INTRODUCTION 1<br />

The Eight Principles of Jumeirah Village 1<br />

The Jumeirah Village - Master Plan and Development <strong>Code</strong> 2<br />

Contents of the Development <strong>Code</strong> 2<br />

1. GENERAL PROVISIONS 3<br />

Section 1.01. Title 3<br />

Section 1.02. Authorities 3<br />

Section 1.03. Purpose & Intent 3<br />

Section 1.04. Applicability 3<br />

Section 1.05. Amendments 3<br />

Section 1.06. Measuring System 3<br />

2. REVIEW AUTHORITY 4<br />

Section 2.01. General Authority 4<br />

Section 2.02. Development <strong>Code</strong> Administrator 4<br />

Section 2.03. Development Review Board 4<br />

3. ZONE 6<br />

Section 3.01. Establishment of Zones 6<br />

Section 3.02. Official Zoning Map 6<br />

Section 3.03. Interpretation of Boundaries 6<br />

Section 3.04. Uniform Application of Zones 6<br />

4. USE 9<br />

Section 4.01. Types of Use 9<br />

Section 4.02. Use Categories 9<br />

Section 4.03. Conditional Use 9<br />

Section 4.04. Accessory Use or Structure 9<br />

Section 4.05. Temporary Use 12<br />

5. FORM CODE – <strong>MID</strong>-<strong>RISE</strong> LOTS 13<br />

Section 5.01. General 13<br />

Section 5.02. Building Configuration and Size 13<br />

Section 5.03. Building Setbacks 14<br />

Section 5.04. Urban Design 14<br />

Section 5.05. Architectural Treatments 14<br />

6. PARKING AND LOADING 17<br />

Section 6.01. Purpose and Type 17<br />

Section 6.02. General Provisions 17<br />

Section 6.03 Space Requirements 17<br />

Section 6.04. Space and Lot Design 17<br />

Section 6.05. Loading Areas 19


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

j u m e i r a h v i l l a g e - M I D R I S E d e v e l o p m e n t c o d e<br />

<br />

Introduction<br />

i n t r o d u c t i o n<br />

The Eight Principles of Jumeirah Village<br />

Jumeirah Village is a community designed to embody a vision<br />

of peace, harmony, health, and happiness – a community with<br />

the highest standards of quality of life created by capturing<br />

the best characteristics of Arab and Western culture. Overall,<br />

eight principles form the foundation of Jumeirah Village:<br />

Sense of Peace and Community<br />

Jumeirah Village promotes an environment that features<br />

peace and harmony among neighbors. Emphasis is placed<br />

upon creating an atmosphere that promotes friendship,<br />

family, healthy interaction and other dynamic traits that<br />

set the neighborhoods of this community apart from other<br />

development.<br />

Pedestrian Friendliness<br />

Walking and biking are more than exercise. They are an<br />

invitation to meet friends, allow children to play, and live life<br />

at a slower pace. The design of Jumeirah Village promotes<br />

walking, biking and other alternatives through creation of a<br />

convenient and entertaining atmosphere, including features<br />

such as pedestrian access, landscaping, stores, street<br />

furniture, architectural detail, and open spaces.<br />

Water and Green Space<br />

Green spaces and water represent a healthy life and<br />

abundance in comparison to the stark beauty of the desert.<br />

Throughout Arab history, oases have served as attractions<br />

providing nourishment and focal points for gathering and<br />

association. Jumeirah Village celebrates the importance<br />

of greenery and water in the desert landscape through<br />

development of open spaces and water features that connect<br />

the neighborhoods and Zones of the community. Many of the<br />

public amenities found in Jumeirah Village including parks,<br />

sports fields, schools, mosques, and more are strategically<br />

clustered in the green spaces to create accessible gathering<br />

places reminiscent of the importance of the historic oasis.<br />

Mix of Symmetry and Natural Form<br />

Symmetry is a critical component of Islamic art, Arab<br />

architecture and Western urban design. However, many of<br />

the most successful communities and spaces in the world<br />

have “evolved” through a natural, organic pattern. Jumeirah<br />

Village is intentionally designed to capture a sense of<br />

symmetry through an organized radial pattern and median<br />

streets that end in a large-scale central park. At the same<br />

time, the design also allows neighborhoods and open spaces<br />

to occur in a more natural, pedestrian friendly manner.<br />

Mixed Use<br />

Actively mixed uses are a part of many of the most dynamic<br />

and successful communities throughout the world. Mixing<br />

uses promotes accessibility to major community features<br />

such as parks and commercial centers and provides natural<br />

gathering places for residents. Jumeirah Village intertwines<br />

uses in a manner that builds both economic viability and a<br />

sense of community.<br />

Icons and Focal Points<br />

Landmarks are an important component of the community as<br />

a tool for sense of direction, community recognition, and local<br />

pride. The unique towers, the central park, the interconnected<br />

series of open spaces, the meandering water feature, and<br />

the town centers are all icons that are unique to Jumeirah<br />

Village.<br />

Strong Public Space & Private Space<br />

A home is recognized as a place for privacy throughout Arab<br />

and Western culture. Today, the opportunity for privacy is<br />

increasingly more important as a healthy escape from the<br />

bustle of life. At the same time, however, public spaces<br />

are expected to be locations of significant and dynamic<br />

interaction – places for gathering, relaxing, entertaining, and<br />

shopping. Jumeirah Village offers a broad range of choices<br />

for privacy and proximity to public space. The best of both<br />

worlds is found throughout the community.<br />

Health and Happiness<br />

Jumeirah Village - is a living and working environment<br />

that offers superior quality of life, including a healthy and<br />

enjoyable living environment. The numerous, interconnected<br />

green spaces and clustered gathering spaces are<br />

intentionally designed to promote a healthy physical lifestyle.<br />

Neighborhoods are intended to promote social interaction.<br />

Jumeirah Village was created by applying these Eight<br />

Principles throughout the design process. Neighborhoods<br />

are designed to be places of interaction and enjoyment that<br />

are always within easy walking distance of parks, public


J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e - o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

i n t r o d u c t i o n<br />

amenities, shopping needs, and friends. The streetscape<br />

is designed to be attractive, functional and inviting to both<br />

motorists and pedestrians. Jumeirah Village offers an<br />

immense number of choices in housing and neighborhoods<br />

amenities ranging from secluded villas to the bustle of living<br />

in the Town Center.<br />

The Jumeirah Village<br />

Master Plan and Development <strong>Code</strong><br />

Two documents guide the development of Jumeirah Village<br />

to ensure that the community reaches its full potential and<br />

appropriately applies the Eight Principles – The Master Plan<br />

and the Development <strong>Code</strong>. These documents work together<br />

to span the divide between the vision for Jumeirah Village<br />

and the standards necessary to ensure that all is completed<br />

according to plan.<br />

The Master Plan<br />

The purpose of the Master Plan is to set the general<br />

foundation for the physical design of Jumeirah Village. The<br />

Master Plan represents the physical layout of lots, open<br />

spaces and amenities throughout the site. The Master Plan<br />

also includes the overall design strategy that evolved from<br />

the initial Eight Principles for the project. It discusses the<br />

major features and characteristics that make Jumeirah<br />

Village unique, from the broad description of the relationship<br />

between neighborhoods, open spaces, streets, and centers<br />

to more detailed discussion of the appearance of the<br />

streetscape and the types of uses expected in the various<br />

community “centers”. The Master Plan establishes the<br />

general Circulation Plan for the community and, even here,<br />

the Eight Principles have been combined with the need for<br />

efficient and safe travel choices. The Master Plan document<br />

is accompanied by two Master Plan Maps – an illustrated<br />

map that generally depicts the look of a completed project<br />

and a digital map that delineates the specific location and<br />

coordinates of lots and spaces.<br />

The Development <strong>Code</strong><br />

The Master Plan is a guide, a detailed layout of spaces and<br />

Block Guidelines that provide clues to the detailed design<br />

of Jumeirah Village. The Development <strong>Code</strong> is a tool for<br />

implementing the Master Plan. It provides the regulatory<br />

framework that ensures structures and uses are located<br />

according to plan and that the anticipated high quality of life<br />

for residents, employees and guests in Jumeirah Village is<br />

realized. The Development <strong>Code</strong> is specifically designed to<br />

carry out several functions:<br />

A. Ensure design that promotes the highest principles of<br />

general health, welfare and safety for individuals that<br />

live, work or visit the community.<br />

B. Provide the minimum standards needed to carry out<br />

the vision established by the Master Plan. The intent of<br />

the Development <strong>Code</strong> is to focus, not reign in, creative<br />

freedom.<br />

C. Establish procedures needed for Jumeirah Village<br />

LLC to successfully carry out the requirements of the<br />

Development <strong>Code</strong>.<br />

D. Provide the tools to make sound decisions regarding the<br />

inevitable evolution of Jumeirah Village. Communities<br />

must change over time to remain dynamic. However,<br />

change does not have to come at the cost of maintaining<br />

the Eight Principles that make Jumeirah Village unique.<br />

This <strong>Code</strong> ensures that sufficient information and<br />

procedures are available to allow the community, and<br />

the tools used to guide development in the community,<br />

to change in ways that benefit Jumeirah Village over the<br />

long term.<br />

Contents of the Development <strong>Code</strong><br />

The Development <strong>Code</strong> for Jumeirah Village is designed<br />

to address a broad range of issues important to carrying<br />

out the functions described above and meeting the Eight<br />

Principles that serve as the foundation for the community. The<br />

guidelines address many issues common to all communities,<br />

but once again, they also show an attention to detail unique<br />

to Jumeirah Village. For example, traditional streets are<br />

designed with sufficient width to provide parking but codes<br />

commonly require that a development accommodate all<br />

potential parking on the site. In Jumeirah Village, however,<br />

on-street parking is strongly encouraged and is considered<br />

part of meeting parking requirements.<br />

Contents of the Development <strong>Code</strong> are broken down as<br />

follows:<br />

A. General Provisions. Introduce the Development <strong>Code</strong> and<br />

provide the purpose, intent and applicability of the <strong>Code</strong>.<br />

B. Review Authority. Confirms Jumeirah Village LLC as the<br />

ultimate authority regarding development in Jumeirah<br />

Village and designates representatives responsible for<br />

carrying out the daily duties of administering the <strong>Code</strong>.<br />

C. Zones. Divides the community into areas of common<br />

interest and typology for purposes of regulation.<br />

D. Use. Designates permitted uses in each of the zones of<br />

Jumeirah Village.<br />

E. Form. Addresses the location, size and design of all<br />

structures in the community.<br />

F. Parking. Establishes guidelines for provision, location,<br />

type and design of parking areas.<br />

G. Signs. Discusses permitted sign types by purpose,<br />

location, size, number, intent, and detail.<br />

H. Landscape and Fencing. Acknowledges the benefits of<br />

adding “green spaces” and screening to the community<br />

as a means of “softening” the built environment,<br />

improving aesthetics, and adding additional opportunities<br />

for recreation.<br />

I. Administration and Procedures. Provides the tools and<br />

processes needed to administer the Development <strong>Code</strong>.<br />

J. Definitions. Describes the various technical or specific<br />

terms found throughout the Development <strong>Code</strong>.<br />

K. Application Checklists. Ensure that appropriate and<br />

sufficient information is conveyed by the potential<br />

applicant to Jumeirah Village LLC when requesting to<br />

develop a site.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

<br />

1. General Provisions<br />

Section 1.01. Title<br />

This Development <strong>Code</strong> is hereby officially known as the<br />

“Jumeirah Village - South Development <strong>Code</strong>”. References<br />

to “this <strong>Code</strong>” shall be interpreted as references to the<br />

Jumeirah Village Development <strong>Code</strong>.<br />

Section 1.02. Authorities<br />

1.02.01. Authority of Jumeirah Village LLC<br />

Jumeirah Village LLC is responsible for promoting and control<br />

of development of Jumeirah Village. As a result, Jumeirah<br />

Village LLC is granted the authority to establish regulations<br />

and guidelines to manage the use and development of all<br />

land, water and structures within the boundaries of Jumeirah<br />

Village. Jumeirah Village LLC shall have the right to approve<br />

or deny all applications for development within Jumeirah<br />

Village.<br />

In accordance with the recital on the property title, Jumeirah<br />

Village LLC has the authority to:<br />

A. Implement and ensure compliance with this <strong>Code</strong>.<br />

B. Appoint an authority or individual to review and approve<br />

or deny a Concept Plan, Site Plan or Building Permit.<br />

C. Amend and interpret this code, as needed.<br />

D. Establish and enforce additional rules, guides and<br />

requirements, as determined to be appropriate.<br />

1.02.02. Authority of Other Entities<br />

Nothing in this <strong>Code</strong> relieves the developer or landowner<br />

from the responsibility to acquire all additional permits or<br />

approvals as needed for site development or construction<br />

in Jumeirah Village, including, but not limited to approval<br />

from Dubai Municipality (DM), Dubai Electricity and Water<br />

Authority (DEWA), Dubai Ports, Customs and Free Zone<br />

Corporation, and the Department of Civil Defence.<br />

Section 1.03. Purpose & Intent<br />

This <strong>Code</strong> is established for the purpose of promoting the<br />

public health, safety and general welfare of the present and<br />

future residents, employees and guests of Jumeirah Village<br />

and promoting safe, orderly and healthful development. The<br />

Master Plan for Jumeirah Village is the fundamental guide<br />

to all decisions made under this <strong>Code</strong>. This <strong>Code</strong> regulates<br />

development in order to achieve objectives of the plan that<br />

include, but are not limited to, the following:<br />

A. Implement the Block Guidelines established in the plan<br />

and defined in this <strong>Code</strong> that dictate the character and<br />

pattern of development of the area.<br />

B. Enhance safety from fire, panic, and other dangers.<br />

C. Promote health and general welfare;<br />

D. Provide adequate light and air;<br />

E. Prevent or minimize conflicts or negative impacts among<br />

adjacent land uses.<br />

F. Facilitate adequate provision of transportation, water,<br />

wastewater, parks and open spaces, other public<br />

facilities.<br />

G. Maintain property values by stabilizing expectations and<br />

ensuring predictability in development.<br />

H. Establish a process that effectively and fairly applies the<br />

regulations and standards of this <strong>Code</strong>.<br />

Section 1.04. Applicability<br />

The regulations established by this <strong>Code</strong> shall be considered<br />

minimum requirements for development as follows:<br />

A. No building, structure or land shall be used or reused<br />

and no building or structure shall be constructed,<br />

reconstructed, occupied, moved, or structurally altered<br />

unless in conformity with the appropriate regulations<br />

established within this <strong>Code</strong>.<br />

B. No part of a yard, open space, off-street parking or<br />

loading space necessary for compliance by a building<br />

or structure for purposes of meeting the regulations<br />

of this <strong>Code</strong> shall be likewise used by another building<br />

or structure for compliance unless such shared use of<br />

resources is permitted by this <strong>Code</strong> and approved by<br />

Jumeirah Village LLC.<br />

C. All landscaping, parking, and signs shall be expected<br />

to meet the requirements of this <strong>Code</strong>. Approval shall<br />

be granted by Jumeirah Village LLC before a sign may<br />

be constructed, altered or otherwise displayed within<br />

Jumeirah Village.<br />

D. Yards and lots shall not be reduced below dimensions<br />

and area requirements established in this <strong>Code</strong>.<br />

Likewise, no structure or building shall be permitted to<br />

exceed requirements regarding bulk standards.<br />

E. In the event that requirements of this <strong>Code</strong> conflict or<br />

compete with requirements of other lawfully adopted<br />

rules, regulations, ordinances, or resolutions, the most<br />

restrictive shall apply.<br />

Section 1.05. Amendments<br />

Jumeirah Village LLC shall have the authority to amend<br />

this <strong>Code</strong>, as needed. Amendments shall be completed in<br />

accordance with Section 9, Administration & Procedures of<br />

this <strong>Code</strong>.<br />

1.05.01. New Development<br />

New development taking place after amendment to the<br />

Development <strong>Code</strong> shall be expected to meet requirements<br />

of the <strong>Code</strong> as amended. Development shall be required to<br />

meet an amended <strong>Code</strong> if an application for approval has not<br />

been submitted or a submitted application has not received<br />

approval prior to adoption of the new code amendment.<br />

1.05.02. Existing Development<br />

Existing development, including development that is under<br />

construction or has received approval by Jumeirah Village<br />

LLC, shall be exempt from meeting requirements established<br />

by code amendments adopted following application<br />

approval. Improvements to existing development shall meet<br />

requirements as amended at the time of application for<br />

approval of said improvements.<br />

Section 1.06. Measuring System<br />

The Standard International (SI) system of measurement shall<br />

be considered the accepted and official measuring system<br />

for this <strong>Code</strong>. All applications, figures and other materials<br />

submitted for approval shall utilize the Standard International<br />

system.<br />

G E N E R A L P R O V I S I O N S


J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

r e v i e w a u t h o r i t y<br />

2. Review Authority<br />

Section 2.01. General Authority<br />

2.01.01. Delegation of Authority<br />

As stated in Section 1.02.01, Authority of Jumeirah Village<br />

LLC, this section certifies that Jumeirah Village LLC is<br />

responsible for promoting and control of development of<br />

Jumeirah Village. As a result, Jumeirah Village LLC has the<br />

right to approve or deny all applications for development<br />

within Jumeirah Village. To assist in administration of these<br />

duties, Jumeirah Village LLC is authorized to delegate<br />

responsibilities, including but not limited to:<br />

A. Daily administration of this <strong>Code</strong>, the Master Plan for<br />

Jumeirah Village and other plans related to Jumeirah<br />

Village.<br />

B. Ability to receive, review, approve, request modification,<br />

or deny applications for development.<br />

C. Requests or decisions to amend or interpret this <strong>Code</strong>.<br />

D. Enforcement of the requirements established by this<br />

<strong>Code</strong>.<br />

2.01.02. Summary of Review Authority<br />

Jumeirah Village LLC hereby establishes a Jumeirah Village<br />

Development <strong>Code</strong> Administrator and a Development Review<br />

Board (DRB) for the purpose of administering the majority<br />

of activity related to this <strong>Code</strong>. Table 2.01, Roles and Duties,<br />

summarizes the purpose of each entity.<br />

2.01.03. Conformity with Development <strong>Code</strong><br />

No employee of Jumeirah Village LLC granted authority by<br />

this <strong>Code</strong> may approve or issue a permit for a development<br />

application that does not meet the provisions of this <strong>Code</strong>.<br />

Any approval or permit issued in conflict with the provisions<br />

of this <strong>Code</strong> shall be considered null and void.<br />

2.01.04. Final Authority<br />

Jumeirah Village LLC reserves the right to final authority on<br />

all items related to promotion and control of development<br />

of Jumeirah Village. All decisions made by Jumeirah Village<br />

LLC, including appeals of decisions made by the Development<br />

<strong>Code</strong> Administrator or Development Review Board shall be<br />

considered final.<br />

Section 2.02. Development <strong>Code</strong> Administrator<br />

2.02.01. Designation<br />

Jumeirah Village LLC shall designate a Development <strong>Code</strong><br />

Administrator to maintain daily administration of affairs<br />

related to development activity in Jumeirah Village.<br />

2.02.02. General Development Application Duties<br />

As noted in Table 2.01, Roles and Duties, the Development<br />

<strong>Code</strong> Administrator shall accept, review, request<br />

modification, approve, or deny the following development<br />

applications based upon the requirements established by this<br />

<strong>Code</strong>:<br />

A. Concept Plan<br />

B. Site Plan<br />

C. Building Permit<br />

2.02.03. Staff Duties on Behalf of Development Review<br />

Board<br />

In addition to duties described in Section 2.02.02, the<br />

Development <strong>Code</strong> Administrator shall act as staff to the<br />

Development Review Board providing the following services:<br />

A. Accept, review, and recommend actions upon<br />

Development <strong>Code</strong> amendments, Zoning Map<br />

amendments, variances, exceptions, and conditional<br />

uses.<br />

B. Complete Findings of Fact for each decision reached by<br />

the Development Review Board.<br />

C. Respond to the applicant with Findings of Fact.<br />

2.02.04. Additional Duties<br />

Additional duties assigned to the Development <strong>Code</strong><br />

Administrator include:<br />

A. Conduct Pre-Application Meetings as needed with<br />

potential applicants prior to formal submission.<br />

B. Monitor and enforce the regulations established by this<br />

<strong>Code</strong>.<br />

C. Interpret the requirements of this <strong>Code</strong>.<br />

D. Prepare and amend any forms and application<br />

information to be utilized in the development review and<br />

approval process.<br />

Section 2.03. Development Review Board<br />

2.03.01. Designation<br />

Jumeirah Village LLC shall designate a Development Review<br />

Board (DRB) for purposes of approving or denying requests<br />

to vary from the requirements of this <strong>Code</strong>, amend the <strong>Code</strong><br />

or Zoning Map, or appeal a decision of the Development <strong>Code</strong><br />

Administrator.<br />

2.03.02. Appointment<br />

Jumeirah Village LLC shall appoint a panel consisting of no<br />

more than five members to serve on the Development Review<br />

Board. Three members of the DRB shall be regular members.<br />

Two additional members shall serve as alternates. Meetings<br />

of the DRB shall occur regularly on a basis that shall not<br />

exceed once a month unless approved by the three regular<br />

members of the DRB.<br />

2.03.03. Powers & Duties<br />

As noted in Table 2.01, Roles and Duties, the DRB shall be<br />

charged with the following activities:<br />

A. Review, approve and deny applications for Variances,<br />

Exceptions and Conditional Uses including the<br />

establishment of Findings of Fact.<br />

B. Approve or deny proposed amendments to the<br />

Development <strong>Code</strong> or the Zoning Map as requested by an<br />

applicant, Jumeirah Village LLC staff, the Development<br />

<strong>Code</strong> Administrator, or the DRB.<br />

C. Hear appeal of any decision made by the Development<br />

<strong>Code</strong> Administrator.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

<br />

R E V I E W A U T H O R I T Y<br />

Table 2.01,<br />

Roles and Duties<br />

Role<br />

Jumeirah Village LLC Development <strong>Code</strong> Administrator Development Review Board (DRB)<br />

Final authority and administrator of<br />

responsibilities related to implementation<br />

and amendment of this Development<br />

<strong>Code</strong>. Delegates duties as necessary and<br />

hears appeals of any actions taken by the<br />

Development Review Board.<br />

Responsible for daily administration of<br />

the Development <strong>Code</strong> including the<br />

designated authority to make administrative<br />

decisions. Develops a report of review and<br />

recommendation regarding items sent to the<br />

Development Review Board.<br />

Responsible for approval or denial of items<br />

requiring possible variation or alteration of<br />

this <strong>Code</strong>. Appeals actions taken by the<br />

Development <strong>Code</strong> Administrator.<br />

Administrative Actions<br />

Concept Plan<br />

Site Plan<br />

Building Permit<br />

Amendments & Exceptions<br />

<strong>Code</strong> Amendment<br />

Zoning Map Amendment<br />

Variance<br />

Exception<br />

Conditional Use<br />

Other Duties<br />

Accepts Notice of Intent Questionnaire<br />

Conducts Pre-Application Meeting<br />

Administers and Accepts Applications for<br />

Development<br />

Reviews Applications for Completeness<br />

Develops Reports to the DRB and Jumeirah<br />

Village LLC<br />

Enforces Development <strong>Code</strong><br />

Interprets Development <strong>Code</strong><br />

Appointment and<br />

Pre-Qualification of Consultants<br />

Hears appeals of DRB decisions<br />

Hears appeals of DRB decisions<br />

Responsible for Approval<br />

or<br />

Denial<br />

Submits review and recommendations<br />

to DRB, completes DRB findings report,<br />

and responds to applicant<br />

Hears appeals of Administrator’s decisions<br />

Responsible for Approval or<br />

Denial with Findings of Fact<br />

Hears appeals of DRB decisions Responsible Party Hears appeals of Administrator’s decisions<br />

Approves Consultants for Service Accepts applications and maintains register --


J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

Z o n e s<br />

3. Zones<br />

Section 3.01. Establishment of Zones<br />

For the purposes of this <strong>Code</strong>, the site is divided among seven<br />

zones, as shown in Table 3.01, General Zone Information.<br />

Section 3.02. Official Zoning Map<br />

3.02.01 Location and Changes<br />

A. Jumeirah Village is divided into zones as noted and<br />

maintained by the Official Zoning Map, hereafter referred<br />

to as the Zoning Map. The Zoning Map, maintained in the<br />

offices of Jumeirah Village LLC, is considered a part of<br />

this Development <strong>Code</strong>.<br />

B. Any zoning changes shall be recorded on the Zoning<br />

Map by Jumeirah Village LLC and each change shall be<br />

registered on the map with a number and note indicating<br />

the change.<br />

C. No change shall be made to the Zoning Map except<br />

in conformity with requirements of this <strong>Code</strong>. Any<br />

unauthorized change shall be null and void and have no<br />

force or effect.<br />

D. The Zoning Map shall be the final authority regarding<br />

zone boundaries.<br />

Section 3.03. Interpretation of Boundaries<br />

In the event of uncertainty regarding the precise location of<br />

boundaries, the following guidelines shall apply:<br />

A. Boundaries approximately following the center line<br />

of streets or alleys shall be considered to follow such<br />

center lines.<br />

B. Boundaries approximately following lot lines shall be<br />

considered to follow such lot lines.<br />

C. Boundaries parallel to rights-of-way shall be considered<br />

to follow such rights-of-way.<br />

D. In all variances other than those listed above, Jumeirah<br />

Village LLC shall make a written interpretation of zone<br />

boundaries.<br />

Section 3.04. Uniform Application of Zones<br />

No building, structure, or land shall be used or occupied,<br />

and no building or structure shall be erected, constructed or<br />

reconstructed except in conformity with this <strong>Code</strong>.<br />

3.02.02 Digital Map<br />

Jumeirah Village LLC may publish duplicate versions of the<br />

Zoning Map or utilize a digital mapping system to maintain the<br />

Zoning Map without diluting the final authority of the physical<br />

Zoning Map available in the offices of Jumeirah Village LLC.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

<br />

Z o n e s<br />

Table 3.01,<br />

General<br />

Zone<br />

Information<br />

Description<br />

Function<br />

• Lowest density<br />

residential areas offer<br />

a suburban feel with<br />

proximity to urban<br />

services.<br />

• Structures are single<br />

family, detached homes<br />

surrounded by a private<br />

yard.<br />

• Mix of uses is minimal<br />

with commercial activity<br />

limited to home offices.<br />

• Located primarily in<br />

southern “triangle” portion<br />

of the site and far right<br />

corner of the “circle.”<br />

• Low density residential<br />

use offers a compromise<br />

between suburban single<br />

family villas and multifamily<br />

living.<br />

• Structures are flexible in<br />

use - allowing single family<br />

attached townhomes<br />

with limited front and rear<br />

yards, as well as apartment<br />

flats.<br />

• Mix of uses is minimal<br />

with commercial activity<br />

limited to home offices.<br />

• Located throughout the<br />

site and creatively used to<br />

surround range of medium<br />

and high density activities.<br />

• Variety of Medium<br />

density residential building<br />

surrounded by other Mid-<br />

Rises and flex units.<br />

• Structures are medium<br />

to high range in height,<br />

multifamily buildings with<br />

an attached carpark.<br />

• Open spaces are<br />

incidental with the<br />

exception of optional roof<br />

gardens.<br />

• Use for Mid-Rise G+4<br />

is primarily residential<br />

with ground floor retail<br />

activity possible. Mix use<br />

is allowed for G+10 &<br />

G+16 with retail possible<br />

on Ground & First Floors<br />

and Commercial on First,<br />

Second & Third Floors.<br />

Most institutional uses are<br />

permitted by right.<br />

• Located throughout<br />

the “circle” portion of the<br />

site along and within the<br />

major roadways and in<br />

the “triangle” portion of<br />

the site adjacent to tower<br />

parcels.<br />

• High density units in 3<br />

configurations and heights:<br />

Gateway Tower, Boulevard<br />

Tower and Pre-sold Tower.<br />

• Multifamily skyscrapers<br />

of varying heights with<br />

attached an above/below<br />

ground carpark.<br />

• Open spaces are<br />

incidental with the<br />

exception of optional roof<br />

gardens.<br />

• Located along major<br />

roadway connecting Town<br />

Center within the site and<br />

surrounding arterials.<br />

• Use is primarily<br />

residential, but maybe a<br />

mix of residential, retail (on<br />

Ground & First Floor), and<br />

commercial (on Second &<br />

Third Floors).<br />

• For Presold Towers,<br />

commercial use is<br />

permitted.<br />

• High density, mixed-use<br />

units that create a series of<br />

dynamic, urban cores for<br />

Jumeirah Village.<br />

• Multi-unit skyscrapers<br />

of varying heights with<br />

an urban “podium” and<br />

an attached above/below<br />

ground carpark.<br />

• Open spaces may<br />

include plazas, urban<br />

greens and roof gardens.<br />

• Primarily a location for<br />

office use, although may<br />

be a mix of residential,<br />

office, hotel and retail.<br />

• Located in three specific<br />

areas of the project.<br />

• Allows hotel or office<br />

above retail.<br />

• Low density, commercial<br />

retail located within<br />

the large median of the<br />

“triangle” portion of the<br />

site and within each of the<br />

“circle” districts.<br />

• Structures are limited<br />

height and serve a portion<br />

of the commercial retail<br />

needs of the project.<br />

• The formal green spaces<br />

of the median surround<br />

this portion of the site with<br />

additional open space<br />

desirable, but optional.<br />

• Located within easy<br />

access of the majority of<br />

the “triangle” portion of<br />

the site, particularly by<br />

automobile.<br />

Live High High High High High None None<br />

Work Low Low Medium Medium High Medium Low<br />

Shop None None Low Medium High High Low<br />

Play Medium Medium Medium Low Low Low High<br />

• Large open spaces<br />

designed to provide<br />

recreation, gathering<br />

opportunities and civic<br />

services within walking<br />

distance.<br />

• Includes Village Centers<br />

as defined in Block<br />

Guidelines.<br />

• Structures are limited<br />

height and complimentary<br />

to the open space.<br />

• Primarily functions<br />

as active and passive<br />

recreation space, including<br />

a number of water<br />

features. Institutional<br />

uses are permitted by<br />

right, as well as limited<br />

neighborhood commercial<br />

activity.<br />

• Open space connects<br />

virtually all of Jumeirah<br />

Village..


J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

Z o n e s<br />

Figure 3.01,<br />

Zoning Map<br />

“Triangle” Side<br />

“Circle” Side


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

<br />

4. Use<br />

u s e<br />

Section 4.01. Types of Use<br />

Use categories are listed in Tables 4.01a and 4.01b. The<br />

following serve as a key to the Land Use Tables and indicate<br />

treatment for each use according to Zone.<br />

4.01.01. Permitted Uses<br />

A “P” indicates that a specific use is permitted by right within<br />

the given Zone. Such uses must meet all other appropriate<br />

requirements of this <strong>Code</strong>.<br />

4.01.02. Conditional Uses<br />

A “C” indicates that a use is permitted provided that the<br />

project appropriately responds to additional criteria.<br />

Conditional uses must meet all other appropriate<br />

requirements of this <strong>Code</strong>.<br />

4.01.03. Accessory Uses<br />

An “A” indicates the use as accessory to the primary use on<br />

a given site. An Accessory Use is permitted by right assuming<br />

that additional requirements established in Section 4.04,<br />

Accessory Use or Structure, are met.<br />

4.01.04. Uses Not Allowed<br />

An “-“ indicates that a particular use is not permitted within a<br />

given Zone.<br />

Section 4.02. Use Categories<br />

4.02.01. Classification<br />

Use categories classify land uses and activities based<br />

upon a similar function, product or physical characteristics.<br />

Characteristics include the type and amount of activity, the<br />

type of customers or residents, how goods or services are<br />

sold or delivered, likely impact on surrounding properties, and<br />

site conditions.<br />

4.02.02. Determination of Use<br />

In the event that a use is not listed or classification is<br />

otherwise required, Jumeirah Village LLC shall classify the<br />

use as appropriate. Following are criteria for determining<br />

classification:<br />

A. Actual or Anticipated characteristics of the activity.<br />

B. Approximate size of site area or floor space.<br />

C. Amounts of sales and customer type generated.<br />

D. Number and character of employees.<br />

E. Hours of operation.<br />

F. Building and site arrangement.<br />

G. Vehicles used and parking requirements.<br />

H. Number of vehicle trips generated.<br />

I. Required signage.<br />

J. Advertisement of use.<br />

K. Likely impact on surrounding properties.<br />

L. Ability to operate independently of other activities on a<br />

site.<br />

Section 4.03. Conditional Use<br />

4.03.01. Criteria for Approval<br />

Approval of a use in a given Zone is conditional if the use can<br />

be made compatible assuming specific criteria have been<br />

met to address negative impacts upon the surrounding area.<br />

Following are variables for consideration of approval of a<br />

Conditional Use:<br />

A. Conformity and compatibility with the approved Master<br />

Plan for Jumeirah Village.<br />

B. The proposed Conditional Use will not adversely impact<br />

the surrounding area or the overall development of<br />

Jumeirah Village.<br />

C. The location, size, intensity, and accessibility of the use<br />

will not adversely impact the marketability of surrounding<br />

uses or reduce the anticipated standard of living.<br />

D. The size, floor, area, mass, and general appearance<br />

of the proposed structure are to be compatible with<br />

surrounding structures.<br />

E. Adjacent streets and utilities have sufficient capacity to<br />

meet infrastructure requirements of the Use.<br />

F. Access to the site is acceptable to Jumeirah Village LLC.<br />

G. Adequate parking will be available and in accordance<br />

with criteria established by this <strong>Code</strong>.<br />

H. Impacts such as night lighting and noise have been<br />

successfully addressed.<br />

4.03.02. Conditions<br />

Jumeirah Village LLC may place conditions upon approval of<br />

a Conditional Use Permit to reduce or mitigate impacts upon<br />

surrounding uses.<br />

4.03.03. Transferability<br />

Approval of a Conditional Use is not transferable to new<br />

tenants or operators.<br />

Section 4.04. Accessory Use or Structure<br />

4.04.01. Criteria<br />

A use or structure shall be considered an Accessory Use or<br />

Accessory Structure if it meets the following criteria:<br />

A. The use or structure is subordinate to or serves the<br />

primary use or principal structure.<br />

B. The use is subordinate in area, extent or purpose to the<br />

primary use.<br />

C. The use is located on the same lot as the primary use.<br />

D. The use is included in calculation of maximum lot<br />

coverage.<br />

4.04.02 Permitted Accessory Uses<br />

Following are permitted Accessory Uses and Accessory<br />

Structures in Jumeirah Village:<br />

A. Home Office and Caretakers quarters as noted in Tables<br />

4.01a and 4.01b, as well as 4.04.04, Home Office of this<br />

Development <strong>Code</strong>.<br />

B. Storage structures not exceeding 10 percent of the<br />

maximum lot coverage and maintaining compatibility of<br />

scale, materials and design with the principal structure.<br />

C. Commercial or Institutional uses such as cafes or<br />

mosques for the exclusive use of employees associated<br />

with commercial or office use.<br />

D. Solar panels and similar features, awnings, canopies,<br />

carports, and other amenities attached or directly related<br />

to the primary structure.<br />

E. Trash or refuge storage and enclosures.<br />

F. Radio, television or other telecommunications antennas.<br />

G. Temporary uses associated with construction sites.<br />

4.04.03 Prohibited Accessory Uses<br />

The following uses are prohibited in Jumeirah Village:<br />

A. Open storage of loaded and unloaded vehicles.<br />

B. Open storage of materials, supplies or equipment.<br />

C. Outdoor display for sale of items such as automobiles,<br />

furniture, appliances or other large-scale materials.<br />

D. Raising, breeding, or keeping of dogs, cats, birds or other<br />

animals for sale, feeding or slaughter.<br />

4.04.04 Home Office<br />

A home office is permissible as a use in given Zones, as noted<br />

in Tables 4.01a and 4.01b, if it meets the following criteria:<br />

A. The home office is clearly incidental to the residential<br />

use of the dwelling.<br />

B. Business connected to the home office is conducted<br />

entirely within a residential structure.<br />

C. No outside storage of any kind is related to the home<br />

office.<br />

D. The residential character of the dwelling and the lot<br />

are not altered in any way to account for a home office,<br />

including additional parking, placement of a business<br />

related sign, or display of wares in a manner as to be<br />

visible to the outside.<br />

E. Deliveries by commercial vehicles occur only between<br />

8am and 6pm.<br />

F. The home office creates no disturbing or offensive noise,<br />

vibration, smoke, dust, odor, heat, glare, unhealthy or<br />

unsightly condition, traffic, or parking problem.<br />

G. The home office shall not result in the off-street or onstreet<br />

parking of more than two vehicles at any one time<br />

not owned by members of the occupant family.<br />

H. The business conducted within the home office does not<br />

involve retail sales or services.


10 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

u s e<br />

Table 4.01a,<br />

Permitted Land<br />

Uses: Residential<br />

& Institutional<br />

Residential<br />

Single Family Villa P - - - - - -<br />

Townhome - P - - - - -<br />

Multifamily Apartment - - P P P - -<br />

Home Office A A A A A - -<br />

Caretaker Dwelling A A - - - - -<br />

Cultural/Recreation<br />

Park or Open Space P P P P P P P<br />

Recreation Center C C C C C C P<br />

Play Area P P P P P P P<br />

Sports Fields C C - - C - P<br />

Institutional<br />

School C C - - P P P<br />

Mosque P P P P P P P<br />

Library/Cultural Center C - P - P P P<br />

Medical Facility - - P P P P P<br />

Hospital - - C C P - -<br />

Civil Defence - - P - P P P<br />

Fire Station - - P - P P P<br />

Police Station - - P - P P P<br />

Daycare/Nursery C - P - P P P<br />

Municipality Services - - P - P P P<br />

Post Office - - P - P P P<br />

Carpark Structure - - P P P P P


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

11<br />

u s e<br />

Table 4.01b,<br />

Permitted Land<br />

Uses: Commercial,<br />

Utility & Industrial<br />

Commercial<br />

Office, General - - C C P P -<br />

Eating Establishments<br />

Indoor Restaurant - - C P P P P<br />

Outdoor Cafe’ - - C P P P P<br />

Entertainment<br />

Indoor Entertainment - - - P P P C<br />

Outdoor Entertainment - - - P P P C<br />

Convenience Grocery - - C P P P P<br />

General Retail - - C P P P P<br />

Temporary Vendor - - - C P P P<br />

Serviced Apartments - - P P P P -<br />

Hotel - - - C P - -<br />

Boutique Hotel - - C C P - -<br />

Service Establishments<br />

General Sales - - - C P P -<br />

Personal Services - - C C P P -<br />

Repair Service - - - - C C -<br />

Gas Station - - - - - P -<br />

Utility and Communication<br />

Public Utility - - C C C C C<br />

Transmission Station - - C C C C C<br />

Waste Related Services - - - - C C C<br />

Industrial - - - - - - -


12 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

U s e<br />

4.04.05. Boutique Hotels<br />

Boutique Hotels may be considered for boulevard Mid Rise 1<br />

& Mid Rise 2 subject to approval by Jumeirah Village LLC.<br />

Boutique Hotels are Hotels with the maximum number of<br />

rooms= 150.<br />

Figure 4.01,<br />

District Overview<br />

4.04.06. Accessory Use Development Standards<br />

The following standards shall apply to all accessory<br />

structures:<br />

A. The combination of all structures on a property, including<br />

the primary structure and all accessory structures, shall<br />

not exceed any requirements established in 5.0, Form, for<br />

the given Zone.<br />

B. No accessory structure shall be constructed upon a<br />

property prior to completion of the primary structure.<br />

C. Fences and walls shall not be considered an accessory<br />

structure unless required to conceal an accessory use,<br />

in which case the fence or wall shall be of sufficient<br />

height to screen such use from public view, if required<br />

and shall be in accordance with Section 8.04, Fencing.<br />

4.04.07. School Sites<br />

A. The Total buildable area - not including parking<br />

structures, basements, balconies and rooftop mechanical<br />

enclosures - will be set at FAR 2.0. This area will be<br />

calculated to the exterior of all exterior wall enclosures<br />

and will include all service areas and elevator shafts and<br />

shall exclude substations and all service shafts.<br />

B. The maximum average floor plate area for school lots<br />

shall be 50% of lot area.<br />

C. The maximum allowable height is G+3<br />

Section 4.05. Temporary Use<br />

4.05.01. Permitted Temporary Uses<br />

Unless otherwise prohibited by this <strong>Code</strong>, the following<br />

temporary uses and structures may be permitted provided<br />

that they do not adversely affect surrounding properties nor<br />

disrupt the normal activity associated with Permitted Uses:<br />

A. Contractor’s office, construction equipment sheds and<br />

lay down areas, haul roads, access roads, burrow/fill<br />

sites and other construction related uses.<br />

B. A real estate office.<br />

C. A car park.<br />

4.05.02. Duration of Temporary Use<br />

A. A temporary use shall be granted for a maximum time<br />

duration of 24 months by Jumeirah Village LLC. An<br />

extension of time for continuance of a temporary use<br />

may be granted by Jumeirah Village LLC upon request<br />

and review.<br />

B. Within 30 days following expiration of the granted time<br />

duration, the lot shall be cleared of all debris and all<br />

temporary structures. A guaranty or signed contract with<br />

a disposal firm may be required as part of approval of any<br />

Temporary Use Permit.<br />

4.05.03. Temporary Use Development Standards<br />

The following standards shall apply to all temporary uses and<br />

structures, unless otherwise noted:<br />

A. Hours of operation shall be determined by Jumeirah<br />

Village LLC upon approval of the permit for the temporary<br />

use.<br />

B. Temporary sanitary facilities must be approved by<br />

Jumeirah Village LLC.<br />

C. Temporary uses shall meet all landscaping, fencing and<br />

sign requirements established for the given Zone.<br />

D. Parking for the temporary use may be required, including<br />

a stabilized drive to the parking area.<br />

4.05.04. Storage of Materials and Equipment<br />

No materials, supplies, tools, or equipment, including trucks<br />

and other vehicles of the developer, shall at any time be<br />

placed or stored in any area within Jumeirah Village. other<br />

than the specified lot. Storage shall occur inside a closed,<br />

temporary building, or behind a visual barrier or fence of<br />

such design and construction to screen such areas from<br />

public view in conformance with Section 8.04, Fencing.<br />

Such temporary structures, fences and visual barriers shall<br />

require approval by Jumeirah Village LLC and shall not<br />

extend over the designated boundary.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

13<br />

5. Form <strong>Code</strong> – Mid-Rise Lots<br />

Table 5.02,<br />

Building<br />

Configuration<br />

& Size<br />

f o r m c o d e – M I D R I S E l o t s<br />

Zone <strong>Code</strong> MRH MRM MRA MRP<br />

FAR 8.0 8.0 3.0 2.5<br />

Average Floor Plate 50% of Parcel 75% of Parcel 65% of Parcel 50% of Parcel<br />

Ground Retail FAR 0.15 0.15 0.1 0<br />

First Floor Retail FAR 0.15 0.15 0 0<br />

First, Second, Third<br />

Floor commercial<br />

FAR<br />

1.0 1.0 0 0<br />

Maximum Height G + 16 Stories G + 10 Stories G + 4 Stories G + 4 Stories<br />

Upper Floor Setback at 16th Floor at 10th Floor at 5th Floor at 5th Floor<br />

The Retail & Commercial FAR is included in total building FAR<br />

Figure 5.01,<br />

Mid-Rise and Boulevard Mid-Rise Buildings in the foreground<br />

Section 5.01. General<br />

5.01.01. Applicability<br />

Design requirements established in Section 5.0, Form shall be<br />

applicable to all sites and structures in the Boulevard Mid-<br />

Rise and Mid-Rise Zones unless specifically exempted by this<br />

<strong>Code</strong>.<br />

5.01.02. Relationship to Eight Principles and Master Plan<br />

Development requirements regarding urban form are<br />

incorporated into this <strong>Code</strong> as a means of implementing<br />

design criteria established in the Jumeirah Village Master<br />

Plan, ensuring a high quality of life and minimizing the<br />

opportunity for adverse impacts on the functionality of the<br />

community.<br />

5.01.03. Subdivision of Property<br />

Subject to the approval of Jumeirah Village (L.L.C), land in<br />

the Flex and Town Centre plots in Jumeirah Village may be<br />

subdivided if each of the lots created by the subdivision<br />

meets all requirements of this code for the zone in which<br />

they are located. Land subdivision of other plot types is not<br />

permitted.<br />

Section 5.02. Building Configuration and Size<br />

5.02.01. Building Elements<br />

Each type of mid-rise development shall comply with<br />

the configuration as stipulated in Table 5.02 Building<br />

Configuration & Size. The primary facade with main<br />

entrance should always be facing the primary street and<br />

any secondary entrance may front along secondary streets.<br />

Setbacks shall be provided at the street, alley and paseo<br />

edges.<br />

5.02.02. Maximum Built Up Area<br />

The total gross buildable area - not including parking<br />

structures, basements, balconies, and rooftop mechanical<br />

enclosures - will be set as per the FARs specified in Table<br />

5.02 Building Configuration and Size. This area will be<br />

calculated to the exterior of all wall enclosures and will<br />

include all service areas and elevator shafts and shall<br />

exclude substations and all service shafts. The table above<br />

also specifies maximum allowable FAR for any ground floor<br />

retail use within the buildings.<br />

5.02.03. Average Floor Plate<br />

A. The average floor plate area for buildings on various<br />

Mid-Rise lots is specifed in Table 5.02 Building<br />

Configuration & Size.<br />

B. The average floor plate area of all buildings will be<br />

calculated by dividing the total buildable area by the total<br />

number of floors.<br />

C. The average floor plate shall comprise of gross areas<br />

including but not limited to all living spaces, walls,<br />

service and core areas.<br />

5.02.04. Building Height<br />

A. The maximum height of various Mid-Rise structures shall<br />

be as per the Table 5.02 Building Configuration & Size.<br />

B. The calculation of the number of stories shall begin at<br />

ground level and include the ground floor, mezzanines, or<br />

any levels commonly considered a story. Penthouses for<br />

mechanical equipment and basements that are not more<br />

than 1m above grade are not included.<br />

C. Items not considered in calculation of height shall<br />

include architectural treatments, antennas, parapets,<br />

spires, domes and other such features to be approved by<br />

Jumeirah Village LLC.<br />

D. The floor-to-floor dimension of each story shall be a<br />

minimum of 3m and a maximum of 5m. Any area of<br />

occupancy over 30 sqm shall be counted as a story.


14 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

f o r m c o d e – M I D R I S E l o t s<br />

Figure 5.02,<br />

Boulevard Mid-Rise 1 Typical Site Plan<br />

5.02.05. Orientation and Entry<br />

A. All street and paseo edges of the lot shall have occupied<br />

building frontage in the ratio prescribed for street<br />

setbacks in Section 5.03 and with the quantity of glazing<br />

prescribed in Section 5.04.02. The height of such frontage<br />

shall be a minimum of four stories.<br />

Figure 5.04,<br />

Boulevard Mid-Rise 1 Lot and Building View<br />

B. The primary façade and major building entries shall face<br />

the major street bordering the lot.<br />

C. In the case of lots with side streets or paseos the primary<br />

entries must face the primary street.<br />

D. In buildings with allowable ground floor retail, entries for<br />

residential and retail use shall be clearly identified using<br />

appropriate signages.<br />

5.02.06. Parking Location and Vehicle Access<br />

A. Parking parking is preferred below grade. A a parking structure<br />

shall be as follows:<br />

1. Boulevard Mid Rise 1 & 2:<br />

Figure 5.03,<br />

Boulevard Mid-Rise 2 Typical Site Plan<br />

A parking structure of no more than G g + 3 will be<br />

allowed above grade with setbacks of 13m from<br />

streets and paseos and zero setbacks from the side<br />

and rear shared parcel lines.<br />

2. Boulevard Mid Rise 3 & 4:<br />

A parking structure of no more than G + 1 will be<br />

allowed above grade with setbacks of 13m from<br />

streets and paseos and 5 m setbacks from the side<br />

parcel lines and alley parcel lines.<br />

Figure 5.05,<br />

Mid-Rise 2 Lot and Building View<br />

B. No parking structure may front on a Street or Paseo at<br />

the building’s ground level. The parking façade must have<br />

architectural treatments consistent with the occupied<br />

sections of the building.<br />

C. All curb cuts for access to parking shall be located<br />

along an alley when possible. When located along a<br />

street, curb cuts may not be located within 23m of an<br />

intersection and 3m of a property line.<br />

Section 5.03. Building Setbacks<br />

5.03.01 Street and Paseo<br />

A. For all street and Paseo conditions, all buildings shall


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

15<br />

Figure 5.06,<br />

Mid-Rise 3 Typical Site Plan<br />

front on a minimum of 80% of the length of lot line within<br />

2-4m of the property line.<br />

5.03.02. Shared Parcel Edges<br />

A. In the case of shared side and rear parcel lines, the<br />

lower stories of the structure below the required setback,<br />

may be built up to the property line.<br />

Figure 5.09,<br />

Mid-Rise 3 Lot & Building View<br />

f o r m c o d e – M I D R I S E l o t s<br />

5.03.03. Upper Story Setback<br />

A. If buildings are built to their maximum height, the setback<br />

requirements from Table 5.02 Building Configuration<br />

& Size will apply to the street, paseo or alley edges of<br />

building. The minimum setback for upper-most floors<br />

from builidng line shall be at least 3m. This setback shall<br />

be utilized as a balcony, with trellis and loggia treatments<br />

wherever possible.<br />

Section 5.04. Urban Design<br />

Figure 5.07,<br />

Mid-Rise 4 Typical Site Plan<br />

5.04.01. Ground Floor Treatment<br />

A. Any allowed ground floor retail use shall be located on<br />

all of the adjacent streets with its main entry from the<br />

primary street. This entry shall be cleary visible from the<br />

sidewalk.<br />

B. The residential Lobby and entryway shall be clearly<br />

visible from the sidewalk and any drop off area shall not<br />

isolate entry from the sidewalk.<br />

Figure 5.08,<br />

Mid-Rise 4 Lot and Building View<br />

C. Exterior building materials, particularly at the pedestrian<br />

level, should be selected with consideration given to use,<br />

durability and maintenance.<br />

5.04.02. Transparency<br />

A. Transparency shall constitute glass with less than 30<br />

percent reflectance. No mirror or highly colored glass is<br />

permitted.<br />

B. The percent of glazing of the façade shall be a minimum<br />

of 20% on the front and rear elevations.<br />

5.04.03. Open space<br />

A. Each parcel shall incorporate at least 150 sqm of open<br />

space. Such open space may be located on top of the<br />

car park structure, at grade, or on roof.


16 J u m e i r a h V i l l a g e S o u t h - M I D R I S E D e v e l o p m e n t C o d e<br />

J U M E I R A H V I L L A G E L L C<br />

f o r m c o d e – M I D R I S E l o t s<br />

Section 5.05. Architectural Treatments<br />

5.05.01. Horizontal/Vertical Articulation<br />

A. No building shall extend greater than 20m horizontally<br />

without a discernible vertical offset or change in<br />

elevation treatment.<br />

5.05.02. Mix of Permitted Materials<br />

A. In order to create unity at the street level, at least 50%<br />

of the non-glazed area of the facade shall be covered in<br />

limestone. The other materials utilized to cover facades<br />

shall be compatible in color and texture with limestone<br />

(such as stucco, cast stone or tile).<br />

5.05.03. Screening of Mechanical Equipment and Parking<br />

A. Mechanical equipment, to the extent possible should<br />

be placed on the roof of any structure. Mechanical<br />

equipment located on a roof shall be screened through<br />

development of a “top” for the structure.<br />

B. Mechanical equipment that must be located below the<br />

roof and car park structures should be located to the side<br />

or rear of a structure and designed to be architecturally<br />

compatible with the remainder of the structure including<br />

incorporation of appropriate materials to assist in<br />

screening.<br />

5.05.04. Color<br />

The color palette selected by applicant shall be generally<br />

compatible with limestone as well as the colors of<br />

surrounding development, with the rear and side of the<br />

primary structure completed in a color compatible with the<br />

front façade.<br />

5.05.05. Lighting<br />

A. Lighting designed to illuminate any or all of a site shall<br />

be fully concealed to avoid direct visibility from a street<br />

right-of-way and shall be designed to avoid unreasonable<br />

encroachment of light upon surrounding sites.<br />

B. Commercial parking, loading and staging areas shall<br />

be expected to incorporate lighting during evening<br />

operation.<br />

C. Lighting shall be provided at all entry and exit points<br />

of structures as well as locations throughout the site<br />

in which it is determined by Jumeirah Village LLC that<br />

safety may be compromised.<br />

D. Roof lighting shall be permissible following approval by<br />

Jumeirah Village LLC.<br />

5.05.06. Balconies<br />

A. Balconies may be counted as part of the multi-family<br />

open space requirement. There is no requirement that all<br />

or even any balconies be provided.<br />

B. Balconies should be well integrated into the façade<br />

composition, and may not appear as boxes that protrude<br />

from the side of the building. Devices that help integrate<br />

balconies include: partially or fully recessing the balcony<br />

into the façade, placing the balcony at an inside corner<br />

of the building, and placing the balcony on the roof of a<br />

lower floor where the building steps back.<br />

C . Balconies are meant to be fully or partially exterior<br />

places, not a bonus room that does not count towards<br />

the allowed floor area of the building. To protect this<br />

and the views from other units, balconies may not be<br />

glassed-in or have opaque wall surfaces except as<br />

allowed in this section.<br />

D. Openwork structures (such as trellises) and plantings<br />

are encouraged, but must not block more than 30% of<br />

the façade area they occupy on any side that protrudes<br />

beyond the building face.<br />

E. The following strictures apply to balconies:<br />

1. Balconies may extend up to 2m from the building<br />

face.<br />

2. Balconies may protrude into a setback or public<br />

right-of-way up to 1m.<br />

3. Balconies may be fully enclosed up to 1.1m above<br />

floor height (i.e. railing height.)<br />

4. Opaque walls above 1.1m are allowed only when<br />

balconies of different units are physically joined<br />

together. In this case the opaque wall may not be<br />

higher than 2m above floor height<br />

5.05.07. Roofscape<br />

A. Any mechanicals on the exterior, such as air handling<br />

units and communications antennae / dishes shall be<br />

roof-mounted and screened from sight from public space<br />

and other buildings within suitable enclosure areas.<br />

If screening areas are mounted atop roofs of lower<br />

portions of a building, care should be taken to minimize<br />

the visual impact from higher floors.<br />

B. With the exception of parapets along facades and<br />

feature accents such as domes and trellises, rooftops<br />

shall be flat.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

17<br />

pa r k i n g a n d l o a d i n g<br />

6. Parking and Loading<br />

Section 6.01. Purpose and Type<br />

Parking and loading requirements are established as part<br />

of this <strong>Code</strong> to ensure that all activities in Jumeirah Village<br />

are provided adequate and reasonable parking and loading<br />

facilities to meet the needs of structures and uses.<br />

6.01.01. On Street Parking<br />

On street parking is strongly encouraged throughout<br />

Jumeirah Village as a flexible, efficient parking option. On<br />

street parking shall be permitted along all streets throughout<br />

Jumeirah Village, except in the instance that a frontage road<br />

accompanies a street, parking shall only occur along the<br />

frontage road.<br />

A. On street parking located adjacent to the front lot line of<br />

a lot shall be included in meeting parking requirements<br />

for that particular lot.<br />

B. All on street parking shall be designed as parallel<br />

parking. No diagonal parking is permitted along local and<br />

primary streets of Jumeirah Village.<br />

C. On street parking shall have a minimum length of 7m and<br />

a minimum width of 2.5m unless otherwise dictated by<br />

Jumeirah Village LLC.<br />

6.01.02. Parking Types<br />

Opportunities for parking shall be classified in four categories<br />

as follows:<br />

A. On street parking. Permitted in all Zones throughout<br />

Jumeirah Village.<br />

B. Driveway/Carpark. Parking exclusive to Villa and<br />

Townhome Zones appropriate to low density, limited use<br />

activities.<br />

C. Carpark Structure. Appropriate to areas with high density<br />

or a desire to preserve space. Carpark structures are<br />

restricted by location, design and appearance. Ability to<br />

place parking below grade, improves the efficiency of<br />

carpark structures.<br />

D. Open Lot. Paved, marked, open area adjacent to a<br />

structure. An open lot is considered an inefficient system<br />

of parking appropriate only in areas with significant<br />

traffic, but limited density.<br />

6.01.03. Parking by Zone<br />

Parking type is determined to have an impact upon the visual<br />

character and overall efficiency of a lot or block. Table 6.01,<br />

General Parking Requirements indicates the type of parking<br />

permitted in each Zone. A “P” indicates that the specific type<br />

of parking is permitted within the given Zone.<br />

Section 6.02. General Provisions<br />

6.02.01. Location of Parking<br />

A. Location of parking in relationship to structures on a lot<br />

and the streetscape are regulated by Table 6.01, General<br />

Parking Requirements and guided by the guidelines<br />

related to parking in Design Principles.<br />

B. With the exception of on street parking and driveways<br />

permitted in the Villa Zone, all parking is to be screened<br />

from general view.<br />

6.02.02. Shared Parking<br />

Two or more structures or areas may share parking provided<br />

that all height, design and other criteria established within<br />

Section 6, Parking and Loading are met and approval is<br />

granted by Jumeirah Village LLC.<br />

6.3.03. Approval Required<br />

Parking and loading shall require approval by Jumeirah<br />

Village LLC prior to construction or use. No concept plan or<br />

site plan approval shall be granted if Jumeirah Village LLC is<br />

unable to determine that parking and loading areas meet the<br />

requirements of Section 6 of this <strong>Code</strong>.<br />

Section 6.03<br />

Space Requirements<br />

6.03.01. Number of Spaces<br />

Table 6.02, Parking Spaces Required, designates the minimum<br />

number of parking spaces necessary by type of land use.<br />

6.03.02. Bicycle Accommodations<br />

One bicycle rack shall be required for each 30 parking spaces<br />

of a specific use and shall count as one parking space.<br />

6.03.03. Calculating Space Requirements<br />

A. Those requirements including a square meter measure<br />

shall base measurements on gross floor area.<br />

B. In the event that calculations result in a fraction greater<br />

than one-half (.5), the number shall be rounded up to<br />

the next whole number. Otherwise, the number shall be<br />

rounded down.<br />

Section 6.04. Space and Lot Design<br />

6.04.01. Parking Space Size<br />

A. Parking spaces shall conform to the requirements<br />

established in Table 6.03, Parking Area Dimensions.<br />

B. Required parking spaces shall have minimum dimensions<br />

of not less than 2.5 meters in width and 5.5 meters in<br />

length.<br />

C. In parking areas with 20 or more parking spaces, up to<br />

15 percent may be designated as “small car” spaces<br />

with minimum dimensions of not less than 2.5 meters in<br />

width and 5 meters in length. Small car spaces should be<br />

grouped and identified for exclusive use of small cars.<br />

6.04.02. Parking and Drive Aisle Widths<br />

A. Parking and drive aisle widths adjoining off street parking<br />

must meet the minimum standards described in Table<br />

6.03, Parking Area Dimensions.<br />

B. End caps of parking aisles shall include a maximum<br />

radius of 4 meters.<br />

6.04.03. Access<br />

A. No parking space shall have direct access to a street<br />

except on street parking spaces. Off street parking<br />

spaces shall be accessible without backing into or<br />

otherwise entering a street.<br />

B. All off street parking areas shall be limited to one point<br />

of two-way operation access with the exception of<br />

those parking areas that exceed a total of 100 spaces, in<br />

which case two points of two-way operation access are<br />

permitted.<br />

6.04.04. Access Standards<br />

Access driveways for parking and loading shall meet the<br />

following design standards:<br />

A. Access for emergency vehicles and loading shall have a<br />

minimum vertical clearance of 5.5 meters.<br />

B. Curb cuts shall not be placed closer than 10 meters from<br />

a curb line intersection, measured from the nearest edge<br />

of the access driveway.<br />

C. Access driveways shall have a minimum width of<br />

3.75m for one-way operation or 6.0 meters for two-way<br />

operation.<br />

D. At no time shall the total width permitted for access<br />

exceed 30 percent of the total street frontage.<br />

6.04.05. Markings and Accessories<br />

A. Each required off-street parking space shall be<br />

individually identified by surface markings in accordance<br />

with adopted standards. Aisles and maneuvering areas<br />

shall also be clearly marked with directional and traffic<br />

information as determined necessary.<br />

B. Wheel stops or a continuous curb shall be provided<br />

along the boundary line of a parking area or within<br />

proximity to structures, pedestrian areas, or landscaping.<br />

C. Lighting shall be installed as needed for purposes of<br />

safety and shall be installed in a manner to prevent light<br />

from reaching beyond the intended area.<br />

6.04.06. Landscaping, Screening and Drainage<br />

D. Landscaping and fencing shall be provided in<br />

accordance with the requirements of Section 8,<br />

Landscape and Screening of this <strong>Code</strong>. Additional<br />

setbacks for parking areas may be required to meet<br />

landscaping and screening requirements.<br />

E. A carpark structure shall maintain the design theme of<br />

the adjacent structure, including a minimum standard of<br />

architectural detail and screening integrated into design<br />

of all parking or loading areas.<br />

F. Parking and loading areas shall be graded, paved with<br />

a material acceptable to Jumeirah Village LLC, drained,<br />

and maintained to avoid dust, erosion or excessive water<br />

flow.<br />

6.04.07. Vehicle Stacking Areas<br />

Vehicle stacking may be a consideration in “staging areas”<br />

such as schools, banks or parking areas for commercial retail<br />

or entertainment activities. In such instances, the following<br />

requirements shall apply:<br />

PA R K I N G A N D L O A D I N G


18 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

PA R K I N G A N D L O A D I N G<br />

Table 6.01,<br />

General Parking<br />

Requirements<br />

Type of Parking<br />

On Street (visitors only) P P P P P P P<br />

Driveway/Carpark P P - - - - -<br />

Carpark Structure - - P P P P P<br />

Open Lot - - - - - P P<br />

Added Requirements<br />

Permitted Height (in<br />

stories not including ground<br />

level)<br />

- - Mid Rise 1 & 2 (3 levels)<br />

Mid Rise 3 & 4 (1 level)<br />

Parking Limitations - - parking to be located<br />

to rear of site<br />

Visibility of Parking visible from local street visible from access<br />

street/alley<br />

not visible from<br />

primary street<br />

4 4 2 2<br />

no parking permitted<br />

on ground floor along<br />

primary street<br />

not visible from<br />

primary street<br />

no parking permitted<br />

on ground floor along<br />

primary street<br />

access point visible<br />

from primary street<br />

Location of Vehicle Access local street alley access street/alley access street/alley designated rear of block<br />

(see Design Principles)<br />

- -<br />

screened, but visible<br />

from primary street<br />

access street<br />

screened, but visible<br />

from primary street<br />

access street<br />

Location of Loading - - access street/alley access street/alley designated rear of block access street access street<br />

Visibility of Loading - - screened from alley screened from alley screened from rear<br />

of block<br />

Landscaped Deck<br />

(see Section 8)<br />

primary street<br />

- - Yes Yes Yes Yes -<br />

primary street


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

19<br />

A. Vehicle stacking areas must be provided on-site and may<br />

not impede on or off-site traffic movement.<br />

B. The number of vehicles to be considered in the vehicle<br />

stack shall be determined in coordination with Jumeirah<br />

Village LLC.<br />

PA R K I N G A N D L O A D I N G<br />

Section 6.05. Loading Areas<br />

6.05.01. Location of Loading Areas<br />

Loading areas shall be located beyond the view of the<br />

general public as determined in Table 6.01, General Parking<br />

Requirements.<br />

A. Bus and taxi pick up/drop off areas shall be permitted in<br />

areas visible to the general public.<br />

B. The right-of-way shall not be used as a location for<br />

general loading or unloading of goods and services. No<br />

part of any vehicle shall be permitted to extend into a<br />

local or primary street during loading or unloading.<br />

6.05.02. Typical Space Requirements<br />

A. Loading spaces shall have a minimum width of 3<br />

meters and a length of 12 meters, exclusive of aisle and<br />

maneuvering space.<br />

B. Loading spaces shall have a minimum vertical clearance<br />

of 5.5 meters.<br />

C. Inside turning radius shall be a minimum of 9 meters.<br />

6.05.03. Semi-Trailer Space Requirements.<br />

A. Loading spaces shall have a minimum width of 3.5m<br />

and a length of 17m, exclusive of aisle and maneuvering<br />

space.<br />

B. Loading spaces shall have a minimum vertical clearance<br />

of 5.5m.<br />

C. Inside turning radius shall be a minimum of 12.5m.<br />

6.05.04. Design of Loading Areas<br />

Loading areas shall be screened from the view of the general<br />

public and designed to fit appropriately into the design theme<br />

of the surrounding structure.


20 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

PA R K I N G A N D L O A D I N G<br />

Table 6.02,<br />

On-Site Parking Spaces Required<br />

Use<br />

Residential<br />

Studio to 1 Bedroom Unit<br />

Space Requirement<br />

1 space per unit<br />

2 Bedroom Unit 1.5 space per unit<br />

3 Bedroom Unit 2 spaces per unit<br />

4 or More Bedroom Unit 3 spaces per unit<br />

Visitor Parking<br />

Cultural/Recreation<br />

Park or Open Space<br />

Recreation Center<br />

Play Area<br />

Sports Fields<br />

Institutional<br />

School<br />

1 space per 35 car spaces provided<br />

TBD<br />

TBD<br />

TBD<br />

TBD<br />

1 per classroom<br />

1 per 45 sq meter of administration area<br />

1 bus parking space per 3 classes<br />

Table 6.03,<br />

Parking Area Dimensions<br />

<br />

<br />

<br />

Mosque<br />

Library/Cultural Center<br />

Medical Facility<br />

Fire Station<br />

Daycare/Nursery<br />

Municipality Services<br />

Post Office<br />

Commercial<br />

Office, General<br />

Eating Establishments<br />

Entertainment<br />

Retail & Service<br />

Hotel/Boutique Hotel<br />

Staff<br />

Restaurants<br />

Utility/Communication<br />

Public Utility<br />

Waste Related Services<br />

TBD<br />

1 per 60 sq. meters<br />

1 per 60 sq. meters<br />

TBD<br />

1 per 60 sq. meters<br />

1 per 30 sq. meters<br />

1 per 30 sq. meters<br />

1 per 50 sq. meters + 10% for visitors<br />

1 per 25 sq. meters<br />

1 per 5 seats<br />

1 per 25 sq. meters of leasable space<br />

1 per 5 rooms<br />

1 for each hotel room containing kitchen<br />

1 per 2 hotel suits<br />

1 for each flat upto 150 sq meters floor area<br />

2 for each flat over 150 sq meters floor area<br />

1 per 2 employees<br />

1 per 45 sq. meters of restaurant area<br />

1 per 60 sq. meters of gross floor area<br />

1 per 60 sq. meters<br />

<br />

<br />

<br />

<br />

Parking Angle (in degrees) Parallel 45 60 75 90<br />

Stall Width (in meters) 2.7 2.7 2.7 2.7 2.5<br />

Stall Length (in meters) 7 7 7 7 5.0/ 5.5<br />

Aisle Width (in meters) 4 3.75 4.5 6 6<br />

Access Driveway Width (in meters) 6 6 6 6 6<br />

Overall Width (in meters) 9 16.5 18.1 18.75 17/ 18<br />

Turning radius (in meters) 4 4 4 4 4<br />

For further Parking requirements refer new JAFZA regulations


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

21<br />

s i g n s<br />

7. Signs<br />

S I G N S<br />

Section 7.01. General<br />

All signs erected, altered, displayed, or relocated in Jumeirah<br />

Village shall be constructed, maintained and removed<br />

according to the standards established by this <strong>Code</strong>.<br />

Section 7.01.01. Signs Permitted by Zone<br />

Table 7.01, Signs by Zone indicates sign classification by<br />

Zoning Zone according to type and purpose. A “P” indicates<br />

that a classification of sign is permitted by right within<br />

the given Zone. Permitted signs must meet all appropriate<br />

requirements of this <strong>Code</strong>.<br />

Section 7.01.02. Summary of Standards<br />

Tables 7.02, Sign Standards by Purpose provides a description<br />

of sign requirements permitted according to:<br />

A. total permitted sign area.<br />

B. maximum number.<br />

C. sign type.<br />

D. maximum height.<br />

E. lighting requirements.<br />

Section 7.01.03. Required Approval<br />

All temporary or permanent signs erected, altered, displayed<br />

or relocated in Jumeirah Village require approval from<br />

Jumeirah Village LLC in accordance with the development<br />

review process described in Section 9, Administration and<br />

Procedures.<br />

Table 7.01,<br />

Signs by Zone<br />

Zone<br />

Midrise P P P P P<br />

Tower P P P P P P<br />

Town Center P P P P P P<br />

Neighborhood Retail P P P P P<br />

Ramblas P P P P P<br />

Open Space P P P P P<br />

Purpose<br />

Identification P P P P P<br />

Information P P<br />

Advertisement<br />

P<br />

Section 7.01.04. Sign on Premise<br />

All signs in Jumeirah Village shall be located on the site for<br />

which information or advertisement is intended.<br />

Section 7.01.05. Exemptions<br />

The following signs are exempt from the requirements of this<br />

<strong>Code</strong>:<br />

A. Signs which are wholly within individual building<br />

enclosures and which can be viewed only by the<br />

occupants and visitors to that building.<br />

B. Traffic, parking, warning, danger, street name, utility<br />

marker, official signs and legal notices issued by<br />

Jumeirah Village LLC.<br />

C. Works of art that do not include a commercial message.<br />

D. Address plate incidental to sign regulations no greater<br />

than 0.3 square meters in total area.<br />

Section 7.02. Abandoned Signs<br />

All signs shall be removed within 60 calendar days of the date<br />

that the business, person or activity that the signs identifies<br />

or advertises ceases to operate on the site on which the sign<br />

is located.<br />

Section 7.03. Master Sign Plan<br />

A Master Sign Plan shall be submitted for all applications for<br />

development that include signs beyond those exempted in<br />

accordance with Section 7.01.05, Exemptions. The Master<br />

Sign Plan shall show the location of the proposed signs and<br />

detail dimensions, proposed color, material, and method of<br />

illumination.<br />

Section 7.04. Prohibited Signs<br />

No sign shall be erected, altered or displayed which:<br />

A. Moves, makes sounds, revolves or uses waving, blinking,<br />

flashing, vibrating, flickering or otherwise animated<br />

lighting.<br />

B. Constitutes a traffic hazard, by reasons of size, location,<br />

projection, content, color or manner of illumination.<br />

C. Is affixed to utility poles, trees, stones, bushes, other<br />

natural features or other signs.<br />

D. Obstructs light, air, ingress or egress from a required<br />

door, window or other opening.<br />

E. Is structurally unsafe or not kept in good repair or<br />

maintenance.<br />

F. Advertises a business or product no longer operated or<br />

sold.<br />

G. Projects more than 1 meter into the public right-of-way<br />

or within 1 meter of an adjacent street, as measured from<br />

the farthest projection of the sign.<br />

H. Obstructs neighboring signs or pedestrian traffic, either<br />

physically or visually.<br />

I. Is mounted on a roof.


22 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

S I G N S<br />

s i g n s<br />

Table 7.02,<br />

Sign Standards<br />

by Purpose<br />

Total Permitted Sign Area Maximum Number Sign Type<br />

Maximum<br />

Height of Sign<br />

Artificial<br />

Lighting<br />

Other Conditions<br />

Time Limit for Removal<br />

Permanent Signs<br />

Location or Tenant<br />

Identification<br />

1.5 sq. meter per linear meter of plot<br />

frontage (excepting tower sign)<br />

As approved by Jumeirah<br />

Village LLC<br />

As approved by Jumeirah<br />

Village LLC<br />

As approved by Jumeirah<br />

Village LLC<br />

Directional/Informational 0.1% of lot area As approved by Jumeirah<br />

Village LLC<br />

Canopy<br />

canopy height<br />

Projecting 4 meters internal or<br />

external<br />

Wall 3 meters internal or<br />

external<br />

1 per plot Tower 2 meters below<br />

top of upper<br />

shaft<br />

Pedestal<br />

Wall<br />

3.5 meters<br />

2.5 meters<br />

internal or<br />

external<br />

As approved<br />

by Jumeirah<br />

Village LLC<br />

Advertisement 3 sq. meter Window 3.0 meters none --<br />

Temporary Signs<br />

Real Estate<br />

Special Event or Sale<br />

Contractor Advertisement<br />

Future Facility Advertisement<br />

1 sq. meter in Villa and Townhome Zones &<br />

0.5% of lot area in other Zones up to 4 sq.<br />

meters<br />

minimum of 1 sq. meter or 0.5% of lot area<br />

up to 3 sq. meters<br />

1 sq. meter in Villa and Townhome Zones<br />

& 0.5% of lot area in other Zones up to 10<br />

sq. meters<br />

1 sq. meter in Villa and Townhome Zones &<br />

0.1% of lot area in other Zones up to 6 sq.<br />

meters<br />

1 per street frontage Pedestal, Wall or<br />

Window<br />

2 per street frontage Pedestal, Wall or<br />

Window<br />

1 per lot Ground, Pedastal,<br />

Wall, or Window<br />

1 per street frontage Ground, Pedastal,<br />

Wall, or Window<br />

Minimum 3 square meters of total sign area reserved for<br />

each ground floor business<br />

4 sq. meter per linear meter of building frontage, not to<br />

exceed 200 sq. meters<br />

No advertising message permitted<br />

Within 60 days from date that<br />

business ceases operation at<br />

the site of the sign<br />

2 meters -- Advertise only the site on which sign is located On or before closing date of sale<br />

3 meters -- Include only the name, date, time and content of event 14 days prior and 2 days after<br />

the sale or event<br />

4 meters front light<br />

external<br />

4 meters front light<br />

external<br />

Advertise only information related to the consultants<br />

licensed to work on the project including name, address,<br />

phone number, and internet web site. Sign to be sufficiently<br />

durable to remain in a high quality condition through its use<br />

on location.<br />

Advertise only information related to the facilities and<br />

amenities to be located on the site including uses, size and<br />

date of availability. May advertise a project contact for<br />

additional information including an address, phone number,<br />

and internet web site. Sign to be sufficiently durable<br />

to remain in a high quality condition through its use on<br />

location.<br />

10 days after issuance of<br />

Certificate of Occupancy<br />

10 days after issuance of<br />

Certificate of Occupancy


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

23<br />

s i g n s<br />

S I G N S<br />

J. Is Portable, except temporary A-frame signs.<br />

K. Contains strings of light not permanently mounted to a<br />

rigid background.<br />

L. Is Inflatable and tethered to balloons greater than 50cm<br />

in diameter.<br />

M. Is an electronic message center in fixed or traveling<br />

mode.<br />

Section 7.05. Lighting<br />

Sign lighting shall be arranged and maintained so that the<br />

source is not directly visible from a public right-of-way or<br />

adjacent property. Artificial lighting is allowed as permitted in<br />

Table 7.02, Sign Standards by Purpose.<br />

Section 7.06. Maintenance<br />

Each applicant that receives approval for a sign in Jumeirah<br />

Village shall be responsible for maintaining such sign in a<br />

secure and safe condition. If Jumeirah Village LLC is of the<br />

opinion that a sign is not secure, safe or in good state of<br />

repair or maintenance, such sign shall be considered to be in<br />

a violation of this <strong>Code</strong> and enforcement proceedings shall be<br />

commenced.<br />

Section 7.07. Language<br />

The content of all signs shall be displayed in both Arabic and<br />

English, with equivalent translations of all sign content.<br />

Section 7.08. Dimensions<br />

7.08.01. Computation of Area of Individual Signs<br />

A. The area of a sign shall be computed as the entire<br />

advertising area of the sign, including any framing or<br />

trim used to differentiate a sign face from the structure<br />

against which a sign face is placed.<br />

B. Where a sign consists of individual letters, words or<br />

symbols attached to a surface, building, canopy, awning,<br />

or wall, the sign area shall be the area of the smallest<br />

rectangle which completely encompasses all letters,<br />

words or symbols and accompanying background of a<br />

color different than the natural color of the wall. Where<br />

such sign includes multiple words, each word located in<br />

the same plane shall be computed separately.<br />

7.08.02. Computation of Area of Multi-faced Signs<br />

The area for a sign with more than one face shall be<br />

computed by adding together the area of all sign faces<br />

visible from any one point. Two identical sign faces shall be<br />

computed as a single face under the following conditions:<br />

<br />

A. Sign faces are placed back to back so that both faces<br />

cannot be viewed from any point at the same time.<br />

B. Sign faces are substantially similar.<br />

Al Karaba Tailor<br />

7.08.03. Computation of Height<br />

The height of a sign shall be computed as the distance from<br />

ground level to the top of the highest attached component<br />

of the sign unless otherwise stated in Table 7.02, Signs<br />

Standards by Purpose.<br />

7.08.04. Computation of Maximum Total Permitted Sign Area<br />

and Maximum Number of Signs<br />

The permitted sum of the area of all individual signs and the<br />

total number of permitted signs shall be computed based on<br />

standards identified in Table 7.02, Sign Standards by Purpose.<br />

Section 7.09. Temporary Signs<br />

Specific signs may be located in Jumeirah Village on a<br />

temporary basis. Temporary signs shall be required to meet<br />

the sign area, maximum number, sign type, maximum height,<br />

lighting and time limit requirements established in Table 7.02,<br />

Sign Standards by Purpose. No site plan will be approved<br />

unless all proposed temporary signs conform to the standards<br />

stated in Table 7.03. Permitted temporary signs include those<br />

addressing:<br />

A. Real estate.<br />

B. A special event or sale, including A-frame signs.<br />

C. Contractor advertisement.<br />

D. Future facility advertisement.<br />

Al Karaba Bakery<br />

Figure 7.02,<br />

General Sign Measurements<br />

C<br />

A<br />

F<br />

E<br />

two sign<br />

faces count<br />

as one<br />

width<br />

length<br />

height<br />

C. Sign faces are part of the same sign structure.<br />

Sale<br />

3 Dhs.


24 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

L A N D S C A P E A N D F E N C I N G<br />

8. Landscape and Fencing<br />

Section 8.01. General<br />

8.01.01. Purpose<br />

Landscaping and fencing regulations are established as<br />

part of this <strong>Code</strong> to encourage pleasant and attractive<br />

surroundings and to contribute to the relief of heat, noise,<br />

dust and glare through the proper placement of plants and<br />

fences and to provide for the needs of security and privacy.<br />

8.01.02. General Standards<br />

Table 8.01, Landscape and Fencing Standards provides<br />

a general list of landscape and fencing requirements<br />

associated with this <strong>Code</strong>.<br />

8.01.03. Irrigation and Maintenance<br />

A. Required landscape areas shall be provided with a fixed<br />

and permanent irrigation system for planted areas,<br />

protected by adequate back flow prevention, designed<br />

and installed in accordance with the following general<br />

provisions:<br />

1. Water conservation shall be accomplished in<br />

manually operated (hose-bib) system by the<br />

installation of flow limiting devices.<br />

2. Applicable codes shall be used for the design and<br />

installation of automatic control systems.<br />

B. In all Zones, required landscaped areas shall be<br />

permanently maintained including the proper pruning,<br />

weeding and removal of litter, fertilizing and replacement<br />

of plants when necessary.<br />

C. To minimize problems created by blowing sand and dust<br />

all ground planes in the exterior areas of parcels shall be<br />

treated so that there is no bare ground. Pavement, stone<br />

mulch or groundcovers are acceptable means of treating<br />

the earth.<br />

8.01.04. Safety<br />

No landscaping shall be permitted that endangers health or<br />

public safety by creating a traffic or fire hazard, obstructing<br />

vision, or detracts from the use of surrounding property.<br />

8.01.05. Landscape Plan Requirement<br />

As part of any application for Concept Plan and Site Plan<br />

approval, a Landscape Plan shall be submitted showing the<br />

proposed landscape development, irrigation system and<br />

fences. The Landscape Plan may be combined with other<br />

plans provided all proposed landscaping is adequately<br />

detailed on the plan.<br />

Section 8.02. Special Requirements by Zone<br />

8.02.01. Town Center and Tower Zone<br />

There are no special landscaping requirements in the Town<br />

Center and Tower Zones other than roof garden requirements.<br />

8.02.02. Neighborhood Retail Zone<br />

A. Vegetation utilized to meet the Open Lot landscaping<br />

requirement shall not be considered as all or part of the<br />

open space requirement.<br />

B. Open space is intended to be largely urban in nature and<br />

shall include 75 percent paved area. At least 50 percent<br />

of the paved area shall be shaded by buildings, trellises<br />

or shade trees.<br />

8.02.03. Mid-Rise Apartment Zone<br />

A. For each required Mid-Rise Apartment open space as<br />

described in Section 5.13, the following shall apply:<br />

1. Between 40 and 70 percent of the passive recreation<br />

areas shall be covered with a mix of paving<br />

materials including concrete, brick, block, stone,<br />

or pavers and a minimum of 50 percent of the<br />

paved area shall be shaded using a combination of<br />

buildings, trellises, vines, and shade trees.<br />

2. Each required open space shall have at least one<br />

water feature that covers a minimum of 1 square<br />

meter of area.<br />

B. Front yard open areas shall include a minimum of one<br />

shade tree for every 8 meters of open frontage.<br />

8.02.04 Villa and Townhome Zones<br />

Each lot in the Villa Zone shall have at least 3 trees in the<br />

front yard area, at least one of which shall be a shade tree.<br />

Each lot in the Townhome Zone shall have at least one shade<br />

tree in the front yard.<br />

8.02.05 Village Centers within the Open Space Zone<br />

A required courtyard or plaza within the Open Space Zone<br />

shall have a minimum of 75 percent paved area. At least<br />

50 percent of the paved area shall be shaded by buildings,<br />

trellises or shade trees.<br />

Section 8.03. Paseos and Roof Gardens<br />

In keeping with the Eight Principles guiding the design of<br />

Jumeirah Village, paseos and roof gardens are hereby<br />

incorporated into the community as a means of providing<br />

additional green space and recreational amenities.<br />

8.03.01. Paseos<br />

Each paseo shall be located in the Townhome Zone and<br />

designed to provide both paved and landscaped areas in a<br />

small, private court.<br />

A. Between 50 to 75 percent of the interior ground plane of<br />

a paseo shall be paved. The remaining area shall include<br />

a vegetative ground cover or stone mulch.<br />

B. A minimum of 50 percent of the paved area shall be<br />

covered in brick, stamped concrete, stone, unit pavers or<br />

other type of detailed, pedestrian scale paving material.<br />

C. A minimum of 8 shade trees shall be planted and<br />

maintained in a healthy growing condition in each paseo.<br />

D. Each Paseo shall have a minimum of one small scale<br />

water feature.<br />

8.03.02. Roof gardens.<br />

Roof gardens shall be required or encouraged in accordance<br />

with Table 8.02, Roof Gardens, and shall consist of a mix of<br />

paving, shade, water features, trees and shrubs as follows:<br />

A. Roof gardens shall be between 50 and 85 percent paved.<br />

B. A minimum of 50 percent of the paved area shall be<br />

covered in brick, stamped concrete, stone, unit pavers or<br />

other type of detailed, pedestrian scale paving material.<br />

At least 50 percent of the paved area shall be shaded<br />

with shade trees or vines on trellises.<br />

C. Unpaved areas shall be covered in plant material or<br />

stone mulch.<br />

D. Each roof garden shall have at least one water feature<br />

for every 2,500 square meters of pavement. Each water<br />

feature shall be at least 1 square meter in area.<br />

Section 8.04. Fencing<br />

8.04.01. Required Fences<br />

Fences shall be required as appropriate within each Zone as<br />

indicated in Table 8.01, Landscape and Fencing Standards.<br />

A. Each lot in the Villa Zone or Townhome Zone shall include<br />

a perimeter fence along the boundaries of the lot.<br />

B. Fences between properties in the Villa and Townhome<br />

Zones shall consist of a single, shared fence along the<br />

property line.<br />

C. Fences, including foundations, shall be placed entirely<br />

inside the lot or parcel to which they belong except in the<br />

instance of a single, shared fence along a property line.<br />

D. Fences shall be constructed of durable materials that<br />

are compatible with buildings on the same lot in terms<br />

of materials, finish, color and appearance. No fences of<br />

wood, plastic, or chain link shall be allowed.<br />

E. Fences shall be a uniform height of 2 meters, except as<br />

described in Section 8.04.02.<br />

8.04.02. Fence Types<br />

A fence may be classified as one of the following:<br />

A. Solid Fence. A solid fence shall be constructed of<br />

concrete block and stucco and have no openings larger<br />

than 100 cm in diameter or width or 300 cm tall. Solid<br />

fences may have a decorative cap of which no more than<br />

50 percent of the top may be 100 cm or less above or<br />

below the required uniform height.<br />

B. Half Fence. A semi-solid fence shall have a solid lower<br />

half constructed of concrete block and stucco, and upper<br />

half that is of open design, in which a physical separation<br />

shall be maintained between the two sides of the fence<br />

but the visual connection between the two sides shall<br />

remain. Alternately, a full vertical open section may be<br />

used, as long as the open design areas constitute at least<br />

1/3 of the total length of the fence, and no solid section is<br />

greater than 3 meters long.<br />

l a n d s c a p e a n d f e n c i n g


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

25<br />

l a n d s c a p e a n d f e n c i n g<br />

Table 8.01,<br />

Landscaping<br />

and Fencing<br />

L A N D S C A P E A N D F E N C I N G<br />

Front and Side Yard<br />

Solid Fence Yes Street edge of Paseo - - - - -<br />

Half Fence<br />

Yes<br />

Yes - - - -<br />

Facing on interior or paseo<br />

Open Fence Yes Yes - - - -<br />

No Fence - - Yes Yes Yes Yes Yes<br />

Rear Yard<br />

Solid Fence Yes - Facing Alley - - Optional -<br />

Half Fence - -<br />

- - - -<br />

Facing interior courtyard<br />

Open Fence - - - - - -<br />

or roof garden<br />

No Fence - Yes Yes Yes - Yes<br />

Alley Fence<br />

Solid Fence - Yes Yes - - Yes -<br />

No Fence Yes - - Yes Yes - Yes<br />

Loading Area Fence<br />

Solid Fence - - Yes Yes Yes Yes -<br />

No Fence Yes Yes - - - - Yes<br />

Vertical Front Yard Trellis and Vines<br />

Solid Fence Mandatory Mandatory Optional - - Optional -<br />

Other Fence Optional Optional Optional - - - -<br />

Horizontal Front Yard Trellis over Sidewalk<br />

Required Yes Yes Yes - - - -<br />

Not Required - - - Yes Yes Yes Yes<br />

Special Landscape<br />

Requirements**<br />

Front yard and ground<br />

plane<br />

* A half fence includes a solid lower half with an open top half<br />

** as described in the text of Section 8<br />

Interior of paseo Roof garden Roof garden Roof garden<br />

Plaza or Courtyard<br />

Landscaping<br />

Plaza or Courtyard for<br />

Village Center Clusters


26 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

L A N D S C A P E A N D F E N C I N G<br />

Table 8.02,<br />

Roof Gardens<br />

l a n d s c a p e a n d f e n c i n g<br />

Roof Garden Requirement*<br />

Podium - - 90% 80% 90% Optional Optional<br />

Lower Shaft - - 50% 50% 50% - -<br />

Middle Shaft - - 50% 30% 30% - -<br />

Upper Shaft to Top - - 50% Optional Optional - -<br />

Carpark Roof - - 75% 75% 90% Optional 100%**<br />

* percentage of available space at the specified level<br />

** if carpark is below ground<br />

C. Open Fence. An open design fence shall be constructed<br />

of wrought iron, aluminum or other acceptable material<br />

and shall maintain a physical separation between the<br />

two sides of the fence, but shall maintain open, visual<br />

contact between the two sides.<br />

Section 8.05. Parking Areas<br />

8.05.01. Required Landscaping in Open Lot<br />

A. A minimum of 5 percent of an Open Lot parking area with<br />

space for five or more vehicles shall be landscaped.<br />

B. There shall be one shade tree for every 25 cars in an<br />

Open Lot.<br />

8.05.02. Plan Requirement<br />

Placement of vegetation in any Open Lot shall be indicated on<br />

any Landscape Plan submitted for Concept Plan or Site Plan<br />

approval.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

27<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s<br />

9. Administration and Procedures<br />

Figure 9.01,<br />

Development Plan Process<br />

Pre-Application<br />

Meeting<br />

Concept Plan<br />

(Optional)<br />

Site Plan<br />

Application<br />

General discussion of the project<br />

with the applicant prior to a<br />

significant expenditure of resources.<br />

Administrator to determine if<br />

Concept Plan is needed.<br />

Allows for continued review and<br />

discussion between Adminstrator<br />

and Applicant. Level of required<br />

content is increased. Beneficial for<br />

complex projects.<br />

Detailed documentation of project<br />

and review by Administrator.<br />

Necessity of Variances or Exceptions<br />

is determined and addressed at this<br />

stage (if necessary).<br />

Building Permit<br />

Application<br />

To be granted upon review of final<br />

review of all construction documents<br />

and determination that all<br />

additional approvals (including EIA,<br />

if needed) have been met.<br />

Section 9.01. General<br />

9.01.01. Applications<br />

Jumeirah Village LLC shall utilize a series of applications<br />

and processes to ensure that development activity or<br />

other actions meet the overall goals of the Jumeirah<br />

Village - Master Plan and the specific requirements of the<br />

Development <strong>Code</strong>. The application process further serves as<br />

a tool for communication between the potential developer or<br />

applicant and Jumeirah Village LLC.<br />

9.01.02. General Development Plan Process<br />

A single development planning process, as shown in Figure<br />

9.01, Development Plan Process, shall be utilized by Jumeirah<br />

Village LLC in all development related activity in Jumeirah<br />

Village, including new construction or alteration of existing<br />

structures, signs, parking or other amenities.<br />

9.01.03. Simultaneous Submission of Applications<br />

A single development may require several applications prior<br />

to approval of a building permit. To increase efficiency, the<br />

Development <strong>Code</strong> Administrator may permit an applicant to<br />

submit applications for approval to the same development<br />

simultaneously, assuming that submissions continue to follow<br />

the sequence described in Figure 9.01. As an exception, an<br />

applicant may submit a request for a Variance, Exception or<br />

Conditional Use simultaneous with a Site Plan application<br />

if the need for such application is already known to the<br />

potential applicant and the Development <strong>Code</strong> Administrator.<br />

9.01.04. Prequalification of Consultants<br />

All engineering, architecture and allied professionals utilized<br />

in development of plans and implementation of the project<br />

must be licensed and registered by Jumeirah Village LLC<br />

to perform work in Jumeirah Village. Approval of specific<br />

consultants to be used for a project must occur prior to<br />

submission of a Concept Plan or Site Plan application.<br />

9.01.05. Application Checklists<br />

Application forms shall be provided by Jumeirah Village<br />

LLC for completion by any potential applicant. Application<br />

Checklists includes a list of items needed from an applicant<br />

as needed or appropriate.<br />

9.01.06. Additional Information<br />

The Development <strong>Code</strong> Administrator has the authority<br />

to waive information or to request additional information<br />

as appropriate throughout the process. Reasonable time<br />

required to obtain and provide additional information shall not<br />

be considered in meeting time requirements established by<br />

this <strong>Code</strong>.<br />

Section 9.02. Common Review Requirements<br />

9.02.01. Pre-Application Meeting<br />

Prior to submitting an application for consideration, a<br />

potential applicant must request and attend a Pre-Application<br />

Meeting with the Development <strong>Code</strong> Administrator. The<br />

purpose of the Pre-Application Meeting shall be to:<br />

A. Familiarize the applicant with Jumeirah Village LLC,<br />

Jumeirah Village, the Master Plan, the Development<br />

<strong>Code</strong>, and any other requirements. The Development<br />

<strong>Code</strong> Administrator shall ensure that the potential<br />

applicant is aware of the application process and<br />

the requirements that must be met to receive project<br />

approval.<br />

B. Allow the Development <strong>Code</strong> Administrator and potential<br />

applicant to discuss the potential project. Discussion is<br />

intended to ensure that applications for development<br />

are submitted in an efficient manner and that the final<br />

product best meets the vision of the Master Plan and the<br />

requirements of this <strong>Code</strong>.<br />

C. Determine the need for a Concept Plan. In making<br />

a determination between requiring a Concept Plan<br />

or permitting the applicant to apply for a Site Plan,<br />

the Development <strong>Code</strong> Administrator shall consider<br />

the complexity of the project, the need for additional<br />

information and other considerations as determined<br />

necessary. The applicant may also specifically request to<br />

submit a Concept Plan.<br />

D. Evaluate the need for additional approvals. If the<br />

Development <strong>Code</strong> Administrator determines that a<br />

proposed project will not meet the requirements of this<br />

<strong>Code</strong>, the applicant may prepare to request a Variance or<br />

Exception. As an alternative, the applicant may request<br />

an amendment to the Development <strong>Code</strong> or Zoning Map.<br />

Should the applicant opt to apply for an amendment to<br />

the Development <strong>Code</strong> or Zoning Map, approval shall<br />

be necessary prior to submitting a Concept Plan or Site<br />

Plan.<br />

9.02.02. Development Intent Questionnaire<br />

To request a Pre-Application Meeting, a potential<br />

applicant must complete and submit a Development Intent<br />

Questionnaire. The Questionnaire shall be based on the<br />

checklist included in Application Checklists and designed to<br />

provide the general information needed fulfill the purpose of<br />

the Pre-Application Meeting.<br />

9.02.03. Review for Completeness<br />

A. The Development <strong>Code</strong> Administrator is responsible for<br />

ensuring that each application is complete for review<br />

and consideration. Determination of Completeness shall<br />

be made within five working days of submission of any<br />

application.<br />

B. In the event that the Development <strong>Code</strong> Administrator<br />

determines that an application is incomplete, the<br />

applicant shall be notified and given a specific period<br />

of time (such as five working days) to resubmit the<br />

application. If, upon expiration of the specified time<br />

period, the applicant has not provided the requested<br />

information, the application shall be rejected.<br />

C. Determination that an application is complete shall not<br />

preclude the Development <strong>Code</strong> Administrator or the<br />

DRB from denying an application or requesting additional<br />

information, as needed.<br />

9.02.04. Appeals<br />

As noted in Section 2.01, Roles and Duties, an appeals<br />

process is established in the event that an applicant feels<br />

that denial was unjustified. All appeals of decisions rendered<br />

by the Development <strong>Code</strong> Administrator shall be forwarded<br />

to the DRB for review and consideration, including the<br />

reasons the applicant feels the denial was in error. Similarly,<br />

all decisions of the DRB, including appeals findings, will be<br />

reviewed and decided by Jumeirah Village LLC. As discussed,<br />

in Section 2, Review Authority, decision by Jumeirah Village<br />

LLC shall be final.<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S


28 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S<br />

Figure 9.02,<br />

Pre-Application Review Process<br />

Pre-Application<br />

Meeting Stage<br />

Concept Plan<br />

Stage<br />

(Optional)<br />

Site Plan<br />

Stage<br />

Building Permit<br />

Stage<br />

Yes<br />

No<br />

Development Intent<br />

Application<br />

Submitted<br />

Review for<br />

Completeness<br />

Pre-Application<br />

Meeting Conducted<br />

Is a Concept Plan<br />

Needed?<br />

Section 9.03. Concept Plan<br />

9.03.01. Submission of Materials<br />

The applicant shall submit to Jumeirah Village LLC two sets of<br />

all design materials required in the Application Checklists as<br />

well as the Concept Plan Application.<br />

A. Generally, the Concept Plan shall conceptually show to<br />

scale property boundaries, approximate location and<br />

dimensions of all structures, setbacks, location and<br />

general information regarding signs, parking areas,<br />

entryways, topography, north orientation, a description of<br />

general bulk requirements, landscaping and schematic<br />

floor plans, and elevations of at least three sides of<br />

all structures. Specific requirements are provided in<br />

Application Checklists.<br />

B. An additional CAD file of the Concept Plan may be<br />

submitted as a supplement to required materials. If<br />

submitted, the CAD file should be in a format that is<br />

acceptable to Jumeirah Village LLC, including file format,<br />

separation of design elements into layers, and clean line<br />

work.<br />

C. A spreadsheet summary of all development data, in<br />

compliance with the requirements of this <strong>Code</strong> (such as<br />

lot area, built up area and parking provision).<br />

9.03.02. Plan Review Process<br />

A. The approval process shall follow the steps highlighted in<br />

Figure 9.03, Concept Plan Review Process and discussed<br />

throughout Section 9, Administration and Procedures.<br />

B. The Development <strong>Code</strong> Administrator shall review the<br />

application in its ability to meet the vision of the Jumeirah<br />

Village Master Plan and the requirements of this <strong>Code</strong>.<br />

If all requirements are met, the Development <strong>Code</strong><br />

Administrator shall approve the application. If additional<br />

information is needed, the Administrator shall request<br />

additional information.<br />

C. The Development <strong>Code</strong> Administrator shall notify the<br />

applicant of final action, including approval or denial of<br />

the application. One set of the plans marked as approved<br />

or denied shall be accompanied by a letter and returned<br />

to the applicant while the second set shall be similarly<br />

marked and retained by Jumeirah Village LLC.<br />

D. The Development <strong>Code</strong> Administrator reserves the right<br />

to approve a Concept Plan with conditions, assuming<br />

that such conditions serve to bring the project into<br />

compliance with this <strong>Code</strong>.<br />

E. If approval is conditional, the applicant may request a<br />

meeting with the Development <strong>Code</strong> Administrator to<br />

discuss the conditions and request reconsideration.<br />

Following further review, the Development <strong>Code</strong><br />

Administrator shall notify the applicant of revisions, if<br />

any, to the final action.<br />

9.03.03. Time<br />

A. The Development <strong>Code</strong> Administrator shall approve or<br />

deny a Concept Plan within 10 working days of receipt<br />

of the application and determination of completeness.<br />

Notification of approval or denial shall be made within<br />

5 working days of final action, for a total of 15 working<br />

days.<br />

B. Upon approval, the applicant shall have no more than<br />

3 months to submit a Site Plan application. Following 3<br />

months, a Concept Plan shall be considered expired. An<br />

extension of time may be granted by Jumeirah Village<br />

LLC upon request.<br />

C. If approval is conditional, the applicant shall be deemed<br />

to have agreed with all conditions unless, within 15<br />

working days, the applicant requests a meeting with the<br />

Development <strong>Code</strong> Administrator to review the decision.<br />

D. Within 15 working days of meeting the applicant to<br />

discuss the conditional approval, the Development <strong>Code</strong><br />

Administrator shall notify the applicant of revisions, if<br />

any, to the final action.<br />

Section 9.04. Site Plan<br />

9.04.01. Submission of Materials<br />

A. The applicant shall submit to Jumeirah Village LLC<br />

two sets of all design materials required in Application<br />

Checklists as well as the Site Plan Application.<br />

B. Generally, the Site Plan shall accurately show to scale<br />

property boundaries, location and dimensions of all<br />

structures, all building wall elevations and setbacks,<br />

parking areas, entryways, topography, north orientation,<br />

Figure 9.03,<br />

Concept Plan Review Process<br />

Pre-Application<br />

Meeting Stage<br />

Concept Plan<br />

Stage<br />

(Optional)<br />

Site Plan<br />

Stage<br />

Building Permit<br />

Stage<br />

Yes<br />

Yes with<br />

Conditions<br />

Concept Plan<br />

Application and<br />

Materials Submitted<br />

Review for<br />

Completeness<br />

Application Review<br />

Is More Information<br />

Needed?<br />

No<br />

Yes<br />

Is the Application<br />

Approved?<br />

No<br />

Letter of<br />

Rejection<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

29<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s<br />

Figure 9.04,<br />

Site Plan Review Process<br />

Pre-Application<br />

Meeting Stage<br />

Concept Plan<br />

Stage<br />

(Optional)<br />

Site Plan<br />

Stage<br />

Building Permit<br />

Stage<br />

Yes<br />

Yes with<br />

Conditions<br />

Site Plan Application<br />

and Materials<br />

Submitted<br />

Review for<br />

Completeness and<br />

Modifications<br />

Application Review<br />

Is More Information<br />

Needed?<br />

No<br />

Yes<br />

Does the Project<br />

Require a Variance,<br />

Exception or<br />

Conditional Use?<br />

No<br />

Is the Application<br />

Approved?<br />

Yes<br />

No<br />

To DRB for<br />

Consideration<br />

Letter of<br />

Rejection<br />

a description of bulk details, and detailed floor plans.<br />

A master sign plan and a master landscape and open<br />

space plan, including irrigation, shall be incorporated<br />

into the Site Plan Application, Specific requirements are<br />

provided in Application Checklists.<br />

C. A CAD file of the Site Plan must be submitted. The CAD<br />

file should be in a format that is acceptable to Jumeirah<br />

Village LLC, including file format, separation of design<br />

elements into layers, and clean line work.<br />

9.04.02. Minor Modifications to Approved Concept Plan<br />

The applicant may be permitted to make minor modifications<br />

to the approved Concept Plan prior to Site Plan application.<br />

All said modifications should be noted for review by the<br />

Development <strong>Code</strong> Administrator.<br />

9.04.03. Plan Review Process<br />

A. The approval process shall follow the steps highlighted<br />

in Figure 9.03, Site Plan Review Process and discussed<br />

throughout Section 9, Administration and Procedures.<br />

B. The Development <strong>Code</strong> Administrator shall review the<br />

application in its ability to meet the vision of the Jumeirah<br />

Village - Master Plan and the requirements of this <strong>Code</strong>.<br />

If all requirements are met, the Development <strong>Code</strong><br />

Administrator shall approve the application. If additional<br />

information is needed, the Administrator shall request<br />

additional information.<br />

C. The Development <strong>Code</strong> Administrator shall determine<br />

if a request for variance or exception is warranted or if<br />

the project requires approval as a Conditional Use. If so,<br />

the Administrator will notify the applicant of the need<br />

for approval by the DRB prior to approval of a Building<br />

Permit.<br />

D. The Development <strong>Code</strong> Administrator shall notify the<br />

applicant of final action, including approval or denial of<br />

the application. One set of the plans marked as approved<br />

or denied shall be accompanied by a letter and returned<br />

to the applicant while the second set shall be similarly<br />

marked and retained by Jumeirah Village LLC.<br />

E. The Development <strong>Code</strong> Administrator shall provide<br />

the applicant with a list of various additional approvals<br />

and studies needed prior to Building Permit approval,<br />

including, if needed, completion of an Environmental<br />

Impact Assessment (EIA).<br />

F. The Development <strong>Code</strong> Administrator reserves the<br />

right to approve a Site Plan with conditions, assuming<br />

that such conditions serve to bring the project into<br />

compliance with this <strong>Code</strong>.<br />

G. If approval is conditional, the applicant may request a<br />

meeting with the Development <strong>Code</strong> Administrator to<br />

discuss the conditions and request reconsideration.<br />

Following further review, the Development <strong>Code</strong><br />

Administrator shall notify the applicant of revisions, if<br />

any, to the final action.<br />

9.04.04. Time<br />

A. The Development <strong>Code</strong> Administrator shall approve<br />

or deny a Site Plan within 15 working days of receipt<br />

of the application and determination of completeness.<br />

Notification of approval or denial shall be made within<br />

5 working days of final action, for a total of 20 working<br />

days.<br />

B. Upon approval, the applicant shall have no more than 3<br />

months to submit a Building Permit application. Following<br />

3 months, a Site Plan shall be considered expired. An<br />

extension of time may be granted by Jumeirah Village<br />

LLC upon request.<br />

C. If approval is conditional, the applicant shall be deemed<br />

to have agreed with all conditions unless, within 15<br />

working days, the applicant requests a meeting with the<br />

Development <strong>Code</strong> Administrator to review the decision.<br />

D. Within 15 working days of meeting the applicant to<br />

discuss the conditional approval, the Development <strong>Code</strong><br />

Administrator shall notify applicant of any revisions to the<br />

final action.<br />

Section 9.05. Building Permit<br />

9.05.01. Submission of Materials<br />

A. Generally, the Building Permit shall include final<br />

drawings and construction documents as needed to<br />

commence construction.<br />

B. The Building Permit application and all drawings will be<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S


30 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S<br />

accompanied by approval of all additional applications<br />

and studies, including requirements for Variance,<br />

Exception or Conditional Use by the DRB.<br />

C. A CAD file of the Site Plan must be submitted as a<br />

component of required materials. The CAD file should be<br />

in a format that is acceptable to Jumeirah Village LLC,<br />

including file format, separation of design elements into<br />

layers, and clean line work.<br />

9.05.02. Minor Modifications to Approved Site Plan<br />

The applicant may be permitted to make minor modifications<br />

to the approved Site Plan prior to Building Permit application.<br />

All said modifications should be noted for review by the<br />

Development <strong>Code</strong> Administrator. The Development <strong>Code</strong><br />

Administrator reserves the right to determine that proposed<br />

changes are beyond “minor modifications” and reject such<br />

changes.<br />

9.05.03. Plan Review Process<br />

A. The approval process shall follow the steps highlighted<br />

in Figure 9.05, Building Permit Review Process and<br />

discussed throughout Section 9, Administration and<br />

Procedures.<br />

B. The Development <strong>Code</strong> Administrator shall conduct final<br />

review the application in its ability to meet the vision of<br />

the Jumeirah Village Master Plan and the requirements<br />

of this <strong>Code</strong>. If all requirements are met, the Development<br />

<strong>Code</strong> Administrator shall approve the application. If<br />

additional information is needed, the Administrator shall<br />

request additional information.<br />

C. The Development <strong>Code</strong> Administrator shall notify the<br />

applicant of final action, including approval or denial of<br />

the application. One set of the plans marked as approved<br />

or denied shall be accompanied by a letter and returned<br />

to the applicant while the second set shall be similarly<br />

marked and retained by Jumeirah Village LLC.<br />

D. Upon receipt of an approved Building Permit, the<br />

applicant may begin construction.<br />

9.05.04. Time<br />

A. The Development <strong>Code</strong> Administrator shall approve or<br />

deny a Building Permit within 15 working days of receipt<br />

of the application and determination of completeness.<br />

Notification of approval or denial shall be made within<br />

5 working days of final action, for a total of 20 working<br />

days.<br />

B. Upon approval, the applicant shall have no more than 3<br />

months to utilize an approved Building Permit. Following<br />

3 months, if the applicant has not initiated construction<br />

or is otherwise unable to prove progress, the Building<br />

Permit shall be considered expired. An extension of time<br />

may be granted by Jumeirah Village LLC upon request.<br />

Section 9.06. Variance<br />

9.06.01. Submission of Materials<br />

Generally, the application shall include all materials required<br />

to indicate the requested variance. If submitted as part of the<br />

Development Plan process, materials submitted for Site Plan<br />

review will largely be sufficient.<br />

9.06.02. General Criteria<br />

The Development Review Board may issue a variance from<br />

the requirements of the Development <strong>Code</strong> if such action is<br />

not contrary to the interest of residents, investors, employees,<br />

and guests of Jumeirah Village. The Development Review<br />

Board must also find that, due to special conditions, literal<br />

enforcement of the Development <strong>Code</strong> would result in undue<br />

and unnecessary hardship based upon the following criteria:<br />

A. Extraordinary conditions regarding the specific land<br />

involved are such that strict enforcement of this <strong>Code</strong><br />

would deprive the applicant of reasonable use of the<br />

land.<br />

B. The Variance would not be detrimental to the health,<br />

welfare, safety, morals, order, convenience, or prosperity<br />

of surrounding residents, investors, employees, and<br />

guests of Jumeirah Village.<br />

C. The conditions are unique to this site and do not apply to<br />

other locations found in the same Zone.<br />

D. The extraordinary conditions have not been created as a<br />

result of actions by the applicant.<br />

E. The Variance would be consistent with the spirit and<br />

intent of the Jumeirah Village Master Plan and this <strong>Code</strong>.<br />

F. Condition of the site and enforcement of this <strong>Code</strong> would<br />

prohibit or unreasonably restrict use of the land.<br />

Figure 9.05,<br />

Building Permit Review Process<br />

Pre-Application<br />

Meeting Stage<br />

Concept Plan<br />

Stage<br />

(Optional)<br />

Site Plan<br />

Stage<br />

Building Permit<br />

Stage<br />

Building Permit<br />

Application and<br />

Materials Submitted<br />

Review for<br />

Completeness and<br />

Modifications<br />

Application Review<br />

Is More Information<br />

Needed?<br />

No<br />

Yes<br />

Have all Additional<br />

Approvals been<br />

Obtained?<br />

Yes<br />

Is the Application<br />

Approved?<br />

No<br />

Yes<br />

No<br />

Letter of<br />

Rejection<br />

Building<br />

Permit<br />

Granted<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

31<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s<br />

Figure 9.06,<br />

Development Review Board Process<br />

Pre-Application<br />

Meeting Stage<br />

Concept Plan<br />

Stage<br />

(Optional)<br />

Site Plan<br />

Stage<br />

Building Permit<br />

Stage<br />

Yes<br />

Yes with<br />

Conditions<br />

Variance, Exception<br />

or Conditional Use<br />

Application and<br />

Materials Submitted<br />

Review for<br />

Completeness<br />

Review Application<br />

and Generate Report<br />

for DRB<br />

Is More Information<br />

Needed?<br />

No<br />

Yes<br />

Does DRB Determine<br />

that Application<br />

Meets Criteria?<br />

No<br />

Yes<br />

Is the Application<br />

Approved?<br />

Letter of<br />

Rejection<br />

9.06.03. Variance Process<br />

A. The approval process shall follow the steps highlighted<br />

in Figure 9.06, Development Review Board Process and<br />

discussed throughout Section 9, Administration and<br />

Procedures.<br />

B. The Development <strong>Code</strong> Administrator shall complete a<br />

report to the Development Review Board including an<br />

overview of the request for Variance, a recommendation<br />

of approval or denial, and proposed findings of fact to<br />

support the recommendation.<br />

C. The Development Review Board shall consider the<br />

recommendation of the Development <strong>Code</strong> Administrator<br />

and determine final action, including approval or denial<br />

of the application and specific findings of fact.<br />

D. The Development <strong>Code</strong> Administrator shall notify the<br />

applicant in writing of final action, including approval or<br />

denial of the application.<br />

E. The Development Review Board reserves the right to<br />

approve a Variance with conditions, safeguards or<br />

restrictions as needed to address any adverse impacts<br />

resulting from the Variance.<br />

9.06.04. Time<br />

A. The Development <strong>Code</strong> Administrator shall submit<br />

a report to the Development Review Board within<br />

15 working days of receipt of the application and<br />

determination of completeness.<br />

B. The Development Review Board shall take final action<br />

on the application for Variance within 15 working days<br />

of receiving the report from the Development <strong>Code</strong><br />

Administrator. Notification of approval or denial shall be<br />

made within 5 working days of final action, for a total of<br />

20 working days.<br />

C. Upon approval of a building permit, the applicant shall<br />

have no more than 3 months to utilize an approved<br />

Variance. Following 3 months, if the applicant has not<br />

initiated construction or is otherwise unable to prove<br />

progress, the Variance shall be considered expired. An<br />

extension of time may be granted by Jumeirah Village<br />

LLC upon request.<br />

Section 9.07. Exception<br />

9.07.01. Submission of Materials<br />

Generally, the application shall include all materials required<br />

to indicate the requested exception. If submitted as part of<br />

the Development Plan process, materials submitted for Site<br />

Plan review will largely be sufficient.<br />

9.07.02. General Criteria<br />

The Development Review Board may issue an exception from<br />

the requirements of the Development <strong>Code</strong> if such action is<br />

not contrary to the interest of residents, investors, employees,<br />

and guests of Jumeirah Village. The Development Review<br />

Board must also find that special conditions proposed by<br />

the applicant, while not in compliance with all requirements<br />

of the Development <strong>Code</strong>, are more or equally appropriate<br />

toward meeting the spirit of the Master Plan and this <strong>Code</strong>.<br />

Approval of the exception shall be based upon the following<br />

criteria:<br />

A. The proposed project remains compatible with<br />

surrounding land uses and is not detrimental to the<br />

health, welfare, safety, morals, order, convenience,<br />

or prosperity of surrounding residents, investors,<br />

employees, and guests of Jumeirah Village.<br />

B. The proposed exception will provide an equal or greater<br />

means of meeting the purposes of this <strong>Code</strong> than literal<br />

enforcement of existing requirements.<br />

C. The extraordinary conditions proposed by the applicant<br />

are unique to the project or the site.<br />

D. The exception would be consistent with the spirit and<br />

intent of the Jumeirah Village Master Plan and this <strong>Code</strong>.<br />

9.07.03. Exception Process<br />

A. The approval process shall follow the steps highlighted<br />

in Figure 9.06, Development Review Board Process and<br />

discussed throughout Section 9, Administration and<br />

Procedures.<br />

B. The Development <strong>Code</strong> Administrator shall complete a<br />

report to the Development Review Board including an<br />

overview of the request for Exception, a recommendation<br />

of approval or denial, and proposed findings of fact to<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S


32 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S<br />

support the recommendation.<br />

C. The Development Review Board shall consider the<br />

recommendation of the Development <strong>Code</strong> Administrator<br />

and determine final action, including approval or denial<br />

of the application and specific findings of fact.<br />

D. The Development <strong>Code</strong> Administrator shall notify the<br />

applicant in writing of final action, including approval or<br />

denial of the application.<br />

E. The Development Review Board reserves the right to<br />

approve an Exception with conditions, safeguards or<br />

restrictions as needed to address any adverse impacts<br />

resulting from the Variance.<br />

9.07.04. Time<br />

A. The Development <strong>Code</strong> Administrator shall submit<br />

a report to the Development Review Board within<br />

15 working days of receipt of the application and<br />

determination of completeness.<br />

B. The Development Review Board shall take final action<br />

on the application for Exception within 15 working days<br />

of receiving the report from the Development <strong>Code</strong><br />

Administrator. Notification of approval or denial shall be<br />

made within 5 working days of final action, for a total of<br />

20 working days.<br />

C. Upon approval of a building permit, the applicant shall<br />

have no more than 3 months to utilize an approved<br />

Exception. Following 3 months, if the applicant has not<br />

initiated construction or is otherwise unable to prove<br />

progress, the Exception shall be considered expired. An<br />

extension of time may be granted by Jumeirah Village<br />

LLC upon request.<br />

9.07.05. Runs with the Use<br />

Unless otherwise specified in the approval by the DRB, an<br />

exception applies only to the specific use or project for which<br />

it is granted. No new use or project shall be permitted to<br />

utilize the exception without prior approval by the DRB.<br />

Section 9.08. Conditional Use<br />

9.08.01. Submission of Materials<br />

Generally, the application shall include all materials required<br />

to indicate the requested conditional use. If submitted as part<br />

of the Development Plan process, materials submitted for Site<br />

Plan review will largely be sufficient.<br />

9.08.02. General Criteria<br />

The Development Review Board may issue approval of a<br />

Conditional Use if the proposed project meets the criteria<br />

established in Section 4.3, Conditional Use.<br />

9.08.03. Conditional Use Process<br />

A. The approval process shall follow the steps highlighted<br />

in Figure 9.06, Development Review Board Process and<br />

discussed throughout Section 9, Administration and<br />

Procedures.<br />

B. The Development <strong>Code</strong> Administrator shall complete<br />

a report to the Development Review Board including<br />

an overview of the request for Conditional Use, a<br />

recommendation of approval or denial, and proposed<br />

findings of fact to support the recommendation.<br />

C. The Development Review Board shall consider the<br />

recommendation of the Development <strong>Code</strong> Administrator<br />

and determine final action, including approval or denial<br />

of the application and specific findings of fact.<br />

D. The Development <strong>Code</strong> Administrator shall notify the<br />

applicant in writing of final action, including approval or<br />

denial of the application.<br />

E. The Development Review Board reserves the right<br />

to approve a Conditional Use with added conditions,<br />

safeguards or restrictions as needed to address any<br />

adverse impacts resulting from the Variance.<br />

9.08.04. Time<br />

A. The Development <strong>Code</strong> Administrator shall submit<br />

a report to the Development Review Board within<br />

15 working days of receipt of the application and<br />

determination of completeness.<br />

B. The Development Review Board shall take final action<br />

on the application for Conditional Use within 15 working<br />

days of receiving the report from the Development <strong>Code</strong><br />

Administrator. Notification of approval or denial shall be<br />

made within 5 working days of final action, for a total of<br />

20 working days.<br />

C. Upon approval of a building permit, the applicant shall<br />

have no more than 3 months to utilize an approved<br />

Conditional Use. Following 3 months, if the applicant<br />

has not initiated construction or is otherwise unable to<br />

prove progress, the Conditional Use shall be considered<br />

expired. An extension of time may be granted by<br />

Jumeirah Village LLC upon request.<br />

9.08.05. Runs with the Use<br />

Unless otherwise specified in the approval by the DRB, a<br />

Conditional Use applies only to the specific use or project for<br />

which it is granted. No new use or project shall be permitted<br />

to utilize the exception without prior approval by the DRB.<br />

Section 9.09. Development <strong>Code</strong> Amendment<br />

9.09.01. Request for Amendment<br />

A Development <strong>Code</strong> Amendment may be requested by<br />

an applicant seeking Development Plan approval, the<br />

Development <strong>Code</strong> Administrator, the Development Review<br />

Board, or Jumeirah Village LLC. The authority to approve<br />

an amendment to this <strong>Code</strong> is granted to the DRB, however,<br />

Jumeirah Village LLC remains the final authority and may<br />

choose to amend the <strong>Code</strong> without DRB approval.<br />

9.09.02. General Criteria<br />

The Development Review Board may amend the Development<br />

<strong>Code</strong> if the following criteria are met:<br />

A. The proposed amendment is not detrimental to the<br />

health, welfare, safety, morals, order, convenience,<br />

or prosperity of surrounding residents, investors,<br />

employees, and guests of Jumeirah Village.<br />

B. The proposed exception will provide an equal or greater<br />

means of meeting the purposes of this <strong>Code</strong> than current<br />

requirements.<br />

C. The proposed amendment is consistent with the Master<br />

Plan and will not adversely impact the mobility and<br />

infrastructure systems of Jumeirah Village.<br />

9.09.03. Amendment Process<br />

A. The Development <strong>Code</strong> Administrator shall complete<br />

a report to the Development Review Board including<br />

an overview of the request for amendment, including a<br />

recommendation regarding the proposed amendment<br />

and potential impacts.<br />

B. The Development Review Board shall consider the<br />

recommendation of the Development <strong>Code</strong> Administrator<br />

and determine to approve, reject or modify the proposed<br />

amendment.<br />

C. If the request to amend the Development <strong>Code</strong> was<br />

submitted by an applicant for Development Plan<br />

approval, the Development <strong>Code</strong> Administrator shall<br />

notify the applicant in writing of final action, including<br />

approval or denial of the amendment.<br />

9.09.04. Time<br />

Upon approval, an amendment to the Development shall<br />

take place immediately upon final action by the Development<br />

Review Board.<br />

Section 9.10. Zoning Map Amendment<br />

9.10.01. Request for Amendment<br />

A Zoning Map Amendment may be requested by an applicant<br />

seeking Development Plan approval, the Development <strong>Code</strong><br />

Administrator, the Development Review Board, or Jumeirah<br />

Village LLC. The authority to approve an amendment to Zoning<br />

Map related to this <strong>Code</strong> is granted to the DRB, however,<br />

Jumeirah Village LLC remains the final authority and may<br />

choose to amend the Zoning Map without DRB approval.<br />

9.10.02. General Criteria<br />

The Development Review Board may amend the Zoning Map<br />

if the following criteria are met:<br />

A. The proposed amendment is beneficial to the orderly,<br />

efficient and economic development of Jumeirah Village<br />

and will enhance or protect the health, welfare, safety,<br />

morals, order, convenience, or prosperity of surrounding<br />

residents, investors, employees, and guests of the<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

33<br />

a d m i n i s t r at i o n a n d p r o c e d u r e s<br />

community.<br />

B. The site or sites involved in the proposed amendment are<br />

more suitable for uses and standards permitted in the<br />

proposed Zone than in the current Zone.<br />

C. The proposed amendment is consistent with the Master<br />

Plan and will not adversely impact the mobility and<br />

infrastructure systems of Jumeirah Village.<br />

D. The proposed change in the Zoning Map will remain<br />

compatible with the character of the surrounding area.<br />

9.10.03. Amendment Process<br />

A. The Development <strong>Code</strong> Administrator shall complete<br />

a report to the Development Review Board including<br />

an overview of the request for amendment, including a<br />

recommendation regarding the proposed amendment<br />

and potential impacts.<br />

B. The Development Review Board shall consider the<br />

recommendation of the Development <strong>Code</strong> Administrator<br />

and determine to approve, reject or modify the proposed<br />

amendment.<br />

C. If the request to amend the Zoning Map was submitted<br />

by an applicant for Development Plan approval, the<br />

Development <strong>Code</strong> Administrator shall notify the<br />

applicant in writing of final action, including approval or<br />

denial of the amendment.<br />

9.10.04. Time<br />

Upon approval, an amendment to the Development shall<br />

take place immediately upon final action by the Development<br />

Review Board.<br />

Section 9.11. Enforcement<br />

9.11.01. Compliance Required<br />

A. No person may use, occupy, or develop land, buildings<br />

or other structures, or authorize or permit the use,<br />

occupancy, or development of land, buildings or other<br />

structures except in accordance with all applicable<br />

provisions of this <strong>Code</strong>.<br />

B. The developer of any building or land in violation of this<br />

<strong>Code</strong>, as well as any architect, builder, contractor or<br />

other professional consultant who may have assisted or<br />

contributed to such violation shall be considered guilty of<br />

a violation of this <strong>Code</strong>.<br />

C. Any use, arrangement or construction differing from<br />

officially approved plans shall be deemed in violation of<br />

this <strong>Code</strong>.<br />

9.11.02. Responsibility for Enforcement<br />

A. The Development <strong>Code</strong> Administrator is given authority<br />

on behalf of Jumeirah Village LLC to enforce the<br />

requirements of this <strong>Code</strong>, including the ability to<br />

monitor all development and operation of activities<br />

within Jumeirah Village. Jumeirah Village LLC shall have<br />

ultimate authority for enforcement and shall impose<br />

penalties for violation of this <strong>Code</strong> as appropriate.<br />

B. Any individual may make the Development <strong>Code</strong><br />

Administrator aware of potential violations. To investigate<br />

a complaint, the Development <strong>Code</strong> Administrator<br />

must be provided a detailed account of the violation,<br />

the period of occurrence and, if possible, the alleged<br />

responsible parties. All complaints shall be maintained<br />

on record by the Development <strong>Code</strong> Administrator.<br />

9.11.03. Notice of Intent<br />

A. Upon determination of a violation, the Development<br />

<strong>Code</strong> Administrator shall give notice to the individual or<br />

individuals responsible for said violation with instructions<br />

for discontinuance and compliance. The Administrator<br />

shall provide a reasonable time for compliance.<br />

B. The Development <strong>Code</strong> Administrator is hereby<br />

authorized to immediately suspend activities without<br />

notice that cause imminent destruction of property or<br />

injury to persons.<br />

9.11.04. Penalties<br />

Jumeirah Village LLC reserves the right to take all appropriate<br />

actions and initiate proceedings to prevent unlawful<br />

construction, to recover damages, or to restrain, correct, or<br />

abate any violation of this <strong>Code</strong>. One or more of the following<br />

penalties may be assessed against any person involved with<br />

violations of this <strong>Code</strong>:<br />

A. Removal or correction of the violation at the owner’s<br />

expense.<br />

B. A fine of up to Dhs. 1,000 for each day that a violation<br />

exists after the specified reasonable time provided by the<br />

Notice of Intent has expired, as calculated from the date<br />

of issuance.<br />

C. A one time fine for each occurrence of a violation<br />

including:<br />

• 1,000 Dhs. upon the initial occurrence<br />

• 2,000 Dhs. upon the second occurrence<br />

• 3,000 Dhs. upon the third occurrence<br />

• 10,000 Dhs. upon any subsequent occurrences.<br />

D. Discontinuance of utility services until the violation has<br />

been addressed to the satisfaction of Jumeirah Village<br />

LLC.<br />

E. Removal of a consultant from the register of consultants<br />

licensed to perform work in Jumeirah Village.<br />

F. In the case of a violation which endangers public health<br />

or safety, arrest and detention for a period of time<br />

established by a court of jurisdiction.<br />

A D M I N I S T R AT I O N A N D P R O C E D U R E S


34 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

D E F I N I T I O N S<br />

10. Definitions<br />

d e f i n i t i o n s<br />

Abutting: A common border with or being separated from<br />

such common border only by a roadway, easement or rightof-way.<br />

Access: The place or way by which pedestrians and vehicles<br />

have a safe and usable ingress and egress to a property or<br />

use. An unobstructed way or means of approach to private<br />

entry to or exit from a property.<br />

Access Driveway: The area between the traveled portion of<br />

a road and a parking lot used by motor vehicles for access to<br />

and from a car park, but does not include an aisle.<br />

Accessory Use: A use customarily incidental to and related to<br />

a principal use established on the same lot.<br />

Addition: An extension or increase in floor area or height of a<br />

building or structure.<br />

Adjacent: Abutting, directly connected to, or bordering.<br />

Applicant: The person, party or corporation applying for<br />

approval or permission; normally understood to be the owner,<br />

leaseholder or developer of the lot.<br />

Building: A permanently located structure having a room<br />

supported by walls or columns but excluding any courtyard<br />

such structure may have provided, however, that no form of<br />

fabric, tent or vehicle shall be considered a building.<br />

Building, Accessory: A building devoted to an accessory<br />

use or structure that is complementary to the primary use or<br />

structure.<br />

Building Height: The vertical distance measured of a<br />

structure measured in number of stories beginning at the<br />

average elevation of the finished grade at the front of the<br />

building to the highest story of the structure. Penthouse,<br />

mechanical equipment and architectural features that<br />

comprise the “top” of the structure shall not be considered in<br />

the overall structure height.<br />

Build-To Line: The line parallel to the front lot line upon which<br />

the edge of a building located closest to the street must be<br />

located.<br />

Buildable Area: That portion of a lot upon which a building,<br />

structure, pavement, or other improvements may be placed<br />

after designation of areas such as front, rear and side yards.<br />

Building Permit: An authorization granted by Jumeirah<br />

Village LLC certifying that the design of a proposed structure<br />

or development to be erected on a designated lot complies<br />

with all relevant provisions applicable to this <strong>Code</strong>. The permit<br />

allows building construction to commence.<br />

Building, Primary: A building within which is conducted the<br />

principal use permitted on the lot, as provided by this <strong>Code</strong>.<br />

Car Park: Land used to park motor vehicles.<br />

Carpark Structure: a building or structure consisting of more<br />

than one level and used to temporarily store motor vehicles.<br />

Change of Use: Any use which differs from the previous use<br />

of a building or land.<br />

Conditional Use: A use which has certain characteristics<br />

which may be detrimental to the surrounding area, but which<br />

may be permitted within a Zone with designated mitigation<br />

measures.<br />

Construction Plans: The maps, drawings and specifications<br />

indicating the proposed location and design of improvements<br />

to be installed.<br />

Courtyard: A landscaped, outdoor open space surrounded by<br />

walls or fences or other materials utilized to establish a sense<br />

of boundary.<br />

Density: The number of dwelling units per unit of land.<br />

Development: The construction, reconstruction, conversion,<br />

erection, alteration, relocation, or enlargement of any building<br />

or structure; any mining, excavation or landfill; and any land<br />

disturbance in preparation for any of the above.<br />

Development <strong>Code</strong> Administrator: Individual designated<br />

by Jumeirah Village LLC to be responsible for daily<br />

administration of the Development <strong>Code</strong>.<br />

Development Intent Questionnaire: Application to be filled<br />

out by a potential applicant as the initiating step in the<br />

Development Plan approval process.<br />

Development Plan: A combination of applications and<br />

submissions to be submitted to Jumeirah Village LLC that are<br />

necessary to gain approval for project construction..<br />

Development Review Board: Entity selected by Jumeirah<br />

Village LLC to be responsible for approval or denial of items<br />

requiring possible variation or alteration of this <strong>Code</strong>.<br />

Zone: A geographic area within which specific development<br />

regulations assigned by this <strong>Code</strong> shall apply.<br />

Zoning Map: An official map that identifies Zones that are<br />

subject to the specific use and development regulations of<br />

this <strong>Code</strong>.<br />

Driveway: An access to a required off-street parking facility<br />

or an off-street loading area.<br />

Dwelling: A building used as a self-contained residence that<br />

must include a kitchen sink, food preparation facilities, a bath<br />

or shower, and a closet pan and washbasin.<br />

Dwelling Unit: One or more habitable rooms constituting a<br />

self-contained unit with a separate entrance and used or<br />

intended to be used for living and sleeping purposes.<br />

Dwelling, Multiple Unit: A building divided into two or more<br />

dwelling units, each of which is occupied or intended to be<br />

occupied as a permanent home or residence. Also known as<br />

an Apartment Structure.<br />

Easement: A grant of one or more of the property rights by the<br />

property owner to and/or for use by the public, a corporation,<br />

or another person or entity.<br />

Egress: An exit.<br />

Environment: The physical factors of the surroundings of<br />

human beings including the land, water, atmosphere, climate,<br />

sound, odors, tastes, the biological factors of animals and<br />

plants and the social factor of aesthetics.<br />

Existing Use: The lawful use of a building, lot or structure at<br />

the time of the enactment of these regulations.<br />

Exception: Permission to depart from the design standards in<br />

the ordinance for reasons as described in Section 9.07 of this<br />

<strong>Code</strong>.<br />

Façade: The exterior walls of a building exposed to public<br />

view or that wall viewed by persons not within the building.<br />

Feature: Fixtures, components or appurtenances attached<br />

to, contiguous to or otherwise related to a building, structure<br />

or property including, without limitation, materials, overlays,<br />

moldings, sculptures, fountains, light fixtures, windows, and<br />

monuments.<br />

Fence: A construction, not considered a structure, which is<br />

designed for screening or enclosing. Landscaping screens of<br />

a height of over 1 meter shall be considered a fence whereas<br />

random plantings of any height shall not be considered a<br />

fence.<br />

Findings of Fact: Statement of facts upon which a decision by<br />

the Development Review Board has been reached.<br />

Floor Area: The total horizontal area of all floors of a building<br />

measured from the exterior surface of the outside walls,<br />

including all floors below ground level but exclusive of vent<br />

shafts and courts.<br />

Floor Area Ratio (FAR): The ratio used to control the size of<br />

a building in relation to the size of its lot. FAR is expressed<br />

as a ratio (such as 1.5 to 1) by which the area of the lot is<br />

compared with the total allowable gross floor area of the<br />

building or buildings, excluding parking and nonhabitable<br />

areas along the exterior of the structure such as balconies<br />

and mechanical equipment. Stairs, elevators and other<br />

service areas located withing the structure are included in<br />

the FAR calculation.<br />

Frontages: Configuration of the front façade of a structure<br />

along, at minimum, the first two floors, including the ground<br />

floor.<br />

Grade: The elevation of the surface of the ground at any point<br />

on a site.<br />

Grade, Existing: The elevation of the surface of the existing<br />

undisturbed ground at any point on a site.<br />

Grade, Finished Floor: The final elevation of the ground<br />

surface after man-made alterations, such as grading,<br />

grubbing, filling, or excavating, have been made on the<br />

ground surface.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

35<br />

d e f i n i t i o n s<br />

D E F I N I T I O N S<br />

Guest House: An accessory building for the housing of<br />

temporary guests, not containing a kitchen and not being<br />

rented or leased.<br />

Height, Building: The vertical distance from grade to average<br />

height of the highest roof structure.<br />

Home Office: A conditional, accessory use permitted in<br />

specific Zones that allows operation of small business in a<br />

home providing that impacts are mitigated and a conditional<br />

use permit issued.<br />

Hotel: A building offering temporary accommodations for<br />

eight (8) or more guests which may provide as accessory<br />

uses restaurants, meeting rooms, and recreation facilities.<br />

Illuminated: A sign utilizing an artificial or a reflective light<br />

source.<br />

Impervious Cover: Any hard-surfaced, man-made area<br />

that does not readily absorb or retain water, including but<br />

not limited to building roofs, parking and driveway areas,<br />

graveled areas, sidewalks and paved recreation areas.<br />

Improvement: Any building, structure, place, fence, gate,<br />

landscaping, tree, wall, car park, or other object constituting<br />

a physical feature which is not a natural feature.<br />

Ingress: An entry.<br />

Intersection: The crossing of two (2) or more roads at grade.<br />

Landscaping: The treatment and maintenance of a property<br />

or yard area with a combination of vegetation (ground cover,<br />

plants, shrubs, or trees), natural elements (brick, rocks, or<br />

water) and other natural or decorative features (walkways,<br />

fences, pools, fountains, or benches).<br />

Landscape Plan: A plan submitted as part of a package<br />

for Development Plan approval indicating the proposed<br />

landscape development, irrigation system and fences.<br />

Loading Space, Off-street: Space logically and conveniently<br />

located for bulk pickups and deliveries, scaled to delivery<br />

vehicles expected to be used, and accessible to such<br />

vehicles when required off-street parking spaces are filled.<br />

Lot: A piece, parcel, or plot of land occupied by or to be<br />

occupied by one principal building, its accessory buildings<br />

and frontage on a street.<br />

Lot Area: The total extent of surface, measured in a horizontal<br />

plane, within the lot lines of a lot.<br />

Lot Coverage: The percentage of the area of a lot or parcel of<br />

land, which is occupied by buildings or structures.<br />

Lot Frontage: That portion of a lot which abuts a road.<br />

Lot Line: Any line bounding a lot as herein defined.<br />

Lot Line, Front: A line separating an interior lot from a street.<br />

In the case of a corner lot, the orientation of existing or<br />

proposed development shall be used to determine which lot<br />

line shall be considered the front.<br />

Lot Line, Rear: A lot line which is opposite and most distant<br />

from the front lot line. In the case of an irregular lot, the<br />

rear lot line shall be an assumed line parallel to and at the<br />

maximum distance from the front lot line.<br />

Lot Line, Side: Any lot boundary line not a front lot line or a<br />

rear lot line.<br />

Lot Width: The width of a lot at the minimum building setback<br />

line.<br />

Master Plan: The Jumeirah Village Master Plan.<br />

Native Plant: Any species that is indigenous within the local<br />

region.<br />

Noise: Any undesirable audible sound.<br />

Occupied: Arranged, designed, built, altered, converted,<br />

rented, leased, occupied or intended to be occupied.<br />

Open Lot: An area of open land other than a road, used or<br />

intended to be used to provide space for the parking or<br />

storage of motor vehicles, including parking spaces, loading<br />

spaces, maneuvering aisles, and other areas providing<br />

access to parking or loading spaces.<br />

Parking, Off-Street: An off-street parking space consists of<br />

a space adequate for parking an automobile with room for<br />

opening doors on both sides together with properly related<br />

access to a public street, including maneuvering room.<br />

Paseo: A public walk or boulevard designed exclusively for<br />

use of pedestrians and including limited amenities as urban<br />

open spaces.<br />

Permitted Uses: Any use allowed in a Zone by right.<br />

Plant Materials: Living trees, shrubs, vines, ground covers,<br />

sod, and flowering annuals, biennials and perennials adapted<br />

to the environment of Dubai<br />

Plaza: An urban open space that is surrounded by streets and<br />

structures, largely paved and possibly including landscaping,<br />

public art, seating or other features.<br />

Public Facilities: Services or facilities provided by<br />

government or government agencies for the benefit of the<br />

general public and to which the public will have access.<br />

Remodeling: The refashioning or alteration (whether<br />

structural or not) of a building or structure without its<br />

established use being changed.<br />

Right-of-Way: A strip of land acquired by reservation,<br />

dedication or condemnation and intended to be occupied by<br />

a road, crosswalk, sidewalk, railroad, electric transmission<br />

lines, oil or gas pipeline, water line, sanitary or storm sewer,<br />

and other uses.<br />

Screening: A method of visually obscuring nearby structures<br />

or land uses (car park, outdoor storage) from another with<br />

the use of one or a combination of fencing, walls, dense<br />

vegetation, or berms.<br />

Setback: A line established by development control<br />

regulations, generally parallel with and measured from the<br />

front property line, defining the limits of a lot in which no<br />

building, accessory building or structure may be located<br />

above the ground.<br />

Setback, Rear: A setback extending the full width of the lot in<br />

the area between the rear lot line and the rear building line.<br />

Setback, Side: A setback extending the full width of the lot in<br />

the area between a side lot line and a side building line.<br />

Sign: Any device designed to inform or attract the attention<br />

of a person not on the premises on which the sign is located.<br />

It means any structure, wall, natural object, or other device<br />

used for visual communication which is visible from any<br />

street or means of access and is used to advertise or direct<br />

attention to an activity, product, place, person, or business.<br />

Sign, Awning: A sign that is mounted, painted or attached to<br />

an awning, canopy or marquee.<br />

Sign, Flashing: A sign having a conspicuous and intermittent<br />

variation in the illumination.<br />

Sign, Illuminated: Any sign designed to emit or brightly reflect<br />

artificial light.<br />

Sign, Ground: A sign which is less than 1.5 meters from the<br />

ground or is supported by a sign structure that is placed on or<br />

anchored in the ground and is independent of any building or<br />

other structure.<br />

Sign, Pedestal: A sign that is mounted on one or more<br />

freestanding poles or other support so that the bottom edge<br />

of the sign face is more than 0.5 meters from contact with a<br />

solid base or the ground. Also sometimes known as a “pole<br />

sign.”<br />

Sign, Projecting: A sign that is partially or wholly dependent<br />

upon a building for support and that projects more than 30<br />

centimeters from such building.<br />

Sign, Temporary: A sign or advertising display constructed of<br />

cloth, canvas, fabric, wood or other light material intended to<br />

be displayed for a short period of time.<br />

Sign, Tower: A large scale sign that is mounted near the top<br />

of a tower that is generally used as a means of identifying an<br />

important tenant or the name of a facility.<br />

Sign, Wall: Any sign posted or painted in suspended from or<br />

otherwise affixed to the wall of any building or structure in an<br />

essentially flat position or with the exposed face of the sign in<br />

a plane approximately parallel to the plane of such wall.


36 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

D E F I N I T I O N S<br />

d e f i n i t i o n s<br />

Sign, Window: Any sign that is placed inside a window,<br />

upon the window, or upon the window pane or glass, and<br />

is intended to be visible from the exterior of the window.<br />

Merchandise displays shall not be considered a window sign.<br />

Street: A right-of-way which has been improved and is<br />

intended for motor vehicle traffic and provides access to<br />

property.<br />

Taxi Rank: The use of land as a base of operations for a<br />

taxicab or other land-vehicle passenger transport service.<br />

Temporary Use: A use established for a limited duration with<br />

the intent to discontinue such use upon the expiration of the<br />

time period.<br />

Trellis: A frame of latticework designed for purposes of<br />

providing visual appeal and shade along pedestrian corridors<br />

of Jumeirah Village.<br />

Variance: Permission to depart from the literal requirements<br />

of a this <strong>Code</strong>, where such a variance would not be contrary<br />

to the public interest and where the a literal enforcement of<br />

the ordinance would result in unnecessary hardship.<br />

Yard, Front: The area from one side lot line to the other side<br />

lot line and between the primary structure and the street on<br />

which the lot fronts. On a corner lot (lots abutting on two or<br />

more streets at their intersections), the front yard shall face<br />

the shortest street dimension of the lot.<br />

Yard, Rear: A space extending across the full width of the<br />

lot between the principal building and the rear lot line and<br />

measured perpendicular to the building to the closest point of<br />

the rear lot line.<br />

Yard, Side: A space extending from the front yard to the<br />

rear yard between the principal building and the side lot line<br />

measured perpendicular from the side lot line to the closest<br />

point of the principal building.


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

37<br />

a p p l i c at i o n c h e c k l i s t s<br />

Application Checklists<br />

Development Intent Questionnaire Contents<br />

o<br />

o<br />

o<br />

o<br />

General Applicant Information<br />

Applicant information to include:<br />

1. Name<br />

2. Contact information (address, telephone, fax, email)<br />

3. Expatriate Status<br />

Sponsor Information<br />

If applicant is an expatriate, sponsor information is<br />

required, including:<br />

4. Name of Agent/Sponsor<br />

5. Contact Information for Agent/Sponsor (address,<br />

telephone, fax, email)<br />

Construction Information<br />

Determine the type of construction activity to be carried<br />

out such as:<br />

6. New Construction (of primary structure, accessory<br />

structure, parking, signs, or other amenities)<br />

7. Redevelopment or Alteration (of primary structure,<br />

accessory structure, parking, signs, or other<br />

amenities)<br />

Project Type<br />

Determine the type of project expected to be developed<br />

according to:<br />

8. Type of Structure (Villa, Townhome, Mid-Rise, Tower,<br />

low scale retail, public or civic)<br />

9. Type of Activities (Residential, Entertainment,<br />

Restaurant, Hotel, General Retail, Office, Service,<br />

Recreation, Education, Institutional, Other)<br />

10. If one or more of uses is expected to be a hotel, the<br />

number of units, staff and food outlets should be<br />

provided.<br />

o<br />

o<br />

o<br />

Concept<br />

Discussion of the concept for the project in as much<br />

detail as needed or possible to aid in discussion during<br />

the Pre-Application Meeting. Illustrations or concept<br />

sketches, if available, should be submitted with the<br />

Development Intent Questionnaire.<br />

Anticipated Project Needs<br />

11. Indication of desired location in Jumeirah Village as<br />

well as anticipated land requirements<br />

12. Project Development Services such as architecture,<br />

landscape architecture, engineering, site design, or<br />

other<br />

13. Financial Services<br />

Time of Anticipated Construction and Completion<br />

Estimated timeline for project to commence as well as<br />

time of completion. Key dates throughout the process, if<br />

known, should also be included.<br />

Master Form Contents<br />

General requirements:<br />

A. 2 copies of all materials<br />

B. Drawings clearly labeled in the lower right hand corner<br />

C. Drawings to be folded to A4 size with labels clearly<br />

visible<br />

o<br />

o<br />

o<br />

o<br />

General Applicant Information<br />

Applicant information to include:<br />

15. Name<br />

16. Contact information (address, telephone, fax, email)<br />

17. Expatriate Status<br />

18. Development Application Tracking Number<br />

Sponsor Information<br />

If applicant is an expatriate, sponsor information is<br />

required, including:<br />

19. Name of Agent/Sponsor<br />

20. Contact Information for Agent/Sponsor (address,<br />

telephone, fax, email)<br />

Action Requested<br />

Actions may include Approval for Concept Plan, Site<br />

Plan, Building Permit, Variance, Exception, Conditional<br />

Use, Development <strong>Code</strong> Text Amendment, or Zoning Map<br />

Amendment<br />

Construction Information<br />

Indicate the type of construction activity to be carried out<br />

such as:<br />

21. New Construction (of primary structure, accessory<br />

structure, parking, signs, or other amenities)<br />

22. Redevelopment or Alteration (of primary structure,<br />

accessory structure, parking, signs, or other<br />

amenities)<br />

o<br />

o<br />

o<br />

Project Type<br />

Indicate the type of project expected to be developed<br />

according to:<br />

23. Type of Structure (Villa, Townhome, Mid-Rise, Tower,<br />

low scale retail, public or civic)<br />

24. Type of Activities (Residential, Entertainment,<br />

Restaurant, Hotel, General Retail, Office, Service,<br />

Recreation, Education, Institutional, Other)<br />

25. If one or more of uses is expected to be a hotel, the<br />

number of units, staff and food outlets should be<br />

provided.<br />

Concept<br />

Discussion of the concept for the project as it has<br />

evolved through the Pre-Application and Development<br />

Plan process.<br />

Certifications<br />

Indication of the seal and certification of all architects,<br />

engineers and other allied professionals involved<br />

with the project as licensed and registered to work in<br />

Jumeirah Village and certifying the authenticity, quality<br />

and preparation of submitted documents.<br />

A P P L I C AT I O N C H E C K L I S T S


38 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

A P P L I C AT I O N C H E C K L I S T S<br />

Concept Plan Checklist<br />

o<br />

Master Application Form<br />

o<br />

Notation of materials to be used on site including type, color, texture, transparency, and location<br />

a p p l i c at i o n c h e c k l i s t s<br />

o<br />

Design Statement<br />

The applicant discussing the impact of the project on Jumeirah Village. and the methods used to meet the vision of the<br />

Master Plan and meet the Eight Principles guiding community design<br />

o<br />

o<br />

Floor and roof plans (scale of 1:200) indicating each roof and floor, proposed uses, roof gardens, penthouses and<br />

location of mechanical equipment<br />

Calculations of Floor Area Ratio and Maximum Lot Coverage<br />

o<br />

Documentation<br />

Table of architects, engineers, contractors and other allied professionals to be working on the project and certification that<br />

they have been licensed and registered by Jumeirah Village LLC<br />

o Layout Plan (Scale of 1:1,000)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

Location of lot in relation to Jumeirah Village, adjacent streets and surrounding development<br />

Zone in which project and surrounding sites are located<br />

o Site Plan (Scale of 1:200)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o Conceptual Parking and Loading Plan (scale of 1:200)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

o<br />

o<br />

Calculations indicating the total number of parking spaces anticipated for the project, the number of on-street spaces<br />

adjacent to the project, and number of bicycle units supported<br />

Site plan and elevations as needed to indicate conceptual design of parking area including number of floors (if needed)<br />

below and above ground, parking and lane dimensions, location of access, screening techniques employed and details<br />

to ensure compatibility with the structure and site design<br />

Location and design of loading areas<br />

Space for vehicle stacking, if needed<br />

o<br />

o<br />

o<br />

o<br />

o<br />

o<br />

o<br />

o<br />

o<br />

Site dimensions, lot description and reference coordinates<br />

Street pavement lines<br />

Build-to line and setbacks<br />

Location of proposed primary and accessory buildings<br />

Location and measure of parking area, type of parking and points of access<br />

Location of services and facilities such as refuse containers and complimentary fencing/screening<br />

Existing features and proposed alterations to structures or other features of the site<br />

Existing and proposed site contours<br />

Conceptual Architectural Details<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

o<br />

Perspective or elevation renderings clearly showing the proposed style, appearance and form of all buildings and<br />

improvements<br />

Description of techniques used to meet Form standards of the Development <strong>Code</strong> (including bulk, articulation and<br />

differentiation)<br />

Elevations (scale of 1:200) of a minimum of 3 building faces for each structure including delineation of podium, shaft<br />

(lower, middle and upper sections) and top<br />

o Conceptual Master Sign Plan (scale of 1:200)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

Calculations indicating the amount of sign space and type of permitted signs available to the project<br />

Anticipated location, dimensions, design, and type of signs to be utilized throughout the site in relationship to lot lines,<br />

setbacks, structures, amenities, and the streetscape<br />

o Conceptual Master Landscape Plan (scale of 1:200)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

o<br />

o<br />

o<br />

Calculations of required landscaping and fencing<br />

Site Plan indicating the anticipated location, materials and type of landscape and fencing treatment, including roof<br />

gardens, plazas, courtyards, and open spaces<br />

If fencing is required, the type of fencing that is to be employed, including materials and location<br />

Service Requirement<br />

Estimated infrastructural requirements to support staff, utilities and facilities<br />

Estimated Irrigation Needs<br />

An estimate in liters of the total peak daily irrigation water requirements for all proposed plantings based upon the<br />

Conceptual Landscape Plan, including an estimate for grass, if any<br />

o<br />

Optional CAD files


d u b a i , u . a . e . - o c t o b e r 2 0 0 6<br />

J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e<br />

39<br />

a p p l i c at i o n c h e c k l i s t s<br />

Site Plan Checklist<br />

o<br />

o<br />

Master Application Form<br />

Design Statement<br />

The applicant discussing the impact of the project on Jumeirah Village and the methods used to meet the vision of the<br />

Master Plan and meet the Eight Principles guiding community design<br />

o<br />

Detailed Architectural Details<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

Perspective or elevation renderings clearly showing the proposed style, appearance and form of all buildings and<br />

improvements<br />

A P P L I C AT I O N C H E C K L I S T S<br />

o<br />

o<br />

Documentation<br />

Table of architects, engineers, contractors and other allied professionals to be working on the project and certification that<br />

they have been licensed and registered by Jumeirah Village LLC<br />

Layout Plan<br />

If the project required a Concept Plan, then the Layout Plan for the Site Plan approval shall be the same with changes<br />

incorporated from the Concept Plan process<br />

o<br />

o<br />

o<br />

Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

Location of lot in relation to Jumeirah Village , adjacent streets and surrounding development<br />

Zone in which project and surrounding sites are located<br />

o Site Plan (Scale of 1:200)<br />

If the project required a Concept Plan, then the Site Plan shall be the same with changes incorporated from the Concept<br />

Plan process<br />

o<br />

o<br />

o<br />

o<br />

o<br />

Detailed Description of techniques used to meet Form standards of the Development <strong>Code</strong> (including bulk, articulation<br />

and differentiation)<br />

Detailed plans of each floor of primary and accessory structures including all development, improvements or<br />

alterations. Roof plans shall be include and accessory structures shall include carpark structures and serve facilities<br />

such as refuse areas. All indoor and outdoor spaces shall be clearly delineated, including roof gardens and other<br />

required spaces.<br />

Detailed elevations (scale of 1:100) of all building faces for each structure including delineation of podium, shaft (lower,<br />

middle and upper sections) and top<br />

Two or more sections (scale of 1:100) drawn at right angles through each structure and indicating internal and<br />

external floor levels, window sill heights, parapet heights, penthouses, roof gardens, mechanical equipement, and the<br />

relationship to surrounding structures<br />

Detailed drawings shall include location of fences, walls, parking areas, signs, landscaping and lighting for purposes of<br />

context and review<br />

o<br />

Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

Samples of materials to be used on site including type, color, texture, transparency, and location<br />

o<br />

Site dimensions, lot description and reference coordinates<br />

o<br />

Calculations of Total Floor Area, Floor Area Ratio and Maximum Lot Coverage<br />

o<br />

o<br />

Street pavement lines<br />

Build-to line and setbacks<br />

o Detailed Parking Plan (scale 1:100)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

o<br />

o<br />

o<br />

Location of proposed primary and accessory buildings<br />

Location and measure of parking area, type of parking and points of access<br />

Location of services and facilities such as refuse containers and complimentary fencing/screening<br />

Existing features and proposed alterations to structures or other features of the site<br />

Existing and proposed site contours<br />

o Grading and Drainage Plan (scale of 1:200)<br />

A site plan and two cross-sections through the site in each main direction indicating existing and finished levels with areas<br />

of cut and fill emphasized in shading. Drainage flow on site plan must be shown to an approved stormwater inlet or to an<br />

access way that leads to a street<br />

o<br />

o<br />

o<br />

o<br />

Calculations indicating the total number of parking spaces anticipated for the project, the number of on-street spaces<br />

adjacent to the project, and number of bicycle units supported<br />

Site plan and elevations as needed to indicate detailed design of parking area including number of floors (if needed)<br />

below and above ground, parking and lane dimensions, location of access, screening techniques employed and details<br />

to ensure compatibility with the structure and site design<br />

Location and design of loading areas<br />

Space for vehicle stacking, if needed<br />

o Detailed Master Sign Plan (scale 1:100)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

Calculations indicating the amount of sign space and type of permitted signs available to the project<br />

o<br />

Precise location, dimensions, design, and type of signs to be utilized throughout the site in relationship to lot lines,<br />

setbacks, structures, amenities, and the streetscape<br />

o<br />

A single elevation depicting each permanent sign


40 J u m e i r a h V i l l a g e - M I D R I S E D e v e l o p m e n t C o d e o c t o b e r 2 0 0 6<br />

J U M E I R A H V I L L A G E L L C<br />

A P P L I C AT I O N C H E C K L I S T S<br />

o Detailed Master Landscaped Plan (scale of 1:100)<br />

o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date<br />

o<br />

o<br />

o<br />

o<br />

Calculations of required landscaping and fencing<br />

Schedule of plants and materials to be incorporated into the project including name, quantity and reference to the<br />

Landscape Master Plan<br />

Site plan and section detail of location of landscape treatments, including trees, shrubs, ground cover and lawns<br />

Location and section detail of hard surface materials, water features and fencing to be located on the project site<br />

a p p l i c at i o n c h e c k l i s t s<br />

o<br />

Irrigation Calculations<br />

o Irrigation water demand calculations relating to the proposed plantings shown and described in the Landscape Master<br />

Plan, including the peak daily plant water consumption as indicated in liters and calculated at the peak season of July<br />

o<br />

o<br />

o<br />

Monthly projected irrigation water consumption figures covering the effect of leaching and other off-season practices<br />

Irrigation site plan (scale of 1:200) indicating the location and capacity of the irrigation water storage tanks, tank<br />

connections, and details of the distribution system.<br />

A timetable for timing in relationship to irrigation of landscaping at maturity<br />

o Utility Plan (scale of 1:200)<br />

Schedule and plan indicating coordinates, depths, levels, and sizes of all pipes, conduits and connections regarding<br />

water (potable and for irrigation), wastewater, electricity, telephone, and other utilities from points of entering the site to<br />

distribution including, if required, transformers, switch boxes, meters and emergency generator.<br />

o<br />

o<br />

o<br />

Electricity Calculations and Diagrams<br />

o Final electricity load calculations for the development expressed in kVA<br />

o<br />

Detailed electrical diagrams indicating details of distribution and circuit breakers<br />

Refuse Plan<br />

Calculation of anticipated refuse to be accumulated as well as provisions made for storage and disposal<br />

Construction Schedule<br />

o Proposed time schedule for completion of the project as initiated upon receiving an approved Building Permit<br />

o<br />

Management plan describing the organization of work to be completed on the project in coordination with the provided<br />

time schedule, including plans for onsite supervisory personnel