30.01.2013 Views

19 DER Technical Requirements for Interconnection in Germany

19 DER Technical Requirements for Interconnection in Germany

19 DER Technical Requirements for Interconnection in Germany

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Overview | Exist<strong>in</strong>g requirements <strong>in</strong> <strong>Germany</strong> | Upcom<strong>in</strong>g codes on the European level | Summary<br />

Exist<strong>in</strong>g requirements <strong>in</strong> <strong>Germany</strong><br />

BDEW <strong>Technical</strong> Guidel<strong>in</strong>e Generat<strong>in</strong>g Plants Connected to the Medium-Voltage Network<br />

requirements:<br />

> generation control – i.e. power curtailment on demand<br />

> frequency control – by reduc<strong>in</strong>g active power <strong>in</strong> the event of over frequency<br />

> voltage control – by use reactive power<br />

> dynamic grid support – with the option to provide reactive current to dim<strong>in</strong>ish voltage dips<br />

(AKA: “fault ride through” (FRT) / “low voltage ride through” (LVRT) / “zero power mode”)<br />

> certification of<br />

SMA Solar Technology AG<br />

> “units” (e.g. PV <strong>in</strong>verters) based on type test<strong>in</strong>g and<br />

> plants (as a comb<strong>in</strong>ation of one or more “units” and further equipment i.e. trans<strong>for</strong>mers,<br />

cables, etc.) based on simulation<br />

Knopf/Rogalla, April 12, 2012, EPRI/PJM/NREL workshop, PJM <strong>Interconnection</strong>, Norristown, PA<br />

6

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!