01.02.2013 Views

ESO Annual Report 2004

ESO Annual Report 2004

ESO Annual Report 2004

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

ased on the conservative assumption<br />

that segments would receive unprotected<br />

Aluminium coatings, requires that 5 segments<br />

be processed within a single day<br />

(10 hours, daytime). Spare segments allow<br />

for such operations to be executed without<br />

overhead on science time. The highest<br />

technology involved is in the 2-m class<br />

coating tanks, and in the metrology system<br />

embedded into the handling tool, for<br />

semi-automatic replacement and coarse<br />

phasing of the segments under maintenance.<br />

As segments integration starts<br />

after most major subsystems have been<br />

completed and provisionally accepted<br />

on-site, first light may follow rapidly. According<br />

to current estimates, science<br />

could start within 19 months after the integration<br />

of the first segment, with a total<br />

collecting area equivalent to that of a<br />

50-m telescope.<br />

The estimated schedule to completion is<br />

currently under thorough review. The<br />

baseline plan would allow first light five<br />

years after construction begin, start<br />

of science one year later and completion<br />

11 years after construction start. The<br />

critical path to first light is set by the structure,<br />

enclosure, and above all the 8-m<br />

mirrors of the corrector and the first generation,<br />

2.3-m class adaptive mirror. Options<br />

are currently being explored, whereby<br />

early financial commitments would<br />

allow for a faster schedule. Such commitments<br />

would represent roughly 5 % of<br />

the total capital investment, and include,<br />

most notably, the early purchase of<br />

two 8-m blanks, and of competitive final<br />

designs of the structure, enclosure,<br />

and first generation adaptive unit. A higher<br />

cash flow in the early phases of construction<br />

would also be necessary.<br />

Several concept studies on OWL instrumentation<br />

have begun, in close collaboration<br />

with the astronomical community<br />

(most of them are carried out outside<br />

<strong>ESO</strong>), to explore the requirements imposed<br />

on instruments by the science cases,<br />

and the related feasibility issues. Specific<br />

instrument-related science cases are<br />

also being developed, in close contact<br />

with the other science activities described<br />

earlier.<br />

ELT Design Study<br />

During <strong>2004</strong>, substantial effort has been put<br />

into the negotiation of the final scope of<br />

work and budget for the ELT Design Study. The<br />

project, approved for partial funding by the<br />

European Commission, covers the development<br />

of enabling technologies and concepts for an<br />

Extremely Large Telescope, without prejudice to<br />

its actual design. As such, the activities covered<br />

by this project are complementary with those<br />

specifically undertaken for the design of OWL.<br />

The design and testing of position actuators, of<br />

metrology systems, the development of breadboards<br />

for the evaluation of performance under<br />

wind excitation, for the on-sky evaluation of<br />

wavefront control techniques including phasing<br />

(APE), prototyping of thin adaptive shells,<br />

site characterization, etc. are typical examples<br />

of tasks covered by the ELT Design Study.<br />

As parallel, but not redundant activities, the<br />

OWL design and the ELT Design Study benefit<br />

from mutual feedback, their respective schedules<br />

ensure that progress is made in an optimized<br />

timeframe, and their complementarities<br />

ensure cost-effective developments. Indeed the<br />

parallelization of activities is crucial, as delays<br />

in the ELT Design Study would potentially delay<br />

design and analysis activities with OWL, and<br />

vice-versa.<br />

The ELT Design Study gathers 30 partners,<br />

mostly European, and including academic<br />

as well as industrial resources, under <strong>ESO</strong>’s<br />

lead. The proposal was submitted to the<br />

EC in March <strong>2004</strong>, and received very high<br />

marks. The total project cost was estimated at<br />

42 M€, out of which 22 M€ were requested<br />

to the EC. It was approved at a level 8.4 M€ in<br />

EC funding i.e. 14 M€ lower than initially requested.<br />

Utmost effort has been undertaken by<br />

most partners in order to cut costs without<br />

significant de-scoping, as requested by the EC,<br />

and to maintain the level of self funding at<br />

the pre-cut values. This included increasing the<br />

<strong>ESO</strong> contribution to 9.4 M€.<br />

OWL Instruments<br />

In support of the on-going OWL Feasibility<br />

Study, several Instrument Concept studies have<br />

also been started by the Instrumentation<br />

division with the astronomical and technical<br />

support of institutes in France, Germany,<br />

Italy, The Netherlands, Sweden, Switzerland<br />

and the United Kingdom. The capabilities<br />

being explored include an ultra-stable, high resolution,<br />

optical spectrograph to measure the<br />

cosmic expansion from the observation of high<br />

redshift sources; a wide field camera with partial<br />

adaptive optics atmospheric correction for<br />

the study of faint stars and galaxies; a multiobject,<br />

near IR spectrograph; a small field, diffraction<br />

limited planetary camera-spectrograph<br />

for the detection of earth-like planets; a submillimetre<br />

camera for the detection and study of<br />

dusty, high redshift star forming galaxies; a<br />

thermal infrared camera-spectrograph for the<br />

investigation of regions of star formation in<br />

the Galaxy and at high redshift, and an instrument<br />

for the study of quantum optics phenomena<br />

in astrophysics. The specific purpose<br />

of these studies is to elaborate on the science<br />

goals which are expected to make the<br />

largest impact; test the viability of building<br />

the required instruments and interfacing them<br />

with the telescope; identify any required technical<br />

developments and provide a rough idea of<br />

possible costs. More generally, this exercise<br />

will make the <strong>ESO</strong> community more familiar with<br />

the OWL concept and provide them with the<br />

opportunity to contribute actively to its detailed<br />

definition and design.<br />

0.6�<br />

1.7�<br />

<strong>ESO</strong> <strong>Annual</strong> <strong>Report</strong> <strong>2004</strong><br />

Simulated point spread<br />

function in K-band, with<br />

residual phasing errors,<br />

under good seeing conditions,<br />

with bright guide<br />

star (m K = 8) and single<br />

conjugate adaptive<br />

optics (first generation).<br />

41

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!