Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
PANDR
Pandrol Industries Inc.
175 John-F. Kennedy Street
Saint-Jerome, Quebec J7Y 4B5
Té1. : (800) 667-4709 ou (450) s6s-9100
Fax : (800) 442-9817
Trainee Workbook
Module L
Thermite Welding
with the
Pandrol LP CJ & AP CJ
Calorite Thermite \Melding Kit
.l
e
The LP CJ & AP CJ V/eld
Process
Trainee Workbook
2019 Edition
Trainee Worhbooh
Module I
e T."t
2
TYøinee Worhbook Module 1
Course Information
Introductíon
3
Tlainee Worhbooh Mod,ule 1
Table of Contents
page
I
il
Course Inforrnation
Table of Contents
Introduction
Foreword
General Course Goals & Objectives
Lesson Introduction
Course Content & Schedule
The LP CJ & AP CJ Thermite Weld
Rationale
Objectives
3
4
5
6
7-8
I
10
11
L2
12
III Module 1
The 13 Steps
Step l: Job Preparation
Step 2: Site Preparation
Step 3: Track Preparation
Step 4: Rail-end Preparation
Step 5: Rail-end Alignment
Step 6: Mold Preparation
Step 7: Preheating
Step 8: Charge Preparation
Step 9: Pouring
Step 10: Demolding & Shearing
Step 11: Hot Grinding
Step 12: Cold Grinding
Step 13: Finishing
Exception Conditions
13
I4
t7
18
20
24
27
39
44
48
50
53
57
59
61
63
IV Module 2
Hands-on LP CJ & AP CJ Wetd
67
4
Tlainee Worlzbook
Module I
Introductíon
Thermite welding is the application for welding rail of the aluminothermic process,
that is, the reduction of an oxide by a more reactive metal. In merely twenty seconds,
the charge, a mixture of aluminum, iron oxide and appropriate quantities of alloying
elements, produces enough molten steel to weld any size rail.
Calorite is the thermite charge developed by Railtech. Through over 90 years of
experience in the aluminothermic production of chromium and with the help of its steel
foundry engineers, Railtech has developed high efficiency charges adapted to the
different rail chemistries.
Pandrol Industries now manufactures Calorite materials in Canada. This permits
rapid delivery of all standard materials and a faster response to special requests.
There are two processes available. The limited preheat weld should be the choice when
the weld must be done quickly as in the case of rail laying programs. If the welds are
close together and the same people can start setting up the next weld during
preheating, the standard preheat process should be considered.
Thermite Welding - Important Points
1. The gap required of 25 - 28 mm (1", minus 0"/plus +1/8") is the same regardless of
the rail or process used. The rail are aligned with a slight crown at the joint to
compensate for the uneven cooling rates in the rail section. The Railtech rail
alignment beam and the A-Frame Aligner are designed to facilitate this operation.
2. The hardware is simple and universal. No need to carry different equipment for
different rails. The equipment has been made as light as possible. If space is a
problem, 25 mm (1") is all that is required under the rail.
3. Air propane preheating is available for both the limited preheat or standard
preheat processes.
4. Now it is time to make the weld. The crucible is positioned over the mold and, in
merely one minute, the weld is completed.
5. While the weld is cooling, it is time to start the Matweld or Railtech weld shear
which has been designed to facilitate the removal of surplus metal and make it
safer. Of course the hot cut chisel may still be used.
6. A little grinding around the rail head and the trains can run again
5
Trainee Workbook
Mod,ule I
Foreword
Calorite is a process for thermite welding which has been successfully used to weld rails
since 1903. Calorite materials are produced following precise formulas developed by
metallurgical engineers. The process has been proven on thousands of welds made
under various conditions in countries all over the world. Every precaution is taken to
insure that the materials in your kit are of the highest quality. However, the quality of
the weld will depend to a great extent on you and your ability to follow the procedures
outlined in this booklet. DO NOT TAKE SHORT CUTS. DO NOT SUBSTITUTE
any part of the welding apparatus with homemade or otherwise obtained components.
When welding under rain or snowfall, adequate cover must be provided to protect the
materials and crucible from moisture. Also make sure that there is no water under the
joints to avoid molten metal coming in contact with water when metal pours from the
crucible.
Finally it is very important to verifii that the disposable crucible and the cover have not
been damaged.
Equiprnent Required
Wood or Steel Wedges
Straight Edge
Gap Gauge
Support & Clamp Ass'y
Mold Frame Ass'y (3 pces)
Packing Rod
Slag Basin
Preheating equipment
Crucible Fork
Hot Cut Chisel and Sledge Hammer
Grinder
Rail Weld Shear (optional)
Alignment Beam (optional)
Rail Saw (optional)
Standard track hand tools
A-Frame Aligner (optional)
6
Trainee Worhbook Module 1
General Course GoaI
There are millions of thermite welds that have been installed across
Canada, with over 50,000 welds added every year. Incorrect or
inconsistent welding procedure is contributing to failures. The
safety and service implications of just one failure speak for
themselves-
The goal of the LP CJ & AP CJ Thermite Welding Course is to
provide you with the necessary skills ço that you will be able to
consistently perform a reliable LP CJ or AP CJ thermite weld in a
safe manner under a variety of weather and rail conditions with the
minimum amount of track down-time.
Traínee Worhbook
This Trainee W'orkbook is designed to act as a guide as you
participate in the course. It includes useful information on LP CJ
&AP CJ thermite welding in general, The 13 Steps in the AP & AP-
CJ thermite weld procedure, and exception conditions that you may
encounter. This workbook can also serve as a reference manual
that you can refer to whenever performing a LP CJ & AP CJ
thermite weld.
This workbook will be used throughout the course as both a
workspace and a resource guide. With the exception of the quizzes,
everything you need to read or write is in this workbook.
I
TYa.inee Worhbook
Mod,ule I
Course Objectiues
At the end of this course you will be able to:
1
2
3.
4.
5.
6
7
I
I
10.
11.
L2.
13
14.
15
Recognize the potential liability of weld failure in terms of
both financial and service costs;
Understand your role & responsibility in the reliability of
each weld;
List several advantages & difference between the LP CJ &AP
CJ weld procedure and other thermite processes;
List the fundamental techniques that guarantee a reliable
weld;
Recognize the track, rail & weather conditions necessary for
a successful thermite weld;
Recognize & assemble the required thermite welding
accessories & material;
List the 13 main steps in the LP CJ &AP CJ thermite
welding process;
Recognize & follow the correct welding sequence;
Recognize specific, time, temperature and exception criteria
within the steps;
Identify key process areas critical to weld reliability.
Prepare the track, rail & required thermite weld accessories;
Execute a LP CJ or AP CJ thermite weld with respect to
sequence, time, temperature and exception criteria;
Complete the weld and return the track & structure to
standard;
Perform a weld safely with a minimum of track down-time;
Complete the quiz: On the criteria related to thermite
welding.
I
Tlainee Worhbook
Mod,ule I
Lesson Introduction
The LP CJ &AP CJ Therrníte WeId
9
Tlaínee Worhbook Module 1
Lesson Introduction
Course Content
This morning's activities wilL include:
. An overview of what a LP CJ &AP CJ weld is
. Why we are all here to review the process
. An overview of the 13 major steps in the LP CJ &AP CJ
thermite welding process
o A detailed look at each of the 13 steps using video and
demonstration material
. A review of exception conditions... abnormal or unusual
situations that you may find when performing a weld
This afbernoon's activities will include:
. Performing and evaluating a LP CJ OR AP CJ weld in
teams of three
. A final quiz to reinforce the key points
Schedule
. There will be breaks in the morning session
. Lunch will be from approximately to
. Because of the workload, there will only be one break in
the afternoon
¡ With your cooperation, the course should finish by
-
10
Trainee Worhbook,
Module I
Course Introductíofl, (cont'd,)
The LP CJ &AP CJ Thermite Weld
o Thermite is an abbreviation of 'aluminothermic'...
because once ignited, a mixture of alloys, aluminum and.
iron burns at very high (thermal) temperatures
-
2480"C (4500'F)
-
creating molten steel that pours into
a mold around two rail-ends
. For those of you who may not be familiar with the LP CJ
process, LP stands for'Limited/Quick Preheat'... because
of the relatively short preheat time compared to other
processes. AP stands for'Avec Prechauffage'and refers
to the Longer Preheat process.
o CJ stands for'Creuset Jetable'which means the crucible
is disposable... making it a one-shot process that does
not require reusing the crucible.
. Some advantages of the CJ crucible are:
- you don't have to clean the crucible
- you don't have to preheat the crucible
- the thimble comes pre-installed
- you need fewer pieces of equipment
- the crucible is lighter
. As a result, the temperature of each LP CJ &AP CJ
pour is very consistent. Consistency is a word you will
be hearing a lot today because consistency is one of the
keys to a successful, reliable weld each and every time
¡ Also, the LP CJ &AP CJ is environment-friendly
because the crucible is biodegradable and decomposes as
it cools
11
TYainee Worhbooh
Mod,ule I
Course Introduction (cont'd,)
Rationale
. Analysis of weld failures reveal incorrect or inconsistent
welding procedures as one of the contributing factors
¡ Weld failure can lead to:
- train delays
- disruption of service
- derailments
- increased operating costs
Objectives
¡ Every time you perform a thermite weld, you put your
name on that weld
. The purpose of this course is to make sure that each
time you do, you have confidence in the reliability of the
weld you have just done
. We are going to achieve this by emphasizing 4
techniques that will guarantee you a reliable LP CJ or
AP CJ weld every time. It's called CAST. CAST are
four letters that stand for:
- Consistent work practices
- Accuracy
- the correct Sequence of $teps
- and Tirning
. If you remember those four letters and the words they
stand for, you will remember how to CAST a perfect
thermite weld every time
t2
T?ainee Worhbook
Mod,ule I
Module I
The 13 Steps
13
TYainee Worhbooh
Mod,ule I
The 13 Steps
A successful LP CJ &AP CJ thermite weld can be seen as
13 separate steps that must be done in a specifi.c sequence
EJ
1. Job Preparation:
¡ Using a standard checklist to assure that you have all
necessary tools, materials, equipment, and information
before you leave for the weld site
2. Site Preparation:
. Evaluate the general site condition
. Correct any situations that create a potential fire or
safety hazard
.,Ër
Fil
3. Track Preparation:
. Secure the rail so that it doesn't move during joint
preparation, alignment and welding
4. Rail-end Preparation:
. Inspect, & prepare the joint to a condition acceptable for
thermite welding
DI
5. Rail-end Alignment:
o Set-up the correct gap, peak (also called the'crown'or
'vertical alignment'), horizontal alignment, and
eliminate unequal cant between rail-ends
. A critical step where inconsistent work will lead to weld
failure
I4
TYainee Workbooh Module 1
The 13 Steps (cont'd,)
6. Mold Preparation:
. Prepare and assemble the mold components & apply
fusal paste
. Another critical area where poor work will lead to weld
defects
7. Preheating:
r Heat the mold & rail-ends for a specified time
o Another area where accuracy and timing are important
H .I 8. Charge Preparation:
. fnspect components for moisture and damage
. Assemble the CJ crucible & charge
9. Pouring:
. End the preheating at the correct time
o Position the CJ crucible centered over the mold
¡ Ignite the charge & monitor the pour
10. Demolding & Shearing:
o At a specified time after the pour... demold, shear and
remove debris
15
TYainee Worhbook
Mod,ule I
The 13 Steps (cont'd.)
11. Hot Grinding:
¡ Grind the weld close to the rail
¡ Blend the gauge & field surfaces
12. Cold Grinding:
. Grind the weld flush with the rail to blend with the
running surface
. Accuracy during hot & cold grinding contribute to weld
reliability
13. Finishing:
. fnspect, document & tag the weld
r Restore the track to standard
. Clear the site
. Cancel the track protection
16
Trainee Worhbooh
Module I
Step 1: Job Preparation
Consumables Checklist
t Fusal paste
tr lgnition fuses
tr Gasoline & oil for power tools
tr Sufficient gasoline, propane & oxygen
tr CJ kits (2 boxes) per weld
tr Three spare kits (per day)
tr Tie plugs
tr Spare railfasteners, tie plates & pads
tr Spare closure rail (weight, type, length)
tr Cutting disks
tr Grinding wheels
tr Soap stone
tr LD. tags & adhesive
D Forms, manuals, protection documentation
GJ Hardware Checklist
tr Mold clamp
tr Mold jackets (2)
D Base plates (2)
tr Slag basin
tr CJ fork
Pre & Post-heating Equipment
D Preheating unit
tr Burner & support stand
tr Regulator
D Air & propane hose
tr Turbo torch
tr Approved ignition device
tr Torch
f,¡ Heat retarding blanket or shield
Safetv Equipment Checklist {** recommendations)
tr Welder's goggles
tr Face shield
tr Welder's gloves
tr Leggings
tr Hearing protection
tr Respirator
tr First aid kit
tr Fire protection equipment
tl Manufacturer's Safety Data Sheets
Power Tools Checklist
tr Railsaw
tr lmpact wrench (optional)
tr Hydraulic rail expander
D Hydraulic weld shear
tr Profile grinder or utility grinder
Hand Tools Checklist
tr Adjustable wrench
tr Track wrench
tr Lining bar
tr Claw bar
tr Sledge hammer
tr Spiking maul
tr Hot cut chisel
D Hammer
tr Railpositioner
tr Clip applicator
D Anchor applicator (if required)
tr Tamping bar
tr Shovel
tr Wedges
tr Wire brush
tr l.D. tag stamps
Tools to fix power tools
D Rail alignment equipment: alignment beam,
rail raisers, decanter, positioner, gauge rods
(optional)
Measurement Tools Checklist
B Welder's straight edge, 1m (3 ft)
tr Taper & railwear gauge
D Railthermometer
tr Stop watch
tr Tape measure
D Temperature indicating crayons
lnformation Checklist
tr Arrange track protection
tr Conduct job briefing
**please refer to your company's safety
policy as it takes precedence
t7
T\ainee Worhbook Mod,ule 1
Step 2: Site Preparation
When you first get to the job site, certain things must be
done before you remove one single tool from the welding
truck.
¡ Check-out safety hazards:
- moisture, snow or frost in ballast
- slippery conditions
- multi-track
- obstacles
- traffic near level crossing
. Check-out fire hazards:
- dry grass, brush, wood chips
- flammable material
- combustible rail lubricators
. Find suitable location for disposal hole:
Caution!
Check for underground cables before digging!
. If necessary, update your job briefing so that:
- everyone knows about aII hazards
- each person is assigned responsibilities: (safety
watch, fire watch, first aid, etc.)
o Position fire fighting equipment nearby
o Wet down any dry/flammable material
Hot Tip! . Check for safety & fire hazards!
. Update your job briefing!
. Do not wet down the area immediately near the
weld or disposal hole!
. Make sure the area immediately near the weld or
disposal hole is free of anv form of moisture!
18
Trainee Worhbooh
Module I
Step 2: Site Preparation (cont'd,)
Questions
Ql: Why must you check to see if the ballast below the
weld atea and at the disposal hole is free of moisture,
snow or frost?
a
Q2: What precaution should you take when welding on
multi-track territory?
a
Q3: Why are obstacles near the weld area a safety hazard?
a
o
Q4: Why is welding near a level crossing considered a
safety hazard?
o
19
Trq,irLee Worhbooh
Module I
Step 3: Trach Preparution
'ån
. Verifr line & surface
. Place thermometer on rail
¡ Ensure rail type & weight is compatible w/ CJ kit
. Verifu that the gap is no closer than100 mm (4") from
tie. However, the design of the base plate holder
permits installation closer to a tie when necessary.
. Remove ballast for 100 mm (4") below the gap
. Tighten anchors for at least 15m (50 ft)
o Loosen/remove fasteners for 3 ties to each side of the
gap
. On wood ties: make match marks on rail base to tie
plate, tie plate to tie on third tie to each side of the gap
. On concrete ties: make match marks on rail base to tie
on third tie to each side of the gap
. Ties with match marks must be unanchored
. Check that the shear & grinder are operational
. If a rail expander is used make sure that it is properly
positioned to allow the use of the weld shear should this
equipment be used to cut the excess metal.
Hot Tip!
It is critical that all anchors or fasteners are tight and
the track secured. If the rail moves later on:
. The gap will change, and the rail-ends will not be
heated correctly!
. The fusal paste around the molds may crack,
causing a run-through!
20
Tlainee Workbooh Module 1
Step 3: Trach Preparatiorù (cont'd.)
Questions
Q1: Why must you eyeball the joint?
a
o
Q2: Why must you put the thermometer on the rail now,
and not later?
a
o
Q3: Why should you check the branding and stamping on
both rail-ends now?
o
2L
TYainee Worhbooh Mod,ule 1
Step 3: Trach Preparatiotù (cont'd,)
Q4: Why must the rail gap be at least 100 mm (a in) from
the nearest tie?
o
a
Q5: What can you do to make sure the gap doesn't change
while you are setting up the weld?
a
a
o
Q6: What must you do when making match marks on
wood ties?
1
2
3
On concrete ties?
1
2
22
Trøinee Worhbook
Mod,ule I
Step 3: Trach Preparatíotu þont'd,)
Q7: lVhy should you check out the weld shear & grinder
now?
o
a
23
TYainee Workbooh
Step 4: Rail-end Preparatíon
--II *-
Mod,ule I
r A gap must not be positioned over a tie
. Inspect rail-ends & bolt holes for cracks, batter, defects,
and previous weld material
. Veri& that any drilled holes are further than 100 mm (4
in) from the rail-end
. Rail-ends must always be cut with a rail saw
. Veri& that rail-ends are square/perpendicular with a
tolerance 0.8 mm (1/32 in)
. Clean the rail-ends with a wire brush (or grinding tool)
for at least 100 - 150 mm (a - 6 in)
. The weld aîea is defined as 0.5 m (18 in) to either side of
the gap
Hot Tip!
The rail-end.s must:
. be square & perpendicular
. be cut with a rail saw (Figure 1)
¡ not have been previously welded by gas or electric
welding
Otherwise a defective weld may result!
figure I
24
Trainee Workbooh Mod.ule 1
Step 4: Rail-end Preparatiorù (cont'd,)
Questions
Ql: Why can't a rail-end that has been built up by gas or
electric welding be thermite welded?
o
o
Q2: Why must the rail-ends be free of defects and foreign
material?
o
Q3: Why must the rail-ends be square & perpendicular?
o
o
25
Trainee Worhbook
Mod,ule I
Step 4: Rail-end Preparation (cont'd,)
Q4: Why must all drilled holes be a minimum of 100
mm (4 in) away from the rail-end?
o
o
Q5: Why must rail-ends that have been torch-cut and have
cooled be cut back a minimum of 100 mm (a in) with
a rail saw?
o
o
Q6: When using a standard LP CJ OR AP CJ kit, why can
the maximum difference in rail height not exceed
3/16th in?
o
a
26
Trainee Worhbooh Module 1
Step 5: Rail-end Alignment
Alignment is the most difficult and critical procedure in
any thermite welding process
. In the alignment step, there are 4 sub-steps to correctly
align the rail-ends for a thermite weld:
- Gap
- Peak (also known as vertical alignment)
- Horizontal alignment
- Unequal cant between rail-ends
o They must be done in that order
Eyeballing the weld
. Before you begin the alignment procedure you must
assess the general leveL of the roadbed, looking for
problems such as:
- Hanging ties
- Low joints
Hot Tip!
If you do have hanging ties or a low joint, surface
the area before continuing with the alignment
procedure!
. Remove any splice bars as well as any spikes, anchors,
rail fasteners, tie pads or insulators for one or two ties to
either side of the weld location
. Next, 'eyeball'the alignment of the weld location by
bend.ing over the rail and sighting along the upper
fillet... the area just underneath the rail head on the
gauge side
27
TYainee Worhbooh Mod,ule 1
Step 5: Raíl-end Alígnment (cont'd,)
¡ Look to see if the peak of the rail-ends is:
- level
- high
- low
- unequal
figure 2 figure 3
figure 4 figure 5
¡ And finally, see if the horizontal alignment is:
tn
out
in-line
figure 6 figure 7
figure I
28
Trainee Worhbooh Mod,ule 1
Step 5: Rail-end Alígnment (cont'd,)
. Eyeballing the rail gives you important information on:
- what rail movement will be necessary to align the
rail-ends
- where to position wedges, spikes & track jacks to
achieve alignment
Gap
. Measure the gap at both sides of the rail head & base
. The gap can onl)' be: 25 mm (1 in)
not more than 28 mm (1-1l8 in)
25 to 28 mm
(1 to 1-1/8 inch)
figure 9
Caution!
Never add or remove steel to the rail length unless
otherwise directed, as it will affect the stress-free
temperature of the rail.
29
Trainee llorkbook
Module I
Step 5: Rail-end Alignment (cont'd)
Peak (Vertical Alignment): Wood ties
. Tap in 1 wedge und.er each side of each tie plate to
either side of the gap... just enough so that each tie
plate is snug up against the rail base
. Place a welder's straight-edge across the gap
centered on the running surface. The clearance
between the end of the straight edge and the running
surface is how you measure the'peak'
. Check the peak with a Starrett taper gauge. For
wood ties it must be 3.2 mm (1/8 in)
. Taking into consideration what you saw when you
eyeballed the rail-ends... and what the straight edge
indicates... adjust the wedges until you have the
correct peak at both ends ofthe straight edge
o or... adjust the peak using a 'rail raiser', if available
. If a rail-end is too high (without wedges), lower it by
jacking up the high rail with a track jack placed 8 to
12 ties back from the rail-end
Caution!
o Do not to 'hump'the track! Slack offspikes!
o The track jacks must remain in place until the weld has
cooled down below 370"C (700'F).
o Never step on the rail during alignment.
o Don't step on the ties in the weld area until after the pour,
3.2 3.2 mm (1/8 in)
figure 10
30
Trainee lï/orkbook
Module I
Step 5: Rail-end Alignment (cont'd,)
r:
Ll
t:
Horizontal Alignment: Wood ties
r Check both sides of the head, web & base for the
entire length of the straight edge across both railends
. If the head, web or base of one rail is wider than the
other, divide any difference in width equally, keeping
the straight edge parallel to the surface
c[ËÉcEÊËcI
tCr:CËËLÌrlrlLl
tlr=LlËËL:Ët*Ê
t: f:C
L C:t
Crl
* r::
tü
rlür:r:C:gL:tËË
Bür:t:CÊCrlC'l
¡
r: r:
*r:
l:C
ct
c
rl
I
c:
Ll
Ë
C
c
C:üLll:Ctlr:
ccËÉ*¡:Ë
ÊËcc**rl
DrltCL:tË
figure 11
t
Ê
rl
ü
r:
Ê
L1
L:
t::
L:
|] r::
C: E:
üË
Cü
tl
T:
t:
c
rl
c f
r:: Cr::L*
ËÊE:trÊ
ËL:ËËL:
L: r:: Ë Ll C:
n
L
n
figure
*Ctl
ÐrlL:
¡l Ll f:
r:C: ü
12
. Taking into consideration what you sa\M when you
eyeballed the rail-ends... and what the straight edge
indicates... determine which rail is out-of-line... and
to which side (gauge/field)
o Move the out-of-line rail back into alignment using
the tie plate. This is done by driving a spike straight
down at least half-way into the tie, against the
outside of the gauge or field side of the tie plate under
the out-of-line rail
t:
Ë c
f:
Ê I
Ê t:
figure 13
Caution!
. Do not hit the rail with the
hammer! Move the rail with
the tie plate.
. Do not drive the spike in at
an angle. It will cause the tie
plate to ride up on the spike!
31
Trainee l{orkbook
Module I
Step 5: Rail-end Alignrnent (cont'd)
. Check the horizontal alignment with a straight edge
against the gauge side of the base of the rails across
the gap
¡ To adjust the alignment, move the tie plate by
bending the spike in slightly, then tapping it down
further into the tie.
r Repeat this procedure until the base of the out-of-line
rail is back in-line
. In a curve, a rail positioner or gauge rods will make
the job easier
e If available, a 'rail alignment beam' will facilitate
peak and horizontal alignment on wood ties...
especially in curves or at level crossings
Unequal Cant Between Rail-ends: Wood ties
. Check the gauge side of the heads & bases across the
gap with a straight edge
. If the bases are aligned... but the heads are not,
unequal cant between rail-ends is present
r The rail with the head furthest out is the rail with
excessive cant
. Raise the spikes on that rail for a minimum of 12 - I5
ties back foom the rail-end, on the side with excessive
cant
32
Trainee Workbook
Module I
Step 5: RaíI-end Alignment (cont'd)
a
I
figure 14
¡ On the same side of the same rail, place a wedge
under a tie plate L2 - L5 ties back... to 'roll' the rail
back into alignment
. Hold a straight edge on the gauge side of the heads
and tap in the wedge until the heads align
. Re-check the gap, peak, horizontal alignment, and
unequal rail cant between rail-ends... and adjust
accordingly
. fn a curve, gauge rods will make the job easier
. If available, a rail canter placed 4 ties back from the
rail-end can be used to correct unequal cant between
rail-ends... instead of a wedge
Hot Tip!
Never try to adjust unequal cant between rail-ends at the
immediate weld location!
Concrete Ties
. The alignment process for rail-ends on concrete ties is
a bit different because there are no tie plates to
wedge... and you can't use spikes to adjust the
horizontal alignment
. To align the rail-ends on concrete ties, begin the
same way as you do for wood ties:
- eyeball the weld location
- verifu the gap
Ða)
Trainee Workbook
Module I
Step 5: Rail-end Alígnrnent (cont'd)
Peak: Concrete ties
. Make sure the tie pads have been removed, and place
a welder's straight edge centered on the running
surface of the rail, across the gap
. For concrete ties, the peak must be 1.6 mm (1/16 in)
at both ends of the straight edge
. Taking into consideration what you saw when you
eyeballed the rail-ends... and what the straight edge
indicates... position one wedge under the rail, on the
side that appears to be furthest out-of-line
. Do this on the first tie on both sides of the weld
location
o Adjust the wedges until you have the correct peak at
both ends of the straight edge, or...
. adjust the peak using a 'rail raiser', if available
. If a rail-end is too high (without wedges), lower it by
jacking up the high rail with a track jack placed a
minimum of 8 to 12 ties back from the rail-end
Caution!
o Be careful not to 'hump' the track. Remove the fasteners
if necessary.
o The track jacks must remain in place until the weld has
cooled down below 370"C (700'F).
1.6 6i 1.6 mm (1/16 in)
c:
t
* r:
t::
Ë
t
C rLl
Ê rC:
C:C
ËË rl
rlI úrl
figure l5
34
Trainee llorkbook
Module I
Step 5: Rail-end Alígnment (cont'd)
Horizontal Alignment: Concrete ties
o If either of the rails is out-of-line, remove the gauge
or field side rail fastener from the second tie from the
rail-end, and position a short wedge on its side
between the rail base and the cast hold-down
. Check the horizontal alignment with a straight edge
against the gauge side of the base of the rails across
the gap
. Tap the sideways wedge in or out to adjust the base
of the out-of-line rail
¡ If available, a 'raiL alignment beam' will facilitate
peak and horizontal alignment on concrete ties...
especially in curves or at level crossings
. A'rail positioner'can also be used in curves to
maintain horizontal alignment
t: C t D
Ë
rl rl
c
Ër
Ll !l
t: t:C ËÉ
c: cc ¡-L !l
rl
rl
r:t
tlttC|::t
t r-j
CCL:
figure 16
35
Trainee llorkbook
Module I
Step 5: Raíl-end Alisnment (cont'd)
Unequal Cant Between Rail-ends: Concrete
. Check the gauge side of the heads & bases across the
gap with a straight edge
¡ If the bases are aligned... but the heads are not...
unequal cant between rail-ends is present
. The rail with the head furthest out is the rail with
excessive cant
. On the side with excessive cant, remove the rail clips
one at a time, working awal¡ from the rail-end
o If the heads are not aligned after removing six rail
clips, tap in a wedge under the rail base 12 to 15 ties
back on the same side of the same rail... to'roll' the
rail back into alignment
. Re-check the gap, peak, horizontal alignment, and
unequal cant between rail-ends... and adjust
. If available, a rail canter placed four ties back from
the rail-end can be used instead of a wedge
rl ç t: I:I: t ¡l
@
figure 17
Hot Tip!
o An incorrect gap can result in a poor bond between the
rail-ends!
o Incorrect peak means the running surface will be too high
or low when the weld cools!
o Poor line will result in irregular gauge!
o When possible, roll rail in to maintain gauge
o ljnequal cant between rail-ends will promote fatigue weld
failure!
o Removing track jacks too early will result in a misaligred
weld!
36
Traìnee l4/orkbook
Module l
Step 5: Rail-end Alígnment (cont'd)
Questions
Ql: When you'eyeball'a weld location, what are you
looking for?
o
a
O
Q2: Why must you align the rail-ends in the order of
gap, peak, horizontal alignment, and unequal cant
between rail-ends?
o
Q3: Why must you check the gap?
o
a
Q4: Why is there a specific gap tolerance?
a
a
37
Trainee Workbook
Module I
Step 5: Rail-end Alígnment (cont'd)
Q5: Why must you set up a peak on the rail-ends?
a
Q6: Why is the peak for wood & concrete ties different?
a
Q7: When correcting unequal rail cant between railends
with a wedge, why must it be placed a
minimum of 12 to 15 ties back from the rail-end?
a
Q8: Why must the rail bases be aligned when correcting
unequal cant between rail-ends?
a
Q9: Why must gap, peak, horizontal alignment &
unequal cant between rail-ends be checked again
after any adjustment is made?
o
a
38
Trainee llorkbook
Module l
Step 6: Mold Preparation
o Protect mold from moisture
. Verifr LP or AP CJ kit contents
r Install support and clamp ass cj. Secure the mold clamp to
rail so that its arms are positioned as shown in FigurelS
when extended. W'hen welding short plugs, it is
recommended to place the clamp on the solidly fastened rail.
tI
I
a
I t
figure 18
-rE
¡ Cut a small notch in the top of matching edges of each halfmold
with hack saw blade (Figure 19). The notch should be
on the opposite side from the mold clamp assembly. This
makes an opening to let surplus molten slag fl.ow into slag
basin when weld is made.
fïgure 19
39
Trainee Workbook
Module I
o Place mold halves together on rail, and gently rub back and
forth against the rail so they seat properly and make good
contact at the top. Make certain all sand dust is removed
from the rail.
o Put each mold half in its frame and place on rail so that
mold is centered over gap. Be sure that faces of both rails
can be seen from the top of the mold looking down
(Figure 20). Secure to rail by tightening mold clamp screws.
Mold should not extend below rail. Grind if necessary to
remove excess by using the mold base plate or a fiIe.
fi¡5- Eri$
figure 20
¡ Place the mold base plate on the plate holder. Roll paste
into 25mm (1") cylinder and apply all around base plate.
Flatten to same thickness as base plate (Figure 21). Place
under mold halves and secure with hangers. Compact paste
on long edges with packing rod (Figurc 22). Press paste at
both ends with fingers.
a
figure 21 ftgure 22
40
Trainee Vlorkhook
Module I
. Tap base plate.
. Fill groove around the rail and between the mold halves
with paste (8 mm bead approximately) and press in firmly
with fi"ngers to avoid leaks. Then add a bigger bead of paste
(approximately 25 mm), again press firmly and smooth out
the paste surface (Figure 23). MAKE sURE No pAsrn DRops
INTO MOLD. NOrp: It is a good idea to cover mold opening
with cardboard during sealing operations to keep mold
cavity free of all foreign matter.
o Place slag basin on the rail under the opening in the mold.
Seal the joint between the basin lip and the mold with
additional paste (Figure 24). Line slag basin with dry
sand"/crushed mold
figure 23 figure 24
o Place dry sand on moist area under gap
4l
Trainee l4/orkbook
Module I
Step 6: Mold Preparation (cont'd,)
Centering the base plate
¡ When clamping the base plate in place under the mold
ensure it is centered on both sides of the mold.
Questions
Ql: Why must you examine the contents of a LP CJ or AP CJ
mold kit... even if the box is in good condition?
o
o
Q2: Why should you tap the base plate when mounting it to
the base of the rail?
o
Q3: Why must you check gap & alignment before installing
mold clamp ass cj
o
o
42
Trainee llorkbook
Module I
Step 6: MoId Preparation (cont'd,)
Q4: Why must you start packing a mold by smearing a small
amount of fusal paste in the crevice then back it up with a
larger amount?
o
o
Q5: Why must you rub the side molds on the rail?
o
Q6: Why is it important to center the side molds over the railends?
o
o
a
43
Trainee llorkbook
Module l
Step 7: Preheating
o Note & record the rail temperature
o Position & adjust the burner and its support stand onto the
rail. If necessary adjust centering screws so that the burner
is centered on the rail. This need only be done once for each
rail size. Position the burner on the stand so that t]rre nozzle
is centered on the gap (Figurc 25).
frgure 25
. Angle the nozzLe to the side to facilitate lighting
o Start the preheating motor
o Open the supply valve(s) to:
Mixture Air X'uel
Air/Propane 3.5 psi. 4-5 psi
Tip
You may have to increase the fuel pressure if the tanks are low or
cold.
44
Trainee Workbook
Moùile I
o Ignite the nozzle with a torch & reposition it
o Adjust the airlfuel supply for sound & flame height
Mixture
X'lame Heieht
Air/Propane
150 mm (6 in)
. Check that the heating colour on the 4 groove tops in the
mold is the same
o Start the stopwatch
o Make sure plug has been dried by heating over one riser for
10 - 15 seconds before the end ofthe preheat.
. Make sure both rail ends heat evenly until they are cherry
red, especially at the base. If one rail is heating faster than
the other, move the burner toward the hot rail. It may be
helpful to remove the burner to see the color of the rail. The
flame will resume when the burner is replaced.
o After removing the burner, shut the propane valve first and
then, stop the engine.
Hot Tip!
o Start the preheating stopwatch only after the flame has been
properly adjusted!
o Preheating time must be exactly 6 minutes for LP CJ
o Preheating time for AP CJ differs according to the type of rail and
process parameters. Ask Pandrol for assistance if required.
o Don't forget to heat the diverter plug on the edge of the mold...
where you won't forget it!
o Force gently the diverter plug into the gate!
45
Trainee Workbook
Module I
Step 7: Preheating (cont'd,)
Centering the Flame
¡ During the preheat, make sure that the flame is burning in
the mold... not just above the mold gates
o At the same time, you must verifii that the fl.ame is directed
straight down into the mold
*æ-
r
i
r
figure 26 frgure 27
Questions
Ql: Why is it necessary to note & record the rail temperature
before preheating the rail?
a
o
Q2: Why must you adjust the burner support stand & nozzle
in the gate position before lighting it?
o
Q3: Why should the burner nozzle be tilted slightly to the side
when lighting it?
o
46
Trainee Workbook
Module I
Step 7: Preheatíng þorut'd,)
Q4: Once the nozzLe is burning correctly, why is it important
to direct the flame straight down into the mold?
o
Q5: How do you check to make sure the flame is directed
straight down into the mold?
a
Q6: Why must you start the stopwatch only once the flame is
correctly adjusted?
a
o
Q7: Why must you constantly monitor the flame inside the
mold?
a
Q8: Why must the correct pressure on the fuel supply be
maintained?
a
Q9: Why must the diverter plug be heated?
a
47
Trainee Workbook
Module I
Step 8: Charge Preparation
o This step may be performed during the Preheating.
o Set up the crucible in a dry location
o Check the charge bag for signs of punctures or moisture
o Inspect the crucible for any damage or debris
. Verifu that the thimble is in place
o Open the bag and pour the contents into the crucible
o Stir the charge by hand and make a mound in the center
¡ Insert an ignition fuse and cover the crucible
o Place the packing boxes and charge bag in the disposal hole
Hot Tip!
Always veriflz that:
o the crucible is clean, free of defects with no cracks!
o the thimble is securely in place!
¡ the charge bag is sealed & dty... before opening!
48
Trainee Workbook
Module l
Step 8: Charge Preparatíorù (cont'd,)
Questions
Q1: What important step must be done after inspecting the
charge... but before opening the charge bag?
o
Q2: V[hy must the charge be stirred?
a
O
a
Q3: Why must the contents of a LP or AP CJ charge kit be
inspected before use?
o
o
a
49
Trainee l4torkbook
Module I
Step 9: Pouring
¡ Put on welder's goggles & gloves
o At 6 minutes remove the burner nozzle from the mold for LP
CJ weld
o Place the diverter plug snug into the top gate. Press down
firmly for good seal (Figure 28).
¡ Set the crucible on top. Twist the crucible either clockwise
or counter-clockwise locking the guide plates in place; this
ensures that the crucible is centered over the gap.
o While holding the cover open, Iight ignition fuse by touching
inside of mold.
r Insert ignition fuse at an angle into charge in crucible (to a
maximum depth of 25 mm or 1 inch), igniting the charge
(Figure 29).
!
Lr
¡,
figure 28 fi.gure 29
¡ Cover crucible. When reaction is complete and metal starts
to fLow, wear dark glasses for protection.
o When the slag stops pouring, start the stopwatch
50
Trainee l4/orkbook
Module I
Preheater shutdown
¡ While the crucible is being positioned and the charge
ignited, shutdown the preheater by:
- first shutting off the fuel supply
- then stopping the compressor
Hot Tip!
o Never shut-off the fuel supply to the burner while it is still
positioned in the mold!
¡ Place the ignition fuse only 25 mm (1 in) into the charge!
o The stopwatch must be started exactly when the last bit of slag
drips out of the mold!
51
Trainee ll'orkbook
Module l
Step 9: Pouríng ftont'd,)
Questions
Ql: What protective equipment must a welder be wearing
before igniting the charge?
o
o
Q2: Why must you stop the preheat for a LP CJ at exactly 6
minutes?
o
o
Q3: Why must the burner nozzle be removed from the mold
before the fuel supply is shut offl
a
Q4: Why must the diverter plug be in place?
o
Q5: Why must the ignition fuse be placed only 25 mm (1 in)
into the charge?
a
52
Trainee l(orkbook
Module I
Step 10: Demolding & Shearing LP CJ weld
At 4 minutes after the pour:
o Remove crucible using a crucible fork
o After slag solidifies (approx. 3 min.) remove slag basin and
dump in safe, dry place where workmen will not come in
contact with it. Keep it away from flammable material or
fire may result. CAUTION: AVOID DUMPING ON
DAMP GROUND OR IN WATER AS AN EXPLOSION
MAY RESULT. Place slag basin in safe place for cooling.
Caution workmen against touching or stepping on it.
Remove the mold clamp, mold jackets and base plate
o At 5 minutes after the pour
¡ After about 5 minutes, slowly release base plate retaining
mechanism (Figure 30).
¡ Release mold clamp screws. Remove mold frames and mold
clamp assembly (Figure 31).
t
figure 30
figure 3l
53
Trainee l(orkbook
Module I
. With a hot cut chisel, score the outside of mold at top of rail,
then with shovel on one side of mold, push mold slowly with
chisel into shovel (Figure 32) and place into a disposal hole.
If metal runs when the top of the mold is broken, maintain
the mold in place and wait a few more seconds.
o Remove any dry fusal paste from running surface
At,5-1.12 minutes after the pour
¡ Immediately after the mold has been broken a\ñ¡ay, cut off
surplus metal on rail head. There are two ways to do this:
1) With hot cut chisel and sledge hammer (Figure 33).
Avoid cutting into rail head or metal in the weld below
running level of rail. 2) With the Matweld weld shear
(Figure 34). This removes excess metal quickly and safely.
No more accidents due to metal splinters.
t
figure 32
figure 33
54
Trainee llorkbook
Module I
figure 34
¡ Nick risers at the bottom \ /ith chisel while still hot
(Figure 35). When cold, they can be easily broken away.
figure 35
Danger!
Hot Tip!
o CAUTION: If a rail expander has been used, do not release
pressure until the weld is sufficiently cool to avoid hot tears.
o Bend the base risers over so they are clear of the profiIe
der
o Carry the slag basin level so that hot weld material will not spill
out!
¡ Never dispose of hot weld material in water!
¡ Do not place a hot slag basin on a concrete tie!
¡ Do not empty the contents of the slag basin into the disposal hole
until it has cooled!
o Make sure the shear is ready!
¡ Demold at 5 minutes!
o Shear at 5-Il2 minutes!
55
Trainee Workbook
Module I
Step 10: Demolding & Shearing (cont'd,)
Questions
Ql: Why should the mold never be removed before 5 minutes?
O
Q2: Why should the head of the mold never be sheared before
5Il2 minutes?
a
Q3: What are the signs of a 'hot tear'?
o
56
Trainee l(orkbook
Module I
Step 11: Hot Grínding
o Put on personal protection equipment
- Face shield
- Hearing protection
- Respirator
- Leggings
o Grind weld metal to 0.8 mm (1/32 in) from rail steel
o Grind contour radius flush or blend-in
o Grind gauge and field side flush or blend-in
How Close?
o When hot grinding, it is important to leave at least 0.8
mm (1/32 in) of the weld metal on the running surface above
the rail steel
o If you grind the weld metal flush with the rail steel when
the weld is still hot, you will have a low weld when it cools
o Remove the wedges 15 minutes after the pour to allow the
weld to cool to level
¡ If track jacks were used to lower the rail-ends, they can be
removed 30 minutes after the pour
figure 36
figure 37
Hot Tip!
Keep your distance from the rail steel!
57
Trainee V[orkhook
Module I
Step 11: Hot Grinding (cont'd,)
Questions
Ql: What is the very fi.rst step in hot grinding?
a
Q2: At what time can you start hot grinding?
o
Q3: Why should you never grind the weld metal any closer
than 0.8 mm (L132 in) to the rail steel?
o
Q4: Why should the wedges be removed 15 minutes after the
pour?
o
58
Trainee llorkbook
Module I
Step 12: CoId Grínding
o Make sure the base risers have been removed
After t hour
o Eyeball the peak
o Finish grinding after weld cools to air temperature. Grind
until full length of 1 meter (3 feet) straight edge contacts rail
on running and vertical surfaces of rail head (Figure 38).
CAUTION: Trains should not run on track until rail has
cooled to less than 375" C (700" Ð.
I
a
figure 38
Hot Tip!
Take your time. Do not'blue'the weld!
59
Trainee llorkbook
Module I
Questions
Ql: Why must the base (inner) risers and mold material be
removed from the web & base?
a
Q2: How close can you cold grind weld metal to the rail steel?
o
Q3: Why should you avoid'blueing'the rail when cold
grinding?
o
Q4: Why veri$' the weld by checking it with a straight edge &
'eyeballing' it... after grinding?
o
Q5: What are the high low-low tolerances for cold grinding?
o
60
Trainee Vl/orkhook
Module I
Step l3: Fínishíng
¡ Visually inspect the weld
o Tamp 2 ties to each side of the weld... and any others that
need to be tamped
o Plug wood ties & replace all rail fasteners and-/or insulators
¡ Recheck rail level with 1 meter (3 feet) straight edge to
insure level surface.
o Locate all hot metal (slag, cut-offs, etc...) and put in sage location to
safeguard from fires.
o Collect all refuse for disposal (boxes, plastic bags, etc...).
o Fill in the disposal hole
o Load tools, thermometer, etc.
o Stamp and install the welding tag
¡ Complete the welding documentation
o Clear aII equipment & personnel from the site
o Cancel track protection once you are in the clear
Questions
Ql: Why must you inspect a weld once it is finished?
o
o
a
Q2: What information must be included on the welding
documentation form?
1
2
3
Ð
6
7
4
61
Trainee l|/orkbook
Module I
Q3: What is the last thing you do before leaving the job site?
a
62
Trainee Workbook
Module I
Exception Conditíons
There are situations where rail condition, different types of
metallurgy, or even temperature will require variations in the
standard LP CJ or AP CJ welding procedures. The most
common are:
o Partly worn rail where the difference in the wear of the head
width & height results in an uneven surface on the head,
gauge or freld side
¡ Cold weather conditions
o The use of rail expanders
o Afreeze-up (when a charge does not pour)
Worn rail
o In the case of unequal head width, the solution is to:
- Align the base & web of the rail
- When grinding after the weld, blend-in the field & gauge
side to line
o In the case of unequal rail height, less than 3/16th in, the
solution is to:
- Align the running surface and offset the height
difference in the base of the rail
DiffÉfi:ncè
ln He.:d
Webs
Båsss
figure 39 figure 40
63
Trainee Workbook
Module I
E xceptíon Conditions (cont'd,)
Difference in rail height greater than 3/16th in
There are limits to the acceptable difference in the height of the
two rail-ends.
¡ The difference in the height of the heads cannot exceed 3/16th
in
o If the difference is greater than 3/16th use the appropriate
compromise kit
Figure 41
Peak Adjustments
o As the rail gets colder, the rail needs more of a peak to
compensate for the increased tension placed on the weld as it
cools, pulling it down
o Therefore there are exceptions to the 1.6 mm to 3.2 mm (1/16
in to 1/8 in) peak rule... under extreme temperature conditions
+ +
figwe 42
64
Trainee Workbook Module 1
Exception Conditions (cont'd,)
Cold Weather Conditions
o Cold weather is defined as:
- Windy or precipitation (snow or rain)
- Temperature below 15'C (60'F)
Warm-up Procedure
o If the rail temperature is below 15'C (60"F), the rail must be
warmed up with a turbo-torch to 37"C (100"F) before or during
the pre-heating procedure
o The length of rail that you must preheat (measured to either
side of the mold) varies according to the rail temperature
Rail Temp
+15'C (60'F) to -9'C (16'F)
Lensth of rail to warm
76 cm (30 in) to 91 cm (36 in)
- 9"C (16"F) to -15"C (5'F) 91 cm (36 in) to 122 cm (48 in)
-15"C (5'F) or lower
I22 cm (48 in) minimum
table I
Cooling Procedure
o During cold weather conditions, there is also a risk that the
weld will cool-down too fast
o If the ambient temperature is below 15"C (60'F)... or if it is
extremely windy or rainy... cover the weld immediately after
shearing with a shovel and a heat retarding blanket or a
shield for at least 10 minutes before grinding
65
Trainee Workbook
Module I
Exceptíon Condítions (cont'd,)
Post-weld Procedure: Rail Expanders
¡ In the event that you are using rail expanders, you can only
remove them once the rail temperature has dropped below:
Stress
Tension
Compression
Temperature
370"C (700.F)
600'c (1100"F)
Emergency Procedure: Freeze-up
One rare and potentially dangerous situation that you may
encounter is a freeze-up... a condition where the charge ignites,
but the weld doesn't pour out within a minute.
o If this happens:
- Leave the crucible where it is and clear the weld site
- Return after the crucible has discharged & clean up
- Cut out the weld and cut in a closure rail
End of Module I
66
Tlainee Workbook Module 2
ule 2
Hands-On LP CJ &AP CJ Weld
67
Trainee Worþ,book
Mod,ule 2
Hands-On LP CJ & AP CJ WeId
Procedure
Work in teams of three:
o One observer who's job is to:
- Help prepare the necessary tools & material
- Monitor the progress of the two welders making sure:
' they follow the correct procedure
' they work safely through all stages
¡ Two welders who will work as a team to perform a LP or AP
CJ weld
Your work must be verified at critical'check-points' by the
instructor before:
1. Mold Preparation
- make sure the track is secure
- check the condition of the rail-ends
- check alignment
2. Preheating
- check the mold & preheat set-up
- verifiz weld shear & grinder are operational
- monitor starting & adjustment of preheater
3. Igniting the Charge
- check preheat & charge
- monitor ignition & pour
- watch for a run-through
4. Demolding and Shearing
- monitor demolding & shearing
- look for a'hot tear'
5. Cold grinding
- check hot grinding depth & alignment
- verifiz that wedges are removed at 15 minutes
Caution!
Do not proceed beyond these 5 'checkpoints' until you
have been checked out by the instructor and given the
'go-ahead' to continue.
68
Tlainee Workbook
Mod.ule 2
Hands-on LP CJ &AP CJ Weld (cont'd)
Note: Because the weld has to cool approximately one hour
before cold grinding can be done, cold grinding will not be done in
this hands-on exercise.
Once your hot grinding work has been checked, return the track
to standard and clean-up your work-site.
. At each of the 5'checkpoints', you will be asked to verifr:
1. Mold
I Track secure:
- sufficient anchors
- anchors tight against ties
- match marks.
r Rail-end condition:
- no foreign welding material
- rail-ends square & perpendicular
- clearance from ties, bolt holes, ballast
o Alignment:
gâp
peak (vertical alignment)
horizontal alignment
unequal cant between rail-ends
69
Tla,inee Worþbook
Module 2
Hands-on LP CJ &AP CJ Weld (cont'd)
2. Preheating
o Side molds correctly aligned:
- to each other
- to the gap
o Side molds correctly secured
o Base plate coruectly prepared with fusal paste, straight
and centered,
¡ Apply additional fusal paste:
- rail base, web & head
- joint between side of mold and slag basin
- ensure no excess paste inside mold (inspect with
flashlight)
o Slag basin in place w/ dry sand & diverter plug
o Preheating burner properly positioned
o Weld shear and grinder are operational
3. Ignite Charge
r Preheater is heating correctly
¡ Diverter plug heating on edge of mold
¡ Charge prepared in crucible & close by
¡ Ignition fuse in place
¡ Demolding tools ready nearby
¡ Personal protective equipment on
4. Demolding & Shearing
o Remove side plates, base plate and mold clamps at 4
minutes
o Demold at 5 minutes
o Shear at5Il2 minutes
¡ Check for'hot tear'
70
Trq,inee Workbook Module 2
Hands-on LP CJ 82, AP CJ Weld (cont'd)
5. Cold Grinding
o Weld:
- head cut & cleared
- risers removed
r Hot grind:
- no grinding of rail steel
- head contour to gauge & field side
- gauge & freld side flush and/or blended
Tip
Follow the procedure in your Job Aids and remember the
key to CASTing a good weld: Consistency, Accuracy,
the right Sequence of $teps and Tirning.
Evaluation
o Once you have all fi.nished, you will be evaluating another
team's work... based on the criteria that was established in the
course.
¡ When the exercise is frnished, help clean up the weld sites and
return/store the tools.
End of Module 2
7t
Instructor Guide
Module l
Step 2: Site Preparat¡on
Q1: Why must you check to see if the ballast below the
weld area and at the disposal hole is free of
moisture, snow or frost?
. lf any moist ballast comes in contact with molten
slag or sfeel it will explode and/or splatter hot
weld material
Q2: What precaution should you take when welding on
multi-track territory?
. Depending on the type of protection, a Safety
Watch may be necessary to ensure that
employees do not foul live track
Q3: Why are obstacles near the weld area a safety
hazard?
. Obstacles rncrease the risk of an accident :
- when handling hot weld material,
- when clearing the site in the event of an
u n stopp able r u n -th ro u g h
Q4: Why is welding near a level crossing considered a
safety hazard?
. A Safety Watch may be necessary to direct traffic
or protect employees from traffic
Step 3: Track Preparation
oÃ
Q1: Why must you eyeball the joint?
. lndicates what kind of line & surface the track has
at the weld e.g. is it high, Iow, in , out or level
. Determine if there is sufficient ballast section
. lt will help with rail-end alignment later
Q2: Why must you put the thermometer on the rail now,
and not later?
. The thermometer has to be on the railfor at least
10 minutes to get an accurate reading
. The railtemperature determines if a railwarm-up
is necessary
72
Instructor Guide
Module I
Step 4: Rail-end Preparation
Q3: Why should you check the branding and stamping
on both rail-ends now?
. Make sure that both rail-ends are compatible with
the weld kit before preparing the rail-ends
Q4: Why must the rail gap be at least 100 mm (a in)
from the nearest tie?
. Need room for the base plate
. Room for packing fusal paste around the base
plate
Q5. What can you do to make sure the gap doesn't
change while you are setting up the weld?
. Tighten anchors
. Make match marks
. Use hydraulic rail expanders, if required
Q6: What must you do when making match marks on
wood ties?... concrete ties?
. Wood:
- Mark base of railto tie plate
- Mark tie plate to tie
- Tie must be unanchored. or the tie may move
with the rail-
. Concrete:
- Mark base of railto tie
- Clips must be removed. or the tie may move
with the rail
Q7: Why should you check out the weld shear & grinder
now?
. Check shear jaws for sharpness & setting
. Make sure grinder has good grinding sfone
. Lasf chance to verify that shear & grinder are in
working order before the track is put out of service
Q1: Why can't a rail-end, that has been built up by gas
or electric welding, be thermite welded?
. Different metals present
. Thermite materialwill not bond correctly
73
Instructor Guide
Module I
Q2: Why must the rail-ends be free of defects and
foreign material?
. May result in a defective weld
Q3: Why must the rail-ends be square & perpendicular?
. Even heating
. Even distribution of metal during the pour
Q4: Why must all drilled holes be a minimum of 100 mm
(4 in) away from the rail-end?
. Cannot be tested ultrasonically if too c/ose
. Any closer may cause a defective weld or rail
Q5: Why must rail-ends, that have been torch-cut and
have cooled, be cut back a minimum of 100 mm (4
in) with a rail saw?
. Rapid heating & cooling from a torch cut may
result rn sfress cracks
. Removes a// sfress cracks created by torch cutting
Súep 5; Rail-end Alignment
Q6: When using a standard kit, why must the maximum
difference in rail height not exceed 3116 in?
. lf difference in rail height exceeds 3/16 in, the
standard mold will require too much fusal paste.
This could result in a run-through
. A Compromise Rit must be used
Ql: When you 'eyeball' a weld location, what are you
looking for?
. Hanging fies & low joints
. What rail movement willbe necessary to align the
rail-ends
. Where to position wedges, sprkes & track jacks to
achieve alignment
Q2: Why must you align the rail-ends in the order of
gap, peak, horizontal alignment, and unequal cant
between rail-ends?
74
Instructor Guide
Module I
. /f is the quickesf & mosf efficient way of achieving
correct alignment
Q3: Why must you check the gap?
. Make sure you have the required distance
between the rail-ends
. lt could change during the alignment procedure
Q4: Why is there a specific gap tolerance?
. Too wide: insufficient preheat temperature and
weld material
. Too narrow: rail heads too hot, ral öases not hot
enough, weld material overflow
Q5: Why must you set up a peak on the rail-ends?
. More metal in head area than web & óase so if
contracts more as rT cools, pulling down the weld
to levelwhen it returns to its originaltemperature
Q6: Why is the peak for wood & concrete ties different?
. Wood has more'give'than concrete, so the weld
drops more when cooling
Q7: When correcting unequal rail cant between railends
with a wedge, why must it be placed a
minimum of 12to 15 ties back from the rail-end?
. Any closer will affect peak & horizontal alignment
Q8: Why must the rail bases be aligned when correcting
unequal cant between rail-ends?
. Unequal canted rail may result in fatigue weld
failure
Q9: Why must gap, peak, horizontal alignment &
unequal cant between rail-ends be checked aqain
after any adjustment is made?
. Loosening/removing more fasteners can affect the
gap
. Adjusting unequal cant between rail-ends may
affect peak & horizontal alignment
Step 6: Mold Preparation
75
Instructor Guide
Module l
Q1: Why must you examine the contents of a mold kit,
even if the box is in good condition?
. Damage to mold parts
. Sþns of moisture on mold
Q2: Why should you tap the base plate while mounting it
to the base of the rail?
. Make sure it fits properly (snug)
Q3: Why must you check gap & alignment again after
the base plate & brick are clamped on?
. Clamp can disturb alignment
. Lasf chance to check alignment before side molds
are positioned
Q4: Why must you start packing a mold by smearing a
small amount of fusal paste in the crevice, then
back it up with a larger amount?
. Small amount forms a fine seal
. Large amount backs up initial seal
Q5: Why must you rub the side molds on the rail?
. Adjusts each side mold to the minor differences ìn
rail suffaces. Better fit
Q6: Why is it important to center the side molds over the
rail-ends?
. They will be centered over the base plate
. lf the mold is off center, molten steelwill not be
distributed equally... causing defects
. lf mold is off center, rail-ends will not preheat
equally... causing defects
Step 7: Preheating
Q1: Why is it necessary to note & record the rail
temperature before preheating the rail?
76
Instructor Guide
Module l
. C/osesf record of the ra¡ltemperature at the time
of the pouring of the weld
. To determine whether or not the rail-ends have to
be warmed
Q2: Why must you adjust the burner support stand &
nozzle in the gate position before lighting it?
. Less adjustmenfs once the nozzle is lit achieves
the correct flame and temperature faster
Q3: Why should the burner nozzle be tilted slightly to
the side when lighting it?
. Makes it easier to light
Q4: Once the nozzle is burning correctly, why is it
important to direct the flame straight down into the
mold?
. Flame entering at an angle will not heat the railends
and mold uniformly... resulting in hot & cold
spofs
Q5: How do you check to make sure the flame is
directed straight down into the mold?
. Verify that the heating colour r.s fhe sarne on all
four groove tops
Q6: Why must you start the stopwatch only once the
flame is correctly adjusted?
. lf you do not have the correct flame temperature, it
will not heat the rail-ends to the correct
temperature during the 6 minute preheat
. lf flame rb nof correctly adjusted, it could go out
Q7: Why must you constantly monitor the flame inside
the mold?
. lf flame ts nof correctly adjusted, it may burn only
above the mold gafes... and not inside
Q8: Why must the correct pressure on the fuel supply be
maintained?
77
Instructor Guide
Module I
a
Correct pressure will deliver correct flame
temperature & will heat rail-ends to correct
temperature in 6 minutes
Súep 8; Charge Preparation
Sfep 9; Pouring
Q9: Why must the diverter plug be heated?
. To remove moisture... which will cause molten
steelto splatter during the pour
Ql: What important step must be done after inspecting
the charge... but before open¡ng the charge bag?
. Transfer the charge tag from the bag to the
welding report form
Q2: Why must the charge be stirred?
. Detect any lumps... which indicate moisture
. Mix any elements that may have settled
. Make a mound on the charge surface to get a
smoother reaction when ignited
Q3: Why must the contents of a kit be inspected before
use?
. Charge bag must not be punctured or moist
. Crucible must not be damaged
. Thimble must be in place
Q1: What protective equipment must a welder be
wearing before igniting the charge?
. Welder's g/oves & goggles
Q2: Why must you stop the preheat at 6 minutes?
. Insufficient preheat will cause defects... resulting in
a poor bond
. Excessive heat can cause run-through
78
Inslructor Guide
Module I
Q3: Why must the burner nozzle be removed from the
mold before the fuel supply is shut off?
. The cold air from the cornpressor will cool-down
the hot rail-ends.
Step 10: Demolding & Shearing
Step l1: Hot Grinding
Q4: Why must the diverter plug be in place?
. The diverter plug ensures the proper flow of
molten steel into the mold
Q5: Why must the ignition fuse be placed only
25 mm (1 in) into the charge?
. lf placed too deep, the charge reaction will be
abnormal, activating the thimble to release the
molten sfee/ foo soon
Ql: Why should the mold never be removed before 5
minutes?
. Too rapid cool-down will result in a defective weld
(it will be too brittle)
. Possib/e mold leakage on side
Q2: Why should the head of the mold never be sheared
before 6 1/2 minutes?
. Metal will be too soft, resulting in a 'hot tear'
Q3: What are the signs of a 'hot tear'?
. Small lateralfissures on gauge, field and running
surface
Q1: What is the very first step in hot grinding?
. Put on personal protection equipment
Q2: At what time can you start hot grinding?
79
Instructor Guide
Module l
lmmediately after shearing... unless you have cold
weather conditions or must post-heat the rail
Q3. Why should you never grind the weld metal any
closer than 0.8 mm (1132 in) to the rail steel?
. As the weld continues to cool, it willfall by
approximately that amount, leaving a low weld
Q4: Why should the wedges be removed 15 minutes
after the pour?
. The weld must be allowed to coolto level
Step l2: Cold Grinding
Q1: Why must the base (inner) risers and mold material
be removed from the web & base?
. lf there is a break at the weld, the nsers can bridge
the track circuit, and the block won't'drop'
Q2: How close can you cold grind weld metal to the rail
steel?
. Flush ... blending it in if necessary
Q3: Why should you avoid 'blueing'the rail when cold
grinding?
. Affects the microstructure of the running surface
Q4: Why should you verify the weld by checking it with a
straight edge & 'eyeballing' it... after grinding?
. Check fo see if it is 'high' or 'low'
. Use that information to adjust the peak on your
next weld
Step 13: Finishing
Q5: What are the high-low tolerances for cold grinding?
. 0.25 mm (0.01 in) high,0low
Q1: Why must you inspect a weld once it is finished?
. Look for sþns of 'hot tears'
. Look for visual defects
. Check alignment
80
Instructor Guide
Module I
Q2: What information must be included on the welding
documentation form?
. D"y, month, year
. Weld LD. number
. Charge tag
. Location (mileage)
. Welder number
. Railtemperature
. Weather conditions (under'Comments')
Q3: What is the last thing you do before leaving the job
site?
. Make sure the sife is clean & clear of allequipment
& material and safe for traffic
8t
InstrucÍor Guide
Name- PIN Date Score
Quiz 1: The LP CJ or AP GJ Welds
QI
Name four items of personal protection equipment that must be worn when
grinding.
1
2.
3.
4.
Q2
What two types of gauges must be included on your Measurinq Tools
checklist?
1
2
Q3: Welds must not be located over ties.
a) True
b) False
Q4: Anchors must be tightened for a minimum of _ to either side of the
rail-ends.
a)
b)
c)
d)
sm(15ft)
10 m (30 ft)
15 m (50 ft)
33 m (100 ft)
Q5: A tie must be a minimum of _ from the rail gap.
a) 75 mm (3 inches)
b) 100 mm (4 inches)
c) 125 mm (5 inches)
d) 150 mm (6 inches)
I
InsÍructor Guide
Q6:AnydrilledhoIemustbenoGloserthan-fromtheendoftherail.
a) 75 mm (3 inches)
b) 100 mm (4 inches)
c) 125 mm (5 inches)
d) 150 mm (6 inches)
Q7: During what step should the operation of the hydraulic weld shear be
checked?
a) Pouring
b) Preheating
c) Preparing the mold
d) Rail-end alignment
e) Rail-end preparation
Q8
Which of the following conditions require that the rail-end be cut back
beyond the defect, and a closure rail be cut in?
(More than one answer may be correct)
a) Crack in rail-end or bolt hole
b) Rail-end batter
c) Repair welding on rail-ends
d) Horizontal split head
e) Vertical split head
Q9
Burrs, flow, paint, oil, rust & scale must be removed for a minimum of
from the rail-ends?
a)
b)
c)
d)
e)
25 mm - 50 mm (1 to 2 inches)
50 mm - 100 mm (2to 4 inches)
100 mm - 150 mm (4 to 6 inches)
150 mm - 200 mm (6 to 8 inches)
200 mm - 300 mm (8 to 12 inches)
Ql0: Which following rail-end gaps would not be acceptable for a standard LP
CJ or AP CJ thermite weld?
a) 22 mm (7/8 inch)
b) 25 mm (1 inch)
c) 28 mm (1-1l8 inch)
2
Inslructor Guide
Ql1: On wood tie territory, what is the standard peak measured at each end of a
welder's straight edge?
a) 0.8
b) 1.6
c) 3.2
d) 6.4
mm (1/32 inch)
mm (1/16 inch)
mm (1/8 inch)
mm (1/4 inch)
Q12: Throughout the weld area, rail-ends must be horizontally aligned for at
least
a)
b)
c)
d)
0.5 m (18 inches)
1.0 m (3 feet)
1.5 m (4.5 feet)
2.0 m (6.0 feet)
Q13: To correct unequal cant between rail-ends, how far back from the gap must
the spikes be pulled and a wedge inserted?
a)4
b)8
c)1
d) 1
to 7 ties
to 11 ties
2to 15 ties
6 to 20 ties
Q14: You open both boxes of a weld kit and find the following components. One
important component is missing. What is it?
. 2 half molds
. 1 bottom brick
Missing:
' 1 welding charge in sealed package
. 1 CJ crucible & thimble
.1 CJ cover
Ql5: What is the correct 4!¡
pressure for an airlpropane preheat?
a)
b)
c)
3.0 psi
3.5 psi
pst
4to5
a
-t
Instruclor Guide
Q16: When us¡ng propane as a preheating fuel, how high must the flames extend
out of the riser holes?
a
b
c)
50 mm (2 inches)
100 mm (4 inches)
150 mm (6 inches)
Q17: During the preheating procedure, when must the stopwatch be started?
a) As soon as the preheating unit is started
b) As soon as the torch burner head is lit
c) As soon as the flame height & the sound is correct
Q18: How long must the rail-ends and mold be heated to achieve the correct preweld
temperature?
a) 3-112 minutes
b) 6 minutes
c) I minutes
d) 10 minutes
Ql9: lf a charge bag has clearly been punctured, but there are no signs of
moisture, can the charge still be used?
a
b
Yes
No
Q20: To time the cooling period, when must the stopwatch be started?
a) When the charge is ignited
b) When the charge begins to pour
c) When the slag begins to run into the slag basin
d) When the slag stops running into the slag basin
4
Instruclor Guide
Q2l: What p¡ece of personal protective equipment ¡s worn exclus¡vely during the
pour?
a) Leggings
b) Respirator
c) Welder's goggles
d) Face shield
Q22: At what time after the pour can demolding begin?
a) 3-112 minutes
b) 5 minutes
c) 8 minutes
d) 10 minutes
e) 15 minutes
Q23: At what time after the pour can the wedges be removed?
a)
b)
c)
d)
10 minutes
15 minutes
20 minutes
30 minutes
Q24: When cold grinding, what is the tolerance for the running surface of the
weld?
a)0
b)0
c)0
d) 0
25 mm (0.01 inch) high and 0.25 mm (0.01 inch) low
25 mm (0.01 inch) high and nothing low
37 mm (0.015 inch) high and 0.25 mm (0.01 inch) low
37 mm (0.015 inch) high and nothing low
5
Inslructor Guide
Quiz 2: Exception Conditions
Qf
When measuring the difference in rail height between the two rail-ends at
the gap, what is the maximum acceptable difference for a standard LP CJ
or AP GJ thermite weld kit?
a)
b)
c)
d)
3/16 inch
1/16 inch
1/8 inch
114 inch
Q2
Above what temperature is it p! necessary to protect a hot thermite weld
with a heat retarding blanket or shield?
a) 15"C (60'F)
b) 10.c (50.F)
c) 5'C (40'F)
d) 0"c (32.F)
Q3: How long must a heat retarding blanket or shield be kept on?
a) At least 3-112 minutes
b) At least 5 minutes
c) At least 10 minutes
d) At least 20 minutes
Q4: Above what rail temperature is it not necessary to use a turbo-torch to
warm up the rail-ends before preheating?
a)1 5.C (60"F)
b)1 0.c (50.F)
c) 5"C (40.F)
d) 0.c (32.F)
Q5
When required, to what temperature must the rail-ends be warmed up to,
before the preheating procedure?
a) 37"C (100'F)
b) 67.C (150"F)
6
Instructor Guide
c) 93.C (200.F)
7
Inslructor Guide
Q6: When under tension, the rail must cool down to what temperature before
the hydraulic rail expanders can be removed?
a) 370"C (700.F)
b) 425C (800.F)
c) 480"C (900.,F)
d) 600.c (1100.F)
Q7: lf a charge ignites, but does not pour out, how must you respond to the
'freeze-up' cond ition?
a) Carefully lift the crucible with the CJ fork & put it gently in the disposal hole
b) Leave the crucible where it is and evacuate the weld site
I
Inslructor Guide
Quiz Administration
Quiz l:
QT
Name four items of personal protection equipment that must be worn when
grinding.
1.
2.
3.
4.
5.
6.
Hearing protection
Respirator
Face shield
Leggings
Eye protection
Welder's gloves
Q2
What two types of gauges must be included on your Measurinq Tools
checklist?
1
2
Starrett taper gauge
Rail wear gauge (rail profile gauge)(head loss gauge)
Q3: Welds must not be located over ties.
a) True
b) False
A3: A weld must never be positioned over a concrete or wood tie
Q4 Anchors must be tightened for a minimum of _ to either side of the
rail-ends.
a) 5m(15ft)
b) 10 m (30 ft)
c) 15 m (50 ft)
d) 33 m (100 ft)
A4
Anchors must be tightened for a minimum of 15 m (50 ft) to either srde of the railends,
otherwise the rail(s) could move, changing the gap.
I
Instructor Guide
Quiz Administration
Q5: A tie must be a minimum of from the ra¡l gap.
a)
b)
c)
d)
75 mm (3 inches)
100 mm (4 inches)
125 mm (5 inches)
150 mm (6 inches)
A5
A tie must be a minimum of 100 mm (4 inches) from the ra¡l gap, to provide
sufficient room for the mold assembly.
Q6:AnydrilledhoIemustbenocloserthan-fromtheendoftherail.
a) 75 mm (3 inches)
b) 100 mm (4 inches)
c) 125 mm (5 inches)
d) 150 mm (6 inches)
A6
Any drilled hole must be no closer than 100 mm (4 inches) from the end of the
rail, otherwise it cannot be accurately tested.
Q7
During what step should the operation of the hydraulic weld shear be
checked?
a) Pouring
b) Preheating
c) Preparing the mold
d) Rail-end alignment
e) Rail-end preparation
A7= ldeally, the operation of the hydraulic weld shear should be checked during railend
preparation before aligning the rail-ends because if the weld shear is placed
on the rail (to check the jaw size & set-up), it could alter the alignment.
2
Instructor Guide
Quiz Administration
Q8
Which of the following conditions require that the rail-end be cut back beyond
the defect, and a closure rail be cut in?
(More than one answer may be correct)
a) Crack in rail-end or bolt hole
b) Rail-end batter
c) Repair welding on rail-ends
d) Horizontal split head
e) Vertical split head
A8
All of the listed conditions require that the rail-end be cut back beyond the defect,
and a closure rail of no /ess fñan the minimum specified length be cut in.
However, if a vertical split head is discovered in a string of CWR, the entire
length of railwith the same heat number, ingot number and rail letter must be
removed from the track... including any butt welds.
Q9: Burrs, flow, paint, oil, rust & scale must be removed for a minimum of
from the rail-ends?
a) 25 mm - 50 mm (1 to 2 inches)
b) 50 mm - 100 mm (2 to 4 inches)
c) 100 mm - 150 mm (4 to 6 inches)
d) 150 mm - 20O mm (6 to 8 inches)
e) 200 mm - 300 mm (8 to 12 inches)
A9: Burrs, flow, paint, oil, rust & sca/e must be removed for a minimum of 100 mm -
150 mm (4 to 6 inches) from the rail-ends... the approximate area the molds
cover.
Q10: Which following rail-end gaps would not be acceptable for a standard LP
CJ or AP CJ thermite weld?
al 22 mm (7/8 inch)
b) 25 mm (1 inch)
c) 28 mm (1-1l8 inch)
3
Instructor Guide
Quiz Administrafion
Ql l: On wood tie territory, what is the standard peak measured at each end of a
welder's straight edge?
a) 0.8 mm (1/32 inch)
b) 1.6 mm (1/16 inch)
cl 3.2 mm (1/8 inch)
d) 6.4 mm (1/4 inch)
Al l: On wood tie territory, the standard peak measured at each end of a welder's
straight edge ts 3.0 mm (1/8 inch). lt is only 1.5 mm (1/16 inch) on concrete ties
because they have /ess þive' than wood ties.
Ql2: Throughout the weld area, rail-ends must be horizontally aligned for at
least
a) 0.5 m (18 inches)
b) r.0 m (3 feet)
c) 1.5 m (4.5 feet)
d) 2.0 m (6.0 feet)
412: Rail-ends must be horizontally aligned for at least 1.0 m (3 feet) throughout the
weld area... the length of a welder's straight edge.
Q13: To correct unequal cant between rail-ends, how far back from the gap must
the spikes be pulled and a wedge inserted?
a) 4toTties
b) I to 11 ties
cl '12 to l5 ties
d) 16 to 20 ties
413: To correct unequal cant between rail-ends, sprkes must be pulled for 12 to 15
ties back from the gap, and a wedge inserted under the 12th to 15th tie. A Track
jack is placed I to 12 ties back to lower a rail-end that has too much peak.
Q14: You open both boxes of a LP CJ or AP CJ weld kit and find the following
components. One important component is missing. What is it?
. 2 half molds
. 1 bottom brick
Missing. diverter plug
. 1 welding charge in sealed package
. 1 CJ crucible & thimble
.1 CJ cover
4
Instructor Guide
Quiz Administration
Q15: What is the correct a¡r pressure for an a¡r/propane preheat?
a) 3.0 psi
b) 3.5 psi
c) 4to5psi
Q16: When us¡ng propane as a preheating fuel, how high must the flames extend
out of the riser holes?
a) 50 mm (2 inches)
b) 100 mm (4 inches)
c) 150 mm (6 inches)
416: The flames extend out of the riser holes for 150 mm (6 inches) when us¡ng
propane as a preheating fuel, 100 mm (4 inches) when using qasoline.
Ql7: During the preheating procedure, when must the stopwatch be started?
a) As soon as the preheating unit is started
b) As soon as the torch burner head is lit
c) As soon as the flame height & the sound is correct
417: During the preheating procedure, the stopwatch be started as soon as the flame
height & the sound is correct.
5
Instructor Guide
Quiz Administration
Ql8: How long must the rail-ends and mold be heated to achieve the correct preweld
temperature?
a) 3-112 minutes
b) 6 minutes
c) 8 minutes
d) 10 minutes
418: The rail-ends and mold must be heated for exactly 5 minutes to achieve the
correct pre-weld temperature. Any shorter will result in poor bonding and
poss,ö/e weld failure... any longer will dry out the fusal paste risking a poss/b/e
run-through.
Ql9: lf a charge bag has clearly been punctured, but there are no signs of
moisture, can the charge still be used?
a)
b)
Yes
No
419: Any charge bag that has been punctured, regardless of the absence of any signs
of moisture cannot be used. lt must be mixed with dry sand & scattered along
the right-of-way.
Q20: To time the cooling period, when must the stopwatch be started?
a) When the charge is ignited
b) When the charge begins to pour
c) When the slag begins to run into the slag basin
d) When the slag stops running into the slag basin
420: To time the cooling period, the stopwatch be started when the slag sfops running
into the slag basin.
Q21: What piece of personal protective equipment is worn exclusively during the
pour?
a) Leggings
b) Respirator
c) Welder's goggles
d) Face shield
A2'l: Welder's goggles with glass /enses must be worn during the pour to protect your
eyes from weld splatter... which will melt a face shield.
6
Instruclor Guide
Quiz Administration
Q22:. At what time after the pour can demolding begin?
a) 3-112 minutes
b) 5 minutes
c) I minutes
d) 10 minutes
e) 15 minutes
422: Demolding must beg¡n at 5 minutes. Any sooner will risk a run through or'hot
tear'... any later, and the top of the mold will be difficult to cut off.
Q23: At what time after the pour can the wedges be removed?
a)
b)
c)
d)
10 minutes
15 minutes
20 minutes
30 minutes
l.23= Wedges must be removed 15 minutes after the pour... to allow the weld to cool
to level.
Q24:. When cold grinding, what is the tolerance for the running surface of the
weld?
a) 0.25 mm (0.01 inch) high and 0.25 mm (0.01 inch) low
b) 0.25 mm (0.01 inch) high and nothing low
c) 0.37 mm (0.015 inch) high and 0.25 mm (0.01 inch) low
d) 0.37 mm (0.015 inch) high and nothing low
l.24: When cold grinding, the tolerance for the running surface of the weld is 0.25 mm
(0.01 inch) high and nothing low.
7
Instructor Guide
Quiz Administration
Quiz 2= Exception Conditions
QI
When measuring the difference in rail height between the two rail-ends at
the gap, what is the maximum acceptable difference for a standard LP CJ
or AP CJ thermite weld kit?
a) 3/16 inch
b) 1/16 inch
c) 1/8 inch
d) 114 inch
A1
When measuring the difference in rail height between the two rail-ends at the
gap, 3/16 inch is the maximum acceptable difference. Any greater difference in
rail height requires a Compromise kit.
Q2: Above what temperature is it not necessary to protect a hot thermite weld with a
heat retarding blanket or shield?
a)1 5"C (60.F)
b)1 0.c (50.F)
c) 5.C (40.F)
d) 0.c (32"F)
A2 A hot thermite weld must be protected by a heat retarding blanket or shield
under cold weather conditions... which is defined as an ambient temperature that
rs /ess than 15t (60T), and/or when windy or rainy.
Q3: How long must a heat retarding blanket or shield be kept on?
a) At least 3-1l2 minutes
b) At least 5 minutes
c) At least 10 minutes
d) At least 20 minutes
A3: A heat retarding blanket or shield must be kept on for at least 10 minutes after
demolding.
I
Instructor Guide
Quiz Administration
Q4: Above what ra¡ltemperature is it not necessary to use a turbo-torch to
warm up the rail-ends before preheating?
a) 15"C (60.F)
b) 10"c (50"F)
c) 5"C (40"F)
d) 0.c (32"F)
A4: A turbo-torch must be used to warm up the railwhen the rail temperature is
below 15t (60F).
Q5
When required, to what temperature must the rail-ends be warmed up to,
before the preheating procedure?
a) 37'C (100"F)
b) 67.C (150.F)
c) 93"C (200'F)
A5: lf necessary, the rail must be warmed up to 37 t (100f) before the preheating
procedure.
Q6
When under tension, the rail must cool down to what temperature before
the hydraulic rail expanders can be removed?
a) 370"G (700"F)
b) 425"C (800.F)
c) 480"C (900"F)
d) 600.c (1100"F)
A6
When under tension. the rail must cooldown to 370f (700T) before the
hydraulic rail expanders can be removed. lf they are removed any sooner, the
weld could be stretched.
Q7: lf a charge ignites, but does not pour out, how must you respond to the
'freeze-up' condition?
a) Carefully lift the crucible with the CJ fork & put it gently in the disposal hole.
b) Leave the crucible where it is and evacuate the weld site.
A7:,
lf a charge ignites, but does not pour out, the crucible is unstable and could
collapse, releasing molten steel around the weld location. Leave the crucible
I
Instructor Guide
Quiz Administration
where it is and evacuate the weld site. Return later to clean up the site once the
sfee/ fias cooled.
t0