02.12.2012 Views

Advanced Nuclear Power - AREVA

Advanced Nuclear Power - AREVA

Advanced Nuclear Power - AREVA

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Yankee Rowe Decommissioning<br />

and Demolition Nearly Complete<br />

By the end of 2004, decommissioning<br />

and demolition of the Yankee<br />

Rowe nuclear power station, a 175<br />

MW PWR in Western Massachusetts,<br />

owned by the Yankee Atomic Electric<br />

Company (YAEC) will be completed.<br />

This plant was the third nuclear<br />

power plant built in the US and the<br />

first built in New England.<br />

Framatome ANP’s ties to Yankee Rowe<br />

extend back to plant operation<br />

through the Yankee <strong>Nuclear</strong> Services<br />

Division that was purchased by Duke<br />

<strong>Power</strong>’s Engineering & Services<br />

(DE&S) division in 1997 and became<br />

part of Framatome ANP in 2003.<br />

When the plant shut down, Yankee<br />

Rowe made a commitment to the<br />

community to not only safely<br />

decommission the plant and prepare<br />

the site for future use, but also to keep<br />

the community informed about those<br />

activities. This safety-conscious and<br />

cooperative attitude played a major<br />

role in the successful completion<br />

of decommissioning activities to date.<br />

In June 2003, Yankee Rowe achieved<br />

one million work hours without a<br />

lost-time accident.<br />

Decommissioning Work<br />

Framatome ANP managed the initial<br />

decommissioning for YAEC until<br />

August 2000, when the decision<br />

was made to transfer Yankee Rowe’s<br />

spent fuel to dry storage. The company<br />

designed and helped manage the<br />

construction of the Yankee Rowe<br />

independent spent fuel storage<br />

installation (ISFSI) which began almost<br />

immediately. While this was going on,<br />

Framatome ANP provided fabrication<br />

oversight of the dry storage system<br />

components and performed an<br />

Once PCB paint and asbestos was<br />

removed from the buildings,<br />

demolition began.<br />

inspection of the accessible spent fuel<br />

assemblies stored in the fuel pool.<br />

Framatome ANP, working as a<br />

subcontractor for NAC International<br />

who was awarded the contract for<br />

the dry storage system, performed fuel<br />

loading and all associated fuel pool<br />

activities. These included confirmatory<br />

fuel inspections and characterization;<br />

and the reconstitution and sipping of<br />

damaged fuel. The first concrete<br />

storage cask was loaded and placed on<br />

the ISFSI pad in June 2002, with<br />

the final cask placed in June 2003.<br />

The YAEC and Framatome ANP<br />

team designed and operated a system<br />

to pump the 570 m 3 of water from the<br />

spent fuel pool and process the water<br />

before releasing it into the nearby<br />

Sherman Pond.<br />

Demolition<br />

Actual demolition, performed by<br />

DEMCO, a New York based company,<br />

began in November 2003. Initial<br />

work was slowed by the need to<br />

remove PCB paint and asbestos from<br />

Demolition of the containment<br />

shell required dividing the shell<br />

into 130 sections.<br />

many buildings before demolition<br />

could proceed.<br />

By early 2004, the landscape around<br />

Yankee Rowe had changed dramatically.<br />

The turbine building and many other<br />

buildings had been demolished and<br />

demolition crews were cutting 130<br />

sections from the containment shell.<br />

The 14.5 tons concrete reactor support<br />

structure will then be brought down<br />

by the controlled use of explosives.<br />

Demolition is scheduled to be<br />

completed in 2004, with green field<br />

achieved in 2005.<br />

Framatome ANP continues to fill key roles<br />

in the Yankee organization by providing<br />

management, oversight, radiation protection,<br />

laboratory analysis, waste shipping<br />

controls, engineering, licensing, quality<br />

assurance, administrative, and health and<br />

safety support. “Framatome ANP has<br />

provided integral support throughout the<br />

decommissioning process at Yankee<br />

Rowe,” said YAEC Vice President Greg<br />

Maret. “Their expertise has been an asset<br />

to the project.”<br />

<strong>Advanced</strong> <strong>Nuclear</strong> <strong>Power</strong> N O 11 November 2004 25

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!