Khakanjinskoye (Okhotsk Mining and Geological Company)In thousands USD, except as indicated <strong>2004</strong> г.Direct mining expenses 12 848Stripping and mine development adjustments 4Third−party smelting, refining and transportation costs−By−product credits silver (7 449)By−product credits (217)Other 197Cash Operating Costs 5 383Royalties 2 608Production taxes 667Total Cash Costs 8 658Depreciation 5 227Depletion \ amortization−Reclamation and mine closure 55Total Production Costs 13 940By−product (method 1): Silver as a by−productProduction costs 16 324By−product credits (7 666)8 658<strong>Report</strong>ed gold ounces produced 75 795<strong>Report</strong>ed total cash costs per ounce 114<strong>Report</strong>ed noncash costs per ounce 70Total production costs per ounce 184Note:The calculations take into account that silver is a co−product at the Khakanjinskoye deposit (according to Gold In−stitute Standards). In 2003, only mining operations took place at the Khakanjinskoye deposit; no metal productionoccurred.74 <strong>Polymetal</strong> annual report <strong>2004</strong>
Dukat and Lunnoye (Magadan Silver, Silver Territoty)In thousands USD, except as indicated <strong>2004</strong> 2003Direct mining expenses 50,603 31,527Stripping and mine development adjustments 228 549Third−party smelting, refining and transportation costs − −By−product credits (32,300) (12,601)Other − 139Cash Operating Costs 18,532 19,614Royalties 8,038 5,254Production taxes 1,910 66Total Cash Costs 28,480 24,934Depreciation 3,491 2,945Depletion \ amortization − −Reclamation and mine closure 11 17Total Production Costs 31,982 27,896By−product (method 1): Gold as a by−productProduction costs 60,780 37,535By−product credits (32,300) (12,601)28,480 24,934<strong>Report</strong>ed silver ounces produced 16,933,856 9,765,675<strong>Report</strong>ed total cash costs per ounce 1.68 2.55<strong>Report</strong>ed noncash costs per ounce 0.21 0.30Total production costs per ounce 1.89 2.86NotePrecious metals production at the Dukat and Lunnoye deposits is a single technological process. The above figuresare calculated for both deposits together. Silver is a co−product at the deposit. Calculations are[This was into ac−count during calculations] based on Gold Institute Standards.Appendix #2: Production costs by Gold Institute Standard75
- Page 1 and 2:
Annual report2004St. Petrsburg1
- Page 3 and 4:
Annual Report2004St. Petersburg3
- Page 5 and 6:
FinancialhighlightIndicator Meas. u
- Page 7 and 8:
2004Key eventsFebruarynew managemen
- Page 9 and 10:
koye gold mine. This cost increasec
- Page 11 and 12:
MineralResourcesVladimir T. Ryabukh
- Page 13 and 14:
Igor V. Venatovsky,First Deputy CEO
- Page 15 and 16:
Sergey A. Cherkashin,CFOSalesFinanc
- Page 17 and 18:
Denis G. Pavlov,Head of TreasuryDep
- Page 19 and 20:
At the Dukat and Lunnoye depos−it
- Page 21 and 22:
ProductionfacilitiesoverviewProduct
- Page 23 and 24: Victor R. Wulfert,Managing Director
- Page 25 and 26: Victor R. Wulfert,Managing Director
- Page 27 and 28: Andrey V. Novikov,Managing Director
- Page 29 and 30: Sergey G. Antipin,Managing Director
- Page 31 and 32: Vorontsovskoye(Northern Urals Gold,
- Page 33 and 34: Alexander V. Bulavin,Head of Licens
- Page 35 and 36: Dukat depositconducting a feasibili
- Page 37 and 38: GlobalpositioningIn 2004, world sil
- Page 39 and 40: CorporategovernancePolymetal follow
- Page 41 and 42: Hazardous facilities at the deposit
- Page 43 and 44: Personnel at mining facilitiesCompa
- Page 45 and 46: Upgrading skillsIn 2004, the compan
- Page 47 and 48: ManagementVitaly NESISCEOMr. Nesis
- Page 49 and 50: ZAOPricewaterhouseCoopers AuditSred
- Page 51 and 52: JSC “ISPA “POLYMETAL”STATEMEN
- Page 53 and 54: JSC “ISPA “POLYMETAL”CONSOLID
- Page 55 and 56: The Group’s 100% interest in avar
- Page 57 and 58: Deferred developmentexpendituresIn
- Page 59 and 60: NOTE 3Variable Interest EntityStart
- Page 61 and 62: Investments mainly represent or−d
- Page 63 and 64: Loans from NIKoil Bank in total ofU
- Page 65 and 66: Future payments under capital lease
- Page 67 and 68: Note 24Income TaxThe income tax exp
- Page 69 and 70: In accordance with FAS 141, thecont
- Page 71 and 72: NOTE 30Subsequent eventsBank loan r
- Page 73: Vorontsovskoye (Northern Urals Gold
- Page 77 and 78: 1) Per ounce of gold produced or so