6SCL’s<br />
steps<br />
to take before starting<br />
a new project<br />
SCL Groundworks share advice for getting a clear idea<br />
of what it will take to get you your dream new-build<br />
or extension, before you start out sclgroundworks.co.uk<br />
To prepare land for a new-build or extension, the<br />
preferred starting point is often to get in touch with<br />
an architect to create the design of the project.<br />
Once the architect has created an initial scope of<br />
specification for what you wish to achieve, you will<br />
be able to go to a structural engineer to organise the<br />
groundworks. Finding the right engineer is just as<br />
important a step as finding a good architect, as the groundworks<br />
will create the base that the building will rely upon. This can<br />
take up to 4 weeks depending on the complexity of the project.<br />
Your engineer may ask for tests such as boreholes, or<br />
soakage tests to be undertaken. It is also advisable to take<br />
soil samples to analyse their waste classification, as this can<br />
have a large impact on the cost of the project. These can<br />
take two or three weeks for results from tests being carried out.<br />
Don’t miss our June issue’s<br />
Kitchen & Bathroom Supplement<br />
full of ideas to remodel and update<br />
Out from 1st June<br />
Obtaining quotes for services and utilities. This is<br />
also important for new-builds as the quotes provide<br />
contractors clear information at the beginning of the<br />
project and help prevent any unknown costs early in<br />
the build. This would usually take four weeks from contractors<br />
receiving information and drawings, to allow for a visit to the<br />
site and a competitive price to be drawn up. When obtaining<br />
quotations from contractors it is important for them to visit<br />
the site to understand access, ground levels and other external<br />
factors. To get an accurate quote you should also give them:<br />
• full but concise information on how long<br />
you wish for the build to take<br />
• clear detailed drawings of the plans<br />
• payment term information<br />
• clarification on whether you expect to hold a retention<br />
(a percentage of the project’s valuation which is held<br />
for a rectification period of the works). This is usually<br />
12 months at 5%, with 2.5% paid on completion and<br />
2.5% paid once the rectification period is complete<br />
Speak with local estate agents about the value the project<br />
could add and compare this against build costs to assess<br />
potential returns and whether the scheme is viable.<br />
Weigh up all of your costs against what you could<br />
gain from the project and make a decision!<br />