Singapore - Trenchless International
Singapore - Trenchless International
Singapore - Trenchless International
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
October 2010 - <strong>Trenchless</strong> <strong>International</strong> PROjeCts<br />
Piloting to success in jacksonville<br />
by Stephen Tait<br />
Mears Group, Inc. recently completed a 7,400 foot horizontal directional drilling (HDD) bore<br />
in Jacksonville, Florida, US, a design-build project that allows a regional energy producer to<br />
expand its natural gas pipeline to serve new facilities.<br />
TO cOMPLeTe The project, Mears<br />
drilled a 7,400 foot pilot hole beneath<br />
the st Johns River at a depth of<br />
130 feet below river bottom to install the<br />
16 inch steel pipe. It is an essential link in a<br />
50 mile pipeline that ends at the<br />
Jacksonville Electric Authority (JEA)<br />
Greenland Energy Center.<br />
though just 1.4 miles of the 50 mile<br />
pipeline, which is owned by tECO<br />
Peoples Gas, the section under the st.<br />
John’s River proved the most daunting in<br />
planning stages.<br />
Director of Engineering for tECO<br />
Peoples Gas Mark Haney said “this was<br />
the biggest obstacle to go from one side<br />
to the other.”<br />
HDD was virtually the only option to<br />
install the pipeline through that area. Mr<br />
Haney said “Other than HDD, there were<br />
no other good options.”<br />
But project officials said the timing of<br />
the project was also a major issue.<br />
Mr Haney said that the pipeline providing<br />
service to the power plant will<br />
be operational by 1 January 2011. that<br />
means JEA was dependent on the pipeline<br />
being in place in time to move<br />
forward on the operation of the power<br />
plant. to help ensure a timely project,<br />
The Mears rig in action.<br />
tECO hired Mears to complete a designbuild<br />
project.<br />
Project Manager for J.R. Giese<br />
Operations–Mears’ sub-consultant–John<br />
Fluharty said “If it is not built on time you<br />
literally have a billion dollar power plant<br />
there with no fuel.”<br />
Mr Fluharty said design-build allowed<br />
Mears to drill a pilot hole months in<br />
advance to pulling product pipe to ensure<br />
the project was feasible.<br />
“tECO wanted to know that early<br />
enough in the process so they would<br />
know if they needed to go in another<br />
direction, and wanted a true partnership<br />
put together so they could work out all the<br />
issues related to this special feasibility<br />
hole we did in advance,” Mr Fluharty said.<br />
Design-build is relatively new to the<br />
HDD industry, Mr Fluharty said.<br />
Design-build offers a subtle but important<br />
difference from the typical procedure<br />
for HDD projects. In the typical process,<br />
a company such as tECO would hire an<br />
engineer to develop plans, procure a<br />
construction company to implement those<br />
plans and then construct the project<br />
– often called design-bid-build. Designbid-build<br />
requires multiple contracts.<br />
With design-build, however, a single<br />
company is hired to engineer and to build<br />
the project, all under a single contract.<br />
susan Hines of the Design-Build<br />
Institute of America says utilising designbid-build<br />
can create contention between<br />
the engineer or designer of a project and<br />
the company that constructs the project.<br />
she said it creates a disconnect between<br />
the two parties that can often turn contentious<br />
because of concerns of liability<br />
and litigation.<br />
For instance, Ms Hines said when the<br />
construction company finds changes<br />
need to be made to designs during<br />
“Other than HDD, there were<br />
no other good options.”<br />
construction, it takes paper work and<br />
dialogue for the changes to be approved<br />
and implemented.<br />
“It slows things down a lot,” Ms<br />
Hines said.<br />
In the end, design-build projects help<br />
to improve two important aspects of any<br />
project – money and time.<br />
Design-build projects cost at least 6 per<br />
cent less than design-bid-build projects<br />
and are constructed 12 per cent faster,<br />
according to the Design-Build Institute of<br />
America. At the same time, the institute<br />
reports that design-build projects earned<br />
the highest owner satisfaction than other<br />
project concepts.<br />
“One of the main advantages of designbuild<br />
is the fact that everyone on the<br />
design and construction job is on the<br />
same side,” Ms Hines said. “they are all<br />
sharing in the risks and the rewards of a<br />
job well done.”<br />
she added, “Owners save money, they<br />
save time.”<br />
Mears drilled the feasibility pilot hole for<br />
the project in November 2009 and product<br />
pipe was pulled in April 2010.<br />
Mears Project superintendent Mike<br />
Maxwell said the crew drilled from both<br />
sides of the st Johns River and intersected<br />
the two holes under the river – a waterway<br />
lined with stately homes and used mostly<br />
for recreational purposes.<br />
A 330,000 pound rig was used for the<br />
pilot hole on one side of the river and a<br />
140,000 pound rig was used to drill from<br />
the opposite side.<br />
Mears utilised its 500,000 pound<br />
rig to perform the reaming and to pull<br />
the product pipe through the hole, Mr<br />
Maxwell said.<br />
Additionally, Mr Maxwell said, the crews<br />
reamed the bore to 24 inch diameter and<br />
then swabbed the hole before pulling the<br />
product pipe. the crew drilled through<br />
sandy silt before making it to clay for the<br />
drill’s running depth.<br />
“It was fairly easy going; we were able<br />
to use a jetting bit all the way through,” Mr<br />
Maxwell said.<br />
Mr Maxwell said the length of the drill<br />
combined with the unique aspects of the<br />
job, made it a satisfying accomplishment.<br />
40 41<br />
PROjeCts<br />
October 2010 - <strong>Trenchless</strong> <strong>International</strong>