13.07.2015 Views

Financial Report (January 1, 2010 - December 31, 2010)

Financial Report (January 1, 2010 - December 31, 2010)

Financial Report (January 1, 2010 - December 31, 2010)

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

• Installation of approximately 22.80 MW of power generation capacity in the APSs of Samos (1 G/S x 8.25 MW),Κalimnos (1 G/S x 8.25 MW), Μykonos (1 G/S x 5.88 MW) and in the LPS of Megisti (2 G/S x 0.25 MW each) is inprogress.Environmental Management• Acting towards the improvement of the environmental behavior of its Power Generation Units GBU during <strong>2010</strong>proceeded in:o Completion of Megalopolis A’ Unit III’s flue gas desulfurization Project of € 86.5 m. budgeted value. Performancetests were successfully completed in August 11, <strong>2010</strong> and the Project is under the procedure of TemporaryAcceptance.o Implementation of a series of Projects for the upgrading of existing Units and their antipollution equipment (wastetreatment systems, noise reduction works, construction of central flue gas stacks etc.).• Furthermore, during <strong>2010</strong>:ooGBU continued the systematic monitoring of the monitoring, recording and reporting system for CO2 emissions ofall thermal Units which are under European Trading System for emissions rights and the systematic monitoring ofair pollutants emissions, as well as of the air quality monitoring Networks.GBU continued the adaptation to the ISO 14001:2004 Standard of the already operating EnvironmentalManagement Systems (EMS) in Power Stations in order to certify them.• In <strong>2010</strong> the new Directive <strong>2010</strong>/75/EU for Industrial Emissions has been issued. In the framework of updatingGeneration’s Strategy, for the time period after 2015, alternative approaches are examined and evaluated for adaptingexisting Units to Directive’s requirements.Transmission Business UnitCapital expenditure amounted to Euro 88.8 millionIn <strong>2010</strong>, new investments in the Transmission System have been made totaling € 81,5 m., in accordance with the Five YearsTransmission Development Studies (2009-2013) requirements.• The expansion of the EHV Substation in Acharnes has been constructed.• The construction of the EHV Substation in Lagada and the construction of EHV the Substation in Nea Santa werecontinued.• The construction of the GIS Substation in Atherinolakkos was continued.• The construction of Skala substation has been completed.• The expansion of substations Aitolikou, Platamona, Methanon, Rethymnou, Ioannina I and Ioannina II was completed.• The construction of the new GIS Substation in Heraklio Ι has been completed.• The construction of the 400 kV Aliveri – System transmission line (overhead and underground) was continued.• The conductor replacement of the 150 kV Sitia – Ierapetra transmission line was completed.• The construction of the 150 kV Skala – System was completed.• The refurbishing of the 150 kV Alexandroupoli – Didimotixo transmission line was started.• The construction of the 400 kV Amyntaio-Lagadas transmission line was continued.• The construction of the 150 kV Rethymno – Spili transmission line was started.• Furthermore expansions or reinforcements in many 150/20 kV Substations have been completed.• The construction of the cable lines 150 kV Heraklio I-Transmission System and the construction of cable line Finikas-Nea Helvetia have been completed.• The installation of the 150 kV shunt capacitor bank at Velos substation was completed.• The installation of 12 automated 20 kV capacitor control systems were completed in 8 substations.• The environmental impact study of the EHV Patras was completed.• The environmental impact study for the following projects was completed.o EHV Megalopoli substation and its companion transmission lines.o 400 kV transmission line of EHV Megalopoli substation to EHV Patra substation.• 10 new environmental studies for Lines and Substations have been submitted.• The public deliberation concerning the issues of the Declaration of the connection of Cycladic Islands with theconnected Transmission System has been completed.Distribution Business UnitCapital expenditure amounted to Euro 462.7 millionDevelopment & Exploitation of Distribution Network1,800 km of new MV Network have been manufactured as well as 2,200 km of new LV Network and 3,200 new transformerswere installed, while there were 8,000 network removals.Distribution Network Users came to 7,564,7777 of which 9,961 are connected to MV.12

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!