8<br />

421 Passons Boulevard Grade Separation<br />

THE BRUT FOrCE<br />

by<br />

stEvE roBErt<br />

gonZALEZ<br />

BrAun<br />

we are in the final months of<br />

construction of the Passons Boulevard<br />

Grade Separation, and the project is<br />

coming together. The major items of<br />

work in Stages 3 and 4 are finished.<br />

The bridge construction is complete<br />

with trains now running on the new<br />

track.<br />

Once trains were switched onto the<br />

new bridge in april, the construction<br />

of the pump station began. The pump<br />

station is 28 feet below grade at its<br />

deepest point and is located directly<br />

adjacent to the live railroad tracks. Because of the close proximity to the tracks, shoring was required in order to excavate the structure.<br />

Construction of the structure took about three months to complete and the mechanical and electrical work is now underway.<br />

In the past few months we have completed all of the curb and gutter along Passons Boulevard and rivera road. as well as most of the aC<br />

paving. Crews have been working extended hours and weekends in order to perform work on numerous change orders and still complete<br />

critical items of work on their scheduled dates. The PCC pavement on the Passons underpass was placed on September 11 and 12 and we<br />

are now in the process of finishing the remaining subcontracted items. Fencing, irrigation, landscaping and electrical work are ongoing<br />

through the project site.<br />

Passons Boulevard is scheduled to open to traffic in late October. Once Passons Boulevard is open to traffic, we will start Stage 5 of<br />

construction, which are the Serapis avenue Improvements. This work includes demo and removal of the existing at-grade crossing at<br />

the BNSF track and Serapis avenue, and the installation of curb and gutter, sidewalks, fencing, irrigation, planting and street lighting. we<br />

anticipate all work on the project to be complete by the end of November.<br />

Forming and placing rebar for pump station walls.<br />

Placing PCC pavement on Passons Boulevard.