ceneri base tunnel | switzerland<br />
dismantling of existing and temporary<br />
structures. A contract to build <strong>the</strong><br />
1 km viaduct on <strong>the</strong> Lugano – Bellinzona<br />
line was signed on December<br />
16 2010 and work began on what<br />
will be <strong>the</strong> centrepiece of <strong>the</strong> Nodo di<br />
Camorino in early 2011. Construction<br />
of <strong>the</strong> 400 m long viaduct for <strong>the</strong> Bellinzona<br />
– Lugano track is due to commence<br />
in 2012.<br />
Sou<strong>the</strong>rn portal works<br />
To ensure that excavation of <strong>the</strong> running<br />
tunnel over <strong>the</strong> PTL road tunnel<br />
close to <strong>the</strong> sou<strong>the</strong>rn portal at Vezia<br />
was complete before <strong>the</strong> road opened, a<br />
start was made on driving a 300 m section<br />
in <strong>the</strong> opposite direction in spring<br />
2010. Progress was aided by favourable<br />
geology and co-operation from <strong>the</strong> local<br />
community, so that <strong>the</strong> point where<br />
<strong>the</strong> two tunnels cross was reached<br />
ahead of schedule in July 2010.<br />
By <strong>the</strong> end of 2010 <strong>the</strong> drive had<br />
progressed beyond <strong>the</strong> critical area,<br />
and in April 2011 <strong>the</strong> 300 m top section<br />
for both single-track running<br />
tunnels was fully excavated. Around<br />
200 m of <strong>the</strong> lower part of <strong>the</strong> tunnel<br />
has still to be excavated. Now in<br />
progress is a 170 m section of open<br />
cut that will be covered over later.<br />
Several structures are required for<br />
<strong>the</strong> next section, which runs in <strong>the</strong><br />
open as far as <strong>the</strong> Massagno tunnel.<br />
These include a 650 m long retaining<br />
wall above <strong>the</strong> SBB main line as well<br />
as sound barriers. Being carried out<br />
in conjunction with SBB, this work is<br />
currently on schedule.<br />
Construction of <strong>the</strong> Ceneri base<br />
tunnel will absorb around SFr2∙5bn<br />
of <strong>the</strong> SFr12∙3bn total cost of building<br />
<strong>the</strong> Gotthard low-level corridor.<br />
About SFr724m had been spent by<br />
<strong>the</strong> end of 2010 and contracts signed<br />
for <strong>the</strong> Ceneri Base Tunnel to date are<br />
toge<strong>the</strong>r worth SFr2∙1bn, keeping <strong>the</strong><br />
project within budget. l<br />
The extensive<br />
construction<br />
site at Sigirino<br />
includes <strong>the</strong> main<br />
spoil disposal<br />
area.<br />