7 - REQUIREMENTS MONITORING AND CONTROLLING<br />
Once the requirements have been baselined, any suggested change to requirements initiates the change<br />
management process. Changes need to be analyzed, which typically involves performing an impact analysis to<br />
evaluate the proposed change in relation to how it will affect other requirements, the product, the project, and the<br />
program. Additional information on impact analysis can be found in Section 7.3.2.<br />
There can be less formality in approving requirements in an adaptive approach, yet there should still be some<br />
norm or informal agreement on what should be approved, how it should be approved, and when it should be<br />
approved. The product owner is the primary point of contact for adaptive projects and is, therefore, ultimately<br />
responsible for approving requirements.<br />
7.2.4 Manage Requirements Change Requests<br />
A change request process should be defined in the planning domain. Managing change requests involves<br />
following the defined process for the project to ensure that changes are managed and requirements are updated<br />
only once the approved change management protocols are followed.<br />
In an adaptive life cycle, the defined change request process commonly adds new requirements to the<br />
backlog, and then adds planning sessions for follow-up iterations or sprints to review the entire backlog and use<br />
a prioritization process to determine the next set of features for the subsequent iteration or sprint. This approach<br />
provides multiple opportunities to address new or modified requirements over the course of a project.<br />
The Practice Standard for Project Configuration Management defines in detail the configuration change<br />
management process. Applying configuration change management principles may provide a number of assurances,<br />
including:<br />
• The correct version of the configuration item is in use by the project team;<br />
• Changes to configuration items are made only by authorized individuals;<br />
• A planned means of notifying stakeholders of approved changes to configuration items is in place; and<br />
• A record of configuration item changes is kept to support auditing and project closure activities.<br />
PMI defines the following individual phases of the configuration change management process in the Practice<br />
Standard for Project Configuration Management :<br />
• Establish baseline,<br />
• Submit change request,<br />
• Verify change request,<br />
• Evaluate impacts,<br />
• Review decision and plan,<br />
• Implement change if approved, and<br />
• Conclude change process.<br />
Impacts of this process should be communicated and monitored (see also Section 7.2.6).<br />