The number of reaming passes that will be determined by the hardness of the<br />

material being reamed and the ability to remove cuttings from the hole.<br />

8.6 Testing<br />

As noted in Section 3.4.4, the pipe string is often hydrostatically pretested prior to<br />

pull back. This segment of pipe is then also tested as part of the mainline pressure<br />

test. Pretesting and testing of the installed pipe upon completion of the drill<br />

should follow CAPP’s 1996 Guidelines <strong>for</strong> Hydrostatic Test Water Management.<br />

September 2004 <strong>Planning</strong> <strong>Horizontal</strong> <strong>Directional</strong> <strong>Drilling</strong> <strong>for</strong> <strong>Pipeline</strong> <strong>Construction</strong> Page 8-6