DIRECTORS’ REPORT<br />
4. Solutions Centre Activity<br />
Your Company’s Solutions Centre Activitys provides<br />
a complete range of electrical solutions for industries<br />
and utilities, from substations to power distribution<br />
systems, with proven expertise in handling projects<br />
from concept to completion. Our range of offerings<br />
cover intake/ evacuation sub-stations, electrical<br />
balance of plant (eBoP), electrical distribution<br />
systems, medium and low voltage packages,<br />
customised packages for specific needs, power<br />
distribution for infrastructure, providing extended<br />
warranty and long term maintenance support.<br />
During the year, your company’s Solution Centre<br />
maintained its leadership as a key player in the<br />
project business market segments and also entered<br />
into new business segments such as Cement,<br />
Mining & Metal, Powergen, Renewables, Oil &<br />
Gas, Infrastructure and others. It notched up<br />
several successes in commissioning of complex<br />
projects in these segments. Some of these projects<br />
are highlighted below.<br />
Regen Powertech<br />
Your Comany’s Solution Centre teams achieved<br />
a record by delivering Regen Powertech’s Wind<br />
based power plant ahead of the target schedule<br />
for the project.<br />
Daimler India<br />
Daimler India is the second reference in the<br />
Automobile segment that has been commissioned<br />
by the Solution Centre. This project involved supply,<br />
installation, testing and commissioning of Substation<br />
with associated cabling and SCADA system.<br />
Moserbaer, Patan<br />
Your Company’s Solution Centre teams<br />
demonstrated a high level of expertise with the<br />
commissioning of Moserbaer’s solar PV plant at<br />
Patan, Gujarat. To date, this is the highest capacity<br />
project commissioned by the teams and which<br />
includes main evacuation substation and pooling<br />
stations.<br />
Bajaj Infrastructure<br />
Bajaj Infrastructure’s 2x45 MW power plant at 5<br />
locations in UP has been commissioned while<br />
residual work is in progress. This is the key order<br />
we have executed in powergen segment. The job<br />
involved 132 kV evacuation substation, generator<br />
transformer, HT switchboards, GCB, SCADA and<br />
other associated supplies viz busducts, earthing<br />
etc.<br />
Azure Power<br />
Azure Power is the first ever Solar PV plant executed<br />
by Solution Centre. It added 10 MW capacity to<br />
the Grid. It involved 66/11 kV main evacuation<br />
substation and 11/0.3 kV pooling stations with<br />
associated cabling and other works.<br />
16 | Schneider Electric Infrastructure Limited