- Page 1 and 2: STATE OF WISCONSINDEPARTMENT OF TRA
- Page 3 and 4: PREFACEWisconsin Department Of Tran
- Page 5 and 6: PREFACESECTION 102 BIDDING REQUIREM
- Page 7 and 8: PREFACE104.2 Revisions to the Contr
- Page 9 and 10: PREFACE106.2 Supply Source and Qual
- Page 11 and 12: PREFACE108.6 Character of WorkersCo
- Page 13 and 14: PREFACE501.3.9 PozzolansAdd this ne
- Page 15 and 16: PREFACE643.2.4 DrumsRevise this sub
- Page 17 and 18: TABLE OF CONTENTSPART IGENERAL REQU
- Page 19 and 20: TABLE OF CONTENTS501.3.6.4.4 Physic
- Page 21 and 22: TABLE OF CONTENTS628.2.5.1 Geotexti
- Page 23 and 24: PART IGENERAL REQUIREMENTS AND COVE
- Page 25 and 26: 101.3 DefinitionsSAE Society of Aut
- Page 27 and 28: Contractor The individual, partners
- Page 29 and 30: Pavement structure The combination
- Page 31 and 32: Surface course One or more layers o
- Page 33 and 34: 102.3.2 Department May Not Issue(1)
- Page 35 and 36: 102.7.1.2 Bidder-Generated Schedule
- Page 37 and 38: 102.13 Disqualification of Bidders1
- Page 39 and 40: 103.5 Contract Bond(1) At the time
- Page 41 and 42: 104.2.2.3 Change Orders for Enginee
- Page 43 and 44: (2) The department understands that
- Page 45 and 46: to open sections of the road to pub
- Page 47 and 48: (3) The cost of final cleanup is in
- Page 49: 5. A statement specifying the time
- Page 53 and 54: (4) If there is a discrepancy on a
- Page 55 and 56: 105.8 Authority and Duties of Inspe
- Page 57 and 58: (2) The engineer may deny the appli
- Page 59 and 60: 105.13.6 Review Panel(1) If the con
- Page 61 and 62: 106.2.4 Conditional Approval of Mat
- Page 63 and 64: (2) Required sampling and testing m
- Page 65 and 66: SECTION 107 LEGAL RELATIONS AND RES
- Page 67 and 68: 107.12 Responsibility for Damage an
- Page 69 and 70: (4) Do not blast on the railroad's
- Page 71 and 72: (2) Conduct all work over, on, or a
- Page 73 and 74: 107.23 Antitrust Assignment Clause(
- Page 75 and 76: 108.1 Subletting the ContractSECTIO
- Page 77 and 78: 108.4.2.2 Monthly Progress Meetings
- Page 79 and 80: 108.4.3.4 Engineer's Right to Reque
- Page 81 and 82: 8. Show completing the work within
- Page 83 and 84: 108.6 Character of Workers(1) Provi
- Page 85 and 86: 108.9.3 Contract Time for Calendar
- Page 87 and 88: (2) This deducted sum is not a pena
- Page 89 and 90: (5) The department may allow the co
- Page 91 and 92: (2) The engineer will determine the
- Page 93 and 94: (3) Provide the justification withi
- Page 95 and 96: (7) For equipment not listed in the
- Page 97 and 98: (2) General field supervision costs
- Page 99 and 100: 109.6.3.2 Materials109.6.3.2.1 Gene
- Page 101 and 102:
PART IIEARTHWORK201.2 Construction
- Page 103 and 104:
205.2.6 Unclassified ExcavationDele
- Page 105 and 106:
(9) Backfilling of structural plate
- Page 107 and 108:
PART IIIBASE COURSES304.1 Descripti
- Page 109 and 110:
304.2.6 Gradation RequirementsRepla
- Page 111 and 112:
308.5 Basis of PaymentReplace parag
- Page 113 and 114:
401.3.4 Asphalt, Type ACDelete the
- Page 115 and 116:
403.4 Quality AssuranceReplace para
- Page 117 and 118:
SECTION 407 ASPHALTIC CONCRETE PAVE
- Page 119 and 120:
407.2.3 Acceptance of Pavement Mixt
- Page 121 and 122:
407.2.5.2 Liquid Antistripping Agen
- Page 123 and 124:
407.4 Measurement(1) The department
- Page 125 and 126:
410.3.2 Salvaged Asphaltic Pavement
- Page 127 and 128:
415.2.2 ConcreteReplace paragraph t
- Page 129 and 130:
415.5.10 Curing of ConcreteReplace
- Page 131 and 132:
(4) The contractor shall not: heat
- Page 133 and 134:
415.5.15.2.4 Maturity Method(1) The
- Page 135 and 136:
(4) When verification tests indicat
- Page 137 and 138:
416.2.6 Concrete Pavement GapsRepla
- Page 139 and 140:
(6) The department may prohibit the
- Page 141 and 142:
501.4.3.3 General Use(1) For all co
- Page 143 and 144:
501.5.5 Fly ashDelete the entire te
- Page 145 and 146:
(2) The contractor shall protect al
- Page 147 and 148:
(3) On structures where the deck co
- Page 149 and 150:
505.2.6.2 Dowel Bars(1) Coat dowel
- Page 151 and 152:
508.5.3 Timber Piling, DeliveredRep
- Page 153 and 154:
512.4.2 Permanent Steel Sheet Pilin
- Page 155 and 156:
except as provided below; and for f
- Page 157 and 158:
PART VIINCIDENTAL CONSTRUCTION601.2
- Page 159 and 160:
completion of the work; and for all
- Page 161 and 162:
(23) Steel Plate Beam Guard, Energy
- Page 163 and 164:
(3) Concrete Median Sloped Nose con
- Page 165 and 166:
623.2.2 Calcium Chloride(1) Furnish
- Page 167 and 168:
628.2.5.1 Geotextile FabricReplace
- Page 169 and 170:
Add the following new subsection:62
- Page 171 and 172:
628.4.5 Silt Fence, DeliveredReplac
- Page 173 and 174:
Add the following new subsection:62
- Page 175 and 176:
631.5.1 SoddingReplace paragraph on
- Page 177 and 178:
(4) For contractor-designed bases,
- Page 179 and 180:
643.2.4 DrumsReplace the entire tex
- Page 181 and 182:
except as specified in the contract
- Page 183 and 184:
645.2.4 Geotextile Fabric, Type DF
- Page 185 and 186:
646.4.7 Locating No-Passing ZonesRe
- Page 187 and 188:
SCHEDULE OF BID ITEMS ADDED AND RET
- Page 189 and 190:
65099 Construction Staking, Initial
- Page 191 and 192:
65010 Construction Staking, Subgrad
- Page 193 and 194:
62003 Concrete Median Sloped Nose m
- Page 195 and 196:
BID ITEMS RETIRED - SI METRIC (EAS
- Page 197:
ERRATA SHEETConversion Table (page