Create
Final Report - Acare
Final Report - Acare
- No tags were found...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
48<br />
The incubation contractor should be under an<br />
obligation to report at once any work having<br />
the effect of rendering the basic concept<br />
technically non-viable. The contract terms<br />
should permit termination of the contract in<br />
appropriate cases.<br />
The incubation contractor should be required<br />
to report against the envisaged output of the<br />
incubation.<br />
The contracts should take into account<br />
the original submission, the nature of the<br />
exploration to be conducted, the importance<br />
of the originating person or group, and the<br />
availability of appropriate competences.<br />
6.7.6. Testing Incubation<br />
The incubation process has not been tested<br />
during the CREATE project. It was never the<br />
intention to do so and this for several reasons:<br />
• The time span of the project was limited and<br />
insufficiently long to develop the approach<br />
to incubation and carry out a test of the<br />
process within the project span.<br />
• The testing of a single idea and building<br />
conclusions from that test is not aligned<br />
to the reality that incubation will only be<br />
expected to have positive results (i.e. to<br />
spawn successful mainstream projects) in a<br />
minority of cases.<br />
• The scope for funding such an experiment<br />
was not feasible within the project funds<br />
allocated.<br />
• The process of incubation itself is relatively<br />
straightforward.<br />
However, all other parts of the work intended<br />
to support the Work Package have been tested<br />
with team and external workshops being used<br />
to test ideas and confirm their applicability.<br />
6.7.7. Lessons Learnt<br />
During the CREATE project the following lessons<br />
were learnt about the incubation process and its<br />
implementation:<br />
• There are no existing mechanisms that fit<br />
the needs described by the CREATE project.<br />
• Project proposals can be expected both<br />
from the supporting processes described in<br />
CREATE and directly from enterprises with<br />
the competence to make them.<br />
• In order to convince industrial enterprises<br />
to undertake the exploratory research<br />
required in incubation the work will need<br />
to be funded at close to the 100% level.<br />
6.7.8. Compliance with project aims<br />
Within the limitation of the original plan<br />
which did not provide for actually testing an<br />
incubation process the aims of the project<br />
have been discharged. The incubation<br />
phase has been defined, the way in which<br />
incubation contracts could be placed has<br />
been proposed and the output from an<br />
incubation contract has been generically<br />
defined. Given that the processes necessary<br />
to place and successfully execute incubation<br />
contracts have not been demonstrated there<br />
is a desire to begin the process by using the<br />
mechanisms that exist in Framework 7 to<br />
conduct a process trial. This could well be<br />
separated from the implementation of the<br />
CREATE process in Framework Programme<br />
8. The conditions suitable for such a trial are<br />
discussed in section 7 below.<br />
6.8. IPR and the CREATE Process<br />
It is proposed that the CREATE process should<br />
follow the IPR principles and practice developed<br />
for Framework Programme 7 as far as they can<br />
be adapted to this purpose.<br />
It is not expected, but must be allowed for,<br />
that pre-existing IPR will be a significant<br />
factor in developing the ideas submitted<br />
for incubation. Incubation may be the first<br />
real stage where Foreground knowledge is<br />
developed and this must not be allowed to<br />
become a lock on the development of the<br />
idea in further research. Recommendations for<br />
applying the FP7 principles are made in more<br />
detail in Appendix D.<br />
7. Implementation Issues<br />
The step from the work of CREATE to<br />
implementing a structure for stimulating<br />
innovation is a significant one. A number of<br />
issues have to be resolved that are above and<br />
beyond the fundamental decision of whether<br />
the funding can be obtained. These issues are:<br />
e) The CREATE process owner.<br />
f) How the management of the process<br />
should be provided for and in particular<br />
whether the process should be<br />
administered by the European Commission<br />
or by an agency.<br />
g) Making a start to incubation under<br />
Framework Programme 7<br />
h) Continuing development of the process<br />
under Framework Programme 8.<br />
i) How the stakeholder community of<br />
aviation can be engaged with the process.