Interim measures<br />

� The enduring access working groups will consider<br />

whether the following can be implemented by April<br />

2009:<br />

� SO release of short-term access rights<br />

(CAP161)<br />

� Entry capacity sharing (CAP163)<br />

2a. Interim connect & manage<br />

� <strong>National</strong> <strong>Grid</strong> has been working with Ofgem to<br />

define a process in which derogations from<br />

<strong>GB</strong>SQSS can be used to provide access ahead of<br />

the completion of certain reinforcements