Singapore - Trenchless International
Singapore - Trenchless International
Singapore - Trenchless International
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
October 2010 - <strong>Trenchless</strong> <strong>International</strong> INdUstRy INNOvAtIONs<br />
jack in the box<br />
by James Thomson, Chairman, Jacked Structures SA<br />
James Thomson, owner and principal of Jason Consultants Group until 2003, recently formed<br />
Jacked Structures SA. Here Mr Thomson details the different concepts of installation.<br />
The JackING Of large structures,<br />
such as road underpasses, pedestrian<br />
subways and culverts uses trenchless<br />
jacking methods.<br />
I developed and pioneered these techniques<br />
in the 1960s and 1970s when<br />
working with a major international contractor.<br />
the initial projects were for pedestrian<br />
subways using large diameter pipes to<br />
provide the structure. the next development<br />
was to jack box sections for culverts<br />
and pedestrian subways. With this experience<br />
we increased the dimensions to<br />
accommodate larger structures. Figure<br />
1 illustrates a typical situation where a<br />
pedestrian subway is driven under a rail<br />
embankment to allow separation of traffic<br />
and pedestrians.<br />
Figure 1 A Pedestrian subway under rail<br />
embankment.<br />
the most basic approach, which is still<br />
widely used, is box jacking where the<br />
structure is constructed on a launch pad<br />
adjacent to where it is to be installed and<br />
is jacked into the ground with excavation<br />
taking place in the shield.<br />
Dealing with a face excavation which<br />
can be typically 15 m wide and 8 m<br />
high you need to compartmentalise the<br />
shield, which is fixed to the front of the<br />
structure – very much like Brunel’s shield<br />
for the very first tunnel under the thames<br />
back in 1823. You also need to provide<br />
thousands of tonnes of jacking capability<br />
to push such large sections, which in<br />
turn needs the provision of suitable reaction.<br />
the frictional loads on a rectangular<br />
structure are much greater than experienced<br />
when installing circular sections<br />
so there is a need to introduce anti-drag<br />
systems to reduce this.<br />
Many installations have been undertaken<br />
under roads, rail tracks and<br />
runways. Figure 2 shows one of the<br />
first projects undertaken in the early<br />
1970s where two underpasses were<br />
driven below a major road in North<br />
London to provide access to Brent Cross<br />
shopping centre. Perhaps the most high<br />
profile installation was the three large<br />
underpasses jacked under rail tracks in<br />
Boston, Us as part of the Big Dig project.<br />
these boxes were approximately 24 m<br />
wide, by 11 m high and the longest drive<br />
was 109 m. Figure 3 gives some idea<br />
of their size and the large number of<br />
hydraulic rams that were used. Because<br />
of the ground conditions – which were<br />
mainly soft marine deposits with old piles<br />
and buried quay walls – the ground was<br />
stabilised by freezing.<br />
Figure 2 Brent Cross jacked Underpass<br />
under A41.<br />
Figure 3 Jacked Boxes Boston Big Dig.<br />
Box jacking, where the track is temporarily<br />
supported and structures are<br />
installed directly below the rail tracks, is<br />
widely used in Europe.<br />
there are some inherent limitations in<br />
box jacking and in recognition alternatives<br />
approaches have been developed.<br />
If provision is made with the rail authority,<br />
it is possible to obtain brief possession<br />
to undertake work. With this in mind I<br />
developed the modular approach.<br />
Using a series of precast jacked boxes,<br />
abutments and central piers can be<br />
constructed without disrupting rail operations.<br />
As can be seen, a whole series of<br />
operations can be undertaken from the<br />
boxes such as cross strutting and finally<br />
stressing the boxes together and infilling<br />
with concrete. During a short track<br />
possession the bridge deck can be slid<br />
in or bridge beams placed to complete<br />
the structure. A large number of such<br />
jobs have been undertaken in the UK.<br />
A typical installation is the Wandsworth<br />
under-bridge shown at figure 4. this<br />
concept minimises the exposed face at<br />
any time and requires much less launch<br />
area as only relatively small jacking pits<br />
are needed.<br />
Figure 4 Wandsworth Under-Bridge<br />
London.<br />
More recently a new patented development<br />
is the jacked deck which can<br />
be combined with the modular system to<br />
provide a complete structure without disrupting<br />
rail services. the modular system is<br />
used but the top box is modified internally<br />
to allow a slide track to be installed. these<br />
top boxes are also designed with a removable<br />
section which exposes the track as the<br />
deck is jacked into place. the jacked deck,<br />
which can be formed from a complete cast<br />
on site structure or formed from precast<br />
beams, is fitted with a compartmentalised<br />
shield where excavation takes place. this<br />
same concept can also be used with a<br />
jacked circular tube or box providing an<br />
access gallery which allows piling to be<br />
undertaken to provide abutment walls and<br />
the installation of the slide track.<br />
this approach is currently being used<br />
to install a 20 m wide by 126 m long traffic<br />
underpass under rail tracks in UK.<br />
Another patented approach is to install<br />
The relentless growth of<br />
cities is creating a demand<br />
to install structures below<br />
existing facilities and<br />
buildings. The potential<br />
applications for creating<br />
large underground spaces<br />
by jacked methods without<br />
disruption are unlimited.<br />
initially jacked foundation boxes with<br />
removable lids and install in these boxes a<br />
slide track. In this case, precast arch sections<br />
are jacked in along the track with lids<br />
being removed within the shield as excavation<br />
takes place.<br />
the Jacked Arch has a number of advantages<br />
such as the reduction of jacking loads<br />
and face stability is improved. the use of<br />
precast arch sections also minimises the<br />
launch area. this approach enables larger<br />
spans and longer length to be installed.<br />
Metro station structures are quite possible<br />
and full support to the excavation as work<br />
advances would be provided thereby eliminating<br />
the risk of collapse.<br />
there are other techniques used such as<br />
the provision of advanced support structures<br />
where a canopy is installed as an<br />
initial support for the final structure. typical<br />
approaches are shown in the graphic<br />
at figure 5. the steel tubes that form the<br />
canopy can be installed by pipe ramming,<br />
microtunnelling or auger boring.<br />
Figure 5 Advanced support structures.<br />
Although the majority of Jacked structure<br />
installations have been in Europe, projects<br />
have been undertaken in Us, India,<br />
Canada, south Africa, Indonesia, taiwan,<br />
Korea, Japan and Australia.<br />
the relentless growth of cities is creating<br />
a demand to install structures below existing<br />
facilities and buildings. the potential<br />
applications for creating large underground<br />
spaces by jacked methods without disruption<br />
are unlimited. the separation of road<br />
and pedestrian traffic from rail traffic is<br />
essential to avoid the all too frequent accidents<br />
that occur at rail crossings. Valuable<br />
and scarce development land cut off by<br />
rail tracks and highways can be accessed.<br />
New underground space such as parking<br />
garages and storage can be created.<br />
One interesting possibility that was put<br />
to me in Australia was the possibility of<br />
installing wine storage caverns. I am hoping<br />
this will go ahead and I might get the<br />
opportunity to check out the quality of<br />
wine stored.<br />
Biography<br />
James Thomson has been involved in<br />
<strong>Trenchless</strong> Technology over many years and<br />
in developing and designing the installation of<br />
large structures since the late 1960s. He was<br />
the owner and principal of Jason Consultants<br />
Group until 2003, a company specialising in<br />
<strong>Trenchless</strong> Technology including a number<br />
of jacked structure project. His experience<br />
in the field has led him to develop some<br />
concepts that have been patented. Along with<br />
experienced colleagues who have worked with<br />
him over the years he recently formed Jacked<br />
Structures SA. A consultancy specialising in<br />
developing concepts, detailed engineering,<br />
installation design and contract management<br />
for these projects. Work is undertaken for<br />
owners, consultants and contractors.<br />
Further information is available on the Jacked Structures SA web site<br />
www.jackedstructures.com<br />
Maxi-Rig Directional Drills<br />
Auger Boring Machines<br />
Product Tooling & Accessories<br />
Mud Pump & Cleaning Systems<br />
Oil & Gas Drill Rigs<br />
Mid-Size Directional Drills<br />
Exceptional Force … Reliable Results.<br />
For 40 years, customers worldwide have<br />
come to know American Augers as a<br />
dedicated manufacturer of underground<br />
technology equipment, which includes<br />
state-of-the-art horizontal directional<br />
drills, earth boring machines, mud pump<br />
and cleaning systems, oil and gas drill<br />
rigs, and various product tooling or<br />
accessory items. Each of the product<br />
categories produce equipment that<br />
maintains rugged, unsurpassed power,<br />
and industry leading designs.<br />
AA Company island Ad TI.indd 1 12/14/09 4:57 PM<br />
44 45<br />
INdUstRy INNOvAtIONs<br />
October 2010 - <strong>Trenchless</strong> <strong>International</strong> 45