defined under the following heads but not limited to:<br />

i. Design & Detail Engineering as per M/S Mecon Limited report NO.<br />

MEC/05/28/23MN/<strong>GAIL</strong>/06 (enclose as annexure-1).<br />

ii. Planning & Scheduling<br />

iii. Tendering & Ordering including Purchase <strong>of</strong> all equipment <strong>and</strong> materials,<br />

award <strong>of</strong> <strong>work</strong>s <strong>contract</strong>s, Custom clearance <strong>of</strong> foreign supplied items if any &<br />

their Transportation from Indian port to site etc. Tendering & Ordering to be<br />

done as per <strong>GAIL</strong>’s C&P Procedure.<br />

iv. Inspection/ Expediting <strong>of</strong> equipment/Materials being manufactured by<br />

vendors including <strong>contract</strong>ors supplied items <strong>and</strong> inspection <strong>of</strong> <strong>work</strong>s being<br />

carried out by the <strong>work</strong>s <strong>contract</strong>or, Quality assurance <strong>and</strong> Quality control.<br />

v. Stores Management & material accounting during the project time.<br />

vi. Construction Management & Supervision<br />

vii. Project Commissioning/ Commissioning Assistance.<br />

viii. Project Cost Control, Management & Monitoring.<br />

ix. Project close out.<br />

The <strong>scope</strong> <strong>of</strong> <strong>work</strong> broadly includes followings:<br />

i) Installation /replacement <strong>of</strong> approximately 200 metre <strong>of</strong> various size<br />

pipe in Vizag <strong>and</strong> 25 metre <strong>of</strong> various size pipe in Cherapally.<br />

ii) Installation /replacement <strong>of</strong> various size valves, strainers, flanges,<br />

hydrants, monitors, pressure gauge, switch <strong>and</strong> other accessories in<br />

Vizag <strong>and</strong> Cherapally.<br />

iii) Installation <strong>of</strong> additional water spray system in Vizag <strong>and</strong> Cherapally.<br />

iv) Installation <strong>of</strong> two nos. each new diesel driven 616(m3/hr) Fire water<br />

pumps with associated accessories on the existing fire water<br />

pumps(410 m3/hr) foundation with the required modification<br />

(Preferably by back <strong>of</strong> existing pumps by the pump vendor).<br />

v) Associated Fire detection <strong>and</strong> alarm system.<br />

vi) Associated Electrical & instrumentation <strong>work</strong>s.<br />

vii) Associated Civil <strong>work</strong>s<br />

viii) Installation <strong>of</strong> pressure safety valves<br />

PMC deliverables:<br />

The PMC is required to submit all deliverables within the schedule time line as<br />

per the requirement mentioned in various sections <strong>of</strong> this document. The<br />

deliverables includes all documents, drawings, Plan, Schedule, Costing, Best<br />

Practices, Replies etc mentioned under various disciplines <strong>of</strong> the WBS<br />

elements. The deliverables are summarized as under but not limited to:<br />

a) All Periodic Reports, Daily Progress Reports during construction,<br />

Customized Reports, presentations, best practices/ international practices<br />

required for submission to Management / External Agencies.