty Stick or CP 617/617L Putty Pad by Hilti.<br />

3. CP 645 Wrap Strip by Hilti.<br />

4. CP 658 Firestop Plug by Hilti.<br />

5. Metacaulk Fire Rated Putty by RectorSeal.<br />

6. SpecSeal Putty by STI.<br />

7. Moldable Putty+ by 3M.<br />

8. TREMstop MP (Moldable Putty) or Putty Stick by Tremco.<br />

E. Silicone Sealant: Single-component, moisture-curing, silicone-based elastomeric, non-sag grade.<br />

1. CLK N/S by Nelson Firestop Products.<br />

2. CP 601S by Hilti.<br />

3. Metacaulk 835 by RectorSeal.<br />

4. SpecSeal PEN 300 by STI.<br />

5. 2000+ Silicone by 3M.<br />

6. FYRE-SIL or SL by Tremco.<br />

F. Silicone or Polyurethane Foam: Two-Component, liquid elastomer that, when mixed, expands and cures in place<br />

to produce a flexible, nonshrinking foam.<br />

1. SpecSeal PEN 200 by STI.<br />

2. 2001 Silicone RTV Foam by 3M.<br />

3. CP 620 Fire Foam by Hilti.<br />

07840 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


G. Intumescent Collar: Factory-fabricated, intumescent collar.<br />

1. PCS by Nelson Firestop Products.<br />

2. CP 642 or CP 643 by Hilti.<br />

3. Metacaulk Pipe Collar by RectorSeal.<br />

4. SpecSeal SSC Collars by STI.<br />

5. Plastic Pipe Device, RC Pack, or RC One Collar by 3M.<br />

6. TREMstop D by Tremco.<br />

H. Intumescent Composite Sheet, Pillows and Mortar, or Blocks: Products used to firestop large openings.<br />

1. CPS by Nelson Firestop Products.<br />

2. FS 657 Fireblocks by Hilti.<br />

3. CP 637 Firestop Mortar by Hilti.<br />

4. CP 675T Firestop Board by Hilti.<br />

5. SpecSeal SSB Pillows and SpecSeal SSM Firestop Compound by STI.<br />

6. CS-195+ Composite Sheet by 3M.<br />

7. TREMstop PS by Tremco.<br />

I. Sprayable Fire-Rated Mastic: Products used to firestop construction joints.<br />

1. CP672 Speed Spray by Hilti.<br />

2. Specseal Elastomeric Spray by STI.<br />

3. Firedam Spray 200 by 3M.<br />

4. TREMstop Acrylic Spray (A-SP) by Tremco.<br />

J. Packing Material: Manufacturer's standard mastic, putty, ceramic fiber blanket, or mineral wool to be used as fill<br />

or backing material for firestopping.<br />

1. Mineral Wool by Nelson Firestop Products.<br />

2. Mineral Wool by Hilti.<br />

3. Fire Safing or Backer Rod by RectorSeal.<br />

4. Mineral Wool by STI.<br />

5. Fire Barrier 5A,15A, and 20A or PM4 Packing Material by 3M.<br />

6. TREMstop FS Blanket by Tremco.<br />

7. CP 777 Speed Plugs (preformed mineral wool designed for top of wall fluted metal deck packing material)<br />

by Hilti.<br />

K. Substitutions: Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Remove loose dirt and oil from penetration surfaces.<br />

B. Place hangers or damming materials in penetration to hold firestopping materials, if necessary.<br />

3.2 INSTALLATION<br />

A. Keep caulk and putty away from heat, open flame, sparks, or other sources of ignition during application and until<br />

product cures. Use only with adequate ventilation.<br />

B. Follow manufacturer charts for appropriate material to achieve required fire rating in various locations.<br />

C. Install firestopping at penetrations of fire rated wall materials in accordance with manufacturer's published<br />

instructions.<br />

D. Install firestopping at penetrations and construction joints of fire rated walls and floors in accordance with<br />

manufacturer’s published instructions and in accordance with UL Fire Resistance Directory.<br />

07840 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 FIELD QUALITY CONTROL<br />

A. Site Inspection: Upon completion of installation, Manufacturer’s Representative shall inspect installed<br />

firestopping to verify work complies with the manufacturer’s requirements.<br />

3.4 FIRESTOPPING SCHEDULE<br />

A. Provide firestopping complying with UL assemblies specified below.<br />

Penetration Assembly Nelson Hilti RectorSeal STI 3M Tremco<br />

Metal Pipe CMU Wall 8" CAJ1203 CAJ 1149 or CAJ1114 or CAJ1079 or CAJ1001 or CAJ1064 or<br />

Thick or Less<br />

CAJ1155 or CAJ1115 CAJ1217 CAJ1009 CAJ1302<br />

Non-Metallic<br />

Pipe<br />

Gypsum Board<br />

Partition<br />

CMU Wall 8"<br />

Thick or Less<br />

Gypsum Board<br />

Partition<br />

WL1083 or<br />

WL1030<br />

CAJ2086<br />

WL2071<br />

CAJ8049 or<br />

CAJ4033<br />

Cable Tray CMU Wall 8"<br />

Thick or Less<br />

Gypsum Board<br />

Partition WL4003<br />

Insulated CMU Wall 8"<br />

Metal Pipe thick or Less<br />

Gypsum Board<br />

Partition WL5036<br />

Construction CMU Wall to<br />

Gaps - Head Metal Deck - - - -<br />

of Wall to Gyp Bd Parti'n<br />

Roof Deck to Metal Deck - - - -<br />

Construction CMU Wall to<br />

Gaps - Wall CMU Wall - - - -<br />

to Wall<br />

END OF SECTION<br />

Gyp Bd Parti'n<br />

to Gyp Bd<br />

Parti'n<br />

CAJ5008 or<br />

CAJ5059<br />

CAJ1226<br />

WL1054 or WL1026 or WL1049 or WL1003 or WL1278 or<br />

WL1058 WL1034 WL1079 WL1009 WL1158<br />

CAJ2110 or WJ2025 CAJ2064 or<br />

CAJ2233 or<br />

CAJ2109<br />

CAJ2045 CAJ2005 CAJ2184<br />

WL2098 or WL2104 WL2093, WL2002 or WL2083 or<br />

WL2078 or<br />

WL2029 or WL2005 WL2129<br />

WL2341<br />

WL2288<br />

CAJ4035 or<br />

CAJ4020 or CAJ4003 CAJ4075<br />

CAJ4017 CAJ8043 CAJ4029<br />

WL4011 or<br />

WL4005 or<br />

WL3043 or<br />

WL4019 - - - - WL4008 WL4004 WL3131<br />

CAJ5090 or WJ5016 or CAJ5021 or CAJ5001 or CAJ5121<br />

CAJ5091 CAJ5070 CAJ5029 CAJ5002 CAJ5111<br />

WL5028 or<br />

WL5014 or<br />

WL-5115<br />

WL5029 WL5057 WL5051 WL5001 WL-5081<br />

HWD0098 TL/PV 60-01<br />

- - - - HWD0013 HWD0092<br />

HWD0042 or<br />

HWD0049 HWD0014 - - - - HWS0003 HWD0091<br />

WWD1011,<br />

WWD1012or - - - - - - - - WWS1001<br />

WWD0017<br />

WWD1050,<br />

WWD0043,<br />

TL/PV60-01<br />

or<br />

WWD-1052<br />

- - - - - - - - - - - - - - - - WWS0004 - - - -<br />

07840 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 07900 (07 9000) – JOINT SEALERS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Joint sealants for interior and exterior joints in vertical surfaces and horizontal nontraffic surfaces.<br />

2. Joint sealants and fillers in interior concrete floor slab-on-grade joints.<br />

3. Joint sealant and fillers in exterior concrete sidewalks and pavement adjacent to building.<br />

B. Related Requirements:<br />

1. Division 2 - Joint fillers and sealants for joints in sidewalk and pavement not adjacent to building.<br />

2. Section 04200 - Unit Masonry Assemblies: Installation of expansion joint filler (compression seal) and<br />

control joint sealer in masonry walls.<br />

3. Section 07500 - Membrane Roofing: Sealants associated with roofing.<br />

4. Section 07840 - Firestopping: Joint seals around penetrations of fire-rated assemblies.<br />

5. Section 09650 - Resilient Flooring: Joint subfloor filler for control/construction joints concealed by floor<br />

finish material.<br />

6. Section 09680 - Carpet: Joint subfloor filler for control/construction joints concealed by floor finish<br />

material.<br />

7. Section 09900 - Paints and Coatings: Protection of wall joints from painting prior to sealing.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only<br />

B. ASTM International (ASTM):<br />

1. ASTM C 920 - Elastomeric Joint Sealants.<br />

2. ASTM C 1330 - Cylindrical Sealant Backing for Use with Cold Liquid Applied Sealants.<br />

3. ASTM D 1056 - Flexible Cellular Materials-Sponge or Expanded Rubber.<br />

4. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Installer Qualification Certification: Provide Installer Qualification Certification in the form of a letter from the<br />

product manufacturer listing Installer qualifications as specified in Quality Assurance paragraph below. Include<br />

manufacturer’s certification, specific project and location and list of projects. Provide certification from product<br />

manufacturer for Installers of the following:<br />

1. Polyurea Joint Filler.<br />

C. Product Data: Brand name, chemical composition, installation directions and certificates of compliance with<br />

required standards for the following products:<br />

1. Elastomeric joint materials (sealant and back-up material).<br />

2. Preformed expansion (isolation) joint filler (PMEJ).<br />

3. Polyurea joint filler.<br />

4. Submit 30 days prior to first concrete placement.<br />

1.4 QUALITY ASSURANCE<br />

A. Installer Qualifications:<br />

1. Certified by the manufacturer as qualified to install the material to be used.<br />

2. List of at least 15 projects, with locations, performed by Installer within the last 3 years and similar in type<br />

and size to this project.<br />

07900 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Interior sealants in food preparation areas shall meet the compositional requirements for use in USDA regulated<br />

facilities, as required by FDA according to 21 CFR 177.2600, and local Authorities Having Jurisdiction.<br />

1.5 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store and protect products in compliance with the requirements of Section 01600.<br />

1.6 PROJECT CONDITIONS<br />

A. Do not install solvent curing sealants in enclosed building spaces.<br />

B. Maintain temperature and humidity recommended by sealant manufacturer during and after installation.<br />

C. Do not proceed with installation of joint sealants under the following conditions:<br />

1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant<br />

manufacturer.<br />

2. When joint substrates are wet.<br />

3. Where joint widths are less than those allowed by joint-sealant manufacturer for applications indicated.<br />

4. Where contaminants capable of interfering with adhesion have not yet been removed from joint substrates.<br />

PART 2 - PRODUCTS<br />

2.1 ELASTOMERIC SEALANTS (BUILDING)<br />

A. General: Comply with ASTM C 920 and other requirements indicated for each liquid-applied chemically curing<br />

sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related<br />

to exposure and joint substrates.<br />

B. Suitability for Contact with Food: Where sealants are indicated for joints that will come in repeated contact with<br />

food, provide products that comply with 21 CFR 177.2600. Sealants identified as (Non-USDA) shall not be used<br />

in food preparation areas.<br />

C. Manufacturers: Provide products by the following manufacturers to the extent specified for the specific product.<br />

1. BASF Building Systems (Formerly Sonneborn Building Products), (952) 496-6000, Craig Agney.<br />

2. Convenience Products, (800) 325-6180.<br />

3. CSS Polymers, Inc., (770) 645-0101.<br />

4. Dow Corning Corporation.<br />

5. Euclid Chemical Co., (877) 438-3826.<br />

6. GE Silicones & GE Sealants and Adhesives. (Momentive Performance Materials), (877) 943-7325.<br />

7. HI-TECH Structural Epoxy Systems (Progressive Fastening), (800) 454-5530.<br />

8. Metzger/McGuire, (800) 223-6680.<br />

9. Pecora Corporation, (215) 796-1401, Keith Waters.<br />

10. Tremco Sealant/Weatherproofing Division, (800) 841-3778.<br />

11. VersaFlex Inc., (913) 321-1416.<br />

12. W. R. Meadows, Inc., (847) 214-2100.<br />

D. Polyurethane Sealants (USDA compliant, unless otherwise noted):<br />

1. Polyurethane Sealant #1 (P1): ASTM C 920, Type S, Grade NS, Class 25, single component.<br />

a. Vulkem 116, Dymonic, or Dymonic FC by Tremco.<br />

b. Dynatrol I-XL, by Pecora.<br />

c. Sonolatic NP-1, by BASF (Sonneborn).<br />

2. Polyurethane Sealant #2 (P2): ASTM C 920, Type S, Grade P, Class 25, single component.<br />

a. Vulkem 45 (Non-USDA), by Tremco.<br />

b. Urexpan NR-201, by Pecora.<br />

c. Sonolastic SL-1, by Sonneborn.<br />

3. Polyurethane Sealant #3 (P3): ASTM C 920, Type M, Grade NS, Class 50, multi-component.<br />

a. Dymeric 240-240FC, by Tremco.<br />

b. Sonolastic NP-2 by BASF (Sonneborn).<br />

c. Dynatrol II (Non-USDA) by Pecora.<br />

07900 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Silicone Sealants (USDA compliant, unless otherwise noted):<br />

1. Silicone Sealant #1 (S1): ASTM C 920, Type S, Grade NS, Class 25.<br />

a. Spectrem 1, Spectrem 2 or Spectrem 3 by Tremco.<br />

b. 791 Silicone Perimeter Sealant (Non-USDA) by Dow.<br />

c. 864 or 890 by Pecora.<br />

d. Sonolastic 150 by BASF (Sonneborn).<br />

e. SilPruf (Non-USDA) by GE.<br />

f. Titebond 100% Silicone Sealant by Franklin International.<br />

2. Silicone Sealant #2 (S2): ASTM C 920, Type S, Grade NS, Class 25, mildew resistant.<br />

a. Tremsil 200, by Tremco.<br />

b. 898 by Pecora.<br />

c. 786 Silicone Sealant (Non-USDA) by Dow.<br />

d. Sanitary SCS 1700 (Non-USDA) by GE.<br />

F. Sealant Color:<br />

1. For interior and exterior exposed to view areas, match color of adjacent paint color finish or other adjacent<br />

finish color.<br />

2. For joints where plumbing fixtures meet adjacent floor and wall finishes, match color of plumbing fixture.<br />

3. Use clear sealant where applied to stainless steel surfaces.<br />

2.2 EXPANDING FOAM SEALANTS<br />

A. Polyurethane Expanding Foam Sealants:<br />

1. Polyurethane Expanding Foam Sealant #1 (EF1): Closed-cell foam and non-flammable propellant; urea<br />

formaldehyde-free, CFC-free; UL Class 1 Foam with flame spread of 20 and smoke developed of 25 as<br />

tested in accordance with ASTM E84.<br />

a. Touch'n Seal Quick Cure by Convenience Products.<br />

b. Space Invader by GE Sealants & Adhesives.<br />

B. Preformed Control Joint Filler:<br />

1. Regular Joint: 2-5/8 inches by 1-1/2 inches; rubber.<br />

a. RS-STANDARD Control Joint by Hohmann & Barnard, Inc., Hauppauge, NY (800) 645-0616.<br />

b. Masonry Control Joint No. 571 by Greenstreak, St. Louis, MO (800) 325-9504.<br />

2. Tee Joint: 2-5/8 inches by 1 inch; rubber.<br />

a. RS-TEE Control Joint by Hohmann & Barnard, Inc.<br />

b. Masonry Control Joint No. 572 by Greenstreak.<br />

C. Expansion Joint Filler (Compression Seal):<br />

1. Backerseal (Grayflex) expanding precompressed foam by Emseal Joint Systems, Ltd., Westborough, MA<br />

(800) 526-8365.<br />

2. Willseal 600 polyurethyene foam joint sealing tape by Willseal USA, Pelham, NH (800) 438-0684.<br />

2.3 JOINT-SEALANT BACKING (BUILDING)<br />

A. Sealant Backing (Backer Rod): Provide sealant backings of material and type that are nonstaining; are compatible<br />

with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by<br />

sealant manufacturer based on field experience and laboratory testing.<br />

1. Cylindrical Sealant Backings: Closed or bi-cellular backer rod conforming to ASTM C 1330 Type B or<br />

Type C, approved by joint-sealant manufacturer for joint application indicated, and of size and density to<br />

control sealant depth and otherwise contribute to producing optimum sealant performance. The use of<br />

ASTM C Type O open cell backer rod is prohibited.<br />

a. Backer Rod for Exterior Masonry: Closed cell foam, oversized 50 percent; self-expanding.<br />

2. Elastomeric Tubing Sealant Backings: Neoprene, butyl, EPDM, or silicone tubing complying with ASTM<br />

D 1056.<br />

B. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing<br />

sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint where such adhesion<br />

would result in sealant failure. Provide self-adhesive tape where applicable.<br />

07900 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 INTERIOR SLAB ON GRADE JOINT SEALANT MATERIALS<br />

A. Preformed Expansion (Isolation) Joint Filler (PMEJ) Strips: Flexible closed-cell synthetic foam expansion joint<br />

strips, non-extruding, for full depth of concrete.<br />

1. Ceramar Flexible Foam Expansion Joint, by W.R. Meadows.<br />

2. Deck-O-Foam Expansion Joint Filler, by W.R. Meadows.<br />

3. Expansion Joint Filler, by BASF Building Systems (Degussa) (Formerly Sonneborn Sonolastic).<br />

B. Elastomeric Joint Materials:<br />

1. Sealant:<br />

a. Polyurethane Sealant: No. 2 (P2) as specified above.<br />

b. Color: Match color of adjacent exposed surface of concrete slab.<br />

c. Sealant shall be compatible with construction material placed against it.<br />

2. Joint Back-Up Material:<br />

a. Polyethylene Foam, 100% closed cell.<br />

b. Material shall be compatible with construction material to be placed against it such as tile adhesive.<br />

C. Polyurea Joint Filler (PY1): Rapid setting, two-component polyurea polymer liquid of 100% solids content, Shore<br />

A Hardness 85 to 92, compatible with construction material placed against it (USDA compliant, unless otherwise<br />

noted).<br />

1. Spall-Pro RS 88, by Metzger/McGuire.<br />

2. Euco Qwik Joint 200 (Non-USDA), by Euclid Chemical.<br />

3. VersaFlex SL/85, by VersaFlex.<br />

4. Quick Joint 85, by CSS Polymers<br />

5. Match color of adjacent exposed surface of concrete floors.<br />

2.5 EXTERIOR SIDEWALK AND PAVEMENT JOINT MATERIALS<br />

A. Joint Back-up Material: Polyethylene foam, 100% closed cell.<br />

B. Sealant:<br />

1. Dow 888, by Dow Corning.<br />

2. 301 NS by Pecora.<br />

3. Spectrum 800 or 900 by Tremco.<br />

C. Soft Preformed Joint Filler: Flexible closed-cell non-extruding synthetic foam expansion joint strips.<br />

1. Ceramar Flexible Foam Expansion Joint, by W.R. Meadows.<br />

2. Deck-O-Foam Expansion Joint Filler, by W.R. Meadows.<br />

3. Expansion Joint Filler, by BASF Building Systems (Degussa) (Formerly Sonneborn Sonolastic).<br />

2.6 ACCESSORIES<br />

A. Primer: Non-staining type, recommended by sealant manufacturer to suit application.<br />

B. Joint Cleaner: Non-corrosive and non-staining type, recommended by sealant manufacturer; compatible with joint<br />

forming materials.<br />

2.7 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that surfaces and joint openings are ready to receive work and field measurements are as indicated on<br />

Drawings.<br />

07900 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.2 PREPARATION<br />

A. Clean and prime joints in accordance with manufacturer's instructions.<br />

B. Remove loose materials and foreign matter which might impair adhesion of sealant.<br />

C. Remove joint backing material previously inserted to protect joint from painting.<br />

D. Verify that joint backing and release tapes are compatible with sealant.<br />

E. Protect elements surrounding work of this Section from damage or disfiguration.<br />

3.3 INSTALLATION<br />

A. Install sealant in accordance with manufacturer's instructions.<br />

B. Measure joint dimensions and size materials to achieve required width/depth ratios.<br />

C. Install sealant backings of kind indicated to support sealants during application and at position required to produce<br />

cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant<br />

movement capability.<br />

1. Do not leave gaps between ends of sealant backings.<br />

2. Do not stretch, twist, puncture, or tear sealant backings.<br />

3. Remove absorbent sealant backings that have become wet before sealant application and replace them with<br />

dry materials.<br />

D. Install bond breaker where joint backing is not used.<br />

E. Apply sealant within recommended temperature ranges. Consult manufacturer when sealant cannot be applied<br />

within recommended temperature ranges.<br />

F. Install sealant free of air pockets, foreign embedded matter, ridges, and sags.<br />

G. Tool joints concave.<br />

3.4 INTERIOR SLAB ON GRADE JOINT SEALING AND FILLING<br />

A. General:<br />

1. Seal/fill contraction, isolation and construction joints in floor slabs and pavements, unless otherwise<br />

indicated on Drawings or specified herein.<br />

2. Unless noted otherwise, use polyurea joint filler in floor slab contraction and construction joints.<br />

3. Use elastomeric joint sealant in isolation joints and textured concrete joints.<br />

4. Do not seal joints under resilient flooring or carpet with materials specified herein. Reference Section<br />

09650 or 09680 for joint subfloor filler materials and placement under floor covering.<br />

B. Cleaning:<br />

1. Immediately prior to sealing/filling, clean joints to full depth of sealant/filler in accordance with<br />

manufacturer’s recommendation.<br />

2. Remove dirt, debris, saw laitance, and other foreign material from joint. Clean inner joint walls<br />

mechanically using dustless dry-cut saw, or similar tool, to the full depth of saw cuts and 2 inch minimum<br />

depth in construction joints that may have not been saw cut to create a support shelf.<br />

3. Remove form release agent, curing compound, or other components.<br />

C. General Installation:<br />

1. Commence placing floor joint sealant / filler no sooner than 30 days after first placement of concrete.<br />

2. If joint is wet or damp, allow joint to dry for 72 hours prior to filling.<br />

3. Delay floor joint sealing / filling operations until facility’s environmental systems have been placed in<br />

operation for 14 days.<br />

07900 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Mix and install sealant and filler in accordance with manufacturer’s recommendations. Use primer if<br />

recommended for specific application.<br />

5. Choke off shrinkage crack if necessary at bottom of contraction joint or void below construction joints by<br />

the following methods.<br />

a. Saw Cut Contraction Joints:<br />

1) Place 1/8 inch to 1/4 inch (maximum) layer of dry-bagged silica sand in joint to be epoxy<br />

filled. Do not use compressible backer rod.<br />

b. Construction Joints Through Slab: Fill by one of the following methods:<br />

1) Fill joint with dry-bagged silica sand to within 2 inches of slab surface.<br />

2) Insert compressible backer rod to a minimum depth of 2 inches below slab surface.<br />

6. Do not allow sealant / filler to extend over joint edges in finished condition.<br />

D. Elastomeric Joint Sealant Installation:<br />

1. Use joint back-up material.<br />

2. Tool surface where required to provide smooth, attractive appearance and geometry recommended by<br />

sealant manufacturer.<br />

E. Polyurea Joint Filler Installation:<br />

1. Installation shall be by Installer who is approved in writing by the manufacturer’s corporate office for this<br />

project.<br />

2. Do not use joint back-up material (i.e., backer rod, sand, etc.) except below bottom of saw cut in<br />

construction joints. Provide a minimum joint filler depth of 2 inches for backer rod material.<br />

3. Install test sample of the polyurea joint filler to determine if filler will leave a stain, shadow, or film on slab<br />

surface.<br />

4. If test sample reveals stain, shadow, or film, use joint filler stain preventing film at joints to receive<br />

polyurea joint filler.<br />

5. Fill joint using single pass method. Fill joint full depth from bottom to top, leave slight crown at slab<br />

surface.<br />

6. Add extra filler prior to filler set if needed to prevent depressed areas. If concave filler is already set,<br />

abrade with wire wheel or similar tool to minimum depth of 1/4” below surface prior to refilling.<br />

7. Razor off crowned filler flush with floor surface after filler has sufficiently set.<br />

8. Remove stain preventing film (if used). Film shall be removed by joint filler installer immediately after<br />

shaving joint filler.<br />

9. One week prior to Grand Opening, refill joints if:<br />

a. Joint filler sidewall separation or splitting exceeds 1/32 in.<br />

b. Joint filler surface profile is concave, crowned, or chattered or if voids occur.<br />

10. Follow manufacturer’s requirements for joint preparation for proper adhesion.<br />

F. Isolation Joints: Form isolation joints of preformed joint-filler strips (PMEJ) where indicated.<br />

1. Extend joint fillers full width and depth of joint.<br />

2. Terminate joint filler or otherwise provide joint sealant cavity of not less than 1/2 inch or more than 1 inch<br />

below finished surface if joint sealant is indicated.<br />

3. Place top of joint filler flush with finished concrete surface if joint sealant is not indicated.<br />

4. Furnish joint fillers in one-piece lengths. Where more than one length is required, lace or clip joint-filler<br />

sections together.<br />

5. Protect top edge of joint filler during concrete placement with metal, plastic, or other temporary preformed<br />

cap. Remove protective cap after concrete has been placed on both sides of joint.<br />

3.5 EXTERIOR SIDEWALK AND PAVEMENT JOINT SEALING AND FILLING<br />

A. Fill and seal sidewalk and pavement joints in areas of pavement adjacent to the building. Joint filling and sealing<br />

of sidewalks and pavement not adjacent to building is specified in Division 2.<br />

B. Joint Fillers: Extend joint fillers full-width and depth of joint, and not less than 1/2-inch or more than 1-inch<br />

below finished surface where joint sealer is indicated. Furnish joint fillers in 1-piece lengths for full width being<br />

placed, wherever possible. Where more than 1 length is required, lace or clip joint filler sections together.<br />

C. Joint Sealants: Joints shall be sealed as shown and scheduled and shall be installed in accordance with<br />

manufacturer's recommendations.<br />

07900 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.6 CLEANING<br />

A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning<br />

materials approved in writing by manufacturers of joint sealants and of products in which joints occur.<br />

3.7 SCHEDULE<br />

A. Provide sealants in accordance with the following schedule as applicable. Joint sealing required by the drawings<br />

or required for a complete and proper installation but not listed in the following schedule shall be sealed as<br />

necessary regardless of whether shown or scheduled. Such joints not shown or scheduled shall be sealed with<br />

sealants consistent with specified materials or as recommended by the manufacturer for the specific application.<br />

SITE<br />

MATERIAL TO<br />

Concrete Sidewalk Control<br />

Joint<br />

Concrete Sidewalk<br />

Expansion Joint<br />

Concrete Sidewalk<br />

Expansion Joint<br />

Patterned Concrete<br />

Expansion Joint<br />

EXTERIOR JOINTS<br />

MATERIAL<br />

Concrete Sidewalk 1/4"<br />

JOINT<br />

WIDTH<br />

Concrete Curb 1/2" Same<br />

CMU Wall 1/2" Same<br />

SEALANT TYPE<br />

Sidewalks adjacent<br />

to Building: See<br />

MATERIALS Par.<br />

Otherwise: See<br />

Division 2.<br />

Concrete Sidewalk 1/2" See Division 2.<br />

BUILDING WALL<br />

Concrete Paving Control<br />

Joint<br />

Concrete Paving Expansion<br />

Joint<br />

Concrete Paving Expansion<br />

Joint<br />

Concrete Paving Expansion<br />

Joint<br />

Concrete Stair Expansion<br />

Joint<br />

Concrete Stair Expansion<br />

Joint<br />

Concrete Stair Expansion<br />

Joint<br />

Concrete Curb Expansion<br />

Joint<br />

Concrete Curb Expansion<br />

Joint<br />

CMU Wall Control Joint,<br />

3/8"<br />

CMU Wall Expansion Joint,<br />

1"<br />

Concrete Paving 1/4"<br />

Concrete Paving 1/2" Same<br />

Concrete Stem Wall 1/2" Same<br />

Concrete Floor Slab 1/2" Same<br />

CMU Wall 1/2" P1 or P3<br />

Concrete Stem Wall 1/2" P1 or P3<br />

Concrete Paving 1/2" P1 or P3<br />

Pavement adjacent<br />

to Building: See<br />

MATERIALS Par.<br />

Otherwise: See<br />

Division 2.<br />

Concrete Curb 1/2" See Division 2<br />

CMU Wall 1/2" Same<br />

CMU Wall 3/8" P1 or P3<br />

CMU Wall 1" P1 or P3<br />

EIFS Wall CMU Wall 1/2" P1 or P3<br />

07900 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


EXTERIOR JOINTS<br />

MATERIAL TO MATERIAL<br />

JOINT<br />

WIDTH<br />

SEALANT TYPE<br />

EIFS Wall Cast Concrete Shapes 1/2" P1 or P3<br />

EIFS Wall Expansion Joint EIFS Wall 1” P1 or P3<br />

EIFS Cornice/Trim EIFS Cornice/Trim 1/2" P1 or P3<br />

EIFS Cornice/Trim CMU Wall 1/2" P1 or P3<br />

WALL FLASHING Metal Flashing Metal Flashing S1<br />

Metal Flashing CMU Wall 1/4" P1 or P3<br />

Metal Flashing EIFS Wall 1/4" P1 or P3<br />

Metal Flashing<br />

Aluminum Storefront<br />

Frame<br />

1/4" P1 or P3<br />

SOFFITS Gypsum Soffit Control Joint Gypsum Soffit 3/8" P1 or P3<br />

Gypsum Soffit Perimeter<br />

Expansion Joint<br />

EIFS 3/8" P1 or P3<br />

Gypsum Soffit Perimeter<br />

Expansion Joint<br />

CMU Wall 3/8" P1 or P3<br />

Metal Soffit Panel Trim EIFS P1 or P3<br />

Metal Soffit Panel Trim CMU Wall P1 or P3<br />

WALL<br />

PENETRATIONS<br />

Aluminum Storefront Frame<br />

Aluminum Storefront<br />

Frame<br />

1/4" P1 or P3<br />

Aluminum Storefront Frame CMU Wall 1/4" P1 or P3<br />

Aluminum Storefront Frame EIFS Wall 1/4" P1 or P3<br />

Aluminum Storefront Sill Cast Concrete Shapes 1/4" P1 or P3<br />

Aluminum Storefront Sill Concrete Slab 1/4" P1 or P3<br />

Aluminum Storefront Door<br />

Threshold<br />

Concrete Slab<br />

P1 or P3<br />

Translucent Insulated Panels<br />

Translucent Insulated<br />

Panels<br />

1/4" S1<br />

Translucent Insulated Panels EIFS Wall 1/4" S1<br />

Translucent Insulated Panels Metal Flashing 1/4" S1<br />

Hollow Metal Door Frame CMU Wall 1/4" P1 or P3<br />

Hollow Metal Door Frame Tube Steel Frame 1/4" P1 or P3<br />

Hollow Metal Door<br />

Threshold<br />

Concrete Slab<br />

P1 or P3<br />

Steel Corner Angle Frame CMU Wall 1/4" P1 or P3<br />

Steel Pipe Through CMU Wall 1/2" P1 or P3<br />

Steel Pipe Through EIFS Wall 1/2" P1 or P3<br />

Steel Pipe Through Concrete Wall 1/2" P1 or P3<br />

Steel Conduit Through CMU Wall 1/2" P1 or P3<br />

Steel Conduit Through EIFS Wall 1/2" P1 or P3<br />

Steel Conduit Through Concrete Wall 1/2" P1 or P3<br />

Ganged Steel Conduit<br />

Through<br />

Ganged Steel Conduit<br />

Through<br />

CMU Wall 1/2" P3<br />

EIFS Wall 1/2" P3<br />

07900 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


MATERIAL TO<br />

Ganged Steel Conduit<br />

Through<br />

EXTERIOR JOINTS<br />

MATERIAL<br />

JOINT<br />

WIDTH<br />

Concrete Wall 1/2" P3<br />

PVC Pipe Through CMU Wall 1/2" P1 or P3<br />

PVC Pipe Through EIFS Wall 1/2" P1 or P3<br />

PVC Pipe Through Concrete Wall 1/2" P1 or P3<br />

Copper Pipe Through CMU Wall 1/2" P1 or P3<br />

Copper Pipe Through EIFS Wall 1/2" P1 or P3<br />

Copper Pipe Through Concrete Wall 1/2" P1 or P3<br />

SEALANT TYPE<br />

ROOF MEMBRANE<br />

AREA<br />

Roofing Membrane Roofing Membrane See Section 07500<br />

Roofing Membrane<br />

Waterproof Wall<br />

Membrane<br />

See Section 07500<br />

Roofing Membrane Metal Fascia See Section 07500<br />

Roofing Membrane<br />

Molded Pipe<br />

Flashing<br />

See Section 07500<br />

Waterproof Membrane Metal Fascia P1 or P3<br />

Waterproof Membrane<br />

Metal Plates and<br />

Bolts<br />

P1 or P3<br />

Waterproof Membrane Steel Conduit 1/2" P1 or P3<br />

Metal Cap Flashing Joint Metal Cap Flashing 1/8" S1<br />

Metal Cap Flashing<br />

Expansion Joint<br />

Metal Cap Flashing 1" S1<br />

Metal Cap Flashing Gasketed Fasteners S1<br />

Skylight Flashing Joints Skylight Flashing S1<br />

Vent Flashing Joints Vent Flashing S1<br />

Smoke Vent Flashing Joints Smoke Vent Flashing S1<br />

RTU Flashing Joints RTU Flashing S1<br />

Waterproof Membrane<br />

Termination Bar<br />

CMU Wall 1/4" S1<br />

Steel Gutter Steel Gutter S1<br />

Steel Gutter Steel Downspout S1<br />

Steel Downspout Steel Downspout S1<br />

Urethane Rubber Seal<br />

System<br />

Steel Pipe/ Flue Varies See Section 07500<br />

ROOF<br />

METAL/<br />

FIBERGLASS<br />

PANELS<br />

Roof Panel<br />

Flue Penetration<br />

Flashing<br />

P1 or P3<br />

Roof Panel Gutter P1 or P3<br />

Roof Panel End Closure P1 or P3<br />

07900 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


MATERIAL TO<br />

INTERIOR JOINTS<br />

MATERIAL<br />

FLOOR Concrete Floor: Concrete Floor<br />

Contraction and<br />

Construction Joint<br />

JOINT<br />

WIDTH<br />

1/4"<br />

Expansion Joint 3/4" Same<br />

Isolation Joint<br />

See<br />

Dwgs<br />

Same<br />

Concrete Curb In Grocery Concrete Floor Same<br />

Ceramic Tile Expansion<br />

Joints<br />

Quarry Tile Expansion<br />

Joints<br />

Floor Joints Beneath Floor<br />

Finish Materials (VCT or<br />

PVC Flooring or Carpet)<br />

SEALANT TYPE<br />

See Par<br />

MATERIALS<br />

Ceramic Tile Manuf P1 or P3<br />

Quarry Tile Manuf P1 or P3<br />

Mop Sink Floor P1 or P3<br />

Transition Strip (Korlyte) Concrete Slab PY1<br />

See Section 09650<br />

(Resilient Flooring)<br />

See Section 09680<br />

(Carpet)<br />

Sanitary Cove Base (SCB) Floor See Section 09655<br />

Wood Base Concrete Floor P1 or P3<br />

WALLS<br />

CMU Wall Control Joint,<br />

3/8"<br />

CMU Wall Expansion Joint,<br />

1"<br />

Rated Gypsum Board Wall<br />

Control Joint<br />

Rated Gypsum Board Wall<br />

CMU Wall 3/8" P1<br />

CMU Wall 1" P1<br />

Rated Gypsum Board<br />

Wall<br />

Metal Roof Deck<br />

See Section 07840 -<br />

Firestopping<br />

Rated Gypsum Board Wall Rated CMU Wall Same<br />

Gypsum Board CMU Walls 3/8" P1<br />

Cement Board Cement Board P1 or P3<br />

Cement Board Gypsum Board P1 or P3<br />

Ceramic Tile Wood Trim P1 or P3<br />

Ceramic Tile<br />

Galvanized Steel Base<br />

Trim<br />

P1 or P3<br />

Ceramic Tile Stainless Steel S1 or S2<br />

Ceramic Tile Ceramic Tile P1 or P3<br />

Non-Fiberglass Reinforced Galvanized Steel Base<br />

Wall Panel (NRP)<br />

Trim<br />

S1 or S2<br />

Non-Fiberglass Reinforced<br />

Wall Panel (NRP)<br />

Ceramic Tile<br />

S1 or S2<br />

Stainless Steel Corner<br />

Guards<br />

Ceramic Tile<br />

S1 or S2<br />

Stainless Steel Corner<br />

Guards<br />

Wall<br />

S1 or S2<br />

Plastic Base<br />

Grocery Equipment<br />

Wall<br />

P1 or P3<br />

Plastic Base Ceramic Tile Wall P1 or P3<br />

Plastic Base Gypsum Board Wall P1 or P3<br />

Plastic Base Concrete Floor P1 or P3<br />

Plastic Base Quarry Tile Floor P1 or P3<br />

07900 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


INTERIOR JOINTS<br />

MATERIAL TO MATERIAL<br />

JOINT<br />

WIDTH<br />

SEALANT TYPE<br />

Sanitary Cove Base (SCB) Wall See Section 09655<br />

Joints shown on the<br />

drawings to be sealed with<br />

Expanding Foam Sealant<br />

EF1<br />

Wood Base Plywood Wainscot P1<br />

WALL<br />

PENETRATIONS<br />

Aluminum Storefront Frame<br />

Alum Storefront<br />

Frame<br />

1/4" P1<br />

Aluminum Storefront Frame CMU Wall 1/4" P1<br />

Aluminum Storefront Frame Gypsum Board Wall 1/4" P1<br />

Aluminum Storefront Sill Cast Concrete Shapes 1/4" P1<br />

Aluminum Storefront Sill Gypsum Board Wall 1/4" P1<br />

Hollow Metal Door Frame CMU Wall 1/4" P1<br />

Hollow Metal Door Frame Gypsum Board Wall 1/4" P1<br />

Steel Structural Member<br />

Through<br />

Gypsum Board Wall 1/4” P1<br />

Steel Corner Angle Frame CMU Wall 1/4" P1<br />

Steel Pipe Through CMU Wall 1/2" P1<br />

Steel Pipe Through Gypsum Board Wall 1/4" P1<br />

Steel Conduit Through CMU Wall 1/2" P1<br />

Steel Conduit Through Gypsum Board Wall 1/4" P1<br />

PVC Pipe Through CMU Wall 1/2" P1<br />

PVC Pipe Through Gypsum Board Wall 1/2" P1<br />

Copper Pipe Through CMU Wall 1/2" P1<br />

Copper Pipe Through Gypsum Board Wall 1/2" P1<br />

Steel Pipe Through Rated CMU Wall See Section 07840<br />

Steel Pipe Through Rated Gyp Board Wall See Section 07840<br />

Steel Conduit Through Rated CMU Wall See Section 07840<br />

Steel Conduit Through Rated Gyp Board Wall See Section 07840<br />

PVC Pipe Through Rated CMU Wall See Section 07840<br />

PVC Pipe Through Rated Gyp Board Wall See Section 07840<br />

Copper Pipe Through Rated CMU Wall See Section 07840<br />

Copper Pipe Through Rated Gyp Board Wall See Section 07840<br />

TOILET FIXTURES<br />

Sink Ceramic Tile Wall S2<br />

Floor Mount Toilet Ceramic Tile Floor S2<br />

Wall Mount Toilet Ceramic Tile Wall S2<br />

Wall Mount Urinal Ceramic Tile Wall S2<br />

07900 - 11<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


GROCERY<br />

EQUIPMENT<br />

INTERIOR JOINTS<br />

MATERIAL TO MATERIAL<br />

JOINT<br />

WIDTH<br />

SEALANT TYPE<br />

Pre-manufactured Freezer<br />

/Cooler<br />

Concrete Curb<br />

P1 or P3<br />

Refrigerated Case Trim Refrigerated Case S1 or S2<br />

Refrigerated Case Trim Concrete S1 or S2<br />

Non-Fiberglass<br />

Stainless Steel Equipment Reinforced Plastic<br />

S1 or S2<br />

(NRP) Wall Panels<br />

Stainless Steel Equipment Ceramic Tile S1 or S2<br />

EWC Electric Water Coolers Ceramic Tile P1 or P3<br />

COUNTER TOPS<br />

Plastic Laminate Counter<br />

Tops<br />

Plastic Laminate Counter<br />

Tops<br />

Gypsum Board Walls<br />

Plastic Laminate<br />

Walls<br />

S2<br />

S2<br />

END OF SECTION<br />

07900 - 12<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 08110 (08 1100) – STEEL DOORS AND FRAMES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished steel doors, panels, frames.<br />

2. Owner furnished glazed light frames.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: Products provided by Owner and installed by Contractor.<br />

2. Section 04200 - Unit Masonry Assemblies: Masonry mortar fill of metal frames. Placement of anchors<br />

into wall construction.<br />

3. Section 08710 - Door Hardware: Door hardware coordination.<br />

4. Section 08337 - Coiling Counter Shutters.<br />

5. Section 08800 - Glazing: Glass in steel doors and frames.<br />

6. Section 09250 - Gypsum Board: Door frame attachment to metal wall framing.<br />

7. Section 09900 - Paints and Coatings: Field painting of doors and frames.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI A250.6 - Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames.<br />

2. ANSI A250.8 (Formerly SDI-100) - Recommended Specifications for Standard Steel Doors and Frames.<br />

3. ANSI A250.10 - Test Procedure and Acceptance Criteria for Prime Painted Steel Surfaces for Steel Doors<br />

and Frames.<br />

4. ANSI A250.11 (Formerly SDI-105) - Recommended Erection Instructions for Steel Frames.<br />

C. ASTM International (ASTM):<br />

1. ASTM C 578 - Rigid, Cellular Polystyrene Thermal Insulation.<br />

2. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

D. National Fire Protection Association (NFPA):<br />

1. NFPA 80 - Fire Doors and Windows.<br />

2. NFPA 252 - Fire Tests for Door Assemblies.<br />

E. Underwriters Laboratories (UL):<br />

1. UL 10B - Fire Tests of Door Assemblies.<br />

1.3 QUALITY ASSURANCE<br />

A. Regulatory Requirements:<br />

1. Installed Fire Rated Door Assemblies: Conform to NFPA 80, NFPA 252, and UL 10B for fire rated class,<br />

as indicated on Drawings.<br />

1.4 DELIVERY, STORAGE AND PROTECTION<br />

A. Section 01600 - Product Requirements: Transport, handle, store, and protect products.<br />

08110 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Product Delivery: Owner’s Supplier will make delivery of products to jobsite ready for installation. Contractor<br />

shall contact to establish a product delivery and installation date and establish a coordination procedure.<br />

C. Product Compliance Inspection: Inspect delivered products for compliance with product descriptions in Part 2<br />

herein. Report discrepancies to the Architect.<br />

D. Product Packaging: Doors will be shipped in manufacturer's standard packaging with identification markings on<br />

each component or package.<br />

E. Acceptance at Site: Receive products as specified in Section 01640.<br />

F. Verify quantity of products furnished with Bills of Lading provided with products.<br />

1. Report discrepancies in product quantity delivered, or damage to products delivered to Owner immediately.<br />

Upon notification, Owner will arrange for delivery of replacement products. Note description of product<br />

quality discrepancies and/or product damage on Bill of Lading.<br />

G. Manufacturing Defects: Report suspected product manufacturing defects to Wal-Mart Construction Manager and<br />

Owner's Supplier. Upon notification, Owner will arrange for repair of manufacturing defects.<br />

H. Protect doors and frames with resilient packaging. Break seal on-site to permit ventilation.<br />

1.5 PROJECT CONDITIONS<br />

A. Field Measurements: Verify that field measurements are as indicated on shop drawings.<br />

B. Coordination: Coordinate the work with door opening construction, door frame and door hardware installation.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner’s steel door and frame Supplier will furnish steel doors and frames specified herein under provisions of<br />

Section 01640 for installation by Contractor.<br />

1. Owner’s Supplier: D.H. Pace Inc., Springfield, MO, Mark Lyons, (417) 831-5585,<br />

mark.lyons@dhpace.com<br />

B. Descriptions and related provisions of products by Owner’s Supplier as specified herein are included as<br />

requirements for supplier of equipment to be furnished by Owner and are included as information only to<br />

Contractor.<br />

2.2 DOORS FURNISHED BY OWNER<br />

A. Interior Doors: ANSI A250.8, Level 1 and Physical Performance Level C (Standard-Duty), 1-3/4 inches thick,<br />

Model 1 (Full Flush), 0.032 min. thickness (20 gage) cold-rolled steel, optional core construction as specified<br />

below.<br />

B. Exterior Doors: ANSI A250.8; Level 2 and Physical Performance Level B (Heavy Duty), 1-3/4 inches thick,<br />

Model 1, (Full Flush), 0.042 min. thickness (18 gage), ASTM A 653, Commercial Steel (CS), Type B, with an<br />

A60 zinc-iron-alloy (galvannealed) coating cold-rolled steel, polyurethane or polystyrene foam insulated core<br />

construction as specified below.<br />

1. Fabricate head flush with top edge to exclude water.<br />

08110 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Core Construction:<br />

1. Manufacturer’s standard Kraft-paper honeycomb, polystyrene, polyurethane, polyisocyanurate, mineral<br />

board of vertical steel stiffener core.<br />

a. Fire Door Core: As required to provide fire-protection ratings indicated.<br />

b. Thermal-Rated (Insulated) Doors: R-value of not less than 2 when tested according to ASTM<br />

C1363. Strength of bond between core and steel face sheet shall exceed strength of core so that<br />

delamination will not occur under operating conditions.<br />

2.3 FRAMES FURNISHED BY OWNER<br />

A. Interior Drywall Frames: 0.053 min. thickness (16 gage), cold-rolled steel, mitered welded units.<br />

1. Jamb Depth: Sized to fit wall thickness.<br />

B. Interior Masonry Frames: 0.053 min. thickness (16 gage), cold-rolled steel, mitered and welded units.<br />

1. Jamb Depth: Sized to fit wall thickness.<br />

C. Exterior Frames: 0.053 min. thickness (16 gage) steel, A60 galvannealed coating (ASTM A 653), mitered and<br />

welded units.<br />

1. Jamb Depth: 5-3/4", unless otherwise indicated on Drawings.<br />

2.4 FRAME ANCHORS FURNISHED BY OWNER<br />

A. Jamb Anchors:<br />

1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit frame size, not less than 0.042<br />

inch thick, with corrugated or perforated straps not less than 2 inches wide by 10 inches long; or wire<br />

anchors not less than 0.177 inch thick.<br />

2. Stud-Wall Type: Designed to engage stud, welded to back of frames; not less than 0.042 inch thick.<br />

3. Compression Type for Drywall Slip-on Frames: Adjustable compression anchors.<br />

B. Floor Anchors: Formed from same material as frames, not less than 0.042 inch thick.<br />

2.5 ACCESSORIES FURNISHED BY OWNER<br />

A. Rubber Silencers: Resilient rubber. Specified in Section 08710.<br />

B. Glazing Stops: Rolled steel channel shape, butted corners; prepared for countersink style screws.<br />

C. Plaster Guards: Provide 26 gage steel plaster guards or mortar boxes, welded to frame, at back of hardware<br />

cutouts in masonry openings.<br />

2.6 ACCESSORIES PROVIDED BY CONTRACTOR<br />

A. Board Insulation Blocking: ASTM C 578, Type IV (density 1.6 pcf minimum), 1 inch thick. Provide one of the<br />

following or equivalent by another manufacturer:<br />

1. Greenguard - CM, by Pactiv Building Products, Atlanta, Georgia (800) 241-4402, www.green-guard.com<br />

2. Styrofoam SM, by The Dow Chemical Co, Midland MI, (800) 232-2436, www.dow.com/styrofoam<br />

3. Foamular 250, by Owens-Corning, (800) 438-7465, www.owenscorning.com<br />

B. Glazed Lights in Fire-Rated Doors: Provide UL Labeled Fire-Rated Glass Assembly specified in Section 08800.<br />

2.7 PROTECTIVE COATINGS<br />

A. Bituminous Coating: Fibered asphalt emulsion, field applied.<br />

08110 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.8 FABRICATION<br />

A. Fabricate hollow metal work to be rigid and free of defects, warp, or buckle. Accurately form metal to required<br />

sizes and profiles, with minimum radius for thickness of metal. Where practical, fit and assemble units in<br />

manufacturer's plant. To ensure proper assembly at site, clearly identify work that cannot be permanently factory<br />

assembled before shipment.<br />

B. Fabricate doors and frames in accordance with ANSI A250.8.<br />

C. Fabricate concealed stiffeners, edge channels, and hardware reinforcement from either cold- or hot-rolled steel<br />

sheet.<br />

D. Hollow Metal Doors:<br />

1. Exterior Doors: Provide weep-hole openings in bottom of exterior doors to permit moisture to escape.<br />

Seal joints in top edges of doors against water penetration.<br />

2. Glazed Lites: Factory cut openings in doors.<br />

3. Fabricate top and bottom edges of doors with closures of same material as face sheets.<br />

E. Hollow Metal Frames: Where frames are fabricated in sections due to shipping or handling limitations, provide<br />

alignment plates or angles at each joint, fabricated of same thickness metal as frames.<br />

1. Welded Frames: Weld flush face joints continuously; grind, fill, dress, and make smooth, flush, and<br />

invisible.<br />

2. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed fasteners unless otherwise<br />

indicated.<br />

3. Grout Guards: Weld guards to frame at back of hardware mortises in frames to be grouted.<br />

4. Floor Anchors: Weld anchors to bottom of jambs and mullions with at least four spot welds per anchor.<br />

5. Fabricate frames to suit masonry wall coursing with 4 inch head member.<br />

F. Transom Bars for Glazed Lights: Fixed type, of same profiles as jamb and head.<br />

G. Silencers: Prepare frames for silencers.<br />

1. Single Doors: Provide 3 single rubber silencers on strike side.<br />

2. Double Doors with Mullions: Provide 3 single rubber silencers on each door, on strike side.<br />

3. Double Doors without Mullions: Provide 2 single silencers on frame head.<br />

H. Fire Rated Doors and Frames: Attach fire rated label to each door and each frame unit. Do not paint over labels.<br />

I. Undercut non-fire rated doors as indicated on drawings.<br />

J. Where multiple openings are indicated, fabricate double wide frames of material gauge as scheduled. Joint frames<br />

at swing jamb using minimum 16 gauge insert spline connection full length. After assembly, fill joint with epoxy<br />

filler, allow to harden, and finish smooth and flush.<br />

1. Fabricate impost base anchor, providing for minimum of two anchors per impost. Base shall fit impost<br />

inside profile with "force fit".<br />

K. Hardware Preparation: Factory prepare hollow metal work to receive templated mortised hardware as specified in<br />

Section 08710.<br />

1. Fabricate doors and frames with hardware reinforcement welded in place.<br />

2. Locate hardware as indicated, or if not indicated, according to ANSI A250.8.<br />

3. Reinforce doors and frames to receive nontemplated, mortised and surface-mounted door hardware.<br />

4. Comply with applicable requirements in ANSI A250.6 for preparation of hollow metal work for hardware.<br />

5. Coordinate locations of conduit and wiring boxes for electrical connections with Division 16 Electrical<br />

Sections.<br />

6. Provide mortar guard boxes.<br />

08110 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.9 STEEL FINISHES<br />

A. Prime Finish: Apply manufacturer's standard primer immediately after cleaning and pretreating.<br />

B. Shop Primer: Manufacturer's standard, fast-curing, lead- and chromate-free primer complying with<br />

ANSI/SDI A250.10 acceptance criteria; recommended by primer manufacturer for substrate; compatible with<br />

substrate and field-applied coatings despite prolonged exposure.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify substrate conditions, opening sizes and tolerances are acceptable for proper installation.<br />

3.2 INSTALLATION<br />

A. Install frames in accordance with ANSI A250.11.<br />

B. Install doors in accordance with ANSI A250.8.<br />

C. Do not field cut hollow metal doors.<br />

D. Coordinate with adjacent wall construction for anchor placement.<br />

E. Coordinate installation of glass and glazing.<br />

F. Coordinate installation of doors with installation of hardware specified in Section 08710.<br />

G. Provide board insulation blocking at exterior hollow metal frames. Glue blocking in frame jambs (strike side and<br />

hinge side) at height indicated on Drawings.<br />

H. Factory install glazed light assemblies in accordance with manufacturer's published instructions for fire-rating<br />

required and compliance with referenced standards.<br />

3.3 ADJUSTING AND CLEANING<br />

A. Test for smooth operation through full range of swing; make necessary adjustments.<br />

B. Coordinate adjustment of doors with installation of hardware. Adjust doors and hardware for smooth and balanced<br />

door movement.<br />

END OF SECTION<br />

08110 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 033111<br />

SECTION 08311 (08 3113) – ACCESS DOORS AND FRAMES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Secton Includes:<br />

1. Fire-rated and Non-Fire rated access doors and frames for walls and ceilings.<br />

B. Related Requirements:<br />

1. Section 09250 - Gypsum Board: Openings in gypsum board ceilings.<br />

2. Section 09900 - Paints and Coatings: Field paint finish.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

2. ASTM A879 - Steel Sheet, Zinc Coated by the Electrolytic Process for Applications Requiring Designation<br />

of the Coating Mass on Each Surface.<br />

3. ASTM A1008 - Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength<br />

Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable.<br />

4. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and Materials.<br />

C. National Fire Protection Association (NFPA):<br />

1. NFPA 80 - Fire Doors and Windows.<br />

2. NFPA 252 - Fire Tests for Door Assemblies.<br />

D. Underwriters Laboratories (UL):<br />

1. UL 10B - Fire Tests of Door Assemblies.<br />

2. UL 263 - Fire Tests Of Building Construction And Materials.<br />

1.3 QUALITY ASSURANCE<br />

A. Perform Work in accordance with UL requirements.<br />

B. Fire-Rated Access Doors and Frames: Provide units complying with NFPA 80 that are identical to assemblies<br />

tested for fire-test-response characteristics per the following test method and that are listed and labeled by UL or<br />

another testing and inspecting agency acceptable to authorities having jurisdiction:<br />

1. NFPA 252 or UL 10B for vertical access doors and frames.<br />

2. ASTM E 119 or UL 263 for horizontal access doors and frames.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Provide access doors by one of the following manufacturers:<br />

1. Milcor, Inc. (Commercial Products Group), Bensenville, IL (630) 595-7320, Don Fessenden.<br />

2. Acudor Products, Inc., Fairfield, NJ (800) 722-0501.<br />

3. Nystrom Building Products, Minneapolis, MN (800) 547-2635 or (612) 781-7850.<br />

B. Substitutions: Not Permitted.<br />

08311 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 STEEL MATERIALS<br />

A. Steel Sheet: Uncoated or electrolytic zinc-coated, ASTM A 879 with cold-rolled steel sheet substrate complying<br />

with ASTM A 1008, Commercial Steel (CS), exposed.<br />

B. Metallic-Coated Steel Sheet: ASTM A 653, Commercial Steel (CS) with A60 zinc-iron-alloy (galvannealed)<br />

coating or G60 mill-phosphatized zinc coating.<br />

C. Drywall Beads: 0.0299-inch zinc-coated steel sheet to receive joint compound.<br />

D. Manufacturer's standard finish factory primed finish.<br />

2.3 ACCESS DOORS AND FRAMES FOR WALLS AND CEILINGS<br />

A. Flush Access Doors and Frames:<br />

1. Fabricated from steel sheet.<br />

2. Exposed Trim Type:<br />

a. Model NT by Nystrom.<br />

b. Model M 3202 by Milcor.<br />

c. Model UF 5000 by Acudor.<br />

3. Trimless Frame:<br />

a. Model MW by Nystrom.<br />

b. Model DW 3203 by Milcor.<br />

c. Model DW 5040 by Acudor.<br />

4. Locations: Wall and ceiling.<br />

5. Door: Minimum 0.060-inch- thick sheet metal.<br />

6. Frame: Minimum 0.060-inch- thick sheet metal with 1-1/4-inch- wide, surface-mounted trim.<br />

7. Hinges: Spring-loaded, concealed-pin type or continuous piano.<br />

8. Latch: Cam latch with interior release. Provide latch for all units unless specified to have locks.<br />

9. Lock: Cylinder with 2 keys. Provide lockable cylinders as follows:<br />

a. Exterior locations.<br />

10. Units larger than 24 inches on the hinge side shall have two locks or latches.<br />

B. Fire Rated, Insulated, Flush Access Doors and Frames.<br />

1. Fabricated from steel sheet.<br />

2. Exposed Trim or Trimless Type:<br />

a. Model IT or IW by Nystrom.<br />

b. Model UFR 3218 by Milcor.<br />

c. Model FW 5050 by Acudor.<br />

3. Locations: Wall and ceiling surfaces.<br />

4. Fire-Resistance Rating: Not less than that of adjacent construction.<br />

5. Temperature Rise Rating: 250 deg F at the end of 30 minutes.<br />

6. Door: Flush panel with a core of mineral-fiber insulation enclosed in sheet metal with a minimum<br />

thickness of 0.036 inch.<br />

7. Frame: Minimum 0.060-inch- thick sheet metal with 1-inch- wide, surface-mounted trim.<br />

8. Hinges: Concealed-pin type or continuous piano.<br />

9. Automatic Closer: Spring type.<br />

10. Latch: Self-latching device operated with interior release.<br />

C. Size: Minimum 24 x 36 inches except where otherwise shown on the drawings.<br />

1. Trash Chute Door: Coordinate size of trash chute access door with trash compactor vendor.<br />

08311 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 EXTERIOR INSULATED ACCESS DOORS<br />

A. Exterior Insulated Access Door and Frame Unit: For installation in exterior walls to interstitial space above<br />

vestibule. Insulated and gasketed door and frame unit with exterior key-operated handle. Steel, prime painted<br />

grey, 24 x 36 inches min. unless otherwise indicated.<br />

1. Product Number XTL2436, by Nystrom.<br />

2. Substitutions: Similar product by other manufacturers.<br />

2.5 FINISH<br />

A. Base Metal Protection: Factory prime coat units with electrostatic baked on electrostatic powder. For ceiling<br />

units, prime exposed edges with coat of rust-inhibitive paint.<br />

PART 3 - EXECUTION<br />

3.1 INSPECTION<br />

A. Verify rough openings for door and frame are correctly sized and located.<br />

B. Beginning of installation means acceptance of existing conditions.<br />

3.2 INSTALLATION<br />

A. Install units in accordance with manufacturer's instructions.<br />

B. Install units plumb, square and flush with adjacent ceiling or wall surface. Secure rigidly in place.<br />

C. Position to provide convenient access to concealed work requiring access.<br />

D. Provide weather tight installation at exterior locations.<br />

3.3 ACCESS DOOR SCHEDULE<br />

A. Provide access door and frame suitable for the application.<br />

B. Install trimless access door and frame in interior gypsum board walls and ceilings and other locations suitable and<br />

adaptable for trimless installation.<br />

C. Install exposed trim access door and frame where at exterior locations and where impractical to install trimless<br />

installation.<br />

D. Install access doors in ceilings and walls in locations as shown on the Drawings, at valves, controls, and manual<br />

dampers requiring access, and as required by code and governing authorities.<br />

E. For access doors adjacent to secure areas (Cash/Counting Room), coordinate location with Wal-Mart Construction<br />

Manager.<br />

END OF SECTION<br />

08311 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 08332 (03 3315) – OVERHEAD ROLLING CLOSURE<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Owner furnished overhead rolling closure, motor operated, for Pharmacy, for installation by<br />

Contractor.<br />

1.2 QUALITY ASSURANCE<br />

A. Installer Qualifications: Approved by overhead rolling closure manufacturer.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Handle, deliver, and store in manufacturer's original packaging, following manufacturer's recommendations.<br />

C. Receive Owner Furnished products in compliance with the requirements of Section 01640.<br />

D. Store in a dry area and in a manner to prevent damage.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's supplier will furnish overhead rolling closures and accessories<br />

specified herein for installation by the Contractor.<br />

B. Descriptions and specifications of Owner furnished items and equipment hereinafter are included as information to<br />

the Contractor only and not to be considered as Contractor requirements unless otherwise stated.<br />

2.2 MANUFACTURER<br />

A. Wal-Mart Supplier: QMI Security Solutions, Itasca, IL (800) 446-2500, FAX (630)980-6364.<br />

2.3 OVERHEAD ROLLING CLOSURE (WAL-MART FURNISHED – CONTRACTOR INSTALLED)<br />

A. Model: Countersafe Rolling Shutter System, curtain style AL6-E-51, by QMI.<br />

B. Description: Aluminum overhead coiling security curtain with continuous C sections of extruded slats.<br />

C. Substitutions: Comply with the requirements of Section 01600.<br />

2.4 COMPONENTS<br />

A. Side Track: Extruded aluminum tracks lined with insulation, woven polypropylene runners. Color: To match<br />

slats.<br />

B. Mounting: Manufacturer’s standard mounting hardware for mounting as shown on the drawings.<br />

C. Bottom Bar: Heavy duty extruded aluminum section, 0.050-inch wall thickness.<br />

08332 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Locking Mechanism: Two, thumb-turn “Best” cylinder locks installed in bottom bar, one at each end, operable<br />

from the interior of the pharmacy.<br />

E. Counterbalance: Tempered helical torsion high cycle spring mounted on housings and solid torsion rods<br />

permanently lubricated and enclosed within steel pipe shaft.<br />

F. End Caps: Steel end plates no less than 3/16” thick bolted to structural support tubes.<br />

G. Finishes: Manufacturer's standard clear anodized coating on exposed aluminum; manufacturer’s standard finish<br />

on other metal components.<br />

H. Operator: Motor operated.<br />

I. Motor: Single phase 110V-60Hz UL recognized. Motor Model/Size EHJ. Provide emergency egress device<br />

allowing manual operation in case of power outage.<br />

J. Interior aluminum overhead coiling security grille designed for pharmacy applications with integrated anti push up<br />

security features.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATIONBY CONTRACTOR<br />

A. Install assembly in accordance with manufacturer's published instructions.<br />

B. Use anchorage devices to securely fasten assembly to supporting construction and building framing without<br />

distortion or stress.<br />

C. Securely and rigidly brace components suspended from structure. Fit and align assembly including hardware.<br />

Level and plumb to provide smooth operation.<br />

D. Adjust installations to operate smoothly and easily. Clean surfaces with manufacturer’s recommended cleaners.<br />

END OF SECTION<br />

08332 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 08337 (08 3314) – COILING COUNTER SHUTTERS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Owner furnished pharmacy coiling counter shutter doors for installation by Contractor.<br />

B. Related Requirements:<br />

1. Section 07900 - Joint Sealants: Installation of sealant at visible joints around frames and tracks.<br />

1.2 QUALITY ASSURANCE<br />

A. Installer Qualifications: Approved by coiling counter shutter door manufacturer.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Handle, deliver, and store in manufacturer's original packaging, following manufacturer's recommendations.<br />

C. Receive Owner Furnished products in compliance with the requirements of Section 01640.<br />

D. Store in a dry area and in a manner to prevent damage.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's supplier will furnishcoiling counter shutters and accessories specified<br />

herein for installation by Contractor.<br />

B. Product descriptions and specifications of Owner furnished items and equipment hereinafter are included as<br />

information to the Contractor only and not to be considered as Contractor requirements unless otherwise stated.<br />

2.2 MANUFACTURER<br />

A. Wal-Mart Supplier will be QMI Security Solutions, Elmhurst, IL (630) 529-7111.<br />

2.3 COILING COUNTER SHUTTERS (WAL-MART FURNISHED - CONTRACTOR INSTALLED)<br />

A. Model: CounterSafe Rolling Shutter System, curtain type AL6-E-P-51, by QMI.<br />

B. Description: Aluminum extruded profile with locking device.<br />

C. Operation:<br />

1. Manual strap operation for curtains 3 feet wide or less.<br />

2. Geared pole crank operation for curtains greater than 3 feet wide.<br />

D. Color: Grey.<br />

E. Substitutions: Comply with the requirements of Section 01600.<br />

08337 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION BY CONTRACTOR<br />

A. Examine surfaces and adjacent. Do not proceed with Work until unsatisfactory conditions have been corrected.<br />

1. Openings shall be to the dimensions indicated.<br />

2. Door support framing shall be installed at locations indicated.<br />

3.2 INSTALLATION BY CONTRACTOR<br />

A. Install doors in accordance with manufacturer's published instructions.<br />

B. Use anchorage devices to securely fasten assembly to wall construction and building framing without distortion or<br />

stress.<br />

C. Fit and align assembly including hardware; level and plumb, to provide smooth operation.<br />

D. Install joint sealant at visible joints around frames and tracks as specified in Section 07900.<br />

END OF SECTION<br />

08337 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 08360 (08 3613) – SECTIONAL OVERHEAD DOORS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Sectional overhead doors furnished and installed by Owner.<br />

1. Manually operated, insulated and uninsulated steel sectional overhead doors.<br />

2. Manually operated, aluminum sectional overhead doors.<br />

B. Related Requirements:<br />

1. Section 07900 - Joint Sealants: Installation of sealant at frame perimeter.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI Z97.1 - For Safety Glazing Materials Used In Buildings - Safety Performance Specifications And<br />

Methods Of Test.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-<br />

Dip Process.<br />

2. ASTM C 1048 - Heat-Treated Flat Glass - Kind HS, Kind FT Coated and Uncoated Glass.<br />

3. ASTM E 330 - Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform<br />

Static Air Pressure Difference.<br />

D. American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI):<br />

1. ASCE/SEI 7 - Minimum Design Loads for Buildings and Other Structures.<br />

E. Consumer Product Safety Commission (CPSC):<br />

1. CPSC 16 CPR Part 1201.<br />

F. Door and Access Systems Manufacturer’s Association International (DASMA):<br />

1. DASMA 102 - Sectional Overhead-Type Doors<br />

2. DASMA 108 - Standard Method for Testing Sectional Garage Doors and Rolling Doors: Determination of<br />

Structural Performance Under Uniform Static Air Pressure Difference.<br />

1.3 SUBMITTALS<br />

A. Submittal Process: Supplier shall submit the following to Architect for information and record only.<br />

1. Product Data: Submit Product Data sheets for each type door showing compliance with the specified<br />

physical properties.<br />

2. Shop Drawings: For each type door installation and for special components not dimensioned or detailed in<br />

manufacturer's product data. Include plans, elevations, sections, details, and attachments to other work<br />

including details and attachment of steel door track guards.<br />

08360 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Certification: Copy of signed Certified Statement from manufacturer showing door schedule of doors listing<br />

each door, by door number, provided with the following information:<br />

a. Door manufacturer and model number.<br />

b. Door type (aluminum or steel).<br />

c. Design windload values shown on Drawings, manufacturer’s tested windload value of door and<br />

calculated design windload for each specific door location shown on Drawings.<br />

d. Description of modifications, if any, to the specified door model to meet windload conditions.<br />

e. Window size and glazing material, if applicable.<br />

1.4 QUALITY ASSURANCE<br />

A. Installation shall be by manufacturer’s qualified and authorized installers. Installation by unauthorized installers<br />

will not be accepted.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Product Delivery: Wal-Mart Supplier will deliver products to Site to be received by Contractor. Contact shall be<br />

made between Contractor and Supplier to coordinate product delivery and installation.<br />

B. Product Packaging: Deliver overhead doors in manufacturer's original packaging with identification markings on<br />

each component or package.<br />

C. Acceptance at Site: Inspect products upon delivery of products to Site to verify quantity of products furnished and<br />

shall report discrepancies in quantity delivered or obvious damage to products delivered to Wal-Mart and Supplier.<br />

D. Handle, store, and protect products in accordance with Section 01600 and manufacturer’s recommendations.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's Supplier will furnish and install sectional overhead doors as described<br />

within this Section.<br />

B. Unless otherwise specified, provisions specified herein for products provided by Owner are included as<br />

requirements to Supplier of equipment to be furnished by Owner and are included as information only to Contractor.<br />

2.2 PERFORMANCE REQUIREMENTS<br />

A. Sectional doors shall meet performance requirements specified without failure due to defective manufacture,<br />

fabrication, installation, or other defects in construction and without requiring temporary installation of reinforcing<br />

components.<br />

B. Structural Performance: Provide doors designed to sustain wind load pressures shown on the drawings as calculated<br />

by the manufacturer in accordance with ASCE/SEI 7 (See Structural Drawing Sheet S0). Exterior sectional doors<br />

shall withstand the effects of gravity loads, and the loads and stresses within limits and under conditions, locations,<br />

and door sizes indicated when tested in accordance with ASTM E 330 or DASMA 108.<br />

C. Doors shall withstand design wind loads without evidencing deformation or disengagement of door components,<br />

shall remain in the opening throughout the duration of the test, and shall be deemed fully operable at the conclusion<br />

of the test in accordance with test standards specified above.<br />

2.3 MANUFACTURERS<br />

A. Manufacturer and Wal-Mart Supplier:<br />

1. Overhead Door Corporation, Lewisville, TX. National Accounts Manager: Angela Burgess, Toll Free (800)<br />

972-1730 extension 7134 or direct 469-549-7134.<br />

08360 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 STEEL SECTIONAL OVERHEAD DOORS<br />

A. Model: Series 591 Steel Insulated Door by Overhead.<br />

1. Steel Door Sections: Ribbed and textured profile, minimum 0.015 inch thick structural quality carbon steel<br />

(interior and exterior face) G60 galvanized in accordance with ASTM A 653.<br />

a. Panel Thickness: 1-5/8 inch min.<br />

2. Tracks, Supports, and Accessories: 3 inch track, galvanized, with leaf bumpers (stops), ball bearing roller<br />

guides, brackets, bracing, and reinforcing. Track arrangement shall be as indicated on Drawings.<br />

3. Weather Seals: EPDM rubber bulb-type strip at head, jambs, and door bottoms.<br />

4. Counterbalance: 50,000 cycle torsion spring mechanism for manual operation.<br />

5. Hardware: Chrome plated or galvanized.<br />

6. Lock: Interior mounted slide.<br />

7. Insulation: CFC-free and HCFC-free polyurethane, fully encapsulated.<br />

8. Thermal Values: R-value of 14.86, U-value of 0.067.<br />

9. Air Infiltration: 0.08 cfm at 15 mph; 0.08 cfm at 25 mph.<br />

10. Vision Panels: Clear thermal pane acrylic insulating glazing set into rubber or neoprene glazing channels, or<br />

plastic frames for metal door sections. Locate where indicated on Drawings.<br />

11. Hoist: Manual rope lift.<br />

12. Rollers: Heavy duty with steel ball bearings in case hardened stall races.<br />

B. Fabrication:<br />

1. Fabricate sectional doors to comply with DASMA 102 unless otherwise indicated.<br />

2. Fabricate door sections not more than 24 inches high, with horizontal meeting edges rolled to form weather<br />

seal.<br />

3. Enclose ends and provide reinforcing required for stability.<br />

C. Anchorage Devices: Adhesive stud anchors as shown Drawings and as specified in Section 05090.<br />

D. Finish:<br />

1. Receiving Area Doors: Two coat baked-on polyester factory finish. Apply to exterior and interior faces.<br />

Color: Factory white.<br />

2. Cart Storage Doors: Factory primed ready for field painting. Field paint in accordance with Section 09900.<br />

Color: As shown on Drawings.<br />

2.5 ALUMINUM SECTIONAL OVERHEAD DOORS<br />

A. Model: Series 521 Aluminum Doors.<br />

B. Components:<br />

1. Aluminum Door Sections: Stile and rail assembly secured with 1/4 inch diameter through rods having the<br />

following characteristics:<br />

a. Panel Thickness: 1-3/4 inch.<br />

b. Aluminum Panel: 0.050 inch thick, alloy 6063-T6.<br />

c. Glazing: Tempered Glass, ASTM C1048, Kind FT (Fully Tempered), Condition A (Uncoated), Type I<br />

(Transparent Glass, Flat), Quality q3 (Glazing Select). Comply with ANSI Z97.1 and CPSC 16CFR<br />

Part 1201.<br />

1) Thickness: 1/8 inch unless otherwise shown or specified.<br />

2. Tracks, Supports, and Accessories: 3 inch galvanized track with leaf bumpers (stops), ball bearing roller<br />

guides, brackets, bracing, and reinforcing.<br />

a. Track: Track as indicated on Drawings.<br />

3. Weather Seal: Flexible PVC at head, jambs, and door bottoms.<br />

4. Counterbalance: Torsion spring mechanism for manual operation.<br />

5. Hardware: Galvanized steel hinges and fixtures.<br />

6. Hoist: Manual chain lift.<br />

7. Rollers: Heavy duty with steel ball bearings in case hardened steel races.<br />

8. Fabricate door sections not more than 24 inches high, with horizontal meeting edges rolled to form weather<br />

seal.<br />

08360 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


9. Enclose ends and provide reinforcing required for stability.<br />

10. Factory Finish: Clear anodized aluminum finish.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and substrates receiving attachments. Verify opening sizes, tolerances, reinforcements, and<br />

conditions are acceptable. Do not proceed with Work until unsatisfactory conditions have been corrected.<br />

3.2 PREPARATION<br />

A. Coordinate construction of door openings within walls. Verify door head is parallel to floor.<br />

B. Coordinate installation and locations of structural supports for door assembly.<br />

3.3 INSTALLATION BY OWNER<br />

A. Install doors in accordance with manufacturer's published instructions.<br />

1. Stockroom Doors: Position stops so bottom edge of door is minimum of 12 inches above top of masonry<br />

opening when door is in up position.<br />

2. Other Doors: Position stops so bottom edge of door is flush with top of opening when door is in up position.<br />

B. Use anchorage devices to securely fasten assembly to wall construction and building framing without distortion or<br />

stress.<br />

C. Fit and align assembly including hardware, level and plumb, to provide smooth operation.<br />

3.4 INSTALLATION BY CONTRACTOR<br />

A. Grout concrete masonry unit cells for attachment of track and counterbalance mechanism.<br />

B. Install metal fabrications for support and attachment of door assembly, where required.<br />

C. Install sealants at joints around frames and tracks as specified in Section 07900.<br />

END OF SECTION<br />

08360 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 102706<br />

SECTION 08381 – FLEXIBLE STRIP DOORS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Flexible plastic strip doors.<br />

PART 2 - PRODUCTS<br />

2.1 FLEXIBLE STRIP DOORS-AT-GRADE DOOR<br />

A. Manufacturers: Subject to compliance with requirements, provide flexible strip doors as manufactured by one of<br />

the following:<br />

1. Model No. S10B3 by Mueller Door Corporation, Wauconda, IL, Suzanne Miller, (800) 981-2040.<br />

2. Model No. 12023, by Frommelt Industries, Inc., Dubuque, IA (800) 553-5560 or (866) 852-1500.<br />

B. Components:<br />

1. Strips: 12 inch wide, 0.120 gage, vinyl strips with 2/3 overlap.<br />

2. Brush Weatherstripping: Part No. B-0772, 3 inch polypropylene brush and Part No. A-0086 aluminum<br />

retainer, by Action Industries; Cleveland, OH (800) 321-1130.<br />

3. Mounting Bracket: Manufacturers standard studded steel cantilever extension bracket with 2 inch by 2 inch<br />

studded front box beam.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Verify condition of existing opening. Make opening square and plumb.<br />

B. Secure mounting head support structure in place in accordance with manufacturer's published instructions and as<br />

indicated on Drawings. Field cut studded extension bracket to appropriate length to allow 1 inch clearance<br />

between back side of box beam and sectional overhead door track.<br />

C. Wrap curtain around corners of wall brackets and return to wall construction, providing lap at each strip as<br />

defined.<br />

3.2 ADJUSTING AND CLEANING<br />

A. Provide 1 inch clearance between bottom of flexible strip door and finish floor.<br />

END OF SECTION<br />

08381 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 08383 (08 3816) – TRAFFIC DOORS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished full-height traffic doors for installation by Contractor.<br />

2. Owner furnished café style traffic doors for installation by Contractor.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: Provisions for products supplied by Owner.<br />

2. Section 05500 - Metal Fabrications: Prepared opening with steel channel jambs and head.<br />

1.2 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer’s recommendations.<br />

B. Product Delivery: Owner’s traffic door Supplier will deliver products to Site ready for installation. Contact<br />

Owner’s Supplier to establish a product delivery and installation date and coordination procedure.<br />

C. Product Compliance Inspection: Inspect delivered products for compliance with product descriptions in this<br />

Section. Report discrepencies to the Architect.<br />

D. Product Packaging: Doors will be shipped in manufacturer's standard packaging with identification markings on<br />

each component or package.<br />

E. Acceptance at Site: Receive products as specified in Section 01640.<br />

1. Verify quantity of products furnished with Bills of Lading provided with products.<br />

2. Note description of product quality discrepancies and/or product damage on Bill of Lading.<br />

3. Report discrepancies in product quantity delivered, or damage to products delivered to Wal-Mart<br />

immediately.<br />

4. Upon notification, Wal-Mart will arrange for delivery of replacement products.<br />

F. Manufacturing Defects: Report suspected product manufacturing defects to Wal-Mart Construction Manager and<br />

Owner's Supplier. Upon notification, Wal-Mart will arrange for repair of manufacturing defects.<br />

G. Store doors and accessories in unopened packages in protected dry area to prevent damage from environmental<br />

and construction operations.<br />

1.3 WARRANTY<br />

A. Door Panel: Ten years on panel against manufacturer’s defects.<br />

B. Hardware: Lifetime warranty.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner's traffic door Supplier (specified below under Manufacturers) will furnish traffic doors specified as follows<br />

under provisions of Section 01640 for installation by Contractor.<br />

1. Full-Height Traffic Doors.<br />

2. Café Traffic Doors.<br />

08383 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Descriptions and related provisions of products by Owner’s Supplier as specified herein are included as<br />

requirements forSupplier of products to be furnished by Owner and are included as information only to Contractor.<br />

2.2 MANUFACTURER<br />

A. Chase Doors, Cincinnati, OH. Contact: Geri Brazeal, (541) 504-4808.<br />

2.3 FULL-HEIGHT TRAFFIC DOORS<br />

A. Description: High impact plastic traffic door,gasketed or non-gasketed as shown on Drawings.<br />

B. Door Panel: U.S.D.A. compliant, solid high density polyethylene panels or non-CFC urethane filled polyethylene<br />

plastic sandwich panels with textured surfaces on both sides. Minimum thickness as follows:<br />

1. 8 ft. Wide x 9 ft. High Openings: 3/4 inch thick panel.<br />

2. All Other Openings: 1/2 inch thick panel.<br />

C. Gaskets (Seals): Provide integrated nylon brush or rubber perimeter seal package. Provide solid gasket seals at<br />

food preparation areas as shown on the drawings. Color: Black.<br />

D. Hardware: Enclosed stainless steel positive-close double acting hinges interconnected by full length powder<br />

coated aluminum spline. Color: Black.<br />

E. Vision Panel: Integrated, non-gasketed 1/4 inch thick polycarbonate. Size: 200 square inch per leaf. Locate<br />

bottom of panel to be not more than 43 inches above finished floor.<br />

F. Jamb Guards: Space saving low profile integrated steel jamb guards. Color: Matte stainless steel.<br />

G. Impact Bumper: Two-foot height impact absorbing tear drop shaped bumper each side of door.<br />

H. Door Color: Khaki or black as shown on Drawings.<br />

2.4 CAFÉ TRAFFIC DOORS<br />

A. Door: High impact café style abbreviated form plastic traffic door.<br />

B. Door Panel: 1/2 inch thick U.S.D.A. compliant high density polyethylene panels having textured surfaces both<br />

side.<br />

C. Hardware:<br />

1. Hinge: Positive close, gravity type, double acting, enclosed adjustable hinge system.<br />

2. Lock (Pharmacy Cabinet Mounted Café Doors Only): Provide slide lock Mueller Model number CL 6010.<br />

Lock may be by other manufacturers provided it is equivalent or better in all respects to the following:<br />

a. Material: Stainless Steel.<br />

b. Slide Bolt Minimum Thickness: 5/16 inch diameter.<br />

c. Slide Mounting Bracket Minimum Thickness: 3/32 inch.<br />

d. Slide Throw Minimum: 2 inches.<br />

e. All projections shall have radius edges.<br />

f. Slide Body shall have additional 3/8 inch holes for padlock.<br />

g. Latch shall be affixed to café panel with at least 3 fasteners.<br />

D. Door Color: Black or gray as shown on Drawings.<br />

1. Gray shall be Metallic Gray.<br />

E. Hardware Color: Black.<br />

F. Provide cutouts on pairs of doors as shown on Drawings.<br />

08383 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


G. Bollard: Steel post with black urethane coated finish.<br />

2.5 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that openings are ready to receive work and opening dimensions and clearances are as indicated on<br />

Drawings.<br />

3.2 INSTALLATION (BY CONTRACTOR)<br />

A. Install door unit assembly to manufacturer's installation instructions and manufacturer's location and installation<br />

drawings.<br />

B. Frame Mounted Traffic Doors: Use anchorage devices to fastenfull-height traffic door assembly to door frame<br />

construction without distortion or imposed stresses.<br />

C. Bollard Mounted Café Doors: Install café doorsas free standing pedestal (bollard) mounted in accordance with<br />

manufacturer’s instructions.<br />

1. Install bollard in core drilled holes in concrete floor in accordance with manufacturer’s instructions. Fill<br />

space between bollard and floor slab with non-metallic non-shrink grout.<br />

D. Cabinet Mounted Café Doors: Install cabinet mounted café doors in accordance with Drawings.<br />

E. Fit and align door assembly level and plumb.<br />

F. Adjust door assembly to provide smooth operation from closed to full open position.<br />

3.3 CLEANING<br />

A. Remove protective material from pre-finished surfaces.<br />

B. Remove labels and visible markings.<br />

C. Wash down surfaces with a solution of mild detergent in warm water, applied with soft, clean wiping cloths. Wipe<br />

surfaces clean.<br />

END OF SECTION<br />

08383 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 08411 (08 4313) – ALUMINUM FRAMED STOREFRONTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Aluminum storefront doors.<br />

2. Door hardware.<br />

B. Related Requirements:<br />

1. Section 08462 - Automatic Sliding Entrance Doors: Coordination between components.<br />

2. Section 08710 - Finish Hardware: Hardware schedules for doors.<br />

3. Section 08800 - Glazing: Glass products.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Architectural Manufacturers Association (AAMA):<br />

1. AAMA 611 - Voluntary Specifications for Anodized Architectural Aluminum.<br />

C. ASTM International (ASTM):<br />

1. ASTM A 123 - Zinc (Hot-Dip Galvanized) Coatings On Iron And Steel Products.<br />

2. ASTM E 283 - Standard Test Method For Determining Rate Of Air Leakage Through Exterior Windows,<br />

Curtain Walls, And Doors Under Specified Pressure Differences Across The Specimen.<br />

3. ASTM E 331 - Water Penetration Of Exterior Windows, Skylights, Doors, And Curtain Walls By Uniform<br />

Static Air Pressure Difference.<br />

D. Americans with Disabilities Act of 1990: Accessibility Guidelines for Buildings and Facilities.<br />

E. American National Standards Institute (ANSI):<br />

1. ANSI A117.1 - Specifications for Making Buildings and Facilities Accessible to and Usable by Physically<br />

Handicapped People.<br />

1.3 SYSTEMS DESCRIPTION<br />

A. Storefront System Performance Requirements:<br />

1. Air Infiltration: ASTM E 283. Air infiltration rate shall not exceed 0.06 cfm/ft2 at a static air pressure<br />

differential of 6.24 psf.<br />

2. Water Penetration Under Static Pressure: Systems do not evidence water penetration through fixed glazing<br />

and framing areas when tested according to ASTM E 331 at a minimum static-air-pressure difference of 20<br />

percent of positive wind-load design pressure, but not less than 6.24 lbs/sq. ft.<br />

3. Structural Performance: Maximum deflection of L/175 of span under a windload pressure calculation by<br />

the manufacturer based on the design wind loads shown on the Structural Drawings but not less than 20 psf.<br />

1.4 QUALITY ASSURANCE<br />

A. Regulatory Requirements: Conform to disabled access requirements of the following:<br />

1. State or Local requirements (where applicable).<br />

2. ANSI A117.1.<br />

3. ADA (Americans with Disabilities Act - 1990) requirements for entrance door access, entrance doors and<br />

hardware.<br />

08411 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Manufacturer: Kawneer Company, Inc. Contacts as follows:<br />

1. Central Area: Chicago, IL, (630) 773-3700, FAX (800) 345-3761.<br />

2. Eastern Area: Bloomsburg, PA, (877) 505-3756, FAX (800) 786-4097.<br />

3. Southern Area: Atlanta, GA, (800) 304-2079, FAX (800) 304-2081.<br />

4. Western Area: Visalia, CA, (877) 505-3785, FAX (800) 759-2810.<br />

B. Kawneer product designations are used within this Section to identify aluminum framed storefront types and<br />

associated products unless noted otherwise.<br />

C. Alternate Manufacturers: Subject to compliance with project requirements, unless otherwise specified, aluminum<br />

framed storefronts and accessories equivalent to the Kawneer products specified by one of the following alternate<br />

manufacturers may be provided:<br />

1. EFCO Corporation; Monett, MO, (800) 221-4169.<br />

2. Southwest Aluminum Systems, Inc.; Chandler, AZ, (602) 961-2000.<br />

3. Tubelite, Inc.; Reed City, MI, (800) 866-2227.<br />

4. Vistawall Architectural Products; Terrell, TX, (800) 869-4567.<br />

D. Substitutions: Comply with the requirements of Section 01600.<br />

2.2 FRAMING<br />

A. Interior Framing System: TRIFAB VG 450, by Kawneer. 1-3/4 x 4-1/2 inch nominal dimension, extruded<br />

aluminum flush glazed framing system for uninsulated glazing systems.<br />

B. Exterior Framing System: TRIFAB VG 450 by Kawneer. 1-3/4 x 4-1/2 inch nominal dimension, extruded<br />

aluminum flush glazed framing system for uninsulated glazing systems.<br />

C. Exterior Framing System: TRIFAB VG 451 by Kawneer. 2 x 4-1/2 inch nominal dimension, extruded aluminum<br />

flush glazed framing system for insulated glazing systems.<br />

D. Receptor Channel: Model No. 451VG570 and 451VG572, by Kawneer or equivalent for system specified.<br />

E. Finish: Match storefront system.<br />

F. Member Wall Thickness: Each framing member shall provide structural strength to meet specified performance<br />

requirements.<br />

2.3 DOORS<br />

A. Doors: Series 350 swing door, medium stile, by Kawneer. Door sizes indicated on Drawings.<br />

1. Top Rail: 6-1/2 inch, single piece.<br />

2. Bottom Rail: 10 inch.<br />

3. Glazing: 1/4 inch thick units per Section 08800, with standard bevel glass stops.<br />

2.4 HARDWARE<br />

A. Provide hardware specified below and as scheduled in Section 08710.<br />

B. Closers: Single Acting Doors: Model 4111S-CUSH x TB x 689 by LCN, heavy duty, parallel arm only, surface<br />

closer meeting ADA-90 requirements, independently hung, with adjustable back check and 100 degree hold-open;<br />

slim line half covers, spray painted aluminum to match aluminum storefront system. Attachment: Thru-bolted in<br />

door. No drop-plates allowed.<br />

08411 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Hinges: Continuous aluminum geared hinge, concealed leaf, heavy duty, finish to match door finish. Roton<br />

Model 780-112HD as manufactured by Hager or equivalent.<br />

D. Push: Type CP-2 push by Kawneer Company, Inc. Finish: #14 Clear Anodized. Mount push bar at 42 inches<br />

above finish floor.<br />

E. Pull: Type CO-9 pull by Kawneer Company, Inc. Finish: #14 Clear Anodized.<br />

F. Door Holder: 1221-4 cast iron, finish to match door color, by Trimco - Triangle Brass Mfg. Co.<br />

G. Weatherstripping:<br />

1. Head and Jamb: Replaceable wool, polypropylene, or nylon wool pile with aluminum strip backing,<br />

recessed in frame.<br />

2. Sill: Semi-rigid polymeric material on aluminum anodized to match door; EPDM sweep strip; 38-560 by<br />

Kawneer or similar by other named manufacturers.<br />

H. Threshold: See Section 08710.<br />

I. Glass Guards: Nominal 1/2 inch by 2 inch aluminum bars, mounted at heights shown, flush mounted stile-to-stile.<br />

Coordinate with Section 08462.<br />

1. Install glass guards both faces of doors.<br />

J. Flush Bolt/Interlocking Device:<br />

1. Exterior Doors: 3 point lock. Provide the following:<br />

a. Controller Locking System by Kawneer.<br />

2. Interior Doors: 2 point lock (jamb and header bolts only). Provide one of the following:<br />

a. Controller Locking System by Kawneer.<br />

b. Model No. 6003-1063 2 point lock by Truth Hardware. For distributor, call (800) 866-7884.<br />

3. Substitutions: None accepted.<br />

K. Deadbolt Locks: Mortise type, Adams Rite MS-1850A with 4089 exit indicator, less cylinder. See Section 08710<br />

for cylinders and thumbturns.<br />

L. Lever Lockset: Adams Rite 4530-36-101, finish 628, less cylinder. See Section 08710 for cylinder.<br />

M. Flush Bolts: Kawneer top and bottom flush bolts.<br />

2.5 FABRICATION<br />

A. Fabricate components with minimum clearances and shim spacing around perimeter of assembly, yet enabling<br />

installation and dynamic movement of perimeter seal.<br />

B. Rigidly fit and secure joints and corners. Make joints and connections flush, hairline, and weatherproof.<br />

C. Develop drainage holes with moisture pattern to exterior.<br />

D. Prepare components to receive anchor devices. Fabricate anchorage items. Arrange fasteners, attachments, and<br />

jointing to ensure concealment from view.<br />

E. Prepare components with internal reinforcement for door hardware.<br />

F. Reinforce framing members for imposed loads.<br />

G. Accessories:<br />

1. Brake Metal Closures: Minimum 0.040 inch thick aluminum x length required. Finish shall match<br />

adjacent related work.<br />

08411 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Provide clean sharp edges, uniform in appearance and consistent in shape. Secure in place with concealed<br />

fasteners where possible. Exposed fasteners shall match enclosure fabrication.<br />

3. Sill Flashing: Fabricate to configuration indicated and required of minimum 0.040 inch aluminum having<br />

exposed edges hemmed. Finish shall match adjacent related work.<br />

H. Hardware: Coordinate with hardware supplier and prepare door for field installation as required for hardware<br />

specified and scheduled in Section 08710.<br />

2.6 FINISHES<br />

A. Exposed Aluminum Surfaces: Architectural Class I anodic coating, AA-M12 C22 A41, conforming to AAMA<br />

611, 0.018 mm minimum thickness. #14 Clear, unless otherwise indicated on Drawings.<br />

B. Concealed Steel Items: Galvanized in accordance with ASTM A 123 to 2.0 oz/sq ft.<br />

C. Apply two coats of bituminous paint to concealed aluminum and steel surfaces in contact with cementitious or<br />

dissimilar materials.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify wall openings are ready to receive work of this Section. Verify dimensions, tolerances, and method of<br />

attachment with other work.<br />

B. Beginning of installation means acceptance of existing conditions.<br />

3.2 INSTALLATION<br />

A. Install storefront system components in accordance with manufacturer's instructions.<br />

B. Use anchorage devices to securely attach frame assembly to structure.<br />

C. Align assembly plumb and level, free of warp or twist. Maintain assembly dimensional tolerances, aligning with<br />

adjacent work.<br />

D. Brake Metals:<br />

1. Set sill flashing in full bed of sealant. Provide riveted end laps of not less than 3 inches.<br />

E. Pack fibrous insulation in shim spaces at perimeter of assembly to maintain continuity of thermal barrier.<br />

F. Install perimeter sealant and backing materials in accordance with Section 07900.<br />

G. Install glass in accordance with Section 08800, to glazing method required to achieve performance criteria.<br />

H. Install hardware using templates provided and in accordance with disabled access regulatory requirements for<br />

hardware. Refer to Section 08710 for cylinders and installation requirements.<br />

1. Cylinder and Thumb Turn: 48 inches above finished floor.<br />

I. Set thresholds in bed of mastic and secure.<br />

J. Adjust operating hardware and crash bars for smooth operation.<br />

3.3 TOLERANCES<br />

A. Variation from Plane: 0.03 inches per foot maximum or 0.25 inches per 30 feet, whichever is less.<br />

08411 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Misalignment of Two Adjoining Members Abutting in Plane: 0.015 inches.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect storefront system installation and attachment to building structure.<br />

B. Inspect door operation and hardware installation.<br />

3.5 CLEANING<br />

A. Wash down exposed surfaces using a solution of mild detergent in warm water, applied with soft, clean wiping<br />

cloths. Take care to remove dirt from corners. Wipe surfaces clean.<br />

B. Remove excess sealant by moderate use of mineral spirits or other solvent acceptable to sealant manufacturer.<br />

END OF SECTION<br />

08411 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 08462 (08 4229) – AUTOMATIC SLIDING ENTRANCE DOORS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished and installed electric operated automatic sliding entrance doors with transom assemblies,<br />

including frames, glazing, and hardware.<br />

2. Control System: Motion detection and hold open safety system.<br />

3. Video camera system.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

2. Section 08411 - Aluminum Framed Storefronts: Aluminum framed storefront system for installation of<br />

automatic sliding entrance doors.<br />

3. Section 08800 - Glazing: Storefront system glass.<br />

4. Section 16100 - Wiring Methods: Power to automatic doors.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Association of Automatic Door Manufacturers (AAADM):<br />

1. AAADM Inspector Certification Program.<br />

C. American National Standards Institute (ANSI):<br />

1. ANSI A117.1 - Guidelines For Accessible And Usable Buildings And Facilities.<br />

2. ANSI (BHMA) A156.10 - Power Operated Pedestrian Doors.<br />

3. ANSI Z97.1 - Safety Glazing Material Used in Buildings.<br />

D. ASTM International (ASTM):<br />

1. ASTM C 1048 - Heat Treated Flat Glass - Kind HS, Kind FT Coated and Uncoated Glass.<br />

2. ASTM E 1886 - Standard Test Method for Performance of Exterior Windows, Curtain Walls, Doors, and<br />

Impact Protective Systems Impacted by Missile(s) and Exposed to Cyclic Pressure Differentials.<br />

3. ASTM E 1996 - Performance of Exterior Windows, Curtain Walls, Doors, and Impact Protective Systems<br />

Impacted by Windborne Debris in Hurricanes.<br />

E. Consumer Products Safety Standards for Architectural Glazing: CPSC 16 CFR, Part 1201.<br />

F. Americans with Disabilities Act of 1990: Accessibility Guidelines for Buildings and Facilities.<br />

1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-Installation Conference:<br />

1. Convene Pre-installation Conference at Site one week prior to commencing Work of this Section. Require<br />

attendance of parties directly affecting Work of this Section, including, but not limited to, Wal-Mart<br />

Construction Manager, Contractor Project Field Superintendent, Aluminum Storefront job foreman,<br />

Automatic Entrance Door Manufacturer's Technical Representative, electrical subcontractor field<br />

supervisory personnel, and any subcontractor, supplier, or installer directly affecting, or affected by Work<br />

of this Section.<br />

2. Contact Wal-Mart Construction Manager two weeks prior to Pre-installation Conference to confirm<br />

schedule.<br />

08462 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Review foreseeable methods and procedures related to automatic entrance door Work, including the<br />

following:<br />

a. Tour, inspect, and discuss condition of door assembly openings, connections to building structure,<br />

electrical requirements, and other preparatory work performed by other trades.<br />

b. Review automatic entrance door system requirements including drawings, specifications and other<br />

contract documents.<br />

c. Review required submittals, both completed and yet to be completed.<br />

d. Review and finalize construction schedule related to automatic entrance door Work and verify<br />

availability of materials, installer's personnel, equipment and facilities needed to make progress and<br />

avoid delays.<br />

e. Review required inspections, operational testing, and certifying procedures.<br />

f. Review weather and forecasted weather conditions, and procedures for coping with unfavorable<br />

conditions.<br />

g. Review preparation and installation procedures and coordinating and scheduling required with<br />

related work.<br />

4. Record discussions of conference and decisions and agreements (or disagreements) reached, and furnish<br />

copy of record to each party attending.<br />

1.4 QUALITY ASSURANCE<br />

A. Installer Qualifications:<br />

1. Automatic and barrier free door equipment shall be installed by the manufacturer’s factory trained installers<br />

or shall be installers as recommended and approved by the automatic door operator manufacturer.<br />

2. Installers shall be certified and recognized by and in accordance with the AAADM Inspector Certification<br />

Program.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Product Delivery: Automatic Entrance Door Supplier will deliver products to Site and install products. Automatic<br />

Entrance Door Supplier will contact Contractor after Award of Contract to establish a product delivery and<br />

installation date and establish a coordination procedure.<br />

B. Product Packaging: Automatic Entrance Doors will be delivered in manufacturer's standard packaging with<br />

identification markings on each component or package.<br />

C. Acceptance at Site: Inspect products with Automatic Entrance Door Supplier upon delivery of products to Site.<br />

1. Verify quantity of products furnished.<br />

2. Report discrepancies in product quantity delivered, or damage to products delivered to Automatic Entrance<br />

Door Supplier and Wal-Mart immediately. Upon notification, Wal-Mart will arrange for delivery of<br />

replacement products.<br />

D. Manufacturing Defects: Report suspected manufacturing defects to Wal-Mart Construction Manager and<br />

Automatic Entrance Door Supplier. Upon notification, Wal-Mart will arrange for repair of manufacturing defects.<br />

E. Handle, store, and protect products in compliance with the requirements of Section 01600 and manufacturer’s<br />

recommendations.<br />

1.6 WARRANTY<br />

A. Provide manufacturer's three year warranty. Include coverage of complete system for failure to meet specified<br />

requirements. Include cost of material and labor for repairs and adjustments.<br />

08462 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's automatic entrance door Supplier will furnish and install automatic<br />

entrance doors as described within this Section.<br />

B. Unless otherwise specified, provisions specified herein of products provided by Owner are included as<br />

requirements for Supplier of products to be furnished by Owner and are included as information only to<br />

Contractor.<br />

2.2 MANUFACTURER<br />

A. Stanley Access Technologies, Farmington, CT. Contact: Mark Crudi, National Accounts Project Manager, (860)<br />

679-6493.<br />

2.3 PERFORMANCE REQUIREMENTS FOR AUTOMATIC SLIDING ENTRANCE DOORS<br />

A. Design system to operate, hold open, and close doors under wind and suction loads calculated by the manufacturer<br />

based on the design wind loads shown on the Structural Drawings but not less than a windload pressure of 20 PSF.<br />

B. Provide for dimensional distortion of components during operation.<br />

C. Provide for opening and closing operation of door panels in the event of power failure.<br />

D. Operating Temperature Range: -20 F to 130 F ambient.<br />

E. Eliminate system performance interference by ambient light and radio frequencies.<br />

F. Provide sliding doors and side panels with break-away capability where scheduled or shown.<br />

2.4 REGULATORY REQUIREMENTS FOR AUTOMATIC SLIDING ENTRANCE DOORS<br />

A. Conform to applicable code for automatic release of control drive unit to permit manual opening of doors.<br />

B. State or Local requirements (where applicable).<br />

C. Comply with ANSI A156.10 and ANSI A117.1.<br />

D. ADA (Americans with Disabilities Act - 1990) requirements for entrance door access, entrance doors and<br />

hardware.<br />

E. Products Requiring Electrical Connection: Listed and classified by Underwriters Laboratories, Inc., as suitable for<br />

the purpose specified and indicated.<br />

2.5 AUTOMATIC SLIDING ENTRANCE DOORS<br />

A. Exterior Doors: Dura-Glide Series 3000 with Stan-Vision by Stanley. Overhead concealed slide door system with<br />

sidelights and transom where indicated, full breakout of doors and sidelights unless otherwise scheduled to be nonbreakaway,<br />

and doorway monitoring device to control door opening, closing, and hold open functions, single or<br />

pair as indicated.<br />

B. Interior Doors: Dura-Glide Series 3000 with Stan-Vision as manufactured by Stanley. Overhead concealed slide<br />

door system with sidelights and transom (interior) where indicated, full breakout of doors and sidelights unless<br />

otherwise scheduled to be non-breakaway, and doorway monitoring device to control door opening, closing, and<br />

hold open functions, single or pair as indicated.<br />

08462 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Door and Transom Sizes: As shown on Drawings.<br />

2.6 OPERATING SYSTEM COMPONENTS<br />

A. Visual Sensing System (Motion Detector): Stan-Vision Series as manufactured by Stanley.<br />

1. The system consists of the following major components:<br />

a. Two CCD (Closed Circuit Digital) visual sensors with mounting templates, one visual sensor<br />

controller, a four-channel encoder, two RG-59 cables for connecting the visual sensors to the visual<br />

sensor controller.<br />

2. The system shall connect with the Stanley interface board, motor encoder assembly, and the Stanley Dura-<br />

Glide microprocessor control box.<br />

3. Provide one unit center mounted above doorway on each side of header.<br />

B. Jamb / Stile Mounted Frontal View Camera System:<br />

1. CMOS video camera system by Stanley. The system consists of the following major components:<br />

a. Jamb mounted CMOS color camera with mounting hardware.<br />

b. Camera I/O interface module for power connection and video output connection located within the<br />

header assembly.<br />

2. Camera system shall be mounted within the jamb tube that supports the door assembly.<br />

3. Provide one camera at approach side of each sliding door.<br />

4. Provide one camera each side of Garden Center sliding door.<br />

C. Power Requirements: Dedicated 120V AC, 5 Amp, 60 Hz, single phase power with solid earth ground connection.<br />

2.7 DOOR COMPONENTS, HARDWARE AND ACCESSORIES<br />

A. Doors: Narrow stile aluminum doors.<br />

1. Top Rail: Manufacturer’s standard.<br />

2. Bottom Rail: 10 inches high.<br />

3. Horizontal Muntins: Provide two muntins, locate at 24 inches and 42 inches above finish floor. Align with<br />

bumper guards and push bars on aluminum storefront system entrance door as indicated on Drawings.<br />

4. Stiles: 2-1/4 inches.<br />

5. Glass:<br />

a. Interior Doors: Clear tempered glass; ASTM C1048, Kind FT (Fully Tempered), Condition A<br />

(Uncoated), Type I (Transparent Glass, Flat), Class 1 (Clear), Quality q3 (Glazing Select). Conform<br />

to ANSI Z97.1 and CPSC 16 CFR Part 1201.<br />

1) Thickness: 1/4 inch.<br />

2) Identification: Permanently identify by manufacturer. Etch or ceramic fire identification on<br />

glass visible when unit is glazed.<br />

b. Exterior Doors and Transoms: Tinted tempered glass; ASTM C 1048, Kind FT (Fully Tempered),<br />

Condition A (Uncoated), Type I (Transparent Glass, Flat), Class 2 (Tinted Heat Absorbing and<br />

Light Reducing), Quality q3 (Glazing Select). Conform to ANSI Z97.1 and CPSC 16CFR Part<br />

1201.<br />

1) Thickness: 1/4 inch.<br />

2) Color: Bronze tint, U.N.O.<br />

3) Identification: Permanently identify by manufacturer. Etch or ceramic fire identification on<br />

glass visible when unit is glazed.<br />

B. Finish: Match finish of aluminum entrances and storefronts specified in Section 08411.<br />

C. Door Hardware and Accessories:<br />

1. Pivots: Allows break-away sliding panel and sidelights to break away to full open position to provide<br />

immediate egress at any point in door movement.<br />

2. Panic break-away shall be code approved, acceptable to Authorities Having Jurisdiction.<br />

3. Top Door Arm: Door holders for all break-away door panels.<br />

4. Quick disconnect wiring harness.<br />

5. Power Switch: 5 position "On/Off/Hold Open" switch; full automatic, reduced automatic, and exit only.<br />

08462 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


6. Adjustable door sweeps (exterior doors only).<br />

7. Finger Protection: Provide finger protection between sidelight and sliding door when door is in open<br />

position.<br />

8. Lock:<br />

a. Cylinder: Slide doors shall include two point lock securing lead edges of door styles together and to<br />

hanger assembly.<br />

b. Electric Solenoid Locking System (Exterior Doors): Provide automatic locking mechanism to<br />

secure doors in closed position when the door is closed to outside entry (ENTER/NO). Provide failsafe<br />

control. Provide door unit with exterior access by key control switch mounted at outside jamb<br />

to disengage electric solenoid locking system and open door.<br />

9. "Watchdog" monitoring of microprocessor.<br />

10. Keyed Cylinder (Outside): Specified in Section 08710 (Furnished by Contractor).<br />

11. Perimeter pile weatherstripping.<br />

12. Thresholds:<br />

a. Provide aluminum threshold of profile shown for doors when scheduled in Section 08710.<br />

b. Provide edge profile suitable for installation adjacent to entrance tile where applicable.<br />

c. Length: Opening width plus 2 inches minimum.<br />

13. Glass Guards (Crash Bars): Nominal 1/2 inch by 2 inch aluminum bar with 1 inch projection from<br />

mounting surface. Mount on doors where and as shown on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine existing conditions with Automatic Entrance Door Supplier prior to start of door installation.<br />

B. Examine surfaces and adjacent areas in which Work is performed. Report conditions that may adversely affect<br />

satisfactory execution of Work to Wal-Mart Construction Manager. Do not proceed with Work until<br />

unsatisfactory conditions have been corrected.<br />

3.2 PREPARATION BY CONTRACTOR<br />

A. Provide door openings to size indicated on Drawings.<br />

B. Provide door head level and parallel with floor at door opening. Size and configuration shall be as indicated on the<br />

Drawings.<br />

C. Provide door jambs parallel and plumb.<br />

D. Provide power to location at door required by door manufacturer ready for power connection.<br />

3.3 INSTALLATION BY OWNER<br />

A. Automatic entrance doors and operating system will be installed by Automatic Entrance Door Supplier personnel.<br />

B. Installation will be in accordance with manufacturer's published instructions.<br />

C. Anchorage devices will be used to securely fasten assembly to adjacent construction without distortion or stress.<br />

D. Hardware will be installed in accordance with ANSI A117.1 requirements and local adopted disabled access<br />

requirements for hardware.<br />

E. Joint sealing between door frames and walls will be by Automatic Entrance Door supplier in accordance with<br />

Section 07900.<br />

F. Doors shall be rendered non-breakaway when scheduled on Drawings.<br />

08462 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.4 INSTALLATION BY CONTRACTOR<br />

A. Make final power connections to automatic entrance doors as specified in Section 16100.<br />

B. Furnish and install keyed cylinder and thumbturn if and where specified in Section 08710.<br />

C. Interface with Other Work:<br />

1. Coordinate locations of power connections and requirements.<br />

2. Coordinate locations of building management alarm connections and requirements.<br />

3. Coordinate requirements for door openings required for automatic entrance door installation.<br />

3.5 FIELD QUALITY CONTROL<br />

A. Site Tests: Upon completion of installation, test operation of automatic entrance doors and operating system.<br />

Make all necessary adjustments as required and retest.<br />

B. Inspection:<br />

1. Inspect automatic entrance doors and operating system installation in accordance with AAADM<br />

requirements.<br />

2. Correct deficiencies in Work which inspection indicates are not in compliance with Contract Documents.<br />

END OF SECTION<br />

08462 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II - Base 082611<br />

SECTION 08710 (08 7100) – DOOR HARDWARE AND HARDWARE SCHEDULE<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Hardware for doors.<br />

2. Thresholds.<br />

3. Weatherstripping, seals and door gaskets.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: Provisions for Owner Furnished Items.<br />

2. Section 06100 - Rough Carpentry: Blocking for miscellaneous hardware mounting.<br />

3. Section 06200 - Finish Carpentry: Hardware for cabinetry and other finish carpentry.<br />

4. Section 08110 - Steel Doors and Frames: Hardware coordination.<br />

5. Section 08411 - Aluminum Framed Storefronts: Hardware coordination.<br />

6. Section 08462 - Automatic Sliding Entrance Doors: Hardware coordination.<br />

7. Section 16100 - Wiring Methods: Electrified hardware coordination.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. Americans with Disabilities Act (ADA):<br />

1. 28 CFR Part 36 - ADA Standards for Accessible Design.<br />

C. American National Standards Institute (ANSI):<br />

1. ANSI A 117.1 - Specifications for Making Buildings and Facilities Accessible to and Usable by Physically<br />

Handicapped People.<br />

2. ANSI A 156.2 - Bored and Preassembled Locks and Latches.<br />

3. ANSI A 156.6 - Architectural Door Trim.<br />

4. ANSI A 156.13 - Mortise Locks and Latches.<br />

5. ANSI A 156.15 - Release Devices – Closer Holder, Electromagnetic and Electromechanical.<br />

D. National Fire Protection Association (NFPA):<br />

1. NFPA 80 - Fire Doors and Windows.<br />

2. NFPA 101 - Code for Safety to Life from Fire in Buildings and Structures.<br />

3. NFPA 252 - Fire Tests of Door Assemblies.<br />

E. Underwriters Laboratories (UL):<br />

1. UL 10B - Fire Tests of Door Assemblies.<br />

2. UL 305 - Panic Hardware.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect door hardware products in compliance with the requirements of Section<br />

01600 and manufacturer's recommendations.<br />

08710 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Product Delivery: Wal-Mart Supplier will deliver products to Site ready for installation. Contact Wal-Mart<br />

Supplier to establish product delivery and installation date and coordination procedure.<br />

C. Product Packaging: Products will be shipped in manufacturer's standard packaging with identification markings<br />

on each component or package.<br />

D. Acceptance at Site: Receive products as specified in Section 01640.<br />

1. Verify quantity of products furnished with Bills of Lading provided with products.<br />

2. Report discrepancies in product quantity or quality, or damage or damage to products to Wal-Mart<br />

Construction Manager immediately. Note description of product quality discrepancies and/or product<br />

damage on Bill of Lading.<br />

3. Upon notification, Wal-Mart will arrange for delivery of replacement products.<br />

E. Store products in unopened packages in protected dry area to prevent damage from environmental and<br />

construction operations.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner's or Wal-Mart’s Supplier will furnish hardware specified herein under provisions of Section 01640 for<br />

installation by Contractor.<br />

B. Descriptions and related provisions of products by Supplier as specified herein are included as requirements by the<br />

supplier of equipment to be furnished by the Owner or Wal-Mart and are included as information only to<br />

Contractor.<br />

2.2 MANUFACTURERS<br />

A. Provide hardware as scheduled in Hardware Schedule in Part 3 of this Section.<br />

B. Wal-Mart/Owner Supplier:<br />

1. Positive Lock Exit Device (Wal-Mart Furnished): Positive Lock; Contact Kimbra White (800) 342-7670.<br />

2. All Other Hardware Items (Owner Furnished): D.H. Pace Inc., Springfield, MO, Mark Lyons,<br />

(417) 831-5585, mark.lyons@dhpace.com<br />

C. Product Designations: Hardware may be any of the products listed within the tables below for each specific type.<br />

Substitutions will not be permitted.<br />

D. Hardware Manufacturer Designations:<br />

ID Manufacturer Telephone ID Manufacturer Telephone<br />

Ar Arrow (ASSA ABLOY) (800) 233-0478 Re Reese Enterprises, Inc. (800) 328-0953<br />

De Detex Corporation (800) 729-3839 Ri Rixson (ASSA ABLOY) (800) 457-5670<br />

GJ Glynn-Johnson (Ingersoll Rand (800) 525-0336 Ro Rockwood (ASSA ABLOY) (814) 926-2026<br />

Security Technologies (IR)<br />

H Hager Companies (800) 325-9995 Sc Schlage (IR) (800) 847-1864<br />

I H. B. Ives (IR) (877) 613-8766 Sec Securitron (ASSA ABLOY)<br />

LCN LCN Closers (IR) (800) 526-2400 Sel Select Hinges (800) 423-1174<br />

Mc McKinney (ASSA ABLOY) (717) 346-7551 S Stanley Hardware (800) 622-4393<br />

NG National Guard Products, Inc. (800) 647-7874 T Trimco (Triangle Brass Mfg) (800) 637-8746<br />

P Pemko Mfg. Co. (805) 642-2600 VD Von Duprin (IR) (800) 999-0408<br />

Po Positive Lock (800) 342-7670<br />

08710 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.3 REGULATORY REQUIREMENTS<br />

A. Perform work in accordance with the following standards:<br />

1. ANSI A117.1<br />

2. NFPA 101.<br />

3. NFPA 80.<br />

4. NFPA 252.<br />

5. UL 10B.<br />

6. UL 305.<br />

B. Conform to applicable code for requirements applicable to fire rated doors and frames.<br />

C. Products Requiring Electrical Connection: Listed and classified by Underwriters Laboratories, Inc. (UL), and<br />

acceptable to Authority Having Jurisdiction as suitable for the purpose specified and indicated.<br />

D. Conform to applicable local, State or Federal disabled access requirements for the installation and operation of<br />

door hardware.<br />

2.4 FINISHES<br />

A. Provide finishes as specified in Part 2 of this Section unless otherwise indicated in the Hardware Schedule for the<br />

specific hardware item.<br />

2.5 HINGES<br />

A. Material:<br />

1. Mortise Butts: Provide full mortise-type hinges with stainless steel pins, except steel pins with steel hinges;<br />

non-removable pin (NRP) for exterior and public interior exposure, non-rising pin, flat button with<br />

matching plugs, 4-1/2 inches x 4-1/2 inches unless otherwise shown.<br />

2. Ball-bearing Type Hinges: Swaged, inner leaf beveled, square corners.<br />

3. Continuous Geared Hinge: Full surface type hinge of 6063 T6 Aluminum with thermoplastic polyester<br />

bearings, 90 min. fire rated, clear finish. Provide self-drilling threaded fasteners for frame and thru bolts<br />

for door.<br />

B. Hinges by types:<br />

Type Description Finish MANUFACTURER/MODEL<br />

Stanley Hager McKinney<br />

H-2 Butts: Medium weight door, low frequency, 652 F179 1279 T2714<br />

steel<br />

H-4 Butts: Medium weight door, average 652 FBB179 BB1279 TB2714<br />

frequency, steel<br />

Select Hinge Hager<br />

H-7 Hinge: Continuous geared hinge CL SL21 SD x Roton 780-210<br />

SDTF x<br />

FDH<br />

Stanley Hager McKinney<br />

H-8 Hinge: Surface mounted 3 inches x 3 inches US2H 808BP 1808 705<br />

H-9 Butts: Heavy weight, stainless steel 630 FBB199 BB1199 T4B3386<br />

H-11 Butts: Medium weight, stainless steel 630 FBB191 BB1191 TB3386<br />

2.6 LOCKS, LATCHES, AND BOLTS<br />

A. Materials:<br />

1. Cylindrical Locks: ANSI A 156.2, Series 4000 Grade 1, equipped with 6-pin tumbler; "keyed alike".<br />

Provide 2-3/4 inch backset. Provide two keys for each lock.<br />

08710 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Mortise Locks: ANSI A 156.13, Grade 1, equipped with 6-pin tumbler; "keyed alike". Provide 2-3/4 inch<br />

backset. Provide two keys for each lock.<br />

3. Provide Schlage standard C123 keyway (except Pharmacy).<br />

4. Provide Schlage Primus XP cylinders for Pharmacy 300 series locks.<br />

5. Master key, key alike or different as directed.<br />

6. Quantity: In addition to two keys for each lock, provide the following:<br />

a. Cylinder Change Keys: 6 change keys per change.<br />

b. Master Keys: 10.<br />

7. Latch Sets: Provide push-button releases by turning lever, closing door, or turning emergency release key<br />

through hole in outside knob.<br />

8. Strikes: ANSI Strikes, 1-1/4 x 4-7/8 inches, with curved lip. Wrought box strikes, with extended lip for<br />

latch bolts, except open strike plates may be used in wood frames. Provide dustproof strikes for foot bolts.<br />

9. Tactile Warning: Provide locks with tactile warning for handicapped codes when required by Authority<br />

Having Jurisdiction.<br />

B. Locks by types:<br />

Type Description Finish MANUFACTURER/MODEL<br />

Schlage<br />

L-1 Mortise Cylinder 626 20-001<br />

L-2 Mortise Cylinder 626 20-001-1-1/4 inches<br />

L-3 Rim Cylinder 626 20-022<br />

L-4 Classroom Lock 626 ND70PD-Rhodes<br />

L-5 Storeroom Lock (F86) 626 ND80PD-Rhodes-25<br />

L-6 Office Lock (F82) 626 ND50PD-Rhodes-10-025<br />

L-7 Passage Latch (F75) 626 ND10S-Rhodes-10-025<br />

L-8 Privacy Lock (F76) 626 ND40S-Rhodes-10-025<br />

L-9 Dead Bolt Lock 626 B661P<br />

L-10 Access Control Lock 626 KC5196-2<br />

L-11 Entrance Lock (F81/82) 626 ND53PD-Rhodes-10-025<br />

L-12 Storeroom Lock with 626 L9480-06L<br />

deadbolt<br />

L-13 Institutional Lock (F87) 626 ND82PD-Rhodes-10-025<br />

L-15 Entrance Lock with deadbolt 626 L9453-06L<br />

L-16 Dead Bolt Lock with 626 B663P<br />

Thumbturn (Classroom<br />

Function)<br />

L-17 Storeroom Lock (Grade 2) 626 AL80PD-Saturn<br />

L-18 Privacy Lock (Grade 2) 626 AL40S-Saturn<br />

L-20 Office Lock<br />

626 AL50PD-Saturn<br />

(Grade 2)<br />

L-21 Passage Latch (Grade 2) 626 AL10S-Saturn<br />

L-22 Thumbturn 626 09-905NHxB502-292<br />

2.7 EXIT DEVICES<br />

A. Materials:<br />

1. Provide exposed metal to match hardware.<br />

2. Size and mount units indicated or, if not indicated, to comply with manufacturer's recommendations for<br />

exposure condition. Reinforce substrate as recommended.<br />

08710 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Exit Devices by types:<br />

Type Description Finish MANUFACTURER/MODEL<br />

Von Duprin unless otherwise noted.<br />

E-1 Exit Device: Rim, exit only, UL listed. 626 99EO-F<br />

E-2 Exit Device: Rim, exit only, with alarm. Provide exterior<br />

access model, time delay, or weatherproof when scheduled.<br />

08710 - 5<br />

600 Positive Lock:<br />

THPA Series (Size as required for door<br />

scheduled)<br />

O/A - Outside Access<br />

TDL -Time Delay<br />

WE - Weatherproof<br />

E-3 Exit Device: Surface vertical rod (top rod only), lever trim, 626 9927L-F-BE-LBR<br />

blank escutcheon, UL listed.<br />

E-4 Exit Device: Concealed vertical rod, lever trim, blank 626 9948L-F-BE<br />

escutcheon, UL listed<br />

E-5 Exit Device: Rim, lever trim, blank escutcheon, UL listed. 626 99L-F-BE<br />

E-7 Exit Device: Rim, pull trim. 626 99NL x 697NL<br />

E-8 Exit Device: Rim delay exit device, pull trim, with alarm.<br />

Power Transfer #EPT-10<br />

Power Supply #PS 914<br />

626<br />

SP28<br />

CX9975L x<br />

992L<br />

(06 Lever)<br />

E-10 Exit Device: Rim, exit only 626 99EO<br />

E-11 Exit Device: Rim, weatherproof, exit only, with alarm. 626 Detex:<br />

E-14 Exit Device: Vertical Rod, exit only, with alarm. Provide<br />

outsite access model or time delay when scheduled.<br />

V40 EB W AL RWE<br />

600 Positive Lock:<br />

THPA Series<br />

(O/A) - Outside Access<br />

(TDL) -Time Delay<br />

E-16 Exit Device: Rim, lever trim 626 99L-992L-NL<br />

E-18 Exit Device: Rim, lever trim, UL Listed 626 99L-F-992L-NL<br />

E-19 Exit Device: Surface vertical rod, no outside trim, exit only, 626 9927EO-F<br />

UL listed.<br />

E-20 Exit Device: Rim, lever trim, blank escutcheon 626 99L-BE<br />

E-21 Exit Device 626 99EO<br />

E-22 Exit Device Trim 626 CM993-MGK-FSE-06-KD<br />

E-23 Exit Device: Rim, lever trim, with alarm<br />

Power Transfer #EPT-10<br />

Power Supply #PS-914<br />

E-24 Exit Device: Rim, lever trim, with alarm<br />

Power Transfer #EPT-10<br />

Power Supply #PS-914<br />

2.8 PULLS AND PUSHES<br />

A. Materials: ANSI A 156.6 for 0.050 inch thickness.<br />

B. Push and Pulls by types:<br />

626<br />

SP28<br />

626<br />

SP28<br />

CX99NL-F x 696-NL<br />

CX99EO-F<br />

Type Description Finish MANUFACTURER/MODEL<br />

Ives Trimco Rockwood<br />

P-1 Push 3-1/2 x 15 630 8200 1001-2 70B<br />

P-2 Pull 3-1/2 x 15 630 8311-5 1012-2 137x70B<br />

P-3 Pull 8 inches CTC x 3/4 inch 630 8103-8 1194-2 107<br />

dia<br />

P-4 Pull 5-1/4 cc 630 8111-5 1102T 132<br />

P-5 Pocket Door Pull Latching black 1069L<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.9 CLOSERS<br />

A. Materials & Features:<br />

1. ANSI A 156.4, grade 1.<br />

2. ADA/ANSI A117.1<br />

3. UL listed.<br />

4. Non-handed, non-sized; adjustable 1-6.<br />

5. 180 degree door opening.<br />

6. Standard cover.<br />

7. Multiple backcheck location valve.<br />

8. Extreme temperature fluid.<br />

9. Sex nuts and bolts (SNBs).<br />

10. Provide exposed metal to match hardware.<br />

11. Size and mount units indicated or, if not indicated, to comply with manufacturer's recommendations for<br />

exposure condition. Reinforce substrate as recommended.<br />

B. Closers by types:<br />

Type Description Finish MANUFACTURER/MODEL<br />

LCN<br />

C-4 Closer: Regular Arm 689 4011-REG<br />

C-5 Closer: Parallel Arm 689 4111-EDA<br />

C-6 Closer: Regular Arm 689 4031-REG<br />

C-7 Closer: Parallel Arm 689 4031-EDA<br />

C-8 Closer: Parallel Arm, HO 689 4111-HEDA<br />

C-9 Closer: Parallel Arm, HO, positive 689 4111-H-CUSH<br />

stop<br />

C-10 Closer: Regular Arm, HO 689 4031-H<br />

C-11 Closer: Parallel Arm, positive stop 689 4031-CUSH<br />

C-12 Closer: Parallel Arm, positive stop 689 4111-CUSH<br />

2.10 DOOR PROTECTION PLATES<br />

A. Materials: J100 Protection Plates conforming to ANSI A 156.6, stainless steel, 0.050" (1.2 mm) minimum<br />

thickness. Mount centered, flush with bottom of door. Screws: Phillips head sheet metal screws plated to match<br />

plate.<br />

B. Protection Plates by types:<br />

Type Description Size Finish MANUFACTURER/MODEL<br />

Ives Trimco Rockwood<br />

K-2 Kick Plate 10" x (DW-2") 630 8400 K1050 J102<br />

K-3 Armor Plate 34" x (DW-2") 630 8400 K1050 J101<br />

K-4 Armor Plate 41” x (DW-2”) 630 8400 K1050 J101<br />

Notch for lockset<br />

K-5 Kick Plate 18" x (DW-2") 630 8400 K1050 J102<br />

K-6 Armor Plate (UL Rated) 34" x (DW-2") 630 8402 UL KA050-2 Fire Rated K1050F<br />

K-7 Armor Plate (UL Rated) 36" x (DW-2") 630 8402 UL KA050-2<br />

Fire Rated<br />

K1050F<br />

2.11 STOPS, HOLDERS AND BUMPERS<br />

A. Materials:<br />

1. Door Stop mounting: Methods to suit substrates encountered (plastic anchor, drywall anchor, expansion<br />

shield).<br />

08710 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Provide gray rubber exposed resilient parts.<br />

3. Do not furnish aluminum floor stops.<br />

4. For most doors, the preferred door stop is Wall Stop type S-1 and is specified as such in the hardware<br />

schedule. However, if circumstances prevent a wall stop installation (door too far from perpendicular wall,<br />

door swing into adjacent glass, etc.) then substitute a type S-3 or S-4 floor stop as indicated for use<br />

intended.<br />

5. Adjust height of floor stops to suit undercut of adjacent door.<br />

B. Stops, Holders and Bumpers by types:<br />

Type Description Finish MANUFACTURER/MODEL<br />

Ives Trimco Rockwood<br />

S-1 Wall Stop 630 WS407CVX W1276CS 409<br />

S-2 Stop & Holder 626 FS445 1207 477<br />

S-4 Floor Stop 626 FS438 1212 3/4ES 442<br />

Rixson<br />

Glynn-Johnson<br />

S-5 Overhead Stop - 3-0 doors 626 9-336 904S<br />

S-6 Overhead Stop - 2-6 doors 626 9-236 902S<br />

S-7 Stop & Holder. Kick down<br />

type satin chrome<br />

Ives Trimco Rockwood<br />

FS452-4 1220-4FF 458<br />

Rixson<br />

Glynn-Johnson<br />

S-8 Overhead Stop. Medium duty 630 10-236 452S<br />

2.12 ELECTROMAGNETIC DOOR HOLDERS<br />

A. Materials & Features:<br />

1. ANSI A 156.15, Grade 1.<br />

2. UL listed.<br />

3. Magnet protected against transients and surges up to 600 volts.<br />

4. 24V DC<br />

5. Holding force 35 lbs., nominal.<br />

6. Low residual magnetism for easy release of door.<br />

7. Electrical values +10% -15%.<br />

8. Provide exposed metal to match hardware.<br />

B. Electromagnetic Door Holders by types:<br />

Type Description Finish MANUFACTURER/MODEL<br />

LCN<br />

Rixson<br />

DH-1 Door Holder 689 SEM 7850 689 FM-998 SA<br />

08710 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.13 THRESHOLDS<br />

A. Thresholds by types:<br />

Type Description MANUFACTURER/MODEL<br />

National Pemko Reese<br />

Guard<br />

T-1 Threshold: 5 inches x 1/4 inch, abrasive. 425HD-SIA 1715AK 5”<br />

5”<br />

T-4 Threshold: 2 inches x 1/8 inch, stainless steel plate, smooth surface,<br />

beveled 1 side only. Transition threshold between concrete slab and<br />

BAR6SS-2-<br />

10bevel<br />

vinyl tile.<br />

Set threshold in full bed of silicone sealant, butted to adjacent vinyl<br />

tile. Anchor into concrete slab with Hilti Kwik-Con II, #14-134 TFH<br />

fasteners spaced at 6-inch centers using Matched Tolerance drill bit for<br />

dense concrete.<br />

T-9 Threshold: 5 inches, aluminum, stop seal 896S 2005AT S483AS<br />

T-10 Threshold: 5 inches, aluminum, stop seal 898V 2006AT<br />

2.14 WEATHERSTRIPPING<br />

A. Weatherstripping by types:<br />

Type Description MANUFACTURER/MODEL<br />

National Guard Pemko Reese<br />

W-3 Door Bottom Sweep, surface mounted sweep, anodized 201NA 315CN 323A<br />

aluminum, neoprene seal.<br />

W-4 Meeting Stile Gaskets, aluminum, silicone insert seal. 160S 303AS 807A<br />

W-5 Jamb Door Gaskets, adhesive application, silicone seal. 5050B S88D 797B<br />

W-9 Jamb and Head Weatherstripping: Self Adhesive Seal 5075B S773D<br />

2.15 MISCELLANEOUS HARDWARE<br />

A. Silencers: Provide in metal door frames, unless not permitted for fire rating, or unless bumper-type<br />

weatherstripping is provided; three for each single door frame, two for double-door frame.<br />

B. Miscellaneous Hardware by types:<br />

Type Description Size Finish MANUFACTURER/MODEL<br />

Stanley Ives Rockwood<br />

M-1 Hasp & 3-1/2 602 SP915 WS1920<br />

Staple inches<br />

M-3 Surface 4 inches 626 40 630<br />

Bolt<br />

M-4 Viewer 626 700 620<br />

Ives Trimco Rockwood<br />

M-5 Extension<br />

Flush<br />

Bolts (UL)<br />

12<br />

inches<br />

626 458 3917 555<br />

M-6 Automatic<br />

Flush Bolt<br />

626 FB42 1948<br />

Ives Trimco Rockwood<br />

M-8 Silencers SR64 1229-A 608<br />

National Guard Pemko Reese<br />

M-9 Drip Cap 16A 346CxFW R201A<br />

08710 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Type Description Size Finish MANUFACTURER/MODEL<br />

Stanley Ives Rockwood<br />

Ives<br />

Trimco<br />

M-10 Door Coordinator COR x MB x FL 3092 x MB x W<br />

Arrow<br />

Detex<br />

M-11 Door Alarm 626 130 Series AL EAX-500<br />

M-12 Door Alarm gray Alarm: EAX-2500F<br />

Transformer: PP5152-3<br />

Rockwood<br />

M-14 Mail Slot 630 RS-2-1251-32D<br />

M-15 Latch Protector 630 321<br />

Von Duprin Schlage Securitron<br />

M-16 Electric Strike, grade 630 6211<br />

1, FSE (fail secure),<br />

24VDC unless noted<br />

otherwise in schedule<br />

M-17 Power Supply PS902<br />

M-18 Push Button 660PB<br />

M-19 Electric Strike 626 UNL-24<br />

M-20 Power Supply BPS-24-1<br />

M-21 Keypad & Controller DK-26SS<br />

M-21a Keypad DK-26PSS<br />

M-22 Power Transfer SP28 EPT10<br />

M-23 Magnetic Stripe Card MAG1<br />

Von Duprin<br />

M-24 Mullion 626 9954<br />

M-25 Strike 626 499F<br />

2.16 FABRICATION<br />

A. Finish and Base Material Designations: Number indicates Builders Hardware Manufacturer’s Association<br />

(BHMA) Code or nearest traditional U.S. commercial finish.<br />

B. Where base material and quality of finish are not otherwise indicated, provide at least commercially recognized<br />

quality.<br />

C. Fasteners: Provide door hardware manufactured to comply with published templates prepared for machine, wood,<br />

and sheet metal screws. Provide screws that comply with commercially recognized industry standards for<br />

application intended, except aluminum fasteners are not permitted. Provide Phillips flat-head screws with finished<br />

heads to match surface of door hardware, unless otherwise indicated.<br />

1. Fire-Rated Applications:<br />

a. Wood or Machine Screws: For the following:<br />

1) Hinges mortised to doors or frames.<br />

2) Strike plates to frames.<br />

3) Closers to doors and frames.<br />

b. Steel Through Bolts: For the following unless door blocking is provided:<br />

1) Surface hinges to doors.<br />

2) Closers to doors and frames.<br />

3) Surface-mounted exit devices.<br />

2. Spacers or Sex Bolts: For through bolting of hollow-metal doors.<br />

3. Gasketing Fasteners: Provide noncorrosive fasteners for exterior applications and elsewhere as indicated.<br />

08710 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that doors and frames are ready to receive Work and dimensions are as instructed by the manufacturer.<br />

B. Verify that electric power is available to power operated devices and of the correct characteristics.<br />

3.2 INSTALLATION<br />

A. Hardware Mounting Heights: Door and Hardware Institute Recommended Locations for Builders Hardware for<br />

Standard Steel Doors and Frames, except as otherwise indicated.<br />

1. Conform to requirements of applicable local, State or Federal disabled access requirements for the<br />

installation and operation of door hardware.<br />

2. Install electromagnetic door holder at 24 inches above finish floor elevation at manufacturer’s<br />

recommended distance from the door’s leading edge.<br />

B. Install each hardware item to comply with manufacturer's instructions and recommendations, unless otherwise<br />

specified.<br />

C. Thru-bolt closers on doors.<br />

D. Vestibule Thresholds: Install as shown on Drawings.<br />

3.3 FIELD QUALITY CONTROL BY OWNER<br />

A. Manufacturer's Technical Representative will provide site observation at completion of installation of doors and<br />

hardware including the following.<br />

1. Inspect closers; exit devices (except Detex and Positive Lock); locks, latches, and bolts; and electric strikes.<br />

2. Verify hardware installed is as specified.<br />

3. Verify proper installation.<br />

4. Verify proper operation.<br />

B. Manufacturer’s Technical Representative shall be the manufacturer of the items to be inspected. Contractor shall<br />

notify the following manufacturer’s representative completion of installation doors and hardware:<br />

1. Jerry Davis, IR Security & Safety National Accounts Manager (678) 906-2106, jerry_davis@irco.com<br />

C. Manufacturer’s Technical Representative will prepare Observation Report and submit to Architect for posting by<br />

Architect of deficiencies on the Wal-Mart Observation Log. Observation Report will indicate the following:<br />

1. Store number and location.<br />

2. Time and date of observation.<br />

3. Name and contact information of Manufacturer’s Technical Representative.<br />

4. Summary of observation.<br />

5. Identification of deficiencies describing precise door number, hardware item, nature of deficiency, and<br />

recommended resolution.<br />

6. Signature of Manufacturer’s Technical Representative.<br />

3.4 ADJUSTING<br />

A. Hardware Adjustment: Adjust hardware for proper operation and function one month after Substantial<br />

Completion. Instruct Wal-Mart personnel in proper maintenance and adjustment.<br />

08710 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.5 HARDWARE SCHEDULE<br />

A. Hardware Set numbers below correspond to the Door Schedule as shown on the drawings.<br />

B. Any hardware item specified in the Tables in Part 2 above which corresponds to the mark associated with the item<br />

(E.g., “H-1, E-2, etc.) as shown in the Hardware Schedule below may be provided.<br />

Door 100A - Sales: HM, Pair, Exterior w/ Exit Device<br />

3 pr. H-11 Butts<br />

2 ea. E-14 Alarm Exit Device<br />

1 ea. T-9 Threshold<br />

2 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

1 pr. W-4 Meeting Style Gaskets<br />

Door 100B - Sales: HM, Two Singles, Exterior w/ Exit Device<br />

3 pr. H-11 Butts<br />

2 ea. E-2 Alarm Exit Device<br />

2 ea. T-9 Threshold<br />

2 ea. W-3 Door Bottom Weatherstrip<br />

2 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Door 100C - Sales: HM, Two Singles, Exterior w/ Exit Device<br />

3 pr. H-11 Butts<br />

2 ea. E-2 Alarm Exit Device<br />

2 ea. T-9 Threshold<br />

2 ea. W-3 Door Bottom Weatherstrip<br />

2 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Doors 100D - Sales: HM, Single, Exterior w/ Exit Device<br />

1-1/2 pr. H-11 Butts<br />

1 ea. E-2 Alarm Exit Device<br />

1 ea. T-9 Threshold<br />

1 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Doors 100E - Sales: HM, Single, Exterior w/ Exit Device<br />

1-1/2 pr. H-11 Butts<br />

1 ea. E-2 Alarm Exit Device<br />

1 ea. T-9 Threshold<br />

1 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Door 101C - Vestibule: Aluminum/Glass, Bi-Parting Automatic w/ Breakaway<br />

1 ea. L-1 Keyed Cylinder<br />

1 ea. Locking Device See Section 08462.<br />

1 ea. Threshold See Section 08462.<br />

All other hardware furnished by door manufacturer as specified in Section 08462.<br />

08710 - 11<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Door 101D - Vestibule: Aluminum/Glass, Bi-Parting Automatic w/ Breakaway<br />

1 ea. L-1 Keyed Cylinder<br />

1 ea. Locking Device See Section 08462.<br />

1 ea. Threshold See Section 08462.<br />

All other hardware furnished by door manufacturer as specified in Section 08462.<br />

Door 102A - Mechanical: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 ea. K-3 Armor Plate<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 104A - Cart Storage: Sectional Overhead, Steel<br />

Hardware furnished by door manufacturer as specified in Section 08360.<br />

Door 107A - Cash: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-12 Storeroom Lock w/ Deadbolt<br />

1 ea. C-4 Closer<br />

3 ea. M-8 Silencers<br />

1 ea. S-1 Wall Stop<br />

2 ea. M-4 One-Way Viewer Mount 1 ea @ 48” & 60” AFF<br />

Door 108A - Counting: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-12 Storeroom Lock w/ Deadbolt<br />

1 ea. C-4 Closer<br />

3 ea. M-8 Silencers<br />

1 ea. S-1 Wall Stop<br />

2 ea. M-4 One-Way Viewer Mount 1 ea @ 48” & 60” AFF<br />

Door 109A - Equipment: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

3 ea. M-8 Silencers<br />

1 ea. S-1 Wall Stop<br />

Door 112A – Elec-2: HM, Single, Exterior w/ Exit Device, w/ Outside Access<br />

1-1/2 pr. H-11 Butts<br />

1 ea. E-2 Alarm Exit Device (O/A) w/ mortise cylinder and removable core<br />

1 ea. P-3 Pull<br />

1 ea. T-9 Threshold<br />

1 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Door 113A – Store Manager’s Office: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-6 Office Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

08710 - 12<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Door 119A – AP Office: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-20 Office Lockset<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 127A - Closet: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

3 ea. M-8 Silencers<br />

1 ea. S-8 Overhead Stop<br />

Door 141A - Hallway: HM, Pair, Exterior w/ Exit Device<br />

3 pr. H-11 Butts<br />

2 ea. E-14 Alarm Exit Device<br />

1 ea. T-9 Threshold<br />

2 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

1 pr. W-4 Meeting Style Gaskets<br />

Door 141B - Hallway: HM, Pair, w/ Exit Device, UL Label, Interior<br />

2 ea. H-7 Continuous Geared Hinge<br />

2 ea. E-4 Exit Device<br />

2 ea. C-6 Closer<br />

1 set W-5 Door Gaskets<br />

1 pr. W-4 Meeting Style Gaskets<br />

2 ea. K-6 Armor Plate<br />

2 ea. DH-1 Door Holder<br />

Door 141C - Hallway: HM, Pair, w/ Exit Device, UL Label, Interior<br />

2 ea. H-7 Continuous Geared Hinge<br />

2 ea. E-4 Exit Device<br />

2 ea. C-6 Closer<br />

1 set W-5 Door Gaskets<br />

1 pr. W-4 Meeting Style Gaskets<br />

2 ea. K-6 Armor Plate<br />

2 ea. DH-1 Door Holder<br />

Door 141D - Hallway: HM, Pair, w/ Exit Device, UL Label, Interior<br />

2 ea. H-7 Continuous Geared Hinge<br />

2 ea. E-4 Exit Device<br />

2 ea. C-6 Closer<br />

1 set W-5 Door Gaskets<br />

1 pr. W-4 Meeting Style Gaskets<br />

2 ea. K-6 Armor Plate<br />

2 ea. DH-1 Door Holder<br />

Door 151B - Breakroom: HM, Single, w/ Exit Device<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. E-5 Exit Device<br />

1 ea. C-8 Closer<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

08710 - 13<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Door 151C - Breakroom: HM, Single, w/ Exit Device<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. E-5 Exit Device<br />

1 ea. C-8 Closer<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 153A – UPC/UPS: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 ea. S-5 Overhead Stop<br />

3 ea. M-8 Silencers<br />

Door 154A - Electrical: HM, Single, Interior, w/ Exit Device<br />

1 ea. H-7) Continuous Geared Hinge<br />

1 ea. E-5 Exit Device<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

1 ea. C-7 Closer<br />

Door 154B - Electrical: HM, Single, Interior, w/ Exit Device<br />

1 ea. H-7) Continuous Geared Hinge<br />

1 ea. E-5 Exit Device<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

1 ea. C-7 Closer<br />

Door 159A - Sprinkler: HM, Single, Interior<br />

1 ea. H-7) Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

1 ea. C-7 Closer<br />

Door 167A - Family Toilet: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-8 Bathroom Privacy Lock<br />

1 ea. C-4 Closer<br />

1 ea. K-3 Armor Plate<br />

1 ea. S-7 Stop and Holder<br />

3 ea. M-8 Silencers<br />

Door 168E – Site to Store Storage: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-5 Storeroom Lock<br />

1 ea. C-9 Closer<br />

1 ea. K-3 Armor Plate<br />

3 ea. M-8 Silencers<br />

Door 171A - Invoicing: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-5 Storeroom Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

08710 - 14<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Door 172A - Training Room: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea L-6 Office Lockset<br />

1 ea. C-9 Closer<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 173A - Personnel: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 175A – Ad Office: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-6 Office Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 176A – Hallway: HM, Single, Exterior w/ Exit Device<br />

1-1/2 pr. H-11 Butts<br />

1 ea. E-2 Alarm Exit Device<br />

1 ea. T-9 Threshold<br />

1 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 set M-9 Drip Cap<br />

Door 176B – Hallway or Corridor: HM, Pair, Interior, Exit Device<br />

2 ea. H-7 Continuous Geared Hinge<br />

2 ea. E-19 Exit Device<br />

2 ea. M-11 Door Alarm<br />

1 ea. L-2 Cylinder for Alarm<br />

1 ea. C-7 Closer<br />

2 ea. S-1 Wall Stop<br />

2 ea. M-8 Silencers<br />

Door 178A - Receiving (GM): HM, Single, Exterior w/ Exit Device<br />

1-1/2 pr. H-11 Butts<br />

1 ea. E-2 Alarm Exit Device<br />

2 ea. M-4 One-Way Viewer Mount 1 ea @ 48” & 60” AFF<br />

1 ea. T-9 Threshold<br />

1 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Door 178B - Receiving (GM): Sectional Overhead, At Grade, Exterior<br />

Hardware furnished by door manufacturer per Section 08360.<br />

Door 178C - Receiving (GM): Sectional Overhead, Exterior<br />

Hardware furnished by door manufacturer per Section 08360.<br />

Door 178D - Receiving (GM): Sectional Overhead, Exterior<br />

Hardware furnished by door manufacturer per Section 08360.<br />

Door 178E - Receiving (GM): Sectional Overhead, Exterior<br />

Hardware furnished by door manufacturer per Section 08360.<br />

08710 - 15<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Door 178M – Receiving (GM): Full Height Traffic, Pair<br />

1 ea. T-4 Threshold<br />

Hardware furnished by door manufacturer per Section 08383.<br />

Door 181A – Mens Toilet: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-8 Bathroom Privacy Lock<br />

1 ea. C-4 Closer<br />

1 ea. K-3 Armor Plate<br />

1 ea. S-7 Stop and Holder<br />

3 ea. M-8 Silencers<br />

Door 182A – Womens Toilet: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-8 Bathroom Privacy Lock<br />

1 ea. C-4 Closer<br />

1 ea. K-3 Armor Plate<br />

1 ea. S-7 Stop and Holder<br />

3 ea. M-8 Silencers<br />

Door 185A – Bale and Pallet Storage: Ornamental Metal, Pair<br />

Hardware furnished by fence manufacturer per Section 02823.<br />

Door 200A – Rack-In-A-Box: HM, Pair, Interior<br />

2 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 set M-5 Extension Flush Bolts<br />

2 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

1 ea. Astragal (Inactive leaf) by HM door mfg<br />

08710 - 16<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PHARMACY<br />

Door 300A - Pharmacy: HM, Single, Pass-Thru, w/ Shutter Cutout<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-15 Entrance Lock w/ Deadbolt Primus XP<br />

1 ea. C-5 Closer<br />

2 ea. K-2 Kick Plate<br />

3 ea. M-8 Silencers<br />

Door 300B - Pharmacy: Coiling Counter Shutter<br />

Hardware furnished by door manufacturer per Section 08337.<br />

Door 300C - Pharmacy: Coiling Counter Shutter<br />

Hardware furnished by door manufacturer per Section 08337.<br />

Door 300E - Pharmacy: Coiling Counter Shutter on HM Door<br />

Hardware furnished by door manufacturer per Section 08337.<br />

Door 300H - Pharmacy: Overhead Rolling Closure<br />

Hardware furnished by door manufacturer per Section 08332.<br />

Door 301A - Pharmacy Toilet: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-18 Bathroom Privacy Lock<br />

1 ea. C-11 Closer<br />

3 ea. M-8 Silencers<br />

Door 302A - Pharmacy Checkout Café Traffic, Single<br />

Harware furnished by door manufacturer per Section 08383.<br />

Door 304A – Pharmacy Storage: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-5 Storeroom Lock<br />

1 ea. C-7 Closer<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

08710 - 17<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


GARDEN CENTER<br />

Door 500G – Inside Sales: Aluminum/Glass, Bi-Parting Automatic, Exterior<br />

1 ea. L-1 Keyed Cylinder<br />

1 ea. L-22 Thumbturn<br />

1 ea. Locking Device See Section 08462.<br />

All other hardware furnished by door manufacturer as specified in Section 08462.<br />

Door 500H – Inside Sales: Aluminum/Glass, Single Slide Automatic, Exterior<br />

1 ea. L-1 Keyed Cylinder<br />

1 ea. Locking Device See Section 08462.<br />

All other hardware furnished by door manufacturer as specified in Section 08462.<br />

Door 500J – Inside Sales: HM, Single, Exterior w/ Exit Device<br />

1-1/2 pr. H-11) Butts<br />

1 ea. E-2 Alarm Exit Device<br />

1 ea. T-9 Threshold<br />

1 ea. W-3 Door Bottom Weatherstrip<br />

1 set W-9 Jamb & Head Weatherstrip<br />

1 ea. M-9 Drip Cap<br />

Door 500K – Inside Sales: HM, Two Singles<br />

2 ea. H-7 Continuous Geared Hinge<br />

2 ea. L-12 Storeroom Lock w/ Deadbolt<br />

2 ea. C-4 Closer<br />

6 ea. M-8 Silencers<br />

2 ea. S-1 Wall Stop<br />

Door 501A - Outside Live Goods: HM, Single, Exterior with Exit Device<br />

1-1/2 pr. H-11 Butts<br />

1 ea. E-2 Alarm Exit Device (WE)<br />

3 ea. M-8 Silencers<br />

Door 501J - Outside Live Goods: Ornamental Metal, Pair w/Exit Device<br />

2 ea. E-11 Exit Device w/ Alarm<br />

2 ea. L-3 Cylinder for Alarm<br />

All other hardware furnished by fence manufacturer as specified in Section 02823.<br />

08710 - 18<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


GROCERY AREA<br />

Door 912A – Deli Prep: Full Height Traffic, Pair<br />

Hardware furnished by door manufacturer, Section 08383.<br />

Door 931A – Dry Produce Prep: Full Height Traffic, Pair<br />

Hardware furnished by door manufacturer, Section 08383.<br />

Door 981A – EDC #4: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-5 Storeroom Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

Door 982A – Mechanical #1: HM, Single<br />

1 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

1 ea. T-9 Threshold<br />

Door 983A – Mechanical #2: HM, Pair, Interior<br />

2 ea. H-7 Continuous Geared Hinge<br />

1 ea. L-17 Storeroom Lock<br />

1 set M-5 Extension Flush Bolts<br />

2 ea. S-1 Wall Stop<br />

3 ea. M-8 Silencers<br />

1 ea. Astragal (Inactive leaf) by HM door mfg<br />

Door 991A – Stockroom-A: Full Height Traffic, Pair<br />

Hardware furnished by door manufacturer per Section 08383.<br />

END OF SCHEDULE<br />

08710 - 19<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 08800 (08 8000) – GLAZING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Glass and glazing for interior and exterior metal frames and doors.<br />

2. Window Hardware: Sliding glass track assembly.<br />

B. Related Requirements:<br />

1. Section 08110 - Steel Doors and Frames: Glazed doors and fixed window frames.<br />

2. Section 08411 - Aluminum Framed Storefronts: Aluminum storefront framing system.<br />

3. Section 08462 - Automatic Sliding Entrance Doors: Glazed doors.<br />

4. Section 08710 - Door Hardware: Hardware coordination.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI Z97.1 - Safety Performance Specifications and Methods of Test for Safety Glazing Material Used in<br />

Buildings.<br />

C. ASTM International (ASTM):<br />

1. ASTM C 920 - Elastomeric Joint Sealants.<br />

2. ASTM C 1036 - Flat Glass.<br />

3. ASTM C 1048 - Heat-Treated Flat Glass - Kind HS, Kind FT Coated and Uncoated Glass.<br />

4. ASTM D 2000 - Classification System for Rubber Products in Automotive Applications.<br />

5. ASTM E 1886 - Standard Test Method for Performance of Exterior Windows, Curtain Walls, Doors, and<br />

Impact Protective Systems Impacted by Missile(s) and Exposed to Cyclic Pressure Differentials.<br />

6. ASTM E 1996 - Performance of Exterior Windows, Curtain Walls, Doors, and Impact Protective Systems<br />

Impacted by Windborne Debris in Hurricanes.<br />

D. Consumer Product Safety Standards for Architectural Glazing CPSC 16 CFR, Part 1201.<br />

E. Flat Glass Marketing Association (FGMA):<br />

1. FGMA - Glazing Manual and Glazing Sealing Systems Manual.<br />

F. National Fire Protection Agency (NFPA):<br />

1. NFPA 252: Standard Methods of Fire Tests of Door Assemblies.<br />

2. NFPA 257: Standard on Fire Test for Window and Glass Block Assemblies.<br />

G. Underwriters Laboratories, Inc. (UL):<br />

1. UL 10B - Fire Tests of Door Assemblies.<br />

1.3 SUBMITTALS<br />

A. Contract Closeout Submittals: Submit the following under provisions of Section 01770.<br />

1. Letters of Certification: Submit certification from fire-protection-rated glazed light manufacturer that<br />

permancent label identification is applied on each glazed light.<br />

08800 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 QUALITY ASSURANCE<br />

A. Conform to FGMA Glazing Manual for glazing installation methods.<br />

B. Provide permanent labeling for safety glass indicating conformance with specified standards.<br />

C. Fire-Protection-Rated Glazing Labeling: Permanently mark fire-protection-rated glazing with a UL label of<br />

certification or label of certification of a testing agency acceptable to Authorities Having Jurisdiction. Label shall<br />

indicate manufacturer's name, test standard, whether glazing is for use in fire doors or other openings, whether or<br />

not glazing passes hose-stream test, whether or not glazing has a temperature rise rating of 450 degrees and the<br />

fire-resistance rating in minutes.<br />

PART 2 - PRODUCTS<br />

2.1 GLASS MATERIALS<br />

A. Tempered Glass: ASTM C 1048, Kind FT (Fully Tempered), Condition A (Uncoated), Type I (Transparent<br />

Glass, Flat), Quality q3 (Glazing Select).<br />

1. Conform to ANSI Z97.1 and CPSC 16CFR Part 1201.<br />

2. Tempered glazing panels as specified in the Glass Schedule below (including doors, sidelights, storefronts,<br />

and transoms) shall comply with the CPSC 16CFR Part 1201 criteria for Category I or II as follows:<br />

a. Glazing Panels 9 sq. ft. or less: Category I.<br />

b. Glazing Panels more than 9 sq. ft.: Category II.<br />

c. Thickness:<br />

1) 1/4 inch unless otherwise shown or specified.<br />

2) 3/8 inch at butt glazing where shown on Drawings.<br />

3. Clear: Class 1 (Clear).<br />

4. Tinted: Class 2 (Tinted Heat Absorbing and Light Reducing).<br />

a. Color: Solarbronze by PPG Industries, Inc.<br />

B. Acid-etched Glass: Tempered, acid-etched, ASTM C 1048, Kind FT (Fully Tempered), Condition A (Uncoated),<br />

Type I (transparent glass, flat), Class 1 (clear), Quality q3 (glazing select). Provide the following product:<br />

1. SF101 by Viracon, Owatonna, MN (800) 533-2080.<br />

C. Insulated Units: Double pane units, tempered glass, as specified above.<br />

1. Clear: Both inner and outer panes of clear tempered glass as specified above.<br />

2. Acid etched: Inner pane of clear tempered glass with acid etched No. 3 surface and outer pane of tinted<br />

tempered glass as specified above.<br />

3. Unit Thickness: 1 inch thick units; 1/4 inch thick inner and outer panes, with 1/2 inch air space between.<br />

D. Fire-Protection-Rated Glazing, General: Listed and labeled by a testing agency acceptable to Authorities Having<br />

Jurisdiction, for fire-protection ratings indicated, based on testing according to NFPA 252 for door assemblies and<br />

NFPA 257 for window assemblies.<br />

1. Vision Light Metal Frame: Manufacturer's standard frame formed of 0.048-inch- thick, cold-rolled steel<br />

sheet and approved for use in doors of fire-protection rating indicated. Factory prime for field painting.<br />

Size as indicated on Drawings.<br />

2. Laminated Ceramic Glazing: Laminated glass made from two plies of clear, ceramic flat glass; 5/16-inch<br />

total nominal thickness; for fire doors and frame assemblies rated up to 1-1/2 hours, tested and certified to<br />

meet requirements of standard UL 10B and CPSC 16CFR Part 1201 criteria for Category I and Category II<br />

applications. Provide the following product:<br />

a. FireLite Plus by Nippon Electric Glass Company, Ltd., and distributed by Technical Glass Products,<br />

Snoqualmie, WA, (800) 426-0279.<br />

3. Glazing Tape: Closed cell polyvinyl chloride (PVC) foam, coiled on release paper over adhesive on two<br />

sides, maximum water absorption by volume of 2 percent. Glass panels that exceed 1,393 sq. inches for<br />

90-minute ratings shall be glazed with fire-rated glazing tape supplied by manufacturer.<br />

08800 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Identification:<br />

1. Each unit of tempered glass shall be permanently identified by the manufacturer. The identification shall<br />

be etched or ceramic fired on the glass and be visible when the unit is glazed.<br />

2.2 GLAZING COMPOUNDS<br />

A. Polysulphide Sealant: Two component, chemical curing, non-sagging type; cured Shore A hardness of 15-25.<br />

B. Silicone Sealant: Single component, chemical curing; capable of water immersion without loss of properties; nonbleeding,<br />

non-staining; cured Shore A hardness of 15-25.<br />

1. Color: Clear.<br />

C. Acrylic terpolymer compounded especially for glazing; non-hardening, non-staining, and non-bleeding.<br />

2.3 GLAZING ACCESSORIES<br />

A. Setting Blocks: Resilient blocks of 70 to 90 Shore A durometer hardness; compatible with glazing sealant.<br />

B. Spacers: Resilient blocks of 40 to 50 Shore A durometer hardness; self adhesive on one side; compatible with<br />

glazing sealant.<br />

C. Filler Rods: Closed cell or jacketed foam rods of polyethylene, butyl, neoprene, polyurethane, or vinyl;<br />

compatible with glazing sealant.<br />

D. Joint Cleaners, Primers, and Sealers: As recommended by glazing sealant manufacturer.<br />

E. Gaskets: ASTM D2000, SBC 415 to 3BC 620; extruded or molded neoprene or EPDM, black.<br />

F. Butt Joint “H” Trim: CRL Satin Anodized 1/4" "H" Channel, by C.R. Laurence Company Inc., Los Angeles, CA<br />

(800) 421-6144.<br />

G. Stainless Steel Frame (Pharmacy Privacy Wall Glass Frame): CRL Brushed Stainless Anodized Wet Glaze 1-1/2"<br />

Deep "U" Channel Catalog No. WU1BSCL, by C.R. Laurence Company Inc., Los Angeles, CA (800) 421-6144.<br />

H. Aluminum Angle (Pharmacy Privacy Wall Glass Retainer): CRL 1” Satin Anodized Angle Extrusion. Catalog<br />

No. D1634A, by C.R. Laurence Company Inc., Los Angeles, CA (800) 421-6144.<br />

2.4 SLIDING WINDOW HARDWARE<br />

A. Sliding Glass Track (UPC/Merch Windows): Zinc-plated steel sliding glass window track assembly including<br />

upper channel, shoe, ball-bearing carrier, lower track, and nickel finish adjustable lock. Provide sliding glass<br />

window assembly Model No. KV P992 and Lock KV 965, as manufactured by Knape & Vogt Manufacturing<br />

Company.<br />

2.5 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify surfaces of glazing channels or recesses are clean, free of obstructions, and ready for work of this Section.<br />

3.2 PREPARATION<br />

A. Clean contact surfaces; prime or seal where recommended by sealant manufacturer for intended application.<br />

08800 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Inspect glass edges immediately prior to setting; discard those with edge damage that will contribute to glazing<br />

failure.<br />

3.3 GLAZING<br />

A. Locate setting blocks at quarter points of sill; set in sealant if heel or toe bead is required.<br />

B. Install spacers inside and out except where preshimmed tape or glazing gaskets are to be used.<br />

C. Set each piece in a series to other pieces in pattern draw, bow, or other visually perceptible characteristics.<br />

D. Provide glazing sealants and gaskets as required for particular glazing application. Coordinate with other Sections<br />

for material compatibility.<br />

E. Gaskets:<br />

1. Provide adequate anchorage, particularly for driven-in wedge gaskets.<br />

2. Miter and weld ends of channel gaskets at corners to provide continuous gaskets.<br />

3. Seal face gaskets at corners with sealant to close opening and prevent withdrawal of gaskets from corners.<br />

F. Do not leave voids in glazing channels except as specifically indicated or recommended by glass manufacturer.<br />

Force sealant into channel to eliminate voids. Tool exposed surfaces to slight wash away from joint. Trim and<br />

clean promptly.<br />

G. Do not allow sealant to close weeps of aluminum framing.<br />

H. Provide filler rod where sealants are used in the following locations:<br />

1. Head and jamb channels.<br />

2. Colored glass over 75 united inches in size.<br />

3. Clear glass over 125 united inches in size.<br />

3.4 INSTALLATION - BUTT GLAZED METHOD<br />

A. Apply “H” Trim at butt joints at locations shown on the drawings in accordance with manufacturer’s instructions.<br />

3.5 SLIDING WINDOW TRACK INSTALLATION<br />

A. Attach sliding window track assembly to hollow metal frame with double faced tape or adhesive as recommended<br />

by the manufacturer.<br />

3.6 ADJUSTING AND CLEANING<br />

A. Immediately prior to Wal-Mart acceptance of Project, replace broken or otherwise damaged glass. Wash and<br />

polish glass inside and out.<br />

08800 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.7 GLASS SCHEDULE<br />

A. Provide type of glass specified for the applications scheduled as follows:<br />

APPLICATION/LOCATION<br />

TYPE OF GLASS<br />

Interior Windows<br />

Clear tempered glass unless otherwise shown or specified.<br />

Interior Hollow Metal Doors<br />

Clear tempered or fire-rated glass as scheduled on Drawings.<br />

Pharmacy privacy wall<br />

Clear tempered glass as shown on Drawings.<br />

Interior storefront including storefront doors Clear tempered glass.<br />

Exterior storefront<br />

Tinted tempered glass.<br />

Exterior storefront doors<br />

Tinted tempered glass.<br />

Exterior storefront at breakroom and cart storage Insulated acid-etched glass.<br />

Locations shown<br />

Butt Glazed Glass.<br />

Interior Automatic Sliding Doors and Transoms Specified in Section 08462.<br />

Exterior Automatic Sliding Doors and Transoms Specified in Section 08462.<br />

END OF SECTION<br />

08800 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


P+R Architects 060410<br />

SECTION 09100 – LATH AND PLASTER (STUCCO)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Provide Lath and Plaster (Stucco) work as shown on Drawings and as specified, complete. Include without<br />

limitation:<br />

1. All plastering work.<br />

2. Metal Lath.<br />

3. Lathing accessories including expansion screeds, casing beads, corner beads and all similar items normal to<br />

lathing and plastering.<br />

4. Protection of vent screeds during plastering.<br />

1.2 REFERENCE STANDARDS<br />

A. ASTM International (ASTM):<br />

1. ASTM C91 - Standard Specification for Masonry Cement.<br />

2. ASTM C150 - Standard Specification for Portland Cement.<br />

3. ASTM C207 - Standard Specification for Hydrated Lime for Masonry Purposes.<br />

4. ASTM C595 - Standard Specification for Blended Hydraulic Cements.<br />

5. ASTM C897 - Standard Specification for Aggregates for Job-Mixed Portland Cement-Based Plasters.<br />

6. ASTM C1157 - Standard Performance Specification for Hydraulic Cement.<br />

7. ASTM C1329 - Mortar Cement.<br />

8. ASTM C926 - Standard Specification for Application of Portland Cement-Based Plaster.<br />

9. ASTM C1063 - Standard Specification for Installation of Lathing and Furring to Receive Interior and<br />

Exterior Portland Cement-Based Plaster.<br />

B. Canadian Standards Association (CSA):<br />

1. CSA A3001 - Cementitious Materials for Use in Concrete.<br />

2. CSA A3002 - Masonry Cement.<br />

C. Reference Specifications: "Plaster And Drywall Systems Manual" as published by the Information Bureau, Lath,<br />

Plaster and Drywall, Los Angeles, California.<br />

D. Comply with codes, laws, ordinances and regulations of local Authorities having jurisdiction over this part of the<br />

work.<br />

1.3 RELATED WORK<br />

A. Related Work specified elsewhere includes but it is not limited to:<br />

1. Metal framing: Refer to Section 05400.<br />

2. Wood framing: Refer to Section 06100.<br />

3. Insulation in walls: Refer to Section 07210.<br />

4. All work in connection with gypsum drywall: Refer to Section 09250.<br />

5. Painting of standard colored stucco finish: Refer to Section 09900.<br />

6. Clear waterproofing of unpainted integral colored plaster if required by this Project Manual or the<br />

Drawings: As recommended by the integral colored plaster manufacturer.<br />

1.4 SUBMITTALS<br />

A. The Contractor shall prepare 48" x 48" square field sample of the required Plaster Finish at the site for written<br />

approval by the Architect. Refer to Section 01330.<br />

B. Finish Color Coat: Submit samples for the approval of the Architect.<br />

09100 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.5 GENERAL REQUIREMENTS<br />

A. Field Conditions: Verify drawing dimensions with actual field conditions. Inspect related work and adjacent<br />

surfaces. Report to the Architect all conditions that prevent proper execution of this work.<br />

B. Delivery: Deliver all materials in their original containers with seals unbroken and manufacturer's name and<br />

product identification clearly legible on each package.<br />

C. Storage: Store so as to preclude damage from moisture or from any other source.<br />

D. Scaffolding and Protection: Provide, install and maintain for the duration of the work all scaffolding, staging,<br />

trestles and planking necessary for the work in strict conformity with applicable laws and ordinances, and so as not<br />

to interfere with or obstruct the work of others. Provide all forms of protection as necessary to preserve the work<br />

of other trades free from damage.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Metal Lath and Lathing Accessories: Longest available lengths, fabricated of zinc-alloy for exterior.<br />

1. Metal Lath with waterproof backing: "Stucco-Rite", standard type SFB with double grade "D" paper<br />

backing over all exterior sheathing and single grade "D" paper backing at unsheathed exterior stud walls, as<br />

manufactured by the K-Lath Corporation for use on vertical surfaces with Portland Cement Plaster.<br />

2. Bitumen Underlayment: "Perm-A-Barrier" as manufactured by Grace Construction Products for use at all<br />

horizontal surfaces under lath and plaster.<br />

3. Corner Reinforcement (Exterior): Fabricate from expanded metal lath with large openings or 18 gage<br />

minimum welded or woven wire.<br />

4. Expansion Joints: 28 gauge, plain, perforated or expanded flange. As per plans or vertically @ 20' o.c. if<br />

not specifically designated. Verify with Architect.<br />

3. Special Screeds: Preformed to profiles as detailed with perforated flanges (see drawings).<br />

4. Provide stucco stop at all plaster terminations.<br />

B. Materials for Plastering:<br />

1. Portland Cement: ASTM C150, Type I. Use only one manufacturer's brand throughout the work.<br />

2. Hydrated Lime: Normal hydrated, conforming to ASTM C207, Type N, made into putty, or special finish<br />

hydrated, conforming to ASTM C207, Type S.<br />

3. Aggregates:<br />

a. Sand Aggregates (washed natural sand): Clean, sharp, and free from clay, loam or other foreign<br />

matter. Conform to ASTM C897, graded as follows:<br />

Sieve Size % Retained Sieve Size % Retained<br />

4 0 30 30-65<br />

8 0-10 50 70-90<br />

16 10-40 100 90-100<br />

b. Base Coats: Not more than 50% retained between any two consecutive sieves nor more than 25%<br />

between the No. 50 and No. 100 sieves.<br />

c. Finish Coat: 20/30 Grade Sand for fine sand float finish, unless otherwise indicated. Where smooth<br />

finish is indicated, use 30/60 Grade Sand. Provide standard float finish with 16/20 Grade Sand only<br />

as specifically indicated on drawings.<br />

4. Water: Clean and from a source intended for domestic consumption.<br />

5. Bonding agent (when required): "Weld-Crete" for Portland cement plaster, or equivalent products of Upco,<br />

H. B. Fuller or Thoro.<br />

09100 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Finish Color Coat: Provide a manufactured Portland cement and lime product, specifically formulated for spray<br />

application in a standard color and texture as indicated on the Drawings. Colors shall match samples approved by<br />

the Architect. Standard color shall be as close as possible to paint color listed on drawings.<br />

1. Refer to Drawings for Color Schedule.<br />

2.2 MIXES<br />

A. Portland Cement Plaster:<br />

1. Scratch Coat: 1 part cement, 4 parts sand, 1/10 part lime or lime putty, and water.<br />

2. Brown Coat: 1 part cement, 5 parts sand, 1/10 part lime or lime putty, and water.<br />

3. If plastic cement is used, omit the lime or lime putty.<br />

4. Finishing Coats: For typical sand finish, use one part Portland cement and 3 parts find sand with sufficient<br />

hydrated lime added to make mortar work easily under the trowel, but not in excess of 10% of cement<br />

volume.<br />

5. Mix integrally colored plaster in accordance with manufacturer's directions.<br />

2.3 MEASURING AND MIXING<br />

A. Measure all materials in calibrated boxes; shovel measurements are prohibited. For mechanical mixing,<br />

completely discharge the mixer and remove all set or partially hardened material before loading the next batch.<br />

Partially set material may not be retempered or used.<br />

B. Mix all materials in the proportions specified, adding only sufficient water to attain proper consistency for proper<br />

application.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Examine surfaces designated to receive work described in this Section for conditions adversely affecting the<br />

finished work. Repair or replace surfaces not meeting tolerances or quality requirements governing substrate<br />

construction prior to initiating this work.<br />

3.2 LATH APPLICATION<br />

A. Metal Lath: Apply to all surfaces to receive plaster, in plane with studs and on all areas so scheduled. Tie lath<br />

with 18 gauge wire. Use typical metal lath for areas not otherwise indicated.<br />

B. Bitumen Underlayment: Apply bitumen underlayment to all horizontal surfaces at "plant-ons", exposed parapet<br />

wall tops, plastered barrel vaults or any other horizontal surface under lath and plaster. Penetrating roofing nails<br />

shall be smooth shank electro-galvanized. Install according to manufacturers recommendations and specifications.<br />

C. Reinforce all penetrations with additional metal lath.<br />

3.3 PLASTERING<br />

A. Perform the work in accordance with the best standards of practice related to the trade, and properly coordinate the<br />

plastering work with the work of other trades. Comply with all applicable requirements of the governing Building<br />

Code, including Fire-Resistive Standards.<br />

B. Arrange and install plastering work when and as required to conceal or connect with work of others in a finished<br />

manner. Ascertain if inspections of concealed work are necessary or have been made before this work is installed.<br />

Uncover any work covered before inspections are made when directed by the Architect or other authority having<br />

jurisdiction.<br />

C. Application of plaster by machine methods is approved providing it can be demonstrated that uniformly<br />

satisfactory results can be obtained.<br />

09100 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Rod and straightedge plaster to uniform surfaces in true plane and finish free form laps, cracks, checks or other<br />

structural defects, and surface imperfections, and flush with grounds, corner beads, base screed, outlet boxes and<br />

similar details.<br />

E. Finish at Flush Trim: Tool to a slight "V" where detailed. Provide scoring where indicated. Plane surface shall<br />

not vary more than 1/8" when tried with a 10 ft. straightedge, except where closer tolerances are specified.<br />

F. Take special care when working into re-entrant corners to see that the plaster is not allowed to build out beyond<br />

the established finished wall plane. Do not lap successive coats over laps in former coats. Avoid joining marks by<br />

working top and bottom of area at same time.<br />

3.4 APPLICATION OF PORTLAND CEMENT PLASTER<br />

A. Thickness of Plaster: Not less than 7/8" thick on Lath, and 1/2" thick on Masonry for all exterior plastering.<br />

B. Portland Cement Plaster Base Coats on Metal Lath: Apply scratch coat to metal reinforcement with sufficient<br />

material and pressure to embed the reinforcement in a full 1/2" of plaster. Before the scratch coat has hardened,<br />

rake in a horizontal direction to provide keying for the brown coat. After initial set, keep continuously moist for<br />

48 hours, then allow to dry. Apply brown coat to scratch coat, bring out to grounds 1/8" below finish coat,<br />

straighten to a true surface, float and compact, and leave sufficiently rough to assure adequate bond for finish coat.<br />

Make no cold joints in brown coat over cold joints in the scratch coat. Leave brown coat surface free of<br />

imperfections, which might reflect in the finish coat. Moist cure brown coat for 48 hours and allow to set for 7<br />

days before applying finish coat.<br />

C. Portland Cement Finish: Lightly dampen brown coat before applying finish coat. Apply finish coat to an<br />

approximate thickness of 1/8" and bring to a finish to match approved sample.<br />

D. Plaster on Masonry and Concrete: Apply bond coat in accordance with manufacturer's recommendations. Apply<br />

and cure Portland cement plaster in two coats to total required thickness.<br />

3.5 INSPECTION, PATCHING AND REPAIR<br />

A. Inspection: Plaster will be rejected if finished surfaces are not of uniform thickness, not plumb or true to plane,<br />

are not of uniform texture, or if excessive cracking results.<br />

B. At completion of work, touch-up minor damage to prefinished adjacent surfaces to the satisfaction of the Owner’s<br />

representative. Replace materials damaged or stained at no additional cost to Owner.<br />

3.6 PREPARATION FOR PAINTING<br />

A. Plaster (Stucco) shall be cured at least 30 days before painting; pH must be 10.0 or lower. Surfaces must be<br />

sound, clean, dry, free of oil, grease, curing agents or sealers, efflorescence, loose aggregate and other foreign<br />

matter.<br />

B. Prior to the start of painting, repair damaged portion of plastering where required and as directed by Owner’s<br />

representative. Neatly and accurately patch and repair work to match finish of adjoining work. Where plaster<br />

surfaces are marred, discolored, stained or otherwise damaged, carry patching and repairing to the limits as<br />

determined and, where necessary, remove the finish coat and replace with new and acceptable work. Cut out<br />

broken or damaged portions of plaster and repair with new work. Cut out cracks not less than 1" wide, undercut to<br />

form key, and plaster full and smooth. Moisten edges of patch area before new plaster is applied. Match plaster<br />

patches to adjacent work.<br />

C. All integrally colored stucco not to be painted shall have final application of fog coat to assure uniformity of color,<br />

as recommended by the manufacturer.<br />

END OF SECTION<br />

09100 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 09250 (09 2900) – GYPSUM BOARD<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Interior non load-bearing steel stud partition framing (designed for 5 pounds per square foot uniform load<br />

perpendicular to partition).<br />

2. Suspension system for interior gypsum ceilings and soffits.<br />

3. Gypsum board.<br />

4. Gypsum sheathing.<br />

5. Tile backer materials: Backer panels for wall tile and non-fiberglass reinforced plastic panels (NRP).<br />

6. Textured wallboard coating.<br />

B. Related Requirements:<br />

1. Section 05400 - Cold-Formed Metal Framing: Load-bearing steel stud exterior and interior wall framing<br />

20 gage and heavier and ceiling joists. Metal stud header wall framing and bracing supported from roof<br />

structure.<br />

2. Section 06100 - Rough Carpentry: Wood furring strips, plywood, blocking, and fasteners attached to<br />

partition framing.<br />

3. Section 07210 - Building Insulation: Thermal and acoustical insulation.<br />

4. Section 07840 - Firestopping: Installation of firestopping at penetrations of fire-rated partitions.<br />

5. Section 09511 - Acoustical Panel Ceilings: Metal grid suspension system for suspended acoustical panel<br />

ceilings.<br />

6. Section 09900 - Paints and Coatings: Paint finish applied to gypsum board.<br />

7. Section 10231 - Soffit Vents: Soffit vents.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

2. ASTM C 475 - Joint Compound and Joint Tape for Finishing Gypsum Board.<br />

3. ASTM C 557 - Adhesives for Fastening Gypsum Wallboard to Wood Framing.<br />

4. ASTM C 645 - Nonstructural Steel Framing Members.<br />

5. ASTM C 754 - Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products.<br />

6. ASTM C 840 - Application And Finishing Of Gypsum Board.<br />

7. ASTM C 954 - Steel Drill Screws for the Application of Gypsum Board or Metal Plaster Bases to Steel<br />

Studs From 0.033 inches to 0.112 inches in Thickness.<br />

8. ASTM C 1002 - Steel Self-Piercing Tapping Screws For The Application Of Gypsum Panel Products Or<br />

Metal Plaster Bases To Wood Studs Or Steel Studs.<br />

9. ASTM C 1177 - Glass Mat Gypsum Substrate for Use as Sheathing.<br />

10. ASTM C 1178 - Coated Glass Mat Water-Resistant Gypsum Backing Panel.<br />

11. ASTM C 1396 - Gypsum Board.<br />

12. ASTM C 1629 - Standard Classification for Abuse-Resistant Nondecorated Interior Gypsum Panel<br />

Products and Fiber-Reinforced Cement Panels.<br />

13. ASTM C 1658 - Glass Mat Gypsum Panels.<br />

14. ASTM D 3273 - Standard Test Method for Resistance to Growth of Mold on the Surface of Interior<br />

Coatings in an Environmental Chamber.<br />

15. ASTM D 3274 - Standard Test Method for Evaluating Degree of Surface Disfigurement of Paint Films by<br />

Microbial (Fungal or Algal) Growth or Soil and Dirt Accumulation.<br />

09250 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Gypsum Association (GA):<br />

1. GA-214 - Levels of Gypsum Board Finish.<br />

2. GA-216 - Application and Finishing of Gypsum Board.<br />

3. GA-234 - Control Joints For Fire-Resistance Rated Systems.<br />

4. GA-600 - Fire Resistance and Sound Control Design Manual.<br />

D. Steel Framing Industry Association (SFIA):<br />

1. Member listing.<br />

E. Steel Stud Manufacturer's Association (SSMA):<br />

1. Member listing.<br />

1.3 QUALITY ASSURANCE<br />

A. Installer Qualifications: Company specializing in the installation of light gage metal framing components and<br />

gypsum wallboard with minimum 5 years documented experience.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Protect metal framing from corrosion, deformation, and other damage during delivery, storage, and handling.<br />

C. Store and protect metal framing with weatherproof covering, and ventilate to avoid condensation.<br />

D. Deliver materials in original packages, containers, or bundles bearing brand name and identification of<br />

manufacturer or supplier.<br />

E. Stack gypsum board flat to prevent sagging.<br />

1.5 PROJECT CONDITIONS<br />

A. Environmental Limitations: Establish and maintain environmental conditions for applying and finishing gypsum<br />

board in conformance with GA-216.<br />

B. Do not install paper-faced gypsum panels until installation areas are enclosed and conditioned.<br />

C. Do not install panels that are wet, those that are moisture damaged, and those that are mold damaged.<br />

PART 2 - PRODUCTS<br />

2.1 GENERAL<br />

A. Fire-Resistance-Rated Assemblies: For fire-resistance-rated assemblies, provide materials and construction<br />

identical to those tested in assembly indicated according to ASTM E 119 by an independent testing agency.<br />

Products used in the assembly shall carry a classification label from a testing laboratory acceptable to<br />

Authority Having Jurisdiction.<br />

2.2 FRAMING MATERIALS<br />

A. Manufacturer: Subject to compliance with requirements, provide products of one of the following:<br />

1. ClarkDietrich Building Systems, West Chester, OH (513) 870-1100.<br />

2. The Steel Network, Raleigh, NC (888) 474-4876.<br />

3. Other manufacturers listed as a member of SSMA or SFIA.<br />

09250 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Recycled Content of Steel Products: Provide steel framing products with an average recycled content of steel<br />

products such that the postconsumer recycled content plus 1/2 of pre-consumer recycled content is not less than<br />

25 percent.<br />

C. Interior Non-load Bearing Partition Framing: ASTM C 645 and C 754; galvanized sheet steel, channel shaped,<br />

punched for utility access, depth and gages as indicated below unless otherwise indicated on Drawings.<br />

1. Partition having an unbraced length of 12 feet or Less: Minimum 25 gage (18 mil).<br />

2. Partition having an unbraced length greater than 12 Feet: Minimum 20 gage (30 mil).<br />

3. Partition (bulkheads) suspended from overhead having an unbraced length of 10 Feet or Less: Minimum<br />

25 gage (18 mil).<br />

4. Partition height 8 feet and less: Minimum 25 gage (18 mil).<br />

5. Partition height 8 - 16 feet: Minimum 22 gage (27 mil).<br />

6. Partition height 16 feet and higher: Minimum 20 gage (30 mil).<br />

D. Option: Modified framing members of equivalent thickness for 20 and 25 gage metal such as UltraSTEEL by<br />

ClarkDietrich may be used in lieu of traditional framing members.<br />

E. Partition Floor Tracks and Runners: ASTM C 645; galvanized sheet steel, channel shaped, same depth and gage<br />

as studs, tight fit; solid web.<br />

F. Deflection Track: ASTM C 645; deep leg track at roof deck or structure to provide vertical travel as indicated.<br />

1. Contractor's Option: Manufacturer’s standard double or single deflection track as follows:<br />

a. VertiClip or VertiTrack by The Steel Network. If this option is used, track may be 20 gauge (30<br />

mil) for all stud sizes.<br />

b. FastTop Clip by ClarkDietrich.<br />

c. SLP-TRK by Brady Innovations as distributed by ClarkDietrich.<br />

G. Furring and Bracing: ASTM C 645; galvanized sheet steel.<br />

1. Studs: ST25 - 2-1/2 inch deep, 25 gage (18 mil).<br />

2. Studs: ST25 - 3-5/8 inch deep, 25 gage (18 mil).<br />

3. Resilient Furring Channels: 1/2 inch deep x 2-1/2 inch wide, 25 gage (18 mil).<br />

4. Hat-Shaped Channels: 7/8 inch deep x 1-1/2 inch wide, 25 gage (18 mil) or 1-1/2 inch deep x 2-1/2 inch<br />

wide (30 mil) as shown on the drawings.<br />

5. Cold-Formed Channels: 3/4 x 1/2 inch and 1-1/2 x 17/32 inch, 16 gage (54 mil).<br />

6. Z Furring Channel: 1-1/2 inch deep, 25 gage (18 mil).<br />

7. Clip Angles: 2 inches x 2 inches x 16 gage (54 mil) x 1/4 inch less than stud width.<br />

8. Contractor’s Option: In lieu of cold-formed channels and clip angles for horizontal wall bridging,<br />

Contractor may provide one of the following:<br />

a. Bridge Bar by The Steel Network.<br />

b. TradeReady Spazzer 9200 Bridging and Bracing Bar by ClarkDietrich.<br />

H. Ceiling Joists, Tracks, Headers at Partition Openings, Framing Attachment Angles, and Fasteners: Specified in<br />

Section 05400.<br />

I. Partition Framing Fasteners: Corrosion-resistant self-drilling self-tapping steel screws.<br />

1. 22 Gage (27 mil) Framing: ASTM C 1002; 3/8 inch Type S pan head.<br />

2. 20 Gage (30 mil) and Heavier Framing: ASTM C 954; 5/8 inch Type S-12 low-profile head.<br />

J. Bracing to Framing Attachment Angle Fasteners: #12 diameter pan head corrosion-resistant self-drilling screws.<br />

K. Partition Floor Track Anchorage Device: Low velocity powder-actuated drive pins; minimum 0.138 inch shank<br />

diameter x 1-1/2 inch shank length with 7/8 inch diameter washer.<br />

1. Hilti PAT System using X-ZF 37 P8S36 Pins, by Hilti, Tulsa, OK (800) 879-8000.<br />

2. Ramset/Red Head System using 1500SD Pins, by ITW Ramset/Redhead, Wood Dale, IL (630) 350-0370.<br />

09250 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


L. Wall Furring to Concrete or Masonry Wall Fasteners: Hex head sleeve anchors; minimum 1/4 inch diameter x<br />

minimum 1-1/8 inch embedment.<br />

1. Slv Anch HX 5/16 x 2-1/2, by Hilti, Tulsa, OK (800) 879-8000.<br />

2. Dynabolt HN-1413, by ITW Ramset/Redhead, Wood Dale, IL (708) 350-1558.<br />

M. Furring Channel to Masonry or Concrete Surface Fasteners: Low velocity powder-actuated drive pins of size to<br />

suit application.<br />

N. Flat Straps and Plates: ASTM A 653; galvanized sheet steel, gage, shape, and configuration as indicated on<br />

Drawings.<br />

1. Contractor's Option: In lieu of 2-inch continuous metal strap at deflection tracks, Contractor may provide<br />

one of the following:<br />

a. Bridge Bar by The Steel Network.<br />

b. TradeReady Spazzer 9200 Bridging and Bracing Bar by ClarkDietrich.<br />

O. Suspension System:<br />

1. Tie Wire: ASTM A 641/A 641M, Class 1 zinc coating, soft temper, double strand of 16 ga wire.<br />

2. Wire Hangers: ASTM A 641/A, Class 1 zinc coating, soft temper, 8 ga.<br />

3. Carrying Channels: ASTM C 645; galvanized sheet steel, 1-1/2 x 17/32 inch, 16 gage (54 mil).<br />

4. Furring Channels: ASTM C 645; galvanized, hat-shaped, rigid furring channels, 7/8 inch deep.<br />

5. Furring Channel Clips: ASTM C 645; galvanized sheet steel, 1-1/2 inch.<br />

2.3 GYPSUM BOARD MATERIALS<br />

A. Manufacturers: Subject to specified requirements, provide gypsum board and accessories by the<br />

following manufacturers:<br />

1. United States Gypsum Company, Chicago, IL. (800) 874-4968.<br />

2. CertainTeed Corp (Saint-Gobain), Tampa, FL (866) 427-2872.<br />

3. Georgia-Pacific, Atlanta, GA (800) 284-5347.<br />

4. National Gypsum Company, Gold Bond Building Products, Charlotte, NC (800) 628-4662.<br />

5. Temple-Inland, Diboll, TX (972) 235-4448.<br />

6. The Steel Network, Raleigh, NC (888) 474-4876 (Accessories only).<br />

7. ClarkDietrich Building Systems, West Chester, OH (513) 870-1100 (Accessories only).<br />

8. Fry Reglet, (800) 237-9773 (Accessories only).<br />

B. Standard Gypsum Board: ASTM C 1396; 1/2 inch and 5/8 inch thick, maximum permissible length; ends square<br />

cut, tapered edges. Provide one of the following products:<br />

1. Sheetrock by United States Gypsum.<br />

2. ProRock by Certainteed.<br />

3. ToughRock by Georgia-Pacific.<br />

4. Gold Bond Gypsum Board by National Gypsum.<br />

5. Gypsum Board by Temple-Inland.<br />

C. Water Resistant Gypsum Board: ASTM C 1396 or C 1658, 1/2 inch thick, maximum permissible lengths; ends<br />

square cut, tapered edges. Mold resistance of water resistant gypsum board shall score a rating of not less than 10<br />

when tested in accordance with ASTM D 3273. Provide one of the following products:<br />

1. Sheetrock Brand Mold Tough by United States Gypsum.<br />

2. Gold Bond Brand XP Gypsum Board by National Gypsum.<br />

3. DensArmor Plus by Georgia-Pacific.<br />

4. ProRoc M2Tech by Certainteed.<br />

5. ComfortGuard Mold Resistant by Temple Inland.<br />

D. Fire Resistant Gypsum Board: ASTM C 1396, Type X; 5/8 inch thick, maximum permissible lengths; ends<br />

square cut, tapered edges; core material as required to comply with Underwriters Laboratories (UL) assemblies<br />

indicated on Drawings. Provide one of the following products:<br />

1. Sheetrock Firecode X by United States Gypsum.<br />

2. ProRock Type X by Certainteed.<br />

09250 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. ToughRock Fireguard by Georgia-Pacific.<br />

4. Gold Bond Fire Shield by National Gypsum.<br />

5. Type X Gypsum Board by Temple-Inland.<br />

E. Water and Fire Resistant Gypsum Board: ASTM C 1396, Type X; 5/8 inch thick, maximum permissible lengths;<br />

ends square cut, tapered edges, core material as required to comply with Underwriters Laboratories (UL)<br />

assemblies indicated on Drawings. Mold resistance of water and fire resistant gypsum board shall score a rating<br />

of not less than 10 when tested in accordance with ASTM D 3273. Provide one of the following products:<br />

1. Sheetrock Mold Tough Firecode “C” Core by United States Gypsum.<br />

2. Gold Bond Brand XP Fire-Shield C Gypsum Board by National Gypsum.<br />

3. ComfortGuard Type X by Temple Inland.<br />

F. Impact Resistant Gypsum Board: ASTM C 1396 or C 1658, ASTM C 1629; thickness as shown, manufactured to<br />

produce greater resistance to surface indentation and through-penetration than standard gypsum panels. Provide<br />

one of the following products:<br />

1. Sheetrock Brand Abuse-Resistant Gypsum Wallboard by United States Gypsum.<br />

2. Hi-Abuse Brand XP Wallboard by National Gypsum.<br />

3. ProRoc Brand Abuse-Resistant Gypsum Board by CertainTeed.<br />

4. DensArmor Plus Abuse Resistant Gypsum Board by Georgia-Pacific.<br />

5. ComfortGuard Abuse Resistant Gypsum Board by Temple Inland.<br />

G. Impact and Water Resistant Gypsum Board: ASTM C 1396, ASTM C 1658, ASTM C 1629; thickness shown,<br />

manufactured to produce greater resistance to surface indentation and through-penetration than standard gypsum<br />

panels and providing water resistant gypsum core with paperless facing and mold resistance with a rating of not<br />

less than 10 when tested in accordance with ASTM D 3273. Provide the following product:<br />

1. DensArmor Plus Abuse Resistant Gypsum Board by Georgia-Pacific.<br />

H. Gypsum Board Fasteners:<br />

1. Metal Framing: ASTM C 954 and C 1002, Type S-12 bugle head, corrosion-resistant self-drilling selftapping<br />

steel screws.<br />

a. One Layer 1/2 Inch: 1 inch.<br />

b. One Layer 5/8 Inch: 1-1/8 inch.<br />

c. Two Layers 5/8 Inch: 1-7/8 inch.<br />

2. Wood Furring: ASTM C 1002, 1-1/4 inch, Type W bugle head, corrosion-resistant self-drilling steel<br />

screws.<br />

I. Gypsum Board Accessories: Subject to compliance with project requirements and unless otherwise specified,<br />

provide the specified gypsum board accessories below or equivalents by one of the manufacturers listed above:<br />

1. Corner Beads: Sheetrock Brand No. 104 Dur-A-Bead galvanized steel corner bead by United States<br />

Gypsum.<br />

2. Edge Trim: Galvanized steel casing.<br />

a. No. 200-B, L shape by United States Gypsum for tight abutment at edges.<br />

b. No. 200-A, J shape by United States Gypsum at other locations.<br />

3. Control Joint Accessory Piece: No. 093 roll-formed zinc by ClarkDietrich.<br />

4. Vertical Movement Joint Trim: No. DRMZ-625-200 aluminum Z shape trim by Fry Reglet.<br />

5. Adhesive: Commercial adhesive complying with ASTM C 557.<br />

6. Acoustical Insulation: Specified in Section 07210.<br />

7. Firestopping: Specified in Section 07840 for penetrations of fire-resistive rated gypsum board.<br />

2.4 JOINT TREATMENT MATERIALS<br />

A. General: Comply with ASTM C 475.<br />

B. Joint Tape:<br />

1. Interior Gypsum Wallboard: Paper tape.<br />

2. Exterior Gypsum Soffit Board: Paper tape.<br />

3. Gypsum Sheathing Board: 10/10 grid glass mesh tape.<br />

09250 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Backer Panels: Glass-Mat Backer Material: 10/10 grid glass mesh tape.<br />

C. Joint Compound:<br />

1. Interior Gypsum Wallboard:<br />

a. Sheetrock Brand Ready-Mixed Lightweight All-Purpose Joint Compound with Dust Control by<br />

United States Gypsum.<br />

b. ProForm Lite Ready Mix Joint Compound with Dust-Tech by National Gypsum.<br />

2. Exterior Applications:<br />

a. Exterior Gypsum Soffit Board: Use setting-type taping compound and setting-type, sandable<br />

topping compound.<br />

b. Gypsum Sheathing Board: As recommended by sheathing board manufacturer.<br />

3. Backer Panels: Glass-Mat Backer Materials: Use setting-type taping compound as recommended by backer<br />

panel manufacturer and that is rated 10 when tested in accordance with ASTM D 3273 and evaluated in<br />

accordance with ASTM D 3274.<br />

2.5 GYPSUM SHEATHING BOARD<br />

A. ASTM C 1396 and ASTM C 1177; water resistant gypsum core surfaced on face and back with inorganic glass<br />

fiber mats; thickness shown on the drawings, maximum permissible lengths; ends square cut. Provide one of the<br />

following products:<br />

1. SecureRock by United States Gypsum.<br />

2. eXP Sheathing by National Gypsum.<br />

3. Dens-Glass Gold sheathing by Georgia-Pacific.<br />

4. GlasRoc sheathing by CertainTeed.<br />

5. GreenGlass sheathing by Temple-Inland.<br />

B. Sheathing Board Fasteners: ASTM C 954 and ASTM C 1002, 1 inch length for 1/2 inch sheathing board and 1-<br />

1/4 inch length for 5/8 inch thick sheathing board, Type S-12 bugle head, corrosion-resistant self-drilling steel<br />

screws.<br />

2.6 BACKER MATERIALS<br />

A. Glass-Mat Backer Materials: Glass-mat moisture resistant gypsum core backer materials complying with ASTM<br />

C 1178. Glass-Mat Backer Material shall score a rating of 10 when tested according to ASTM D 3273.<br />

Thickness as shown on Drawings. Provide Type X where required as shown on the drawings. Provide one the<br />

following products:<br />

1. DensShield Tile Backer by Georgia-Pacific.<br />

2. GreenGlass Tile Backer by Temple-Inland.<br />

3. GlasRoc Tilebacker by Certainteed.<br />

4. Gold Bond eXP Tile Backer by National Guard.<br />

2.7 TEXTURE FINISHES<br />

A. Primer: As recommended by textured finish manufacturer.<br />

B. Provide textured finish as specified in Publication SA 933 of United States Gypsum, Orange Peel pattern, or<br />

equivalent by other wallboard manufacturers.<br />

2.8 SUBSTITUTIONS<br />

A. Reference Section 01600.<br />

09250 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine existing conditions and adjacent areas where products will be installed and verify that conditions<br />

conform to product manufacturer's requirements. Verify that building framing components are ready to receive<br />

Work. Verify that rough-in utilities are in-place and located where required. Do not proceed until unsatisfactory<br />

conditions have been corrected.<br />

B. Examine panels to assure they are dry and free of moisture and mold damage as evidenced by discoloration,<br />

sagging, irregular shape, fuzzy or splotchy surface contamination, and discoloration.<br />

3.2 INTERFACE WITH OTHER WORK<br />

A. Coordinate erection of studs with hollow metal door and window frames, sliding window, and overhead coiling<br />

door frames.<br />

B. Coordinate installation of anchors, supports, and blocking for mechanical, electrical, and building accessory items<br />

installed within framing.<br />

3.3 INSTALLATION - STEEL FRAMING, GENERAL<br />

A. Installation Standards: Comply with ASTM C 754, and ASTM C 840 requirements that apply to framing<br />

installation and with further details and instruction by gypsum board manufacturer's written construction<br />

guidelines.<br />

B. Install supplementary framing, blocking, and bracing at terminations in gypsum board assemblies to support<br />

fixtures, equipment services, heavy trim, grab bars, toilet accessories, furnishings, or similar construction.<br />

Comply with United States Gypsum's "Gypsum Construction Handbook".<br />

3.4 INSTALLATION - PARTITION FRAMING<br />

A. Install studs and fasteners in accordance with manufacturer's published instructions, ASTM C 754, GA-216, and<br />

GA-600.<br />

B. Install bracing at terminations in assemblies.<br />

C. Do not bridge building control and expansion joints with non-load-bearing steel framing members. Frame both<br />

sides of joints independently.<br />

D. Install studs so flanges within framing system point in same direction.<br />

E. Metal Stud Spacing: Unless otherwise noted, provide interior framing at maximum 24 inches on center. Provide<br />

16 inches on center maximum spacing for walls to receive ceramic tile.<br />

F. Align stud web openings horizontally.<br />

G. Splice studs with minimum 8 inch nested lap, fasten each stud flange with minimum two screws.<br />

H. Construct corners using minimum three studs.<br />

I. Double stud at wall openings, door and window jambs, maximum 2 inches from each side of openings.<br />

J. Place studs as indicated on Drawings, minimum 2 inches from abutting walls.<br />

K. Install headers at partition openings using load-bearing C-shaped joists specified in Section 05400.<br />

09250 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


L. Install framing between studs for attachment of mechanical and electrical items.<br />

M. Install intermediate studs above and below openings to match wall stud spacing.<br />

N. Install tracks (runners) at floors and overhead supports. Refer to Drawings for indication of partitions extending<br />

to finished ceiling only and for partitions extending through ceiling to building structure above.<br />

O. Maintain clearance under structural members to avoid deflection transfer to studs.<br />

1. Where indicated, construct partition to accommodate vertical deflection.<br />

2. Install optional products by The Steel Network specified in Part 2 above in accordance with manufacturer's<br />

printed instruction.<br />

a. Install clip with step bushing in center of slotted hole.<br />

b. Use a minimum of two fasteners per clip leg to connect clip to structure and partition framing.<br />

c. Attach clip to each stud by screwing through the center of each step bushing.<br />

P. Fasten studs adjacent to door and window frames, partition intersections, and corners to top and bottom runner<br />

flanges in double-stud fashion with metal lock fastener tools.<br />

1. Securely fasten studs to jamb and head anchor clips of door and borrowed-light frames.<br />

2. Place horizontally a cut-to-length section of runner with web-flange bend at each end. Fasten with<br />

minimum one screw per flange.<br />

3. Position a cut-to-length stud (extending to top runner) at vertical panel joints over door frame header.<br />

Q. Fire-Resistance-Rated Partitions: Install framing to comply with fire-resistance-rated assembly indicated and<br />

support closures and to make partitions continuous from floor to underside of solid structure.<br />

R. Lateral Bracing for Metal Studs:<br />

1. In metal stud partitions and bulkheads where length of metal studs is over 8 feet, install lateral bracing<br />

using one of the following methods:<br />

a. Install 1-1/2 inch cold-rolled channel through stud web holes and screw attach in place with clip<br />

angles. Lap channels by nesting one inside the other to a depth of at least 8 inches and wire tie<br />

together.<br />

b. Install optional Bridge Bar by the Steel Network specified in Part 2 above in accordance with the<br />

manufacturers printed instructions.<br />

c. Install field-cut runner for solid bridging at each end of wall, adjacent to wall openings, and 10 feet<br />

on center maximum. Install 1-1/2 inch wide, 20 gage (30 mil) strap bracing on both sides of stud.<br />

Fasten strap bracing to each solid bridging runner section with four screws.<br />

2. Gypsum Board Partitions: Space lateral bracing at the following intervals:<br />

a. Provide bracing at ceiling line or at mid-span of studs at areas without ceilings.<br />

S. Install braced framing of steel stud framing as indicated on Drawings. Use only screw attachments.<br />

T. Blocking: Screw attach wood blocking between studs. Install blocking for support of plumbing fixtures, toilet<br />

partitions, wall cabinets, toilet accessories and hardware.<br />

09250 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


U. Framing Fastening: Fasten framing in accordance with manufacturer's published instructions and schedule below,<br />

unless indicated otherwise on Drawings.<br />

Connection<br />

Floor Track to Concrete<br />

Partition Stud to Floor Track<br />

Stud Brace Web to Stud Web<br />

Plates and Straps to Studs<br />

Stud Web to Stud Web<br />

Stud Brace Web to Attachment Angle<br />

Lateral Bracing to Partition Stud Using Clip<br />

Angles<br />

Runner to Header<br />

Fastener<br />

1 - Pin at 32 inches on center<br />

1 - Screw each side at each flange<br />

2 - Screws<br />

2 - Screws<br />

2 - Screws<br />

2 - Screws<br />

2 - Screws to stud and 2 - Screws to cold<br />

rolled channel<br />

1 - Screw at 16 inches on center,<br />

maximum 6 inches from each end<br />

3.5 INSTALLATION - SUSPENDED CEILING<br />

A. Unless otherwise shown, install suspended ceilings in accordance with the following requirements.<br />

B. Suspend ceiling hangers from building structure as follows:<br />

1. Install carrying channels 4 feet on center with hanger wire spaced a max of 4 feet on center along carrying<br />

channels. Attach furring channels spaced 16 inches on center perpendicular to carrying channels with<br />

double strand of saddle tied tie wire or furring channel clips. Apply 1/2 inch gypsum board with its long<br />

dimension at right angles to the furring channels. Attach gypsum board with 1" self drilling drywall screws<br />

12 inches on center in the field of the board 8 inches or 12 inches on center at butt joints, located not more<br />

than 1/2 inch from edges.<br />

2. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are<br />

not part of supporting structural or ceiling suspension system. Splay hangers only where required to miss<br />

obstructions and offset resulting horizontal forces by bracing, countersplaying, or other equally effective<br />

means.<br />

3. Where width of ducts and other construction within ceiling plenum produces hanger spacing that interferes<br />

with the location of hangers required to support standard suspension system members, install supplemental<br />

suspension members and hangers in form of trapezes or equivalent devices. Size supplemental suspension<br />

members and hangers to support ceiling loads within performance limits established by referenced<br />

standards.<br />

4. Secure wire hangers by looping and wire-tying, either directly to structures or to inserts, eyescrews, or<br />

other devices and fasteners that are secure and appropriate for substrate, and in a manner that will not cause<br />

them to deteriorate or otherwise fail.<br />

5. Do not attach hangers to steel deck tabs.<br />

6. Do not attach hangers to steel roof deck. Attach hangers to structural members.<br />

7. Do not connect or suspend steel framing from ducts, pipes, or conduit.<br />

C. Installation Tolerances: Install steel framing components for suspended ceilings so members for panel attachment<br />

are level to within 1/8 inch in 12 feet measured lengthwise on each member and transversely between parallel<br />

members.<br />

D. Isolate suspension systems from building structure where they abut or are penetrated by building structure to<br />

prevent transfer of loading imposed by structural movement.<br />

3.6 INSTALLATION - FURRING<br />

A. Furring Channels:<br />

1. Attach vertically spaced at maximum 16 inches on center, to masonry and concrete surfaces with hammer<br />

set or powder driven fasteners staggered 24 inches on center on opposite flanges.<br />

2. Nest channels 8 inches at splices and anchor with 2 fasteners in each wing.<br />

09250 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Wall Furring:<br />

1. Secure top and bottom runners to structure.<br />

2. Space metal studs at maximum 16 inches on center.<br />

3. Furring for Fire Rating: Install metal furring as required for fire resistance ratings indicated on Drawings,<br />

and to GA-600 requirements.<br />

3.7 INSTALLATION - ACOUSTICAL ACCESSORIES<br />

A. Place acoustical insulation in partitions tight within spaces, around cut openings, behind and around electrical and<br />

mechanical items within or behind partitions, and tight to items passing through partitions as specified in Section<br />

07210.<br />

3.8 INSTALLATION - GYPSUM BOARD<br />

A. Install gypsum board in accordance with manufacturer's published instructions, ASTM C 840, GA-216, and GA-<br />

600.<br />

1. Use water resistant gypsum board at wet areas including walls and ceiling in toilet rooms, janitor closets,<br />

and food prep areas as applicable and where shown.<br />

2. Use fire resistant gypsum board at locations of fire-resistive rated assemblies indicated on Drawings.<br />

3. Use water and fire resistant gypsum board at locations of fire-resistive rated assemblies where water<br />

resistant gypsum board is specified.<br />

4. Use standard gypsum board at locations not indicated to be fire resistant or water resistant type.<br />

B. Where applicable, install ceiling panels before the installation of wall panels.<br />

C. Erect single layer gypsum board in most economical direction in accordance with ASTM C 840, with attachment<br />

to firm bearing surfaces over framing members. Do not align panel joints with edges of openings.<br />

D. Treat cut edges, holes, fastener heads, and joints, including those at angle intersections, in water resistant gypsum<br />

board and exterior gypsum soffit board with specified joint compound. Treat prior to installation.<br />

E. Place gypsum panels over supporting framing members with panel ends aligning and parallel with framing<br />

members. Leave bottom edge spacing above floor in accordance with GA-216.<br />

F. Install fasteners spaced and located in accordance with GA-216 or ASTM C840.<br />

3.9 INSTALLATION - GYPSUM SHEATHING<br />

A. Install gypsum board sheathing in accordance with manufacturer's published instructions.<br />

B. Erect single layer gypsum board sheathing horizontally with attachment to firm bearing.<br />

C. Place edge trim where gypsum board sheathing abuts dissimilar materials. Use longest practical length.<br />

D. Using screws, attach panels in place at maximum 12 inches on center, perimeter and field, to supporting framing.<br />

E. Protect exposed gypsum core at perimeter edges and penetrations by covering core with metal trim.<br />

3.10 INSTALLATION - BACKER MATERIALS<br />

A. Install glass-mat backer materials where indicated to receive glass-mat backer material. Install in accordance with<br />

manufacturer’s instructions.<br />

3.11 JOINT TREATMENT<br />

A. Install joint treatment in accordance with GA-216.<br />

09250 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Install corner bead, trim, and casing in accordance with GA-216.<br />

C. Install control joints full height of partition with 1/2 inch gap between board edges and between studs. Control<br />

joints shall be installed in accordance with the gypsum manufacturer’s recommended guidelines for control joints<br />

or the Gypsum Association GA-234 for control joint in fire rated systems. Apply sealant at base of joint and<br />

control joint accessory piece at face. Install control joints at the following locations:<br />

1. Where a wall or partition runs in an uninterrupted straight plane exceeding 30 linear feet.<br />

2. At pairs of doors, install vertical control joint at each jamb. At single doors, install control joint at latch<br />

side of jamb.<br />

3.12 FINISH<br />

A. Apply gypsum board finish in accordance with manufacturer's published instructions and GA-214 finish levels.<br />

B. Provide gypsum board finish levels at locations as follows:<br />

1. Level 0 (GA-214): No taping, finishing, or accessories necessary.<br />

a. Exposed surfaces above 12 ft high in Cart Storage Area.<br />

2. Level 1 (GA-214): Joints and interior angles have tape embedment set in joint compound. Surface free of<br />

excess joint compound. Tool Marks and ridges are acceptable.<br />

a. Areas above ceilings where required by drawings.<br />

b. Concealed areas.<br />

c. Interior exposed gypsum surfaces not indicated to be painted.<br />

3. Level 3 (GA-214): Joints and interior angles have tape embedded in joint compound and one additional<br />

coat of joint compound applied over all joints and interior angles and two separate coats of joint compound<br />

are applied over joints, angles, fastener heads, and accessories. Surface smooth and free of tool marks and<br />

ridges.<br />

a. Interior gypsum surfaces indicated to be painted.<br />

3.13 FIELD QUALITY CONTROL<br />

A. Inspect metal framing erection, placement, spacing, fasteners, and connections to building.<br />

B. Inspect gypsum board installation, fastener type, spacing, and finish level.<br />

C. Inspect installation of firestopping penetrations of fire-restive rated partitions and at voids between top of partition<br />

and building structure.<br />

3.14 PROTECTION<br />

A. Protect adjacent surfaces from drywall compound and promptly remove from floors and other non-drywall<br />

surfaces.<br />

B. Protect installed interior non load-bearing steel stud partition framing, gypsum board, gypsum sheathing and tile<br />

backer materials from damage until Substantial Completion.<br />

END OF SECTION<br />

09250 - 11<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 09310 (09 3013) – CERAMIC TILE<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Ceramic wall tile,floor tile and accessories.<br />

2. Ceramic floor tileand accessories furnished by Owner for installation by Contractor.<br />

B. Related Requirements:<br />

1. Section 03312 - Cast-In-Place Concrete Slabs: Flooring substrate finish and preparation.<br />

2. Section 07900 - Joint Sealers: Sealant at tile penetrations and control/construction joints.<br />

3. Section 09250 - Gypsum Board: Glass-mat backer material for wall tile.<br />

4. Section 10260 - Wall and Corner Guards: Surface applied corner guards on tile.<br />

1.2 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-Construction Training Meeting: Prior to tile installation, Conduct training meeting with mandatory attendance<br />

by Contractor, tile installation contractor, Wal-Mart Construction Testing Laboratory, and Wal-Mart Construction<br />

Manager.<br />

1. The meeting program shall include a viewing of the Latacrete Manufacturer’s Tile Installation Instruction<br />

Video. The video will be provided to Contractor by Owner pre-negotiated supplier with the Owner<br />

furnished products.<br />

2. Attendance Verification: Prepare attendance roster showing attendees and a statement attesting each<br />

attendee has completed the training. Roster shall be verified and signed by Wal-Mart Construction<br />

Manager.<br />

1.3 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Insitute (ANSI):<br />

1. ANSI A108, A118, A136 - American National Standards for the Installation of Ceramic Tile (Includes<br />

ANSI A108.01, A108.02, A108.1A-C, 108.4 -.13, A118.1-.12, and ANSI A136.1).<br />

a. ANSI A108.02 - Materials, Environmental, and Workmanship, General Requirements.<br />

b. ANSI A108.5 - Installation of Ceramic Tile with Dry-Set Portland Cement Mortar or Latex Portland<br />

Cement Mortar.<br />

c. ANSI A118.1 - Dry-Set Portland Cement Mortar.<br />

d. ANSI A118.4 - Latex-Portland Cement Mortar.<br />

2. ANSI A137.1 - Specifications for Ceramic Tile.<br />

C. Tile Council of North America, Inc. (TCNA):<br />

1. TCA Handbook for Ceramic Tile Installation.<br />

1.4 SUBMITTALS<br />

A. Extra Stock Materials: Provide one unopened box of each type, composition, color, pattern, and size of ceramic<br />

tile with label indicating store number and date. Submit to Wal-Mart Construction Manager at Date of Substantial<br />

Completion.<br />

1.5 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

09310 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Deliver and store packaged materials in original containers with seals unbroken and labels intact until time of use.<br />

C. Receive Owner Furnished products in compliance with the requirements of Section 01640.<br />

D. Prevent damage or contamination to materials by water, freezing, foreign matter, and other causes.<br />

1.6 SITE CONDITIONS<br />

A. Do not install adhesives in a closed, unventilated environment.<br />

B. Maintain 50 degrees F during installation of mortar materials.<br />

PART 2 PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under Provisions of Section 01640, Owner Supplier will furnish the following products to be installed by the<br />

Contractor:<br />

1. Ceramic tile CT-2including setting materials, additives, leveling compound, transition strip, and accessories<br />

as required for the installation of CT-2 tile.<br />

2. Owner supplied products shall be as specified in MATERIALS paragraph below.<br />

3. Products will be supplied to the Site as a bundle complete and ready for installation.<br />

4. Owner Supplier: Haines, Jones & Cadbury, Inc. (800) 459-7099.<br />

2.2 PRODUCT PROCUREMENT<br />

A. Products specified herein, except Owner furnished materials, shall be direct purchased by the General Contractor<br />

from a pre-negotiated supplier. Reference Section 01600 for additional information regarding Direct Purchase<br />

Products. Pre-negotiated Supplier shall be as follows:<br />

1. Haines, Jones &Cadbury, Inc. Contact: Customer Service (800) 459-7099, Fax (479) 756-8998, Email<br />

info@hjcinc.com.<br />

2.3 MANUFACTURERS<br />

A. Ceramic Tile: Provide products by the following manufacturers as specified:<br />

1. American Olean Tile Company, Dallas, TX.<br />

2. Crossville Ceramics, Crossville, TN.<br />

3. Dal-Tile Corporation, Dallas, TX.<br />

4. StonePeak Ceramics, Chicago, IL.<br />

5. Marazzi USA, Sunnyvale, TX.<br />

B. Floor Leveling Compound: Provide products by any of the following as specified:<br />

1. Laticrete International, Bethany, CT.<br />

2. Mapei Corporation, Deerfield Beach, FL.<br />

C. Mortar and Grout: Provide products by the following manufacturers as specified:<br />

1. Laticrete International, Bethany, CT.<br />

2.4 MATERIALS<br />

A. Provide Standard grade tile that complies with ANSI A137.1 for types, compositions, and other characteristics<br />

indicated.<br />

09310 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Floor and Wall Tile: Provide tile and grout specified herein as applicable as shown on the drawings. Provide sizes<br />

specified or as shown on the drawings. Provide only products specified. Provide product of one of the<br />

manufacturers where more than one is specified. Provide matching inside and outside corners, and trim. Provide<br />

matching 2 inch cove base unless specified otherwise.<br />

1. CT-1 (White):<br />

a. 0100 Gloss White by Dal-Tile.<br />

2. CT-2 (Red) (Owner furnished, Contractor installed):<br />

a. DP1224 River Red by StonePeak.<br />

3. CT-3 (Red): Cove base: Not used.<br />

a. Same as CT-2.<br />

4. CT-6 (Medium Tan):<br />

a. K174 Mexican Sand by Dal-Tile.<br />

b. 122 Kerton Brown by American Olean.<br />

5. CT-7 (Brown):<br />

a. Q181 Cotto by Dal-Tile.<br />

b. 107 Russet by American Olean.<br />

6. CT-8 (Dark Green):<br />

a. K112 Timberline by Dal-Tile.<br />

b. 103 Hunter Green by American Olean.<br />

7. CT-9 (Light Brown): Accent Tile.<br />

a. 160022 Rialto Terra Venetian Stone Collection Series, by Del Conca.<br />

b. TV0T06 TuscanValley Adobe Sunset by Mannington.<br />

8. CT-10 (Dark Blue):<br />

a. K189 Navy by Dal-Tile.<br />

b. 117 Navy by American Olean.<br />

9. CT-11 (Brown): Extra Forrest by StonePeak.<br />

a. CT-11: TL1224 12x24 field tile.<br />

b. CT-11A: TL0612 6x12 accent tile.<br />

10. CT-12 (Lt. Tan):<br />

a. Semi-Gloss, D-0136 Fawn by Dal-Tile.<br />

b. 159 Taupe Mist by American Olean.<br />

11. CT-15 (Black):<br />

a. K111, Black by Dal-Tile.<br />

b. 49 Gloss Black by American Olean.<br />

12. CT-16 (Tan):<br />

a. Keystone Select, D175 Mexican Sand Speckle by Dal-Tile.<br />

b. 11633 Speckled Pecan by Crossville.<br />

13. CT-17 (Almond):<br />

a. Semi Gloss, 0135 Almond by Dal-Tile.<br />

b. 12 Gloss Almond by American Olean.<br />

14. CT-17SL (Slim Foot): S3619TN, by Dal-Tile.<br />

15. CT-18 (Brown): Sanitary Floor Cove Molding.<br />

a. Extra Forrest by StonePeak.<br />

1) Cove Base: TL212 by StonePeak.<br />

2) Cove Outside Corner: TL2OC by StonePeak.<br />

b. Mountain by Crossville.<br />

1) Cove Base: SWM310212CBS by Crossville.<br />

16. CT-19 (Ivory):<br />

a. HWH1224001 Extra Ivory by StonePeak.<br />

17. CT-20 (Brown): Accent Tile.<br />

a. TL0312 Extra Forrest by StonePeak Ceramics.<br />

18. CT-23 (Forest):<br />

a. USG612C017 Forest 6” x 12” Cove Base, by StonePeak.<br />

19. CT-24 (Orange):<br />

a. Semi Gloss, Q090 Pumpkin Spice by Dal-Tile.<br />

09310 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


20. CT-25 (Ivory): Extra Desert by StonePeak.<br />

a. CT-25A: HWG1212020 12x12 field tile.<br />

b. CT-25B: HWG0312020 3x12 accent tile.<br />

c. CT-25C: HWG0T12020 12x12 triangle tile.<br />

d. CT-25D: HWG0612020 6x12 field tile.<br />

21. CT-26 (Ivory): Same as CT-25.<br />

22. CT-27 (Deep Ivory):<br />

a. HWG0606021 Extra Dusty Trail by StonePeak.<br />

23. CT-31: 6 x 6 inch (Crossville) or 2 x 2 inch (Dal-Tile). If 2 x 2 inch tiles are used, 9 tiles shall be installed<br />

for each 6 x 6 inch tile shown on the Drawings.<br />

a. A634 Terra Rosata by Crossville Ceramics.<br />

b. 6549 Matte Cotto by Dal-Tile.<br />

24. CT-32: 6 x 6 inch (Crossville) or 2 x 2 inch (Dal-Tile). If 2 x 2 inch tiles are used, 9 tiles shall be installed<br />

for each 6 x 6 inch tile shown on the Drawings.<br />

a. A310 Bamboo by Crossville.<br />

b. 6536 Matte Spice by Dal-Tile.<br />

25. CT-33: 6 x 6 inch (Crossville) or 2 x 2 inch (Dal-Tile). If 2 x 2 inch tiles are used, 9 tiles shall be installed<br />

for each 6 x 6 inch tile shown on the Drawings.<br />

a. B410 Doges Gold by Crossville.<br />

b. 6547 Matte Mustard by Dal-Tile.<br />

26. CT-34 (Caramel):<br />

a. Caramel Crystal Stone by Marazzi.<br />

C. Mortar:<br />

1. Dry Set Portland Cement Mortar: ANSI A118.1.<br />

2. Latex-Portland Cement Mortar: ANSI A118.4<br />

D. Grout: SpectraLOCK Grout by Laticrete.<br />

1. G-1 (Dark Gray): Platinum #42 by Laticrete.<br />

2. G-2 (Dark Gray): Platinum #42 by Laticrete (Owner furnished, Contractor installed).<br />

3. G-3 (Lt. Tan): Parchment #61 by Laticrete.<br />

4. G-4 (Brown): Chestnut Brown #1266 by Laticrete.<br />

5. G-5 (Ivory): Almond #85 by Laticrete.<br />

6. G-6 (Tan): Mocha #35 by Laticrete.<br />

7. G-10: Quarry Red #46 by Laticrete.<br />

8. G-13(Beige): Sand Beige #30 by Laticrete.<br />

9. G-14: Mushroom #39 by Laticrete.<br />

10. G-15 (Black): Raven #45 by Laticrete.<br />

E. Grout Cleaning Additive: LATICRETE SpectraLOCK PRO Cleaning Additive.<br />

F. Floor Leveling Compounds and Primer:<br />

1. Ultraplan M20 by Mapei.<br />

a. Primer: Primer L (formerly Ultraprime L) by Mapei.<br />

2. Laticrete 86 Latilevel Self Leveling Underlayment by Laticrete.<br />

a. Admix and Primer for Underlayment by Laticrete.<br />

G. 12 x 24 Tile Setting Materials: Use the followingspecifically for setting and sealing the 12 x 24wall and floor tile<br />

and associated trim. 12 x 24 tiles are shown in the Schedule Finish Key on the drawings.<br />

1. Mortar: 255 MultiMax Multipurpose Thin-set Mortar (floors and walls) by Laticrete.<br />

2. Floor Leveling Compounds and Primer: As specified above.<br />

3. Calking: Latasil Tile and Stone Silicone Sealant for use at cove base and interior corners.<br />

H. Sealant: Specified in Section 07900.<br />

I. Glass-Mat Tile Backer Board: Specified Section 09250.<br />

09310 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


J. Transition Strips:<br />

1. Transition Strip Between Concrete Slab Or VCT And Ceramic Tile: 3-1/2 inch x 1/2 inch satin anodized<br />

aluminum sloped transition ramp, Reno-Ramp AERP-125-B-90 by Schluter Systems, Plattsburg NY.<br />

Contact: Earl Maicus (800) 472-4588, Ext 111.<br />

K. Stainless Steel Vertical Inside Corner Trim: EHK U11, stainless steel, by Schluter.<br />

L. Stainless Steel Top and Corner Trim - C: Rondec-E, 3/8 x 1 1/4, stainless steel, by Schluter.<br />

M. Stainless Steel Corner Trim - B: ECK-E, 1-1/2 x 1-1/2, E37 V2A110,stainless steel, by Schluter.<br />

N. Tile Edge Transition - D: Schluter Schiene E110, stainless steel, by Schluter.<br />

O. Stainless Steel Corner Guard - A: Specified in Section 10260.<br />

P. Toilet Tile Installation Accessories: 1/2” notched trowel and drill bits (1/4”, 13/64”, 11/64, 3/16, and 1/8” for<br />

drilling tiles) for installation of tile in toilets.<br />

Q. Substitutions: Comply with the requirements of Section 01600.<br />

2.5 MORTAR MIX AND GROUT<br />

A. Mix mortars and grouts to comply with requirements of referenced standards and manufacturers for proportioning<br />

of materials, water or additive content; type of mixing equipment, selection of mixer speeds, mixing containers,<br />

and mixing time to produce mortars and grouts of uniform quality with optimum performance characteristics for<br />

application indicated.<br />

PART 3 EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions. Do not proceed until required substrate levelness is achieved<br />

and unsatisfactory conditions have been corrected.<br />

3.2 PREPARATION<br />

A. Protect surrounding work from damage or disfiguration.<br />

B. Vacuum clean existing substrate and damp clean.<br />

C. Seal substrate surface cracks with filler.<br />

D. Level existing substrate surfaces in accordance with TCA installation requirements and remove peaks or valleys<br />

using floor leveling compound specified. Prime, clean, and prepare concrete surface as required by manufacturer<br />

and apply leveling compound in accordance with manufacturer’s instructions.<br />

E. Prepare substrate surfaces with sealers or conditioners as recommended by adhesive manufacturer.<br />

3.3 INSTALLATION<br />

A. ANSI Tile Installation Standards: Comply with parts of ANSI A108 Series "Specifications for Installation of<br />

Ceramic Tile" that apply to types of setting and grouting materials shown and specified.<br />

B. TCA Installation Guidelines: TCA's "Handbook for Ceramic Tile Installation". Comply with applicable TCA<br />

installation methods.<br />

09310 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Lay tile to pattern indicated. Do not interrupt tile pattern through openings.<br />

D. Cut and fit tile tight to penetrations. Form corners and bases neatly.<br />

E. Place tile joints uniform in width, subject to variance in tolerance allowed in tile size. Make joints watertight,<br />

without voids, cracks, excess mortar, or excess grout.<br />

F. Sound tile after setting. Replace hollow sounding units.<br />

G. Allow tile to set for a minimum of 48 hours prior to grouting.<br />

H. Grout Tile Joints: Grout space shall be 1/16-inch for all tile joints except the following:<br />

1. Entry: 1/8 inch.<br />

I. Apply sealant to junction of tile and dissimilar materials, at tile penetrations, and at tile expansion joints.<br />

J. Transition Strip: Install transition strip at transitions between ceramic tile and concrete or VCT. Install during tile<br />

placement in accordance with transition strip manufacturer’s instructions.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect ceramic tile installation, joints, grout line alignment, and attachment to substrate.<br />

3.5 CLEANING AND PROTECTING<br />

A. Cleaning: On completion of placement and grouting, clean all ceramic tile surfaces so they are free of foreign<br />

matter.<br />

1. Initially clean and remove grout residue from tile as soon as possible according to tile and grout<br />

manufacturer's written instructions. Use cleaners recommended by tile and grout manufacturers and only<br />

after determining that cleaners are safe to use by testing on samples of tile and other surfaces to be cleaned.<br />

Protect metal surfaces and plumbing fixtures from effects of cleaning. Flush surfaces with clean water<br />

before and after cleaning.<br />

2. Begin final cleaning approximately 1 hour after initial cleaning of the grout. Mix cleaning additive to 2<br />

gallons of clean, cool water. Use a white scrub pad to lightly scrub apart any of the leftover residue<br />

remaining on the surface of the tile. Drag a clean, damp sponge diagonally over the scrubbed surfaces to<br />

remove any froth and residue. Rinse sponge often and change water every 50 sq. ft. Allow cleaned areas<br />

to dry and inspect entire surface of tile. Repeat process if haze remains.<br />

3. If haze remains 24 hours after installation, clean surfaces using straight white vinegar or bleaching type<br />

cleanser by methods described in preceding paragraph.<br />

4. Clean tile with cleaning materials recommended by tile manufacturer one day prior to Date of Substantial<br />

Completion.<br />

B. Protection:<br />

1. Protect installed tile work with cardboard, kraft paper, plywood, or other heavy covering during<br />

construction period to prevent staining, damage, and wear. If recommended by tile manufacturer, apply<br />

coat of neutral protective cleaner to completed tile walls and floors.<br />

2. Prohibit traffic from floor finish for 72 hours after installation.<br />

END OF SECTION<br />

09310 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 102910<br />

SECTION 09330 (09 3016) – QUARRY TILE<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Quarry floor tile.<br />

2. Metal edge strips.<br />

B. Related Requirements:<br />

1. Division 3 - Concrete: Flooring substrate finish and preparation.<br />

2. Section 07900 - Joint Sealers: Sealant at tile penetrations and control/construction joints.<br />

3. Section 09310 - Ceramic Tile.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ANSI International (ANSI):<br />

1. ANSI A108, A118, A136 - American National Standards for the Installation of Ceramic Tile (Includes<br />

ANSI A108.01, A108.02, A108.1A-C, 108.4 -.13, A118.1-.12, and ANSI A136.1).<br />

a. ANSI A108.02 - Materials, Environmental, and Workmanship, General Requirements.<br />

b. ANSI A108.5 - Installation of Ceramic Tile with Dry-Set Portland Cement Mortar or Latex Portland<br />

Cement Mortar.<br />

c. ANSI A118.1 - Dry-Set Portland Cement Mortar.<br />

d. ANSI A118.4 - Latex-Portland Cement Mortar.<br />

2. ANSI A137.1 - Specifications for Ceramic Tile.<br />

C. Tile Council of North America, Inc. (TCNA):<br />

1. TCA Handbook for Ceramic Tile Installation.<br />

1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Pre-Construction Training Meeting: Prior to tile installation, conduct training meeting with mandatory attendance<br />

by Contractor, tile installation contractor, Wal-Mart Construction Testing Laboratory, and Wal-Mart Construction<br />

Manager. Meeting program shall include a viewing of Laticrete Manufacturer’s Tile Installation Instruction<br />

Video. The video will be provided to Contractor by Wal-Mart Supplier specified in Section 09310.<br />

1.4 Attendance Verification: Prepare attendance roster showing attendees and a statement attesting each attendee has<br />

completed the training. Roster shall be verified and signed by the Construction Manager.<br />

1.5 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Pre-installation Meeting Attendance Roster.<br />

C. Maintenance Material Submittal: Provide one unopened box of tile with label indicating store number and date.<br />

Submit to Wal-Mart Construction Manager at Date of Substantial Completion.<br />

09330 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.6 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in accordance with the requirements of Section 01600 and<br />

manufacturer’s recommendations.<br />

B. Deliver and store packaged materials in original containers with seals unbroken and labels intact until time of use.<br />

C. Prevent damage or contamination to materials by water, freezing, foreign matter, and other causes.<br />

1.7 PROJECT CONDITIONS<br />

A. Do not install adhesives in a closed, unventilated environment.<br />

B. Maintain 50 degrees F during installation of mortar materials.<br />

PART 2 PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Tile: Provide products by the following manufacturers to the extent as specified in the Materials paragraph below:<br />

1. Dal-Tile Corporation, Dallas, TX. Contact: Paulett Newman, National Account Director (877) 556 5728<br />

or (214) 309 3408.<br />

2. American Olean Tile Company, Dallas, TX. Contact: Gina Norman (214) 309-4559.<br />

3. Summitville Tiles, Inc., Summitville, OH. Contact: Steve Clary (330) 223-1551 for local distributor.<br />

4. Metropolitan Ceramics, Canton, OH. Contact: Ellen Yossarian (603) 942-8787 or Terrie Chastain, (888)<br />

325-3945.<br />

B. Mortar and Grout: Provide products by the following manufacturers:<br />

1. Laticrete International, Bethany, CT, (800) 243-4788.<br />

2.2 MATERIALS<br />

A. Provide Standard grade tile that complies with ANSI A137.1 for type, composition, and other characteristics<br />

indicated.<br />

B. Provide tile and grout of type and color as specified herein as applicable as shown on the drawings. Provide sizes<br />

specified or as shown on Drawings. Provide product of one of the manufacturers where more than one is<br />

specified.<br />

C. Quarry Tile: Unglazed floor tile.<br />

1. QT-1: Raised pattern.<br />

a. Sure Step, Q32 Fawn Gray, by American Olean.<br />

b. Wal-Mart Tread, N46 Shadow Gray, by American Olean.<br />

c. Dal-Pavers, Gray Suretread, by Dal-Tile.<br />

d. Metro Tread Systems, 57T Stone Gray, by Metropolitan Ceramics.<br />

2. QT-3: Abrasive aggregate embedded in surface.<br />

a. Quarry Colors, Q06 Fawn Gray, by American Olean.<br />

b. X Quarry Basics, 57X Puritan Gray, by Metropolitan Ceramics.<br />

c. Quarry Textures, #TO3 Ashen Gray, by Dal-Tile.<br />

3. QT-31: Abrasive aggregate embedded in surface.<br />

a. Q40 Red Blaze, by Dal-Tile.<br />

b. 10 Summitville Red, by Summitville Tiles.<br />

c. 0Q01 Canyon Red, by American Olean<br />

4. QT-34: Smooth Finish.<br />

a. 0Q40 Red Blaze, by Dal-Tile.<br />

b. 0Q01 Canyon Red, by American Olean.<br />

09330 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


5. QT-35: Smooth Finish.<br />

a. 0T08 Sahara Sand, by Dal-Tile.<br />

6. QT-36: Smooth Finish.<br />

a. 0T01 Diablo Red, by Dal-Tile.<br />

D. Mortar:<br />

1. Dry Set Portland Cement Mortar: ANSI A118.1.<br />

2. Latex-Portland Cement Mortar: ANSI A118.4.<br />

3. Epoxy Mortar: ANSI A118.3.<br />

E. SpectraLOCK Grout, by Laticrete:<br />

1. G-1: Platinum #42.<br />

2. G-10: Quarry Red #46.<br />

3. G-11: Midnight Black #22.<br />

4. G-12: Mocha #35.<br />

5. G-13: Raven #45.<br />

6. G-16: (Beige) Marble Beige #17.<br />

7. G-17: (Beige) River Rock #38.<br />

8. G-18: Copper Beech #36.<br />

9. G-19: Latte #40.<br />

F. Control Joints:<br />

1. Dal-Seal CIS membrane by Dal-Tile, Dallas, TX, (800) 933-8453.<br />

G. Sealant: Specified in Section 07900.<br />

H. Transition Strip: 3-1/2 inch x 1/2 inch satin anodized aluminum transition ramp, Reno Ramp AERP-125-B-90, by<br />

Schluter Systems, Plattsburgh, NY. Contact: Earl Maicus (800) 472-4588, Ext. 111.<br />

I. Substitutions: Comply with the requirements of Section 01600.<br />

2.3 MORTAR MIX AND GROUT<br />

A. Mix mortars and grouts to comply with requirements of referenced standards and manufacturers for proportioning<br />

of materials, water or additive content; type of mixing equipment, selection of mixer speeds, mixing containers,<br />

and mixing time to produce mortars and grouts of uniform quality with optimum performance characteristics for<br />

application indicated.<br />

PART 3 EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions.<br />

3.2 PREPARATION<br />

A. Protect surrounding work from damage or disfiguration.<br />

B. Vacuum clean existing substrate and damp clean.<br />

C. Seal substrate surface cracks with filler. Level existing substrate surfaces to acceptable flatness tolerances.<br />

D. Prepare substrate surfaces with sealers or conditioners as recommended by adhesive manufacturer.<br />

E. Blending: For tile exhibiting color variations, use factory blended tile or blend tiles at Site before installing.<br />

09330 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 INSTALLATION<br />

A. ANSI Tile Installation Standards: Comply with parts of ANSI A108 Series "Specifications for Installation of<br />

Ceramic Tile" that apply to types of setting and grouting materials shown and specified.<br />

B. TCA Installation Guidelines: TCA's "Handbook for Ceramic Tile Installation". Comply with applicable TCA<br />

installation methods.<br />

C. Lay tile at locations and in pattern indicated. Do not interrupt tile pattern through openings.<br />

1. Lay Metro Tread Systems by Metropolitan Ceramics in basket weave (alternating) pattern.<br />

D. Cut and fit tile tight to penetrations. Form corners neatly.<br />

E. Place tile joints uniform in width, subject to variance in tolerance allowed in tile size. Make joints watertight,<br />

without voids, cracks, excess mortar, or excess grout.<br />

F. Sound tile after setting. Replace hollow sounding units.<br />

G. Control Joints: Provide tile control joints over control and construction joints in concrete slab. Remove all debris<br />

from concrete joint before starting installation of membrane.<br />

1. Following manufacturer's printed recommendations for installation, provide continuous x minimum 24"<br />

wide membrane.<br />

2. Set membrane in full bed of modified thin-set bond coat.<br />

3. Lap membrane and make single cut, reducing total thickness to one membrane.<br />

4. Following recommendation from thin-set mortar manufacturer, set tile in accordance with referenced TCA<br />

setting method.<br />

H. Allow tile to set for a minimum of 48 hours prior to grouting.<br />

I. Grout tile joints.<br />

1. Provide continuous elastomeric grout joints on each side of bridged concrete joint following<br />

recommendation and requirements of TCA EJ171.<br />

J. Apply sealant to junction of tile and dissimilar materials, at tile penetrations, and at tile expansion joints.<br />

K. Transition Strip: Install transition strip at transitions between quarry tile and concrete or VCT. Install during tile<br />

placement in accordance with transition strip manufacturer’s instructions.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect tile installation, joints, grout line alignment, and attachment to substrate.<br />

3.5 CLEANING<br />

A. On completion of placement and grouting, clean all tile surfaces so they are free of foreign matter.<br />

1. Initially clean and remove grout residue from tile as soon as possible according to tile and grout<br />

manufacturer's written instructions. Use cleaners recommended by tile and grout manufacturers and only<br />

after determining that cleaners are safe to use by testing on samples of tile and other surfaces to be cleaned.<br />

Protect metal surfaces and plumbing fixtures from effects of cleaning. Flush surfaces with clean water<br />

before and after cleaning.<br />

2. Begin final cleaning approximately 1 hour after initial cleaning of the grout. Mix cleaning additive to 2<br />

gallons of clean, cool water. Use a white scrub pad to lightly scrub apart any of the leftover residue<br />

remaining on the surface of the tile. Drag a clean, damp sponge diagonally over the scrubbed surfaces to<br />

remove any froth and residue. Rinse sponge often and change water every 50 sq. ft. Allow cleaned areas<br />

to dry and inspect entire surface of tile. Repeat process if haze remains.<br />

3. If haze remains 24 hours after installation, clean surfaces using straight white vinegar or bleaching type<br />

cleanser by methods described in preceding paragraph.<br />

09330 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Remove excess mortar and grout from floor and wall surfaces without damage.<br />

C. Clean tile with cleaning materials recommended by tile manufacturer one day prior to Date of Substantial<br />

Completion.<br />

3.6 PROTECTION<br />

A. Prohibit traffic from floor finish for 72 hours after installation.<br />

B. Protect installed tile work with cardboard, Kraft paper, plywood, or other heavy covering during remainder of<br />

construction period to prevent staining, damage, and wear.<br />

C. If recommended by tile manufacturer, apply coat of neutral protective cleaner to completed tile floors.<br />

END OF SECTION<br />

09330 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 052711<br />

SECTION 09511 (09 5113) – ACOUSTICAL PANEL CEILINGS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Suspended metal grid ceiling system.<br />

2. Acoustical panels.<br />

3. Perimeter trim.<br />

B. Related Requirements:<br />

1. Section 13900 - Fire Suppression: Sprinkler heads in ceiling system.<br />

2. Section 15800 - Air Distribution: Air diffusion devices in ceiling system.<br />

3. Section 16500 - Lighting: Light fixtures attached to ceiling system.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM C 635 - Metal Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings.<br />

2. ASTM C 636 - Installation of Metal Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels.<br />

3. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

4. ASTM E 1264 - Acoustical Ceiling Products.<br />

C. American Society of Civil Engineers (ASCE):<br />

1. ASCE 7 - Minimum Design Loads for Buildings and Other Structures.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Product Data: Provide manufacturer’s product data for suspension systems, showing all components.<br />

C. Shop Drawings: Show the following:<br />

1. Layout of grid components and hanger spacing, including perimeter support wires.<br />

2. Locations and methods of attachment of grid to walls. Clearance where grid is not attached to walls.<br />

3. Connection of ends of main beams and cross tees.<br />

4. Locations and details of compression struts and horizontal restraint wires or rigid bracing.<br />

5. Locations and details of seismic separation joints.<br />

6. Bracing for changes in ceiling plane.<br />

7. Locations and support details for light fixtures, diffusers, and other items within the ceiling system.<br />

D. Evaluation Report: ICC-ES report verifying code compliance for systems with alternative materials, design or<br />

methods of construction not specifically prescribed by the building code.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

B. Deliver acoustical units in manufacturer's original unopened containers with brand name and type clearly marked.<br />

09511 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Store under cover in dry, watertight conditions.<br />

D. Prior to installation, store acoustical units for 24 hours minimum at same temperature and relative humidity as<br />

space where Work will be installed.<br />

1.5 PROJECT CONDITIONS<br />

A. Environmental Requirements: Maintain uniform temperature range of 60-85 degrees F, and humidity of no more<br />

than 70 percent relative humidity prior to, during, and after installation.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Provide products by the following manufacturers as specified:<br />

1. Armstrong World Industries Incorporated, Lancaster, PA (800) 448-1405.<br />

2. CertainTeed Ceilings, Valley Forge, PA (800) 233-8990.<br />

3. Chicago Metallic Corporation, Chicago, IL (800) 323-7164.<br />

4. Gold Bond Building Products, National Gypsum Company, Charlotte, NC (704) 365-7300.<br />

5. USG Interiors, Chicago, IL (800) 950-3839.<br />

2.2 REGULATORY REQUIREMENTS<br />

A. Surface Burning Characteristics in Accordance with ASTM E 84 for Class A finish:<br />

1. Flame Spread: Less than 25.<br />

2. Smoke Density: Less than 50.<br />

B. Seismic Performance: Acoustical ceiling shall withstand the effects of earthquake motions determined according<br />

to ASCE 7.<br />

C. Food Serving and Preparation Areas where Scheduled:<br />

1. United States Department of Agriculture (USDA): Approved for incidental food contact.<br />

2.3 SUSPENSION SYSTEM<br />

A. Provide suspension system specified herein for the corresponding ACT system as applicable as shown on the<br />

drawings. Provide suspension system compatible with acoustical panels selected.<br />

B. Grid: ASTM C 635, heavy duty, steel exposed T; nominal 1 inch width; stab-in connections.<br />

C. Accessories: Stabilizer bars, clips, and splices.<br />

D. Grid Finish: White.<br />

E. Support System: Hot or cold rolled steel channels; galvanized hanger wire, minimum 12 gage.<br />

F. Edge Moldings: Metal channel with exposed flange to match suspension system. Minimum 2 inch wide<br />

horizontal leg.<br />

G. Compression Struts: Telescoping compression strut designed to attach to main tees at each splayed wire location,<br />

preventing upward movement of ceiling grid system. Provide either of the following:<br />

1. Donn Compression Post by USG.<br />

2. Field fabricated compression struts as detailed on drawings.<br />

H. ACT-1: Non Fire-Rated Suspension System. Provide one of the following:<br />

1. Prelude 15/16 inch, XL #7300 Exposed Tee System by Armstrong.<br />

2. Classic Stab System, 15/16 inch, #CS12-12-15 by CertainTeed.<br />

09511 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. 1200 System by Chicago Metallic.<br />

4. Donn DX System by USG.<br />

I. ACT-2: Non Fire-Rated Suspension System meeting USDA guidelines for ceilings in food preparation areas.<br />

Provide one of the following:<br />

1. 15/16 Co-Extruded Clean Room by Armstrong.<br />

2. Classic Environmental Stab System, 15/16 inch, #EVS 12-12-15 by CertainTeed.<br />

3. Environmental 1260/1280, 15/16 inch, by Chicago Metallic.<br />

4. Donn DXLA, 15/16 inch, by USG.<br />

J. Substitutions: Comply with the requirements of Section 01600.<br />

2.4 ACOUSTICAL LAY-IN PANELS<br />

A. Provide acoustical panels specified herein for the corresponding ACT system as applicable as shown on the<br />

drawings.<br />

B. Acoustical Panel Standard: Comply with ASTM E 1264.<br />

C. ACT-1: Non Fire-Rated Panels, square edge, nonperforated, abuse-resistant vinyl film facing, size as shown.<br />

Provide one of the following:<br />

1. Vinyl Faced Fiberglass Ceiling Panels, Random Fissured, Item #2911 by Armstrong.<br />

2. Premier Hi-Lite ClimaPlus Kapok Panels, unperforated, Item #7057G by USG.<br />

3. Versatone Unperforated Vintage, Item #1530-VIN-1 by CertainTeed.<br />

4. Coral Soft Touch Series, Item #7010-01F by Chicago Metallic.<br />

D. ACT-2: Non fire-rated square edge, non-perforated vinyl faced gypsum panels which satisfy USDA/FSIS<br />

guidelines for sanitary applications. Sizes as shown. Provide one of the following:<br />

1. VinylRock by CertainTeed.<br />

2. Sheetrock Lay-in Ceiling Panel ClimaPlus by USG.<br />

3. Gridstone Brand Ggypsum Ceiling Panels by National Gypsum.<br />

E. Substitutions: Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions. Do not proceed until unsatisfactory conditions have been<br />

corrected.<br />

B. Verify that layout of hangers will not interfere with other Work.<br />

3.2 INSTALLATION – GENERAL<br />

A. Interface with Other Work:<br />

1. Do not install acoustical ceilings until building is enclosed, heating is provided, dust generating activities<br />

have terminated, and overhead work is completed, tested, and approved.<br />

2. Schedule installation of acoustic units after interior wet work is completed.<br />

3. Install after major above ceiling work is complete.<br />

4. Coordinate location of hangers with other Work.<br />

B. Site Tolerances:<br />

1. Variation from Flat and Level Surface: 1/8 inch in 12 feet.<br />

09511 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 INSTALLATION - SUSPENSION SYSTEM<br />

A. Install system in accordance with ASTM C 636, ASCE 7 and manufacturer's published instructions.<br />

B. Rigidly secure acoustical ceiling system including integral mechanical and electrical components with maximum<br />

deflection of 1/360.<br />

C. If metal deck is not supplied with hanger tabs, coordinate installation of hanger clips during steel deck erection.<br />

Provide additional hangers and inserts as required.<br />

D. Hang system independent of walls, columns, ducts, pipes and conduit. Where carrying members are spliced,<br />

avoid visible displacement of face plane of adjacent members. Where ducts or other equipment prevent regular<br />

spacing of hangers, reinforce nearest affected hangers and related carrying channels to span extra distance.<br />

E. Locate system on room axis according to Reflected Ceiling Plan, where indicated on Drawings, or locate system<br />

to a balanced grid design with edge units no less than 50 percent of acoustical panel size where Reflected Ceiling<br />

Plan not shown on Drawings.<br />

F. Do not support components on main runners or cross runners if weight causes total dead load to exceed deflection<br />

capability. Do not eccentrically load system, or produce rotation of runners.<br />

G. Install edge molding at intersection of ceiling and vertical surfaces using longest practical lengths. Miter corners.<br />

Provide edge moldings at junctions with other interruptions. Secure at 16 inches on center.<br />

H. Install compression struts and secure system with tie wires as indicated on Drawings.<br />

1. Fasten strut to main runner, extend to and fasten to structural member supporting roof.<br />

2. Compression strut and splayed hanger wires shall be provided as follows:<br />

a. One assembly per each light fixture.<br />

b. Locate at maximum of 12 feet on center in both directions with first point within 6 feet from each<br />

partition.<br />

I. Install additional 12 ga. tie wire from grid to structure to support Bakery/Deli Menu Board System (MBS).<br />

Additional wire to be installed at 4’-0” o.c. at or within 2’-0” of center line of MBS. Each MBS section (4’-6” or<br />

8’-0” in length) to receive no less than three (3) additional 12 ga. tie wires. Install additional 12 ga. tie wire to<br />

mechanical registers or 2x4 light fixtures located within 12” of centerline of Bakery/Deli Menu Board System.<br />

3.4 INSTALLATION - ACOUSTICAL PANELS<br />

A. Fit acoustic units in place free from damaged edges or other defects. Install acoustic units level, in uniform plane,<br />

and free from twist, warp, and dents.<br />

3.5 FIELD QUALITY CONTROL BY CONTRACTOR<br />

A. Inspect acoustical panel placement, ceiling grid suspension system installation and connection to structure.<br />

3.6 FIELD QUALITY CONTROL BY OWNER<br />

A. Wal-Mart Construction Testing Laboratory (CTL) will perform acoustical panel ceiling inspection specified<br />

herein at no cost to the Contractor in accordance with Section 01458.<br />

B. CTL shall perform periodic special inspection during installation of acoustical panel ceilings, including acoustical<br />

panel placement, ceiling grid suspension system installation and connection to structure.<br />

09511 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.7 CLEANING<br />

A. Clean exposed surfaces of acoustical ceilings including trim, edge moldings, and suspension system members.<br />

END OF SECTION<br />

09511 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 09650 (09 6500) – RESILIENT FLOORING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished resilient flooring and adhesive.<br />

2. Owner furnished PVC to Concrete transition strip.<br />

3. Contractor furnished resilient flooring accessories.<br />

4. Preparation of Contraction/Construction Joints under floor finishes.<br />

5. Contractor installation of resilient flooring and accessories.<br />

6. Floor Treatment: Application of stripper and finish to resilient flooring.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

2. Section 03312 - Cast-In-Place Concrete Slabs: Floor substrate surface.<br />

3. Section 09655 - Resilient Base and Accessories: Resilient flooring base.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are<br />

referenced within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 648 - Critical Radiant Flux of Floor-Covering Systems Using a Radiant Heat Energy Source.<br />

2. ASTM E 662 - Specific Optical Density of Smoke Generated by Solid Materials.<br />

3. ASTM F 710 - Preparing Concrete Floors to Receive Resilient Flooring.<br />

4. ASTM F 1066 - Vinyl Composition Floor Tile.<br />

5. ASTM F 1700 - Solid Vinyl Floor Tile.<br />

6. ASTM F 1869 - Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous<br />

Calcium Chloride.<br />

1.3 QUALITY ASSURANCE<br />

A. Regulatory Requirements for Resilient Flooring:<br />

1. Critical Radiant Flux: ASTM E 648. More than 0.45 Watts per square centimeter.<br />

2. Specific Optical Smoke Density: ASTM E 662. Less than 450.<br />

B. Floor Treatment Applicator Qualifications:<br />

1. Company Requirements: Company specializing in performing work as specified herein with minimum 3<br />

years documented experience.<br />

2. Stripper Applicator Crew Requirement: Four-man crew, one to apply solution ahead of auto scrubber, one<br />

to run auto scrubber, two with mops and buckets to pick up dirty solution residues behind the auto scrubber<br />

and rinse floor prior to applying finish.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Owner Furnished Product Delivery: Owner Supplier will deliver products to jobsite for Contractor to receive on<br />

delivery date established by Contractor.<br />

B. Wal-Mart Carpet/Tile Plan: Issued to Contractor by Wal-Mart 90 days prior to GM Start Date as identified in<br />

Schedule of Events.<br />

C. Product Packaging: Resilient flooring and accessories will be packaged in manufacturer's standard cartons.<br />

09650 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Acceptance at Site: Receive Owner furnished products as specified in Section 01640.<br />

1. Verify quantity of products furnished with Bill of Material provided with Owner furnished products.<br />

2. Store resilient flooring indoors and protect from excessive cold, heat, temperature fluctuations, humidity<br />

and moisture penetration. Store flooring on original pallets with no multiple stacking of pallets. Check<br />

material for consistency of run item and shade numbers. Store adhesive in same manner as flooring and<br />

protect from freezing.<br />

3. Report discrepancies in product quantity delivered or damage to products delivered to Wal-Mart Store<br />

Planning Division within 24 hours.<br />

4. Upon notification by Contractor, Owner will arrange for delivery of replacement products.<br />

5. Note description of product quantity discrepancies and/or product damage on Bill of Lading.<br />

E. Storage:<br />

1. Store materials in a secure area to prevent loss due to theft or damage. Store flooring and adhesive<br />

materials in controlled climate conditions when recommended by manufacturer label instruction. Do not<br />

allow adhesive to freeze. Store adhesives in environment between 60 and 80 degrees.<br />

F. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

1.5 PROJECT CONDITIONS<br />

A. Environmental Requirements:<br />

1. Store flooring materials for three days prior to installation in area of installation to achieve temperature<br />

stability.<br />

2. Maintain ambient temperature at 60 - 80 degrees F for 7 days prior to installation.<br />

3. Maintain ambient temperature required by adhesive manufacturer (no less than 72 degrees F three days<br />

prior to, during, and 24 hours after installation of materials).<br />

1.6 SCHEDULING<br />

A. Schedule resilient flooring installation to prevent damage to resilient flooring and to prevent movement of<br />

construction materials over area of resilient flooring.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner Supplier will furnish the following for installation by the Contractor:<br />

1. Resilient flooring.<br />

2. Primer and adhesive.<br />

3. PVC to concrete transition strip with fasteners.<br />

B. Owner’s Supplier:<br />

1. PVC Plank (PVC) Flooring: Schwarz Supply Source, Morton Grove, IL. Contact: Nancy Quach (847)<br />

967-4085.<br />

2. PVC to Concrete Transition Strip and Fasteners: Haines, Jones & Cadbury, Inc. Contact: Customer<br />

Service, (800) 459-7099, Fax (479) 756-8998, Email info@hjcinc.com.<br />

3. Vinyl Composition Tile (VCT) Flooring: One of the following as determined by Owner:<br />

a. Armstrong: Contact Jeff Gobbell (281) 593-5405.<br />

b. Tarkett: Contact Allison Harris, Linron Company (713) 802.9137.<br />

C. Quantity Furnished:<br />

1. PVC: Owner will determine quantities of PVC flooring and adhesive required and deliver to project site.<br />

2. PVC to Concrete Transition Strip: Owner will determine quantities of PVC to concrete transition strip<br />

required and deliver to project site.<br />

3. VCT: Contractor shall determine quantity of each type of VCT resilient flooring and resilient flooring<br />

adhesive required, and complete the attached Order Form for the applicable flooring to indicate quantities.<br />

09650 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Product descriptions and specifications of Owner furnished items and equipment hereinafter are included as<br />

information to Contractor only and not to be considered as Contractor requirements unless otherwise stated.<br />

2.2 PRODUCTS<br />

A. PVC Plank Flooring: Plank Flooring, 7” x 48” x 1/8” strips, virgin PVC composition, by Matworks.<br />

1. PVC-1 (Woodgrain): Woodgrain by Matworks.<br />

2. PVC Adhesive: Pressure sensitive, low VOC, Spray-Lock by Interlock Industries, Inc. Chattanooga, TN.<br />

Contact: Wal-Mart Coordinator (423) 305-6151 Ext. 133.<br />

B. PVC Flooring to Concrete: Transition Strip: 2” x 1/8” extruded aluminum transition strip, beveled one edge at 10<br />

degrees, predrilled for fasteners at not more than 12” o.c.<br />

1. Transition Strip - one of the following:<br />

a. No. 8132, by National Guard Products, Inc.<br />

b. 2" CTC Reducer by Ceramic Tool Co.<br />

2. Fasteners: Hilti Qwik-Con II, #14-134 TFH (1/4” x 1-3/4 Torq Flathead).<br />

C. Vinyl Composition Tile (VCT): ASTM F 1066, Class 1, solid-color tile or Class 2, through-pattern tile, nonasbestos<br />

formulated, 0.125 inch thick, 12 by 12 inches square, Standard EXCELON Imperial Texture or Safety<br />

Zone slip resistant by Armstrong or Azrock by Tarkett. Pattern and color numbers listed below will be furnished<br />

as applicable as shown on the drawings.<br />

1. VCT-9 (White):<br />

a. Cortina No.V789, Windrift.<br />

b. 51941 Polar White by Armstrong.<br />

2. VCT-12 (Tan):<br />

a. Cortina No. V-984, Elemental by Tarkett.<br />

b. 57501 Nougat by Armstrong.<br />

3. VCT-13 (Blue):<br />

a. Cortina No.V-965, Night Sky by Tarkett.<br />

b. 51874 Grayed Blue by Armstrong.<br />

4. VCT-14 (Yellow):<br />

a. Cortina No.V-982, Maple Sugar by Tarkett.<br />

b. 51878 Golden by Armstrong.<br />

5. VCT-15 (Rust):<br />

a. Cortina No.V-988, Spicenut by Tarkett.<br />

b. 51948 Cinnamon Brown by Armstrong.<br />

6. VCT-16 (Red):<br />

a. Cortina No. V-951, Red Pepper by Tarkett.<br />

b. 51814 Pomegranate Red by Armstrong.<br />

7. VCT-17 (Blue):<br />

a. Cortina No. V-927, True Blue by Tarkett.<br />

b. 51820 Marina Blue by Armstrong.<br />

8. VCT-18 (Yellow):<br />

a. Cortina No. V-619, Saffron by Tarkett.<br />

b. 51878 Golden by Armstrong.<br />

9. VCT-19 (White): Slip Resistant Tile.<br />

a. Granite SR135-3, Neutral White by Tarkett.<br />

b. 57005 Stone Beige by Armstrong.<br />

D. VCT Adhesive: Franklin 780 Premium Multipurpose Flooring Adhesive by Franklin International, water resistant<br />

type, VOC less than 50 g/l.<br />

E. Primers: Types as suitable for specific material and substrates encountered. Primer VOC shall be not greater than<br />

50 g/L as set forth in the California’s South Coast Air Quality Management District (SCAQMD) Rule No. 1168.<br />

F. Substitutions: Not permitted unless otherwise specified.<br />

09650 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.3 CONTRACTOR FURNISHED ACCESSORIES<br />

A. Floor Treatment Materials:<br />

1. Stripper: Pro Strip Extra Heavy Duty Stripper, by SC Johnson Wax Professional.<br />

2. Floor Finish: Signature High Performance UHS Finish, by SC Johnson Wax Professional.<br />

B. Transition Strip - Vinyl Composition or Solid Vinyl to Concrete: Resilient edge strip; minimum width 1 inch, 1/8<br />

inch thickness; tapered bullnose edge. Color: Black.<br />

C. Transition Strip - Vinyl Composition Tile to Concrete (Seasonal Box): No. BAR6SS-2-10 bevel, 2" x 1/8"<br />

Stainless Steel Transition Strip by National Guard Products. Stainless steel plate, smooth surface, beveled one<br />

edge, predrilled for fasteners at not more than 12” o.c.<br />

1. Fasteners: Qwik-Con II, #14-134 TFH (1/4” x 1-3/4 Torq Flathead) by Hilti.<br />

D. Subfloor Filler: Provide one of the following:<br />

1. Cementitious Based Underlayment Subfloor Filler:<br />

a. Ardex SD-F Feather Finish, by Ardex Engineered Cements. Contact: Ben Mack (724) 203-5060.<br />

b. Levelayer l, by Dayton Superior.<br />

c. No. 547 UniPro Universal Underlayment by W.W. Henry. Contact: Ben Mack (724) 203-5060.<br />

2. Epoxy Subfloor Filler: Epolith P or G, two-part 100% solids flexible epoxy joint filler, by BASF Building<br />

Systems (Formerly Degussa), (800) 433-9517.<br />

E. Fast Set Portland Cement/latex Based Patch: Provide the following product:<br />

1. Kwik Patch by Azrock.<br />

2. If Kwik Patch is unavailable, provide one of the following products:<br />

a. Plani-Patch by Mapei Corp., Deerfield Beach, FL (800) 426-2734.<br />

b. Featherfinish by Ardex Engineered Cements, Aliquippa, PA (888) 512-7339.<br />

2.4 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to the<br />

following requirements for substrate conditions. Do not proceed until unsatisfactory conditions have been<br />

corrected.<br />

1. Verify concrete floors are free of excessive moisture, hydrostatic pressure, alkalinity, scale, and dusting.<br />

2. Verify concrete floors are plane to tolerances specified in Section 03312.<br />

3. Verify concrete floors are free from oil, grease, dust, construction debris, loose or scaly paints or coatings,<br />

incompatible curing or sealing compounds, and other substances that may impair adhesion of adhesive and<br />

finish materials.<br />

4. Verify temperature of conditioned space has been maintained at 60 - 80 degrees F for period of 7 days prior<br />

to installation. Maintain specified temperature range for duration of flooring construction.<br />

5. Remove existing flooring.<br />

6. Do not install new resilient flooring over existing resilient flooring.<br />

7. If existing substrate conditions exist considered to require repair beyond normal scope of preparation,<br />

notify Architect by RFI for prior to proceeding.<br />

3.2 PRE-INSTALLATION TESTING<br />

A. Bond Test: Determine suitability of concrete substrate for receiving resilient flooring with regard to moisture<br />

content and curing compounds. Conduct bond tests by adhering 3 feet by 3 feet panels of specified floor covering<br />

with specified adhesive. Test will be considered passed if after several days panels are well bonded, difficult to<br />

remove, and display no signs of moisture or adhesive degradation.<br />

09650 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Moisture content tests and pH tests will be conducted by Owner’s Construction Testing Laboratory (CTL) at no<br />

cost to Contractor. Moisture tests will be made to ensure that moisture content in concrete substrate does not<br />

exceed 5 percent as measured by Calcium Carbide Hygrometer Procedure or 5 pounds/1000 sq. ft./24 hours as<br />

measured by Rubber Manufacturers Association Quantitative Calcium Chloride Test. Tests shall be taken in<br />

sufficient number and locations as required to obtain results representative of various areas to be covered by<br />

resilient flooring. CTL shall report test results to the Wal-Mart Construction Manager.<br />

1. Contractor’s Responsibility for Pre-installation Testing by CTL:<br />

a. Notify CTL when slab is considered sufficiently dry for testing.<br />

b. Coordinate schedule such that final tests are taken not more than 24 hours prior to application of<br />

flooring.<br />

3.3 PREPARATION<br />

A. Concrete Substrates: Unless otherwise specified herein, prepare substrate according to ASTM F 710.<br />

1. Prepare substrates according to flooring manufacturer's written recommendations and as outlined below to<br />

ensure adhesion of resilient products.<br />

2. Remove ridges, bumps, protrusions, and other irregularities by sanding, grinding, or similar means.<br />

3. Properly prepare and fill contraction and construction joints with cementitious based underlayment subfloor<br />

filler or epoxy subfloor filler as specified in Part 2 in this Section and as noted on the drawings. Do not<br />

seal joints under flooring using joint fillers specified for concrete slabs in Section 07900.<br />

4. Fill cracks, holes, and depressions with cementitious based underlayment subfloor filler and sand smooth as<br />

necessary to achieve a level, flat surface.<br />

5. Prohibit traffic until filler is cured. Thereafter, keep unnecessary traffic in work areas to a minimum.<br />

B. Remove paint, oils, waxes, sealers and curing compounds not compatible with adhesive to be used. Avoid<br />

organic solvents or liquid adhesive removers.<br />

3.4 INSTALLATION<br />

A. Install resilient flooring in accordance with manufacturer's published instructions at locations indicated on Wal-<br />

Mart Carpet/Tile Plan.<br />

B. Schedule resilient flooring installation to prevent damage to resilient flooring and to prevent movement of<br />

construction materials over area of resilient flooring.<br />

C. Open number of floor material cartons to provide quantity required to cover each area; mix pieces within single<br />

shade lot to ensure shade variations do not occur within any one area. When working with more than one lot, plan<br />

lot placement and location to minimize possible shade differences.<br />

D. Apply adhesive in accordance with manufacturer’s directions. Follow adhesives open time by spreading only<br />

enough adhesive to permit installation of floor materials before initial set. Do not spread adhesive for overnight<br />

dry.<br />

E. VCT Flooring Installation:<br />

1. Lay flooring from center marks established parallel to building walls.<br />

2. Allow minimum 1/2 full size tile width at room or area perimeter.<br />

3. Adjust tile layout as required to avoid use of units less than 1/2 tile.<br />

4. Install tile to square grid pattern with all joints aligned and pattern grain alternating with adjacent unit to<br />

produce basket weave pattern unless indicated otherwise on Drawings.<br />

F. Plank Flooring Installation:<br />

1. Install plank strips from side-to-side, not front-to-back, of store.<br />

2. Install plank strips with random end-joint offset over entire area. Cut planks in random sizes for starter<br />

pieces and alternate the size of the starter piece to avoid a repeating joint pattern. The shortest starter piece<br />

shall be not less than 12 inches.<br />

3. Overall plank flooring layout shall produce a complete random appearance of joint spacing, with end joints<br />

staggered a minimum of 6 inches apart.<br />

G. Wipe down adhesive bleed through during installation.<br />

09650 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


H. Rolling: Set flooring into place, thoroughly cross roll with a 100-150 pound three-sectional roller before adhesive<br />

set time expires to attain full adhesion.<br />

I. Terminate flooring at centerline of door openings where adjacent floor finish is dissimilar. Where flooring<br />

continues through door opening, continue established pattern with no interruption.<br />

J. Install transition strips at unprotected or exposed edges where flooring terminates.<br />

1. Set metal transition strips butted to adjacent flooring. Anchor into concrete slab with specified fasteners.<br />

Drill concrete with Matched Tolerance Drill Bit for Dense Concrete by Hilti.<br />

K. Scribe flooring to walls, columns, cabinets, floor outlets, and other appurtenances to produce tight joints.<br />

L. Continue flooring under movable type partitions without interrupting floor pattern.<br />

M. On installations involving flooring placement over existing asphaltic based (black) adhesives, use fast set Portland<br />

cement/latex based patch specified in Part 2 above.<br />

3.5 FIELD QUALITY CONTROL<br />

A. Inspect resilient flooring installation, pattern, layout, and attachment to substrate.<br />

3.6 CLEANING<br />

A. Remove excess adhesive from floor, base, and wall surfaces without damage.<br />

B. Broom clean resilient flooring after application.<br />

3.7 FLOOR TREATMENT<br />

A. Provide floor treatment for new resilient flooring.<br />

B. Examine surfaces and adjacent areas where products will be applied and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions. Do not proceed until satisfactory conditions have been<br />

corrected.<br />

C. Stripping VCT:<br />

1. Mix one part stripper to four parts water.<br />

2. Apply solution liberally to a manageable area of the floor and let solution set for 10 minutes prior to<br />

scrubbing. Do not allow the stripper to dry. Re-wet as necessary.<br />

3. Scrub VCT floor using an auto scrubber with maximum pad pressure or a slow speed buffer equipped with<br />

black pads or stripping brushes. Make at least three passes over each tile to remove mill finish.<br />

4. Thoroughly rinse the floor to remove any residue of cleaning or stripper solution.<br />

5. Let floor dry completely prior to application of floor finish.<br />

D. Cleaning PVC:<br />

1. Clean PVC flooring with a commercial flooring cleaner using mop or scrubber with white pads.<br />

2. Apply stripper only as necessary to remove adhesive bleed-thru.<br />

a. Apply diluted stripper solution liberally to a manageable area of the floor and let solution set for 10<br />

minutes prior to scrubbing. Do not allow the stripper to dry. Re-wet as necessary.<br />

3. Pick up cleaning or stripper solution from floor using the auto scrubber with clear water and red pads.<br />

4. Thoroughly rinse the floor to remove any residue of cleaning or stripper solution.<br />

5. Let floor dry completely prior to application of floor finish.<br />

E. Finishing:<br />

1. Apply floor finish in accordance with manufacturer's instructions.<br />

2. Vinyl Composition Flooring: Apply four coats of floor finish to floor. Burnish floor after 24 hours after<br />

final application and again prior to store opening.<br />

3. Slip Resistant VCT Tile: Apply two coats of floor finish to floor.<br />

09650 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. PVC Plank Flooring: Apply two light coat of floor finish to floor with a 24” rayon mop in direction of<br />

wood grain of plank. Do not burnish.<br />

5. Allow a minimum of 45 minutes drying time between coats.<br />

6. HVAC shall be in operation during drying and curing of floor finish.<br />

3.8 PROTECTION<br />

A. Prohibit traffic on floor finish for 48 hours after installation.<br />

B. Maintain adhesive manufacturer’s specified temperature range until completion construction operations.<br />

END OF SECTION<br />

09650 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


RESILIENT FLOORING ORDER FORM<br />

Instructions:<br />

To procure Vinyl Composition Tile or Solid Vinyl Plank flooring, complete this form in full and fax to the Vendor as<br />

follows.<br />

Tarkett: Linron Company: FAX: (713) 802.1654, Voice: (713) 802.9137<br />

Armstrong: Sally Leash: FAX (800) 446-8069 , Voice (717) 396-4491 or<br />

Lisa Braas: FAX (800) 446-8069, Voice (717) 396-5477<br />

Show quantities as taken from the architectural drawings. An overage of 2-3% of the actual floor area shall be included in the<br />

Contractor’s order. The Carpet & Tile plan shall be used for final location of the flooring. The flooring vendor will monitor<br />

quantities of all orders. Prior to releasing orders, the vendor will inform the Wal-Mart Construction Manager when there<br />

appears to be excessive overage.<br />

Additional material required beyond this original order without a Change Order will be back charged to the Contractor.<br />

Delivery dates shall be scheduled with the Vendor.<br />

Order shall be placed 90 days prior to possession date allowing for a 2 week lead time.<br />

Verify quantity of material delivered and notify Construction Planning within 24 hours if delivered quantities do not match<br />

Order Form.<br />

QUANTITY FROM CONTRACTOR’S<br />

CARPET & TILE PLAN ORDER (SQ. FT.)<br />

(SQ. FT.)<br />

• VCT-3: Slip Resistant, Lite<br />

• VCT-4: Slip Resistant, Dark<br />

• VCT-9: White<br />

• VCT-12: Tan<br />

• VCT-13: Blue<br />

• VCT-14: Yellow<br />

• VCT-15: Rust<br />

• VCT-16: Red<br />

• VCT-17: Blue<br />

• VCT-18: Yellow<br />

• VCT-19: Slip Resistant, White<br />

• OTHER: ___________________________________<br />

• OTHER: ___________________________________<br />

• OTHER: ___________________________________<br />

Required delivery date<br />

Superintendent<br />

Please print Superintendent's name<br />

General Contractor<br />

Date<br />

Superintendent’s Cell Phone<br />

General Contractor’s Phone<br />

Job Site Address: Wal-Mart Store #<br />

Job Site Phone:<br />

09650 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 042911<br />

SECTION 09655 (09 6513) – RESILIENT BASE AND ACCESSORIES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Plastic Base (B).<br />

2. Sanitary Cove Base (SCB).<br />

3. Resilient Stair Treads and Accessories.<br />

B. Related Requirements:<br />

1. Section 07900 - Joint Sealers: Sealant between bases and floor or wall surfaces.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

2. ASTM F 710 - Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring.<br />

3. ASTM F 2169 - Standard Specification for Resilient Stair Treads.<br />

1.3 DELIVERY, STORAGE AND HANDING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

1.4 SITE CONDITIONS<br />

A. Environmental Requirements:<br />

1. Store flooring materials for three days prior to installation in area of installation to achieve temperature<br />

stability.<br />

2. Maintain ambient temperature required by adhesive manufacturer (no less than 72 degrees F for 48 hours)<br />

three days prior to, during, and 24 hours after installation of materials.<br />

PART 2 - PRODUCTS<br />

2.1 PRODUCT PROCUREMENT<br />

A. Sanitary cove base products specified in this Section shall be direct purchased by the General Contractor from a<br />

pre-negotiated supplier. Reference Section 01600 for additional information regarding Direct Purchase Products.<br />

1. Pre-negotiated Supplier shall be Haines, Jones & Cadbury, Inc. Contact: Customer Service, (800) 459-<br />

7099, Fax (479) 756-8998, Email info@hjcinc.com.<br />

2.2 PRODUCTS<br />

A. Plastic Base: Style B, Plas-tex Dura Base by Parkland Plastics, Inc., Middlebury, IN (574) 825-4336 or (800) 835-<br />

4110.<br />

1. Model: Provide models specified below corresponding to mark number of base as shown on Drawings:<br />

a. B6: Model No. PTX2131P.<br />

b. B9: Model No. PTX2137P.<br />

c. B11: Model No. PTX6143P.<br />

d. Size: As scheduled on Drawings.<br />

09655 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Color: Black.<br />

3. Fasteners: Black flathead countersunk screws, length sufficient to penetrate substrate and metal stud wall<br />

framing.<br />

B. Sanitary Cove Base: As manufactured by Murphy Manufacturing, Denver, CO. Purchase sanitary cove base, base<br />

accessories, installation accessories and adhesive sealant as indicated in Product Procurement paragraph above.<br />

1. Material: Antimicrobial plastic, open core construction.<br />

2. Grade: Standard.<br />

3. Size: As shown.<br />

4. Edge: As shown.<br />

5. Finish: Smooth.<br />

6. Color: As applicable as shown on Drawings.<br />

a. SCB1 - Red. SCB1 sanitary cove base for quarry tile.<br />

b. SCB2 - Grey. SCB2 sanitary cove base for quarry tile.<br />

c. SCB4 - Red. SCB4 sanitary cove base for vct/epoxy/concrete.<br />

d. SCB5 - Grey. SCB5 sanitary cove base for vct/epoxy/concrete.<br />

e. SCB6 - Tan (Mushroom). SCB6 sanitary cove base for quarry tile.<br />

f. SCB7 - Tan (Mushroom). SCB7 sanitary cove base for vct/epoxy/concrete.<br />

7. Base Accessories:<br />

a. Special Shapes: Inside and outside corners, splicers, and end caps.<br />

1) 90 degree Corners: Shop prefabricated heat welded corners.<br />

2) 45 degree Corners: Shop prefabricated heat welded corners.<br />

3) Other than 90 and 45 degree Corners: Field fabricated as shown on Drawings.<br />

b. Button Caps.<br />

c. Splicers.<br />

8. Installation Accessories:<br />

a. Forstner Bit: 1/2 inch diameter.<br />

9. Adhesive/Sealant: Water resistant type, VOC less than 50 g/L. Provide one of the following products as<br />

selected by Wal-Mart Pre-negotiated Supplier:<br />

a. Seal Bond 96 (SB96) by Michigan Adhesive Mfg., Inc. Color: Gray, red or tan to match base.<br />

b. Greenchoice Titebond Weathermaster by Franklin International. Color: Gray, red, or tan to match<br />

base as follows:<br />

1) Grey: Color No. 44741.<br />

2) Red: Color No. 44231.<br />

3) Tan: Color No. 46381.<br />

C. Fasteners for Sanitary Cove Base: As indicated in sanitary cove base manufacturer’s written instructions and as<br />

shown on Drawings.<br />

D. Resilient Stair Treads:<br />

1. Manufacturer: Nora Rubber Flooring, Freudenberg Building Systems, Inc., Lawrence, MA 01843, (978)<br />

689-0530.<br />

2. One-Piece Nosing, Tread and Riser: Manufactured in accordance with ASTM F 2169, Type TS.<br />

a. Surface Design: Raised round pastilles.<br />

b. Color: Mocha.<br />

c. Installation Tape: Nora Stepfix.<br />

d. Stair-Tread-Nose Filler: Two-part epoxy compound recommended by resilient tread manufacturer<br />

to fill nosing substrates that do not conform to tread contours.<br />

E. Trowelable Leveling and Patching Compounds: Latex-modified, portland cement based or blended hydrauliccement-based<br />

formulation provided or approved by manufacturer for applications indicated.<br />

F. Building Tape: 25 mil polyethylene backed ruberized adhesive membrane tape, BT-25XL Building Tape by<br />

Proteco Wrap Co., Denver, CO (800) 759-9727.<br />

G. Regulatory Requirements: Conform to applicable code for flame/fuel/smoke rating requirements in accordance<br />

with ASTM E 84.<br />

09655 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


H. Substitutions: Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Resilient Stair Treads:<br />

1. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.<br />

2. Concrete Substrates for Resilient Stair Treads and Accessories: Prepare according to ASTM F 710.<br />

a. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.<br />

b. Remove substrate coatings and other substances that are incompatible with adhesives and that<br />

contain soap, wax, oil, or silicone, using mechanical methods recommended by manufacturer. Do<br />

not use solvents.<br />

c. Alkalinity and Adhesion Testing: Perform tests recommended by manufacturer.<br />

d. Moisture Testing: Perform tests recommended by manufacturer. Proceed with installation only<br />

after substrates pass testing.<br />

3. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound and<br />

remove bumps and ridges to produce a uniform and smooth substrate.<br />

4. Do not install resilient products until they are same temperature as the space where they are to be installed.<br />

a. Move resilient products and installation materials into spaces where they will be installed at least 48<br />

hours in advance of installation.<br />

3.2 INSTALLATION<br />

A. Plastic Base:<br />

1. Fit joints tight and vertical. Maintain minimum measurement of 18 inches between joints.<br />

2. Install base on solid backing. Bond tight to wall and floor surfaces.<br />

3. Scribe to fit door frames and other interruptions.<br />

4. Miter and adhesively bond plastic base joints together.<br />

5. Pre-drill plastic base and trim for attachment of screws. Unless otherwise shown, attach plastic base at 24<br />

inches on center into metal stud wall framing.<br />

B. Sanitary Cove Base: Install base in accordance with manufacturer’s written instructions and as shown on<br />

Drawings.<br />

C. Resilient Stair Treads: Install Resilient Stair Treads in accordance with manufacturer’s written instructions.<br />

D. Building Tape: Install building tape at base of wall behind resilient base or at joints as shown on Drawings.<br />

Install in accordance with manufacturer’s instructions.<br />

3.3 CLEANING<br />

A. Remove excess adhesive from floor, base, and wall surfaces without damage.<br />

END OF SECTION<br />

09655 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 09680 (09 6800) – CARPET<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Carpet tiles, adhesive, and accessories furnished by Owner for installation by Contractor in the following<br />

areas:<br />

a. Pharmacy.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to products furnished by Owner.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. Carpet and Rug Institute (CRI):<br />

1. CRI 104 - Standard for Installation of Commercial Carpet.<br />

1.3 SCHEDULING<br />

A. Schedule installation to prevent damage to carpet by subsequent construction activities.<br />

1.4 QUALITY ASSURANCE<br />

A. Installer Qualifications: A qualified installer who is certified by the Floor Covering Installation Board or who can<br />

demonstrate compliance with its certification program requirements.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Product Delivery: Carpet will be delivered to Site for Contractor to receive on delivery date established by<br />

Contractor. To establish product delivery date and quantity of carpet required, contact the following three weeks<br />

prior to desired delivery:<br />

1. Wal-Mart Store Planning Division, Anna Booth or Katy Brewer, (479) 273-4088.<br />

B. Acceptance at Site: Receive products as specified in Section 01640. Verify quantity of products furnished with<br />

Bill of Material provided with products. Report discrepancies in product quantity delivered or damage to products<br />

delivered to contact specified above. Upon notification by Contractor, arrangement will be made for delivery of<br />

replacement products. Note description of product quantity discrepancies and/or product damage on Bill of<br />

Lading.<br />

C. Comply with CRI 104, Section 5, "Storage and Handling".<br />

D. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer’s recommendations.<br />

E. Protect packaged adhesive from temperature cycling and cold temperatures. Keep adhesives away from any<br />

ignition source.<br />

F. Do not store roll goods on end.<br />

09680 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.6 SITE CONDITIONS<br />

A. Maintain areas to receive carpet at constant minimum temperature of 45 to 50 degrees F for minimum three days<br />

prior to and during installation.<br />

1. Comply with carpet manufacturer's surface moisture requirements.<br />

2. Provide negative alkalinity at substrate.<br />

B. Provide continuous ventilation during and after installation.<br />

C. Do not install carpet until wet work in spaces is complete and dry, and ambient temperature and humidity<br />

conditions are maintained at the levels indicated for Project when occupied for its intended use.<br />

D. Provide lighting levels of 80 foot candles measured mid-height at substrate surface.<br />

E. Comply with CRI 104, Section 6.1, "Site Conditions; Temperature and Humidity".<br />

F. Do not install adhesive applied carpet over concrete slabs until slabs have cured and are sufficiently dry to bond<br />

with adhesive and concrete slabs have pH range recommended by manufacturer.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner will furnish carpet products for installation by Contractor.<br />

Descriptions and specifications of Owner furnished products hereinafter are included as information to Contractor<br />

only and not to be considered as Contractor requirements unless otherwise stated.<br />

2.2 CARPET FURNISHED BY OWNER<br />

A. Carpet will be provided as applicable as shown on Drawings.<br />

B. C-1: Cushon Back Carpet Tile (Pharmacy): Geometry by Interface. CushonBac Plus Tile, tufted tip sheared<br />

pattern loop, 100% Solutia yarn. Furnished by Owner, installed by Contractor.<br />

1. Tile Size: 50 cm x 50 cm (19.69 in. square).<br />

2. Pattern: Geometry.<br />

3. Color: Optical.<br />

2.3 ACCESSORIES FURNISHED BY OWNER<br />

A. Adhesive: Franklin 780 Premium Multipurpose Flooring Adhesive by Franklin International, water resistant type,<br />

VOC less than 50 g/l.<br />

B. Primer: Type recommended by adhesive and carpet manufacturer; compatible with substrate. Primer. VOC shall<br />

be not greater than 50 g/L as set forth in the California’s South Coast Air Quality Management District<br />

(SCAQMD) Rule No. 1168.<br />

C. Transition Strip: Rubber transition strip.<br />

2.4 ACCESSORIES FURNISHED BY CONTRACTOR<br />

A. Subfloor Filler: Provide one of the following:<br />

1. Cementitious Based Underlayment Subfloor Filler:<br />

a. Ardex SD-F Feather Finish, by Ardex Engineered Cements. Contact: Ben Mack (724) 203-5060.<br />

b. Levelayer l, by Dayton Superior.<br />

c. No. 547 UniPro Universal Underlayment by W.W. Henry. Contact: Ben Mack (724) 203-5060.<br />

09680 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Epoxy Subfloor Filler: Epolith P or G, two-part 100% solids flexible epoxy joint filler, by BASF Building<br />

Systems (Formerly Degussa), (800) 433-9517.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions. Do not proceed until unsatisfactory conditions have been<br />

corrected. Verify that substrate surface is clean, true, and free of irregularities.<br />

3.2 PREPARATION<br />

A. Prepare substrate for product installation in accordance with manufacturer's published instructions.<br />

B. Properly prepare and fill contraction and construction joints under carpeting with cementitious based underlayment<br />

subfloor filler or epoxy subfloor filler as specified in Part 2 above.<br />

C. Vacuum clean surfaces free of loose particles.<br />

3.3 INSTALLATION<br />

A. Install carpet and accessories in accordance with manufacturer’s instructions.<br />

B. Comply with CRI 104, Section as applicable for the application method used.<br />

C. Install transition strips at locations shown on Drawings.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect installation, pattern matching, and attachment to substrate.<br />

B. Correct deficiencies in Work which inspection indicates are not in compliance with Contract Documents.<br />

3.5 CLEANING AND PROTECTION<br />

A. Perform the following operations immediately after installing carpet:<br />

1. Remove excess adhesive, seam sealer, and other surface blemishes using cleaner recommended by carpet<br />

manufacturer.<br />

2. Remove yarns that protrude from carpet surface.<br />

3. Vacuum carpet using commercial machine with face-beater element.<br />

B. Protect installed carpet to comply with CRI 104, Section 15, “Protection of Indoor Installations".<br />

C. Protect carpet against damage from construction operations and placement of equipment and fixtures during the<br />

remainder of construction period. Use protection methods indicated or recommended in writing by carpet<br />

manufacturer.<br />

END OF SECTION<br />

09680 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 09900 (09 9100) – PAINTS AND COATINGS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Field applied paints and finishes for interior and exterior surfaces (Partial Owner Furnished/Partial<br />

Contractor furnished, Contractor Installed).<br />

B. Related Requirements:<br />

1. Section 01640- Owner Furnished Products.<br />

2. Section 01743 - Hazardous/Universal Waste Management and Disposal.<br />

3. Section 09100 - Lath and Plaster (Stucco).<br />

4. Section 09250 - Gypsum Board: Textured Coatings.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM E 2129 - Standard Practice for Data Collection for Sustainability Assessment of Building Products.<br />

1.3 ADMINISTRATIVE REQUIREMENTS<br />

A. Scheduling and Coordination: Complete painting work at locations indicated to receive exterior building signage<br />

prior to new signage installation or reinstallation of existing signage previously removed and salvaged.<br />

1.4 SUBMITTALS<br />

A. Applicator Qualifications Statement: Submit statement of applicator qualifications in accordance with Section<br />

01330. Submit within 30 days of contract award.<br />

B. Closeout Documents: Submit Manufacturer’s Inspection Report of post-installation site visit specified hereinafter<br />

and in accordance with Section 01770.<br />

1.5 QUALITY ASSURANCE<br />

A. Regulatory Requirements:<br />

1. VOC Content: Provide paint and coating materials that conform to Federal, State, and Local restrictions for<br />

Volatile Organic Compounds (VOC) content.<br />

2. Toxicity/EQ: Comply with federal, state, and local toxicity and environmental quality regulations and with<br />

federal requirements on content of lead, mercury, and heavy metals. Do not use solvents in paint products<br />

that contribute to air pollution.<br />

B. Elastomeric Coating Field Sample:<br />

1. Apply elastomeric coating weatherproofing system to 10 ft by 10 ft sample panel at location on the building<br />

as directed.<br />

2. Apply in accordance with specified colors, texture, workmanship, and application requirements.<br />

3. Obtain Wal-Mart Construction Manager inspection and approval of sample panel.<br />

4. Maintain approved sample panel during construction as a standard for judging completed Work. Do not<br />

alter, move, or destroy panel until Work is completed.<br />

5. Apply scheduled final elastomeric coat to sample panel simultaneous with final coat of adjacent wall<br />

surface.<br />

09900 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Elastomeric Coating Applicator Qualifications: Applicator having minimum 5 years documented experience in<br />

the application of elastomeric coatings and approved in writing by coating manufacturer.<br />

D. Elastomeric Coating Manufacturer's Technical Representative: A coating manufacturer’s representative shall<br />

provide field service at site as required.<br />

E. Elastomeric Coating Pre-Installation Conference:<br />

1. Pre-Installation Conference:<br />

a. Convene a pre-installation conference at the site, one week prior to commencing Work of this<br />

Section.<br />

b. Contact Wal-Mart Construction Manager two weeks prior to pre-installation conference to confirm<br />

schedule.<br />

c. Attendance:<br />

1) Contractor.<br />

2) Coating subcontractor.<br />

3) Coating manufacturer's technical representative.<br />

d. Agenda:<br />

1) Substrate condition including manufacturer’s written approval.<br />

2) Sequence and method of application of coating system.<br />

e. Record discussions of conference and decisions and agreements (or disagreements) reached, and<br />

affix signatures of all attendees. Furnish copy of record to the Wal-Mart Construction Manager and<br />

to each party attending.<br />

F. Post-Installation Site Visit: Upon completion, Manufacturer's Technical Representative shall provide field service<br />

including site visit and observation of completed coating system installation.<br />

1. Prepare inspection report of site visit and submit as a closeout submittal.<br />

1.6 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Product Order and Delivery: Prepare and order all coating materials and accessories for Contractor furnished<br />

products and arrange delivery of Owner furnished products and submit together to Owner Supplier specified<br />

hereinbefore. Owner Supplier will deliver products to site on delivery date established by Contractor. To arrange<br />

product order and delivery, contact Supplier.<br />

C. Acceptance at Site: Receive products as specified in Section 01640.<br />

1. Verify quantity of products furnished with Bill of Material provided with Owner furnished products.<br />

2. Report discrepancies in product quantity delivered or damage to Supplier.<br />

3. Upon notification by Contractor, Supplier will arrange for delivery of replacement products.<br />

4. Note description of product quantity discrepancies and/or product damage on Bill of Materials.<br />

D. Paint orders shall identify the store number, location, and address of project.<br />

E. Delivery of paint materials shall be in sealed original labeled containers, bearing manufacturer's name, type of<br />

paint, brand name, lot number, brand code, coverage, surface preparation, drying time, cleanup requirements, color<br />

designation, and instructions for mixing and/or reducing. Notify Supplier when delivered products to not conform<br />

to these requirements.<br />

1.7 ENVIRONMENTAL REQUIREMENTS<br />

A. Apply paint finishes only when moisture content of surfaces is within manufacturer's acceptable ranges for type of<br />

finish being applied.<br />

B. Minimum surface temperatures or ambient air temperature shall be as follows for the specified coatings unless<br />

otherwise specifically stated by the manufacturer for the specific coating:<br />

1. Alkyd and interior and exterior latex finishes: 50 degrees F.<br />

09900 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Varnish and transparent finishes: 65 degrees F.<br />

3. All coatings: 5 degrees F above dew point.<br />

C. Provide continuous ventilation and heating facilities to maintain temperatures above the manufacturer’s stated<br />

minimum surface and air temperature for 24 hours prior to, during, and 48 hours after application of interior<br />

finishes.<br />

D. Do not apply paint in areas where dust is being generated.<br />

E. Provide lighting level in areas being painted of 80 foot candles measured mid-height at substrate surface.<br />

F. Waste Management:<br />

1. Comply with requirements of Sections 01742 and 01743.<br />

2. Obtain paint in containers of the largest size practical for each color, sheen, and type.<br />

3. Remove excess paint from containers and dispose in accordance with MSDS data and local environmental<br />

regulations for paint products.<br />

4. Expose waste paint to air and allow paint to dry.<br />

5. Return reusable drums and totes to manufacturer.<br />

6. Clean and recycle containers that cannot be returned to manufacturer.<br />

1.8 ELASTOMERIC COATING WARRANTY<br />

A. Contractor shall obtain Intent-to-Warrant statement from Coating Manufacturer prior to coating application.<br />

B. Submit warranty as part of closeout documents in accordance with Section 01770.<br />

C. Material: Provide manufacturer’s material warranty, including labor for re-application, to cover:<br />

1. Waterproofing above grade.<br />

2. Bonding.<br />

3. Weathering.<br />

D. Workmanship: Provide manufacturers workmanship warranty to cover labor for deficient workmanship and<br />

application.<br />

E. Warranty Period:<br />

1. Provide 10 year material and workmanship warranty for new unpainted surfaces and 5 year warranty for<br />

recoating of previously painted surfaces.<br />

F. Prepare Application for Limited Warranty included at the end of this Section for submission to elastomeric paint<br />

manufacturer. Follow instructions on form.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner’s supplier will furnish a limited portion of the specified products in the<br />

quantities as specified hereinafter on the Owner furnished Quantity Schedule for installation by the Contractor.<br />

1. Owner supplied products will conform to the specifications included in this section.<br />

2. Owner Supplier: Sherwin Williams Company. Contact: Kevin Behm, (216) 566-1558,<br />

Kevin.c.behm@sherwin.com<br />

B. Products Provided (Furnished and Installed) by the Contractor: The Contractor shall provide all products specified<br />

herein which are not scheduled to be Owner furnished.<br />

09900 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Quantity Furnished: Owner will furnish coatings in the quantities shown on the Owner Furnished Quantity<br />

Schedule at the end of this Section. The quantity furnished by Owner is not to be considered fully sufficient for<br />

the total project. Supplemental required quantities to those of Owner furnished coatings including additional<br />

quantities of Owner furnished coatings, coatings not furnished by Owner, and other materials and accessories as<br />

determined by the Contractor necessary for the complete project, shall be furnished by the Contractor at Contractor<br />

expense. Supplemental coating quantities shall be obtained from the Owner Supplier. Owner furnished coatings<br />

are not differentiated by color. The Contractor shall identify on the order, the appropriate colors as required.<br />

2.2 MATERIALS<br />

A. Paint: Owner furnished and Contractor provided coating materials shall be the product of Sherwin Williams Co.<br />

as specified in the Painting Schedule hereinafter. Substitutions will not be permitted.<br />

B. Accessory Materials (Contractor Provided): Accessory materials not specifically indicated herein but required to<br />

achieve the finishes specified, shall be provided by the Contractor and shall be of highest quality and as<br />

recommended by the manufacturer.<br />

1. Paint Thinners: Type recommended by paint or coating manufacturer for paint or coating system, VOC<br />

compliant, first line commercial quality. Do not use solvents for thinning paint materials.<br />

2. Patching Materials: Low VOC Latex filler.<br />

C. Carpet Adhesive Cleaner (Contractor Provided): Mohawk Nu-Spraylok Adhesive Cleaner (DK138) as distributed<br />

by Mohawk Group. (800) 428-8311.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be applied and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions. Do not proceed until unsatisfactory conditions have been<br />

corrected.<br />

B. Beginning of application indicates acceptance of substrate conditions.<br />

3.2 PREPARATION<br />

A. Apply paint only on surfaces free of dirt, rust, scale, grease, moisture, scuffed surfaces, and conditions otherwise<br />

detrimental to formation of a durable paint film.<br />

B. Perform preparation and cleaning procedures in accordance with paint manufacturer's published instructions for<br />

each particular substrate condition.<br />

1. Provide barrier coats over incompatible primers or remove and reprime as required.<br />

2. Remove hardware, hardware accessories, machined surfaces, plates, lighting fixtures, and similar items in<br />

place and not to be painted or provide surface applied protection prior to surface preparation and painting<br />

operations. Reinstall all removed items after completion of paint work.<br />

3. Clean surfaces to be painted before applying paint or surface treatment. Remove oil and grease prior to<br />

mechanical cleaning.<br />

C. Ferrous Metals: Clean ferrous surfaces that are not galvanized or shop-coated, of oil, grease, dirt, loose mill scale,<br />

and other foreign substances by solvent or mechanical cleaning.<br />

1. Touch-up shop-applied prime coats where damaged or bare. Clean and touch-up with same type shop<br />

primer.<br />

D. Galvanized Surfaces: Clean free of oil and surface contaminants with non-petroleum based solvent. Apply coat of<br />

etching primer if required by paint manufacturer.<br />

09900 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Cementitious Materials: Prepare cementitious surfaces to be painted by removing efflorescence, chalk, dust, dirt,<br />

grease, oils, and by roughening as required to remove glaze.<br />

1. Determine alkalinity and moisture content of surfaces to be painted by performing appropriate tests.<br />

a. Alkalinity shall be a maximum ph of 13 and a minimum of 6.<br />

b. If surface alkalinity is outside range specified above, correct condition before application of paint.<br />

c. Do not paint over surfaces where moisture content exceeds that permitted in manufacturer's printed<br />

instructions.<br />

2. Clean and etch floor surfaces scheduled to be painted with a commercial solution of muriatic acid, or other<br />

etching cleaner. Flush floor with clean water to neutralize acid and allow to dry before painting. Mask<br />

floor surfaces not to be cleaned and etched.<br />

a. Sealer Removal: Prior to etching, remove curing compound and sealers with strong solvents such as<br />

xylene, MEK, toluene or commercial paint strippers or by sandblasting or other similar mechanical<br />

action.<br />

F. Interior Surfaces of Precast Concrete Panels:<br />

1. Remove bond breakers.<br />

2. Remove curing compound if it is not compatible with coating system.<br />

3. Remove fins and projections.<br />

4. Patch cracks, pockets, holes, breakouts, surface irregularities, and damaged surfaces.<br />

a. Fine cracks up to 1/32 inch: Brush or knife Tex Cote Flex Patch Buttery or Knife into cracks and<br />

bring to smooth and flush with concrete surface.<br />

b. Cracks 1/32 inch to 1/8 inch: Fill uniform with surrounding surfaces with Tex Cote Flex Patch<br />

Smooth.<br />

c. Cracks 1/8 inch to 3/8 inch: Fill with Tex Cote Skim Cote.<br />

d. Cracks 3/8 inch or wider: Fill with cementitious patching compound; #2 Portland cement; 60-80<br />

mesh sand, Tex Bond acrylic bonding agent and water.<br />

5. Record and report pH test results to Elastomeric Coating Manufacturer’s Technical Representative.<br />

6. Roof and parapet top caps shall be installed and sealed against water penetration prior to coating. Verify<br />

water tightness.<br />

G. Wood: Clean wood surfaces to be painted of dirt, oil, and other foreign substances with scrapers, mineral spirits,<br />

and sandpaper, as required. Sandpaper smooth those finished surfaces exposed to view, and dust off. Scrape and<br />

clean small, dry, seasoned knots and apply a thin coat of white shellac or other recommended knot sealer, before<br />

application of priming coat. After priming, fill holes and imperfections in finish surfaces with putty or plastic<br />

wood filler. Sandpaper smooth when dried.<br />

1. Prime, stain, or seal wood required to be job-painted immediately upon delivery to job. Prime edges, ends<br />

faces, undersides, and backsides of such wood, including cabinets and counters.<br />

2. Seal tops, bottoms, and cut-outs with a heavy coat of varnish or equivalent sealer immediately upon<br />

delivery to job.<br />

H. Plaster (Stucco): Stucco shall be cured at least 30 days before painting; pH must be 10.0 or lower. Surfaces must<br />

be sound, clean, dry, free of oil, grease, curing agents or sealers, efflorescence, loose aggregate and other foreign<br />

matter.<br />

1. Refer to Section 09100 - Lath and Plaster (Stucco) for additional information.<br />

I. Gypsum Board: Fill minor defects with filler compound. Spot prime defects after repair.<br />

1. Prepare gypsum board surfaces to receive paint P-9 as shown on the drawings with textured coating<br />

specified in Section 09250.<br />

2. Exterior Gypsum Board Sheathing: Exterior gypsum board sheathing to receive a paint finish shall be<br />

prepared for painting with joint treatment and skim coating as specified in Section 09250.<br />

J. Previously Painted Surfaces: Prepare previously painted surfaces in accordance with manufacturer’s<br />

recommendations. Remove loose paint by scrape or wire brush as necessary. Clean surfaces thoroughly and<br />

roughen existing paint surfaces by lightly sanding. Clean and remove mildew using trisodium phosphate. Touch<br />

up bare surfaces with prime coat scheduled. Painted surfaces with existing sound prime or finish coats do not<br />

require additional prime coating. Finish coats shall be applied in number and DFT specified.<br />

09900 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 APPLICATION<br />

A. Apply coating systems specified in the Painting Schedule hereinafter for the corresponding surface. Shop primed<br />

surfaces will not require field applied 1st coat (primer) specified in the Painting Schedule.<br />

B. Apply paint products in accordance with manufacturer's published instructions using application procedures<br />

approved for the particular application and substrate.<br />

C. Apply each coat to the Dry Film Thickness (DFT) specified which represents the minimum Dry Film Thickness in<br />

mils per coat. Apply each coat to uniform coverage.<br />

D. Apply each coat slightly darker than preceding coat unless otherwise approved by Wal-Mart Construction<br />

Manager. Sand smooth surfaces lightly between coats to achieve specified finish.<br />

E. Allow drying time between coats as recommended by the manufacturer.<br />

F. Apply additional coats when undercoats, stains, or other conditions show through final coat until paint film is of<br />

uniform finish, color, and appearance. Surfaces, including edges, corners, crevices, welds, and exposed fasteners<br />

shall receive minimum dry film thickness equivalent to that of flat surfaces.<br />

G. Block Fillers: Apply block fillers to concrete masonry units at rate to provide complete coverage with pores filled.<br />

H. Prime Coats: Before application of finish coats, apply a prime coat of material as scheduled or as recommended<br />

by manufacturer to material scheduled to be painted or finished that has not been shop primed. Recoat primed and<br />

sealed surfaces where evidence of suction spots or unsealed areas in first coat appears, to assure a finish coat with<br />

no burn through or other defects due to insufficient sealing.<br />

3.4 MECHANICAL AND ELECTRICAL EQUIPMENT<br />

A. Replace identification markings on mechanical or electrical equipment when painted over or spattered.<br />

B. Where exposed piping, conduit, and electrical equipment are to be painted, paint color and texture shall match<br />

adjacent surfaces.<br />

C. Paint both sides and edges of plywood backboards for electrical equipment prior to installation.<br />

D. Prepaint Gas piping prior to installation. Touch up paint after installation. Colors shall be as follows:<br />

1. Exterior Piping on Roof (Yellow): P5, OSHA Standard Safety Yellow.<br />

2. Interior Piping in Receiving and Stockroom Areas (Yellow): P5, OSHA Standard Safety Yellow.<br />

3. Piping in all Other Areas: Color to match adjacent surfaces.<br />

3.5 APPLICATION OF ELASTOMERIC COATINGS<br />

A. General:<br />

1. Concrete masonry unit walls shall have been installed at least 21 days prior to elastomeric coating<br />

application.<br />

2. Begin system application at rear of building and work toward front. Begin system application at top of wall<br />

and work down. Begin application of system in the presence of Manufacturer's Technical Representative.<br />

3. Do not paint sealants. Paint wall prior to sealant application in building joints. Protect joints to be sealed<br />

by inserting calking backer rods at face of wall.<br />

4. Apply coatings in accordance with manufacturer's recommendations.<br />

5. Apply cold weather coatings at surface and ambient temperatures at or above manufacturer’s recommended<br />

application temperatures and rising.<br />

09900 - 6<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Application:<br />

1. Primer:<br />

a. Apply primer to masonry surfaces when and as recommended by the manufacturer as a part of the<br />

elastomeric system. Provide written documentation from manufacturer if primer coat is or is not<br />

required.<br />

2. Block Filler:<br />

a. Apply using brush, roller, or spray unless recommended by manufacturer to use brush only. For<br />

spray application, use airless equipment and back roll material into voids of substrate.<br />

b. Comply with manufacturer's published instructions for application rate appropriate for profile,<br />

texture, and porosity of substrate.<br />

3. Coating:<br />

a. Allow block filler to dry 24 to 48 hours before proceeding with subsequent coating.<br />

b. Apply material by brush, roller, plaster type sprayer, or low pressure sprayer unless recommended<br />

by manufacturer to use brush only. Back roll brushed or sprayed material. Cross roll roller-applied<br />

material. Finish material with brush and roller strokes in one direction. For spray application, use<br />

airless equipment.<br />

c. Apply two coats with a minimum dry film thickness (DFT) as specified in the Painting Schedule.<br />

d. Provide pinhole free finish coat.<br />

e. Match approved elastomeric coating field samples for color and sheen.<br />

3.6 FIELD QUALITY CONTROL<br />

A. Inspect painting and coating application for scheduled material, color, sheen, specified thickness (DFT), and<br />

coverage.<br />

B. Elastomeric Coatings:<br />

1. Maintain schedule of application of system in field office for Owner's review.<br />

2. Manufacturer's Representative Inspection: At completion of application, obtain Manufacturer's<br />

Representative (must be same individual present at pre-installation conference) inspection of application<br />

and color. Compare application with sample panel. Provide Manufacturer's Representative Report of<br />

deficiencies to Contractor and Wal-Mart Construction Manager.<br />

3.7 CLEANING<br />

A. As work proceeds and upon completion, promptly remove paint where spilled, splashed, or spattered.<br />

B. During progress of work keep premises free from unnecessary accumulation of tools, equipment, surplus<br />

materials, and debris.<br />

C. Collect waste, cloths, and material which may constitute a fire hazard, place in closed metal containers, and<br />

remove daily from site.<br />

D. Upon completion of work, leave premises neat and clean.<br />

3.8 PROTECTION<br />

A. Protect other surfaces from paint and damage. Repair damage as a result of inadequate or unsuitable protection.<br />

09900 - 7<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.9 PAINT COLOR SCHEDULE<br />

A. Provide following colors as applicable as shown or scheduled on the drawings.<br />

Mark<br />

Color Number/Name By Sherwin<br />

Williams unless otherwise shown.<br />

P1 SW# 1234 Evening Shadow<br />

P2 SW# 7664 Steely Gray<br />

P3<br />

SW# 1504 Nobility Blue, OR<br />

SW# 6510 Loyal Blue<br />

P4 SW# 1602 Theater Red<br />

P5 OSHA Standard Safety Yellow<br />

P6 SW# 6811 Honorable Blue<br />

P7 Pittsburgh Paints #2537 Blossom White<br />

P8 SW# 7005 Pure White<br />

SW# 7042 Shoji White. Apply over<br />

P9 textured coating specified in Section<br />

09250<br />

P10 SW# 6061 Tan Bark<br />

P11 SW# 6115 Totally Tan<br />

P12 SW# 6112 Biscuit<br />

P13 SW# 6454 Shamrock<br />

P14 SW# 6677 Goldenrod<br />

P15 SW# 7669 Summit Gray<br />

P16 SW# 7074 Software<br />

P17 SW# 7689 Row House Tan<br />

P18 SW#7507Stone Lion<br />

P19 SW# 6094 Sensational Sand<br />

P20 SW# 7036 Accessible Beige<br />

P21 SW# 4081 Safety Red<br />

P22 Pantone Color System PMS 286C.<br />

P23 SW# 7005 Pure White<br />

P24 SW# 2819 Downing Slate<br />

P25 SW# 0045 Antiquarian Brown<br />

P26 SW# 6080 Utterly Beige<br />

P27 SW# 6103 Tea Chest<br />

P28 SW# 6124 Cardboard<br />

P29 SW# 6420 Queen Anne’s Lace<br />

P30 SW# 2018 Pink Beige<br />

P31 SW# 2016 Canberra<br />

P32 SW# 6387 Compatible Cream<br />

P33 SW# 6385 Dover White<br />

P34 SW# 6519 Hinting Blue<br />

P35 SW# 7071 Gray Screen<br />

P36 SW# 6989 Domino<br />

P37 SW# 0046 White Hyacinth<br />

P38 SW# 6102 Portabello<br />

P39 SW# 6122 Camelback<br />

P40 SW# 6665 Gardenia<br />

P41 SW# 6100 Practical Beige<br />

P42 SW# 6372 Inviting Ivory<br />

P43 SW# 6667 Afterglow<br />

P44 SW# 6666 Enjoyable Yellow<br />

Mark<br />

P45<br />

P46<br />

P47<br />

P48<br />

P49<br />

P50<br />

P51<br />

P52<br />

P53<br />

P54<br />

P55<br />

P56<br />

P57<br />

P58<br />

P59<br />

P60<br />

P61<br />

P62<br />

P63<br />

P64<br />

P65<br />

P66<br />

P67<br />

P68<br />

P69<br />

P70<br />

P71<br />

P72<br />

P73<br />

P74<br />

P75<br />

P76<br />

P77<br />

P78<br />

P79<br />

P80<br />

P81<br />

P82<br />

P83<br />

P84<br />

P85<br />

P86<br />

P87<br />

P88<br />

P89<br />

P90<br />

Color Number/Name By Sherwin<br />

Williams unless otherwise shown.<br />

SW# 0044 Hubbard Squash<br />

SW# 7006 Extra White<br />

SW# 0051 Classic Ivory<br />

SW# 7722 Travertine<br />

SW# 7019 Gauntlet Grey<br />

SW# 6382 Ceremonial Gold<br />

SW# 6662 Summer Day<br />

SW# 6334 Flower Pot<br />

SW# 6810 Lupine<br />

SW# 6432 Garden Spot<br />

SW# 6285 Grape Harvest<br />

SW# 6500 Open Seas<br />

SW# 2848 Roycroft Pewter<br />

SW# 6006 Black Bean<br />

SW# 0077 Classic French Gray<br />

SW# 6053 Reddened Earth<br />

SW# 6079 Diverse Beige<br />

SW# 6172 Hardware.<br />

SW# 2340 Buff<br />

SW# 6332 Coral Island<br />

SW# 6378 Crisp Linen<br />

SW# 6085 Simplify Beige<br />

SW# 6114 Bagel<br />

SW# 6113 Interactive Cream<br />

SW# 6340 Baked Clay.<br />

SW# 2838 Polished Mahogany<br />

SW# 7051 Analytical Gray.<br />

SW# 6658 Welcome White.<br />

SW# 6214 Underseas<br />

SW# 6659 Captivating Cream<br />

SW# 2804 Renwick Rose Beige<br />

Custom Match # 076 Walmart Medium<br />

Blue<br />

SW# 6087 Trusty Tan<br />

SW# 2445 Creamy White<br />

SW# 6359 Sociable<br />

SW# 6060 Moroccan Brown<br />

SW# 6148 Wool Skein<br />

SW# 7679 Golden Gate<br />

SW# 6082 Cobble Brown<br />

SW# 7641 Collonade Gray<br />

SW# 2823 Rookwood Clay<br />

SW# 6356 Copper Mountain<br />

SW# 2807 Rookwood Medium Brown<br />

SW# 7517 China Doll<br />

SW# 6062 Rugged Brown<br />

SW# 7502 Dry Dock<br />

09900 - 8<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Mark<br />

P91<br />

P92<br />

P93<br />

P94<br />

P95<br />

P96<br />

P97<br />

P98<br />

P99<br />

P100<br />

P101<br />

P102<br />

P103<br />

P104<br />

P105<br />

P106<br />

P107<br />

P108<br />

Color Number/Name By Sherwin<br />

Williams unless otherwise shown.<br />

SW# 7513 Sanderling<br />

SW# 7536 Bittersweet Stem<br />

SW# 7538 Tamarind<br />

SW# 6258 Tricorn Black<br />

SW# 7702 Spiced Cider<br />

SW# 7705 Wheat Penny<br />

SW# 7710 Brandy Wine<br />

SW# 7718 Oak Creek<br />

SW# 7722 Travertine<br />

SW#6521 Notable Hue<br />

SW#7694(EXT) Exterior Dromedary<br />

Camel<br />

SW#7518 Beach House<br />

SW#6095 Toasty<br />

SW# 6867 Fireworks<br />

SW#6526 Icelandic<br />

SW#6675 Afternoon<br />

SW#7698 Straw Harvest<br />

SW# 6991 Black Magic<br />

Mark<br />

P109<br />

P110<br />

P111<br />

P112<br />

P113<br />

P114<br />

P115<br />

P116<br />

P117<br />

P118<br />

P119<br />

P120<br />

P121<br />

P122<br />

P123<br />

P124<br />

P125<br />

Color Number/Name By Sherwin<br />

Williams unless otherwise shown.<br />

SW#7506 Loggia<br />

SW# 7043 Worldly Gray<br />

SW# 7531 Canvas Tan<br />

SW# 6676 Butterfield<br />

SW#6674 Jonquil<br />

SW#7720 Deer Valley<br />

SW#6076 Turkish Coffee<br />

Pantone Color System 368C<br />

SW# 6429 Baize Green<br />

SW# 6720 Paradise<br />

SW# 6895 Laughing Orange<br />

SW# 6887 Navel<br />

SW# 6905 Goldfinch<br />

SW# 6413 Restoration Ivory<br />

SW# 6380 Humble Gold<br />

SW# 7522 Meadowlark<br />

SW# 6923 Festival Green<br />

3.10 PAINT SHEEN SCHEDULE<br />

A. Gloss:<br />

1. Exterior metal surfaces.<br />

2. Exterior hollow metal doors and frames (inside and outside surfaces).<br />

3. Roof hatch (inside and outside surfaces).<br />

4. Interior & exterior pipe bollards.<br />

5. Interior & exterior metal railings.<br />

6. Metal stair stringers and handrails.<br />

7. Metal fixed ladders and cages.<br />

8. CMU accent colors.<br />

B. Semigloss:<br />

1. Interior hollow metal doors and frames.<br />

2. Interior hollow metal window frames.<br />

3. Wood trim or simulated wood trim scheduled to be painted.<br />

4. Coiling metal counter doors.<br />

5. Toilet gypsum board ceilings.<br />

6. Interior face of all walls within Pharmacy and exterior face of Pharmacy front wall (sales floor side)<br />

7. Interior columns surfaces to receive epoxy finish.<br />

C. Eggshell:<br />

1. All surfaces to be painted where a sheen is not otherwise specified.<br />

D. Flat:<br />

1. Exterior Insulation and Finish System.<br />

2. Stucco.<br />

3. Exterior gypsum board ceilings.<br />

4. Exterior concrete.<br />

09900 - 9<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.11 ITEMS TO BE PAINTEDSCHEDULE<br />

A. Paint surfaces as shown or scheduled on the drawings including, but not limited to, the following items.<br />

1. Exterior: Paint existing exterior surfaces as indicated by Painting Schematic and Exterior Building<br />

Elevations on the Drawings. Paint all new exterior surfaces including, but not limited to:<br />

a. Hollow metal doors and frames.<br />

b. Metal opening frames and trim.<br />

c. Metal flashing and downspout (surfaces exposed from ground level).<br />

d. Metal gutters (surfaces exposed to view from ground level).<br />

e. Cast iron downspout boots.<br />

f. Metal fascias (vertical face).<br />

g. Parapet walls, roof side (where roofing does not occur).<br />

h. Pipe bollards where shown to be painted.<br />

i. Metal railings.<br />

j. Roof hatch.<br />

k. Satellite dish support (from bottom of deck to top of support).<br />

l. Exposed rooftop refrigeration and HVAC support framing.<br />

m. Shop primed metal canopies and canopy supporting steel structure.<br />

n. Underside of metal roof panels where exposed.<br />

o. Overhead doors if shown.<br />

p. Exposed precast concrete wall panels at locations shown to be painted.<br />

q. Stucco.<br />

r. Exterior Wood.<br />

s. Paving graphics and markings.<br />

t. Exposed piping and conduit, hangers and supports.<br />

2. Interior: Paint existing interior surfaces as indicated on the Drawings and Paint Color Schedule at end of<br />

this Section. Paint all new interior surfaces as scheduled on Drawings including, but not limited to:<br />

a. Hollow metal doors and frames.<br />

b. Hollow metal window frames.<br />

c. Overhead coiling doors.<br />

d. Metal opening frames and trim.<br />

e. Gypsum wallboard.<br />

f. Exposed concrete unit masonry.<br />

g. Exposed precast concrete wall panels at locations shown to be painted.<br />

h. Pipe Bollards shown to be painted.<br />

i. Metal railings.<br />

j. Exposed plywood (except plywood wainscot).<br />

k. Exposed mechanical ductwork, hangers and supports (if exposed structure is scheduled to be<br />

painted).<br />

l. Exposed piping and conduit, hangers and supports (if exposed structure is scheduled to be painted).<br />

m. Exposed piping, conduit, and electrical equipment occurring in finished areas where it will be<br />

exposed to the public.<br />

n. Exposed fire protection piping, hangers and supports (if exposed structure is scheduled to be<br />

painted).<br />

o. Exposed overhead structure including joists, girders, bridging, miscellaneous metal fabrications and<br />

deck (if scheduled to be painted).<br />

p. Exposed structure columns.<br />

q. Wall accent stripes, signage, and graphics.<br />

r. Floor striping, graphics, and markings.<br />

s. Metal stair stringers and handrails.<br />

t. Exposed wood trim.<br />

B. Do not paint the following Items:<br />

1. Aluminum, brass, bronze, stainless steel, and chrome plated steel.<br />

2. Pre-finished items, such as toilet compartments, acoustical ceiling materials, mechanical, and electrical<br />

equipment or factory finished metal panels and trim.<br />

3. UL, FM, and other code-required labels.<br />

09900 - 10<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


4. Equipment identification, performance rating, and name plates.<br />

5. Finish hardware.<br />

3.12 PAINTING SCHEDULE<br />

A. Apply paint to the substrate surface scheduled as applicable as specified or as shown on the drawings in<br />

accordance with the following:<br />

Surface Sheen 1st Coat<br />

EXTERIOR PAINTING SCHEDULE<br />

DFT<br />

(mils) VOC<br />

2nd and 3rd Coats<br />

(per (g/l)<br />

coat)<br />

DFT<br />

(mils)<br />

(per<br />

coat)<br />

VOC<br />

(g/l)<br />

Ferrous<br />

Metal<br />

Ferrous<br />

Metal<br />

Over factory<br />

painted<br />

surface<br />

Ferrous<br />

Metal<br />

(Existing<br />

roof<br />

mounted<br />

equip<br />

framing to<br />

remain)<br />

Ferrous<br />

Metal<br />

(Satellite<br />

dish support<br />

and exposed<br />

rooftop<br />

refrigeration<br />

and HVAC<br />

support<br />

framing.<br />

Gloss<br />

Gloss<br />

Gloss<br />

Gloss<br />

Pro Industrial ProCryl Universal<br />

Primer B66-310<br />

Pro Industrial Zero VOC Enamel,<br />

B66-600 Series<br />

All States except CA: Epolon II<br />

Rust Inhibitive Epoxy Primer<br />

B67W400, B67A400, B67A400<br />

State of CA: Macropoxy 646-<br />

100, B58W620, B58V620<br />

Pro Industrial ProCryl Universal<br />

Primer B66-310<br />

3.0 100 2 Coats: Pro Industrial Zero VOC<br />

Enamel, B66-600 Series<br />

4.0 0 1 Coat: Pro Industrial Zero VOC<br />

Enamel, B66-600 Series<br />

4.0<br />

5.0-<br />

10.0<br />

300<br />


Surface Sheen 1st Coat<br />

EXTERIOR PAINTING SCHEDULE<br />

DFT<br />

(mils) VOC<br />

2nd and 3rd Coats<br />

(per (g/l)<br />

coat)<br />

DFT<br />

(mils)<br />

(per<br />

coat)<br />

VOC<br />

(g/l)<br />

Concrete<br />

Masonry<br />

Unit<br />

Elastomeric<br />

(50 degrees<br />

F or above)<br />

Concrete<br />

Masonry<br />

Unit<br />

Elastomeric<br />

(Below 50<br />

degrees F)<br />

Concrete<br />

Masonry<br />

Unit<br />

(Accent<br />

Coating)<br />

Exterior<br />

Insulation<br />

and Finish<br />

System<br />

Fiber<br />

Cement<br />

Siding<br />

Precast<br />

Concrete<br />

Exposed<br />

Timber,<br />

Purlins,<br />

Plywood,<br />

Wood<br />

Exposed<br />

Timber,<br />

Purlins,<br />

Plywood,<br />

Wood<br />

Gypsum<br />

Board<br />

(Ceiling)<br />

Concrete<br />

Pavement<br />

Flat Heavy Duty Block Filler B42W46 18.0 100 2 Coats: Conflex XL High Build<br />

Elastomeric, A5-400<br />

Flat<br />

Gloss<br />

Loxon Block Surfacer, A24W200<br />

(Above 35°F).<br />

Pro Industrial Zero VOC Enamel,<br />

B66-600 Series(Apply to<br />

Elastomeric)<br />

Flat A-100 Exterior Latex Finish, A6-<br />

100 Series<br />

Flat<br />

Flat<br />

Semi-<br />

Transp<br />

arent<br />

Stain<br />

Opaqu<br />

e Stain<br />

Flat<br />

Eggshell<br />

Loxon Concrete and Masonry<br />

Primer, B28W8300<br />

Loxon Concrete and Masonry<br />

Primer, B28W8300<br />

WoodScapes Polyurethane Stain<br />

A15T5<br />

1 Coat: WoodScapes Latex Stain<br />

A15W51<br />

A-100 Exterior Latex Primer,<br />

B42W43<br />

Setfast Acrylic Waterborne<br />

Traffic Marking Paint, TM<br />

226/227<br />

8.0 81 2 Coats: UltraCrete Solvent Borne<br />

Masonry Coating, B46 Series(Above<br />

20° F)<br />

4.0 0<br />

1.3 49 1 Coat: A-100 Exterior Latex Finish,<br />

A6-100 Series<br />

3.2 96 2 Coats: A-100 Exterior Latex Finish,<br />

A6-100 Series<br />

3.2 96 2 Coats: A-100 Exterior Latex Finish,<br />

A6-100 Series<br />

1.3 79 1 Coat: WoodScapes Polyurethane<br />

Stain A15T5<br />

1.3-<br />

2.6<br />


Surface Sheen 1st Coat<br />

INTERIOR PAINTING SCHEDULE<br />

DFT<br />

(mils)<br />

(per<br />

coat)<br />

VOC<br />

(g/l)<br />

2nd and 3rd Coats<br />

DFT<br />

(mils)<br />

(per<br />

coat)<br />

VOC<br />

(g/l)<br />

Ferrous<br />

Metal<br />

(Except as<br />

otherwise<br />

scheduled)<br />

Ferrous<br />

Metal<br />

(Except as<br />

otherwise<br />

specified)<br />

Ferrous<br />

Metal<br />

(Dryfall<br />

system over<br />

shop primed<br />

steel -<br />

overhead<br />

structure)<br />

Ferrous<br />

Metal<br />

(Dryfall<br />

system over<br />

unprimed<br />

steel -<br />

overhead<br />

structure)<br />

Ferrous<br />

Metal<br />

(Columns<br />

and Hollow<br />

Metal Door<br />

Frames as<br />

shown on<br />

Drawings to<br />

receive<br />

epoxy)<br />

Galvanized<br />

Metal<br />

(Exposed<br />

Ductwork)<br />

Galvanized<br />

Metal<br />

(freezer /<br />

cooler<br />

panels)<br />

Concrete<br />

Walls<br />

Concrete<br />

Walls<br />

Gloss<br />

Semigloss<br />

Eggshell<br />

Eggshell<br />

Semigloss<br />

Eggshell<br />

Eggsh<br />

ell<br />

Gloss<br />

Eggshell<br />

Pro Industrial ProCryl Universal<br />

Primer B66-310<br />

ProCryl Universal Primer B66-<br />

310<br />

Waterborne Acrylic Dryfall, B42<br />

Series<br />

Touch up prime welds, bare spots,<br />

blemishes, and scratches with Pro<br />

Industrial ProCryl Universal<br />

Primer B66-310<br />

Pro Industrial ProCryl Universal<br />

Primer B66-310<br />

All states except CA: Epolon II<br />

Rust Inhibitive Epoxy Primer<br />

B67W400, B67A400, B67A400<br />

State of CA: Macropoxy 646-<br />

100, B58W620, B58V620<br />

Pro Industrial ProCryl Universal<br />

Primer B66-310<br />

Pro Industrial ProCryl Universal<br />

Primer B66-310<br />

Loxon Concrete and Masonry<br />

Primer, B28W8300<br />

Loxon Concrete and Masonry<br />

Primer, B28W8300<br />

2 100 All States except CA:<br />

2 Coats: Pro Mar 200 Interior Latex<br />

Gloss Enamel, B21W200<br />

State of CA:<br />

2 Coats: Solo Gloss Low VOC<br />

Enamel, B21WJ Series<br />

2 100 2 coats Pro Green 200 Interior Latex<br />

Semi-Gloss Enamel, B31-600 Series<br />

4.5 58<br />

2 100 1 coat: Waterborne Acrylic Dryfall,<br />

B42 Series<br />

4.0<br />

5.0-<br />

10.0<br />

300<br />


Surface Sheen 1st Coat<br />

INTERIOR PAINTING SCHEDULE<br />

DFT<br />

(mils)<br />

(per<br />

coat)<br />

VOC<br />

(g/l)<br />

2nd and 3rd Coats<br />

DFT<br />

(mils)<br />

(per<br />

coat)<br />

VOC<br />

(g/l)<br />

Concrete<br />

Masonry<br />

Unit<br />

Concrete<br />

Masonry<br />

Unit<br />

Gypsum<br />

Board<br />

Gypsum<br />

Board<br />

Gypsum<br />

Board<br />

Wood<br />

Wood<br />

(Exposed<br />

laminated<br />

wood roof<br />

structure)<br />

Wood<br />

(Transparent<br />

sealer)<br />

Concrete<br />

Floors<br />

Gloss PrepRite Block Filler, B25W25 8.0 45 All States except CA:<br />

2 Coats: Pro Mar 200 Interior Latex<br />

Gloss Enamel, B21W200<br />

State of CA:<br />

2 Coats: Solo Gloss Low VOC<br />

Enamel, B21WJ Series<br />

Eggsh<br />

ell<br />

Gloss<br />

PrepRite Block Filler, B25W25 8.0 45 2 Coats: Pro Green 200 Interior Latex<br />

Eggshell Enamel, B20-600 Series<br />

Pro Green 200 Latex Primer,<br />

B28W600<br />

Pro Green 200 Latex Primer,<br />

B28W600<br />

Pro Green 200 Latex Primer,<br />

B28W600<br />

Pro Green 200 Latex Primer,<br />

B28W600<br />

PrepRite ProBlock<br />

Interior/Exterior Latex Primer<br />

Sealer B51 Series<br />

Wood Classics Varnish Sanding<br />

Sealer, B26V43<br />

Macropoxy 646-100, B58W620,<br />

B58V620<br />

1.5 43 All States except CA<br />

2 Coats: Pro Mar 200 Interior Latex<br />

Gloss Enamel, B21W200<br />

State of CA:<br />

2 Coats: Solo Gloss Low VOC<br />

Enamel, B21WJ Series<br />

1.5 43 2 Coats: Pro Green 200 Interior Latex<br />

Semi-Gloss Enamel, B31-600 Series<br />

1.5 43 2 Coats: Pro Green 200 Interior Latex<br />

Eggshell Enamel, B20-600 Series<br />

1.5 43 2 Coats: Pro Green 200 Interior Latex<br />

Semi-Gloss Enamel, B31-600 Series<br />

1.4 97 2 Coats: Pro Green 200 Interior Latex<br />

Semi-Gloss Enamel, B31-600 Series<br />

1.2 522<br />

Semigloss<br />

Eggshell<br />

Semigloss<br />

Semigloss<br />

Semigloss<br />

5.0-<br />

10.0<br />


3.13 OWNER FURNISHED COATINGS QUANTITY SCHEDULE<br />

Sherwin Williams<br />

Coating Product Number<br />

EXTERIOR<br />

END OF SECTION<br />

Product Description<br />

Gallons Provided by<br />

Owner<br />

B42W46 Heavy Duty Block Filler 746<br />

OR<br />

A24-W200 Loxon Block Surfacer (Below 50 F)<br />

A5-400 Conflex XL High Build Elastomeric 813<br />

OR<br />

B46 Series UltraCrete Solvent Borne Masonry Coating (Below 50 F)<br />

Sherwin Williams<br />

Coating Product Number<br />

INTERIOR<br />

Product Description<br />

Gallons Provided by<br />

Owner<br />

B20-600 Pro Green 200 Interior Latex Eggshell Enamel, 165<br />

B21W200 Pro Mar 200 Interior Latex Gloss Enamel<br />

30<br />

B21WJ Series<br />

OR<br />

Solo Gloss Low VOC Enamel (for California only)<br />

B28W600 Pro Green 200 Latex Primer 60<br />

B31-600 Pro Green 200 Interior Latex Semi-Gloss Enamel 20<br />

B42 Series Waterborne Acrylic Dryfall 1200<br />

09900 - 15<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


BLANK PAGE<br />

09900 - 16<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


Application for Limited Warranty<br />

(Elastomeric Coatings)<br />

(To be completed by paint contractor)<br />

Wal-Mart Supercenter____Sam’s Club_____ Market_____Store #________Prototype __________<br />

Store Address:<br />

City___________________________State____________________ Zip__________________________________________<br />

Paint Contractor<br />

Paint Contractor’s Address<br />

City____________________________State___________________________________Zip__________________________<br />

Phone No.________________________Fax No.<br />

Paint Contractor Contact<br />

General Contractor<br />

General Contractor Contact___________________________________________Job Site Phone ______________________<br />

SURFACE PREPARATION: (Completed by Manufacturer & applicator prior to coating)<br />

Substrate construction (Concrete Block, Tilt-up Concrete, Metal)<br />

Date job started________________________________Weather conditions<br />

Did another contractor clean the substrate? Yes____No_____Explain<br />

Was substrate in acceptable condition prior to your coating application? Yes_____ No_____<br />

If no, attach documentation with explanation.<br />

Were all surfaces approved for application of coating?___________________________________<br />

(Painting contractor) Date<br />

___________________________________<br />

(Manufacturer) Date<br />

PRIMER/BLOCK FILLER<br />

List product used______________________________Manufacturer<br />

Total square feet (wall)_________________________Gallons used<br />

Date completed_______________________________Applicator’s initials<br />

WATERPROOF COATING SYSTEM:<br />

Coating system______________________________Manufacturer<br />

Manufacturer’s representative________________________________________Phone No.<br />

Purchased from______________________________Address<br />

City_______________________________________State<br />

Phone No.__________________________________Contact<br />

09900 - 17<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


APPLICATION:<br />

Number of finish coats________________________Procedure (Spray/back roll, etc.)<br />

Note mils Dry Film Thickness (DFT) required per each coat of finish.<br />

Date application started_______________________Weather conditions<br />

List wall surface area in square footage (per each color):<br />

Color:_____________________________________ square feet:<br />

Color:_____________________________________ square feet:<br />

Color:_____________________________________ square feet:<br />

Total gallons applied (per each color):<br />

Color:_____________________________________ gallons:<br />

Color:_____________________________________ gallons:<br />

Color:_____________________________________ gallons:<br />

Accent stripes:<br />

Color:_____________________________________ square feet:_________________gallons:<br />

Color:_____________________________________ square feet:_________________gallons:<br />

Applicator acknowledges completion of work related to the surface preparation and application of the elastomeric coating<br />

system.<br />

Date job completed:___________________________Applicators Signature:<br />

This Application for Limited Warranty will not be accepted unless complete information is provided. Any deceptive<br />

information contained in this application for Limited Warranty is grounds for voiding the Limited Warranty.<br />

Upon completion of this application form, submit to the corporate office of the coating system manufacturer for processing.<br />

When approved, the manufacturer will submit a 10-year (5-year for recoating of previously painted surfaces) Limited<br />

Warranty Certificate to be included in the closeout documents specified in Specifications Section 01770.<br />

END OF FORM<br />

09900 - 18<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072210<br />

SECTION 09965 – GRAFFITI-RESISTANT COATINGS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Permanent anti-graffiti coating system.<br />

B. Related Sections:<br />

1. Section 07190 - Water Repellents: Clear water repellent coating for application on unpainted masonry or<br />

concrete surfaces.<br />

2. Section 09900 - Paints and Coatings: Paint of surfaces on which graffiti coatings are applied.<br />

1.2 QUALITY ASSURANCE<br />

A. Contractor Qualifications: Installer shall be a firm with not less than three years of successful experience in<br />

application of coatings of type required on substrates similar to those of this project. The firm shall be approved<br />

by the manufacturer of the coating for installation of their product.<br />

B. Manufacturer's representative shall inspect substrate conditions including alkalinity and moisture content. Obtain<br />

written approval from representative before proceeding with work.<br />

1.3 SUBMITTALS<br />

A. Submit in accordance with Section 01330.<br />

B. Instructions: Provide instructions bearing manufacturer's name, coating type, and recommended installation<br />

procedures. Provide methods and material instruction for graffiti removal. Include adhesive-backed graffiti<br />

removal instruction label suitable for application to interior surface.<br />

C. Submit proof of purchase (Invoice of materials purchased) and proof of delivery of coating materials.<br />

D. Manufacturer’s Warranty: Submit one copy of manufacturer's warranty for specified materials.<br />

E. Field Sample: Apply graffiti resistant coating to field mock-up sample representing exterior wall surface to be<br />

coated. Apply coating system over a minimum 3 ft x 3 ft test area and test removal of applied spray paint in<br />

presence of Construction Manager for approval using removal methods recommended by the manufacturer.<br />

1. Obtain Wal-Mart Construction Manager inspection and approval of sample panel.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Section 01600 - Product Requirements: Transport, handle, store, and protect products.<br />

B. Paint orders to the manufacturer or supplier shall identify the store number, location, and address of project.<br />

Contractor shall require a record keeping account be established and maintained by the paint supplier which<br />

records graffiti resistant paint type, brand, and quantity purchased, for the specific project.<br />

C. Deliver coating materials in sealed original labeled containers, bearing manufacturer's name, type of paint, brand<br />

name, lot number, brand code, coverage, surface preparation, drying time, cleanup requirements, color<br />

designation, and instructions for mixing and/or reducing.<br />

D. Store materials at minimum ambient temperature of 45 degrees F and a maximum of 90 degrees F in ventilated<br />

area and as required by manufacturer's instructions.<br />

09965 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


E. Prevent fire hazards and spontaneous combustion.<br />

1.5 WARRANTY<br />

A. Provide manufacturers written warranty guaranteeing effective graffiti removal for not less than 10 years and<br />

warrant that treated surfaces can be effectively and repeatedly cleaned of graffiti without damage or loss of<br />

effectiveness of the graffiti resistant coating. Manufacturer shall, for the duration of the warranty period,<br />

guarantee replacement of product and labor to remove graffiti and replace graffiti resistant coating where graffiti<br />

removal has shown to be ineffective.<br />

1.6 PROJECT CONDITIONS<br />

A. Environmental Requirements: Follow manufacturer's recommendations for temperature range in which coating<br />

may be applied.<br />

PART 2 - PRODUCTS<br />

2.1 GRAFFITI RESISTANT COATING<br />

A. Graffiti resistant coating shall be a clear, non-sacrificial graffiti resistant coating which provides protection for<br />

exterior vertical surfaces from permanent graffiti staining and damage caused by spray paint and marking pens.<br />

Coating shall be suitable for application to painted and unpainted surfaces including masonry, concrete, metals,<br />

and EIFS. Product shall be of type such that recoating with the underlying paint is possible without removal of the<br />

graffiti resistant coating. Product shall be a coating that dries clear, non-yellowing, with a low luster.<br />

1. Manufacturer:<br />

a. VandlGuard Non-Sacrificial Graffiti Coating by Rainguard International Products Company,<br />

Corona del Mar, CA, (949) 675-2811.<br />

2. Substitutions: Not permitted.<br />

B. Water Repellent (For first coat on unpainted concrete and masonry surfaces): As specified in Section 07190.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify all surfaces are ready to receive coating in accordance with manufacturer’s printed requirements.<br />

Beginning of installation indicates acceptance of substrate.<br />

B. Unpainted Concrete and Masonry: Verify water repellent has been applied in accordance with Section 07190 to<br />

new or non-painted concrete and masonry surfaces prior to the application of the anti-graffiti coating.<br />

3.2 PREPARATION<br />

A. Surface shall be free of dirt, dust, contaminants such as curing compounds, hardeners, bond breakers, and form<br />

release. Allow painted surfaces to cure properly. Do not water blast painted surfaces. Assure surfaces are clean<br />

and dry.<br />

B. Mask or otherwise protect adjacent surfaces not scheduled to receive coating. If applied on unscheduled surfaces<br />

such as glass, remove immediately, by approved method.<br />

C. Protect landscaping, property, and vehicles from over spray and drift.<br />

3.3 APPLICATION<br />

A. Apply coating in accordance with manufacturer's published instructions.<br />

B. Application Rate: Apply each coat at the manufacturers published application rate.<br />

09965 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.4 SURFACES TO BE COATED<br />

A. Apply graffiti resistant coating to all exterior exposed building surfaces visible from the ground level, including<br />

concrete, masonry, metal doors and frames, sheet metal items, downspouts, EIFS, stucco, wood, painted metal<br />

bollards, pneumatic tubing, and metal railing. Apply coating to painted and unpainted surfaces. Exclude<br />

horizontal surfaces subject to wheel or foot traffic.<br />

B. Apply to exterior non-building vertical surfaces including solid or semi-solid fencing, segmental block or concrete<br />

panel retaining walls, and masonry screening as applicable.<br />

C. On building surfaces, apply coating system to first definitive continuous horizontal demarcation including change<br />

in paint color or surface material but not less than 12 feet above finish grade. Apply to full height of exterior<br />

overhead or coiling door surfaces. Apply to top of building if no definitive continuous horizontal demarcation<br />

lines exist. Exclude wall and door surfaces behind fenced enclosures such as Garden Center, Battery Storage, or<br />

Compressor House Enclosure.<br />

3.5 MAINTENANCE<br />

A. Apply cleaning instructions label to interior wall location as directed by the Construction Manager.<br />

3.6 FIELD QUALITY CONTROL<br />

A. Verify application rate by periodic on-site inspection and calculation of area covered compared to consumption of<br />

coating material used. Document inspections showing total area covered and number and volume of coating<br />

containers used.<br />

END OF SECTION<br />

09965 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 123010<br />

SECTION 10160 (10 2113.13) – METAL TOILET COMPARTMENTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Stainless steel toilet compartments and screens, floor mounted, head rail braced.<br />

B. Related Requirements:<br />

1. Section 06100 - Rough Carpentry: Framing and plates within walls.<br />

2. Section 10810 - Toilet Accessories: Coordinate compartment installation with subsequent accessory<br />

installation.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Subject to compliance with project requirements, provide stainless steel toilet compartments and screens, as<br />

manufactured by the following:<br />

1. Mills Partitions (a subsidiary of Bradley).<br />

2. Accurate Partitions Corp.<br />

3. Flush Metal Partition Corp.<br />

4. Global Steel Products, Deer Park, NY.<br />

B. Products of named manufacturers shall strictly comply with all material and fabrication provisions specified<br />

below.<br />

2.2 PRODUCT PROCUREMENT<br />

A. Products specified herein shall be direct purchased by the General Contractor from a pre-negotiated supplier.<br />

Reference Section 01600 for additional information regarding Direct Purchase Products. Pre-negotiated supplier<br />

shall be as follows:<br />

1. Haines, Jones & Cadbury, Inc. Contact: Customer Service, (800) 459-7099, Fax (479) 756-8998, Email<br />

info@hjcinc.com.<br />

2.3 METAL TOILET PARTITIONS<br />

A. Stainless Steel Compartments and Screens: Provide one of the following:<br />

1. Model:<br />

a. Sentinel Overhead Braced, Series 400 by Mills.<br />

b. Stainless Steel by Accurate Partitions.<br />

c. Stainless Steel by Flush Metal.<br />

d. Stainless Steel by Global Steel Products.<br />

2. Panels: Form panels as two-piece interlocking unit with corners brazed and finished smooth. Panel face<br />

shall be stainless steel 304, insulated honeycomb core adhered to inner surfaces with moisture resistant<br />

adhesive.<br />

a. Side Panels and Doors: 22 gauge sheet steel, 1 inch thick composite panel.<br />

b. Pilasters: Min. 22 gauge sheet steel, 1-1/4 inch thick composite panel.<br />

3. Finish: Textured "diamond" pattern similar to Rigidized 5WL. Pattern in panels shall be without seams.<br />

B. Urinal Screens: Wall hung type, 24 inches by 48 inches to match toilet compartments.<br />

C. Pilaster Shoes: 3 inches high; one-piece stainless steel.<br />

10160 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Headrail: Extruded clear anodized type 6463T5 aluminum channel; anti-grip design.<br />

E. Wall and Side Panel Mounting Brackets: 18 gauge stainless steel #4 finish. Brackets shall be one piece<br />

continuous roll-formed shape, pre-punched and free of sharp edges. Resistance and/or spot welded brackets will<br />

not be acceptable.<br />

F. Join panel and pilaster with full length continuous stainless steel bracket to eliminate sight between stalls.<br />

G. Hardware:<br />

1. Hinge: Cast stainless steel, wrap-around and through-bolted.<br />

2. Latch: Cast stainless steel service mounted slide latch, thru-bolted. Strike keeper shall be wrap-around<br />

type, thru-bolted.<br />

3. Coat Hook and Wall Bumper: Cast stainless steel with rubber bumper.<br />

4. Pull Handle: Cast stainless steel, through-bolted to door.<br />

H. Screws/Fasteners: Tamper proof, stainless steel, 6-lobe/pin sex bolts.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Take site dimensions. Verify correct spacing of plumbing fixtures.<br />

B. Verify correct location of built-in framing, anchorage, and bracing.<br />

3.2 INSTALLATION<br />

A. Install partitions secure, rigid, plumb, level, and square. Secure units in position with manufacturer’s<br />

recommended anchoring devices and in accordance with manufacturer's instructions.<br />

1. Provide for adjustment due to minor floor variations.<br />

2. Install adjacent components for consistency of line and plane.<br />

B. Maintain 1/2 inch space between wall and panels, and between wall and pilasters.<br />

C. Attach panels and pilasters to bracket with through sleeve, tamperproof bolts, and nuts. Locate head rail joints at<br />

pilaster centerlines.<br />

D. Anchor urinal screen panels to walls with brackets in accordance with manufacturer's instructions to suit<br />

supporting wall construction.<br />

E. Attach panel brackets securely to walls using anchor devices.<br />

F. Conceal floor fastenings with pilaster shoes.<br />

G. Equip each door with hinges, one door latch and one coat hook and bumper. Align hardware to uniform clearance<br />

at vertical edges of doors, not exceeding 1/4 inch.<br />

H. Install pull handles on both sides of toilet partition doors for handicapped and ambulatory stalls.<br />

3.3 ADJUSTING<br />

A. In-Swinging Doors: Adjust hinges to hold doors in partially open position when unlatched.<br />

B. Out-Swinging Doors: Adjust hinges to gently return doors to closed position.<br />

10160 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.4 CLEANING<br />

A. Remove protective plastic coating from stainless steel partitions. Remove any residue from the plastic coating<br />

with mild soap and water.<br />

B. Muriatic acid or other caustic chemicals shall not be used to clean stainless steel products. Muriatic acid for<br />

cleaning masonry or similar hydrochloric acid type cleaners must immediately be neutralized and scrubbed off<br />

with clean water if splashed, sprayed, spilled or otherwise in contact with a stainless steel component.<br />

C. Immediately prior to possession by Owner, clean stainless steel toilet compartments and screens thoroughly using<br />

soap, ammonia, or mild detergent and water. Apply with sponge or soft cloth, rinse with clear water and wipe dry.<br />

Always rub in the direction of polish lines. Rinse thoroughly with fresh water after every cleaning operation.<br />

Clean and polish toilet partitions to a spotless luster. Wipe dry to avoid water marks.<br />

END OF SECTION<br />

10160 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


P + R LIBRARY 11/15/10<br />

SECTION 10240 – EQUIPMENT SCREENS<br />

PART 1 - GENERAL<br />

1.01 SUMMARY<br />

A. Provide Equipment Screens as shown on drawings and as specified, complete. Include without limitation:<br />

1. Pre-formed thermoplastic panel for enclosing roof top mechanical equipment.<br />

2. Aluminum weldement framing for direct attachment of screening panels to mechanical equipment.<br />

a. No base or curb required unless shown otherwise on Drawings.<br />

3. Aluminum extrusions for easy access to mechanical equipment for servicing.<br />

B. Products Not Installed or Furnished in This Section:<br />

1. Field painting of prime painted screens.<br />

2. Touch-up painting required for scratches and screw heads.<br />

C. Related Work specified elsewhere includes without limitation:<br />

1. Section 01330 - Submittal Procedures.<br />

2. Section 07721 - Manufactured Curbs.<br />

3. Section 09900 - Paints and Coatings.<br />

4. Section 15700 - Heating, Ventilating, And Air Conditioning Equipment.<br />

1.2 REFERENCES<br />

A. ASTM International (ASTM):<br />

1. ASTM B 221 - Aluminum and Aluminum Alloy Extruded Bars, Rods, Wire Profiles, and Tubes.<br />

B. The Aluminum Association, Inc:<br />

1. AA ADM-1516166 - Aluminum Design Manual.<br />

C. American Society of Civil Engineers (ASCE):<br />

1. Minimum Design Loads for Buildings and Other Structures, latest edition.<br />

1.3 QUALITY ASSURANCE<br />

A. Regulatory Requirements: Comply with requirements of building Authorities having jurisdiction in Project location.<br />

B. Manufacturer Qualifications: Minimum five (5) years documented experience producing systems specified in this<br />

section.<br />

C. Installer Qualifications: The system installer shall be certified by the system manufacturer as an "Approved<br />

Installer."<br />

D. Pre-Installation Meeting:<br />

1. Convene at job site seven (7) calendar days prior to scheduled beginning of construction activities of this<br />

section to review requirements of this section.<br />

2. Require attendance by representatives of the installing subcontractor, (who will represent the system<br />

manufacturer) and other entities directly affecting, or affected by, construction activities of this section.<br />

3. Notify Architect four (4) calendar days in advance of scheduled meeting date.<br />

10240 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


1.4 SYSTEM DESCRIPTION<br />

A. Design Criteria:<br />

1. Manufacturer is responsible for the structural design of all materials, assembly and attachments to resist snow,<br />

wind, suction and uplift loading at any point without damage or permanent set.<br />

a. Framing shall be designed in accordance with the Aluminum Design Manual, ASCE.<br />

1.5 SUBMITTALS<br />

A. Product Data: Submit manufacturer's catalog data, detail sheets, specification and other data sufficient to indicate<br />

compliance with these Specifications. Refer to Section 01330 for requirements.<br />

B. Shop Drawings: Indicate layouts heights, component connection details, and details of interface with adjacent<br />

construction. Mark data to indicate:<br />

1. Rooftop mechanical equipment to be enclosed.<br />

C. Samples:<br />

1. Samples of Materials: Thermoplastic panels.<br />

2. Color: To match roof color, U.N.O.<br />

D. Certification: Manufacturer's Certificate of Compliance certifying that thermoplastic panels supplied meet or exceed<br />

requirements specified.<br />

E. Closeout Submittals: Warranty documents, issued and executed by manufacturer, countersigned by Contractor.<br />

Refer to Section 01770 for Closeout requirements.<br />

1.6 DELIVERY, STORAGE AND HANDLING<br />

A. Delivery: Deliver materials to site in manufacturer's original, unopened containers and packaging, with labels clearly<br />

indicating manufacturer and material.<br />

B. Storage and Handling: Protect materials and finishes during handling and installation to prevent damage.<br />

1.7 PROJECT CONDITIONS<br />

A. Field Measurements: Take measurements in field, of actual rooftop units for fit without gaps. Indicate measurements<br />

on shop drawings fully documenting any field condition that may interfere with the screen system installation.<br />

1.8 COORDINATION<br />

A. Installer for work under this Section shall be responsible for coordination of panel and framing sizes and required<br />

options which the Mechanical Contractor's requirements.<br />

1. Request information on sizes and options required from the Mechanical Contractor.<br />

B. Submit shop drawings to the Mechanical Contractor and obtain written approval of shop drawings from the<br />

Mechanical Contractor, prior to fabrication.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURER<br />

A. Acceptable Products: "Envisor Screening System" by CityScapes, Inc., 4200 Lyman Court, Hilliard, OH 43026,<br />

(877) SCREENS / 727-3367 http://www.cityscapesinc.com<br />

B. No Substitutions.<br />

10240 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 MATERIALS<br />

A. Thermoplastic Panels: Fabricated from rigid medium impact therm-formed ABS (Acrylic Butylene Styrene) sheets.<br />

1. Minimum thickness: 3/16".<br />

B. Framing: Aluminum Plate, Shapes and Bar: ASTM B 221, alloy 6061-T5 or 6063-T5.<br />

C. Threaded Fasteners: All screws, bolts, nut and washers shall be Zinc Coated.<br />

1. Weldement fasteners shall be #10-16 x zinc TEK screws. Length shall be as required to develop full holding<br />

capacity of screw when fastened to Mechanical Equipment.<br />

2. Provide lock washer or other locking device at all bolted connections.<br />

2.3 FABRICATION<br />

A. Provide factory-formed panel systems with continuous interlocking panel connections and indicated or necessary<br />

components: Form all components true to shape, accurate in size, square and free from distortion or defects. Cut<br />

panels to precise lengths indicated on approved shop drawings.<br />

1. Panel Configuration: Unless otherwise shown on Drawings, provide as follows:<br />

a. Embossed ribs.<br />

b. Texture: Haircell.<br />

2. Provide special shaped corner panels at corners.<br />

3. Provide notched panels where required for flues.<br />

B. Trim and Closures: Fabricated from 24 gauge metal, manufacturer’s standard coating system finish.<br />

1. Provide top trim as indicated.<br />

C. Framing: Fabricate and assemble components in largest practical sizes, for delivery to the Site.<br />

1. Construct corner frames to required shape with joints tightly fitted and welded.<br />

2. Supply components required for anchorage of framing. Fabricate anchors and related components of material<br />

and finish as required, or as specifically noted.<br />

2.4 FINISHES<br />

A. Aluminum Framing: Mill.<br />

B. Panel Coating: Manufacturer's standard coating system, factory-applied.<br />

C. Color: As selected from manufacturer’s standard. Match roof color unless noted otherwise on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examination: Examine conditions under which construction activities of this section are to be performed.<br />

B. Submit written notification to Architect and Screen manufacturer if such conditions are unacceptable.<br />

C. Beginning of installation indicates acceptance of substrate and existing conditions.<br />

3.2 INSTALLATION<br />

A. Install units in accordance with the manufacturer's instructions and approved shop drawings. Keep perimeter lines<br />

straight, plumb, and level. Provide brackets, anchors, and accessories necessary for a complete installation.<br />

B. Fasten structural supports to HVAC units without damaging operation of the unit.<br />

1. Provide corner and mid-span weldements as required by approved shop drawings so that the panels are<br />

supported uniformly.<br />

10240 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2. Fasten bottom rail using quick release pins to permit ease of access to HVAC units.<br />

C. Insert thermoplastic panels into structural supports, except where fixed attachment points are indicated. Butt<br />

thermoplastic panels to adjacent panels for uniform fit. Fasten fixed panels in accordance with the shop drawings.<br />

D. Metal Separation: Where aluminum materials would contact dissimilar materials, apply a coat of bituminous paint,<br />

concealed, on one or both surfaces where dissimilar metals would otherwise be in contact.<br />

E. Do not cut or abrade finishes, which cannot be restored. Return items with such finishes to shop for required<br />

alterations.<br />

3.3 ERECTION TOLERANCES<br />

A. Maximum misalignment from true position: 1/4".<br />

3.4 CLEANING AND PROTECTION<br />

A. Remove all protective masking from material immediately after installation.<br />

B. Protection:<br />

1. Ensure that finishes and structure of installed systems are not damaged by subsequent construction activities.<br />

2. If minor damage to finishes occurs, repair damage in accordance with manufacturer's recommendations;<br />

provide replacement components if repaired finishes are unacceptable to Architect.<br />

C. Prior to Substantial Completion: Remove dust or other foreign matter from component surfaces; clean finishes in<br />

accordance with manufacturer's instructions.<br />

D. Clean units in accordance with the manufacturer's instructions.<br />

END OF SECTION<br />

10240 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 093011<br />

SECTION 10260 (10 2601) – WALL AND CORNER GUARDS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Surface applied corner guards.<br />

2. Wall guards.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products, and Architectural Drawings: Walmart furnished and installed<br />

refrigerated case corner protection (stainless steel angle corner guards).<br />

2. Section 09310 - Ceramic Tile: Integrally installed stainless steel corner trim associated with ceramic wall<br />

tile.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURER<br />

A. Provide guards by one of the following manufacturers as specified:<br />

1. American Floor Products Co., Inc. (800) 342-0424.<br />

2. InPro Corporation, Muskego, WI (262) 679-9010.<br />

3. IPC Door and Wall Protection Systems (800) 222-5556.<br />

4. Parkland Plastics Incorporated, Middlebury, IN (574) 825-4336.<br />

5. Pawling Corporation (800) 431-3456, Contact Jennifer Killmer.<br />

6. Schluter Systems, Plattsburgh, NY (800) 472-4588.<br />

2.2 CORNER GUARDS<br />

A. Plastic:<br />

1. Clear Plastic:<br />

a. Space (CG-2145) Corner Guard, clear, 1/8-inch thick, 2-1/2 x 2-1/2 inches x 48 inches, by<br />

American Floor.<br />

b. Clear Polycarbonate Corner Guards (CGT-18), 2-1/2 inches x 2-1/2 inches x 48 inches, by Pawling.<br />

2. Rigid Plastic:<br />

a. Rigid Plastic Corner Guard, 1/2-inch thick, 3 x 3 inches x 32 inches, unless otherwise shown, color<br />

black, by Parkland Plastics.<br />

b. Fasteners: Galvanized flathead countersunk screws, length sufficient to penetrate substrate.<br />

B. Stainless Steel: 16 gage, 1-1/2 x 1-1/2 inches, unless otherwise shown.<br />

1. ECK-K by Schluter.<br />

2. Lunar CG-2143, Style L-1, by American Floor.<br />

3. CG-51 by Pawling.<br />

4. S181124C-304 by InPro.<br />

5. Adhesive:<br />

a. KURDI-fix by Schluter.<br />

b. ADH-50 Adhesive by Pawling.<br />

c. Equivalent by other manufacturers or as recommended by the corner guard manufacturer.<br />

d. Adhesive VOC shall be not greater than 80 g/L as set forth in the California South Coast Air Quality<br />

Management District (SCAQMD) Rule No.1168.<br />

C. Angle Steel Corner Guards: Angle steel corner guards applied to plywood wainscot shall be ASTM A36 structural<br />

steel angle, size as shown on Drawings.<br />

10260 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.3 WALL GUARDS<br />

A. Plastic Wall Guard (Pharmacy): Vinyl bumper on continuous aluminum retainer, 3” high x 12 ft long section x 1”<br />

projection, lightly pebbled or matte finish, color black or gray as shown on the drawings. Provide one of the<br />

following:<br />

1. WG-3 Wall Guard by Pawling.<br />

a. Black: No. 1 Black.<br />

b. Gray: No 210 Silver Gray.<br />

2. 500 Wall Guard by IPC.<br />

a. Black: No 0152 Black.<br />

b. Gray: No. 0105 Silver.<br />

B. Accessories: End caps, outside corners, brackets, and fasteners, as recommended by wall guard manufacturer.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine substrates and wall areas, with installer present, for compliance with requirements for installation<br />

tolerances and other conditions affecting performance of work.<br />

1. Examine walls to which wall guards will be attached for blocking, grounds, and other solid backing that<br />

have been installed in the locations required for secure attachment of support fasteners.<br />

2. Proceed with installation only after unsatisfactory conditions have been corrected.<br />

3.2 PREPARATION<br />

A. Before installation, clean substrate to remove dust, debris, and loose particles.<br />

3.3 INSTALLATION<br />

A. Install in accordance with manufacturer's instructions, square and plumb, secured rigidly in position.<br />

B. Position corner guard 4 inches above finished floor. Coordinate installation of resilient base and painting with<br />

corner guard installation.<br />

C. Plastic:<br />

1. Attach clear plastic corner guards by methods recommended by the manufacturer for the surface applied.<br />

2. Attach rigid plastic corner guards with countersunk screw fasteners at 6 inches on center. Fill countersunk<br />

holes with plugs matching rigid plastic material.<br />

D. Attach stainless steel corner guards starting at top of base, unless otherwise shown, and set tight to wall with<br />

mastic adhesive.<br />

3.4 SCHEDULE<br />

A. Corner Guards:<br />

1. Locate clear plastic corner guards in sales areas accessible by public at unprotected corners of gypsum<br />

board, plastic laminate, and wallcovering and at other locations as shown on the drawings, unless otherwise<br />

indicated or specified to receive other type of corner guards.<br />

2. Locate rigid plastic corner guards at millwork at locations shown on Drawings.<br />

3. Locate stainless steel corner guards where shown on Drawings.<br />

4. Locate angle steel corner guards where shown on Drawings.<br />

B. Wall Guards: Locate wall guards where shown on Drawings.<br />

END OF SECTION<br />

10260 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II - NP 012910<br />

SECTION 10293 (10 8113) – BIRD CONTROL DEVICES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Stainless steel bird barrier spikes.<br />

1.2 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and in<br />

accordance with manufacturer’s published requirements.<br />

PART 2 - PRODUCTS<br />

2.1 BIRD BARRIER SPIKES<br />

A. Nixalite Premium Model Bird Barrier Strip: Stainless steel wire and strip barrier by Nixalite of America Inc., East<br />

Moline, IL, (888) 212-8682, info@abcbirdcontrol.com<br />

1. Wires: High grade stainless steel, 0.041 inch diameter, full-hard spring temper, 250,000 lbs/in tensile<br />

strength.<br />

2. Base Strip: High grade stainless steel, 0.25 inches wide x 0.02 inches thick, full anneal.<br />

3. Strip Lengths: 24 or 48 inches.<br />

4. Model S: 4 inches high, 4 inches wide, no less than 120 wire points per foot. Full 180-degree wire<br />

coverage.<br />

5. Model H: 4 inches high, 2 inches wide, no less than 60 wire points per foot, 90 degree wire coverage. For<br />

use on surfaces less than 2 inches in depth and for use with Model S as required to achieve full coverage.<br />

6. Finish: Natural stainless steel finish.<br />

2.2 ACCESSORIES<br />

A. Mounting Hardware: Manufacturer’s standard stainless steel mounting hardware as recommended and appropriate<br />

for the surface on which devices are applied. Provide all appurtenances required for a complete and proper<br />

installation.<br />

2.3 SUBSTITUTIONS<br />

A. Comply with the requirements of Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where bird control products will be installed and verify that surfaces conform<br />

to product manufacturer's requirements for substrate conditions. Do not proceed until unsatisfactory conditions<br />

have been corrected.<br />

3.2 INSTALLATION<br />

A. Install bird control devices in accordance with manufacturer’s instructions.<br />

B. Cut strips where necessary to fit the surface properly.<br />

C. Extend wires over outside edge of surface by at least 1/4 inch. Extend base strips over any open end of surface by<br />

at least 1/2 inch.<br />

10293 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Do not apply paint or coatings over the installed bird control devices or mounting hardware.<br />

END OF SECTION<br />

10293 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 033111<br />

SECTION 10350 (10 7500) – FLAGPOLES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Aluminum flagpoles.<br />

2. Flags.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. The Aluminum Association, Inc. (AA):<br />

1. AA DAF45 - Designation System for Aluminum Finishes.<br />

C. ASTM International (ASTM):<br />

1. ASTM B 221 - Aluminum And Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, And Tubes.<br />

2. ASTM B 917 - Standard Practice For Heat Treatment Of Aluminum-Alloy Castings From All Processes.<br />

D. National Association of Architectural Metal Manufacturers (NAAMM):<br />

1. NAAMM 1001 - Guide Specifications for Design of Metal Flagpoles Manual.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330. Submit required submittals within 30 days after contract award.<br />

B. Product Data: Submit manufacturer’s specific installation requirements (including preparation by other trades)<br />

and instructions for each type of flagpole specified. Include elevation and details showing installation, fittings and<br />

accessories, grounding, anchoring, and support systems necessary for each type of flagpole.<br />

1. Include details of foundation system for ground-set flagpoles.<br />

C. Structural Calculations: Show compliance with indicated wind design loads. Include analysis data for specific flag<br />

size, signed and sealed by a Professional Engineer registered in State in which the Project is located.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:<br />

1. American Flagpole, A Kearney-National, Inc. Company, Abingdon, VA (800) 368-7171.<br />

2. Concord Industries, Inc., Dallas, TX (800) 527-3902.<br />

3. Eder Flag Manufacturing Company, Oak Creek, WI (800) 558-6044.<br />

B. Substitutions: Comply with the requirements of Section 01600.<br />

10350 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 PERFORMANCE REQUIREMENTS<br />

A. Structural Performance: Provide flagpoles capable of withstanding the effects of wind loads determined according<br />

to NAAMM FP 1001.<br />

1. Flag Size: Design flagpole based upon 4 foot x 6 foot nylon flag.<br />

2. Basic Wind Speed: Design flagpole based on 85 mph minimum wind speed.<br />

2.3 FLAGPOLES<br />

A. Groundset Flagpoles: Provide cone tapered ground set flagpole fabricated from extruded aluminum tubing<br />

complying with ASTM B 221, Alloy 6063, with a minimum wall thickness of 5/32 inch. Heat treat after<br />

fabrication to comply with ASTM B 917, Temper T6.<br />

1. Length: 30 feet exposed. Overall length shall be as shown to include unexposed portion below ground.<br />

2. Mounting: Ground sleeve type.<br />

2.4 FITTINGS AND ACCESSORIES<br />

A. Finial Ball: Manufacturer's standard flush-seam ball, sized as indicated to match flagpole-butt diameter.<br />

1. Finish: Gold Anodized.<br />

B. External Halyard: Ball-bearing, non-fouling rotating or stationary truck assembly of cast metal with continuous<br />

5/16-inch-diameter, braided nylon halyard, ground hoisted.<br />

C. Cleats: Cast aluminum 9 inch min. with fasteners.<br />

1. Finish exposed metal surfaces to match flagpole.<br />

D. Halyard Flag Snaps: Provide two swivel snap hooks per halyard.<br />

E. Cleat Box: Aluminum box with cylinder lock. Provide 2 keys.<br />

F. Mounting Hardware:<br />

1. Provide ground sleeve assembly including sleeve, centering wedges, collar, ground rod, and other required<br />

accessories.<br />

2.5 FINISHES<br />

A. Natural Satin Finish: Provide fine, directional, medium satin polish (AA-M32); buff complying with AA-M20; in<br />

accordance with AA DAF45, and seal aluminum surfaces with clear, hard-coat wax.<br />

2.6 FLAGS<br />

A. Provide 4 ft. by 6 ft. nylon American flag with sewn stripes and embroidered stars.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine areas where flagpoles will be installed. Do not proceed with Work until unsatisfactory conditions have<br />

been corrected.<br />

3.2 INSTALLATION<br />

A. Install flagpoles where and as shown and according to manufacturer's written instructions.<br />

B. Install halyard and snaps leaving installation ready for use.<br />

C. Install cleat inside lockable cleat box as shown on drawings.<br />

10350 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.3 ADJUSTING AND CLEANING<br />

A. Clean flagpole surfaces immediately prior to installation.<br />

B. Adjust operating devices for smooth halyard and flag function.<br />

END OF SECTION<br />

10350 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 032709<br />

SECTION 10671 – PHARMACY RACKS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished, Contractor installed metal racks for pharmaceutical storage.<br />

B. Products Installed, But Not Furnished Under This Section:<br />

1. Under provisions of Section 01640, Wal-Mart will furnish Pharmacy Racks for installation by Contractor<br />

as described within this Section.<br />

C. Related Sections:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to products furnished by others.<br />

1.2 DELIVERY, STORAGE AND HANDLING<br />

A. Product Delivery: Racks will be delivered to jobsite for Contractor to receive on delivery date established by<br />

Contractor. To establish product delivery date, contact the following three weeks prior to desired delivery:<br />

Mary Hubble, Manager GIS & Supply Chain Fixture, Wal-Mart Store Planning Division<br />

(479) 277-1271.<br />

B. Product Packaging: Racks will be shipped unassembled. Manufacturer's published installation instructions for<br />

assembly and installation will be included in package.<br />

C. Acceptance at Site: Receive products as specified in Section 01640. Verify quantity of products furnished with<br />

Bill of Material provided with products. Report discrepancies in product quantity delivered or damage to products<br />

delivered to contact specified above. Upon notification by Contractor, arrangement will be made for delivery of<br />

replacement products. Note description of product quantity discrepancies and/or product damage on Bill of<br />

Lading.<br />

D. Section 01600 - Product Requirements: Transport, Handle, Store, and Protect products.<br />

1.3 SCHEDULING<br />

A. Schedule installation to prevent damage to racks by subsequent construction activities.<br />

PART 2 - PRODUCTS<br />

2.1 RACKS (WAL-MART FURNISHED, CONTRACTOR INSTALLED)<br />

A. Racks will be the manufacturer and product of one of the following. Contact Wal-Mart Store Planning to for<br />

determination of the specific manufacturer for this project. Contact the specific manufacturer for information<br />

regarding racks to be installed.<br />

1. L. A. Darling Company, Paragould, AR; Contact: Justin Sage, National Account Manager, (800) 682-5730<br />

or (479) 464-2832.<br />

2. Lozier Corporation, Omaha, NE; Contact: Bill Reznicek, National Account Manager, (479) 254-0834.<br />

3. Madix Store Fixtures, Nick Gibson, (479) 366-4965 ngibson@madixinc.com<br />

B. Accessories: Racks will be provided complete with all parts and hardware for a complete assembly and<br />

installation.<br />

10671 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed and verify that surfaces conform to product<br />

manufacturer's requirements for substrate conditions. Do not proceed until unsatisfactory conditions have been<br />

corrected.<br />

3.2 PREPARATION<br />

A. Prepare for product installation in accordance with manufacturer's published instructions.<br />

B. Vacuum clean surfaces free of loose particles.<br />

3.3 INSTALLATION<br />

A. Install racks at locations shown within Pharmacy.<br />

B. Install in accordance with manufacturer’s instructions.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect installation and attachment to floor.<br />

B. Correct deficiencies in Work which inspection indicates are not in compliance with Contract Documents.<br />

3.5 CLEANING AND PROTECTION<br />

A. Clean entire racks after erection is complete.<br />

END OF SECTION<br />

10671 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 103009<br />

SECTION 10672 (10 5627) – MOBILE STORAGE CARTS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Mobile plastic storage carts.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURED UNITS<br />

A. Mobile Plastic Storage Carts: Polyethylene cart Model 622 by Gilmore-Kramer Company, Providence, RI (800)<br />

544-3137.<br />

1. Capacity: 8 bushel (61 gallon).<br />

2. Dimensions: 34 L x 22 W x 23 D.<br />

3. Material: 1/4-inch molded polyethylene tub mounted on 1/4-inch plywood.<br />

4. Rollers: Four heavy duty casters.<br />

5. Color: Beige.<br />

B. Substitutes: Not permitted.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Place carts at locations at beneath Courtesy Desk as shown on the drawings.<br />

END OF SECTION<br />

10672 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 062510<br />

SECTION 10675 (10 5629) – MODULAR RACK AND FENCE SYSTEM<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Wal-Mart furnished Garden Center metal rack/fence system and accessories for installation by Contractor.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Wal-Mart furnished products.<br />

2. Section 02823 - Ornamental Metal Fences and Gates: Contractor furnished and installed ornamental fence<br />

and gates for Garden Center.<br />

3. Section 08110 - Steel Doors and Frames: Contractor furnished and installed steel doors and frames.<br />

C. Related Documents:<br />

1. Rack/Fence System Instruction Manual: Manual may be obtained for review purposes prior to construction<br />

by contacting the Wal-Mart Construction Purchasing Department identified below.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI MH16.1 - Specifications for the Design, Testing and Utilization of Industrial Steel Storage Racks.<br />

1.3 DEFINITIONS<br />

A. Rack/Fence Supplier: Manufacturer of products separately contracted by Wal-Mart.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Product Delivery: Rack/Fence Supplier will deliver products to jobsite for Contractor to receive on delivery date<br />

established by Contractor. To arrange product delivery, contact the following three months prior to anticipated<br />

installation: Wal-Mart Store Planning at (479) 277-2633 or (479) 204-0173.<br />

B. Installation Drawings and Instructions: Complete and comprehensive rack and fence system assembly, erection,<br />

and installation instructions will be delivered to Contractor with Wal-Mart furnished products.<br />

C. Product Packaging: Products will be packaged in manufacturer's standard cartons.<br />

D. Acceptance at Site: Receive, store and protect products as specified in Section 01640 and manufacturer’s<br />

recommendations.<br />

1. Verify quantity of products furnished with Bill of Material provided with Wal-Mart furnished products.<br />

2. Report discrepancies in product quantity delivered or damage to Wal-Mart Construction Division<br />

immediately.<br />

3. Upon notification by Contractor, Wal-Mart will arrange for delivery of replacement products.<br />

4. Note description of product quantity discrepancies and/or product damage on Bill of Lading.<br />

10675 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Wal-Mart Rack/Fence Supplier will furnish metal rack/fence system and accessories under provisions of Section<br />

01640 for installation by Contractor.<br />

B. Descriptions and specifications of Owner furnished items and equipment hereinafter are included as information to<br />

the Contractor only and not to be considered as Contractor requirements unless otherwise stated.<br />

C. Rack/Fence System: System will include the components as described and detailed on Drawings. Modular Rack<br />

and Fence System design and testing shall conform to the requirements of ANSI MH16.1.<br />

D. Quantity Furnished: Product quantities required are determined by Wal-Mart Supplier.<br />

E. Fence Screening Mesh: Type HR1 Mesh: 2” x 2” x 9 gage wire mesh panel as shown on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLERS<br />

A. Work required for the installation of the Modular Rack and Fence System shall be by one of the following prequalified<br />

installers:<br />

1. Hendee Enterprises Incorporated, Houston, TX (800) 231-7275. Contact: Crystal Genovese<br />

Crystalg@hendee.com.<br />

2. HH Technologies, Inc., Bremen, AL (800) 219-0117, Extension 1122. Contact: Randy Remington<br />

randyr@hired-hand.com.<br />

3. Ludy Greenhouse Manufacturing Corporation, New Madison, OH (800) 255-5839. Contact: Leah<br />

Scantland Leah.Scantland@ludy.com.<br />

4. Rough Brothers Incorporated, Cincinnati, OH (800) 543-7351, Ext 217. Contact: Tommy Reed<br />

treed@roughbros.com.<br />

B. Any similar company specializing in performing work required for the installation and/or furnishing of similar of<br />

products as those specified above with minimum 5 years documented experience may be used for installation upon<br />

acceptance and approval by Wal-Mart.<br />

3.2 EXAMINATION<br />

A. Examine conditions and adjacent areas where products and materials will be installed and verify that conditions<br />

conform to product manufacturer's requirements for installation.<br />

3.3 INSTALLATION (BY CONTRACTOR)<br />

A. Assemble and install entire rack and fence system including screening mesh, wire decking, and gates in<br />

accordance with Instruction Manual included with rack/fence system materials.<br />

B. Non-Loaded Rack Limits: Out of Plumb and Out of Straight Limits for non-loaded racks shall not exceed 1/4<br />

inch for any 10 ft height and 1/2 inch for total vertical height.<br />

C. Unit Levelness: Horizontal rack members shall be level within 1/4 inch per 10 ft length, non-cumulative. Shim as<br />

required using shims furnished by the rack/fence supplier.<br />

D. Secure rack/fence system base plates to the concrete slab as shown on the drawings using anchors furnished by the<br />

rack/fence supplier of sufficient length to allow for the thickness of the rack base plate and required shims and to<br />

provide not less than 4 inch embedment length.<br />

E. Provide hollow metal mandoors and frames as shown on Drawings and as specified in Section 08110.<br />

10675 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.4 PROTECTION<br />

A. Protect installed modular rack and fence system from damage until completion of construction operations.<br />

END OF SECTION<br />

10675 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 10810 (10 2813) – TOILET ACCESSORIES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Toilet accessories and attachment hardware.<br />

B. Related Requirements:<br />

1. Section 01600 - Product Requirements: General procedures related to products.<br />

2. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

3. Section 06100 - Rough Carpentry: Blocking for attachment of accessories.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ANSI International (ANSI):<br />

1. ANSI A117.1 - Accessible and Usable Buildings and Facilities.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Wal-Mart will furnish toilet accessories for installation by Contractor as<br />

follows and as scheduled in Part 3 below:<br />

1. Soap Dispensers.<br />

2. Paper Towel Dispensers, Surface Mounted (Grocery Areas only).<br />

3. Toilet Handicap Signs.<br />

2.2 PRODUCT PROCUREMENT<br />

A. All Contractor provided accessory items specified herein shall be direct purchased by the General Contractor from<br />

Wal-Mart’s pre-negotiated supplier. Reference Section 01600 for additional information regarding Direct<br />

Purchase Products. Pre-negotiated supplier shall be as follows:<br />

1. Haines, Jones & Cadbury, Inc. Contact: Customer Service, (800) 459-7099, Fax (479) 756-8998, Email<br />

info@hjcinc.com<br />

2.3 MANUFACTURERS<br />

A. Provide products from the following manufacturers as specified in the Schedule of Accessories hereinafter:<br />

1. American Specialties Co., Inc., Deer Park, NY.<br />

2. Bobrick Washroom Equipment, Inc., Jackson, TN.<br />

3. Bradley Corporation, Menomonee, WI.<br />

4. Foundations, Inc., Medina, OH.<br />

5. Compass Asia, Inc.<br />

6. Excel Dryer Corporation, East Longmeadow, MA.<br />

7. Ginger, Ft. Mill, SC.<br />

8. Koala Kare Products (A Division of Bobrick), Englewood, CO.<br />

9. Laurel Metal Products, Inc., Lincolnwood, IL.<br />

10. Meek Manufacturing Company, Fort Smith, AR.<br />

11. Saniflow Corp., Miami, FL.<br />

12. World Dryer Corporation.<br />

10810 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Comply with the requirements of Section 01600.<br />

2.4 MATERIALS<br />

A. Stainless Steel: AISI Type 302/304.<br />

B. Mounting Devices: Hot-dip galvanized after fabrication or of same material as accessory unit.<br />

C. Adhesive: Epoxy type contact cement.<br />

D. Thread Lock Compound (For Coat Rack Fastener): Loctite 242, by Henkels Corporation, (860) 571-5100.<br />

E. Finishes:<br />

1. Chrome/Nickel Plating: Polished finish.<br />

2. Stainless Steel: No. 4 satin finish, unless specified otherwise.<br />

3. Shop Primed Ferrous Metals: Pretreat and clean, spray apply one coat primer and bake.<br />

2.5 FABRICATION<br />

A. Weld and grind smooth joints of fabricated components.<br />

B. Form exposed surfaces from one sheet of stock, free of joints. Form surfaces flat without distortion. Maintain flat<br />

surfaces without scratches or dents.<br />

C. Provide steel anchor plates and anchor components for installation on building finishes. Hot-dip galvanize ferrous<br />

metal anchors and fastening devices.<br />

D. Back paint components where contact is made with building finishes to prevent electrolysis.<br />

E. Shop assemble components and package complete with anchors and fittings.<br />

PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Deliver inserts and rough-in frames to Site at appropriate time for building-in. Use templates and rough-in<br />

measurements as required.<br />

B. Verify that blocking is appropriately installed and ready to receive accessories.<br />

C. Rough Wall Openings: Provide rough wall opening (RWO) in compliance with ADA Accessibility Guidelines, as<br />

detailed on architectural drawings, and as described in the Schedule of Accessories.<br />

3.2 INSTALLATION<br />

A. Install fixtures, accessories, and items in accordance with manufacturer's instructions and as shown on Drawings.<br />

Install accessories within toilet rooms and install accessories and soap dispensers in other areas in addition to toilet<br />

rooms where shown on Drawings. Use tamper-proof fasteners.<br />

B. Install true, plumb, and level, securely and rigidly anchored to wall framing.<br />

C. Locate Toilet handicap signs as shown on the AHC drawings. Apply signs to door and wall surfaces with vinyl<br />

adhesive tape.<br />

3.3 SCHEDULE OF ACCESSORIES<br />

A. Soap Dispensers: Furnished by Wal-Mart for installation by Contractor.<br />

10810 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Sanitary Napkin Dispenser:<br />

1. Model No. 10-04684-Recessed by American Specialties, Inc.<br />

a. Finish: Stainless Steel.<br />

b. Rough Wall Opening: 16” W x 26” H x 6-1/4” D.<br />

2. Model No. 4017-45 by Bradley.<br />

a. Finish: Stainless Steel.<br />

b. Rough Wall Opening: 12” W x 26” H x 6-1/2” D.<br />

C. Sanitary Napkin Disposal:<br />

1. Model No. 0473-1A by American Specialties, Inc.<br />

a. Finish: Stainless Steel.<br />

2. Model No. 4722-15 by Bradley.<br />

a. Finish: Stainless Steel.<br />

D. Paper Towel Dispensers, Recessed: Pull Core Paper Towel Cabinet and Waste Receptacle.<br />

1. Model D4693-6 by American Specialties.<br />

a. Rough Wall Opening: 15-3/4” W x 54-1/2” H x 10-1/4” or 4-1/4” D depending on wall type. Top<br />

of RWO 3/4” below top of unit.<br />

2. Model No. 236-WM as manufactured by Bradley.<br />

a. Rough Wall Opening: 15-3/4” W x 54-1/2” H x 7-1/2” D.<br />

3. Provide collar when and as required for depth of wall stud.<br />

E. Paper Towel Dispensers, Surface Mounted:<br />

1. At Pharmacy and Pharmacy Toilet: Furnished and installed by Wal-Mart.<br />

2. At Grocery: Furnished by Wal-Mart for installation by Contractor.<br />

F. Toilet Paper Dispensers.<br />

1. Model No. 5425 by Bradley Corporation.<br />

2. Model No. 0040 by American Specialties.<br />

G. Electric Hand Dryers: Stainless steel, surface mounted, automatic (no-touch) model. One of the following:<br />

1. Model MO6ACS-UL Speedflow by Saniflow.<br />

2. Model 2902-287400 Aerix by Bradley.<br />

H. Diaper Changing Table and Accessories:<br />

1. Changing Table: Provide one of the following:<br />

a. Foundations, Inc.: Stainless Steel Baby Changing Station Recessed Mount; Model No. 100-SSC-<br />

MCB.<br />

b. Koala Kare Products: Stainless Steel Baby Changing Station Recessed Mount KB110-NLRF.<br />

2. Accessories: Provide accessories by one of the following manufacturers:<br />

a. Manufacturer: Koala Kare Products.<br />

1) Diaper Dispenser: Koala Model No. KB143-SS-Recessed or Laural Model No. 2100-D<br />

Recessed with Koala Model No. KB144-99 collar; Rough Wall Opening 12-1/2”W x 42-1/4”<br />

H x 5-1/2” D.<br />

2) Sanitary Liner Dispenser: Koala Model No. KB134-SSLD-Recessed; Rough Wall Opening<br />

7-7/8” W x 16-1/2” H x 4-1/4” D.<br />

b. Manufacturer: Foundations, Inc.<br />

1) Diaper Dispenser: Foundations, Inc. Model No. 105-SS-SM-Recessed with 025-SS<br />

recessing flange; Rough Wall Opening 12-3/4” W x 42-1/4” H x 5-1/4” D.<br />

2) Sanitary Liner Dispenser: Bradley Model No. 2441-Recessed; Rough Wall Opening 11-3/8”<br />

W x 15-11/16” H x 4” D.<br />

3. Diaper Disposal: Bradley Model No. 356-35, Stainless Steel with hinged lid.<br />

I. Toilet Seat Cover Dispensers: Surface mounted (one per each water closet), 22 gage 18-8 type 304 stainless steel,<br />

satin finish.<br />

1. Model No. 0477SM, by American Specialties.<br />

2. Model No. B221, by Bobrick.<br />

10810 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Model No. 5831, by Bradley.<br />

J. Small Framed Mirrors: No. 1 quality 1/4 inch float glass electrolytically copper plated, tempered glass. Mitered<br />

stainless steel frame; concealed theft resistant wall hanger. Mirror size shall be 24 x 36 unless otherwise shown.<br />

1. Model No. M1513, by Meek.<br />

2. Model No. 781-024362, by Bradley.<br />

K. Large Framed Mirrors (Dressing Mirror): No. 1 quality 1/4 inch float glass electrolytically copper plated,<br />

tempered glass. Stainless steel angle frame; concealed theft resistant wall hanger. Mirror size shall be 20” x 60”.<br />

1. Model No. M1513, by Meek.<br />

2. Model No. 781-020602, by Bradley.<br />

L. Child Safety Seat: Surface mounted.<br />

1. Model No. 103-BQS, by Foundations, Inc.<br />

2. Model No. KB-102, by Koala.<br />

M. Coat Rack: Surface mounted.<br />

1. Model No. 2810D by Ginger (Double Coat Rack).<br />

2. Model No. 2810T by Ginger (Triple Coat Rack).<br />

3. Model No. 2810Q by Ginger (Quad Coat Rack).<br />

4. Install coat rack fasteners using thread lock compound specified in Part 2 above. Apply thread lock<br />

compound to fasteners in accordance with manufacturer’s instructions.<br />

N. Wall Mounted Flower Vase (Flower Sconce): Surface mounted.<br />

1. Model No. CKS14B Stainless Steel Flower Vase, by Styles and Stainless.<br />

2. Model No. AD4-0028 Stainless Steel Vase Bracket, by Bradley.<br />

O. Restroom Needs Cleaning Switch Sign: Approximately 2”x4” sign.<br />

P. Grab Bars: 18 gage stainless steel; 1-1/4 inch diameter, (1-1/2 inch diameter where required by Local Code)<br />

textured grip surface; concealed mounting consisting of welded-on mounting flange with snap-on cover flange or<br />

escutcheon. Location, quantity, and length shall be as shown.<br />

1. Model No. 3700 P, by American Specialties.<br />

2. Model No. B-5806.99, by Bobrick.<br />

3. Model No. 832-2, by Bradley.<br />

4. Model No. PB23XX Series by Compass (1-1/2 inch diameter only).<br />

Q. Toilet Signage:<br />

1. Toilet wall and doors signs shall conform to California Handicapped Code Title 24 requirements. Provide<br />

signs of size, configuration, and color as shown on the AHC Drawings. Signs shall be as manufactured by<br />

SourceOne or by other manufacturer normally engaged in the production of equivalent signs.<br />

2. Signs shall be non-glare matte finish plastic injection molded plate with 1/32” raised image relief area.<br />

Symbols shall be 8” x 8” with 5/16” radius corners. Symbols shall be white with white 5/8” Helvetica<br />

Medium upper case letters and Grade 2 Braille.<br />

R. Lighted Restroom Sign: LED lighted sign in metal box frame with stenciled thermoplastic face plate and battery<br />

backup.<br />

1. Model No. HSG300-SW-B, by Healthcare Lighting, Erie, PA (800) 274-4510.<br />

2. Color: Blue.<br />

3. Size: 8-1/4 x 12-3/8 inches.<br />

4. Electrical: 120 VAC.<br />

5. Message Text: RESTROOM NEEDS CLEANING.<br />

10810 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.4 CLEANING<br />

A. Protection and Cleaning of Toilet Accessories and Attachment Hardware Prior to Possession:<br />

1. Immediately prior to possession, clean stainless steel accessories and attachment hardware thoroughly<br />

using soap, ammonia, or mild detergent and water. Apply with sponge or soft cloth, rinse with clear water<br />

and wipe dry. Always rub in the direction of polish lines. Rinse thoroughly with fresh water after every<br />

cleaning operation. Clean and polish to a spotless luster. Wipe dry to avoid water marks.<br />

2. Clean and polish stainless steel accessories and mirror surfaces to a spotless luster.<br />

END OF SECTION<br />

10810 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082605<br />

SECTION 11025 – LOCK BOXES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Lock box key vault for Pharmacy.<br />

2. Lock box key vault for fire department emergency building access.<br />

1.2 QUALITY ASSURANCE<br />

A. Pre-Installation Meetings: Meet with fire department to determine requirements for lock box type and coordinate<br />

exact location for installation and mounting of box on building.<br />

PART 2 - PRODUCTS<br />

2.1 MANUFACTURERS<br />

A. Pharmacy Lock Box:<br />

1. Master Lock Co., Oak Creek, WI. Phone: (800) 558-5528.<br />

2. Roper Lock Box, Hudson OH. Phone: (800) 466-9312.<br />

3. Substitutions: Not permitted.<br />

B. Fire Department Lock Box:<br />

1. Knox Box by The Knox Company, Phoenix, AZ. Phone: (800) 552-5669.<br />

2. Alternate Manufacturers: As approved by fire department.<br />

2.2 MANUFACTURED UNITS<br />

A. Pharmacy Lock Box: Wall mounted, combination lock, metal box. Provide one of the following:<br />

1. 5401D Select Access Wall Mount Key Storage by Master Lock Co.<br />

2. Avanti/Guardian by Roper Lock Box.<br />

B. Fire Department Lock Box:<br />

1. UL labeled, weather resistant, factory finished, heavy duty steel lock box.<br />

2. Model: Type and size as required by fire department.<br />

3. Ordering: Complete manufacturer's Authorization/Order Form and obtain local fire department authorized<br />

signature on form before processing.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install pharmacy lock box at locations shown on the drawings.<br />

B. Install fire department lock box at location required by fire department in accordance with manufacturers<br />

published instructions.<br />

END OF SECTION<br />

11025 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 082611<br />

SECTION 11160 (11 1330) – LOADING DOCK EQUIPMENT<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Wal-Mart furnished and installed loading dock equipment.<br />

B. Related Requirements:<br />

1. Section 03310 - Structural Concrete and Exterior Concrete Slabs: Concrete pit for dock levelers.<br />

2. Section 05500 - Metal Fabrications: Steel angle frame around dock leveler pit.<br />

1.2 SUBMITTALS<br />

A. Closeout Submittals: Submit the following Wal-Mart Supplier Furnished Items in accordance with the<br />

requirements of Section 01770.<br />

1. Operations and Maintenance Manuals.<br />

2. Documentation of final service performed on levelers as specified in Part 3.<br />

3. Certificate of Inspection included at the end of this Section.<br />

4. Warranties specified in Part 2 of this Section.<br />

1.3 QUALITY ASSURANCE<br />

A. Provide dock equipment by a single manufacturer, except for safety gate.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Product Delivery: Wal-Mart Supplier will deliver products to Site to be received by Contractor. Wal-Mart<br />

Supplier will contact Contractor to coordinate product delivery and installation.<br />

B. Receive and unload Owner furnished products in compliance with the requirements of Section 01640.<br />

C. Product Packaging: Dock equipment will be delivered in manufacturer's standard packaging with identification<br />

markings on each component or package.<br />

D. Acceptance at Site: Inspect products upon delivery of products to Site to verify quantity of products furnished.<br />

Report discrepancies in quantity delivered or obvious damage to products delivered to Wal-Mart Construction<br />

Manager and Wal-Mart Supplier.<br />

E. Store and handle dock seals in a manner to avoid damage to fabric. Comply with manufacturer's published<br />

instructions for minimum and maximum temperature requirements for storage.<br />

F. Handle, store, and protect products in accordance with the requirements of Section 01600.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER PROVIDED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's Supplier will furnish and install loading dock equipment.<br />

Descriptions and specifications of Owner provided products are included as information to Contractor only and are<br />

not to be considered as Contractor requirements unless otherwise stated.<br />

1. Wal-Mart Loading Dock Equipment Supplier:<br />

a. BCI Management Group; Conway, AR. Contact: Tom Barlow (888) 654-2687.<br />

11160 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.2 DOCK SEALS<br />

A. Model: FPW-22V-WP8-WF by Nordock.<br />

B. Description:<br />

1. Side Pads: Length equal to clear opening height, beveled profile 12 inches wide at front and 8 inches wide<br />

at back. If driveway approach is not level, taper side pads inward or outward as necessary from bottom to<br />

top so that face of pad is perpendicular to the trailer bed when setting at the dock on the driveway approach<br />

and to provide minimum 6 inch uniform compression of pad from top to bottom.<br />

2. Head Pad: 12 inch height by length to equal 2 feet longer than clear opening width with projection to<br />

match projection at top of side pads.<br />

3. Clear Opening Size: As indicated on Drawings.<br />

4. Provide breather slots for pads.<br />

5. Core: High-density urethane foam core with supporting frame.<br />

6. Cover Fabric: Vinyl coated nylon, 22 oz/sq yd, black.<br />

7. Wear Pleats: Full height of side pads, 40 oz/sq yd vinyl coated nylon, with 8 inch exposure, black. Extra<br />

40 ounce wearface on face of head pad, black.<br />

8. Guide Stripes: Manufacturer's standard width stripe full height of side pads, yellow.<br />

9. Supporting Frame: 2 inch kiln-dried, preservative treated wood fully encased with cover fabric, or rollformed<br />

galvanized steel with polyurethane foam core chemically bonded to steel frame and fully encased<br />

with cover.<br />

10. Hardware: Galvanized steel.<br />

2.3 DOCK LEVELERS<br />

A. Model: AirDock Air Powered Dock Leveler by Nordock.<br />

B. Description:<br />

1. Air bag operation, with low pressure, high volume air system to raise and lower platform.<br />

2. 7 feet wide by 8 feet long nominal size; minimum dynamic capacity of 35,000 lbs.<br />

3. 12 inch lip beyond bumper face, below dock control, secure from illegal entry, and full range side<br />

telescopic toe guards.<br />

4. Performance Requirements:<br />

a. Maximum Gross Moving Load (forktruck weight + load): 13,000 pounds.<br />

b. Maximum Forktruck Speed With Load: 6 miles an hour.<br />

c. Forktruck Wheel Configuration: Both 3 and 4 wheel.<br />

d. Assumed Usage: Up to 4 trucks per day per door, seven days a week.<br />

e. Assume angled approach traffic pattern on and off deck.<br />

5. Stump out elimination provisions.<br />

6. Service Range: 12 inches above and below dock level.<br />

7. Brush style weatherseal with galvanized steel frame at dock plate perimeter.<br />

8. Extended night lock feature.<br />

9. Dock Bumpers: Two steel faced dock bumpers, 20 inches high and 11 inches wide. Contractor shall<br />

evaluate existing site conditions including driveway approach, distance, angle, and door head height to<br />

determine adequate bumper pad thickness. Provide bumper with steel face totaling a minimum 5.25 inch<br />

projection from face of dock.<br />

10. Remote wall-mount push button controls with single phase 115v blower motor. Provide a hinged padlock<br />

lockable cover and padlock.<br />

C. Warranty: Warrant the following for the period stated from the date of installation.<br />

1. Warrant complete front and rear hinge assemblies for a period of 20 years.<br />

2. Warrant structural components including deck lip or frame assembly and welding from structural defects<br />

for a period of ten years.<br />

3. Warrant all lifting components for a period of five years.<br />

4. Warrant dock bumpers against defects in workmanship the dock bumper face against wear for a period of<br />

10 years.<br />

5. All other components shall be covered for one year from date of installation.<br />

11160 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


2.4 WHEEL CHOCKS<br />

A. Model: L-88 by Nordock.<br />

B. Description:<br />

1. Laminated rubber pads assembled on 3/4 inch bolts and compressed between 1/4 inch plates. Unit will<br />

have eye bolt or loop for attachment of chain.<br />

2. Meets OSHA and DOT requirements.<br />

3. Provide 20 foot long approved chain and attach to concrete wall at dock with expansion anchors. Locate on<br />

driver's side of truck trailer.<br />

2.5 OPERATION CHART<br />

A. Description: Operation chart for dock levelers and edge-of-dock levelers outlining operational instruction.<br />

Adhesive backed vinyl faced sticker suitable for permanent application to composite or steel dock doors. Chart<br />

shall not include maintenance instructions.<br />

2.6 SAFETY GATES<br />

A. Model: Dock Sentinel Safety Gate by Nova Technology, LLC.<br />

B. Description: Manually operated safety gate to provide impact protection to interior side of overhead dock doors<br />

and personnel safety barrier.<br />

1. Operating Height:<br />

a. Closed Position: Top of gate 42 inches a.f.f.<br />

b. Open Position: Top of stanchions maximum 9 feet a.f.f.<br />

2. Door Opening Width: As indicated on Drawings.<br />

3. Frame: Vertical steel end posts with steel horizontal protection bars at 6 3/4 inches a.f.f. and 42 inches a.f.f.<br />

4. Finish: Safety yellow.<br />

5. Locking Mechanism: Positive locking in open position.<br />

C. Warranty: Warrant the following for the period stated from the date of installation.<br />

1. Warrant structural components from structural defects for 10 years.<br />

2. Warrant non-structural components for one year.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine existing conditions and adjacent areas where products will be installed and verify that conditions<br />

conform to product manufacturer’s requirements. Verify that building elements required for product installation<br />

are ready to receive work. Do not proceed until unsatisfactory conditions have been corrected.<br />

B. Verify size of pit and equipment anchorage requirements.<br />

3.2 INSTALLATION<br />

A. Install loading dock equipment in accordance with manufacturer’s published instructions at locations shown on the<br />

drawings.<br />

B. Apply sealant between dock wall and dock seal as shown on Drawings.<br />

C. Install wheel chock at each new dock door and at each existing dock door to remain on driver’s side of door.<br />

Provide 20 foot long, 1/4-inch plated chain for each wheel chock. Attach chain to foundation wall by expansion<br />

anchor on driver’s side of door.<br />

11160 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Dock Equipment shall be installed by manufacturer’s qualified and authorized installers. Installation by<br />

unauthorized installers will not be accepted.<br />

3.3 INTERFACE WITH OTHER WORK<br />

A. Interface with Other Work: Coordinate size and location of cast-in-place concrete dock leveler or edge of dock<br />

leveler block-outs, pits, reinforcement, frames, inserts, and formwork with Contractor before start of concrete<br />

placement.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Manufacturer Services: Provide on-site field inspection by manufacturer’s authorized representative and<br />

authorized installer verifying that installation and operation of products specified herein are in accordance with<br />

manufacturer’s recommendations and instructions.<br />

3.5 ADJUSTING AND CLEANING<br />

A. Installed equipment shall be cleaned and fully adjusted for proper operation at time of installation.<br />

B. Dock levelers and edge-of-dock levelers shall be serviced, cleaned, and adjusted by original installer within two<br />

weeks prior to grand opening. Submit documentation of final service on levelers as specified in Part 1.<br />

C. Apply operation chart for dock leveler and edge-of-dock leveler on inside face of each dock door centered at 5 ft<br />

above floor.<br />

END OF SECTION<br />

11160 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


CERTIFICATE OF INSPECTION<br />

SECTION 11160<br />

LOADING DOCK EQUIPMENT<br />

Project Location:<br />

Date: ______________<br />

(City)<br />

(State)<br />

Project Number:<br />

Store Number:<br />

The following loading dock equipment has been inspected and approved:<br />

Dock Seals:<br />

Dock Levelers:<br />

Edge of Dock Levelers:<br />

Wheel Chocks:<br />

Dock Bumpers:<br />

Safety Gates:<br />

Product Mfg and Model:<br />

Product Mfg and Model:<br />

Product Mfg and Model:<br />

Product Mfg and Model:<br />

Product Mfg and Model:<br />

Product Mfg and Model:<br />

Statement of Conformance:<br />

The undersigned hereby declares that the Product identified above by manufacturer's name and model number is the product<br />

specified and is suitable for the intended use as defined within the Contract Documents and has been provided and placed in<br />

operational condition by a manufacturer’s authorized installer and in accordance with the manufacturer's published<br />

instructions and the Contract Documents.<br />

SUPPLIER (MANUFACTURER’S AUTHORIZED REPRESENTATIVE):<br />

(Contact name of supplier of above product)<br />

Phone Number: ( )<br />

(Supplier name and address)<br />

MANUFACTURER’S AUTHORIZED INSTALLER:<br />

(Contact name of company installing above product)<br />

Phone Number: ( )<br />

(Company name and address)<br />

PRIME CONTRACTOR:<br />

(Contact name of Contractor)<br />

(Contractor signature and Title of Signatory)<br />

11160 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 072911<br />

SECTION 11400 (11 4000) – FOOD SERVICE EQUIPMENT<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Wal-Mart furnished food service equipment.<br />

2. Equipment final connections.<br />

B. Related Requirements:<br />

1. Section 15100 - Building Services Piping and Equipment: Connections to plumbing systems.<br />

2. Section 15600 - Refrigeration Equipment: Connections to refrigeration systems.<br />

3. Section 15700 - Heating, Ventilating, and Air Conditioning Equipment: Connections to heating and colling<br />

units.<br />

4. Section 16100 - Wiring Methods: Connections to electrical systems.<br />

1.2 ADMINISTRATIVE REQUIREMENTS<br />

A. Coordinate with Wal-Mart’s Food Service Equipment Supplier so that forklift equipment (provided by Contractor)<br />

is available to unload equipment from truck and place into position.<br />

B. Coordinate installation of food service equipment among related trades, vendors and installers.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Wal-Mart’s equipment supplier will contact Contractor after Award of Contract to establish a product delivery and<br />

installation date and establish a coordination procedure. In the event contact or coordination cannot be made with<br />

Wal-Mart’s supplier, contact Store Planning as specified in Section 01640.<br />

B. Transport, handle, store, and protect products in compliance with the requirements of Section 01600 and<br />

manufacturer's recommendations.<br />

C. Receive Owner Furnished products in compliance with the requirements of Section 01640.<br />

D. Receive, unload and store Wal-Mart furnished equipment, as indicated in Equipment Schedule on Drawings, in a<br />

location that will not interfere with orderly completion of work. Protect equipment from damage.<br />

E. Transport equipment not in crates by hand only.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED EQUIPMENT<br />

A. Under provisions of Section 01640, Wal-Mart's Food Service Equipment Supplier will furnish food service<br />

equipment for installation by either Wal-Mart or the Contractor as indicated in Equipment Schedule on Drawings.<br />

2.2 FOOD SERVICE EQUIPMENT (FURNISHED BY WAL-MART)<br />

A. Food service equipment and related items designated in the Equipment Schedule or elsewhere on Drawings to be<br />

furnished by Wal-Mart will be purchased by Wal-Mart under separate contract.<br />

B. Breakroom Refrigerated Case: Three door, glass front, self contained cabinet, Model GDM-72, by True Food<br />

Service Equipment, Inc., O’Fallon, MO (800) 325-6152.<br />

11400 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


PART 3 - EXECUTION<br />

3.1 PREPARATION<br />

A. Verify that mechanical, plumbing, and electrical rough-ins have been properly located.<br />

B. Obtain necessary drawings, manufacturer's product data, and other data to provide a complete and proper<br />

installation.<br />

C. Check field dimensions prior to installing equipment. Verify necessary clearances and means of access from<br />

equipment storage to final position.<br />

D. Provide two skilled laborers to work for a period of three days, exclusively to assist in Bakery unload, set up, and<br />

cleanup.<br />

E. Provide two skilled laborers to work for a period of three days, exclusively to assist in Rotisserie unload, setup,<br />

and cleanup.<br />

F. Provide the following equipment during set up: One forklift, four 4-wheel dollies, one Johnson bar.<br />

3.2 INSTALLATION<br />

A. Uncrate and set equipment in place plumb, level, and properly secured.<br />

B. Equipment installation shall be by Wal-Mart or Contractor as scheduled on Drawings. Installation shall be in<br />

accordance with manufacturer’s requirements and installation instructions, unless otherwise indicated on<br />

Drawings.<br />

C. Final Connections: Contractor shall perform final mechanical, plumbing, and electrical connections for Wal-Mart<br />

installed equipment and Contractor installed equipment as required and recommended by manufacturer.<br />

D. Waste Cooking Oil Tank: Install Waste Cooking Oil Tank and make ready for use by date of Possession.<br />

E. Relocate existing Waste Cooking Oil Tank (if existing tank requires relocation) to the new location shown on<br />

Drawings such that there will be minimal disruption in the availability of the system for use by the existing food<br />

service operation.<br />

3.3 FIELD QUALITY CONTROL BY OWNER<br />

A. Wal-Mart’s Food Service Equipment Supplier or Wal-Mart Furnished Equipment Manufacturer’s Representative<br />

will conduct operational tests on Wal-Mart Furnished Equipment at no cost to Contractor, except for items<br />

specifically indicated to be tested by Contractor below.<br />

B. Wal-Mart’s Food Service Equipment Supplier or Wal-Mart Furnished Equipment Manufacturer’s Representative<br />

will conduct operational tests of equipment through full operational cycle and operate for a sufficient time to<br />

verify that equipment is operating within manufacturer's specifications.<br />

C. Operational tests will be completed no later than one week after Date of Possession.<br />

D. Contractor’s Responsibility: Provide adjustments or changes as required from operation test results.<br />

3.4 FIELD QUALITY CONTROL BY CONTRACTOR<br />

A. Conduct operational tests of the following items.<br />

1. Three compartment stainless steel sinks.<br />

2. Stainless steel hand sinks.<br />

3. Reverse osmosis water system.<br />

11400 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Conduct operational tests of equipment through full operational cycle and operate for a sufficient time to verify<br />

that equipment is operating within manufacturer's specifications.<br />

C. Complete operational tests no later than one week after Date of Possession.<br />

3.5 CLEANING<br />

A. Remove tape, wrapping, packing and such items used to facilitate shipping and handling from equipment.<br />

B. Clean equipment as specifically recommended by equipment manufacturer.<br />

END OF SECTION<br />

11400 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 042611<br />

SECTION 13080 – SEISMIC PROTECTION FOR MECHANICAL, ELECTRICAL AND REFRIGERATION.<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. The requirements for seismic protection measures to be applied to mechanical, electrical and refrigeration<br />

equipment, systems and appurtenances specified herein.<br />

B. Related Sections:<br />

1. Section 01330 – Submittal Procedures.<br />

2. Section 01770 – Contract Closeout.<br />

3. Section 07721 – Manufactured Curbs: Requirements for seismic roof curbs.<br />

C. Contractor Responsibilities:<br />

1. Secure the services of and coordinate with the Seismic Restraint Manufacturer, including obtaining shop<br />

drawings, equipment cut sheets and other data required by the Seismic Restraint Manufacturer for their<br />

seismic design work.<br />

2. Install seismic restraint equipment specified by the Seismic Restraint Manufacturer in accordance with the<br />

construction documents provided by the Seismic Restraint Manufacturer.<br />

3. Provide seismic restraint attachment plates cast into housekeeping pads, concrete inserts, double sided<br />

beam clamps, etc. in accordance with the requirements of the Seismic Restraint Manufacturer.<br />

4. Prior to the start of MEP work submit a Quality Assurance Plan which includes the following:<br />

a. Seismic restraint shop drawings, equipment cut sheets, and seismic design calculations.<br />

b. Letter of Certification from the Seismic Restraint Manufacturer which includes:<br />

1) A statement that the factory trained representative of the Seismic Restraint Manufacturer has<br />

received the factory training necessary to perform the field inspection required in Part 3 of<br />

this specification.<br />

2) Certification stating that all seismic restraint and equipment for all connections to the<br />

structure or anchoring to the floor have been coordinated with the structural engineer of<br />

record.<br />

3) A Letter of Certification from the seismic engineer which certifies all components and<br />

assemblies comply with all applicable codes.<br />

c. Quality Assurance Plan Distribution List:<br />

1) (1) One copy for Professional Engineer of Record - Structural, for information only.<br />

2) (1) One copy for Professional Engineer of Record - Mechanical, Electrical, Plumbing and<br />

Refrigeration, for information only. Contact for submission: Deborah Baldwin, 1805 N<br />

Second Street Rogers, AR 72756 (479)636-5004, djb@bgark.com<br />

3) (1) One copy, with (5) copies of cut sheets and shop drawings for General Contractor.<br />

4) (1) One copy of submittal transmittal only for Architect of Record.<br />

5. When required by the local Authority Having Jurisdiction (AHJ), submit all MEP Seismic Restraint<br />

calculations, specifications, drawings and details as a deferred submittal. Submit deferred submittals in<br />

accordance with Section 01330.<br />

6. Following the completion of the seismic restraint installation, submit the following (refer to distribution list<br />

above):<br />

a. The inspection report as described in the "Vendor Observation" paragraph below, per specifications<br />

Section 01330 "Submittal Procedures" and specification section 01770 "Contract Closeout".<br />

b. A letter of compliance from the Seismic Engineer with the Engineer's seal and signature certifying<br />

that all seismic restraint components and assemblies were provided and installed per the code and<br />

the Quality Assurance Plan.<br />

13080 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


D. Seismic Restraint Manufacturer Responsibilities:<br />

1. Determine the type and location of seismic supports required for the mechanical, electrical and refrigeration<br />

elements shown on the contract drawings based on the Seismic Design Category, the size and weight of the<br />

supported element and the distance to the structure from which the element will be installed.<br />

2. Prepare submittals in accordance with requirements in individual specification sections and specification<br />

Section – 01330 “Submittal Procedures”.<br />

3. Provide Seismic Certification and Analysis as follows:<br />

a. Provide seismic restraint calculations for all equipment as required by the Building Code and AHJ.<br />

Calculations shall be stamped by a registered professional engineer with at least five years of seismic<br />

design experience, licensed in the state of the project location, and employed by the manufacturer<br />

of the seismic restraint products.<br />

b. Analysis shall indicate calculated dead loads, static seismic loads and capacity of materials utilized<br />

for connections to equipment and structure. Analysis must detail anchoring methods, bolt diameter,<br />

embedment and/or welded length. All seismic restraint devices shall be designed to accept, without<br />

failure, the seismic forces prescribed by the applicable building code requirements, acting through<br />

the equipment center of gravity. Overturning moments may exceed forces at ground level.<br />

4. Provide the installing contractor with a set of "Installation Procedures" detailing how the seismic restraint<br />

components are to be installed.<br />

1.2 SUBMITTALS<br />

A. The Seismic Restraint Manufacturer shall provide submittals for products, per specification Section – 01330<br />

“Submittal Procedures” and specification Section – 01770 “Contract Closeout”. Submittals shall be signed and<br />

sealed by a registered professional engineer with at least five years of seismic design experience, licensed in the<br />

state of the job location, and employed by the manufacturer of the seismic restraint products. The submittals shall<br />

contain the following:<br />

1. Descriptive Data:<br />

a. Catalog cut sheets or data sheets on specific restraints and equipment roof curbs detailing<br />

compliance with the specification.<br />

b. Detailed schedules of flexible and rigidly mounted equipment, showing seismic restraints.<br />

c. If building has expansion joints, special design consideration for piping crossing these joints must<br />

be shown in the MEP submittal data.<br />

2. Shop Drawings:<br />

a. Provide templates, erection details, and installation details.<br />

b. Indicate thickness, type, grade, class of metal, and dimensions.<br />

c. Show construction details, reinforcement, anchorage, and installation with relation to other building<br />

systems and construction.<br />

d. Show details of suspension and support for ceiling hung equipment.<br />

e. Provide specific details of seismic restraints, and anchors; and include number, size and locations<br />

for each piece of equipment.<br />

f. Where walls, floors, slabs or supplementary steel work are used for seismic restraint locations,<br />

provide details of acceptable attachment methods for ducts, conduit and pipe to these portions of the<br />

building structure.<br />

3. Layout Drawings:<br />

a. Show locations and types of seismic restraints for all equipment, piping and conduit. Coordinate<br />

locations for seismic restraints with the structure and with other mechanical, electrical, and<br />

refrigeration components.<br />

4. Submittal Distribution List: submit to General Contractor for distribution as described in Section 1.1.C.<br />

B. Seismic Restraint Manual: A seismic restraint manual shall be prepared by the Seismic Restraint Manufacturer<br />

and submitted by the Contractor, per specification Section 01770 “Contract Closeout”, that which contains the<br />

basis of the design for the seismic support systems, product data, shop drawings and layout drawings. A copy of<br />

the seismic restraint manual shall be kept on the jobsite for the duration of the project.<br />

13080 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


1.3 QUALITY ASSURANCE<br />

A. Professional Engineer Qualifications: The professional engineer employed by the Seismic Restraint Manufacturer<br />

shall be legally qualified to practice in the jurisdiction where the Project is located and shall be experienced in<br />

providing engineering services of the kind indicated. Engineering services are defined as those performed for<br />

installations of seismic restraints that are similar to those indicated for this Project in material, design, and extent.<br />

1.4 SEISMIC DESIGN CATEGORIES<br />

A. Seismic protection for seismic concerns of all mechanical, electrical, and refrigeration systems shall meet<br />

minimum requirements of the local building code for the Seismic Design Category as described in the structural<br />

drawings.<br />

1.5 EQUIPMENT AND SYSTEMS PROTECTED BY SEISMIC RESTRAINT<br />

A. Equipment and systems protected by seismic restraint as required by the Building Code for the given seismic<br />

design category may include but not be limited to the following:<br />

1. Mechanical Systems (including owner supplied items)<br />

a. Gas Distribution Systems<br />

b. Domestic Water Supply Systems<br />

c. Sanitary Drain, Waste and Vent Piping Systems<br />

d. Oil Piping Systems<br />

e. Compressed Air Systems<br />

f. Roof Mounted HVAC Equipment<br />

g. Suspended HVAC Equipment<br />

h. Drop Box Diffusers<br />

i. Water Heaters<br />

j. Domestic Hot Water Storage Tanks<br />

k. Waste Oil Cooking Tank<br />

l. Hydronic Distribution Piping<br />

2. Electrical Systems (including owner supplied items)<br />

a. Conduit<br />

b. Bus Duct<br />

c. Cable Tray<br />

d. Panelboards<br />

e. Switchgear<br />

f. Light Fixtures<br />

g. Transformers<br />

3. Refrigeration Systems (including owner supplied items)<br />

a. Refrigerant Piping<br />

b. Condensate Piping<br />

c. Unit Coolers<br />

d. Compressor Racks or Compressor Houses<br />

e. Air-cooled Condensers<br />

f. Evaporative Condensers<br />

g. Cooling Towers<br />

h. Condenser Water Piping<br />

i. Condensing Units<br />

13080 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


1.6 RELATED WORK<br />

A. Housekeeping Pads<br />

1. The Seismic Restraint Manufacturer shall prepare housekeeping pad reinforcement and pad attachment details<br />

and design.<br />

2. Coordinate housekeeping pads with the Seismic Restraint Manufacturer and size to provide a minimum<br />

edge distance of ten (10) bolt diameters all around the outermost anchor bolt to allow development of full<br />

drill-in wedge anchor ratings. If cast-in anchors are to be used, size the housekeeping pads to accommodate<br />

the ACI requirements for bolt coverage and embedment.<br />

B. Supplementary Support Steel<br />

1. Contractor shall supply supplementary support steel for all equipment, piping, etc. including roof mounted<br />

equipment.<br />

PART 2 - PRODUCTS AND MATERIALS<br />

2.1 MANUFACTURERS<br />

A. Seismic restraint and flexible couplings shall be provided by the following manufacturers. No substitutions will be<br />

permitted.<br />

1. Mason Industries, Inc.<br />

a. Contact: Jim Sadler, (631) 348-0282.<br />

2. Amber/Booth Company, Inc.<br />

a. Contact: Chip Morrow, (973) 838-1780.<br />

3. Vibration Eliminator, Inc.<br />

a. Contact: Werner Stebner, (281) 639-7161.<br />

b. Email contact: wstebner@gmail.com<br />

B. All seismic restraints shall be of the same manufacturer and shall be certified by the manufacturer.<br />

2.2 NON-ISOLATED SEISMICALLY RATED ROOF CURBS<br />

A. Non-isolated seismically rated rooftop curb systems shall be provided under specification Section 07721 –<br />

“Manufactured Curbs”.<br />

2.3 FLEXIBLE PIPE CONNECTIONS<br />

A. Water Service<br />

1. For flanged connections – A double sphere arch rubber expansion joint constructed of molded reinforced<br />

neoprene with integral steel floating flanges. Connectors shall be suitable for a maximum working pressure<br />

(4 to 1 safety factor) of 150 psi and 225 degree F. Spring loaded control units shall be furnished to limit<br />

movement to within acceptable tolerances. As well as seismically rated for job site specialty application.<br />

2. For threaded connections – A double spherical rubber hose connector, constructed of molded neoprene, nylon<br />

cord reinforced, with female pipe unions each end. Connectors shall be suitable for a maximum working<br />

pressure (4 to 1 safety factor) of 150 psi and 225 degree F. Connectors shall have cable control units to<br />

limit movement to within acceptable tolerances. As well as seismically rated for job site specialty application.<br />

B. Compressed Air Service: For flanged connection – a flanged metal hose connector constructed of stainless steel<br />

hose and braid with carbon steel plate flanges. Connector shall be double braided with a minimum live length<br />

equal to four times the diameter. Connector shall be installed with the long axis perpendicular to the motion to be<br />

absorbed.<br />

1. For threaded connection – a metal hose connector constructed of stainless steel hose and braid with carbon<br />

steel NPT threaded end fittings. Connector shall be double braided and have a minimum live length equal<br />

13080 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


to four times the diameter. Connector shall be installed with the long axis perpendicular to the motion to be<br />

absorbed.<br />

C. General<br />

1. Flexible metal hose type joints may be used for aboveground or underground piping, up to 8" pipe diameter.<br />

Where permitted in other sections of these specifications, joints utilizing split-half couplings with<br />

grooved or shouldered pipe ends may be used.<br />

2.4 RESTRAINTS, BRACES, ANGLES<br />

A. Seismic Cable Restraints shall consist of galvanized steel aircraft cables sized to resist seismic loads with a<br />

minimum safety factor of two and arranged to provide all-directional restraint. Cables must be pre-stretched to<br />

achieve a certified minimum modulus of elasticity. Cable end connections shall be steel assemblies that swivel to<br />

final installation angle and utilize two clamping bolts to provide proper cable engagement. Cables must not be<br />

allowed to bend across sharp edges.<br />

B. Seismic solid braces shall consist of steel angles or channels to resist seismic loads with a minimum safety factor<br />

of 2 and arranged to provide all directional restraint. Seismic solid brace end connectors shall be steel assemblies<br />

that swivel to the final installation angle and utilize two through bolts to provide proper attachment.<br />

C. Steel angles, sized to prevent buckling, shall be clamped to pipe or equipment rods utilizing a minimum of three<br />

ductile iron clamps at each restraint location when required. Welding of support rods is not acceptable.<br />

D. Pipe clevis cross bolt braces are required in all restraint locations. They shall be special purpose preformed<br />

channels deep enough to be held in place by bolts passing over the cross bolt.<br />

E. Joist attachment hardware shall consist of 2 cast pieces. The top piece shall incorporate a groove that fits between<br />

the two angles making up the upper cord of the bar joist. Lower assembly shall neoprene friction pad. Top piece<br />

shall have threaded hole to allow attachment of cable brace assemblies.<br />

PART 3 - EXECUTION<br />

3.1 SWAY BRACES FOR MECHANICAL, ELECTRICAL, AND REFRIGERATION SYSTEMS AND<br />

EQUIPMENT<br />

A. Sway braces shall be installed to preclude damage during a seismic event. Bracing shall be installed in accordance<br />

with the seismic restraint manufacturer’s instructions and shop drawing submittals.<br />

3.2 PIPING AND CONDUIT PENETRATION REQUIREMENTS<br />

A. All piping 3 inches in diameter and smaller shall be installed with 1" clearance from all obstructions. A 2"<br />

clearance is required for pipe sizes larger than 3 inches.<br />

B. Insulated and un-insulated pipes and conduit passing through walls and partitions (except smoke and fire walls and<br />

partitions) shall be run through not less than No. 12 gauge steel pipe sleeves finishing flush with the finished wall<br />

surfaces. Piping and conduit shall be centered in the sleeves to assure free movement. Caulk between piping or<br />

conduit and sleeves.<br />

3.3 FLEXIBLE COUPLINGS OR JOINTS<br />

A. Where shown on drawings, flexible couplings shall be installed to preclude damage during a seismic event.<br />

Bracing shall be installed in accordance with the seismic restraint manufacturer’s instructions and shop drawing<br />

submittals.<br />

3.4 ANCHOR BOLTS<br />

13080 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


A. All floor or pad mounted equipment required by any Section of these specifications shall use cast-in-place or<br />

female wedge type anchor bolts. Anchor bolts must conform to ASTM A 307. Female wedge anchors shall have<br />

an evaluation report number from ICBO Evaluation Service. Anchor bolts shall have an embedded straight length<br />

equal to at least twelve times nominal diameter of the bolt. Anchor bolts shall conform to the applicable codes and<br />

standards for the various equipment weights or the manufacturer's installation recommendations, whichever is the<br />

more stringent.<br />

B. If beam clamps are used to hang piping, ducts or equipment, and at the point of seismic restraint, clamp bolt must<br />

have a single hardened point along with a 14 gauge metal strap that secures the beam clamp to the other truss side<br />

of beam. Hammer strap tightly to eliminate any potential beam slippage.<br />

3.5 COORDINATION WITH STRUCTURAL ENGINEER<br />

A. Overstressing of the building structure shall not occur because of overhead support of equipment. Contractor shall<br />

submit loads to the structural engineer of record for coordination purpose. Generally bracing may occur from:<br />

1. Flanges of structural beams.<br />

2. Upper truss chords in bar joist construction.<br />

3. Cast in place inserts or wedge type drill-in concrete anchors.<br />

3.6 INSTALLATION<br />

A. Install seismic protection systems in strict accordance with all applicable local, state, and/or federal codes.<br />

Installation shall also be in strict accordance with component manufacturer’s requirements and standards and with<br />

industry construction standards. Whenever conflicts occur between codes or standards and the manufacturer’s<br />

requirements, the more stringent shall apply.<br />

B. Anchor interior and exterior mounts and hangers.<br />

C. Install cables to prevent excessive seismic motion and arrange them in a manner such that they do not engage<br />

during normal operation.<br />

D. All anchoring fasteners must only use flat washers, Torquing data and requirements of bolts must be provided and<br />

installed as per seismic/wind engineers written specifications.<br />

3.7 VENDOR OBSERVATION<br />

A. Vendor Inspector: Employ a factory trained representative during construction to observe the work specified and<br />

to ensure that it conforms to the Contract Documents. Factory trained representative shall be a qualified person<br />

employed by the Seismic Restraint Manufacturer, who shall demonstrate competence and specialized experience,<br />

to the satisfaction of the engineer of record employed by the Seismic Restraint Manufacturer, for inspection of the<br />

seismic protection of mechanical, electrical and refrigeration systems.<br />

B. Inspection Reports: Ensure that the Inspection Report is furnished from the Vendor Inspector to the Engineer of<br />

Record employed by the Seismic Restraint Manufacturer. At the end of the work, ensure that a final, signed report<br />

is submitted by the Vendor Inspector, stating whether the work requiring vendor observation was, to the best of the<br />

Vendor Inspector’s knowledge, in conformance with the Contract documents. The Inspection Report shall be<br />

submitted as described above in “Submittals” paragraph.<br />

C. Discrepancies: Discrepancies shall be brought to the immediate attention of the Contractor for correction, and<br />

then, if uncorrected, to the Architect, Owner, and Engineer of Record employed by the Seismic Restraint<br />

Manufacturer.<br />

END OF SECTION<br />

13080 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 093011<br />

SECTION 13121 (13 3100) – FABRIC STRUCTURES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished Garden Center aluminum trusses and accessories to be installed by Contractor.<br />

2. Owner furnished shade cloth to be installed by Contractor.<br />

3. Visual Screening Fabric.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

2. Section 02823 - Ornamental Metal Fences and Gates: Shade cloth canopy truss support columns.<br />

1.2 DELIVERY, STORAGE, AND HANDLING<br />

A. Product Delivery: Aluminum Truss Supplier will deliver products to jobsite for Contractor to receive on delivery<br />

date established by Contractor. Contact Aluminum Truss Supplier to coordinate and establish product delivery<br />

date.<br />

B. Installation Drawings and Instructions: Delivered to Contractor with Owner furnished products.<br />

C. Product Packaging: Products will be packaged in manufacturer's standard cartons.<br />

1. Trusses: Four trusses per bundle. Trusses weigh approximately 3 pounds 8 ounces per lineal foot.<br />

2. Truss Hardware: Boxes approximately 24 inches x 8 inches x 20 inches.<br />

3. Shade Cloth: Boxes approximately 30 inches x 20 inches x 25 inches.<br />

D. Acceptance at Site: Receive, store, and protect products in compliance with the requirements of Section 01640<br />

and manufacturer’s recommendations.<br />

1. Verify quantity of products furnished with Bill of Material provided with Owner furnished products.<br />

2. Report discrepancies in product quantity delivered or damage to Wal-Mart Construction Division<br />

immediately, (479) 204-0704.<br />

3. Note description of product quantity discrepancies and/or product damage on Bill of Lading.<br />

4. Upon notification by Contractor, Owner will arrange for delivery of replacement products.<br />

E. Receive, store, and protect products in compliance with the requirements of Section 01640 and manufacturer’s<br />

recommendations.<br />

F. Protect roll materials from damage by storing on end.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner Aluminum Truss Supplier will furnish aluminum trusses and shade<br />

cloth for installation by Contractor.<br />

B. Descriptions and specifications of Owner furnished products are included as information to Contractor only and<br />

are not to be considered as Contractor requirements unless otherwise stated.<br />

C. Owner Aluminum Truss Supplier:<br />

1. Hendee Enterprises Incorporated, Houston, TX (800) 231-7275. Contact: Crystal Genovese<br />

walmart@hendee.com (713) 796-6119.<br />

13121 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


D. Quantity Furnished: Product quantities required are determined by Aluminum Truss Supplier.<br />

E. Aluminum Trusses:<br />

1. 12 inch high Truss System.<br />

2. Lengths: Furnished in standard lengths in two foot increments.<br />

3. Hardware: Mounting brackets, cross bracing, angle brackets, bolts, and washers.<br />

4. Color: Clear Aluminum.<br />

F. Shade Cloth: Vinyl impregnated woven polyester yarn, heat set for stability.<br />

1. Color: Spiced Sand, U.N.O.<br />

2. Shade Cloth Shade Factor: 45%.<br />

G. Visual Screening Fabric: Vinyl impregnated woven polyester yarn, heat set for stability.<br />

1. Color: Black.<br />

2. Shade Factor: 80%.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine conditions and adjacent areas where products and materials will be installed and verify that conditions<br />

conform to product manufacturer's requirements.<br />

3.2 INSTALLATION - ALUMINUM TRUSSES (BY CONTRACTOR)<br />

A. Coordinate location and installation of steel post columns provided in Section 02823.<br />

B. Install aluminum trusses in accordance with suppliers published instructions.<br />

C. Attach mounting brackets to Garden Center truss support columns.<br />

D. Attach one end of truss to mounting bracket. Hold opposite end of truss to other mounting bracket to determine<br />

required truss length. Cut truss to required length. Repeat for each truss requiring field cutting.<br />

E. Fit trusses into mounting brackets and attach.<br />

F. Install truss "X" bracing between trusses.<br />

G. Install shade cloth attachment tubing between truss mounting brackets.<br />

3.3 INSTALLATION - SHADE CLOTH (BY CONTRACTOR)<br />

A. Install shade cloth panels to aluminum truss system in accordance with suppliers published instructions.<br />

B. Each shade cloth panel installed individually to truss system by rope lacing in a zigzag pattern on all four sides of<br />

panel.<br />

C. Install rope lacing through grommets in shade cloth panel and around truss top chords and attachment tubing<br />

between trusses.<br />

3.4 INTERFACE WITH OTHER WORK<br />

A. Coordinate installation of light fixtures to aluminum trusses at locations indicated on Drawings.<br />

13121 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3.5 FIELD QUALITY CONTROL<br />

A. Inspect installation of all components and attachments.<br />

END OF SECTION<br />

13121 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II – NP 062411<br />

SECTION 13123 – GLAZED STRUCTURES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Factory fabricated Greenhouse glazed canopy system.<br />

2. Tubular steel framework and supports.<br />

3. Gable end fans.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A 307 - Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength.<br />

2. ASTM A 449 - Hex Cap Screws, Bolts and Studs, Steel, Heat Treated, 120/105/90 KSI Minimum Tensile<br />

Strength, General Use.<br />

3. ASTM A 500 - Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes.<br />

4. ASTM A 653 - Steel sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot-Dip Process.<br />

5. ASTM A 1008 - Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength<br />

Low-Alloy With Improved Formability, Solution Hardened, Baked Hardenable.<br />

6. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

C. American Welding Society (AWS):<br />

1. AWS D1.1 - Structural Welding Code.<br />

2. AWS D1.3 - Structural Welding Code - Sheet Steel.<br />

D. National Fire Protection Association (NFPA):<br />

1. NFPA 70 - National Electrical code.<br />

E. Related Requirements:<br />

1. Section 02823 - Ornamental Metal Fences and Gates: Ornamental metal fences and gates at glazed canopy.<br />

2. Section 03310 - Cast-In-Place Structural Concrete: Concrete for footings and exterior slabs.<br />

3. Section 03312 - Cast-In-Place Concrete Slabs (Interior): Concrete for interior slabs.<br />

4. Section 05300 - Metal Deck: Garden Center metal canopy deck.<br />

5. Section 07620 - Sheet Metal Flashing and Trim: Flashing at interface between building and glazed canopy.<br />

6. Section 13121 - Fabric Structures: Garden Center aluminum trusses and shade cloth.<br />

7. Section 13900 - Fire Suppression: Fire sprinkler system installed in glazed canopy structure.<br />

8. Section 15100 - Building Services Piping: Storm water piping for glazed canopy gutters and trench drains.<br />

9. Section 15700 - Heating, Ventilating, and Air Conditioning Systems. Garden Center circulating air flow<br />

fans.<br />

10. Section 16100 - Wiring Methods: Electrical system installed in structure.<br />

11. Section 16500 - Lighting: Lighting fixtures installed in glazed canopy structure.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Product Data: Manufacturer data for glazed structure material.<br />

13123 - 1<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


C. Shop Drawings:<br />

1. Assembly dimensions, locations and spacing of structural members, columns, trusses, connections and<br />

attachments.<br />

2. Floor plan of area showing locations and types of columns, roof structure and roofing.<br />

3. Roof, skirt and gable end dimensions, panel materials and layout, general construction details and methods<br />

of attachment.<br />

4. Indicate welds by standard welding symbols adopted by AWS.<br />

5. Shop drawings shall be prepared under the direction of a Professional Civil or Structural Engineer<br />

registered in State in which the Project is located.<br />

D. Calculations: Structural calculations for system structure.<br />

E. Submit all submittals within 30 working days of Contract date.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Transport, handle, store, and protect products in compliance with the requirements of Section 01600.<br />

B. Stack material to prevent twisting, bending, or abrasion, and to provide ventilation. Comply with manufacturer's<br />

published instructions for job site storage, handling, and protection.<br />

C. Prevent contact with materials during storage which may cause discoloration or staining.<br />

D. Do not overload roof structure with stored materials. Storage or walking on completed roof surfaces not permitted.<br />

1.5 WARRANTY<br />

A. Glazed Canopy System: Correct defective Work, including leaks, discoloration, and excessive thermal or<br />

structural movement, for one year after Date of Substantial Completion.<br />

PART 2 - PRODUCTS<br />

2.1 SYSTEM DESCRIPTION AND DESIGN REQUIREMENTS<br />

A. Glazed Canopy Structure: Manufacturer designed and shop fabricated integral sloped canopy system. Glazed<br />

canopy system consists of fiberglass and metal roof panels, polycarbonate skirts and gable ends; sheet metal<br />

gutters and gutter drops; structural framework including column supports; and gable end fans.<br />

B. Garden Center door surrounds including polycarbonate panels, posts and headers, and girts for all Garden Center<br />

doors including remote (shade cloth area) doors shall be provided by the glazed canopy manufacturer.<br />

C. Glazed Canopy System, including gable fans, shall be furnished and installed by one supplier.<br />

D. Glazed Canopy Structure Design Requirements:<br />

1. Comply with the current edition of the National Greenhouse Manufacturers Association "Standards for<br />

Design Loads in Greenhouse Structures".<br />

2. Design structural components and develop shop drawings under direct supervision of a professional<br />

engineer licensed in the State where Project is located.<br />

3. Evaluation Report: The product proposed for use from the specified products shall have a current<br />

Evaluation Report (ICC-ER) by the International Code Council Evaluation Service (ICC-ES) showing<br />

compliance with the International Building Code or the model code within the jurisdiction of the project<br />

and as required by the Authority Having Jurisdiction.<br />

4. Design Data: Conform to applicable local code requirements for roof dead load, roof live load, collateral<br />

load, wind load, seismic load, and snow load.<br />

5. Glazed canopy structure shall be designed to provide for automatic sprinkler system as specified in Section<br />

13900.<br />

13123 - 2<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


6. Work within this Section shall comply with national code design limitations for fiberglass roof panel area<br />

as shown on Drawings as well as with state and local model codes.<br />

E. Products Requiring Electrical Connection: Listed and classified by testing firm acceptable to Authority Having<br />

Jurisdiction as suitable for the purpose specified and indicated.<br />

2.2 MANUFACTURERS<br />

A. Glazed Canopy: Subject to compliance with project requirements, provide products by the following<br />

manufacturers:<br />

1. Hendee Enterprises Incorporated, Houston, TX (800) 231-7275. Contact: Crystal Genovese<br />

walmart@hendee.com (713) 796-6119.<br />

B. Substitutions: Comply with the requirements of Section 01600.<br />

2.3 CANOPY<br />

A. Roof Panels:<br />

1. Fiberglass (FRP) Panels: Provide one of the following FRP panel products:<br />

a. 1040 Forty Series Roofing Panels by Resolite, Zelienople, PA, (724) 452-6800.<br />

1) Weight: 10 oz per square foot.<br />

2) Fiberglass Material: FS25A translucent.<br />

3) Profile: 7.2 inches x 1.5 inches.<br />

4) Finish: EMB/Smooth.<br />

5) Color: 31 White.<br />

6) Light Transmittance: 40%.<br />

b. Series 250 PFR by Enduro Systems, Inc., Tuff Span, Houston, TX, (713) 358-4169.<br />

1) Profile: 7.2 inches x 1.5 inches.<br />

2) Finish: EMB/Smooth.<br />

3) Color: Tuff Span N2002T.<br />

4) Light Transmittance: 40%.<br />

2. Metal Panels:<br />

a. Profile: 7.2 inch x 1-1/2 inch rib height, 36 inch width.<br />

b. Thickness: 24 gage.<br />

c. Factory Finish: Fluorpolymer coating containing a minimum of 70 percent Pennwalt Kynar 500<br />

resin with a minimum of 1.2 mil dry film thickness.<br />

d. Color: Manufacturer's standard "White".<br />

e. Subject to the specified requirements, provide one of the following ribbed galvalume steel sheet<br />

metal products:<br />

1) Mega-Rib by McElroy Metal, Bossier City, LA, (800) 950-6531.<br />

2) Hefti-Rib by Fabral Metal Roof and Wall Systems, Lancaster, PA, (800) 477-2741.<br />

3) I-C72 by Metal Sales, Longmont, CO, (800) 289-7663.<br />

3. Substitutions: Comply with the requirements of Section 01600.<br />

B. Skirt, Gable End, and Door Surround Glazing: Provide the following:<br />

1. Lexan Thermoclear LTT2R8 by SABIC Innovative Plastics, Pittsfield, MA, (800) 323-3783.<br />

a. Material: Approved Class CC-1 polycarbonate.<br />

b. Thickness: 8mm.<br />

c. Color: Opal White.<br />

d. Flame Spread Rating: 25 or less as tested in accordance with ASTM E 84.<br />

2. Substitutions: Comply with the requirements of Section 01600.<br />

C. Structure Columns, Posts, Trusses, Purlins, and Bridging:<br />

1. Provide welded one or two piece shop prefabricated galvanized structural trusses and tubular steel columns<br />

and framing.<br />

2. Secondary framing may include extruded aluminum members with mill finish.<br />

13123 - 3<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


3. Materials:<br />

a. Steel Plates Less Than 3/16 Inch Thick: ASTM A 1008, Grade 50.<br />

b. Steel Tubes Less Than 3/16 Inch Thick: ASTM A 500, Grade A.<br />

c. Cold-Formed Shop Fabricated Steel Shapes: ASTM A 1008, Grade 50, F y =50 ksi, F u =65 ksi.<br />

d. Aluminum Shapes: Alloy 6063-T6.<br />

4. Steel Plate and Tube Galvanizing: ASTM A 653, G90.<br />

D. Fasteners:<br />

1. Bolts: Type as appropriate for design requirements.<br />

a. ASTM A 307 hot dip galvanized bolts or stainless steel fasteners.<br />

b. ASTM A 449 tempered steel bolts and studs.<br />

2. Screws: Galvanized self drilling with hex washer head.<br />

E. Gutters: Minimum 14 gage galvanized formed sheet steel.<br />

F. Downspouts: Minimum 24 gage galvanized formed sheet steel.<br />

G. Flashing and Gasketing: Sheet metal flashing and resilient gasketing to provide watertight installation.<br />

H. Additional Items:<br />

1. Provide additional components including brackets, spacers, connectors, and other items required for<br />

erection.<br />

2. Items shall be galvanized or of corrosion resisting materials.<br />

3. Provide miscellaneous items required for complete installation including base plates, anchor bolts, gutter<br />

boots, fasteners and other items recommended by the manufacturer.<br />

I. Welding: AWS D1.1 and AWS D1.3 type required for materials being welded.<br />

J. Framing Finish: Finish steel by hot dip galvanizing after fabrication or fabricate using pre-galvanized tubing with<br />

welded joints treated by shop applied thermo spray zinc coating process using zinc wire to provide rust protection.<br />

2.4 FANS<br />

A. Gable Fans (GF): Gable fans shall be located and as scheduled on Mechanical Drawings.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine conditions and adjacent areas where glazed canopy system will be installed. Verify that conditions<br />

conform to product manufacturer's requirements and installation conditions. Do not proceed until unsatisfactory<br />

conditions have been corrected.<br />

3.2 ERECTION - FRAMING<br />

A. Erect framing in accordance with manufacturer's published instructions.<br />

B. Provide for erection wind loads. Provide temporary bracing to maintain structure plumb and in alignment until<br />

completion or erection and installation of permanent bracing.<br />

C. Set column base plates in non-shrink grout to achieve full plate bearing.<br />

D. Do not field cut or alter structural members without approval.<br />

3.3 INSTALLATION<br />

A. Install glazed panels in accordance with manufacturers published instructions.<br />

13123 - 4<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


B. Coordinate with installation of related flashings.<br />

C. Seal roof, skirt and gable end glazing to provide weathertight installation.<br />

D. Install flashing, gasketing, gutters, and additional items.<br />

E. Gable Fans: Mount gable end fans on interior side of canopy gable exhausting to the outside of the building as<br />

shown on Drawings.<br />

3.4 INTERFACE WITH OTHER WORK<br />

A. Coordinate installation of the following items at locations indicated on Drawings.<br />

1. Fence and gate post locations with glazed canopy structure columns.<br />

2. Concrete footing locations with glazed canopy structure columns and posts.<br />

3. Sheet metal flashing at interface between building and glazed canopy.<br />

4. Storm water piping with gutter openings for rain water leaders and locations of glazed canopy structure for<br />

attachment of rainwater leaders.<br />

5. Lighting fixtures and attachment to glazed canopy structure and supports.<br />

3.5 FIELD QUALITY CONTROL<br />

A. Inspect glazed canopy structure installation and installation of associated components.<br />

B. Test all operating items and assure proper performance.<br />

3.6 CLEANING<br />

A. Remove any protective material from prefinished surfaces.<br />

B. Wash exposed surfaces; wipe surfaces clean.<br />

C. Remove excess glazing sealant by methods recommended by glazing manufacturer.<br />

D. Touch up damaged finishes. Remove and replace components that cannot be satisfactorily repaired.<br />

E. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and apply galvanizing repair<br />

material.<br />

END OF SECTION<br />

13123 - 5<br />

Walmart SC #5641 – La Habra, CA PWO – 04/11/11


UniSpec II 012811<br />

SECTION 13425 (26 2710) - SUB-METERING INSTRUMENTATION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Sub-metering instrumentation system including data logger and CT sub-meters furnished by Owner for installation<br />

by Contractor.<br />

2. Main demand sub-meter for the sub-metering instrumentation system furnished and installed by Owner.<br />

3. Low voltage wiring, terminations, and accessories for sub-meter system.<br />

B. Related Requirements:<br />

1. Section 16050 - Basic Electrical Materials and Methods.<br />

2. Section 16100 - Wiring Methods.<br />

3. Section 16405 - Electrical Distribution Center (EDC).<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI C 12.1 - Electric Meters Code for Electricity Metering.<br />

2. ANSI C 12.20 - Standard for Electricity Meter - 0.2 and 0.5 Accuracy Classes.<br />

C. Underwriters Laboratories (UL):<br />

1. UL 508 - Standard of Safety for Industrial Control Equipment.<br />

1.3 CLOSEOUT SUBMITTALS<br />

A. Closeout Submittals: Comply with the requirements of Section 01770.<br />

1. Record Letter of Conformance: Submit using the format provided at the end of this Section.<br />

B. Submit the following reports to Energy ICT at walmart@energyict.com as well as recipients specified in Division<br />

01.<br />

1. Data logger store load report.<br />

2. Data logger screen captures.<br />

1.4 APPROVED SUB-METER SYSTEM CONTRACTORS<br />

A. The General Contractor shall select one of the following sub-meter system contractors for installation of the submetering<br />

system.<br />

1. Nexrev, 601 Development Drive, Plano, TX 75074. Contact: Ken Logsdon, kenlogsdon@nexrev.com. Office:<br />

(972) 578-0505 Cell: (318) 840-5536.<br />

2. Besco, 629 Broadway NW, Knoxville, TN 37917. Contact: Tom Ryan, tryan@besco.com. Office: (865)<br />

342-5706 Cell: (865) 740-6709.<br />

3. Jett Electric, LLC, 7806 N. Hwy 81, Duncan, OK 73533. Contact: David Meadows, submetering@jettelectricinc.com.<br />

Office: 580-251-9858 Cell: 580-678-1696.<br />

4. Ellsworth Electric, 4425 N. Hwy. 81, Duncan, OK. Contact: Shane Elam, shane@ellsworthelectric.com.<br />

Office: (800) 725-2967 Cell: (580) 656-1886.<br />

1.5 WARRANTY<br />

13425 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


A. Provide 1 year warranty on installation. The warranty shall cover the following:<br />

1. Labor and service due to failure for 1 year beyond the Grand Opening date.<br />

B. Provide a minimum 24 hr response time to warranty issues.<br />

C. Warranty on Owner furnished equipment will be provided by Wal-Mart Supplier.<br />

1.6 PERMITS<br />

A. Obtain necessary permits, licenses, approvals, and certificates of inspection as required by Authorities Having Jurisdiction<br />

for a completed project.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Products Furnished and Installed by Owner: The Owner’s Supplier will furnish and install the main demand submeter<br />

as specified herein.<br />

B. Products Furnished by Owner and installed by Contractor: Under provisions of 01640, sub-metering instrumentation<br />

equipment as specified herein will be furnished by Owner’s Supplier including data logger and CT sub-meters<br />

for installation by the Contractor.<br />

C. Owner’s Supplier: Owner’s Supplier will be the EDC vendor as specified in Section 16405.<br />

D. Descriptions and related provision for products and equipment by Owner’s Supplier as specified hereinafter are included<br />

as information to the Contractor only and not to be considered as Contractor requirements unless otherwise<br />

stated.<br />

2.2 MAIN DEMAND SUB-METER (OWNER FURNISHED AND INSTALLED)<br />

A. Manufacturer and Product Model: Square D model PM 800 Series.<br />

1. Communications:<br />

a. One RS 485 port, two digital inputs, and one digital output.<br />

b. Modbus protocol for integration with Energy Management System.<br />

c. 1 pulse output for kWh-pulsing or external controlled output.<br />

d. 2 inputs for demand input synchronization.<br />

2. Performance and Accuracy:<br />

a. ANSI C 12.20.0.5 Accuracy Class.<br />

b. Measures per phase voltage, current, peak current, watts, VARs, kWh.<br />

c. Measure and display THD, frequency, power factor.<br />

3. Display:<br />

a. Backlit LCD display.<br />

b. Can display five lines of information simultaneously.<br />

c. Tactile buttons for menu operation.<br />

4. Input Voltage Characteristics:<br />

a. Measure up to 480V AC Direct.<br />

b. Measure up to 1.6MV AC with external VT.<br />

c. Impedance 2MOhms (phase to phase) / 1MOhm (phase to neutral).<br />

d. Frequency Range (45 to 65Hz).<br />

5. Input Current Characteristics:<br />

a. CT Ratings: Primary Adjustable from 5A to 32767A.<br />

b. Measurement Input Range: 5mA to 6A.<br />

c. Impedance: Less than .1 Ohms.<br />

d. Load: Less than .15VA.<br />

13425 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


2.3 DATA LOGGER (OWNER FURNISHED)<br />

A. Manufacturer and Product Model: Energy ICT model RTU+ Server<br />

1. Hardware and Software<br />

a. LED indicators for the following:<br />

1) One power on indicator.<br />

2) Two ethernet connectivity indicators (one for each channel).<br />

3) Two RX/TX indicators (one for transmission, one for receiving).<br />

4) Eight digital I/O indicators (four for digital inputs, four for digital outputs).<br />

5) Two application dependent LEDs.<br />

6) One “watchdog” monitoring indicator.<br />

b. Minimum of two USB 2.0 connectors.<br />

c. Memory: 4GB of compact flash memory with a 1.4 GB divided rescue partition.<br />

d. Operating System: Linux OS with Derby Database.<br />

e. Data collection software with extended protocol library.<br />

2. Communications:<br />

a. One RS 485 port.<br />

b. Modbus protocol.<br />

3. Input and Output Characteristics:<br />

a. Ability to collect analog or digital data from 32 inputs.<br />

b. VGA connector for local connectivity by laptop.<br />

4. Pre-Installed Channel Labels:<br />

a. Pre-programmed drop down menus for each channel.<br />

b. Pre-programmed channel labels shall include labels from the Owner’s approved list.<br />

2.4 CT SUB-METERS (OWNER FURNISHED)<br />

A. Manufacturer and Product Model: Veris Industries model H8036<br />

1. Characteristics:<br />

a. Three split-core CTs.<br />

b. Electronics embedded inside of master CT sub-meter.<br />

c. Conform to UL 508 safety standards for industrial control equipment.<br />

d. Internally isolated to 2000V AC.<br />

e. Meter case isolation shall be 600V AC.<br />

2. Performance and Accuracy:<br />

a. Measure RMS power, instantaneous demand, and consumption.<br />

b. Accept directly any voltage input up to 480V AC.<br />

c. Accuracy to +/- 1% from 10% to 100% of the rated current.<br />

d. Conform to ANSI C 12.1 metering standards.<br />

3. Communications:<br />

a. Report serially over an RS-485 network.<br />

b. Use the Modbus/RTU protocol.<br />

c. kWh variable shall be stored in non-volatile memory.<br />

2.5 REGULATORY REQUIREMENTS<br />

A. Sub-metering system components shall be UL listed for use as an integral part of the Sub-metering system.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION BY OWNER<br />

A. Owner’s Supplier will:<br />

1. Provide (furnish and install) main demand sub-meter specified herein.<br />

2. Furnish the data logger and ship to the General Contractor for installation by the sub-meter contractor.<br />

a. Stencil a location for the data logger to be installed.<br />

13425 - 3<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


. Locate data logger within 3 feet from the EMS.<br />

3. Furnish CT sub-meters.<br />

a. Install CT sub-meters that are located in the main EDC1.<br />

b. Install the conductors through the center of each CT sub-meter installed. Conductors shall not be in<br />

contact with the CT sub-meter.<br />

c. Furnish all remaining CT sub-meters and ship to the General Contractor for installation by the submeter<br />

contractor.<br />

4. Install locking breakers for CT sub-meter as shown on drawings.<br />

5. Assign channel numbers to each CT sub-meter as shown on drawings.<br />

6. Each CT sub-meter installed by the EDC vendor shall be labeled. Labels shall include:<br />

a. Modbus amperage.<br />

b. Modbus address (CT sub-meter number).<br />

c. Modbus description (Panel or load served).<br />

EXAMPLES: 100A CT26 AHU2 or 100A CT27 AHU3<br />

3.2 INSTALLATION BY CONTRACTOR<br />

A. The sub-meter contractor selected by the General Contractor shall:<br />

1. Obtain the latest Sub-Metering Programming Guide prior to installation. Obtain guide from Energy ICT at<br />

walmart@energyict.com.<br />

2. Install CT sub-meters as shown on Drawings. Install the conductors through the center of each CT submeter<br />

installed. Conductors shall not be in contact with the CT sub-meter.<br />

3. Install data logger. Mount data logger in the location stenciled in by the EDC vendor and located not more<br />

than 3 ft. from the EMS.<br />

4. Provide low voltage wiring and required accessories.<br />

5. Make terminations and connections to EMS system. Use Belden 1120A cable to connect to EMS system.<br />

6. Assign channel numbers for field installed CT sub-meter.<br />

7. Label each CT sub-meter installed by the sub-meter Contractor. Labels shall include:<br />

a. Modbus amperage.<br />

b. Modbus address (CT number).<br />

c. Modbus description (Panel or load served).<br />

EXAMPLES: 100A CT26 AHU2 or 100A CT27 AHU3<br />

13425 - 4<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


8. Make final connections to the data logger.<br />

9. Provide a cord and plug for the data logger.<br />

10. Use heat shrink on wire terminations.<br />

11. Label each wire a minimum of one inch from end, indentifying cable.<br />

12. Where required, use 3M Scotchlok type interconnects. Wire-nuts are not allowed.<br />

13. Program the data logger in accordance with the Programming Guide<br />

a. Configure channel functions. Set each channel to the modbus master protocol.<br />

b. Configure channel parameters. Set proper register settings for each channel.<br />

c. Configure channel names and units. Channels are reserved and shall be configured as shown on the<br />

latest EICT load report. The load report can obtained from the Walmart Energy Department.<br />

14. Verify closure of the digital inputs on the data logger.<br />

15. Verify that data logger demand display matches the EMS.<br />

16. Verify that all channels are monitored accurately.<br />

17. Reports: Submit as required in Part 1.<br />

a. Prepare load report in Microsoft Excel format provided by Owner.<br />

b. Submit load report as a PDF document.<br />

c. Provide screen captures as follows:<br />

1) Configuration channel parameters.<br />

2) Configuration channel functions.<br />

3) Status page.<br />

3.3 FIELD QUALITY CONTROL<br />

A. Functional Performance Testing (FPT): FPT will be conducted by Wal-Mart Engineer of Record at no cost to<br />

Contractor in accordance with Section 01454. FPT will be performed after Wal-Mart possession date.<br />

END OF SECTION<br />

13425 - 5<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 13425 – SUB-METERING INSTRUMENTATION<br />

Project Location:<br />

Date:<br />

(City & State)<br />

Project Number:<br />

Store Number:<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 – Contract Closeout.<br />

The undersigned hereby declares that the Sub-metering instrumentation systems (hereafter referred to as the “Systems”)<br />

is installed and is in general conformance with the Contract Documents, applicable Codes, and shop drawings. The “Systems”<br />

have been provided and placed in operational condition in accordance with the manufacturer's published instructions<br />

and the Contract Documents.<br />

____________<br />

(Contractor Signature)<br />

____________ Phone Number: ( )<br />

(Contractor name and address)<br />

Recommendation of Acceptance:<br />

This Recommendation of Acceptance is provided as a Record Document in accordance with Section 01770 – Contract Closeout.<br />

We recommend Wal-Mart accept the installation of the “Systems” (as referenced above). The “Systems” are found to<br />

be in general conformance with the Contract Documents, and Approved Drawings. This recommendation is based on MEP<br />

Site Observation and Functional Performance Test witnessed on ___________________ (Report Date), and follow up verification<br />

of identified issues conducted on ___________________ (Trip Date, Report Date).<br />

While this review is an integral part of this project, it does not relieve the Contractor of their responsibility to comply with<br />

the applicable provisions of the Contract Documents along with the mandated codes and standards. These examinations shall<br />

not be construed as a check of every item nor does it prevent Authorities Having Jurisdiction from hereafter requiring corrections<br />

of errors in plans or installation.<br />

WAL-MART’S MECHANICAL CONSULTANT:<br />

(Wal-Mart’s Mechanical Consultant Signature)<br />

Phone Number: ( )<br />

(Wal-Mart’s Mechanical Consultant name and address)<br />

13425 - 6<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 022511<br />

SECTION 13810 (25 5100) - ENERGY MANAGEMENT SYSTEM (EMS)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes: Complete Energy Management System (EMS)<br />

1. Owner furnished, Contractor installed energy management equipment.<br />

2. Contractor furnished and installed conduit and related fittings, bushings, wire ties, fasteners, bolts, panduit<br />

labels, hangers, and wire connectors.<br />

B. Related Requirements:<br />

1. Section 06100 - Rough Carpentry: Installation of 3/4-inch plywood backboard as shown on drawings.<br />

2. Section 01640 - Owner Furnished Products.<br />

3. Section 07840 – Firestopping<br />

4. Section 15700 - Heating, Ventilating, and Air Conditioning Equipment.<br />

5. Section 13425 – Sub-Metering Instrumentation.<br />

6. Division 16: 120 VAC control wiring.<br />

7. Division 16: Transformers, interface panels, phase loss sensor, and terminate all 120 VAC control wiring<br />

for Energy Management.<br />

8. Division 16: 120 VAC Dedicated circuit for power to system and a 480 VAC 3 phase dedicated circuit for<br />

phase monitor voltage sensing.<br />

9. Section 16405 - Electrical Distribution Center: Pre-installed equipment and wiring as part of the electrical<br />

distribution center.<br />

C. Contractor Responsibilities:<br />

1. Coordinate release of Owner furnished equipment with Wal-Mart Mechanical Services Department.<br />

2. Install Energy Management System equipment scheduled or shown on drawings and described in this<br />

Section.<br />

3. Provide (furnish and install) conduit and related fittings, bushings, wire ties, fasteners, bolts, panduit labels,<br />

hangers, and wire connectors<br />

4. Make terminations to Owner furnished equipment.<br />

1.2 CLOSEOUT SUBMITTAL<br />

A. Record Letter of Conformance: Submit Contractor’s Record Letter of Conformance in accordance with Section<br />

01770 and on the forms attached at the end of this section.<br />

B. Energy Management Punch List: Submit completed punch list to Wal-Mart Stores Inc., 2001 SE 10th Street, Bentonville,<br />

AR 72712-0550, Attention: Mechanical Services Department Construction Manager, for verification of<br />

completion.<br />

C. EMS Start-Up Report: Submit completed report Wal-Mart Stores, Inc., 2001 SE 10 th Street, Bentonville, AR<br />

72712-0550, Attention: Mechanical Services Department Construction Manager, for verification of completion.<br />

D. As-Built Drawings:<br />

1. Provide in the main EDC framed or laminated as-built drawings for Building Automation System<br />

communication loop.<br />

2. Provide near the refrigerated case input controller backboard, framed or laminated as-built drawings of the<br />

layout of refrigerated case module communication loop and sensors connected to refrigerated case input<br />

controllers.<br />

1.3 QUALITY ASSURANCE<br />

A. Provide one qualified technician available to handle emergencies connected with Energy Management work from<br />

the time job begins until the end of the 90 day warranty.<br />

13810 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Contractor Qualifications: Use manufacturer approved installers.<br />

1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Section 01600 – Product Requirements: Transport, handle, store, and protect products.<br />

B. Handle, deliver, and store in manufacturer's original packaging, following manufacturer's recommendations.<br />

C. Store in a dry area and in a manner to prevent damage.<br />

D. Equipment shall remain boxed until ready for installation.<br />

E. Notify Owner of equipment received from carrier in damaged conditions and shortages. Obtain verification of<br />

damage from carrier’s truck driver.<br />

1.5 WARRANTY<br />

A. Provide warranty and service on all equipment and materials installed. Warranty shall include failures during installation<br />

and for 90 days beyond store Grand Opening date. Warranty shall include labor and parts for equipment<br />

covered under the specifications. Owner’s EMS Supplier will furnish replacement parts for failures of Owner furnished<br />

equipment parts during installation period and for one year beyond store Grand Opening date. Obtain replacement<br />

parts from EMS Supplier. Owner will not pay additional cost associated with repair or replacement of<br />

materials and parts during the warranty period. Additional cost attributed to equipment failures shall be handled directly<br />

with the EMS Supplier.<br />

1. In the event the Contractor fails to respond to emergency calls or fails to perform required maintenance or<br />

repairs during a warranty period, the Owner will have the right to have the repair or maintenance performed<br />

by another contractor. In this case, the Contractor agrees to pay Owner the involved amount of the services<br />

performed plus 15 percent. Maximum response time to emergency calls shall be as follows:<br />

a. Building Automation System - 8 hours<br />

b. Refrigeration Control System - 2 hours<br />

2. If the Contractor subcontracts the warranty work, the 90-day warranty responsibility remains with the<br />

primary Contractor. The Contractor shall resolve all payments between the two parties. The Owner will not<br />

be involved in resolving payment issues. If the Energy Management Contractor fails to respond to warranty<br />

calls, Wal-Mart will remove that contractor from the New Store Bid List until such a time when all disputes<br />

or claims are settled.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner’s Energy Management Supplier will furnish Energy Management System equipment scheduled or shown<br />

on drawings under provisions of Section 01640 for installation by the Contractor. EMS supplier and contact information<br />

is as follows:<br />

B. Novar:<br />

1. General Inquiries: (800) 741-7795.<br />

2. Account Manager: Steve Toth (479) 254-7460.<br />

2.2 ENERGY MANAGEMENT SYSTEM EQUIPMENT (OWNER FURNISHED/CONTRACTOR INSTALLED)<br />

A. Energy monitoring and control system components shall be as indicated on Drawings.<br />

2.3 ASSOCIATED EMS MATERIALS (CONTRACTOR FURNISHED AND INSTALLED)<br />

A. Conduit and Accessories: Conduit, and associated fittings and boxes shall conform to requirements of Section<br />

16100. Provide type and size as appropriate for conditions and locations as shown on the drawings.<br />

13810 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Current Transducers: Provide revenue-grade current transducers by the EMS Supplier. For pricing and ordering information<br />

contact EMS Supplier.<br />

C. For replacement of damaged parts, provide controls manufactured by the EMS Supplier. For pricing and ordering<br />

information, contact EMS Supplier.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install EMS components in accordance with EMS Supplier installation instructions and make 24 VAC control<br />

terminations as required.<br />

B. Address EMS equipment and controllers and mark on equipment label.<br />

C. In portions of installation where conduit is not necessary, tie wrap cables every 36 inches or a minimum distance<br />

of the bar joist spacing. Cables shall be supported by the building structure.<br />

D. Provide wire ties for EMS cable. Colors shall be black UV resistant for RTU and sensor mast assembly, white for<br />

inside store in open ceilings, and any color in EDC houses and in EMS equipment.<br />

E. Install Energy Management Sensors where shown on drawing or to EMS Supplier installation and hardware<br />

mounting procedures.<br />

F. Verify proper Application Specific Controllers are installed in equipment in accordance with EMS Supplier installation<br />

and hardware mounting procedures.<br />

G. Generic Input/Output Controller (IOC):<br />

1. Ground IOC with #12 green awg wire.<br />

2. IOC legend shall be typed<br />

3. IOC lock down screws shall be tightened<br />

H. Global Network Controller (GNC):<br />

1. Provide a solidly grounded green insulated conductor, minimum size of #12 AWG, from GNC to system<br />

ground buss at main distribution board.<br />

2. Mount GNC display 60 to 72 inches from finished floor, at eye level for the average height person.<br />

3. Provide required clearances for GNC Ethernet connection.<br />

4. GNC lock down screw shall be tightened.<br />

I. Cable:<br />

1. Provide communication cable between network devices.<br />

2. Do not splice EMS cables for EMS components inside or 5 feet or less outside the building.<br />

3. Splices shall be soldered, heat shrinked, and concealed in a junction box.<br />

4. Cables from rack house to condensers shall be in conduit or sealtite.<br />

5. Cables shall be sealed in roof top unit. (Duct seal, caulk, or other type of sealant.)<br />

6. Cable shall have heat shrink at terminating ends. (No tape allowed.)<br />

7. No drooping or excessive sagging cables.<br />

8. No cable shall run though a raw metal edge hole. Use bushings and chase nipples as needed.<br />

9. Fire rated and sheetrock walls that have EMS cables passing through them shall have an EMT pipe sleeve<br />

with bushings on the ends. Fire caulk will be provided by others.<br />

J. Outdoor Assembly:<br />

1. Mount outdoor assembly to 1-1/4 inch rigid conduit through roof (provided by others).<br />

2. Install sensor assembly 5 feet above roof and a minimum of ten feet from edge of roof or from HVAC<br />

equipment.<br />

13810 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3. On old work when a roofer is not on site, bolt mast on back wall with 3/8” all thread. Check with Wal-Mart<br />

Construction first for direction.<br />

K. Conduit:<br />

1. EMT Conduit:<br />

a. The number of conductors permitted in single tubing shall not exceed the percentage fill listed in<br />

NEC.<br />

b. There shall be no more than the equivalent of four-quarter bends (360 degrees total) between pull<br />

points.<br />

c. Bends in the tubing shall be made so that the tubing will not be damaged and the internal diameter<br />

of the tubing will not be effectively reduced.<br />

d. All cut ends of tubing shall be reamed to remove rough edges.<br />

e. Boxes and fittings shall comply with NEC.<br />

f. Tubing shall be supported at least every 10 feet and within 3 feet of junction boxes or devices<br />

2. Armored Cable:<br />

a. Type AC cable shall be secured by approved staples, hangers, and straps, as not to damage the cable,<br />

at intervals not more than 4 1/2 feet and within 12 inches of junction box or other device<br />

b. Fittings shall be used at all ends of armored cables and meet NEC specifications.<br />

c. Bends shall be made so as not to damage cable.<br />

3. Run conduit from zone sensor directly to junction box and use flex conduit into the roof top unit.<br />

4. Run conduit along bar joist for communication loop and clamp securely.<br />

5. Provide panduit in electrical rooms and refrigerated case input controller mounting area where necessary.<br />

L. Bushings:<br />

1. Provide properly bushed opening for raceways ending as open conduit.<br />

2. Cables shall pass through a bushing into the roof top unit.<br />

M. Light Dimming:<br />

1. Tie light dimming fixtures together by conduit, flex, or box 14 gauge wire or larger.<br />

2. Home run to dimming control shall be 14 gauge or larger in conduit or flex.<br />

3. MC cable is permitted for connecting light fixtures together for low voltage control purposes.<br />

4. Separation between lighting power supply wiring and lighting control wiring shall comply with NEC.<br />

3.2 IDENTIFICATION<br />

A. Label refrigeration sensors at location in cases with electronic, permanent labels.<br />

B. Provide electronic, permanent labels with 3/4 inch nominal size numbers corresponding to associated rooftop unit<br />

for zone temperature sensors.<br />

C. Label each wire a minimum of one inch from end, identifying cable.<br />

D. Label breakers for Energy Management System with orange stickers: “DO NOT TURN OFF!”<br />

3.3 CLEANUP<br />

A. During the course of the Work, the area in which the Contractor is working shall be kept in an orderly, reasonably<br />

clean condition. Keep gang boxes, spools of wire, and boxes off of sales floor. Tools, supplies, etc. shall remain<br />

only as long as they are in use.<br />

3.4 START-UP<br />

A. Final payment will not be made until start-up reports and EMS Letter of Conformance are submitted.<br />

B. The Contractor shall schedule and coordinate start-up.<br />

C. Equipment installation shall be complete and made ready for start-up as required for functioning and start-up procedures.<br />

13810 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


D. Failure by the Contractor to have equipment ready for start-up at scheduled time will result in reimbursement by<br />

the Contractor to Wal-Mart of costs plus 10 percent incurred by required attendees.<br />

E. Fill out the EMS supplier-furnished checkout paperwork as follows and submit to Wal-Mart Mechanical Services<br />

Department.<br />

1. Pre-checkout forms: Wal-Mart Support Installation Form, HVAC Information, and Pre-Checkout<br />

Verification Form.<br />

2. Checkout forms: Refrigerated Case Sensor Input Verification, Phase Loss Information, Operating<br />

Information and Manager’s Orientation.<br />

F. Start-up shall include but not limited to the following:<br />

1. Verify all modules are communicating.<br />

2. Verify all terminations are correct.<br />

3. Verify all sensor locations.<br />

4. Verify, icebath, and calibrate to +/- one degree Fahrenheit if needed on all refrigeration sensors connected<br />

to refrigerated case input controllers<br />

5. Replace any modules or sensors that are defective.<br />

3.5 CHECKOUT<br />

A. Coordinate with Wal-Mart EMS Supplier (Vendor Support) for final checkout. System documentation shall not be<br />

completed until Contractor has received final checkout verification number from Wal-Mart EMS Vendor Support.<br />

B. Checkout shall include, but is not limited to, the following:<br />

1. Complete Pre-checkout.<br />

2. Complete on-line checkout.<br />

3. Network status.<br />

4. Phase loss monitors.<br />

5. Override verification.<br />

6. Sensor verification.<br />

7. Address verification.<br />

8. Alarm log verification.<br />

9. Transducer verification<br />

10. AHU sensor verification.<br />

11. Light dimming: Dim lights from 100% down to minimum and back up to 100% to demonstrate proper<br />

operation.<br />

12. ALS & hi/lo output verification.<br />

13. RTU sensor verification.<br />

14. CO 2 sensor verification.<br />

15. RTU damper/actuator verification.<br />

3.6 FUNCTIONAL PERFORMANCE TESTING (FPT)<br />

A. FPT will be conducted by Wal-Mart Engineer of Record at no cost to the Contractor in accordance with Section<br />

01454. FPT will be performed after Wal-Mart Possession Date. Deficiencies noted and related to the Contractor’s<br />

installation responsibilities shall be corrected prior to Grand Opening.<br />

B. END OF SECTION<br />

13810 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 13810 – ENERGY MANAGEMENT SYSTEM<br />

Project Location:<br />

Date:<br />

(City & State)<br />

Project Number:<br />

_____________________________________________________<br />

Store Number:<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 – Contract Closeout.<br />

The undersigned hereby declares that the Energy Management System (hereafter referred to as the “Systems”) is installed<br />

and is in general conformance with the Contract Documents, applicable Codes, and shop drawings. The “Systems”<br />

have been provided and placed in operational condition in accordance with the manufacturer's published instructions and the<br />

Contract Documents.<br />

_____________________________________________________________<br />

(Contractor Signature)<br />

___________________________________________________________ Phone Number: (<br />

(Contractor name and address)<br />

) _________________<br />

Recommendation of Acceptance:<br />

This Recommendation of Acceptance is provided as a Record Document in accordance with Section 01770 – Contract Closeout.<br />

We recommend Wal-Mart accept the installation of the “Systems” (as referenced above). The “Systems” are found to<br />

be in general conformance with the Contract Documents, and Approved Drawings. This recommendation is based on MEP<br />

Site Observation and Functional Performance Test witnessed on ___________________(Report Date), and follow up verification<br />

of identified issues conducted on ___________________ (Trip Date, Report Date).<br />

While this review is an integral part of this project, it does not relieve the Contractor of their responsibility to comply with<br />

the applicable provisions of the Contract Documents along with the mandated codes and standards. These examinations shall<br />

not be construed as a check of every item nor does it prevent authorities from hereafter requiring corrections of errors in plans<br />

or installation.<br />

WAL-MART’S MECHANICAL CONSULTANT:<br />

(Wal-Mart’s Mechanical Consultant Signature )<br />

(Wal-Mart’s Mechanical Consultant name and address)<br />

Phone Number: (<br />

)_________________<br />

13810 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 012811<br />

SECTION 13900 - FIRE SUPPRESSION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Automatic sprinkler systems.<br />

2. Fire protection sprinkler piping work with feed and cross main piping, branch line piping, test valves, test<br />

connections, and sprinklers.<br />

3. Flow indicators, valves, gauges, alarms, drain piping, and supervisory switches.<br />

4. System design, installation and certification.<br />

B. Related Requirements:<br />

1. Section 02510 - Water Distribution Systems.<br />

2. Section 09900 - Paints and Coatings.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A 47 - Ferritic Malleable Iron Castings.<br />

2. ASTM A 53 - Pipe, Steel, Black And Hot-Dipped, Zinc-Coated, Welded And Seamless.<br />

3. ASTM A 135 - Electric-Resistance-Welded Steel Pipe.<br />

4. ASTM A 234 - Piping Fittings Of Wrought Carbon Steel and Alloy Steel For Moderate And High<br />

Temperature Service.<br />

5. ASTM A 536 - Ductile Iron Castings.<br />

6. ASTM A 795 - Black And Hot-Dipped Zinc-Coated (Galvanized) Welded And Seamless Steel Pipe For<br />

Fire Protection Use.<br />

7. ASTM A 865 - Threaded Couplings, Steel, Black Or Zinc-Coated (Galvanized) Welded Or Seamless, For<br />

Use In Steel Pipe joints.<br />

C. American Society of Mechanical Engineers (ASME):<br />

1. ASME B 16.1 - Cast Iron Pipe Flanges And Flanged Fittings.<br />

2. ASME B 16.3 - Malleable Iron Threaded Fittings.<br />

3. ASME B 16.4 - Gray Iron Threaded Fittings.<br />

4. ASME B 16.5 - Pipe Flanges And Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard.<br />

5. ASME B 16.9 - Factory-Made Wrought Buttwelding Fittings.<br />

6. ASME B 16.11 - Forged Fittings, Socket-Welding And Threaded.<br />

D. Building Code:<br />

1. As shown on the Drawings.<br />

E. Factory Mutual System (FM):<br />

1. Approval Guide, Latest edition.<br />

F. National Fire Protection Association (NFPA):<br />

1. NFPA 13, 2007 Edition - Installation of Sprinkler Systems.<br />

2. NFPA 24, 2007 Edition - Standard for the Installation of Private Fire Service Mains and their<br />

Appurtenances.<br />

3. NFPA 70, 2008 Edition - National Electrical Code.<br />

13900 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


G. Underwriters Laboratory (UL):<br />

1. UL Fire Protection Directory – Latest Edition.<br />

1.3 SUBMITTALS<br />

A. Code Compliance Submittals to Authorities Having Jurisdiction (AHJ):<br />

1. Provide Deferred Submittals to AHJ per requirements of 01330. Drawings and calculations have not been<br />

submitted to the AHJ for code compliance by Wal-Mart's Fire Protection Consultant.<br />

a. Submit the following:<br />

1) Product data.<br />

2) Shop drawings.<br />

3) Additional data as may be required by NFPA 13 and Wal-Mart’s Fire Protection Consultant.<br />

2. Drawings and calculations have been submitted to the AHJ for code compliance by Wal-Mart's Fire<br />

Protection Consultant.<br />

B. Submittal Procedure:<br />

1. Reference Section 01330 for general submittal procedures. Conform to provisions of Section 01330 unless<br />

otherwise specified herein.<br />

2. Within 30 days after award of prime contract, send submittals to Wal-Mart’s Fire Protection Consultant as<br />

specified in Section 01330. Allow 30 day turn-around on submittals sent to Wal-Mart’s Fire Protection<br />

Consultant.<br />

a. Fire Protection Consultant’s electronic drawing files (i.e., DWG, DWF, PDF, etc.) will not be<br />

provided to the Contractor for the purpose of submittals nor will the Fire Protection Consultant<br />

assist with production of submittal information including shop drawings and material data.<br />

b. If the Contractor fails to submit a complete Fire Suppression submittal package within 30 days after<br />

award of contract, the Contractor shall pay the Owner $250.00 per day as liquidated damages and<br />

not as a penalty, until the fully completed Fire Suppression submittal package is received by Wal-<br />

Mart’s Fire Protection Consultant.<br />

c. Send a copy of the Letter of Transmittal sent with the submittals to the Architect indicating date of<br />

and content of transmittal.<br />

3. Submittals shall be complete, accurate, and in full compliance with contract requirements for proper and<br />

timely approval.<br />

4. Contractor shall respond to shop drawing review comments within 15 days of receipt.<br />

5. Maintain two copies of approved documents on site.<br />

C. Submittal Rejection:<br />

1. Wal-Mart’s Fire Protection Consultant will reject submittals which do not comply with Contract<br />

Documents. If submittal is rejected by Wal-Mart’s Fire Protection Consultant for any reason, Wal-Mart<br />

Stores, Inc., will back-charge the Contractor $200.00 via Change Order, to cover the processing costs of<br />

each subsequent review until submittal is approved. Submittal rejections include, but are not limited to, the<br />

following reasons:<br />

a. Design Issues: Incorrect densities, design areas, equipment sprinkler spacing, hose station missing,<br />

incomplete system design, etc. No changes in design area, number of sprinklers operating, pipe<br />

sizes, number of branch lines, number of mains, or deviation of water supply from that shown on the<br />

Contract Documents shall be approved by Wal-Mart’s Fire Protection Consultant. This is not<br />

intended to limit the Contractor from making minor modifications to system design for coordination<br />

purposes.<br />

b. Incorrect Water Test: Failure to use Wal-Mart water test found on project fire protection Contract<br />

Documents. No other water test data is permitted for system design submittals to Wal-Mart’s Fire<br />

Protection Consultant.<br />

c. Incorrect Material: Do not propose pipe, sprinklers or backflow preventers not indicated in Contract<br />

Documents. Products not specified in contract documents are cause for rejection.<br />

d. Incorrect Valves: Do not propose OS&Y valves when wall PIV's are indicated in the Contract<br />

Documents.<br />

2. Rejected submittals shall be revised and resubmitted until approved. Extension of time will not be allowed<br />

for rejected submittals.<br />

13900 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


a. The Fire Suppression subcontractor shall revise and resubmit rejected submittals within 15 days of<br />

receipt of rejected submittals.<br />

b. The Contractor shall verify that the Fire Suppression subcontractor has addressed all required<br />

revisions in the resubmittal.<br />

1.4 CLOSEOUT SUBMITTALS:<br />

A. Submit the following under provisions of Section 01770.<br />

1. Maintenance Data: Include components of system, servicing requirements, inspection data, and owner’s<br />

manuals.<br />

2. Training Requirements: Provide operational training to Wal-Mart. Include system control operation, Fire<br />

Pump (if provided) manual and abort functions, trouble procedures, auxiliary functions and emergency<br />

procedures.<br />

3. Contractor’s Material Test Certificates: Provide Copies of completed Underground, Aboveground, and<br />

Fire Pump (if applicable) Contractor’s Material Test Certificates. Contractor’s Material And Test<br />

Certificate For Underground Piping is attached at the end of this Section.<br />

4. As-Built Shop Drawings: Indicate installed location of components including piping, sprinklers, hangers,<br />

valving, inspector's test stations, auxiliary drains, and hose stations (if required). Also include corrections<br />

noted during the site observation process and reflect revisions, addenda, and construction change directives<br />

implemented on the project.<br />

5. Contractor's Record Letter of Conformance for Fire Suppression: Upon satisfactory Fire Sprinkler Site<br />

Observation and Acceptance Test (FPAT), Wal-Mart’s Fire Protection Consultant will issue to the<br />

Contractor a Contractor's Record Letter of Conformance for Fire Suppression. The Contractor shall<br />

complete the Record Letter of Conformance, obtaining all signatures (Consultant, Sub Contractor, and<br />

Contractor) and submit original for payment per Contract Documents. One Record Letter of Conformance<br />

shall be completed and submitted for Fire Sprinkler Systems, Fire Pump Systems and Water Storage Tanks<br />

associated with the project.<br />

B. At Project completion, present to the Store Manager the As built Drawings enclosed in a plastic pipe tube (fixed<br />

cap at one end and a threaded-cap on the other end) for storage in the Riser Room.<br />

C. In addition to the copies of Documents delivered to the Store Manager, distribute additional copies of documents<br />

as indicated below:<br />

1. Contractor shall deliver copies of the As-Built shop drawings and Contractor's Record Letter of<br />

Conformance for Fire Suppression and Contractor’s Material Test Certificates (Underground, Overhead,<br />

and Fire Pump) in both hard copy and electronic form (PDF or PLT) to Wal-Mart’s Fire Protection<br />

Consultant.<br />

1.5 SYSTEM DESCRIPTION<br />

A. System shall provide coverage for all building areas including, but not limited to, areas scheduled in this Section.<br />

Contract Documents have been prepared in accordance with NFPA 13 (working plans) except for fabrication<br />

information. The Contract Documents are prepared to a level consistent with that level required by the Authorities<br />

Having Jurisdiction to gain plan check approval. No changes in design area, number of sprinklers operating, pipe<br />

sizes, number of branch lines, number of mains, or deviation of water supply from that shown on the drawings<br />

shall be approved by Fire Protection Consultant. This is not intended to limit the Contractor from making minor<br />

modifications to system design for coordination purposes. The Contractor shall review the Contract Documents<br />

for completeness and to ensure that the Contract Documents meet all Authorities Having Jurisdiction<br />

requirements. Discrepancies with NFPA or Authorities Having Jurisdiction requirements shall be brought to the<br />

attention of the Fire Protection Consultant prior to bid. The Contractor shall complete the fire protection Contract<br />

Documents to provide all final required detail such as fabrication details, final pipe cuts, hanger cuts, and other<br />

miscellaneous details not required by the Authority Having Jurisdiction for approval. Contractor is responsible to<br />

coordinate design with all trades and disciplines.<br />

13900 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


1. Fire Protection Consultant has submitted Contract Documents to Authorities Having Jurisdiction for review<br />

and approval. Contractor shall provide all other documents, qualifications, submittals and coordination<br />

necessary to obtain approval by Authorities Having Jurisdiction. All changes made to the Contract<br />

Documents by the Contractor shall be submitted to the Fire Protection Consultant for approval prior to<br />

fabrication or installation. Refer to Section 01330 for submittal requirements.<br />

B. Provide system complying with NFPA 13, Authorities Having Jurisdiction and Contract Documents. Densities<br />

and areas of application shown or specified have been developed based on NFPA requirements, engineering<br />

judgment and insurance carrier requirements.<br />

C. Provide 5 psi safety factor between supply curve and demand point, including hose stream allowance.<br />

D. Base areas of application on actual floor area protected by sprinklers.<br />

E. Include hose allowance as required in schedule in the hydraulic calculations as required by NFPA 13.<br />

F. If overhead doors open in horizontal position, provide sprinklers below door when the door is in a horizontal<br />

position.<br />

G. Provide hangers, supports and earthquake bracing per applicable building codes, Contract Documents, and NFPA<br />

13 and Authority Having Jurisdiction.<br />

H. Interface sprinkler system with fire protection supervisory system.<br />

I. Provide 2-1/2" Fire Department hose valves. Locate as indicated on Drawings. Additional hose valves may be<br />

required by Authority Having Jurisdiction; location to be coordinated with Authority Having Jurisdiction and<br />

Engineer of Record.<br />

1.6 QUALITY ASSURANCE<br />

A. Installer Qualifications: Company specializing in performing work of this Section with minimum three years<br />

experience and a minimum of a NICET Certified Engineering Technician (Level III) Fire Sprinkler Designer on<br />

staff responsible for project.<br />

B. Installer shall have a sprinkler contractor license issued by the Authorities Having Jurisdiction.<br />

C. Regulatory Requirements: Provide certificate of compliance from Authorities Having Jurisdiction indicating<br />

approval of field acceptance tests.<br />

1.7 EXTRA MATERIALS<br />

A. Provide extra sprinklers under the provisions of NFPA 13. Provide suitable wrenches for each sprinkler type.<br />

Provide a minimum of 24 spare sprinklers as follows:<br />

1. 12 Sales Floor Type<br />

2. 4 Dry Pendent<br />

3. 2 each of other type present for a minimum of 24.<br />

B. Provide sprinkler and sprinkler wrench cabinet(s) per NFPA 13, adjacent to sprinkler risers.<br />

C. Provide hydraulic calculation placard attached to each riser.<br />

1.8 DELIVERY, STORAGE, AND HANDLING<br />

A. Deliver, store, and protect products to site under provisions of Section 01600.<br />

13900 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Store products in shipping containers and maintain in place until installation. Provide temporary inlet and outlet<br />

caps. Maintain caps in place until installation.<br />

PART 2 - PRODUCTS<br />

2.1 MATERIALS<br />

A. Provide UL Listed or FM Approved materials complying with NFPA 13, unless noted otherwise in Contract<br />

Documents.<br />

2.2 FIRE PROTECTION PIPING - BELOW GROUND<br />

A. Ductile Iron Pipe: Minimum working pressure Class 350.<br />

2.3 FIRE PROTECTION PIPING - ABOVE GROUND<br />

A. Pipe: Steel pipe, conforming to the applicable requirements of NFPA 13, and ASTM A 53, ASTM A 135, or<br />

ASTM A 795, as applicable.<br />

1. Wet Pipe Systems, Utilizing Threaded Pipe:<br />

a. Schedule 40 black steel pipe.<br />

b. Threadable lightwall sprinkler pipe with corrosion resistance ratio of 1.0 or greater after threading.<br />

c. Pipe located outdoors and piping in non-conditioned spaces shall be externally galvanized.<br />

2. Wet Pipe Systems, Utilizing Roll Grooved Pipe.<br />

a. Schedule 10 black steel pipe.<br />

b. Lightwall sprinkler pipe with corrosion resistance ratio of 1.0 or greater.<br />

c. Pipe located outdoors and piping in non-conditioned spaces shall be externally galvanized.<br />

3. Dry Pipe Systems: Same as wet pipe systems except pipe shall be galvanized, zinc coated internally and<br />

externally.<br />

B. Fittings: Provide one of the following:<br />

1. Cast-Iron Threaded Flanges: ASME B16.1.<br />

2. Cast-Iron Threaded Fittings: ASME B16.4.<br />

3. Malleable-Iron Threaded Fittings: ASME B16.3.<br />

4. Steel, Threaded Couplings: ASTM A 865.<br />

5. Steel Welding Fittings: ASTM A 234, ASME B16.9, or ASME B16.11.<br />

6. Steel Flanges and Flanged Fittings: ASME B16.5.<br />

7. Steel, Grooved-End Fittings: UL-listed and FM-approved, ASTM A 47, malleable iron or ASTM A 536,<br />

ductile iron; with dimensions matching steel pipe and ends factory grooved according to AWWA C606.<br />

Roll groove only, cut groove unacceptable.<br />

8. Steel Fittings and Cast Iron fittings shall not be used for dry pipe systems.<br />

9. Fitting type shall match pipe. Galvanized fittings shall be used for dry pipe systems and wet pipe systems<br />

located in non-conditioned spaces.<br />

10. Crimp-type couplings shall not be used.<br />

11. Plain end fittings (socket, FIT, roustabouts, etc) shall not be used.<br />

C. Flexible Piping Systems: At Contractor’s option, UL listed and FM approved flexible piping connections to<br />

sprinklers may be used for both suspended and sheetrock ceilings when suitable for their intended use.<br />

1. Description: Connections shall include a fully welded (non-mechanical fittings), braided, leak-tested<br />

sprinkler drop with a minimum internal corrugated hose diameter of 1 inch, lengths of 2 ft to 6 ft., and a<br />

one-piece multi-port ceiling bracket with removable attachment hub and self-securing integrated snap-on<br />

clip-ends for attachment to ceiling grid without the need for a screw fastener.<br />

2. Acceptable Manufacturer: Flex Head series 2000 by Flexhead Industries of Holliston, MA (800) 829-6975<br />

or (508) 893-9596, Fax (508) 893-6020.<br />

13900 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2.4 BACKFLOW PREVENTER ASSEMBLIES<br />

A. Subject to compliance with design and requirements of Authority Having Jurisdiction, provide Backflow<br />

Preventer Assembly as follows:<br />

1. 2 Inch Connections and Smaller: If Authorities Having Jurisdiction require double check, double detector<br />

check, or reduced pressure type devices use ASSE or USC Cross Connection approved device.<br />

2. 2-1/2 Inch Through 10 Inch Connections:<br />

a. Existing double detector check type, 8" Hersey.<br />

3. Provide backflow preventer assemblies in accordance with manufacturer's recommendations and<br />

requirements of Authorities Having Jurisdiction and Contract Documents.<br />

2.5 MAINTENANCE AIR COMPRESSOR<br />

A. Subject to compliance with requirements, provide tank mounted UL Listed or FM Approved air compressor<br />

system.<br />

1. Provide electric, air-cooled, oil-less compressor.<br />

2. Motor: 1/3 horsepower.<br />

3. Power: 120 volt, single phase, 60 Hz. Hard wire per NEC and manufacturer's requirements.<br />

2.6 SPRINKLERS.<br />

A. Replace any existing sprinkler that has signs of leakage, paint applied (other than by the sprinkler manufacturer),<br />

corrosion, damage, or loading; or is installed in the improper orientation. Provide new sprinkler with identical K-<br />

Factor, temperature rating, and response type as the existing.<br />

B. Subject to compliance with requirements, provide UL Listed or FM Approved automatic sprinklers. Provide<br />

sprinklers with nominal 5.6, 8.0, 11.2, or 16.8 K-factor. Sidewall sprinklers are not acceptable, unless noted<br />

otherwise. Provide the following sprinkler types:<br />

1. Areas With Exposed Structure Above: Upright or pendent sprinkler, bronze.<br />

2. Areas With Ceilings and Surface Mounted Light Obstructions: Pendent sprinkler, white, with two-piece<br />

white escutcheon plate.<br />

3. Areas With Gypsum or Lay-in Ceilings: Pendent sprinkler, white, with two-piece semi-recessed white<br />

escutcheon plate.<br />

C. Standard Sprinklers: Glass bulb sprinklers are acceptable. Sprinklers with o-rings not permitted.<br />

D. Dry Pendent Sprinklers shall be Concealed type Globe Model GL5681, Tyco Model TY3555, or Victaulic V3301.<br />

1. Substitutions: Not permitted.<br />

E. Dry Horizontal Sidewall Sprinklers shall be Tyco Model TY3355, TY5339 or Reliable R5734.<br />

1. Tyco Model TY5339 for extended coverage ordinary hazard (ECOH) installations.<br />

2. Substitutions: Not permitted.<br />

F. For projects that require seismic bracing, install ceiling sprinklers per one of the following:<br />

1. Install sprinklers with flexible piping<br />

2. Provide one inch clearance around sprinkler. Cover the larger opening by installing either a Recessed<br />

Canopy Coverage Extension or Kydex Ring by Fire Protection Products or an expansion plate by Viking.<br />

2.7 ACCESSORIES<br />

A. Electric Bell: Provide 8 inch diameter, 24 volt AC, electric bell, Model No. PBA248, by Potter Electric Signal of<br />

St. Louis, Missouri. Provide bell on exterior of building on wall at riser. Locate as required by Contract<br />

Documents and Authorities Having Jurisdiction.<br />

13900 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Wet Sprinkler System Water Flow Detectors: Equip sprinkler system risers with double pole vane type flow<br />

detector, Model No. VSR, by Potter Electric Signal of St. Louis, Missouri, or Model No. WFD, by System Sensor<br />

of St. Charles, Illinois. Set adjustable delayed signal at 30 seconds. Wal-Mart will connect to alarm system. Mount<br />

water flow indicators no higher than 6 feet above finish floor.<br />

C. Drypipe Sprinkler System Water Flow Detector: Equip Drypipe System risers with pressure activated flow<br />

detector, Model PS10-2A, by Potter Electric Signal of St. Louis, Missouri.<br />

D. Drypipe Sprinkler System Air Pressure Supervisory Switch: Equip Drypipe System risers with air pressure<br />

supervisory switch, Model PS40-2A, by Potter Electric Signal of St. Louis, Missouri. Set pressure switch at 10 psi<br />

below the air compressor start and at 10 psi above the air compressor stop.<br />

E. Control Valve Supervisory Switches:<br />

1. Equip post indicator valves with tamper switches, Model No. PCVS-2, by Potter Electric Signal of St.<br />

Louis, Missouri, or Model No. PIBV2, by System Sensor of St. Charles, Illinois. Wal-Mart will connect to<br />

alarm system.<br />

2. Equip outside screw and yoke valves with tamper switches, Model No. OSYSU-2 by Potter Electric Signal<br />

of St. Louis, Missouri. Wal-Mart will connect to alarm system.<br />

3. Provide ball type control valves leading to alarm initiating devices, Model No. RBVS, by Potter Electric<br />

Signal of St. Louis, Missouri. Wal-Mart will connect to alarm system.<br />

4. All other valves capable of controlling water to the Fire Protection Sprinkler systems shall have appropriate<br />

tamper switches. Wal-Mart will connect to alarm system.<br />

F. Fire Department Connections: Provide Fire Department connections in accordance with Contract Documents and<br />

Authority Having Jurisdiction. Equip with threads/connections compatible with hoses utilized by the local fire<br />

department.<br />

1. Drain: 3/4 inch automatic drip, piped to outside or approved drainage location.<br />

2. Label: "Auto Sprinkler".<br />

3. Finish: Rough brass.<br />

4. Thread/Connection: Verify with Authorities Having Jurisdiction.<br />

G. Wire Cage Sprinkler Guards:<br />

1. Provide guards on pendent sprinklers located within 7'-6" of finished floor, except for semi-recessed and<br />

concealed sprinklers.<br />

2. Provide guards on sprinklers located beneath overhead doors.<br />

H. Substitutions: Not permitted unless otherwise noted.<br />

2.8 FIRE PUMP<br />

A. Fire Pump not permitted.<br />

PART 3 - EXECUTION<br />

3.1 GENERAL INSTALLATION REQUIREMENTS<br />

A. Install system and equipment in accordance with NFPA 13 and manufacturer's instructions.<br />

3.2 INSTALLATION - BELOW GROUND PIPING<br />

A. Provide piping, system components and pipe restraints per NFPA 24. Provide underground sprinkler lead-in from<br />

5 feet outside of building. Support barrel of pipe for entire length on compacted bedding. Excavate for couplings,<br />

fittings and valves.<br />

13900 - 7<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Keep interior of pipe free from dirt and other foreign material as installation progresses. Plug open ends when<br />

work is stopped. Join lengths with couplings in accordance with pipe manufacturer's instructions.<br />

C. Provide post indicators and fittings as necessary. Provide a ¾ inch conduit with pull string from any remote Fire<br />

Protection System valve equipped with a tamper switch. Route into the building per Contract Documents.<br />

D. Provide concrete thrust blocks as required by NFPA 24. Place concrete between undisturbed soil and fittings. Do<br />

not cover coupling flanges or other joints with concrete.<br />

3.3 INSTALLATION - ABOVE GROUND PIPING<br />

A. Provide piping in accordance with NFPA 13.<br />

B. Locate top beam clamp or thru bolt connection near joist panel points per pipe support detail.<br />

C. Provide piping to conserve building space. Do not interfere with use of building space and other work.<br />

D. Group piping whenever practical at common elevations.<br />

E. Prepare pipe, fittings, supports, and accessories for finish painting. Where pipe support members are welded to<br />

structural building framing, scrape, brush clean, and apply one coat of zinc rich primer to welding. Protect<br />

sprinkler to ensure sprinklers do not receive field paint. Remove protective covering after painting. Replace<br />

sprinklers having paint other than factory finish with new sprinklers. Cleaning and reuse of painted sprinklers is<br />

prohibited.<br />

F. Examine other work indicated on the Drawings and conditions at job site. Coordinate routing of work with other<br />

construction trades to avoid interference with other installations. Do not cut building structural members, beams,<br />

joists, etc. for routing of sprinkler piping.<br />

G. Seal pipe penetrations through fire rated walls or floors to achieve fire resistance equivalent to fire separation<br />

required. Provide wall plates at all penetrations. Provide zinc coated (galvanized) all-thread rod for hanging dry<br />

system piping.<br />

H. Provide valves with stems upright or horizontal.<br />

I. Route piping and locate sprinklers as required to avoid building structure, equipment, plumbing piping, heating<br />

and air conditioning piping, ductwork, lighting fixtures, electrical conduits and bus ducts, and similar work.<br />

Locate center of sprinkler a minimum of 6 inches off ceiling grid.<br />

1. Final location of lighting and exposed ductwork shall have priority over pipe routing and final sprinkler<br />

locations.<br />

2. Sprinkler piping in sales area without a ceiling and stockroom shall be located above bottom of joists.<br />

Minimum height of sprinkler piping in areas with ceilings shall be 1’-0” above ceiling.<br />

J. Relocate inspector's test valves as required for new building and merchandise layout. Locate at five feet minimum<br />

to seven feet maximum above finish floor. If acceptable with the Authority Having Jurisdiction, relocate to fire<br />

riser assembly.<br />

K. Provide pressure relief valves on gridded wet pipe systems.<br />

L. Provide protection from freezing for sprinkler piping exposed to freezing conditions per Contract Documents and<br />

NFPA 13.<br />

M. Provide valves, backflow prevention devices, check valves, and drains per Contract Documents and Authorities<br />

Having Jurisdiction.<br />

N. Use full lengths of pipe except where needed to accommodate changes in direction or for space limitations.<br />

13900 - 8<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3.4 IDENTIFICATION<br />

A. Apply signs to control, drain, test and alarm valves to identify their functions. Provide lettering sizes and styles<br />

per Authorities Having Jurisdiction. Provide hydraulic placard for each sprinkler system in accordance with<br />

NFPA 13. Stencil riser/zone numbers on risers.<br />

B. Provide a sprinkler zone map that clearly identifies the location of all: areas protected, control valves, dry pipe<br />

valve, inspector’s test valves, auxiliary drains, pumps, and tanks. Sprinkler Zone Map shall be laminated in<br />

plastic. Permanently attach to wall in fire sprinkler riser room.<br />

3.5 FIELD QUALITY CONTROL<br />

A. General: Contractor shall schedule, coordinate and conduct all tests required by Authorities Having Jurisdiction<br />

and Wal-Mart’s Fire Protection Consultant. Contractor shall modify, replace or retest as required by Authorities<br />

Having Jurisdiction and / or Wal-Mart’s Fire Protection Consultant.<br />

B. Flush, test, and inspect sprinkler system according to NFPA 13 "Systems Acceptance" Chapter. Test the systems,<br />

including the underground water mains, and the aboveground piping and components to assure that equipment and<br />

components function as intended. Pressure test the systems in accordance with NFPA 13 and NFPA 24. The<br />

Contractor shall have available copies of as-built drawings.<br />

1. Under Ground Fire Protection Piping:<br />

a. Test per NFPA 24.<br />

b. Flush underground mains and lead-in connections thoroughly to remove foreign material before<br />

connection is made to above ground system piping. Minimum flow rate shall not be less than the<br />

maximum water flow demand rate of the system and not less than necessary to provide a velocity of<br />

10 feet per second. Continue flushing for sufficient time to ensure thorough cleaning. Provide<br />

proper disposal of water from flushing operation.<br />

c. Perform Hydrostatic tests per NFPA 24.<br />

2. Above Ground Fire Protection Piping:<br />

a. Test per NFPA 13.<br />

b. Inspect welds and verify welder's qualifications per Authorities Having Jurisdiction.<br />

c. Perform Hydrostatic tests per NFPA 13.<br />

3. Backflow Prevention Assembly Forward Flow Test.<br />

4. Operation of control valves and flowing of inspector's test connections to verify operation of alarm devices<br />

including alarm switches. After operation of control valves has been completed, assure that control valves<br />

are in the open position.<br />

5. Main Drain flow test.<br />

C. Fire Sprinkler System Construction Follow Up: Wal-Mart’s Fire Protection Consultant (as specified in Section<br />

01330) will conduct a Pre Construction Conference Call, Mid Installation Site Observation, and Fire Sprinkler<br />

Site Observation and Acceptance Test (FPAT). The purpose of the Pre Construction Conference call is to review<br />

status of project, notify contractor of status of approvals, and review project expectations. The purpose of the Mid<br />

Installation Site Observation is to verify type of material, progress of installation (rough-in should be complete<br />

and ready for ceiling paint), and, if possible, re-verify available water supply. The purpose of the Fire Sprinkler<br />

System Site Observation is to determine if the fire sprinkler systems are in general conformance with Contract<br />

Documents and shop drawings. The Contractor shall coordinate with Wal-Mart’s Fire Protection Consultant for<br />

the time and date of the test. Scheduling for the FPAT shall begin one month prior to possession with FPAT being<br />

conducted one to two weeks prior to possession. FPAT shall occur prior to possession. A representative sample<br />

checklist is available upon request.<br />

1. Pre Construction Conference Call: The Contractor shall contact Wal-Mart’s Fire Protection Consultant<br />

within 2 weeks after Contract Award to schedule the Pre Construction Conference Call with the Contractor,<br />

Fire Sprinkler Contractor, and Fire Pump Vendor (if applicable). The conference call will be held 30 days<br />

after Award. Mid Installation Site Observation will be scheduled at time of Pre Construction conference<br />

call.<br />

13900 - 9<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2. Mid Installation Site Observation: Wal-Mart’s Fire Protection Consultant will meet the Contractor and<br />

Sprinkler Contractor representatives at the scheduled time. Mid Installation Site Observation will be<br />

conducted and documented. FPAT will be scheduled at time of Mid Installation Site Observation.<br />

3. FPAT: Wal-Mart’s Fire Protection Consultant will meet the Contractor, Sprinkler Contractor and Alarm<br />

Central representatives at the scheduled time. At scheduled time, Contractor/Sprinkler Contractor shall be<br />

ready to initiate Acceptance tests as outlined herein. Prior to initiating tests, the following information shall<br />

be reviewed and copies provided to Wal-Mart’s Fire Protection Consultant:<br />

a. Contractor’s Material and Test Certificate for Underground Piping. Provide the completed<br />

Contractor’s Material And Test Certificate For Underground Piping provided at the end of this<br />

Section. All portions of the certificate shall be completed prior to Acceptance testing.<br />

b. Contractor’s Material and Test Certificate for Aboveground Piping (By System). As a minimum, the<br />

form shall contain information indicated in sample form shown in NFPA 13 (i.e. Figure 16.1 of<br />

2002 edition). Certificate shall be complete and verify all information except Dry pipe test section<br />

and hydrostatic test section. Dry pipe section may be completed during Acceptance Test.<br />

Hydrostatic test may be completed in the future and a copy forwarded to Wal-Mart’s Fire Protection<br />

Consultant at a later date.<br />

c. Sprinkler Zone Map.<br />

d. Approved Shop Drawings.<br />

e. Fire Pump Factory Test Curve (if applicable).<br />

4. After these documents have been reviewed, Acceptance Test shall be initiated by Contractor/Sprinkler<br />

Contractor in the order determined by Wal-Mart’s Fire Protection Consultant. Each of these tests shall be<br />

interfaced with the fire alarm system. Contractor shall arrange for system to be put in test and arrange to be<br />

able to silence local alarms during Acceptance Test. It is preferable that Alarm Central Technician be on<br />

site and available to assist during the Acceptance Test. Contractor shall coordinate with Alarm Central. The<br />

Contractor shall provide all personnel, material, equipment, lifts, air and water pumps, hand tools, and<br />

apparatus necessary to complete the above required testing. The Contractor shall notify the store<br />

management that the above tests are scheduled.<br />

5. The following tests shall be conducted by the Contractor/Sprinkler Contractor and witnessed by Wal-<br />

Mart’s Fire Protection Consultant. Generally this is the order the tests shall be conducted, but the Wal-<br />

Mart’s Fire Protection Consultant may require tests be conducted in any order deemed appropriate.<br />

Determination of order will be made while on site.<br />

a. Water Storage Tank (if applicable): Sprinkler Contractor shall drop water level, overflow tank, and<br />

operate tank heaters. Typically, this is the second test in the Acceptance Test.<br />

b. Water Flow Test: Contractor or Sprinkler Contractor shall conduct a water flow test in accordance<br />

with NFPA 291 near the lead in to the fire sprinkler system to verify anticipated water supply is<br />

available. If a fire pump is present, and tested, this test will not be required.<br />

c. Dry pipe Systems: Sprinkler Contractor shall operate dry system to verify High, and Low air<br />

pressure settings as well as water delivery time. This test typically follows the Water Flow Test or<br />

Fire Pump/Tank test depending on site conditions.<br />

d. Inspector’s Test: Sprinkler Contractor shall operate each Inspector’s Test to verify flow switch<br />

operates within 90 seconds (preferred time is 45 seconds, minimum time is 30 seconds). This test<br />

typically follows the Dry pipe system Acceptance Test.<br />

e. System Control Valves: Sprinkler Contractor shall operate each system control valve to verify<br />

functionality. This test typically follows the Inspector’s Acceptance Test.<br />

f. Antifreeze Systems (if applicable): Sprinkler Contractor shall test antifreeze mixture to verify<br />

proper solution ratio. This test typically follows the System Control Valve Acceptance Test.<br />

g. Hydrostatic Test: Sprinkler Contractor shall hydrostatically test all systems simultaneously.<br />

Typically this will be the last test initiated, and depending on schedule may not be fully witnessed<br />

by Wal-Mart’s Fire Protection Consultant. Contractor/Sprinkler Contractor shall certify and provide<br />

signed off copies of test certificates proving successful completion of Hydrostatic tests prior to full<br />

acceptance.<br />

6. In addition to conducting the Fire Protections Systems Acceptance Test, a Fire Sprinkler System Site<br />

Observation of the installed systems will also be conducted. Wal-Mart’s Fire Protection Consultant will<br />

conduct and document a site observation of the fire sprinkler systems (and fire pump / tank as applicable).<br />

At the conclusion of this observation, an exit interview will be conducted with the Contractor to review and<br />

identify issues that need correction prior to acceptance of the system.<br />

13900 - 10<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


D. Replace sprinkler system components that do not pass test procedures and retest to demonstrate compliance.<br />

Repeat procedure until satisfactory results are obtained. The installation shall not be considered accepted until<br />

identified discrepancies have been corrected and test documentation is properly completed and received.<br />

E. If any portion of the system acceptance process, including but not limited to site observation, acceptance testing<br />

and fire pump testing, is required to be repeated or rescheduled due to non-compliance with Contract Documents<br />

or code, unpreparedness of site or equipment for testing on scheduled date, and/or unsatisfactory results obtained,<br />

and a revisit is required, rescheduling may take up to four weeks and may result in Contractor being back charged<br />

for Wal-Mart’s Fire Protection Consultant’s additional time and expenses as well as Owner Supplied Equipment<br />

Representative’s time and expenses required to be present for testing (i.e., fire pump)..<br />

F. Prior to interior store finishing, test existing and new above ground pressure piping for leakage in accordance with<br />

NFPA 13 Systems Acceptance in presence of Authority Having Jurisdiction and Owner's representative. Maintain<br />

test pressure at the high end for two hours. Test pressure: 200 psi or 50 psi over normal operating pressure,<br />

whichever is greater. Conduct test in accordance with NFPA 13, Hydrostatic Tests. Submit documentation per<br />

Contract Closeout Submittals of this section and 01770.<br />

END OF SECTION<br />

13900 - 11<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 13900<br />

FIRE SUPPRESSION<br />

Project Location:<br />

Date:<br />

(City & State)<br />

Project Number:<br />

Store Number:<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. The undersigned hereby declares that the fire sprinkler system(s) (hereafter referred to as the “Systems”) is<br />

installed and is in general conformance with the Contract Documents and shop drawings and submitted product data. The<br />

“Systems” have been provided and placed in operational condition in accordance with the manufacturer's published<br />

instructions and the Contract Documents.FIRE SPRINKLER SUBCONTRACTOR:<br />

(Subcontractor Signature)<br />

(Subcontractor name and address)<br />

Phone Number: ( )<br />

CONTRACTOR:<br />

(Contractor Signature)<br />

(Contractor name and address)<br />

Phone Number: ( )<br />

Recommendation of Acceptance:<br />

This Recommendation of Acceptance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. We recommend Wal-Mart accept the installation of the “Systems” (as referenced above). The “Systems” are found<br />

to be in general conformance with the Contract Documents, and Approved Shop Drawings. This recommendation is based on<br />

Fire Sprinkler Site Observation and Acceptance Test (FPAT) conducted on ___________________(Report Date), and<br />

follow up verification of identified issues conducted on ___________________ (Trip Date, Report Date).<br />

While this review is an integral part of this project, it does not relieve the Contractor of their responsibility to comply with<br />

the applicable provisions of the Contract Documents along with the mandated codes and standards. These examinations shall<br />

not be construed as a check of every item nor does it prevent authorities from hereafter requiring corrections of errors in plans<br />

or installation.<br />

WAL-MART’S FIRE PROTECTION CONSULTANT:<br />

(Wal-Mart’s Fire Protection Consultant Signature )<br />

(Wal-Mart’s Fire Protection Consultant name and address)<br />

Phone Number: ( )<br />

END OF FORM<br />

13900-12<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


CONTRACTOR’S MATERIAL AND TEST CERTIFICATE FOR UNDERGROUND PIPING<br />

Store Number:<br />

Date:<br />

City, ST:<br />

Pipe Type and Class: Type Joint :<br />

Underground<br />

Pipes<br />

And<br />

Joints<br />

Test Description<br />

Pipe conforms to NFPA 13/24: □ Yes □ No<br />

Fittings conform to NFPA 13/ 24: □ Yes □ No<br />

If no explain :<br />

Joints anchored clamped, strapped, or blocked in accordance with NFPA 13/24: □ Yes<br />

If no, explain:<br />

Flushing: Flow the required rate until water is clear and indicated by no collection of foreign material<br />

in burlap bags at outlets such as hydrants and blow-offs. Flush at flows not less than 390 gpm for 4 in.<br />

pipe, 880 gpm for 6 in. pipe, 1560 gpm for 8 in. pipe, 2440 gpm for 10 in. pipe, and 3520 gpm for 12<br />

in. pipe. When supply cannot produce stipulated flow rates, obtain maximum available.<br />

Hydrostatic: All piping and attached appurtenances subjected to system working pressure shall be<br />

hydrostatically tested at 200 psi or 50 psi in excess of the system working pressure, whichever is<br />

greater, and shall maintain that pressure ± 5 psi for 2 hours.<br />

Hydrostatic Testing Allowance: Where additional water is added to the system to maintain the test<br />

pressures required by 10.10.2.2.1, the amount of water shall be measured and shall not exceed the limits<br />

of the equation in the Leakage Test section.<br />

New underground piping and lead in flushed according to NFPA 13/24: □ Yes □ No<br />

If no, explain :<br />

□ No<br />

Flushing Test<br />

Hydrostatic Test<br />

How flushing flow was obtained:<br />

Public water<br />

□<br />

Tank or Reservoir □<br />

Fire pump<br />

□<br />

All new underground piping hydrostatically<br />

tested at ________ psi for _______ hours.<br />

If no, explain:<br />

SD P<br />

L =<br />

148 ,000<br />

Through what type opening:<br />

Hydrant butt<br />

□<br />

Open pipe<br />

□<br />

Joints Covered: □ Yes □ No<br />

L =<br />

(________ ft) × (_________<br />

in) × (_______<br />

) psi<br />

148,000<br />

Leakage Test<br />

Hydrants<br />

L= testing allowance, gal per hr<br />

S= length of pipe, ft<br />

D= nominal diameter of pipe, in.<br />

P= Avg test pressure during hydrostatic test, psi<br />

L= Allowable leakage: ________gal ______hrs<br />

Leakage measured: ________gal ______hrs<br />

Leakage actual< leakage allowed?<br />

□ Yes □ No<br />

Number installed: Manufacturer & Model: All operate satisfactorily:<br />

□ Yes □ No<br />

Water control valves left wide open: □ Yes □ No<br />

If no, explain:<br />

Hose threads of fire department connections and hydrants compatible with AHJ: □ Yes<br />

□ No<br />

Contractor Firm & Contact Name:<br />

Signatures<br />

Signature: Title: Date:<br />

AHJ Witness:<br />

Representing:<br />

Signature: Title: Date:<br />

END OF FORM<br />

13900-13<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


BLANK PAGE<br />

13900-14<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 033111<br />

SECTION 15050 - BASIC MECHANICAL MATERIALS AND METHODS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Hangers and Supports: Pipe supports.<br />

B. Related Requirements:<br />

1. Section 13900 - Fire Suppression: Fire Protection Sprinkler system piping.<br />

2. Section 15100 - Building Service Piping and Equipment: Domestic water, reverse osmosis, sanitary drain<br />

and vent, interior storm water, and condensate piping. Piping Insulation. Pipe freeze protection.<br />

3. Section 15190 - Fuel Gas Piping: Natural and LP gas piping.<br />

4. Section 15600 - Refrigeration Systems.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Society of Mechanical Engineers (ASME):<br />

1. ASME B31.9 - Building Services Piping.<br />

C. Cast Iron Soil Pipe Institute (CISPI):<br />

1. Cast Iron Soil Pipe and Fittings Handbook.<br />

D. Manufacturers Standardization Society of The Valve and Fittings Industry Inc. (MSS):<br />

1. MSS SP-69 - Pipe Hangers and Supports – Selection and Application.<br />

2. MSS SP-89 - Pipe Hangers and Supports - Fabrication and Installation Practices.<br />

1.3 QUALITY ASSURANCE<br />

A. Comply with rules and regulations of public utilities and municipal department affected by connection of services.<br />

B. Laws, codes, and ordinances shall take precedence except where work called for by Drawings and Specifications<br />

exceeds code requirements in quality or quantity.<br />

1.4 CONSTRUCTION DOCUMENTS<br />

A. Drawings and Specifications show pipe and duct sizes, general routing and location, and describe various systems.<br />

These documents describe equipment, including size, general location, usage, support, and auxiliary requirements.<br />

Contract Documents do not, however, detail certain job requirements. Drawings are intended to cover layout and<br />

design of the Work and are not to be scaled for exact measurements. Where specific detail and dimension for mechanical<br />

Work are not shown on Drawings, take measurements and make layouts as required for proper installation<br />

of mechanical Work in coordination with other Work on project.<br />

1.5 DELIVERY, STORAGE AND HANDLING<br />

A. Follow manufacturer's published directions in the delivery, storage, protection, installation, piping, and wiring,<br />

and start-up of equipment and materials.<br />

15050 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


PART 2 - PRODUCTS<br />

2.1 HANGERS AND SUPPORTS<br />

A. Pipe Hanger Schedule: Pipe hangers, except for fire suppression piping, shall be as specified in Schedule I at the<br />

end of this Section. Trapeze hangers for multiple parallel pipes shall be installed as shown on the drawings.<br />

B. Hangers and supports for fire suppression piping shall be as shown on the drawings.<br />

C. Wall Support for Pipe Sizes to 3 Inches: Steel riser clamp.<br />

D. Wall Support for Pipe Sizes 4 Inches and Over: Welded steel bracket and wrought steel clamp, adjustable steel<br />

yoke and cast iron roll for hot pipe sizes 6 inches and over.<br />

E. Vertical Support: Steel riser clamp.<br />

F. Provide copper plated hangers and supports for uninsulated copper piping. Provide plastic inserts for uninsulated<br />

copper piping penetrating metals studs.<br />

PART 3 - EXECUTION<br />

3.1 HANGERS AND SUPPORTS<br />

A. Support pipes throughout building, both horizontally and vertically in accordance with requirements herein and as<br />

shown on the drawings. Attach to structure overhead as shown on drawings. Do not use fasteners which penetrate<br />

the roof deck.<br />

B. In areas without ceilings, secure insulation shields to insulation with pressure sensitive tape at each end of shield.<br />

C. Piping Support Spacing: Support horizontal piping above slab, except fire suppression piping, as shown in Schedules<br />

I-III at the end of this Section.<br />

1. Support fire suppression piping at spacing as shown on the Fire Protection (FP) drawings.<br />

D. Install hangers to provide minimum 1/2 inch clear space between finished covering and adjacent work.<br />

E. Place a hanger within one foot of each horizontal elbow.<br />

F. Support vertical pipe runs at roof, at floor, and at maximum 15-foot intervals.<br />

G. Space supports not more than five feet apart at valves, strainers or piping accessories larger than 2 inches.<br />

H. Install hangers and supports to allow controlled thermal and seismic movement of piping systems, to permit freedom<br />

of movement between pipe anchors, and to facilitate action of expansion joints, expansion loops, expansion<br />

bends, and similar units.<br />

I. Comply with the requirements of Section 09900 for field painting and touch-up.<br />

3.2 ADJUSTING<br />

A. Hanger Adjustments: Adjust hangers to distribute loads equally on attachments and to achieve indicated slope of<br />

pipe.<br />

B. Load Distribution: Adjust hangers and supports so that piping live and dead loads and stresses from movement<br />

will not be transmitted to connected equipment.<br />

15050 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


C. Pipe Slopes: Adjust hangers and supports to provide indicated pipe slopes and to not exceed maximum pipe deflections<br />

allowed by ASME B31.9 for building services piping.<br />

D. Trim excess length of continuous-thread hanger and support rods to 1-1/2 inch.<br />

3.3 OPERATION PRIOR TO ACCEPTANCE<br />

A. Contractor may operate any equipment provided that the operation is supervised and the Contractor retains full responsibility<br />

for properly maintaining equipment and the full manufacturers warranty remains unaffected from the<br />

time of Owner’s possession.<br />

3.4 SCHEDULES: Schedules below apply to all piping, except fire suppression piping, hung inside the building.<br />

SCHEDULE I - PIPE HANGER SCHEDULE<br />

Pipe Service Pipe Size Hanger Type B-Line Globe Grinnell<br />

(Anvil) No.<br />

PHD<br />

Uninsulated<br />

Steel or PVC<br />

or CPVC<br />

Uninsulated<br />

Copper<br />

Cast Iron<br />

Soil Pipe<br />

2" & smaller Split Ring B-3173 with 721 108 with 114 500 with 114<br />

B-3224<br />

2-1/2" &<br />

larger<br />

Clevis B-3100 404/407 260 450<br />

2" & smaller Ring B-3170-CT 301 CT 99 152<br />

2-1/2" &<br />

larger<br />

Clevis B-3104-CT 407 CT 65 442<br />

All Clevis B-3102 404 260 420<br />

Insulated<br />

Steel or PVC<br />

2" & smaller,<br />

2 1/2” &<br />

larger<br />

Clevis<br />

B-3100 with<br />

shield<br />

404 with<br />

shield<br />

260 with<br />

shield<br />

450 with<br />

shield<br />

Insulated<br />

Copper<br />

2" & smaller Clevis B-3104 with<br />

shield<br />

2 1/2" &<br />

larger<br />

Clevis<br />

B-3100 with<br />

shield<br />

411 with<br />

shield<br />

408 with<br />

shield<br />

CT 65 with<br />

shield<br />

260 with<br />

shield<br />

442 with<br />

shield<br />

442 with<br />

shield<br />

15050 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


SCHEDULE II - PIPING SUPPORT SCHEDULE<br />

Maximum Spacing In Feet<br />

Copper Steel Cast Iron PVC CPVC<br />

6’ max up to<br />

1-1/4” I.D.<br />

10’ max all<br />

other<br />

12' max<br />

5’ max, except may be 10’ max<br />

where 10’ lengths are installed.<br />

Min one hanger at each joint.<br />

4' max<br />

3’ max up to<br />

1” I.D.<br />

4’ max all<br />

other<br />

SCHEDULE III - PIPING SUPPORT SCHEDULE<br />

(GAS PIPE)<br />

Maximum Spacing In Feet<br />

Pipe I.D.<br />

Steel<br />

1/2" 6'<br />

3/4" and larger 8'<br />

END OF SECTION<br />

15050 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 012811<br />

SECTION 15100 (22 1000) - BUILDING SERVICES PIPING AND EQUIPMENT<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Under-building slab and aboveground domestic water pipes, tubes, fittings, and specialties inside the<br />

building.<br />

2. Garden Center irrigation water piping.<br />

3. Reverse osmosis water system piping.<br />

4. Sanitary waste and vent piping.<br />

5. Interior storm drainage piping.<br />

6. Air conditioning condensate piping.<br />

7. Waste cooking oil piping.<br />

8. Water piping and drain piping specialties.<br />

9. Grease interceptors.<br />

10. Pipe freeze protection.<br />

11. Pumps including sump pumps, liquid transfer pump stations, & domestic water booster pumps.<br />

12. Connection of miscellaneous equipment furnished under other Sections.<br />

B. Related Requirements:<br />

1. Section 06100 - Rough Carpentry: Preservative pressure treatment for wood blocking pipe supports.<br />

2. Section 02532 - Sewage Lift Stations.<br />

3. Section 07530 - Elastomeric Membrane Roofing: Isolation pads for pipe supports on roofing.<br />

4. Section 07620 - Sheet Metal Flashing and Trim: Flashing of roof penetration.<br />

5. Section 02300 - Earthwork: Backfilling and compacting trenches.<br />

6. Division 13 - Fire Suppression fire pumps.<br />

7. Section 15050 - Basic Mechanical Materials and Methods: Piping hangers and supports.<br />

8. Section 15480 - Domestic Water Heaters: Recirculating pumps for domestic water heating system.<br />

9. Section 16100 - Wiring Methods.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. The publications are<br />

referred to within the text by the basic designation only.<br />

B. American Society of Mechanical Engineers (ASME):<br />

1. ASME A13.1 - Scheme for the Identification of Piping Systems.<br />

C. American National Standards Institute (ANSI):<br />

1. ANSI B16.18 - Cast Copper Alloy Solder Joint Pressure Fittings.<br />

2. ANSI B16.22 - Wrought Copper & Copper Alloy Solder-Joint Pressure.<br />

D. American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE):<br />

1. ASHRAE 90.1 - Energy Efficient Design of New Buildings Except New Low-Rise Residential Buildings.<br />

E. ASTM International (ASTM):<br />

1. ASTM A53 - Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless.<br />

2. ASTM A74 - Hub and Spigot Cast Iron Soil Pipe and Fittings.<br />

3. ASTM A536 - Ductile Iron Castings.<br />

4. ASTM A861 - High-Silicon Iron Pipe and Fittings.<br />

5. ASTM A888 - Hubless Cast Iron Soil Pipe and Fittings.<br />

6. ASTM B75 - Seamless Copper Tube.<br />

15100 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


7. ASTM B88 - Seamless Copper Water Tube.<br />

8. ASTM B135 - Seamless Brass Tube.<br />

9. ASTM B306 - Copper Drainage Tube (DWV).<br />

10. ASTM B584 - Copper Alloy Sand Castings for General Applications.<br />

11. ASTM C564 - Rubber Gaskets for Cast Iron Soil Pipe and Fittings.<br />

12. ASTM C921 - Determining the Properties of Jacketing Materials for Thermal Insulation.<br />

13. ASTM C1277 - Shielded Couplings Joining Hubless Castiron Soil Pipe and Fittings.<br />

14. ASTM C1540 - Heavy Duty Shielded Couplings Joining Hubless Cast Iron Soil Pipe and Fittings.<br />

15. ASTM D1785 - Poly vinyl Chloride (PVC) Plastic Pipe, Schedules 40, 80, and 120.<br />

16. ASTM D2000 - Standard Classification System for Rubber Products in Automotive Applications.<br />

17. ASTM D2467- Polyvinyl Chloride (PVC) Plastic Pipe Fittings, Schedule 80.<br />

18. ASTM D2564 - Solvent Cements for Polyvinyl Chloride (PVC) Plastic Pipe and Fittings.<br />

19. ASTM D2609 - Plastic Insert Fittings for Polyethylene (PE) Plastic Pipe.<br />

20. ASTM D2665 - Poly(Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings<br />

21. ASTM D2855 - Making Solvent-Cemented Joints with Polyvinyl Chloride (PVC) Pipe and Fittings.<br />

22. ASTM D3311 - Drain, Waste, and Vent (DWV) Plastic Fittings Patterns<br />

23. ASTM E84 - Surface Burning Characteristics of Building Materials.<br />

24. ASTM E96 - Water Vapor Transmission Materials.<br />

25. ASTM F439 - Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe Fittings, Schedule 80.<br />

26. ASTM F441 - Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe, Schedules 40 And 80.<br />

27. ASTM F493 - Solvent Cements for CPVC Pipe and Fittings.<br />

28. ASTM F656 - Primers For Use in Solvents Cement Joints of Poly (Vinyl Chloride) (PVC) Plastic Pipe and<br />

Fittings.<br />

29. ASTM F876 - Crosslinked Polyethylene (PEX) Tubing.<br />

30. ASTM F2014 - Non-Reinforced Extruded Tee Connections for Piping Applications.<br />

F. American Water Works Association (AWWA):<br />

1. AWWA C104 - Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water.<br />

2. AWWA C115 - Flanged Ductile-Iron Pipe with Ductile-Iron or Gray-Iron Threaded Flanges.<br />

3. AWWA C151 - Ductile-Iron Pipe, Centrifugally Cast.<br />

4. AWWA C651 - Disinfecting Water Mains.<br />

G. Hydraulic Institute (HI):<br />

1. HI M103 (ANSI/HI 1.4) - Centrifugal Operations.<br />

H. International Association of Plumbing and Mechanical Officials (IAPMO):<br />

1. IAPMO/ANSI Z1001- Prefabricated Gravity Grease Interceptors.<br />

I. NSF International (NSF):<br />

1. NSF 61 Annex G - Weighted Average Lead Content Evaluation Procedure to a 0.24 Percent Lead<br />

Requirement.<br />

J. Plumbing and Drainage Institute (PDI):<br />

1. PDI WH 201- Water Hammer Arrestors.<br />

K. Underwriters Laboratories (UL):<br />

1. UL 778 – Motor-Operated Water Pumps.<br />

1.3 SUBMITTALS<br />

A. Comply with the requirements of Section 01330.<br />

B. Product Data: Submit product data and installation details for grease interceptor to Authority Having Jurisdiction<br />

for approval. Include rated capacities, operating characteristics, and accessories.<br />

15100 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


C. Water Samples: Submit to Authorities Having Jurisdiction in accordance with the requirements of Cleaning and<br />

Disinfection paragraph in Part 3.<br />

1.4 CLOSEOUT SUBMITTALS<br />

A. Submit the following as described in the testing and inspection requirements in Part 3 below as a part of closeout<br />

submittals in accordance with Section 01770.<br />

1. Video Inspection Report: Furnish one copy of Video Inspection Report to Wal-Mart Construction Manager<br />

within one week after completion of inspection.<br />

2. Dye Test Report: Furnish one copy of Dye Test report to Wal-Mart Construction Manager within one<br />

week after completion of test procedure.<br />

3. Disinfection report.<br />

4. Certification: Provide statement of certification of the following:<br />

a. Verification of Dye Test Contractor qualifications.<br />

b. Statement of completion that Work is in accordance with specified requirements.<br />

c. Name and signature of General Contractor.<br />

d. Names and signatures of Dye Test Contractor.<br />

5. Certification: Provide statement of certification of the following:<br />

a. Verification of Video Inspection Contractor qualifications.<br />

b. Statement of completion that Work is in accordance with specified requirements.<br />

c. Name and signature of General Contractor.<br />

d. Names and signatures of Video Inspection Contractor.<br />

6. Certification: Submit domestic water supply copper piping assembly system manufacturer’s certification<br />

that piping system is installed in accordance with manufacturer’s recommendations.<br />

1.5 QUALITY ASSURANCE<br />

A. Domestic Water Supply Copper Piping Assembly Installer Qualifications: If Contractor provides any of the<br />

optional domestic water supply copper piping assembly systems specified in Part 2, Installer shall be a certified<br />

installer of system provided.<br />

B. Video Inspection Contractor Qualifications: Inspection shall be conducted by Contractor with at least 2 years<br />

experience in the specific work involved.<br />

C. Dye Test Contractor Qualifications: Testing shall be conducted by Contractor with at least 2 years experience in<br />

the specific work involved.<br />

D. Regulatory Requirements:<br />

1. Lead-Free Compliance: Domestic water piping and fittings, pumps, water piping specialties and specialty<br />

plumbing fixtures shall comply with the requirements of NSF 61 Annex G.<br />

1.6 DELIVERY, STORAGE, AND HANDLING<br />

A. Receive and handle Owner Furnished products in compliance with the requirements of Section 01640.<br />

B. Transport and handle Direct Purchase and Contractor Furnished products in compliance with the requirements of<br />

Section 01600.<br />

C. Store and protect Owner Furnished, Direct Purchase and Contractor Furnished products in compliance with the<br />

requirements of Section 01600.<br />

15100 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner’s supplier will furnish domestic water booster pumps, if and as shown<br />

and scheduled in Pump Schedules on Drawings, for installation by Contractor.<br />

2.2 DIRECT PURCHASE PROCUREMENT<br />

A. The following items shall be direct purchased by Contractor from Owner’s Pre-negotiated Supplier.<br />

1. Water piping specialties including vacuum breakers, water pressure regulators, mixing valves, and hose<br />

reels as scheduled on the Drawings on the Plumbing Fixture/Water Piping Specialties Schedule.<br />

2. Drainage specialties including floor drains (except FD2 hub drains), trench drains, roof drains, deck drains,<br />

floor cleanouts, yard cleanouts, wall cleanouts, hose bibbs, and hydrants as scheduled on the Drawings on<br />

the Drain/Cleanout/Hose Bibb/Hydrant Schedule.<br />

B. Pre-negotiated Supplier:: Haines, Jones & Cadbury, Inc., Contact: Customer Service, (800) 459-7099, fax (479)<br />

756-8998, Email: info@hjcinc.com.<br />

C. Reference Section 01600 for additional information regarding Direct Purchase Products.<br />

2.3 DOMESTIC WATER PIPING<br />

A. Water Piping Above Grade:<br />

1. Type "L" hard drawn, seamless copper water tube, ASTM B88.<br />

2. Jointing: Join with wrought copper pressure fittings, ANSI B16.22. Make joints using "lead free" solder<br />

and a non-corrosive, paste-type flux. Core solder is not permitted. Solder shall be solid string or wire type.<br />

Where soldered copper piping is connected to threaded brass piping, use cast brass adaptor.<br />

3. At Contractor’s option, in lieu of a soldered copper piping system as specified above, any of the following<br />

copper pipe assembly systems may be used.<br />

a. CTS Copper Grooved Piping System by Victaulic Company of America: Copper tubing systems<br />

from 2 inch through 8 inch shall be installed using mechanical pipe couplings of a bolted type, with<br />

pressure-responsive gaskets and grooved end copper or bronze fittings. The CTS System shall<br />

include the following components:<br />

1) Copper Tube: Type "L" hard drawn, seamless copper water tube, ASTM B88.<br />

2) Mechanical Couplings: Style 606 rigid couplings 2 inch – 8 inch for copper consisting of a<br />

ductile iron cast housing, a synthetic rubber gasket of a pressure-responsive design, with<br />

plated nuts and bolts to secure unit together.<br />

3) Coupling Housings: Ductile iron conforming to ASTM A536, Grade 65-45-12, with a copper<br />

color alkyd enamel paint coating.<br />

4) Gaskets: Molded of Grade “E” EPDM synthetic rubber, conforming to ASTM D2000,<br />

designation 2CA615A25B24F17Z, and recommended for potable water service within the<br />

specified temperature range of –30 to +230 degrees F. Gaskets shall conform to the copper<br />

tube size (CTS) outside diameter and coupling housing inside diameter.<br />

5) Flange Adapters: Style 641 adapters 2 inch - 6 inch, ductile iron ASTM A536, Grade 65-45-<br />

12, engaging directly into roll grooved copper tube and fittings and bolting directly to ANSI<br />

Class 125 cast iron and Class 150 steel flanged components; installer shall provide standard<br />

flange bolts.<br />

6) Fittings: Full flow copper fittings with grooves designed to accept Victaulic grooved end<br />

couplings. Fittings shall be copper per ASTM B75 alloy C12200; or bronze sand castings per<br />

ASTM B584 copper alloy CDA 844 (81-3-7-9) per ANSI B16.18. Use Style 47 dielectric<br />

waterways when connecting dissimilar metals in liquid systems.<br />

15100 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


7) Valves: Series 608 Butterfly valves, 2-1/2 inch – 6 inch, 300 psi, with grooved ends, cast<br />

bronze body to CDA-836 (85-5-5-5), rubber encapsulated ductile iron disc, ASTM A536,<br />

Grade 65-45-12. Bubble tight, dead-end or bi-directional service as required.<br />

15100 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


. Press-connect copper pipe fitting system by one of the following:<br />

1) ProPress by Viega.<br />

2) Xpress by Elkhart Products Corporation.<br />

c. Mechanically formed tee fitting system by T-Drill Industries in accordance with ASTM F 2014.<br />

B. Water Piping Below Grade (Under Slab):<br />

1. 1-1/2 Inches and Smaller:<br />

a. Crosslinked PE (PEX) tubing, ASTM F876 without joints beneath the slab.<br />

b. Type "K" soft copper without joints beneath slab.<br />

2. 2 Inches and Larger: Type K hard drawn with brazed fittings.<br />

C. Chrome-Plated Seamless Brass Tube: ASTM B135.<br />

D. Insulation:<br />

1. Manufacturers: Subject to compliance with requirements, provide insulation as manufactured by one of the<br />

following:<br />

a. CertainTeed.<br />

b. Imcoa (Nomaco K-Flex).<br />

c. Knauf.<br />

d. Owens-Corning.<br />

e. Johns Manville.<br />

f. Armacell.<br />

2. Provide one of the following types of insulation throughout the project:<br />

a. Rigid Glass Fiber: Type ASJ/SSL, maximum k factor at 75 degrees F of 0.23 Btu-in/hr.f.sq ft, 3<br />

lb/cu.ft density. Vapor barrier jacket shall be white kraft paper with glass fiber yarn, bonded to<br />

aluminized film conforming to ASTM C921, with a maximum moisture vapor transmission rate of<br />

0.02 perm-inch in accordance with ASTM E96. Insulate fittings with PVC covers with glass fiber<br />

inserts.<br />

b. Polymer Foam Insulation: Arctictherm by Imcoa or equal. Maximum k factor at 75 degrees F of<br />

0.25 Btu-in/hr.f.sq ft, 1.5 lbs/cu. ft. density, maximum flame spread and smoke development of 25<br />

and 50, respectively per ASTM E84. Insulate fittings with pre-formed foam covers.<br />

c. Elastomeric Flexible Closed Cell Insulation: AP Armaflex W (white) by Armacell or equal.<br />

Maximum k factor at 75 degrees F of 0.28 Btu-in/hr.f.sq ft, maximum flame spread and smoke<br />

development of 25 and 50, respectively. Insulate fittings per manufacturer's recommendations.<br />

3. Insulation Color: White.<br />

4. Insulation Thickness: Provide minimum insulation thickness for water piping in compliance with ASHRAE<br />

90.1 and the following:<br />

a. Hot Water:<br />

1) Branch runouts for nonrecirulating systems up to 1-1/2" in diameter and less than 12 feet in<br />

length: 1/2 inch insulation.<br />

2) Pipes 2 inch in diameter and less: 1 inch insulation.<br />

3) Pipes 2-1/2 inch to 4 inch: 1-1/2 inch insulation.<br />

b. Cold Water: 1/2 inch insulation.<br />

2.4 GARDEN CENTER IRRIGATION WATER PIPING<br />

A. Piping Above Grade: PVC pipe, ASTM D1785, Schedule 80, gray.<br />

1. Fittings: ASTM D2467, PVC.<br />

2. Joints: ASTM D2855, solvent weld with ASTM D2564 Solvent cement.<br />

2.5 REVERSE OSMOSIS WATER SYSTEM PIPING<br />

A. Piping Above Grade: CPVC plastic pipe, ASTM F 441, Schedule 80, plain ends.<br />

1. CPVC Plastic Pipe Fitting: ASTM F439, Socket-type fittings, Schedule 80 fittings.<br />

2. CPVC Solvent Cement: ASTM F493.<br />

15100 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3. CPVC Primer: ASTM F656.<br />

B. Piping Below Grade: Crosslinked PE (PEX) tubing, ASTM F876. Joints shall not be used under slab.<br />

C. Plastic Ball Valve: 150-psig working pressure, 250 degree F maximum operating temperature, full port design, 1<br />

or 2 piece body design, CPVC body and ball, polytetrafluoroethylene seats, EPDM seals, and tee handle with<br />

socket connections.<br />

D. Piping and fitting shall carry the NSF International (NSF) Seal of Approval for potable water application.<br />

E. Final Connection Tubing.<br />

1. Final Connection Tubing: Crosslinked PE (PEX) tubing, ASTM F876 with insert fittings conforming to<br />

ASTM D2609.<br />

2.6 SANITARY WASTE AND VENT PIPING<br />

A. Soil, Waste, and Vent Piping: Provide any of the following as applicable:<br />

1. PVC Pipe: May be used for sanitary drainage pipes (drain, waste, and vent) where permitted by Authority<br />

Having Jurisdiction.<br />

a. Solid-Wall PVC Pipe: ASTM D2665, drain, waste, and vent. Cellular (foam) core PVC not<br />

permitted.<br />

b. PVC Socket Fittings, ASTM D2665, made to ASTM D3311, drain, waste, and vent patterns.<br />

2. Cast Iron (Above grade only): Cast iron soil pipe and fittings, coated inside and outside, ASTM A74 or<br />

ASTM A888. Provide weight of pipe as required by code for location and duty.<br />

3. Ductile-Iron Pipe (Above grade only): AWWA C151 or AWWA C115 ductile-iron pipe, with AWWA<br />

C104 cement-mortar lining.<br />

4. Copper Drainage Tubing (Above grade only): Copper drainage tubing conforming to ASTM B306.<br />

5. ABS Pipe: Not Permitted.<br />

B. Joints:<br />

1. Cast Iron Pipe (Above grade only): Push-on compression gasketed type joint for hub and spigot, ASTM<br />

C564. No-hub mechanical joints with center stops, ASTM C1277 or ASTM C1540.<br />

2. PVC Pipe: Solvent-welded joints.<br />

3. Copper Drainage Tubing: Join with wrought copper pressure fittings, ANSI B16.22. Make joints using<br />

"lead free" solder and a non-corrosive paste type flux. Core solder shall not be used. Solder shall be solid<br />

string or wire type.<br />

C. Traps:<br />

1. Provide deep seal P-traps for floor drains, including drains furnished as integral parts of floor-type mop<br />

basins, and similar fixtures.<br />

2.7 INTERIOR STORM DRAINAGE PIPING<br />

A. Pipe: As specified for sanitary waste and vent piping.<br />

B. Insulation: Rigid glass fiber, maximum k factor at 75 degrees F of 0.27 Btu-in/hr.f.ft, 3lb/cu.ft density, minimum<br />

of 1 inch thick. Vapor barrier jacket shall be white kraft paper with glass fiber yarn, bonded to aluminized film<br />

conforming to ASTM C921, with a maximum moisture vapor transmission rate of 0.02 perm-inch in accordance<br />

with ASTM E96.<br />

1. Manufacturers: Subject to compliance with requirements, provide insulation as manufactured by one of the<br />

following:<br />

a. CertainTeed.<br />

b. Knauf.<br />

c. Owens-Corning.<br />

d. Johns Manville.<br />

15100 - 7<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2.8 AIR CONDITIONING CONDENSATE PIPING<br />

A. Condensate Trap: Install trap furnished with RTU.<br />

B. Condensate Piping Above the Roof: ASTM A 53, Schedule 40 galvanized steel with galvanized malleable iron or<br />

galvanized steel fittings.<br />

C. Condensate Piping Below the Roof: PVC plastic pipe and fittings conforming to requirements specified for<br />

sanitary waste and vent piping hereinbefore.<br />

D. Insulation: As specified for domestic water piping, 1/2 inch thick for condensate piping below the roof.<br />

2.9 WASTE COOKING OIL PIPING<br />

A. Outlet (Discharge) and Vent Piping: ASTM A53 Schedule 40 galvanized steel pipe with 150 lb galvanized steel<br />

threaded fittings.<br />

2.10 PUMPS<br />

A. Subject to compliance with Project requirements, provide pumps of manufacturers, types, and model numbers as<br />

indicated on the Pump Schedules on the Drawings. Pumps shall include sump pumps and domestic water booster<br />

pumps to the extent shown, and accessories therefor.<br />

B. UL Compliance: Comply with UL 778 for motor-operated water pumps.<br />

2.11 WATER PIPING SPECIALITIES<br />

A. Subject to compliance with Project requirements, provide piping specialties of manufacturers, types, and model<br />

numbers as indicated on the Plumbing Schedules on the Drawings. Water piping specialties shall include such<br />

items as hose bibbs, hydrants, valves, backflow preventers, vacuum breakers, mixing valves, pressure reducing<br />

(regulating) valves, expansion tanks, water hammer arresters, trap primers, and accessories therefor.<br />

2.12 DRAINAGE PIPING SPECIALITIES<br />

A. Subject to compliance with Project requirements, provide piping specialties of manufacturers, types, and model<br />

numbers as indicated on the Plumbing Schedules on the Drawings. Drainage piping specialties shall include floor<br />

and roof drains, deck drains, cleanouts and accessories therefor.<br />

2.13 GREASE INTERCEPTORS<br />

A. Provide grease interceptor and associated piping as shown on the drawings and as acceptable to the Authority<br />

Having Jurisdiction. Minimum size shall be as indicated.<br />

B. Construct, label and install grease interceptor in accordance with IAPMO/ANSI Z1001.<br />

2.14 SPECIALITY PLUMBING FIXTURES<br />

A. Subject to compliance with Project requirements, provide specialty plumbing fixtures of manufacturers, types, and<br />

model numbers as scheduled on the Drawings.<br />

2.15 PIPE FREEZE PROTECTION<br />

A. Pipe freeze protection system shall include the following:<br />

1. Parallel circuit heating cable.<br />

15100 - 8<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2. Transformers.<br />

3. Outdoor ambient thermostat.<br />

4. Junction boxes.<br />

5. Branch circuit wiring and conduit as specified in Section 16100.<br />

6. Other items as necessary to complete system.<br />

B. Components:<br />

1. Heating Cable: Parallel circuit, jacketed cable, self-limiting, 120 volt. Provide XL-Trace as manufactured<br />

by Raychem/Tyco or CO Series by Delta-Therm.<br />

a. Provide minimum 5 watts per lineal foot (or more) as required for specified piping and insulation<br />

per manufacturer's published instructions.<br />

b. Provide termination fittings for direct connection to junction boxes.<br />

2. Junction Boxes: NEMA 5 watertight..<br />

3. Outdoor Ambient Thermostat: Provide thermostat with adjustable contacts. Set contacts to close at 40<br />

degrees F on decreasing temperature.<br />

2.16 SUBSTITUTIONS<br />

A. Reference Section 01600.<br />

PART 3 - EXECUTION<br />

3.1 PIPING INSTALLATION<br />

A. Install piping neatly and parallel with, or perpendicular to, lines of the structure. Install pipe hangers as specified in<br />

Section 15050 to maintain accurately aligned piping systems, adequately supported both laterally and vertically.<br />

B. Backfill and compact trenches for piping below the slab per Section 02300.<br />

C. Provide Schedule 40 steel pipe sleeve, minimum of one size larger than the protected pipe, for underground piping<br />

routed beneath structural footings. Extend sleeve 24 inches in both directions beyond the footing.<br />

D. Where practical, connect two or more vents together and extend as one vent through roof. Make vent connections<br />

to stacks by appropriate use of 45 degree wyes, long sweep quarter bends, sixth, eighth, or sixteenth bends, except<br />

that sanitary tees may be used on the vertical stacks.<br />

E. Extend vent piping 12 inches above roof line or more if required by Authority Having Jurisdiction. Coordinate<br />

installation with roofing.<br />

F. Conceal piping in chases, interior walls, furred spaces, and above ceiling.<br />

G. Identify nonpotable water systems by color markings or metal tags in accordance with ASME A13.1.<br />

H. Make piping connections to fixtures and equipment with chrome-plated seamless brass tube with cleanout plug<br />

and escutcheon.<br />

I. For items to be installed on split face CMU, grind surface of CMU to a smooth finish for tight installation. Seal<br />

with silicone sealant in accordance with Section 07900.<br />

J. Connect piping and fittings in accordance with manufacturer’s instructions using specialty tools as required and<br />

recommended by the manufacturer.<br />

3.2 PIPING INSULATION - INSTALLATION<br />

A. Domestic Hot and Cold Water Lines: Insulate lines above slab. Do not insulate garden center irrigation piping nor<br />

Reverse Osmosis piping.<br />

15100 - 9<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Interior Air Conditioning Condensate Piping: Insulate condensate piping below roof.<br />

C. Interior Horizontal Storm Drainage Piping Above Grade: Adhere insulation with 6 inch wide adhesive strips on 16<br />

inch centers. Provide 16 gage annealed tie wire, spiral wound, or tied at 16 foot centers for securing insulation<br />

until adhesive sets. Butt insulation and seal joints with 2 inch wide foil tape adhered over joints. Insulate<br />

horizontal piping and vertical elbows. Do not insulate drain bodies.<br />

3.3 PUMP INSTALLATION<br />

A. Install pumps where shown on the drawings and in accordance with manufacturer’s instructions.<br />

B. Pump Installation Standard: Comply with HI M103 for installation of sump and domestic water pumps.<br />

3.4 WATER PIPING SPECIALITIES INSTALLATION<br />

A. Install backflow preventers in each water supply to mechanical equipment and systems and to other equipment<br />

where shown and water systems that may be sources of contamination. Comply with Authorities Having<br />

Jurisdiction.<br />

1. Locate backflow preventers in same room as connected equipment or system.<br />

2. Install drain for backflow preventers with atmospheric-vent drain connection with air-gap fitting, fixed airgap<br />

fitting, or equivalent positive pipe separation of at least two pipe diameters in drain piping and pipe to<br />

floor drain. Locate air-gap device attached to or under backflow preventer. Simple air breaks are not<br />

acceptable for this application.<br />

3. Do not install bypass piping around backflow preventers.<br />

B. Install water regulators with inlet and outlet shutoff valves. Install pressure gages on inlet and outlet.<br />

C. Install balancing valves in locations where they can easily be adjusted.<br />

D. Install temperature-actuated water mixing valves with check stops or shutoff valves on inlets and with shutoff<br />

valve on outlet.<br />

1. Install thermometers and water regulators if specified.<br />

2. Install cabinet-type units recessed in or surface mounted on wall as specified.<br />

E. Install Y-pattern strainers for water on supply side of each control valves and pressure-reducing valves.<br />

F. Install water hammer arresters in water piping according to PDI-WH 201.<br />

G. Install supply-type, trap-seal primer valves with outlet piping pitched down toward drain trap a minimum of<br />

1 percent, and connect to floor-drain body, trap, or inlet fitting. Adjust valve for proper flow.<br />

H. Drawings indicate general arrangement of piping and specialties.<br />

3.5 LABELING AND IDENTIFYING<br />

A. Equipment Nameplates and Signs: Install engraved plastic-laminate equipment nameplate or sign on or near each<br />

of the following:<br />

1. Intermediate atmospheric-vent backflow preventers.<br />

2. Reduced-pressure-principle backflow preventers.<br />

3. Double-check backflow-prevention assemblies.<br />

4. Water pressure-reducing valves.<br />

5. Primary, thermostatic, water mixing valves.<br />

6. Supply-type, trap-seal primer valves.<br />

B. Distinguish among multiple units, inform operator of operational requirements, indicate safety and emergency<br />

precautions, and warn of hazards and improper operations, in addition to identifying unit.<br />

15100 - 10<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3.6 DRAIN PIPING SPECIALTIES INSTALLATION<br />

A. Install backwater valves in building drain piping. For interior installation, provide cleanout deck plate flush with<br />

floor and centered over backwater valve cover, and of adequate size to remove valve cover for servicing.<br />

B. For floor cleanouts for piping below floors, install cleanout deck plates with top flush with finished floor.<br />

C. For cleanouts located in concealed piping, install cleanout wall access covers, of types indicated, with frame and<br />

cover flush with finished wall.<br />

D. Install floor drains at low points of surface areas to be drained. Set grates of drains flush with finished floor,<br />

unless otherwise indicated.<br />

1. Position floor drains for easy access and maintenance.<br />

2. Install floor-drain flashing collar or flange so no leakage occurs between drain and adjoining flooring.<br />

Maintain integrity of waterproof membranes where penetrated.<br />

3. Install individual traps for floor drains connected to sanitary building drain, unless otherwise indicated.<br />

E. Install roof drains at low points of roof areas according to roof membrane manufacturer's written installation<br />

instructions.<br />

1. Install roof-drain flashing collar or flange so that there will be no leakage between drain and adjoining<br />

roofing. Maintain integrity of waterproof membranes where penetrated.<br />

2. Position roof drains for easy access and maintenance.<br />

F. Install deep-seal traps on floor drains and other waste outlets, if indicated.<br />

G. Install floor-drain, trap-seal primer fittings on inlet to floor drains that require trap-seal primer connection.<br />

1. Exception: Fitting may be omitted if trap has trap-seal primer connection.<br />

2. Size: Same as floor drain inlet.<br />

H. Install air-gap fittings on draining-type backflow preventers and on indirect-waste piping discharge into sanitary<br />

drainage system.<br />

I. Install grease interceptors, including trapping, venting, and flow-control fitting, according to Authorities Having<br />

Jurisdiction and with clear space for servicing.<br />

1. Install cleanout immediately downstream from interceptors not having integral cleanout on outlet.<br />

2. Connect inlet and outlet to unit, and connect flow-control fitting and vent to unit inlet piping. Install valve<br />

on outlet of automatic drawoff-type unit.<br />

J. Install traps on plumbing specialty drain outlets. Omit traps on indirect wastes unless trap is indicated.<br />

K. Install escutcheons at wall, floor, and ceiling penetrations in exposed finished locations and within cabinets and<br />

millwork. Use deep-pattern escutcheons if required to conceal protruding pipe fittings.<br />

3.7 PIPE FREEZE PROTECTION<br />

A. Install heating cable at locations shown on drawings for pipe freeze protection.<br />

B. Cut heating cable to length required for pipe lengths and watt per foot requirements. Secure to pipe and install in<br />

accordance with manufacturer's published instructions.<br />

3.8 CLEANING AND DISINFECTION<br />

A. Clean and disinfect potable domestic water piping as follows:<br />

1. Purge new piping and parts of existing piping that have been altered, extended, or repaired before using.<br />

15100 - 11<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2. Use purging and disinfecting procedures prescribed by Authorities Having Jurisdiction. If methods are not<br />

prescribed, use procedures described in AWWA C651 or follow procedures described as follows:<br />

a. Flush piping system with clean, potable water until dirty water does not appear at outlets.<br />

b. Fill and isolate system according to either of the following:<br />

1) Fill system or part thereof with water/chlorine solution with at least 50 ppm of chlorine.<br />

Isolate with valves and allow to stand for 24 hours.<br />

2) Fill system or part thereof with water/chlorine solution with at least 200 ppm of chlorine.<br />

Isolate and allow to stand for three hours.<br />

c. After the standing time, flush system with clean, potable water until the chlorine is purged from the<br />

system.<br />

B. Submit water samples in sterile bottles to Authorities Having Jurisdiction. Repeat procedures if biological<br />

examination shows contamination.<br />

C. Reports: Prepare disinfection reports signed by the Authority Having Jurisdiction and submit to Architect with<br />

Closeout Submittals.<br />

3.9 PIPE TESTS<br />

A. Test underground piping prior to backfilling and before installing equipment and before insulation is applied,<br />

using specified methods and conditions. Subject piping to test for not less than 24 hours. Make necessary<br />

replacements or repairs and repeat tests until entire system, including equipment, is accepted as satisfactory.<br />

B. Install equipment, operate systems, clean out scale, dirt, oil, waste, and foreign matter, and correct additional<br />

leaks.<br />

C. Test plumbing drainage systems under 10 foot static head for a period of not less than 24 hours. Test water<br />

systems under 150 psig hydrostatic pressure.<br />

D. Test each reduced-pressure-principle backflow preventer and double-check backflow-prevention assembly<br />

according to Authorities Having Jurisdiction and the device's reference standard.<br />

E. All pipe tests specified in this Section shall be to five feet outside building lines or to point of connection to<br />

exterior lines. Drains to oil/grease interceptor (separator) shall be tested to the point of the oil/grease inteceptor<br />

outlet.<br />

3.10 GREASE/OIL INTERCEPTOR TANK DYE TEST<br />

A. Perform dye testing on piping scheduled to be connected to the grease or oil interceptor and show evidence that all<br />

drains are properly connected to the correct interceptor.<br />

B. Dye Test Contractor Qualifications: Specified in Part 1.<br />

C. Certification: Provide dye test certification as specified in Part 1.<br />

D. Preparation:<br />

1. Scheduling:<br />

a. Identify Authority Having Jurisdiction (AHJ) presiding over drainage system into which discharges<br />

flow and determine whether prior notification to AHJ is required before scheduling dye test.<br />

b. Obtain approvals and permits required by AHJ for dye testing.<br />

c. Perform tests after plumbing rough-in is complete and before the floor slab is placed.<br />

d. Determine if states or local jurisdictions require specific color dyes for the various drain tests.<br />

2. Drains To Be Tested: Inspect drains in the areas listed below. Test all drains where more than one drain<br />

exists in an area.<br />

a. Bakery.<br />

b. Rotisserie Display.<br />

15100 - 12<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


c. Snack Bar.<br />

d. Compactor (Interior & Exterior).<br />

e. Deli Processing.<br />

f. Demo Room.<br />

g. Fresh Meat Prep.<br />

h. Produce Prep.<br />

E. Dye Test Procedure:<br />

1. Test each drain separately according to the procedure outlined.<br />

2. Locate drains to be tested. Locate grease and oil interceptor. Open the manholes over the grease and oil<br />

interceptor and verify that it is the correct structure.<br />

3. Station one person at the interceptor with the manhole open. Barricade the area appropriately to prevent<br />

accidental personnel or vehicular entry. Station another person at the inside drain to be tested. Connect hose<br />

to a nearby spigot (usually located in the bakery department) and remove the cover over the floor drain.<br />

Avoid spilling water on the sub-grade.<br />

4. Notify person at interceptor by radio that the test is about to begin. Add water from the hose into the floor<br />

drain and inject dye into the water stream. Notify person at interceptor that the test has begun. The person<br />

at the interceptor shall notify the person at the floor drain as soon as the dye appears at the interceptor. The<br />

dye at the interceptor should generally appear within ten minutes from the introduction of the dye into the<br />

floor drain.<br />

5. If the dye does not appear at the interceptor, continue to add dye with the running water and open cleanouts<br />

to check if any dye is apparent in the lines. Document which cleanouts do and do not have the appearance<br />

of dye. Check all other interceptors to determine presence of dye.<br />

6. If dye is not detected at any of the inspected locations, inspect the nearest manhole of the sanitary sewer<br />

system for the presence of dye. If there is a retention pond onsite, inspect the pond for the presence of dye.<br />

7. Document dye test activities including the time dye was added at each drain location and the time period<br />

between when dye was added and when it was detected. Identify any irregular occurrence of dye in the<br />

interceptors, cleanouts, or sewer lines.<br />

8. Upon completion of testing, replace all floor drain, vault, and manhole covers. Notify the Wal-Mart<br />

Construction Manager when the testing has been completed.<br />

F. Dye Test Report:<br />

1. Submit in accordance with requirements in Part 1.<br />

2. Submit bound report in MS Word format.<br />

3. Provide report of drains and pipes tested and defects noted. Include the following:<br />

a. Store number and location.<br />

b. Name of General Contractor.<br />

c. Name of Plumbing Contractor and Dye Testing Contractor.<br />

d. Test date.<br />

e. Documentation of dye test activities and irregular occurrences as required above.<br />

f. Plan of piping network tested. Indicate layout and size of each line tested and the point of discharge<br />

to the sanitary sewer or other location.<br />

3.11 UNDERGROUND PIPING VIDEO INSPECTION<br />

A. General: Perform video inspection of underground sewer piping from the point of connection to the manhole<br />

outside the building through the mains and through the single takeoff to each fixture.<br />

B. Perform video inspection of existing sewer piping and coordinate repair of deficiencies with Wal-Mart<br />

Construction Manager. An equitable adjustment will be made in the contract price for additional work directed and<br />

performed.<br />

C. Video Inspection Contractor Qualifications: Specified in Part 1.<br />

D. Video Inspection Certification: Provide video inspection certification as specified in Part 1.<br />

15100 - 13<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


E. Video Taping Requirements:<br />

1. Video camera designed for express purpose of sewer line inspection.<br />

2. Camera and apparatus capable of extending to all points of piping required within 2 inch to 8 inch diameter<br />

pipe.<br />

F. Procedure:<br />

1. Inspect sewer pipes with video camera no earlier than 30 days after floor slab has been poured. Sections of<br />

sewer determined to be deficient shall be uncovered and repaired or replaced to satisfaction of Owner.<br />

Retest repaired section.<br />

2. Adequately flush and clean sewer piping prior to video inspection<br />

3. Provide additional video inspection at contractor's expense if there are clogging problems within the first<br />

year warranty and if requested by owner.<br />

G. Video Inspection Report:<br />

1. Submit in accordance with requirements in Part 1.<br />

2. Submit bound report in MS Word format.<br />

3. Provide summary report of pipes inspected and defects noted<br />

4. Log shall show the exact measure location of faults such as, but not limited to:<br />

a. Open joints.<br />

b. Broken, cracked or collapsed pipe.<br />

c. Accumulation of debris or obstructions.<br />

d. Evidence of infiltration.<br />

e. Water depth variation and sags.<br />

f. Protrusions.<br />

5. The reference location shall include the distance away from the reference point of entry such as manhole or<br />

cleanout and the position of the fault as to the bottom, top or side of the pipe.<br />

6. Provide plan of piping network covered with notations.<br />

3.12 ADJUSTING<br />

A. Set field-adjustable pressure set points of water pressure-reducing valves.<br />

B. Set field-adjustable flow of balancing valves.<br />

C. Set field-adjustable temperature set points of temperature-actuated water mixing valves.<br />

3.13 PROTECTION<br />

A. Protect drains during remainder of construction period to avoid clogging with dirt or debris and to prevent damage<br />

from traffic or construction work.<br />

B. Place plugs in ends of uncompleted piping at end of each day or when work stops.<br />

END OF SECTION<br />

15100 - 14<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


BLANK PAGE<br />

15100 - 15<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 022307<br />

SECTION 15190 – FUEL GAS PIPING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Natural gas piping.<br />

2. Gas valves and regulators.<br />

B. Related Sections:<br />

1. Section 09900 - Paints and Coatings<br />

2. Section 15050 - Basic Mechanical Materials And Methods<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American National Standards Institute (ANSI):<br />

1. ANSI B31.9 - Building Services Piping Code.<br />

C. American Society of Mechanical Engineers (ASME):<br />

1. ASME B16.3 - Malleable Iron Threaded Fittings.<br />

D. ASTM International (ASTM):<br />

1. ASTM A 53 - Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless.<br />

2. ASTM A 234 - Pipe Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and Elevated Temperatures.<br />

E. National Fire Protection Association (NFPA):<br />

1. NFPA 54 - National Fuel Gas Code.<br />

1.3 QUALITY ASSURANCE<br />

A. Certifications:<br />

1. Product Certificates: Provide Manufacturer's Certification for gas regulators if required by Authority Having<br />

Jurisdictions.<br />

2. Welding: Pipe welders shall be certified and bear evidence of certification 30 days prior to commencing<br />

work on this project. When directed, welders shall be retested at Contractor's expense when evidence indicates<br />

a lack of welder proficiency. Certification will be by Pittsburgh Testing Laboratories or other approved<br />

authority.<br />

PART 2 - PRODUCTS<br />

2.1 FUEL GAS PIPING (ABOVE GRADE)<br />

A. Piping: Black steel, standard weight, Schedule 40 ASTM A 53.<br />

1. Piping 2 inches and smaller: Welded or threaded with malleable iron fittings including couplings.<br />

2. Piping 2-1/2 inches and larger: Welded, with butt-welded fittings.<br />

B. Fittings: ASME B16.3, malleable iron or ASTM A 234, forged steel welded type.<br />

C. Joints: NFPA 54, threaded or welded to ANSI B31.9, ASME Section 1.<br />

15190 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2.2 GAS SHUT-OFF VALVES<br />

A. Quarter-turn Ball Valve: UL listed for natural gas service or LP gas service as required; threaded ends, with bronze<br />

body, chrome plated brass ball, "Teflon" or "TFE" seats and seals, blowout-proof stem, adjustable packing gland,<br />

and vinyl-covered steel handle. Provide valves by one of the following:<br />

1. Conbraco (Apollo): 80-100 series (1/4”-3”)<br />

2. Nibco: T-585-70-UL series (1/2”-1”), T-580-70-UL series (1-1/4”-3”)<br />

3. Watts: B6000-UL series (1/4”-4”)<br />

2.3 PRESSURE REGULATORS<br />

A. Gas Pressure Reducing Regulators: Provide commercial style regulators manufactured by Sensus Metering Systems<br />

(North America Metering), Fisher Regular, or Actaris Metering Systems as scheduled on the drawings. Regulators<br />

shall have internal pressure relief valves.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install interior piping neatly and parallel with, or perpendicular to, lines of the structure. Install pipe hangers as<br />

specified in Section 15050 to maintain accurately aligned piping systems, adequately supported both laterally and<br />

vertically<br />

B. Extend rigid gas piping to exterior gas appliances and install shut-off valve, dirt leg, and union at each appliance.<br />

C. Provide flexible gas hose connections to all indoor heating equipment, maximum length of 24”.<br />

D. Conform to NFPA 54 and applicable local codes.<br />

E. Roof Protection: Protect roofing with welding blankets.<br />

F. Prime interior gas piping before installation. Complete installation of gas piping before roof deck is painted. Conform<br />

to Section 09900 for painting and for touch-up on the job site.<br />

G. Prime and paint exterior gas piping before installation. Conform to Section 09900 for painting and for touch-up on<br />

the job site.<br />

H. Identify interior gas piping with color markings on top of pipe in accordance with ASME A13.1.<br />

3.2 FIELD QUALITY CONTROL<br />

A. Testing:<br />

1. Pressure test piping at 60 psig, or as required by Authority Having Jurisdiction if more stringent.<br />

2. Maintain full test pressure for a period of 30 minutes, and make visual inspection for tightness of system.<br />

END OF SECTION<br />

15190 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 052810<br />

SECTION 15410 (22 4000) - PLUMBING FIXTURES<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Plumbing fixtures.<br />

2. Plumbing fixture trim.<br />

B. Related Requirements:<br />

1. Section 01600 - Product Requirements: Requirements for Pre-Negotiated Suppliers.<br />

2. Section 01770 – Contract Closeout: Operation and maintenance data requirements.<br />

3. Section 07900 - Joint Sealers: Sealant for fixtures at wall and floors.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. American Society of Mechanical Engineers (ASME):<br />

1. ASME /ANSI A112.18.1 - Plumbing Fixture Fittings.<br />

C. NSF International (NSF):<br />

1. NSF 61 Annex G - Weighted Average Lead Content Evaluation Procedure to a 0.24 Percent Lead<br />

Requirement.<br />

1.3 SUBMITTALS<br />

A. Section 01770 – Contract Closeout: Procedures for Closeout Submittals.<br />

B. Closeout Submittals:<br />

1. Operation and Maintenance Data: Include manufacturer's descriptive literature, operating instructions,<br />

maintenance and repair data, and parts listing for plumbing fixtures.<br />

1.4 QUALITY ASSURANCE<br />

A. Regulatory Requirements:<br />

1. Products Requiring Electrical Connection: Listed and classified by Underwriter's Laboratories,<br />

Incorporated, and acceptable to the authority having jurisdiction as suitable for the purpose specified and<br />

indicated.<br />

2. Disabled Access: Conform to applicable local, State or Federal disabled access requirements for the<br />

installation, mounting heights, and operation of plumbing fixture.<br />

3. Lead-Free Compliance: Fixtures and fixture trim shall comply with the requirements of NSF 61 Annex G<br />

for lavatories, sinks and water coolers.<br />

1.5 DELIVERY, STORAGE, AND HANDLING<br />

A. Section 01600 - Material and Equipment: Transport, handle, store, and protect products.<br />

B. Accept fixtures on site in factory packaging. Inspect for damage.<br />

C. Protect installed fixtures from damage by securing areas and by factory packaging in place to protect fixtures and<br />

prevent use.<br />

15410 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


PART 2 - PRODUCTS<br />

2.1 DIRECT PURCHASE PROCUREMENT<br />

A. The following items shall be direct purchased by the General Contractor from a pre-negotiated supplier.<br />

1. Toilet plumbing fixtures and associated trim, and accessories, as scheduled on the Drawings on the Toilet<br />

Plumbing Fixture Schedule. The pre-negotiated supplier shall be as follows:<br />

a. Haines, Jones & Cadbury, Inc., Contact: Customer Service, (800) 459-7099, fax (479) 756-8998,<br />

Email: info@hjcinc.com.<br />

2. Sinks and eyewash plumbing fixtures as shown on the Drawings on the Plumbing Fixture/Water Piping<br />

Specialties Schedule. The pre-negotiated supplier shall be as follows:<br />

a. Haines, Jones & Cadbury, Inc., Contact: Customer Service, (800) 459-7099, fax (479) 756-8998,<br />

Email: info@hjcinc.com.<br />

B. Reference Section 01600 for additional information regarding Direct Purchase Products.<br />

2.2 MANUFACTURERS<br />

A. Subject to compliance with Project requirements, provide plumbing fixtures of manufacturers indicated on Drawings.<br />

2.3 FIXTURES<br />

A. Fixture types and model numbers shall be as scheduled on the drawings.<br />

B. Substitutions: Not permitted.<br />

2.4 FIXTURE TRIM<br />

A. Provide each fixture complete with required trim. Exposed piping and trim shall be polished chrome-plated brass.<br />

Provide each fixture with chrome angle stop valves.<br />

B. Provide flow-limiting device which limits flow to not more than 2.2 gpm for each sink except service and 3-<br />

compartment sinks. Provide devices integral with fixture trim, wherever possible, and products of same manufacturer<br />

as fixture trim.<br />

C. Lavatory faucets for public use or within public restrooms shall be of the electronic self-closing type and shall<br />

have a maximum flow rate of 0.5 GPM in accordance with ASME/ANSI A112.18.1. Provide devices integral with<br />

fixture trim, wherever possible, and products of same manufacturer as fixture trim.<br />

D. Flush Valves: Subject to compliance and compatible with plumbing fixtures as scheduled on the drawings. Provide<br />

flush valves that do not exceed code requirements for maximum gallons per flush.<br />

E. Provide trim as required to permit scheduled lavatory to be installed for handicap use.<br />

F. Provide bolt caps with retainer clips on water closets.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas where products will be installed. Verify that conditions conform to product<br />

manufacturer's requirements and installation conditions. Do not proceed until unsatisfactory conditions have been<br />

corrected.<br />

1. Verify that walls and floor finishes are prepared and ready for installation of fixtures.<br />

2. Verify that plumbing piping for fixture is in the correct location and of the correct type.<br />

15410 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3.2 PREPARATION<br />

A. Rough-in fixture piping connections in accordance with minimum sizes indicated on Drawings for particular fixtures.<br />

3.3 INSTALLATION<br />

A. Install fixtures and trim in accordance with manufacturer's published instructions. Make final connections.<br />

B. Support each fixture in rigid manner which permits no perceptible movement of fixture by manually applied<br />

forces. Seal space between fixtures and floor or walls with silicone sealant.<br />

C. Install each fixture with trap which is easily removable for servicing and cleaning.<br />

D. Install components level and plumb. Install toilet seats on water closets.<br />

E. Install and secure fixtures in place with carriers and bolts.<br />

F. Solidly attach water closets to floor or wall as required.<br />

G. Seal fixtures to wall and floor surfaces with sealant as specified in Section 07900, color to match fixture.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect plumbing fixture and trim installation, attachment to building, operation, and connections. Ensure that fixtures<br />

are installed and operate in conformance with disabled access requirements.<br />

1. Prior to final acceptance, inspect faucets, flush valves, stop valves, and similar devices, to determine that<br />

they operate properly and discharge proper quantities of water. Correct any deficiencies as directed by<br />

Owner's representative.<br />

3.5 ADJUSTING AND CLEANING<br />

A. Operate and adjust stops or valves for intended water flow rate to fixtures without splashing, noise or overflow.<br />

1. Replace malfunctioning units.<br />

2. Replace washers and seals of leaking and dripping faucets and stops.<br />

B. Clean fixtures, trim, and accessories of foreign materials, including labels, before final acceptance.<br />

END OF SECTION<br />

15410 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


BLANK PAGE<br />

15410 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 123010<br />

SECTION 15480 - DOMESTIC WATER HEATERS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Domestic water heaters.<br />

2. Accessories.<br />

3. Recirculating pumps associated with domestic water heating system.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. National Fire Protection Association (NFPA):<br />

1. NFPA 54 - National Fuel Gas Code.<br />

C. American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE)<br />

1. ASHRAE 90.1 - Energy Efficient Design Of New Buildings Except New Low-Rise Residential Buildings.<br />

PART 2 - PRODUCTS<br />

2.1 DIRECT PURCHASE PROCUREMENT<br />

A. Water heating systems including water heaters, storage tanks, expansion tanks, and recirculation pumps as<br />

scheduled on the Drawings on the Water Heating System Schedule shall be direct purchased by the General<br />

Contractor from a pre-negotiated supplier.<br />

B. Pre-negotiated Supplier: Haines, Jones & Cadbury, Inc., Contact: Customer Service, (800) 459-7099, fax (479)<br />

756-8998, Email: info@hjcinc.com.<br />

C. Reference Section 01600 for additional information regarding Direct Purchase Products.<br />

2.2 ELECTRIC WATER HEATERS<br />

A. Glass-lined electric storage-type water heater of size and capacity indicated on Drawings.<br />

1. Heating elements shall be suitable for electrical current having characteristics indicated on Drawings, and<br />

complete with necessary operating and safety controls.<br />

2. Each tank shall be equipped with magnesium anodes for corrosion protection.<br />

3. Heaters shall be UL listed and labeled, meeting efficiency requirements of ASHRAE 90.1.<br />

4. Water heaters shall be California Energy Commission certified.<br />

2.3 GAS WATER HEATERS<br />

A. Glass-lined gas storage-type water heater of size and capacity indicated on Drawings.<br />

1. Gas fired water heaters shall be equipped to burn Natural gas and design certified by the American Gas<br />

Association under Volume III tests for commercial heaters for delivery of 180 degrees F water.<br />

2. Water heater shall be approved by National Sanitation Foundation and meeting efficiency requirements of<br />

ASHRAE 90.1 and other applicable energy codes.<br />

3. Heater shall be equipped with boiler type handhole cleanout. Heater working pressure shall be 150 psi.<br />

15480 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


4. Water heater shall be equipped with the following:<br />

a. Automatic gas shutoff device and safety shutoff in the event pilot flame is extinguished.<br />

b. Gas pressure regulator set for type of gas supplied.<br />

c. An approved draft diverter.<br />

d. Extruded magnesium or aluminum anode rod rigidly supported for cathodic protection.<br />

5. Heater tank shall be insulated and encased in corrosion-resistant steel jacket; baked-on enamel finish; floor<br />

shield and legs.<br />

6. Controls: Integral automatic water thermostat with temperature range adjustable from 120 degrees to 180<br />

degrees F. (49 degrees to 82 degrees C).<br />

7. Relief Valves: Temperature and pressure relief valves shall be, ASME and/or AGA stamped, of the sizes<br />

and types required to meet ASME and/or AGA Code temperature steam rating for discharge capacity.<br />

2.4 STORAGE TANKS<br />

A. Hot water storage tanks shall be as scheduled on the drawings.<br />

2.5 ACCESSORIES<br />

A. Relief Valves: Provide ASME and AGA stamped temperature and pressure relief valves, of the sizes and types<br />

required to meet ASME and AGA Code temperature steam rating for discharge capacity, unless valves are<br />

furnished as integral part of water heaters or water heating system storage tanks.<br />

B. Expansion Tanks: Provide expansion tank as scheduled on the drawings. Tank shall be closed type, welded steel,<br />

design working pressure of 125 psi, with internal diaphragm to separate water from air charge.<br />

2.6 PUMPS<br />

A. Recirculation pumps for the water heating system shall be as scheduled on the drawings.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install in accordance to requirements of Authority Having Jurisdiction, and written recommendations of equipment<br />

manufacturer’s installation instructions.<br />

B. Set air charge, mount, and install expansion tanks in accordance with manufacturer's installation instructions.<br />

C. Install gas piping adjacent water heater to allow service and maintenance.<br />

D. Connect Gas piping to gas burner with drip leg, tee, shutoff valve, and union.<br />

E. Install and connect gas water heater in accordance with NFPA 54.<br />

END OF SECTION<br />

15480 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 033111<br />

SECTION 15600 (23 6000) – REFRIGERATION SYSTEMS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished refrigeration equipment for installation by Contractor.<br />

2. Refrigeration equipment related items provided by Contractor.<br />

B. Related Requirements:<br />

1. Section 07721 – Manufactured Curbs: Curbs for roof-mounted refrigeration equipment.<br />

2. Section 07900 – Joint Sealers: Products for use in sealing pipe penetrations.<br />

3. Section 13810 – Energy Management Systems.<br />

4. Section 15050 – Basic Mechanical Materials and Methods: Hangers and supports for refrigeration system<br />

piping.<br />

5. Section 16050 – Basic Electrical Materials and Methods.<br />

6. Section 16100 – Wiring Methods.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. ASTM International (ASTM):<br />

1. ASTM A 536 - Ductile Iron Castings.<br />

2. ASTM B 75 - Seamless Copper Tube.<br />

3. ASTM B 280 - Seamless Copper Tube for Air Conditioning and Refrigeration Field Service.<br />

4. ASTM B 584 - Copper Alloy Sand Castings for General Applications.<br />

5. ASTM D 2000 - Standard Classification System for Rubber Products in Automotive Applications.<br />

6. ASTM D 2665 - Polyvinyl Chloride (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings.<br />

7. ASTM D 2564 - Solvent Cements for Polyvinyl Chloride (PVC) Plastic Pipe and Fittings.<br />

8. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

C. American National Standards (ANSI):<br />

1. ANSI B 16.22 - Wrought Copper Alloy Solder Joint Pressure Fittings.<br />

D. British Standards Institution (BSI):<br />

1. BS 5391 – Acrylonitrile Butadiene Styrene (ABS) Pressure Pipe.<br />

2. BS 5392 – Acrylonitrile Butadiene Styrene (ABS) Fittings for Use With ABS Pressure Pipe.<br />

1.3 CLOSEOUT SUBMITTALS<br />

A. Comply with the requirements of Section 01770.<br />

B. Refrigeration Installation Handover Document / Sign Off Sheet: Submit completed Refrigeration Installation<br />

Handover Document / Sign Off Sheet to Wal-Mart Stores, Inc., 2001 SE 10 th Street, Bentonville, AR 72712-0550,<br />

Attention: Mechanical Services Construction Manager.<br />

C. Record Documents: Provide laminated half-size refrigeration and energy management drawings, installed on<br />

interior side of compressor room door or on interior side of door panel.<br />

D. Letter of Conformance: Submit Contractor’s Record Letter of Conformance on the form at the end of this Section.<br />

E. Operation and Maintenance Data: Collect operation and maintenance manuals furnished by the case and rack<br />

OEMs and store them together at the refrigeration rack.<br />

15600 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


1.4 DELIVERY, STORAGE AND HANDLING<br />

A. Transport, handle and store products in accordance with the requirements of Section 01600.<br />

B. Receive Owner furnished products in accordance with the requirements of Section 01640.<br />

1.5 WARRANTY<br />

A. Provide warranty and service on equipment and materials installed regardless of whether equipment or materials<br />

were furnished by Contractor.<br />

B. Provide supplemental warranty service to include failures during installation and for 90 days beyond store Grand<br />

Opening date. The supplemental warranty shall include labor, parts, primary refrigerant and secondary coolant for<br />

repairs to installed refrigeration equipment and piping.<br />

1. Response time to emergency calls shall be within two hours.<br />

C. Owner’s equipment manufacturer (OEM) supplier will furnish replacement parts for failures of OEM parts during<br />

installation period and for one year beyond store Grand Opening date. Contractor shall obtain replacement parts<br />

from equipment manufacturer. Owner will not pay additional costs associated with repair or replacement of<br />

materials and parts during the warranty period.<br />

D. In the event the Contractor fails to respond to emergency calls or fails to perform required maintenance or repairs<br />

during warranty period, the Owner will have the right to have the repair or maintenance performed by another<br />

contractor. In this case, the Contractor agrees to pay the Owner the invoiced amount of the services performed plus<br />

15 percent.<br />

E. If the service contractor discontinues or drops their service level because the Contractor has failed to make<br />

payment to subcontractor on completed warranty work, Wal-Mart will remove that Contractor from New Stores<br />

Bid List until such time when all disputes or claims are settled.<br />

F. Perform inspection of installation 90 days after store Grand Opening date. Make necessary corrections and<br />

adjustments. Complete refrigeration punch list. Send completed punch list to Wal-Mart Stores, Inc., 2001 S.E. 10 th<br />

St., Bentonville, AR 72716-0550, Attention: Mechanical Services Department, for verification of completion.<br />

Notify Wal-Mart Mechanical Services Construction Manager (MSCM) prior to inspection.<br />

1.6 At 90 day inspection, provide lubrication, leak tests of all joints, flare nuts, and tightening of strapping. Perform<br />

leak test on small leak setting of refrigerant leak detector. Change replaceable suction, liquid, and oil filters. Place<br />

suction, liquid, and oil filters in a sealable plastic bag to prevent setting off any leak detection system. Leave oil<br />

filters and dryers in motor room for inspection by Wal-Mart Mechanical Services Construction Manager.<br />

A. At the end of warranty period, certify in a letter to the Owner that equipment and materials installed or connected<br />

are functioning properly. Include certification that systems are free of leaks and are maintaining satisfactory<br />

temperatures at normal control adjustments.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner will furnish refrigeration equipment as scheduled and shown on Drawings under provisions of Section<br />

01640 for installation by the Contractor.<br />

1. Condensers.<br />

2. Condensing Units.<br />

3. Evaporators.<br />

4. Compressor Rack Systems.<br />

5. Refrigerated cases.<br />

6. Ice flakers.<br />

7. Produce misting system.<br />

15600 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2.2 OWNER PROVIDED PRODUCTS<br />

A. Owner will furnish and install refrigeration equipment as scheduled and shown on Drawings.<br />

1. Walk-in Freezers and Coolers.<br />

2.3 MATERIALS (CONTRACTOR FURNISHED AND INSTALLED)<br />

A. Refrigeration Piping:<br />

1. Provide piping for refrigeration systems as specified in Schedule I below and as indicated on Drawings.<br />

a. Copper Tubing and Fittings: ASTM B 280, type ACR, hard drawn tubing. Tubing shall be factory<br />

cleaned, ready for installation, and have ends capped to protect cleanliness of pipe interior prior to<br />

shipping. Provide wrought copper pressure fittings, ANSI B16.22.<br />

b. ABS Piping and Fittings: BS 5391 and BS 5392, manufactured for class E pressure bearing service.<br />

B. PVC Piping and Fittings: ASTM D2665, schedule 40 drain, waste, and vent. Refrigeration Piping Insulation:<br />

1. Provide insulation for piping as specified in Schedule I below and described in this Section.<br />

2. Products: Subject to compliance with requirements, provide one of the following:<br />

a. AP Armaflex by Armacell.<br />

b. Aeroflex by Aeroflex International Co., Ltd.<br />

c. Insul-Tube by K-Flex USA.<br />

d. Rubatex by Rubatex International, LLC.<br />

3. Elastomeric Flexible Closed Cell Insulation: Maximum k factor at 75 degrees F of 0.28 Btu-in/hr.f.sq ft,<br />

maximum flame spread and smoke development of 25 and 50, respectively per ASTM E84.<br />

a. Insulation color: black.<br />

Schedule I<br />

Piping Service Piping Size Piping Material Insulation<br />

Thickness<br />

R404A/R407A - Suction<br />

1-3/8 inches Type L Hard Drawn Copper, Sealed<br />

1 inch<br />

R404A/R407A - Suction<br />

R404A/R407A - Liquid<br />

and smaller<br />

1-5/8 inches<br />

and larger<br />

All<br />

ACR Tubing<br />

Type L Hard Drawn Copper, Sealed<br />

ACR Tubing<br />

Type L Hard Drawn Copper, Sealed<br />

ACR Tubing<br />

1-1/2 inch<br />

1/2 inch<br />

R744 – Carbon Dioxide<br />

R744 – Carbon Dioxide<br />

1-3/8 inches<br />

and smaller<br />

1-5/8 inches<br />

and larger<br />

Type L Hard Drawn Copper, Sealed<br />

ACR Tubing<br />

Type K Hard Drawn Copper,<br />

Sealed ACR Tubing<br />

1-1/2 inch<br />

1-1/2 inch<br />

Propylene Glycol / Water<br />

Propylene Glycol / Water<br />

Evaporator Condensate - Inside<br />

Refrigerated Walk-in Boxes<br />

Operating at 32°F or Below<br />

Evaporator Condensate - Outside<br />

Refrigerated Walk-in<br />

Boxes and Inside Boxes<br />

Operating Above 32°F<br />

1-3/8 inches<br />

and smaller<br />

1-5/8 inches<br />

and larger<br />

Type L Hard Drawn Copper or<br />

Pressure Rated ABS<br />

Type L Hard Drawn Copper or<br />

Pressure Rated ABS<br />

1 inch<br />

1-1/2 inch<br />

All Type L Hard Drawn Copper 1 inch<br />

All<br />

Schedule 40 PVC, Solid Core,<br />

DWV<br />

N/A<br />

C. Valves:<br />

1. Subject to compliance with requirements, provide valves as manufactured by one of the following:<br />

a. Henry Technologies.<br />

b. Mueller Industries.<br />

15600 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


2. Valves shall be full port ball type valves, with a minimum working pressure of 700 PSIG, a working<br />

temperature range of -40 degrees F to 300 degrees F, and specifically designed for use with the refrigerant<br />

or secondary cooling medium that is contained within the system. The valve body shall be forged brass and<br />

hermetically sealed. Bolted body valves are not permitted.<br />

D. Pipe Freeze Protection:<br />

1. Heating Cable: Subject to compliance with requirements, provide one of the following:<br />

a. Raychem XL-Trace by Tyco Thermal Controls, LLC.<br />

b. CO Series by Delta-Therm Corporation.<br />

2. Heating cable shall be self regulating, 120 volt, 5 watts per linear foot.<br />

PART 3 - EXECUTION<br />

3.1 FIELD FABRICATION<br />

A. Perform cutting of tubing with wheel-type cutter where possible, and ream tubing to original bore. Where saw<br />

cutting is required, drag tubing clean after reaming. Drag clean tubing left open after cutting and sanding prior to<br />

installation.<br />

B. Make joints with use of brazing alloy containing minimum of 15 percent silver. Clean joints thoroughly before<br />

brazing and have dry nitrogen at 1/2 psi pressure flowing through tubing during brazing.<br />

C. Install replacement parts (i.e. expansion valves, heat exchangers, sight glasses) using Harris Stay Brite #8,<br />

excluding parts in hot gas lines. Use heat dams in all instances.<br />

3.2 INSTALLATION<br />

A. Install refrigeration equipment in accordance with manufacturer’s instructions.<br />

B. Attach rooftop refrigeration equipment to structural support frame as shown on Drawings.<br />

C. Suspend refrigeration piping as shown on Drawings, with supports spaced in accordance with the requirements of<br />

Section 15050. Install pipe hangers no farther than two feet on each side of 90 degree turns.<br />

D. Under no condition shall pipes touch each other when necessary to cross pipes. Offset or insulate to insure no<br />

contact. Refrigerant piping shall not come in contact with electrical conduit or other dissimilar grounded metals.<br />

E. Seal penetrations through exterior building walls and walk-in coolers and freezers with urethane foam and silicone<br />

caulk as specified in Section 07900.<br />

F. Install electronic suction pressure regulator valves, thermostatic expansion valves, liquid solenoids, thermostats,<br />

and heat exchangers. Provide sufficient pipe at evaporator outlet to install thermostatic expansion valve sensing<br />

bulb, ensuring 100% contact with pipe.<br />

G. Trap evaporators at coil outlet and vertical suction line risers. P-Traps shall be one piece, short radius type at<br />

bottom of risers. Size P traps to match horizontal pipe or coil outlet pipe. Do not reduce to riser size. Take vertical<br />

risers as high as possible (just below structure). On risers above 16 feet, provide double oil traps spaced as shown<br />

on Drawings.<br />

H. Pitch horizontal suction lines minimum of one inch per twenty feet of run in direction of refrigerant flow. Ensure<br />

no oil traps are formed in piping.<br />

I. Liquid supply line tees shall be bullheaded inside cases. Suction lines shall not be bullheaded.<br />

J. Install 1/4 inch king valve on top of inverted trap on inlet side of field installed condensers. Install valve at highest<br />

point in the discharge line. Provide king valves with brass or steel caps.<br />

K. Suction lines and return lines that are tee'd into a common return line shall be tee'd into the top.<br />

15600 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


L. Provide Schrader valve access on each suction line leaving evaporators.<br />

M. The pipe routing, case, condenser, and compressor rack locations shall not deviate from Drawings without<br />

approval from Wal-Mart Mechanical Services Construction Manager and refrigeration EOR.<br />

N. Provide branch supply and return line ball valves for isolation purposes as indicated on refrigeration piping plans.<br />

Install valves in a fully accessible location. Insulate isolation valves in accordance with refrigeration line<br />

insulation requirements.<br />

O. Slip insulation over pipe before making joints. Split type insulation is acceptable on fittings only. Install insulation<br />

in conformance with manufacturer's recommendations, including glued joints. If receiver is mounted outside,<br />

provide UV protection for pipe insulation on the liquid line from the receiver to the refrigeration rack by<br />

application of a covering or coating specifically for the purpose of UV protection and as recommended by the<br />

manufacturer.<br />

P. Make final electrical connections, including slave wiring, to refrigerated cases, evaporators, field installed<br />

refrigeration control valves, defrost heaters, cooler and freezer box door lights and anti-sweat heaters, and<br />

compressor houses. Make connections per wiring diagrams and instructions from equipment supplier. Comply<br />

with the requirements of Section 16100 and applicable electrical codes.<br />

Q. Provide condensate lines from evaporators to outside of walk-in freezers and coolers, and adapt to individual PVC<br />

trap. Terminate in common condensate header. Clean markings off of PVC with solvent. Install self regulating<br />

heating cable on condensate drains inside freezer boxes that are to operate at or below 32 degrees F.<br />

R. Install unions on condensate drains in walk-ins close to drain pan. Allow clearance for pans to hinge open.<br />

Provide heating cable on condensate lines inside walk-ins with temperature 32 degrees or less and insulate. Install<br />

common condensate line outside the walk-in. Paint non-insulated copper drain lines to match walk-in box.<br />

S. Maintain slope of one inch per ten feet of horizontal run for condensate lines. Provide traps in condensate lines<br />

outside of walk-ins just before entering common condensate line.<br />

3.3 IDENTIFICATION<br />

A. Provide engraved plastic identification tags, 2 inch by 3 inch in size, attached with screws or pop rivets.<br />

B. Identify refrigeration equipment with matching numbers as shown on the Refrigeration Energy Management<br />

Drawings:<br />

1. Identify circuits with corresponding number and circuit.<br />

2. Identify refrigeration equipment, including compressor houses, racks, walk-ins, sensor or thermostat<br />

locations, and hot water tanks.<br />

3. Identify cases with an approximate location of field installed control valves.<br />

C. Provide job notebook with model and serial numbers, refrigerant charge per rack, warranty expiration date,<br />

emergency service telephone numbers in resealable plastic envelope. Log Work performed after start-up, warranty<br />

or non-warranty, in job notebook and referred to by refrigeration system designation (LTA, MTB, etc). Locate job<br />

notebook in mechanical refrigeration house.<br />

D. Write refrigerant charge per rack in black indelible marker on each system compressor breaker panel.<br />

3.4 CASE SETTING<br />

A. Set cases level and in line with transit. Shim at each vertical support or at maximum 4 foot intervals with<br />

galvanized plates, as floor conditions require.<br />

B. Apply butyl caulking compound at case joints. Reseal joints if seal is broken.<br />

C. Do not cut bottom case rails.<br />

15600 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


D. Hang case shelving and place pans in refrigerated cases, including door shelving in dairy cooler.<br />

3.5 TESTING, EVACUATION, CHARGING, AND FILLING<br />

A. Notify Wal-Mart Mechanical Services Construction Manager one week in advance of pressure/vacuum and<br />

evacuation tests.<br />

B. When refrigeration connections have been completed, test refrigerant piping system for leaks with dry nitrogen at<br />

a minimum of 150 PSIG, but not to exceed 200 PSIG, with compressor suction and discharge valves closed, and<br />

all other valves in system open, with exception of transducers which must be kept closed during pressure testing<br />

and evacuation procedures. Hold pressure for 24 hours. If leaks are found, isolate leaks, discharge gas and repair<br />

leaks, and then repeat test.<br />

C. Evacuate system with vacuum pump specifically manufactured for vacuum duty, having capability of pulling<br />

vacuum of 50 microns or more. Do not evacuate system by use of the refrigeration compressor. Evacuate each<br />

system to an absolute pressure not exceeding 500 microns. Do not pull vacuums on transducers. Break vacuum to<br />

2 PSIG with dry nitrogen. Repeat evacuation process, again breaking vacuum with dry nitrogen. System shall<br />

hold 500 microns for twenty-four hours.<br />

D. Provide primary refrigerant and secondary coolant as indicated on refrigeration Drawings and as required for<br />

proper operation of systems. Check the refrigeration Drawings and the equipment manufacturer’s labeling prior to<br />

charging of refrigeration system. Notify refrigeration EOR of conflicts prior to charging system.<br />

E. Charge refrigerant directly from original drums. Charge system by means of charging fitting in liquid line.<br />

F. Fill compressors with oil to manufacturer’s recommended levels and fill oil reservoirs to 1/2 full. Top off the<br />

reservoirs with oil after the system has run for a minimum of 24 hours.<br />

3.6 SYSTEM START-UP<br />

A. Conduct system start-up as follows:<br />

1. Adjust E.P.R. and E.E.P.R. valves, pilot line regulators, thermostatic expansion valves, liquid hold-back<br />

valves, balance valves, compressor high and low pressure switches, receiver pressurization, subcooler EPR,<br />

and liquid pressure regulator.<br />

2. Complete refrigerant and oil charge.<br />

3. Adjust oil float levels and replace liquid, suction, and oil line filter/dryers.<br />

4. Verify pressure and temperature gauges are accurate.<br />

B. After compressor is started, continue charging until system has sufficient refrigerant for proper operation. Do not<br />

overcharge. Do not leave compressor operating unattended and unmatched until system is properly charged with<br />

refrigerant and oil. Charge receivers to 40 percent with unit in heat reclaim in 100 percent condenser and all<br />

condenser fan controls set properly. Maintain these levels throughout warranty period. If at end of warranty period,<br />

receiver level has dropped, completely re-check system for leaks. Repair leaks and bring system back to original<br />

charge level.<br />

C. Complete system balance by the end of the fifth day of start up.<br />

D. Complete Refrigeration Installation Handover Document / Sign Off Sheet and submit as specified in Part 1.<br />

E. Do not add oil while system is short of refrigerant unless oil level is inadequate for system operation.<br />

F. Final payment will not be made until Refrigeration Installation Handover Document / Sign Off Sheet is received<br />

and job notebook is completed and placed in the mechanical refrigeration house.<br />

15600 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3.7 OPERATION AND CHECK-OUT<br />

A. Set expansion valve superheat on systems per manufacturer’s recommendations. Balance multi-plex systems to<br />

within 2 degrees of target and with not more than 2 degrees variation in discharge air temperature between cases.<br />

Verify superheat settings after fixtures have been loaded with product.<br />

B. Change replaceable liquid line filter dryers, oil system dryers, and suction line filter dryers after 24 hours of initial<br />

run time.<br />

3.8 FIELD QUALITY CONTROL<br />

A. If directed by the Wal-Mart Mechanical Services Construction Manager, cut out five randomly selected joints to<br />

verify use of dry nitrogen during brazing operations. Inspect joints for oxidation in the presence of the MSCM. For<br />

each joint which shows evidence of oxidation, cut out an additional joint. If four fittings are found oxidized,<br />

rework all joints including those removed for inspection.<br />

B. Site Observations and Functional Performance Testing (FPT): Observation and FPT visits will be conducted by<br />

the Wal-Mart Engineer of Record at no cost to the Contractor in accordance with Section 01454. The Engineer of<br />

Record will validate the refrigeration systems at start-up or the week after start-up. FPT shall occur one to six<br />

weeks after Grand Opening.<br />

1. Contractor’s Responsibilities:<br />

a. Correct installation deficiencies prior to Grand Opening.<br />

b. Provide qualified labor to assist EOR in refrigeration functional performance tests as specified in<br />

Section 01454.<br />

END OF SECTION<br />

15600 - 7<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


REFRIGERATION INSTALLATION<br />

HANDOVER DOCUMENT / SIGN OFF SHEET<br />

All sections of this document must be completed before the installation will be accepted.<br />

Store No. ___________ Location:<br />

City, State<br />

Store Type:<br />

SC, SAMS, NM<br />

Grand Opening Date:<br />

Project Type:<br />

Installing Contractor:<br />

Equipment Supplier:<br />

Refrigerant:<br />

System Type:<br />

Heat Reclaim:<br />

Energy Mgt System (EMS):<br />

Verisae Data Submitted:<br />

Date of project Grand Opening for warranty purposes<br />

New Store/Club, Relocation, Remodel, Capital Expenditure (Capex)<br />

Contractor’s name and branch location, if applicable<br />

Hill PHOENIX, Kysor Warren, Zero Zone, Hussmann<br />

R 407A, R410A, etc.<br />

Direct Expansion (DX), CO 2 , Glycol Secondary Loop<br />

Domestic Water, N/A<br />

Novar, Danfoss, CPC<br />

Date Submitted or N/A<br />

Comments:<br />

APPROVAL<br />

The work carried out during this project is complete and the standard achieved is acceptable.<br />

Name of Wal-Mart Mechanical Services Signature Date<br />

Construction Manager<br />

Notice to WM MSCM:<br />

By signing this form, you are confirming the following:<br />

The work detailed above is complete and all systems are operating as intended.<br />

All handover documentation has been completed and you are satisfied with its contents.<br />

All issues are either resolved or you are satisfied with the plan for resolution.<br />

15600 - 8<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


REFRIGERATION INSTALLATION<br />

HANDOVER DOCUMENT / SIGN OFF SHEET<br />

Machine Rooms<br />

All sections of this document must be completed before the installation will be accepted.<br />

Store No. ___________ Location:<br />

City, State<br />

Store Type:<br />

SC, SAMS, NM<br />

Name of technician carrying out checks and completing this form<br />

Date<br />

Type of machine room<br />

Machine room supplier<br />

Rack, hybrid house, weatherpac<br />

Hill PHOENIX, Kysor Warren, Zero Zone<br />

Circle yes or no<br />

Are weatherpacs bolted to steel?................................................................................................................. yes / no<br />

Are all penetrations properly sealed?.......................................................................................................... yes / no<br />

Do all power sockets and lights operate correctly?..................................................................................... yes / no<br />

Do all exhaust fans operate correctly? ........................................................................................................ yes / no<br />

Are all weatherpac doors hung properly and operating correctly? ............................................................. yes / no<br />

Is there any damage to the room which needs repair? ................................................................................ yes / no<br />

All shields and hoods installed correctly?................................................................................................... yes / no<br />

Are Operation and Maintenance (O and M) manuals left on site?.............................................................. yes / no<br />

Are drawings mounted on the walls of machine rooms? ............................................................................ yes / no<br />

Have liquid line filter dryers, oil system dryers, and suction line filter driers<br />

been changed after 24 hours of run time?............................................................................................ yes / no<br />

Is leak detection installed?.......................................................................................................................... yes / no<br />

Has leak detection been tested and certified functional? ............................................................................ yes / no<br />

Are electrical drawings mounted inside electrical panels? ......................................................................... yes / no<br />

Are all electrical distribution panels labeled correctly?.............................................................................. yes / no<br />

Are all trunking lids and junction box covers in place?.............................................................................. yes / no<br />

Have all relevant labels been fixed to major items of equipment? ............................................................. yes / no<br />

Is the machine room clean and free from rubbish?..................................................................................... yes / no<br />

Capital Expenditure (CAPEX) and Remodel Projects<br />

Have all existing, redundant materials (conduit, pipe work, etc.)<br />

been stripped out or made safe?........................................................................................................... yes / no<br />

Comments:<br />

15600 - 9<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


REFRIGERATION INSTALLATION<br />

HANDOVER DOCUMENT / SIGN OFF SHEET<br />

Refrigeration Vacuum Test<br />

All sections of this document must be completed before the installation will be accepted.<br />

Store No. ___________ Location:<br />

City, State<br />

Store Type:<br />

SC, SAMS, NM<br />

Wal-Mart Construction Manager<br />

Installing Contractor<br />

Contractor’s Address<br />

Street<br />

Contractor’s Phone<br />

City, State, ZIP<br />

Contractor’s Email Address<br />

Name of Person Attesting to Vacuum<br />

Gauge Used for Testing<br />

Phone<br />

Manufacturer Type Model # Range in Microns<br />

First<br />

Second<br />

Final<br />

Date of Final<br />

Pressure at<br />

Check-In<br />

A B C D E F<br />

Signature<br />

Comments:<br />

Date<br />

15600 - 10<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


REFRIGERATION INSTALLATION<br />

HANDOVER DOCUMENT / SIGN OFF SHEET<br />

Rack A<br />

All sections of this document must be completed before the installation will be accepted.<br />

Store No. ___________ Location:<br />

City, State<br />

Store Type:<br />

SC, SAMS, NM<br />

Name of technician carrying out checks and completing this form<br />

Date<br />

Rack Type<br />

Rack Manufacturer<br />

Rack Model No.<br />

Refrigerant Type<br />

Parallel Recip, Rack in a Box (RIB), Modular<br />

Rack Serial No.<br />

Record System Refrigerant Charge<br />

Does the refrigerant type match what is called for on the legend? (Circle yes or no)<br />

yes / no<br />

Verify the main power voltage. L1 > GD L1 > L2<br />

L2 > GD<br />

L1 > L3<br />

L2 > GD<br />

L1 > L3<br />

Verify the control voltage.<br />

Confirm operation of power failure (PF) module and record settings. Delay Voltage<br />

Are all electrical connections tight? (Circle yes or no)<br />

yes / no<br />

Compressor Manufacturer<br />

Record model number of each compressor. Verify that model numbers match legend.<br />

Compressor 1 Compressor 2<br />

Compressor 3 Compressor 4<br />

Compressor 5 Compressor 6<br />

Record running amps for each compressor.<br />

COMP 1 COMP 2<br />

Loaded L1 _______ L2 _______ L3 _______ Loaded L1 _______ L2 _______ L3 _______<br />

Unloaded L1 _______ L2 _______ L3 _______ Unloaded L1 _______ L2 _______ L3 _______<br />

COMP 3 COMP 4<br />

Loaded L1 _______ L2 _______ L3 _______ Loaded L1 _______ L2 _______ L3 _______<br />

Unloaded L1 _______ L2 _______ L3 _______ Unloaded L1 _______ L2 _______ L3 _______<br />

COMP 5 COMP 6<br />

Loaded L1 _______ L2 _______ L3 _______ Loaded L1 _______ L2 _______ L3 _______<br />

Unloaded L1 _______ L2 _______ L3 _______ Unloaded L1 _______ L2 _______ L3 _______<br />

15600 - 11<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


Allow the oil pressure switch to trip on each compressor to ensure proper operation. After oil pressure trips, wait two<br />

minutes and check crankcase heater operation. Record amp draw of each crank case heater.<br />

C1 _______ C2 _______ C3 _______ C4 _______ C5 _______ C6 _______<br />

Adjust and record compressor’s start delay timer setting.<br />

C1 _______ C2 _______ C3 _______ C4 _______ C5 _______ C6 _______<br />

Adjust and record compressor’s HP cut out switch setting.<br />

C1 _______ C2 _______ C3 _______ C4 _______ C5 _______ C6 _______<br />

Is EMS suction transducer calibrated? (Circle yes or no)<br />

yes / no<br />

Record the EMS rack suction pressure settings. Cut In Cut Out<br />

Check and record the rack suction pressure. EMS Gauge<br />

Check and record the suction temperature. EMS Meter<br />

What is the rack superheat?<br />

Have all Evaporator Pressure Regulators (EPRs) been set correctly? (Circle yes or no)<br />

yes / no<br />

Note: Individual EPR settings to be recorded on case start-up documents.<br />

Check and record the ambient temperature. EMS Meter<br />

Is EMS discharge transducer calibrated? (Circle yes or no)<br />

yes / no<br />

Check and record the discharge pressure. EMS Gauge<br />

Check and record the discharge temperature. EMS Meter<br />

Check and record the drop leg temperature. EMS Meter<br />

Does this rack have hot water / heat reclaim?<br />

yes / no<br />

Record heat reclaim control settings. Reclaim t’stat Electric heater t’stat<br />

Note: Reclaim thermostat should be set to 140 F. Electric back up thermostats should be set to 130 F.<br />

Check and record correct heater element voltage.<br />

Record the rack high pressure EMS lockout setting.<br />

Does this rack have ambient subcooling (surge)? (Check yes or no)<br />

yes / no<br />

Check and record the EMS surge setpoints. Cut In Cut Out<br />

Check for correct operation. Is system operating OK? (Check yes or no)<br />

Does this rack have subcooling? (Check yes or no)<br />

yes / no<br />

yes / no<br />

Record liquid subcooling temp EMS set point.<br />

Record actual liquid temperature.<br />

Record EPR / EEPR setting (as applicable).<br />

15600 - 12<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


Record outlet pressure regulator (OPR) setting (if applicable).<br />

Record bypass valve setting (if applicable).<br />

Confirm correct operation. Is system operating OK? (Check yes or no)<br />

yes / no<br />

Condenser Manufacturer<br />

Condenser Model No.<br />

Is condenser clean and free from debris? (Circle yes or no)<br />

Are condenser fan motors rotating correctly? (Circle yes or no)<br />

Does store location require condenser fins to be coated? (Circle yes or no)<br />

yes / no<br />

yes / no<br />

yes / no<br />

Does this condenser have a Variable Freq. Drive (VFD) controlling the fan motors? (Circle yes or no) yes / no<br />

Confirm correct settings and operation of VFD. (Circle yes or no)<br />

If no VFD, confirm correct condenser control by EMS. (Circle yes or no)<br />

Confirm correct settings and operation of condenser split. (Circle yes or no)<br />

Confirm correct operation of condenser drain down system. (Circle yes or no)<br />

Is inverted trap installed on inlet side of condenser pipe work? (Circle yes or no)<br />

Is test valve installed on inlet side of condenser pipe work? (Circle yes or no)<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

Record setting of liquid hold back valve.<br />

Is receiver level alarm device operating? (Circle yes or no)<br />

yes / no<br />

Record level of refrigerant in tank. %<br />

Are caps for all valves installed and tightened at end of startup? (Circle yes or no)<br />

yes / no<br />

Record setting of rack high pressure cut out switch.<br />

Is sufficient oil in the oil reservoir? (Circle yes or no)<br />

Is the oil level in each compressor correct? (Circle yes or no)<br />

Is the oil clear in color and free of oxidation after minimum 24 runtime? (Circle yes or no)<br />

yes / no<br />

yes / no<br />

yes / no<br />

Comments:<br />

15600 - 13<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


REFRIGERATION INSTALLATION<br />

HANDOVER DOCUMENT / SIGN OFF SHEET<br />

Rack A<br />

All sections of this document must be completed before the installation will be accepted.<br />

Store No. ___________ Location:<br />

City, State<br />

Store Type:<br />

SC, SAMS, NM<br />

Name of technician carrying out checks and completing this form<br />

Date<br />

All system identification labels installed? (Circle yes or no)<br />

All expansion valve strainers cleaned? Check three strainers per rack. (Circle yes or no)<br />

yes / no<br />

yes / no<br />

List circuit numbers of strainers checked.<br />

Are condensate drains operating correctly? (Circle yes or no)<br />

Are all glass doors adjusted properly? (Circle yes or no)<br />

Are cases shimmed every 4 feet? (Circle yes or no)<br />

Are case to case joints sealed? (Circle yes or no)<br />

At bottom penetrations in cases, is foam shaved flat and sealed?<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

System No.<br />

Case No.<br />

Make<br />

Model<br />

Length (feet)<br />

Float Circuit? (Circle yes or no)<br />

yes / no<br />

EPR Setting psi Lighting Amps<br />

EMS Setting Cut In degrees F Fan Amps<br />

EMS Setting Cut Out degrees F Defrost Amps<br />

Superheat Setting degrees F Trim Heater Amps<br />

Confirm that the breakers to the following circuits are labeled correctly. (Circle yes or no)<br />

Lighting<br />

Fans<br />

Defrost<br />

Trim Heaters<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

15600 - 14<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


System No.<br />

Case No.<br />

Make<br />

Model<br />

Length (feet)<br />

Float Circuit? (Circle yes or no)<br />

yes / no<br />

EPR Setting psi Lighting Amps<br />

EMS Setting Cut In degrees F Fan Amps<br />

EMS Setting Cut Out degrees F Defrost Amps<br />

Superheat Setting degrees F Trim Heater Amps<br />

Confirm that the breakers to the following circuits are labeled correctly. (Circle yes or no)<br />

Lighting<br />

Fans<br />

Defrost<br />

Trim Heaters<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

System No.<br />

Case No.<br />

Make<br />

Model<br />

Length (feet)<br />

Float Circuit? (Circle yes or no)<br />

yes / no<br />

EPR Setting psi Lighting Amps<br />

EMS Setting Cut In degrees F Fan Amps<br />

EMS Setting Cut Out degrees F Defrost Amps<br />

Superheat Setting degrees F Trim Heater Amps<br />

Confirm that the breakers to the following circuits are labeled correctly. (Circle yes or no)<br />

Lighting<br />

Fans<br />

Defrost<br />

Trim Heaters<br />

yes / no<br />

yes / no<br />

yes / no<br />

yes / no<br />

15600 - 15<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


REFRIGERATION INSTALLATION<br />

HANDOVER DOCUMENT / SIGN OFF SHEET<br />

Rack Data Collection for Verisae<br />

Store No. ___________ Location:<br />

City, State<br />

Store Type:<br />

SC, SAMS, NM<br />

Project Type (circle one): New Store Relocation Expansion<br />

Rack Letter (circle one):<br />

A B C D E F G<br />

Remote Condenser 1 Remote Condenser 2<br />

Remote Condenser 3 Remote Condenser 4<br />

Remote Condenser 5 Remote Condenser 6<br />

Remote Condenser 7<br />

Refrigerant Type (circle one): R22 R404A R422D R422A R134A R407A Other<br />

Full Charge lbs oz<br />

Charge Method (circle one): Actual Receiver Calculation On Site Measurement<br />

Temperature (circle one): Low Medium<br />

Manufacturer (circle one): Hill PHOENIX Kysor Tyler Systematic Zero Zone Other<br />

Model No.<br />

Serial No.<br />

Rack Letter (circle one):<br />

A B C D E F G<br />

Remote Condenser 1 Remote Condenser 2<br />

Remote Condenser 3 Remote Condenser 4<br />

Remote Condenser 5 Remote Condenser 6<br />

Remote Condenser 7<br />

Refrigerant Type (circle one): R22 R404A R422D R422A R134A R407A Other<br />

Full Charge lbs oz<br />

Charge Method (circle one): Actual Receiver Calculation On Site Measurement<br />

Temperature (circle one): Low Medium<br />

Manufacturer (circle one): Hill PHOENIX Kysor Tyler Systematic Zero Zone Other<br />

Model No.<br />

Serial No.<br />

15600 - 16<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 15600 – REFRIGERATION SYSTEMS<br />

Project Location:<br />

Date:<br />

(City & State)<br />

Project Number:<br />

Store Number:<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. The undersigned hereby declares that the Refrigeration Systems (hereafter referred to as the “Systems”) are<br />

installed and in general conformance with the Contract Documents, applicable Codes, and shop drawings. The Systems have<br />

been provided and placed in operational condition in accordance with the manufacturer's published instructions and the<br />

Contract Documents.<br />

(Contractor Signature)<br />

(Contractor name and address)<br />

Phone Number: (<br />

)___________________<br />

Recommendation of Acceptance:<br />

This Recommendation of Acceptance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. We recommend Wal-Mart accept the installation of the Systems (as referenced above). The Systems are found to<br />

be in general conformance with the Contract Documents. This recommendation is based on periodic refrigeration site<br />

observation and functional performance tests conducted during the construction of the project.<br />

While this review is an integral part of this project, it does not relieve the Contractor of his responsibility to comply with the<br />

applicable provisions of the Contract Documents along with the mandated codes and standards. These examinations shall not<br />

be construed as a check of every item nor does it prevent authorities from hereafter requiring corrections of errors in plans or<br />

installation.<br />

WAL-MART’S REFRIGERATION CONSULTANT:<br />

(Wal-Mart’s Refrigeration Consultant Signature )<br />

(Wal-Mart’s Refrigeration Consultant name and address)<br />

Phone Number: (<br />

)__________________<br />

15600 - 17<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


BLANK PAGE<br />

15600 - 18<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 033111<br />

SECTION 15700 (23 6000) - HEATING, VENTILATING, AND AIR CONDITIONING EQUIPMENT<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Heating, ventilating, and air conditioning systems.<br />

a. Roof Top Air Conditioning Units.<br />

b. Roof Exhaust Fans.<br />

c. Kitchen Exhaust Hood, Exhaust Fan, and Fire Suppression System.<br />

d. Air Handling Units.<br />

e. Air Curtains.<br />

B. Related Requirements:<br />

1. Section 01454 - Architect-Engineer Quality Assurance.<br />

2. Section 01455 - Mechanical Equipment Testing, Adjusting, and Balancing: Test and balance.<br />

3. Section 01600 - Product Requirements: Direct purchased products through pre-negotiated suppliers.<br />

4. Section 01640 - Owner Furnished Products.<br />

5. Section 07815 - Mineral Fiber Fireproofing (if specified): Grease exhaust duct fireproofing.<br />

6. Section 07721 - Manufactured Curbs: Curbs for roof top heating, ventilating, and air conditioning<br />

equipment.<br />

7. Section 13810 - Energy Monitoring and Control Systems: Cable sets and conduit for remote temperature<br />

sensor, control wiring, and related components for energy management system.<br />

1.2 DEFERRED SUBMITTALS - EXHAUST HOOD AND DUCT SYSTEMS<br />

A. Product Data:<br />

1. Manufacturer data on kitchen exhaust hood, exhaust fan, and fire suppression system.<br />

2. Underwriter's Laboratories (UL) listing number and data.<br />

3. National Fire Protection Association (NFPA) compliance data.<br />

B. Quality Assurance/Control Submittals: Current ICBO, BOCA, SBCCI or NER Evaluation Report approvals for<br />

hood and fire suppression system.<br />

C. Shop Drawings:<br />

1. Drawings for each exhaust hood showing location in relation to food service equipment, construction,<br />

configuration, clearances from equipment, dimensions and materials.<br />

2. Details of fire suppression system.<br />

3. Details of exhaust hood system connection to building structure.<br />

4. Details of system attachment to exhaust riser.<br />

D. Submit deferred submittals in accordance with Section 01330.<br />

1.3 CLOSEOUT SUBMITTAL<br />

A. Record Letter of Conformance: Submit Contractor’s Record Letter of Conformance in accordance with Section<br />

01770 and on the forms attached at the end of this Section.<br />

1. Kitchen exhaust hood fire suppression system.<br />

2. HVAC mechanical systems.<br />

1.4 QUALITY ASSURANCE<br />

A. Certifications: Each item of equipment available with capacity ratings certified by AMCA and/or ARI, shall be<br />

furnished with capacity ratings so certified.<br />

15700 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


1.5 DELIVERY, STORAGE, AND HANDLING<br />

A. Heating, Ventilating, and Air Conditioning Equipment Furnished by Owner and Installed by Contractor: Include in<br />

Contract Amount costs incurred for receiving, storage, and labor. Contractor shall be responsible for costs arising<br />

when replacement materials must be reshipped due to loss or damage on job site after acceptance of original<br />

shipment. Immediately upon award of Contract, coordinate release of units for delivery to site with contacts<br />

specified in this Section. Provide crane service to hoist HVAC units directly from truck to roof.<br />

1.6 SCHEDULING<br />

A. Milestone Completion Date: Complete Work of this Section on or before Delivery date specified in Section<br />

01640, "Items Furnished by Others Schedule."<br />

B. Coordinate Contract interface Work of this Section to provide for energy management system operation and<br />

testing in accordance with energy management system Milestone Completion date.<br />

C. Schedule testing and balancing in accordance Section 01455.<br />

1.7 WARRANTY<br />

A. After acceptance by Owner, supply materials and labor warranty for components supplied under this Section,<br />

except as specifically noted for Owner furnished equipment.<br />

B. Owner furnished equipment shall be turned over to Owner in good working order. Prior to acceptance by Owner,<br />

equipment failures are under manufacturer's warranty. Notify equipment warranty contact specified herein for<br />

replacement or reimbursement information prior to beginning repairs. After acceptance by Owner, Contractor is<br />

not responsible for warranty repair.<br />

1.8 SYSTEM STARTUP<br />

A. Roof top air conditioning units (RTU), and air handling unit (AHU) start-up shall be by the manufacturer factory<br />

trained personnel at no cost to the Contractor. The RTU manufacturer will conduct two start-up visits. AHU<br />

manufacturer will conduct one start-up visit. Start up visits will include the following:<br />

1. Initial Start-Up:<br />

a. Remove shipping brackets and hardware<br />

b. Verify OEM equipment protections are functioning<br />

c. Verify motor/compressor rotation<br />

d. Verify motor amperage<br />

e. Verify gas pressure<br />

2. Final Start-Up:<br />

a. Verify items from Initial Start-Up<br />

b. Complete manufacturer’s equipment start-up procedure<br />

c. Verify unit sequence of operation<br />

B. The Contractor shall schedule and coordinate start-up visits. Final start-up of RTUs, AHUs shall include<br />

equipment manufacturer (OEM), and the Engineer of Record (EOR at EOR’s discretion) in attendance. Final startup<br />

shall be scheduled six weeks in advance and shall be scheduled to occur two weeks prior to Possession week.<br />

Verify actual schedule with Wal-Mart Mechanical Services Construction Manager.<br />

C. Equipment installation shall be complete and made ready for start-up including electric, gas, water, or other<br />

utilities as required for functioning and start-up procedures.<br />

D. Failure by the Contractor to have equipment ready for start-up at scheduled time shall result in reimbursement by<br />

the Contractor to Wal-Mart of costs plus 10 percent incurred by required attendees.<br />

15700 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


E. The Contractor shall conduct start-up operations for equipment specified herein other than RTUs and AHUs.<br />

Perform start-up in accordance with manufacturer's printed installation and start-up instructions. Mechanical<br />

failure, prior to acceptance by Owner, shall be repaired by Contractor through warranty agreement with<br />

manufacturer. Record start-up data on forms included at the end of this section. Retain one copy on site and<br />

submit one copy to EOR for review and approval.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner will furnish heating, ventilating, and air conditioning equipment as follows under provisions of Section<br />

01640 for installation by the Contractor.<br />

1. Roof top air conditioning units.<br />

2. Air handling unit.<br />

3. Kitchen Exhaust Hood, Exhaust Fan, and Fire Suppression System.<br />

2.2 ROOF TOP AIR CONDITIONING UNITS (OWNER FURNISHED - CONTRACTOR INSTALLED)<br />

A. Roof top air conditioning units will be furnished by Owner for installation by Contractor.<br />

B. Roof Top Air Conditioning Units: Manufactured by Lennox, Inc.<br />

1. Technical and Warranty Contacts:<br />

a. Jeff O'Dell National Account Technical Consultant and Warranty Contact (972) 497-5173.<br />

b. Tommy Boneta, National Account Technical Consultant and Warranty Contact (972)-497-7743.<br />

2. Start up and Commissioning contacts:<br />

a. Dedicated Wal-Mart Technical, Pre Start, Commissioning Hotline (866) 659-0756<br />

b. Courtney Marrero, Project Manager (Pre start up/Commissioning) (972) 497-7575.<br />

3. Equipment Quotes and Delivery contacts:<br />

a. Mary Mitchell, Lennox National Accounts (972) 497-6782.<br />

b. Al White, Lennox National Accounts (972) 497-6856.<br />

c. Esteban Diaz Lennox National Accounts (972)-497-6925.<br />

4. Account Manager:<br />

a. Pat Trlica (405) 340-1622.<br />

C. Where required for roof top units, factory mount and wire smoke detectors in roof top unit unless noted otherwise<br />

on RTU schedule on Drawings.<br />

2.3 EXISTING ROOF TOP AIR CONDITIONING UNITS<br />

A. Where required, provide smoke detectors in existing roof top units.<br />

2.4 ROOF EXHAUST FANS<br />

A. Roof Fans: Low contour, spun aluminum hood and base sections with curb cap, bird screen, and other accessories<br />

as scheduled on Drawings. Provide centrifugal fans with direct or belt drive motor, mounted on resilient supports<br />

with isolators between support and base. Provide motor with thermal overloads. Locate motor out of exhaust air<br />

stream. Provide UL listed and AMCA certified fans, of capacities and electrical characteristics as scheduled on<br />

Drawings.<br />

2.5 KITCHEN EXHAUST HOOD, EXHAUST FAN AND FIRE SUPPRESSION SYSTEM (OWNER FURNISHED<br />

- CONTRACTOR INSTALLED)<br />

A. Description: Exhaust hood system including hood, exhaust fan, and factory installed fire suppression system as<br />

indicated on the drawings.<br />

15700 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Manufacturer:<br />

1. Exhaust Hood System: Captive-Aire, Raleigh, NC.<br />

2. Contacts:<br />

a. Jennifer Blackley (800) 965-0420 ext. 540.<br />

b. Deborah Johnson (800) 965-0420 ext. 545.<br />

c. Christy Morden (800) 965-0420 ext. 543.<br />

3. Factory Installed Fire Suppression System Supplier: ANSUL Inc., Houston TX.<br />

2.6 AIR HANDLING UNIT (OWNER FURNISHED - CONTRACTOR INSTALLED)<br />

A. Roof top air handling unit will be furnished by Owner for installation by Contractor.<br />

B. Roof top air handling unit manufacturer:<br />

1. Munters. Contact: John Grossman, (800) 229-8557. Warranty Contact: Kevin Koenning, (800) 229-8557.<br />

C. Where required, smoke detectors will be factory mounted and wired in roof top unit unless noted otherwise on<br />

desiccant wheel unit schedule on Drawings.<br />

2.7 AIR CURTAINS<br />

A. Air curtains shall be of the model and characteristics as shown on the drawings. Air curtains shall be Contractor<br />

furnished - Contractor installed. Units shall be by one of the manufacturers specified.<br />

1. Berner International Corp., New Castle, PA. Supplier Contact: Sales Dept, (800) 245-4455.<br />

2. Powered Aire, Inc., Greenville, PA Supplier Contact: Jay Lynn, (888) 321-2473.<br />

B. Product Procurement:<br />

1. Units shall be Direct Purchase Products purchased directly by the General Contractor through a Pre-<br />

Negotiated Supplier specified above in accordance with requirements specified in Section 01600.<br />

2. Obtain equipment pricing and purchasing instructions through Pre-Negotiated Supplier Contact.<br />

3. Send purchase orders to Pre-Negotiated Supplier contact.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install equipment per manufacturer’s instructions and requirements of Authority Having Jurisdiction (AHJ).<br />

B. Air Handling and Roof Top Air Conditioning Units:<br />

1. Coordination:<br />

a. Coordinate installation, testing, and completion dates with energy management system (EMS)<br />

installer.<br />

b. Coordinate installation with equipment manufacturers and Engineer of Record<br />

c. Coordinate installation and testing and balancing with ITBA as specified in section 01455.<br />

2. Label units with 6 inch black permanent paint stencil. Number units as indicated on Drawings. Locate label<br />

for each unit so it can be read from the roof hatch.<br />

3. Do not set roof top equipment on curbs until installation of roofing base flashing has been completed.<br />

4. Label RTUs scheduled with CO2 sensors with 3 inch red permanent paint stencil. Label units “IAQ” and<br />

locate label for each unit so it can be read from the roof hatch.<br />

C. Kitchen Exhaust Hood, Exhaust Fan, and Fire Suppression System:<br />

1. Install kitchen exhaust hood with factory installed fire suppression system, exhaust fan, and associated<br />

ductwork.<br />

2. Owner’s fire suppression system supplier will provide fire suppression system final connections at no cost<br />

to the Contractor.<br />

15700 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


D. Air Curtains: Install air curtain to avoid obstructions to the air stream when the grille is directed 20 degrees to<br />

either side. Outlet nozzle shall be not more than 1 inch above the top of the door opening. If circumstances require<br />

a higher mounting, locate the unit 3/8 inch away from the wall for each inch the unit is raised above the door<br />

opening. Seal void space between air curtain and wall.<br />

3.2 FIELD QUALITY CONTROL<br />

A. Field Quality Control shall be performed by the Contractor unless otherwise specified.<br />

B. Roof Top Air Conditioning Units:<br />

1. Testing and balancing will be performed by Owner’s Independent Testing and Balancing Agency (ITBA)<br />

in accordance with Section 01455 at no cost to the Contractor.<br />

2. Full testing and balancing shall be performed only on new or relocated units or units with modified<br />

ductwork.<br />

3. Limited testing and balancing as follows shall be performed on existing units with ductwork not being<br />

modified. Record readings for inclusion into final report for Owners’ use, and label the units as “Existing”:<br />

a. Test and record fan speeds (rpm), CFM, and full load amperes. Record voltage at each unit.<br />

b. Test and adjust system for a minimum of 10% of outside air.<br />

c. Test and record suction and discharge external static pressures at respective plenums. Seal access<br />

holes with rubber or metal snap-in plugs. The use of duct tape to seal access holes will not be<br />

permitted.<br />

d. Test and record entering air temperatures. (Dry Bulb heating and cooling; Wet Bulb cooling.)<br />

e. Test and record leaving air temperature. (Dry Bulb heating and cooling; Wet Bulb cooling.)<br />

f. Test and record outside air Dry Bulb and Wet Bulb temperatures.<br />

g. Verify and record proper operation of all stages of gas or electric heating sections.<br />

h. Verify proper control operation of unit as applicable.<br />

C. Kitchen Exhaust Hood, Exhaust Fan, and Fire Suppression System: Follow the procedures below for the<br />

observation and acceptance testing of the fire suppression system.<br />

1. Fire Protection Consultant’s Responsibilities: Wal-Mart’s Fire Protection Consultant will perform the<br />

following quality control activities at no cost to the Contractor:<br />

a. Schedule observation and acceptance testing in conjunction with the final fire sprinkler system<br />

observation.<br />

b. Contact hood manufacturer to obtain fire suppression system supplier’s contact information.<br />

c. Coordinate observation and acceptance testing schedule of fire suppression system with Contractor.<br />

d. Prior to observation and acceptance testing, obtain drawings approved by AHJ from fire suppression<br />

system supplier.<br />

2. Contractor’s Responsibilities:<br />

a. Coordinate observation and acceptance testing schedule with fire suppression system representative.<br />

b. Require sub contractors involved in work related to the fire suppression system to attend<br />

observation and acceptance testing.<br />

c. Verify all electrical, mechanical, and gas piping systems are complete and functioning prior to and<br />

at the time of the test.<br />

d. Additional charges incurred by Fire Protection Consultant, and fire suppression system<br />

representative due to Contractors lack of preparation shall be paid by Contractor.<br />

3. Fire Suppression System Supplier’s Responsibilities: Wal-Mart’s fire suppression system supplier will<br />

perform the following QC activities at no cost to the Contractor.<br />

a. Send drawings approved by AHJ to Fire Protection Consultant and provide one copy of drawings<br />

for use on site during observation and testing acceptance.<br />

b. Verify fire suppression system installation and connections are complete and properly functioning<br />

prior to the acceptance test.<br />

c. Additional charges incurred by Fire Protection Consultant and Contractor due to fire suppression<br />

system representative’s lack of preparation shall be paid by fire suppression system representative.<br />

15700 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


d. Provide multiple activations of the system necessary to complete the acceptance testing as follows:<br />

1) Perform acceptance testing in accordance with the ANSUL R-102 Design Manual in the<br />

presence of the Fire Protection Consultant.<br />

2) Actuate the system to demonstrate proper installation and piping connections (such as<br />

balloon test to confirm nozzle operation).<br />

3) Demonstrate device connections including fusible links and manual activation device.<br />

4) Demonstrate proper operation of shunt trip breaker, emergency gas shut-off valve, and signal<br />

activation to the building fire alarm.<br />

5) Demonstrate proper sequence of events for additional items required by AHJ or ANSUL R-<br />

102 Design Manual as required for acceptance of system including but not limited to fan and<br />

ventilation interlocks.<br />

e. Modification for proper system performance will be made at the time of observation and acceptance<br />

test when practical. Expenses incurred for additional acceptance tests due to the lack of proper<br />

operation will be the charged to the fire suppression system supplier.<br />

D. Air Curtains: Follow procedure outlined below to verify directional vanes are set correctly.<br />

1. With air door operating and door in its full open position, verify there are no obstructions to the air flow.<br />

2. Determine the air stream split location by holding a cloth approximately 12 inches above the floor. Move<br />

the cloth back and forth in doorway to verify air is being directed to both the inside and outside. The split<br />

location is determined when the cloth is vertical with minimal or no movement. The split location shall be 6<br />

inches outside the doorway at 12 inches above the floor.<br />

3. If split location is not correct and directional vanes need to be adjusted, disconnect power source, remove<br />

the cover housing and loosen the two vane mounting screws located on each end of the outlet nozzle.<br />

Adjust directional vanes by grasping each vane with a pair of pliers and twisting. Protect vanes with a cloth<br />

to prevent scratching with pliers. After correct adjustments have been made, retighten vane mounting<br />

screws, reassemble air curtain, and connect power supply.<br />

E. Functional Performance Testing (FPT): FPT will be conducted by Wal-Mart Engineer of Record at no cost to the<br />

Contractor in accordance with Section 01454. FPT will be performed after Wal-Mart possession date.<br />

Deficiencies noted and related to the Contractor’s installation responsibilities shall be corrected prior to Grand<br />

Opening.<br />

3.3 PROTECTION<br />

A. Protect RTUs and AHUs from damage, including but not limited, to paint spray and drywall dust. Replace air<br />

filters regularly to preclude damage. Damage incurred due to Contractor neglect will be repaired by manufacturer<br />

at Contractor’s expense.<br />

END OF SECTION<br />

15700 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


AIR CURTAIN START-UP REPORT<br />

Page _____ of<br />

PROJECT<br />

LOCATION<br />

UNIT DATA<br />

UNIT<br />

NO.*<br />

UNIT<br />

NO.*<br />

UNIT<br />

NO.*<br />

UNIT<br />

NO.*<br />

UNIT<br />

NO.*<br />

UNIT<br />

NO.*<br />

Manufacturer<br />

Area Served<br />

Model No.<br />

Serial No.<br />

Nameplate KW<br />

TEST DATA ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL<br />

Units have been cleaned (YES)<br />

(NO)<br />

Airstream split location has been<br />

verified and air vane adjusted<br />

Thermostat has been tested in all<br />

positions. Location of airstream split<br />

above the floor and away from door.<br />

* Unit number shall correspond to number on Drawings.<br />

START-UP DATE TIME READINGS BY<br />

VERIFIED BY<br />

(General Contractor)<br />

REMARKS:<br />

15700 - 7<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 15700 – HEATING, VENTILATION, AND AIR CONDITIONING EQUIPMENT<br />

ANSUL HOOD SUPPRESSION SYSTEM(S)<br />

Project Location:<br />

Date:<br />

(City & State)<br />

Project Number: Store Number: Number of Systems: _______<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. The undersigned hereby declares that the fixed ANSUL exhaust hood suppressions systems (hereafter referred to<br />

as the “Systems”) is installed and is in general conformance with the Contract Documents, applicable Codes, and shop<br />

drawings. The “Systems” have been provided and placed in operational condition in accordance with the manufacturer's<br />

published instructions and the Contract Documents.ANSUL AUTHORIZED INSTALLER:<br />

(Subcontractor Signature)<br />

(Subcontractor name and address)<br />

Phone Number: ( )<br />

CONTRACTOR:<br />

(Contractor Signature)<br />

(Contractor name and address)<br />

____________<br />

____________ Phone Number: ( )<br />

Recommendation of Acceptance:<br />

This Recommendation of Acceptance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. We recommend Wal-Mart accept the installation of the “Systems” (as referenced above). The “Systems” are found<br />

to be in general conformance with the Contract Documents, and Approved Shop Drawings. This recommendation is based on<br />

ANSUL System Site Observation and Acceptance Test (FPAT) witnessed on ___________________(Report Date), and<br />

follow up verification of identified issues conducted on ___________________ (Trip Date, Report Date).<br />

While this review is an integral part of this project, it does not relieve the Contractor of their responsibility to comply with<br />

the applicable provisions of the Contract Documents along with the mandated codes and standards. These examinations shall<br />

not be construed as a check of every item nor does it prevent authorities from hereafter requiring corrections of errors in plans<br />

or installation.<br />

WAL-MART’S FIRE PROTECTION CONSULTANT:<br />

(Wal-Mart’s Fire Protection Consultant Signature )<br />

(Wal-Mart’s Fire Protection Consultant name and address)<br />

Phone Number: ( )<br />

15700 - 8<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


CONTRACTOR'S RECORD LETTER OF CONFORMANCE<br />

SECTION 15700 – HEATING, VENTILATION, AND AIR CONDITIONING EQUIPMENT<br />

HVAC MECHANICAL SYSTEM(S)<br />

Project Location:<br />

Date:<br />

(City & State)<br />

Project Number:<br />

Store Number:<br />

Statement of Conformance:<br />

This Record Letter of Conformance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. The undersigned hereby declares that the HVAC mechanical systems (hereafter referred to as the “Systems”) is<br />

installed and is in general conformance with the Contract Documents, applicable Codes, and shop drawings. The “Systems”<br />

have been provided and placed in operational condition in accordance with the manufacturer's published instructions and the<br />

Contract Documents. ____________<br />

(Contractor Signature)<br />

(Contractor name and address)<br />

____________ Phone Number: ( )<br />

Recommendation of Acceptance:<br />

This Recommendation of Acceptance is provided as a Record Document in accordance with Section 01770 – Contract<br />

Closeout. We recommend Wal-Mart accept the installation of the “Systems” (as referenced above). The “Systems” are found<br />

to be in general conformance with the Contract Documents, and Approved Shop Drawings. This recommendation is based on<br />

MEP Site Observation and Functional Performance Test witnessed on ___________________(Report Date), and follow up<br />

verification of identified issues conducted on ___________________ (Trip Date, Report Date).<br />

While this review is an integral part of this project, it does not relieve the Contractor of their responsibility to comply with<br />

the applicable provisions of the Contract Documents along with the mandated codes and standards. These examinations shall<br />

not be construed as a check of every item nor does it prevent authorities from hereafter requiring corrections of errors in plans<br />

or installation.<br />

WAL-MART’S MECHANICAL CONSULTANT:<br />

(Wal-Mart’s Mechanical Consultant Signature )<br />

(Wal-Mart’s Mechanical Consultant name and address)<br />

Phone Number: ( )<br />

15700 - 9<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


BLANK PAGE<br />

15700 - 10<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 033111<br />

SECTION 15800 - AIR DISTRIBUTION<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Ductwork, dampers, inlets and outlets for HVAC systems.<br />

B. Related Requirements:<br />

1. Section 01455 - Mechanical Equipment Testing, Adjusting, and Balancing: Testing and balance of HVAC<br />

systems.<br />

2. Section 15700 - Heating, Ventilating, and Air Conditioning.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. Air Movement and Control Association (AMCA):<br />

1. AMCA 500 – Test Methods for Louvers, Dampers And Shutters<br />

C. ASTM International (ASTM):<br />

1. ASTM A 653 - Steel Sheet, Zinc-Coated (Galvanized), or Zinc-Iron Alloy-Coated (Galvannealed) by the<br />

Hot Dip Process.<br />

2. ASTM C 553 - Mineral Fiber Blanket Thermal Insulation for Commercial and Industrial Applications<br />

3. ASTM C 1071 - Thermal and Acoustical Insulation (Mineral Fiber, Dust Lining Material.<br />

4. ASTM C 1136 - Flexible, Low Permeance Vapor Retarders for Thermal Insulation<br />

5. ASTM C 1290 - Flexible Fibrous Glass Blanket Insulation Used to Externally Insulate HVAC Ducts<br />

6. ASTM E 84 - Surface Burning Characteristics of Building Materials.<br />

7. ASTM E 96 - Standard Test Methods for Water Vapor Transmission of Materials<br />

8. ASTM E 119 - Fire Tests Of Building Construction And Materials.<br />

D. National Fire Protection Association (NFPA):<br />

1. NFPA 90A - Installation of Air Conditioning and Ventilating Systems.<br />

2. NFPA 90B - Installation of Warm Air Heating and Air-Conditioning Systems<br />

3. NFPA 96 - Ventilation Control And Fire Protection Of Commercial Cooking Operations<br />

E. Sheet Metal Air Conditioning Contractors National Association (SMACNA):<br />

1. SMACNA 1035 - HVAC Duct Construction Standards - Metal & Flexible<br />

F. British Standards Institution (BSI):<br />

1. BS 302 - Stranded Steel Wire Ropes.<br />

G. North American Insulation Manufacturer’s Association (NAIMA)<br />

1. AH 124 - Fibrous Glass Duct Liner Standard<br />

1.3 QUALITY ASSURANCE<br />

A. Comply with NFPA 90A unless otherwise indicated.<br />

15800 - 1<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


1.4 SCHEDULING<br />

A. Milestone Completion Date: Complete Work of this Section on or before Delivery date specified in Section 01640,<br />

"Items Furnished by Others Schedule."<br />

B. Schedule testing and balancing in accordance Section 01455 after completion of system start-up requirements.<br />

1.5 WARRANTY<br />

A. Warrant ductwork for period of one year from date of final acceptance of job against noise and vibration under full<br />

range of operating conditions.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner's supplier will furnish drop box diffusers as specified hereinafter for<br />

installation by the Contractor. All other items specified in this section shall be Contractor furnished and installed.<br />

B. Duct transitions and return air plenums for RTUs and AHUs without drop boxes shall be provided by Contractor.<br />

C. Descriptions and specifications of Owner furnished items and equipment hereinafter are included as information to<br />

the Contractor only and not to be considered as Contractor requirements unless otherwise stated.<br />

2.2 SHEET METAL DUCTWORK<br />

A. Sheet Metal Ductwork: Continuous hot-dip mill galvanized, minimum coating of G60, lock-forming quality steel<br />

sheets, in accordance with ASTM A653.<br />

B. Gages: Sheet metal gage as specified in SMACNA 1035 but not less than the following.<br />

1. Rectangular Duct: 26 gage for all sizes.<br />

2. Round Duct: Prime grade steel sheets, by United Sheet Metal Co. Inc. or equivalent.<br />

a. 14 inch diameter and smaller: 26 gage.<br />

b. 15 inch diameter through 26 inch diameter: 24 gage.<br />

c. 27 inch diameter through 36 inch diameter: 22 gage.<br />

C. Round ductwork shall be spiral seam where exposed and not insulated on sales floor area and spiral or longitudinal<br />

seam in all other areas.<br />

D. Ductwork connections for round duct may be made using SpiralMate self-sealing duct connection system by<br />

Ductmate Industries (800) 245-3188.<br />

2.3 DUCTWORK INSULATION<br />

A. Manufacturers:<br />

1. CertainTeed.<br />

2. Knauf.<br />

3. Schuller (Manville).<br />

4. Owens/Corning.<br />

B. Substitutions: Not permitted.<br />

C. Duct Liner: Fibrous-Glass complying with ASTM C 1071, NFPA 90A, or NFPA 90B; and NAIMA AH124.<br />

1. Mininum Thermal Conductivity: R-Value at 75 deg F mean temperature.<br />

a. Type I, Flexible: R-3.7 per inch<br />

15800 - 2<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


. Type II, Rigid: R=4.2 per inch.<br />

D. Duct Wrap: Mineral-fiber blanket insulation with factory applied FSK or vinyl jacket. Insulation shall be mineral<br />

or glass fibers bonded with a thermosetting resin, complying with ASTM C 553, Type II (for use on surfaces at<br />

temperatures up to 1700 deg. F) and ASTM C 1290. Factory-applied jackets shall conform to the following:<br />

1. FSK Jacket: Aluminum-foil, fiberglass-reinforced scrim with kraft-paper backing; complying with<br />

ASTM C 1136, Type II.<br />

2. Vinyl Jacket: White vinyl with a permeance of 1.3 perms when tested according to ASTM E 96,<br />

Procedure A, and complying with NFPA 90A and NFPA 90B.<br />

2.4 SELF-SEALING SPIRAL DUCTWORK SYSTEM (CONTRACTOR OPTION)<br />

A. General:<br />

1. At the option of the Contractor, self-sealing ductwork system may be used in lieu of round built-up system.<br />

2. Meet or exceed SMACNA's Leakage Class 3 requirements with no additional sealants.<br />

B. Manufacturer:<br />

1. Lindab Inc., Stamford, CT (800) 797-7476.<br />

C. Round Spiral Sheet Metal Ductwork System:<br />

1. SPIROsafe as manufactured by Lindab, Inc.<br />

2. Duct: Galvanized, minimum coating designation of G60, lock-forming quality steel sheets, in accordance<br />

with ASTM A653.<br />

3. Substitutions: Not permitted.<br />

D. Fittings:<br />

1. SPIROsafe as manufactured by Lindab, Inc.<br />

2. End gaskets EPDM rubber, factory installed, U-profile, double lipped.<br />

E. Control Dampers: SPIROsafe DSU as manufactured by Lindab, Inc.<br />

F. Supply Grilles: SPIROcomfort RGS-3 as manufactured by Lindab, Inc.<br />

2.5 DUCTWORK FOR REMOVAL OF GREASE AND SMOKE LADEN VAPORS<br />

A. Manufacturer: Metal-Fab Inc., Wichita, KS,<br />

1. Contact: CVP Department, (800) 835-2830.<br />

B. Product Description:<br />

1. Zero Clearance Series 3G Grease Duct by Metal-Fab.<br />

2. Factory prefabricated, double wall type, listed for venting of grease laden air from kitchen hoods requiring<br />

grease duct as described in NFPA 96.<br />

3. Rated for continuous operation at 500 F and intermittent operation at 2000 F.<br />

4. All components of the grease duct system shall be provided by the manufacturer to ensure the system meets<br />

the requirements of the listing including duct supports, guides, drain fittings, cleanouts, roof curbs, hood or<br />

fan adapters, fittings and expansion joints required to install the duct.<br />

5. Grease duct shall conform to requirements of ASTM E119, 2-hour fire resistance rating and 3-hour fire<br />

engulfment with subsequent hose stream test, and shall be listed by the following agencies with the<br />

associated listed reports:<br />

a. UL 1978 (File MH8251) - Grease Ducts for Restaurant Cooking Appliances.<br />

b. UL 2221 (File R15388) - Tests of Fire Resistive Grease Duct Enclosure Assemblies.<br />

C. Fabrication:<br />

1. The duct sections shall be constructed of an inner wall and an outer wall with ceramic fiber insulation<br />

between the walls. The inner wall shall be constructed of 304 or 430 stainless steel, 0.035 inch thickness for<br />

all sizes. The outer wall shall be constructed of aluminized steel, 0.024 inch thickness for sizes 6" to 24"<br />

and 0.034 inch thickness for sizes 26" to 36". Inner and outer walls shall be connected by means of spacer<br />

clips which shall maintain concentricity of the annular space and allow unobstructed differential thermal<br />

15800 - 3<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


expansion of inner and outer walls. The duct shall include a 3" thickness of ceramic fiber insulation<br />

between the inner and outer walls. The duct wall assembly shall be tested and listed at 0 clearance to<br />

combustibles.<br />

2. Inner pipe joints shall be held together by means of formed vee bands and sealed with P080 Grease Duct<br />

Sealant. Nuts for the inner and outer bands shall be retained by means of free-floating cages to allow easy<br />

alignment. Screws shall be of the hex head type with shoulder stops and tapered “lead-in” threads for easy<br />

starting.<br />

D. Curb Delivery: The manufacturer, General Contractor, and Mechanical Contractor shall coordinate fabrication of<br />

curbs and delivery to the job site sufficiently in time for installation concurrently with other rooftop curbs<br />

specified in Section 07721.<br />

2.6 VOLUME CONTROL DAMPERS<br />

A. Manual Dampers: Provide manual volume-control dampers where indicated and of the type and model number as<br />

scheduled on the drawings. Frame and blades shall be galvanized steel. Provide ceiling doors where required in<br />

accordance with Section 08311.<br />

1. Manufacturers: Provide dampers by one of the following:<br />

a. A.E.S. Inc, East Tallassee, AL, Contact: Chad Burt (800) 786-0402.<br />

b. Sisneros Brothers Mfg, Contact: Joshua Gallegos (800) 499-0106.<br />

c. Ruskin Company, Kansas City, MO, (816) 761-7476.<br />

2. Round Dampers: Dampers shall have end bearings and center locking control handle with position<br />

indicator. Control handle shall be Durodyne KL-7R or Ventlok 639. Provide 2-inch extension to protect<br />

insulation.<br />

3. Rectangular Dampers: Dampers shall have single blade or multiple inter-locked opposed blades with shaft<br />

bearings, 3/8 inch square control shaft and center locking control handle. Control handle shall be Durodyne<br />

KL7 or Ventlok 639.<br />

B. Field fabricated dampers shall not be used.<br />

C. Substitutions: Not permitted unless otherwise specified.<br />

2.7 FIRE DAMPERS<br />

A. Dampers: UL labeled, constructed and installed in accordance with NFPA 90A and UL instructions. Size dampers<br />

to provide free area equal to duct dimensions.<br />

B. Provide hanger design, and methods of hanging and supporting compatible with the structure.<br />

2.8 AIR INLETS AND OUTLETS<br />

A. Grilles, registers, ceiling outlets, and ceiling inlets shall be as indicated on Drawings. Wall mounted and hard<br />

ceiling mounted air inlets and outlets shall be provided with heavy-duty sponge or soft felt gaskets.<br />

2.9 DROP BOX DIFFUSERS (OWNER FURNISHED - CONTRACTOR INSTALLED)<br />

A. Manufacturer: Wal-Mart supplier for drop box diffusers will be as follows<br />

1. AES Industries, Tallassee, AL, Contact: Chad Burt (800) 786-0402.<br />

B. General Description: Drop boxes will be constructed of 18 gauge galvannealed/galvanized (paintable) steel sheet<br />

conforming to ASTM A 653, min. A60 coating designation, with integral 18 gauge minimum air diverters. Drop<br />

boxes shall be fully welded. Mechanical fastened seams shall not be used. Diffusers shall be fully adjustable<br />

double deflection drum louvers. Base louver in 6-way box shall be double deflection with opposed blade dampers.<br />

Provide air tight gaskets at louver connections to drop box. Drop boxes shall be insulated with 1” x 1.5 lb density<br />

duct liner glued with 100% coverage of adhesive and pin spotted to all interior surfaces per SMACNA. Provide 14<br />

gauge mounting brackets, 2”x 2”x 1/4” pre-punched angles, 3/8” all thread rod, beam clamps, and additional nuts<br />

and washers.<br />

15800 - 4<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


C. Accessory Package: Manufacturer shall provide mounting accessory package for each drop box consisting of the<br />

following:<br />

1. 2" x 2" x 1/4" pre-punched angles (or Unistrut).<br />

2. 3/8" all thread rod (pre-cut).<br />

3. Beam clamps.<br />

4. All bolts, nuts and washers.<br />

A. 6-Way Drop Box Performance Criteria:<br />

Unit<br />

Size<br />

6-Way Diffuser - Louver Schedule<br />

Box<br />

Type Total CFM Drum Louver Size Base Louver Size Minimum Throw (ft)<br />

5 Ton 6-way 2000 6 x 12 6 x 18 33<br />

10 Ton 6-way 4000 6 x 18 6 x 18 47<br />

20 Ton 6-way 6000 -7000 10 x 25 6 x 18 61<br />

25 Ton 6-way 8000 - 10000 12 x 30 6 x 18 74<br />

Base louver in 6-way box shall be double deflection with opposed blade dampers. Provide air tight gaskets at<br />

louver connections to drop box.<br />

B. Finish: Prime and finish coat in the shop. Paint exposed screws and fasteners to match drop box. Finish coating<br />

shall be color to match Sherwin-Williams #SW6385 “Dover White”.<br />

1. Alkyd Primer: One coat PPG Multigrip Epoxy Ester Dry Fog #6-157.<br />

2. Alkyd Finish: One coat PPG Speedhide Super-Tech Dry Fog Coating, Eggshell # 6-151.<br />

2.10 DUCT TRANSITIONS AND RETURN AIR PLENUMS (OWNER FURNISHED - CONTRACTOR<br />

INSTALLED)<br />

A. Manufacturer: Owner supplier for duct transitions and return air plenums will be as specified above for drop box<br />

diffusers.<br />

B. General: Fabricate supply air duct transitions and return air plenums for RTUs and AHUs with drop boxes of<br />

minimum 24 gauge paint grip steel per SMACNA duct construction standards. Provide 1 1/2" flange turned out<br />

to fasten to roof curb. Size supply transitions as required to transition from roof curb to drop boxes. Size opening<br />

in return air plenums for the unit CFM and cover opening with a 1”x 1” 16 gauge wire mesh with removable<br />

frame. Insulate supply and return duct as specified in paragraph DUCT INSULATION below. Glue duct liner with<br />

100% coverage of adhesive and pin spotted to all interior surfaces per SMACNA. Provide neoprene gasket<br />

material sufficient for installation of transitions and plenums. Mounting accessory packages shall be provided<br />

with the drop box asssembly.<br />

C. Finish: Paint grip steel prepared for field prime and finish coat.<br />

D. Paint hardware that will be exposed to the public, including, but not limited to, screw heads in drop boxes.<br />

E. Coordination: Manufacturer will label and package duct transitions and return air plenums for each RTU and<br />

provide assembly instructions in each package.<br />

2.11 DUCT SEALERS<br />

A. Manufacturer: Provide duct sealers of one of the following:<br />

1. Kingco 11376 or 10526 by ITW TACC.<br />

2. Ductmate PROseal.<br />

3. United McGill Duct-Sealer.<br />

4. Trans-Continental Equipment Co. (TCE) - MP Multi-purpose Duct Sealant.<br />

5. Hardcast #601 Iron-Grip.<br />

6. Hardcast Aluma-Grip Tape.<br />

15800 - 5<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


B. Substitutions: Not permitted.<br />

2.12 TYPE B DOUBLE WALL FLUE VENTS<br />

A. Products: Where shown on drawings, provide flue systems from the same manufacturer throughout the project.<br />

Type “B” gas vent flue, double-wall, air insulated venting system for gas fired equipment, tested under UL 441<br />

testing standard and labeled “UL”. Flues shall be complete with flue caps, necessary fittings, connectors, flashing<br />

cone, storm collar, supports, and other accessories.<br />

B. Manufacturer: Provide Type B gas vent flue of one of the following:<br />

1. Selkirk Metalbestos: Type B RV or QC.<br />

2. Hart & Cooley: Type B Gas Vent System, round.<br />

3. Metal-Fab: Type B Gas Vent or BigVent, round.<br />

4. American Metal: AmeriVent® Type B Vent, round.<br />

C. Substitutions: Not permitted.<br />

2.13 SINGLE WALL FLUE VENTS<br />

A. Products: 18 gage continuous hot-dip mill galvanized, minimum coating of G60, lock-forming quality steel sheets,<br />

in accordance with ASTM A653.<br />

PART 3 EXECUTION<br />

3.1 FABRICATION<br />

A. Fabrication requirements apply to new and modified ductwork.<br />

B. Fabricate, erect, and install ductwork for heating, ventilating, and air conditioning systems per SMACNA 1035<br />

and the requirements of the Authority Having Jurisdiction.<br />

C. Make joints air tight on supply, return, and exhaust ducts. Seal transverse and longitudinal joints with duct sealer<br />

unless otherwise noted. Seal exhaust ducts with exterior seal as required to assure positive seal.<br />

3.2 DUCT INSULATION<br />

A. Insulate ducts in accordance with SMACNA 1035. Do not insulate exhaust ductwork unless otherwise shown or<br />

specified.<br />

B. Rectangular Duct:<br />

1. Interior supply duct and air plenums: 1-1/2 inch liner.<br />

2. Interior return duct and air boots: 1-1/2 inch liner.<br />

3. Exterior supply and return duct: 2 inch rigid liner.<br />

C. Round Duct:<br />

1. Insulate the following round duct with duct wrap:<br />

a. Supply and return duct in receiving areas.<br />

b. Supply and return duct above finished ceilings.<br />

2. Duct Wrap Thickness:<br />

a. 2-inch (R=6.0 minimum installed value).<br />

3. Overlap facing and staple securely.<br />

3.3 DUCTWORK FOR REMOVAL OF GREASE AND SMOKE LADEN VAPORS<br />

A. Install grease duct in accordance with instructions and assembly drawings provided by the manufacturer.<br />

B. Support grease duct from building structure using rigid structural shapes for attachment of fixed point supports<br />

15800 - 6<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


(Plate Support Assembly). Anchor supports to structure by welding, bolting, steel expansion anchors, or concrete<br />

inserts. Size of structural shapes shall be in accordance with manufacturer’s recommendations.<br />

C. Clean all grease ducts of dust and debris prior to final connection to appliances.<br />

D. Protect incomplete grease duct installations by attaching temporary closures over open ends of sections.<br />

E. The installation of the grease duct system shall be inspected and certified by the manufacturer’s representative. A<br />

copy of the certification report shall be included in the job Closeout to Wal-Mart Construction Manager.<br />

3.4 AIR INLETS AND OUTLETS<br />

A. Locations of outlets indicated on Drawings are approximate. Coordinate with other trades to make symmetrical<br />

patterns. Determine locations by established pattern of lighting fixtures, or architectural reflected ceiling plan.<br />

B. Install fire radiation dampers and other devices at air inlets and outlets where required by codes and regulations of<br />

governing authorities. Dampers shall be UL labeled, constructed and installed in accordance with NFPA 90A and<br />

UL instructions.<br />

3.5 DROP BOX DIFFUSERS, DUCT TRANSITIONS, AND RETURN AIR PLENUMS<br />

A. Install drop boxes and associated duct transitions and return air plenums in accordance with the manufacturer’s<br />

installation instructions and as detailed on the drawings.<br />

B. Labeling: Contractor shall label drop box diffusers by painting the appropriate RTU number in black 6” letters on<br />

the bottom of each drop box.<br />

3.6 DUCT SUPPORTS<br />

A. Support horizontal and vertical sheet metal duct work in accordance with Schedule(s) at the end of this section.<br />

B. Do not use fasteners which penetrate roof deck.<br />

1. Provide seismic restraints and other components as required on Drawings and Section 13080.<br />

3.7 FIRE DAMPERS<br />

A. Install approved fire dampers in air ducts or air inlets and outlets where required by codes and regulations of<br />

governing authorities. Install access doors in ducts at all fire dampers.<br />

3.8 PROTECTION<br />

A. Protect work, equipment and material to prevent obstruction, damage or breakage. Close pipe openings with caps<br />

or plugs during installation. Cover and protect equipment against dirt, water, chemical or mechanical injury. At the<br />

completion of work, thoroughly clean all equipment and deliver the entire system in an unblemished condition<br />

3.9 TESTING<br />

A. Prepare systems for test and balance as specified in Section 01455.<br />

B. In coordination with Section 01455, make changes in pulleys, belts, ductwork, and dampers as required for correct<br />

balance as recommended by air balance and testing agency.<br />

15800 - 7<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


3.10 SCHEDULES<br />

SCHEDULE I – DUCT SUPPORT SCHEDULE<br />

MINIMUM HANGER SIZE<br />

RECTANGULAR DUCTWORK<br />

Maximum Half of<br />

Duct Perimeter*<br />

Pair at 10 ft Spacing Pair at 8 ft spacing Pair at 5 ft spacing Pair at 4 ft spacing<br />

Strap Rod Strap Rod Strap Rod Strap Rod<br />

P/2 = 30" 1" x 22 ga 10 ga 1" x 22 ga 10 ga 1" x 22 ga 12 ga 1" x 22 ga 12 ga<br />

P/2 = 72" 1" x 18 ga 3/8” 1" x 20 ga 1/4" 1" x 22 ga 1/4" 1" x 22 ga 1/4"<br />

* Perimeter = Sum of Sides<br />

ROUND DUCTWORK<br />

Diameter Maximum Spacing Strap<br />

24" and less 12' 1" x 22 ga<br />

26"-36" 12' 1" x 20 ga<br />

END OF SECTION<br />

15800 - 8<br />

Walmart SC #5641 - La Habra, CA PWO 04/11/11


UniSpec II 022610<br />

SECTION 16050 (26 0500) - BASIC ELECTRICAL MATERIALS AND METHODS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Electrical Identification<br />

2. Hangers and Supports<br />

3. Conduit Sleeves<br />

4. Grounding and Bonding<br />

B. Related Requirements:<br />

1. Section 09900 - Paints and Coatings: Field painting of hangers and supports.<br />

2. Section 13810 - Energy Management System (EMS)<br />

3. Section 16100 - Wiring Methods<br />

4. Section 16405 - Electrical Distribution Centers<br />

5. Section 16452 - Track Busway System<br />

6. Section 16500 - Lighting<br />

7. Section 16700 - Communication<br />

PART 2 - PRODUCTS<br />

2.1 ELECTRICAL IDENTIFICATION (Non EDC Items)<br />

A. Nameplates: Provide laminated plastic nameplates with 3/4 inch minimum contrasting-color engraved letters.<br />

2.2 HANGERS AND SUPPORTS<br />

A. Manufacturers:<br />

1. Unistrut Metal Framing, Unistrut Corporation, Wayne, MI, (800) 521-7730 or contact Steve Goldstein 800-<br />

243-1054 ext 111.<br />

2. ERICO, Solon, OH, (440) 349-2630.<br />

3. Minerallac Fastening Systems, Hampshire, IL, (877) 285-2200.<br />

B. Conduit and Equipment Supports: Hangers shall be Series P3000 or P3300 channels by Unistrut depending on<br />

load and span involved. Use Pipe Hangers by Minerallac, or Caddy Clips by ERICO only where impractical to<br />

install Unistrut Hangers.<br />

C. Attach hangers and supports to structure overhead by methods approved at job site. Do not use fasteners which<br />

penetrate the roof deck.<br />

2.3 CONDUIT SLEEVES<br />

A. Sleeves: Galvanized, black steel or schedule 40 PVC pipe.<br />

2.4 GROUNDING AND BONDING<br />

A. Insulated Grounding Bushing: Steel with feed-thru lugs.<br />

B. Insulated Equipment Ground Wire: Copper.<br />

PART 3 - EXECUTION<br />

16050 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


3.1 INSTALLATION<br />

A. Install specified materials in accordance with manufacturer's recommendations and as indicated on Drawings.<br />

B. Cutting and Patching: Where cutting is required through walls, floors, or ceilings, make openings no larger than<br />

required and repair affected surfaces to match adjacent surfaces.<br />

C. Nameplates: Bolt or pop-rivet nameplates to equipment. Clearly identify equipment or equipment served, such as<br />

"BALER", "COMPACTOR," etc. Install nameplates for each safety switch, contactor, time switch, pushbutton and<br />

other similar equipment.<br />

D. Electrical Equipment Supports: Support electrical equipment with hangers and supports specified above or in<br />

another approved manner where details are not indicated.<br />

E. Sleeves: Install where conduits pass through concrete floors. Caulk sleeves through outside walls above grade<br />

with sealant as specified in Section 07900.<br />

F. Fastening and Anchoring: Fasten conduit straps, disconnect switches, panelboards, and other equipment secured<br />

to walls and slabs with cadmium plated screws or bolts and lead cinch anchors or expansion bolts and install in<br />

holes drilled with proper size masonry drill. Properly size anchors in accordance with manufacturer's<br />

recommendations for load to be supported.<br />

G. Torque all conductor connection terminations including those in EDC to manufacturer's recommended values.<br />

Inspect panelboards for physical damage, proper alignment, anchorage, and grounding. Check proper installation<br />

and tightness of connections for circuit breakers, fusible switches, and fuses.<br />

3.2 GROUNDING<br />

A. General: Ground all metallic conduits, supports, cabinets, equipment, system neutrals, metal building structures,<br />

and other items required to be grounded in accordance with the NEC and other applicable codes and as indicated<br />

on drawings.<br />

B. Equipment Grounding:<br />

1. Make conduits electrically continuous using proper fittings, connections, grounding bushings, etc.<br />

2. Where Galvanized Rigid Metal Conduit (GRC) penetrates the grade outdoors or penetrates the slab, install<br />

insulating grounding bushings.<br />

3. Install an insulated equipment ground wire as shown on drawings.<br />

C. Metal Underground Cold Water Pipe: Connect to electrical system if available and permitted by local codes.<br />

Install jumpers around water meters, valves, or other devices which might cause an interruption of continuity<br />

during service.<br />

D. Concrete Encased Electrodes: Where indicated on the Drawings, furnish and install electrodes, jumpers, and<br />

approved fittings in accordance with Grounding Electrode Detail .<br />

E. Ground Rods: If ground rods are required, install two 5/8 inch minimum diameter Copperweld rods driven<br />

vertically not less than 12 feet apart and each with 8 feet of length in contact with the soil.<br />

3.3 TESTING<br />

A. Upon completion of installation, perform continuity tests on power and equipment branch circuit conductors.<br />

Inspect wire and cable for physical damage. Verify proper phasing connections.<br />

B. Measure ground resistance from system neutral connection at service entrance to convenient ground point on<br />

building water pipe using suitable ground testing equipment.<br />

16050 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


C. Test receptacles with circuit tester to ensure proper polarity, grounding, and continuity of circuits.<br />

D. Load test GFCI receptacles.<br />

END OF SECTION<br />

16050 - 3<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


BLANK PAGE<br />

16050 - 4<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 022511<br />

SECTION 16100 (26 0500) - WIRING METHODS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Wire and Cable.<br />

2. Conduit.<br />

3. Outlet boxes and Conduit Fittings.<br />

4. Nonmetallic Floor Boxes.<br />

5. Wiring Devices.<br />

6. Wire Connectors.<br />

7. Fire Alarm/Security Alarm System Rough-In.<br />

8. Cable Trays.<br />

B. Related Requirements:<br />

1. Section 13810 - Energy Management System (EMS).<br />

2. Section 16050 - Basic Electrical Materials and Methods: Hangers and Supports.<br />

3. Section 16405 - Electrical Distribution Centers.<br />

4. Section 16452 - Track Busway System.<br />

5. Section 16500 - Lighting.<br />

6. Section 16700 - Communication.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. National Fire Protection Association (NFPA):<br />

1. NFPA 70 - National Electrical Code (NEC).<br />

C. National Electrical Manufacturers Association (NEMA):<br />

1. NEMA VE 1 – Metal Cable Tray Systems.<br />

D. ASTM International (ASTM):<br />

1. ASTM D 698 - Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ftlbf/ft).<br />

2. ASTM D 1557 - Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ftbf/ft3).<br />

E. Underwriters Laboratories (UL):<br />

1. UL 1569 - Metal Clad Cables.<br />

1.3 QUALITY ASSURANCE<br />

A. Final Power Plan Review Meeting:<br />

1. A Final Power Plan Review Meeting shall be held on-site to review the Final Power Plan and<br />

scheduling requirements. The mandatory attendees shall be the Construction Manager, General<br />

Contractor, Electrical Contractor, Security Services Representative, CCTV Representative, and<br />

Store Planning Field Manager. The meeting shall be scheduled by the General Contractor<br />

approximately 14 days after receipt of Final Power Plan Drawings. At least ten days advance<br />

notification shall be given to all attendees.<br />

16100 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


2. The purpose of the meeting will be to review the Final Power Plan requirements and to schedule<br />

completion dates for various critical components of the Final Power Plan.<br />

3. The Construction Manager will review the PCOB and EWA process at this meeting, as it applies<br />

to the Final Power Plan requirements.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner will furnish and install fire and security alarm system. Contractor shall<br />

provide rough-in as specified herein.<br />

2.2 WIRE AND CABLE<br />

A. Electrical Components and Devices: Listed and labeled as defined in NFPA 70, Article 100, by a nationally<br />

recognized testing agency and marked for use.<br />

B. Wire and cable shall bear UL label and shall conform to standards established for such materials by nationally<br />

recognized agencies.<br />

C. Provide code gauge, soft annealed copper wire, not less than 98 percent conductivity and of 600 volt class.<br />

D. Aluminum Alloy Conductors: Compact, stranded Stabiloy AA-8000 series. Aluminum alloy conductors may be<br />

used at Contractor’s option where permitted by local utility company and Authority Having Jurisdiction unless<br />

otherwise noted on drawings. Limit use of aluminum alloy conductors to service entrance and feeder conductors<br />

#6 AWG and larger.<br />

E. Conductors:<br />

1. Insulation type shall be one of the following:<br />

a. THHN<br />

b. THWN<br />

c. XHHW<br />

d. XHHW-2<br />

2. Type:<br />

a. #10 and smaller – stranded or solid.<br />

b. #8 and larger - stranded<br />

F. Interlocked Armor Metal Clad (MC) Cable: Contractor's option as allowed by Authorities Having Jurisdiction.<br />

MC cable shall have the following characteristics:<br />

1. Aluminum MC-Lite or Standard MC.<br />

2. Minimum size conductor, #12 AWG copper, including green insulated equipment ground, sized in<br />

accordance with the NEC.<br />

3. Overall moisture resistant tape.<br />

4. Galvanized steel or aluminum interlocked cladding.<br />

5. Manufactured in accordance with UL 1569.<br />

G. Wire smaller than #12 AWG not permitted unless otherwise noted. #14 AWG, type MTW or TFF permitted for<br />

signal and pilot control circuits unless otherwise noted.<br />

H. Color code:<br />

SYSTEM NEUTRAL<br />

VOLTAGE COLOR<br />

PHASE<br />

240/120V White A-black<br />

B-red<br />

GROUND<br />

green<br />

ISOLATED<br />

GROUND<br />

green W/ yellow tracer<br />

16100 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


208/120V white A-black<br />

B-red<br />

C-blue<br />

green<br />

green W/ yellow tracer<br />

480/277V Light gray or white with colored<br />

stripe other than yellow<br />

A-brown<br />

B-orange<br />

C-yellow<br />

green<br />

green W/ yellow tracer<br />

I. Color code #8 AWG and smaller phase and neutral conductors by continuous outer covering. Conductors #6 AWG<br />

and larger may be color coded by tape. Tape shall have minimum of two complete wraps around conductor at 6<br />

inches from terminations, splices, and junction points.<br />

J. Identify circuit numbers with synthetic cloth or plastic labels at splice and junction points.<br />

2.3 CONDUIT<br />

A. Conduit types shall be as follows and shall bear UL or ETL label:<br />

1. Galvanized Rigid Metal Conduit (GRC): Hot-dip galvanized.<br />

2. Intermediate Metal Conduit (IMC): Hot-dip galvanized.<br />

3. Electrical Metallic Tubing (EMT): Hot-dip galvanized.<br />

4. Schedule 40 heavy-wall Polyvinyl Chloride (PVC).<br />

5. Flexible Metal Conduit: Zinc-coated steel or Aluminum.<br />

6. Liquid Tight Flexible Steel Conduit with PVC jacket.<br />

7. MC Cable: Steel or Aluminum Cladding<br />

B. Conduit Sizes: Size conduit in accordance with NEC unless noted otherwise on Drawings, but not less than the<br />

following:<br />

1. Alarm and Data Systems: 3/4 inch.<br />

2. Flexible Metal Conduit: For connection of recessed light fixtures in suspended ceilings, 3/8 inch.<br />

For connection of other equipment subject to vibration: 1/2 inch.<br />

3. Underground Conduit in Parking Lot: 1 inch.<br />

4. Other Uses: 1/2 inch.<br />

2.4 OUTLET BOXES AND CONDUIT FITTINGS<br />

A. Outlet boxes and conduit fittings shall bear UL or ETL label.<br />

B. Boxes: Comply with NEC in regard to maximum allowable number of conductors.<br />

1. Interior Boxes: Hot-dip galvanized, 4 inches minimum octagon or square, unless otherwise noted.<br />

Provide single or multiple gang outlet boxes as required for flush installation in drywall<br />

construction. Provide masonry boxes for outlets installed flush in concrete unit masonry. Provide<br />

single surface-mounted outlet boxes for utility type boxes.<br />

2. Exterior Boxes: Provide masonry boxes for outlets installed flush in concrete unit masonry.<br />

3. Outlet Boxes: Suitable for supporting lighting fixtures if intended for that purpose.<br />

4. Ceiling Fan Boxes: Rated and listed for mounting ceiling fans.<br />

C. Conduit Fittings:<br />

1. Indoor EMT Fittings: Diecast or steel set screw type.<br />

2. Outdoor EMT Fittings: Steel Compression type.<br />

3. Outdoor GRC, IMC, or EMT Box Connectors: Weather-tight hubs.<br />

4. Threadless GRC or IMC Fittings: Not permitted.<br />

5. Indoor GRC or IMC connectors.<br />

6. PVC Fittings: Solvent weld type for PVC conduit.<br />

7. Locknuts and bushings<br />

16100 - 3<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


2.5 NONMETALLIC FLOOR BOXES<br />

Type Hubbell Carlon Wiremold<br />

Floor Box PFB1 E971FB 882C<br />

Brass Cover Plate S3925 w/ S3082 E97BR2 w/ E97ABR2 895<br />

2.6 CABLE TRAY<br />

A. Manufacturers: Complete system by one of the following:<br />

1. Wiremold/Legrand, West Hartford, CT. (877) 295-3472.<br />

2. Chalfant Manufacturing Company, Brunswick, OH. (330) 273-3510.<br />

3. Cablofil/LeGrand E-Z Tray, (618) 566-3230.<br />

B. Description:<br />

1. NEMA VE 1, basket style, wire mesh, or solid bottom cable tray.<br />

2. Material: Steel.<br />

3. Finish: Prime coated.<br />

4. Inside Width: 12 inches.<br />

5. Inside Depth: 4 inches.<br />

6. Manufacturer's standard clamps, hangers, brackets, splice plates, blind ends, barrier strips,<br />

connectors, and grounding straps.<br />

2.7 WIRING DEVICES<br />

A. Branch Circuit Switches: Specification grade rated 20A 120/277V AC as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Single Pole HBL1221GY PS20AC1-GRY 2221GY 1221-2GY<br />

3-Way HBL1223GY PS20AC3-GRY 2223GY 1223-2GY<br />

4-Way HBL1224GY PS20AC4-GRY 2224GY 1224-2GY<br />

Dimmers<br />

Lutron: NT-600-GR<br />

Single Pole<br />

Occupancy Sensor<br />

(Dual Technology)<br />

Double Pole<br />

Occupancy Sensor<br />

(Dual Technology)<br />

AD1277GY1<br />

AD1277GY2<br />

Sensor Switch:<br />

PDT-GY<br />

Sensor Switch:<br />

WSD-PPT-2P-GY<br />

Not Available<br />

Not Available<br />

OSSMT-MD-G<br />

Not Available<br />

B. Receptacles - Straight Blade Nylon Grounding - Type Outlet Devices: Specification grade as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Single Receptacle 20A 125V (5-20R) HBL5361GRY 5361GRY 5361GY 5361-GY<br />

Duplex Receptacle 20A 125V (5-20R) HBL5362GY 5362GRY 5362GY 5362-GY<br />

Duplex Receptacle 20A 125V Isolated IG5362 IG5362 IG5362RN 5362-IG<br />

Ground (5-20R)<br />

GFCI Duplex Receptacle 20A 125V (5- GF20GYLA 2095-GRY VGF20GY 7899-GY<br />

20R)<br />

GFCI Weather Resistant Duplex<br />

GFTR20GY 2095TRWRGR WRVGF20 W7899-GY<br />

Receptacle 20A 125V (5-20R)<br />

Y<br />

GY<br />

Single Receptacle 15A 250V 2 pole 3<br />

Wire Grounded (6-15R)<br />

HBL5661I 5671-I 5661V 5661-I<br />

16100 - 4<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


Single Receptacle 20A 250V 2 pole 3<br />

Wire Grounded (6-20R)<br />

Single Receptacle 30A 250V 2 pole 3<br />

Wire Grounded (6-30R)<br />

Single Receptacle 20A 125/250V 3 pole 4<br />

Wire Grounded (14-20R)<br />

Single Receptacle 30A 125/250V 3 pole 4<br />

Wire Grounded (14-30R)<br />

Single Receptacle 20A 3 Phase 250V 3<br />

pole 4 Wire Grounded (15-20R)<br />

Single Receptacle 30A 3 Phase 250V 3<br />

pole 4 Wire Grounded (15-30R)<br />

Single Receptacle 50A 3 Phase 250V 3<br />

pole 4 Wire Grounded (15-50R)<br />

HBL5461I 5871I 5461GY 5461-GY<br />

HBL9330 3801 5700N 5372<br />

HBL8410 3820 5759 Not Available<br />

HBL9430A 3864 5744N 278<br />

HBL8420 Not Available Not Not Available<br />

Available<br />

HBL8430A 5740 8430N 8430<br />

HBL8450A 5750 8450N 8450<br />

C. Receptacles - Locking Nylon Grounding - Type Outlet Devices: Specification grade as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Single Locking Receptacle 15A 125V<br />

(L5-15R)<br />

Single Locking Receptacle 15A 125V<br />

Isolated Ground (L5-15R)<br />

Duplex Locking Receptacle 15A 125V<br />

(L5-15R)<br />

Duplex Locking Receptacle 15A 125V<br />

Isolated Ground (L5-15R)<br />

Single Locking Receptacle 20A 125V<br />

(L5-20R)<br />

Single Locking Receptacle 20A 125V<br />

Isolated Ground (L5-20R)<br />

Single Locking Receptacle 30A 125V<br />

(L5-30R)<br />

Single Locking Receptacle 30A 125V<br />

Isolated Ground (L5-30R)<br />

Single Locking Receptacle 20A 250V 2<br />

Pole 3 Wire Grounded (L6-20R)<br />

Single Locking Receptacle 30A 250V 2<br />

Pole 3 Wire Grounded (L6-30R)<br />

Single Locking Receptacle 30A 250V 2<br />

Pole 3 Wire Isolated Ground (L6-30R)<br />

Single Locking Receptacle 20A 125/250V<br />

3 pole 4 Wire Grounded (L14-20R)<br />

Single Locking Receptacle 30A 125/250V<br />

3 pole 4 Wire Grounded (L14-30R)<br />

Single Locking Receptacle 50A 600V 2<br />

pole 3 Wire Grounded (Non-Nema)<br />

Single Locking Receptacle 50A 125/250V<br />

3 pole 4 Wire Grounded (Non-Nema)<br />

HBL4710 4710 CWL515R 4710<br />

IG4710 IG4710 IGL515R 4710-IG<br />

HBL4700I 4700 4700 4700<br />

IG4700A IG4700 IG4700 4700-IG<br />

HBL2310 L520-R CWL520R 2310<br />

IG2310 IGL520-R IGL520R 2310-IG<br />

HBL2610 L530-R CWL530R 2610<br />

IG2610 IGL530-R IGL530R 2610-IG<br />

HBL2320 L620-R CWL620R 2320<br />

HBL2620 L630-R CWL630R 2620<br />

IG2620 IGL630-R IGL630R 2620-IG<br />

HBL2410 L1420-R CWL1420R 2410<br />

HBL2710 L1430-R CWL1430R 2710<br />

HBL3771 3771 3771 3771<br />

CS6369 CS6369 CS6369 CS63-69<br />

D. Connectors - Cord Mounted Locking Nylon Grounding - Type to match Plugs as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Locking Connector 15A 125V (L5-15R) HBL4729C PSL515-C 4731N 4729-C<br />

Locking Connector 20A 125V (L5-20R) HBL2313 L520-C CWL520C 2313<br />

16100 - 5<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


Locking Connector 20A 3 Phase 250V 3<br />

Pole 4 Wire Grounded (L15-20R)<br />

HBL2423 L1520-C CWL1520C 2423<br />

E. Connectors - Cord Mounted Corrosion Resistant Locking Nylon Grounding - Type to match Plugs as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Corrosion Resistant Locking Connector<br />

20A 125V (L5-20R)<br />

Corrosion Resistant Locking Connector<br />

20A 125/250V 3 Pole 4 Wire Grounded<br />

(L14-20R)<br />

Corrosion Resistant Locking Connector<br />

20A 3 Phase 250V 3 Pole 4 Wire<br />

Grounded (L15-20R)<br />

Corrosion Resistant Locking Connector<br />

30A 3 Phase 120/208V 4 Pole 5 Wire<br />

Grounded (L21-30R)<br />

HBL23CM13 CRL520-C CRL520C 23CM-13<br />

HBL24CM13 CRL1420-C CRL1420C Not Available<br />

HBL24CM23 Not Available CRL1520C Not Available<br />

HBL28CM13 Not Available Not<br />

Available<br />

F. Plugs - Cord Mounted Nylon Grounding - Type to match Outlet Devices as follows:<br />

Not Available<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Plug 20A 125V 2 Pole 3 Wire Grounded<br />

(5-20P)<br />

Plug 20A 250V 2 Pole 3 Wire Grounded<br />

(6-20P<br />

Plug 20A 3 Phase 250V 3 Pole 4 Wire<br />

Grounded (15-20P)<br />

Plug 30A 3 Phase 250V 3 Pole 4 Wire<br />

Grounded (15-30P)<br />

Plug 50A 3 Phase 250V 3 Pole 4 Wire<br />

Grounded (15-50P)<br />

HBL5366CA PS5366SSAN 5366AN 5366-CA<br />

HBL5466CA PS5466SSAN 5466AN 5466-CA<br />

HBL8421C Not Available Not Not Available<br />

Available<br />

HBL8432C 5741-AN 8432AN 8432-P<br />

HBL8452C 5751-AN 8452AN 8452-P<br />

G. Plugs - Cord Mounted Locking Nylon Grounding - Type to match Outlet Devices as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Locking Plug 15A 125V 2 Pole 3 Wire<br />

Grounded (L5-15P)<br />

Locking Plug 20A 250V 2 Pole 3 Wire<br />

Grounded (L6-20P)<br />

Locking Plug 30A 250V 2 Pole 3 Wire<br />

Grounded (L6-30P)<br />

Locking Plug 20A 3 Phase 250V 3 Pole 4<br />

Wire Grounded (L15-20P)<br />

HBL4720C PSL515-P 4721N 4720-C<br />

HBL2321 L620-P CWL620P 2321<br />

HBL2621 L630-P CWL630P 2621<br />

HBL2421 L1520-P CWL1520P 2421<br />

H. Plugs - Cord Mounted Corrosion Resistant Locking Nylon Grounding - Type to match Outlet Devices as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Corrosion Resistant Locking Plug 20A<br />

125V 2 Pole 3 Wire Grounded (L5-20P)<br />

Corrosion Resistant Locking Plug 20A<br />

125/250V 3 Pole 4 Wire Grounded (L14-<br />

20P)<br />

HBL23CM11 CRL520-P CRL520P 23CM-11<br />

HBL24CM11 CRL1420-P CRL1420P Not Available<br />

16100 - 6<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


Corrosion Resistant Locking Plug 20A 3<br />

Phase 250V 3 Pole 4 Wire Grounded<br />

(L15-20P)<br />

Corrosion Resistant Locking Plug 30A 3<br />

Phase 120/208V 4 Pole 5 Wire Grounded<br />

(L21-30P)<br />

HBL24CM21 Not Available CRL1520P Not Available<br />

HBL28CM11 Not Available Not<br />

Available<br />

Not Available<br />

I. Pin & Sleeve - Insulated Water Tight - Type Outlet Devices: Specification grade as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Water Tight Receptacle 30A 250V 2 Pole<br />

3 Wire Grounded (Non-Nema)<br />

Water Tight Receptacle 60A 250V 2 Pole<br />

3 Wire Grounded (Non-Nema)<br />

HBL330R6W PS330R6W CD330R6W 330R6W<br />

HBL360R6W PS360R6W CD360R6W 360R6W<br />

J. Boots: Weatherproof Boots for Locking Plug and Connector Bodies - Type to match Devices as follows:<br />

Type Hubbell Pass & Seymour Cooper Leviton<br />

Corrosion Resistant Boots for Locking<br />

Plug and Connector 20/30A 125V (L5-<br />

20)<br />

Corrosion Resistant Boots for Locking<br />

Plug and Connector 20/30A 125/250V 3<br />

Pole 4 Wire Grounded (L14-20)<br />

Corrosion Resistant Boots for Locking<br />

Plug and Connector 20/30A 3 Phase 250V<br />

3 Pole 4 Wire Grounded (L15-20)<br />

Corrosion Resistant Boots for Locking<br />

Plug and Connector 30A 3 Phase<br />

120/208V 4 Pole 5 Wire Grounded (L21-<br />

30)<br />

HBL60CM31<br />

&<br />

HBL60CM32<br />

HBL60CM35<br />

&<br />

HBL60CM36<br />

HBL60CM35<br />

&<br />

HBL60CM36<br />

HBL60CM35<br />

&<br />

HBL60CM36<br />

CRL2030-RBP<br />

& CRL2030-<br />

RBC<br />

CRL2030-RBP<br />

& CRL2030-<br />

RBC<br />

CRL2030-RBP<br />

& CRL2030-<br />

RBC<br />

CRL2030-RBP<br />

& CRL2030-<br />

RBC<br />

BM1 &<br />

BM2<br />

6031-Y & 6032-Y<br />

BL1 & BL2 6033-Y & 6034-Y<br />

BL1 & BL2 6033-Y & 6034-Y<br />

BL1 & BL2 6033-Y & 6034-Y<br />

K. Cover Plates:<br />

1. Nylon cover plates for flush mounted devices.<br />

2. Galvanized steel plates where devices are installed on exposed fittings or boxes.<br />

3. 302 stainless steel cover plates for recessed outlet boxes in masonry walls.<br />

4. Blank cover plate on all boxes without device.<br />

Type<br />

Thomas &<br />

Pass &<br />

Hubbell Intermatic<br />

Betts<br />

Seymour<br />

Single gang GFCI duplex receptacle, weatherproof,<br />

while-in-use, lockable vertical metallic cover plate<br />

Red Dot<br />

CKMUV<br />

WP26M WP1010MC WIUC10CA<br />

GV<br />

Single gang GFCI duplex receptacle, weatherproof, Red Dot WP26MH WP1010HM WIUC10CA<br />

while-in-use, lockable horizontal metallic cover plate<br />

Single gang deep box twistlock receptacle,<br />

weatherproof, while-in-use, lockable vertical metallic<br />

cover plate<br />

Double gang two GFCI duplex receptacles,<br />

weatherproof, while-in-use, lockable vertical metallic<br />

cover plate<br />

CKMU<br />

Red Dot<br />

CKLSVL<br />

Red Dot 2CKU<br />

WP7D<br />

Not<br />

Available<br />

C<br />

Not<br />

Available<br />

WP1030MC<br />

L. Colors:<br />

1. Unless otherwise noted, wiring devices and cover plates shall be gray nylon.<br />

2. Blank Cover Plates: On boxes without devices or fixtures, provide same type and color as those<br />

installed on devices in the same room or area.<br />

GH<br />

Not<br />

Available<br />

Not<br />

Available<br />

16100 - 7<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


3. Isolated ground receptacles: Orange nylon cover plates with panelboard name and circuit number<br />

printed in 3/16 inch black lettering on clear adhesive label (Brady label or equal) adhered to plate.<br />

4. Cover plates for wiring devices mounted in NRP panels shall match the color of NRP panels.<br />

2.8 WIRE CONNECTORS<br />

A. Splices:<br />

1. #8 AWG and Smaller: Ideal Wingnut, 3M Scotchlok, or equal connectors of proper size. 3M No.<br />

567 in-line self-stripping connectors will be permitted only at ballast lead connections in<br />

fluorescent light rows.<br />

2. #6 AWG and Larger: Solderless lugs and connectors.<br />

2.9 FIRE AND SECURITY ALARM SYSTEM ROUGH-IN<br />

A. Electrical Backboard: 4x8 sheets of 3/4-inch plywood as specified in Section 06100 and shown on the drawings.<br />

B. Fire Alarm/Security Alarm System Grounding Conductors: Provide #6 AWG, copper grounding conductor.<br />

C. Fire Alarm/Security Alarm Conduit System: Provide conduit system with pull string and outlet box including<br />

remote conduit to fire pump, control valve supervisory switches (PIV valves) or tank as indicated on Drawings and<br />

outlined below.<br />

1. If shut off valve is located remote from store building, provide 3/4 inch conduit with pull string<br />

from remote location to building entrance location.<br />

2. If pump and pump controls are located remote from store building, provide 2 inch conduit with<br />

pull string from the remote location to building entrance location.<br />

3. If tank and tank indicators are located remote from store building, provide 2 inch conduit with pull<br />

string from remote location to building entrance location.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION – GENERAL<br />

A. Installation of all products and equipment specified herein shall be by the Contractor.<br />

B. Install specified materials in accordance with manufacturer's recommendations.<br />

C. Where switches are ganged, provide permanently installed steel barriers between switches or provide separate<br />

boxes and separate coverplates for each circuit.<br />

D. Access to Equipment: Coordinate access doors to allow for easy access of equipment for repair and maintenance.<br />

E. Trenching: Perform trenching and backfilling as specified in Section 02300. Maintain 7.5 inch center to center<br />

horizontal and vertical spacing at service entrance conduits.<br />

F. Aluminum Alloy Conductors: Aluminum alloy conductors may be used at Contractor’s option where permitted by<br />

local utility company and Authorities Having Jurisdiction. Limit use of aluminum conductors to service entrance<br />

and feeders to #6 AWG and larger. Splices in service entrance and feeders will not be permitted. Utilize oxidation<br />

inhibiting compound (Penetrox, De-ox) at conductor terminations.<br />

3.2 HANGERS AND SUPPORTS<br />

A. Hangers and Supports are specified in Section 16050.<br />

3.3 WIRE<br />

A. Tie wrap groups of conductors in switchboards and panel boards.<br />

16100 - 8<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


3.4 CONDUIT<br />

A. Installation:<br />

1. Install conduit concealed, except in unfinished areas and where indicated on Drawings.<br />

2. Support conduit by means of specified hangers.<br />

3. Clean PVC conduit per manufacturer's recommendations before application of solvent cement.<br />

4. Coordinate flashings where conduit penetrates roof membrane.<br />

5. Paint metallic conduit under concrete slab or where installed in contact with earth. Apply two 6<br />

mil coats of PVC or Asphalt paint continuously along entire length of conduit prior to installation<br />

below grade. Do not run conduit in concrete slab.<br />

6. Install flexible metal conduit or liquid tight flexible metal conduit for final connections to dry-type<br />

transformers, baler, air compressors, HVAC equipment, motors and other vibrating equipment.<br />

7. Coordinate installation of conduit in masonry work.<br />

8. Do not install conduit under slab unless indicated on Drawings. Conduit installed below slab shall<br />

be galvanized rigid metal (GRC), intermediate metal conduit (IMC), or Schedule 40 PVC.<br />

9. Route above grade conduit parallel or perpendicular to building lines.<br />

10. Maintain minimum of 6 inches clearance at flues and heat sources.<br />

11. Install double locknut and bushings when terminating GRC or IMC conduit, except where conduit<br />

terminates in threaded hub.<br />

12. Install insulated throat bushings on all PVC conduit runs.<br />

B. Location:<br />

1. Galvanized Rigid Metal Conduit (GRC): Permitted for general exposed or concealed work above<br />

or below grade.<br />

2. Intermediate Metal Conduit (IMC): Permitted for general exposed or concealed work above or<br />

below grade.<br />

3. Electrical Metallic Tubing (EMT): Permitted for general exposed or concealed work above grade.<br />

4. Polyvinyl Chloride Rigid Nonmetallic Conduit (PVC) Unless Noted Otherwise on Drawings:<br />

Permitted for below-grade use when permitted by local governing codes.<br />

5. Flexible Metal Conduit: Permitted in attic spaces and exposed in lengths of 6 feet or less for<br />

connections to equipment in dry areas. Not permitted for general exposed or concealed work. For<br />

connection of recessed light fixtures in suspended ceilings and connection of other equipment<br />

subject to vibration.<br />

6. Liquid tight Flexible Metal Conduit: Permitted exposed in lengths of 6 feet or less for connections<br />

to food service equipment, refrigeration equipment and other vibrating equipment in damp<br />

locations where rigid connections are not suitable unless otherwise indicated on Drawings.<br />

7. MC Cable: Permitted only where concealed inside partitions and above finished ceilings. Cable<br />

exposed on walls or in open bar joist areas will not be permitted. Cut cable with manufacturer's<br />

recommended armor stripping tool. Provide manufacturers approved connectors.<br />

3.5 WIRING DEVICES<br />

A. Replace outlets or devices improperly located or installed. Set outlets and devices plumb or horizontal and extend<br />

to, but not project above, finished surface.<br />

B. Unless otherwise noted, receptacles, switches, and other wiring devices shall not be mounted back-to-back.<br />

C. Install receptacles so that the ground prong is in the down position.<br />

3.6 CABLE TRAYS<br />

A. Install in accordance with manufacturer's instructions and NEMA VE 1.<br />

B. Provide supports at each connection point, flat elbows, vertical transitions, at the end of each run, and at other<br />

points to maintain spacing between supports of 10 feet maximum.<br />

16100 - 9<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


3.7 WIRE CONNECTIONS<br />

A. Make final connection of motors, starters, disconnects, and other items furnished under other Sections.<br />

3.8 FIRE AND SECURITY ALARM SYSTEM ROUGH-IN<br />

A. Install fire alarm/security alarm conduit system, raceways, 120 volt supply connections, and fire alarm grounding<br />

conductor.<br />

B. Install Fire Alarm/Security Alarm systems on plywood backboard located as shown on drawings.<br />

C. Fire Alarm/Security Alarm System Grounding Conductors: Install from fire/security service equipment to<br />

electrical service grounding electrode system or dry type transformer grounding electrode system.<br />

3.9 PROTECTION<br />

A. Protect installed products from damage until completion of construction operations.<br />

END OF SECTION<br />

16100 - 10<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 032610<br />

SECTION 16265 (26 3353) - STATIC UNINTERRUPTIBLE POWER SUPPLY<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Wal-Mart furnished uninterruptible power supply (UPS) and UPS maintenance bypass cabinet for installation<br />

by Contractor.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

2. Section 16100 – Wiring Methods: Wiring and electrical accessories including boxes and conduit not furnished<br />

by UPS supplier.<br />

1.2 ADMINISTRATIVE REQUIREMENTS<br />

A. Conform to Contractor Milestone work scheduling as shown on Drawings.<br />

B. UPS System Supplier will deliver equipment to Site for Contractor to receive in accordance with delivery date<br />

specified in Section 01640. Wal-Mart will revise delivery date for products if delivery date does not conform to<br />

Contractor construction scheduling. Contact Wal-Mart Asset Administration (479) 277-3167 to schedule delivery<br />

date.<br />

1.3 DELIVERY, STORAGE, AND HANDLING<br />

A. Handle, store, and protect products in compliance with the requirements of Section 01600 and manufacturer’s recommendations.<br />

B. Equipment Packaging: UPS equipment will be packaged in a crate and palletized, each pallet weighing approximately<br />

870 pounds.<br />

C. Acceptance at Site: Receive equipment as specified in Section 01640. Place pallets in final location as indicated<br />

on Drawings. Do not uncrate UPS system and maintenance bypass cabinet. Uncrating and inspection for damage<br />

will be performed by Wal-Mart prior to installation.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Wal-Mart's UPS system supplier will furnish UPS equipment specified herein<br />

and shown on Drawings for installation by Contractor.<br />

B. Descriptions and specifications of Owner furnished items and equipment hereinafter are included as information to<br />

Contractor only and not to be considered as Contractor requirements unless otherwise stated.<br />

2.2 UPS EQUIPMENT (WAL-MART FURNISHED)<br />

A. UPS System and Maintenance Bypass cabinet will be as shown on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION (BY CONTRACTOR)<br />

16265 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


A. Install UPS system and UPS maintenance bypass cabinet in accordance with manufacturer’s instructions and as<br />

shown on Drawings.<br />

B. Install grounding as shown on Drawings after UPS is set in place and inspected by Wal-Mart Construction Manager.<br />

C. Provide backing materials as required for secure installation of UPS maintenance bypass cabinet.<br />

D. Install associated boxes, conduit, and wiring not furnished by Wal-Mart in accordance with Section 16100.<br />

END OF SECTION<br />

16265 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 103009<br />

SECTION 16405 (26 2600) - ELECTRICAL DISTRIBUTION CENTER<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Pre-Manufactured Electrical Distribution Center.<br />

B. Related Requirements:<br />

1. Section 01500 - Temporary Facilities and Controls: Coordinate installation of foundations and floor slab<br />

preparations for early installation of EDC unit(s). EDC unit is designed for early use in the project and is<br />

intended for use as temporary power.<br />

2. Section 01640 - Owner Furnished Products General procedures related to Owner furnished products.<br />

3. Section 03312 - Cast-In-Place Concrete Slabs: Early preparation of concrete base(s) for setting of EDC<br />

prior to laying of CMU walls.<br />

4. Section 13425 – Sub-Metering Instrumentation: Coordinate and contract sub-metering installation with<br />

approved list of Sub-Meter System Contractors.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

A. National Fire Protection Association (NFPA)<br />

1. NFPA 70 - National Electrical Code (NEC)<br />

1.3 SYSTEM DESCRIPTION<br />

A. EDC unit is manufactured complete as follows:<br />

1. Switchboard.<br />

2. Panelboards.<br />

3. Dry type, step-down transformers.<br />

4. Grounding conductors from each transformer to ground chase through the floor of EDC, with sufficient<br />

length of conductor for field connection to grounding electrode.<br />

5. Plywood mounting boards, stenciled and pre-wired for telephone, alarm, energy management, and intercom<br />

equipment.<br />

6. Service outlets, general and emergency illumination.<br />

7. Detachable lift connections.<br />

8. All power and control wiring that originates and terminates between components within EDC room<br />

B. Electrical Distribution Centers will be listed by ETL Laboratories or Underwriters Laboratories as complete<br />

assembly and will bear appropriate label showing that listing.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Obtain manufacturer's information drawings, rigging diagrams, and equipment specifications to assure that<br />

Electrical Distribution Centers will be received, installed and connected to provide complete installation of system<br />

with no damage to components or adjacent work.<br />

B. Electrical Distribution Centers are manufactured and delivered as weatherproof units. Maintain units in<br />

weatherproof condition until building is enclosed, then remove weatherproof roof and door packaging.<br />

C. Owner's Electrical Distribution Center (EDC) supplier will provide rigging drawings, templates, and instructions<br />

16405 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


for installation of EDC.<br />

1.5 SEQUENCING AND SCHEDULING<br />

A. The responsibility of Work under this Section includes, but is not limited to, the following:<br />

1. Contact EDC manufacturer to coordinate and schedule delivery to site.<br />

2. Early preparation of EDC shall include the following:<br />

a. Installation and preparation of structural support for EDC Unit.<br />

b. Grounding requirements for EDC Unit.<br />

c. Receipt and placement of EDC Unit within building structure.<br />

3. Place EDC unit in full operation.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Wal-Mart’s supplier will furnish the following for installation by the<br />

Contractor.<br />

B. Descriptions and related provisions of products by supplier as specified herein are included as requirements by the<br />

supplier of equipment to be furnished by the Owner or Wal-Mart and are included as information only to the<br />

Contractor.<br />

1. Electrical Distribution Center (EDC): Pre-manufactured electrical distribution center.<br />

2. Remote panelboards, transformers, enclosed circuit breakers, and related equipment as indicated on<br />

Drawings.<br />

2.2 PRE-MANUFACTURED ELECTRICAL DISTRIBUTION CENTER<br />

A. Owner-Furnished EDC, by PCX Corporation. Contact: Walmart Account Executive (866) 564-6454<br />

Walmart@PCXCorp.com<br />

PART 3 EXECUTION<br />

3.1 EXAMINATION<br />

A. Examine surfaces and adjacent areas in which Work under this Section is to be performed. Report in writing to<br />

Wal-Mart Construction Manager prevailing conditions that may adversely affect satisfactory execution of Work.<br />

Do not proceed with Work until unsatisfactory conditions have been corrected.<br />

3.2 PREPARATION<br />

A. Ensure that concrete encased grounding electrodes have been provided and coordinated with EDC installation.<br />

B. Structure: Set EDC on prepared base, plumb and level, in strict accordance with manufacturer's instructions at<br />

location(s) indicated on Drawings. Secure in place in accordance with manufacturer's instruction.<br />

3.3 INSTALLATION<br />

A. Contractor shall provide the following installation:<br />

1. Check terminations and re-torque per manufacturer's instructions.<br />

2. Installation and termination of electrical service entrance.<br />

3. Installation and termination of "Field Installed" feeder wiring as indicated on Drawings.<br />

4. Installation and termination of branch circuit wiring including power, lighting and other controlled load<br />

circuits.<br />

5. Installation of grounding electrodes and grounding electrode conductors as indicated on Drawings.<br />

6. Terminate grounding electrode and equipment grounding conductors to grounding electrode(s).<br />

16405 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


7. Remove temporary roof skin after building is enclosed and weatherproof cover is no longer necessary.<br />

3.4 ELECTRICAL SERVICE<br />

A. Perform Work in strict compliance with the local utility's requirements.<br />

END OF SECTION<br />

16405 - 3<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


BLANK PAGE<br />

16405 - 4<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 022610<br />

SECTION 16410 (26 2817) - ENCLOSED SWITCHES AND CIRCUIT BREAKERS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Safety disconnect switches.<br />

B. Related Requirements:<br />

1. Section 16100 - Wiring Methods.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. National Electrical Manufacturers Association (NEMA)<br />

1. NEMA 250 – Enclosures for Electrical Equipment (1000 volts maximum).<br />

PART 2 - PRODUCTS<br />

2.1 SAFETY SWITCHES<br />

A. Switch Interior:<br />

1. Dead-front construction with hinged arc suppressor and switch blades which are fully visible in the off<br />

position and with door open.<br />

B. Switch Mechanism:<br />

1. Quick-make and quick-break operating handle and mechanism with a delete dual cover interlock to prevent<br />

unauthorized opening of the switch door in the "on" position or closing the switch mechanism while the<br />

door is open.<br />

2. Provide electrical interlock switch to de-energize control wiring as required.<br />

3. Line and load terminals of the device rated 100 amperes or less shall be rated for 75 degrees C.<br />

4. Provide operating handle with provisions for installation of a padlock in "off" or "on" positions.<br />

C. Ratings:<br />

1. Switches horsepower rated for 600 volts, 60 Hz, heavy-duty type.<br />

2. Where switches are indicated to be fused, furnish with provisions for fuses.<br />

D. Enclosures:<br />

1. NEMA 1, code gauge sheet steel with hinged cover, except where exposed to weather.<br />

2. If exposed to weather, provide NEMA 3R enclosure.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install motor and circuit disconnect in accordance with manufacturer's recommendations. Applicable Codes shall<br />

take precedence over drawing details.<br />

B. Provide properly sized grounding lug and terminations for all safety switches.<br />

END OF SECTION<br />

16410 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


BLANK PAGE<br />

16410 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 052810<br />

SECTION 16452 – TRACK BUSWAY SYSTEMS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished track busway systems.<br />

B. Related Sections:<br />

1. Section 01640 - Owner Furnished Products. General procedures related to Owner furnished products.<br />

2. Section 16050 - Basic Electrical Materials and Methods.<br />

1.2 REFERENCES<br />

A. The publications listed below form a part of this specification to the extent referenced. Publications are referenced<br />

within the text by the basic designation only.<br />

B. Underwriters Laboratories (UL):<br />

1. UL 857 – Busways.<br />

C. National Electrical Manufacturers Association (NEMA):<br />

1. NEMA AB1 - Molded Case Circuit Breakers and Molded Case Switches.<br />

1.3 QUALITY ASSURANCE<br />

A. Track busway and electrical components will bear a UL Label.<br />

1.4 DELIVERY, STORAGE, AND HANDLING<br />

A. Storage and Protection: Provide proper facilities for handling and storage of materials to prevent damage to edges,<br />

ends, and surfaces. Keep materials dry and protected from weather. Track busway showing signs of rust or<br />

weathering shall be replaced at Contractors expense.<br />

B. Contact vendor at least 4 weeks prior to desired delivery date to arrange for delivery of track busway.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. The track busway system will be furnished by the Owner’s supplier for installation by the Contractor.<br />

2.2 MANUFACTURERS<br />

A. The Owner’s supplier will be as follows:<br />

1. Starline Track Busway - Contact Bruce Henry or Randy Mathews, walmart@megreps.com, (501) 821-6200<br />

or (866) 730-4816.<br />

2.3 TRACK BUSWAY SYSTEM (OWNER FURNISHED)<br />

A. Description and Ratings: The Track Busway System shall be as indicated on the drawings and in accordance with<br />

the following:<br />

1. Voltage Ratings: 300V, 480V or 600V.<br />

2. Frequency: 60 Hz.<br />

16452 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


3. Ampacity: 40A, 50A, 60A, 100A, 160A or 225A.<br />

4. Conductors: Copper, 100% continuous rating at ambient temperatures below 40 degrees C / 104 degrees F,<br />

electrically isolated from the housing.<br />

5. Grounding: Aluminum housing at 100% or optional isolated ground bus.<br />

6. System shall comply with UL 857.<br />

B. System Designations:<br />

Frame Size<br />

Track<br />

Busway<br />

Type<br />

Amperage<br />

Neutral<br />

Amps<br />

Voltage<br />

Rating<br />

Poles Iso Ground lbs/ft<br />

Standard<br />

AIC<br />

Small B40 40 40 480 2,4 No 1.25 5K<br />

Small B50 50 50 480 2,4 No 1.25 5K<br />

Small B60C 60 60 480 2,4 No 1.25 5K<br />

Medium B60 60 60 300 & 2,4 No 1.25 10K<br />

600*<br />

Medium B100C 100 100 600 2,3,4 No 1.75 10K<br />

Large B100A 100 100 600 3,4 No 2.75 22K<br />

Large B100G 100 100 300 & 3,4 Yes 3.25 22K<br />

600*<br />

Large B100NG 100 200 300 & 3,4 Yes 3.25 22K<br />

600*<br />

Large B160 160 160 600 3,4 No 3.25 22K<br />

Large B160G 160 160 300 3,4 Yes 3.25 22K<br />

Large B225 225 225 600 3,4 No 3.25 22K<br />

Large B225G 225 225 300 3,4 Yes 3.25 22K<br />

*Track Busway available in 300 volt rating (used on 120/208V systems) and 480/600 volt rating (used on 277/480V systems)<br />

C. Frame and Enclosure:<br />

1. Extruded aluminum housing acting as 100% ground.<br />

2. Housing lengths shall be 5, 10, or 20 foot standard.<br />

3. Housing shall be slotted to receive mounting hangers for suspension from structure.<br />

4. Housing shall be open on the bottom to accept plug-in units anywhere along its length.<br />

D. Plug-in Units:<br />

1. Units shall be polarized to avoid incorrect installation.<br />

2. Units shall utilize circuit breakers for branch circuit protection, complying with NEMA AB1.<br />

3. Units shall have locking clips or bolt-on tabs to secure units to the busway.<br />

4. Units utilizing drop cords shall be manufactured with cord grips and receptacles as indicated on the<br />

drawings.<br />

5. Units shall have an indicator light mounted to the bottom of the plug-in unit for each circuit breaker. The<br />

indicator light shall light up when the circuit breaker loses power.<br />

6. Units shall have labels indicating circuit description and phasing.<br />

7. Units shall be shipped after final power plans are issued.<br />

E. Provide hardware required for a complete installation such as nuts, bolts, threaded rods, and unistrut channels.<br />

PART 3 EXECUTION<br />

3.1 INSTALLATION (BY CONTRACTOR)<br />

A. Install track busway system in accordance with manufacturer's installation instructions and as indicated on the<br />

drawings.<br />

B. Track busway sections shall be connected in accordance with the manufacturer’s recommendations utilizing<br />

16452 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


connectors furnished by the manufacturer.<br />

C. Install manufacturer furnished end pieces and end caps at the ends of each run and as indicated on the drawings.<br />

END OF SECTION<br />

16452 - 3<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


BLANK PAGE<br />

16452 - 4<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec II 033111<br />

SECTION 16500 (26 5100) - LIGHTING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished lighting fixtures for installation by Contractor.<br />

2. Acrylic lighting panels at pharmacy.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

1.2 QUALITY ASSURANCE<br />

A. Fixtures and their electrical components will bear a UL Label.<br />

1.3 DELIVERY, STORAGE, AND HANDLING<br />

A. Storage and Protection: Provide proper facilities for handling and storage of materials to prevent damage to edges,<br />

ends and surfaces. Keep materials dry, fully protected from weather. Fixtures showing signs of rust or weathering<br />

will be replace at Contractors expense.<br />

B. Contact vendor at least 4 weeks prior to desired delivery date to arrange for delivery of lighting fixtures.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Owner’s Lighting Vendor (hereinafter referred to as “vendor”) will furnish lighting fixtures, lamps, and Protect-A-<br />

Lamp covers, as indicated on Drawings, for installation by Contractor.<br />

2.2 LIGHTING FIXTURES (OWNER FURNISHED, CONTRACTOR INSTALLED)<br />

A. Owner’s Lighting Vendor(s): Lighting fixtures will be supplied by one or more of the following:<br />

1. AcuityBrands Lighting (Lithonia), Conyers, GA, (800) 207-0363, Wal-Mart Team. Ernest.Johnson@AcuityBrands.com<br />

2. CREE Lighting, Morrisville, NC (501) 448-2035, Gloria Lercher.<br />

2.3 ACRYLIC LIGHTING PANEL AT PHARMACY (CONTRACTOR PROVIDED)<br />

A. Acrylic Lighting Panel, Item #1A20084A, prismatic white, 23-3/4 inches x 47-3/4 inches, by Plaskolite, Inc., Colombus,<br />

OH (800) 848-9124.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION<br />

A. Install lighting fixtures, lamps, lighting panels, and connections in accordance with manufacturer's recommendations<br />

and as indicated on Drawings.<br />

B. Coordinate exact mounting location of lighting fixtures with building structure and other trades prior to installation.<br />

Continuous rows shall be installed straight and true.<br />

16500 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


C. Attach fixtures to ceiling grid. Install four to six feet of flexible conduit from recessed fixtures installed in lay-in<br />

ceiling grid systems to outlet boxes supported from building structural system.<br />

D. Verify ceiling and wall details. Install fixtures complete with proper mounting arrangements for ceiling or wall<br />

construction encountered.<br />

E. Where indicated on Drawings, install Protect-A-Lamp covers and caps.<br />

F. Provide additional hardware required to complete installation such as nuts, bolts, threaded rods, and Unistrut<br />

channels.<br />

G. Install acrylic lighting panel as indicated on Drawings.<br />

3.2 MAINTENANCE AND REPLACEMENT DURING CONSTRUCTION<br />

A. Provide material and labor to deep clean lighting fixtures with anti-static cleaning fluid. Replace lamps with building<br />

paint overspray one week prior to possession at Contractor’s expense.<br />

B. Maintain lighting fixtures, ballasts and lamps during construction, possession, and until store Grand Opening. Coordinate<br />

replacement of defective, lost, or damaged equipment with vendor.<br />

C. Owner Responsibility (Including Vendor):<br />

1. Provision for oversupply of 3 percent additional lamps with initial lighting fixture shipment.<br />

2. Costs for replacement for normal failure covered by warranty of any fixture, lamp, or ballast prior to Grand<br />

Opening. Evaluation of abnormally high failure percentage and replacement covered under warranty will<br />

be provided by vendor on site.<br />

3. Costs for replacement of parts damaged during shipment. Charges will be made to shipping carrier or responsible<br />

party.<br />

D. Contractor Responsibility:<br />

1. Coordinate vendor on-site evaluation of abnormal component failures of ballast and lamps over 3 percent<br />

oversupply at least two weeks prior to Grand Opening. Provide labor for routine and normal maintenance<br />

of equipment including troubleshooting and determination of lighting failure.<br />

2. Material and labor costs for replacement of loss, breakage, or other damage due to fault of Contractor including<br />

lamps within the 3 percent initial oversupply.<br />

3. Contact vendor to order replacement parts in time to have all fixtures fully operational prior to Grand<br />

Opening.<br />

E. Replacement Procedure - General:<br />

1. Immediately notify vendor and request replacement of damaged fixtures, ballasts or lamps delivered to the<br />

jobsite.<br />

2. If shipping damage is concealed, notify carrier and vendor within 15 days of acceptance of the freight. Provide<br />

vendor a copy of the written notification sent to the carrier.<br />

3. Use 3 percent lamp oversupply for replacement for any reason prior to Grand Opening. Order additional<br />

lamps only after oversupply is exhausted.<br />

a. Maintain accounting log for disposition of lamp oversupply. Identify on log, the date, location, and<br />

reason for replacement of each lamp used from the oversupply.<br />

b. Retain log for review by vendor and Owner for determination of cost responsibility.<br />

F. Additional Ballast Replacement Procedure:<br />

1. Order replacement ballast from vendor. Request Return Authorization number from vendor to return defective<br />

ballast no later than Grand Opening.<br />

2. Return all defective ballast to vendor. Vendor will arrange pickup and return, including shipping costs, of<br />

defective ballast. Cost for ballast not returned within the specified time frame or returned but not defective<br />

will be automatically charged to Contractor.<br />

16500 - 2<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


END OF SECTION<br />

16500 - 3<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


BLANK PAGE<br />

16500 - 4<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


UniSpec – Civil (Master Site Specifications) 011111<br />

SECTION 16525 (25 5630) - SITE LIGHTING<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Owner furnished exterior site lighting luminaires for installation by Contractor.<br />

2. Owner furnished site lighting poles for installation by Contractor.<br />

3. Site lighting accessories provided by Contractor.<br />

B. Related Requirements:<br />

1. Section 01600 –Product Requirements<br />

2. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

3. Section 02300 - Earthwork: Trenching, backfill, and compaction for utilities.<br />

4. Division 3 - Concrete: Concrete for foundations.<br />

5. Section 16050 - Basic Electrical Materials and Methods: Grounding and bonding.<br />

6. Section 16100 - Wiring Methods: Conduit, wire and cable.<br />

1.2 QUALITY ASSURANCE<br />

A. Fixtures and their electrical components will bear a UL Label.<br />

1.3 DELIVERY, STORAGE AND HANDLING<br />

A. Receive Owner furnished products in compliance with the requirements of Section 01640.<br />

B. Report substantial damage which will require pole replacement immediately to Wal-Mart Construction Manager.<br />

C. Handle, store, and protect products in compliance with the requirements of Section 01600 and manufacturer's recommendations.<br />

D. Do not use cutting instruments (i.e. knives) to remove pole packaging material.<br />

PART 2 - PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Under provisions of Section 01640, Owner’s Site Lighting Vendor (hereinafter referred to as “vendor”) will furnish<br />

lighting fixtures, lamps, and poles, as indicated on Drawings, for installation by Contractor.<br />

2.2 SITE LIGHTING LUMINAIRES (OWNER FURNISHED, CONTRACTOR INSTALLED)<br />

A. Owner’s Lighting Luminaire Vendor(s): Lighting fixtures will be supplied by one or more of the following as selected<br />

by Wal-Mart:<br />

1. Acuity Brands Lighting (Lithonia), Conyers, GA, (800) 207-0363, Wal-Mart Team.<br />

cherryl.bruce@acuitybrands.com.<br />

2. LSI Industries, Cincinnati, OH, (800) 436- 7800, Ext. 3213. Cheri Kieffer.<br />

cheri.kieffer@lsi-industries.com.<br />

3. Visionaire, Rancho Dominguex, CA 90220 (310) 512-6480, Erik Van Wier<br />

evanwier@visionairelighting.com.<br />

4. GE Lighting Solutions, Cleveland, OH (216) 266-4042, John Downing, Walmart_outdoor@ge.com.<br />

2.3 SITE LIGHTING POLE (OWNER FURNISHED, CONTRACTOR INSTALLED)<br />

16525-1<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


A. Owner’s Pole Vendor(s): Poles will be supplied by one or more of the following as selected by Wal-Mart:<br />

1. Acuity Brands Lighting (Lithonia), Conyers, GA, (800) 207-0363, Wal-Mart Team.<br />

cherryl.bruce@acuitybrands.com.<br />

2. LSI Industries, Cincinnati, OH, (800) 436- 7800, Ext. 3213. Cheri Kieffer.<br />

cheri.kieffer@lsi-industries.com<br />

3. Visionaire, Rancho Dominguex, CA 90220 (310) 512-6480, Erik Van Wier<br />

evanwier@visionairelighting.com<br />

2.4 SITE LIGHTING POLE ACCESSORIES (CONTRACTOR FURNISHED, CONTRACTOR INSTALLED)<br />

A. Light Pole Base Pull Box (poles with security cameras): PVC, UL listed, CSA certified, NEMA 4X. Carlon<br />

E1212C24 with E1212DIV field installable divider. In the case of damage, provide Carlon replacement<br />

E1212L24.<br />

B. Light Pole Junction Box (poles with security cameras): NEMA 4, Hoffman A.<br />

C. Paved Area Pull Box: Quazite PG1730BA28 box 17” x 30” x 28” with PG1730HH00.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION BY CONTRACTOR<br />

A. Install Owner and Contractor furnished site lighting products in accordance with manufacturers’ recommendations<br />

and as indicated on Drawings.<br />

B. Apply touch-up paint to site lighting poles.<br />

C. Provide electrical system for site lighting including wiring, conduit and exterior coating GRC bends and elbows<br />

for underground conduit as specified in Section 16100.<br />

D. Comply with the requirements for trenching and backfilling specified in Section 02300.<br />

E. Provide grounding of pole and fixture as indicated on Drawings and as specified in Section 16050.<br />

F. Provide concrete foundations for site lighting poles as specified in Division 3.<br />

3.2 MAINTENANCE AND REPLACEMENT DURING CONSTRUCTION<br />

A. Maintain lighting fixtures, lamps, ballast/drivers and poles during construction, possession, and until store Grand<br />

Opening. Coordinate replacement of defective, lost, or damaged equipment with site lighting vendor.<br />

B. Owner Responsibility:<br />

1. Costs for replacement for normal failure covered by warranty of any fixture, lamp, or ballast/driver prior<br />

to Grand Opening. Evaluation of abnormally high failure percentage and replacement covered under warranty<br />

will be provided by vendor on site.<br />

2. Costs for replacement of parts damaged during shipment. Charges will be made to shipping carrier or responsible<br />

party.<br />

C. Contractor Responsibility:<br />

1. Provide Performance Testing at least four weeks prior to Substantial Completion.<br />

2. Coordinate vendor on-site evaluation of abnormal component failures of ballast/driver and lamps at least<br />

two weeks prior to Substantial Completion. Provide labor for routine and normal maintenance of equipment<br />

including troubleshooting and determination of lighting failure.<br />

3. Provide material and labor for replacement of loss, breakage, or other damage due to fault of Contractor<br />

including lamps.<br />

4. Contact vendor to order replacement parts in time to have fixtures fully operational three weeks prior to<br />

Grand Opening.<br />

16525-2<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


D. Replacement Procedure – General:<br />

1. Immediately notify vendor and request replacement of damaged fixtures, ballast/drivers, or lamps delivered<br />

to the jobsite.<br />

2. If shipping damage is concealed, notify carrier and vendor within 15 days of acceptance of freight. Provide<br />

vendor a copy of the written notification sent to the carrier.<br />

E. Additional Ballast/Driver Replacement Procedure:<br />

1. Order replacement ballast/driver from vendor. Request Return Authorization number from vendor to return<br />

defective ballast/driver no later than Grand Opening.<br />

2. Return all defective ballast/drivers to vendor. Vendor will arrange pickup and return, including shipping<br />

costs, of defective ballast/driver. Cost for ballast/driver not returned within the specific time frame or returned<br />

but not defective will be charged to the Contractor.<br />

3.3 FIELD QUALITY CONTROL BY CONTRACTOR<br />

A. Performance Testing: Conduct parking lot lighting test at least four weeks prior to Substantial Completion consisting<br />

of dusk to dawn operation of luminaires and lamps for 100 hours. Do not energize fixtures during daylight<br />

hours to avoid liability for heat damage to fixtures. Witness and certify continuous operation and time duration of<br />

test. Replace defective components with replacement Owner furnished components in accordance with Section<br />

01640. Reinstall components at least three weeks prior to Grand Opening.<br />

END OF SECTION<br />

Deleted: Anytown, USA<br />

Deleted: -<br />

16525-3<br />

Deleted: 11110000<br />

La Habra, CA – 5641-01 11/07/11


UniSpec II 092509<br />

SECTION 16700 (27 0000) - COMMUNICATIONS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Wal-Mart Furnished and Installed Satellite Dish Equipment.<br />

2. Wal-Mart Furnished and Installed Voice/Data System.<br />

3. Contractor Furnished and Installed Door Buzzer at Truck Dock and Stockroom.<br />

B. Related Requirements:<br />

1. Section 01640 - Owner Furnished Products: General procedures related to Owner furnished products.<br />

2. Section 16100 - Wiring Methods: Outlet boxes and conduit fittings<br />

1.2 SEQUENCING AND SCHEDULING<br />

A. Satellite Dish Milestone Completion Date: Complete installation of conduit, power, and interface work for satellite<br />

dish mounting on or before Delivery date.<br />

B. Voice/Data Milestone Completion Date: Complete installation of Voice/Data/EFP system ground conductor,<br />

Voice/Data/EFP conduit system, and interface work on or before Delivery date.<br />

PART 2 - PRODUCTS<br />

2.1 SATELLITE DISH EQUIPMENT<br />

A. Equipment: Satellite dish equipment will be furnished and installed by Wal-Mart.<br />

B. Cabling: Satellite Dish Communication (IFL) Cable will be furnished, installed, and terminated by Wal-Mart.<br />

C. Contractor shall provide #14 AWG soft iron pull wire or heavy nylon cord in each conduit for pulling satellite cable<br />

to each termination point.<br />

2.2 VOICE/DATA SYSTEM<br />

A. Voice/Data cable equipment will be furnished and installed by Wal-Mart.<br />

2.3 SIGNAL SYSTEMS<br />

A. Contractor shall provide door buzzer at truck dock and stockroom.<br />

B. Provide Hubbell Catalog No. 1281MO momentary switch in flush switch box with Hubbell Cat. No. 1795 weatherproof<br />

cover at truck dock personnel door and Edwards Cat. No. 1065-N5, 120 volt AC buzzer in flush switch<br />

box with Slater Cat. No. S-771N louvered cover plate in Stockroom as indicated on Drawings. Signal system wiring<br />

shall be No. 12AWG unless otherwise indicated on Drawings.<br />

PART 3 - EXECUTION<br />

3.1 CONTRACTOR INSTALLATION REQUIREMENTS<br />

A. Install Voice/Data conduit system, Voice/Data grounding conductor, and signal systems as indicated on Drawings.<br />

16700 - 1<br />

Walmart SC #5641 - La Habra, CA PWO - 04/11/11


B. Install satellite dish electrical conduit, power to satellite dish mounting, and satellite cable conduit system as indicated<br />

on Drawings.<br />

C. Install signal system as indicated on Drawings. Install flush mounted, single gang masonry boxes for mounting of<br />

push buttons and bells in masonry walls.<br />

D. Plywood Mounting Panel: Install as indicated on drawings.<br />

E. Voice/Data System Grounding Conductors: Install #6 AWG, copper grounding conductor from Voice/Data service<br />

equipment to electrical service grounding electrode system or dry type transformer grounding electrode system.<br />

F. Voice/Data Conduit System: Install conduit system as indicated on Drawings, including:<br />

1. Voice/Data service conduit.<br />

2. Other conduits as indicated on Drawings. Install #14 AWG soft iron pull wire or heavy nylon cord in each<br />

conduit for pulling the Voice/Data cable to each termination point.<br />

3. Install outlet boxes conforming to requirements of Section 16100. Include cover plates.<br />

END OF SECTION<br />

16700 - 2<br />