PRECINCT 2 - COMMISSIONER CYNTHIA LONG<br />
<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />
<strong>REVISED</strong> <strong>May</strong> 3, 2013<br />
DESIGN<br />
BID<br />
ESTIMATED CONST. SCHEDULE<br />
2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN ENGINEER<br />
BID LETTING<br />
START FINISH ADVERTISEMENT<br />
START FINISH<br />
ENVIRONMENTAL<br />
CLEARANCE<br />
PROGRESS - ACTION ITEMS - REMARKS<br />
Lakeline Blvd. Phase 2<br />
(Old Quarry Rd to Old 2243) - County<br />
Baker-Aicklen<br />
Jan 2012 <strong>May</strong> 2013<br />
TBD<br />
(Pending ROW Acquisition)<br />
Due Diligence<br />
Investigations<br />
Completed:<br />
Fall 2012<br />
Easements have been acquired for the Gilpin property, and Baker-Aicklen is beginning design adjustments<br />
to eliminate retaining walls. TCEQ approval of the CZP was received on 11/13/12. One ROW parcel<br />
(Spring/Summer tract) remains to be closed.<br />
Lakeline Blvd. Phase 3<br />
(Crystal Falls Pkwy to Old Quarry Rd) - Developer<br />
Baker-Aicklen<br />
Jan 2012<br />
<strong>May</strong> 2013<br />
Late Spring 2013<br />
Early Summer<br />
2013<br />
Early 2014<br />
Due Diligence<br />
Investigations<br />
Completed:<br />
Fall 2012<br />
Baker-Aicklen received draft plans for Developer phase from subconsultant RPS-Espey and is preparing to<br />
submit 100% PS&E next week. The bidding procedure was provided to KB Home on 4/15/13. The<br />
developer agreement with KB Home was approved by the Court on 2/5/13.<br />
Seward Junction Improvements Study<br />
(CR 213, CR 259, CR 260, CR 263, CR 266)<br />
Loomis Partners<br />
Aug 2011<br />
Feb 2013<br />
N/A<br />
Due Diligence<br />
Investigations To Be<br />
Completed:<br />
TBD<br />
Loomis is finalizing their work authorization for schematic development. Loomis submitted the revised<br />
Krause Farm Historical Research Report on 3/1/13, in response to the 2/13/13 GEC comments. A project<br />
update meeting was held on 1/7/13 to discuss archeological constraints and a final recommended<br />
alignment in the northeast quadrant.<br />
US 183 at RM 1869<br />
Gonzalez-De La<br />
Garza &<br />
Associates<br />
Oct 2011<br />
Spring 2013<br />
TBD<br />
Categorical Exclusion<br />
Anticipated Approval:<br />
Spring 2013<br />
Walker has completed survey field work and submitted draft topo files on 4/30/13. Gonzalez-De La Garza<br />
has begun work on the 30% PS&E. TxDOT is preparing an AFA for the project. TxDOT approved the<br />
signal location, and provided traffic comments on the preliminary signal plans on 12/19/12. Cox-McLain<br />
has begun environmental investigations.<br />
Lakeline Blvd. at US 183<br />
Kimley Horn<br />
Nov 2011<br />
Feb 2013<br />
TBD<br />
N/A<br />
Kimley-Horn submitted the 90% design submittal on 2/26/13 and it is currently under review. A meeting<br />
with TxDOT to discuss future plans for US 183 was held on 8/10/12, and a weaving analysis was submitted<br />
on 9/4/12. TxDOT provided comments on the weaving analysis on 9/6/12. Kimley-Horn submitted the<br />
final report on 1/18/12, and it was transmitted to TxDOT and the City of Austin on 1/18/12.<br />
CR 258 (Sunset Ridge to Reagan Blvd)<br />
CEC<br />
<strong>May</strong> 2012<br />
Mar 2013<br />
TBD<br />
Due Diligence<br />
Investigations<br />
Completed:<br />
Fall 2012<br />
A project update meeting to discuss potential alignments and project issues was held on 2/14/13. CEC is<br />
moving forward with 60% PS&E. Comments on 30% PS&E were returned on 9/14/12, and a comment<br />
review meeting was held on 9/14/12. Blanton received the archeological permit from THC on 9/11/12.<br />
* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 3 of 8