Phase 2: Preparation of the Installation
2.5 – Connection of Neu Plus Current Exits
Connect the Black Cables #4,6,8 [12] to
the Positive outputs of the Neu Plus.
Connect the Black Cables #5,7,9 [12] to
the Neu Plus Negative outputs.
Connect the Black Cables #0 [12] from the
terminal outputs to GDN Line.
1.5.1
Stick Neu Plus to the wall with Double
Sided Tape [14].
Fit the Short Circuit Terminals [4] on the
Rail [6].
At the end of Phase 2, your installation should
be in accordance with the figure on the next
page.