2. PROGRESS REPORTS<br />
2.1 SAFETY OFFICER (R. Atapattu)<br />
Minutes of the Meeting<br />
CANADA-FRANCE-HAWAII TELESCOPE CORP.<br />
SAFETY REPRESENTATION COMMITTEE<br />
15 <strong>May</strong> <strong>2004</strong><br />
<strong>Present</strong>: Rohendra Atapattu, Laurie Dale, Todd Szarlan for Susan Brotman, Nadine Manset for Thierry<br />
Forveille, DeeDee Warren, Lisa Wells, Billy Mahoney for Kanoa Withington, and Roger Wood. Absent:<br />
Coleen Hickman, Sharon Potter, and Yasu Uchima.<br />
1. Call to Order<br />
A. Rohendra Atapattu called the meeting to order at 13:30<br />
2. Approval of 14 March <strong>2004</strong> Minutes<br />
3. Minutes were approved as written.<br />
4. Review of New Accidents & Incidents<br />
B. One injury was reported. An employee suffered back injury while assisting with raising the WFC<br />
to reach the crane. Suggestion to avoid this hazard were to (1) add 3’ legs to WFC to that it could<br />
reach crane or (2) put longer straps on crane to reach WFC.<br />
C. One incident was reported. An OA discovered a small glycol spill on the 5 th floor. The daycrew<br />
cleaned up the spill. It was suggested that a detection device could be installed that would warn of<br />
the leak and shut down systems.<br />
D. Rohendra reported on the most recent MKSS Ranger speed report. Two CFHT vehicles were<br />
noted driving above 35mph (36mph and 38mph) at approximately 16:45 on the survey dates.<br />
5. Concerns, Accidents & Incidents<br />
E. Previously reported items:<br />
(1) It was noted that the EEV does not have a rope or an AED. Rohendra sent email advising<br />
MKSS and will bring up these concerns at the MKSS Safety meeting<br />
(2) Compressed gas cylinders at the summit have been fitted with proper protective guards.<br />
Protective guards need to be ordered for cylinders at headquarters. (Action item for<br />
Rohendra.)<br />
(3) Immediately following the meeting, Roger and Rohendra rearranged cables in large conference<br />
room to reduce trip hazard. (item closed)<br />
(4) Laurie Dale reported that the Admin Groups would like a procedure to be prepared that<br />
addresses situations when immediate help is needed in the front office due to a direct or<br />
perceived threat. The committee suggests that the procedure also address a situation when a<br />
“silent” emergency evacuation of the building is warranted. The admin group met with a local<br />
police officer to discuss possible solutions. (Rohendra and DeeDee will develop an<br />
Emergency Response Plan to be reviewed and implemented. – still pending.)