7 - REQUIREMENTS MONITORING AND CONTROLLING<br />

Once the requirements have been baselined, any suggested change to requirements initiates the change<br />

management process. Changes need to be analyzed, which typically involves performing an impact analysis to<br />

evaluate the proposed change in relation to how it will affect other requirements, the product, the project, and the<br />

program. Additional information on impact analysis can be found in Section 7.3.2.<br />

There can be less formality in approving requirements in an adaptive approach, yet there should still be some<br />

norm or informal agreement on what should be approved, how it should be approved, and when it should be<br />

approved. The product owner is the primary point of contact for adaptive projects and is, therefore, ultimately<br />

responsible for approving requirements.<br />

7.2.4 Manage Requirements Change Requests<br />

A change request process should be defined in the planning domain. Managing change requests involves<br />

following the defined process for the project to ensure that changes are managed and requirements are updated<br />

only once the approved change management protocols are followed.<br />

In an adaptive life cycle, the defined change request process commonly adds new requirements to the<br />

backlog, and then adds planning sessions for follow-up iterations or sprints to review the entire backlog and use<br />

a prioritization process to determine the next set of features for the subsequent iteration or sprint. This approach<br />

provides multiple opportunities to address new or modified requirements over the course of a project.<br />

The Practice Standard for Project Configuration Management defines in detail the configuration change<br />

management process. Applying configuration change management principles may provide a number of assurances,<br />

including:<br />

• The correct version of the configuration item is in use by the project team;<br />

• Changes to configuration items are made only by authorized individuals;<br />

• A planned means of notifying stakeholders of approved changes to configuration items is in place; and<br />

• A record of configuration item changes is kept to support auditing and project closure activities.<br />

PMI defines the following individual phases of the configuration change management process in the Practice<br />

Standard for Project Configuration Management :<br />

• Establish baseline,<br />

• Submit change request,<br />

• Verify change request,<br />

• Evaluate impacts,<br />

• Review decision and plan,<br />

• Implement change if approved, and<br />

• Conclude change process.<br />

Impacts of this process should be communicated and monitored (see also Section 7.2.6).<br />

46 ©2016 Project Management Institute. Requirements Management: A Practice Guide