Rural Water News Spring 2008<br />
Mayo<br />
Ballycroy GWS recently<br />
appointed a part-time m<strong>an</strong>ager<br />
to help with the process of<br />
preparing for commissioning<br />
of their new water treatment<br />
pl<strong>an</strong>t.<br />
Commissioning has been<br />
delayed because of raw water<br />
quality issues. A drum filter<br />
is being installed upstream<br />
from the pl<strong>an</strong>t in order to<br />
address this issue.<br />
A 5 km section of critical<br />
mains has been replaced <strong>an</strong>d<br />
the process of switching consumers<br />
over to the new network<br />
is about to commence.<br />
This should reduce the<br />
amount of water loss on the<br />
network.<br />
***<br />
There are similar raw water<br />
issues in Killeen GWS <strong>an</strong>d a<br />
drum filter is also being<br />
installed there.<br />
***<br />
A full-time m<strong>an</strong>ager has been<br />
appointed by Fahy GWS.<br />
The DBO treatment pl<strong>an</strong>t is<br />
at <strong>an</strong> adv<strong>an</strong>ced stage of construction,<br />
with Mech<strong>an</strong>ical &<br />
Electrical installation progressing<br />
well.<br />
Commissioning of the pl<strong>an</strong>t<br />
should take place in April or<br />
early May.<br />
***<br />
Nine of the thirteen pl<strong>an</strong>ts in<br />
Mayo DBO bundle 1 are now<br />
operational. They include<br />
B r a c k l o o n / S p a d d a g h ,<br />
Laghta, Lough Carra,<br />
Drummin, Lough Mask/<br />
Creevagh, Kilmeena,<br />
Glenhest, Kilmovee/Urlaur,<br />
<strong>an</strong>d Belderrig.<br />
***<br />
The Part 8 pl<strong>an</strong>ning application<br />
for Mayo DBO bundle 2<br />
will go before the April<br />
meeting of Mayo County<br />
Council. This process was<br />
delayed following the intervention<br />
of The National Parks<br />
& Wildlife Service who<br />
raised concerns about pl<strong>an</strong>s<br />
for some schemes in the bundle<br />
that are located in Special<br />
Areas of Conservation<br />
(SACs).<br />
TSSL Ltd won the tender for<br />
for this bundle <strong>an</strong>d contracts<br />
will be signed following the<br />
formal gr<strong>an</strong>ting of pl<strong>an</strong>ning<br />
permission for the various<br />
works.<br />
***<br />
Almost 50 km of piping has<br />
been laid by Carty<br />
Contractors out of a total of<br />
90 km in the adv<strong>an</strong>ce works<br />
contract. Currently the contract<br />
is running 2 months<br />
ahead of schedule.<br />
Most of this pipe has been<br />
laid in the PBKS (Prizon,<br />
Ballyvary, Keelogues &<br />
Straide) area.<br />
***<br />
Mayo RWMC held its quarterly<br />
meeting in Castlebar on<br />
Wednesday 26 March.<br />
The meeting heard that the<br />
l<strong>an</strong>d ownership dispute that<br />
has delayed construction of<br />
the DBO treatment pl<strong>an</strong>t at<br />
Glencorrib GWS remains<br />
unresolved.<br />
A resolution passed at a<br />
Special General Meeting of<br />
Glecorrib members on 29<br />
J<strong>an</strong>uary reads ‘that this SGM<br />
of Glencorrib GWS here<br />
authorises <strong>an</strong>d instructs the<br />
m<strong>an</strong>agement committee to<br />
take whatever action is<br />
deemed necessary to protect<br />
our existing rights <strong>an</strong>d legal<br />
entitlements at out intake<br />
works <strong>an</strong>d pumping station<br />
site, at Lough Corrib <strong>an</strong>d to<br />
secure this site for the completion<br />
of our new water<br />
treatment pl<strong>an</strong>t <strong>an</strong>d associated<br />
works.’<br />
***<br />
Logboy GWS <strong>an</strong>d Sraheens<br />
(Aghagower) GWS have<br />
connected to the public main.<br />
Coogue, Larg<strong>an</strong>boy <strong>an</strong>d<br />
Holywell schemes are still<br />
awaiting permission to connect.<br />
Upgrading of Keenagh<br />
GWS is in progress <strong>an</strong>d<br />
should be completed by mid-<br />
2008.<br />
***<br />
Kilcummin, Moyne/Meelick,<br />
Rathoma, Tooreen/Fotish,<br />
Tiernaur were recently takenin-charge.<br />
The takeover of<br />
process is well adv<strong>an</strong>ced in<br />
the case of Brize,<br />
Cloonfinnaun, Cloongull<strong>an</strong>e,<br />
Logacurra, Farragh, Lakehill,<br />
Bollingl<strong>an</strong>a <strong>an</strong>d Rookfield<br />
Group Water Schemes.<br />
Recently-appointed m<strong>an</strong>agers from four County Mayo group water schemes, joined three schemes from Sligo’s South East DBO bundle for training<br />
in the NFGWS Quality assur<strong>an</strong>ce system. The course was held in the<br />