- Page 1: NAVFAC Ocean Thermal EnergyConversi
- Page 5: 3.2.2 Risks........................
- Page 8 and 9: Figure 2‐53 CWP Connection Closin
- Page 10 and 11: Figure 2‐110 CWP Hook‐up Step 1
- Page 12 and 13: Table 2‐27 Power Delivery Trade S
- Page 14 and 15: The 2.5‐MW Mini‐Spar’s functi
- Page 16: 1 IntroductionThe Naval Facilities
- Page 19 and 20: Range Facility (PMRF) on Kauai wher
- Page 21 and 22: CriteriaBaseline Floating Option La
- Page 23 and 24: This volume addresses the 2.5‐MW
- Page 25 and 26: 2 Configuration Report, CDRL A014;
- Page 27 and 28: platform has an estimated cost of a
- Page 29 and 30: spar’s mild seakeeping motions, t
- Page 31 and 32: vapor continues downward to one of
- Page 33 and 34: MotorMagCouplingPumpFigure 2‐8 Le
- Page 35 and 36: inform OTEC design and regulatory g
- Page 39 and 40: Figure 2‐12 Cell Spar Coupled Ana
- Page 41 and 42: Table 2‐4 Extreme Anchor Loads In
- Page 43 and 44: 2.3.4.2 CWP Fatigue Loads and Strai
- Page 45 and 46: 97% value is plotted, showing that
- Page 47 and 48: 2.4 Platform and Mooring Segment2.4
- Page 49 and 50: 2.4.2.1.1 Cell ArrangementThe OTEC
- Page 51 and 52: Hydrodynamic analysis to date has f
- Page 53 and 54:
Figure 2‐19 AccommodationsSource:
- Page 55 and 56:
d. (2) Able Seamen and (1) Ordinary
- Page 57 and 58:
Figure 2‐22 Platform Main Deck2.4
- Page 59 and 60:
The machinery that is located in th
- Page 61:
The air intake for the machinery sp
- Page 67 and 68:
2.4.4.7 Fresh Water SystemsFreshwat
- Page 69 and 70:
2.4.4.12 IncineratorAn incinerator
- Page 71 and 72:
Figure 2‐25 OTEC Water FlowConfig
- Page 73 and 74:
Figure 2‐26 Water Flow Through th
- Page 75 and 76:
configurations may be possible. Fur
- Page 77:
Z‐AXIS (+ UP)Z‐AXIS(+ UP)X‐AX
- Page 80 and 81:
2.4.7.3 Upright In‐Service Condit
- Page 82 and 83:
The hull girder section modulus for
- Page 84 and 85:
2.4.10.1.2 Post‐Demonstration Per
- Page 86 and 87:
2.4.10.3 Anchor SubsystemThe variou
- Page 88 and 89:
The U.S. Navy provides recommendati
- Page 90 and 91:
2.4.11 Cold Water Pipe Element2.4.1
- Page 92 and 93:
dynamic head with a period in the 1
- Page 94 and 95:
Figure 2‐45 First and Second Coll
- Page 96 and 97:
2.4.11.2.4 CWP DynamicsThe CWP is s
- Page 98 and 99:
cycle, building added conservatism
- Page 100 and 101:
Figure 2‐52 CWP Connection to Spa
- Page 102 and 103:
often have voids. Although voids ca
- Page 104 and 105:
throughout fatigue loading. Fatigue
- Page 106 and 107:
De-mister: -45 m Turbine (Datum): 0
- Page 108 and 109:
2.5.2 Power Generation Segment Over
- Page 110 and 111:
Red = Thermal PowerGreen = Mechanic
- Page 112 and 113:
The red‐shaded entries in the tab
- Page 115 and 116:
components are shown in Figure 2‐
- Page 117 and 118:
Figure 2‐67 Detail of Water Flow
- Page 119 and 120:
The temperature and pressure sensor
- Page 121 and 122:
2.5.2.6 Condenser Heat ExchangerThe
- Page 123 and 124:
condensation process is gravity con
- Page 125 and 126:
The Hx is constructed of alternatin
- Page 127 and 128:
2.5.2.8 Working Fluid Subsystem2.5.
- Page 129 and 130:
Figure 2‐78 OTEC Process Piping D
- Page 131 and 132:
Figure 2‐79 Left: Magnetic Drive
- Page 133 and 134:
should have external insulation cap
- Page 135 and 136:
2.5.3 Electrical Generation Element
- Page 137 and 138:
Axial‐impulse turbines, such as i
- Page 139 and 140:
The issue of operating in a marine
- Page 141 and 142:
Figure 2‐86 Functional Block Diag
- Page 143 and 144:
The requirements for the Power Deli
- Page 145 and 146:
2.6.2 Onboard Distribution ElementT
- Page 147 and 148:
safety risks are mitigated. Further
- Page 149 and 150:
2.6.2.7 Power Transmission ElementF
- Page 151 and 152:
The dynamic stress on the cable is
- Page 153 and 154:
Figure 2‐94 Submarine Cable Descr
- Page 155 and 156:
Table 2‐34 Mini‐Spar Motions, 1
- Page 157 and 158:
2.6.2.11 Shore Grid Connection Elem
- Page 159 and 160:
2.7.2 Computer Integrated Process A
- Page 161 and 162:
communications protocols used for I
- Page 163 and 164:
2.7.3.5 Safety, Security, Communica
- Page 165 and 166:
VSAT Maritime Satellite Communicati
- Page 167 and 168:
Instrumentation (TSI) system. Beari
- Page 169 and 170:
2.7.4.4 Electrical Power Delivery I
- Page 171 and 172:
Installation PhaseDetails3. Mooring
- Page 173 and 174:
2.8.2.1 Ballast PlanThe ballast pla
- Page 175 and 176:
#2 Anchor Hook‐upThe spar is towe
- Page 177 and 178:
Figure 2‐107 Location of CWP Asse
- Page 179 and 180:
CWP Upending:The CWP is towed to th
- Page 181 and 182:
2.8.2.5 Offshore Equipment Installa
- Page 183 and 184:
The following ground rules and assu
- Page 185 and 186:
Figure 2‐115 Seawater and Ammonia
- Page 187 and 188:
2.8.3.1.4 Removal of Platform from
- Page 189 and 190:
3 Development Plan, CDRL A021; 2.5
- Page 191 and 192:
Table 3‐1 Status of Key Technolog
- Page 193 and 194:
Component/SubsystemType Maturity Le
- Page 195 and 196:
3.2.2 RisksAny program of this size
- Page 197 and 198:
Risk NameHeat Exchanger CorrosionCW
- Page 199 and 200:
The configuration incorporates feat
- Page 201 and 202:
For the ammonia and seawater pumps,
- Page 203 and 204:
used. If adequate ground cover does
- Page 205 and 206:
level for fabrication and assembly.
- Page 207 and 208:
3.3.6.5 Long Lead ItemsThe followin
- Page 209 and 210:
provide for the measurement and con
- Page 211 and 212:
3.3.8.2.2 Ammonia CircuitAs the amm
- Page 213 and 214:
3.3.8.3 Integration of Machinery Sp
- Page 215 and 216:
2. Government‐Industry Partnershi
- Page 217 and 218:
Verify sensor calibration and proce
- Page 219 and 220:
3.3.11 Two‐Year Demonstration Pro
- Page 221 and 222:
Motions (classic six degrees of fre
- Page 223 and 224:
one of the flange joints or instrum
- Page 225 and 226:
Spar also provide a good opportunit
- Page 227 and 228:
Temperature rises- Submarine cable
- Page 229 and 230:
will be designed to store the data
- Page 231 and 232:
Figure 3‐6 Environmental Manageme
- Page 233 and 234:
Navy to support inherently governme
- Page 235 and 236:
thresholds. On the whole, the analy
- Page 237 and 238:
floaters) and nekton (larger motive
- Page 239 and 240:
Analysis NeedTradeoff analysis of s
- Page 241 and 242:
GeneralDesign of aquatic and marine
- Page 243 and 244:
3.4.2.6.1 Alternative Consideration
- Page 245 and 246:
2010; see Appendix J, Table 1) to d
- Page 247 and 248:
Qualified marine biologists will id
- Page 249 and 250:
solids, is very labor intensive and
- Page 251 and 252:
Figure 3‐9 Comparison of Daily Av
- Page 253 and 254:
Ocean Engineering should evaluate t
- Page 255 and 256:
The OTEC Mini‐Spar is an OTEC pil
- Page 257 and 258:
Figure 3‐11 Estimated Environment
- Page 259 and 260:
3.5 Program PlansA detailed MS Proj
- Page 261 and 262:
3.6 ROM Cost EstimatesThe SSOPP con
- Page 263 and 264:
3.7 Financing OptionsIn Section 1,
- Page 265 and 266:
AcronymsABSADCPAFBAFFFAH36AHTAHUAHV
- Page 267 and 268:
AcronymEBIEDASEEEEIPSEFDCEIPSEISEMC
- Page 269 and 270:
AcronymINCOSEINUIPTIR&DIRIGIRPIVIWR
- Page 271 and 272:
AcronymDefinitionOCCLOffice of Coas
- Page 273 and 274:
AcronymTEAACTEWACTGATHDTLCTLRTNTSIT