09.01.2013 Views

Singapore - Trenchless International

Singapore - Trenchless International

Singapore - Trenchless International

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

October 2010 - <strong>Trenchless</strong> <strong>International</strong> PROjeCts<br />

Piloting to success in jacksonville<br />

by Stephen Tait<br />

Mears Group, Inc. recently completed a 7,400 foot horizontal directional drilling (HDD) bore<br />

in Jacksonville, Florida, US, a design-build project that allows a regional energy producer to<br />

expand its natural gas pipeline to serve new facilities.<br />

TO cOMPLeTe The project, Mears<br />

drilled a 7,400 foot pilot hole beneath<br />

the st Johns River at a depth of<br />

130 feet below river bottom to install the<br />

16 inch steel pipe. It is an essential link in a<br />

50 mile pipeline that ends at the<br />

Jacksonville Electric Authority (JEA)<br />

Greenland Energy Center.<br />

though just 1.4 miles of the 50 mile<br />

pipeline, which is owned by tECO<br />

Peoples Gas, the section under the st.<br />

John’s River proved the most daunting in<br />

planning stages.<br />

Director of Engineering for tECO<br />

Peoples Gas Mark Haney said “this was<br />

the biggest obstacle to go from one side<br />

to the other.”<br />

HDD was virtually the only option to<br />

install the pipeline through that area. Mr<br />

Haney said “Other than HDD, there were<br />

no other good options.”<br />

But project officials said the timing of<br />

the project was also a major issue.<br />

Mr Haney said that the pipeline providing<br />

service to the power plant will<br />

be operational by 1 January 2011. that<br />

means JEA was dependent on the pipeline<br />

being in place in time to move<br />

forward on the operation of the power<br />

plant. to help ensure a timely project,<br />

The Mears rig in action.<br />

tECO hired Mears to complete a designbuild<br />

project.<br />

Project Manager for J.R. Giese<br />

Operations–Mears’ sub-consultant–John<br />

Fluharty said “If it is not built on time you<br />

literally have a billion dollar power plant<br />

there with no fuel.”<br />

Mr Fluharty said design-build allowed<br />

Mears to drill a pilot hole months in<br />

advance to pulling product pipe to ensure<br />

the project was feasible.<br />

“tECO wanted to know that early<br />

enough in the process so they would<br />

know if they needed to go in another<br />

direction, and wanted a true partnership<br />

put together so they could work out all the<br />

issues related to this special feasibility<br />

hole we did in advance,” Mr Fluharty said.<br />

Design-build is relatively new to the<br />

HDD industry, Mr Fluharty said.<br />

Design-build offers a subtle but important<br />

difference from the typical procedure<br />

for HDD projects. In the typical process,<br />

a company such as tECO would hire an<br />

engineer to develop plans, procure a<br />

construction company to implement those<br />

plans and then construct the project<br />

– often called design-bid-build. Designbid-build<br />

requires multiple contracts.<br />

With design-build, however, a single<br />

company is hired to engineer and to build<br />

the project, all under a single contract.<br />

susan Hines of the Design-Build<br />

Institute of America says utilising designbid-build<br />

can create contention between<br />

the engineer or designer of a project and<br />

the company that constructs the project.<br />

she said it creates a disconnect between<br />

the two parties that can often turn contentious<br />

because of concerns of liability<br />

and litigation.<br />

For instance, Ms Hines said when the<br />

construction company finds changes<br />

need to be made to designs during<br />

“Other than HDD, there were<br />

no other good options.”<br />

construction, it takes paper work and<br />

dialogue for the changes to be approved<br />

and implemented.<br />

“It slows things down a lot,” Ms<br />

Hines said.<br />

In the end, design-build projects help<br />

to improve two important aspects of any<br />

project – money and time.<br />

Design-build projects cost at least 6 per<br />

cent less than design-bid-build projects<br />

and are constructed 12 per cent faster,<br />

according to the Design-Build Institute of<br />

America. At the same time, the institute<br />

reports that design-build projects earned<br />

the highest owner satisfaction than other<br />

project concepts.<br />

“One of the main advantages of designbuild<br />

is the fact that everyone on the<br />

design and construction job is on the<br />

same side,” Ms Hines said. “they are all<br />

sharing in the risks and the rewards of a<br />

job well done.”<br />

she added, “Owners save money, they<br />

save time.”<br />

Mears drilled the feasibility pilot hole for<br />

the project in November 2009 and product<br />

pipe was pulled in April 2010.<br />

Mears Project superintendent Mike<br />

Maxwell said the crew drilled from both<br />

sides of the st Johns River and intersected<br />

the two holes under the river – a waterway<br />

lined with stately homes and used mostly<br />

for recreational purposes.<br />

A 330,000 pound rig was used for the<br />

pilot hole on one side of the river and a<br />

140,000 pound rig was used to drill from<br />

the opposite side.<br />

Mears utilised its 500,000 pound<br />

rig to perform the reaming and to pull<br />

the product pipe through the hole, Mr<br />

Maxwell said.<br />

Additionally, Mr Maxwell said, the crews<br />

reamed the bore to 24 inch diameter and<br />

then swabbed the hole before pulling the<br />

product pipe. the crew drilled through<br />

sandy silt before making it to clay for the<br />

drill’s running depth.<br />

“It was fairly easy going; we were able<br />

to use a jetting bit all the way through,” Mr<br />

Maxwell said.<br />

Mr Maxwell said the length of the drill<br />

combined with the unique aspects of the<br />

job, made it a satisfying accomplishment.<br />

40 41<br />

PROjeCts<br />

October 2010 - <strong>Trenchless</strong> <strong>International</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!