04.02.2022 Views

214010-020-mtn-home-2019-10-31-wfps-report

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

DocuSign Envelope ID: 1DD36D19-77D0-4780-B72C-98AC28C4B145

Mountain Home Water Facilities Planning Study Update October 2019

Storage Shortfall

Keller Associates recommends that all future wells be outfitted with onsite backup power

generators. Doing so will decrease the DEQ emergency storage requirement for the City,

thus dropping the overall storage required.

Due to the recent construction of Tank 1B, it is not anticipated that the City will require an

additional storage tank prior to 2040 if future wells are equipped with standby power.

Towards the end of the 20-year planning period the City should begin considering adding

additional storage capacity. Keller Associates recommends that the location and size of

future storage facilities be reevaluated in future planning efforts. The optimum storage size

and location will be a function of many parameters (i.e. growth rates, location of

development, well locations, remaining life and condition of existing facilities, and available

transmission). A second storage facility at the Tank 2 site or replacement of the Tank 2

should be one of the options considered in future planning efforts.

Pumping Delivery Shortfall

Complete pipeline improvements that will allow Well 9 to pump directly to the medium

pressure zone. If additional fire protection is needed in the upper pressure zone in the future,

upsize the Pilot Booster pumps at that time.

Fire Flow Shortfall

The distribution pipeline improvements necessary to correct the fire flow shortfall were

identified in Chapter 3 and will be included as part of the capital improvement plan. The

immediate need of ISRB deficient structures will be met by implementing Priority 1

improvements. Priority 2 improvements will resolve commercial and residential area fire flow

deficiencies. Phasing for these improvements along with other future improvements are

illustrated in Figure 4.1 of Appendix A. The City should be aware that notification of those

residences not meeting minimum fire flow requirements may be required until such time that

adequate fire flows can be provided. The type and frequency of notification will need to be

coordinated with DEQ.

High System Pressures

Outfit future wells with VFDs to maintain desired hydraulic grade in the system. Additionally,

require pressure regulators on new services where system pressures have the potential to

exceed 80 psi, with approval from DEQ.

Low System Pressures

Complete the Priority 1 improvements, including the installation of isolation valves that alter

the medium pressure zone to encompass the existing low-pressure areas. Complete

additional transmission pipeline improvements as required for new developments.

Future System Improvements

As the City continues to grow, it is important to ensure the water system grows in a planned

manner with appropriate transmission and distribution sizes. It is recommended that the

minimum line size allowed in the system be 8 inches in diameter. Figure 4.1 in Appendix A

illustrates the proposed layout for larger transmission lines. Many of the transmission

pipeline improvements within the City could be coordinated with roadway projects. Because

the need for these future lines is likely to be driven by development and will also likely occur

beyond the current 20-year planning window, only the upsize costs (portion likely to be paid

for by the City) have been included as part of the Capital Improvement Plan. Computer

model evaluations should be completed with each new major development to ensure that

adequate infrastructure is in place for the development.

CITY OF MOUNTAIN HOME | KA 214010-020 30

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!