BUILDING UPDATE
Ventilation plant on the roof
Glass in and first coat of paint on walls
Panel heaters being fitted in
multi-purpose/sports hall
Tiling in the toilets
By Christmas we will have reached
the halfway stage of our 48-week
construction programme with
completion targeted for 7 th June 2021.
Parsons & Joyce have made very good
progress with the upper roof now
being complete, most of the windows
glazed, internal partitions built,
mechanical and electrical installations
well advanced, toilets are being tiled
and the first coat of paint has been
applied to the walls on the upper
floors.
Hopefully, you will be able to see for
yourselves all that has been happening
over the last 6 months when we open
the site for tours on Saturday 23 rd
January.
At the beginning of December, we
had spent approximately £1.3m on
construction and remain within our
budget and our anticipated cashflow.
Thank you for your continued giving
which is supporting these works.
The fitting out has also commenced
with the wiring for the audio-visual
installation, so all the cables are
concealed within the walls and above
the ceilings. The funding for the fit
out is gaining momentum. We have
the opportunity to contribute to reach
the total of £360,000 over our gift
weekend on 29 th and 30 th January to
enable the completion of all that needs
to be done.
God has blessed us in many ways
throughout the last year. Let us give
him thanks for his faithfulness and
provision as we look forward to the
completion and opening on our new
church building next summer for his
glory and the growth of his kingdom.
Balcony tiered seating under construction
Keith MCKAY | Trustee