Case Study - Singapore Metro - tetra
Case Study - Singapore Metro - tetra
Case Study - Singapore Metro - tetra
- No tags were found...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Integration & Implementation Phase‣ Project kick.off in 1997‣ Design completed in 1998‣ The integration platform with OCC based on 1 SCN and 2 BS’s wereinstalled in Syseca/Thales premises located in Paris on May 2000 for ISCS-TETRA integration‣ The first train and locomotive radio equipment were despatched on June2000‣ The Test Tracking System in Valenciennes has been commissioned onNovember 2000‣ The equipment despatch in <strong>Singapore</strong> was completed on May 2001‣ The System Commissioning in <strong>Singapore</strong> was started in January 2002;‣ Train Run Test was completed in until May 2003‣ Revenue service opened on 20th June 2003.3 sept 2008TETRA: The Next Ten YearsSlide 10