WILLIAMSON COUNTY ROAD BOND PROGRAM REVISED May 3 ...
WILLIAMSON COUNTY ROAD BOND PROGRAM REVISED May 3 ...
WILLIAMSON COUNTY ROAD BOND PROGRAM REVISED May 3 ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
PRECINCT 4 - COMMISSIONER RON MORRISON<br />
<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION<br />
(CONT'D)<br />
ENGINEER CONTRACTOR OBSERVER BID AWARD<br />
<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />
<strong>REVISED</strong> <strong>May</strong> 3, 2013<br />
NOTICE TO<br />
PROCEED<br />
CONSTRUCTION<br />
START<br />
FINISH<br />
PROGRESS - ACTION ITEMS - REMARKS<br />
13IFB00118<br />
CR 108<br />
(US 79 to Limmer Loop)<br />
Karen Friese &<br />
Associates<br />
DNT GEC 02/05/13 02/22/13 03/04/13 Due 11/29/13<br />
DNT continued to excavate to subgrade and is hauling off roadway excavation spoils. The Contractor set CTB along Limmer Loop<br />
for the Culvert H extension, began setting 24” and 30” RCP on Storm Line E, and set 2-24” RCP for Culvert D.<br />
PROJECTS BIDDING / CONTRACTING<br />
ENGINEER<br />
ADVERTISEMENT<br />
BEGINS<br />
BID LETTING<br />
BID AWARD<br />
ANTICIPATED<br />
N.T.P.<br />
ESTIMATED CONST. SCHEDULE<br />
START<br />
FINISH<br />
PROGRESS - ACTION ITEMS - REMARKS<br />
13IFB00119<br />
CR 170<br />
(South of SH 45 to North of Pflugerville Parkway)<br />
Baker-Aicklen 12/30/12 01/23/13 03/04/13 Jun 2013 Jun 2013 Mar 2014<br />
PreConstruction Meeting is scheduled for 5/10/13. AT&T relocation is anticipated to be complete by the end of <strong>May</strong>. Construction<br />
contracts have been executed with BPI. The Notice of Award was issued to BPI on 3/13/13. The Commissioners Court approved<br />
the award of the construction contract to BPI Environmental on the 3/5/13. Manville relocations continue and are nearing<br />
completion. Atmos and Oncor relocations are complete. AT&T Metro is moving forward with design, and will be relocating to<br />
Oncor's poles. All ROW parcels have been acquired or have Possession and Use agreements.<br />
2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN<br />
CR 119<br />
(Limmer Loop to Chandler Rd)<br />
ENGINEER<br />
Bury & Partners<br />
DESIGN<br />
BID<br />
ESTIMATED CONST. SCHEDULE<br />
BID LETTING<br />
START FINISH ADVERTISEMENT<br />
START FINISH<br />
Jan 2011 <strong>May</strong> 2013<br />
TBD<br />
ENVIRONMENTAL<br />
CLEARANCE<br />
Due Diligence<br />
Investigations<br />
Completion Date: Winter<br />
2011/2012<br />
PROGRESS - ACTION ITEMS - REMARKS<br />
Bury & Partners submitted 100% PS&E on 4/11/13, and it is currently under review. The additional SUE<br />
investigation of gas lines has been completed and analyzed for potential conflicts, and review comments<br />
on the 90% PS&E were returned on 3/8/13.<br />
Chandler Road Expansion<br />
(FM 1460 to SH 130)<br />
Seiler Lankes <strong>May</strong> 2012 June 2013 TBD<br />
Due Diligence<br />
Investigations<br />
Completion Date: TBD<br />
Comments were received from the City of Round Rock on 3/22/13, and a meeting with Seiler Lankes to<br />
discuss was held on 3/26/13. Seiler Lankes submitted the 60% design package on 2/19/13 and it is<br />
currently under review. An update meeting with the City of Round Rock was held on 12/10/12. Seiler<br />
Lankes is coordinating with Baker-Aicklen regarding developer planned median openings and future<br />
intersections.<br />
CR 110 Middle<br />
(North of Limmer Loop to CR 107)<br />
Kimley Horn Jan 2013 June 2013<br />
TBD<br />
Due Diligence<br />
Investigations<br />
Completion Date: TBD<br />
A meeting to review alternatives was held on 4/16/13, and a meeting with Atmos to discuss potential<br />
impacts to their facilities was held on 4/26/13. Kimley Horn submitted an alternatives layout on 3/5/13.<br />
Kimley Horn submitted a data collection request on 1/31/13. Right of Entry requests were sent out on<br />
2/12/13, and ROE has been received for all but one parcel.<br />
CR 110 South<br />
(US 79 to Limmer Loop)<br />
RW Armstrong Jan 2013 June 2013<br />
TBD<br />
Due Diligence<br />
Investigations<br />
Completion Date: TBD<br />
A design meeting was held with RWA on 4/30/13. Notified RWA on 3/12/13 that ROE has been received<br />
for all parcels. RW Armstrong submitted a property owner list for Right of Entry requests on 2/1/13, and<br />
Right of Entry requests were sent out on 2/8/13. A design kick-off meeting was held on 2/6/13, and RW<br />
Armstrong is proceeding with preliminary design.<br />
* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 7 of 8