25.01.2023 Views

airport-cdm-manual-2017 (1)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

With this list of criteria, the six Concept Elements

are developed and defined in this document. These

Concept Elements are dependent on each other, and

hence require a recommended order of implementation.

However, local considerations, such as size and

complexity of the airport, may require simultaneous

implementation of all elements or influence the type of

element implementation e.g. sequencing on a small

airport can be done manually rather the automatically,

if this enables the airport to meet the information accuracy

requirements set in the next chapters.

Below, the list of Concept Elements is presented:

n

n

n

n

n

n

Information Sharing

Milestone Approach

Variable Taxi Time

Pre-departure Sequencing

Adverse Conditions

Collaborating Management of Flight Updates

Of the available Airport CDM Concept Elements, Information

Sharing is essential in as much as it creates

the foundation by enabling the sharing of information

and creating a common situational awareness. In addition,

it potentially brings predictability and resource

efficiency benefits. After the creation of this information

platform (see also chapter 3.2), the main priority is implementation

of the Target Off-Block Time (TOBT) by

using the Milestone Approach to improve predictability

during the turn-round process of aircraft. Together,

Information Sharing and the Milestone Approach are

the essential requirements for implementation of the

remaining Concept Elements.

2.7 Inventory for Implementation

An obvious method of minimising costs is to utilise

existing resources to the maximum extent possible,

including networks, computers, displays, etc.

è

Airport CDM elements implemented as software

applications are neither computation

intensive nor mission critical in the sense

that an ATC system is.

Existing networks and other hardware can usually be

used, minimising the need for buying new equipment.

Adding the Airport CDM elements to existing systems

can be cost effective, however it should be borne in

mind that modifying host systems may be more expensive

than building appropriate interfaces into the

software application itself.

è

n An inventory of partners’ existing systems

is required (see to Attachment 3.2)

n Appropriate resources may already be

available

2.8 Gap Analysis and Completeness

Assessment

Before commencing an implementation project, it is

recommended that each airport has a Gap Analysis

performed by EUROCONTROL or an independent

consultancy company. This analysis has the purpose

to achieve a clear vision of what is available

and what is missing within the airport partners’ technical

infrastructure (see Attachment 3.2).

è

All Airport CDM projects must commence

with the implementation of Airport CDM Information

Sharing. Other elements can be

selected and implemented either simultaneously

as one process or in the recommended

order to enable the successive elements to be

most beneficial at the location in question.

At the end of the implementation project an external

Completeness Assessment will be performed by

either EUROCONTROL or a consultancy company,

in order to recommend to Network Operations on

the exchange of DPI messages to feed the network

with airport Target Take Off Time (TTOT) predictions.

This Completeness Assessment will be conducted

2-10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!