SITING THE uB<strong>VIP</strong><br />
<strong>The</strong> site should be chosen by the family with assistance from the<br />
Environmental Health Technician and should be at least 30<br />
metres from a well. <strong>The</strong> toilet site should be:<br />
*Down hill from a well or borehole – to reduce possible<br />
underground contamination of the water supply.<br />
*Where the soil is firm – to avoid possible latrine collapse<br />
*On slightly raised ground – so that rainwater can drain<br />
away from the site of the toilet<br />
*Near the house – for the convenience of the householders<br />
*Away from trees – so that air can flow easily over the<br />
pipe<br />
*<strong>The</strong> orientation of the structure - to provide the best<br />
privacy for the users<br />
Stages of construction<br />
<strong>The</strong> stages of construction are as follows:<br />
1. Dig the pit.<br />
2. Make the concrete slab<br />
3. Line the pit with bricks and fit the cured slab<br />
4. Build the superstructure<br />
Stage 1. Dig the pit<br />
Dig a round pit 2m deep and 1.7m in diameter. Dig the<br />
pit with straight sides and a flat bottom.<br />
6