12.07.2015 Views

CWRB Briefing Slides - U.S. Army Corps of Engineers

CWRB Briefing Slides - U.S. Army Corps of Engineers

CWRB Briefing Slides - U.S. Army Corps of Engineers

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

66Office <strong>of</strong> Water Project ReviewBarrier Island Restoration Cost SharingConcern: The report indicates that the barrier island restorationwould be conducted at 100% Federal cost. The appropriate costsharing should be 65% Federal to reflect the project purpose <strong>of</strong>Ecosystem Restoration.Reason: Cost sharing for ecosystem restoration projects is 65/35.Although the construction is being conducted on or near Federallyowned lands the purpose <strong>of</strong> the project is to provide ecosystemhabitat benefits.Resolution: The report will be modified to reflect the appropriatecost sharing <strong>of</strong> 65% Federal and 35% non-Federal.Resolution Impact: Concern resolved

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!