You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Yankee Rowe Decommissioning<br />
and Demolition Nearly Complete<br />
By the end of 2004, decommissioning<br />
and demolition of the Yankee<br />
Rowe nuclear power station, a 175<br />
MW PWR in Western Massachusetts,<br />
owned by the Yankee Atomic Electric<br />
Company (YAEC) will be completed.<br />
This plant was the third nuclear<br />
power plant built in the US and the<br />
first built in New England.<br />
Framatome ANP’s ties to Yankee Rowe<br />
extend back to plant operation<br />
through the Yankee <strong>Nuclear</strong> Services<br />
Division that was purchased by Duke<br />
<strong>Power</strong>’s Engineering & Services<br />
(DE&S) division in 1997 and became<br />
part of Framatome ANP in 2003.<br />
When the plant shut down, Yankee<br />
Rowe made a commitment to the<br />
community to not only safely<br />
decommission the plant and prepare<br />
the site for future use, but also to keep<br />
the community informed about those<br />
activities. This safety-conscious and<br />
cooperative attitude played a major<br />
role in the successful completion<br />
of decommissioning activities to date.<br />
In June 2003, Yankee Rowe achieved<br />
one million work hours without a<br />
lost-time accident.<br />
Decommissioning Work<br />
Framatome ANP managed the initial<br />
decommissioning for YAEC until<br />
August 2000, when the decision<br />
was made to transfer Yankee Rowe’s<br />
spent fuel to dry storage. The company<br />
designed and helped manage the<br />
construction of the Yankee Rowe<br />
independent spent fuel storage<br />
installation (ISFSI) which began almost<br />
immediately. While this was going on,<br />
Framatome ANP provided fabrication<br />
oversight of the dry storage system<br />
components and performed an<br />
Once PCB paint and asbestos was<br />
removed from the buildings,<br />
demolition began.<br />
inspection of the accessible spent fuel<br />
assemblies stored in the fuel pool.<br />
Framatome ANP, working as a<br />
subcontractor for NAC International<br />
who was awarded the contract for<br />
the dry storage system, performed fuel<br />
loading and all associated fuel pool<br />
activities. These included confirmatory<br />
fuel inspections and characterization;<br />
and the reconstitution and sipping of<br />
damaged fuel. The first concrete<br />
storage cask was loaded and placed on<br />
the ISFSI pad in June 2002, with<br />
the final cask placed in June 2003.<br />
The YAEC and Framatome ANP<br />
team designed and operated a system<br />
to pump the 570 m 3 of water from the<br />
spent fuel pool and process the water<br />
before releasing it into the nearby<br />
Sherman Pond.<br />
Demolition<br />
Actual demolition, performed by<br />
DEMCO, a New York based company,<br />
began in November 2003. Initial<br />
work was slowed by the need to<br />
remove PCB paint and asbestos from<br />
Demolition of the containment<br />
shell required dividing the shell<br />
into 130 sections.<br />
many buildings before demolition<br />
could proceed.<br />
By early 2004, the landscape around<br />
Yankee Rowe had changed dramatically.<br />
The turbine building and many other<br />
buildings had been demolished and<br />
demolition crews were cutting 130<br />
sections from the containment shell.<br />
The 14.5 tons concrete reactor support<br />
structure will then be brought down<br />
by the controlled use of explosives.<br />
Demolition is scheduled to be<br />
completed in 2004, with green field<br />
achieved in 2005.<br />
Framatome ANP continues to fill key roles<br />
in the Yankee organization by providing<br />
management, oversight, radiation protection,<br />
laboratory analysis, waste shipping<br />
controls, engineering, licensing, quality<br />
assurance, administrative, and health and<br />
safety support. “Framatome ANP has<br />
provided integral support throughout the<br />
decommissioning process at Yankee<br />
Rowe,” said YAEC Vice President Greg<br />
Maret. “Their expertise has been an asset<br />
to the project.”<br />
<strong>Advanced</strong> <strong>Nuclear</strong> <strong>Power</strong> N O 11 November 2004 25