7 - REQUIREMENTS MONITORING AND CONTROLLING<br />
Key requirements should be identified and marked as such, and monitored continuously. These requirements,<br />
sometimes referred to as key performance indicators, are those requirements for which the inability to meet a<br />
threshold value puts the project at risk of failing to meet the business need of the organization.<br />
7.2 Requirements Monitoring and Controlling Activities<br />
After creating the traceability matrix during elicitation and analysis, requirements monitoring and controlling key<br />
processes include approving baseline requirements, managing changes to requirements, monitoring requirements<br />
status, and communicating results. Once the requirements baseline is established, the person primarily responsible<br />
for the requirements ensures that they are managed and that changes to the requirements are addressed through<br />
the defined change management process. Figure 7-1 describes the process flow.<br />
Requirements Monitoring and Controlling<br />
Requirements<br />
Planning<br />
Iterative Functions<br />
Iteratively Plan<br />
Requirements<br />
Monitoring and<br />
Controlling<br />
Trace<br />
Requirements<br />
Baseline<br />
Requirements<br />
Monitor<br />
Requirements<br />
Manage<br />
Change to<br />
Requirements<br />
Approve Requirements<br />
and Communicate<br />
Document and<br />
Communicate Results<br />
Figure 7-1. Requirements Monitoring and Controlling Activities Diagram<br />
7.2.1 Prepare for Requirements Monitoring and Controlling<br />
Requirements monitoring and controlling planning is completed during requirements management planning and<br />
considers interactions among the requirements elicitation, analysis, and evaluation domains. Because requirements<br />
monitoring and controlling activities occur across all of these domains, decisions about how requirements will be<br />
controlled and traced should be made before the creation of requirements and captured within the requirements<br />
management plan.<br />
7.2.1.1 Set Up System for Managing Requirements and Traceability<br />
Identification of the appropriate requirements management methods and tools for a project was discussed in<br />
Section 4.2.3. In order to monitor and control requirements, a tool may be purchased or used. This tool should be<br />
made available, with the appropriate training provided to the requirements management team before initiating the<br />
elicitation and analysis domains.<br />
44 ©2016 Project Management Institute. Requirements Management: A Practice Guide