Regeneration<br />
Estimated Costs to Complete<br />
(figures exclude VAT unless noted)<br />
Construction<br />
Consultants’ Fees £140,000<br />
Boundary dispute £20,000<br />
Balance of Construction;<br />
QS Estimate @ 05.03.19<br />
£3,100,000 £3,260,000<br />
Fit-out<br />
Audio Visual £150k - £250k £200,000<br />
Kitchen Utensils £8,000<br />
Kitchen<br />
£34,500 £43,000<br />
Café £50,000<br />
Seating £35,000<br />
Furniture £15,000<br />
Fittings £15,000<br />
Others £5,000 £363,000<br />
Miscellaneous, e.g.<br />
insurance, hoarding<br />
licence, car park<br />
£35,000<br />
VAT on Café £50,000<br />
Total Estimated Costs £3,708,000