In addition to having an EPP, it is essential to have qualified people onsite to<br />
enact the plan, to handle deviations to the plan and to report events properly to the<br />
authorities. Having an environmental specialist or biologist onsite to liaise<br />
directly with the DFO habitat biologist or other similar authority can prove useful.<br />
Effective communication of unintended events and subsequent mitigation actions<br />
to the authorities may reduce delays or unwarranted en<strong>for</strong>cement actions<br />
contingency planning, e.g., inadvertent returns, (see also Section 10.3.2); and<br />
reclamation.<br />
September 2004 <strong>Planning</strong> <strong>Horizontal</strong> <strong>Directional</strong> <strong>Drilling</strong> <strong>for</strong> <strong>Pipeline</strong> <strong>Construction</strong> Page 9-6