24.08.2015 Views

Stage 2F Acid Sulphate Soils Management Plan - Newcastle Coal ...

Stage 2F Acid Sulphate Soils Management Plan - Newcastle Coal ...

Stage 2F Acid Sulphate Soils Management Plan - Newcastle Coal ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Acid</strong> Sulfate Soil <strong>Management</strong> <strong>Plan</strong>PREFACEIn accordance with Condition 1.10, Schedule 2 of the Project Approval (06_0009), the specified time period forthis <strong>Acid</strong> Sulfate Soil <strong>Management</strong> <strong>Plan</strong> (ASSMP) is for the <strong>Stage</strong> <strong>2F</strong> construction phase (i.e. approximately25 months commencing in the first quarter of 2012) of the <strong>Newcastle</strong> <strong>Coal</strong> Infrastructure Group <strong>Coal</strong> ExportTerminal up to 66 million tonnes per annum capacity. Notwithstanding, any subsequent revision of this CNMPduring the Project construction phase will be submitted to the Director-General of the Department of <strong>Plan</strong>ning andInfrastructure for approval.1 INTRODUCTIONThe <strong>Newcastle</strong> <strong>Coal</strong> Infrastructure Group (NCIG) <strong>Coal</strong> Export Terminal (CET) (the Project) is located onKooragang Island in <strong>Newcastle</strong>, New South Wales (NSW) (Figure 1). The overall Project includes theconstruction and operation of a CET up to 66 million tonnes per annum (Mtpa), including associated rail and coalhandling infrastructure and wharf/shiploading facilities on the south arm of the Hunter River.NCIG is the proponent of the Project and is a consortium of the following six companies:Hunter Valley Energy <strong>Coal</strong> Limited;Centennial <strong>Coal</strong> Company Limited;Gloucester <strong>Coal</strong> Pty Limited;Peabody Energy Australia <strong>Coal</strong> Pty Limited;Yancoal Australia Limited; andWhitehaven <strong>Coal</strong> Limited.NCIG was granted Project Approval (06_0009) on 13 April 2007. Construction of <strong>Stage</strong> 1 of the Projectcommenced in January 2008, with operations of the <strong>Stage</strong> 1 Project components commencing in the third quarterof 2010. These works allow the CET to operate up to the initial Project capacity of 30 Mtpa. The <strong>Stage</strong> 1 Projectcomponents included the construction of:rail infrastructure including one train unloading station;the southern portion of the coal storage area including two combined stacker/reclaimers; andwharf facilities including one shiploader and two shipping berths.The <strong>Stage</strong> 2AA construction activities commenced in the fourth quarter of 2010. The construction phase isexpected to continue until mid-2012 and, when complete, will increase the capacity of the CET to 53 Mtpa. The<strong>Stage</strong> 2AA Project components include the construction of:a second train unloading station and associated rail infrastructure;a portion of the coal storage area including a third combined stacker/reclaimer; anda second shiploader.<strong>Stage</strong> <strong>2F</strong> of the Project is anticipated to commence in the first quarter of 2012 and the construction phase isexpected to take approximately two years. When <strong>Stage</strong> <strong>2F</strong> activities are complete the CET will be able to operateat the maximum approved capacity of 66 Mtpa. The <strong>Stage</strong> <strong>2F</strong> Project components will include the construction of(Figure 2):the northern portion of the coal storage area including the fourth combined stacker reclaimer; andwharf facilities including the third shipping berth (K10); andThe northern rail spur will be constructed as a separate package of works, and as such does not form a part ofthis ASSMP.1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!