01.06.2016 Views

Rail conquers the Alps

1spJ1Ka

1spJ1Ka

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

GOTTHARD BASE TUNNEL | SWITZERLAND<br />

handling are essential to ensure that<br />

<strong>the</strong> right components are in precisely<br />

<strong>the</strong> right place at <strong>the</strong> right time. Many<br />

items of equipment are mass-produced<br />

and have to be ordered in good<br />

time and <strong>the</strong>n supplied and delivered,<br />

all <strong>the</strong> time meeting <strong>the</strong> required quality<br />

standards. Components are stored<br />

temporarily at <strong>the</strong> work bases and<br />

sorted according to <strong>the</strong> requirements<br />

for each shift or day before <strong>the</strong>y are<br />

taken into <strong>the</strong> tunnel.<br />

Commissioning<br />

The commissioning process will<br />

be carried out in several stages. Once<br />

installation is complete, every single<br />

component will be tested to ensure<br />

that it functions correctly. The first<br />

section to be completed will be <strong>the</strong><br />

west bore between Faido and Bodio,<br />

which has been designated as <strong>the</strong> initial<br />

test section. More than 15 km long,<br />

it will be used from 2013 for tests at up<br />

to 200 km/h, allowing <strong>the</strong> complex interworking<br />

of all items of equipment<br />

to be thoroughly tested. Any lessons<br />

learnt from this test phase will be applied<br />

to <strong>the</strong> remaining sections of <strong>the</strong><br />

tunnel.<br />

Only when <strong>the</strong>se tests have been<br />

completed can <strong>the</strong> actual commissioning<br />

start. This will be organised in<br />

two phases.<br />

In Phase A AlpTransit Gotthard<br />

The Biasca<br />

work base near<br />

<strong>the</strong> sou<strong>the</strong>rn<br />

portal was<br />

used to prepare<br />

equipment and<br />

machinery to<br />

lay <strong>the</strong> first<br />

ballastless track<br />

on <strong>the</strong> Faido –<br />

Bodio section.<br />

AG as <strong>the</strong> tunnel contractor has to<br />

prove that <strong>the</strong> installations function<br />

correctly and that <strong>the</strong> safety requirements<br />

have been met. Test running is<br />

scheduled to take place over a period<br />

of several months to ensure that every<br />

component works faultlessly.<br />

In Phase B <strong>the</strong> main responsibility<br />

switches to <strong>the</strong> future operator, SBB<br />

AG. Only when SBB has demonstrated<br />

that all is working flawlessly — with<br />

staff in place and test freight and passenger<br />

trains operating — will <strong>the</strong> Federal<br />

Transport Office grant permission<br />

for <strong>the</strong> start of commercial services.<br />

SBB will also need to prove that it can<br />

cope with any kind of incident happening<br />

within <strong>the</strong> tunnel. l<br />

<strong>Rail</strong>way Gazette International | July 2011 43

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!