Issue 9 Jan 2009.indd - Ministry of Defence
Issue 9 Jan 2009.indd - Ministry of Defence
Issue 9 Jan 2009.indd - Ministry of Defence
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
feature<br />
• • To equip and support our armed forces for operations now and in the future • • defence equipment and support • • To equip and support our<br />
19<br />
ll allow the<br />
ed, before<br />
nstalled.<br />
2010 with<br />
ai Zhenhua<br />
crane to<br />
p to 1,000<br />
ded from an<br />
lower trolley<br />
nes.<br />
the three<br />
lifting<br />
r blocks to<br />
concrete<br />
metres into<br />
de <strong>of</strong> the<br />
h further<br />
ock on the<br />
cted through<br />
e and will be<br />
crane rails.<br />
see the<br />
ncluded the<br />
, who saw<br />
VF project<br />
parations for<br />
9,” he said.<br />
ill rest on<br />
nd will be<br />
vour and<br />
ready and<br />
esting as<br />
Queen<br />
lifting the<br />
task’<br />
Above: No 1 dock, being made ready for<br />
its next guest, the fi rst <strong>of</strong> the new aircraft<br />
carriers<br />
Right: the c<strong>of</strong>ferdam in place<br />
Below: concrete is removed during<br />
demolition works for widening <strong>of</strong> the dock<br />
entrance<br />
Dam marks big milestone<br />
A MAJOR milestone has already passed at Rosyth’s No 1 dock<br />
with the completion <strong>of</strong> a c<strong>of</strong>ferdam, a huge enclosure <strong>of</strong> steel and<br />
rock fill extending 14 metres from the basin floor to dockside level.<br />
The c<strong>of</strong>ferdam creates a dry working environment where the civil<br />
contractor can work.<br />
Five circular steel 18.5m diameter cells have been built to sit<br />
on the bed <strong>of</strong> the main basin and then filled in with thousands <strong>of</strong><br />
tonnes <strong>of</strong> imported rock. It is the biggest c<strong>of</strong>ferdam <strong>of</strong> this type<br />
built for many years.<br />
“Modifying a dock in a marine environment like this is not<br />
easy,” said Babcock civil engineer Mike Murray. “The design<br />
and installation <strong>of</strong> the temporary works needed to hold back the<br />
water during the construction period can be very challenging.<br />
The No 1 dock c<strong>of</strong>ferdam alone weighs more than 50,000 tonnes<br />
and has to resist around 8,000 tonnes <strong>of</strong> thrust imposed by the<br />
retained water in the basin. It has to be buildable and sealable.<br />
Sealing is the craft bit and the difficulty is making the seal at the<br />
basin bed.<br />
“We are on time. The No 1 dock c<strong>of</strong>ferdam was constructed in<br />
six weeks and is working well.”<br />
When work on No 1 dock has finished the c<strong>of</strong>ferdam will be<br />
removed and installed at the basin entrance along with another<br />
bespoke structure on the river side to allow the entrance to be<br />
widened.