11.07.2015 Views

land acquisition/sez & displacement – 2011 - Indian Social Institute

land acquisition/sez & displacement – 2011 - Indian Social Institute

land acquisition/sez & displacement – 2011 - Indian Social Institute

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Land issues hit road work (4)Thiruvananthapuram: The delay in <strong>land</strong> <strong>acquisition</strong> in certain stretches for road development is affectingwork under the City Roads Improvement Project (CRIP). Work being taken up on a total of 18.62 km, invarious road corridors, is scheduled for completion by September. “We have completed even bitumenworks in 16 km (of the 18.62 km) taken up under the second phase. But the authorities have not handedover <strong>land</strong> in some critical areas, though the matter was taken up at the highest level,” an official ofTrivandrum Road Development Company Ltd. (TRDCL), the implementing agency of CRIP, told TheHindu. There is delay in handing over <strong>land</strong> belonging to the Travancore Devaswom Board (TDB) nearAyurveda College on MG Road. Close to 600 metres of <strong>land</strong> along the cemetery and Mar Thoma Churchat Pattoor would also be required. Acquisition would also be required for the construction of a flyoveracross the arterial road at Melepazhavangadi and relocation of shops behind the city bus stand at EastFort. The TRDCL had decided not to wait for the handing over of the <strong>land</strong> in these critical corridors. “Oncethe <strong>land</strong> is handed over and the utilities shifted, we will take up and complete the remaining work,” theofficial said. Till then, these areas will continue to be bottlenecks in the CRIP corridors. The 260-metrestretch extending from Pazhavangadi to East Fort and the Pulimoodu-Ayurveda College stretch will bethe main bottlenecks on the arterial road. The work on the Pazhavangadi - East Fort stretch can be takenup only after the construction of a flyover at Melepazhavangadi and relocation of traders on the PowerHouse and Thakaraparambu roads. In Corridor III (extending from Museum to Overbridge via BakeryJunction and Thampanoor) the first layer of bitumen laying had been completed till Model SchoolJunction. The work on the footpath and median was nearing completion. Traffic signals had been installedat the Panavila junction. Vehicle movement would be streamlined and medians constructed at theGeneral Hospital junction (in the Airport-Asan Square stretch, Corridor IV). In Corridors V and VI, TRDCLhad decided to complete tarring up to the Parthas junction on the Power House road by the month end.Bitumen work will be completed in the Pattoor-Vanchiyoor stretch and on the West Fort-Sreekanteswaram stretch by August. In the Pattom-Medical College-Ulloor stretch, TRDCL had decidedto complete work in the Pattom-Pottakuzhi section by this month. The Murinjapalam bridge would bedemolished to construct a four-lane bridge. A temporary bridge would be constructed. The 0.36-kmUlloor-Kochulloor road, to be developed under Phase II, is moving slow due to the delay in laying asewage line. In Corridor 10, from Kowdiar to Peroorkada, the authorities had decided to put in placesolar-powered traffic signals at Peroorkada. Work on 41.95 km had been taken up under CRIP — 14.26km in the first phase, 18.62 in the second, and 9.06 km in the final phase. Under phase II, work was takenup on the 0.244-km LMS - Students Centre stretch, 1.35-km Vellayambalam – Sasthamangalam, 2.63-kmLMS – Attakulangara, 2.02-km Museum - Bakery Junction – Thampanoor – Overbridge, 0.87-km Airport-MLA Hostel, 0.54 Vanross Junction - Secretariat west gate, 2.3-km Kowdiar - Pattom, 0.81-km Pattom –Murinjapalam - Medical College - Ulloor, 0.36-km Ulloor - Kochulloor, 2.01-km Kowdiar - Peroorkada,1.43-km Peroorkada - Vazhayila, 1.02-km Attakulangara – Sreevarahom - Eenchakkal, and 2.98-kmMurinjapalam - Poonthi Road - NH Bypass stretches. (The Hindu 21/8/11)Anti-Posco protesters prevent coastal road construction (4)Pradip: After a few days lull, the proposed Posco plant site in Orissa’s Jagatsinghpur district on Saturdaywitnessed noisy scenes with anti-project activists preventing start of construction of a coastal road.Activists of Posco Pratirodh Sangram Samiti (PPSS) chased a group of people who had been to an areaunder Dhinkia panchayat along the sea for construction of a coastal road. The proposed coastal road isplanned to be laid from the Paradip Oil Refinery to Posco area, the foundation for which was laidyesterday. As the contractor and workers were proceeding to the site during the day, PPSS activistsprotested the move and chased them away, official sources said. The district administration had a toughtime in convincing a large number of protesters who blocked the road at Gadakujanga by erectingbamboo baricades. Like the protests at Gobindpur and Nuagaon, the protestors at Gadakujanga includedwomen and children under the banner of Kunjabehary Anchalik Surakshya Samittee (KASS) since August16. Gadakujanga is one of the three routes to Posco site from Balitutha junction. The other routes throughGobindpur and Nuagaon remained blocked by PPSS and United Action Committee (UAC), a pro-industryoutfit. The district administration along with police force and a magistrate went to Gadakujanga toconvince the protesters to lift the agitation as all works including tree felling, ground levelling and removalof betel vines remained suspended since August 16. “We had discussion with them. We will resume thework at Posco site after convincing the people”, Additional District Magistrate, Paradip, Surajit Das said.Leaders of KASS alleged that police had converted Posco area into their fiefdom through “dagagiri”.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!