ceneri base tunnel | switzerland<br />

dismantling of existing and temporary<br />

structures. A contract to build <strong>the</strong><br />

1 km viaduct on <strong>the</strong> Lugano – Bellinzona<br />

line was signed on December<br />

16 2010 and work began on what<br />

will be <strong>the</strong> centrepiece of <strong>the</strong> Nodo di<br />

Camorino in early 2011. Construction<br />

of <strong>the</strong> 400 m long viaduct for <strong>the</strong> Bellinzona<br />

– Lugano track is due to commence<br />

in 2012.<br />

Sou<strong>the</strong>rn portal works<br />

To ensure that excavation of <strong>the</strong> running<br />

tunnel over <strong>the</strong> PTL road tunnel<br />

close to <strong>the</strong> sou<strong>the</strong>rn portal at Vezia<br />

was complete before <strong>the</strong> road opened, a<br />

start was made on driving a 300 m section<br />

in <strong>the</strong> opposite direction in spring<br />

2010. Progress was aided by favourable<br />

geology and co-operation from <strong>the</strong> local<br />

community, so that <strong>the</strong> point where<br />

<strong>the</strong> two tunnels cross was reached<br />

ahead of schedule in July 2010.<br />

By <strong>the</strong> end of 2010 <strong>the</strong> drive had<br />

progressed beyond <strong>the</strong> critical area,<br />

and in April 2011 <strong>the</strong> 300 m top section<br />

for both single-track running<br />

tunnels was fully excavated. Around<br />

200 m of <strong>the</strong> lower part of <strong>the</strong> tunnel<br />

has still to be excavated. Now in<br />

progress is a 170 m section of open<br />

cut that will be covered over later.<br />

Several structures are required for<br />

<strong>the</strong> next section, which runs in <strong>the</strong><br />

open as far as <strong>the</strong> Massagno tunnel.<br />

These include a 650 m long retaining<br />

wall above <strong>the</strong> SBB main line as well<br />

as sound barriers. Being carried out<br />

in conjunction with SBB, this work is<br />

currently on schedule.<br />

Construction of <strong>the</strong> Ceneri base<br />

tunnel will absorb around SFr2∙5bn<br />

of <strong>the</strong> SFr12∙3bn total cost of building<br />

<strong>the</strong> Gotthard low-level corridor.<br />

About SFr724m had been spent by<br />

<strong>the</strong> end of 2010 and contracts signed<br />

for <strong>the</strong> Ceneri Base Tunnel to date are<br />

toge<strong>the</strong>r worth SFr2∙1bn, keeping <strong>the</strong><br />

project within budget. l<br />

The extensive<br />

construction<br />

site at Sigirino<br />

includes <strong>the</strong> main<br />

spoil disposal<br />

area.<br />

<strong>Rail</strong>way Gazette International | July 2011 51