<strong>Middle</strong> <strong>Fork</strong> <strong>Irrigation</strong> <strong>District</strong>


<strong>Middle</strong> <strong>Fork</strong> <strong>Irrigation</strong> <strong>District</strong> boundaries are the <strong>Middle</strong> <strong>Fork</strong> of the Hood River on the west and the East <strong>Fork</strong> of the Hood<br />

River on the east and north. On the south the watershed for the <strong>District</strong> extends onto the northern slopes of Mt. Hood and<br />

includes Eliot, Langille and Coe Glaciers. The small town of Parkdale, is located near the center of MFID irrigated lands.<br />

Locally the area is described as being in the Upper Hood River Valley.


Hydroelectric power is generated at three locations year around as an integral part of the <strong>Middle</strong> <strong>Fork</strong><br />

<strong>Irrigation</strong> <strong>District</strong> water distribution system. Within each powerhouse are water turbine generators, control<br />

panels and the required hydraulic control and station service equipment. The three powerhouses, allowing<br />

for differences in turbine configuration and site requirements, are similar in design and construction. Pelton<br />

water turbines are used in powerhouses one and three, where water is returned to the stream at<br />

atmospheric pressure. The Francis turbine in powerhouse two is a totally enclosed pipeline system, where<br />

the operating head is determined by downstream conditions. Financing for the hydroelectric project totaled<br />

7.5 million dollars.


Clear Branch Dam<br />

Laurance Lake Reservoir<br />

The dam is an earth and rock zone fill<br />

approximately 1350 feet long with a top width<br />

of 28 feet. Height of the dam is 106 feet and<br />

water depth at the spillway crest elevation is<br />

100 feet. Construction was under the<br />

authority of the Watershed Protection and<br />

Flood Prevention Act (Public Law 566).<br />

When full the spillway elevation is<br />

2978 feet msl. The surface of<br />

Laurance lake is approximately 130<br />

acres.<br />

Minimum flow regimes below Clear Branch Dam are:<br />

3 cfs for the period starting July 10 and extending through October 7 of each year.<br />

50% of calculated reservoir inflow up to 20 cfs from October 8 through July 10.<br />

These flows can be reduced at the discretion of the fishery management agencies if t would be in the<br />

interest of fisheries resources to do so in so far as such reduction does not interfere with the primary<br />

function of the reservoir.


Old Coe Diversion<br />

The Coe Branch Diversion is located<br />

approximately 0.8 miles upstream of the<br />

confluence with <strong>Middle</strong> <strong>Fork</strong> of Hood River,<br />

being within the SE ¼ NE ¼ Section 27 T 1<br />

S. R 9 E. Original construction was<br />

completed in December 1987. The Coe<br />

Creek Diversion was upgraded in the fall of<br />

2009. The dam and drop inlet grate<br />

structure was removed and replaced with a<br />

25 ft long angled concrete water entry wall,<br />

fish bypass channel and drop pools. An<br />

agency approved 50 foot FCA horizontal flat<br />

plate dual stage screen was installed. This<br />

resulted in the addition of 3 miles of<br />

upstream habitat for fish and met water<br />

quality standard objectives and restoration<br />

priorities in the Hood River Basin.<br />

New Coe Creek Diversion


Old Eliot Diversion<br />

Construction on the Eliot Branch Diversion was started September 13,<br />

1965 and was completed December 10, 1965. Due to glacial<br />

outbursts/debris torrent events the facilities have been<br />

replaced/repaired four times. The Eliot Diversion is located on Eliot<br />

Branch (Creek) approximately 1 mile upstream from the <strong>Middle</strong> <strong>Fork</strong><br />

Hood River, five miles southwest of Parkdale, OR in SW 1/4 NE 1/4<br />

Section 26, Township 1 South, Range 9 East of the Willamette<br />

Meridian.


In November 2006, a debris flow completely destroyed the Eliot diversion and<br />

the Eliot branch moved approx 1,000 feet to the East..


The Diversion facilities were rebuilt with a<br />

side channel inlet and criteria fish screen<br />

in the spring of 2007. From the diversion<br />

facilities water enters the Eliot ditch. The<br />

ditch provides conveyance of water from<br />

the point of diversion to the sediment<br />

basin. At the Sediment Basin waters from<br />

Clear Branch Dam, Coe Creek diversion<br />

and Eliot Diversion can be mixed and<br />

distributed into the system<br />

New Eliot Creek Diversion


Penstock Damage


Coe Damage