5. Estimated Investment to Modify 7FA Burning NG to Syngas<br />
We have not executed a conversion of a NG 7FA to syngas so detailed<br />
costs are not available except through an engineered commercial<br />
proposal including a detailed analysis of the site, fuel and operational<br />
requirements.<br />
However, provided that the syngas meets our current standard<br />
specification requirements, an indicative cost would be in the range of<br />
$6MM-$7MM per unit with an approximate 6 week outage for<br />
completion of conversion.