- Page 1 and 2: PYRAMID CONSTRUCTION STAGES
- Page 3 and 4: Pyramid Construction After millenni
- Page 5 and 6: Site preparation for the constructi
- Page 7 and 8: After topping the gravel layer with
- Page 9 and 10: Next test was conducted and the hor
- Page 12 and 13: A few days after completion of the
- Page 14 and 15: It all started with a check on the
- Page 19 and 20: Entrance to the pyramid is on the n
- Page 21 and 22: We then applied a layer of diesel o
- Page 23 and 24: PHASE 3
- Page 25 and 26: First, the reinforcement for the st
- Page 27 and 28: The external and internal forms wil
- Page 29 and 30: Here we see the erection of the ext
- Page 31 and 32: PHASE 4
- Page 33 and 34: On July 28, we started to erect the
- Page 35 and 36: The second stage of the formwork er
- Page 37 and 38: Here the concrete is being poured t
- Page 39 and 40: Here we see the forms for the water
- Page 41 and 42: The middle section of the pyramid h
- Page 43 and 44: The internal chamber - the second f
- Page 45 and 46: On August 23, we started to remove
- Page 47 and 48: PHASE 5
- Page 49 and 50: On the second level of the pyramid
- Page 51 and 52: At this stage of the work the forms
- Page 53 and 54: The form walls of the internal cham
- Page 55 and 56: The forms from the central section
- Page 57 and 58: The conical channel moving from the
- Page 59 and 60: The surface is washed out in prepar
- Page 61 and 62: To the right there is the entrance
- Page 63 and 64: By October 20 the external forms we
- Page 65 and 66: PHASE 6
- Page 67 and 68:
The pyramid continues to grow talle
- Page 69 and 70:
Due to space restrictions, we erect
- Page 71 and 72:
The resonator chambers of the upper
- Page 73 and 74:
In the upper part of the vault of t
- Page 75 and 76:
The cone shaped forms for the well
- Page 77 and 78:
We planned the last phase of concre
- Page 79 and 80:
In the center, there is a square en
- Page 81 and 82:
The cage for the upper chamber was
- Page 83 and 84:
The entrance opening was also prepa
- Page 85 and 86:
Now we will go up the ladder to the
- Page 87 and 88:
Still up the stairs we go to the fo
- Page 89 and 90:
Here it is. This is a special room,
- Page 91 and 92:
PHASE 8
- Page 93 and 94:
As a result of the work with the wa
- Page 95 and 96:
Only by the beginning of June 2008,
- Page 97 and 98:
The wall aligning of the central ch
- Page 99 and 100:
At the same time there were framing
- Page 101 and 102:
They easily and quickly understand
- Page 103 and 104:
There have been a lot of rumors spr
- Page 105 and 106:
Dabbed on the walls inside the pyra
- Page 107 and 108:
The first day of the eastern side a
- Page 109 and 110:
The next stage is the western side
- Page 111 and 112:
The walls of the internal chamber h
- Page 113 and 114:
Along with it, beginning from the u
- Page 115 and 116:
By 11 November 2008 the works on sh
- Page 117 and 118:
Winter and spring 2009 brought us a
- Page 119 and 120:
By the beginning of August 2009 all
- Page 121 and 122:
Further we started the installation
- Page 123 and 124:
The next stage will be the erection
- Page 125 and 126:
The tile laying was started from th
- Page 127 and 128:
The erection of the framing scaffol
- Page 129 and 130:
Along with finishing the works on t
- Page 131 and 132:
On the northern side almost 5 rows
- Page 133 and 134:
The preparations for the pyramidion
- Page 135 and 136:
On October 15 the upper area for th