1 st Case study : Conversion from 2 pass overburden to<br />

cast to place at Simplot Phosphates<br />

Mr Cassidy Mc Allister study: The Original Operation<br />

- The original operation was performed with 3 passes of 21m the<br />

higher cover, 12m the lower cover and in the end the phosphate.<br />

- Each Passes included a drill and blast followed by truck and shovel<br />

removal.<br />

- The pit width was 100 m and the cast to place was around 7%.<br />

18