Madison Messenger - Madison Health Special Edition - January 13th, 2019
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>January</strong> 13, <strong>2019</strong> MADISON MESSENGER SPECIAL EDITION - Page 13<br />
Time flies from groundbreaking to grand opening<br />
From planning to completion, <strong>Madison</strong><br />
<strong>Health</strong>’s expansion and renovation project<br />
took approximately 3.5 years. The following<br />
are highlights of the construction journey:<br />
Project planning: Summer 2015-Summer<br />
2016<br />
Design development: Fall/Winter 2016<br />
Site preparation: Spring-Summer 2017<br />
Energy plant construction: Spring-December<br />
2017<br />
Two-story addition: Fall 2017-December<br />
2018<br />
Old power plant and bridge demolition:<br />
<strong>January</strong> 2018<br />
Construction of concourse between<br />
main hospital and Park Avenue Medical<br />
Building and construction of the pre- and<br />
post-surgery rooms: <strong>January</strong>-December<br />
2018<br />
Renovation and opening of Birthing<br />
Center: April-July 2018<br />
Opening of the medical specialist office<br />
space: October 2018<br />
Opening of the Cancer Center: <strong>January</strong><br />
<strong>2019</strong><br />
Opening of the Emergency Department:<br />
<strong>January</strong> <strong>2019</strong><br />
<strong>Madison</strong> <strong>Health</strong> partnered with healthcare<br />
architect firm, Trinity: PDA, to plan<br />
and design the project. Dublin-based<br />
O’Brien Robinson Construction Services<br />
served as the construction manager.<br />
The hospital breaks ground on its expansion project in June 2017. On hand are: (from<br />
left) Dr. Michael Caligiuri, Dr. Mitch Spahn, Dr. Richard Streck, Tom Blincoe, <strong>Madison</strong><br />
<strong>Health</strong> CEO Dana Engle, Rep. Bill Dean, <strong>Madison</strong> County Commissioner David Dhume,<br />
London Mayor Pat Closser, Senator Bob Hackett, Buddy Byers and Diane Byers.<br />
A view of the two-story addition from Park Avenue in <strong>January</strong> 2018<br />
A crew works to enclose the stairwell on<br />
the two-story addition in July 2018.<br />
Ron Lewis, the hospital’s former director<br />
of maintenance, has fun with temporary<br />
signage that helped visitors navigate the<br />
hospital grounds during construction.<br />
The framework for the concourse connecting<br />
the Park Avenue Medical Building with<br />
the main hospital goes up in March 2018.<br />
Flooring is installed in the new Emergency<br />
Department in October 2018.<br />
<strong>January</strong> <strong>2019</strong>: Work finishes up on the hospital’s new main entrance, which faces Park<br />
Avenue and sits between the new two-story addition and the new pre- and post-surgery<br />
rooms and concourse to the Park Avenue Medical Building.<br />
Ready for grand opening day on Jan. 18, <strong>2019</strong>