25.01.2023 Views

airport-cdm-manual-2017 (1)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

and solutions offered by Airport CDM. Instructors

should be fully trained on the Airport CDM concept,

and have credits via the Instructor Course provided

by EUROCONTROL.

With the organisation structure in place, the next step

will be to develop a multi partner project management

plan, and assign staff to the described functions.

2.5 Programme and Project

Management

Once all partners involved have indicated their willingness

to implement the selected functionality, a common

multi-partner Program (or Project) Management

Plan (PMP) will be created, which organises all activities,

projects, and planning. It is important to get all

partners to sign up to an agreed version of the PMP so

that everyone has a common reference document.

è

The PMP should be developed based on

best project management practices, such

as those defined by the non profit Project

Management Institute (www.pmi.org).

While all partners participate on a voluntary basis, one

should be appointed as program manager, with the

aim of ensuring the setting up of the PMP with the

help of all partners involved. The main responsibility

of the Program Manager will be to ensure the plan is

executed within time and budget.

è

It is important that the partners agree and

appoint an Airport CDM Program Manager

to manage all the organisational aspects.

The Program or Project Manager could be one of

the main partners or from an independent, neutral

organisation focusing only on overall program and

project management activities. The Program Manager

will be in overall control of the day-to-day project coordination

and will report to a Project Steering Committee

composed of each partner’s representatives.

The Program Manager will maintain an action/decision

register to enable tracing of all decisions taken

by the project committee, or within the project.

The contents of the PMP should be selected from the

following indicative list, on the understanding that local

requirements will determine the final contents:

n

n

n

n

n

n

n

n

n

n

n

n

Scope (the outline of the project)

Objectives (Specific, Measurable, Achievable,

Relevant and Time-oriented)

A description of the phases of the project

(Concept, Development, Execution Termination)

Projects and Project Management

Risk Management

Quality Management

Work Packages (who is responsible for work and

when and how it is to be delivered)

Work Breakdown Structure (WBS)

Deliverables

Communication plan

Finance and Funding

Partners and resources

A responsibility assignment matrix can be used to

identify the roles and responsibilities of each partner

throughout the project.

A work breakdown structure (WBS) will detail a list of

work packages, including the inter-dependency between

each of them, required to achieve the overall

project objective. Each work package will be defined

using a standard description template, for example:

n

n

n

Person responsible

Objectives

Duration

2-8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!