12.05.2015 Views

Transformer Transportation Damage, A Case Presentation of a Low ...

Transformer Transportation Damage, A Case Presentation of a Low ...

Transformer Transportation Damage, A Case Presentation of a Low ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

DERAILMENT EVENT<br />

<strong>Transportation</strong> <strong>of</strong> the 450 MVA transformer from the factory to the utility’s site required rail shipment given that the<br />

shipping weight was on the order <strong>of</strong> 500,000 lbs. While the transformer was being transferred in a railroad<br />

switching yard, the railcar became derailed. The railcar was traveling at a relatively low speed at the time <strong>of</strong> the<br />

derailment; the derailment event did not turn over the transformer or railcar. The impact recorder on the derailed<br />

railcar recorded the relatively low impacts <strong>of</strong> X: 0.5g, Y: 3.0g and Z: 0.5g. One rail twisted over on its side due to<br />

the weight <strong>of</strong> the transformer and railcar. It was reported that the transformer and railcar traveled the length <strong>of</strong> about<br />

one railcar on the rail ties, see Figure 1. It was believed that riding over the rail ties subjected the transformer to a<br />

short but significant vibration event due to the multiple low level impacts that it experienced [3].<br />

Derailment <strong>of</strong> <strong>Transformer</strong> Railcar during Shipment<br />

Figure 1<br />

There were some external signs <strong>of</strong> possible damage to the transformer but they were not significant. The paint on<br />

some tank end gusset welds had small hairline cracks indicating that the weld joint was overstressed. The paint at<br />

the bottom base plate braces was chipped <strong>of</strong>f indicating contact between the tank base and bracing members.<br />

Neither <strong>of</strong> these was proven to be due to the derailment event and they did not appear to be significant or to indicate<br />

other possible damage. The electrical acceptance testing performed on the transformer upon arrival at the utility’s<br />

site did not indicate any problems with the transformer. SFRA testing was performed and there were no major<br />

problems detected but the results were inconclusive since there was no reference test performed before shipment that<br />

could be used for comparison purposes.<br />

The manufacturer, at this point in time, did not believe that there was damage sustained to the transformer and did<br />

not recommend any further investigation <strong>of</strong> the incident; however, the purchaser arranged for an internal inspection<br />

<strong>of</strong> the transformer before accepting the unit.<br />

INTERNAL INSPECTION<br />

An internal inspection <strong>of</strong> the transformer was performed at the utility’s site before the transformer was removed<br />

from the railcar. The unit was opened up and a dry air supply connected to the tank to help reduce the exposure <strong>of</strong><br />

the cellulose insulation to moisture. The core and coils assembly and mechanical members were inspected. As is<br />

common with many transformers designed in recent years, the internal clearances were tight and limited access at<br />

times during the inspection.<br />

The internal inspection identified signs <strong>of</strong> overall movement <strong>of</strong> the core and coil assembly with respect to the tank.<br />

Tear marks in the pressboard isolation sheets used between the bottom <strong>of</strong> the core clamps and the tank bottom<br />

indicated longitudinal movement <strong>of</strong> the core and coils assembly relative to the tank, see Figure 2. The pressboard<br />

sheets were held in place with a steel locating pin welded to the tank bottom and a “guide rail” was located at the<br />

edge <strong>of</strong> the sheets. The sheets showed tear marks from the locating pins and “guide rails”, evidence that the core<br />

and coils assembly moved about 2 in. from end-to-end with respect to the tank base plate during shipment.<br />

© 2010 Doble Engineering Company -77 th Annual International Doble Client Conference<br />

All Rights Reserved<br />

2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!